Professional Documents
Culture Documents
619 HVDC Connection of Offshore Wind Power Plants (2015)
619 HVDC Connection of Offshore Wind Power Plants (2015)
619 HVDC Connection of Offshore Wind Power Plants (2015)
Working Group
B4.55
May 2015
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
WG Members:
Main Authors:
Hjerrild (DK),
Guixot (ES)
Contributing WG Members:
(UK),
Weyrich (DE),
Copyright © 2015
“Ownership of a CIGRE publication, whether in paper form or on electronic support only infers right
of use for personal purposes. Unless explicitly agreed by CIGRE in writing, total or partial
reproduction of the publication and/or transfer to a third party is prohibited other than for personal
use by CIGRE Individual Members or for use within CIGRE Collective Member organisations.
Circulation on any intranet or other company network is forbidden for all persons. As an exception,
CIGRE Collective Members only are allowed to reproduce the publication.
Disclaimer notice
“CIGRE gives no warranty or assurance about the contents of this publication, nor does it accept any
responsibility, as to the accuracy or exhaustiveness of the information. All implied warranties and
conditions are excluded to the maximum extent permitted by law”.
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
TABLE OF CONTENTS
GLOSSARY OF ABBREVIATIONS AND SPECIAL TERMS ............................................................... I
EXECUTIVE SUMMARY ..................................................................................................................... III
1 INTRODUCTION ............................................................................................................................ 1
1.1 Background .........................................................................................................................1
1.2 Technical Brochure (TB) Scope ..........................................................................................2
2 VSC-HVDC CONFIGURATIONS................................................................................................... 4
2.1 Introduction .........................................................................................................................4
2.2 Background .........................................................................................................................4
2.3 General VSC-HVDC Design Considerations ......................................................................5
2.4 VSC HVDC Configurations .................................................................................................8
2.4.1 Point-to-Point Connection ...........................................................................................8
2.4.2 Multi-Infeed Connection ..............................................................................................8
2.4.3 Emerging Configurations - Multi-Terminal VSC-HVDC ..............................................9
2.4.4 Future Configurations - VSC-HVDC Grid .................................................................10
2.5 Basic Offshore WPP Configuration ...................................................................................11
2.6 Basic Configuration of Point-to-Point VSC HVDC for Offshore WPP ...............................13
2.7 Balance of the Plant ..........................................................................................................13
2.8 References ........................................................................................................................14
3 HVDC CONNECETD OFFSHORE WPPS: WTG SELECTION AND CONCEPTUAL DESIGN
LAYOUTS .................................................................................................................................... 15
3.1 Introduction .......................................................................................................................15
3.2 Unique Aspects of WTGs for Offshore Applications .........................................................15
3.2.1 Factors affecting availability of Offshore WTGs .......................................................16
3.2.2 Offshore WTG Design Targets .................................................................................16
3.3 WTG Technologies ...........................................................................................................17
3.3.1 Type 3: Doubly-fed Induction Generator ..................................................................17
3.3.2 Type 4 Full Scale Converter Connections ................................................................17
3.3.3 Foundations of Offshore WTG’s ...............................................................................18
3.3.4 Future Trends in Offshore WTG Technology ...........................................................20
3.4 Connection Between VSC HVDC Converter Station and WPP Collector Substations .....20
3.5 WPP Collector Station Transformers ................................................................................22
3.6 Design of the WPP Internal Cable Collector Network .......................................................23
3.6.1 Cable Technology .....................................................................................................23
3.6.2 Substation Placement ...............................................................................................23
3.6.3 Cable Routing and Cable Sizing ...............................................................................24
3.6.4 Emergency Stand-by Power .....................................................................................26
3.7 Design of the WPP HVDC Export Cable Connection .......................................................26
3.8 Bibliography .....................................................................................................................27
4 FUNCTIONAL REQUIREMENTS FOR HVDC AND OFFSHORE WIND POWER PLANT........ 29
4.1 Introduction .......................................................................................................................29
4.2 System Under Analysis .....................................................................................................29
4.3 Control and Protection Functions Required ......................................................................30
4.3.1 Functions required ....................................................................................................30
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
AC Alternating Current
AGC Automatic Generation Control
AIS Air Insulated Substation
AVC Automatic Voltage Control
BOP Balance of Plant
CAPEX Capital Expenditure
CMS Condition Monitoring Systems
DC Direct Current
DECC Department of Energy and Climate Change
DFIG Doubly-Fed Induction Generator
EMF ElectroMagnetic Field
EMT ElectroMagnetic Transient
ENTSO-E European Network of Transmission System Operators
for Electricity
EU European Union
FRT Fault-Ride-Through
FSC Full Scale Converter
GC Grid Codes
GCP Grid Connection Point
GIS Gas-Insulated Switchgear
HVAC High Voltage AC
HVDC High Voltage DC
IGBT Insulated Gate Bipolar Transistor
IP Intellectual Property
LCOE Levelised Cost of Energy
LCC Line Commutated Converter
Page i
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
MI Mass Impregnated
MMC Modular Multilevel Converter
MVAC Medium Voltage AC
NGET National Grid Electricity Transmission
O&M Operation and Maintenance
Ofgem Office of Gas and Electricity Markets
OFTO Offshore Transmission Operator
OPEX Operating Expenditures
POI Point of Interconnection
PWM Pulse Width Modulation
R&D Research and Development
RMS Root Mean Square
SPWM Sinusoidal PWM
STATCOM STATic COMpensator
SVC Static Var Compensator
TB Technical Brochure
VSC Voltage Sourced Converter
WG Working Group
WIPOS Wind Power Offshore Substation
WPP Wind Power Plant
WTG WTG Generator
XLPE Crossed-Linked Polyethylene
Page ii
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
EXECUTIVE SUMMARY
The first wave of HVDC connected offshore wind power plants (WPPs) has been commissioned and
many more are planned in the North Sea, along with other sites around the world. VSC-based HVDC
has become the preferred solution for large offshore WPPs, with cable distances typically above 100
km (including both offshore cable and on shore cable to the converter terminal) to the AC grid
connection point.1 This is largely due to several technology advantages offered by VSCs, when
compared to other HVAC or HVDC options, resulting in a more economically attractive transmission
solution.
In addition, a number of HVDC submarine cable connections for power exchange between countries
are being planned and the possibility of connecting WPPs to these interconnections, and to future
HVDC grids, are being seriously considered. The issues associated with expanding a WPP and HVDC
connections with equipment from multiple vendors are subjects which need to be developed further,
but are outside the scope of this brochure.
Compliance with Grid Codes (GCs), which define the performance during normal and abnormal
operating conditions, is another subject area in need of further development. Existing GCs are
however written for AC connected WPPs, and for an offshore WPP these conditions typically apply
only at the AC grid connection point. This raises the possibility of optimizing the overall WPP and the
HVDC converter, with potential economic and maintenance benefits. However, if the HVDC connection
and the WPP are provided by different vendors, such optimization cannot be done properly unless
concerns about IP rights and operation benefits are clearly laid out and understood by all stakeholders
involved.
Guidelines and recommendation for point to point and multi terminal HVDC connection of offshore
WPPs are therefore highly needed and of mutual interest for the HVDC and WTG industries in order to
be able to provide the best possible solutions for all stakeholders.
1
It must be noted that the choice of HVAC vs HVDC transmission requires detailed cost‐benefit analysis
based on individual projects’ needs, based on factors like water depth, sea bed profile, distance from shore,
ac substation connection, and other routing challenges.
Page iii
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
1 INTRODUCTION
1.1 Background
Driven by EU’s 20% renewable energy target by 2020, the first wave of VSC HVDC connected
offshore wind power plants (WPPs) have been commissioned around the world, but with a notable
high concentration to be found in the North Sea. These early WPP projects have been located 130-
200 km from the point of common coupling (PCC), including both offshore and on shore cables to the
converter terminal, thereby making HVDC the most appropriate technology to use for power
transmission to mainland grids, recognizing the limitations in AC submarine transmission at such
distances. In addition, VSC HVDC technology offers several unique advantages suitable for such
environmentally harsh and difficult sitings, with yet greater energy yield potentials. A partial list
includes:
Ability to continuously transfer any power level (zero to maximum rating) in both directions,
thereby facilitating WPP start up, and operation at low wind speeds
Ease of integration with WTG Generators (WTGs) in islanded grids with very low fault current
levels (i.e., no need for synchronous condensers, as would be the case with LCC HVDC
applications)
Normally, no need for harmonic filters and additional reactive power resources1
Improved performance during onshore AC disturbances - Because the VSC converters are self-
commuted, commutation failures will not occur in case of ac grid disturbances
Blackstart capability - ability to supply the auxiliary power needs of the offshore WPP when
WTGs are not operating (e.g., due to low wind, or excessively high wind, conditions)
Feasibility of building compact, partially or fully tested and assembled, converter stations
resulting in lower costs and risks for the off-shore platform
Ability to use XLPE cables since the operating voltage polarity is unchanged and independent
of the direction of the power flow (XLPE cables are not capable of withstanding the voltage
reversal which happens with LCC HVDC applications). It should also be mentioned that MI
cables are still a viable alternative, particularly at higher DC voltages.
The first VSC HVDC connected off-shore WPP project (BorWin1, 400MW, +/- 150 kV, 125km off the
coast of Germany) was commissioned in 2009. Even though a number of similar projects have been
commissioned, or are under various stages of design and construction, it is generally recognized that
this method of transferring energy harvested from offshore WPPs is in its early stages of maturity.
Compared to a large population of WPPs connected to AC grids, VSC HVDC transmission completely
changes the electrical environment, presenting new challenges and opportunities for operation during
1
However, AC filters may be required for converters using PWM‐switching strategies. In order to
compensate AC cables, under no/light load conditions, additional shunt reactors at the offshore converter
stations may be required.
Page 1
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
normal and abnormal conditions. Similarly, most HVDC links have been developed as point-to-point
connections between AC transmission systems. From the electrical point of view, offshore WPPs
constitute weak islanded grids.
At present, the industry is developing standards and commonly accepted grid codes, while gaining
deeper understanding of the integrated WPPs and VSC HVDC systems. Furthermore, there is also
growing knowledge of, and experience with, the design and operation of such projects. So, even
though current projects have to develop their own design and operational philosophies, with deeper
experience, and longer reported operational history, future optimally designed projects are expected.
It should be noted that there exists a number of prior, and on-going, CIGRE WGs tasked with further
understanding and developments of related subject areas; including: “Feasibility of HVDC Grids “(WG
B4.52 TB), “Special Considerations for AC Collector Systems and Substations associated with HVDC
connected Wind Power Plants” (WG B3.36), and “Guidelines for Preparation of Connection
Agreements or Codes for HVDC Grids” (WG B4.56). Finally, WG B4-62 was recently formed to
examine issues with connection of WPPs to weak AC networks, and the use of FACTS devices, and
WTG controls, to facilitate their integration in AC networks.
It is against this background that the WG B4-55 was tasked to identify the key technical challenges
unique to VSC HVDC connection of offshore WPPs and to develop guidelines and recommendations
for more technically robust, and economically attractive, system designs.
Chapter 2 begins with an overview of currently deployed VSC HVDC technologies by leading
manufacturers, and trends towards future control and design architectures. Discussions include unique
aspects of control and protection philosophies, as offshore WPP isolated grids present special
challenges in comparison to those connected to AC grids. Strategies to respond to AC and DC
disturbances are described, as well as preferred methods of protection, communication, and
equipment application. This Chapter also provides an overview of the HVDC VSC building blocks that
will be used throughout this TB. Various schemes and conceptual layouts are presented to describe
current and future HVDC system configurations. Brief discussions on off-shore platform configurations
and balance of plant sub-systems are also included. For a more detailed description of the special
requirements that need to be considered during the design of an offshore AC collector station
connected to an HVDC link, in comparison to a substation that is connected directly to the onshore site
by means of AC export cables, readers are recommended to refer to the TB developed by CIGRE WG
B3-36 “Special Considerations for AC Collector Systems and Substations associated with HVDC
connected Wind Power Plants”.
Chapter 3 focuses on topics related to selection, design, construction, and operation of WTGs and
WPPs, unique to VSC HVDC connected offshore projects. Special requirements for such applications,
including reliability & availability, higher environmental stress due to harsh sea conditions, operation &
maintenance (O&M) costs, foundations, and cables requirements are also discussed. Discussion on
potential emerging technologies and future R&D needs for more cost effective offshore WPP projects
Page 2
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
are presented. Readers are referred to the TB developed by the CIGRE WG B3-36 for more in-depth
discussion on this topic. The latter part of this chapter is dedicated to description of various WPP
conceptual layouts and designs - from individual WTGs up to the offshore HVDC converter. The main
topics discussed are: HVAC Cables, possible WPP cluster arrangements, key elements of WPP
collector grids, main interfaces between WPPs and VSC HVDC converter terminal, control and
protection requirements, offshore AC platform needs, and WPP balance of plant description.
Functional requirements for VSC HVDC connected WPPs are discussed in Chapter 4. This is an
important aspect as different manufacturers are likely to supply the WPP and HVDC converter
equipment. Discussions include key control coordination topics, including: active and reactive power
management, offshore grid frequency, start and stop sequences, fault ride-through capabilities, main
AC grid support, coordination between VSC HVDC and WPP, operation under communication failure,
and offshore auxiliary power needs under low wind conditions. Control coordination under normal and
fault conditions are described and colour coded figures are used to illustrate various scenarios.
Chapter 5 discusses topics related to the interconnection requirements. These are evolving topics as
transmission operators in each country are gaining experience with the first wave of VSC HVDC
connected WPPs and interface connection points are drawn based on different ownership models.
This chapter begins by describing models adopted by Great Britain and Germany. The remainder of
this chapter is devoted to various grid code requirements mandated by the transmission operator to
ensure safe and secure operation of VSC HVDC connected WPP under normal and abnormal
conditions. Key topics covered include: voltage and reactive power, active power and frequency
control, protection and fault ride-through, power quality, communication and information exchange,
model and data provision, and commissioning, compliance testing and operational sequence. This
chapter concludes with specific examples of grid codes adopted in Germany (TenneT), Great Britain
(NGET), and the European Network of Transmission System Operators for Electricity (ENTSO-e).
Chapter 6 describes the various studies required during the design and planning stages to ensure an
optimal design of a VSC HVDC connected offshore WPP, in compliance with control and equipment
specifications, grid codes, and the full range of potential operation conditions. For each study, the
objectives, methodology, data and modelling needs, and the use of study outcomes are described.
Main characteristics of the commissioned, planned, or under construction VSC HVDC connected
offshore WPP projects are presented in Chapter 7. For each project, publicly available information
regarding ratings, WPP cluster design, platform design, HVAC and HVDC cable lengths and types,
and other relevant information are presented in a common format.
The final Chapter in this TB summarises the unique design challenges of integrating offshore WPPs
using VSC-HVDC transmission, including sub-system technology details and design options. From
this, there are a number of overarching functional objectives and design principles which can be
identified. Also, there are a number of areas where there are multiple design approaches. The
appropriateness of each approach depends on a host of technical, commercial and environmental
requirements applicable to individual projects. Chapter 8 summarises these design principles in the
form of general guidelines, recommendations and conclusions.
