TAB-BAH-0003-MS-PL-00188 - Method Statement For Installation of Plumbing Pumps, Control Panel and Accessories-PM2
TAB-BAH-0003-MS-PL-00188 - Method Statement For Installation of Plumbing Pumps, Control Panel and Accessories-PM2
lt
Qatar Emiri Corps of Engineers 41_;bill4l_»A~I ~~\ c::~
P.O. Box: 5735 - 9575 Doha- Qatar _;--.J:J- L:...,.lll 9575- 5735 : y (.)4
Ref: QECE/WING7/DKABIC-108-0l/20/05977
Date:
14 OCT 2020 RE~~:·~,ED ' v ' ~·-~.J
Reference to the above subject and your Document Transmittal Ref. No: TAB-BAH-0003-DSS-
GN-00526 (Rev-00) dated 16 September 2020, please find hereunder the status as follows:
Sl. No. Submittal Ref. No. I Doc No. Type of Documents Approval Status
------- ~
TAB-BAH-0003-MS-PL-00188 of Plumbing Pumps (Booster, (
1 Revise Re-sub it&
Rev-00
(II
8~~/
\ -
(C·fl!i-01)
For your information and action. Info !Action
PO v
PJC
,..
PMl v
Regards, PM2 v
PM3 v
QUA
__ v
DSG ------~
HR
c
'
CON
'\
'\.
MfP
HSE
-~
For/ I PRO
T£N
Major General (Engineer)
DC --
Commander, Qatar Emiri Corps of Engineers (QECE)
2"d Lt. Hamad Jaber Al-Marri
Branch Office
--
----
• I I
Date: 1'-.. r~kl~
Encl. : As above •t l , -
Attn: Major Gen. (Eng) Essa Ali AI-Kubaisi Purpose of Issue: For Approval
DOCUMENT DETAIL NUMBER
S.NO. OF COPY
DOCUMENT NUMBER REV TITLE I DESCRIPTION ISSUED FOR ENCLOSED
Method Statement for Installation of
Plumbing Pumps (Booster, Transfer &
TAB-BAH-0003-MB-PL-00188 00 For Approval
Circulation Pumps), Control Panel and
Accessories
The above listed documents are received and checked against the docu sheet and are found to be
complete
Doc;ym~nt Receival
Received By:
., .. ...
Senior Engineer oeQlj
Project Coordinator
References TAB-BAH-0003-DSS-GN-00526
Electrical Comments :
Method Statement for Installation of Plumbing Pumps{Booster, Transfer & Circulation Pumps),
Control Panel and Accessories
Item 2 Reference :
1. Provide pre-installation check for Earthing Connections of Pump Motor Frames, Controllers
Enclosure to nearest Earthing Bar/Earthing Loop.
2. Provide pre-installation check of Electrical Cables Connection, proper conduit knock out in
enclosure, etc.
1. Provide installation Method for Earthing/Bonding connection of Pump Motor Frames and
Controllers Enclosure to nearest Earthing Bar/Earthing Loop. All Non-current Carrying
Metallic Parts of Motors/ Enclosure of Controller shall be connected to the Earthing Loop in
the Pump Rooms/Area. ·
2. Prior to termination of all Electrical/Control Cables, ensure that insulation resistance test has
been conducted.
Prepared by:{}t
~ 0 (J(rv>J;tl
Engr. Jimmy
QECE-Eiectric gineer
BAHADIR
CONSTRUCTION
Table of Contents
1. SCOPE ......................................................................................................................................3
2. REFERENCE ................................................................•.............................•..............................3
3. DEFINITION & ABBREVIATION ..................................•............................................................3
4. RESOURCES ................•.................................................................................................•.........3
4.1 Equipment & Machinery ...........................................................................................................3
4.2 Manpower ................................................................................................................................4
4.3 Materials ..................................................................................................................................4
5. ORGANIZATION CHART ...........................................................................................................5
6. RESPONSIBILITIES ....... ·······~~~········· .............................•.••.•....... I ................................................ 5
6.1 Project Manager.......................................................................................................................5
6.2 Senior Engineer .......................................................................................................................5
7. PROCEDURE ............................................................................................................................6
7.1 Execution Sequence ................................................................................................................6
7.2 Shop Drawing Preparation and Coordination ...........................................................................6
7.3 Pre-Installation Checks ............................................................................................................ 6
7.4 Permits ....................................................................................................................................7
7.5 Inspection of Material Deliveries ..............................................................................................7
7.61nstallation of Plumbing Pumps, Control panels & accessories ................................................ 7
8. QUALITY ASSURANCE ............................................................................................................8
9. HSE ............•......................................................•.......................................................................8
9.1 PPE Requirements ..................................................................................................................8
9.2 Safety Accessories ..................................................................................................................8
9.3 Information to Personnel ..........................................................................................................8
9.4 Emergency Procedure .............................................................................................................9
9.5 Environmentallssues ...............................................................................................................9
9.6 Hazard Identification and Task Analysis (HiTA) .......................................................................9
10. APPENDIX............................................................•...•.•......................................................•...10
10.1 Risk Assessment ................................................................................................................. 10
Doc. No: TAB-SAH.QUA-F04 Rev No: 00 Rev. Date: 09-Feb-2019 Page2 of10
BAHADIR
CONSTRUCTION
1. SCOPE
b. The scope will also give brief information about safe working procedure to identify
risk through the risk assessment Matrix.
