Download as pdf or txt
Download as pdf or txt
You are on page 1of 20

Qatar Armed Forces ~j ·""'' l; 1 • sw.lt u\_,_..:i.

lt
Qatar Emiri Corps of Engineers 41_;bill4l_»A~I ~~\ c::~
P.O. Box: 5735 - 9575 Doha- Qatar _;--.J:J- L:...,.lll 9575- 5735 : y (.)4

Tel: 44612111 Fax: 44612811 /44605300 44612811 :~\.! 44612111 : -...£J1A

Ref: QECE/WING7/DKABIC-108-0l/20/05977
Date:
14 OCT 2020 RE~~:·~,ED ' v ' ~·-~.J

Bahadir Construction Engineering Contracting & Trading Inc. Co By:..


P.O Box 207229
Doha- Qatar.

Attn: Emre Bakkal


Project Director

Sub: (C-108-01) : Method Statement

Reference to the above subject and your Document Transmittal Ref. No: TAB-BAH-0003-DSS-
GN-00526 (Rev-00) dated 16 September 2020, please find hereunder the status as follows:

Sl. No. Submittal Ref. No. I Doc No. Type of Documents Approval Status

Method Statement for Installation

------- ~
TAB-BAH-0003-MS-PL-00188 of Plumbing Pumps (Booster, (
1 Revise Re-sub it&
Rev-00

Refer to the attached documents for more details.


Transfer & Circulation Pumps),
Control Panel and Accessories\

(II
8~~/
\ -
(C·fl!i-01)
For your information and action. Info !Action
PO v
PJC
,..
PMl v
Regards, PM2 v
PM3 v
QUA
__ v
DSG ------~

HR

c
'
CON

'\
'\.
MfP
HSE
-~
For/ I PRO
T£N
Major General (Engineer)
DC --
Commander, Qatar Emiri Corps of Engineers (QECE)
2"d Lt. Hamad Jaber Al-Marri
Branch Office
--
----
• I I
Date: 1'-.. r~kl~
Encl. : As above •t l , -

Cc : Wing (7) Office

l" U. Maslamani I I" U . lkhater I znd U. Mubarak I BAL ~


IU!IL~i V ~11
.J

'' 1 7 SEP 2020

BAHADIR QATAR ARMED FORCES Q~~~~~s


CONSTRUCTION QATAR EMIRI CORPS OF ENGIN""-"..........---~
------
Client: QATAR ARMED FORCES - QATAR EMIRI CORPS OF
Contractor: BAHADIR CONSTRUCTION
ENGINEERS
Project: C-108-01 Consultant
DSS Ref. No.: TAB-BAH-0003-DSS-GN-00526
DOCUMENT SUBMITTAL SHEET Date: 16-September-20

To: Qatar Emiri Corps of Engineers Type of Documents: Method Statement

Attn: Major Gen. (Eng) Essa Ali AI-Kubaisi Purpose of Issue: For Approval
DOCUMENT DETAIL NUMBER
S.NO. OF COPY
DOCUMENT NUMBER REV TITLE I DESCRIPTION ISSUED FOR ENCLOSED
Method Statement for Installation of
Plumbing Pumps (Booster, Transfer &
TAB-BAH-0003-MB-PL-00188 00 For Approval
Circulation Pumps), Control Panel and
Accessories

The above listed documents are received and checked against the docu sheet and are found to be
complete

Doc;ym~nt Receival

Received By:
., .. ...
Senior Engineer oeQlj
Project Coordinator

0 Approved 0 Approved with Comments r/ Revise & Resubmit 0 Rejected

Doc. No.: TAB-BAH-OC-F03 Rev. No.:OO Rev. Date: 17-June-2019 Page 1 of 1


Project Dukhan Air Base (C-108-01)

References TAB-BAH-0003-DSS-GN-00526

Method Statement TAB-BAH-0003-MS-PL-00188 dated 16 Sept. 2020

Electrical Comments :

Method Statement for Installation of Plumbing Pumps{Booster, Transfer & Circulation Pumps),
Control Panel and Accessories

Item 2 Reference :

1. In Reference, Kahramaa Electricity Wiring Code 2016 (Kahramaa Regulations) must be


indicated

Item 7.3 Pre-Installation Checks

1. Provide pre-installation check for Earthing Connections of Pump Motor Frames, Controllers
Enclosure to nearest Earthing Bar/Earthing Loop.
2. Provide pre-installation check of Electrical Cables Connection, proper conduit knock out in
enclosure, etc.

