Professional Documents
Culture Documents
Pre-Commissioning Tests For Power Cable R3
Pre-Commissioning Tests For Power Cable R3
Pre-Commissioning Tests For Power Cable R3
Pre-Commissioning Test
Procedure
for
Power cable
Prepared By:
Eng. Hatim Gandayh
5/22/2007
Commissioning Service Department
1 of 17
Prepared by:
Eng. Hatim Gandayh Commissioning Engineer
Commissioning Service Department
2 of 17
Test Procedure:
a) The phase undergoing the test is earthed while the other two phases
are unearthed.
b) The main conductor or screen of the cable under test is to be
connected to the negative pole of the Megger.
c) The positive pole of the Megger is to be grounded.
d) Apply test voltage 1000VDC.
e) The phase identification is ok if the resistance becomes zero while
the resistance of other two phases must be very high.
f) Similarly repeat the test for other phases and verify the correctness
of the color-coding.
Prepared by:
Eng. Hatim Gandayh Commissioning Engineer
Commissioning Service Department
3 of 17
Test Procedure:
Prepared by:
Eng. Hatim Gandayh Commissioning Engineer
Commissioning Service Department
4 of 17
Test Procedure:
Prepared by:
Eng. Hatim Gandayh Commissioning Engineer
Commissioning Service Department
5 of 17
4) DC Resistance of Conductor:
Test Procedure:
a) The conductor are shorted at the far end (R-Y & R-B).
b) The other ends of the cables are connected to Bridge according to
equipment instruction.
c) Measure the ambient temperature.
d) Substitute the resistance measured on bridge in the following
formula for temperature correction:-
- For copper
R
R20 = Ω / km
L [1 + 0.00393 × (Τ − 20)]
e) Connect between Y-B and Y-R and repeat from (b) to (d).
f) Connect between B-R and B-Y and repeat from (b) to (d).
g) DC Resistance of copper conductor depends on cable CSA,
conductor material and length of cable.
Prepared by:
Eng. Hatim Gandayh Commissioning Engineer
Commissioning Service Department
6 of 17
ρl
RDC =
A
o
ρ : Material conductivity at 20 C.
l : Length of the cable.
A : Cross Sectional Area.
Prepared by:
Eng. Hatim Gandayh Commissioning Engineer
Commissioning Service Department
7 of 17
Test Procedure:
Prepared by:
Eng. Hatim Gandayh Commissioning Engineer
Commissioning Service Department
8 of 17
I) First Method
Test Procedure:
Test Procedure:
Prepared by:
Eng. Hatim Gandayh Commissioning Engineer
Commissioning Service Department
9 of 17
- Resonance frequency is the worst case in the power system network for
that power cable shall be test under this condition (at XL = XC).
Test Procedure:
Prepared by:
Eng. Hatim Gandayh Commissioning Engineer
Commissioning Service Department
10 of 17
e) Apply test voltage between cable conductor and metallic screen for
test duration.
f) The results will be automatically recorded on lab top computer and
they are printed out.
g) Test pass if no breakdown occurs within test time.
h) Measure again insulation resistance after HV test.
Notes:
Prepared by:
Eng. Hatim Gandayh Commissioning Engineer
Commissioning Service Department
11 of 17
Test Procedure:
Prepared by:
Eng. Hatim Gandayh Commissioning Engineer
Commissioning Service Department
12 of 17
8) Conductor Capacitance:
Test Procedure:
Prepared by:
Eng. Hatim Gandayh Commissioning Engineer
Commissioning Service Department
13 of 17
Test Procedure:
Prepared by:
Eng. Hatim Gandayh Commissioning Engineer
Commissioning Service Department
14 of 17
Test Procedure:
Notes:
Prepared by:
Eng. Hatim Gandayh Commissioning Engineer
Commissioning Service Department
15 of 17
Test Procedure:
Prepared by:
Eng. Hatim Gandayh Commissioning Engineer
Commissioning Service Department
16 of 17
- Bonding normally has been made for the sheath of the cable at all joints.
- When correctly bonding, no current may flow in the sheath of the cables
in case of ideal situation (This is only when all cable sections have the
same length and the spacing between the cables is constant along the
cable route). Actually, some induction current always flows in the sheath
due to actual cable section lengths that may differ from section to other.
- Induction current should not be more than 3% - 5% of the injection
current.
- Link box cable (Ground Cable) has inner sheath
(main conductor) and outer sheath (cable screen).
For example:
Inner of Red Outer of Yellow
Inner of Yellow Outer of Blue
Inner of Blue Outer of Red
Prepared by:
Eng. Hatim Gandayh Commissioning Engineer
Commissioning Service Department
17 of 17
Test Procedure:
Prepared by:
Eng. Hatim Gandayh Commissioning Engineer