Sr. 2 year Work Area quantity ( Rs. / Value No. quantity per day Unit). 1 Housekeeping of plant area 1.1 RWPH 1 700 2500 1750000 1.2 FWPH 1 700 2500 1750000 1.3 DWPH 1 700 2500 1750000 1.4 RWTP 1 700 2500 1750000 1.5 IAPA 1 700 2500 1750000 1.6 DM 1 700 2500 1750000 1.7 COOLING TOWERS 1 700 2500 1750000 1.8 ECTS 1 700 2500 1750000 1.9 TANK FARMS / HGU 1 700 2500 1750000 1.10 GANTRY /FLARE AREA 1 700 2500 1750000 1.11 SWITCH YARD 1 48 2500 120000 Total 7048 1,76,20,000
2 Housekeeping of building area
2.1 SWITCH YARD 1 731 700 511700 OPERATOR ROOM IN DM/CPU AND 2.2 1 700 700 490000 CHEMICAL AREA 2.3 UCR 1 731 700 511700 CT1/2/3/FWPH Operator room and 2.4 1 700 700 490000 chlorination building and chemical area RWTP Control Room and chemical houses 2.5 1 700 700 490000 and area 2.6 ECTS CONTROL ROOM 1 731 700 511700 2.7 ECTS CHEMICAL HOUSE 1 731 700 511700 2.8 OCR 1 731 700 511700 2.9 PLCR 1 731 700 511700 2.10 SUB STATION BULDING-11 1 540 700 378000 2.11 SUB STATION BULDING-12 1 540 700 378000 2.12 SUB STATION BULDING-13 1 540 700 378000 2.13 SUB STATION BULDING-14 1 540 700 378000 2.14 SUB STATION BULDING-15 1 540 700 378000 2.15 SUB STATION BULDING-16 1 540 700 378000 2.16 SUB STATION BULDING-17 1 540 700 378000 2.17 SUB STATION BULDING-18 1 540 700 378000 2.18 SUB STATION BULDING-19 1 540 700 378000 2.19 SUB STATION BULDING-20 1 540 700 378000 2.20 SUB STATION BULDING-21 1 540 700 378000 2.21 220 KV switchyard 1 540 700 378000 TOTAL 12966 90,76,200 3 No. of Toilet cleaning Rate Sr. Number 2 year Work ( Rs. / Value No. per day quantity Unit). 3.1 Daily Toilet cleaning 34 24820 125 3102500 3.2 Opal working day toilet cleaning 23 12420 125 1552500 Total 37240 46,55,000 Total From 1+2+3 = Rs 3,13,51,200/-