2.
~FE~'f~~Avf'lr/t 6l;e{;f1ttU tf W lalfl tf CAPE' 2()/ b
• QCS 2014
• Project Specifications
• Approved Material Submittals
• Approved Drawings
• Inspection & Test Plan
• Manufacturer Recommendation Installation Instructions
• Project HSE Plan
•
3. DEFINITION & ABBREVIATION
"Abbreviation Definition
BAH MIS Bahadir Construction
CLIENT (QECE) Qatar Emiri Corps of Engineers
HSE Health, Safety & Environment
IR Inspection ReQuest
ITP lnsQection Test Plan
MOE Ministry of Environment
MOl Ministry of Interior
MS Method Statement
PQP ProJect QualitY Plan
QA/QC Quality_ Assurance I Quality Control
QCS Qatar Construction Specifications
4. RESOURCES
Doc. No: TAB·BAH..QUA-F04 Rev No:OO Rev. Date: 09-Feb-2019 Page 3of 10
BAHADIR
CONSTRUCTION
4. Measurement Tape/Spirit Level
5. Safety Ladders/Scaffolding
4.2 Manpower
All the above will individually be responsible for a safe and healthy operational environment
consideration of all the workers in their team related to the execution of their duties and any
other personnel.
4.3 Materials
- "Transfer & Booster pumps· (Sizes I Type are as per approved shop Drawings and
material submmals).
- "Circulation Pumps• (Sizes I Type are as per approved shop drawings and material
submittals).
- "Control Panels" (Sizes I Type are as per approved shop drawings and material
submittals).
- •An accessories and valves (Gate valve, Check valve, Flexible connector, Strainers,
etc" (Sizes I Type are as per approved shop drawings and material submittals)
NOTE: All materials shall be confirmed as per approved material submittals, as per
the approved model type, size, rating, color ... ·etc.
The Engineers and foreman on site shall ensure that all necessary equipment is
available as well as fit and safe prior to commencement of work.
I
·--------------J---------------
: Project Engineer I Supervisor !
I I
I I
·------------- ·---------------
I
1
I
~ ,.;
r------------------
-~~
1
: Work Force 1
I I
I I
I I
·-----~-----------~
6. RESPONSIBILITIES
The Project Manager Leads and Directs the team for overall development of the project.
Also, he provides single point of contact in dealing with Employer resolving contractual
Commercial and Technical issues during the progress of the project.
It is the QC/QC Engineer responsibility to ensure that all plant & equipment being calibrated.
Ensure that all Inspection and Tests are carried out as per Project Requirements, Shop
Drawings, Approved method statement.and Inspection Test Plan and that all are properly
recorded. Also responsible for maintaining all Quality documents and Records relevant to
verification throughout the project cycle.
It is the Site Engineer I Site Supervisor's duty to organize the work force In a safe manner and
to ensure that safety and protective equipment are being properly utilized. He also ensures
that the method statement procedure is strictly followed and observes any hold-points noted
on the ITP and notify the Engineer for inspection.
• Enforce the implementation of the HSE management system in the project and support the
7. PROCEDURE
7.1 Execution Sequence
The sequence of construction works are as follows:
Submittal of shop drawings will be done after all necessary coordination is incorporated.
Approved shop drawings will be provided to site engineer for execution. Working with
sketches, parts plans or drawings or any other drawings will not be permitted. Approved shop
drawings will be available in working place during full execution period.
• Ensure that all safety requirements are In place in accordance with project safety plan.
• Ensure that the latest revision of the approved shop drawing and coordination drawing
is used.
