Professional Documents
Culture Documents
610 Offshore Generation Cable Connections (2015)
610 Offshore Generation Cable Connections (2015)
Working Group
B1.40
February 2015
OFFSHORE
GENERATION CABLE
CONNECTIONS
WG B1.40
Members
C. JENSEN, Convenor (DK), T. KVARTS, Secretary (DK),
P. CAVALEIRO (PT), L. R.S. CASALS / E. GUIX (ES), G. DELL’ANNA (IT), W. FRELIN (FR),
H. HEO (KR), F. LESUR (FR), B. MAMPAEY (BE), S. MEIJER (NL), E. OLSEN (NO),
P. O’ROURKE (IE), H. ORTON (CA), R. WILSON (GB), T. WORZYK (SE), R. D. ZHANG (DE)
Corresponding members
X. FENG (CN), O. MATSUNAGA (JP)
Copyright © 2015
Disclaimer notice
“CIGRE gives no warranty or assurance about the contents of this publication, nor does it
accept any responsibility, as to the accuracy or exhaustiveness of the information. All
implied warranties and conditions are excluded to the maximum extent permitted by law”.
ISBN : 978-2-85873-311-8
Offshore Generation Cable Connections
Page 3
Offshore Generation Cable Connections
Page 4
Offshore Generation Cable Connections
Page 5
Offshore Generation Cable Connections
Page 6
Offshore Generation Cable Connections
Page 7
Offshore Generation Cable Connections
Page 8
Offshore Generation Cable Connections
EXECUTIVE SUMMARY
1. INTRODUCTION
In recent years the number and size of installed offshore wind farms have increased rapidly and more and
larger farms are being planned. Other types of offshore generation are expected to come in the near
future, such as tidal and wave energy generation. Submarine cables are and will be an essential part of
this development where they are used as array cables between the generators, as export cables to
connect the offshore generation farms with the onshore transmission grid and even as part of
interconnections between different synchronous systems, countries or price areas.
Because of this expansion of the industry with many new developers, operators and decision makers,
Cigré Study Committee B1 (SC B1) recognised the importance to participate in broadening the
understanding and knowledge of the special challenges related to offshore cable projects. The Technical
Brochure (TB) is a guide for both experienced professionals, who have worked with submarine cables
(design and/or installation) for years, and for engineers with no or limited knowledge in this area. In
addition, people working with consenting issues, authorities, consultants, investors, insurance companies
and other stakeholders will benefit from the overview in this TB regarding challenges and possibilities in
offshore cable projects.
2. SCOPE
The scope of work presented in this technical brochure includes the following main items:
• Initial studies and consenting process
• Choice of HVAC or HVDC technology
• Submarine cable characteristics and cable rating
• Cable installation
• Cable service and maintenance
• Export cables and array cables
• Dynamic cables for floating generation or platforms
Above listed topics regarding submarine cables are treated, so the document is a comprehensive guide to
cables for offshore generation and submarine cables generally. Many subjects are covered at a general
level, and if the reader wants to go into detail, there are frequent references to other TBs.
Interconnections between different countries, synchronous systems or price areas and eventually future
offshore grid solutions can be treated as HVAC or HVDC export cables.
Page 9
Offshore Generation Cable Connections
Chapter 2 contains definitions of abbreviations and terms, which are used in the TB or in the literature
about submarine cables and offshore work.
Chapter 3 describes the initial studies and surveys which should be performed in an offshore cable
project. These are often necessary when planning the cable routes and preparing the consenting
process. Compared with onshore activities the offshore work is much more complicated. The basis in the
discussion with authorities, with cable manufacturers and installation companies is the charts and
offshore surveys of the possible cable routes.
Authorities often require that the sea bed conditions are studied and documented in order to assess the
environmental impact. The environmental impact should be studied related to installation work. Often,
better knowledge results in “better conditions” attached to the permission. That is why surveys are
important in the first stage.
Prior to installation of submarine cables it is very important that there is a thorough knowledge of the
seabed conditions, e.g. water depth, current, sediment transport, wrecks and other assets like cables and
pipes. To protect the cables during their whole life time, they are normally buried into the seabed. The
seabed and the soil conditions can be found through geophysical and geotechnical surveys and they may
determine the burial method. The burial depth is dependent of the soil conditions and the type of threats
to the cable.
Chapter 4 covers the overall system design, where different topologies are discussed. One of the
important choices to make is the degree of redundancy. How many connections from the offshore
substation shall be made to the connection point onshore? What type of connections shall be in the array
grid? What is the right voltage level and what are the losses in the different solutions? The choice
between AC and DC connection is discussed in this chapter.
The power transmission in export cables from offshore wind farms is very fluctuating, because the
production follows the fluctuating wind speed. In order not to design the cables larger than necessary,
some guidelines are given, expressing how to translate an expected wind load into a load profile for the
submarine cable. The load profile can be used as a basis for rating calculation and used in the cable
design.
Chapter 5 discusses the submarine cable design; in particular different types of conductors, insulation
material, screen etc. The function of the different layers is explained.
Submarine cables deviate from land cables in more ways. The submarine cables are normally placed in
salt water for their entire life time. AC submarine cables are normally three-core cables, where land
cables are single-core cables. The submarine cables may be subject to relatively large mechanical forces
during cable laying and possible later repair – depending on water depth. The submarine cables must be
designed to withstand these impacts.
In this TB it is shown how MVAC, HVAC or HVDC submarine cables can be designed. A number of
examples are included and some general recommendations given. The objective is not to guide the cable
designer, but to guide the purchaser, consultant etc. and give a better understanding of what to take into
account in the design phase.
In Chapter 6 the cable installation is discussed. This chapter covers the planning process, the
engineering of the installation, the operational management and reporting and a description of cable
laying vessels and equipment.
Page 10
Offshore Generation Cable Connections
When assets are installed offshore, the costs are significantly higher compared to onshore installation
and the repair cost in case of failure can be very high. Therefore it is very important that all work is well
prepared and follows best practice. Procedures for the different type of work should be agreed before
starting installation or maintenance. The TB does not describe specific procedures, but it draws attention
to the actions and procedures that should be made.
Chapter 7 is about testing of submarine cable systems. This chapter gives an understanding and an
overview of tests relevant for submarine cables and makes references to other TBs from Cigré and
international standards.
Chapter 8 covers the maintenance of submarine cable systems. Offshore installations are in a very
severe environment and it might be necessary to make surveys on a regular basis to find out, if the
submarine cable and its accessories are in a good condition and e.g. still at the required burial depth.
Terminations and other equipment above water can be checked with conventional methods, but cables
buried into the seabed need special equipment.
Chapter 9 deals with submarine cables for offshore generation other than offshore wind turbines in
shallow water. There is focus on floating generation which demands the use of dynamic cables. Floating
generation can be wind, wave or tide. Special mechanical requirements to dynamic cables are discussed
in this chapter.
Chapter 10 is a summary of information that should be provided to companies offering offshore surveys
or companies offering delivery, installation or burial of submarine cables. The chapter does not give a
complete list of all possible requirements or all necessary information, but focus on the most basic
decisions and information to be provided in connection with tender processes related to this type of
offshore work.
Chapter 12 is the bibliography, which contains literature covering more aspects than can be covered in
this brochure. In the different chapters of the TB there are references to the papers and reports
mentioned in the first section of the bibliography. Other papers, which are mentioned in the second
section of the bibliography, are for further reading.
Chapter 13 describes relevant examples and cases about offshore surveys and submarine cable
connections to wind farms.
Page 11
Offshore Generation Cable Connections
4. CONCLUSIONS
The technical brochure gives an overview of the main issues related to cable projects for connecting
offshore power generation. There is an introduction to geophysical and geotechnical surveys, which are
of great importance for such projects. System design and cable design are basic elements in offshore
generation projects. Installation and maintenance are important to understand, to reduce risks and costs
during the engineering phase. The TB has focused on offshore wind farms, but the principles can also be
applied to any submarine cable connection. Also, there is a separate chapter describing dynamic cables,
which are relevant for floating applications.
Besides the technical descriptions, many illustrations and photos have been included to make the
technical brochure easy to read and understand.
Page 12
Offshore Generation Cable Connections
1 INTRODUCTION
1.1 Terms of reference
Cigré Study Committee B1 (Insulated Cables) decided in September 2011 to launch a working group
(WG B1.40) with the title “Offshore Generation Cable Connections”. The Terms of Reference for the
working group is shown below:
Background :
Today a lot of offshore wind farms have been built or are under construction - and even more farms are
already planned. Wind farms have got the main focus, but also cable connections to other types of
offshore generations will come. So at this moment there are already gathered a lot of experiences about
the cables for grid connection, and a lot of that experience could be shared in a Cigré Technical
Brochure(TB) to the common benefit of the entire industry.
For a good part of the offshore projects the companies responsible for the grid connection (TSOs, turnkey
park builders etc.) are first time buyers and do not have experience in purchasing submarine cable, let
alone submarine cables for offshore generation, and some guidance should therefore be appreciated.
Also for the manufacturers mistakes could be avoided with a common knowledge base, and the benefit of
having a well-informed customer is always evident.
There is a need for guidance for asset owners, TSOs, turnkey park builders, cable manufacturers etc.
about relevant studies and surveys to get permission from the authorities, the choices between
technological solutions, the cable design and installation methods for cable connections to offshore
generations.
Scope :
All topics shall be treated so the document can be a comprehensive guide to cables for offshore
generation and interconnection. A lot of the subject can be covered by references to other works, but
shall be mentioned, given the very different background of the readers. The TB covers the following:
1. Initial studies for permission, choice of technology, submarine cable characteristics, cable rating,
installation, service and maintenance
2. Export cables, inter array cables and interconnections
3. Medium and high voltage AC cables
4. HVDC export cables
5. Dynamic cables for floating generation or platforms shall be mentioned
The TB covers the following headings Technical and Strategic issues identified by Cigré as important:
Technical issues:
Increase of right of way capacity and use of overhead, underground and subsea infrastructure, and its
consequence on the technical performance and reliability of the network.
An increasing need for keeping Stakeholders aware of the technical and commercial consequences and
keeping them engaged during the development of the network of the future.
Strategic direction:
The electrical power system of the future
Page 13
Offshore Generation Cable Connections
The brochure is written as a guide for people who are interested in cable connections to offshore wind
farms or other type of offshore generation. The internal cables between the generators (array cables) are
also discussed in the brochure.
The guide can be used as a general guide about submarine cables. The focus in the brochure is how to
handle submarine cables related to offshore wind farms, but the same principles and procedures can be
used for submarine cables for other types of generation. Submarine cables for floating platforms and
generators have their own chapter. These dynamic cables are exposed to high mechanical stresses and
have to fulfil special requirements, which are not generally applicable for “ordinary” static submarine
cables.
Interconnectors, which can be submarine cables in between different countries, between offshore
platfoms or ordinary offshore transmission lines, are not discussed as a specific issue. Interconnectors
can be made with either HVAC or HVDC cables. These cables are generally discussed as export cables
from offshore platforms.
There may be different terms covering the same subject. For example wind turbine and wind generator
are regarded as synonymous. In the same way, the term offshore platform is synonymous with OHVS
(offshore high voltage substation) and offshore substation platform.
The guide can not cover all details, however in this brochure it is possible to get a first knowledge of main
subjects relating to submarine cables – including the necessary offshore surveys and installation issues.
If more details are needed, references to other technical brochures from Cigré or other reports are
mentioned.
WG B1.39 is preparing a similar report, Onshore Generation Cable Connections, which also may be of
general interest to the reader.
WG B4.55 is preparing a report, HVDC connection of offshore wind power plants, which considers system
aspects e.g. voltages, frequencies, protection etc.
Other companies and associations have made similar reports on the same subjects. There may be
relevant information in these reports, which can be found in the bibliography (Chapter 12).
Safety and insurance issues are very important, nevertheless, these topics are not part of the scope, but
may be mentioned in this brochure. For further investigations other reports may be consulted.
Chapter 2 contains definitions of abbreviations and terms, which are used in this brochure or in the
literature about submarine cables and offshore work. Generally the abbreviations are explained or written
in full text, so it is not necessary to look in the explanation chapter so often. The list can also be used to
understand abbreviations found in other brochures, reports etc.
Chapter 3 discusses Initial Studies, Surveys and Permissions and details planning of cable routes
including the possible surveys and consenting process.
Page 14
Offshore Generation Cable Connections
Chapter 4 discusses the System Design, where different topologies are evaluated and the choice
between AC and DC connection is considered.
Chapter 5 discusses the Cable Design, detailing the construction of submarine cables with different types
of conductors, insulation material, screen etc. and the function of the different layers are explained.
Chapter 6 discusses the Cable Installation. This chapter covers the planning process, the engineering of
the installation, the operational management and reporting and a description of cable laying vessels and
equipment.
Chapter 7 discusses the Testing of submarine cable systems. This chapter gives an understanding and
an overview of tests relevant for submarine cables and makes references to other technical brochures
from Cigré and international standards.
Chapter 8 discusses the Maintenance of submarine cable systems. Offshore installations are in a very
severe environment and it is recommended to make surveys on a regular basis to find out, if the
submarine cable and its accessories are in a good condition.
Chapter 9 discusses Submarine cables for other types of generation other than offshore wind. There is
focus on floating platforms or generators which demand the use of dynamic cables. Floating generators
can be wind, wave or tide generators. Special mechanical requirements to dynamic cables are discussed
in this chapter.
Chapter 10 discusses, Guidance to Tenders, This is a summery of information that a cable-client should
provide to companies offering offshore surveys, delivery or installation of submarine cables. The chapter
doesn’t give a complete list of all possible requirements or all necessary information but focus on the
most basic decisions and information to be provided in connection with tender processes related to this
type of offshore work.
Chapter 12 is the Bibliography, which contains literature covering more aspects than can be covered in
this brochure. In the different chapters of this brochure there are references to the papers and reports
mentioned in the first section of the Bibliography. Other papers, which are mentioned in the second
section of the Bibliography, are for further reading.
Chapter 13, Appendices, has relevant examples and cases about offshore surveys and submarine cable
connections to wind farms.
Page 15
Offshore Generation Cable Connections
Subject/abbreviation Definition
ADCP Acoustic Doppler Current Profiler. Similar to sonar, a method to record the
current strength in the water column and to measure water current
velocities.
After Installation Test Tests made to demonstrate the integrity of the cable system as installed.
AIS Air Insulated Switchgear. Switchgear in open air - often used in HV and
EHV substations on land and in DC stations.
Array cable A cable used to collect the power from the individual offshore turbines or
connect the turbines with an offshore HVAC substation.
Connection Point The Connection Point is the point where the grid codes apply. This can be
at the onshore grid, at the individual turbines, or at an offshore substation.
This point is also called the Point of Common Coupling (PCC) or Point of
Connection.
Page 16
Offshore Generation Cable Connections
DCR Dynamic Cable Rating. Same as RTTR (Real Time Thermal Rating).
DDV Drop Down Video – used for visual inspection of seabed and habitats.
DoB Depth of Burial. Vertical distance from upper surface of installed cable to
mean seabed level.
DoL Depth of Lay. Vertical distance from bottom of installed cable to mean
seabed level.
DPR Daily Progress Report. Report issued every twenty four hours detailing
progress and significant events and proposed actions for next period.
DWA Double Wire Armour. Cable protection by two layers of wires to improve the
mechanical performance against special external constraints, torsion,
lateral or pulling efforts.
EHV Extra High Voltage. IEC considers a range II for insulation levels from
220 kV (Um = 245 kV).
EEZ Exclusive Economic Zone. A sea zone (200 nautical miles from the coastal
baseline) prescribed by UNCLOS (United Nations Convention on the Law
of the Sea) relative to special rights of a state over the exploration and use
of marine resources, including energy production from water and wind.
Page 17
Offshore Generation Cable Connections
Export cable A cable connecting an offshore substation to the grid (onshore or offshore),
to export the renewable energy. In case there is no offshore platform, the
cable(s) used for transmission of collected power from the offshore
generation park to shore, is (are) also export cable(s).
Failure The termination of the ability of an item to perform a required function. After
failure, the item has a fault. "Failure" is an event, as distinguished from
"fault", which is a state.
Grid Code The Grid Code establishes the rules governing the operation, maintenance
and expansion of the transmission system and sets out the procedures for
governing the actions of all transmission system users.
Handover Test Test made when cable responsibility changes hands, to help determine, if
the cable has been damaged in the previous process/handling.
HDPE High Density Polyethylene. Plastic material often used for cable ducts, e.g.
those installed by HDD under sea defences.
HPFF High Pressure Fluid Filled (Cable). HV cable system with an insulation
system of paper impregnated with low viscosity fluid under high pressure
Page 18
Offshore Generation Cable Connections
HVDC High Voltage Direct Current. Allows the power transmission on long
distance, with lower losses, between unsynchronized AC transmission
systems.
KP Kilometre Point. Distance along the cable route. KP 0.00 normally being at
the transition joint or offshore termination point of the cable.
LAT Lowest Astronomical Tide. Height of the sea water at the lowest possible
theoretical tide, predicted under average meteorological conditions, used to
define chart datums.
LIDAR Light Detection And Ranging, normally used for laser surveying on shore,
however, can be used for metrological observations from a fixed location.
MI (MIND) Mass Impregnated (Non Draining) (HVDC cables). HVDC cables with an
insulation system of paper or PPL impregnated with high viscosity oil.
Multi Terminal Multi-terminal HVDC links, connecting more than two points.
Systems
Page 19
Offshore Generation Cable Connections
Offshore substation Substation designed for the purpose of transforming the voltage from the
collection voltage to a suitable transmission voltage for efficiently exporting
the power to the onshore network.
OTDR Optical Time Domain Reflectometry. Test device for identifying and locating
deficiencies in an optical fibre.
OWP Offshore Wind Park – the same as Offshore Wind Farm (OWF).
PLGR Pre Lay Grapnel Run. Method of clearing seabed surface of debris,
particularly cables and wires not detected during survey, from full length of
the cable route immediately prior to cable laying operations.