Item 7.61nstallation of Plumbing Pumps, Control Panels & Accessories

1. Provide installation Method for Earthing/Bonding connection of Pump Motor Frames and
Controllers Enclosure to nearest Earthing Bar/Earthing Loop. All Non-current Carrying
Metallic Parts of Motors/ Enclosure of Controller shall be connected to the Earthing Loop in
the Pump Rooms/Area. ·
2. Prior to termination of all Electrical/Control Cables, ensure that insulation resistance test has
been conducted.

Prepared by:{}t
~ 0 (J(rv>J;tl

Engr. Jimmy
QECE-Eiectric gineer
BAHADIR
CONSTRUCTION
Table of Contents

1. SCOPE ......................................................................................................................................3
2. REFERENCE ................................................................•.............................•..............................3
3. DEFINITION & ABBREVIATION ..................................•............................................................3
4. RESOURCES ................•.................................................................................................•.........3
4.1 Equipment & Machinery ...........................................................................................................3
4.2 Manpower ................................................................................................................................4
4.3 Materials ..................................................................................................................................4
5. ORGANIZATION CHART ...........................................................................................................5
6. RESPONSIBILITIES ....... ·······~~~········· .............................•.••.•....... I ................................................ 5
6.1 Project Manager.......................................................................................................................5
6.2 Senior Engineer .......................................................................................................................5
7. PROCEDURE ............................................................................................................................6
7.1 Execution Sequence ................................................................................................................6
7.2 Shop Drawing Preparation and Coordination ...........................................................................6
7.3 Pre-Installation Checks ............................................................................................................ 6
7.4 Permits ....................................................................................................................................7
7.5 Inspection of Material Deliveries ..............................................................................................7
7.61nstallation of Plumbing Pumps, Control panels & accessories ................................................ 7
8. QUALITY ASSURANCE ............................................................................................................8
9. HSE ............•......................................................•.......................................................................8
9.1 PPE Requirements ..................................................................................................................8
9.2 Safety Accessories ..................................................................................................................8
9.3 Information to Personnel ..........................................................................................................8
9.4 Emergency Procedure .............................................................................................................9
9.5 Environmentallssues ...............................................................................................................9
9.6 Hazard Identification and Task Analysis (HiTA) .......................................................................9
10. APPENDIX............................................................•...•.•......................................................•...10
10.1 Risk Assessment ................................................................................................................. 10

Doc. No: TAB-SAH.QUA-F04 Rev No: 00 Rev. Date: 09-Feb-2019 Page2 of10
BAHADIR
CONSTRUCTION
1. SCOPE

This method statement is to describe the procedure of which the installation of


plumbing/water supply pumps {Booster, Transfer & Circulation pumps), control
panels and accessories will be carried out on this project.

a. The scope of Work includes the material delivery inspection, installation


inspection to ensure that plumbing pumps are supplied, installed and inspected
for the works accordance with project requirements.

b. The scope will also give brief information about safe working procedure to identify
risk through the risk assessment Matrix.

2.
~FE~'f~~Avf'lr/t 6l;e{;f1ttU tf W lalfl tf CAPE' 2()/ b
• QCS 2014
• Project Specifications
• Approved Material Submittals
• Approved Drawings
• Inspection & Test Plan
• Manufacturer Recommendation Installation Instructions
• Project HSE Plan


3. DEFINITION & ABBREVIATION

"Abbreviation Definition
BAH MIS Bahadir Construction
CLIENT (QECE) Qatar Emiri Corps of Engineers
HSE Health, Safety & Environment
IR Inspection ReQuest
ITP lnsQection Test Plan
MOE Ministry of Environment
MOl Ministry of Interior
MS Method Statement
PQP ProJect QualitY Plan
QA/QC Quality_ Assurance I Quality Control
QCS Qatar Construction Specifications

4. RESOURCES

4.1 Equipment & Machinery


1. Standard Plumber/Fitter Toolbox
2. Lifting Equipment (fork lift/trolleys)
3. Rotary Hammer

Doc. No: TAB·BAH..QUA-F04 Rev No:OO Rev. Date: 09-Feb-2019 Page 3of 10
BAHADIR
CONSTRUCTION
4. Measurement Tape/Spirit Level
5. Safety Ladders/Scaffolding

4.2 Manpower

S no. Category Purpose


1 Project Manager To plan, coordinate, and lead the works
AU works I activities supervision, and
2 Sr. Mechanical Engineer technical support
3 Mechanical Site Engineer On site physical installation supervision
4 QAIQC Engineer Ensure the quality of works executed on site
5 Supervisor I Foreman Work arrangement and supervision
6 Safety Officer Safety and health matter
7 Skilled worker Skill works
8 Helper To help the workers

All the above will individually be responsible for a safe and healthy operational environment
consideration of all the workers in their team related to the execution of their duties and any
other personnel.

