Professional Documents
Culture Documents
Pgca-Pi-Bod-1-002 - C2 - 2 Piping Design Premise
Pgca-Pi-Bod-1-002 - C2 - 2 Piping Design Premise
Rev. No. : C2
All major changes to the document at this current revision are recorded below.
(Does not include correction of typos or formatting changes)
HOLD LIST
Page 2 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
CONTENTS
1 INTRODUCTION ............................................................................................ 5
1.1 Project Background ........................................................................................ 5
1.2 Facility Description ......................................................................................... 5
1.3 Purpose and Scope of Document ................................................................... 6
1.4 Reference ...................................................................................................... 6
1.4.1 Order of Precedence ..................................................................................................... 6
1.4.2 Company Standards and Project Specifications ........................................................... 7
1.4.3 Referenced Codes and Standards ................................................................................ 8
2 DEFINITIONS AND ABBREVIATIONS......................................................... 14
2.1 Definitions .................................................................................................... 14
2.2 Abbreviations ............................................................................................... 14
2.3 Units of Measurement .................................................................................. 16
3 GENERAL REQUIREMENT ......................................................................... 17
3.1 Environmental .............................................................................................. 17
3.2 Design life .................................................................................................... 17
4 FACILITY LAYOUT REQUIREMENT ........................................................... 18
4.1 General ........................................................................................................ 18
4.2 Equipment Layout ........................................................................................ 19
4.3 Operability and Maintainability ...................................................................... 20
4.4 Accessibility and Clearance.......................................................................... 20
4.5 Pollution Prevention ..................................................................................... 21
5 PIPING DESIGN .......................................................................................... 22
5.1 General ........................................................................................................ 22
5.2 Piping Layout ............................................................................................... 22
5.3 Non-Metallic Piping ...................................................................................... 25
5.4 Piping Clearance .......................................................................................... 25
5.5 Pipeways and Racks .................................................................................... 28
5.6 Branches ...................................................................................................... 28
5.7 Valving ......................................................................................................... 29
5.8 Blanks and Spacers ..................................................................................... 29
5.9 Strainers....................................................................................................... 30
5.10 Drip and Bleed Rings ................................................................................... 30
5.11 Hub and Clamp Connectors ......................................................................... 30
6 PIPE STRESS ANALYSIS AND FLEXIBILITY ............................................. 31
6.1 General ........................................................................................................ 31
7 PIPE SUPPORTS ........................................................................................ 32
7.1 Support Design Criteria ................................................................................ 32
7.2 Loads ........................................................................................................... 33
7.3 Spring Supports ........................................................................................... 34
8 SPECIALITY PIPING ITEMS ........................................................................ 35
8.1 General ........................................................................................................ 35
9 CHEMICAL INJECTION AND SAMPLE CONNECTIONS FOR PIPING ....... 36
9.1 General ........................................................................................................ 36
9.2 Chemical Injection ........................................................................................ 36
9.3 Sample Connections .................................................................................... 36
10 EROSION / CORROSION MONITORING .................................................... 37
10.1 General ........................................................................................................ 37
10.2 Access Fittings ............................................................................................. 37
Page 3 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
11 INSTRUMENTATION ................................................................................... 38
11.1 General ........................................................................................................ 38
11.2 Control Valves .............................................................................................. 38
12 WELLHEADS FLOWLINES AND MANIFOLDS ............................................ 40
12.1 General ........................................................................................................ 40
13 EQUIPMENT INTERFACES ........................................................................ 41
13.1 Pressure Vessels ......................................................................................... 41
13.2 Heat Exchangers .......................................................................................... 41
13.3 Rotating Equipment ...................................................................................... 42
13.3.1 Pumps ......................................................................................................................... 43
13.3.2 Compressors ............................................................................................................... 43
14 UTILITY SYSTEMS ...................................................................................... 44
14.1 Fuel and Utility Gas ...................................................................................... 44
14.2 Instrument Air ............................................................................................... 44
14.3 Utility Air ....................................................................................................... 45
15 PRESSURE RELIEVING SYSTEMS ............................................................ 46
15.1 General ........................................................................................................ 46
15.2 Relief Valves ................................................................................................ 46
16 FLARE AND VENT SYSTEMS ..................................................................... 48
16.1 General ........................................................................................................ 48
16.2 Flare and Vent.............................................................................................. 48
17 VENTS, DRAINS, AND FLUSHING SYSTEMS ............................................ 49
17.1 Vent Connections ......................................................................................... 49
17.2 Drainage Systems ........................................................................................ 49
18 FIREWATER SYSTEM PIPING.................................................................... 50
18.1 General ........................................................................................................ 50
19 PIPING DESIGN AND DOCUMENTATION .................................................. 51
19.1 General ........................................................................................................ 51
19.2 Equipment Layouts....................................................................................... 51
19.3 Piping Plans ................................................................................................. 52
19.4 Detail Drawings ............................................................................................ 52
19.5 Shop Isometric / Spool Drawings.................................................................. 52
Page 4 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
1 INTRODUCTION
MDC Oil and Gas (SK 320) Ltd (“COMPANY”) is the Operator of Block SK320, offshore
Sarawak, Malaysia, as shown in Figure 1.1, under a production sharing contract and is
developing of a number of gas field discoveries in this block. The largest of these,
Pegaga, is the focus of the development. The Pegaga field is in a water depth of about
108m and is in the vicinity of a range of existing infrastructure, as shown in Figure 1.2.
