ENGT 3510 - Project Management Class Project

Project Deliverables by Phase & Process Group


Phase 1 Phase 2 Phase 3 Phase 4 Phase 5
Process
Groups

Initiating --> Planning --> Executing --> 'Ph.4 - Monitoring &


-->Controlling'!A1
Closing

Project Charter Scope Management Plan Work Progress Logs Change Log Procurement Log
Stakeholder Register Work Breakdown Structure Team Member Status Report Project Performance Log Contract Closeout Report
Schedule Management Plan Change Request Status Risk Audit Log Project Closeout Report
Critical Path Network Diagram Quality Audit Contractor Status Log Lessons Learned
Gantt Chart Issue Log Cost Variance Report Jing / Screencast.com
Deliverables

Cost Management Plan Earned Value Status Report Wrap-up Video


Activity Cost Estimates
Quality Management Plan
Resource Management Plan
Communications Management Plan
Risk Management Plan
Procurement Management Plan
Stakeholder Management Plan
Change Management Plan

Document Importance
This document is used for all Class Project activities. Microsoft Project is also used to create specific figures and tables for insertion into this
document. All Classroom and 100% Online Students will use this template to complete their Project Management Class Project.

References
Gido, J., Clements, J., & Baker, R. (2018). Successful Project Management (7th Ed.). Boston, MA: Cengage Learning.
Synder, C.S. (2013). A Project Manager's Book of Forms (2nd Ed.). Wiley: Hoboken, NJ: Wiley.

542272158.xlsx 1 of
All dialogue in this
column (on the right
side of the black bar) is
to help you complete
the project for each
Phase 1-5 worksheet.

You will use this file all


semester long. Adding
information for each
Phase and Process
Group.
Supplemental videos
are available in BB for
Microsoft Project and
other Class Project
particulars.

You will also turn in this


file, with each phase's
entered data, when
each phase is due per
the Course Schedule.

542272158.xlsx 2 of
ENGT 3510 Project Management for ENGT

Project Deliverables by Phase & Process Group


Phase 1 Phase 2 Phase 3 Phase 4 Phase 5

Monitoring &
Initiating --> Planning --> Executing --> Controlling --> Closing

Project Charter
Stakeholder Register

PROJECT CHARTER
Recyclematic
Project Title:

Project Sponsor: Dr. Jeff Ulmer Date Prepared: 2/22/2018

Project Manager: Montellia Gant Project Customer: School of Technology

Date Prepared: Sunday, September 05, 2021

Project Purpose or Justification


Due to the increasing problem with climate change, we have to progress in our journey to change the future of our world.

Project Description

542272158.xlsx 3 of
ENGT 3510 Project Management for ENGT

For this project I will design a machine to recycle objects in a more fashionable way that will entice the new generations to
recycle.

542272158.xlsx 4 of
ENGT 3510 Project Management for ENGT

Project Scope
This machine is priceless because of the value it brings to us as a living species.

Project Stakeholders
John, Jacob, Jinglehiemerschmitt.

Projected Budget (Total Cost)


$100k

Project Timespan & Summary Milestones

Project Initiation Date: 9/5/2021


Phase 1 - Initiating Date Due: 9/10/2021
Phase 2 - Planning Date Due: 10/8/2021
Phase 3 - Executing Date Due: 10/22/2021
Phase 4 - Monitoring & Controlling Date Due: 11/5/2021
Phase 5 - Closing Date Due: 11/19/2021

Approvals

Project Manager: Montellia Gant Project Sponsor: Dr. Jeff Ulmer

Date Accepted: 9/5/2021 Date Approved: 2/22/2018

542272158.xlsx 5 of
ENGT 3510 Project Management for ENGT

542272158.xlsx 6 of
ENGT 3510 Project Management for ENGT

STAKEHOLDER REGISTER

Date Prepared: 9/5/2021

Stakeholder (Employee) Position Requirements & Project Role Expectation

John financial advisory ensure the project stay within/under budget.

Jacob Public relations sells our product image to consumers

Jinglehiemershmitt graphic designer ensures an eyecatching product

542272158.xlsx 7 of
ENGT 3510 Project Management for ENGT

Instructions

The Project Management Class Project was constructed for you to


utilize the tools of Project Management. Use this Excel File for all
of your project work. Update it as you work through the class.

You are allowed to use a topic from your major and estimate the
requirements for each deliverable's values in each "YELLOW" box.

A potential major-specific project could be: industrial process


improvement, electronic device development, setting up a
computer network, or creating and implement a company's Quality
Management System.