PPL Polypropylene Paper Laminate. This material has been developed for MI
cable application in order to increase the maximum transmissible power of
about 30 % with respect to the traditional paper insulated paper, due to the
maximum conductor working temperature of up to 80-85 °C.
Routine test Tests made by the manufacturer on all manufactured components (length
of cable or accessory) to check that the component meets the specified
requirements.
RPL Route Position List – table of coordinates for significant events or features
of a cable system, e.g. start and finish points, alterations of course,
geographical limits, and other information such as water depths.
Page 20
Offshore Generation Cable Connections
SCFF Self Contained Fluid Filled (Cable). HV cable system with an insulation
system of paper impregnated with low viscosity fluid
SVC Static Var Compensator. Non rotating device providing reactive power on
AC networks.
SWA Single Wire Armour. Cable protection by one layer of wires to improve the
mechanical performance against external constraints, lateral or pulling
efforts.
TDM Touch Down Monitoring, real time monitoring by video or other means of
cable touch down on seabed.
Type test Tests made before supplying on a general commercial basis a type of
submarine cable system, in order to demonstrate satisfactory performance
characteristics to meet the intended application.
UXO Un-Exploded Ordnance. Explosive weapons (e.g. bombs or mines) that did
not explode and still present a risk of detonation, potentially decades after
their presumed use. (Sometimes met with acronym UO).
Vessel A vehicle for sea transportation including: barge, boat, ship, life boat, rigid
inflatable boat or pontoon.
Page 21
Offshore Generation Cable Connections
VSC Voltage-Source Converters – VSC is a converter that does not change the
voltage polarity of the cable system when the direction of power flow is
reversed.
Page 22
Offshore Generation Cable Connections
Therefore, it is in the following presupposed that the position of the offshore generation site is established
and only the process of how to develop the routes for the cable connections in between the generators
and the export cable to shore is described. The solution for the overall technical solution and system
design will also be established in parallel, since different solutions may have a significant impact on the
type and number of cable connections that should be studied. The system design is covered in Chapter 4.
The initial studies, surveys and permissions are for both the array cables and the submarine export
cables. In this section the focus is on the export cable routes, but the same considerations may be made
for every submarine cable route.
This chapter describes the various surveys currently available and possible permissions that may be
required. The chapter is divided into 5 sections:
1. Desktop studies
2. Pre-investigations
3. Stakeholders and the public
4. General installation methods
5. Consenting (permissions) process
In Appendix A an example shows how a cable route can be selected based on studies and surveys,
which are described in this chapter.
The main objective of the initial work is to gather sufficient data to make an overall and informed
assessment of which cable routes are the best and to obtain so much knowledge about the technical and
environmental issues, that it is possible to inform the authorities sufficiently to get the permits for the
offshore project.
As a side effect, a lot of the gathered information from the initial surveys may be used as input for detailed
design and construction either directly or with some coordination at little extra cost. Furthermore, the
cable route survey data are important to pass on to the operational phase of the cable.
It may be possible during the initial phase to take an overall look at the possibilities, challenges, risks and
costs. Some of the options may be skipped at this early stage due to them not being feasible, this can
save money and time.
Normally an offshore project involves onshore work packages to enable transportation of energy, these
onshore packages have to be taken into account in the assessment and the consenting process, and
particularly as the onshore cable routing will heavily influence the location of the subsea cable landfall
location. This can be a critical pinch point both for the consenting process and technically.
Page 23
Offshore Generation Cable Connections
these assets are not registered; therefore it is prudent to request what information they currently have. If
there is a knowledge gap, then it may need to be filled later on by survey work.
It is important that all parties involved in an offshore project agree on which geographical coordinate
system is used.
Survey routes
Some of the most basic charts available have nominal depths of the sea floor in relation to Lowest
Astronomical Tide (LAT); the lowest level that can be expected to occur under average meteorological
conditions but under any combination of astronomical conditions, this is referenced to a local harbour or
Datum point. Using the indicative depths and contours, the end location and the possible start locations; a
series of possible route corridors may be determined.
A risk assessment should be done for each route and used in the weighting factor for the determination of
the final route; the Automatic Identification System (AIS) can assist in this manner as an inexpensive and
simple source of historical data on shipping traffic, fishing activities, anchoring practice and other marine
activities. .
Page 24
Offshore Generation Cable Connections
The degree of mobility will determine the need for the number of surveys to be completed immediately
before the start of construction and during its lifetime to account for any change in sea-bed levels or
features. Seabed mobility can lead to cables being buried deeper with possible impact on cable rating or
to free spans where cable can be damaged by anchors or by strumming. The types of sea bed movement
are discussed below:
Sediment transport
Sediment transport is caused by a number of factors, namely the soil conditions and the marine current. If
it is a known area for high current then it is recommended that a survey be commissioned to assess the
impact of installing cables.
Man-made trenches in line with the current flow, may not backfill naturally, consideration of this issue
should be taken when trenching in parallel with the current.
Changes in the depth of local seabed sediments can result from natural processes (e.g. sand wave
migration; incipient erosion/accretion) and/or anthropogenic activities (e.g. dredging) and remain a
primary concern for marine developments.
At a local scale, and over short to medium time-scales (1 – 10 years), the primary risks concern the
vertical variability of the seabed, and its response to moderate and extreme events. In simple terms
changes in seabed elevation will occur wherever there is a local imbalance between sediment supplied
and sediment removed. The risk can be either an increase or decrease in level and the degree of concern
or tolerance to such change would depend on the asset at risk. A risk of bed level variation exists if:
• the hydrodynamic conditions are sufficient to mobilise or transport the regionally available
sediment; and,
• there is a significant thickness of mobile sediment present (which might be eroded or develop
mobile bedforms); or,
• a significant volume of mobile sediment is present outside of the immediate area and a sediment
transport pathway exists to connect it to the site (which might then accumulate).
Further, in complex areas of mobile sediments (e.g. sand waves) it is necessary to consider both
horizontal and vertical changes in seabed elevation attributable to the migration of bedforms. At larger
temporal and spatial scales, the risk is associated with long-term changes in sediment supply due to
natural changes (e.g. sea level changes; increase in magnitude and frequency of storms) or to
anthropogenic impacts.
With the increasing scale of development within the seas, there is a pressing need for better tools to
manage sediment mobility and sediment transport risks associated with developments through the project
life cycle.
At present, approaches used to predict changes in seabed sediment depth are limited by the availability,
accuracy and interpretation of disparate geological, geophysical, bathymetric and metocean information.
This can make project design and site selection problematic and can add further risks and costs to
activities and assets in operational phases of project life cycles.
Page 25
Offshore Generation Cable Connections
Typical approaches to determine the degree of seabed mobility and sediment transport include:
• Desk study based on empirical seabed mobility and sediment transport calculations. This requires
an understanding of the local area including the hydrodynamic regime, sediment characteristics,
water depths etc.
• Bedform analysis to determine rates and magnitude of bed level change. This involves comparing
bathymetric surveys to identify bedform (such as sand wave) migration rates and behaviour of
seabed features such as large sandbanks over time. A simple analysis of bedform asymmetry
provides a good high-level indicator of the net direction of sediment transport, noting that this
requires relatively high resolution bathymetry data in order to distinguish individual bedforms.
• Two-dimensional modelling of bedload sediment transport. This requires information on the
hydrodynamic regime, seabed bathymetry and sediment characteristics. The outputs from this
modelling are typically vector plots showing transport direction and magnitude, which is presented
as sediment flux.
The sediment transport regime and seabed evolution is more complex to quantify than for example the
tidal regime as there are seldom any measured data against which models can be calibrated or to
validate desk based assessments. However an understanding of the sedimentary regime is fundamental
for submarine cable developments.
The danger from the sea bed changing is the possible deep burial (accretion; where sediment has
accrued over the cable to bury it under a large sand wave or an underwater land slide) or scour/erosion
(where the sediment has been removed and exposes the cable and allows the cable to strum/oscillate).
The information determined from the study has input into the Burial Assessment Study, see Section 6.2.5
Seismic activities
If a known cause for seismic activity is within the vicinity of the possible asset, then a risk assessment
should be made to determine the risks and mitigations and subsequent costs per km. The typical
submarine cable risks associated with seismic activity are;
• Tension – as tectonic plates move apart
• Slack, strumming lines and crushing – as tectonic plates move together
• Embrittlement – due to high levels of movement or excess heat
It is not feasible to protect against land movement to an excessive degree or major events, like a
Tsunami, but there are some mitigation techniques such as laying a ‘bight’ (extra length) of cable on the
sea bed where tectonic plates slide against one another or tectonic plates move apart from one another.
Crossing of specific areas with habitats or mating grounds for endangered fauna or marine life should be
considered carefully since it could be difficult to get permission to cross these areas during installation or
for future repairs. In general permissions to access an area should always cover future repairs if possible.
Surveys are typically also assessed by archaeologists in regards to archaeological issues. Already known
historical findings can often be avoided, and knowledge of possible interesting historical findings can be
taken into account in the assessment of different cable routes
Page 26
Offshore Generation Cable Connections
There may also be some local concerns and demands that must be met and which sometimes excludes
some of the solutions.
It is suggested that the most likely restrictions are applied to the initial planning and that discussion with
the local government body can confirm which restrictions are to be applied to the individual landfall
options.
Shipping analysis
Seismic activities
Sediment transport
Environmental issues
Landfall restrictions
3.2 Pre-investigations
When the preliminary assessment has been carried out, the more detailed surveys and studies shall be
made. These surveys are physical in nature and often involve vessels and personnel on site taking
measurements.
In the following subsections the different possible surveys are described at a detail level that should make
it possible to assess which of them are relevant in specific situations. See also Appendix C - Geophysical
surveys.
The seabed profile, water depth, soil conditions etc. are important to know in the design process but also
at a very early stage, in order to find the best cable route.
The surveys mentioned in this section are a very wide-ranging list from which it is recommended to
choose carefully only the surveys relevant for the specific project.
When looking at cable corridors (be it Export or Array), it is typical for the corridor to be consented at
500 m per cable, but this can change due to seabed conditions and negotiations; see also ICPC
Recommendation No. 9 [3.1], e.g. two export cables following the same path would have a corridor of
1000 m. This corridor width is used to allow micro-site engineering when discovering wrecks, UXOs,
boulders etc.
Page 27
Offshore Generation Cable Connections
The number of surveys during the lifetime of the cable system shall be determined from the seabed
mobility and the risk to the cable. The original survey can be used as a fingerprint of the initial site
conditions.
The geophysical and geotechnical surveys must be carried out by vessels that are purposely designed for
the job. The specific survey robustness to offshore conditions and requirements of 24 hr operations with
onboard data processing may lead to minimum requirements to the vessel dimensions. The equipment
itself to be used for the sensing and recording of data is compact and small and can normally be
transported in a pallet sized box.
In the planning and construction phase geophysical surveys are used for providing seabed information to
support the consent processing, the EIA (Environmental Impact Assessment), the design of the cable
route and the cable burial and to document the conditions for the cable installation contractor.
The geophysical survey is together with the geotechnical survey (see Section 3.2.2) a cable route survey.
This activity is carried out in a corridor around one or multiple cable route alternatives. The width of the
corridor should be designed to allow for rerouting of the cables in areas of natural protected reefs,
archaeological findings, potential unexploded ordnances (UXO’s), wrecks and other obstructions. In
recent developments the width of corridors for cable route surveys has been 200m – 1000m.
The geophysical surveys are made from vessels sailing along the cable route with said devices that
make it possible to check different characteristics related to the seabed.
Some surveys can – where the water depth is shallow – be supplemented by airborne methods as LIDAR
(Light Detection And Ranging).
Some of the surveys can be repeated during the lifetime of the cable system and can in this perspective
be seen as a fingerprint of the initial site conditions.
The vessel makes ready and departs for the location, the equipment is lowered into the water, this is
normally in the form of a small Remotely Operated Vehicle (ROV) or torpedo shaped device. The vessel
travels at a set speed (typically 3 to 6 knots), normally determined by the sensor capabilities in a pattern
to collect the most data. Once collected the data is analysed and collated to form a report on the survey
data.
Each method has its own unique characteristics. Depending on the specific purpose of the survey the
following methods should be considered.
• Bathymetry survey – to determine water depths and more importantly gradients which may affect
cable burial. Bathymetry is a basic contour line of the sea bed as shown on charts or scanned.
This is a true reflection of the sea bed, not a hydrographic representation which only indicates
contours to allow safe passage.
• Side scan sonar – to identify and characterise seabed features which may influence routing. Side
scanning sonar uses either 1 or 2 sonar fish.
• Magnetometer/gradiometer – to identify ferrous targets (possible unexploded ordnance).
Magnetometer requires 1 sensor being towed. A gradiometer requires two sensors being towed
with a fixed distance between them.
• Sub bottom profile – to characterise sub-seabed (top 5m) to determine burial strategy. Sub-
bottom profilers require an acoustic source that can operate at a variety of frequencies dependant
on penetration required of the sea bed, and the sea bed material.
• ADCP (Acoustic Doppler Current Profiler) – records current strength in the water column.
Page 28
Offshore Generation Cable Connections
Bathymetry survey
The purpose is to determine the seabed elevation and gradients of various slopes which may affect cable
burial.
The modern method for determining the bathymetric survey is sonar with a multi-beam echo-sounding
instrument. This sends an acoustic note from the hull of the vessel. The time to travel to the sea bed and
return is recorded using a ‘speed of flight’ or ‘velocity of propagation’ the water depth can be determined
using the time response of the acoustic noise.
There are a number of ways to interpret the data; the most common is the pseudo-colour image, with
contours and soundings, See Figure 3-1. Others are pseudo-colour image and processed data image.
Page 29
Offshore Generation Cable Connections
Page 30
Offshore Generation Cable Connections
Sub bottom profiling is carried out by use of high frequency seismic instruments such as a Pinger or a
Chirp. The seismic instrument emits an accosting signal that penetrates the shallow seabed and the soil
stratification can be derived from the measured response signal.
The sub bottom profile needs to be correlated with a geotechnical survey by either Cone Penetrometer
Test (CPT) or core samples. There are several methods to determine the sub-bottom profile. The images
below relate to the instrument.
Sample results are seen in Figure 3-5 and Figure 3-6. The results are used as input to the Burial
Assessment Study (see Section 6.2.5). Furthermore archaeologists and environmental studies relies on
the results of the sub bottom profiling.
The sub bottom profile (Figure 3-7) is an interpretation of the geophysical and geotechnical surveys. The
profile is important to the installation – especially the burial of the cable. It may be difficult to obtain a
reliable sub bottom profile. The layers must be in accordance with the layers found in the geotechnical
surveys (e.g. vibrocore). Even reliable sub bottom profiles must be used with care.
Page 31
Offshore Generation Cable Connections
Seismic refraction
The seismic refraction survey will provide information on the depth and quality of the bedrock and the
overburden. Seismic refraction is a geophysical principle which uses a seismograph and multiple
geophone spacing apart at a fixed distance in an array. The method utilizes the refraction of seismic
waves on geologic layers and rock/soil units in order to characterize the subsurface geologic conditions,
see Figure 3-8; the data can then be interpreted as seen in Figure 3-9.
FIGURE 3-9 SEISMIC REFRACTION INTERPRETATION SHOWING SAND (RED) AND ROCK (BLUE). 1.8 AND 3.7 IS
SEISMIC VELOCITY IN KM/S
Magnetometer / Gradiometer
The purpose is to identify ferrous targets (possible unexploded ordnance, archaeology, pipelines, volcanic
rocks and obstructions). A Magnetometer is a 1D device, only measuring magnitude of a ferrous
Page 32
Offshore Generation Cable Connections
response. A Gradiometer uses several devices in a fixed configuration in order to determine a 2D image
of the site.
The ADCP works by transmitting sound bursts into the water. Particles carried by the water currents
scatter the sound back to the unit, which listens for these echoes. As echoes return from shallower
portions of the water column, the unit assigns different water depths to the corresponding parts of the
echo record. This allows a formation of the vertical profiles of water. Motion of water particles relative to
the unit causes the echo to change in frequency. The system measures this change, known as the
Doppler shift, as a function of depth to obtain water velocity for a number of depths throughout the water
column.
The raw data is processed and the output is typically a table of grain size and movement
rate/displacement over a time period.
The DDV works by lowering a video camera on either a tether, umbilical or an ROV and tracking the
vessel along the route of inspection. The camera records information. This method is impractical for sites
with poor visibility. This is very useful where there are sites of special scientific interest or a protected
area e.g. reef zones. See Figure 3-12 and Figure 3-13.
Page 33
Offshore Generation Cable Connections
Grab Samples
The purpose is to correlate the results from the side scan sonar with samples from the sea bed to ensure
that the measurements are interpreted correctly. Normally the investigation is carried out using a Van
Veen grapple sample. Whilst intrusive in nature it is considered non-intrusive.
This sample method is used in context as a geophysical as well as a geotechnical method to determine
the seabed characteristics. An image of a Van Veen grab can be seen in Figure 3-14.
Page 34
Offshore Generation Cable Connections
After the geophysical surveys are made and assessed together with desktop studies and other relevant
information, those cable routes that are still relevant for the offshore project can be studied in more detail.
The geotechnical surveys are often more expensive on a day rate basis, but the geophysical surveys are
used to provide target points/areas for the geotechnical investigations.
Geotechnical investigations are planned to support the design of the cable burial, the Burial Assessment
Study (Section 6.2.5) and to provide in-situ information about the seabed surface. The conditions can
vary along the route, and different routes can have different soil conditions. The threats from anchors and
trawling gear, local requirements etc. must be taken into account together with the soil strength to find the
optimal burial depth.
The cable design must meet the requirements for the cable rating. This is directly dependent on the
thermal conditions of the surroundings. Therefore it is important to get knowledge of the thermal
conditions of the seabed at an early stage, so this is known before the cable is designed.