The gas and condensate will be exported to the Bintulu MLNG terminals.
North Luconia
395.
• SSIV (Subsea Isolation Valve) Manifold at Pegaga ICPP. 6oN
North Luconia
Delta
SK320
Baram Delta
Central Luconia
West Luconia
4oN Rim
Balingian
Tatau Province
Rev. No. : C2
The purpose of the document is to define the criteria to be used for piping design of
Pegaga Offshore facility by MDC Oil and Gas (SK 320) Ltd (“COMPANY”) as the
Operator of Block SK320.
This document is not intended to make redundant good engineering practices and
consideration will be given to special circumstances where more or less rigorous
criteria should be applied. In case of licenced units, the design criteria of the system
licensor will generally be followed to ensure guarantees unless there is a specific
requirement by COMPANY.
This document shall also be used for the piping materials within Vendor supplied
packages.
This design premise only covers the piping above the pipeline riser hanger flange.
Riser hanger flange and subsequent subsea pipelines are outside the scope of this
document.
1.4 Reference
The reference documents listed below, including industry codes and standards and
COMPANY specifications form an integral part of this general specification. Unless
stated otherwise the applicable version, including relevant appendices and
supplements is the latest revision published at the effective date of the contract.
Any conflict shall be reported to COMPANY for decision. In such a case, and unless
otherwise agreed by COMPANY, the more stringent requirement shall apply.
Page 6 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
Exceptions to or deviations from this document are not permitted unless accepted in
writing by COMPANY.
Detailed below are a number of COMPANY’s general specifications and criteria which
specifically interface with this document.
This list is not exhaustive and where necessary both general and Project specifications
shall be referred for specific requirements.
Reference Title
Page 7 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
Reference Title
Page 8 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
Reference Title
ASME B18.2.1 Square and Hex Bolts and Screws (Inch Series)
ASTM A193 Alloy-Steel and Stainless Steel Bolting Material for high-
temperature service
ASTM A194 Carbon and Alloy Steel Nuts for Bolts for High Pressure
or High Temperature Service, or Both
Page 9 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
Reference Title
Rev. No. : C2
Reference Title
Page 11 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
Reference Title
API STD 594 Check Valves: Wafer, Wafer-Lug, and Double Flanged
Type
API STD 598 Valves Inspection and Testing
API STD 600 Bolted Bonnet Steel Gate Valves for Petroleum and
Natural Gas Industries
API STD 602 Steel Gate, Globe and Check Valves for Sizes DN 100
and Smaller for the Petroleum and Natural Gas
Industries
API STD 609 Butterfly Valves : Double Flanged, Lug- and Wafer-
Type
BS 1868 Specification for Steel Check Valves (Flanged and Butt-
Welding Ends) for the Petroleum, Petrochemical and
Allied Industries
BS 5352 Steel Wedge Gate, Globe and Check Valves 50mm and
Smaller
Page 12 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
Reference Title
Page 13 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
2.1 Definitions
CA : Certifying Authority
Site : Site means the location (s) of the offshore facilities and
Pipelines
2.2 Abbreviations
cP : Centipoise
Page 14 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
FM : Factory Mutual
LP : Low Pressure
RT : Radiographic Test
UL : Underwriters Laboratories
Page 15 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
The units of measurement detailed within the document are derived from the SI
system units, as described below. If not included in the table below the
International System of Units (SI) shall be used.
Parameter Unit
Density kg/m3
Flowrate Nm3/hr
Mass kg
Temperature °C or K
Weight kg
Notes:
Rev. No. : C2
3 GENERAL REQUIREMENT
3.1 Environmental
The Piping system to be supplied for the Pegaga offshore facilities will, unless
otherwise stated on the relevant piping component or equipment datasheets, be
installed in a tropical offshore saliferous environment. The piping and its equipment
related materials of construction and anti-corrosion coatings shall be suitable for the
expected environmental factors and process temperatures plus the predicted
environmental loading.
Minimum °C
Air Temperature 21
Sea Surface Temperature 23.3
Sea Bed Temperature 13.8
Humidity (%) 35
Maximum °C
Air Temperature 39.9
Sea Surface Temperature 33.2
Sea Bed Temperature 27.3
Humidity (%) 100
The 3 second gust and 1 minute average wind speed at 10 m above mean
sea level for a return period of 100 years is 43.7 m/s and 36.1 m/s
respectively.
Material selected for the Pegaga Piping System shall be suitable for 20 years
of design life.
Page 17 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
4.1 General
The primary considerations, for Pegaga facility layout design are safety,
operability, maintainability and the prevention of pollution. High risk
hydrocarbon areas shall be separated from low risk areas, such as the living
quarters and safety systems.
The layout shall be based on the following major principles but not limited to:
The routing of firewater ring mains and deluge piping, high pressure piping,
pipework containing large hydrocarbon inventories and those with a high
frequency leakage potential shall be considered with regard to their
vulnerability to fire and blast overpressures. The use of natural shielding from
vessels, walls and structures shall be made.