Page 3
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
2 VSC-HVDC CONFIGURATIONS
2.1 Introduction
The primary objectives of this chapter are to:
2. describe the main building blocks of the VSC-HVDC link in the context of offshore WPP
integration in the onshore AC system
This chapter provides a background of the subject in the next section, then presents the overall
configuration of the VSC-HVDC link for connecting the off-shore WPP to the host on-shore AC system,
and finally describes the main components of the VSC-HVDC link. This chapter also identifies a set of
requirements, assumptions and criteria that are used in the following chapters of this brochure.
2.2 Background
During the last several years there has been a significant increase in the number of offshore WPPs.
The primary reasons include: lack of suitable onshore locations for additional WPP developments, and
offshore WPP potential to generate significantly higher level of energy – when compared with an
onshore WPP project of the same rating. To transfer the offshore WPP energy to the onshore AC grid,
the VSC-HVDC link provides technical features and economic advantages when the distance between
the offshore WPP and the onshore AC grid extends beyond 100 km, typically. It must be noted that the
choice of HVAC vs HVDC transmission requires further cost-benefit analysis based on individual
projects’ needs.
The ongoing developments in the HVDC technologies, in general, and specifically in the VSC-HVDC
technology, indicate a growing trend in further construction and utilization of point-to-point VSC-HVDC
connection and multi-terminal VSC-HVDC grids. Although the classical LCC HVDC systems currently
offer advantages for specific applications (e.g., bulk power transfer over very long distances) the VSC-
HVDC systems are necessary for integrating long distance offshore WPPs into the onshore AC grids
due to the lack of synchronous generation offshore. The basics of the VSC-HVDC technology,
protection, and control have been widely discussed in the technical literature [1, 2] and therefore are
not discussed in this TB. However, when necessary, the relevant specific characteristics and features
are briefly described and highlighted.
The VSC HVDC system was first implemented as a test installation in 1997, with growing installed
base over the past decade. Currently, there has been an increasing trend in the development of
semiconductor technologies, resulting in further consideration of VSC HVDC technology for
transmission projects around the globe. By the end of 2014, advancements in semiconductor devices
have seen ratings up to 900 MW @ +/-320 kV for WPP connection.
Some of the main advantages of the VSC HVDC technology, compared to the LCC HVDC technology,
are:
scalability
self-commutating capability in systems with no synchronous generators (e.g., offshore WPPs)
capability to use XLPE cables, as the VSC-HVDC does not require the DC voltage polarity
reversal either for power flow direction change nor during AC fault conditions
Page 4
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
One of the considerations regarding the VSC HVDC technology, compared to the LCC HVDC
technology, is the potentially higher converter station losses. The latest developments in the
semiconductor switches as well as developments in the VSC configuration, which can operate at lower
switching frequency without compromising the waveform quality, indicate that the VSC HVDC
converter station losses can be reduced to the levels comparable to that of the LCC HVDC converter
station.
The first VSC-HVDC technology was based on the two-level and the three-level VSC configurations
and the classical PWM switching strategies, e.g., the sinusoidal PWM (SPWM). The VSC HVDC
technology for future installations, including for offshore WPP applications, consider the multilevel VSC
configuration, e.g., the modular multilevel converter (MMC) configuration, and accordingly different
switching strategies. The development of the multilevel VSC for HVDC applications promises:
i decrease in the losses
ii potential for increasing the voltage level and thereby also the power level
iii reduction in the size or even elimination of the AC- and DC-side filter and
iv higher degree of reliability and availability
The developments in the VSC technology for HVDC applications are accompanied by developments of
the extruded DC cable technology. The extruded DC cable technology for commercial use is currently
available for DC voltages of up to 320 kV. For future developments 525 kV extruded HVDC cable
system has been tested [3]. Higher voltage ratings are possible based on the use of the mass-
impregnated cable technology [4]. References [2-5] provide further details on various VSC HVDC
technologies, applications, control and protection strategies, merits and limitations, and for future
onshore and offshore WPP applications.
The first offshore WPP VSC-HVDC connection to the onshore AC system (i.e., the BorWin1 WPP 400
MW, +/- 150 kV), was commissioned in 2009. The subsequent offshore WPP connections to the
onshore AC system, through VSC HVDC links, have been delivered from 2014 onwards. The power
and voltage ratings of the following installations are in the range of 500 to 900-MW and +/-250-kV up to
+/-320-kV, respectively. More detailed overview and information for the installed and planned VSC-
HVDC, for offshore WPP applications, are available in Chapter 7 of this TB.
Page 5
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
During some operational scenarios (e.g., faults on the AC side of the onshore VSC HVDC station) the
power balance between the WPP and the AC system is transiently violated and the generated power
by the WPP cannot be fully injected in the AC side. In such a situation, the excessive power at the
WPP side (with respect to the power that is injected into the onshore AC-side) results in the voltage
rise of the DC link. The DC link voltage must be kept within a pre-specified bound to comply with the
protection requirements and to prevent HVDC shut down. Thus the balance of power needs to be
provided to maintain the DC voltage to limit variations of the DC link voltage. One approach to achieve
this objective is to utilize a DC chopper at the DC-side of the onshore VSC HVDC converter station to
drain the excessive power from the DC link and dissipate it in a properly designed resistor. This
provides ride-through capability to the VSC HVDC system during the close AC system faults and
maintains the WPP operation uninterrupted. However, since cost consideration imposes a practical
limit on the amount of power that can be dissipated by the operation of the chopper system, the VSC
HVDC must be tripped, if the limit is reached. The DC chopper, used in several schemes, is able to
absorb a limited amount of energy from the DC system and limits the voltage in the DC cable system
by preventing cable overcharge to the trip level, or prolongs the DC cable charging time interval, to
enable the other countermeasures to address the problem.
Overall, the DC chopper must provide:
robustness, reliability, and ease of maintenance
independent control based on local voltage measurement
coordinated control with the converter station controller (if applicable)
low or no degree of dependency on communication systems
compliance with the local grid codes
In addition, higher level controls are also required by the VSC HVDC for offshore WPP connection.
These include:
Page 6
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Control of the WPP Output Power. Please refer to the Functional Requirement in Chapter 4 of
this report
Automatic WPP Output Power Control: The power generated by the WTGs can be controlled by
assigning a control function to the offshore VSC HVDC converter to control the WPP power
output, based on frequency control of the WPP AC collector system [6]
Excess power in the onshore AC system results in the AC system frequency increase. In such a case,
it is desirable to actively control and reduce the injected power of the WPP into the AC system. This
can be accomplished by communicating the main AC network frequency deviations to the offshore
VSC HVDC converter station to vary the offshore frequency, or direct the WPP governor to vary their
active power generation. This mode of the combined WPP VSC HVDC operation is analogous to that
of a classical power plant operation under AGC control [7]. The control functions of a WPP-VSC HVDC
are defined based on the connection agreement and the adopted grid codes document.
To guarantee reliable and appropriate control functions of the VSC HVDC in compliance with the
requirements of the offshore WPP and the onshore AC system, there is a need for a bi-directional
communication system between the VSC HVDC stations. For the VSC HVDC integration of offshore
WPP a two-level communication system (e.g., fast and slow) are suggested in Figure 2.1. The high
speed communication could be used for control actions and the low-speed communication could serve
the needs for monitoring functions. The slow communication provides transmission of measured rms
values, device status for interlocking, start-up/shut-down/reconfiguration commands, alarms, and
detailed status of equipment parameters for monitoring or maintenance. The fast communication for
control and protection functions covers the delivery of actual DC voltage, actual active power limits, DC
current limits, converter status (blocked, unblocked), converter protective block actuation, and
converter emergency switch off related actuations.
Figure 2.1: Communication System of an offshore WPP integrated in an AC system through a VSC-HVDC link
Since the existing trends indicate that the point-to-point VSC HVDC system for offshore WPPs will be
extended to the VSC HVDC grid configuration, it may be desirable to design the point-to-point VSC
HVDC system to accommodate the future requirements in the grid context (e.g., provisions for
additional space to allow new pieces of equipment and connection of new DC cables to the offshore
VSC HVDC platform provided this additional space does not substantially increase the cost of the
platform1). However, the main changes in the evolution of the point-to-point VSC HVDC to the VSC
HVDC grid will be related to the control strategies and algorithms. Availability of cost competitive
HVDC circuit breakers, and DC/DC converters, along with potentially new technologies for fast and
effective DC power flow control and DC fault detection, will also impact future HVDC grid
developments.
1
Currently air insulated switchgear (320 kV) requires significant additional space/footprint and thus could
result in higher costs. DC GIS available for 320 kV, and under development for 500 kV, could provide
attractive solutions.
Page 7
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Figure 2.2: Point-to-point VSC- HVDC connection between an offshore WPP and an onshore AC
System
In Figure 2.3, two independent VSC HVDC links (each a point-to-point configuration) connect one
offshore WPP to two different buses of the onshore AC system through VSC HVDC converter stations.
The potential reasons for adopting this configuration include:
Upgrading and increasing the power rating of the WPP beyond the nominal capacity of single
existing VSC HVDC system
Increasing the reliability of the connection and maintaining power flow from the WPP to the AC
system even if one VSC HVDC is out of service due to planned or forced outage events
When this configuration is chosen, full redundancy of the offshore and onshore converters is required.
For further discussion on this topic, please refer to Reference [9].
Page 8
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Grid Connection
Point 2
Figure 2.3: Multi-Infeed VSC- HVDC connection between an offshore WPP and an onshore AC
System
The WPP can participate in the frequency control (primary regulation) of the AC systems [10]. The
drawback of the multi-terminal VSC HVDC (without DC circuit breaker or Full Bridge Converter) is that
a DC side fault requires a complete shut down and restart of all converters and the DC system, as the
fault can only be cleared by opening the AC side circuit breakers of all the VSC HVDC converters.
Offshore DC switching stations (especially if air insulated) add potential project cost and require
considerable maintenance due to harsh offshore conditions.
High equipment ratings, to accommodate high wind/power flow conditions, may result in
additional cost burden for the DC system.
Without economical and reliabale DC breakers, or other fast fault clearing measures, the
stability of the connected AC systems may constrain or not allow such configuration.
Page 9
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Page 10
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Offshore Wind
Farm(s)
AC Grid Converter Onshore Offshore Converter
Onshore Transformers Converter Converter Transformers
=
~ ~
=
=
=
Converter Converter
~
~
Transformers
Transformers
Converter
Converter
Offshore Wind
Farm(s)
AC Grid
The technical brochures form CIGRE Working Groups B4.57 (Guide for development of models for
HVDC converters in a HVDC grid), B4.58 (Devices for load control and methodologies for direct
voltage control in meshed HVDC grid), and B4/B5.59 (Control and protection of HVDC grids) provides
further details on the subject.
Page 11
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Page 12
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
1. AC switchyard
2. Power transformer
3. AC phase reactor (unless comprised into the power transformer)
4. AC shunt damping reactor (if applicable)
5. AC cable on shore
6. Pre-insertion resistor and its by-pass switch (this system is needed to properly energise
the DC network starting from 1 converter)
7. Neutral DC point reactor
8. AC/DC converter
9. Valve room with IGBT modules
10. Control room
11. Pump room
12. Storage room
Page 13
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
2.8 References
[1] CIGRE Technical Brochure No 269, VSC Transmission. CIGRE WG B4.37, 2005.
[2] CIGRE Technical Brochure No 492, Voltage Source Converter (VSC) HVDC for Power
Transmission – Economic Aspects and Comparison with other AC and DC
Technologies. CIGRE Working Group B4.46, 2012.
[3] Gustafsson, A., Saltzer, M., Farkas, A., Ghorbani, H., Quist, T., Jeroense, M. The new
525 kV extruded HVDC cable system. ABB Grid Systems, Technical Paper Aug 2014.
[4] Mahimkar, N., Persson, G., Westerlind, C. HVDC Technology for Large Scale Offshore
Wind Connections. Proc. of Smartelec 2013, Vadodara, India, April, 2013, 5 pp.
[5] Callavik, E. M., Lundberg, P., Bahrman, M. P., Rosenqvist, R. P. HVDC technologies for
the future onshore and offshore grid. Proc. of CIGRE Symposium “Grid of the future”,
Kansas City, USA, October, 2012, 6 pp.
[6] Y. Phulpin, "Communication-Free Inertia and Frequency Control of Wind Gen Erators
connected by an HVDC-Link", IEEE Transactions on Sustainable Energy, 27(2), May
2012, pp. 1136-1137.
[8] R. Sharma, "Electrical Structure of Future Off-Shore Wind Power Plants with a High-
Voltage Direct Current Power Transmission", Ph.D. Thesis, Technical University of
Denmark, Lyngby, 2011.
[10] Offshore Grid Development Plan 2013, first draft. German TSOs. 2013.
http://www.netzentwicklungsplan.de/content/offshore-netzentwicklungsplan-2013-erster-
entwurf
[11] CIGRE WG B3-36 interim draft report, "Special considerations for AC collector systems
and substations associated with HVDC connected wind power plants".
Page 14
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
1. Connection between VSC HVDC converter station and the WPP collector substations
2. Selection of the WPP transformers
3. Design of the WPP internal collector system
4. WPP operational aspects
Note that many of the general design aspects discussed here, such as transformer selection or the
design of the internal collector system, also apply to WPPs having an AC connection to shore.
- Higher wind speeds and waves resulting in higher mechanical stress on all components
- Foundations (including the transition piece and substructure [see 3.3]) and submarine cables
increase the cost of the balance of plant (BOP) in an offshore WPP. Furthermore, the
breakdown of CAPEX for a typical offshore wind power plant is highly dependent on specific
project details that can either be of natural cause (i.e. water depth, soil conditions etc.) or
developer specific decisions (i.e. type of foundation, philosophy of WPP architecture, etc.).
- Weather conditions, distance to shore, and logistics needed for repair and maintenance
contribute to a potential increase in operation and maintenance costs and the down time of the
offshore WTGs compared to onshore WTG. Therefore, careful trade-off balance between
corrective and preventive maintenance costs must be exercised to achieve the desired
reliability and availability.
In order to reduce costs during the early design stages, attention must be paid to remote maintenance
technologies (e.g. automation of components, redundancy built into important systems to avoid
downtime, remote diagnostic tools and Condition Monitoring Systems (CMS)). The reduced
environmental concerns in regards to hub height, visual impact and sound levels, enable offshore wind
turbines to be designed bigger than the onshore variants and achieve a higher energy yield per
individual WTG.
Though generalisation should be made carefully, recent projects have shown that there is a significant
difference between onshore and offshore WPP costs.
