Download as pdf or txt
Download as pdf or txt
You are on page 1of 28

New Deep WSDOT Standard

Sections Extend Spans of


Prestressed Concrete Girders
This paper discusses the new deep precast, prestressed concrete
girder sections that have been adopted as Washington State
Department of Transportation (WSDOT) Standards. Members of the
Pacific Northwest Precast/ Prestressed Concrete Institute, in
cooperation with WSDOT and other affected support industries,
deve loped sections that are deeper and will span further than
previously available WSDOT Standards. Wider spacings and fewer
girder lines can also be used for spans in the range of previous
Stephen J. Seguirant, P.E. WSDOT Standards. The sections are available in both single-piece,
Director of Engineering pretensioned and multiple-piece, post-tensioned segmental
Concrete Technology Corporation versions. This paper discusses practical considerations in
Tacoma, Washington
deve loping the concrete outline, pretensioned span capabilities,
and handling and shipping considerations. An appendix section
provides sample handling and shipping calculations for the longest
girder section and highest level of pretensioning.

ince the early 1960s, precast, have been jointly refined to provide

S prestressed concrete has been


the material of choice for
bridge superstructures for the Wash-
top quality bridge products while si-
multaneously improving production
efficiencies.
ington State Department of Trans- At the 1996 meeting, the author pro-
portation (WSDOT). Consequently, posed that industry and WSDOT
WSDOT has many years of experi- jointly develop new girder sections
ence with the design and use of struc- that would be deeper and span further
turally efficient girder sections. Since than the standard WSDOT sections
1989, the Pacific Northwest Precast/ available at the time. WSDOT enthu-
Prestressed Concrete Institute (PNW/ siastically agreed , and asked industry
PCI) has met annually with WSDOT to take the lead in developing the sec-
to discuss subjects of mutual interest, tions . A wide variety of people have
developing a sense of mutual coopera- been consulted during the develop-
tion. Over this period, WSDOT's ment of the sections , including pro-
Standard Plans and Specification s ducers , contractors, truckers, aca-

92 PCI JOURNAL
demics , and consulting engineers, as the NU girder series• developed at the The section also featured a relatively
well as WSDOT bridge design, bridge University of Nebraska under a PCI- thin and wide top flange. The concrete
rating, construction and transportation sponsored fellowship. The primary outline, dimensions, and section prop-
permitting personnel. This process has goal of the fellowship was to develop erties of the NU girder series are given
been very similar to that described by a girder section that is highly efficient in Ref. 4.
Bardow et al. 1 in the development of in continuous span applications. The For the purpose of adapting this
the New England Bulb-Tee Girder. resulting girder section featured a rela- girder series as standard WSDOT sec-
This paper documents the develop- tively wide bottom flange to enhance tions, several modifications were made
ment of WSDOT's new deep precast, compressive strength in negative mo- to the NU girders. The concrete outline,
prestressed concrete girder sections. ment regions, and to accommodate a dimensions, and section properties of
"Deep" is defined as depths exceeding large number of pretensioned strands. the new WSDOT sections are shown in
those previously available, the deepest
of which was a W74MG girder [1865
mm (73 .5 in .)]. The new section
depths are 2100 and 2400 mm (82.68
and 94 .49 in .). This increases the
available range of depths in approxi-
mate increments of 300 mm (11.81 /15 STIRRUP IAAX.

in.). The sections are detailed in hard


metric units. The primary goal of the
15.2.... SlRAND
study was to increase the span range
capability of standard prestressed con-
crete girders, and to improve economy
by increasing the allowable girder
spacing over previous designs.
Throughout this paper, girders will
be described as pretensioned or post-
tensioned. Pretensioned girders refer
to members that are fabricated,
shipped and erected as one piece with
pretensioned strands as the only
s ource of the prestres s ing force.
Where applicable, pretensioned gird-
ers are more economical than post- Fig . 1. Pretensioned web configuration .
tensioned girders.
Post-tensioned girders are fabricated
in two or more pieces per span and are
subsequently post-tensioned together.
The source of the prestressing force in
post-tensioned girders may be the
post-tensioning tendons acting alone
or may be a combination of preten- 15 STIRRUP
lA AX.
sioned and post-tensioned strands.
Many scenarios exist for assembling
post-tensioned girders. 2 Due to several
considerations (primarily, weight),
post-tensioned girders provide a much
larger span range than pretensioned
girders.
The new girder sections were de-
veloped using the latest available
technical information, including the
1994 AASHTO LRFD Bridge Design
Specifications. 3
25 110 DUCT
COVER
SECTION DEVELOPMENT SAY 200

The starting point for the develop-


ment of the new girder sections was
Fig. 2. Post-tensioned web configuration.

July-August 1998 93
x
u-<
(/) z:::i
335 75 155 0
0~
~z <o
m< fllz
~I!:
_ (/)
:::l
~m
~ ..... OQ:
<G ZUJ
:::l!l.

~g m(/)
oo
FVl zz
Vi. <<
o...-
Cl.C'I
!!:!!'
(/)VI
""'.,;
~-
....,Q:
fi:l~
...
0 &:-n
<-
:I:'"'
e.

(/)
0 UJI()
..... C.:o u .....
N (/)II)
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 ~.
0

0 (/)
~ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

7 SP. 0 50 65

Fig. 3. Pretensioned bottom flange configuration.

Appendix B. The designations for the versions of the sections are called the General Mod ifications
new pretensioned girders are W21MG W21PTMG and W24PTMG girders. As can be seen in Ref. 4, the NU
and W24MG for the 2100 and 2400 Modifications to the NU girders, and girder series has curved surfaces at
mm (82.68 and 94.49 in.) deep sec- the reasons for those modifications, are both the flange edges and the flange/
tions, respectively. The post-tensioned discussed in the following sections. web junctures. The intent of the curved
surfaces is to improve aesthetics and to
facilitate placement and consolidation
of concrete in the wide bottom flange .
Discussions with form fabricators indi-
cated that forms would be somewhat
easier to fabricate with sharp breaks at
the flange edges and with fillets in lieu
of curved surfaces at the flange/web
/15 STIRRUPS IAAX.
junctures. In particular, transitions
P.T. DUCT (110 MAX. 0.0.) from end blocks to web sections in
some post-ten sione d applications
would be easier to accommodate.
Most importantly, WSDOT ex-
pressed a preference for sharp edges
and fillets in lieu of the curved sur-
faces. Accordingly, sharp edges and
fillets have been detailed into the new
sections, as shown in Appendix B. It is
anticipated that the fillet at the junc-
ture of the bottom flange and web will
facilitate concrete placement and con-
solidation in a manner similar to the
165
curved surface of the NU girder.

51 0 We b Width
For preten sio ned girders, a web
width of 155 mrn (6.10 in.) was cho-
Fi g. 4. Post-tensioned bottom flange configuration. sen for the new sections in lieu of 150
94 PCI JOURNAL
mm (5.91 in.) for the NU girders. This maximum aggregate size of 19 mm has chamfered bottom edges, sharp
was derived as shown in Fig. 1. This (0.75 in.). ACI 318-95 5 requires a top edges, and a 75 mm (2.95 in.) fillet
width allows for 15.24 mm (0.60 in.) clear distance between obstructions of in lieu of the curved juncture between
diameter harped strands on 50 mm at least 1.33 times the maximum ag- the flange and web. Although this con-
(1.97 in.) centers, #5 stirrups, and 25 gregate size. With the type of external figuration is slightly thinner than the
mm (0.98 in.) of concrete cover. vibration commonly used on these NU girder, it still provides more than
For post-tensioned girders, a web forms , consolidation of concrete adequate cover over the strand and
width of 200 mm (7.87 in.) was cho- below and around the ducts is not an- mild steel reinforcement. This small
sen for the new sections in lieu of 175 ticipated to be a problem. decrease in the bottom flange thick-
mm (6.89 in.) for the NU girders. This ness was done primarily as a weight
was derived as shown in Fig. 2. The saving measure. With the extended
110 mm (4.33 in.) duct size accommo- Bottom Flange lengths of the pretensioned sections,
dates commercially available post- The bottom flange of the new girder small increases in weight per unit
tensioning systems of up to nineteen is shown in Fig. 3 for pretensioned length add up quickly.
15.24 mm (0.60 in.) diameter strands sections and in Fig . 4 for post-
per tendon, or twenty-nine 12.70 mm tensioned girders. The WSDOT sec-
(0.50 in.) strands per tendon. tion is shown in heavy lines while the Top Flange
Also, the clear distance between the NU section is shown in thin lines. The The top flange of the new girder is
duct and form side is 45 mm ( 1. 77 WSDOT configuration is 5 mm (0.20 shown in Fig. 5 for pretensioned sec-
in.), which is more than twice the in.) thinner than the NU girder series, tions, and in Fig. 6 for post-tensioned

Fig. 5 .
Pretensioned top flange
1245
configuration .

~--------4~7~0--------~~
Fig. 6.
Post-tensioned top flange
configuration .

July-August 1998 95
sary to maintain the stability of the
girder, as discussed later in this paper.
500
For safety reasons , the slope of the
406 harped strands should not exceed 8
{MAX)
horizontal to 1 vertical. This maxi-
mum slope is somewhat arbitrary at
this time because strand manufacturers
have not been able to provide a maxi-
mum safe slope for pretensioned 15.24
mm (0.60 in.) diameter strand.
For post-tensioned girders, the ten-
don layout at midspan is shown in
Fig. 4, and at the anchorage locations
0
N
in Figs. 7 and 8. Anchorage locations
.... may vary depending on the size of
0
8 ...u
Vl the anchorage. The minimum 25 mm
c::i <
a..
(0 .98 in.) clear distance between
Vl
ducts should be maintained through-
e out the entire length of the tendon
until the individual ducts diverge into
the anchorages.
Where neces s ary, pretensioned
strands can be added to supplement
the post-tensioning tendons and to
carry loads imposed on the girder
prior to post-tensioning. Harped pre-
Fig. 7. tensioned strands should be avoided
Post-tensioned end block unless they can be arranged so as not
configu ration. to interfere with the post-tensioning
ducts and anchorages. Concrete
stresses at the girder ends at the re-
girders. Again, the WSDOT section is 15.24 mm (0.60 in.) diameter strands
at 50 mm (1.97 in.) on center must be lease of straight pretensioned strands
shown in heavy lines while the NU
can be controlled by debonding a pre-
section is shown in thin lines. Both the used to realize the full potential of the
determined number of strands for
top and bottom flange edges of the sections. The bottom flange can ac-
new sections are sharp, and again a 75 commodate 46 straight strands. some distance from the ends.
mm (2.95 in.) fillet rep laces the Harped strands are arranged in a maxi-
curved juncture between the flange mum of nine strands per bundle at 75 End Blocks and Transitions
and web. mm (2.95 in.) spacing between the Figs. 7 and 8 show that four post-
The flange has been thickened with harp points. Harp points are assumed tensioning anchor plates up to 406 mm
respect to the NU girder, increasing to be at 40 percent of the span length (16.00 in.) square can fit in the end of a
from 65 to 75 mm (2.56 to 2.95 in.). In from the centerline of bearing, and the W21PTMG girder with the addition of
addition, the slope on the bottom of ratio of straight to harped strands is as- a 500 mm (19.69 in.) wide end block.
the top flange has been increased over sumed to be approximately 2 to 1. This is thought to be the largest com-
that of the NU girder series to be more All calculations in this paper assume mercially available anchor plate for the
in line with current WSDOT standard the top pair of harped strands exit the tendon sizes noted previously. "Spe-
girders. Based on experience, both the girder ends at 50 mm (1.97 in.) from cial" anchorages , as defined by the
flange thickening and slope increase the top of the girder. However, in de- 1994 AASHTO LRFD Bridge Design
were deemed necessary to prevent sign, the location where the harped Specifications, are smaller than plate
chronic problems with cracking of the strands exit the girder ends should be anchorages and will easily fit in the
top flange when removing the forms. held as low as possible while still same end block. The end block length
maintaining the concrete stresses is 1000 mm (39.37 in.) with a transi-
within allowable limits (the center of tion length of 1500 mrn (59.06 in.).
Strand Configuration gravity of all strands at or slightly End blocks and transitions are only
For pretensioned girders, the config- above the lower kern). This will re- required where the post-tensioning an-
uration of straight strands and harped duce the demand on the pretensioning chorages are intended to be embedded
strands between the harp points is abutments. in the girder ends. This most fre-
shown in Fig. 3, and the harped strand The exit location of the harped quently applies to girders that are fab-
pattern at the girder ends is shown in strands is strongly dependent on the ricated in one piece and post-tensioned
Fig. 5. Due to the size of the girders, handling and shipping schemes neces- in the producer' s yard (in cases where
96 PCI JOURNAL
tions and the NU girder series will be
made later in this paper.
END OF
GIRDER
PRETENSION ED
SPAN CAPABILITIES
The span capabilities of the new
WSDOT pretensioned section s are
highly dependent on the assumptions
made in the design. The following sec-
tion presents the design criteria used
0

•"'0 to develop the baseline span capability


0 (/)
envelopes . In general , these are the
0
c;; ~
a..
same criteria used by WSDOT to de-
(/) sign prestressed concrete girders. Sub-
Ill sequent sections show the con se-
quences of varying specific design
assumptions on span capabilities. All
span capabi lities are shown in U.S.
Customary Units.