The living quarters, Control rooms and Technical rooms shall be located at the
non-hazardous area and shall be protected from external fires and noise, by
suitably rated barrier walls.
Page 18 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
Location of the pedestal crane shall ensure clear visual sight for the operator
for offloading supply boats from the normal approach position and the setting-
down of loads on dedicated laydown positions, wherever possible. Laydown
areas shall be provided at each deck level to allow the removal/maintenance of
equipment as required. Monorails and access ways shall be provided to these
laydown areas.
Where helicopter operations are required the platform design shall also comply
with the guidance of CAP 437. Helicopter fuel tanks shall be located remote
from potential sources of ignition and precautions shall be taken to prevent
spilled liquid from flowing into other areas.
Electrical switchgear and control rooms shall be kept free of any liquid piping
systems.
Layouts are to minimise the potential for trapped vapour pockets, and
prevailing weather conditions are to be considered in determining the natural
ventilation.
Page 19 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
The platform design shall also comply with the guidance of CAP 437 as
required, and shall not restrict helicopter operations.
The facility layout shall take into account operation and maintenance
requirements, ensuring sufficient access around equipment are provided and
also satisfy the requirements for material handling.
Access hatches shall be provided for the removal of equipment from one deck
level to another as identified within the Mechanical Handling Study.
A minimum of two escape routes shall be provided from process and utility
areas where normal operation and maintenance activities are undertaken. The
escape route and equipment access shall be provided to meet requirements as
shown below.
Dimension
Width and Distance
(mm)
Minimum Primary Escape Route Width – Around the 1200
periphery of the platform and the escape route leading to
them
Minimum Secondary Escape Route Width 1000
Page 20 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
All ladders shall be provided with safety cages, starting at 2.5m from the base
of the ladder. The safety cage shall extend to 1m above the top of the ladder
and the distance from the rings to the back of the cage shall be a minimum of
700mm. Above requirements is aligned with PGCA-SA-PHI-1-001-Project
Technical Safety Philosophy.
The facility layout shall provide sufficient operating space for maintenance
equipment such as bridge cranes, monorail hoists and hook hoists. Space shall
be kept clear for escape routes, access ways, laydown and maintenance
areas, manholes, access openings, inspection points, hatches, davits and
areas required for equipment and instrument withdrawal.
Care shall be taken with the location of sea water pump suction lines and the
area where outfall caissons are discharging to avoid cross contamination,
particularly the sewage drains caisson. Drip pans shall be provided where
hydrocarbon liquids are contained.
Page 21 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
5 PIPING DESIGN
5.1 General
Pegaga Topside piping system design, layout, support and flexibility shall be
fully in accordance with ASME B31.3, the recommendations of API RP14E and
COMPANY’s technical requirements.
Design of Pegaga pipeline risers, including the pig trap shall be in accordance
with ASME B31.8.
All pipe, fittings, and valves shall conform to the standard specifications for the
service specified, and in particular the appropriate piping class for the intended
service. Pipe, fittings and valves sizes ¼, 1-¼, 2-½, 3-½, 5, 7, 9 and 22 inches
shall not be used except as necessary to connect to equipment, and shall
change to conventional size immediately adjacent to the equipment.
The minimum pipe size to be used shall be ¾” NPS. For chemical injection and
hydraulic systems, piping 1” NPS and below may be substituted by tubing with
twin ferrule type compression fittings.
Dimensions of metallic fittings shall be in accordance with ASME B16.9 & MSS-
SP-43 for butt-weld fittings. Wall thickness of butt-weld fittings shall not be less
than the minimum wall thickness of connecting pipes.
Utility piping serving buildings and areas other than platform Process and Utility
piping areas may be designed to applicable plumbing, heating and ventilation, or
refrigeration codes subject to COMPANY approval.
All piping shall be routed to provide a simple, neat and economical layout to
minimize run lengths and fitting quantities with adequate flexibility and allowing
ease of support and access. Except for removable piping sections required to
Page 22 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
facilitate maintenance, and piping requiring dismantling for cleaning, the use of
unions shall be limited to the connection of flanged components or equipment.
Piping shall typically be routed in the true vertical or horizontal plane, and
generally parallel to column and rows. Diagonal and skewed angle piping runs
should be avoided. All lines requiring a fall or slope as designated on the P&ID's
shall be designed to ensure they slope in the required direction. For major piping
runs, changes in direction shall generally coincide with changes in elevation.
Care shall be taken not to create unnecessary low point pockets or high point
traps. Dead legs in process piping shall be avoided whenever possible.
Lines that branch off from main piping runs preferably shall be routed and
supported with other lines unless the shortest direct route is required.
Piping shall not be routed directly above mechanical equipment such as pumps
or compressors or above operating or maintenance areas. Piping runs shall be
to the front, side, rear or beneath such equipment to facilitate operation and for
easy removal of equipment for inspection, servicing and maintenance. Areas
reserved for removal of heat exchanger bundles, filters, and rotating equipment
components shall be free of overhead piping.
Rev. No. : C2
Piping headers with flanged ends shall be located so that future extension of the
header is not blocked by adjacent piping or equipment.