Page 15
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
The failure rate of the WTG and its components determines the frequency of any corrective
maintenance programmes, however this will have a direct impact on the maintenance cost and
availability. As project ratings and distance from shore increases, owners and operators will have to
examine appropriate O&M strategies to achieve desired objectives. Significantly larger projects and
further distances to the nearest onshore harbour (e.g., greater than 100km) can lead to the
requirement to have offshore based fleets of service technicians. This requires either fixed
accommodation structures (much like in the oil and gas industry) or mobile “Flotel” type vessels to
service both the crew needs as well as the facilities required for storage of spare parts, components,
and maintenance equipment.
In summary, the best way to achieve high energy production from any given turbine, may be to
increase turbine size and availability, whilst maintaining a low OPEX cost due the reduction in
components´ failure rates and reduced mean time to repair.
Page 16
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Since nearly all recent offshore WPP projects are predominantly utilising Type 3 and Type 4 WTG
designs, a more detailed description of each technology is presented below.
Page 17
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Depending on the chosen gearbox and generator type, the size and rotational speed of the generator
changes. Common applications are:
Low-speed (e.g., 4rpm to 20 rpm) multi-pole generators synchronous generator without gearbox,
called direct drive (DD).
Fast speed generators (e.g., 600rpm to 1800rpm) and medium speed generators (e.g., 400rpm to
600rp), which can be equipped with synchronous generator (external excited or permanent magnet) or
asynchronous generator. The medium speed generator WTG does not require a gearbox with a high
speed stage, which decrease the gearbox failure rate.
Low-speed direct drive WTGs need a physically larger design than fast and medium speed ones. As
the generator rotational speed decreases, and the number of poles increases, the diameter or the
length of the generator increases in order to gain the surface area required for electromagnetic
coupling. This means more material is needed, resulting in a heavier and more costly generator but
with decreased number of components. Optimum design must consider the trade-offs between
gearbox and generator alternatives, with considerations on total weight, increased number of
components, maintainability, and replacements in case of failures.
Floating foundations are the next evolution in wind turbine foundation technology. They are currently
only deployed in small scale pilot prototype situations, however in the future this technology is likely to
reach larger scale commercial deployment, opening up otherwise restricted ocean locations (i.e., water
depths over 60 meters- surrounding regions such as Norway, northern Scotland, and Japan).
Page 18
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Model
Page 19
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Designing wind turbines specifically for HVDC technology may influence the trend of the available
technologies to produce systems that are both technically and financially optimised. Utilising the HVDC
technology to fulfil grid code requirements may lead to a reduction of required WTG capabilities,
including: FRT, large reactive power range, or large frequency range. In theory, this may facilitate the
use of other existing technologies such as Type 2 WTG or WTGs with dynamic gear boxes and the
further development of simpler, robust and more economic WTG technologies solely to be connected
to HVDC systems leading to improved WTG reliability and availability.
For example due to the inherent frequency independency of the VSC technology, a symbiosis of
WTGs and HVDC transmission systems gives opportunities to optimise offshore WPP frequencies
while onshore network requirements are still supported. This may be achieved through increase of the
offshore base frequency, or a narrower or wider frequency band dependant on the optimisation in
operation of all offshore components. Another example for a positive impact of a symbioses between
HVDC link and the offshore wind power plant is the reduction in voltage control / reactive power
requirements. The most crucial benefit would be finding an agreement on how the reactive power is
shared between the offshore HVDC converter station and the WTGs. Turbines can be designed to
almost solely produce active power while the offshore converter station would takes care of the
reactive power management. It is worth noting that the economic benefits from the symbiosis of the
WTGs and HVDC transmission systems can only be realized if the regulatory authorities (TSO) allow
such operation through new regulatory requirements, and the offshore HVAC network is small enough
to be operated in such a manner.
Symbioses of HVDC technology and WTGs will further support the development of offshore DC grids
(see Cigré group DC grids B4-52 - HVDC Grid Feasibility Study). Currently, there are several
development activities underway to overcome the challenges associated with availability of DC/DC
converters, DC circuit breakers and DC wind turbines. There are currently no commercially available
large scale DC WTGs.
Page 20
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Voltage levels of the offshore HVAC-system between the HVDC platform and the WPP collector
substation(s) are defined by the available cables. To date these normally range from 132kV, up to
220kV. These cables are of identical technology to those used for HVAC connection of WPPs,
although the cable lengths will typically be shorter.
Cables with cross sections of up to 1200mm2 are common, although higher values are possible.
Please see the relevant brochures from CIGRE study committees B3 and B4 for more information.
J-tubes encase the cable as it transitions from sub-seabed to the platform / turbine. Their name comes
from the shape which not only provides protection, but controls the bending radius of the cable. An
example of a J-tube on the side of a WTG transition piece can be seen in Picture 3-1 below. Note that
this example shows the equipment pre-installation with the end of the j-tubes prepared for transport. It
is important to consider the influence of J-tubes on cable rating offshore as this additional physical
protection causes increased heating effects, and corresponding reduction of cable ratings. Please see
the TB by CIGRE WG B3.26.
The length of the connection between the HVDC offshore platform and the WPP AC-platforms range
between 5 to 40km for German projects. Because of the relatively short length (compared to AC-
connected offshore WPPs) shunt reactors for compensating cable charging currents are usually not
necessary, but may be required due to country specific regulations. However, for larger or multiple
independent projects covering significantly more seabed, particularly those with multiple collector
stations connected via long HVAC cables, there may be a driver for HVAC cable charging current
compensation offshore. This could be addressed by either the VSC-HVDC system, the WTGs
Page 21
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
themselves, or dedicated fixed shunt reactors. The choice of which would depend on capital
expenditure vs. any impact on losses over the lifetime of the project.
Picture 3-1: Transition piece showing j-tubes (prepared for transport to site)
WPP collector station transformers represent the heaviest components on the offshore platforms.
Hence, their rating is mainly limited by weight, size and the available crane capacity (in case a
replacement would be required). It may be beneficial to consider using 60Hz equipment in the offshore
Page 22
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
network due to a slight reduction in size and weight compared to 50Hz equipment. However this would
only be plausible if the equipment can be sourced in reasonable timescales having been type tested /
certified for use offshore.
So far, transformers with ratings up to 240MVA1 have been installed on offshore platforms. Higher
rating transformers of 320 MVA are in planning stage.
The choice of the nominal voltage for WPP internal collector network always represents a trade-off
between capital cost and losses over the lifetime of the project. The higher the voltage levels, the more
WTGs can be connected to one feeder at acceptable losses but at the same time, investment costs
will increase considerably for voltage levels above 33kV. With higher voltage levels the collector arrays
can spread over a greater distance without unacceptable voltage profiles. This is an important factor
for very large WPPs where there is a strong desire to reduce the number of collector platforms, and
thereby capital investment requirements.
Medium voltage submarine cables are available from various manufacturers who offer either copper or
aluminium conductors. The maximum standard cross section for medium voltage cables is typically
800mm2. Larger cross sections of up to 1200mm2 may be available but at increased cost and weight,
however, these may make installation more difficult. Typically the cross section of cable used is
smaller at the end of the string, compared to the start (near the platform) as there is less current to
carry. This can save substantial capital expenditure.
1
One example being West of Duddon Sands WPP in the UK which is owned by DONG Energy and Scottish
Power Renewables
Page 23
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
For improving reliability, or ensuring the supply of auxiliary devices for WTGs, the radial structure
according to Figure 3.5 can be extended into a ring structure as seen in Figure 3.6 structures are
always operated radially, with an open point in each ring.
Page 24
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Provided the cable cross sections are chosen to be large enough, it may be possible to transmit some,
or all, of the available power around the ring if a cable fault were to occur. However, in most cases, the
WPP collector systems offshore are not designed for full redundancy, even if they are equipped with a
ring structure. Although, just being able to have electricity supplied to WTGs that are connected to a
string, which are temporarily out of service (e.g., due to a cable failures) can be of great advantage.
However, fault isolation and system re-configuration may require time consuming manual action
(opening / closing of disconnectors) in a number of turbines unless each has additional switchgear
installed at significant cost and footprint. In any case, the capital cost of additional cable and
switchgear (if desired), plus installation of both, would have to be compared against the likelihood of a
collector network cable failure at various string locations and the cost saving of avoiding auxiliary
stand-by power (e.g., diesel generators) in each WTG, together with any additional power export which
could be achieved.
Other topologies, like star topologies, are also possible but are less common. One reason is the fact
that the area of seabed at one side of the platform must remain free of cables to allow jack-up vessel
access. However it should be noted that although other geographical topologies are possible, there is
little or no difference electrically (e.g., string length and number of turbines per string etc.), and
therefore they are not discussed further in this brochure.
Cable cross sections have to be chosen under the consideration of the following constraints:
Page 25
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Amongst all cable cross sections, which comply with these constraints, the optimal cable cross section
is defined by the minimum net present value (NPV) calculated under the consideration of:
Annual energy losses and revenue are calculated based on the probability distribution of annual wind
speeds (defined by a Weibull-characteristic), the WTG power curve, WTG unavailability, grid
curtailment / constraint and several load flow calculations of the WPP collector network.
For calculating NPV, the WPP anticipated project life (typically 20 to 25 years) and the discount rate
have to be defined for the project in addition to all technical data and cost information.
Page 26
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Laying: sea /sea-bed survey (bathymetry, side scan sonar, bottom profiling, thermal resistivity,
vibrocore sampling, magnetometer, sand waves, obstacles ( including other cables, pipelines,
water depth, water speed, ...), unloading, trenching, post-lay bury, cables to be laid separately
or bundled together for bipolar cables, magnetic compass effect, weather conditions during
laying, mechanical protection (e.g. stone dumping, concrete mattresses), platform terminations
(e.g. J-tubes), shore interfaces, marine traffic during installation.
Repair: availability of proven repair joints, mobilisation, permitted outage
Legal: permits, legislation, regulations, bulletins, policy statements, safety procedures and
rules, technical guidance notes, specifications, codes of practice, handbooks, transmission
procedures, corrosion by or on other installations, fishing, trawling, effects, archaeology,
defence, naval and recreational requirements etc.
Experience from similar installations and experience of the cable technology being used at the
voltage level proposed
On–shore: Of course, a substantial length of cable may also be required on-shore to connect to
the nearest substation. Many of the above requirements need to be also considered for the
onshore section of the connection.
Each of the above needs to be considered in detail so that the connection is designed and installed
properly and the potential risks are minimised.
It is recommended that close attention is paid to the Recommendations on HVDC cables as issued by
Study Committee B1. References [3] to [13] are considered to be relevant.
In addition, it is necessary to take into account the current works of Study Committee B1, which can be
found in references [14] to [19].
3.8 Bibliography
[1] Offshore Netzentwicklungsplan 2013, Erster Entwurf der Übertragungsnetzbetreiber
03.03.2013 Offshore
[3] TB 496 Recommendations for Testing DC Extruded Cable Systems for Power at a
Rated Voltage up to 500kV
[5] TB 379 Update of Service Experience with Underground and Submarine Cables
[7] Electra 214 Addendum to "Recommendations for tests of power transmission DC cables up
to 800 kV" (Electra 189-2000)
[8] Electra 206 Testing DC extruded cable systems for Power Transmission up to 250 kV
Page 27
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
[9] Electra 189 Recommendations for testing of long submarine cables with extruded insulation
for voltage from 30 (36) to 150 (170) kV. Revision 990811+ editorial
amendments 000113
[11] Electra 89 Transient pressure variations in submarine cables of the self-contained oil filled
type
[12] Electra 72 Recommendations for tests of power transmission DC cables for a rated voltage
up to 600 kV.
[13] Electra 32 Recommendations for tests on DC cables for a rated voltage up to 550 kV
[14] WG B1.38 After laying tests on AC and DC cable systems with new technologies
Page 28
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
The analysis of the control and protection integration of the VSC-HVDC converter and the wind power
plant (WPP) requires a clear definition of the configurations considered as well as the requirements
which will be demanded to the overall system in certain scenarios.
The present chapter considers point to point VSC-HVDC connections integrated with wind power
plants based both on DFIG and FSC. The considered scenarios include normal and fault operation. As
far as the requirements are concerned, they include start-up, shut-down and normal operation, the
active power curtailment, the fault ride through capability and the onshore grid support. The onshore
grid support will be mainly implemented in the grid side VSC-HVDC converter but it will require actions
from the WPP.
The required control and protection strategies are discussed looking both at the obtained system
performance and the required communication systems.
The wind turbines will be based on either DFIG or FSC. A configuration mixing both concepts can be
also considered, since it can also be found in large wind power plants.
Page 29
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
o The offshore grid frequency must be controlled at the desired value. This task is
performed by the offshore VSC-HVDC rectifier which imposes the offshore grid
frequency.
o Fault protection.
Main grid functions. VSC-HVDC connections are expected to provide support to the grid where
they are connected:
o Frequency support requires coordinating the onshore VSC-HVDC inverter (which will be
responsible only for measuring the grid frequency and transmitting it offshore), the
offshore VSC-HVDC rectifier and the WPP. The offshore wind plant will be required to
reduce or increase power for onshore grid frequency support.
o Virtual (synthetic) inertia may be required. It would require coordinating the onshore
VSC-HVDC inverter (which will be responsible only for measuring the grid frequency and
transmitting it offshore), the offshore VSC-HVDC rectifier and the WPP in a similar
manner to that required for frequency support.
o Power oscillation damping may be required. It can be based on the onshore VSC-HVDC
inverter injection of active or reactive current. If reactive power is to be injected, the
onshore VSC-HVDC inverter can manage it within its current limits, without affecting the
offshore VSC-HVDC rectifier and the WPP. Active power injection can be more effective
in some grids but it would require coordinating the onshore VSC-HVDC inverter (which
will be responsible only for measuring the grid frequency and transmitting it offshore),
offshore VSC-HVDC rectifier and the WPP.
o For the last three issues (frequency response, virtual inertia and power oscillation
damping), an alternative, which can be considered in some applications, is the usage of
a chopper resistor (or energy storage device) in the VSC-HVDC onshore converter. The
resistor would dissipate (or store in case of energy storage) power in steady-state
ensuring a power reserve that could be used when needed.
Page 30
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
o Fault protection.
o Active power management. Active power will be managed by wind turbine generators in
order to extract the maximum possible power for low wind conditions, extract the
nominal power in high wind conditions and reduce power when needed or required by
the grid operator.
o An appropriate start or stop sequence must be applied considering issues such as the
transformers inrush current and the possible voltage transients. Auxiliary power and
communication system are needed for the start-up and shut/down sequences.
o Provision of auxiliary power to the WPP when there is no available generation (no wind
or excessively high wind).
In order to be able to specify the control and protection functions required, the following situations are
considered:
Page 31
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Normal operation: The wind power plant is operated without any electrical restriction. In this
case all the generated power should flow through the WPP grid and is injected in the VSC-
HVDC cable. This situation is shown in Figure 4.1., where the green lines show the power flow.
P
Substation
P
Converter Station
P
P
Emergency
Power
AC Grid
Offshore Onshore
P P Onshore
Converter Converter
P
~ =
= ~
P
Transformer Platform 1
Restricted operation: Due to planned or unplanned outages, part of the electrical system might
not be available. For example, one of the two transformers on the platform might be
unavailable. Coordinated control will be required to limit the generated wind power. As it is
shown in Figure 4.2, operation at reduced power generation is possible.