Design Criteria for


Pretensioned Girders
Fig. 8. Post-tensioning anchor layout. The design criteria used to develop
the baseline span capability envelopes
for pretensioned girders are as follows :
the precasting plant does not have suf- Aswad 7 proposed an efficiency ratio
1. 1994 AASHTO LRFD Bridge
ficient pretensioning capability) or based on the stress in the bottom
Design Specifications.
when girders are assembled and post- fibers. This efficiency ratio, a , is de-
2. Dead Load: Girder + Deck + 50
tensioned on the ground and erected in fined as:
psf (2.39 kPa) + Concrete Diaphragms
one piece. When girders are assem-
at 40ft (12.19 m) maximum.
bled in place, it is usually most conve-
3. Vehicular Live Load: AASHTO
nient to embed the post-tensioning an-
HL-93, including 33 percent impact
chorages in large end diaphragms, where on truck portion only.
which can be easily reinforced to
withstand the large concentrated
sb = section modulus for bottom 4. Limit States: Service-! (Compres-
fibers s ion) and Service-III (Tension) ,
forces generated by the post-tension-
Ae =cross-sectional area Strength-I.
ing process.
h = depth of section 5. Live Load Distribution: Approxi-
Different girder cross sections from mate method for both flexure and
Girder Efficiency across the country have been com- shear, interior beams.
Two formulas have been proposed pared using these formulas. 8 Figs . 9 6. Girder Spacing: 5 to 10ft (1.52 to
for assessing the efficiency of pre- and 10 show plots of these efficiency 3.05 m).
stressed concrete flexural members. factors for various types of girders . 7. Concrete:
Guyon 6 proposed an equation based on As can be seen , the new WSDOT - Girder J:= 10.0 ksi (68 .95
maximizing section moduli for the top pretensioned girders rank among the MPa) , w e = 156 pcf (24 .51
and bottom fibers for a given cross- highest efficiency factor s. When kN/m 3)
sectional area. This efficiency factor, compared to the NU girders, calcula- J:
- Deck = 6.0 ksi (41.37 MPa) ,
p, is defined as: tions indicate that, depending on we = 155 pcf (24.35 kN/m 3)
which formula is used , the proposed - Ye = 160 pcf (25 .13 kN/m 3) used
sections are either slightly more or in weight calculations
slightly less efficient than their NU - f/; = 4.0 ksi (27.58 MPa) mini-
where counterparts. Because WSDOT does mum
r = radius of gyration of section not allow tension in the bottom fibers 8. Deck Thickness : 7 .87 in . (200
= -JI! Ae under service loads, the Aswad effi- mm), unshored , inc l uding 0 .5 in .
y 1, Yb = distance from center of gravity ciency ratio may not be an appropri- (12.70 mm) wearing surface.
to top and bottom fibers, re- ate indicator of the efficiency of the 9. Prestressing: 0.6 in. (15 .24 mm)
spectively section for its intended use. A direct diameter, 270 ksi (1862 MPa) , low-
I= moment of inertia comparison of pretensioned span ca- relaxation strand, /po = 202.5 ksi ( 1396
Ae = cross-sectional area pabilities of the new WSDOT sec- MPa).
July-August 1998 97
translates into a maximum single-
piece girder length of approximately
185 ft (56.39 m). Subsequent sections
will examine the influence of varying
design assumptions on this envelope.
AASHTO/PCI Girders The span capability envelope of the
W24MG girder section is shown in
Fig. 12. The maximum single-piece
girder length is approximately 172 ft
(52.42 m) . The influence of varying
design assumptions on this envelope
will be similar to that of the W21MG
girder.
Fig . 11 contains a dotted line la-
beled "over-reinforced." For sections
to the right of this line, the ratio of the
depth of the neutral axis to the mo-
ment arm of the prestressed reinforce-
ment exceed s the limit of 0.42
Fig. 9. Guyon efficiency factors (Ref. 6). (AASHTO LRFD Section 5.7.3.3 .1).
For these cases, the equation given for
the maximum nominal flexural resis-
tance of over-reinforce d sections
(AASHTO LRFD Section C5.7 .3.3 .1)
is used . Over-reinforced sections do
not occur in the pretensioned range of
the W24MG girder. Further discussion
NU Girders
New WSDOT Girders of over-reinforced sections will be
provided later in this paper.

Prestress Losses
One of the most significant vari-
ables influencing the span capability
of prestressed concrete girders is the
method used to calculate long-term
prestress losses. Fig. 13 plots calcu-
lated prestress losse s for W21 MG
girders at a 10 ft (3 .05 m) spacing
using four different methods. The PCI
General Method 9 · 10 is a time-step cal-
culation that considers the interaction
Fig. 10. Aswad effic iency factors (Ref. 7). of the different components of los s
during successive intervals of time.
The other three methods result in lump
10. Prestress Losses: AASHTO Compression= 0.6(f;;)
sum values for the final prestress loss.
LRFD Approximate Lump Sum A simple span design is assumed for
For this particular girder configura-
Method or AASHTO LRFD Refined all loads.
tion , the AASHTO LRFD Refined
Method, whichever results in less cal-
Method results in the greatest calcu-
culated loss. Pretensioned Simple Span lated loss , while the method recom-
11. Allowable Stresses: Capabilities
mended by ACI-ASCE Committee
At Service: The span capability envelope for the 423 " results in the least.
Tension= 0 W21MG girder section is shown in The influence of calculated long-
Compression due to perm a- Fig. 11. This envelope assumes that term prestress losses on the span capa-
nent loads = 0.45(!;) the maximum pretensioning capability bility envelope of a W21MG girder is
Compression due to all loads of precasting plants in the Northwest shown in Fig. 14. For the entire range,
= 0.6(j/) is sixty-four each 0.6 in. (15.24 mm) the loss of span capability from one
At Release: diameter strands, and that 200 kips extreme to the other is 5 to 13 percent.
Tension= 0.22-Jl: (889.6 kN) is the maximum weight At higher levels of pretensioning, the
Uc: in ksi) that can be handled and shipped. This available span can be reduced by more
98 PCI JOURNAL
than 18ft (5.49 m). This will undoubt-
edly be accentuated with the longer-
span post-tensioned girders.
Pessiki et al.' 2 have recently evalu-
ated the effective prestress force in
two 28-year-old prestressed concrete
bridge beams. Their conclusion was
that the ave rage actual loss experi-
enced by these beams was approx i-
mately 60 percent of the losses pre-
dicted using curren t calcu lation
methods. Similar results have been re-
ported over the past decade.' 3· 14
The beam section studied by Pessiki
et al. is shown in Fig. 15, along with
material and section properties. Some
properties were measured and
recorded in the study, while others
were assumed for the sake of calcula-
tion. Prestress loss values calcu lated Fig. 11. W21 MG span capab ili ty envelope.
by the fo ur methods described above,
as compared to the measured losses,
are shown in Table 1.
All predicted values overestimate
the actual losses, with the ACI-
ASCE Committee 423 Method pro-
viding the closest estimate. For the
purpose of this paper, subsequent
sections will use either the AASHTO
LRFD Approximate or Refined
Methods, whic hever results in the
lesser va lue. However, significant
benefits can be derived from using a
more rigorous method for calculating
prestress losses. WSDOT has devel-
oped their ow n time-step, rate-of-
creep method, which is used to eval-
uate prestress lo sses in prestressed
concrete girders outside of the usual
design range .

Design Specification
Fig. 12. W24MG span capability envelope.
Fig. 16 compares the span capabi lity
envelopes for the W21MG girder sec-
tion using both the 1994 AASHTO
LRFD Bridge Design Specifications Allowable Tension tension in the precompressed tensile
and the 1996 AASHTO Standard Another significant variable influ- zone under service loads.
Specifications for Highway Bridges, encing span capabi lity is the amount Fig. 17 shows the impact on span ca-
16th Edition. " To ensure a consistent of tension all owed in the precom- pabilities of the W21MG girder section
comparison of the design specifica- pressed tensile zone at the service for the three levels of allowable tension
tions, minimum prestress losses as cal- limit state. The 1994 AASHTO LRFD noted above. There are several ways to
culated by the AASHTO LRFD Ap- Bridge Design Specifications allow interpret this chart. On the vertical axis,
proximate or Refined Methods are 0.19 Jl: (formerly 6 Jl: for J: in psi) each interval of allowable tension rep-
used for both envelopes. The differ- tension for all components not sub- resents a savings of between four and
ence between the two envelopes is jected to severe corrosive conditions. five strands for the same span and
nominal , indicating that the choice of Tension in components subjected to girder spacing, along with the concur-
design specification has little impact severe corrosive conditions is limited rent reduction in required concrete re-
on the span capabilities of the girder to 0.0948 Jl: (formerly 3 Jl: for J: in lease strength. This is probably the
sections. psi). Currently , WSDOT allows no least consequential interpretation.
July-August 1998 99
WSDOT has selected a standard
deck thickness of 8.86 in. (225 mm)
with a 0.39 in. (10 mm) wearing sur-
face for use with the new deep girder
sections.