Note: Refer to {section 6) for further responsibilities of key personnel.

4.3 Materials

- "Transfer & Booster pumps· (Sizes I Type are as per approved shop Drawings and
material submmals).
- "Circulation Pumps• (Sizes I Type are as per approved shop drawings and material
submittals).
- "Control Panels" (Sizes I Type are as per approved shop drawings and material
submittals).
- •An accessories and valves (Gate valve, Check valve, Flexible connector, Strainers,
etc" (Sizes I Type are as per approved shop drawings and material submittals)

NOTE: All materials shall be confirmed as per approved material submittals, as per
the approved model type, size, rating, color ... ·etc.

The Engineers and foreman on site shall ensure that all necessary equipment is
available as well as fit and safe prior to commencement of work.

Doc. No: TAB-BAH-QUA-F04 RevNo:OO Rev. Date: 09-Feb-2019 Page4of10


BAHADIR
CONSTRUCTION
5. ORGANIZATION CHART
r------------------•
: Project Manager :
~-------· t~-------J
,..---------------, ! .----------------·
11 OAJQC Dept ~~:...,._ _ _ _....,.~---..-• 1
~...., HSE Dept 1
1
----------------· ~--------------~

I
·--------------J---------------
: Project Engineer I Supervisor !
I I
I I

·------------- ·---------------
I

1
I

~ ,.;
r------------------
-~~
1
: Work Force 1
I I
I I
I I

·-----~-----------~
6. RESPONSIBILITIES

6.1 Project Manager

The Project Manager Leads and Directs the team for overall development of the project.
Also, he provides single point of contact in dealing with Employer resolving contractual
Commercial and Technical issues during the progress of the project.

6.2 Senior Engineer


It is the Senior Engineer responsibility to ensure that Quality Management System
requirements are fulfilled and strictly implemented. Moreover, to ensure that the works are
carried out in accordance with this method statement.

6.3 QA/QC Engineer

It is the QC/QC Engineer responsibility to ensure that all plant & equipment being calibrated.
Ensure that all Inspection and Tests are carried out as per Project Requirements, Shop
Drawings, Approved method statement.and Inspection Test Plan and that all are properly
recorded. Also responsible for maintaining all Quality documents and Records relevant to
verification throughout the project cycle.

6.4 Site Engineer I Site Supervisor

It is the Site Engineer I Site Supervisor's duty to organize the work force In a safe manner and
to ensure that safety and protective equipment are being properly utilized. He also ensures
that the method statement procedure is strictly followed and observes any hold-points noted
on the ITP and notify the Engineer for inspection.

6.5 Safety Engineer I Officer

• Enforce the implementation of the HSE management system in the project and support the

Doc. No: TAB-BAH-QUA-F04 Rev No: 00 Rev. Date: 09-Feb-2019 PageS of 10


BAHADIR
CONSTRUCTION
relevant construction Supervisors on all HSE matters;
• Ensure that relevant HSE information and training Is provided to all personnel working in the
assigned area;
• Collaborate with Supervisors in assessing training needs for personnel in the assigned area;
• Reports HSE findings to the relevant construction personnel as well as the HSE manager
and follow up the status of implementation of the identified preventive and corrective
actions; Carry out any other assigned HSE activity.

7. PROCEDURE
7.1 Execution Sequence
The sequence of construction works are as follows:

• Shop drawing preparation & coordination


• Obtaining necessary permits
• Inspection of material deliveries
• Installation of Plumbing Pumps, Control panels & Accessories

7.2 Shop Drawing Preparation and Coordination

Submittal of shop drawings will be done after all necessary coordination is incorporated.
Approved shop drawings will be provided to site engineer for execution. Working with
sketches, parts plans or drawings or any other drawings will not be permitted. Approved shop
drawings will be available in working place during full execution period.

• A close coordination with the Main contractor's (Electrical I Mechanical/ Civil/


Architectural/ Structural) engineers shall take place at all the stages of the work, as
early from Shop drawing preparation, coordination, installation, and system test.
• All the system shop drawings must be reviewed and verified by each discipline
engineers to verify all the requirement are covered.