Page 32
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Main onshore AC grid fault: A fault (voltage sag) in the main AC grid reduces drastically the AC
voltage in the onshore VSC-HVDC inverter and therefore reduces the power extraction
capability. These faults can be addressed providing fault ride-through capability by an
appropriate use of a DC chopper in the grid-side VSC converter as shown in Figure 4.3.
P
Substation
P
Converter Station
P
P
Emergency
Power
Offshore Onshore
P AC Grid
Converter Converter Fault Onshore
P
~ =
= ~
P
HVDC chopper
actuation
P
P
Transformer Platform 1
Page 33
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
DC fault: A fault in the VSC-HVDC cable or one of the VSC-HVDC converters will imply the
whole system disconnection. It has to be ensured that the disconnection is performed safely.
WPP grid fault: For faults in the WPP grid, part or all the WPP will be disconnected, the fault
has to be located and isolated rapidly. The disconnected part will depend mainly on the number
of circuit breakers available in the WPP grid and the available redundancy. Since the WPP grid
is an only power electronics grid, the short circuit current will be provided by the several VSC
converters. In must be ensured that the relay protections operate appropriately. This approach
is sketched in Figure 4.4.
P
Substation
P
Converter Station
P
P
Emergency
Power
Fault Transformer Platform 1
Page 34
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Fault in the WPP export cable: For faults in the WPP export cable, the fault will be isolated and
this may lead to the need for power reduction in the wind turbines. Since the WPP grid is an
only power electronics grid, the short circuit current will be provided by the several VSC
converters. In must be ensured that the relay protections operate appropriately. This approach
is shown in Figure 4.5.
P
Substation
Converter Station
Fault
Emergency
Power
Wind turbine
Offshore Onshore AC Grid
power reduction P Converter Converter P Onshore
P
~ =
= ~
Transformer Platform 1
Page 35
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Wind turbine internal fault: Internal faults in the WT will imply the individual WT disconnection.
Reduced power operation. The grid operator may send power references to the WPP in order
to reduce power, mainly due to congestion management issues. In this case a direct
communication will be sent from the grid operator to the WPP which will dispatch reduced
power references to the wind turbines, as shown in Figure 4.6.
Power
Power reduction reduction GRID
WPP CONTROL
P
OPERATOR
Substation
P
Converter Station
P
P
P
Emergency
Power
Transformer Platform 1
Page 36
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Frequency response. In the case of frequency variations, the active power from the WPP may
have to be changed according to the grid code requirements. In this case there are two
possibilities:
o A direct communication is sent from the grid operator control centre to the WPP
(containing the onshore grid frequency or the required WPP active power). The WPP
control dispatches power references to the wind turbines. This approach is shown in
Figure 4.7.
Onshore
frequency /
WPP required
Power reduction active power GRID
WPP CONTROL
P
OPERATOR
Substation
P
Converter Station
P
P
P
Emergency
Power
Transformer Platform 1
Page 37
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
o A direct communication is sent from the onshore VSC-HVDC inverter to the offshore
VSC-HVDC rectifier which changes the offshore grid frequency to mimic the onshore
grid frequency. The wind turbines react accordingly modifying the active power injected.
This approach is shown in Figure 4.8. The grid operator will send commands to switch
the operation mode between frequency sensitive or not sensitive.
P Transformer Platform 1
Substation
P
Converter Station
P
P
Onshore
frequency /
P WPP required
active power
Emergency
Power
Frequency Change
The coordination between the different systems will depend significantly on the delays between the
commands sent and responses obtained. These delays depends on the communication delays, the
controllers execution times and the time response of the commanded devices (for example the wind
turbines).
Because of the (normally) relative short cable connections between the off-shore HVDC converter
station and the wind power plant substations, feed-back voltage control at the wind power plant
connection points is typically not required. It is rather recommended to control reactive power flows in
Page 38
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
order to ensure that active power losses in both the high (between the HVDC platform and collector
substation) and medium voltage (collector network) grids are minimised.
Please note that although this is the minimum required for wind farm operation from a technical point
of view, there may be other reasons why it is necessary to monitor voltage and frequency offshore. For
example if the transmission system operator requires some contribution to voltage control, or if
frequency response is provided by varying the offshore grid frequency rather than sending a signal
direct to the wind farm controller.
The overall (secondary) control structure of the high voltage system is the following:
HVDC converter: Controls voltage magnitude and defines the offshore HVAC system frequency
at the HVDC AC terminals.
WPP deliver active power and regulate reactive power at the WTG connection points for
minimizing losses.
Additionally, there are faster inner control loops in the HVDC-converters and the wind generators, e.g.
for current limitation etc. but the overall control concept will typically follow the above described
principles.
A control integration scheme including communication requirements is shown in Figure 4.9. It can be
noted that the integration can be performed different combinations of the proposed communication
schemes.
G
Pitch HVDC
P*
Q* V, f
WIND
Q* function of V
TURBINE P* function of f V*
CONTROL V, f
f*
COM3
COM4
COM2
Page 39
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
COM1: Communications between the WPP control system and the individual wind turbines, to
allow power dispatching.
COM2: Communications between the grid operator and the WPP control system, to allow
power reductions for congestion management. This can be implemented in different time
frames.
COM3: Communications between the onshore VSC-HVDC converter and the offshore VSC-
HVDC converter to allow active power regulation for frequency support.
COM4: Communications between the grid operator and the onshore VSC-HVDC converter.
Electrical magnitudes as frequency can be used to modulate the information needed for the
coordination allowing devising a system without fast communications between VSC-HVDC and wind
turbines (COM3 would use this approach). Whenever the active power reference of the wind turbines
is to be modified it can be performed by means of communications from the central WPP controller
(COM2 and then COM1) or from the offshore VSC-HVDC converter by modifying appropriately the
offshore grid frequency (or just mirroring the onshore grid frequency on the offshore grid, COM3). Wind
turbine controls can be equivalent as for an onshore or HVAC connected wind turbine.
For HVAC transmission cables, circuit breakers are usually foreseen at both sides. Depending on the
length of the cable, they will be protected by cable differential protection and/or distance protection
relays.
The wind power plant transformers will be equipped with transformer differential protection relays.
The protection system of the cable collector network is based on overcurrent relays acting on circuit
breakers, which are installed at the MV-side of the wind power plant substation. Each of these string
protection relays will trip a complete string.
Sometimes, it can be found in literature that overcurrent protection will not work in conjunction with
HVDC rectifiers because the HVDC converters cannot deliver any currents above rated current.
However, it has to be considered that in the case of a fault on an MV-feeder, the complete current of
the HVDC converter will be redirected into the faulted feeder (as shown in Figure 4.10) and therefore,
the feeder current will increase by a factor, which is (about) equal to the number of feeders in parallel.
Because this number is usually in the range of 5 or 6, there will be sufficient selectivity margin for
overcurrent protection relays.
Additionally, when using wind turbine generators that are equipped with reactive current support, the
wind turbine generators connected to adjacent strings will also contribute to the total short circuit
current, assuming of course that they are in operation.
Page 40
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
HVDC converters can deliver a reactive current up to rated current in the case of low voltages, as it is
also required for wind turbine generators.
Slowly decaying or even increasing over-voltages during the sudden energisation of a wind
power plant transformer (parallel resonance)
High harmonic voltages because of harmonic current injections from the wind power plant
(parallel resonance)
High harmonic voltages because of high amplification factors for harmonic voltages emissions
of the off-shore HVDC converter (parallel resonance).
Page 41
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Figure 4.11: Network impedance at the off-shore connection point of a HVDC connected wind
power plant showing the impact of different cable lengths and transformer inductances
Offshore, if a resonance issue occurs, the wind farm will most likely trip due to the excessively high
voltages. For mitigating such problems, there are the following potential solutions:
Soft energisation of the off-shore wind farms by ramping up the off-shore voltage with all
transformers connected
Built-in filter function in the HVDC controllers for providing sufficient damping
Soft energisation is certainly the easiest way of avoiding inrush currents from the power transformers,
and therefore it avoids the harmonic distortions caused by the inrush currents in the offshore network.
However, it would require that all wind farm grid transformers connected to the same HVDC link would
always have to be energised simultaneously, which represents a considerable operational restriction.
With the help of high-pass or C-type filters, cable resonance problems can usually very well be
mitigated. However, these filters require lots of space and weight and therefore, any solution without
the necessity of additional filters would be preferable.
Hence, the implementation of an active damping function in the offshore HVDC-converter and/or
WTGs would certainly represent the most elegant option. However, such functionality is certainly not
standard at this stage and would require significant testing and tuning.
In the case of relatively short cable connections between the off-shore station and the wind power
plant substation resonance frequencies will be in a very high range making transformer energisation
resonance problems very unlikely.
Generally, as this section shows, resonance problems should be analysed already in relatively early
design stages as additional components may be required off-shore in the case that issues are
detected.
Page 42
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
If emergency stand-by power (e.g. from diesel generation) is being provided to the offshore platform
and/or turbines, this may have to be stopped to make the offshore island ‘dead’ unless the HVDC
manufacturer can synchronise at an appropriate point. Note, however, that if there are multiple
platforms then each may be operating as separate islands.
The onshore converter is firstly coupled to the main AC system. The next step is to allow the coupling
with the offshore converter DC system. Finally, the offshore AC system can be energized.
Onshore: Offshore:
Time
Figure 4.12: Start up/shut down sequence for the VSC-HVDC system for offshore application.
Courtesy of Siemens.
For the offshore wind power plant, once the VSC-HVDC rectifier is energizing the AC system, the
offshore substation can be energized sequentially. Once all the substations are energized, the wind
turbines can be sequentially connected.
For the system shut-down, the first step will be the wind turbines disconnection, followed by the
offshore substation disconnection. Once the offshore substation is de-energized, the offshore VSC-
HVDC can be stopped and finally the onshore VSC-HVDC can be shut down.
Page 43
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
time domain methods and the parameters of the HVDC controllers can be tuned for avoiding such
instability.
The fact that both wind turbine converters and HVDC converters are power electronics based systems,
requires appropriate control coordination for all the range of operation conditions.
Page 44
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
5 INTERCONNECTION REQUIREMENTS
The objective of the interconnection requirement is to ensure that the basic technical rules and
capability for connection to the Grid are defined clearly by specifying technical capability, design and
requirement criteria to achieve safe and secure operation of the power system.
In general terms, interconnection requirements are to provide transparent, non-discriminatory and fair
access to the transmission or distribution network. The need for an increased cooperation and
coordination among WTG and HVDC suppliers to design an optimum connection and to meet Network
operators’ requirements, with potential economic, operational and maintenance benefit is also an
overall objective.
All requirements discussed in the following sections are applicable at the point of connection, which
could apply at the offshore AC collector station or the onshore station, or both; this is illustrated in
Error! Reference source not found..
PPMs terminal AC Collector Station HVDC Offshore Platform Terminal AC Onshore Connection Point
Converter Station
To WTGs
Export
Cable
Capacity:
-Minimum and Maximum;
- InstalledPlants;
- Permissable;
- Financial
OFFSHORE
ONSHORE
OWNERSHIP
Figure 5.1: Interface points located in Offshore and Onshore connected through an HVDC system
This chapter deals solely with offshore connections at sea and associated requirements. Note that this
may vary for WPPs installed on islanded synchronous systems connected through HVDC to a remote
mainland, or parallel connection with a mix of HVAC and HVDC.As far as the onshore station is
Page 45
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
concerned, it is expected that a full range of requirements will apply similarly to requirement for
generators or HVDC interconnector connecting two synchronous zones. Grid codes were originally
developed with synchronous generators in mind and for onshore application. Since WPPs and HVDC
do not have the same characteristics as synchronous generators, this chapter highlights exceptions or
additional requirements for equipment located offshore compared to requirement for DC or AC
connected onshore WPP. The focus is on the offshore WPP station and the remote end VSC HVDC
converter station.
Figure 5.1 shows the different grid entry points connected with an HVDC system, this typically
includes:
A WPP Module;
An AC power station collector and apparatus located offshore to connect distributed WTGs;
An offshore converter station;
An HVDC link (i.e., submarine cable);
An onshore inverter converter station;
AC connection to the local system operator.
This includes the technical data relating to the physical plant installed at the onshore and offshore site
including generator type (or WTG type), plant auxiliaries, converter stations and DC, AC collector
networks and AC cables. The connection agreement shall define the limit, on the amount of power that
a new user can exchange with the network on a sustained basis; this would form the contracted value.
It is worth noting that in the case of a VSC HVDC connection, it is anticipated that the offshore WPP
may be installed in multiple phases. WPP capacity would increase at different stages of the project
execution.
The different terms of capacities, seeing from the AC onshore connection points are illustrated in
Error! Reference source not found..
Page 46
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
The maximum and minimum capacities are contractual terms that are the limit on the amount of power
that a generator or an HVDC site can exchange with the network. It can only change if a modification
to the connection agreement occurs. It is usually reviewed between the plant owner and the TSO after
compliance grid testing. These values are fixed although they depend on ambient conditions or
through the degradation/retrofitting of plant, correction curves are normally submitted as additional
information to take into account ambient condition. Minimum capacity is defined as the level of output
that a WPP or HVDC can sustain without compromising other requirements defined in the Grid code
such as frequency response, reactive power and voltage control.
Administrators of the connection agreements are notified if the power producers desire to change the
minimum or maximum capacity.
Technical data relating to the installed physical plant at a given site includes name plate rating of each
fundamental constituent part.
Generators have a choice of constructing the transmission assets themselves (“generator build”) or to
opt for an Offshore Transmission Owner (OFTO) to do so (“OFTO build”). If they construct the assets
Page 47
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
themselves, then the WPP-HVDC must transfer the assets to an OFTO post-construction and
installation.
Figure 5.2 illustrates the ownership regime for the Great Britain market. Important interface points and
the requirements that apply are briefly described.
Offshore Grid
Entry Point
Offshore
Offshore Power Park Module A
Transmission System
Substation Offshore Power Park Converter Station
Modul A [OFTO]
To WTGs
Export
Cable
Interface Point 1
Emergency
Onshore
Power
Transmission
OFFSHORE System [NGET]
ONSHORE Ownership of
NGET
Ownership of Ownership of
Generator OFTO
Interface Point
This is the point at which the offshore transmission system connects to the onshore transmission
system and this is an ownership and control boundary. It is at this point that all the onshore grid code
requirements apply.
Page 48
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
It must not be forgotten that ownership boundaries are determined by the relevant transmission
licensees and/or distribution licensees. National Electricity Transmission System Security and Quality
of Supply Standard (SQSS) defines the interface point depending on ownership of the first onshore
substation. HV busbars, if the first onshore substation is owned by the offshore transmission owner or
LV busbar if the onshore substation is owned by the onshore transmission owner, this is shown in
Error! Reference source not found..