• All materials will be ordered after approval of the drawings and technical submittals.
• All materials will be transported to the site by the supplier and care shall be taken by
the store keeper to ensure that all materials are not damaged during transit.
• Special care shall be taken by the storekeeper to protect the plumbing pumps from
physical damage.
• On receipt of the material at site, QA/QC Engineer/Site Engineer shall inspect the
material internally and inspection shall be offered to the Engineer for approval in MIR
(Material Inspection Request) form. Any non-conforming materials must be labeled by
storekeeper and returned to quarantine area In accordance with procedure. An internal
NCR will be issued.
• Ensure all the material used, have passed receiving inspection in accordance with QA
procedures and are not damaged or defective.
• Ensure that all Installers and helpers are aware of the correct materials handing and
installation procedures to ensure best quality of workmanship. Training shall be
provided by site engineers/supervisors as and when required.
• All plumbing pumps, panels and accessories shall be cleaned before installation.
• Main contractor to ensure that prior to install the plumbing pumps, panels and
Doc. No: TAB-BAH-QUA-F04 RevNo: OO Rev. Date: 09-Feb-2019 Page6of10
BAHADIR
CONSTRUCTION
accessories, all building surfaces to which the units are being installed must be
completed to acceptable tolerance and are in a suitably clean and dry condition.
Access ladders and scaffoldings during construction will be used at site as per the
safety plan.
Prior to start the work, plumbing engineers/supervisors from the execution team shall
ensure that the latest approved construction drawings are available at site.
Installation of plumbing pumps, controllers and accessories shall be coordinated with
architectural, structural, and MEP works. Any deviation shall be intimated to the
engineer for approval prior to start the work.
• Supervisor shall ensure equipment and correct tools are available for installation and to
achieve compliance with the contract requirements.
7.4 Permits
General Cold work permit and Lifting Permits shall be obtained before executing any critical
hazardous work. Hot works permits shall be obtained from concern department before any
grinding and cutting works start up.
~\J 1 C, ~OTE: All materials shall confirm to the approved material submittals, and the Engineer
lJ ~~~ ""omments on the same (if any), as per the approved model, type, size, rating ... etc.
~~~ }'f. 7.6 Installation of Plumbing Pumps, Control panels & accessories
\l ~
•
• Mark the pump location as per approved drawings.
Make t~~~~ete
Z
ndat' n with the r,qvision for fiXing the foundation bolts for the
pumps. 'J'!"v\lf {) (
• Concrete base shall be done y structural team and the size of the concrete base shall
l be as per approved pump mode and structlw:;;IJ..Q~IIDS. ~ Wl~
J ·~ • Install the pumps on the foundation with bber pads _.,... f).,::r{).~~~A~l~· .
';;:) • Fix and tighten bolts after the installation Of pumps. r\.. IJV"'\{./\. • v ' - J"'\l ~
• Connect the inlet and discharge piping along with all valves and accessories such as
isolation valve, strainers, check valves and pressure gauges with reference to approved
shop drawing.
• Install approved flexible pipe connector to inlet and discharge of pump to avoid any
vibration transmission to the pipe line as per the approved drawings.
• Connection of pressure vessel shall be done with reference to manufacturer'~ 1 i ?
jt{stallation recommendation and approved shop drawing (If applicable). Y"S ·It/"\ v '
• / All electrical/control wiring connection and control panel installation along with all
accessories like pressure transmitter and pressure switches shall follow manufacturer's
c~~
recommendation and approved shop drawings.
• Dry run protection float switches to be installed as per manufacturer's recommendation.
(Wherever applicable). (/
t tt{N1-tt l~ cJ~~· ~~~~·
Doc. No: TAB-BAH-QUA-F04 Rev No: 00 Rev. Date: 09-Feb-2019 Page 7 of 10
BAHADIR
CONSTRUCTION
8. QUALITY ASSURANCE
The Quality Engineer is responsible to review, implement, and amend this site procedure.
QA/QC Engineer/Inspector shall ensure that the check sheets are completed by project
engineer I Site engineer in accordance with the ITP requirements.
The project Engineer I Site Engineer shall ensure that all the works shall be done in
accordance with Method Statement & ITP requirements.
All the correspondence and reports shall be forwarded through approved formats. Frequent
quality checks shall be conducted by QA/QC in inspector. Prior to Engineers any Inspection,
discrepancies noted are to be rectified. Inspection request shall be forwarded to the Engineer
progressively for each stage of the work, upon satisfactory completion. Compliance to
Engineer's comments will be required for approval/ acceptance of the works.