7.3 Pre-Installation Checks

• Ensure that all safety requirements are In place in accordance with project safety plan.
• Ensure that the latest revision of the approved shop drawing and coordination drawing
is used.
• All materials will be ordered after approval of the drawings and technical submittals.
• All materials will be transported to the site by the supplier and care shall be taken by
the store keeper to ensure that all materials are not damaged during transit.
• Special care shall be taken by the storekeeper to protect the plumbing pumps from
physical damage.
• On receipt of the material at site, QA/QC Engineer/Site Engineer shall inspect the
material internally and inspection shall be offered to the Engineer for approval in MIR
(Material Inspection Request) form. Any non-conforming materials must be labeled by
storekeeper and returned to quarantine area In accordance with procedure. An internal
NCR will be issued.
• Ensure all the material used, have passed receiving inspection in accordance with QA
procedures and are not damaged or defective.
• Ensure that all Installers and helpers are aware of the correct materials handing and
installation procedures to ensure best quality of workmanship. Training shall be
provided by site engineers/supervisors as and when required.
• All plumbing pumps, panels and accessories shall be cleaned before installation.
• Main contractor to ensure that prior to install the plumbing pumps, panels and
Doc. No: TAB-BAH-QUA-F04 RevNo: OO Rev. Date: 09-Feb-2019 Page6of10
BAHADIR
CONSTRUCTION
accessories, all building surfaces to which the units are being installed must be
completed to acceptable tolerance and are in a suitably clean and dry condition.
Access ladders and scaffoldings during construction will be used at site as per the
safety plan.
Prior to start the work, plumbing engineers/supervisors from the execution team shall
ensure that the latest approved construction drawings are available at site.
Installation of plumbing pumps, controllers and accessories shall be coordinated with
architectural, structural, and MEP works. Any deviation shall be intimated to the
engineer for approval prior to start the work.
• Supervisor shall ensure equipment and correct tools are available for installation and to
achieve compliance with the contract requirements.

7.4 Permits

General Cold work permit and Lifting Permits shall be obtained before executing any critical
hazardous work. Hot works permits shall be obtained from concern department before any
grinding and cutting works start up.

7.5 Inspection of Material Deliveries

Site Engineer and QC/QC Engineer shall;

• Check the quantities and types with purchase order.


• Check the quality of delivered material.
• Prepare report and mention if there are incomplete or damaged items and keep such
material separately to invite responsible person from supplier.
• Invite Engineer for inspection before execution.