The significant difference between CPTs and vibrocores is that vibrocores do not record pore pressure
values. Also by means of its action of vibrating into and removing the sample from the substrate, a
vibrocore may alter (slightly) the mechanic value of the sample. While vibrocores provide essential
information such as soil composition, plasticity, shear strength and thermal resistivity it is often good
practice to cross reference the shear strength results with CPT data. On principle, the vibrocore data
should be laboratory tested and not site-tested as site testing instruments can be less accurate.
Page 35
Offshore Generation Cable Connections
Two samples may be obtained from each core location. One sample is for examination on the survey
vessel in order to help planning and monitoring the survey and its performance. The other sample is for
analysis in a laboratory.
Marine archaeology
The assessment of marine archaeological interest is of high importance in most countries and involves
the expertise from national and local museum, and the authority on cultural issues.
The preliminary assessment is based on the existing knowledge (desktop study). Then the geophysical
survey is essential to the assessment of the likelihood of marine archaeological interest in the proposed
cable routes. If marine archaeological interests are suspected in the area of the cable installation field
investigations are undertaken. They typically include the use of video surveys and diver inspections. It
might however be more efficient to simply alter the cable route in order to avoid marine archaeological
interest if possible.
The data and charts produced from the geophysical survey are crucial for the screening and scoping of
the environmental investigation needed with regard to benthic fauna and flora. The results of the
geophysical survey, including results of the seabed characterisation studies (sediment analysis) are used
to determine to what extent and in which areas of the proposed cable routes, the following environmental
investigations are needed:
• Using satellite imagery to identify certain structures of marine biological importance on the
seabed. This could for example be reefs, such as bubble-reef structures or areas with
macrophytes. From satellite photos it is possible to predict possible occurrence of aquatic
vegetation.
Page 36
Offshore Generation Cable Connections
• In areas known to contain such marine structures, it can be valuable to include the satellite
photos in the desktop study and use the information in the planning of the route, before the
geophysical survey is undertaken.
• Grab samples for the seabed for identification and statistics on benthic flora and fauna.
• Video surveys of the seabed to identify structures such as reefs.
• Diving to identify structure such as reefs and collect fauna/flora for species identification and
statistics.
Where possible species on a protection list may be present on a cable route, the Drop Down Video can
provide the evidence that the species are even present within the area of concern.
The landfall is often seen to be constructed using a Horizontal Directional Drilling (HDD). It is crucial to
the success of the HDD installation that a site investigation program is carefully adapted to the geometry
of the HDD (depth, length, location of entry and exit points) and a prior knowledge of the ground
conditions. Especially since HDD near shore areas with fluidised soils can be more challenging than
normal onshore HDDs.
Also other methods can be used to enter the landfall. Instead of drilling a pipe from the shore out into the
sea bottom it is in some situations possible to make a trench with a backhoe and bury the pipe in an
ordinary way. In other cases it is possible to pull the submarine cable in an open trench at the
beach/shore without using a pipe as protection. The surveys shall help to find the optimal method. On the
other hand, each method has also certain surveys required in order to install the cables correctly.
Page 37
Offshore Generation Cable Connections
Bathymetric survey
Magnetometer
Geophysical
ADCP
Surveys
DDV
Grab samples
CPT
Geotechnical
Gravity Core/Vibrocore
Surveys
Soil analysis
Seabed characteristics
Video
Archaeology
Environmental
Benthic habitat
mammals
Geophysical methods
survey on the
Geological
Trial pits
landfall
Geotechnical
investigations
The public has no direct influence, but they can raise questions and objections so the politicians have to
react. Myths or rumours can change the conditions in an unfavourable manner. Therefore relevant
information to and dialogue with stakeholders and the public is highly recommended.
3.3.1 Fisheries
The normal area for concern is by local fishermen. Through dialogue their concerns normally can be laid
to rest. The typical concerns are listed below;
• How does the cable affect the fishery, particularly EMF (Electro Magnetic Field) concerns?
• How does fishery influence on the risks for the submarine cable?
• Limitations during construction (work areas)
• Release of the work area for fishing after construction - or not.
• What are the rules?
• Who to negotiate with?
• Bottom trawling
• Near-shore fishery (damage on nets)
• Constrictions after installation, e.g. areas which have been sanitised
Page 38
Offshore Generation Cable Connections
The topic is discussed in Section 6.3 of TB 398, Third Party Damage to Underground and Submarine
Cables.
Two advantages of involving the local fisheries early on is technical information not easily found regards
the site, e.g. seabed make up where fishing/crab pots have been left. The other key advantage is public
relations, where the company and project are seen in a more positive light in respect to others who do not
consult the public or fisheries. The fisheries may voice concerns regards certain methods of cable
protection, but may favour our solutions.
The following are examples of stakeholders with assets close to the possible cable routes:
• Routing of other cables or pipelines
• Subsea assets (i.e. wellheads)
• Special conditions and restrictions, sites of special scientific interest (SSSI), designated areas,
exclusion zones etc.
• Crossing possibilities (International Cable Protection Committee Recommendation 1)
• Oil and Gas licences
• Dredging companies
In the early stage it is important to clarify the conditions for new cables close to other assets. What are
the rights and duties, what are the risks, are there minimum distances to respect, under which
circumstances can crossings be made etc.?
3.3.4 Public
Never underestimate the importance of the public opinion. This is of particular importance where the
cable installation has a direct visual impact (DC converter stations), or where there is a visual impact not
directly attributable to the cable (offshore wind farm).
Page 39
Offshore Generation Cable Connections
Informing the public from the very beginning is of great importance. It is recommended to give information
at an early stage – before decisions are taken, when different solutions are still possible. The public can
in some situations give valuable input. The feeling of being invited and heard is essential.
It is recommended to contact all relevant people and groups and take their input into account. It is not
possible to satisfy everyone, but to be open to their input and take decisions afterwards on a well-
informed basis.
Before starting of offshore surveys the necessary permissions for making surveys must be obtained.
Contact with all relevant agencies is important as delays and/or fines can be incurred if all the required
permissions were not obtained.
Page 40
Offshore Generation Cable Connections
Rules
Trawling
Fisheries
Dynamite fishing
Near-shore fishery
prohibited
traffic
Compass deviations
Subsea assets
Utilities and developers with
Crossing possibilities
Dredging companies
Private landowners
NGOs
Pressure groups
Notices to Mariners
other agencies
Environment Agency
If the authorities on the basis of the environmental impacts decide to make restrictions on the installation
methods they are important to be known before the tender process for the installation has started.
The sections below describe the general information that must be known in the consenting process. The
shown methods are often related to the sea bed conditions, water depth and current. The cable route and
Page 41
Offshore Generation Cable Connections
installation method can be linked, so the environmental impact from installation can be assessed for the
different cable routes.
The final choice of method will be made after the final route has been chosen and after the tender
process regarding installation has been carried out.
A. Cable laying
The cable is laid down on the sea bottom from a cable laying vessel. The laying on the seabed is a
controlled operation with no or very little disturbance on the surroundings.
In situations with long cable lengths it is not always possible to carry the whole length of cable in the
cable laying vessel. One or more joints may be made on the cable. This is an operation that can take
some days and is very depending on the available weather windows.
To protect the coast line and protect the cable, a horizontal directional drilling is often carried out from
behind the natural or man-made sea defence to an appropriate place in the surf zone. A pipe is pulled
through the horizontal drilling, and the cable can be pulled from the sea through the pipe.
The Offshore Substation Platform end of the cable typically has a number of J-tubes or I-tubes to aid in
the installation of the multiple submarine cables. The cables are hung off the structure at the top of the J-
tube or I-tube and the stripped cable is run to either the switchgear or direct to the transformer. The
arrangement at the generator sites can be either a J-tube, an I-tube or free hanging. Each arrangement
has its benefits and downfalls. This should be assessed by the engineering group.
The pulling of the submarine cable will have no or very little impact on the surroundings unless dragged
along the seabed.
C. Cable protection
Depending on the route and the potential for damage by third parties it may (normally) be decided to
protect the cable from mechanical damage. The preferred method is to bury the cable in the seabed, if
this is possible. Where the cable exits the seabed to enter the structure or catenary the cable is usually
protected by applying a Cable Protection System (CPS).
See also Chapter 6, Cable Installation, and TB 398, Third Party Damage to Underground and Submarine
Cables.
Burial Tools
There are several tools available to bury the cable; some of these may be excluded due to consenting
issues.
• Ploughs – The cable runs through the plough setup and a blade cuts a channel in the sea bed for
the cable to be laid in. The plough is controlled by use of winches from the installation vessel; a
depressor guides the cable into the bottom of the trench.
• Water injection blade – either a vessel mounted item or an ROV mounted item; the method is to
fluidise the sea bed or cut a channel in the sea bed using high pressure water jets.
Page 42
Offshore Generation Cable Connections
• Rotary excavator – either a vessel mounted item or an ROV mounted item; the method is to use a
rotary cutter with excavator to cut the channel and move the spoil.
• Plant excavator – a vessel mounted item, normally used for shallow waters due to the reach and
operability of the plant. Requires plant operator to carry out operations based solely on video
feed/GPS from the plant when under water.
• Mass flow excavators, where a large volume of water is directed to an area to excavate an area
by man-made erosion.
The environmental impact from the cable in service shall also be mentioned, because it often shall be
incorporated in the application to the authorities.
It is not possible to make a list that can be used in every project or in different countries, because the
legislation, the organisations and the requirements are not similar all over.
Page 43
Offshore Generation Cable Connections
In international waters knowledge of international sea laws is important. There may be different
permissions and requirements for the different offshore zones (Exclusive Economic Zone (EEZ), 12 miles
zone).
It must be noticed if there is a central marine consent unit or if every individual authority must be
contacted.
From an environmental point of view international regulations and restrictions must also be observed. The
national requirements are of course also very important.
Examples:
• Overall permission of project
• Permission to make surveys
• Permission from authorities responsible for planning
• Permission regarding installation etc. at coasts and near-shore areas
Examples:
• Protected areas
• Reserved areas
• Time restrictions because of birds, tourist etc.
• Noise
• Traffic restrictions
• Conditions about specific routes
• Maximum corridor width
In that way the process is full of iterations. Based on surveys, studies, dialogue with stakeholders and the
public and finally through dialogue with the authorities the final cable routes/corridors and the overall
installation methods can be chosen for the application.
The permissions will often contain some conditions under which the project must be performed. When the
permissions have been received, the final planning and cable- and installation engineering can start. See
Section 6.2 and 6.3.
• Early dialogue
• Handling of iterations
• Applications
• Permissions
Page 44
Offshore Generation Cable Connections
4 SYSTEM DESIGN
Introduction
This chapter discusses the various aspects of system design which should be considered when designing
an offshore infrastructure that will be used to collect and transport generated power to an onshore
electrical infrastructure.
Detailed examination of the various components is provided which form part of the offshore network, plus
examples of existing offshore networks are presented.
The various network topologies that are given allow the reader to compare the initial Capital Expenditure
(CAPEX) with the long-term Operational Expenditure (OPEX) for a number of different solutions. The
development of an offshore network often impacts the onshore grid requiring expansion of the
transmission system to transport the additional offshore generation.
This section looks at the typical requirements, as specified by the Transmission System Operator (TSO)
when applying for a connection onto the transmission system, as well as the key parameters which form
part of the Grid Code. Critical issues which arise when designing a system such as the impact of reactive
compensation, reducing system losses and determining load profiles are all discussed.
Although the solutions are mainly based on offshore wind power generation, the philosophy is also
applicable for all other types of offshore generation. Furthermore, the issues discussed for export cables
may also be relevant for submarine cables that are generally used for offshore infrastructure energy
supplies. WG B4.55 is preparing a report, HVDC connection of offshore wind power plants, which
considers system aspects e.g. voltages, frequencies, protection etc. which also may be of interest.
4.1 Topology
4.1.1 Type of connections to shore
Depending on the location and number of offshore generation plants, different solutions to shore can be
selected.
To evaluate the most optimum solution, the following points have to be taken into account:
• Rated power of the offshore generation plant (or power supply to offshore structure)
• Distance to shore, including the onshore connection length
• CAPEX and OPEX for the different type of connections
• Redundancy which will have a financial impact
• Comparison of losses for the different solutions
• Voltage drop over the AC cables
• De-rating of cables due to thermal influence of multiple cables in parallel
• Possibilities for the landing of several cables
• Environmental impact
• Permits
The following solutions are mainly used for offshore generation (or power supplies):
• Medium Voltage (MV) solution: MV cable connecting offshore generators (array cables 1) and MV
export cables without an Offshore High Voltage Substation (OHVS) (Figure 4-2)
• HVAC solution: MV cable connecting offshore generators (array cables), offshore high voltage
substation with transformer and HVAC export cable (Figure 4-1)
1
Array cables are MV cables in this TB, but in the future they may also be HV cables
Page 45
Offshore Generation Cable Connections
• HVDC solution: MV cable connections offshore (array cables), offshore high voltage substation
with transformer, HVAC export cable to offshore AC/DC converter station and HVDC export cable
to shore (Figure 4-4)
• Combined HVAC and HVDC solution: HVAC connections between more offshore high voltage
substations. HVAC connections from each offshore substation to AC/DC offshore converter
station. From converter station a HVDC connection to shore (Figure 4-5)
• Offshore Grid solutions: Connections to more offshore high voltage substations and/or more
onshore grids (interconnectors).
4.1.1.1 MV SOLUTION
Probably the simplest solution is a connection of the wind farm to shore via one or more export cables at
Um=36kV level (Figure 4-2). This solution is useful for smaller wind farms close to shore, typically closer
than 20 km. The MV offshore cable will be connected to a substation on land. The voltage will usually be
raised to the needed grid voltage by using a step-up transformer on land.
FIGURE 4-2 EXAMPLE OF SMALL OFFSHORE WIND FARM CONNECTION TO ONSHORE GRID USING MV CABLES
Page 46
Offshore Generation Cable Connections
Figure 4-1 shows an example of the connection of an offshore substation to shore via one single export
cable circuit. The generated power is transmitted via this cable to an onshore substation and is then
transmitted via the on shore grid. This solution is particularly useful for larger wind farms further from
shore, typically 20-70 km. In this case it is recommended to adapt the voltage level of the export cable to
the existing voltage level of the substation were the export cable will be connected. If another voltage
level is selected an extra transformer will be needed on land.
To increase the availability and reliability of the complete system, a second export cable circuit can be
installed (Figure 4-3). In this case it is also recommended to use 2 or more (depending on the total power
generated) transformers on the OHVS.
Instead of using two HV export cable circuits it might also be possible to use one EHV export cable circuit
(e.g. 245 kV). In this case a choice has to be made between 2 export cable circuits of lower voltage
(offering redundancy in case of a cable failure) or one export cable circuit at a higher voltage without
redundancy for a cable failure. Besides the redundancy there will be a difference in CAPEX and OPEX for
both solutions.
Page 47
Offshore Generation Cable Connections
There are some challenges in this solution. First of all, it is very costly to build and maintain offshore
construction and installations. Secondly, if a HVDC grid is built with multi terminal converters it may be a
requirement for example that a commutation failure will not switch off more than a single line, so a HVDC
circuit breaker must be introduced. This technology is under development, but size and costs need to be
taken into account.
An alternative to a HVDC grid may be a low frequency AC grid. See Section 4.3.2.
Page 48
Offshore Generation Cable Connections
Several studies have been performed on offshore grid solution but no projects have to the authors’
knowledge been implemented, so no actual experience has been available to present in this TB.
Generally it is an industry standard requirement within all Grid Codes that a dynamic model of the wind
turbine generators is provided to the TSO prior to connecting into the transmission system.
These dynamic models provided to the TSO must include particular data parameters specific to the Wind
Turbine Generators and any associated controls and reactive compensation equipment relevant to the
Wind Farm Power Station scheme. The requirements of these models are used to calculate how
quantities such as Active Power output, Reactive Power output, turbine speed etc. vary as parameters
such as the voltage at the Connection Point change.
Below is a list of key requirements that are assessed in line with the Grid Code prior to a connection
agreement being granted (TB 483 [4.1]):
• Fault ride through requirements
• System frequency and frequency response requirements
• Short circuit requirements
• Transmission system voltage and reactive power capability requirements
• Communication requirements
From a cable’s perspective, details of the Wind Farm Power Plant’s internal network (array cables) must
be supplied. Typically details as listed below are required:
• Total length (m)
• Voltage level (kV)
•
2
Conductor cross-section area per core (mm )
• Conductor type (Al, Cu, etc.)
• Insulation type
• Cable capacitance (μF/km)
• Charging current(A/km)
• Positive and Zero sequence resistance (R1 and R0 Ohm/km)
• Positive and Zero sequence reactance (X1 and X0 Ohm/km)
Once this is examined, the different possibilities for the array cabling can be studied. During this phase
the following points have to be taken into account:
• Cable cross-sections
• Type of available terminations
• Losses
• Rated current of MV switchgear
Page 49
Offshore Generation Cable Connections
Regarding the dimensioning of the cable, smaller cross-sections could be used for connecting turbines
further out in the branch. When making the layout of the array cabling, it’s important to look at the losses
of the different solutions.
Figure 4-6 from TB 483 [4.1] below gives a possible arrangement of array strings, MV switchgear and a
MV/HV transformer for a larger wind farm. In this example 4 array strings are connected to one MV
busbar. Each busbar is connected to a MV winding of one of the two transformers.
In case of a transformer failure, the MV busbars can be connected in series. In this way the remaining
transformer can take over the produced energy of the entire wind farm provided that the produced energy
is not higher than the rated power of this transformer (and each of the secondary windings).
The generator towers are normally connected through tertiary windings of the transformers at the
platform.
Page 50
Offshore Generation Cable Connections
FIGURE 4-6 POSSIBLE ARRANGEMENT OF ARRAY STRINGS, MV SWITCHGEAR AND MV/HV TRANSFORMER FOR
A LARGER WIND FARM
From Section 4.2.1 above, it was stated that the most common voltage class is Um = 36 kV so the
maximum power per string is in the range of 30 to 35 MW. When using wind turbines with power up to 10
MW, the number of wind turbines on a string would be limited to a maximum of 3 to 4 units. This means
that the number of array cables connected to the offshore substation would increase as well as the
numbers of MV switchgear cubicles at 36 kV (Um) on the platforms. This would have a huge impact on the
platform design. Along with the development of higher power wind turbines, there is also a need for a
higher voltage level to connect these wind turbines.
