MECHANICAL COMPLETION TURNOVER FLOWCHART

SYSTEM APPROACHING TO
MECHANICAL COMPLETION
A

Contractor submits Contractor


System Ready for completes cat A
Walkdown Notice items

Fluor/SPCC
verifies items
Fluor confirms that Contractor closure
system is ready for completes
walkdown deficiences

Punchlist items
cat A complete?
NO

Ready?
NO YES

YES Contractor submits Mechanical


Completion Certificate
(System Turned Over)
Contractor submits
Mechanical
Completion
Checklists

Punch list cat NO


B &C items?

Fluor submits to YES


SPCC a System
Walkdown Notice Contractor
completes cat B
& C items

Fluor/SPCC
Walkdown by verifies items
Fluor/SPCC closure

Punchlist items
cat B &C complete?
NO NO
Punch list
cat A items?
YES

YES
FINAL ACCEPTANCE
NOTICE
A

REV 1
30/09/05