~\J 1 C, ~OTE: All materials shall confirm to the approved material submittals, and the Engineer
lJ ~~~ ""omments on the same (if any), as per the approved model, type, size, rating ... etc.
~~~ }'f. 7.6 Installation of Plumbing Pumps, Control panels & accessories
\l ~

• Mark the pump location as per approved drawings.
Make t~~~~ete

Z
ndat' n with the r,qvision for fiXing the foundation bolts for the
pumps. 'J'!"v\lf {) (
• Concrete base shall be done y structural team and the size of the concrete base shall
l be as per approved pump mode and structlw:;;IJ..Q~IIDS. ~ Wl~
J ·~ • Install the pumps on the foundation with bber pads _.,... f).,::r{).~~~A~l~· .
';;:) • Fix and tighten bolts after the installation Of pumps. r\.. IJV"'\{./\. • v ' - J"'\l ~

• Connect the inlet and discharge piping along with all valves and accessories such as
isolation valve, strainers, check valves and pressure gauges with reference to approved
shop drawing.
• Install approved flexible pipe connector to inlet and discharge of pump to avoid any
vibration transmission to the pipe line as per the approved drawings.
• Connection of pressure vessel shall be done with reference to manufacturer'~ 1 i ?
jt{stallation recommendation and approved shop drawing (If applicable). Y"S ·It/"\ v '
• / All electrical/control wiring connection and control panel installation along with all
accessories like pressure transmitter and pressure switches shall follow manufacturer's

c~~
recommendation and approved shop drawings.
• Dry run protection float switches to be installed as per manufacturer's recommendation.
(Wherever applicable). (/
t tt{N1-tt l~ cJ~~· ~~~~·
Doc. No: TAB-BAH-QUA-F04 Rev No: 00 Rev. Date: 09-Feb-2019 Page 7 of 10
BAHADIR
CONSTRUCTION
8. QUALITY ASSURANCE
The Quality Engineer is responsible to review, implement, and amend this site procedure.
QA/QC Engineer/Inspector shall ensure that the check sheets are completed by project
engineer I Site engineer in accordance with the ITP requirements.

The project Engineer I Site Engineer shall ensure that all the works shall be done in
accordance with Method Statement & ITP requirements.

All the correspondence and reports shall be forwarded through approved formats. Frequent
quality checks shall be conducted by QA/QC in inspector. Prior to Engineers any Inspection,
discrepancies noted are to be rectified. Inspection request shall be forwarded to the Engineer
progressively for each stage of the work, upon satisfactory completion. Compliance to
Engineer's comments will be required for approval/ acceptance of the works.

• ac Engineers shall monitor all the stages of the work covered by this method
statement, project specified requirement, and approved shop drawings.
• The Inspection and Test plan (ITP), Inspection request (IR) and check sheets shall be
submitted to the Engineer for approval.

9. HSE
9.1 PPE Requirements
As a minimum the following PPE should be used by staff I Labors;

• Safety Shoes
• Safety eyeglasses
• Hand Gloves
• High visibility vest
• Dusk Mask
• Hard Hat (Safety Helmet)

Any additional PPE as required by local rules or mandatory requirement shall be used.

9.2 Safety Accessories


• Traffic Cones
• Warning/barricade/barrier tape
• Safety signs
• Water container for drinking
• First Aid box
• Access Ladder
• Workers rest area
• Portable toilet
• Fire extinguishers
• Sign boards or Emergency contact details/persons

9.3 Information to Personnel

• Safety Induction shall be done in accordance with Main Contractor HSE Policy prior
to start work In site.
• Safety toolbox meetings to be carried out prior to work to all participating workforce
and registered attendance.
• Before job start, check for protective & safety equipment to be use are in order.

Doc.No:TAEhBAH~UArlF04 Rev No: 00 Rev. Date: 09-Feb-2019 Page 8 of 10


BAHADIR
CONSTRUCTION
• Safety personnel & designated responsible person shall ensure that all above is
carried out & any other statutory requirements are compiled before any works takes.
• Hazzard analysis.
• Personnel shall wear hand gloves, safety shoes, hard hat, ear plug & eye protection
during work.
• Use the correct tools to do the task.
• Removal of any obstructive I protruding materials.
• Measures shall be taken on dust exposure.
• Emergency evacuation plan is dealing with emergency situations on site shall be
implemented.

9.4 Emergency Procedure

DtSCOVFRY Of ACCIDENT I EMERGENcY

ACCESS lliE VICTIM SITUATION

ACCESS NEED FOR FIRST AID I MEDICAl


ASSISTANCE I AMBULANCE

CALl EMERGENCY NO.

EMERGENCY

ljEAISTRE§§ PBQCED!.IRE
Signs I Symptom Treatment
Confusion Call medical assistance immediately
Irrational Behavior Place person in a shaded area