5.3.2 Germany
In December 2006, a German law was put in place to facilitate the planning process for infrastructure
projects and supports the delivery of significant volumes of offshore generation in the North and Baltic
seas (see paragraph 17 section 2.a of Energy Industry Act). The German model requires the
transmission system operator (TSO) to plan, specify, construct and operate the offshore cables from
the grid connection system to the grid connection point (GCP), which is the cable sealing end of the
export cable. Note that the reactors are property of the TSO, but installed on the platform of the
developer.
Consequently, GCP represents the ownership boundary between the connectee’s facility and that of
the TSO as seen in Figure 5.3. It is worth noting that the law is silent about the converter stations;
however the definition of the Grid connection system includes the provision for partial DC transmission
or a direct AC connection.
Page 49
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
POC [Grid
Connection
Point]
To WTGs
Export
Cable
OFFSHORE
ONSHORE
WPP 2
Ownership of Connectee Y
Ownership of Ownership of
Connectees TSO
Figure 5.3: Ownership Interface points in Germany
WPPs connected to the transmission network via VSC HVDC connection could offer a large range of
reactive power control options. The reactive power capability of a VSC HVDC is independently
controlled at both sides of the DC link; the impact on one side does not propagate on the AC network
connected at the remote end. This could make reactive power and voltage control requirements for
offshore and onshore independent and different. For Grid Code reactive power requirements, the VSC
Page 50
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
HVDC connected WPP has the capability to quickly control the reactive power interaction with the
transmission system. Fast control within its wide operational range is feasible. The DC link and the
filter switching are utilized to control the net reactive power exchange and converter HV bus voltage.
Similarly at the offshore converter station, the same inherent capabilities are available, thus when
applied at the off-shore connection point this may reduce, or eliminate the reactive power requirements
on the WPP. This is however subject to national laws or network codes, as it is a common requirement
for generators to provide lagging and leading power factor range.
The minimum requirement for the offshore interconnection is to sufficiently compensate the total
charging of the WPP collector medium-voltage AC (MVAC) cable network and the HVAC cable
between the AC collector network and the VSC HVDC offshore converter platform. The charging of AC
cables should not cause the offshore voltage network to be outside the allowable voltage range. The
choice of circuit breakers and cables, type and number, are directly impacted by permissible voltage
and reactive power exchange.
WPP and HVDC Converter are connected through a cable system at the substation offshore.
Therefore, a careful design of reactive compensation of the cable system has to be developed
considering factors such as the best location for reactive compensation, and if it needs to be controlled
or not. For instance, a 200 km 3-core 33kV WPP collector MVAC undersea cable systems and a 1 GW
WPP (200 WTGs), shunt compensation requirement could be around 20 MVar1 at no load. AC power
from the 200 WTGs will run to an AC platform from which HVAC submarine cables will deliver the
power to an HVDC offshore Converter. Assuming a distance of 2 km between the two platforms and
six parallel 150 kV three-core HVAC submarine cables to deliver 1 GW power. The shunt
compensation requirement in either ends could be around 10 MVar2 at no load.
This requirement could be either placed on the VSC HVDC offshore converter, the AC collector
platform or at the WTG level. The compensating device could be controllable and coordinated with the
connection of the WTG. The operation of the compensation installation may have relaxed measures
for the limitation of harmonic voltages and other EMF requirement. This requirement is less onerous
than the reactive power requirement for the onshore VSC HVDC inverter. The cost implication of such
requirement may be important, in particular, the implication on WTG design, weight, space and
number of bays requirement on the offshore platforms must be carefully evaluated. Imposing the same
requirement, as AC onshore reactive power before they are justified, could make the connection
uneconomical and prevent integration of renewable energy.
The most relevant requirements are related to the active power control, power ramp rate control,
primary and secondary reserves, production set point changes, and start-up and shut-down of units,
etc. For example, in the Eirgrid Grid code, the active power set point, as a percentage of available
1
3 core XLPE-insulated cables with PE sheath and armour cross section 400 mm2, nominal phase capacitance 0.276 uF/km.
23 core XLPE-insulated cables with lead sheath and armour cross section 1000 mm2, nominal phase capacitance 0.23 uF/km.
Page 51
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
power, could be changeable from 15-100%, with a ramp rate from 1-100% of rated WTG capacity per
minute.
The required offshore frequency control during onshore over-frequencies can be achieved by active
power control of the WTGs (i.e., converter and pitch control of the turbine blades), or through shutting
down a portion of the WPP. To provide onshore frequency control during under-frequency events, a
possible approach is to intentionally operate the WPP at reduced power level to provide reserve and
assist the system frequency according to a governor droop and automatic generation control (AGC) by
adjusting the WPP active power set point.
As the number of WPP is increasing, it could be beneficial to consider their control capabilities when
planning and developing requirements and system services. In that case, the power plant controller
should be developed to enable an external control input signal to change the plant output power as
needed. Moreover, the automatic frequency control and power oscillation damping control functions
may also be implemented depending on the system and its control characteristics.
Active power control and frequency response are also requirements that are mandatory for VSC
HVDC connected WPP. Frequency response using a DC connected WPP may require a
telecommunications link between the onshore AC network and the offshore WPP. Examples of active
power control and frequency response control and concept are given in chapter 4 section 4.3.2.
Island of Ireland
3 phase fault at Tarbert
220 kV substation Scotland
3 phase fault at Walpole
400 kV substation
Fault Location 0 % Volts
0 ‐ 15 % Volts
15 ‐ 30 % Volts
30 ‐ 40 % Volts
40 ‐ 50 % Volts
50 ‐ 60 % Volts
60 ‐ 70 % Volts
70 ‐ 80 % Volts
80 ‐ 90 % Volts
France
Page 52
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Figure 5.4: Widespread voltage dips from a fault at a single location in Ireland and Great Britain. 3
Figure 5.4, above, shows the impact on network voltage under fault conditions at particular locations
in Ireland (see left figure) and Great Britain (on the right side). The colour code indicates areas in
which the voltage has fallen between 0% and 90% below nominal nominal voltage due to the fault.
These maps show how widespread the voltage dip can be from a fault at a single location. The low
voltage area could have been made wider by taking minimum generation conditions in the area and
more onerous outages. This would have worsened the impact of transmission fault.
The widespread voltage dips on the maps show the importance of not associating geographical
distance with electrical distance, thus it can be expected that any items of plant, generation or load,
within the coloured areas could be disconnected if these items do not have the necessary capabilities
to withstand the expected voltage drop for a certain duration. This is of a great concern to transmission
system operators. If windfarms or other generation units are unable to withstand voltage drops for a
limited time, they will disconnect from the system. This may cause a cascading voltage and frequency
instability, resulting in the need for load shedding or other actions. Fault Ride Through requirements for
WTG were then added to Grid codes from as early as 2000.
During these low voltage disturbances, individual generators are subjected to additional stresses which
often results in this requirement being the most difficult in terms of compliance. These stresses may be
such that internal protections are activated to prevent stresses that may damage the WTG.
The above is the case for an AC connected WPP, where a nearby fault on the AC grid will penetrate to
the point of connection of the WPP. For turbine technologies with an electrical coupling between the
stator and the grid (e.g., DFIG), this propagation will impose additional mechanical stresses on the
WTG. For the case of a VSC HVDC connected WPP or type four WTG, the mechanical stresses will
be reduced somewhat as the WTG is isolated from the main grid by its internal DC link. In addition,
there are benefits in relation to the DC converter contributing reactive power to the transmission
system during fault conditions.
Responses to system disturbances from WPP connected through VSC HVDC are mainly determined
by control function and the characteristic of the power electronic converter. HVDC converters have
unique characteristics and provide different signature plot of fault current than conventional
synchronous generators. For islanded synchronous systems, such as in Ireland and UK, active current
is given priority during voltage dips whereas for larger system, reactive current is prioritized to maintain
local voltage reducing the propagation of the voltage dip and enhancing transient stability. With HVDC
converters, control flexibility is available to provide either contribution. Typically, interconnection
studies could determine the appropriate post disturbance recovery performance with the system.
A large AC voltage dip at the grid connection point of the DC link will result in a significant reduction in
the active power delivered to the onshore AC system. This will result in a transient DC overvoltage and
excess energy at the DC side of the DC link, which can be dissipated by a DC chopper in order to
reduce the stresses on the WTG and sustain a constant power output from the WTGs. During the fault,
the DC chopper is activated. Once the DC chopper is activated, it will limit the DC voltage, thus
allowing the WTG to continue generation until the fault is cleared and full active power transmission is
3
"Diagram reproduced with the kind permission of EirGrid and National Grid - Copyright National Grid 2013. This diagram may not be reproduced in
any material form (including photocopying and restoring in any medium or electronic means and whether or not transiently or incidentally) without
the written permission of EirGrid or National Grid except in accordance with the provisions of the Copyright, Designs and Patent Acts 1988"
Page 53
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
re-established to the grid. Some manufacturers choose to install the DC chopper near, or at, the
onshore converter station in accordance with space requirements.
In relation to an offshore fault ride through capability, many requirements acknowledge that for a
voltage disturbance on the onshore transmission system, an offshore generator connected via a DC
link may not see the same, or indeed a smaller voltage deviation at the offshore point of connection, as
the same generator connected via an AC link. However, there is still validity in imposing a fault ride
through standard. This is largely due to the fact that the HVDC will play a key role in the offshore grid
voltages. All electrical transients’ rises or dips are to be considered during such events. Another aspect
is for faults occurring on the offshore MV or HV cables, it is expected that some of the offshore system
can be recovered. VSC HVDC and WPP Fault Ride Through requirements should be based on the
load reduction seen by the WPP, as a result of the DC link being unable to transfer full power to the
onshore system during onshore fault conditions, and based on the offshore system voltage recovery,
for offshore AC faults FRT requirements could apply at WTG terminal, WPP connection point, or
interface connection point as defined in section 6.1.
Protection systems based on power quality measurement could be required on project specific
demand in some countries. Power quality can continuously be monitored and when limits are
exceeded, the owner and network operator are informed to take countermeasures. In general, grid
operators and developers’ requirements refer to existing standards and guidelines when requesting
power quality assessments as part of the due diligence to obtain a grid connection. Most referred
standards and guidelines are given in section 5.12.
References [1] and [2] were written for general purposes and are not specific for WPPs, whereas [3] is
specific for WTGs. All have in common assessment methods to estimate distortion levels. These
methods are generally recognized as being conservative by experienced grid operators since it is
expected that the new plant is in compliance for all system condition and future proofed for all future
network possibilities, encompassing all possible equivalent R and X values and background
harmonics.
Waveform distortions caused by WTGs are fairly low. According to field experience, it is very unusual
to find cases of WPPs presenting harmonics problems due to harmonic current injection. The dominant
harmonic issues are typically due to resonance conditions where amplification of background
harmonics (either in the grid background or during energization events) can occur due to the export
and/or array cable networks (The distortion energy created by the WTGs are quite low but the
cumulative effect and their interaction with the electrical network is to be assessed on a case by case
basis.
Page 54
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
The collector system and the WTG transformers absorb an important portion of the WTG generated
distortion. Not considering these key elements in assessment studies results in very pessimistic
distortion estimations at the Point Of Interconnection (POI). A realistic analytical distortion assessment
should include proper modelling of the WTGs and grid conditions which determine the resonance
cases. Such assessment can be used to design or verify suitable Balance of Plant (BoP) or adapt
existing designs to mitigate distortion problems.
The existing guidelines are restrictive and should be followed with caution. Example of standards can
be found in [1] to [5]
Users connecting to the onshore, or offshore, networks are responsible for providing signals for
monitoring the state of the plant, as well as the possibility of communicating with them in order that
operational instructions can be issued through control set-points. The signal lists are specified in terms
of type, band-width and communication links and protocol. These include both signalling requirements
such as meteorological, availability data and settings for Power set points, Ramp Rates, Frequency
Response and Voltage Control. A series of standards are developed to allow application software from
different vendors to exchange information about the configuration and status of an electrical network.
The responsibility to provide validated models, associated documentation, user guide, data and
parameters is on the developers’ side, whereas the responsibility to provide information on the Grid
and methodology to assess compliance is on the system operator. The following table summarises the
typical data provision between the two parties: This is described further in Chapter 6.
Table 5.1 gives an example of data and models required before connection. The HVDC, WPP
developers exchange information with network operators. On the left side, are the data to be provided
by the network operator to the developer. On the right side, are the information prepared by the
developer for submission to the network operator.
Data and document provided by Network Studies, data and document provided by
Operators the developers or manufacturers, via the
Page 55
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
developers
Minimum and Maximum Short Circuit Static, dynamic Models and for special
Current cases (EMT)
Table 5.1: Data and Models Requirement, division of responsibilities by network operators and
developers
For commissioning of an offshore converter station there are two important differences compared to
commissioning of a station onshore. The offshore station is placed on a platform out in the sea and
there is no AC network available offshore when starting, (i.e., it requires black start capability). The
offshore station on the platform has limited access and also has additional auxiliary systems needed
for handling the platform, such as cooling system, fire detection/suppression systems, air conditioning
system, material handling system, telecommunication system, aviation/navigation aid and living
quarter facilities. All these systems are typically fed by an Auxiliary Diesel Generator before the
offshore HVDC converter is started.
Due to the special conditions on the platform specific requirements and regulations on health, safety
and environment have to be followed. The test and commissioning of the offshore converter station
includes inspection during civil works, test equipment, pre-installation and installation verification,
subsystem tests, operational system tests and system acceptance test.
For each stage of the commissioning there are specific test procedures for each kind of
equipment/system. It is most important that as many as possible of these tests and verifications are
performed before delivering the equipment to the platform. Modularization of equipment for offshore
platform can provide advantages to the overall project.
To reach high levels of reliability, automation is commonly used in such power plants, the start-up and
shutdown sequence is an added complexity and could require a power plant control system to control
and supervise the HVDC system and the WPP. During start-up different operational concepts could be
foreseen, those using the energy provided by the HV grid across the HVDC system to start-up the
auxiliaries and those using energy from independent or local supply.
Page 56
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Generally, there are not many grid code requirements specified for the start-up or shutdown of the
power plant, which could lead to different implementation.
The offshore converter station is normally energized from shore as a black start. The start-up
sequence requires a diesel generator on the platform to give power to all auxiliary systems and to
power the control and protection system of the converter until the converter is in operation, build-up of
DC voltage from the onshore station, start generation of an AC voltage in the converter before the
subsequent connection of AC cables to the AC collector network and the auxiliary power to the entire
platform. For further details, see section 4.5.2
In general, Grid Codes have been developed independently, with each jurisdiction having different
technical concerns depending on their specific system requirements. This leads to internationally
varied requirements for WPP. However, most have evolved with similarly structured requirements with
the distinction between codes being evident in the actual figures, values and definitions. These
common structures, which are specific to the technical requirements of WPPs, can often be
categorised as follows; this list is non-exhaustive but rather typical:
At present, most TSOs have yet to modify their respective Grid Codes in order to consider the various
possible connection types associated with offshore generation. The requirements are therefore
generally universal or cover a large connection type or location without distinguishing between offshore
or onshore.
