Professional Documents
Culture Documents
NOTES Project Network Diagrams
NOTES Project Network Diagrams
Introduction
A project is composed of :
o Activities and
o Events
Activities are represented by arcs (Arrows)
o Are directed. This the activity must take place after the occurrence of
the first node in order for the second node to be obtained
Activities have a duration
Events are represented by nodes (circles)
o Well defined occurrence in time
The direction of the arrow determines the precedence relationship
between events (nodes)
Use dummy variables to avoid loops. The leads to the following additional
rules;
o The network should contain no loops
o Each event along a path must have all preceding events and activities
completed before it can be realised
Dummy variables have zero duration and utility
Slack time
The slack time associated with each node is the difference between the latest
and earliest time
The slack time represents the expected delay that can be tolerated when
reaching a node that causes no delay in the time to complete the project.
For the HK international airport example (next page), nodes 1,4,5 and 6 have
zero slack time. Node 2 has 2 years of slack time. Node 3 has 1 year of slack
time.
The critical path (which identifies the important activities not to delay) goes
through the nodes with zero slack time.
Remember dummy variables have no duration, so
the latest time for node 2 is 4-0=4
A 10 -
B 5 -
C 5 -
D 10 C
E 10 A, B, D
F 17 A, B, D
G 10 A, B, D
H 5 G
Practice: 1
Construct a activity network diagram to represent the following
dependencies
o B & C both follow A
o D follows B
o E follows C
o D & E precede F
Practice: 2
Draw the activity network diagram for the following project
o U is the first activity
o S and L can proceed simultaneously when U is finished
o P and T begin when L is finished and can go on together
o H follows T
o Z follows H
o N and A can start after S
o O follows N
o O, A, P and Z must all be done before R, the last activity of the
project, can begin
Practice: 3
Draw the activity network diagram for the following project
o U is the first activity
o S and L can proceed simultaneously when U is finished
o P and T begin when L is finished and can go on together
o H follows T
o Z follows H
o N and A can start after S
o O follows N
o O, A, P and Z must all be done before R, the last activity of the
project, can begin
Practice: 4
Given the precedence relationships in the following table draw the project
network diagram and identify the critical path