Loss of consciousness Wet skin of the person & increase the air movement around
Lack of sweating the person to improve evaporating cooling
Convulsion Cool fluid replacement
Pale hot & dry skin No employee suspect of being ill from heat stress should
send home alone or left unattended unless approved by
physician

9.5 Environmental Issues

Proper disposal of debris shall be carried out according to Local Authority approved dump site
location.

9.6 Hazard Identification and Task Analysis (HITA)

Contractor Shall follow the HITA and if any new activity observed HITA will be revised as
required.

Doc. No: TAB-BAH-QUA-F04 Rev No: 00 Rev. Date: 09-Feb-2019 Page9of 10


BAHADIR
CONSTRUCTION

10. APPENDIX
10.1 Risk Assessment

Doc. No: TAB-BAH-QUA-F04 Rev No: 00 Rev. Date: 09-Feb-2019 Page 10 of10
Contractor: Contract No. C-1 08-01 Client:

RISK ASSESSMENT
BAHADIR FOR METHOD STATEMENT -INSTALLATION OF PlUMBING PUMPS,
CONTROL PANEL AND ACCESSORIES
CONSTRUCTION

ACTIVIlY: INSTALLATION OF PLUMBING PUMPS CONTROL PANEL AND ACCESSORIES

Severe & Fatality - Multiple LTI or Fatality Certain or Imminent- Absence of control measures to
5= I 2. Total structural or environmental damages or 5= prevent occupational hazard to workers, resulting
PMV/Material permanent disability or fatality.
Very Likely- Control measures are not effectively
1. Major- Lost Time Injury (LTI) 2) Operational damages -
4= I 4= implemented; thus, likelihood of hazard occurrence is hi2h.l 01 to 04 I LOW
PMV/Material
resulting to lost Time
1. Restricted - Restricted Work Case (RWC) injuries Likely- Control measures are in place, but the likelihood of
3= I 3=
2. Serious damages to PMV/Materiai/Structure hazard occurrence is minimal, and that the injury is minor I OS to 09 I MEDIUM
1. Minor- Medical Treatment Case (MTC) injuries May Happen -Control measures are in place, but the
2= I 2. Damage repair need from third party for 2= possibility of hazard may occur due to third party or u..___ -
PMV/Material/Structure act or conditions. 110 to 16 1 HIGH

1. Negligible- First Aid Case (FAC)/Minor damages Very Unlikely - Control measures are effectively
1= I 2. Damages is minor and can be repaired internal company 1= implemented, but the resulting injury or illness only l 17to2S I SERIOUS
source requires first aid.

Title: Risk Assessment: Method Statement for Installation of Plumbing Pumps Control Panel and Accessories Page(s):1 of 7
Document No.: TAB-BAH-0003-MS-PL-00188 I Rev. 00 Date: 02/05/2020
Contractor. Client:
Contract No. C-1 08-01

RISK ASSESSMENT
BAHADIR FOR METHOD STATEMENT -INSTALlATION OF PLUMBING PUMPS,
CONTROL PANEL AND ACCESSORIES
CONSTRUCTION

s. l I ····"'·-· .....~ I Controls


no. .
Activity
II Hazard

• Site Access and


Vehicle reversing.
• Unauthorized
• Delivery vehicle and driver will follow the instruction of the access control officer and get the gate pass
before entering the site.
delivery vehicle
Delivery of ' • Ensure all personnel involve go through the site Safety induction before any activities.
• Temporary Access • Task briefing will be conducted before any activities .
1
Plumbing
Pumps, Control I Obstruction by
equipment or
3 3 9 •

Ensure vehicles reverse under supervision
Banks/Flags man must be provided to monitor the movement of the vehicles.
I 2 I 2 I 4
Panel &
accessories another vehicle • Ensure only qualified personnel use/operate lifting equipment
• Failure of lifting • All lifting will be check by qualified personnel before allowed to be use in the site.
I equipment • Prevent unauthorized personnel from entering the risk area during the delivery.

• Proper access will be provided and maintain,


Access to • Trip, Slip & Falling • Do the proper housekeeping,
workplace/Site/ hazard, Improper
Storage area.
• Provide the proper walkway
2 1 access, access • During the safety Induction, signage will be communicated to all workers regarding the access and all
3 3 9 I 1 I 3 I 3
obstruction and others Site safety Sign age.
poor housekeeping.
• Toolbox talks regarding the Access will be conducted to all workers,

Title: Risk Assessment: Method Statement for Installation of Plumbing Pumps Control Panel and Accessories Page(s):2 of 7
Document No.: TAB-BAH-0003-MS-PL-00188 Rev.OO Date: 02/0512020
Contractor: Client:
Contract No. C-108-01

RISK ASSESSMENT
BAHADIR FOR METHOD STATEMENT -INSTAlLATION OF PLUMBING PUMPS,
CONTROL PANEL AND ACCESSORIES
CONSTRUCTION

Residual
Initial risk
s. Activity Hazard
Controls risk
no. L s RR L s RR
Fall on the same • Struck By • Proper monitoring and Supervision will be put in place
level,
Trip and Slip
hazards

I • All operative to receive manual handling training.


I