Deck Strength
Fig. 19 compares envelopes for an
8.86 in. (225 mm) thick deck at
strengths of 4.0, 5.0, 6.0, and 8.0 ksi
(27.58, 34.48, 41.37, and 55.16 MPa).
Within the envelope range where al-
lowable stresses govern the design, the
increased deck strength marginally in-
creases the available span range. How-
ever, deck strength has a significant
impact on the point at which the sec-
tions become over-reinforced, as well
as the point at which the flexural
Fig. 13. Prestress loss comparison . strength becomes inadequate. A deck
strength of 8.0 ksi (55 .16 MPa) elimi-
nates over-reinforced sections from
the available span range. A deck
strength of 6.0 ksi (41.37 MPa) pro-
vides adequate flexural strength
throughout the range. In general, it ap-
pears to be more efficient to increase
the strength of the deck instead of its
thickness, although stronger decks can
pose other problems, such as obtaining
a satisfactory fini sh on the wearing
surface.
WSDOT currently specifies a stan-
dard deck strength of 4.0 ksi (27.58
MPa). It may be necessary to increase
this strength in the upper reaches of
the pretensioned span range to ensure
adequate flexural strength. However, a
few design criteria modifications can
be used to help alleviate this problem.
First, typical design practice conserva-
Fig. 14. Prestress loss envelope comparison. tively neglects the area of the top
flange of the girder when calculating
the depth to the neutral axis. For these
On the horizontal axis, each allowable rived assuming a 6.0 ksi (41.37 MPa), sections, the top flange provides a rel-
tension interval represents an increase in 7.87 in. (200 mm) thick deck with a atively large area of high strength con-
span capability of between 5 and 10 ft 0.5 in. (13 mm) wearing surface. Fig. crete, which effectively reduces the
(1.52 and 3.05 m) for the same number 18 compares this baseline envelope depth to the neutral axis .
of strands and girder spacing. The most with envelopes for 8.86 and 9.84 in. Also, WSDOT currently designs all
significant interpretation is that for each (225 and 250 mm) thick decks, all at girders as simple spans, though they
allowable tension interval, the same strengths of 6.0 ksi (41.37 MPa). Deck are made continuous for dead loads
girder section can be spaced roughly 1 ft thickness is typically a function of applied subsequent to the deck pour,
(0.30 m) further apart. This can lead to girder spacing rather than girder depth. and all live loads, with mild steel rein-
considerable savings if one or more lines The increased weight of the thicker forcement in the deck over the piers.
of girders can be eliminated. deck predictably reduces the available Some reduction in midspan positive
span, though not by a large amount. moments due to continuity would help
Deck Thickness The increased deck thickness also in- reduce the demand on the deck.
As previously mentioned, the base- creases the available span range before Finally, a more rigorous analysis
line span capability envelopes were de- the members become over-reinforced. procedure, such as strain compatibil-
100 PCI JOURNAL
ity , can be employed to determine the
flexural resistance of the member.
Section 8.2.2.5 of the PCI Bridge De-
sign Manual '6 provides a rational ap-
proach to strength calculations.

Comparison with the


Pretensioned NU Girder Series
Fig. 20 plots the span capability en-
velopes of the W24MG and the
NU2400 girder sections. These en- bco
•Cll
N
8"
.
0
co
•Cll
N

velopes are virtually identical, with


the exception of the maximum single-
piece girder length. Because the
W24MG section is slight ly heavier
than the NU2400, its length is limited
to 172ft (52.42 m) vs . 180ft (54.86
m) for the NU2400 .
There is no direct counterpart for
the W21MG girder section in the NU
series, so no comparison of span capa-
bility was made.
CENTER PORTION OF BEAM Cj:_ OF BEARINGS
Concrete Strengths
The required concrete release
strengths are shown in Fig. 21 for dif- Section Properties:
ferent span and strand configurations . Ac = 848 in: bdeck = 95.63 in. !deck= 8.00 in.
These strengths were calculated as- I= 355, 185 in! l c = 800,980 in! lg = 90.42 ft
suming the lifting devices are located Yb = 28.31 in. Ybc = 42.94 in. lspan = 89.00 ft
to ensure a minimum level of stability
during stripping without additional Measured or Known Properties:
bracing . The required strengths range Girder concrete: f c'= 8440 psi
from a minimum of 4.0 ksi (27 .58 Strand: (50) 7/16 in. Diameter, 270 ksi, Stress-Relieved
MPa) to a maximum of over 8.0 ksi /,o = 189 ksi
(55.16 MPa) . Overnight strengths of Distance from centerline to harp point = 14 ft
up to 7.2 ksi (49 .64 MPa) have been Volume-to-surface ratio= 4.67
consistently attained at Concrete Average relative humidity= 70%
Technology Corporation (CTC) with
concrete mixes containing silica fume. Assumed Properties:
Higher release strengths can be
Girder concrete: .f~ = 4000 psi
achieved on an every-other-day basis
W e = 155 pcf
with added cost.
As mentioned previously, the design Deck concrete: f;= 5000 psi
concrete strength used to develop the W e = 155 pcf
span capability envelopes was 10.0 ksi Strand: E, = 28500 ksi
(68 .95 MPa). This value is the maxi- Superimposed dead load = 25 psf
mum that PNW/PCI members feel
they can consistently achieve at this
Fig. 15. Beams studied by Pessiki et al. (Ref. 12).
time . However, it should be empha-
sized that specific projects will not
usually require design strengths of this Table 1. Ca lcu lated prestress losses for beams stud ied by Pess iki et al. (Ref. 12).
magnitude. Based on flexure only, if
Method ES (ksi) SR (ksi) CR (ksi) REL (ksi) Total (ksi)
the span capability envelope of Fig. 11
were replotted for 6.0 ksi (41.37 MPa) AASHTO Refined 13.56 6.50 17.47 16.27 53.80
concrete in the girder, the span capa- AASHTO Approximate 13.56 - - - 50.55
bility is reduced by less than 0.5 per- PCI General 10.84 8.56 9.19 18.65 47 .24
cent. Of course, this limits the range of ACI-ASCE Committee 423 13.15 5.05 10.74 15.66 44.60
available span and spacing configura-
Average measured losses - - - - 34
tions to those below the line labeled
July-August 1998 101
J/; = 6000 psi (41.37 MPa) in Fig. 21.
The applied criteria of zero tension
and simple spans results in the con-
crete strength at release governing the
design. Zero tension is zero tension ,
whether it is applied to 10.0 ksi (68.95
MPa) concrete or 6.0 ksi (41.37 MPa)
concrete. Simple spans place the de-
mand for compression resistance in
the cast-in-place deck, rather than in
the girder. This would not be the case
for girders made continuous, or for
girders in which tension is allowed at
the service limit state.
Additionally, industry statistics have
shown a strong correlation between
concrete release strength, curing time
and temperature, and the design con-
crete strength . For a given mix design,
the more aggressively the concrete is Fi g. 16. Design specification comparison.
cured to achieve a high release
strength , the lower the long-term
strength will be. Consequently , it is
recommended that both the release
and design concrete strengths be spec-
ified as the minimum required by de-
sign for the specific project, rounded
up to the nearest 0.10 ksi (0.69 MPa),
but not less than 4.0 ksi (27.58 MPa)
at release and 7.0 ksi (48.27 MPa) at
28 (or 56) days.

Section Finalization
In the interest of finalizing the new
WSDOT sectio ns, PNW/PCI and
WSDOT separately retained the ser-
vices of BERGER/ABAM Engineers
(B/A), Inc., Federal Way, Washington,
to provide final detailed engineering
and drafting of the Standard Plans for
pretensioned sections only. PNW/PCI
assumed responsibility for providing Fig. 17. Allowable tension compari son.
engineering calculations and sketches,
while WSDOT provided funding for
drafting. The scope of the work B/A 4. For girder ends that tie directly 7. Size the worst-case intermediate
performed included the following : into piers or hinge s through shear cast-in-place concrete diaphragm ,
1. For sections between the end of friction, evaluate the size and dis- and modify the standard detail s
the girder and dv , size the required tance from the girder end to the tem- accordingly.
web reinforcement to resist the worst- porary oak blocks that support the Performance of this scope of work
case bursting and splitting forces. girders during construction. Also , resulted in the generation or modifica-
2. For sections dv from the center of evaluate the quantity of shear friction tion of 28 Standard Plan sheets, half of
beari ng and beyond, evaluate the re- reinforcement projecting from the which were in U.S. Customary Units,
quired web reinforcement for shear end of the girder. the other half in S.I. Units. Appendix
based on the AASHTO LRFD Specifi- 5. Size and detail high strength lift- C contains the Standard Plans for the
cations. ing bars for girders weighing more W21MG section . These plans have
3. Evaluate the maximum required than the capacity of standard lift loops. been stamped "Preliminary" because
bearing pad size and distance from the 6. Provide sample calcu lations for they had not yet been fmalized at the
end, and modify the standard detail s evaluating the stability of the girders time they were submitted for thi s
accordingly. during lifting. paper.
102 PCI JOURNAL
(1.83 m) girder spacing. Allowing
some tension at the service limit state
can increase the girder spacing, or re-
duce the required number of strands.
The current standard W74MG section
can span up to 160ft (48.77 m) at a
4 ft ( 1.22 m) girder spacing. Due to
weight considerations , the length of
the W24MG section is limited to 172
ft (52.42 m). Consequently, the pri-
mary section for extending preten-
sioned girder spans is the W21MG .
The second primary use of the new
WSDOT girder sections is to improve
economy by increasing the girder
spacing over designs using existing
standard girders. As discussed above,
the W74MG ca n span up to 160 ft
(48.77 m) at a 4 ft (1.22 m) girder
Fig. 18. Deck thi ckness comparison. spacing . The same span can be
achieved with a W21MG girder at a 9
ft (2 .74 m) spacing , or a W24MG
girder at nearly 11 ft (3.35 m). The
number of girder lines required per
span can be significantly reduced for
bridges that can tolerate the additional
superstructure depth .

HANDLING AND SHIPPING


OF DEEP GIRDER SECTIONS
Considerations for handling and
shipping deep girder sections relate
primarily to weight, length , height and
lateral stability. The effect of each
variable differs considerably depend-
ing on where the handling is taking
place: in the plant, on the road , or at
the jobsite.

In-Plant Handling of
Fig. 19. Deck strength comparison. Deep Girder Sections
The primary considerations for in-
plant handling are weight and lateral
Web Reinforcement For shear beyond the standard end
stability. As previously mentioned, the
configuration , ca lculation s indicate
A standardized stirrup spacing was maximum weight that can be handled
established for the end of the girder that pairs of #4 stirrups at 18 in. (460
by precasting plants in the Pacific
by hand calc ul ations using the Hal mm) on center should be sufficient for
Northwest is 200 kips (889.6 kN) . Pre-
Birkland Beam Method. A fi ni te ele- most design cases.
tensioning lines are normally long
ment model was used to confirm the enough so that the weight of a girder
res ul ts of the hand calcu lation . Primary Uses of Pretensioned governs capacity , rather than its
Though the fi nite element model indi- Deep Girder Sections length. Headroom is also not generally
cated that the hand calculations were As discussed previous ly, one of the a concern for the deeper sections.
quite conservative, the results of the primary uses of the new pretensioned Lateral stabi lity can be a concern
hand calcu lations were used to size WSDOT girder sections is to increase when handli ng long , slender girders.
the web reinforcement. The resulting the span capabilities of standard pre- When the girder is stripped from the
configuration is very similar to that stressed concrete girders. Assuming form , the prestressing level is higher
used on existing WSDOT standard zero tension, the W21MG section can and the concrete strength is lower than
girders. span up to 182ft (55.47 m) at a 6ft at any other point in the life of the
July-August 1998 103
crete at service up to the maximum al-
lowed by the 1994 AASHTO LRFD
Bridge Design Specifications.
Alternatively, the new girder sec-
tions may be braced to provide ade-
quate stability. Imper and Laszlo dis-
cuss adding temporary prestressing to
the top flange to provide a larger fac-
tor of safety against cracking. Crack-
ing of the top flange degrades the lat-
eral stiffness of the section, and in turn
reduces its lateral stability.
Fig. 22 shows the effects of
adding four temporary 0.6 in . (15.24
mm) diameter strands, jacked to the
same level as the permanent strands,
to the top flange . If the temporary
prestress is introduced prior to strip-
ping the girder from the form, the
Fig. 20. Comparison of span capabilities- W24MG vs. NU2400. lifting devices may be placed closer
to the ends while still maintaining
adequate stability. This, in addition
to the temporary reduction of the ec-
centricity of the total prestress force,
reduces the concrete stresses and al-
lows a reduction in the required re-
lease strength .
Other types of bracing have al so
been used s uccessfully for many
years. These systems are generally
based on experience rather than the-
ory. Other methods of improving lat-
eral stability, such as raising the roll
axis of the girder, 19 are also available.
Sample calculations for handling the
new WSDOT girder sections are pro-
vided in Appendix D.