Type in your project idea's title (pick only one; you will
have it all semester long). Therefore, pick wisely.

Type in your name for Project Manager.

Type in the date that you prepared this.

The reason the project is being chosen. May refer to a


business case, a contract agreement, or any reason.

542272158.xlsx 8 of
ENGT 3510 Project Management for ENGT

Briefly describe your project.

542272158.xlsx 9 of
ENGT 3510 Project Management for ENGT

Scope defines the project - using metrics. Example: "The


kitchen remodeling will increase the value of the house
by $10,000; with only a $3,500 investment."

Stakeholders are people who have an interest and an


influence on the project's success (list 3-4+ team
member's first names (9 max.); plus yourself).

List the total estimated project cost (a ballpark value is


okay)

Look at the Course Schedule. Type in the assigned date


for "Project Initiation Date". Then type in when each
phase is due (also per the Course Schedule).

Type in your name and the date you filled out the
"Project Charter".

542272158.xlsx 10 of
ENGT 3510 Project Management for ENGT

Type in the date that you prepared this.

Type in each fictional team members' first name, their


position in the project, their performance requirements
and expectations.

Note: Stakeholders can be anyone who has contact with


the project. For the sake of this project, we will list your
employees as "Stakeholders".

542272158.xlsx 11 of
ENGT 3510 Project Management for ENGT

Project Deliverables by Phase & Process Group


Phase 1 Phase 2 Phase 3 Phase 4 Phase 5

Monitoring &
Initiating --> Planning --> Executing --> Controlling --> Closing

Scope Management Plan


Work Breakdown Structure
Schedule Management Plan
Critical Path Network Diagram
Gantt Chart
Cost Management Plan
Activity Cost Estimates
Quality Management Plan
Resource Management Plan
Communications Management Plan
Risk Management Plan
Procurement Management Plan
Stakeholder Management Plan
Change Management Plan

SCOPE MANAGEMENT PLAN

Date Prepared:

Project Scope

542272158.xlsx 12 of
ENGT 3510 Project Management for ENGT

Work Breakdown Structure

Copy & paste WBS into this box from Microsoft Project.

SCHEDULE MANAGEMENT PLAN

542272158.xlsx 13 of
ENGT 3510 Project Management for ENGT

Date Prepared:

Schedule Methodology
Critical Path Network using Microsoft Project. Gantt Chart.

Schedule (Critical Path Network Diagram)

Copy & paste your Critical Path Network Diagram


into this box from Microsoft Project.

Schedule (Gantt Chart)

542272158.xlsx 14 of
ENGT 3510 Project Management for ENGT

Copy & paste your Gantt Chart


into this box from Microsoft Project.

COST MANAGEMENT PLAN

Date Prepared:

Cost Determination & Control


Activity Cost Estimates will be used to guide the project. Final cost variances will be controlled appropriately.

Activity Cost Estimates


WBS ID Resource Direct Cost Indirect Cost Buffer Total Cost
$ -

542272158.xlsx 15 of
ENGT 3510 Project Management for ENGT

$ -
$ -
$ -
$ -
$ -
$ -
$ -
$ -
$ -
$ -
$ -
$ -
$ -
$ -

QUALITY MANAGEMENT PLAN

Date Prepared:

Quality Plan

542272158.xlsx 16 of
ENGT 3510 Project Management for ENGT

RESOURCE MANAGEMENT PLAN

Date Prepared:

Team Member, Responsibility, and Authority for Resources


Team Member Responsibility Level of Authority for Resource

COMMUNICATIONS MANAGEMENT PLAN

Date Prepared:

542272158.xlsx 17 of
ENGT 3510 Project Management for ENGT

Communication Methods
Stakeholder Information Method Timing or Frequency Sender

RISK MANAGEMENT PLAN

Date Prepared:

Risk Management Areas & Contingency Plans


Risk Responsibility Risk Prevention Plan Budget Considerations

542272158.xlsx 18 of
ENGT 3510 Project Management for ENGT

PROCUREMENT MANAGEMENT PLAN

Date Prepared:

Procurement Method

Contracts

Performance Metrics

542272158.xlsx 19 of
ENGT 3510 Project Management for ENGT

STAKEHOLDER MANAGEMENT PLAN

Date Prepared:
Add these grading levels below:
C = Current Level of Engagement
D = Desired Level of Engagement
Stakeholder Project Status
Stakeholder (Employee) Unaware Resistant Neutral Supportive Leading

Stakeholder Training Needs


Stakeholder (Employee) Training Needs

542272158.xlsx 20 of
ENGT 3510 Project Management for ENGT

CHANGE MANAGEMENT PLAN

Date Prepared:

Change Management Approach

542272158.xlsx 21 of
ENGT 3510 Project Management for ENGT

Instructions &
information is
provided below.