• ac Engineers shall monitor all the stages of the work covered by this method
statement, project specified requirement, and approved shop drawings.
• The Inspection and Test plan (ITP), Inspection request (IR) and check sheets shall be
submitted to the Engineer for approval.
9. HSE
9.1 PPE Requirements
As a minimum the following PPE should be used by staff I Labors;
• Safety Shoes
• Safety eyeglasses
• Hand Gloves
• High visibility vest
• Dusk Mask
• Hard Hat (Safety Helmet)
Any additional PPE as required by local rules or mandatory requirement shall be used.
• Safety Induction shall be done in accordance with Main Contractor HSE Policy prior
to start work In site.
• Safety toolbox meetings to be carried out prior to work to all participating workforce
and registered attendance.
• Before job start, check for protective & safety equipment to be use are in order.
EMERGENCY
ljEAISTRE§§ PBQCED!.IRE
Signs I Symptom Treatment
Confusion Call medical assistance immediately
Irrational Behavior Place person in a shaded area
Loss of consciousness Wet skin of the person & increase the air movement around
Lack of sweating the person to improve evaporating cooling
Convulsion Cool fluid replacement
Pale hot & dry skin No employee suspect of being ill from heat stress should
send home alone or left unattended unless approved by
physician
Proper disposal of debris shall be carried out according to Local Authority approved dump site
location.
Contractor Shall follow the HITA and if any new activity observed HITA will be revised as
required.
10. APPENDIX
10.1 Risk Assessment
Doc. No: TAB-BAH-QUA-F04 Rev No: 00 Rev. Date: 09-Feb-2019 Page 10 of10
Contractor: Contract No. C-1 08-01 Client:
RISK ASSESSMENT
BAHADIR FOR METHOD STATEMENT -INSTALLATION OF PlUMBING PUMPS,
CONTROL PANEL AND ACCESSORIES
CONSTRUCTION
Severe & Fatality - Multiple LTI or Fatality Certain or Imminent- Absence of control measures to
5= I 2. Total structural or environmental damages or 5= prevent occupational hazard to workers, resulting
PMV/Material permanent disability or fatality.
Very Likely- Control measures are not effectively
1. Major- Lost Time Injury (LTI) 2) Operational damages -
4= I 4= implemented; thus, likelihood of hazard occurrence is hi2h.l 01 to 04 I LOW
PMV/Material
resulting to lost Time
1. Restricted - Restricted Work Case (RWC) injuries Likely- Control measures are in place, but the likelihood of
3= I 3=
2. Serious damages to PMV/Materiai/Structure hazard occurrence is minimal, and that the injury is minor I OS to 09 I MEDIUM
1. Minor- Medical Treatment Case (MTC) injuries May Happen -Control measures are in place, but the
2= I 2. Damage repair need from third party for 2= possibility of hazard may occur due to third party or u..___ -
PMV/Material/Structure act or conditions. 110 to 16 1 HIGH
1. Negligible- First Aid Case (FAC)/Minor damages Very Unlikely - Control measures are effectively
1= I 2. Damages is minor and can be repaired internal company 1= implemented, but the resulting injury or illness only l 17to2S I SERIOUS
source requires first aid.
Title: Risk Assessment: Method Statement for Installation of Plumbing Pumps Control Panel and Accessories Page(s):1 of 7
Document No.: TAB-BAH-0003-MS-PL-00188 I Rev. 00 Date: 02/05/2020
Contractor. Client:
Contract No. C-1 08-01
RISK ASSESSMENT
BAHADIR FOR METHOD STATEMENT -INSTALlATION OF PLUMBING PUMPS,
CONTROL PANEL AND ACCESSORIES
CONSTRUCTION
Title: Risk Assessment: Method Statement for Installation of Plumbing Pumps Control Panel and Accessories Page(s):2 of 7
Document No.: TAB-BAH-0003-MS-PL-00188 Rev.OO Date: 02/0512020
Contractor: Client:
Contract No. C-108-01
RISK ASSESSMENT
BAHADIR FOR METHOD STATEMENT -INSTAlLATION OF PLUMBING PUMPS,
CONTROL PANEL AND ACCESSORIES
CONSTRUCTION
Residual
Initial risk
s. Activity Hazard
Controls risk
no. L s RR L s RR
Fall on the same • Struck By • Proper monitoring and Supervision will be put in place
level,
Trip and Slip
hazards
Loading, • Falling of materials, • Don't place hand or any other body parts under load .
