PROJECT SCHEDULE

ID Task Duration Start Finish October January April July October January April July October January
M E B M E B M E B M E B M E B M E B M E
1 Project - VCX 400 997 days? Thu 28/02/19 Fri 23/12/22
2 Land Clearance & Site Preparation 206 days? Fri 01/01/21 Fri 15/10/21
9 Thai Can Lake (Phase 1-14ha) 42 days? Fri 01/01/21 Mon 01/03/21
5 Effluent Treatment Plant 67 days? Fri 01/01/21 Mon 05/04/21
7 110kV line 51 days? Tue 26/01/21 Tue 06/04/21
8 Main Road from Vo Van Kiet Road to Pulp 91 days? Tue 26/01/21 Tue 01/06/21
6 paper Mill
Waste Water Discharged Pipeline 153 days? Mon 01/02/21 Wed 01/09/21
3 Effluent Treatment Plant 185 days? Mon 01/02/21 Fri 15/10/21
4 Raw water pipeline from Thai Can lake to WTP 206 days? Fri 01/01/21 Fri 15/10/21
60 (including
Overhauling Pump house) 300 days Tue 01/12/20 Mon 24/01/22
61 Mechanical 300 days Tue 01/12/20 Mon 24/01/22
62 Electrical 300 days Tue 01/12/20 Mon 24/01/22
63 Instrumentation 300 days Tue 01/12/20 Mon 24/01/22
27 Construction 369 days? Tue 01/12/20 Sun 01/05/22
42 Pulp Drying Machine 1 110 days Tue 01/12/20 Sat 01/05/21
43 Pulp Drying Machine 2 110 days Tue 01/12/20 Sat 01/05/21
44 Pulp Drying Machine 3 110 days Tue 01/12/20 Sat 01/05/21
45 Evaporation 110 days Tue 01/12/20 Sat 01/05/21
46 Recovery Boiler 110 days Tue 01/12/20 Sat 01/05/21
48 Power Boiler 110 days Tue 01/12/20 Sat 01/05/21
55 Fuel Oil 110 days Tue 01/12/20 Sat 01/05/21
28 Chip receiving and conveying 131 days? Tue 01/12/20 Tue 01/06/21
29 Chips screening and conveying 131 days? Tue 01/12/20 Tue 01/06/21
30 Continuous Cooking Process and Brown Stock 67 days? Mon 01/03/21 Tue 01/06/21
31 Washing Dioxide
Chlorine and Screening Process
Production Plant 131 days? Tue 01/12/20 Tue 01/06/21
32 Oxygen Delignification 67 days? Mon 01/03/21 Tue 01/06/21
33 Bleaching 131 days Tue 01/12/20 Tue 01/06/21
40 Oxygen Plant 131 days Tue 01/12/20 Tue 01/06/21
51 Causticising and Lime Kiln 131 days Tue 01/12/20 Tue 01/06/21
47 Turbines (TG1 and TG2), Feed Water, 88 days Thu 01/04/21 Sun 01/08/21
57 Condensate Handling
Firing pumping station 50 days? Tue 01/06/21 Mon 09/08/21
58 Fire station 50 days? Tue 01/06/21 Mon 09/08/21
49 Demineralised Water Plant 121 days? Fri 09/04/21 Fri 24/09/21
50 Water Treatment Plant 121 days Fri 09/04/21 Fri 24/09/21
52 Coal handling system 129 days? Fri 09/04/21 Wed 06/10/21
56 Cooling tower 120 days Tue 01/06/21 Mon 15/11/21
34 Internal road 132 days Tue 01/06/21 Wed 01/12/21
35 Internal Storm water drain 132 days Tue 01/06/21 Wed 01/12/21
36 Internal Storm water drain 132 days Tue 01/06/21 Wed 01/12/21

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: 20210420-Project sche Milestone Inactive Summary Start-only Critical

Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 1
PROJECT SCHEDULE
ID Task Duration Start Finish October January April July October January April July October January
M E B M E B M E B M E B M E B M E B M E
37 Entry main road 132 days Tue 01/06/21 Wed 01/12/21
38 Raw water pumping station and pipe line 132 days Tue 01/06/21 Wed 01/12/21
54 SO2 Handling 132 days Tue 01/06/21 Wed 01/12/21
41 Chip receiving and conveying 67 days? Wed 20/10/21 Thu 20/01/22
53 Effluent Treatment Plant 262 days Mon 01/03/21 Tue 01/03/22
59 VAM Machine 65 days? Wed 01/12/21 Tue 01/03/22
39 Main gate and security house 109 days Wed 01/12/21 Sun 01/05/22
10 Engineering and Procurement 365 days Wed 06/01/21 Tue 31/05/22
16 Bleaching 65 days Tue 26/01/21 Mon 26/04/21
22 Coal handling system 151 days Mon 08/02/21 Mon 06/09/21
26 VAM Machine 129 days Thu 25/03/21 Tue 21/09/21
23 Raw water pumping station and pipe line 151 days Fri 30/04/21 Fri 26/11/21
18 Evaporation 131 days Tue 01/06/21 Tue 30/11/21
25 SO2 Handling 129 days Fri 11/06/21 Wed 08/12/21
21 Recausticizing and lime kiln 173 days Mon 17/05/21 Wed 12/01/22
12 Chip storage 109 days Wed 25/08/21 Sat 22/01/22
13 Chip screening 109 days Wed 25/08/21 Sat 22/01/22
24 Effluent treatment plan 237 days Tue 02/03/21 Wed 26/01/22
11 Mill wide 130 days Sat 07/08/21 Thu 03/02/22
19 Recovery Boiler 300 days Wed 06/01/21 Tue 01/03/22
17 Pulp Drying Machine 268 days Fri 19/03/21 Tue 29/03/22
20 Turbines (TG1 and TG2), Feed Water, Condensate 268Handling
days Fri 19/03/21 Tue 29/03/22
15 ClO2 plant 166 days Mon 16/08/21 Sun 03/04/22
14 Cooking, washing and screening 258 days Sat 05/06/21 Tue 31/05/22
101 Erection 925 days Thu 28/02/19 Wed 14/09/22
128 Cooling tower 180 days Mon 01/06/20 Fri 05/02/21
111 110kV Station 120 days Wed 25/08/21 Wed 09/02/22
112 DCS system 60 days Mon 13/12/21 Mon 07/03/22
119 HVAC System 90 days Mon 01/11/21 Mon 07/03/22
131 Compressor plant 70 days Mon 20/12/21 Mon 28/03/22
113 Coal Handling System 180 days Mon 26/07/21 Mon 04/04/22
118 Water Drawal System (pump staition) 60 days Mon 10/01/22 Mon 04/04/22
108 ClO2 plant 350 days Tue 01/12/20 Mon 04/04/22
114 Chips storage 200 days Mon 02/08/21 Mon 09/05/22
130 Chips screening and conveying 350 days Mon 04/01/21 Mon 09/05/22 09/05
132 Dicharge pipe of treated effluent to sea (about 300 days Mon 15/03/21 Mon 09/05/22
133 7km)
Oxygen plant 120 days Mon 22/11/21 Mon 09/05/22
115 Effluent Treatment Plant 180 days Wed 01/09/21 Tue 10/05/22
126 Recausticizing and lime kiln 367 days Thu 07/01/21 Fri 03/06/22

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: 20210420-Project sche Milestone Inactive Summary Start-only Critical

Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 2
PROJECT SCHEDULE
ID Task Duration Start Finish October January April July October January April July October January
M E B M E B M E B M E B M E B M E B M E
123 bailing line 90 days Mon 31/01/22 Mon 06/06/22
105 Fuel Oil 180 days Fri 01/10/21 Fri 10/06/22
116 Demineralised Water Plant 91 days Thu 03/02/22 Fri 10/06/22
117 Raw water treated plant 91 days Thu 03/02/22 Fri 10/06/22
129 Fire Hydrant System and Control 180 days Fri 01/10/21 Fri 10/06/22
120 Pulp Drying Machine 1 400 days Tue 01/12/20 Mon 13/06/22
121 Pulp Drying Machine 2 400 days Tue 01/12/20 Mon 13/06/22
110 VAM Machine 90 days Fri 25/02/22 Fri 01/07/22
102 Cooking, washing and screening 428 days Tue 01/12/20 Thu 21/07/22
103 Oxygen Delignification 428 days Tue 01/12/20 Thu 21/07/22
104 Evaporation 886 days Thu 28/02/19 Thu 21/07/22
106 Recovery Boiler 886 days Thu 28/02/19 Thu 21/07/22
109 Bleaching 886 days Thu 28/02/19 Thu 21/07/22
107 SO2 Handling 120 days Fri 04/02/22 Fri 22/07/22
124 Turbines (TG1 and TG2), Feed Water, Condensate 300Handling
days Fri 28/05/21 Fri 22/07/22
136 Balance of Plant 250 days Fri 20/08/21 Fri 05/08/22
122 Pulp Drying Machine 3 300 days Fri 18/06/21 Fri 12/08/22
125 Power Boiler 300 days Fri 18/06/21 Fri 12/08/22
127 Ash handling 180 days Fri 03/12/21 Fri 12/08/22
134 ISBL Piping Fabrication & Erection in all areas 466 days Wed 02/12/20 Wed 14/09/22
135 OSBL Pipe Rack and Piping 200 days Thu 09/12/21 Wed 14/09/22
64 Commissioning 997 days Thu 28/02/19 Fri 23/12/22
94 Cooling tower 10 days Thu 28/02/19 Wed 13/03/19
95 HVAC System 10 days Mon 07/03/22 Fri 18/03/22
65 110kV line and station 38 days Wed 09/02/22 Fri 01/04/22
93 Compressor plant 20 days Mon 28/03/22 Fri 22/04/22
98 Raw water pumping station and pipe line 20 days Mon 04/04/22 Fri 29/04/22
99 DCS system 45 days Mon 07/03/22 Fri 06/05/22
85 Coal handling system 40 days Mon 04/04/22 Fri 27/05/22
66 Effluent treated discharge pipeline 30 days Mon 09/05/22 Fri 17/06/22
67 Chips storage 30 days Mon 09/05/22 Fri 17/06/22
73 Chips screening and conveying 30 days Mon 09/05/22 Fri 17/06/22
77 Oxygen plant 30 days Mon 09/05/22 Fri 17/06/22
88 Recausticizing and lime kiln 30 days Mon 09/05/22 Fri 17/06/22
92 Raw water treated plant 20 days Fri 10/06/22 Thu 07/07/22
90 Effluent treated plant 60 days Tue 19/04/22 Mon 11/07/22
87 Fuel Oil 25 days Fri 10/06/22 Thu 14/07/22
97 Fire station 25 days Fri 10/06/22 Thu 14/07/22
89 CPU plant 30 days Fri 10/06/22 Thu 21/07/22

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: 20210420-Project sche Milestone Inactive Summary Start-only Critical

Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 3
PROJECT SCHEDULE
ID Task Duration Start Finish October January April July October January April July October January
M E B M E B M E B M E B M E B M E B M E
91 Demineralised Water Plant 30 days Fri 10/06/22 Thu 21/07/22
82 Boiler feed water system 30 days Wed 13/07/22 Tue 23/08/22
96 Pulp Drying Machine 3 10 days Fri 12/08/22 Thu 25/08/22
84 Baling line 65 days Mon 06/06/22 Fri 02/09/22
80 So2 Handling 45 days Fri 22/07/22 Thu 22/09/22
83 Turbines (TG1) 45 days Fri 22/07/22 Thu 22/09/22
86 Power Boiler 30 days Fri 12/08/22 Thu 22/09/22
70 Ash handling 45 days Fri 12/08/22 Thu 13/10/22
76 ClO2 plant 60 days Fri 12/08/22 Thu 03/11/22
71 Cooking, washing and screening 45 days Fri 23/09/22 Thu 24/11/22
78 Bleaching 45 days Fri 23/09/22 Thu 24/11/22
69 VAM Machine 60 days Fri 23/09/22 Thu 15/12/22
72 Oxygen delignification 60 days Fri 23/09/22 Thu 15/12/22
74 Turbine 2 45 days Fri 14/10/22 Thu 15/12/22
79 Evaporation 60 days Fri 23/09/22 Thu 15/12/22
81 Recovery Boiler 60 days Fri 23/09/22 Thu 15/12/22
75 Pulp Drying Machine 1 50 days Fri 14/10/22 Thu 22/12/22
100 Pulp Drying Machine 2 50 days Fri 14/10/22 Thu 22/12/22
68 First On-spec product 1 day Fri 23/12/22 Fri 23/12/22

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: 20210420-Project sche Milestone Inactive Summary Start-only Critical

Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 4