Type in the date that you prepared this.

Scope defines the project - using metrics. Example: "The


kitchen remodeling will increase the value of the house
by $10,000; with only a $3,500 investment."

542272158.xlsx 22 of
ENGT 3510 Project Management for ENGT

Scope defines the project - using metrics. Example: "The


kitchen remodeling will increase the value of the house
by $10,000; with only a $3,500 investment."

The Work Breakdown Structure decomposes a


project into discrete deliverables. Use Microsoft
Project to create this diagram.

Type in the date that you prepared this.

542272158.xlsx 23 of
ENGT 3510 Project Management for ENGT

Type in the date that you prepared this.

Use the Work Breakdown Structure information to


estimate times to complete each task. List early
start, early finish, late start, and late finish values
to identify the critical path.

542272158.xlsx 24 of
ENGT 3510 Project Management for ENGT

Use the information you created in the Critical


Path Network Diagram to create your Gantt Chart.
Essentially, use: Task, Team Member Name, Task
Duration, Predecessors, and Start Date (the date
the project was assigned in the Course Schedule).

Type in the date that you prepared this.

542272158.xlsx 25 of
ENGT 3510 Project Management for ENGT

Using your WBS and Team Member Names,


estimate costs in relation to direct costs, indirect
costs, allow a 15% buffer, and then calculate the
total cost (this will be calculated for you in the
sheet.

Type in the date that you prepared this.

Define how quality will be maintained in this project.

542272158.xlsx 26 of
ENGT 3510 Project Management for ENGT

Type in the date that you prepared this.

List Team Member's Name, Responsibility, and Level of


Authority for Resources (Labor, Materials, Equipment,
Facilities, etc…).

Type in the date that you prepared this.

542272158.xlsx 27 of
ENGT 3510 Project Management for ENGT

Type in the date that you prepared this.

List stakeholder's name, information that may be sent,


method used (phone, email, letter), timing (daily,
weekly, etc…), and who the sender is.

Type in the date that you prepared this.

List project risks. Then list who will be responsible to


manage it, the plan to prevent the risk, and if there are
funds set aside to minimize financial shortfalls.

542272158.xlsx 28 of
ENGT 3510 Project Management for ENGT
List project risks. Then list who will be responsible to
manage it, the plan to prevent the risk, and if there are
funds set aside to minimize financial shortfalls.

Type in the date that you prepared this.

Discuss who, and how they, will manage project


procurement for materials, tools, and facilities if
needed.

Discuss the types of contracts that may be written (such


as: lease, buy, rent, etc…). Consider how change
requests may affect procurement activities.

Document metrics that will be used to assess vendor


performance to each contract (example: cost, schedule,
and quality metrics).

542272158.xlsx 29 of
ENGT 3510 Project Management for ENGT

Document metrics that will be used to assess vendor


performance to each contract (example: cost, schedule,
and quality metrics).

Type in the date that you prepared this.

Type in each Stakeholder's (Employee) first name. Then


Add "C" or "D" in relation to the Stakeholder's position
the project.

542272158.xlsx 30 of
ENGT 3510 Project Management for ENGT

Type in each Stakeholder's (Employee) first name. Then


add perceived training needed to help each Stakeholder
to succeed on the project.

Type in the date that you prepared this.

Define how project changes will be handled within the


project.

542272158.xlsx 31 of
ENGT 3510 Project Management for ENGT

Project Deliverables by Phase & Process Group


Phase 1 Phase 2 Phase 3 Phase 4 Phase 5

Monitoring &
Initiating --> Planning --> Executing --> Controlling --> Closing

Work Progress Logs


Team Member Status Report
Change Request Status
Quality Audit
Issue Log

WORK PROGRESS LOGS

Project Title:

Date Prepared:

TEAM MEMBER STATUS REPORT

Date Prepared:

Team Member Accomplishments or Potential Issues

542272158.xlsx 32 of
ENGT 3510 Project Management for ENGT

CHANGE REQUEST STATUS

Date Prepared:

Change Responsibility Impact on Project Budget Considerations

542272158.xlsx 33 of
ENGT 3510 Project Management for ENGT

QUALITY AUDIT

Date Prepared:

Quality Issue Responsibility Impact on Project Budget Considerations

542272158.xlsx 34 of
ENGT 3510 Project Management for ENGT

ISSUE LOG

Date Prepared:

Issue Responsibility Impact on Project Objectives Budget Considerations

542272158.xlsx 35 of
ENGT 3510 Project Management for ENGT

Instructions &
information is
provided below.

