Hazard Identification and Risk Assessment (Hira) : XXX Project
Hazard Identification and Risk Assessment (Hira) : XXX Project
0
REV DATE DESCRIPTION PREPARED CHECKED APPROVED COMPANY
STATUS CODE : A= Issued For Comments, B= Issued For Approval, C= Approved For Construction, D= As Built,
INFO= For Information, ITB = Invitation To Bid
© This document is copyright.
No part may be reproduced or used without the written permission of Premier Oil
INFO
ATTENDANCE LIST
Meeting Subject :
Date :
Chaired by :
Scribed by :
ATTENDANCE
No Name
1
ATTENDANCE LIST
ATTENDANCE
Designation
SUMMARY HIRA ACTIONS
Remark
HAZARD ANALYSIS MEETING RECORD
Consequences /
No. Path Concern Potential Hazard Safety Guarding System Rec. No Recommendation PIC Target No Tasks PIC for Task Remarks
1
Ensure structural check to be done prior to job in Conduct visual check
order to confirming the structural integrity of PLE at 18" piping and 2
auxiliaries other structural
member where the
Structural TA 12 September 2019 a PLE would attach Kusairi Use SI Inspector - Structural
Installation equipment Assurance will be validated by load test prior to
1 placement on deck commencing the activity PM 19 October 2019
2
The angle support located on FTAP to be removed
prior to work commencement in order to remove
obstacle during flare tip replacement work
Demolition of Angle Support Conbit
No additional issue
Pre-work Hotwork identified
2 Shutdown Installation
Start working at 6.0 on day-1. Conbit confirms they
6 days are considered only require 4 days to complete
3 Start up delay
Shutdown windows (19 - 24 sufficient
October) Not enough time
Agreed to use DP1 due to unavailability of DP2 Vessel.
Consequences /
No. Path Concern Potential Hazard Safety Guarding System Rec. No Recommendation PIC Target No Tasks PIC for Task Target for Task Remarks
1
Ensure structural check to be done prior to job in Conduct visual inspection (plus NDT if
order to confirming the structural integrity of PLE required) at 18" piping and 2 other
auxiliaries structural member where the PLE would During shutdown
Structural TA 12 September 2019 a attach Kusairi day-1 Use SI Inspector - Structural
Installation equipment Assurance will be validated by load test prior to Conduct Static Load Test prior to using
placement on deck commencing the activity PM 19 October 2019 a the PLE Conbit During shutdown Static Load Test procedure in place
2
The angle support located on FTAP to be removed
1 prior to work commencement in order to remove Conbit to do cold cutting on the Angle
obstacle during flare tip replacement work Support. Ensure respective tool is
Conbit a provided by Conbit Conbit During shutdown
Demolition of Angle Support b Prepare spare cold cutting tool on site Oki Prior to shutdown
No additional issue
Pre-work Hotwork identified
2 Shutdown Installation
Start working at 6.0 on day-1. Conbit confirms they
6 days are considered only require 4 days to complete
3 Start up delay
Shutdown windows (19 - 24 sufficient
October) Not enough time
Agreed to use DP1 due to unavailability of DP2 Vessel.
Consequences /
No. Path Concern Potential Hazard Safety Guarding System Rec. No Target Recommendation Actionee
Readiness (additional medical test Unaccepted MCU certificate
required by Company (Threadmill) Consult with POI Doctor regarding additional MCU item
requirement (Treadmil), considering personnel MCU certificates
1 already been complied with on UK and Norway Oil and Gas
Review of Personnel Readiness - Conbit Team Associations
FTW 1 Sri Retna / Silvia
Review of Anoa Platform Structural Integrity Initial structural integrity Collapse due the failure of existing POI Structural Integrity and Conbit
structural integrity
Conbit
Conbit to conduct second site visit to assure that current condition
still meet the previous structural study
2
Pre-work Job prior to the Conbit Installation Temporary laydown of Conbit's
Methodology containers not within Cranes's limit Unable to locate Conbit's containers on Prepare lifting and laydown plan as to meet Crane and lifting radius
Main Deck 3 limitations
Conbit/Project
Conbit containers exceeding Crane Load
limitation Unable to lift Conbit's containers onto Conbit's trolley
Main Deck
3
Unable to pull out equipment from
closed container (12.6 Ton loads) 4 Review and assess deck capacity during second site visit (trolley mo
Project
Too big container
Lifting over the side of the existing LQ
area may impair the FW Monitor or
other equipment
Load test Dynamic test (maximum load i.e 12 Do the dynamic load testing gradually starting from 6.6 tonnes to
tonnes); 10 times up and down 12.5 tonnes
No significant issue Procedure is in place 5
4
Static test (8.3 tonnes)
No significant issue Procedure is in place
Project delay. Swaying of vessel affects Hs: 1 m for heavy lifts (> 10
establishment of lifting, whilst dynamic tonnes)
Weather (severe wave) calculation was based on 1 m Hs Hs: 1.5 m for general lifts
Provide material management plan (options ) and rigging plan
during lifting by Conbit.
