CONCRETE INITIAL SETTING TIME TEST

Contractor : PT. ADHI KARYA (Persero) Tbk


Project : LRT LINTAS PELAYANAN 2 CAWANG DUKUH ATAS - JAKARTA
Class of Concrete : FC 33,2 FA 15% R- 8 JAM
Slump : 20 ± 2 CM
Date : 30-Oct-19
PENETRATION
ELAPSE TIME SINCE
NO CHECK TIME BEARING TIME OF MIXING = 11 : 36 WIB
MIXING (hour)
(Lbf/inch²)

1 11 : 50 0 0.23 Keterangan :
2 20 : 00 0 8.40 - Initial setting time terjadi selama 17 : 30 Jam
3 23 : 00 0 11.40 Initial setting time terjadi jika jarum alat penetrasi
4 00 : 00 0 12.40 menunjukkan angka 500 ( lbf/inch² )
5 02 : 00 10 14.40 ASTM C 403
6 03 : 00 60 15.40 - Pada jam : 11 : 36 sampai jam : 00 : 00
7 03 : 45 90 16.15 pembacaan pada penetrometer masih menunjukkan
8 04 : 15 170 16.65 angka 0 ( Nol )
9 04 : 30 250 16.90
10 04 : 45 340 17.15

11 05 : 00 460 17.40

12 05 : 15 560 17.65

CURVE of PENETRATION BEARING vs TIME


700
BEARING SCALE (lbf/inch²)

600
PENETRATION

500

400
Penetration Bearing
300 Initial stting time limit

200

100

0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

ELAPSE TIME SINCE MIXING (hour)

Tested by : Eko Cahyono Date : 30 October 2019


Checked by : Anton Junaedi Date : 31 October 2019