The variation in possible configurations for the connection of offshore generation will create further
complexities for Grid Code issuers since the utilization of different technologies may necessitate a set
of different requirements. This reinforces the need to develop a common structure for which grid code
issuers will use to establish an appropriate standard for offshore grid connections.
Page 57
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Tennet TSO requires a different voltage level for the offshore transmission substation, compared to the
nominal values for onshore transmission systems, different reactive power requirement compared to
onshore and different frequency limit withstand capability. Note that setting a reactive power
requirement dependent on the voltage level is a specification by German transmission system
operators. The nominal offshore operating voltage is V=155kV with the requirement on the WPP to
stay connected within a voltage band of +/- 10%.
The characteristics of a generating plant during faults in the grid are also slightly different for offshore
applications. Both, the onshore and offshore grid codes require a reactive current injection to mitigate
voltage deviations. A voltage dead band of +/- 10% around the zero crossing of ∆V is defined in the
onshore grid code. This dead band serves to ensure that the generating plant is not operating in
voltage support mode in steady state, but rather operates with constant power factor or any other
reactive power characteristic.
5.11.2 Great Britain - National Grid Electricity Transmission plc. (National Grid) [7]
National Grid Code contains explicit technical conditions in relation to offshore DC converter and the
connection of offshore generation via HVDC interconnection.
Offshore WTGs connected by DC link have a choice in regards to fault ride through. The offshore WPP
can comply with a generic fault ride through requirement based on voltage dip duration characteristic
applied at LV side of the offshore platform (33 kV). Alternatively, comply with the existing onshore
requirements that are based on a close-up fault for a total fault clearance time of 140 ms. In the latter
case, the duration of zero voltage is dependent on local protection and circuit breaker operating times.
This duration and the fault clearance times are specified by Bilateral Agreement and Grid code
CC.6.3.15.
The Grid Code imposes similar frequency response requirements of onshore generators to offshore
generators. In addition, due to the decoupling effects of DC links, there is an obligation on the HVDC
connected Offshore Transmission System to make appropriate provisions to enable offshore
generators to fulfil the frequency response requirements of the onshore AC system.
In the case of offshore WPPs, the offshore transmission owner is to provide continuously some sort of
visibility of the onshore system frequency to enable WPPs to satisfy frequency response requirements.
In the case of offshore, WPP and HVDC must be capable to maintain zero transfer of reactive power at
the Offshore Grid Entry Point for all generators with an Offshore Grid Entry Point at the LV Side of the
Offshore Platform at all Active Power output levels under steady state voltage conditions, Grid code
CC.6.3.2. The offshore DC converter reactive capability is specified in a bilateral agreement between
the WPPs, the offshore transmission licensee and GB Grid operator.
Page 58
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
major step in the move towards a legally binding requirement for each member state in Europe. The
purpose of developing network codes is to provide transparent access to transmission networks across
Europe; while taking full advantage of harmonising requirements. This is to facilitate targets of the
European Union on renewable energy sources and distributed generation penetration, as well as
technology innovation and market integration, while ensuring security of supply.
The network code governing the requirements for generators, known as the “Network code for
requirements for grid connection applicable to all generators” [8] in its first public version included
HVDC and DC connected offshore WPP. Following stakeholder consultation, HVDC connected
offshore WPP were removed from the scope of this code. The rationale was that the DC connected
WPP were at a too early stage of technology development and a code for HVDC systems was planned
at later date enabling the formulation of more appropriate requirements with opportunities for
optimisation and synergies with HVDC capabilities. Requirement for Generator deals solely with
synchronous and non-synchronous (WPPs) AC connected to the grid from 800 Watts up, onshore or
offshore DSO and TSO connected.
Chapter 3 of the HVDC network code [9] deals specifically with WPPs that are DC connected via an
HVDC circuit. It is clear that most of this chapter covers the offshore area since HVDC is probably
more feasible for long distance undersea connection.
Most of requirements are comparable to articles of Reference [8] in terms of functionality but can differ
on parameters or characteristic, such as voltage and frequency withstand capability ranges.
It should be noted that the European network code focuses on requirements applicable on the AC
side of the connection point and leaving meshed DC grid requirements and DC point of connection out
of its scope.
WPPs interconnected to the mainland grid through one DC connection have the choice to enter on a
bilateral agreement for reactive power capability. Additionally, there are also provisions for non-50Hz
DC connected application.
At the time of writing this technical brochure, the HVDC connection code was with the European
Commission. The European commission and parliament will make this code binding in law and each
member state is to implement the requirements at national level. Some changes could be foreseen
before the final version of this code.
The VSC connection of an offshore WPP provides a number of grid code compliance advantages
when compared with an AC connection. The decoupling between the onshore transmission system
and the WPP is the key benefit. This brings about advantages in terms of WTG fault ride through
capability and reactive power requirements at the point of connection.
Page 59
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
In terms of voltage fault ride through, a VSC HVDC link can operate through essentially any onshore
AC fault and quickly restore the active and reactive power values to pre-fault values. However, a
voltage dip at the connection point of the DC link will create a corresponding drop in the transmission
capability of the link. This is effectively a load rejection scenario for the WPP and such a fast reduction
in the transmitted power would trigger a significant rise in the WPP bus voltage. The common solution
to such a problem is the inclusion of a DC chopper in the DC system. The DC chopper dissipates the
surplus active power at the WPP. This leaves the WPP largely unaffected during an onshore AC
system fault reducing the possible mechanical stresses on technologies that have an electrical
coupling between the WTG stator and the offshore grid. However, there is still validity in imposing an
offshore fault ride through standard, for offshore AC faults. In this case, WTG active power restoration
is to be provided as quickly as the WTG technology allows it..
Grid codes are key documents for providing clear direction with regards to designing HVDC and WPP
in order to integrate them satisfactory in an existing network. CIGRE through WGB4.56 [10] provides
information required by anyone providing new equipment for an existing HVDC Grid in order that his
terminal will integrate satisfactorily and without any negative impact on the overall system
performance.
Page 60
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
5.12 References
[1] IEEE Std 519-1992, “Recommended Practices and Requirements for Harmonic Control in
Electric Power Systems” April 12, 1993.
[2] IEC 61400-21 Ed. 2.0, “Measurement and assessment of power quality characteristics of grid
connected WTGs” . Ed. 2.0, August, 2008.
[3] BDEW June 2008, “Generating Plants Connected to the Medium-Voltage Network”. BDEW
Technical Guideline, June, 2008.
[4] Assessment of emission limits for the connection of distorting installations to MV, HV and EHV
power systems, IEC Standard 61000-3-6, Ed. 2.0, February, 2008.
[5] Engineering Recommendation G5/4, February 2001
[6] Tennet T TSO. GmbH
“Requirements for Offshore Grid Connections in the Grid of Tennet GmbH TSO”,21 December
2012.
“Technical Specification of procedures, interfaces and technical requirements for offshore wind
farm grid connections”, 20 October 2011.
[7] N. G. E. T. plc,
“National Electricity Transmission System Security and Quality of Supply Standard”, 2012
[8] ENTSO-E, “Network Code on Connection Requirements applicable to all Generators”, March
2013
[9] ENTSO-E “Network Code on High Voltage Direct Current Connections and DC-connected Power
Park Modules”, issued in April 2014
[10] B4-56 Guidelines for Preparation of Connection Agreements or Grid Codes for HVDC Grids
Page 61
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Page 62
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
In CIGRE TB 563 studies needed to be performed during the HVDC system lifecycle [4] are described,
however, primarily focus is on LCC HVDC systems. This TB focuses on the special application using
the VSC HVDC for connection of offshore WPPS. It is important to have validated models of the
components especially the active controlled parts such as WTG and VSC HVDC.
The focus of this chapter is to describe the purpose of each study in order to understand their impact
on the overall system design.
The purpose of making this steady state calculation is to determine the current flows and voltage
profile accross the entire power grid as well as in the individual components, e.g., HVDC converters,
WTGs, transformers, cables and busbars, etc. This is one of first steps that is utilized to verify
fulfilment of the relevant standard, grid code and design requirement for each element and the total
system in general.
These calculations will have to be done several times during the conceptual design stage until the
detailed design and full range of feasiable operating conditions are finalised, as the choice of voltage
and current levels for each component will be based on these calculations.
Hereafter a range of studies to be made in order to show compliances with the relevant grid codes and
standards are listed.
The following boundary conditions are assumed to be known before the calculation can be made. This
is a non-exhaustive list.
Page 63
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
All above points will go through an iterative process during the different stages for the project.
However, they will form a basis for the selection of the right components and elements for the VSC
HVDC connected WPP, such as operation range of the HVDC system, number of transformers,
current and voltage rating of busbars, cables, transformer, etc. Furthermore, this study shall indicate if
extra reactive power compensation devices are required to meet steady state performance
requirements. Having established the operational limitations of the individual components, it is feasible
to design the integrated system to meet all load flow related grid code requirements, standards and
meet project design criteria. In addition, it is also possible to calculate the electric losses and the
reliabilitiy and availability aspects of the project.
Short circuit calculations are more difficult to perform than the load flow calculation, particularly for the
offshore power grid, since the HVDC system and in general all converters are able to control to a
certain extent the short circuit contribution during faults.
The short circuit current contribution for converter technologies (both DFIG and FSC WTGs) is not
sufficiently represented in any standard dealing with short circuit calculation such as IEC, VDE, ANSI
standards, etc. These standards are normally based on synchronous generator technology and the
calculation of the ac component of the short-circuit current at fixed time instants. For example defining
the peak short circuit current (Ip), initial symmetrical short circuit current (RMS) (Ik”), transient
symmetrical short circuit current (RMS) (Ik'). Usually, the rest of the network is considered linear, (e.g.,
the short circuit impedance of a transformer is constant and independent of the voltage drop during the
fault). These models can be used for the protection design, determining the peak short circuit current
and the thermal rating.
Page 64
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
The HVDC system and WTGs with converters are able to control the short circuit current during faults.
This means that the short circuit current contribution during the fault from the HVDC system can be
best defined by the converter manufacturer. In general, the main limitations of the HVDC system
current contributions (i.e. the converter) are the overvoltage and overcurrent limitations of the
converter IGBTs and the speed response of the associated control loops. However, the zero
sequence contribution for the converter transformer is governed by the transformer connection and its
impedance(s), and not by the IGBTs.
An example of short circuit contribution from a converter can be provision of additional reactive current
proportional to the voltage drop as shown below in figure 6.1.
As shown in Figure 6.1 above, the short circuit contribution from the converter is strongly dependent
on the voltage level during the fault. The total reactive current from the converter is the sum of pre fault
reactive current and additional reactive current during the fault. This means that the converter model
should have capability to demonstrate this feature in simulations.
Short circuit calculation at the DC side of the converters would be difficult without very detailed
information of the converters. These calculations are normally made by the converter manufactures.
i. Time and voltage dependent short circuit contribution from the HVDC at the AC sides of the
converters
ii. Time and voltage dependent short circuit contribution for the WTG
iii. Time and voltage dependent short circuit contribution for the other power electronic equipment
if relevant
iv. Standard short circuit data for the other elements of the offshore power grid
Page 65
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
v. Standard short circuit data for the grid connection point onshore
Study objective:
Short circuit studies must include the onshore power grid along with the special short circuit in feed
behaviour of the HVDC converter and WTGs converter.
The studies can include short circuit calculations needed to design the protection of the offshore and
onshore power systems, and to determine the needed rating of each element in the power system e.g.
switchgear, busbar etc.
A range of quasi steady-state studies are made by the manufacturers of the HVDC system, however
some of the studies also need to be made by the wind farm developer where the detailed offshore
power grid is included.
The advantage of this method is that only standard load flow data and some general knowhow of
power system are needed to investigate the dynamic performance of the power grid. Furthermore long
time series (e.g. daily or yearly variation in the power grid) can be investigated fast.
The disadvantages are of course that the time step in the quasi steady state load flow has to be longer
than 100msec as load flow data are used and have to be validated. Furthermore all the time constants
(controller and control loops) with a longer time constant than the time step in the simulation must be
taken into account.
Controllers in the power system with a shorter time constant than the quasi steady state simulated time
step are in general modelled as steady state as in the load flow calculation. One example is modelling
of the AVC controller; in this case the HVDC voltage controller will normally be the fastest which
means that the voltage control of the HVDC will have the steady state value equal to the set point of
the HVDC.
For controller with longer response time than the time step of the quasi steady state simulation, each
controller must be investigated in order to evaluate its influence on the results before the simulations
are performed. An example can be modelling the wind speed variation in a WPP. In this case the
active power and thereby also the voltage profile will change during wind variations. In this case the
response of the AVC has to be investigated before a simulation is performed. The time step in the
quasi steady-state simulation is e.g. 30sec and the total time simulated is one hour (120 data point). In
this case the latency of the tap-changer’s AVC (dead time of the controller may be 1-2 minutes) must
be taken into consideration and included in the simulation in order to get correct variations of e.g. the
voltage profile in the power grid due to wind variations.
Page 66
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
variations in the power grid. The data needed is the step size of the tap changer of the transformer,
and dead time and dead band of the AVC controller.
Study objectives:
Investigating the response and variations due to slow controllers and wind variations in the WPP.
However it is important to emphasize that this method is only valid for slow variations.
Furthermore long term voltage stability can be investigated by using this method.
Determining if RMS simulation and/or Electro-Magnetic transient (EMT) should be used for the
simulation is highly dependent on which level of detail and bandwidth need to be modelled.
Normally, the time step in an RMS simulation is longer than 1ms. The bandwidth for the dynamic
models used in the RMS simulation must of course correspond to the time step chosen for the
simulation. Some RMS simulation software offers the capability of having dynamic devices such as
HVDC at a smaller time step and network solution at normal time step (two time step models). This
enables including faster dynamics within the device. Furthermore some RMS programs are able to
model positive, negative and zero sequence systems whereas others only model the positive
sequence system. In addition to this, the RMS simulation is able to simulate a large number of busbars
at acceptable computation times.
EMT simulation normally uses appropriate time steps given the phenomena to be studied from ms to
µs. This means that the model needs to be much more detailed and have a higher bandwidth than
RMS models.
For each specific project it has to be determined if RMS or EMT must be used for each of the three
types of studies described below.
For the simulation in general, both the offshore and part of the onshore power grid have to be
modelled. In general, it is most interesting to investigate the offshore power grid. However, in many
cases the response of the onshore power grid has an influence on the voltage and current in the
HVDC system and in the offshore power grid. The model for the onshore and offshore power grids and
the HVDC system has to be evaluated to see if it is suitable for simulation.
These simulations may be modelled using different models (RMS or EMT) and using different time
steps, as dictated by the phenomena being investigated. This is further described below.