Unloading of • Collision with other • Trained flag man will be provided to control the movement of equipment.
Plumbing Pumps plant vehicles or • Regular Toolbox talk will be conducted for all workers regarding the Manual Handling.
object, • The lifting equipment must be use & certified.
Forklift or manual
Pallet Jack can be
• Access obstruction • Operator shall be trained and certified by local authority, by third party and copy of certificate will be
by Materials submitted to HSE Department.
3
use during
unloading I
I
• physical injury such
as a bruise, cut,
3 3 9 •
•
Forklift to be use will be inspected and site inspection sticker will be pasted on it.
Proper barricading of the area and sign board in place to avoid unauthorized entry.
2 2 4
Manually puncture and pinch • Operator sound horn/reverse buzzer to give warning. I
I
transfers of point. • Operator will inspect his equipment as per dally checklist. I
equipment • Work in charge shall ensure that dally inspection of the lifting equipment and ensure that daily work
• Musculoskeletal !
Title: Risk Assessment: Method Statement for Installation of Plumbing Pumps Control Panel and Accessories Page(s):3 of 7
Document No.: TAB-BAH-0003-MS-PL-00188 I Rev. 00 Date: 02/0512020
Contractor: Client:
Contract No. C-1 08-01
RISK ASSESSMENT
BAHADIR FOR METHOD STATEMENT -INSTALLATION OF PLUMBING PUMPS,
CONTROL PANEL AND ACCESSORIES ..
CONSTRUCTION
I
Residual
s. Initial risk
Controls risk
Activity Hazard
no. l s RR L s RR
I • PPE will be provided for all workers involved. (Hard Hat, Hand gloves, Safety Vest, Eyes Google's, Dust
mask and Safety Shoe)
r-- II
• Proper storage of the materials will be put In place In a designated area .
• All operatives will be given adequate training.
Material Storage
I • Safety brief on Hazards related will be communicated to concern workers .
Transfer of • Pinch points • Only certified operators will be allowed to operate the lifting equipment.
4 Plumbing pumps • Entrapment 3 3 9 • The area will be barricaded, and appropriate signage's will be pasted .
2 2 4
from storage • Struck by • Only Authorized personnel will be allowed •
area to task
I • Only trained personnel will be allowed•
location • Proper monitoring and supervision will be put in place .
• Trained supervisor must be present during the activities .
I
• Power tools training will be conducted for all workers .
I • Accident and • All the power tools shall be checked by the trained person periodically and visually checked by the
store in-charge before issue.
I incidents from
Use of power
handling of the • Power tools guard must not remove.
5 tools & Hand
power tools
3 3 9 • Inspection record and colour code shall be maintained at store .
2 2 4
tools • Electric shock • Workers must be trained on safe use of power tools.
• Hand injury • Regular TBT will be conducted on Power tools.
• PPE will be use .
• Monitoring and supervision will be put In place .
• Doub_!_e insulated (lllJgs and industrial_ sockets_shall be used.
Title: Risk Assessment: Method Statement for Installation of Plumbing Pumps Control Panel and Accessories Page(s):4 of 7
Document No.: TAB-BAH-0003-MS-PL-00188 I Rev. 00 Date: 02105/2020
Contractor: Client:
Contract No. C-1 08-01
RISK ASSESSMENT
BAHADIR FOR METHOD STATEMENT -INSTALLATION OF PLUMBING PUMPS,
CONTROL PANEL AND ACCESSORIES
CONSTRUCTION
s.
I I
I
Initial risk
Controls
I Residual
risk
I
Activity Hazard
no. l s RR L s RR
Manual • Manually transfer of
• All operatives to receive manual handling training.
the unit can lead to
Handling
physical injuries such • Ensure personnel keep clear of work area with exclusion zones.
as a bruise, cut, • Don't place hand or any other body parts under load during the materials transfer/installation .
6
• Manual I
puncture and 3 3 9 • Regular TBT will be conducted by Supervisor/Foreman in charge regarding the manual handling.
Transfer of
musculoskeletal • Adequate numbers of workers will be provided .
plumbing pumps
disorder • Mechanical means such as materials lifter will be use during the installation and area will be
during the barricaded.
installation • Pinch point
• Fall Hazards • PPW will be worn .
1---
Disposal of
wastage
• Fire • Wastage generated from works shall be removed and stored at designated place and to be disposed
with approved contractor.
7
Waste • Soil Contamination 2 3 6
• Waste segregation will be followed according to the site requirements.