Piping shall not be installed below the lowest deck level unless absolutely
necessary due to its service or route to or from a lower area, such as a boat
landing or pump caisson.
Piping insulation and trace heating shall be provided as detailed on the P&IDs.
Hot lines shall be grouped together and separated from cold lines in order to
control corrosion, thermal expansion and condensation and vapour problems as
much as possible.
For pipes subjected to post weld heat treatment, the minimum spacing between
circumferential weld joints shall be 100mm or 4 times the wall thickness of the
pipe, whichever is greater, as per ASME B31.3 requirement unless otherwise
approved by COMPANY. Minimum spacing shall be measured from toe to toe
and not weld centreline.
Mitred joints and welds shall not be acceptable without written COMPANY
approval. Expansion joints shall not be permitted in corrosive or hydrocarbon
service.
Piping shall not penetrate primary structural steel members or blast walls without
written COMPANY approval. A fire retarding seal shall be provided on all piping
penetrations through fire or blast walls of the same or higher barrier rating.
Page 24 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
Fibreglass reinforced piping (FRP) may be used for seawater, sewage and open
drain services as per project specific Material Selection Report where fluid surge
and water hammer are not encountered. The design, layout and support of
piping systems shall be in accordance with the Manufacturer’s requirements /
recommendations and the technical requirements of the Project.
The FRP Manufacturer shall note that the COMPANY’s technical requirements
do not include complete detailed design, layout, and support or flexibility
requirements specific to the needs of FRP piping systems. The FRP
Manufacturer shall be responsible for providing a complete design, undertaking
any flexibility analysis, including dynamic surge analysis where required, and
shall provide suitable details for the layout and support of the FRP piping system
to the mutual satisfaction of COMPANY and Contractor.
FRP piping shall typically be provided with saddles that provide 180° of
circumferential support in accordance with the FRP pipe Manufacturer’s
recommendations. Valves and heavy components in FRP piping systems shall
be independently supported or suspended to prevent excessive torque, bending
or longitudinal stresses being transmitted to the FRP piping.
Chlorinated Poly Vinyl Chloride (CPVC) piping may be used for hot and cold
water services. The design, layout and support of CPVC piping systems shall be
in accordance with ASTM D2846, and the Manufacturer’s requirements/
recommendations. Pipe supports shall be spaced a maximum of 1000mm apart,
and a CPVC saddle shall be glued to the underside of the pipe at all support
locations. CPVC piping shall not be rigidly anchored to supports; instead it shall
be loosely secured to allow pipe movement.
Non-metallic piping shall not be used for hydrocarbon process services without
written COMPANY approval.
GENERAL
Page 25 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
Minimum clear width beyond the ends of exchangers (plus tube or cover removal
900 mm
length where applicable)
Minimum clear space all round for Locally mounted Instrument panels (WHCP, 1000 mm
HPU, TUTU)
Minimum clearance in front of inspection, cleanout and manway opening;
900 mm
internals removal shall be considered
Clearance required between deck level or platform and bottom of pipe (BOP)
with process drain connection should be provided as shown in below figure:
Preferred bottom of pipe (BOP) of control valve above deck level or platform 400 mm
The minimum clearance between BOP and deck for Flow devices 600 mm
PIPE SPACING
Minimum distance from underside of pipe or insulation to high point of deck level
or platform
200 mm
Except that flanges or valve bodies, shall also be 200mm clear of deck where
controlling
Minimum distance between pipes or insulation of pipes 25 mm
Minimum distance between a flange and a pipe or the insulation of a pipe
(flanges of adjacent pipes running parallel with each other shall be staggered to 25 mm
prevent fouling of flanges)
Minimum distance from pipe to face of steelwork (after allowing for insulation) 75 mm
Minimum distance from flange to face of steelwork, etc 75 mm
Access shall be as per Asian Valve Operation Anthropometry and based on the
valve criticality table shown below.
Minimum clearance between adjacent handwheels, equipment including
50 mm
insulation, structures and any obstruction for valve operation
Clear operating level for use of chain wheels (only with COMPANY approval)
1000 mm
with extension stems kept to a minimum
Page 26 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
Valves not critical for Height and reach distance of these valves are
Operations and operated preferable to be the same as for Category 1
infrequently (less than once valves.
Category 2 per 6 months) for non-routine
(C2) Vertical fixed ladder plus small standing
operation and maintenance
surface are acceptable for valve operation.
Auxiliary equipment to gain access for
maintenance may be acceptable.
Valve criticality described in detail in Human Factor Term of Reference, Doc No:
PGCA-SA-TOR-1-003 and PGCA-SA-TOR-1-004.
Space required for retrieval of corrosion probe / coupon and chemical injection 2000 mm
fitting / quill (To suit
Vendor)
Page 27 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
Where pipeways are provided, utility and service lines shall generally be
grouped separate from process lines with utility and service lines placed on the
top level, and process lines on the lower level of pipe racks wherever possible.
The outer edges of pipe racks shall be allocated to heavy (liquid) lines and large
diameter piping with the centre allocated to light (gas or vapour) lines and small
diameter piping.