Shipping of Deep
Girder Sections
The ability to ship deep girder sec-
Fig. 21. W21 MG girder handling without bracing. tions can be influenced by a large
number of variables , including mode
of transportation, weight , length ,
member. Mast' 7·' 8 has developed meth- strength, because decreasing the dis- height and lateral stability. Some
ods for evaluating the lateral stability tance between lifting devices increases variables are more restrictive than
of long slender members during lift- the concrete stresses at the harp point. others. As such , the feasibility of
ing. Imper and Laszlo'9 describe meth- Stresses at the support may also gov- shipping deep girders is strongly
ods for bracing long slender girders ern, depending on the exit location of site-dependent. The author recom-
for improved stability. the harped strands. mends that routes to the site be in-
The new girder sections are rela- Fig. 21 shows lifting device loca- vestigated during the preliminary de-
tively wide and stiff about their weak tions and resulting concrete release sign phase. To this end, on projects
axes and, as a result, exhibit good sta- strengths that provide the minimum using long, heavy girders, WSDOT
bility, even at their longer preten- recommended stability for a W21MG will place an advisory in their Spe-
sioned lengths. As noted by Mast, the girder without additional bracing, as- cial Provision s including shipping
simplest method of improving stability surning the top harped strands exit at routes , estimated permit fees, escort
is to move the lifting devices away 50 mrn (1.97 in.) from the top of the vehicle requirements, Washington
from the ends . This invariably in- girder. This envelope has been ex- State Patrol requirements, and per-
creases the required concrete release panded to include tension in the con- mit approval time.

104 PCI JOURNAL


Mode of Transportation
Three modes of transportation are
commonly used in the industry: truck,
rail and barge. In Washington State, L = Distance from gird« end to lift loops.
This chart is based on girders of normat
an overwhelming percentage of gird- design. II shoUd not be used lor special
cases. Uft loop locations proyide a minimum
ers is shipped by truck, so discussion FS = 1.0 and FS' = 1.5 with temporary

in subsequent sections will be con- bracing ('*topstrands). Thec:hartassumesa ----+- - - -,+-- - ·-

fined to this mode. However, on spe-


cific projects, it may be economical to
consider rail or barge transportation.
Standard rail cars can usually ac-
commodate larger loads than a stan-
dard truck. Rail cars range in capacity
from approximately 120 to 200 kips
(533 .8 to 889.6 kN). However, unless
the rail system runs directly from the
precasting plant to the jobsite, mem-
bers must be trucked for at least some
of the route, and weight may be re-
stricted by the trucking limitations. Fig. 22. W21 MG girder handling w ith four temporary top strands.
Dimensionally, delivery by rail can
be significantly more restrictive than
by truck. Rail tunnel and other clear-
ances are generally minimized for
standard cars, and are often very tight.
Long precast members may span sev- fiElD BEND TO 135" \#
eral rail cars, and require at least one <7
end support to articulate to accommo-
date the relative turning radius of each
car, which can exacerbate horizontal
clearances at the midpoint of the
member. Dimensional limitations for
rail delivery are heavily route depen- a} Standard Projection
dent, and must be tightly coordinated
with the railroad. Relative to trucks,
rail cars are difficult to obtain on a
consistent and reliable basis.
For marine construction, barge
transportation is usually most econom-
ical. Product weights and dimensions
are generally not limited by barge de-
livery, but by the handling equipment
on either end. In most cases, if a prod-
uct can be made and handled in the
plant, it can be shipped by barge. Of b} Prebent Stirrups
course, this applies only if both the
plant and jobsite are fully accessible
by barge. FlELO BEND TO 135" \#
<7
Weight Limitations
Girders shipped in some states have
weighed in excess of 200 kips (889.6 MECHANICAL CONNECTOR
kN) . The net weight limitation with
trucking equipment currently available
in Washington State is approximately c) Mechanical Splices
167 to 180 kips (742.9 to 800.7 kN), if
a reasonable delivery rate (number of
pieces per day) is to be maintained . Fig. 23. Alternate stirrup projections.

July-August 1998 105


Product weights of up to 200 kips
(889.6 kN) can be hauled with cur-
rently available equipment at a limited
rate. This can be upgraded to a reason-
able rate by round-tripping the equip-
ment if the jobsite is in close proxim-
ity to the plant, or to a rail siding or No. Top Strands Required for FS = 1.0
barge unloading facility.
Local carriers should be consulted
on the feasibility of shipping heavy
girders on specific projects. Of course,
girders can be fabricated and shipped
~-~~~~r ~~S.af~-~-~~-~-~~~~ :a:l.u:.~ .• . • - · ••. •.• . • .• • • •
in two or more segments to reduce the . . ..... ... .
weight. However, it is more economi-
FS' = 1.50
cal to fabricate and ship a single-piece
pretensioned girder whenever possible.

Length Limitations
Length limitations are generally gov-
Fig. 24 . W21 MG factors of safety during shipping.
erned by turning radii on the route to
the jobsite. Potential problems can be
circumvented by moving the support
points closer together (away from the
ends of the girder), or by selecting al-
ternate routes. A rule of thumb of 130
ft (39.62 m) between supports is com-
monly used. The sample calculations of
Appendix D indicate that, on long pre-
tensioned deep girders , the support
points can be moved substantially away No. Top Strands Required for FS = 1.0

from the ends while still maintaining


the concrete stresses within allowable
limits. Length limitations are not ex-
pected to be the governing factor for
most project locations.

Height Limitations
The height of a deep girder section
sitting on a jeep and steerable trailer is
of concern when considering overhead
obstructions on the route to the jobsite. Fi g. 25 . W24MG factors of safety during shipping .
The height of the support is approxi-
mately 6 ft (1.83 m) above the road-
way surface. When adding the depth dard girder sections, as shown in Fig. tiona! stiffness of the support rather
of the girder, including camber, the 23a. Alternate stirrup configurations, than the girder. Methods used to im-
overall height from the roadway sur- as shown in Figs. 23b and c, can be prove lateral stiffness, as discussed by
face to the top of concrete can rapidly used interchangeably to attain ade- Imper and Laszlo, 19 do little to prevent
approach 14ft (4.27 m). Overhead ob- quate clearance, depending on the the truck from rolling. Tentatively,
structions along the route should be route from the plant to the jobsite. Mast suggests factors of safety of 1.0
investigated for adequate clearance in against cracking, and 1.5 against fail-
the preliminary design phase. Obstruc- ure (rollover of the truck). However,
tions without adequate clearance can Lateral Stability During Shipping many girders have been successfully
be bypassed by selecting alternate As discussed previously, long, slen- shipped in Washington State with a
routes. der members can become unstable factor of safety against cracking of
Expectations are that, in some cases, when supported near the ends. How- less than 1.0. This supports Mast's
overhead clearance will not accommo- ever, studies by Mast' 8 conclude that conclusion that the rotational stiffness
date the vertical stirrup projection the stability of girders sitting on flexi- of the truck dominates the behavior of
common on shallower WSDOT stan- ble supports is governed by the rota- the transportation system.
106 PCI JOURNAL
Figs. 24 and 25 show the effects of
the truck's rotational spring stiffness
on the stability of the new sections at a
6 percent superelevation. These charts
represent the longest pretensioned
lengths of the W21MG and W24MG
girders, respectively. They are consid-
ered to be worst-case scenarios for
shipping the new sections, either in
one piece or segmental sections. A
sample calculation for stability during
shipping is given in Appendix D.
The control against craclGng the top
flange is represented by the number of
temporary top strands, jacked to the
same load as the permanent strands,
required to provide a factor of safety
Fig. 26.168 ft (5 1.2 m) long, 180,000 lb (81648 kg) decked bulb-tee girder.
of 1.0. This variable depends on the
combination of girder dead load, pre-
stressing, and tension in the top flange
induced by the girder tilt. The calcu-
lated tilt includes both the supereleva-
tion and its magnification based on the
truck's rotational stiffness.
The factor of safety against rollover
is represented by the dotted lines.
Measurements taken at CTC indicate
that the rotational stiffness of a truck
configured to carry a 168 ft (51.20 m)
long, 180 IGp (800.7 kN) decked bulb
tee was approximately 40,000 in.-IGps
per radian (4519 kN-m/radian). Fig.
26 shows the truck configuration
while Fig. 27 shows the measurements
being taken. For the W21MG girder,
this stiffness would provide a mini-
mum factor of safety of 1.5 for the en-
tire range of span capabilities at up to
a 6 percent superelevation.
In contrast, due to the large top
flange of the decked bulb tee, calcula-
tions indicated a factor of safety of
1.37 at a superelevation of 6 percent.
This result is similar to a long W24MG
girder, which would have a factor of
safety of 1.35 at a 6 percent superele-
vation. The W24MG girder would re-
quire a truck rotational stiffness of ap-
proximately 47,000 in.-IGps per radian
(5310 kN-m/radian) to achieve a factor
of safety of 1.5 at a 6 percent superele-
vation. In any case, the decked bulb
tees of Fig. 26 were successfully
shipped to a remote location.
With respect to the truck's rotational
stiffness, Mast postulates that air sus-
pension provides little or no rotational
stiffness. CTC's measurements sup-
port this notion. The tractor and trailer Fig. 27. Tractor rotational stiffness measurements.