2 2 4
segregation • Waste Segregation
• Regular housekeeping will be followed
Housekeeping
• Regular Toolbox talk on Heat stress will be conducted for all workers
• Stop work will be implemented if there is adverse weather condition.
• Heat Stress • Wear light coloured and loose-fitting clothes
Summer Weather • Heat Stroke • Take a staggered break in places where is sun shelter
8 Condition during • Exhaustion 3 4 12 • Provide enough water to workers to prevent dehydration 2 2 4
the task/Activities. • Collapse • Provide sun shelter for all workers -
• Dehydration • In case of heat stroke ensure ice, packs are available in clinic or cool water to take down temperature
• Comply with summer working hours as dictated in labour law.
• Proper monitoring will be put in place •
Title: Risk Assessment: Method Statement for Installation of Plumbing Pumps Control Panel and Accessories I Page(s):5 of 7
Document No.: TAB-BAH-0003-MS-PL-00188 I Rev.OO I Date: 02/05/2020
Contractor. Client:
Contract No. C-1 08-01
RISK ASSESSMENT
BAHADIR FOR METHOD STATEMENT -INSTALLATION OF PLUMBING PUMPS,
CONTROL PANEL AND ACCESSORIES
CONSTRUCTtON
Initial risk
Residual I
s. Activity Hazard
Controls risk
no. l s RR L s RR
• Induction and training shall be provided to all workers and staffs
• Young workers and persons who have the tendency to take risk shall be identified and supervised
• Accidents and closely.
9 Human behaviour incidents due to
human errors
3 3 9 • All violations related to the Mechanical installation, electrical installation and manipulation I short cut, 2 2 4
electric tools shall be treated seriously and shall be imposed with disciplinary action.
• Horseplay
• Periodic breaks shall be taken to reduce stress and strain on the workers
• All personnel must be aware ofthe project Emergency preparedness and response plan .
• Everyone must know the chain of communication in the event of emergency•
• Emergency contact details shall be displayed at conspicuous area of the site.
• Standby person shall be provided for the emergency shut down of equipment during accidental failure
Execution of and discharges.
10 emergency • Unawareness about
3 3 9 • All emergency equipment must be available and regularly inspected. 2 2 4
the plan
response plan • All personnel must be physically frt: to work on board .
• Trained first aider must be deployed on site for contingencies.
• All search party must be aware of their area of responsibility .
• Regular review of emergency response and_preparedness plan from the main contractor•
Title: Risk Assessment: Method Statement for Installation of Plumbing Pumps Control Panel and Accessories Page(s):6 of 7
Document No.: TAB-BAH-0003-MS-PL.00188 I Rev. 00 Date: 0210512020
Contractor: Client:
Contract No. C-1 08-01
RISK ASSESSMENT
BAHADIR FOR METHOD STATEMENT -INSTALLATION OF PLUMBING PUMPS,
CONTROL PANEL AND ACCESSORIES
CONSTRUCTION
CLASSIFICAnoN OF CHART
Likelihood of Risk
likelihood Description Rating
Unlikely Occurrence close to zero 1 Classification
May Happen Capable of taking Place 2
Likely Tend or Inclined to Occur 3
1-4 Attention Required- Low Risk
I
5-9 Corrective Measures Required- Medium Risk
Very Likely High Inclination of Occurrence 4 10-16 Corrective Action Required- High Risk
Certain Most Definitely Happen- Not "If but When" 5 20-25 Elimination of Hazard - Serious Risk
Severitv of Risk
Severity Description Rating likelihood
Minor Injury First-Aid on Site 1 1 2 3 4 I 5
Minor Injury Treatment Off Site 2 1 1 2 3 4 I 5
Up-to-3 days Injury Limited or no work for three days 3 2 2 4 6 8 I 10
Major Injury Reportable 4 Severity I 3 3 6 9 ll I 15
Death ----- - -
5 '
I 4 4 8 12 ..:r. . ~
5 s 10 lS _, ....... ~
Title: Risk Assessment: Method Statement for Installation of Plumbing Pumps Control Panel and Accessories Page(s):7 of 7
Document No.: TAB-BAH..0003-MS-PL-00188 I Rev. 00 Date: 02/05/2020
BAHADIR
CONSTRUCTION
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERING
METHOD STATEMENT
DOCUMENT TITLE:
METHOD OF.STATEMENT FOR INSTALLATION OF PLUMBING PUMPS (BOOSTER, TRANSFER &
CIRCULATION PUMPS), CONTROL PANEL AND ACCESSORIES