Process lines shall be placed on the same side of the pipe rack as the
equipment they service when possible. Expansion pipe loops shall be installed
over the top of racks where practical.
Pipe entering or exiting pipe racks shall roll out with a change in elevation so as
not to block adjacent pipe slots. If possible, the difference in elevations between
lines oriented with platform north/south and those oriented east/west shall be a
minimum of 600mm. On installations with long runs of pipe, a longitudinal
clearance shall be provided between pipes leaving the pipeway or rack to
accommodate thermal expansion.
Pipeways and racks shall include a minimum of 20% spare space based on
linear width for future requirements.
5.6 Branches
Branch connections in process services shall be located at the top or side of the
header, with the branch line block valve located to allow complete drainage on
each side of the valve. In utility services branches shall be located at the top of
the header, with root valves located in the horizontal section of the branch, close
to the header.
Couplings or other weld-on type branch connections and fittings shall not be
located on a weld joint.
Where required small bore connections nominally 1 1/2 inch & below shall be
braced back to the header in services that give potential for piping vibration such
as well stream piping, rotary compressor piping, reciprocating pumps &
compressor piping, piping subjected to slugging and other services that can
excite pipe vibration. Ensuring small bore connections are safe during start up,
Page 28 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
5.7 Valving
Valves shall be installed to provide suitable isolation and manual control for the
maintenance of the facilities as detailed on the P&IDs. Valve selection shall be
accordance with MPMY-PI-SPC-0003, Manual Valve Specification.
Bypass valves shall be installed where slow warm-up of a system would require
the main block valve to be cracked open during which seating surfaces could be
damaged, to facilitate smooth operation of valves of large diameter, or valves
that need to operate at high differential pressures. Bypass valves shall conform
to the same piping class as the principal valve and may be ball or globe or choke
type. Nominal minimum size of the bypass shall be as indicated in the respective
P&IDs.
Where a bypass line with isolation valve is provided for equipment, the pressure
rating of bypass piping, bypass valve and suction valve shall be of the same
pressure rating as the discharge piping.
Valves shall be located such that their actuator or hand wheel may be
conveniently reached when standing at deck level or from a permanent platform
as per Asian Valve Operation Anthropometry. Horizontally positioned valve
stems however shall not be located between 1400mm and 1900mm above the
deck or operating platform.
Valves which are regularly operated and where the hand wheel is 1900mm or
more above an operating level shall be provided with chain operators or
extension stems. Chain drop shall normally clear operating platforms by
1000mm. Chain operators shall not be acceptable on valves 2 inches and
smaller. Access platforms are preferred to chain operators.
Page 29 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
Removable pipe spools shall be installed at raised face or ring-type joint flanges
too rigid to separate with jackscrews.
For blanks weighing more than 35kg located in horizontal section of pipe and
permanent handling equipment shall be provided, unless mobile lifting
equipment can be easily utilised.
5.9 Strainers
Temporary strainers shall be provided in pump suction lines. The open area
shall typically equal 300 percent (300%) of the cross-sectional area of the pipe.
Piping shall be so arranged that the strainer can be removed without altering the
piping, supports, or pump alignments.
All Y-type strainers shall be installed with the basket downward or 45 deg rolled,
with adequate space to remove the basket from the bottom. Simplex/duplex
basket and bucket type strainers shall be installed in the upright position to allow
the basket/bucket to be lifted out from the top.
Drip and bleed rings shall be installed between a pair of flanges to provide in-
place field pressurisation of relief valves for testing, vent/drain points for close
coupled instrumentation or drain points on congested piping configurations, as
indicated in P&ID’s.
Hub and clamp connectors shall only be used if indicated in P&ID’s and as per
Piping Material Specification, Doc No: MPMY-PI-SPC-0002.
Page 30 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
6.1 General
Pipe stress analysis and flexibility shall be as per project specific Pipe Stress
Design Criteria, PGCA-PI-BOD-1-001.
Page 31 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
7 PIPE SUPPORTS
Pipe supports shall adequately support the piping and prevent excessive loads,
expansion forces and vibration on equipment and vessels. They shall comprise a
rigid steel support structure, generally constructed from angle, channel, tubular
and structural sections, and shall include “U” bolts, shoes, guides, stops,
anchors, restraints, spring hangers, stanchions, dummy legs, etc. Piping
supports shall not be fabricated of cast, ductile, or malleable iron. Pipe support
shall be accordance to Standard Pipe Support Drawings, Doc.No: PGCA-PI-
STD-1-001 To PGCA-PI-STD-1-077.
The Contractor shall be responsible for determining the method of pipe supports
as appropriate or necessary. For example, rigid clamping should not be used on
high temperature insulated piping, on piping that requires flexibility for imposed
movements, or when stresses in the piping system caused by the rigid restraints
exceed the allowable. Temporary supports shall be allowed only if approved in
writing by COMPANY.
All pipe supports shall provide positive support to the pipe from below and
sufficient bracing to prevent excessive deflection or horizontal movement of the
piping system. They shall not rest upon or be welded to grating, deck plate or
other non-structural elements.
Pipe supports that provide support from overhead, such as rod hangers or “U”
bolts clamped or bolted to overhead steel shall not be used unless prior approval
is given by COMPANY.