Type in the Project Title and date that you began on this
Phase.

Type in the date that you prepared this.

542272158.xlsx 36 of
ENGT 3510 Project Management for ENGT

Comment on each Team Member's accomplishments


and potential issues that may affect the successful
completion of the project.

Type in the date that you prepared this.

List potential change requests. Then list who will be


responsible to manage it, how it may affect the project,
and how it may affect the project budget.

542272158.xlsx 37 of
ENGT 3510 Project Management for ENGT
List potential change requests. Then list who will be
responsible to manage it, how it may affect the project,
and how it may affect the project budget.

Type in the date that you prepared this.

List potential quality issues. Then list who will be


responsible to manage it, how it may affect the project,
and how it may affect the project budget. Will it affect
the customer?

542272158.xlsx 38 of
ENGT 3510 Project Management for ENGT

Type in the date that you prepared this.

List other potential project issues. Then list who will be


responsible to manage it, how it may affect project
objectives, and how it may affect the project budget.

542272158.xlsx 39 of
ENGT 3510 Project Management for ENGT

Project Deliverables by Phase & Process Group


Phase 1 Phase 2 Phase 3 Phase 4 Phase 5

Initiating --> Planning --> Executing -->


Monitoring & --> Closing
Controlling

Change Log
Project Performance Log
Risk Audit Log
Contractor Status Log
Cost Variance Report
Earned Value Status Report

CHANGE LOG

Date Prepared:

Previous Phase 3 Change Responsibility Final Impact on Project

542272158.xlsx 40 of
ENGT 3510 Project Management for ENGT

PROJECT PERFORMANCE LOG

Date Prepared:

Accomplishments for this Reporting Period

Accomplishments Planned but Not Completed this Reporting Period

Root Cause of Variances

542272158.xlsx 41 of
ENGT 3510 Project Management for ENGT

RISK AUDIT LOG

Date Prepared:

Risk Management Areas & Contingency Plans


Risk Responsibility Identified Risk Effects (positive or negative)

542272158.xlsx 42 of
ENGT 3510 Project Management for ENGT

CONTRACTOR STATUS LOG

Date Prepared:

Contractor Issue Impact on Project

542272158.xlsx 43 of
ENGT 3510 Project Management for ENGT

COST VARIANCE REPORT

Date Prepared:

Cost Variance Issues

EARNED VALUE STATUS REPORT

Date Prepared:

Earned Value Status

Cost Variance (CV)


Activity or Work Result Planned Value (PV) Earned Value (EV) Actual Cost (AC) CV = EV - AC
(calculated below)

$ -
$ -
$ -
$ -
$ -
$ -

542272158.xlsx 44 of
ENGT 3510 Project Management for ENGT

$ -
$ -
$ -
$ -
$ -
$ -
$ -
$ -
$ -

542272158.xlsx 45 of
ENGT 3510 Project Management for ENGT

Instructions &
information is
provided below.

Type in the date that you prepared this.

Look back over what you did in Phase 3. List how some
changes were successful and potentially how they were
not.

542272158.xlsx 46 of
ENGT 3510 Project Management for ENGT

Type in the date that you prepared this.

Summarize what was done on your project to this point.

Think about what was planned, but was not


accomplished due to some unforseen circumstances.
List two possible planned actions.

542272158.xlsx 47 of
ENGT 3510 Project Management for ENGT

List why the two planned actions were not


accomplished.

Type in the date that you prepared this.

Look back to what you listed in Phase 2 for the Risk


Management Log. Relist items from Phase 2. Discuss
briefly how your Risk Management Plan was effective,
or not effective, for each item.

542272158.xlsx 48 of
ENGT 3510 Project Management for ENGT

Type in the date that you prepared this.

Consider the contractor used for your project. List any


positive or negative issues that have impacted your
project.

542272158.xlsx 49 of
ENGT 3510 Project Management for ENGT

Type in the date that you prepared this.

Using your WBS, and Team Member Names from


Phase 2's Cost Management Plan, discuss the top
2-3 issues that caused variance in cost during the
Execution phase.

Type in the date that you prepared this.