Page 67
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
The reason for having three parts of the fault simulations is that there may be different requirements
for the accuracy of the simulation result and time step in each simulation. During the fault, the peak
value and oscillation (typically a frequency higher than approximately 10Hz) of the fault current and
voltage are important. However, on the other hand, the slower oscillation (typically slower than 10Hz)
of the current, voltage, active and reactive power recovery is important after fault or disturbance during
power grid recovery. This means that the model for simulation of the fault current during the fault
needs to have a higher bandwidth than the model for simulating the recovery after faults or
disturbances. In addition, the time needed to simulate the fault may only be a few seconds, where the
simulation to recover after a fault or a disturbance can take up to a couple of minutes. However, it may
be possible to use the same same model for all three simulations.
Before carrying out the simulation, it must be confirmed whether the models are only valid for positive
sequence and/or also for negative and zero sequence simulation. For three- phase short-circuit
simulations, only the positive sequence system is needed. However, for all asymmetric faults, the
negative and zero sequence systems are also needed.
In case the simulation tool is only able to simulate the positive sequence system data, the data have to
be modified enabling the program to simulate asymmetric faults. However, in the rest of this section, it
is assumed that the simulation tools are able to simulate positive, negative and zero sequence system
data and models.
Additional information on model requirements and time step for each of the three simulations is
described in Sections 6.4.1, 6.4.2 and 6.4.3.
In order to model the current and voltage with the required accuracy the time step has to be lower than
10ms, and even in the μs range. This requirement determines the required bandwidth of the model.
As the short circuit current in the offshore power grid is mainly controlled by the converters (in the
HVDC and WTGs), the voltage dip at each AC terminal of each converter is very important as shown
in Figure 6.1. The non-linear current vs voltage characteristics in Figure 6.1, shows that each converter
may contribute with different steady-state short circuit current. This fact may lead to short circuit
current having the same level as the normal operation current. In this case, the short circuit current
during fault can be difficult to detect by using normal overcurrent relays as known from onshore power
grid, where the fault current is normally higher than the normal operation current.
Having simulated the fault currents and voltages, it is then possible to validate the protection scheme
and make sure that the protective devices are properly coordinated.
It is also necessary to simulate onshore faults in order to verify the size of the chopper of the HVDC
system (or other means to have the fault ride through capability of the HVDC system for an onshore
fault). The onshore fault simulation can also be used to investigate the oscillation/fluctuation in the
HVDC link and in the offshore power grid during and after the onshore fault.
Page 68
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
All models shall be able to model the positive, negative and zero sequences
i. Suitable models of the WTGs and HVDC converters (including the DC link) corresponding to
the time step/bandwidth needed for the simulation.
ii. Suitable models of other relevant elements in the offshore power grid which contain power
electronics like SVCs or STATCOMs.
iii. Models suitable for the simulation of passive elements in the offshore power grid like cables
and transformer (standard load flow data can be used in many cases)
iv. Data required to adequately model the onshore grid connection points suitable for the
simulation
Study objective:
Investigating the short circuit current during all types of faults, at all relevant locations in the power
grid.
6.4.2 Simulation of power recovery and system stability after the disturbance
During the fault, the main focus in the simulation is the fault current and voltage, however, when the
fault has been cleared or after other disturbances (including disconnection of one or more WTG with
full production and disconnection of main offshore transformers), the main purpose of the simulation is
to investigate the power grid recovery and stability. The main focus must be on the voltage
magnitudes, the offshore frequency, and the active and reactive power recovery as the power grid
returns to normal operation. The simulation time step may be longer for this simulation compared with
the time step used in Section 6.4.1 above.
In the offshore power grid, the voltage and frequency will normally be controlled by the HVDC and the
controller has a fast response. However, the converter in the WTG may also have a fast
voltage/reactive power controller controlling the voltage/reactive power at the AC terminal at each
WTG. In addition the WPP may have an overall voltage/reactive power controller controlling the
reactive power and/or the voltage from the WPP. In addition to this, other reactive power
compensation (e.g., SVC) may also contribute to the voltage control.
These controllers have to be coordinated to give a stable voltage at the offshore power grid.
Furthermore, all the converters have reactive power limitations which also may have an impact on the
voltage to recover in the offshore power grid. However, the voltage control in the offshore power grid is
in general a "local" offshore power grid issue and the onshore power grid is of very little importance if
any.
By simulating the active power and frequency recovery in the offshore power grid the oscillation may
have a lower frequency than the recovery of the voltage, as the WTG may have been in fault ride
through mode during the fault. This means that the active power generated by the WTG cannot be
exported to the electrical system and will partly be stored in the form of kinetic energy in the rotor
(shaft) and partly spilled by WTG blade pitch control. . In order to restore the active power generated
for the WTG, the blades of the WTGs have to be turned into the wind again and the rotor speed has to
be controlled back to normal operating range.
Another way to remove the active power generated by the WTG during fault is to use a chopper in the
WTG which can absorb the active power during FRT. This means that the generator in the WTG is
unaffected by the fault. Hereby the active power recovery will be different compared to the option
described above.
Page 69
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
In addition to this, there may be some requirements in the grid code for the rate of change in active
power during the recovering after a fault. This requirement will typically differ from grid code to grid
code.
Furthermore when modelling the active power recovery, the response of the onshore grid may have an
influence on the offshore recovery as there may be some limitation and requirement during the
recovery.
As the voltage, current, active power and reactive power recovery after fault or disturbance is not
modelled separately, the model of the offshore power grid, the HVDC system and the onshore power
grid must be included, however, for the onshore model, the main focus must be on the active power
recovery and response.
Data needed for simulation power system recovery after fault or disturbance:
Same data as described in Section 6.4.1
Study objectives:
Investigating the system power grid recovery and stability after fault and disturbance in the offshore
and onshore power grid.
Another issue during normal operation is how HVDC and WPP can contribute to the overall onshore
system stability and damping of power system oscillation.
Since there is possibility of having control interactions between HVDC and WTG, the bandwidth of
traditional stability models designed for slow electromechanical oscillations would not be good enough.
The main limitation of these models is the negligence of the ac network dynamics (i.e. admittance
matrix method). In this case, a stability model with ac network dynamics modelled using dynamic
phasors can be used to improve the accuracy.
Study objectives:
Investigating offshore grid stability and how the HVDC and the WPP can contribute to the onshore and
offshore stability. Furthermore this method can be used to design power system oscillation damping
controllers.
Page 70
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
The bandwidth for the models of all elements and components in the power grid used in the high
frequency modelling must of course correspond to the time step/frequency range chosen for the
simulation, not only the controllers in the HVDC converter, but also for the model of cables, breakers,
surge arrestors and transformers, etc.
For high frequency simulation, as for quasi steady-state load flow and RMS simulation, all equipment,
components and controllers in the power system until the onshore connection point have to be
investigated in order to evaluate if each element has an influence on the simulation. As an example the
dead time for an AVC of a transformer is much longer than the normal time simulated in an EMT
simulation. However, on the other hand, in EMT simulation high frequency models of all the
components (e.g. cables and transformers) in the power grid is needed.
By using EMT, it is possible to simulate much faster transient events than with RMS simulation. This
could be the insulation coordination study and other transient studies such as high frequency stability
study in the time domain or switching transient study, etc.
Taking the three parts into consideration, the insulation coordination studies are well known and
described in a large range of standards, TBs, and technical papers.
Some studies must be made by the developer of the offshore WPPs including the connection to the
onshore power grid using a HVDC system. One of the most important studies is the high frequency
stability study in the time domain. The instability in the power grid can be caused by the controllers in
each converter interacting with other converter controllers and amplifying oscillations in the power grid.
Looking at the offshore power grid, there is almost no natural power damping (active load), only WTGs
generating power into the offshore power grid and the HVDC which exports the generated active
power to the onshore power grid. This means that the active power is fed from a VSC converter in
each WTG to a VSC converter at the HVDC system offshore. The resistance in the cable and
transformer in the offshore power grid may cause a small damping but from an electric point of view,
Page 71
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
the active power losses in the offshore power grid are small. This means that the power system
stability needs to be investigated carefully both for frequencies below and above the fundamental in
order to avoid unstable controller interactions.
In general, the converter in the WTGs and the HVDC can generate a wider range of frequencies , this
may cause a frequency higher (or actually also lower) than the fundamental frequency. This means
that any frequency can be generated and amplified in case one of the controllers in the converter is not
coordinated correctly with the rest of the controllers and amplifies a given resonance. Another issue
with the controller is that they may be affected by limits which will change the controller response. This
amplification may cause an unstable power grid leading to e.g. the voltage increasing rapidly.
By using an EMT simulation it may be possible to investigate whether the offshore power grid is stable
for frequencies higher than the fundamental. It is important that the model of the converters, in the
WTG , the HVDC and other power electronic equipment, includes all relevant controller, sampling and
dead time, time constants, transfer functions, limiters, etc. in all relevant control modes.
It must be possible to evaluate the stability of the offshore power grid for frequencies up to 2.5kHz, but
in special cases higher frequencies may have to be investigated.
The advantage of using this method to investigate the high frequency stability is that all the limitations,
dead and sampling times are included and their influence on stability is investigated in the time
domain.
The disadvantage of using a time domain simulation for investigation of stability is that the simulation
only has one operating condition. There are large number of different active power generating levels
for the WPP, or different voltages within the normal operation range, which means that in theory there
is an infinite number of operation conditions which must be investigated.
In order to limit the number of EMT simulations, a representative number of operation conditions have
to be selected. One way to select the critical cases is to make a stability study in the frequency
domain.
Page 72
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
The high frequency stability in this brochure is defined as a stability study of the offshore and onshore
power grid for frequencies higher than the fundamental (50 or 60 Hz). In this section the stability issue
will be addressed from a frequency domain perspective.
By using frequency domain models it is possible to use standard control stability approach (e.g.,
Nyquist stability criterion) to investigate the power system stability in a large range of frequencies.
The controller of the converter has to be modelled as a transfer function in the frequency domain. The
transfer function may be different in different operation modes such as exporting or importing active
power to the AC power grid, or controlling reactive power or voltage. However, the number of models
will be very limited, as the number of modes for normal operation is assumed to be less than five.
Having the transfer function of the converter including controller, it is possible to model the power grid
both offshore and onshore. It must be investigated if the offshore and onshore power grid can be
modelled separately which will reduce the complexity of the models.
The advantage of using this method is that each frequency can be simulated separately and not
dependending on the actual operation mode (as long as the converter controller has the same
characteristics in different modes). This means that all operation conditions can be analyzed without
having to run a simulation for each operation point.
The disadvantage of the frequency domain stability analysis is that limiter and non-linear response of
the controller is normally not included.
As described above, it is possible to investigate a large range of operation points by using the
frequency domain stability method. By using this method, it is possible to determine which operation
points should be further investigated by using the time domain stability method described previously.
Study objectives:
Investigating stability of the power grid, at all relevant locations in the power grid including controller
interaction instability.
A better model is a Thevenin or Norton equivalent, where the VSC converter is modelled as a source
and an impedance, at various harmonics. For the model, both the source and the impedance have to
be frequency dependent including both amplitude and angle. Other power quality issues are dealt in a
similar way to onshore wind farm connection.
Page 73
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
The flicker studies are well-known and described in range of standards and brochures. It is assumed
that the standard methods can be used for power system from the WTG all the way to the onshore grid
connection point.
Sub-synchronous interaction may be an issue for the offshore grid as well as for the onshore
connection point for the HVDC, however the studies needed are well know from onshore power grid.
The HVDC converter impedance depends on passive components and the control to some extent.
For each stage, a number of design iterations may be needed, in order to reach a level of details to
allow to proceed to the next stage of the project.
As the power, numbers and locations of WTG and substation is not fixed at this phase the detail level
of studies is limited. In general only simplified load flow and short circuit calculation can be made and
the result can only be given as range of power, current etc.
Dynamic behaviour of the power system can only be described in general terms.
In this stage more detailed load flow studies can be made, including determination of the concept for
voltage/reactive power control of the power system, both offshore and onshore. These load flow
studies require information of the active and reactive power performance of the WTG and HVDC and
on a generic level available data for the other element in the power system.
Short circuit calculations can be made in order to determine the rough short circuits current which will
give the data for rating elements like the switchgear, busbars etc.
Preliminary system stability studies investigating grid faults, fault recovery and load change can be
made from a conceptual perspective where functional requirements can be described.
In some cases it may also be possible to give a first estimate of the harmonic emission level in the
offshore and onshore power grid at this stage of the project.
Page 74
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
design prior to construction/execution. Normally the key elements of the power system, like the WTG
and the HVDC, are defined in this stage. Other elements of the system such as cables and
transformers will be fixed after contract and will be available for the detailed design.
Hereby the range of power, voltage and current are within a band which makes is possible to
determine the rating of each element both from a load flow and a short circuit perspective.
Furthermore, it is also possible at this stage to determine the dynamic behaviour of the power system
and design additional filters for controlling harmonics and/or extra elements for voltage/reactive power
control, if deemed necessary.
Also in this stage all studies required by the grid codes need to be done.
6.8 References
[1] B.H.Bakken, ao, "Stepwise power flow- A new tool to analyse capacity shortage and reserve
requirements" 15th PSCC 2005, Liege, Belgium.
[2] J. Hjerrild ao. "Quasi steady-state time simulations- a powerful tool for evaluation of grid
connection in relation to offshore wind farms", Paper 18, Sixth International Workshop on
Large-scale Integration of Wind Power and Transmission Networks for Offshore Wind Farms,
Delft, the Netherlands, 2006
[3] L.H. Kocewiak, "Harmonics in Large offshore wind farms", PhD. Thesis, Aalborg University,
Denmark, 2012, ISBN 978-87-92846-04-4
[4] CIGRÉ TB 563, "Modelling and Simulation Studies to be performed during the lifecycle of
HVDC Systems", WG B4.38, December 2013.
Page 75
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Connection of offshore WPP via VSC-HVDC to the onshore grid helps overcome some challenges:
For civil engineering: Some major electrical equipment has to be installed under difficult environmental
conditions.
For offshore platform: As much of the module as possible is assembled and pre-tested in a shipyard.
Different possibilities exist for the type of platform chosen; Jacket-top structure, gravity based
structure, self floating/self lifting and float over. Different structures have different advantages and
disadvantages such as the weather window needed for installation, the need for lifting equipment,
material and installation costs.
For weight and size restrictions: The equipment has to be shrunk down to a minimum, using SF6
insulated devices, whenever possible. Attention is paid to the particular protection of the equipment
against the harsh environmental conditions.
Despite of compactness: The module is unique due to its accessibility. Even large pieces of
equipment, such as converter transformers can be changed easily.
The VSC-HVDC represents the ideal power transmission system for such interconnections. It offers
some unique advantages over the conventional HVDC: the design is very compact and synchronous
condensers for voltage support are not necessary.
In this chapter only already built or commercially signed projects are discribed. Neverthless there are a
lot of projects all over the world which are in a planning or design stage. Since many projects are
frequently added to or removed from the planning stage, such projects have been omitted from this
brochure. Additional information about projects under development and in the planning stage may be
found at the homepage of “4C Offshore Limited” (www.4coffshore.com).
Page 76
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
7.2 BorWin1
BorWin1 is the first HVDC project to connect offshore wind. It
connects the first remote offshore wind farm cluster to the
German grid by a 400 MW HVDC Light® transmission system.