Line stops and anchors shall transmit the entire load directly to the supporting
structural member.
Insulated piping shall be supported on pipe shoe type supports, with a minimum
of 25mm clearance between the insulation jacket and the support steel. Pipe
Page 32 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
shoes shall include slots to secure the insulation weather proofing jacket with
metal straps.
To avoid crevice corrosion between pipe and support member, there shall be no
direct contact between (Ferrous & Non Ferrous) pipe and support member.
Isolating pad / I- Rod (high strength thermoplastic rod) shall be used to provide
isolation between the pipe and the support member
7.2 Loads
Considering the above loading scenarios, for critical piping systems, the pipe
support loads shall be based on worst case loading from pipe stress analysis.
For non-critical piping such as utility piping, pipe support loads shall be
estimated.
To cater for the pipe support loads, pipe support design shall use project Pipe
Support Standard where possible. Each support in the Pipe Support Standard
shall be indicated with load bearing capacity to cater for the calculated or
estimated loads. Each load bearing capacity in the Pipe Support Standard shall
be verified by Structural Department.
When it is not possible to use the project Pipe Support Standard, special pipe
supports shall be introduced. Each special pipe support shall be verified by
Structural Department in order to cater to the calculated or estimated loads.
The calculated or estimated pipe support loads shall be provided to and checked
by Structural Department to ensure the integrity of the structures where pipe
supports are located. In this case, any pipe support loads in excess of 10KN
acting horizontally and 20KN acting vertically shall be provided to the Structural
Department for structural integrity checks. Where structural stresses due to
these pipe support loads are deemed excessive, pipe routing / supporting shall
be reviewed
Page 33 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
The use of spring supports shall be avoided wherever possible, however where
required they shall be capable of supporting the pipe under all design conditions,
allowing free expansion and contraction of the piping and prevent excessive
stress induced by transfer of weight to the pipe or connected equipment.
Sizes and types of spring supports shall be selected so that the supports can
carry the full design loads.
Spring supports shall be furnished with factory installed travel stops set at the
cold position. The travel stops shall be easily removable, but capable of acting
as a rigid hanger during erection, and hydrostatic testing. Constant-load
supports shall provide a means of vertical adjustment after erection.
Hanger rods shall be subjected to tensile loading only, and shall have linkages to
permit swing where lateral or axial movement is anticipated.
Page 34 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
8.1 General
Speciality piping items are typically not covered by a design code or standard or
are not standard items and hence not detailed within the piping material
specifications. Speciality piping item shall be design accordance to SP item
Specification, Doc.No: PGCA-PI-SPC-1-002. These includes quick connectors,
hoses, traps, flame arrestors, strainers, sampling connection, access fittings and
etc. Speciality items shall be of standard sizes and materials consistent with the
applicable piping classes.
Page 35 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
9.1 General
Whenever possible, chemical injection lines shall be run under protection in the
shadow of steel.
Instrument tubing and compression fittings may be used for injection pump
suction and discharge piping subject to the following conditions:
Deck penetrations shall be prohibited within the contained area of the chemical
storage tanks.
Sample connections shall be installed in the side of piping rather than on the top
or bottom, and shall be as short as practical unless and otherwise specified by
P&ID’s.
Page 36 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
10.1 General
Coupons and probes shall be placed directly into the flow stream in piping
systems where the presence of sand or two-phase flow might cause erosion of
the piping or where an assessment of the rate of corrosion is required.
Access fittings shall be flanged type. The access fitting shall provide adequate
support for the coupon or probe holder, an accurate indication of the position of
the coupon or probe in the pipe and a protective cover for the probe holder.
Access fittings shall be of the same material as the piping to which they are
attached, and generally located at the top of the pipe. A minimum clearance of
2000mm shall be provided to allow access for removal tool, subject to
confirmation from Vendor, as per 5.4.
The plug body shall provide support for the coupon or probe and shall seal the
pressure of the piping system.
Page 37 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
11 INSTRUMENTATION
11.1 General
The first block valve of the instrument connection shall conform to the
requirements as outlined within COMPANY’s Isolation Design Guideline,
document MPMY-GE-GUI- 0002, and to the piping class of the line or the
equipment to which the instrument connects.
Gas metering system shall not be located at a low point of piping system and the
configuration shall be such that the primary device shall be in self draining
position
Control valve stations shall be oriented in the vertical position and shall have a
compact arrangement with sufficient clearance for removal and operation of all
Page 38 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
control, block and bypass valves, and associated instruments without requiring
disassembly of any other components.
Where a control valve is less than line size, an eccentric reducer shall be located
as close as possible to the valve with the flat side down to allow complete
drainage via a drain valve located between the control valve and the upstream
block valve.
In some cases, pressure and/or flow conditions may vary sufficiently to require a
larger or smaller control valve in the future. If a different control valve is required,
the piping shall be designed for the larger size, and provisions made to facilitate
the change without major piping modifications, such as flanged spools.
Page 39 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
12.1 General
The flowline design and layout shall avoid dead legs, take into consideration
independent wellhead movement due to wave action, and thermal growth, and
shall not obstruct access necessary for well servicing. The wellhead growth shall
be as per Project Pipe Stress Analysis Criteria Doc.No: PGCA-PI-BOD-1-001.