July-August 1998 107


configurations of the truck shown in imate the depths of previously avail- will allow the use of temporary sup-
Fig. 26 were very similar, except that able WSDOT sections. port towers to assemble the girders in
the tractor had two of its dual axles The first deep girder project in place or the girders can be assembled
supported by air suspension. The lat- Washington State was designed by in a staging area and subsequently be
eral stiffness of the tractor was mea- BERGER/ABAM Engineers, Inc. for launched across the river. WSDOT
sured to be about two-thirds of the the City of Kent. A modified version considers the elimination of water
trailer. The 40,000 in.-kips per radian of the segmental W21PTMG girder piers to be a significant benefit, both
(4519 kN-rn/radian) value is the sum was specified for continuous spans of from maintenance and environmental
of the tractor and trailer. 120, 183, and 154ft (36.57, 55.78, and perspectives.
46.94 m). The bridge geometry is Several other bridges using the new
Erection of Deep Girder Sections complex, incorporating a horizontal girder sections are currently in design
curve, superelevation, and an 8.9 per- for various cities and counties within
A variety of methods are used to erect
cent grade. Washington State.
precast concrete girders, depending on
the weight, length, available crane ca- The girder segments consist of nom-
pacity, and site access. The PCI Bridge inal 60 ft ( 18.29 m) long pier head CONCLUDING
Design Manual' 6 describes many of sections with single-piece drop-in seg- REMARKS
these erection scenarios. ments to fill out all three spans. All
segments are chorded to follow the The relationship developed between
As mentioned previously, lifting WSDOT and PNW/PCI has been ben-
long girders during erection is not as horizontal curve. Modifications to the
sections include deepening of the bot- eficial to both parties, as well as the
critical as when they are stripped from regional taxpayers. Mutual coopera-
the forms, particularly when the same tom flange over the intermediate piers
and an increase in web thickness at all tion has improved the quality and
lifting devices are used for both. How- economy of existing precast, pre-
ever, if a separate set of erection de- supports. The deepening of the bottom
flange was necessary to control stressed concrete bridge products. The
vices are used, the girder should be development of new standard deep
checked for stresses and lateral stabil- stresses due to negative moments and
to accommodate a level bearing sur- girder sections gives WSDOT the abil-
ity. In addition, once the girder is set ity to extend spans and remove piers
in place, the free span between sup- face in spite of the severe grade. The
widening of the web was necessary for from environmentally sensitive areas,
ports is usually increased significantly. all with the superstructure material
Mast' 8 points out that this can lead to additional shear capacity.
they prefer to specify. It also gives the
stability problems, particularly if the It should be noted that the
producer members of PNW/PCI ac-
supports are "springy." Wind can also AASHTO Guide Specifications for
cess to markets that have previously
pose a problem. Consequently, when Design and Construction of Segmental
belonged to steel or cast-in-place con-
long girders are erected, they should Concrete Bridges 20 were used in the
crete construction.
immediately be braced at the ends. design of this bridge. It is not certain
PNW/PCI is continuing to work with
that the web widening would have
WSDOT to develop new standards for
been necessary had either the 1994
CURRENT PROJECTS transportation-related structures and to
AASHTO LRFD Bridge Design Spec-
improve existing standards. Standard
The first application of the new ifications' or the 1996 AASHTO Stan-
details and span capabilities for seg-
WSDOT deep girder sections is, oddly dard Specifications for Highway
mentally constructed !-girder bridges
enough, not in Washington State. The Bridges, 16th Edition' 5 been used.
using the newly developed sections are
2002 Olympic Winter Games, to be WSDOT is currently in the process
next on the list. Standardizing sections
held in Salt Lake City, has spurred the of designing their first two bridges
and details for pretensioned or post-
expansion of Interstate 15, resulting in using the new girder sections. The
tensioned, segmental "tub" girders is
a $1.6 billion project including 81 pre- Methow Bridge was originally
also a priority. New sound wall, stay-
stressed concrete I-girder bridges. This planned as a three-span, W74MG
in-place deck panel, and substructure
project is so large that Sverdrup/ girder superstructure. It now has two
element standards have also been
DeLeuw, the lead joint venture consul- spans with pretensioned, single-piece
discussed.
tant, was given the flexibility to choose W21MG girders, roughly 177 ft (54
any standard girder series that proved m) long and weighing 192 kips (854.1
to be the most efficient. kN). This has allowed a pier to be ACKNOWLEDGMENTS
For 16 long span bridges, Sverdrup/ pulled from the water. The author would like to acknowl-
DeLeuw chose the segmental The Twisp Bridge was initially en- edge the many people who con-
W24PTMG section, with spans of up visioned as a two-span W74MG girder tributed to the development of the
to 227ft (69.19 m). Also incorporated bridge. It now has a single 196 ft deep girder standards. Special thanks
into the project are 65 bridges with (60 m) span using the segmental go to Myint Lwin, Chuck Ruth, Yum
shallower versions of the new preten- W24PTMG section, which eliminates Man Tam, and many others at
sioned sections. Girder depths were the water pier entirely. These girders WSDOT's Bridge and Structures Of-
chosen as 1050, 1450 and 1850 mm will be assembled in three pieces and fice. Their enthusiasm and open-
(41.34, 57.09 and 72.83 in.) to approx- post-tensioned together. The contract mindedness made the development of
108 PCI JOURNAL
the new sections possible. Jerry ries. Dr. Tadros assisted with rein- From industry, thanks are extended
Weigel of WSDOT 's Construction forcement details as well as a review to Doug Buss of V. Van Dyke, Inc.
Division provided jobsite construction of the manuscript for this paper. The and Don Taylor Jr. of T & T Truck-
and contract administration expertise. author also appreciates the efforts of ing, Inc. for their help in establishing
From WSDOT' s Motor Carrier Ser- BERGER/ABAM Engineers, Inc., in the feasibility of shipping the new
vices, Barry Diseth helped to establish particular Jim Guarre, Warren Wilson, girder sections. Karsten Olson of
the criteria for shipping these long, and Michelle Tragesser, for taking on Max J. Kuney Co. and Mark Johnnie
heavy girders. the final detailed engineering and draft- of Atkinson Construction Co. helped
Special thanks are also extended to ing of the Standard Plans. Thanks are to establish that there are no "fatal
Dr. Maher Tadros and his colleagues also extended to Paul Bott of Sverdrup/ flaws" in WSDOT's conceptual de-
at the University of Nebraska for their DeLeuw for information of the Salt sign of the Methow and Twisp
work in developing the NU girder se- Lake City 1-15 project. Bridges.

REFERENCES
I. Bardow, A. K., Seraderian, R. L., and Culmo, M.P., "Design, 11. ACI-ASCE Committee 423, "Tentative Recommendations for
Fabrication, and Construction of the New England Bulb-Tee Prestressed Concrete," ACI Journal, V. 54, No. 7, January
Girder," PCI JOURNAL, V. 42, No. 6, November-December 1958, pp. 545-578.
1997, pp. 30-40. 12. Pessiki, S., Kaczinski, M., and Wescott, H. H., "Evaluation of
2. Abdei-Karim, A. M., and Tadros, M . K., State-of-the-Art of Effective Prestress Force in 28-Year-Oid Prestressed Concrete
Precast/Prestressed Concrete Spliced /-Girder Bridges, Pre- Bridge Beams," PCI JOURNAL, V. 41, No. 6, November-
cast/Prestressed Concrete Institute, Chicago, IL, October 1992. December 1996, pp. 78-89.
3. AASHTO, LRFD Bridge Design Specifications, First Edition, 13. Rabbat, B. G., "25-Year-Old Prestressed Concrete Bridge Gird-
American Association of State Highway and Transportation ers Tested," PCI JOURNAL, V. 29, No. 1, January-February
Officials, Washington, D.C., 1994. 1984, pp. 177-179.
4. Geren, K. L. , and Tadros, M. K. , "The NU Precast/Prestressed 14. Shenoy, C. V., and Frantz, G. C., "Structural Tests of27-Year-
Concrete Bridge !-Girder Series," PCI JOURNAL, V. 39, Oid Prestressed Concrete Bridge Beams," PCI JOURNAL,
No. 3, May-June 1994, pp. 26-39. V. 36, No.5, September-October 1991, pp. 80-90.
5. ACI Committee 318, "Building Code Requirements for Struc- 15. AASHTO, Standard Specifications for Highway Bridges, Six-
tural Concrete (ACI 318-95)," American Concrete Institute, teenth Edition, American Association of State Highway and
Farmington Hills, Ml, 1995. Transportation Officials, Washington, D.C., 1996.
6. Guyon, Y., Prestressed Concrete, V. I , Jointly published by 16. PC/ Bridge Design Manual, Precast/Prestressed Concrete
Contractors Record Ltd., London, United Kingdom, and John Institute, Chicago, IL, 1997.
Wiley & Sons, Inc., New York, NY, 1953, p. 239. 17. Mast, R. F., "Lateral Stability of Long Prestressed Concrete
7 . Aswad , A., "An Efficiency Criterion for Pretensioned Beam s, Part 1," PCI JOURNAL, V. 34, No. 1, January-
!-Girders" (unpublished) . February 1989, pp. 34-53.
8. Rabbat, B. G., and Russell, H. G., "Optimized Sections for 18. Mast, R. F., "Lateral Stability of Long Prestressed Concrete
Precast Prestressed Bridge Girders," PCI JOURNAL, V. 27, Beams, Part 2, " PCI JOURNAL, V . 38, No. 1, January-
No.4, July-August 1982, pp. 88-104. February 1993, pp. 70-88.
9. PCI Committee on Prestress Losses, "Recommendations for Es- 19. Imper, R. R., and Laszlo, G., "Handling and Shipping of Long
timating Prestress Losses," PCI JOURNAL, V. 20, No.4, July- Span Bridge Beams," PCI JOURNAL, V. 32, No.6, November-
August 1975, pp. 43-75. December 1987, pp. 86-101.
10. Seguirant, S. J., and Anderson, R. G., "Prestress Losses (Phase 20. AASHTO, Guide Specifications for Design and Construction of
1)," Concrete Technology Associates Technical Bulletin 84B2, Segmental Concrete Bridges, American Association of State
Apri11985. Highway and Transportation Officials, Washington, D.C., 1989.

July-August 1998 109


APPENDIX A- NOTATION

a 1 =length of overhang for lifting M 11 = self-weight bending moment of beam at harp point
a 1 = length of overhang for trucking M 1a1 = lateral bending moment at cracking
Ac = gross concrete area of beam Ms =self-weight bending moment of beam at support
As = area of one prestressing strand N = numboc of prestressing strands
b = distance from end of beam to harp point P; = initial prestressing force after release of prestress
bb =bottom flange width Ps =prestressing force at time of shipping
b1 = top flange width r = radius of gyration = -J I I Ac
dv =effective shear depth r =radius of stability =K 8 /W
e = eccentricity of prestress force sb =bottom section modulus
ee = eccentricity of prestress force at end of beam sf = top section modulus
eh =eccentricity of prestress force at harp point w = weight per unit length of beam
e; =initial eccentricity of center of gravity of beam wc = unit weight of concrete (for elastic modulus
e1if1 =lateral placement tolerance for lifting device calculations)
es =eccentricity of prestress force at support W = total weight of beam
esweep = sweep tolerance for beam x = distance from support to harp point
e1ruck =lateral placement tolerance on truck support y = height of center of gravity of beam above roll axis
e =eh- ee
I
(beam supported from below)
Ec = modulus of elasticity of concrete at design strength Yb = height from bottom of beam to centroid of concrete
Eci = modulus of elasticity of concrete at release strength section
!b = bottom fiber stress Yr =height of roll axis above center of gravity of beam
J: =concrete cylinder strength at time of handling or (hanging beam)
shipping y 1 =height from top of beam to centroid of concrete
f ci =initial concrete cylinder strength at time of release section
of prestress z =lateral deflection of center of gravity of beam
/po =initial jacking stress Zmax = distance from centerline of vehicle to center of dual
fr = modulus of rupture of concrete tires
/s; = effective stress in strand immediately after release Z0 =theoretical lateral deflection of center of gravity of
of prestress beam with full dead weight applied laterally
fss =effective stress in strand at time of shipping z ~ =theoretical lateral deflection of center of gravity of
f, = top fiber stress beam with full dead weight applied laterally, com-
F offset = offset factor that determines distance between roll puted using Jeff for tilt angle ()under consideration
axis and center of gravity of arc of curved beam a = As wad efficiency ratio
FS = factor of safety against cracking a = superelevation angle, or tilt angle of support
FS' =factor of safety against failure Yc =unit weight of concrete including reinforcement
h = overall depth of beam (for weight calculations)
h cg =height of center of gravity of beam above road L1 = total camber
hr = height of roll center above road L1ohang = additional component of upward deflection due to
I = gross major axis moment of inertia of beam overhangs
I = impact during shipping L1ps = component of upward deflection due to prestress
l eff =effective cracked section minor axis (lateral) L1self = component of downward deflection due to self-
moment of inertia weight
ly =gross minor axis (lateral) moment of inertia of () = roll angle of major axis of beam with respect to
beam vertical
K 8 =sum of rotational spring constants of supports 8; =initial roll angle of a rigid beam= eJyr
lg =overall length of beam ()max = tilt angle at which cracking begins
11 = length between lifting devices ()'max =tilt angle at maximum factor of safety against
!span =span length, center-to-center of bearings failure
11 =length between truck supports p = Guyon efficiency factor
M =moment

110 PCI JOURNAL


APPENDIX B- DIMENSIONS AND SECTION PROPERTIES OF
NEW WSDOT STANDARD SECTIONS

Dimensions in mill imeters.


Designation DI D2 D3 D4 DS D6 D7 D8 81 82 83

W21MG 2100 75 75 75 1555 75 115 130 1245 975 !55


W24MG 2400 75 75 75 1855 75 115 130 1245 975 155
W21PTMG 2 100 75 75 75 1555 75 115 130 1290 1020 200
W24PTMG 2400 75 75 75 1855 75 115 130 1290 1020 200

Dimensions in inches.
Designation DI D2 D3 D4 DS D6 D7 D8 81 82 83

W2 1MG 82.68 2.95 2.95 2.95 61.22 2.95 4.53 5. 12 49.02 38.39 6.10
W24MG 94.49 2.95 2.95 2.95 73.03 2.95 4.53 5.12 49.02 38.39 6. 10
W2 1PTMG 82.68 2.95 2.95 2.95 61.22 2.95 4.53 5.12 50.79 40.16 7.87
W24PTMG 94.49 2.95 2.95 2.95 73.03 2.95 4.53 5.12 50.79 40.16 7.87

Secti on properties in S. l. units.