Manufacturers are developing specific offshore equipment for voltage levels up to 66 kV or 72 kV (Um).
However, the main challenges are to keep the size and weight of the switchgear and transformers
acceptable for use on the substation platforms.
Page 51
Offshore Generation Cable Connections
Page 52
Offshore Generation Cable Connections
Decisions to make:
• Is redundancy in array cabling wanted?
• Voltage level of the array cabling (depends on possibilities given by wind-turbine manufacturer)
• Offshore High Voltage Substation (OHVS) or not? (may depend on the distance to shore)
• Are the losses of the array cables important or not?
Each decision has an impact on the investment costs. To make these decisions a high level CAPEX
(Capital Expenses) and OPEX (Operational Expenses) is required for the planned lifetime including
decommissioning.
Page 53
Offshore Generation Cable Connections
Steps to follow:
• Identification of other cables or pipes within the concession
• Positioning of the wind turbines within the concession and type of turbines
• Number of turbines on one string
• Position of the OHVS within the concession
• Array cable length optimisation – determination of the strings
• Cable dimensioning and optimisation within each string
• Number of crossings to make with other cables or conduits
• Cable route for the export cable
• Limitations to the installation possibilities
• Accessibility of towers and OHVS by vessels
For the above steps, several solutions are possible and should be compared with each other.
For HVAC cable systems typical power connections for single core 3-phase cable systems (land based)
are:
• 500 – 1000 MVA at 400 kV (Um = 420 kV)
• 300 – 500 MVA at 230 kV (Um = 245 kV)
• 200 – 300 MVA at 150 kV (Um = 170 kV)
• 150 – 200 MVA at 132 kV (Um = 145 kV)
When using three-core AC submarine cables, there are practical limitations during the production process
(cable diameter and weight). These limitations will also put restrictions on the power transport capabilities
for three-core submarine cables when compared to land based cable systems. Typical ranges of
transmission capacity for three-core submarine cable systems for different voltage levels are:
• 300 – 600 MVA at 400 kV (Um = 420 kV)
• 200 – 350 MVA at 230 kV (Um = 245 kV)
• 150 – 250 MVA at 150 kV (Um = 170 kV)
• 100 – 200 MVA at 132 kV (Um = 145 kV)
The above values are only indicative, since there are a lot of parameters which are influencing the exact
transmission capacity of the cable system such as: ground temperature, thermal resistivity of the
surrounding ground, depth of laying and other heat sources in the vicinity (local hotspots).
Figure 4-11 gives a typical relation between transmission capacity (active power) and length of the cable
system for HVAC and HVDC systems at different voltage levels. The calculations are based on cables
with a cross-section of 1200 mm² copper, a current of 950 A, a frequency of 50 Hz, a power factor (cosφ)
of 1 and a load factor of 1.
Due to the capacitive charging current in HVAC cable systems (A/km), the transmission capacity (active
power) of the cable systems decreases as function of the length. This capacitive charging current is
voltage dependent, the higher the voltage of the HVAC system, the faster the transmission capacity will
decrease as function of the length.
Page 54
Offshore Generation Cable Connections
The charging current is also frequency dependent, this means that for a 60 Hz system compared to 50 Hz
system, the charging current of the cable will be higher by approximately 20% and consequently the cable
circuit length will be 20% shorter to reach zero active power .
FIGURE 4-11: TRANSMISSION CAPACITY VERSUS LENGTH OF THE CABLE SYSTEM FOR NON COMPENSATED
SYSTEMS, 50 HZ (MADE BY WG B1.40)
Higher transmission capacities are possible for each voltage level as shown above. The main purpose is
to show the impact of the voltage level for HVAC and HVDC on the transmission capacity of active power.
It’s possible to increase the transmission capacity (active power) over longer lengths for HVAC systems
when installing reactive compensation. More details are given in Section 4.4.
4.3.2 AC solutions
The most common connection to land or the nearest transmission grid (either onshore or offshore, e.g. an
offshore HVDC substation) is by means of one or several 3-phase AC power cables. These cable
connections are called export cables. See also Figure 4-1 and Figure 4-12.
Appendix D.1 Case study, London Array wind farm, AC export cable solution shows an example with AC
export cables from London Array wind farm.
In most cases the AC export solution consists of a combined cable system with submarine cable(s) from
the offshore substation to the shore, and then continues via transition joints through underground cables
to the AC grid onshore substation. See Figure 4-12
Page 55
Offshore Generation Cable Connections
GIS
Switchgear
3.
6.
2.
Sea Defence Wall
Onshore
Transition Joint
4.
5.
6.
HDD drilling pipe
1.
1. Export Cable, submarine cable including one or several fibre optical elements
2. Hang-off, armour termination
3. Cable sealing end against GIS switchgear
4. Transition Joint to underground cables
5. Underground cables
6. Fibre optical splice box
FIGURE 4-12: TYPICAL LAY-OUT OF MAIN COMPONENTS FOR THE HVAC EXPORT CABLE SYSTEM
The HVAC export cables are mainly 3-core submarine cables with extruded insulation. The 3-core
construction makes it easy to integrate fibre optical elements in the interstices between the power
phases, both for telecommunication and temperature monitoring of the cable. The export interconnection
might consist of one or several 3-core cables of the same type and design. For further details about the
export cable design, refer to Chapter 5, and for information about installation, see Chapter 6.
From the onshore transition joint to the onshore substation the last part of the export cable is typically a
land based underground cable. There are no definite rules for the selection of the underground cables,
but aluminium conductors seem to be favoured over copper conductors that do appear in some
installations. Regardless of the cable type it must be dimensioned to match the capacity of the submarine
export cable with respect to voltage and current rating. Underground cables are beyond the scope of this
technical brochure.
See also TB 556 [4.2], Power System Technical Performance Issues Related to the Application of Long
HVAC Cables, for other system issues that should be considered.
With a proper reactive compensation scheme it is possible to reach a 300 – 400 km route length of export
2
cable in a 220 kV HVAC system assuming 500 - 600 MW per cable at a low frequency of 16 /3 Hz.
The low frequency configuration is achievable with modern wind turbine technology featuring either a full
converter generator, an induction generator (IG) or a double fed induction generator (DFIG) which can be
2
operated independently of the grid frequency. A frequency of 16 /3 Hz (which has been slightly altered to
16.7 Hz due to harmonic issues) has been deployed and proven in electrified railway systems in many
countries for over 100 years.
Cable systems for lower frequency transmission would have same components as systems at 50-60 Hz.
Page 56
Offshore Generation Cable Connections
FIGURE 4-13: LAY-OUT OF LOW FREQUENCY AC TRANSMISSION SYSTEM (PROF. ISTVÁN ERLICH, UNIVERSITY OF
DUISBURG-ESSEN)
When comparing the investment costs, the low frequency transmission system costs will be slightly higher
than a 50-60 Hz HVAC system. This is due to the need for an onshore converter, plus the low frequency
transformers and shunt reactors must be built with more windings and/or larger iron core to accommodate
the necessary magnetic flux at lower frequencies. Still the cost will be much less than a HVDC system,
mainly because an offshore converter platform is not needed.
500
Transmission Capacity [MW]
300
100
0
0 50 100 150 200 250 300 350 400 450
Lenght [km]
FIGURE 4-14 : COMPARISON OF 50 AND 16.7 HZ 220 KV HVAC CABLE (3-CORE 1200 CU) (MADE BY WG B1.40)
As can be seen from Figure 4-15 there is a significant improvement in transmission capacity for a 220 kV
2
(3x1200 mm Cu) HVAC cable when operated at 16.7 vs. 50 Hz.
Slightly better figures can be achieved for even lower frequencies, but larger transformers will be
required.
Low frequency AC transmission systems might be applicable for medium to long distances. For very long
distances (> 500 km) HVDC will be the only solution.
Page 57
Offshore Generation Cable Connections
4.3.3 DC solutions
HVDC links are mainly used for the transmission of large amounts of power over a long distance with low
losses. Today’s HVDC cable systems with VSC converters are rated up to ±320kV, 1100 MW, and can
serve any OWP transmission demand. HVDC cable suppliers are developing extruded HVDC cables for
voltage levels higher than 320 kV and extruded HVDC cables up to 525 kV are now available. If the
offshore generation cluster is very powerful or very remote from shore an HVDC transmission can be
considered. It is well known that the station costs for HVDC are comparatively higher than for HVAC while
the cable cost per kilometre for HVDC are lower than for HVAC. In spite of this known relationship it is not
possible to establish a general break-even distance for the economic decision between HVDC and
HVAC. The comparison between technologies is very much different for land-based systems than for
offshore systems.
The erection of offshore HVDC converters is costly. Like all offshore operations it is affected by risks that
can be managed but which contribute to the overall CAPEX. Also the OPEX of HVDC offshore converters
must be taken into account because service and maintenance of offshore systems is inherently costly.
On the other hand the cabling for HVDC is simpler and less expensive than for HVAC. For the same
transmitted power an HVAC cable system employs larger cross-sections and more individual cables than
a HVDC system. While a pair of bundled HVDC cables can be laid and trenched in a single run, the
equivalent group of HVAC cables must be laid in consecutive runs since no vessel can accommodate the
necessary amount of HVAC cable in the same journey. As a consequence each HVAC cable must be
trenched separately, adding to the CAPEX of HVAC.
The loss evaluation in long systems is in favour of the HVDC solution, especially when taking into account
the high electricity generation costs offshore.
System length and unit prices of the components are the most important factors when deciding between
HVDC and HVAC. There are no catalogue prices for the components or the installation.
For more detailed information regarding HVDC systems, see TB 492 [4.3].
See also Appendix D.2 Case study, German offshore wind farms.
Figure 4-15 shows two examples of the requirements of voltage levels to be reached for different power
factors. The outline (red line) must be guaranteed by the energy supplier. This is a part of the TSO grid
codes.
Page 58
Offshore Generation Cable Connections
FIGURE 4-15: POWER FACTOR REQUIREMENTS OF TWO DIFFERENT TRANSMISSION SYSTEM OPERATORS FOR
GENERATING UNITS CONNECTED TO THE HIGH VOLTAGE 380 KV GRID (M. WILCH [4.4])
Through the control actions of an overall park controller, wind turbines can make use of their reactive
power capabilities. In general, two different control modes are used, namely reactive power control and
voltage control (TB 483 [4.1]). The phase angles of the synchronous machines can be adjusted by the
varying machine excitation. In this way the reactive power can be either leading or lagging, that is
capacitive or inductive.
Array cables connect wind turbine generators and offshore substations with each other. Typically they are
600-1000 meter long with currently a maximum rated voltage of 33 kV (Um = 36 kV). This results in a
reactive power consumption of 40-100 kvar.
Variable speed turbines have the possibility to operate with a power factor between 0.9 capacitive and 0.9
inductive. In other words, it can supply as well as consume reactive power. Generally this is sufficient to
compensate for the array cables.
Induction machines with fixed speed turbines consume reactive power which has to be supplied from the
grid or by imbedded compensation in the wind turbines. In that case, Static Var Compensators (SVC) can
be used to provide the required reactive power.
The need and rating of the compensation equipment depends on the system configuration, wind power
plant power capacity, distance to shore (length of the cable between the onshore and offshore
Page 59
Offshore Generation Cable Connections
substation), voltage and power rates, type of wind turbines, transformer impedance and other electric
devices such as harmonic filters.
Using compensation equipment the current distribution is improved, enabling an equal current at both the
generation and load. Further improvement are possible by locating additional reactors on platform’s along
the cable route; however this is an expensive solution (i.e. offshore platform costs) and normally not used
for cables at sea. However there is the opportunity to compensate the cable, if needed, just when the
cable come onshore..
The following devices can be used to compensate reactive power (FACTS) (TB 483 [4.1]):
• Mechanically switched shunt reactors (MSR)
• Variable shunt reactors with tap-changers
• Thyristor based Static Var Compensators (SVC)
• VSC based SVCs or Synchronous Static Compensators (STATCOM)
The costs for the compensation device are voltage dependent. Compensation devices at higher voltages
are more expensive than compensation at lower voltages and occupy more space.
An example is given in Figure 4-16 below for a 1200 mm² copper 220 kV HVAC three-core submarine
cable system.
FIGURE 4-16: INFLUENCE OF COMPENSATION ON A THREE-CORE SUBMARINE CABLE SYSTEM OF 220KVAC (MADE
BY WG B1.40)
For the middle curve the reactive compensation is installed at both ends of the cable system, whereas for
the upper curve, there is also reactive compensation installed in the middle of the cable system. The latter
system is more complex, especially for offshore cable systems as this means that an intermediate
platform is needed, which increases the CAPEX significantly.
4.5 Losses
The evaluation of losses (load losses and voltage dependent no-load losses) from the different grid
components during the operation is very important for the economic analysis to choose the optimal cable
system design.
Page 60
Offshore Generation Cable Connections
4.5.1 AC versus DC
The losses of a typical AC cable include current-dependent losses and voltage-dependent losses.
Current-dependent losses include conductor losses, sheath losses and armour losses. The voltage-
dependent losses are dielectric losses within the insulation.
In comparison, the losses of DC cables are mainly the current dependent conductor losses. There are
also harmonics (originating from the converters) in the cables which give (small) additional losses.
Furthermore the losses from the other grid components that should be taken into account for both the AC-
and DC-transmission solutions include:
• Losses from the transformer, switchgear and auxiliary systems for both AC and DC-solutions
• Converter losses for the DC-solutions
• Compensation losses from the shunt reactors for the AC-solutions.
Because the losses are primarily current-dependent, the calculation of the cost of losses should be
divided into different load levels, for example from full load to zero load. Furthermore the erection of an
offshore generation plant is normally in time-phases and the integrated power into the grid will be
increased in steps during the first years of operation. For the calculation of the losses those features
should be considered.
The calculation of losses is based on the expected transmission power (in-feed wind power) taking into
account the wind statistics. An example for the calculation of cable losses:
P transmission power
P2 P′
= loss
Pn
2
′
P`nloss
EQUATION 4-1
P 2
′ =(
Ploss ′
) ⋅ Pnloss
Pn
EQUATION 4-2
With the rated transmission power and the associated losses defined by the cable supplier, the losses of
the cable system(s) per year can be summed up by the multiplication results of Equation 4-2 (losses in
kW/km) and the density function shown in Figure 4-17 (duration in hours).
Page 61
Offshore Generation Cable Connections
FIGURE 4-17: EXAMPLE OF DENSITY FUNCTION OF WINDPOWER OUTPUT BASED ON THE FINO WIND SPEED DATA
20
Pi
′ = ∑ Ploss
Wloss ′ (i ) ⋅ f D ( ) ⋅ 8760
i =1 Pn
EQUATION 4-3
′
Wloss is the losses of the cable systems per length unit and per year in kWh/km
Pi
fD ( ) is the density function of wind power output based on the wind speed data in percent for one
Pn
year.
This can also be calculated using duration curves with full load and equivalent full load loss hours.
FIGURE 4-18 DURATION CURVE WITH FULL LOAD AND QUIVALENT TIME
The cost of the cable losses can be calculated considering the availability, the predefined service life of
the wind park, the predicted interest rate and unit loss cost (per kWh).
Page 62
Offshore Generation Cable Connections
OPEX All operational costs including the maintenance costs and costs for losses for the entire
design life of the system.
Goal of the economic analysis should be to optimise the lowest Total Cost of Ownership (TCO = CAPEX
+ OPEX) over the entire design life of the system. A case study of the comparison of the offshore wind
farm grid connections is attached as Appendix D.2 Case study, German offshore wind farms.
Table 4-1 shows some technical general figures for wind turbines in the range 3-5 MW.
Page 63
Offshore Generation Cable Connections
In wind farms there are lots of turbines. Each turbine must be maintained. The output from the wind farm
also depends on the number of turbines in service. The reliability of the turbines, cables, transformers and
switchgear is important and may also be taken into account in the assessment of the load profile.
Recorded data from in service wind farms show that the output can vary considerably from minute to
minute. Figure 4-20 shows an example of wind farm output from the North Sea. The current is shown as 5
minutes average values in Ampere as a function of days. The shown data is for the period with the most
consistent high wind speed, of the available recorded data.
FIGURE 4-20 EXAMPLE : CURRENT (AMPERE) IN EXPORT CABLE FROM WIND FARM DURING 25 DAYS
The output fluctuates but there is no predictable cyclic tendency as known from distribution network.
It is easy to find the maximum current that the cables must be able to transmit. If an export cable is
designed for the maximum output of the wind farm as if it is a constant load, the cable will be over-
dimensioned.
The thermal time constant of the cable and the backfill material/seabed is very long. It might take days,
weeks or months before a steady state condition is reached. Because of that, the cables can be loaded
much higher than the rated current for a shorter period and it is possible to reduce the cable size in the
case of a very fluctuating load. On the other hand it is very important to make an assessment of the
possible load, so that a realistic load profile can be used in the calculation of cable rating.
The load profile must be “translated” into a more simple form, so that it is possible to use the profile in the
rating calculations. There are different ways to do so. One method is to calculate the continuous average
values of the load for a week, a month or three months. See an example of the load factor (load relative
to maximum load) in Figure 4-21.
Page 64
Offshore Generation Cable Connections
FIGURE 4-21: CALCULATED LOAD FACTORS BASED ON THE FINO 1 DATA, 7 DAY AVERAGE VALUE (BLUE) AND 45
DAYS (RED) AVERAGE VALUE, 100 M TURBINE HEIGHT, FROM MARCH 2004 TO MARCH 2011
In Appendix D.4 Load profiles from wind farms, there are some examples that show how to find a load
profile on the basis of recorded wind data or data from similar wind farms in the same area.