Page 40 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
13 EQUIPMENT INTERFACES
Isolation of the vessel for inspection and maintenance shall be as per Isolation
Design Guideline, document MPMY-GE-GUI-0002.
For instrumentation connections, the first block valve off a vessel connection
shall use a piping class root valve in accordance with the appropriate piping
class specification.
Liquid outlet headers shall be piped to permit gravity drainage from the vessel.
Vessel drains operated only during shutdown periods may be provided with
plugs or blanks in lieu of permanently installed valves with COMPANY approval.
Vessel emergency shutdown valves shall be located within 10.0m of the vessel
measured horizontally. The total pipe length from the vessel nozzle to the valve
shall not exceed 15.0m. If, in addition to the normal control system, a manual
actuation station is required, it shall be located at grade close to the shutdown
valve in a location safe from fire exposure.
Piping to shell and tube heat exchangers shall be arranged to provide easy
removal of shell covers, channel covers, channels and tube bundles, and the
exchanger as a complete unit. In addition the piping or check valves shall be
properly located to ensure that cooling medium will remain in the exchanger
should the cooling medium supply be lost.
Inlet and outlet headers for air cooled heat exchangers shall not be located over
or under the tube areas. Piping connections to split-header bundles shall be
designed to provide necessary flexibility to accommodate movements produced
by differential temperature within the bundle.
The location of plate exchangers must be such that adequate access for
maintenance and operability is maintained. The associated pipework should be
designed and supported so that adequate clearance is given to the back of the
exchanger for cleaning/removing the plates.
Page 41 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
Multiple bay heat exchangers shall be provided with a symmetrical inlet piping
arrangement, consisting of multiple cascading headers to equalize the flow to
each bundle.
The required straight run of pipe connection to the suction of equipment shall be
in accordance with Manufacturer’s recommendation and for equipment that
operates in parallel will be of symmetrical layout, not mirror image where
possible.
To protect the pumps and compressors from ingress of harmful material, during
commissioning and initial operation, temporary fine mesh strainers shall be
provided in suction lines, as a minimum requirement, unless a permanent
strainer is required.
Where a bypass line with isolation valve is provided, the pressure rating of
bypass piping, bypass valve and suction valve shall be of the same pressure
rating as the discharge piping.
Page 42 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
13.3.1 Pumps
Suction and discharge block valves shall be located as close as possible to the
pump to permit removal of the pump without having to drain an excessive
amount of liquid.
13.3.2 Compressors
Suction scrubbers shall be located such that the piping upstream of the suction
scrubber and between the scrubber and the compressor shall drain freely to the
scrubber.
Where compressors are connected to a common header, the piping system shall
be designed to accommodate variations in piping temperatures that result from
all combinations of operating and non-operating units.
Where pulsation dampeners are provided, the suction scrubber shall be located
upstream of the pulsation dampener.
Page 43 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
14 UTILITY SYSTEMS
Piping shall be routed to avoid liquid traps, if at all possible. If liquid traps cannot
be avoided, a condensate leg with a ¾ inch block valve (with a plug or blind
flange) shall be installed at the low point.
Valved vents shall be provided at high points to release trapped air from the
piping high points. On purge gas systems, all vents shall be accessible from
platforms or deck.
Fuel gas distribution headers shall be arranged for uniform distribution of gas.
Headers shall be located above the burners and shall be provided with drains
installed at low points, complete with plugs or blind flanges.
Blanket gas regulators and valves shall be located as close to the equipment as
possible, but shall be accessible from deck or a platform.
Purge gas block valves and blow down valves shall be located as close as
possible to the loading valve or system terminating point opposite the flare
header.
Air distribution piping should be arranged with headers and sub-headers and,
where practicable, form a ring main at each deck level. Sufficient isolation valves
shall be provided to ensure that selected sections of the main, or groups of
users, can be isolated without affecting the air supply to other users.
All headers, sub-headers, branches and supply lines shall be properly sized
based on instrument air usage. The minimum size for instrument air headers
shall be 2 inch, for sub-headers 1-½ inch, and for branch lines shall be ¾ inch,
or as indicated in the respective P&IDs.
Sub-headers shall be provided, evenly spaced, along the entire length of the
header, with a minimum of 20% spare connections provided complete with block
valves and plugs or blind flanges.
Instrument air supply lines shall be taken from the top of the header, sub-header
or branch, and provided with a block valve.
Page 44 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
Air distribution piping should be arranged with headers and sub-headers and
where practicable, form a ring main at each deck level. Sufficient isolation valves
shall be provided to ensure that selected sections of the main or groups of users
can be isolated without affecting the air supply to other users.
The minimum size for utility air headers shall be 2 inch and for hose station
branches 1 inch.
Branch connections shall be located on the top of the main header, and block
valves shall be supplied for each branch connection.
Hose stations shall be provided in sufficient quantities, and located to provide full
deck area coverage utilizing hoses in 15.0m sections. They shall be mounted on
structural members approximately 1200mm above the deck shall be provided
with a 1inch ball valve and a 1 inch quick disconnect fitting.