A I Yb Yt sb s, w ly
Designation (mm 2) (mm4 ) (mm) (mm) (mm 3) (mm 3) (kNim) (mm•) VIS
11 8 10
W21MG 627096 3.981 X 10 1007 1093 3.95 1 X 108 3.643 X 10 15.76 2.993 X 10 3. 16
10
W24MG 673547 5.504 X 10 11 11 53 1247 4.775 X 10 8 4.4 12 X 108 16.93 3.003 X JQ 3. 15
11 8 10
W2 1PTMG 721289 4. 329 X 10 1013 1087 4.274 X 10 8 3.982 X 10 18.1 3 3.462 X 10 3.59
W24PTMG 781289 6.023 X 10 11 1159 1241 5. 196 x 108 4.855 X 108 19.64 3.482 X [Q IO 3.6 1

Section prope rti es in U.S. Customary units.


A I Yb Yt sb s, w (kips per ly
Designation (sq in.) (in.4) (in.) (in.) (cu in.) (cu in.) (lineal ft) (in. 4 ) VIS

W2 1MG 972 956,329 39.66 43.02 24,113 22,231 1.08 7 1,9 14 3. 16


W24MG 1044 1,322,223 45.38 49. 11 29, 137 26,925 1.16 72, 138 3.15
W2 1PTMG 111 8 1,040,022 39.88 42.80 26,079 24,30 1 1.24 83,173 3.59
W24PTMG 12 11 1,447, 11 9 45.64 48.85 31,707 29,625 1.35 83,653 3.61

01

os
1
DB 07 I. 05

04

CD CD - - ----
VI
"'

Fig. B1 . Notation fo r dimensions contained in tables.

July-August 1998 111


APPLY APPROVED RETARDANT FOR 6 ETCH NOTES:
LIFTING BARS 2- J5 - TO SID£ FORIJS OR 6 ROUGHENED SURFACE
H.S. THREAD BARS W/ANCHOR
NUT AT 8017011 {UFTING LOOPS
5- 12.70 ' STRANDS AlA Y BE
TR£A TUENT BY APPRO'tl£0 MECHANICAL METHOD
f DIAPHRAGM
I.

2.
ALL OHAILS ON THIS SHEET ME FOR PRETENS/01€0 DESIGN ONLY.

PLAN LENGTH SHALL 8£ INCR£ASED AS NECESSARY TO fXNPENSATE FOR SHORTEN I NG 01£

n~
USED, 5££ NOTF 6) TO PRESTRESS AID SHR I NKAG£ .

3. ALL STRAHJ FOR PRETENSIONING SHALL 8£ JS . 2.f nm 0/NETCR LOW RCLAXATifM STRANDS
{AASHTO U20:S GRAD£ 270).

~~~-==t OCLET£ AT
4. CUT ALL STRAMJS FLUSH WITH TH£ GIRDER ENDS AMJ PAINT WITH AN APPROV£0 CPOXY
RESIN EXCEPT FOR EXTEf«J£0 STRNoDS AS SHOftiN .

INTCRIEDIATE S. EXTE:MJ£0 STRANDS AND BARS ARE PARALLEL TO GIRD£R .


PIERS
6. LIFTING LOOPS SHALL BE 12.70 mn DIAMETER STRAMJ (AASHTO 11203 GRAD£ 270);

~~~~~~~~t~~~:~~ro~~:~~---: ~ ;~ R~ :;~g; --~~~~~~~~4-~~~~:::~::~~~~~~$!==~~~~~~~


·
15 . 24 rrm DIAIETER STRAND SW.LL NOT BE USED FOR LIFTING LOOPS. MRAP THE LIFTING
LOOPS SO THAT £Aal STRAND WILL CARRY AN EQJAL SHARf OF TH£ TOTAL LCMO . EXTDID
LIFTING LOOPS TO WITHIN 75 mn CLEAR OF TH£ BOTTCII OF' TH£ GIRDER, EhDING WITH
A ZJO rrm LONG go D£GR££ HIXJK. IF THf LIFTING LOOPS EXTEND WITHIN 75 rrm OF' THE:
TOP OF TH£ ~y SLAB TI£Y SHALL BE CUT OFF PRIOR TO POURING THC RO.WWAY SLAB .
LIFTING LOOPS AMY ONLY BE USE:D ON GIRDERS WITH LENGTHS AS FOI..L(]tll5,
B • S10 DEGR€£5, GIRDER LENGTH L£5S THAN .J5 . 000 IETERS
B • ~0 O€GR£ES, GIRDER LENGTH LESS THAN .JO . 500 IETERS
0.4 SPAN LENGT>f (C7R ,r::...::c::c7Rc:8£ARIN==GS::o):.._:.±_:JOO:::__ _ _ _ _ _ ____,
7, LIFTING BARS SHALL BE .J5 nm DIAJICTER HIGH STRCNGTH TlfiCADED BARS (AASHTO
GIRDER ELEVA llQN 11275 GRAD£ 150 IIINI'A.M) . LIFTING HARDWARE THAT COI#IECTS TO THREADeD BARS SHALL
END TypE A • OMIT HOLES AND PLACE INseRTS ON THE INTERIOR F'AC£ OF END TypE B BE D£51GNCO NiO OCTAIL£0 BY TIE ca-ITRACTOR . LIFTING FORC£5 ON THR£AD BARS
FOR STUB ABUTIICNT PIER FOR L SHAPED ABUTWCNT PI£R SHALL 8£ II£RTICAL ONLY AND WITHIN 10 D£GR££S OF P£RPCNDICULAR TO A LINE
CXTfRIOR GIRDERS. PLACE HOLES AND INSERTS PARAllEL TO
'MTH END OR OISCON11NVOUS SPAN AT SCTWE:CN PICK POINTS . CONTRACTOR SHALL SI.BIIT CALCULATIONS FOR APPROVAL BY
DIAPHRAGM CAST SKEw. INSERTS SHALL S£ 25 RICHMOND ROCK£T. BURK£
ON GIRD£R END HI- TfNSIL£, LANCASTER AIAUCABI..£ OR APPROVED £QUAL. INTfRitiBJIATE PfER CNGIN£CR IF LIFTING FORCES ARC TO 8£ OTHERWISE .

8. £XTRA CAUTION ltA.JST 8£ EXERCISED IN HANDLING AM) PLACING ALL GIRDERS. ALL
GIRDERS SHALL BC CHECKED TO ENSURE THAT THIT ARC BRACCO NJCai.IATELY TO PRCYeiT
TIPPING AN() TO CONTROL LATERAL SENDING DURING SHIPPING.

9. THE TOP SI..RFACC OF THE GIRDER FLANCC SHALL B£ RCJUG:HCNCD IN ACCORDANCE WITH
SECTION 5-02 . .J(25)H OF THE STAMJARD SP£CIFICAT/OH5.

10 . FOIWS FOR SEARING PAD RECESSES SHALL 8£ CONSTRUCTCD AN() FASTCNED IN Stx:H A
lrW#ICR AS NOT TO CAUSE O..W..GC TO THE GIRDER DURING TH£ STR.AMJ R£LEAS£
OP£RATION .

I I. FOR SAWTEETH OCTAILS SEC WZIMG GIROCR DeTAILS 2 OF 2 .


50+

@I]p- 55PA 0 150


EliBCD J.OOO (TYP)
INTO GIRDER. ADJUST
LOCATK)N TO CLCAR
HARPED STRANDS.
OltiiT FOR END TrPC 8

280 + 82
DtTFNO STRAIGHT STRANDS <f.T@!] rnz ncs o .JOO \1!1f71CAL
(i)1HROUGH{j)UNL£SS HOT<D SFACES. STAGG£R SPAONG ON

L ~
OTHERWSE ON STRAND EXTCNSION TFRNA 7F ST1RRUPS. ADJ.JST 975
D£TAJL. W21t/G GIRDER DETAILS 2 OF 2 CING AT STRANDS 70 CLEAR
OIMT CXTCNS/all FOR END Tl1'C 8 FM £NO TYPE 8 .

:::::ON::::~:£A ®
TypiCAL END ELEVA llON TYPICA L SEC nON
£NO T'YPE: C SHOWN - OTHER ENOS SIMILAR
EXCEPT STRANO £XT£NSION DETAIL. SEE W21AIG
GIROER OETAJLS 2 OF' 2. FOR 82 SEE W211t1G FOR 81 SEE W2111G GIRDER DETAILS 2 OF 2

11 lli~I..IIIINilllY
GIRDER DeTAILS 2 OF 2

-u
Q
'-
0
c
JJ
z
:I>
r
>
""C
""C
m
GIRDeR z
~
ALL HARPED STRANDS IN
EXCESS OF IB SHALL 8£
PLACED 1H THIS BUNDLE
£NO C>"
P.S. CIRD£R J 0
><
(j
90'
\ ( [ ]
....
QRD£R £NO J ~~
ODD STRAND (MAY 8£
AD.AJS7fD TO OTHER
SIDC OF lt£8) TRANSVERSE REINFORCING SA WTEETH QETAILS
AT SKEWED ENDS SAWT££TH ARC FUI.L WO TH - US£ SAWTEETH ""C
ONLY TRANSVCRS£ REJNF SHOWN K£YS f1KJII BOTTOitl OF BOTTOM FZ.ANG£ TO
BOTTOII OF LOitEST HARP£() STRAND AS ~
~
STRAND PATTERN AT GIRDER END AS TOP OF TOP FlANG£ DOttN TO HIGHEST m
HARP£0 S11lANO LOCATION SE.OUCNC£ SHALL 11£ AS SHOIIN{D, @, @, ... ETC.
NQ lf m DfSIGNCR· LOCA1l" HARPED S TRAND sua; THAT C.C. OF COIIBIN£D
HARPED AND STRAIGHT STRAND IS .AJST ABO\£ THE LOIIE'i' KCRN OF TH£
GIROCR SECTION AND THAT TH£ GIRDER IS STABL£ FOR PICKING AND HANDUNG.
HARPED STRANO AS SHOWN IN SECTION 8
W2UIG CIRDCR DETAILS 1 OF 2.
-
r-

~' AH[AO -
BASCO ON CIROER DCFLECTKJN - D AT TMI£ OF SLAB POUR (120 DAl'S)
ON sfA nONiNG HloRPCD STRAIGHT
MIN. CONC.

.,
COMPR. STR!NGTH LOCAT10N OF

I n~ ~
C.G. STRANDS (IN.)
PLAN

~
LENGTH 11
92 Nl N2 PI P2
.u;~ ~~
~
(ALONG NO. OF NO. OF
£ QRD£R ~~ STRANDS (KIPS) STRANDS (KIPS)
GRAD£}
~e £ 'f ro

£J:i.!)_J ~
£NO 2 AHEAD ON STATION BEARING
15.2411 STRAND CHUCK (TYP).
TACK linD TO ANCHOR PL (TYP)
70 1t 3D STffl. STRANO ANCHOR (TYP). £NO TYPE
R<CCSS
y z SAWTf:ETH
PRIOR TO THR£ADING STRANDS
THROUGH ANOKJR Pt.. ANCHOR
ANa-lOR STRANDS ttfTH 2 PIECE IIEZ>Gf"S
BCFOR£ GIRDER ER£C110N. ~ ltE'DGES
ARC SEA TCD TIQ1n. Y IMIICDIA 7n Y BEFORe
~SLEFTC>" £
81 • 0 (G4, G9, GtO)
A ,., 2JO 480 =
STRANDS tilTH 2 Pf£C£ II£DG£S
8£FORC GIRD£R CRCCTION. \£RIFY
PLACING OIAPHRAGitl CONa?CT£..
82- 0 {G5} 8 ,., 0 0 NO
..wGCS ARC 5£A TFD 11CH1Z. Y DiD I BACK ON STA nON
IIIII£DIA 7El. Y BCFORC PLACJNC c. NO 560 2>0 \'FS
DIAPHRAGM CONCRETE. ~ARSRIQ-ITOF c,
8 1 • 2' (G4, C9, CIO} ALT1 ORALT2
0 " NO \'FS
82 - 75 (C5) STRAND EXTENSION

• FOR CONTINUOUS SPAN WITH HING£D CONNECTION TO COLUMN.