Possible breakdown scenarios should be taken into account during the design phase and that proper
measures be based on a risk assessment.
Redundancy can be built-in during the design phase. However, for the export cables, due to the high cost,
there is often no redundancy. In this case it is very important that the selected cable system is a reliable
system. This means that the necessary attention must be paid to the selection and testing of the cable
system (Chapter 7), laying and protection of the cable system (Chapter 6) and after installation tests.
More details regarding testing of cable systems, cable failures and protection of submarine cable systems
can be found in following CIGRE technical brochures:
• TB 379 [4.5] Update of service experience of HV underground and submarine cable systems
• TB 398 [4.6] Third party damage to underground and submarine cables
• TB 490 [4.7] Recommendations for testing of long AC submarine cables with extruded insulation
above 30kV to 500kV
• TB 496 [4.8] Recommendations for Testing DC Extruded Cable Systems for Power Transmission
at a Rated Voltage up to 500 kV
• Electra 171 [4.9] and TB from WG B1.43: Recommendations for mechanical testing of submarine
cables
Page 65
Offshore Generation Cable Connections
The risk assessment should cover the planned lifetime of the system and include the following items:
• Spare parts needed
• Service Level Agreements with contractors and suppliers of major parts.
Feasibility Study Alternative designs are identified To identify the best alternatives technically and
Phase economically
Load flow and short circuit calculations for the To verify that the wind farm can be connected to
connecting (onshore) grid. the grid.
Design Phase Load flow and short circuit calculations for the Technical specification for the collection grid
collecting grid (current ratings required)
Dynamic simulations of interaction between wind Verification of the grid codes and coordination of
farm and connecting grid using the specific wind the TSO’s requirements
generator model
Page 66
Offshore Generation Cable Connections
When using vacuum MV breakers, high frequency voltage oscillations in the reactor can occur during
disconnection due to circuit breaker re-strikes. The use of special RC damping circuits may be employed
to avoid current zero crossing after the first re-strike and therefore prevent high frequency voltage
oscillations and damage to the reactor. For HV export cables it is unlikely that vacuum circuit breakers will
be used, although the principles are still valid.
Circuit breakers can be tested for Transient Recovery Voltage (TRV) associated with fault clearing,
however ordinary switching will cause the generation of very fast transients which if unchecked may
damage insulation and contacts. In both cases, the designer needs to be confident that the condition and
capability of the circuit breaker is not compromised for both fault clearing and ordinary switching when
operated near reactors.
It is important that the grid codes are fulfilled also in the switching situations. There may be large voltage
jumps in case of switching the reactor without simultaneous switching the cable and vice versa. If a
reactor is directly connected to the cable, it must be checked if switching causes zero-miss. In case of
zero-miss of the current, it is not possible to break the current in case of failure. The zero-miss situation
can continue for several seconds.
Page 67
Offshore Generation Cable Connections
5 CABLE DESIGN
5.1 Generic cable design
While there are many different designs of submarine power cables, only a few generic designs are used
for the electric connection of offshore power generation. The following three generic cable types are
widely used for offshore wind power generation, however, the description of a certain design feature in
this context does not exclude cable systems with different designs.
The vast majority of today’s offshore power generation facilities consist of wind turbines on fixed
foundations. Offshore Wind Parks (OWP) with fixed foundations stand in relatively shallow waters, often
less than 40 m. This affects the armour design of array and export cables. Design issues related to
external water pressure, such as water-blocking in the conductor, are relatively easy to accomplish.
The design details of the functional layers of these generic cables are discussed in greater detail in the
sections of this chapter.
Other types of offshore power generation are discussed in Chapter 9. The special demands for dynamic
cables are discussed there.
The technical lifetime of submarine cables is normally 30-40 years, however a large variation between
different cables have been experienced. While a few submarine systems have been abandoned after less
than 20 years due to repeated outages, other systems are still in operation after 50 years.
Submarine cables for the connection of offshore power generation can be classified according to their
purpose.
Array cables are in all known cases three-core AC cables with rated voltages of up to 36 kV. It is
generally accepted that medium-voltage submarine cables with Ur≤36 kV can do without a metallic water
barrier. The use of higher voltages has been discussed in Chapter 4 but has not been pursued yet. Array
cables have a steel wire armour for increased tensional force and mechanical protection.
Since an offshore wind park (OWP) can consist of a large number of turbines it is important that the array
layout is considered in respect to the conductor size and cable size, the cables should be easy to connect
to the turbine and install on the seabed. They are pulled into the turbine towers within elbow steel tubes
(J-tubes). Properties such as flexibility, low friction of the outer surface, reluctance to form loops and kinks
during seabed installation can be important.
If there is an offshore transformer station the export cable transports the collected power from the
offshore transformer station to onshore, or to an offshore converter HVDC station.
Export cables are normally three-core AC cables. If there is an offshore transformer the export cables
operate at around 145 kV AC, with some systems having up to 245 kV system voltage. It is possible to
use three-core 420 kV cables, but these have not yet been used for offshore generation. No export cable
system consisting of single-core AC cables is known to the authors; this does not mean it is not feasible
Page 68
Offshore Generation Cable Connections
or possible. Single-core submarine cables are used in some interconnections and may also be used in
the future as export cables.
Extruded insulation
Page 69
Offshore Generation Cable Connections
Figure 5-2 shows a cross-section of a three-core AC submarine cable. The metallic sheath is commonly
used in HV and EHV AC cables, but not in MV AC cables.
Page 70
Offshore Generation Cable Connections
volume and weight). Particular for HV cables the difference in total weight between copper and aluminium
conductor is not that significant due to the larger cross-section of the aluminium conductor.
Also a cable that is directly laid on the seabed needs to be heavier to avoid cable oscillation with tides
and currents and thus possible abrasion. Increased protection can be made with extra mechanical
strength (armour), thus keeping a lighter conductor. Increasing cable weight can also be achieved by the
armour design.
5.2.5 Economic issues such as availability, initial cost and operating cost
Concerning raw material cost on the world market, copper is more expensive than aluminium. Prices
fluctuate in relation to commodity market quotes. For a constant cross-section, a conductor with a higher
conductivity reduces cable losses and thus decreases operating costs during the complete life cycle. A
suggested economical optimum can be found by using IEC 60287-3-2 [5.2].
Copper has traditionally been preferred for submarine cables, but aluminium can be used. The choice
between copper and aluminium conductors depends upon the optimum design as well as economic
considerations.
IEC 60228 [5.4] specifies the cross-sectional areas for conductors of power cable. This standard covers
solid, stranded (compacted or not) and Milliken conductors. Profiled wire conductors are not covered by
IEC 60228. Other cross-sections (tailor-made conductors) are possible in accordance with customer’s
requirements for specific projects.
The conductor design may be influenced by the transmission scheme in which it has to operate (AC or
DC), as well as proximity and skin effects. AC submarine cables are made of conductors that are very
similar to those used in AC underground cable applications.
Conductor designs contribute to the water propagation rates or to the degree of water blocking of the
conductor. Solid conductors will not allow any water penetration while stranded or profiled wire
conductors can have spacing despite compaction of the layers. Mitigation action must be taken for non-
solid conductors (see Section 5.2.7).
Page 71
Offshore Generation Cable Connections
The water blocking compound is applied during stranding or laying-up of the conductor. Water swellable
powders and tapes are installed in the conductor during manufacture by adding a powder or applying a
fabric tape within the conductor. Most swellable devices are more effective with fresh water when
compared to salt water; TB 490 [5.1]. Mass impregnated cables do not need to have water blocking
compound in the conductor because of the impregnating fluid presence.
Solid Stranded
5.3.2 Insulation
Cross linking of polyethylene (in particular low density polyethylene, LDPE) is an irreversible process (i.e.
no re-melting is possible) that forms three-dimensional networks producing a more thermally stable
insulation with improved mechanical properties particularly at higher operating temperatures. Cross
linking takes place right after extrusion under heat (170-230°C) in a pressurized tube.
Whilst cables with extruded insulation were generally used for electricity distribution or (MV) medium
voltage cables and for the lower transmission voltages, extruded materials have also become the
Page 72
Offshore Generation Cable Connections
insulation of choice for many utility EHV applications for both AC and DC transmission circuits for
underground cables.
For AC cables the recommended insulation thickness is tabulated in Standards (IEC, or National
standards, utility specifications); usually for MV cables the Standards and specifications impose a nominal
thickness while for HV cables the thickness is chosen by the cable manufacturer based on experience
and validated by type tests and where applicable prequalification tests.
The insulation thickness of DC cables is chosen by the cable manufacturer taking into account both the
capacitive electrical stress (caused by the possible transient voltage, e.g. switching and lightning impulse)
and the resistive one (caused by the DC voltage in normal operation). The latter strongly depends on the
temperature difference across the insulation, on the material used and on the manufacturing process.
The degassing time and temperature after extrusion are important parameters to be considered by the
manufacturer since the by-product content can strongly influence the insulation electrical performance.
For DC application specific materials have been developed and new materials are under development.
Once the most suitable insulation material has been defined, particular attention has to be paid to the
cleanliness both of the incoming material and of the material handling used in the plant. The required
level of cleanliness of the incoming material and the proper handling strongly depend on the rated voltage
of the cable.
Extruded submarine HVDC cables are commercially used up to ±320 kV for the time being (2014).
Extruded ±525 kV HVDC cables for underground applications are available and are expected to be
available for submarine use soon. Mass Impregnated (MI) submarine HVDC cables can be used for all
voltages, even over ±500 kV. Mass-impregnated cables cannot be used for AC voltages.
The insulation system has to be tested in accordance with the relevant standard/recommendation (cf.
Chapter 7).
Figure 5-4 shows the distribution of the electric stress inside the cable insulation for a cold isothermal
cable and a loaded cable with a thermal gradient in the insulation of DC cables. The stress distribution in
a HVDC cable’s insulation is controlled by the ohmic resistance of the insulation layers. In a cold
isothermal cable the specific resistivity of all insulation layers is almost uniform and the resulting stress
distribution is according to the blue curve in Figure 5-4. After running the cable with load a thermal
gradient will appear in the insulation leading to a lower specific resistivity of the insulation close to the
conductor, than in the cooler periphery. As a result, the electric stress distribution forms as indicated in
the red curve of Figure 5-4.
Page 73
Offshore Generation Cable Connections
FIGURE 5-4 ELECTRIC STRESS DISTRIBUTION INSIDE THE DC CABLE INSULATION (L. BENARD ET A. [5.5])
Depending on cable design, operating voltage and application these items have to be considered and the
cable designed appropriately.
The most commonly used metallic screen is made from spirally wound overlapping copper tapes or
helically wrapped copper wires. Sometimes copper wire screens are complemented by singular counter-
helical copper tapes. The cross-section of the screen is defined by the fault current to be carried without
exceeding the maximum permissible temperature at the end of the short circuit (IEC 60949 [5,6]). Wire
screens need to have a lay length suitable for the bending of the cable during manufacturing, storage and
installation.
The longitudinal water-tightness of the copper wire screen is provided by swelling tapes under and/or
over the copper wires. The swelling tape under the wires must be semiconductive to provide electric
contact between the wires and the semiconductive layer of the insulation.
The metallic screen can also be made as a metallic sheath (see Section 5.4.2), under the preconditions
that the sheath fulfils the three purposes of the metallic screen mentioned above.
Page 74
Offshore Generation Cable Connections
The metallic sheath which may act as a metallic screen and have a minimum cross-section area to allow
for the passage of short-circuit currents without exceeding the maximum permissible temperature at the
end of the short circuit (IEC 61443 [5.7]). An additional copper wire screen may be used on single-core
cables to increase the short-circuit current capability. When semi-conducting layers are used over each
core of a three-core cable a sharing of the short-circuit currents between the three parallel paths has to
be taken into account.
The most commonly used metallic sheath for the dry cable design consists of an extruded lead alloy
sheath covered by an extruded anticorrosion polymeric sheath or a semiconducting tape. Other emerging
metallic sheath materials are under discussion or implementation as alternatives to lead alloy sheaths. In
present day three-core cable designs the cores have individual lead sheaths.
The metallic sheath shall exhibit a high level of mechanical performance: integrity, capability of bending
during manufacture, installation and repair as well as a certain degree of resistance to fatigue.
The chosen lead alloy for the sheath should be suitable for the specific requirements of submarine
cables. The alloy constituents have a content of less than 1%. The thickness of the metal sheath is set by
mechanical and electrical criteria.
Cable bending is normally no problem for lead sheathed cables due to the high ductility properties of lead.
Repeated bending of the submarine cable during laying/jointing at the exit of the cable laying wheel of the
vessel may in some cases impose a risk of premature fatigue failure.
Setting practical criteria for maximum permissible strain on the lead sheath by calculation is very difficult
because modelling the behaviour of the cable during load cycling and laying/jointing at sea is very
complex because of:
• Differences in the coefficients of fatigue resistance [5.8], [5.9]
• Difficult representation of the geometry of the laying/jointing configuration onboard the vessel
The latter issue can be assessed by a combination of “global analysis” which describes the motion of the
2
cable as a response to sea state, vessel movement and laying wheel , and a “local analysis” which
describes the internal behaviour of the cable constituents.
The resistance of lead alloys sheaths to fatigue has been demonstrated by decades of experience on HV
and EHV submarine static cables with laminated (=paper based) insulation and more recently on
extruded insulation land cables as well as HV extruded insulated submarine cables. The CENELEC
standard EN 50307-2002 "Lead and lead alloys - Lead and lead alloy sheaths and sleeves of electric
cables" [5.10] is a good illustration of this fact and the experience gained in the successful metallurgical
control of lead alloy morphology.
In dynamic MV cable applications with wet cable designs, EPR insulation without a radial water barrier
may be considered because its superior fatigue resistance (cf. 5.4.3).
Suitable installation techniques can substantially relief the fatigue strain on the lead sheath.
Alternative to extruded lead sheaths the metallic sheath can also be manufactured from longitudinally
applied and welded tapes of copper or aluminium. Cables with welded aluminium tapes should be
designed using some sacrificial anode in order to protect aluminium from corrosion.
2
The expression, ”laying wheel”, represents all types of over-boarding methods, such as rotating wheels, chutes, roller chutes,
vertical laying systems, etc.
Page 75
Offshore Generation Cable Connections
Although copper and lead have a high resistance against corrosion an extruded polymeric over-sheath is
commonly applied over the metallic sheath. Its main purpose however, is to provide mechanical
protection to the soft lead sheath.
When an insulating over-sheath is used a potential difference of several kV can arise between the
metallic sheath and armour as a response to fault currents in the cable and/or switching impulse. To
avoid dielectric breakdown of the insulating over-sheath, a semiconducting over-sheath is often used.
Alternatively, earthing connections may be inserted between metal sheath and armour at regular
distances along the cable. The earthing connections have to be designed and manufactured with respect
to important properties:
• Capability to carry any expected fault current with a certain duration
• Capability to carry capacitive current in AC cables
• Water-tightness
• Corrosion resistance
No testing standards or recommendations for the earthing connections are available except Electra 171
[5.11] which requires that the earthing connections, if existent, shall be subject to some mechanical tests.
A wet design tolerates water migration into the cable insulation. In MV submarine cables at voltage levels
according to IEC 60502-2 [5.12], EPR and water-tree retardant XLPE can be used as insulation material
in wet designs, up to a maximum electrical stress set by the cable manufacturer.
For voltage levels according to IEC 60840 [5.13] / 62067 [5.14], HV and EHV submarine cables as
considered in this document, dry designs are normally used. In dry design cables water blocking or water
tightness in both the radial and longitudinal directions is crucial; while in wet design cables radial water
barrier usually does not exist.
In dry design cables the radial water barrier utilises extruded or welded metallic materials. By far the most
common design is the extruded lead sheath as described above. Radial water barriers made of welded or
glued copper or aluminium tapes are used occasionally. It is however to be noted that while extruded lead
sheath and welded copper sheath provide absolute water tightness, the glued solution cannot be
considered as an absolutely water tight solution, due to some diffusivity of the water through glued
overlap. The cable manufacturer has to consider these aspects in the overall cable design. Some
aluminium alloys are more prone to corrosion while others are very corrosion resistive. Radial water
barriers in dry design cables must be free of any defects along the full length to guarantee the water
tightness under the water pressure of the installation conditions. Lead sheaths cannot be used in dynamic
cables due to their fatigue properties.
Longitudinal water-tightness prohibits the migration of water inside the cable after mechanical damage.
Furthermore, without longitudinal water-tightness the water would penetrate continuously into the cable
insulation. An effective water-tight design helps to reduce the necessary repair cable length after
3
damage . Longitudinal water-tightness can also be useful during cable installation when the cable ends
are exposed to air humidity or water splash.
In general, longitudinal water-tightness is accomplished by the use of swelling materials (powder, tapes,
yarns, etc.) under the metallic sheath, in the metallic screen area. These materials swell considerably
when they are exposed to water and block the passage of further water ingress.
Typically water penetration would be less than 30 meters; however depending on the cable design, water
depth and time to repair the penetration length could be longer or shorter.
3
In case of short inter-turbine (array) cables the cable owner may consider replacing the entire length after damage in order to
avoid joints.
Page 76
Offshore Generation Cable Connections
The sealing function must work under the water pressure at installation conditions. Relevant tests on the
degree of water-tightness specified by the manufacturer are described in the test recommendations in TB
490 [5.1].
5.5 Armour
The most prominent construction element of submarine power cables is the armour. It provides the cable
with sufficient tensional strength to withstand:
• Static tensional forces from the weight of the suspended cable during installation and recovery
for repair.
• Dynamic tensional forces from the predominantly vertical movement of the vessel.
The armour also provides torsional stability which can be important during laying. Tensional and torsional
forces also appear when the cable must be recovered for potential repair.