Utility air system shall also be provided with additional connection for temporary
air compressor supply through a check valve and an isolation valve.
Page 45 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
15.1 General
Relief systems with two or more relief valves shall be designed and arranged so
that one valve does not discharge directly into the other.
Valves installed on the inlet and discharge on pressure relief valves shall be full
bore, and shall be equipped with locking devices to prevent unauthorised closing
of the valves.
When rupture disks are located upstream of a relief valve, the pressure relieving
system shall be designed so that if the disk ruptures, the fragments do not
interfere with the relief valve seating.
Page 46 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
line. Prevailing wind direction shall be taken into consideration in deciding the
location of such relief valve discharges.
Relief valves shall be connected to vessels in the vapour space above any
contained liquid.
Page 47 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
16.1 General
The design of flare and vent systems shall be as per Process Design Criteria,
document MPMY-PR-BOD-0001 and Process Design Premise, document no.
PGCA-PR-BOD-1-001.
Typically HP flare, LP flare and atmospheric vent systems shall be provided and
piping is routed via combination of lines, sub headers and headers. The KO
drum shall be provided at the low point within the flare system to collect and
recover any liquids which shall be routed back to the process. All flare system
piping shall slope down to the flare KO drum and stack piping shall slope back to
the flare KO drum.
Check valves are prohibited in this system and the use of block valves shall be
minimised. Where required block valves shall be of full bore type and locked
open position.
To prevent AIV failures, a study shall be performed for all relief and blowdown
valves piping in gas service with design pressure above 70 barg, the study shall
be in accordance with the Energy Institute Guidelines for the Avoidance of
Vibration Induced Fatigue Failure in Process Pipework.
Vent to safe location shall terminate in a vertical run and shall be located a
minimum of 3000 mm above any operating platform within a 7500 mm radius.
Any requirement for passive fire protection of the flare structure shall be
identified as part of the Fire and Explosion Risk Analysis (FERA)
Page 48 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
Vent connections, with permanent block valves, including plugs or blinds, shall
be provided at all piping high points, adequately sized to vent piping within a
reasonable period of time, but shall be ¾ inch as a minimum.
Where pump vents are connected to vapour space of vessel to facilitate priming
or for operation under vacuum, such vents shall be provided with one isolation
valve at the pump end and the other isolation valve at the vessel end.
Drain connections with permanent block valves shall be provided at all piping
low points, sized to drain the piping within a reasonable period of time under
gravity conditions, i.e. not pressurized. As a minimum, drains shall be ¾inch on
lines unless specify otherwise in P&IDs.
The open drain systems shall ensure that water will drain properly and does not
stand or pond at any location. Separate hazardous and non-hazardous gravity
drain headers shall be provided, as required, for each deck level. A minimum
slope of 1:100 should be maintained for open drain system and free draining for
closed drain system.
Drain headers shall be located below the deck level. Liquid seals shall be
provided for all hazardous open deck drains and at each header and to main
drain down comer interface.
Sizing of sanitary drains shall be based on Uniform Plumbing Code fixture unit
values. The minimum size for any single branch into a header shall be 4inch.
The minimum size for any header containing the flow of two or more branch lines
shall be 6 inch. All sanitary drain piping shall slope a minimum of 1/50 of pipe
run.
Page 49 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
18.1 General
Fire water on the facility shall be distributed via a ring main system. The fire
water ring main will supply all of the automatic / manual fixed water systems,
which include fire water deluge systems, monitors, hydrants and hose reels. The
firewater system shall be designed in accordance with the relevant NFPA
requirement.
The fire water ring main shall be routed in such a way as to minimize the risk of
damage from dropped object, fire and explosions. Readily accessible manually
operated isolation valves are to be installed within the fire water ring main to
allow for isolation of any damaged sections or for general maintenance activities.
Fire water system piping shall use GRE for all pipe sizes. Maximum velocities
considered for fire water system piping during full flow condition are 5 m/s for
continuous service and 10 m/s for intermittent service.
Page 50 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
19.1 General
Equipment Layouts shall reflect the overall design philosophy and geometry of
the facility, and show the outline and location of all major equipment as specified
by all disciplines. The drawings shall also show main access and maintenance
ways, drop- out and loading areas, and fire/blast walls. Perimeter dimensions
and dimensions between main grid lines shall be shown.
The equipment layouts shall provide the basis for other disciplines layout
drawing requirements, and shall be updated to reflect any approved changes
found necessary.
True north, platform north and prevailing wind direction shall be shown, and all
elevations shall be taken from the Mean Sea Level (MSL).
Page 51 of 52
Doc. Title : PIPING DESIGN PREMISE
Rev. No. : C2
Piping plans shall be prepared to provide an overview of the piping layout and
pipe support locations at agreed elevations throughout the facilities, supported
by sections to clarify the piping plans, in particular flowlines, and the assembly
between piping and equipment or vessels.
Standard pipe support details may be developed and utilised where this is
considered advantageous. Full calculations shall be provided for COMPANY’s
review for all standard drawings. For special pipe support, detail drawings of
each pipe support shall be provided.
Shop and/or spool drawings shall be provided for fabrication purposes only.
Page 52 of 52