•• FOR CON17NUOUS SPAN FUU Y AXED TO COL.UMN.

&..L....1 .AI..L...2 l,lli~J. IIIINilllY


NQTES m Q£SK;Nf'R:
STRANO EXTENSION DETAIL ~
THIS STRAND EXTfNSION DETAIL IS TO 8£ USED FOR CON11NUOUS SPANS AT MOMENT RESISTING C')
20 CHAMF'fR ON M£8
FOR SIC£WS GR£A TfR
DMPHRAGNS ONLY. THIS 0£TAIL IS NOT APPLICABLE TO CONTINUOUS SPANS USING HINGe OPEN HOLE
THAN 15"
DIAPHRAGMS. DCS1GNER SHALL CALCULATE: THE EXACT NUIJBCR OF ANOiORED CXTmDlJJ STRANDS
NfEO£D FOR EACH STRAND ANCHOR ALTfRNATE: TO 0£\fiOO TH£ REQUIRED UOM£NT CAPACITY AT
HOLES A T END TYPE 8 ONL Y trJ
THE END OF THE: GIRDER. THIS CALCULA 710N SHALl 8f BASCO UPON THE TfNS1l£ STReNGTH m
BEARING RECESS DETAIL OF TH£ STRANDS. THE STReSSES IMPOseD UPON THE ANCJ10R, AND CON~ BEARING AGAINST (j
TH£ PRO.X:CTCD AREA OF TH£ AN010R.
-1
0
z
APPENDIX D- SAMPLE CALCULATIONS
This sample calculation is based on the longest W21MG section with the highest level of pre-
tensioning that can be manufactured in the Pacific Northwest. It is also based on calculation
procedures given by Mast, 17 •18 and bracing methods given by Imper and Laszlo. 19 See those ref-
erences for additional details.

GIVEN

W21 MG Bridge Girder Data


Overall length of girder lg = 185ft (56.39 m)
Clear span length, center-to-center supports lspan = 182ft (55.47 m)
Overall depth of girder h = 82.68 in. (2100 mm)
Top flange width b1 = 49.02 in. (1245 mm)
Bottom flange width bb = 38.39 in. (975 mm)
Gross concrete area of girder cross section Ac = 972 sq in. (627096 mm2)
Major axis moment of inertia I= 956,329 in. 4 (3.981 x 10 11 mm 4 )
Major axis top section modulus S1 = 22,230 CU in. (3.643 X 108 mm 3)
Major axis bottom section modulus Sb = 24,113 CU in. (3.951 X 108 mm 3)
Minor axis moment of inertia Iy = 71,914 in. 4 (2.993 x 10 10 mm4)
Distance from center of gravity of concrete to girder top Yr = 43.02 in. (1093 mm)
Distance from center of gravity of concrete to girder bottom Yb = 39.66 in. (1007 mm)
Girder weight per unit length w = 1.080 kip/ft (15.76 kN/m)
Girder weight W = 199.8 kips (888.8 kN)
Girder Concrete Data
Design strength J; = 10.0 ksi (68.95 MPa)
Unit weight including reinforcement Yc = 160 pcf (25.13 kN/m 3)
Unit weight for elastic modulus calculations We = 155 pcf (24.35 kN/m 3)

Pretensioning Data
See Fig. D2 for pretensioning configuration
Area of one 0.6 in. (15 mm) diameter strand As= 0.217 sq in. (140 mm 2)
Number of 0.6 in. (15 mm) diameter strands N= 64
Initial jacking stress /po = 202.5 ksi (1396 MPa)
Per WSDOT's Standard Specifications:
Effective prestress at 1 day to 1 month (stripping) /s; = 182.5 ksi (1258 MPa)
Effective prestress at 1 month to 1 year (shipping) Iss = 167.5 ksi (1155 MPa)
Lifting and Shipping Parameters
See Fig. D 1 for lifting and shipping configurations
Superelevation angle a= 6 percent
Impact during shipping I = 20 percent
Sweep tolerance (stripping) esweep = 50 percent PCI tolerance
Sweep tolerance (shipping) esweep = 100 percent PCI tolerance
Lift device tolerance elift = 0.25 in. (6.4 mm)
Position tolerance on truck etruck = 1 in. (25.4 mm)
Truck rotational spring stiffness Ke = 41,000 kip-in./rad (4632 kN-rn/rad)
Height of roll center above road h, = 24 in. (610 mm)
Height of center of gravity of girder above road hcg = 111.7 in. (2837 mm)
Distance from center of truck to center of dual tires Zmax = 36 in. (914 mm)

REQUIRED ple of a worst case scenario, so the plotted point falls out-
side the bounds of the chart.)
1. Find lifting device location:
From Fig. 21 for a girder length of 185 ft (56.39 m) with a 1 = 14ft (4.27 m)
64 strands, the lifting device location can be extrapolated at 11 = 157ft (47.85 m)
approximately 14ft (4.27 m). (This is a hypothetical exam- x = b- a 1 = 74.3- 14 = 60.3 ft (18.38 m)
114 PCI JOURNAL
41 000
tg = 185' r = Ke = • = 205.21 in. (5212 mm)
w 199.8

At support:
j, = 2535- (2535)(19.91) + -1270
I 972 22, 230 22, 230

l~·=2J I
= 0.280 ksi (1.93 MPa)

I L275.l tt = 130'
!J
b
= 2535 + (2535)(19.91)- -1270
972 24,113 24,113
t span == 182' = 4.754 ksi (32.78 MPa)
Compression in the bottom flange at the harp point
Fig. 01 . Locations of bearing, lifting devices and truck
governs:
supports.
4 828
+'- =
J et
.iJL
0.6
= ·
0.6
= 8.047 ksi
2. Check stresses at harp point and support, and de-
termine required concrete release strength:
VseJ;; = 8.10 ksi (55.5 MPa)

j, = P; _ P;e + M
E . = 33w 1.5 f7l = 33(155)1.5 .J8iOO
1
ct c 'V J ci IOOO
Ac · S1 S1
= 5731 ksi (39518 MPa)
fb =~+ P;e- M Note: Compression in the bottom flange at the harp point ex-
Ac Sb Sb
ceeds compression in the bottom flange at the support. At this
P; =NAsfsi =(64)(0.217)(182.5) point, the location where the harped strands exit the girder end
= 2535 kips (11274 kN) could be lowered to make these stresses roughly equivalent.
This would not change the required concrete release strength,
eh = 35.52 in. (902 mm)
and would reduce the demand on the pretensioning system.
19 23
es = 16.29 + · (14) = 19.91 in. (506 mm) 3. Compute initial eccentricity e;:
74.3
1 ( lO
16 185) = 1.16 m.
. (29.4 mm)
Mh =lw (l1x-x 2-a12) esweep =

2
2
= 1.~ 8 [(157)(60.3)- (60.3) 2 - 2
(14) ](12) Offset factor= Foffset = -11 ) - -
1 = (157)
- 1 = 0.387
--
[ lg 3 185 3
= 36,515 kip- in. (4126 kN- m)
=
etift 0.25 in. (6.4 mm)
M = waf 2
= _ (1.08)(14) (12) e; = 1.16(0.387) + 0.25 = 0.70 in. (17 .8 mm)
s 2 2
4. Estimate initial camber to correct Yr (PCI Design
= -1270 kip- in. (-144 kN- m) Handbook Method):
At harp point: Precast downward deflection due to self weight:
4 4 3
j, = 2535- (2535)(35.52) + 36,515 L1 _ -Sw/8 _ -5(1.08)(185) (12)
f 972 22, 230 22, 230 self - 384EcJ - 384(5731)(956,329)

= 0.200 ksi (1.38 MPa) = -5 .19 in. (-132 mm)

Q., h =35.52.
C.G.S. (64) 0.6·· STRANDS

r-C.G.C.
__ _L_ _ _ _ _ _ _

b = 74.3' 36.4' b = 74.3'

Fig. 02. Pretensioning confi guration (w ithout temporary top prestressing).

July-August 1998 115


Upward deflection due to prestress: 9. Compute factor of safety against failure FS':

8EcJ EcJ 8
2
L1ps = P;eelg + P;e' [ l/ _
6
![_l 8:nax = ~ e;
2.5z0
= 0.70
2.5(17 .95)
= 0.1249

= (2535)(16.29)(185) (12) +
2 2
z~ = Z.0 (1 + 2.5e~ax) = (17.95)[ 1 + 2.5(0.1249)]
8(5731)(956,329) = 23.55 in. (598 mm)

(2535)(19.23) [(185)
2
-
2
(74.3) ](12)2 FS' = y,e~ax (40.84)(0.1249)
(5731)(956,329) 8 6 z~8~ax + e; (23.55)(0.1249) + (0.70)
= 1.40 <1.5
= 8.94 in. (227 mm)
If FS' < FS, FS' = FS, therefore FS' = 1.46. This is within
Additional upward deflection due to overhang:
a few percent of the suggested factor of safety against fail-
3 3 ure and is probably satisfact~ry. If more stability is consid-
wazl/ _ (1.08)(14)(185) (12)
L1 --- ered necessary, move the lifting devices a few more inches
ohang- 16EcJ- 16(5731)(956,329)
toward midspan and repeat Steps 2 through 9.
= 1.89 in. (47.9 mm)
Total camber at lifting: Check the same beam during transportation:
GIVEN
L1 = L1self + L1ps + L1ohang = -5.19 + 8.94 + 1.89
Local truckers prefer a maximum of 130 ft (39.62 m)
= 5.64 in. (143 mm) between the centers of support of the tractor and trailer for
Adjusted Yr turning radius purposes. Try 11 = 130 ft (39 .62 m), at =
27.5 ft (8.38 m).
= Yt- L1Foffset = 43.02- (5.64)(0.387)
Fig. 24 indicates that girders of this size will need
= 40.84 in. (1037 mm) about five temporary top strands to maintain a factor of
safety of 1.0 against cracking during shipping. Try six
5. Compute Z0 : temporary top strands, jacked to the same level as the
permanent pretensioning.
-
Z 0
= w
1 1 1 1 1
6
( -1! 5 -a 2! 3 +3a 4 ! +-a
1
5)
12EcJylg 10 5 REQUIRED
1.08 10. Computer:
= X
12(5731)(71, 914)(185)
41 000
r = Ke = • = 205.21 in. (5212 mm)
(14 ) (157? + 3(14) (157) + ~ (14) ](12)
5 2 4 5 3
w
[ _!_
10
(157) -
5
199.8
11. Compute tilt angle 8:
=17.95 in. (456mm) y = hcg- hr =111.70- 24 = 87.70 in. (2228 mm)
Increase y by 2 percent to allow for camber. Then, y =
6. Compute 8;: 89.45 in. (2272 mm).
0 70 2
8; =!i..= • =0.01714 2
130
Yr 40.84 F [!J._J
offset = l - _!_ = (
3 185 ) - _!_ = 0.160
3
g
7. Compute tilt angle 8max at cracking:
1 (185)
esweep = g lO = 2.31 0

Ill. (58.7 mm)