All project objectives (work performed with a


result: design work, wall, counter top, etc.) have an
actual earned value. Using your Cost Management
Plan information from Phase 2, provide an
estimate of values on the chart.
542272158.xlsx Round up to the nearest whole dollar (no cents) 50 of
ENGT 3510 Project Management for ENGT

All project objectives (work performed with a


result: design work, wall, counter top, etc.) have an
actual earned value. Using your Cost Management
Plan information from Phase 2, provide an
estimate of values on the chart.

Round up to the nearest whole dollar (no cents)

542272158.xlsx 51 of
ENGT 3510 Project Management for ENGT

Project Deliverables by Phase & Process Group


Phase 1 Phase 2 Phase 3 Phase 4 Phase 5
Monitoring &
Initiating --> Planning --> Executing --> Controlling --> Closing

Procurement Log
Contract Closeout Report
Project Closeout Report
Lessons Learned
Jing / Screencast.com
Wrap-up Video

PROCUREMENT LOG

Date Prepared:

What Worked Well (Scope, Quality, Schedule, Cost, Other)

What Could Have Worked Better (Scope, Quality, Schedule, Cost, Other)

542272158.xlsx 52 of
ENGT 3510 Project Management for ENGT

List What Can be Used in your Next Project

CONTRACT CLOSEOUT REPORT

Date Prepared:

List Contract Disputes and Resolutions

PROJECT CLOSEOUT REPORT

Date Prepared:

Objectives Completion Criteria How Met

542272158.xlsx 53 of
ENGT 3510 Project Management for ENGT

Scope

Quality

Time

Cost

LESSONS LEARNED

Date Prepared:

Lessons Learned

542272158.xlsx 54 of
ENGT 3510 Project Management for ENGT

JING / SCREENCAST.COM WRAP-UP VIDEO

Date Prepared:

Summarized Video & Excel File Instructions


1. Using this Excel file, create (1) Jing video (5 minutes max.) that discusses each Phase of your project. Only (1) video
is to be created (all 5 phases are discussed in this (1) video).
2. Upload the Jing Video up to your Screencast.com account.
3. Post your Class Project Excel file into Blackboard.
4. Post the Screencast.com hyperlink (URL) of your video into Blackboard.

Detailed Video, Class Project Excel File, & Jing / Screencast.com Set-up Instructions
1. Go to this hyperlink and set up our own 2GB Free Version account for streaming videos.
https://www.techsmith.com/screencastcom.html
2. Load Jing on your computer (PC or MAC; it works for both). It is located at:
https://www.techsmith.com/jing-tool.html
3.Use the Jing and Screencast.com tutorials on the website to help you learn how to use these tools. In fact, Jing provides
you with a quick tutorial after loading it. Go to the following hyperlink for those other videos. Otherwise, you will be
lost in how to create, upload, and share the videos.
https://www.techsmith.com/tutorial-jing.html
4. Using your Class Project Excel File, Jing, and your microphone, create a video capture session highlighting your project
phases. To do this, draw your screen capture box around the main dialogue section of your Class Project Excel File
(don't capture the instructions or the header commands), then create your video.
5. Watch and listen to your video. Does it have voice commentary? Is it clear? If not, record again.

542272158.xlsx 55 of
ENGT 3510 Project Management for ENGT

6. Upload your completed video to Screencast.com; copy the URL for loading back into Blackboard.
7. Post your completed Class Project Excel File into Blackboard.
8. Add your Video URL into Blackboard as well.
9. Your done! Good job!

542272158.xlsx 56 of
ENGT 3510 Project Management for ENGT

Instructions &
information is
provided below.

Type in the date that you prepared this.

Consider and list 2-3 things that might have worked well
in your project.

Consider and list 2-3 things that could have worked


better in your project.

542272158.xlsx 57 of
ENGT 3510 Project Management for ENGT

Consider and list 2-3 things that could have worked


better in your project.

Consider and list 2-3 things that should be used in your


next project.

Type in the date that you prepared this.

Consider and list 2-3 vendors, and contract issues, that


could have occurred in your project.

Type in the date that you prepared this.

542272158.xlsx 58 of
ENGT 3510 Project Management for ENGT

List the Major Project Objective, Completion Criteria,


and How it was Met, for Scope, Quality, Time, and Cost.
Only (1) issue for each Excel cell is needed.

Type in the date that you prepared this.

Consider and list 2-3 lessons you have learned when


completing your fictitious project.

542272158.xlsx 59 of
ENGT 3510 Project Management for ENGT

Type in the date that you prepared this.

Follow these instructions. If you have any questions,


email your professor.

542272158.xlsx 60 of
ENGT 3510 Project Management for ENGT

542272158.xlsx 61 of