Page 77
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
7.3 DolWin1
DolWin1 is an 800 MW HVDC Light® transmission link that
which connects offshore wind farms located in the cluster
DolWin1 in the North Sea to the German grid.
The manufacturer is responsible for system engineering including design, supply and installation of the
offshore converter (including the platform), sea and land cable systems and the onshore converter
station. The land cables are laid underground.
Customer TenneT
Commissioning year 2014
Power rating 800 MW
AC voltage 155 kV offshore
380 kV onshore
DC voltage ± 320 kV
HVDC cable 2x75 km submarine cable
2x90 km underground cable
Connected wind farm Meg Offshore 1 - 2x13 km
Borkum West II - 2x7.5 km
Borkum Riffgrund I 2x11.4 km
Equipment offshore HVDCLight® CTL converter
three-phase transformers
converter reactors
AC cable compensation reactors
Equipment onshore HVDC Light® CTL converter
Three-phase transformers
Converter reactors
Insertion resistor
Type of plant Jacket top offshore platform with HVDCLight®
Onshore substation with HVDCLight®
Location onshore Substation Dörpen, Germany
Location offshore DolWin alpha 75 km offshore – NW of island Norderney
Page 78
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
7.4 BorWin2
For the BorWin2 project, a voltage-sourced converter (VSC)
system is supplied – using HVDC PLUS technology – with a
rating of 800 MW. The wind farms Veja Mate and Global Tech
1 are designed to generate 800 MW and will be connected
through an HVDC PLUS link to shore. The converters are
installed on an offshore platform, where the voltage level
isstepped up from 155 to 300 kV AC and then converted to
DC at the same voltage level. The platform accommodates all
the requisite electrical equipment for the HVDC converter
station, two transformers, four AC cable compensation
reactors and high-voltage gas-insulated switchgears (GIS).
The wind power offshore substation (WIPOS) is designed as a
floating, self-lifting platform. Energy is transmitted via subsea
and land cable to Diele close to Papenburg, where an onshore
converter station reconverts the DC back to AC and feed it
into the 400 kV AC network. The entire transmission link started operation in 2015.
7.5 HelWin1
Page 79
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
7.6 SylWin1
Page 80
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
7.7 DolWin2
Page 81
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
The manufacturer is responsible for system engineering including design, supply and installation of the
offshore converter (including the platform), sea and land cable systems and the onshore converter
station. The land cables will be laid underground, thus minimizing environmental impact.
7.8 HelWin2
Page 82
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Page 83
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
7.9 DolWin3
The DolWin3 MaxSine® HVDC link will connect 900MW
offshore wind farm cluster (known as DolWin) in the North
Sea to the German grid.
Page 84
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
7.10 BorWin3
For the BorWin3 project, a voltage-sourced converter (VSC)
system will be supplied – using HVDC PLUS technology –
with a rating of 900 MW. Two or three wind farms are
designed to generate 900 MW and will be connected through
an HVDC PLUS link to shore. The converter will be installed
on an offshore platform, where the voltage level will be
stepped up and converted to ±320 kV DC. The platform will
accommodate all the requisite electrical equipment for the
HVDC converter station, transformers, AC cable
compensation reactors and high-voltage gas-insulated
switchgears (GIS). The wind power offshore substation will be
designed as a high float over platform. Energy will be
transmitted via subsea and land cable to Emden, where an
onshore converter station will reconvert the DC back to AC
and feed it into the 400 kV AC network. The entire
transmission link is expected to begin operation in 2019.
Page 85
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
The power rating of the converters are designed based on customers’ specifications.
Design choices regarding the HVDC cable connections and the WPP array cables must also included
in these discussions, since they operate in a hostile environment and are typically difficult to install and
repair. A fault on a HVDC cable may lead to an extended outage due to the potentially long mobilising
time in assembling the right repair cable and joints and suitable jointing staff. In addition the required
marine vessels must be mobilised, the weather window must be suitable and any necessary permits
obtained.
Any potential overload capability is therefore driven by the specified design being required to operate
continuously at maximum (AC + DC) current at maximum ambient temperature. If the actual ambient
temperature is lower than the design maximum, then there will be some capability to work at higher
current levels without exceeding the maximum allowable temperature on the IGBTs. However, this TB
Page 86
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
strongly suggests that manufacturers’ advise should be sought regarding specific converter station
overload capabilities during operation under lower ambient temperature conditions. Manufacturers’
inputs shall also be required to help develop algorithms that can take into account the device history in
order to capture potential short time overload capability, without risk. Similiarly, HVDC cables, power
transformers, and DC reactors can be loaded higher than nameplate ratings, subject to pre-defined
cooling conditions.
WTGs can operate with a command for maximum power that comes from a central location, which is
widely applied in existing onshore WPPs to achieve a curtailment function. The maximum power
setting is taken within each WTG as a reference, but the functions that manage mechanical stresses
must be allowed to make small modulations around this reference.
WTGs can also adjust power output based upon voltage and frequency sensed on the ac collector
system. These enable riding through grid faults, and also the governor and/or virtual inertia functions
now provided with modern large WTGs.
This characteristic of WTGs means that the VSC HVDC control system cannot include a power
regulator mode.
In addition, interconnection requirements related to control of real power include active power control,
power ramp rate control, primary and secondary reserves, production set point changes, and unit start-
up and shut-down, Modern WTG technologies can respond rapidly (i.e., 10-20% of rating per second)
to ramp-up and ramp-down commands.
The VSC HVDC connected offshore WPPs provide a number of grid code compliance advantages,
when compared to with AC connected onshore WPPs. The primary advantage is the de-coupling
between the onshore AC transmission system and the offshore WPP system. This brings forward
advantages with regard to WTG fault ride through capability and reactive power requirements at the
point of connection.
With regard to low voltage fault ride through, a VSC HVDC link can sustain through AC faults and
quickly restore active and reactive power values to pre-fault levels. However, a voltage dip at the
onshore inverter will cause reduction in VSC HVDC link capability to transport power, with subsequent
rise in offshore grid voltage. The industry accepted solution is the addition of a DC chopper as part of
the overall VSC HVDC system. The DC chopper will absorb energy out of the HVDC system, during
the fault, allowing quick resumption of power evacuation after fault clearing.
8.2.5 Expandability
There has been much discussion of integrating HVDC-connected offshore WPPs into an HVDC
transmission network, or DC grids, supporting wind energy access to multiple markets. It may be
desirable to allow for this possibility in the design of the VSC-HVDC system. In particular, control
Page 87
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
systems would need expandability to accommodate new functions. The potential for future HVDC grid
interconnection also may play a role in the selection of the nominal DC voltage. For more discussion
on HVDC grids, interested readers are suggested to review related TBs by: WG B4-52 “HVDC Grid
Feasibility Study”, WG B4-56 “Grid codes for HVDC grids”, WG B4-58 “Load Flow Control in Meshed
DC Grids”, WG B4-59 “Control and protection of HVDC grids”, and WG B4-60 “ Designing HVDC grids
for optimal reliability and availability performance”.
It would be worth exploring if the system design can be such that conventional WTG technology, as
would be used for an AC connected onshore plant, can be used for an offshore wind plant. There are
several benefits from this approach, among them are the following:
• Cost minimisation associated with a more competitive market for the WTG supply for the WPP,
where the extensive experience of conventional turbines can be directly applied.
• Attaining high reliability based on experience with an extensive fleet of operating WTGs.
• Realising efficient maintenance based on proven practices applied in operating turbines.
• Inherent ability to ride through grid faults.
Page 88
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
Considerations for AC Collector Systems and Substations associated with HVDC connected Wind
Power Plants” (WG B3.36).
Since there is not sufficient experience in operation of HVDC connected offshore WPPs, it is an
industry accepted practice to rely on VSC HVDC and DC chopper for managing the grid disturbance.
The overall operation and control should be designed to minimize the potential for adverse interactions
between the HVDC system and the WTGs. Some new concepts have been presented in the literature
[1] whereby the rectifier could act like a synchronous machine, absorbing power from the WTGs
without restriction. The rectifier could potentially also act to mimic inverter ac voltage so that during on-
shore grid faults the voltage on the WPP collector system will drop in sympathy, thereby triggering the
low-voltage ride through capability that is now a standard requirement in large AC connected WPPs.
The rectifier also sets frequency on the offshore wind collector system to trigger governor functions
within the individual WTGs to achieve a means of managing real power without full reliance on
communication.
In order to correctly conduct such studies, there is a need to address the issue of detailed model
availability and data interchange. Even when data are fully available, great diligence is required in the
analysis, design, and simulation of these systems. When interaction issues arise, either in the design
analysis stage, or in operation, the means need to be established by which the various parties can
work together to resolve the issues.
Readers are also recommended to use guidelines published by CIGRE WG B4-57 “Guide for the
development of models for HVDC converters in HVDC grids”.
An ever increasing population of wind generation systems has evolved to operate with AC networks
operated at medium voltage. The AC grid is assumed reasonably strong relative to the WPP, and able
to absorb the power fluctuations inherent to wind generation. WTGs are expected to ride through low
Page 89
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
voltage conditions on the ac system and promptly resume operation, while open-circuit conditions on
the grid will cause WTGs to stop. These aspects result in the lowest overall system cost when
integrating power from a large number of WTGs. It is therefore prudent to carefully evaluate a scheme
whereby these basic characteristics are retained.
Existing HVDC systems that interconnect AC grids are operated in a power control mode. This must
be different with a wind generation application to allow power to flow as needed by the wind
generators. The consequence is that in normal operation the rectifier must present a voltage source to
the off-shore WPP, while the inverter must regulate dc voltage.
High-bandwidth control loops are typically involved in both HVDC and WTGs, exposing risks for
unintended adverse consequences such as control instability and excess component stress. Large
disturbances, such as faults, require the control systems of both systems to shift from the normal
strategy of capturing wind energy to one focused on protecting the respective hardware from
excessive duty, while retaining ability to rapidly resume operation following fault clearing.
The inverter terminal of the VSC HVDC system must be designed to manage all types of fault events
on the receiving end, provided the DC voltage is maintained within bound by action of the rectifier and
the DC chopper. There is no reason for a fundamental difference in the inverter requirements when
receiving power from wind compared to other interconnection applications.
It is also recommended to inherently minimize risk of adverse control interactions between WTG’s and
VSC HVDC converter. This is essential for resolving the realities of different vendor, operational, and
regulatory entities involved in the overall system.
Start-up and normal operation should be designed with minimum telecommunication requirements.
This will enhances reliability while minimizing overall cost.
Auxiliary power must also be provided to WTGs for start-up and low-wind conditions.
8.3 Conclusions
The first wave of VSC HVDC connected offshore wind power plants (WPPs) have been launched in
the North Sea, along with other sites around the world. These early WPP projects have been located
130-200 km from the point of common coupling (PCC), thereby making HVDC as the most appropriate
technology to use for power transmission to mainland grids, due to limitations for AC submarine
transmission at such distances. In addition, VSC HVDC technology offers several unique advantages
suitable for such environmentally harsh and difficult applications. A partial list includes:
- Ability to continuously transfer any power level (zero to maximum rating) in both directions,
thereby facilitating WPP start up, and operation at low wind speeds
- Ease of integration with WTG Generators (WTGs) in islanded grids with very low fault current
levels (i.e., no need for synchronous condensers, as would be the case with LCC HVDC
applications)
Page 90
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
- Because the VSC converters are self-commuted, commutation failures will not occur in case of
ac grid disturbances
- Ability to supply the auxiliary power needs of the off-shore WPP when WTGs are not operating
(e.g., due to low wind conditions)
- Feasibility of building compact, partially or fully tested and assembled, converter stations
resulting in lower costs and risks for the off-shore platform
- Ability to use XLPE cables not capable of withstanding voltage reversals, since operating direct
voltage polarity is unchanged and independent of the direction of the power flow. Great care
must be exercised in the design, manufacture, testing, installation and repair of these cables, as
the WPP availability may substantially depend on these cables
This TB has focused on exploring unique aspects of planning, design, and operation of VSC HVDC
connected offshore WPPs. Both steady state and dynamic performance characteristics are examined,
along with discussions on impacts on overall system optimization and potential economic and
maintenance benefits.
Going forward, it is expected that VSC HVDC connected offshore WPP projects will continue to attract
developers’ interests due to combination of environmental (siting selections and approvals), economic
(greater energy yield), and technical (see above list) advantages. There are now even potential
projects where the offshore WPPS are actually being planned on land, instead of an offshore sea
platform (e.g., UK – Ireland Greenwire Project), where guidelines in this TB are equally as applicable.
Finally, Members of the WG B4-55 have identified the following research and development areas to
ensure further progress for future VSC HVDC connected off-shore WPP projects:
- Development of a full set of Standards for offshore and islanded VSC HVDC connected
systems
- Collecting and reporting reliability and availability data, similar to what has been done in WG
B4-04, for operating offshore VSC HVDC connected WPPs
- More active coordination between TSOs and manufacturers
- New publications aimed at sharing reference designs, operating and maintenance experience,
and other technical information necessary to further enhance maturity of this rather young
industry.
- Ensuring industry best practices are followed with respect to the design and installation of the
High Voltage AC collector cables between the WTGs, and also with respect to the HVDC
cables between the WPP and the onshore AC substation.
8.4 Outlook
Despite of their many advantages, current VSC converter technologies suffer from their large size,
resulting in higher costs for offshore platforms. In order to signififcantly reduce costs, two major cost
factors can be addressed:
1. Air insulation should be avoided. Air insulation requires a large platform and complex HVAC
equipment.
2. The converter modules and their controls should be simplified, so that both CapEx and OpEx
can be reduced.
Page 91
HVDC CONNECTION OF OFFSHORE WIND POWER PLANTS
One of the boldest moves to reduce size and complexity is to use diode rectifiers instead of a VSC. A
diode recitifier is a completely passive piece of equipment and the diodes can be encapsulated in
insulation liquids. This will reduce the converter dimensions substancially and makes it robust in view
of harsh environmental impacts.
Figure 8.1: Grid connection approach with series connected diode rectifiers
Figure 8.1. shows a simplified single line diagram of a grid connection approach using diode rectifiers
in series connection [2]. This modular concept allows smaller plattforms, with increased flexibility.
One draw back of using diode rectifiers is that they are not able to control and maintain the offshore
AC grid. But this task can be achieved by the WTGs. State of the art offshore WTGs are typically using
full converters to convert generator frequency to grid frequency. The control algorithms of these
powerfull converters can be adopted to provide the necessary additional features without increasing
WTGs costs.
8.5 Reference
[1] Larsen, E., Drobnjak, G., Elahi, H., Proc. Of Symposium on Transmission Networks for
Offshore Wind Power Plants, Aarhus, Denmark, 25-26 October 2011
[2] Peter Menke, “Major breakthrough in DC grid access for large scale offshore wind farms”,
Proc. Of EWEA Offshore conference, Copenhagen, Denmark, 11-12 March 2015
Page 92