75
fr = 7.5-[1:; = · -J8100 = 0.675 ksi (4.65 MPa)
1000 etruck = 1 in. (25.4 mm)
J; = 0.200 ksi (1.38 MPa) compression from Step 2 e; = (0.160)(2.31) + 1 = 1.37 in. (34.8 mm)

M _ 2{fr + J; )Iy _ 2(0.675 + 0.200)(71, 914) E = 33 w 1. 5 r;:; = 33(155)1. -JiO,OOO


5

tar - b - 49.02 c c '\jlc 1000


1

= 2567 kip- in. (290 kN- m) = 6368 ksi (43907 MPa)

8 = Mlat = 2567 = 0.0703 -


Z0 =
w ( -lt
1 1
6
1 5 - a 2 lt 3 + 3a 4 lt + -at 5)
max Mh 36,515 12EJylg 10 5

8. Compute factor of safety against cracking FS: 1.08(12) 3


-~~----'--"-~-X

12(6368)(71, 914 )(185)


1
FS= Z 8; = 17.95 0.01714 =1. 46 >l.O (ok)
-0 + - - (27.5) (130? + 3(27.5) (130) + ~ (27.5)
--+~-- 5 2 4 5
Yr emax 40.84 0.0703 [ _!_
10
(130) -
5
]

116 PCI JOURNAL


= 4.21 in. {107 rum) Tension in "downhill" top flange governs
2 2
fJ= ar+e; = (0.06)(205.21)+1.37 =0.
r- y - Z0 205.21-89.45-4.21
1227 J; = (1L)
7.5
=(
632
7.5
) = 7101 psi

12. Compute stresses of tilted girder at harp point (no =7.101 ksi {48.96 MPa) < 10.0 ksi (ok)
impact): 13. Compute stresses including impact (required by
Ps = NAsfss = (70)(0.217)(167.5) = 2544 kips (11317 kN) the WSDOT Standard Specifications):
Stresses at harp point with +20 percent impact:
(64)(35.52)- (6)( 43.02 -1.97)
eh = 70 !, = 2544- (2544)(28.96) + (20,331)(1.2)
= 28.96 in. (736 mm) I 972 22, 23Q 22, 230
=0.400 ksi (2.76 MPa)
Mh =; (t x-x -a/)
1
2
!J = 2544 + (2544)(28.96)- (20,331)(1.2)
972 24,113 24,113
1.~ 8 [(130)( 46.8)- (46.8) 2 -
b
= (27.5? ](12)
= 4.661 ksi {32.14 MPa)
= 20, 331 kip- in. {2297 kN- m)
Stresses at harp point with -20 percent impact:
!, = 2544- (2544){28.96) + 20,331
!, = 2544- (2544)(28.96) + (20,331)(0.8)
I 972 22, 230 22, 230
I 972 22, 230 22, 230
= 0.218 ksi (1.50 MPa)
=0.035 ksi (0.24 MPa)
!J = 2544 + (2544)(28.96)- 20,331 !J = 2544 + (2544)(28.96)- (20,331)(0.8)
b 972 24,113 24,113
b 972 24,113 24, 113
= 4.830 ksi (33.30 MPa)
=4.999 ksi (34.47 MPa)
Mtar = fJMh = 0.1227{20, 331)
Stresses at support with +20 percent impact:
= 2494 kip- in. {281.8 kN- m)
19 23
Top fiber stress for "uphill" flange: [ 16.29 + · (27.5).]64- (43.02 -1.97)6
e = 74.3
s 70
M lat (12)
2
49 02
2494( · )
2 = 17.88 in. (454 mm)
!, + = 0.218 + ------"-----=~
ly 71,914 M = wa12 = _ (1.08)(27.5) (12)
2

= 1.068 ksi (7.36 MPa) s 2 2


Top fiber stress for "downhill" flange: = -4900 kip- in. (-554 kN- m)

Mlat(br) 2494(49.02) !, = 2544 - (2544 )(17.88) + (-4900)(1.2)


f'-
2 =0.218- 2 I 972 22, 230 22, 230
Jr Iy 71, 914
= 0.306 ksi (2.11 MPa)
= -0.632 ksi (-4.36 MPa)
!J = 2544 + (2544)(17.88)- (-4900){1.2)
Bottom fiber stress for "uphill" flange: b 972 24,113 24,113
Mtar (bb) 2494(38.39) = 4.748 ksi (32.74 MPa)
2 2
fb + = 4.830 + Stresses at support with -20 percent impact:
ly 71,914
= 5.496 ksi {37.89 MPa)
!, = 2544- (2544)(17.88) + (-4900)(0.8)
I 972 22, 230 22, 230
Bottom fiber stress for "downhill" flange:
= 0.395 ksi (2.72 MPa)
Mlat (bb ) 2494(38.39) !J = 2544 + {2544)(17.88)- (-4900)(0.8)
f' -
2 = 4.830- 2 b 972 24,113 24, 113
Jb 1y 71 , 914
=4.667 ksi {32.18 MPa)
= 4.165 ksi {28.71 MPa)
Compression in bottom flange at harp point with -20
Compression in "uphill" bottom flange governs: percent impact governs:

!,' = _h_ = 5.496 !,' = _h_ = 4.999


c 0.6 0.6 c 0.6 0.6
= 9.160 ksi {63.16 MPa) < 10.0 ksi (68.95 MPa) (ok) =8.331 ksi (57.44 MPa) < 10.0 ksi {68.95 MPa) (ok)
July-August 1998 117
14. Compute the tilt angle (}nuu at cracking: 20. Check stresses at harp point and support, and de-
termine required concrete release strength:
75
fr = 7.5fj; = · .JW,OOO = 0.750 ksi (5.17 MPa) P; = (70)(0.217)(182.5) = 2772 kips (12331 kN)
1000
ft = 0.218 ksi (1.50 MPa) compression from Step 12 (64)(35.52)- (6)( 43.02 -1.97)
eh = 70
M _ 2(/r + ft )IY _ 2(0.750 + 0.218)(71, 914)
/at- b - 49.02 =28.96 in. (736 mm)
1
19 23
= 2840 kip- in. (321 kN- m) [ 16.29 + · (12.5)](64)- (43.02 -1.97)6
e = 74.3
(} = = 2840 = 0.1397
Mlat s 70
max Mh 20,331
= 14.33 in. (364 mm)

15. Compute factor of safety against cracking FS: Mh = 1.~ 8 [(160)(61.8)-(61.8) 2 -(12.5)2 ](12)
= 38,313 kip- in. (4329 kN- m)
2
M = _ (1.08)(12.5) (12)
205.21(0.1397- 0.06) s 2
=~~~--~~~~~~~--~
(4.21)(0.1397) + (1.37) + (89.45)(0.1397) = -1012 kip-in. (-114 kN- m)
= 1.13 > 1.0 (ok)
At harp point:
16. Compute tilt angle (};,ax at maximum resisting
arm: ft = 2772- (2772)(28.96) + 38,313
t 972 22,230 22, 230
(}:00.., = Zmax- hra +a= 36- (24)(0.06) + 0.06 = 0.964 ksi (6.65 MPa)
r 205.21
=0.2284 £ - 2772 (2772)(28.96) 38,313
Jb- 972 + 24,113 -24,113
17. Compute z~ at(}~: = 4.593 ksi (31.67 MPa)

z; = zo(1 + 2.5(}max) = 4.21[1+ 2.5(0.2284)] At suppport:


= 6.61 in. (168 mm)
ft = 2772- (2772)(14.33) + -1012
t 972 22,230 22, 230
18. Compute factor of safety against rollover FS':
= 1.019 ksi (7.03 MPa)
FS' = r( e:..a.., -a) .iJ 2772 (2772)(14.33) -1012
(z~e:mu + e; + ye:mu) b = 972 + 24,113 -24,113
- 205.21(0.2284- 0.06) = 4.541 ksi (31.31 MPa)
- [(6.61)(0.2284) + 1.37 + (89.45)(0.2284)]
= 1.48 :d.50 (ok) Compression in the bottom flange at the harp point
governs:
4 593
Check lateral stability and required concrete strength E'. = · = 7.655 ksi
J et 0.6
at release if the temporary top prestressing is introduced
prior to stripping: Use J;; = 7.70 ksi (53.1 MPa)
33 155
19. Find lifting device location: E ·= ( )1.5 -J7700 = 5588 ksi (38530 MPa)
Cl 1000
From Fig. 22 for a girder length of 185 ft (56.39 m) with
64 strands, the lifting device location can be extrapolated at
somewhere between 11 and 13 ft (3.35 and 3.96 m). This 21. Re-compute initial eccentricity e;:
chart is for four top strands, and six are used here, so the re-
sult is not directly applicable. Assume the lifing devices are esweep
1 (185)
= 16 . (29.4 mm)
W = 1.16 m.
12.5 ft (3.81 m) from the ends of the girder as a reasonably
2
conservative estimate.
Offset factor = Foffset = ( 160) -31 = 0.415
a 1 = 12.5 ft (3.81 m) 185
11 = 160ft (47.85 m) elift = 0.25 in. (6.4 mm)
x = 74.3- 12.5 = 61.8 ft (18.84 m) e; = 1.16(0.415) + 0.25 =0.73 in. (18.6 mm)
118 PCI JOURNAL
22. Re-estimate initial camber to correct Yr (PCI 24. Re-compute (}i:
Design Handbook Method):
0 73
Precast downward deflection due to self weight: (}. = · = 0.0177
l 41.17
L1 = -5(1.08)(185)4(12)3 = -5.33 in. (-135 mm)
self 384(5588)(956239)
25. Re-compute tilt angle (}max at cracking:
(16.29)(64)- (43.02 -1.97)6
e = -'------''-'---'---'-----'-----
70 75
e
fr = · .JTiOO = 0.658 ksi (4.54 MPa)
= 11.38 in. (289 mm) 1000

e' = 28.96-11.38 = 17.58 in. (447 mm)


fr = 0.964 ksi (6.65 MPa) compression from Step 20
M _ 2(0.658+0.964)(71,914)
Upward deflection due to prestress: /at- 49.02
2 2
L1 = (2772)(11.38)(185) (12) + = 4759 kip- in. (538 kN- m)
ps 8(5588)(956,329) 4759
(} = = 0.1242
2 2 max 38,313
(2772)(17.58) [(185) - (74.3) ](12)2
(5588)(956,329) 8 6
= 8.05 in. (204 mm) 26. Re-compute factor of safety against cracking FS:
Additional upward deflection due to overhang: 1
FS= 20.62 0.0177 =1. 55 >l.O (ok)
--+--
L1 = (1.08)(12.5)(185?(12)3 = 1.73 in. (43.9 mm) 41.17 0.1242
ohang 16(5588)(956,329)

Total camber at lifting:


27. Re-compute factor of safety against failure FS':
L1 = -5.33 + 8.05 + 1.73 = 4.45 in. (113 mm)
0.73
Adjusted Yr (}max= ( )=0.1190
2.5 20.62
= 43.02- (4.45)(0.415)
z~ = (20.62)[ 1+ 2.5(0.1190)] = 26.75 in. (680 mm)
= 41.17 in. (1046 mm)
FS' = (41.17)(0.1190) = 1. 25 < 1. 5
23. Re-compute Z0 :
(26.75)(0.1190) + (0.73)
3
- 1.08(12)
Zo = 12(5588)(71, 914)(185) X
If FS' < FS, FS' = FS; therefore, FS' = 1.55. The addition
of temporary top prestressing before stripping reduces the
(12.5) (160) + 3(12.5) (160) + ~ (12.5) ]
5 2 3 4 5
[ _!_
10
(160) -
5
required concrete release strength by approximately 400 psi
(2.76 MPa) while improving the lateral stability factors of
= 20.62 in. (524 mm) safety.

July-August 1998 119

You might also like