In addition, and perhaps the most important property in shallow waters, the armour must protect the cable
against external hazards such as:
• External violence during installation
• Direct hits from anchors and falling objects up to a certain impact intensity
• Hooking by anchors and subsequent pulling by the vessel
• Rock dumping on the cable
• Entanglement with trawling fishing gear
• Chafing of cables when passing over rocks in free spans
The risk exposure of each hazard depends strongly on seabed characteristics and burial depth as well as
on the usage pattern of vessels and the local fishing fleet. The design of the armour needs to be adjusted
to reduce the risk of cable damage to a reasonable level.
Two main designs are used to protect the cable from tensional forces (static and dynamic) during laying
and external hazards:
• Single Wire Armour (SWA)
• Double Wire Armour (DWA)
DWA is available in several configurations depending on the lay direction and the lay length (see Figure
5-5):
• DWA with the same lay direction in both layers, can absorb torsions in one direction only
• DWA with different lay direction (also called counter helical DWA): the torsional forces of each
layer counterbalance (or even cancel) out each other
• DWA ”rock armour” type, where the outer layer has a short helical pitch to efficiently protect the
cable from external intrusion (see Figure 5-6)
Often, DWA is used for the ends of the cable to accommodate extra tensional strength during pull-in
through HDD, ducts etc.
Page 77
Offshore Generation Cable Connections
The design of the armour has a strong influence on cable properties like bending stiffness, tensional
stability, torque balance, and the choice of handling, transportation and installation methods.
Submarine power cable armour is generally made up with metal wires wound helically around the cable.
The vast majority of submarine power cables are equipped with one layer of hot-dip galvanized steel
wires forming the armour. But flat armour has also been used successfully, providing the necessary steel
cross-section with a small outer diameter.
The properties of steel wires for armour of submarine cables are regulated in EN-10257-2 [5.16]. For
single-core AC cables other armour materials may be considered to reduce armour losses.
Water depth, cable weight in water (for the calculation of static forces), expected sea state during laying,
wave response of the cable laying vessel, cable mass (for the calculation of dynamic forces), and
horizontal residual bottom tension for the determination of the catenary curve of the cable from the cable
vessel to the sea bottom.
Page 78
Offshore Generation Cable Connections
The armour contributes to the tensional strength of a power cable. In most cases steel of grade 34 with a
tensile strength range of 340<Rm≤540 N/mm is used. A long pitch length results in a larger tensile
2
Single-layer armoured cables (SWA) react with elastic torsional deformation on the application of
tensional stress. In this case a considerable share of the tensional forces is transferred to the conductor,
especially in single-core cables. Conductor welds are normally weaker than the undisturbed conductor
due to the heat-annealed and softened material portion in the weld zone. So the conductor can limit the
tensional strength of the cable.
While the tensile strength of the cable is understood as the maximum tensile force that does not introduce
intolerable structural damages in the cable elements, the breaking strength is usually much higher.
Generally the tensile strength is verified by mechanical tests in accordance with the CIGRE
recommendation “Recommendations for mechanical test on submarine cables” published in Electra 171,
1997 [5.11]. (A new TB from CIGRE WG B1.43 will soon be published to replace Electra 171, the former
recommendation.) The recommendation requires the cable to withstand a tensional bending test (for
laying depth under 500 m water depth) according to the following equation:
H = 0.2 x w x d
Where H is the maximum allowed bottom tension in Newtons (where d is defined to be minimum 200 m)
A single-layer armour normally provides sufficient tensional strength for depths down to 150 m. However,
greater laying depths or difficult laying conditions (pull-in) can motivate a detailed dynamic laying analysis
with dedicated software in order to see if a double armour or different laying methods are needed.
5.5.2 Torsion
Single-layer armoured cables are normally not torsion-balanced. Under tensional forces they develop a
torque that introduces twisting of the cable. If this has not been taken into account properly for the
installation design process the cable may form loops or kinks during the installation, especially if the
bottom tension is not kept under good control.
Torsion balance can be achieved or approximated by a double-layer armour when the two layers are
oriented with opposite helical directions. Also, an anti-twist tape can provide torsion balance in a single-
layer armour. See Figure 5-7.
If the cable is to be coiled 4 during manufacturing or installation, the pitch length and orientation of the
armour layer must be designed accordingly. Most cable vessels with fixed cable tanks or coil pads are
equipped for clockwise coiling. This coiling direction requires a left-hand armour pitch direction (also
known as “S-lay”). Cables with counter-helical double wire armour can only be stored on turntables (they
cannot be coiled).
4
Coiling of a cable is the storage of the cable in a ring/coil on a fixed (non-rotating) surface.
Page 79
Offshore Generation Cable Connections
5.5.3 Protection
Since direct impacts of anchors or fishing gear look very different it is difficult to deduce design rules or
testing standards. No armour can protect the cable against the heaviest anchors; however, since the
impact severity is statistically distributed it seems natural that a double layer of steel wires will protect the
cable from more impacts than a single layer. Since the bending stiffness of a wire goes with the fourth
power of the diameter, an armour with thick wires stands better against lateral forces than one with thin
wires.
An outer armour layer with very short pitch length (so called “rock-armour”) is sometimes used for cable
protection in the harsh land take or beach areas.
In single-core AC cables the armour losses would be high due to the reduced balance and cancellation
afforded by all three phases in one cable. The armour for single-core AC cables is often made of non-
magnetic materials such as copper, bronze, brass, or aluminium to avoid the concentration of magnetic
flux in the armour wires. Another method to reduce losses in the steel armour is to install a concentric
copper wire return conductor. The induced current in the return conductor is of opposite direction to the
conductor current and the magnetic fields are superimposed with the result that the magnetic flux in the
steel armour is reduced substantially or even nullified. If mechanical strength and stability criteria permit,
some of the steel wires may be replaced by plastic filler wires. This reduces weight, magnetic losses, and
possibly costs.
No losses occur in the armour of HVDC cables, no matter if single-core or multi-core. Since DC-current is
applied there is no induced EMF in the outer layers of the cable.
5.5.5 Corrosion
Different kinds of corrosion protection for the armour can be applied. The basic corrosion protection of
armour steel wires is achieved by hot dip galvanizing.
Page 80
Offshore Generation Cable Connections
Additionally the galvanized steel wires are commonly protected by flushing with hot bitumen. The outer
serving made of bitumen-soaked polypropylene strings protect the steel armour from chafing.
This strategy usually works very well for cables buried in the seabed since the content of oxygen is limited
in the seabed. In cables exposed to open sea, for example, risers or dynamic cables, the aforementioned
protective layers may be washed away and the cables are therefore sometimes equipped with an external
extruded polymeric sheath. In markets outside Europe, individual plastic coating of the armour wires is
sometimes selected.
Certain attention must be paid if the cable is subjected to electric stray current in the water, for example
caused by onshore electric facilities, electrodes or return currents from nearby HVDC submarine cables,
active cathodic protection of nearby infrastructure etc.
The serving stabilises the armour layer mechanically, hence reducing the risk for “bird-caging” of the
wires during cable handling.
The friction coefficient of the outer serving must be taken into account for the design of the installation
procedure. A smooth plastic sheath has a lower friction coefficient than a yarn surface which can be
advantageous for cable pull-in into J-tubes. On the other hand, the rough surface of a yarn layer provides
a better grip in linear cable engines or the Capstan wheel. A yarn serving is less expensive than an
extruded serving, and less complex to manufacture.
One or more threads of yarn may be applied with a contrasting colour to make the cable visible for ROV
cameras during the installation and to visually locate the cable after installation.
In-line amplifiers or repeaters are required for distances over 300 km. It is recommended to establish an
attenuation budget for the entire link including the splices.
Page 81
Offshore Generation Cable Connections
phenomena with different properties can be utilized for DTS: Raman scattering and Brillouin scattering.
The latter is sensitive also to mechanical stress on the fibre. Most DTS systems improve their accuracy
by averaging a large number of individual measurements which can add up to measurement times of
many minutes for each reading. Since power cables do not change their temperature quickly, this can be
accepted for the sake of better accuracy and spatial resolution.
Two different types of optical fibres can be used for DTS: Multi-mode (MM) or single-mode (SM). It has
been claimed previously that MM was good for short ranges and SM for long range. Vendor specifications
related to accuracy, resolution, etc. should be analysed carefully before ordering. Since DTS vendors
favourite different types of fibres they should be consulted before the fibre type for the actual cable project
is determined. SM and MM can be installed in the same cable to give more flexibility. It should also be
noted that the installation of submarine amplifiers or repeaters would add considerably to cost and risk of
the project.
The optical fibres in the FO-subcable are enclosed in a metallic tube of stainless steel or copper with
diameter between 2 and 12 mm. Water tightness of the metallic tube is essential. The longitudinal water-
tightness inside the tube is provided by a water-blocking gel.
The metallic tube is surrounded by an extruded polymeric sheath. The FO cable sheath should be made
from semi-conductive material to provide ground potential to the metallic tube. The metallic sheath should
be solidly grounded at the ends of the cable.
The integrated FO cable is being used for three-core cables between the wind turbines, and for three-
core export cables.
Single-core export cables such as used for HVDC export systems can accommodate only very thin
metallic tubes between the armour wires. In most cases only a few fibres can be inside the tube, which is
enough for DTS purposes. If a larger fibre count is required a separate FO submarine cable is being
installed, often bundled with the pair of HVDC cables. The separate FO submarine cables are standard
telecom industry products.
In general, the integration of power cable and FO cable can generate problems especially when repair is
needed. When the fibres in an integrated power cable are faulty the complete cable needs to be cut for
repair of the FO cable. To avoid this situation it may be considered to separate FO and power cable if the
choice is given.
Page 82
Offshore Generation Cable Connections
5.8 Accessories
Cable accessories normally comprise joints and terminations. For submarine cables for offshore power
generation a range of further installation accessories can be necessary.
5.8.1 Joints
Depending on the length of installation many submarine cables for offshore generation facilities do not
need installation joints. Repair preparedness however dictates that there must be a developed concept
for jointing.
Two generic types of joints are available for most types of cables: flexible joints and rigid joints.
In a flexible joint the conductors of the two cable ends are connected by welding or brazing, or a
connector ferrule. The conductor connection is normally flush with the conductor. The insulation of both
cable ends is prepared according to manufacturer proprietary methods. The insulation system is rebuilt
layer-by-layer with well-defined interfaces to the existing cable layers. After the insulation, screening,
sheathing and armour layers are reinstated. The final joint has approximately the same diameter as the
cable and can be handled with the ordinary cable handling machinery. The flexible joint can be
manufactured in the factory to compose long shipping lengths, or on-site. However, some flexible joints
require long manufacturing times which should be taken into account when planning the installation
process.
Flexible joints are available for single-core and three-core cables and for all types of insulation materials.
The continuity of the lead sheath over factory joints is provided by the application of a lead sleeve of
larger diameter over the joint, followed by drawing the sleeve to the under layer diameter and by wipe-
soldering it to the lead sheath of the cable. The continuity of other metallic sheaths or screens should also
be reinstated over factory joints, but may result in some over dimension of the joints and change the
flexibility of the cable locally.
Rigid joints employ a prefabricated insulation sleeve. This joint is not flexible. The ensemble is completed
with water-tight barriers (metallic encasings and/or shrink tubes). The outer enclosure is usually formed
as a metallic cylinder firmly connected to the cable armour. Rigid joints are often faster to install than
flexible joints since there is no need for temperature and pressure processes.
The deployment of rigid joints from the cable laying vessel needs most often a crane facility which in turn
can invoke weather (sea state) and water depth restrictions. A supporting frame of the rigid joint during
laying is often required. See Figure 5-8.
Page 83
Offshore Generation Cable Connections
In case there is a fibre optic cable included in the submarine cable, the optic fibres will be spliced in a
separate external fibre optic splice box.
Air-insulated terminations require a long hollow insulator and large insulation distance to grounded parts
and are therefore used only very rarely on offshore installations since space is precious. An exception is
terminations for HVDC cables which are not connected to transformers nor GIS. They need to be air-
insulated which imposes requirements for free space as well as proper protection against pollution and
salt contamination. They should be installed in indoor environment.
The inter-array medium voltage cables inside the offshore wind turbine tower are terminated in plug-in
arrangements directly into the switchboard. “Elbow” terminations are available for connection of cables
from the floor to the cubicle front plate, and T-connectors allow for cable branching.
Given the restricted space in offshore platforms, cable terminations may need to be optimised regarding
footprint and volume occupation. The harsh environment (salt, wind, etc.) may require compliance with
special corrosion protection specifications.
Page 84
Offshore Generation Cable Connections
Maintenance, repair costs seem to be higher. Additional cable length is also needed for
connection or disconnection.
• Wet mate connectors: Connection or disconnection can be made underwater. In this case,
installation cost and maintenance cost may be lower due to less time needed for
connection/disconnection.
In 2014, dry mate connectors were available up to 132 kV and wet mate connectors were available up to
24 kV. Developments are undergoing to increase voltage level to 36 kV, which is the main output voltage
of offshore generation equipment.
Hang-off
A hang-off is a structure embracing the cable and firmly secured to the cable armour where it comes up to
any platform to safely carry the weight of the hanging cable over the lifetime of the installation. It is often a
split structure that can be assembled around the cable that takes up and locks the armour wires in a
clamp or welding mode. While the hang-off carries the suspended cable it is supported by the platform.
Anchoring devices
The purpose is to secure the submarine cable from involuntary movements caused by gravitational forces
at steep landfalls or seabed movements. Similar to hang-offs, these devices anchor the shore end of the
submarine cable firmly to ground. Often a hang-off is attached to a steel structure based on a ground
concrete structure.
Cable protection
In areas of increased external mechanical impact or in crossing areas the cable may need additional
mechanical protection by means of cast-iron half shells, polymeric enclosures etc. See Chapter 6.
Page 85
Offshore Generation Cable Connections
5.9 Rating
Several methods are available to calculate the rating of offshore generation connection cables, and to
calculate necessary cable dimensions to achieve a required rating:
• Analytical/empirical methods as formalised in IEC 60287 and IEC 60853
• Numerical methods such as Charge Simulation Method, Finite Difference Methods, and Finite
Element Methods
• Mixed methods
The analytical/empirical methods can give a fast result for standard cable installation situations. The
numerical methods can handle more complex geometric and environmental situations or arbitrary load
profiles over time.
IEC 60853 describes how to calculate cable rating with cyclic load. The cyclic load is based on 24 hour
cycles. The standards presuppose either a constant or a 24 hour cyclic load, which is not the case for
offshore wind parks.
Because the analytical methods are based on simplifications they are generally unsuitable for
complicated thermal environments such as layered soil cover, pipeline crossings, grouped cables in J-
tubes etc. In addition, the analytical and empirical methods are unsuitable for the materials with non-linear
properties and usually only useful for calculations of time-independent loads.
The Finite Element Method (FEM) runs as the Finite Difference Method (FDM) with a discretization of the
field space. FEM is an effective numerical calculation method used first in areas of mechanical
engineering and was then used in the 1960s in electrical engineering. Compared with FDM, FEM has an
advantage for complicated configurations, since FEM builds the areas/spaces with triangles instead of
square meshes. Thus, it is flexible, easily customizable and reliable. FEM is particularly suitable for the
analysis of transient processes and for materials with non-linear properties.
Page 86
Offshore Generation Cable Connections
State-of-the art FEM software enables the experienced user to assess the thermal rating of various parts
of the offshore cables with geometries varying in all three dimensions and arbitrary load profiles. The
latter is particularly important for the irregular load patterns of wind generation.
• The landfall where the cable can be routed through sea-defence walls, through HDD (Horizontal
Directional Drilling) with pipes up to 1500 m long and 30 m deep, or through microtunnels.
• I-tubes or J-tubes on offshore platforms or wind turbines. The situation can worsen by pooling
several cables into the same tube. Cable rating calculations in tubes should include the three
heat transfer mechanisms: conduction, convection and radiation.
• Submarine soils with exceptionally high thermal resistivity, e.g. with large organic content.
Despite moisture saturation, thermal resistivities of up to 1.4 K⋅m/W have been reported.
• Vicinity to heat sources such as other power cables, heated pipelines, etc.
Since these “hot spots” constitutes only a small fraction of the cable route it would be very costly to
increase the cable size along the entire route only to meet the rating requirements at the “hot spots”.
Several methods can be considered to maintain the cable rating also on critical locations:
• Using a cable with increased conductor size only in short sections. Transition joints between
different conductor sizes are available from some manufacturers.
• Using aluminium conductor in the main cable route and copper conductor at critical points.
• Reduce armour losses by replacing some steel wires by plastic fillers, or using non-magnetic
armour material.
• Transition from submarine three-core cable to three near-shore single-core cables.
• Using back-fill or pipe-fill material with high thermal conductivity.
• External forced cooling.
Page 87
Offshore Generation Cable Connections
6 CABLE INSTALLATION
6.1 General
The submarine cable installation is not an easy task. Many factors and tasks should be taken into account
before starting the real installation in the open sea. Any unforeseen neglect can lead to accidents or
financial losses. Sometimes the submarine cable installation can be more expensive than the cost of the
cable, especially in a challenging environment.
Based on the initial study, survey data, permissions and the cable design, the scope of the offshore cable
installation will be prepared and defined. The installation contractor shall propose a suitable cable laying
and burial methodology along with capable vessel(s) that can carry out the works. Bad weather conditions
and reasonable endeavour criteria for the cable laying and burial should be agreed by the client and
contractor prior to contract award. The installation windows should also be considered due to the weather
window and sometimes the permission conditions.
This chapter describes what to take into account before, during and after installation of a submarine cable
in regards to technical issues. It is for example not describing how to organize the installation team, the
detailed documents or the safety procedures to follow during the installation.
The following is a non-comprehensive list of tasks in many submarine cable projects. Not all aspects are
discussed in this TB, but the list should give an overview of important issues to take into consideration.
