Plan For Co-Firing Test: Complete Activity of 100 Hrs. Incorporating Both GE and EPQL Timelines
Plan For Co-Firing Test: Complete Activity of 100 Hrs. Incorporating Both GE and EPQL Timelines
August September
13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
www.engro.com 1
Timeline
Time
GE Parallel Activities
(hrs.)
Fuel change-over
Test Run at part load at Unit Shutdown 1
Test
GT Shutdown 2 Back up as running code & as running
constant.
Cooling time / Turning Gear for handover for BI 16 Compare modified code & as running
1st BI 14 Pressure transmitters calibration /
1st BI
8 verification.
GT Zero Speed / Software download / upload
(in parallel) Downloading updated m6b file.
Turning Gear 4
GT Start-up 1
Ramp machine to 70% load 4 Deploy trends and forcing as per test plan.
Conduct Co-Firing & Mix fuel operation as
Test Points Run
Cofiring test points operation 10 per test plan.
Collect & upload test trends for review.
Shutdown 2
Cooling time / Turning Gear for handover for BI 16
Revert to pre test software, download
2nd BI 14
2nd BI backed up code to the Mark VI panel
TG / Offline water wash 12
Turning Gear 4
GT Start-up 1