• Ensure personnel keep clear of work area with exclusion zones.

Loading, • Falling of materials, • Don't place hand or any other body parts under load .
Unloading of • Collision with other • Trained flag man will be provided to control the movement of equipment.
Plumbing Pumps plant vehicles or • Regular Toolbox talk will be conducted for all workers regarding the Manual Handling.
object, • The lifting equipment must be use & certified.
Forklift or manual
Pallet Jack can be
• Access obstruction • Operator shall be trained and certified by local authority, by third party and copy of certificate will be
by Materials submitted to HSE Department.
3
use during
unloading I
I
• physical injury such
as a bruise, cut,
3 3 9 •

Forklift to be use will be inspected and site inspection sticker will be pasted on it.
Proper barricading of the area and sign board in place to avoid unauthorized entry.
2 2 4

Manually puncture and pinch • Operator sound horn/reverse buzzer to give warning. I
I
transfers of point. • Operator will inspect his equipment as per dally checklist. I
equipment • Work in charge shall ensure that dally inspection of the lifting equipment and ensure that daily work
• Musculoskeletal !

disorders briefing Is done for all workers.


• Forklift operator shall have appropriate valid driver's license and third-party training certificate .
• Materials will properly arrange before transfer to designated area for storage or for the Installation
- L __ _
-- - -- ----- - --- --

Title: Risk Assessment: Method Statement for Installation of Plumbing Pumps Control Panel and Accessories Page(s):3 of 7
Document No.: TAB-BAH-0003-MS-PL-00188 I Rev. 00 Date: 02/0512020
Contractor: Client:
Contract No. C-1 08-01

RISK ASSESSMENT
BAHADIR FOR METHOD STATEMENT -INSTALLATION OF PLUMBING PUMPS,
CONTROL PANEL AND ACCESSORIES ..
CONSTRUCTION
I
Residual
s. Initial risk
Controls risk
Activity Hazard
no. l s RR L s RR
I • PPE will be provided for all workers involved. (Hard Hat, Hand gloves, Safety Vest, Eyes Google's, Dust
mask and Safety Shoe)

r-- II
• Proper storage of the materials will be put In place In a designated area .
• All operatives will be given adequate training.
Material Storage
I • Safety brief on Hazards related will be communicated to concern workers .
Transfer of • Pinch points • Only certified operators will be allowed to operate the lifting equipment.
4 Plumbing pumps • Entrapment 3 3 9 • The area will be barricaded, and appropriate signage's will be pasted .
2 2 4
from storage • Struck by • Only Authorized personnel will be allowed •
area to task
I • Only trained personnel will be allowed•
location • Proper monitoring and supervision will be put in place .
• Trained supervisor must be present during the activities .
I
• Power tools training will be conducted for all workers .
I • Accident and • All the power tools shall be checked by the trained person periodically and visually checked by the
store in-charge before issue.
I incidents from
Use of power
handling of the • Power tools guard must not remove.
5 tools & Hand
power tools
3 3 9 • Inspection record and colour code shall be maintained at store .
2 2 4
tools • Electric shock • Workers must be trained on safe use of power tools.
• Hand injury • Regular TBT will be conducted on Power tools.
• PPE will be use .
• Monitoring and supervision will be put In place .
• Doub_!_e insulated (lllJgs and industrial_ sockets_shall be used.

Title: Risk Assessment: Method Statement for Installation of Plumbing Pumps Control Panel and Accessories Page(s):4 of 7
Document No.: TAB-BAH-0003-MS-PL-00188 I Rev. 00 Date: 02105/2020
Contractor: Client:
Contract No. C-1 08-01

RISK ASSESSMENT
BAHADIR FOR METHOD STATEMENT -INSTALLATION OF PLUMBING PUMPS,
CONTROL PANEL AND ACCESSORIES
CONSTRUCTION

s.
I I

I
Initial risk
Controls
I Residual
risk
I
Activity Hazard
no. l s RR L s RR
Manual • Manually transfer of
• All operatives to receive manual handling training.
the unit can lead to
Handling
physical injuries such • Ensure personnel keep clear of work area with exclusion zones.
as a bruise, cut, • Don't place hand or any other body parts under load during the materials transfer/installation .
6
• Manual I
puncture and 3 3 9 • Regular TBT will be conducted by Supervisor/Foreman in charge regarding the manual handling.
Transfer of
musculoskeletal • Adequate numbers of workers will be provided .
plumbing pumps
disorder • Mechanical means such as materials lifter will be use during the installation and area will be
during the barricaded.
installation • Pinch point
• Fall Hazards • PPW will be worn .
1---
Disposal of
wastage
• Fire • Wastage generated from works shall be removed and stored at designated place and to be disposed