• Planning of the complete work and coordination with other parties, e.g. cable and platform
supplier
• Issuing a project specific Quality Management Plan
• Acquisition of Authority approval and certification for undertaking the work, e.g. operational
permits for vessels
• Final route engineering, including amendment of initial cable route alignment if necessary and
additional surveys if required
• Provision of a Burial Assessment Study
• Preparation of crossing designs for cables and pipelines in line with Crossing Agreements;
construction of crossings prior to cable laying and cable protection post-lay
• Temporary pulling facilities on offshore structures for cable pull-in
• Provision of all vessels, port facilities, tools, equipment, work and accommodation facilities as
well as work and accommodation facilities for other parties required to work on the vessels
• Required weather conditions for installation and conditions when work must stop
• Provision of trials for any vessel, spread or equipment and sea trials for cable installation, if
necessary
• Receipt and storage of submarine power cables and accessories at quayside in a port or at cable
manufacturers facility, in the event cable installer is not also the cable manufacturer
• Transportation of submarine power cable and accessories to the Site of installation
• Route Clearance of out-of-service cables and debris identified during survey
• Pre-Lay Grapnel Run (PLGR) immediately prior to cable installation
• Recovery of laid ends and jointing of cables
• Laying of the submarine cables on the seabed and burial by a method to be agreed with
contract’s parties
• Provision of real-time operational data streaming from all cable installation and survey vessels via
a data access platform
• Construction of crossings, including rock placement or other material placement for protection
• Adjustment of cable lengths, cutting of cables, sealing of cable ends and securing of cable ends
by permanent hang-offs at offshore platforms
• Landing of cables to the shore including, if necessary, installation through coastal protection
structures e.g. horizontal directionally drilled conduits
Page 88
Offshore Generation Cable Connections
• Installation on land up to the termination point (transition joint) with the land cables
• Testing of installed cables, eventually, with the jointed land cable
• Documentation of work execution and of permanent works
• Preparation of a plan to undertake a cable repair, should this be necessary during the Work
According to the specific requirements of each project, the work can also include any other item or
service which is considered necessary for completing the cable installation.
6.2 Planning
6.2.1 Planning of the complete work and coordination with other parties 5
Offshore work requires detailed planning to reduce costs and risks. In the planning of the offshore work all
relevant information from initial studies should be used. If necessary, additional offshore
investigations/surveys should be carried out because the survey data is fundamental to the installation
engineering and planning. See Chapter 3.
All operations should be properly planned and programmed for in each phase of the project.
The first stage of planning should be prepared as a part of the tender documents during the tender phase.
In the project execution phase, the detailed planning and engineering should be issued in the form of
procedures based on the first planning.
The planning and engineering of all marine operations should – if possible - be based on tested or proven
technology and methods to reduce risks.
It is recommended that the feasibility of extending proven technology beyond previous limits of use
should be thoroughly documented by technical reports, procedures and work instructions. If necessary in
some specific cases trials should be performed prior to the start of work.
Contingency plans and disaster recovery plans should be prepared for all marine operations.
Often more than one party will be involved in an offshore project. It is important at an early stage to
coordinate the time schedules, communications between parties and access to sites of common interest.
An installation team should consist of relevant parties - typically a cable engineer and an installation
engineer working together from design, tender, procurement, manufacture, transportation, installation and
commissioning as this minimizes interfaces and handovers/lost knowledge.
The interface between the installer and other relevant parties/stakeholders should be clarified as early as
possible, e.g. to the platform supplier, cable supplier and also authorities etc.
The complete and comprehensive documentation should be supplied about working procedures and
works, including any aspect affecting or interfacing with works or activities of other contractors or third
parties.
Based on the method of statement in the tender phase, the procedure should include the following items
as minimum:
5
Other parties means for example cable and platform supplier.
Page 89
Offshore Generation Cable Connections
The procedures for all discrete elements and phases of the work should be defined and provide the detail
of how the installation should be accomplished.
The procedures should give due regard to engineering and weather requirements. Design criteria and
assumptions should be stated and relevant calculations provided.
Procedures should describe the work with a sufficient degree of detail to enable assessment of the
suitability of engineering solutions, tools, equipment, measuring techniques, manpower resources,
vessels etc.
From the very beginning of a project it should be considered how to reduce and manage risks. For
example, who is responsible of the different operations and what determines the transition of
responsibility?
In case of incidents (accidents, damage etc.) it is important that all parties continue their work to reduce
the consequences and to finish the agreed work. The financial aspects of a risk can to some degree be
solved by insurance. A Contractors All Risk (C.A.R) insurance policy is generally used to ensure sufficient
level of insurance of all activities, and that all transfers of responsibilities are covered, so work do not stop
until the responsible part have been identified.
Page 90
Offshore Generation Cable Connections
By flexible and proactive planning, any hazard or delay related to weather or other environmental
conditions should be minimized, such as tides. It is good practise and very important from the point of
settling the risk to have operating weather parameters agreed prior to signing of contract of installation.
The site specific weather forecasts should be available for the specific project area from an agreed
source for the duration of operations.
The route information is normally based on the assessment of the site conditions and should apply as the
basis for cable laying. Obstacles in the path of the planned route can be identified and should be
considered as either a possible route deviation inside the survey corridor or an obstacle to be moved.
By reviewing, the data and all route information with respect to the geophysical and geotechnical
conditions and confirming its adequacy and appropriateness to determine appropriate resources for burial
of the cables, any perceived discrepancies, errors or omissions in the provided data should be brought to
the attention for the involved parties.
The following information should be done at least (see also Chapter 3):
• Route position list for the engineered route
• Straight line diagram showing, as a minimum, start and end points, section lengths for different
cable types, burial depths, crossings and permit boundaries, position of joints if any
• Table of pipeline and cable crossings and other utilities
• North-up and alignment sheets
• Cable and pipeline crossing designs
In order to make the right choice of method and make use of the right tools, it is a good idea to make a
Burial Assessment Study (BAS) for the whole of each cable route to determine the degree of burial
required.
Based on the supplied survey data, any other survey data, existing published material or in-house data
sets, the design or known performance characteristics of the proposed burial machine should be issued.
A geological assessment should be undertaken and a geological description should be provided along the
cable route that characterises the route according to ground conditions including:
• Distribution and extent of seabed sediment types
• Geotechnical properties of seabed sediments in the context of cable burial
• Sea bed morphology and its effects on the efficacy of installation vehicles
• Moving sand dunes
Page 91
Offshore Generation Cable Connections
The Burial Assessment Study should consider what installation techniques and equipment are optimal for
obtaining effective burial in the ground conditions described in the geological assessment (see Section
3.2).
The Route is split into zones of alike issues, e.g. heavy shipping, fishing activities, dredging etc. Each
zone shall have a risk assessment looking at the risk of damage and mitigation. See also TB 398 [6.1].
This activity looks at the potential risks and the soil conditions to set the burial requirements per risk and
per soil type. The result of the assessment can be collected in a Risk Assessment Matrix and a Burial
Depth Matrix.
In the Risk Assessment Matrix the risk (product of probability and consequence) of external damage can
be listed for the different route zones.
In the Burial Depth Matrix the target burial depth of the cables can be listed for the different route zones.
Taken into account the level of protection found in the Risk Assessment Matrix for every zone, the burial
depth can be assessed for different soil conditions and the result listed in the Burial Depth Matrix.
In TB 398 it is shown in more details how risk assessment can be used on cable systems.
In the event of the cable not reaching sufficient burial depth to enable a good protection from the potential
risk, mitigation action may be taken which is either a further burial campaign, rock placement or lay
mattresses.
Health, Safety and Environment, (HSE) policy should be available and ensure all personnel under its
control are conversant with the HSE requirements.
Hazard and Operability Study (HAZOP) should be undertaken for every operation in order to identify and
evaluate problems that may represent risks to personnel or equipment, or prevent efficient operation.
Where operations require under water intervention, utilization of remote operated vehicles (ROVs) should
be the principal method. If for any task the use of ROVs is not feasible or impractical and utilization of
divers is deemed essential then industrial best practice and the local governmental regulations shall be
adhered.
The depth of harbour should be confirmed as suitable for the chosen vessel. The foundations at harbour
and the crane should be suitable to carry the weight of the cable and/or equipment.
Page 92
Offshore Generation Cable Connections
• Weight in water
• Maximum caterpillar force (lateral load)
• Maximum side wall pressure
Other parameters that could influence the choice of installation equipment and method would be;
• Bending stiffness
• Torsional stiffness and balance
Additional considerations that should be assessed are maximum side wall pressure (obtained by the MBR
and MHT) and roller pressure (concentrated-load) which will be determinative for how the cable routing,
distance between rollers etc. is performed on the vessel (or in other cable-ways).
It is important that the cable-way is built so that all the rollers in the bend get in contact with the cable.
a) b)
Figure 6-1 shows a) correct and b) incorrect arrangement of cable rollers. In the latter the cable will be
exposed to concentrated point loads (red arrows) and eventually rolling/milling of cable elements; (the
lead sheath is particularly vulnerable) if the line tension is high. As a general rule this must be avoided
and is an important item to check when inspecting cable routes. Also, most cables are vulnerable to
simultaneous bending in two different geometrical planes. This is specifically critical for cables with bi-
directional armour layers and should be avoided. There should be a straight line of 4-5 x lay-length of the
armour so the wires can have chance to re-settle before a directional change in a different plane.
The temperature of the installation period (time of year) should be taken into consideration as most of the
materials and components in the cable become stiffer and more brittle as the temperature falls. Hence the
cable parameters should be re-assessed if the installation is performed at low temperatures.
Page 93
Offshore Generation Cable Connections
All of the above mentioned factors contribute to the detailed route and also set the final length of the
cable(s). These factors also determine the protection methods to be used along the route such as:
• Direct buried (excavating, jetting or ploughing)
• Rock dumping
• Concrete mattresses
• Cast iron shells
• Ducts and pipes etc.
Normally it is desired to have a proper galvanic separation between the existing cable/pipeline and the
installed cable. For mechanical protection from overlaying rock or mattresses it is common to install an
extra insulation layer on the cable in the crossing points. A known solution is polyurethane half shells that
are wrapped around the cable and secured by stainless straps (Figure 6-2). Thermal insulation of the
mats should also be taken into account in the rating of the cable.
Planning of the crossings should be made during the installation engineering, noting the water depth at
each crossing location so that positioning of the protective mats can be installed correctly taking into
consideration the vessel’s position and the catenary length.
Page 94
Offshore Generation Cable Connections
Sea level
catenary length
Sea bed
Existing cable or pipeline distance to crossing location
When crossing larger object such as oil pipelines it might be necessary to build-up around the object to
avoid free-spanning of the cable. This can be done by means of sand-bags, rocks or concrete
mattresses. Also a protective layer of the same means is used on top of the cable after it is installed.
Grade in (Gi) and Grade out (Go) in Figure 6-4, Figure 6-5 and Figure 6-6 is the distance on each side of
the crossing object. Gi and Go should be considered in the engineering phase and agreed with the asset
owner. The distance x is between the crossing asset and the seabed.
FIGURE 6-4 CROSSING OF LARGE OBJECT (CABLE, PIPE ETC.) WITH NO EXTRA PROTECTION BETWEEN
OBJECTS, PRINCIPAL SKETCH
Figure 6-4 shows a crossing of a three-core submarine cable, which is placed deeper (≥x) than the similar
crossing in Figure 6-5. In Figure 6-6 the depth is even lower.
Page 95
Offshore Generation Cable Connections
FIGURE 6-5 CROSSING OF LARGE OBJECT WITH EXTRA PROTECTIONS BETWEEN OBJECTS, PRINCIPAL SKETCH
Concrete mattresses are typically used for crossing to provide separation and mechanical protection.
Concrete bags are also available.
FIGURE 6-7 MATTRESSES LAID OVER EXPOSED PIPES/SUBMARINE CABLES AT SEA BOTTOM
Page 96
Offshore Generation Cable Connections
If the land fall is the second (last) end of the export cable this requires a lot more effort to perform
correctly. The exact length should be carefully determined and the cable cut at this length. Then the
cable, with the proper over-length, is floated out on inflatable buoyancy elements in a loop before the end
is pulled-in. The buoyancy elements are successively deflated at the landing point as the cable is being
pulled in.
Page 97
Offshore Generation Cable Connections
Pull-in head
The pull-in head comprises a steel base plate and steel body housing with a masterlink (bull-nose) where
the pull-in winch is hooked onto. The armour wires of the cable are terminated in the base plate and the
body is screwed onto the base after sealing of the cable core ends.
Principally the HDD is initiated by a smaller pilot hole, following the designed boring profile with the
controllable pilot drill crown (or bit). Then the drill string is pulled back connected to a larger diameter
reamer to increase the size of the bore .It is not uncommon that the HDD contractor needs multiple times
Page 98
Offshore Generation Cable Connections
of reaming operations to be able to pull in the pipe. At the final reaming the pipe is hooked onto the
reaming crown and pulled in simultaneously.
In some cases it is necessary to flush the drilling hole after the reaming operation before the pipe is pulled
in. This is done by means of a type of mud (e.g. Bentonite type mass). It is important that the HDD
contractor has a waste management plan and system to avoid any wasted material entering into the local
environment, e.g. sea.
FIGURE 6-13 PULLING SUBMARINE CABLE INTO PIPE (HDD), WHICH WILL BE BURIED AFTER PULLING
Pulling in conduits provide additional difficulties such as high pulling tensions, these high tensions can be
mitigated with the use of cable pulling engines, or lubrication.
The most common burial tools used are mechanical plough and water jetting systems. Plough systems
are connected to the host vessel (vessel or barges) and towed. Typically, the burial depth achieved is
Page 99
Offshore Generation Cable Connections
comprised between 1 m – 2 m, depending on the seabed, but recent new designs can reach down 3 m
(or more depending on the seabed). The burial depth is controlled by hydraulic actuators.
A jetting system fluidizes the seabed using a combination of high flow, low pressure and low flow high
pressure water jets to cut into sands, gravels and low to medium strength clays. Jetting tools can be
installed on systems close to a plough design (burial sleds or jet plough) or on ROVs (Remotely Operated
Vehicles) or affixed to the side of a vessel.
Other burial tools are available to cut narrow trenches into hard or rocky seabed: Mechanical rock wheel
cutters and mechanical chain excavators. Both systems used replaceable rock cutting teeth. Mechanical
rock wheel cutter can reach burial depth up to 1.5 m while mechanical chain excavator can reach 4m
trench depth.
The jetting method fluidises the seabed by means of water jets from a special purpose ROV using the
surrounding seawater as pumping medium. This method can only be used in soft or medium density
seabed soil. The cable is guided through the nozzle swords of the ROV and falls into the groove by its
own weight. The cable is then self-buried as the masses fall back in the groove behind the vessel. Some
jetting vessels have additional nozzles on the rear to aid the burying.
The advantage with jetting is gentleness to the cable as (in theory) there is nothing that touches the
cable. The disadvantage is that it is not always possible to bury the cable simultaneously with the cable
laying and it has to be performed as a separate operation post-laying. A non-simultaneously laying may
be preferred to reduce the installation time for the cable laying vessel. Noise and sediment spreading
(turbidity) might also be an issue and should be discussed in the environmental impact study. See
Section 3.1.5 and 3.2.3.
Page 100
Offshore Generation Cable Connections
In the ploughing method, a deep groove is made in the seabed by the plough’s steel share. The cable is
guided through the internal of the ploughing device and directed into the groove as the plough moves
forward. The cable is then self-buried as the masses fall back and covers the cable behind the plough.
The advantage with ploughing is that can be performed together with the cable laying. The disadvantage
is that the cable is engaged inside the machine and the operation is less flexible. For example, to carry
out multiple passes is not possible.
The cable is routed through the device and hence buried in the same operation.
In special cases a combination of ploughing and water jetting might be possible. If the cable route in a
section with hard soil is ploughed before cable laying, the cable can afterwards be buried using a water
jetting device, because the soil has been softened by the ploughing. A vertical injector may be used as an
alternative.
In shallow waters it may be possible to make a trench in the seabed using an excavator placed on a
barge. If the excavator is equipped with Global Positioning System (GPS), it is possible to make accurate
trenches. After cable installation the excavated soil can be put back into the trench, or other backfill
material can be dumped from a vessel.
Page 101
Offshore Generation Cable Connections
Page 102
Offshore Generation Cable Connections
The cast-iron shells are normally installed in conjunction with the installation before the cable leaves the
vessel.
Concrete bags are a simpler version of the mats, consisting of single blocks and can be used where there
is only one cable/pipeline to be protected. The protection degree is obviously lower for the bags than for
the mats.
Concrete mats and bags can be uses on both trenched and non-buried installations. They can be used
also for cable crossings. See Section 6.3.3.
Page 103
Offshore Generation Cable Connections
FIGURE 6-21 CONCRETE MATTRESSES AND BAGS LAID OVER EXPOSED SUBMARINE CABLE
Solutions are available against scour erosion. The principle of anti-scour system is to create an
environment able to slow down the local water current circulation or to disable the seabed sediment
movements (for example by using bags or mattresses around J-tubes or foundations at the sea bed).
For the cable post burial, a discrete as-buried survey can verify the depth of the burial. Normally this
survey should be performed on the whole cable route.
Page 104
Offshore Generation Cable Connections
Typically control and monitoring devices used during laying and burial activities installed on either vessels
or ROVs:
• Redundant dGPS-systems
• Precision echo sounderer
• Data acquisition and display system
• High precision acoustic tracking system (USBL)
• A logging system for all survey outputs for the whole operation period
• Two acoustic scanning profilers
• Precision acoustic altimeter
• Cable tracking device
• Imaging sonar system
• CCTV and lighting systems
Specific projects may require more documentation or documentation to be presented in a special way.
If the cable has been trenched in more than one pass, the as-buried survey report should document the
results after each pass.
Depending upon the construction and handling characteristics, the offshore joints can be divided into:
• Full flexible joint
• Flexible joint with some mechanical restrictions
• Rigid joint
Page 105
Offshore Generation Cable Connections
For the offshore joints, there are also two installation types:
• Omega (with one spare loop)
• Straight (or inline)
During the jointing work, the guarding shall normally be applied for the site as mentioned in Section 6.3.9.