Deck Extension and Module Installation Works 10
Conbit Temporary Laydown (Lack of Project interruption due to difficulty to
laydown space) store projjects material Develop logistic/ storage plan according to layouts of the deck and
vessel (incorporate layout of Vessel and lifting devices involved)
11
Verify the exact dimension/level of attachements points as
precision of brace length is essential. Failure to do so will lead to
project delay as in situ adjustment will take long time and
significant effort. Verification of dimensions to be done on site
Design using sophisticated Tool
Failure/difficulty to finalize brace
8
Misalignment between brace and pin installation Shim plate is adjustable 12 Project
Dimension control
Consequences /
No. Path Concern Potential Hazard Safety Guarding System Rec. No Recommendation Actionee
Readiness (additional medical test Unaccepted MCU certificate
required by Company (Threadmill) Consult with POI Doctor regarding additional MCU item requirement
1 (Treadmil), considering personnel MCU certificates already been complied
Review of Personnel Readiness - Conbit Team with on UK and Norway Oil and Gas Associations
FTW 1 Sri Retna / Silvia
Review of Anoa Platform Structural Integrity Initial structural integrity Collapse due the failure of existing POI Structural Integrity
structural integrity and Conbit
Conbit
Conbit to conduct second site visit to assure that current condition still
meet the previous structural study
2
Pre-work Job prior to the Conbit Installation Temporary laydown of Conbit's
Methodology containers not within Cranes's limit Unable to locate Conbit's containers on Prepare lifting and laydown plan as to meet Crane and lifting radius
Main Deck 3 limitations
Conbit/Project
Conbit containers exceeding Crane Load Unable to lift Conbit's containers onto
limitation Conbit's trolley
Main Deck
3 Limited space and deck capacity
Unable to pull out equipment from
closed container (12.6 Ton loads) 4 Review and assess deck capacity during second site visit (trolley movement)
Project
Too big container
Lifting over the side of the existing LQ
area may impair the FW Monitor or
other equipment
Load test Dynamic test (maximum load i.e 12 Do the dynamic load testing gradually starting from 6.6 tonnes to 12.5
tonnes); 10 times up and down tonnes
No significant issue Procedure is in place 5
4
Static test (8.3 tonnes)
No significant issue Procedure is in place
Project delay. Swaying of vessel affects Hs: 1 m for heavy lifts (> 10
establishment of lifting, whilst dynamic tonnes)
Weather (severe wave) calculation was based on 1 m Hs Hs: 1.5 m for general lifts
Provide material management plan (options ) and rigging plan during
lifting by Conbit.
Deck Extension and Module Installation Works 10
Conbit Temporary Laydown (Lack of Project interruption due to difficulty to
laydown space) store projjects material Develop logistic/ storage plan according to layouts of the deck and vessel
(incorporate layout of Vessel and lifting devices involved)
11
Verify the exact dimension/level of attachements points as precision of
brace length is essential. Failure to do so will lead to project delay as in situ
Design adjustment will take long time and significant effort. Verification of
Failure/difficulty to finalize brace
8
Misalignment between brace and pin
installation
Shim plate is adjustable 12 dimensions to be done on site using sophisticated Tool Project
Dimension control