with approved contractor.
7
Waste • Soil Contamination 2 3 6
• Waste segregation will be followed according to the site requirements.
2 2 4
segregation • Waste Segregation
• Regular housekeeping will be followed
Housekeeping

• Regular Toolbox talk on Heat stress will be conducted for all workers
• Stop work will be implemented if there is adverse weather condition.
• Heat Stress • Wear light coloured and loose-fitting clothes
Summer Weather • Heat Stroke • Take a staggered break in places where is sun shelter
8 Condition during • Exhaustion 3 4 12 • Provide enough water to workers to prevent dehydration 2 2 4
the task/Activities. • Collapse • Provide sun shelter for all workers -
• Dehydration • In case of heat stroke ensure ice, packs are available in clinic or cool water to take down temperature
• Comply with summer working hours as dictated in labour law.
• Proper monitoring will be put in place •
Title: Risk Assessment: Method Statement for Installation of Plumbing Pumps Control Panel and Accessories I Page(s):5 of 7
Document No.: TAB-BAH-0003-MS-PL-00188 I Rev.OO I Date: 02/05/2020
Contractor. Client:
Contract No. C-1 08-01

RISK ASSESSMENT
BAHADIR FOR METHOD STATEMENT -INSTALLATION OF PLUMBING PUMPS,
CONTROL PANEL AND ACCESSORIES
CONSTRUCTtON

Initial risk
Residual I
s. Activity Hazard
Controls risk
no. l s RR L s RR
• Induction and training shall be provided to all workers and staffs
• Young workers and persons who have the tendency to take risk shall be identified and supervised
• Accidents and closely.
9 Human behaviour incidents due to
human errors
3 3 9 • All violations related to the Mechanical installation, electrical installation and manipulation I short cut, 2 2 4
electric tools shall be treated seriously and shall be imposed with disciplinary action.
• Horseplay
• Periodic breaks shall be taken to reduce stress and strain on the workers
• All personnel must be aware ofthe project Emergency preparedness and response plan .
• Everyone must know the chain of communication in the event of emergency•
• Emergency contact details shall be displayed at conspicuous area of the site.
• Standby person shall be provided for the emergency shut down of equipment during accidental failure
Execution of and discharges.
10 emergency • Unawareness about
3 3 9 • All emergency equipment must be available and regularly inspected. 2 2 4
the plan
response plan • All personnel must be physically frt: to work on board .
• Trained first aider must be deployed on site for contingencies.
• All search party must be aware of their area of responsibility .
• Regular review of emergency response and_preparedness plan from the main contractor•

Title: Risk Assessment: Method Statement for Installation of Plumbing Pumps Control Panel and Accessories Page(s):6 of 7
Document No.: TAB-BAH-0003-MS-PL.00188 I Rev. 00 Date: 0210512020
Contractor: Client:
Contract No. C-1 08-01

RISK ASSESSMENT
BAHADIR FOR METHOD STATEMENT -INSTALLATION OF PLUMBING PUMPS,
CONTROL PANEL AND ACCESSORIES
CONSTRUCTION

CLASSIFICAnoN OF CHART

Likelihood of Risk
likelihood Description Rating
Unlikely Occurrence close to zero 1 Classification
May Happen Capable of taking Place 2
Likely Tend or Inclined to Occur 3
1-4 Attention Required- Low Risk
I
5-9 Corrective Measures Required- Medium Risk
Very Likely High Inclination of Occurrence 4 10-16 Corrective Action Required- High Risk
Certain Most Definitely Happen- Not "If but When" 5 20-25 Elimination of Hazard - Serious Risk

Severitv of Risk
Severity Description Rating likelihood
Minor Injury First-Aid on Site 1 1 2 3 4 I 5
Minor Injury Treatment Off Site 2 1 1 2 3 4 I 5
Up-to-3 days Injury Limited or no work for three days 3 2 2 4 6 8 I 10
Major Injury Reportable 4 Severity I 3 3 6 9 ll I 15
Death ----- - -
5 '
I 4 4 8 12 ..:r. . ~
5 s 10 lS _, ....... ~

Title: Risk Assessment: Method Statement for Installation of Plumbing Pumps Control Panel and Accessories Page(s):7 of 7
Document No.: TAB-BAH..0003-MS-PL-00188 I Rev. 00 Date: 02/05/2020
BAHADIR
CONSTRUCTION
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERING

Contract No. C-1 08-01

METHOD STATEMENT

DOCUMENT TITLE:
METHOD OF.STATEMENT FOR INSTALLATION OF PLUMBING PUMPS (BOOSTER, TRANSFER &
CIRCULATION PUMPS), CONTROL PANEL AND ACCESSORIES

MS Ref. No.: TAB-BAH-0003-MS-PL-00188 Rev. No: 00

PREPARED BY: REVIEWED BY. APPROVED BY:


Project QAIQC
Position: QA/QC Chief HSE Manager MEP Manager Project Director
Manager Manager
Stuart Jonathan
Name: Anthony Madayag Erkan Firat Selim Molu Emre Bakkal
Tannahill Wallace

Doc. No: TAB-BAH.QUA-F04 Rev No: 00 Rev. Date: ()9.Felr2019 Page 1 of 10

You might also like