After the joint work, the joint is typically protected by mattresses and/or rock dumping, but may also be
jetted down assisted by divers.
Page 106
Offshore Generation Cable Connections
Owing to the congestion typical around the base of offshore platforms, due to the large number of inter -
array cables present, it should be considered making only first-end pulls at these platforms. “First-end
pull” is the pulling of the first cable end, while the rest of the cable is still on the installation vessel.
Cable operations on platforms are to comply with the safe handling recommendations of the cable
manufacturer, particularly with respect to Minimum Bending Radius (MBR), Maximum Side Wall Pressure
(SWP) and maximum tensile load. The continuous monitoring and logging the pulling tension is
recommended to ensure it is below the mechanical limits of the cable.
The first end is less complex to install as the cable is pulled in directly. The sequence of events generally
follows:
• The first end is pulled in
• The cable is initially secured at the temporary hang-off
• The vessel lays the cable away towards the next location
• The vessel lays a bight of cable either onto a quadrant or onto the sea-bed
• The cable is pulled in and the bight or quadrant is managed from the installation vessel
• The second end temporary hang-off is installed
• Start of cable burial, tension in the cable is released during the burial operation at both ends
through the temporary hang-off
• Once burial operations complete, permanent hang-offs are installed
Page 107
Offshore Generation Cable Connections
During the installation electrical and optical tests can be performed to ensure the cable has not been
damaged during the various stages as some time may have elapsed between operations.
6.3.12 Storage
There are two possibilities for the storage:
• Dry storage at turntable, drum or coil
• Wet storage on the seabed
In the event that a foundation is not present, or it is not possible to pull the cable for any reason upon
arrival at a foundation, it may be necessary for storage of the cable end on the seabed and installation at
a later date, so-called Wet Storage. For this case, there are some points to be considered:
• Waterproof sealing-end, especially for the long storage period
• The cable end(s) shall be fitted with appropriate rigging and ground rope to enable safe recovery
• Position of the cable should be within the surveyed route corridor
• Cable should be identified to the Marine coordinator to inform all parties where there is
unprotected cable and to avoid it
In case of Wet Storage outside the cable corridor it may be necessary to get permission from the relevant
authorities.
If, during an operation, it becomes evident that an operation cannot be performed according to the agreed
Procedure, it is recommended that a revision of the Procedure should be developed and the
consequences for the Work shall be highlighted. The requirement for a safe and effective performance of
the operation shall be maintained.
The Master of any vessel is responsible for the safety of his vessel and all persons working on or from the
vessel. Nothing shall prevent the Master from taking such action as he sees fit to ensure the safety of the
vessel, personnel or third parties or shall diminish the Master's total responsibility for his vessel, or for the
results of any action, which he may choose or be required to take.
All marine liaison should be performed, such as coordination of traffic, reporting the accordant marine
authorities, safety notifications including “Notice to Mariners” and acquisition of port and quay facilities,
pilot services and other assistance necessary to undertake or support the Work.
The employed vessels, their anchors and anchor cables shall be located at a safe distance from other
installations, cables, pipelines, lighthouses, navigation marks, etc., and due consideration shall be given
to such third party infrastructure at all times. Safe distances shall be defined prior to the marine operation,
paying due consideration to water depth, environmental conditions, nature of the operation, third party
requirements and other pertinent factors.
All marine operations close to third party installations or their surrounding safety zones should be
performed in compliance with third party requirements.
It is recommended to provide “emergency responds plans” in case of accidents. These should include
procedures for reporting incidents, but also emergency contact info for relevant authorities, e.g. civil or
naval sea rescue, local environmental authorities etc., and for all involved parties, e.g. onshore contacts
for all involved asset owners, contractors working in and around the work area as well as main vessels
Page 108
Offshore Generation Cable Connections
used. This could be in a common document for all contractors or as individual documents for each
contractor, but with contact lists provided by each contractor to be distributed as amendments to the
emergency response plans of the rest of the contractors. All this to ensure easy access to life saving
assistance in case of emergency.
By far the cheapest installation method is to use cable barges, but barges may have limitations on the
cable length and weight of the cable to be installed as well as water depths greater than 50 metres.
Barges can be fitted with equipment such as cable tensioning caterpillars and storage drums, but
normally do not have turntables. Barges have the option of adding ROV’s and trenching equipment, but
storage of long cable lengths can be an issue as well as the cable design can influence the choice of
cable ship or barge. Laying with barges is slower and it should be assessed in advance, if the barge is
manoeuvrable in the actual water and under the actual weather conditions.
Barges can be fitted with global positioning systems but normally do not have the luxury of thrusters
positioned at the four corners of the vessel as do cable ships. Barges typically rely on anchoring systems
and winches to gain forward movement. Lines extend from the bow, stern and midships to hold the vessel
on station. Small tugs (anchor handling tugs) are used to move individual anchors forward one at a time
while the barge master adjusts the barge position utilising the fixed anchor lines.
Page 109
Offshore Generation Cable Connections
Cable barges may be more useful for wind farm array cable installations rather than cable ships where
the runs may be shorter and the cables are smaller. However, for export cables, barges may be useful for
shorter lengths in shallow waters, but for longer and larger diameter cables, cable ships may provide the
best solution.
However, all of this comes at a cost, so advanced planning and precise project management are
mandatory to prevent cost overruns and to maintain project schedules.
A cable ship along with its ancillary equipment is shown in Figure 6-26 to Figure 6-31.
Page 110
Offshore Generation Cable Connections
FIGURE 6-28 STERN SHEAVE FOR CABLE GUIDANCE DURING INSTALLATION AND RECOVERY
Page 111
Offshore Generation Cable Connections
FIGURE 6-29 MULTIPLE WHEEL LINEAR GRIP ONBOARD CABLE BARGE TO CONTROL CABLE TENSION
Page 112
Offshore Generation Cable Connections
It is recommended to make sure that periodic reports are provided - for example the following:
Weekly Reporting:
• Weekly reports should be provided, aggregating daily progress reports from all activities
occurring in the period into a brief and readily reviewed summary, with a one week look-ahead.
Monthly Reporting:
• Monthly reports should be provided, aimed primarily at Management, summarising progress, any
incidents and payment milestones achieved, with a one month look ahead.
• Accident/Incident reporting.
• A written Incident Report should be made right after occurrence.
Page 113
Offshore Generation Cable Connections
Following the completion of cable installation operations, as-laid documentation should be provided. The
data collected during the Work and related surveys, including for example the as-buried and the as-built
rock berm surveys, should be processed and edited for final presentation in the as-built documentation.
Page 114
Offshore Generation Cable Connections
7 TESTING
Testing of power cables is widely covered by international standards and recommendations (from IEC
and CIGRÉ). The intension of this chapter is therefore only to explain the terminology used, to list and
comment appropriate documents and to point out special issues concerning offshore generation cables.
It is important to have an understanding of submarine cable testing, and to specify and agree on the
specific testing program when ordering/offering the cables. Since no offshore project is alike, the
standards and recommendations to some degree are open for interpretation, and the willingness to pay
for project specific tests can vary.
It should be noticed, that reference to this technical brochure for testing of cables will not be
sufficient to accurately specify the level of testing.
Routine tests
Tests made by the manufacturer on all manufactured components (length of cable or accessory) to check
that the component meets the specified requirements.
Handover test
Test made when cable responsibility changes hands, to help determine, if the cable has been damaged in
the previous process/handling.
Sample tests
Tests made by the manufacturer on samples of complete cable or components taken from a complete
cable or accessory, at a specified frequency, so as to verify that the finished product meets the specified
requirements.
Page 115
Offshore Generation Cable Connections
Type tests
Tests made before supplying on a general commercial basis a type of submarine cable system, in order
to demonstrate satisfactory performance characteristics to meet the intended application.
Once successfully completed, these tests need not be repeated, unless changes are made in the cable or
accessory materials, or design or manufacturing process which might change the performance
characteristics.
Development tests
Test designed and performed for new cable or accessories, in order to analyse and validate designs,
materials, components, production processes, installation conditions or long-term behaviour.
The scope and extent is at the discretion of the manufacturer and results usually are confidential.
Sea trial
An offshore test installation, carried out to demonstrate laying and handling capability or methods or
specific designs of cable or components.
Individual test can be found in the standards and recommendations referenced in Section 7.3
7.2.1.2 WITNESSING
For Routine tests it is a question if all tests are to be witnessed. This is normal for deliveries including only
one or a few lengths of export cable. If there is a delivery of a large number of array cables, then only a
portion of the tests should be witnessed.
Page 116
Offshore Generation Cable Connections
The level of witnessing routine tests of cable accessories should be considered, since this testing may be
carried out in different location(s) than the cable factory and as a part of a different production flow.
It is often remade since several of the tests are good internal tests to assess the quality, and they are
made in the production flow anyway (e.g. dimension control, hot-set).
Notice that the frequency of some of the sample tests specified in the standards and recommendations
are only suggestions and should be agreed in the contract.
Individual test can be found in the standards and recommendations referenced in Section 7.3.
TB 303 [7.1] gives a good tool for evaluating the need for new type testing.
The time schedules for delivery of cable systems for offshore generation are often very compact and
consequences of delay often severe, why it should be considered especially carefully in each case, if a
project specific type test needs to be performed, rather than accepting previously performed test.
It is in the nature of a type test, that there is a statistical probability of any type test object to fail, almost
regardless of the quality of the cable system. At least the number of components included in the test
program should be limited if possible, to the components that have not previously been tested, and the
time schedule should have room for a repetition of any test before first delivery of cable or even before
production start if possible.
Before entering a type test, it should also be declared which of the test circuit components (cable,
accessories) are a part of the type test and type test objects.
If a water penetration test is carried out under a contract, the length of allowed penetration should be
agreed, since it is not specified in the recommendations, as it is for underground cables.
Page 117
Offshore Generation Cable Connections
Also temperature limits, and especially temperature drop over the insulation are important parameters
that must be specified for the type test.
This is important since surge/impulse voltages and temperatures will have direct influence on electrical
field strengths, and often dictate the design (thickness) of the insulation rather than the system voltage.
However, the protection level can be influenced if requirements are made to the converter design early in
the design process, and specific system study on the exposure for lightning flashes of a specific HVDC
system is useful for the determination of relevant impulse test levels.
This is why a PQ test of a land cable system, will normally qualify a submarine cable system, if all
accessories i.e. joint and termination designs are covered. Therefore, attention should be given to flexible
factory joints, which are often hot moulded joints developed for submarine cables only, whereas a rigid
joint is often build-up of (three) prefabricated joints previously developed for underground cable systems.
It is noted in TB 490 that: “The range of PQ approval for submarine cable is therefore more or less related
to the prequalification of the flexible or factory joint”
Normally PQ test reports must be available for review at the time of contract award, since carrying out the
test takes half a year or more up to 150 (170) kV AC and one year or more above, both for above
150 (170) kV AC and for Extruded DC cables, not including assembly and cable production time.
Notice that PQ testing has just been introduced in IEC 60840 [7.5] for voltages up to 150 (170) kV, but
that it is not always required on this voltage level, since it is only required for nominal outer/inner electrical
stress higher than respectively 4/8 kV/mm, or if the manufacturer cannot demonstrate previous service
experience.
TB 303 [7.1] gives a good tool for evaluating PQ testing, and is also a good introduction to the history of
PQ test. Its recommendations are the basis for changes to the latest revisions (2012) of IEC 60840 [7.5]
and IEC 62067 [7.6].
Page 118
Offshore Generation Cable Connections
Up to 30 (36) kV the Electrical field strength is kept relative low because the standard IEC 60502 [7.7]
specifies the insulation thickness and PQ testing has never been deemed necessary for this voltage level.
For DC cables with extruded insulation the recommendation TB 496 [7.3] specifies a prequalification test.
Here it is even more clear that the prequalification is for general qualification only, since the final
switching surge voltage test (and optional impulse voltage test) is specified in relation to the rated voltage,
whereas it may vary in the type test, that may include project specific surge voltage levels. However, in
the case of extruded DC cable it is important that temperature limits from the PQ test is maintained in the
delivered design, i.e. maximum conductor temperature and maximum temperature drop over the
insulation.
The nature of the EQ test makes it possible in some projects to accept EQ test after contract, but it should
be noticed that it still impose a greater risk on the time schedule than a type test and that neither the PQ
nor the EQ test is intended to be project specific.
This recommendation is now under revision by WG B1.43, so for clarity, reference should be made to the
replacing CIGRE Technical Brochure when available, even when referencing standards and
recommendations referring to ELECTRA 171.
Bending without tension, crush test, sidewall force test, impact test, pulling stocking test, sea trial,
handling test for bend restrictor, mechanical test for rigid joint, abrasion test, tensile characterization test,
and friction factor assessment.
It is not the intention that all development tests automatically are part of the testing regime for all
submarine cable systems. If a test is required as part of a type test, project requirement or otherwise
included under a contract, it should be agreed herein.
Three of these tests will be commented separately in the following since they are especially relevant for
offshore generation cable connections.
Mechanically the cable design could easily be tested for this operation in a type test with the standard
tensile bending test, but the mechanical part of the type test in this case should reflect the conditions,
Page 119
Offshore Generation Cable Connections
such as bending radius and forces during the J-tube pulling, rather than only submarine installation as
specified in ELECTRA 171 relating only to water depth. The revision of ELECTRA 171 is, as mentioned,
expected to include side wall pressure tests, but as a development test relevant for J-tube installation, so
if a specific test is required for a project this should be agreed in the contract.
Sea trial
Depending on the offshore experience of the installer/manufacturer and the complexity of the installation
spread, a sea trial could be relevant. It should in each case be specified and agreed upon in the contract
since it is only briefly mentioned in the recommendations.
It should be mentioned, that since water depth is often limited for offshore generation cables connections,
experience from previous projects of the installer and/or manufacturer will often match or exceed the
complexity of projects under this TB.
However, a number of parameters should be considered: Lack of previous experience, new vessel, new
crew, new equipment, changed cable design, handling of new joints, experience with J-tube pull-ins, and
experience with self-installing bend restrictors at J-tubes etc.
It should also be noticed that even a number of changes, each not sufficient to justify a sea trial, could in
combination make a sea trial relevant.
As mentioned it is expected that the revision of ELECTRA 171, will include wording about sea trial as a
development test.
Dynamic testing
Dynamic issues during installation as well as in service are expected to be addressed in the revision of
ELECTRA 171 as development test. Special interest for installations covered by this TB, is vortex
strumming normally in case of free span of the cable along the sea bed, but in this case especially from
the sea bed to the bell-mouth of a J-tube. Also vibration issues inside the J-tubes of towers (especially
installed in deep waters) may have to be considered, if not dealt with in the design of the J-tube, see
Chapter 6 Installation.
After installation, testing should especially be considered with increasing number of offshore joints that of
course have not been tested after assembly on site.
The reason for not recommending the tests in the last bullet point is, that the voltage, which the cable
experience during test, is not comparable to the service voltage, and the advantages with the test is
Page 120
Offshore Generation Cable Connections
mainly in combination with PD measurements in field joints. But if an export cable has field joints, it is
expected to be at a distance from shore where the attenuation of PD signals will have made PD
measurements irrelevant.
In TB 502 “High-Voltage On-Site Testing with Partial Discharge Measurement” [7.9] this PD issue is
discussed and the CIGRÉ WG B1.38 is investigating site testing for a Technical Brochure that may clarify
this issue further.
For array cables an alternative test method such as VLF and DAC may be considered, since equipment is
smaller and with the latest version of IEC 60502 [7.7] VLF (0.1 Hz) is specified as an option for cables up
to 30 (36) kV.
Space at the test locations may still be restrictive and therefore compromise safe working distances or
practices, therefore testing may have to be applied through adjacent equipment, e.g. testing all cables in
a string/branch with one test, by applying voltage through the cables and switchgear.
DC tests are an option for array cables up to 30 (36) kV, however different safety considerations need to
be taken into account due to slow discharging.
At the end, the importance of the cables and the cost and risk of testing must be compared, to evaluate
the need for After Installation Tests.
TDR measurement is described in recommendations referenced in Section 7.3 below. (TB 490 [7.2] and
TB 496 [7.3] respectively)
Page 121
Offshore Generation Cable Connections
The later tests and monitoring will help to clarify issues as a Handover Test, when there is a transfer of
responsibility of the cable, if the cable cannot otherwise be tested before or after a transfer. Generally
fibre cables should be tested at every given opportunity, since it is an inexpensive test that may tell
something about the health of the cable and may reveal if and when a mechanical damage occurred.
Normally, a full test of the fibre optical cable is done as a FAT of from the fibre optical cable factory, again
as a FAT from the submarine power cable factory and finally as an after installation tests.
Measurement of the end to end damping in both directions at both 1310 nm and 1550 nm, and
Reflectrometer measurements (OTDR) at both 1310 nm and 1550 nm.
For intermediate or handover test of the fibre cable it is usually considered sufficient to test single or a few
fibres too ensure that the power cable have not been submitted to a severe mechanical event, and often,
only OTDR measurements are performed since one cable end may not be available for testing.
Fibres are quite fragile, and the space in the power cable usually allows for more fibres than needed, why
it may be considered to allow for some failed fibres in delivered cable, if it is not suspected, that the failure
is due to a general mechanical overload of the fibre cable or the entire power cable.
TB 490 “Recommendations for Testing of Long AC Submarine Cables with Extruded Insulation for
System Voltage above 30 (36) kV to 500 (550) kV” [7.2]
This recommendation will reference to underlying test specifications, where the most important are listed
below.
IEC Standards
The basis for electrical test of AC submarine cables, are the two IEC standards for testing of HV and EHV
underground cables covering each a voltage span:
IEC 60840, “Power cables with extruded insulation and their accessories for rated voltages above 30 kV
(Um = 36 kV) up to 150 kV (Um = 170 kV)” [7.5]
IEC 62067, “Power cables with extruded insulation and their accessories for rated voltages above 150 kV
(Um = 170 kV) up to 500 kV (Um = 550 kV) “ [7.6]
Page 122
Offshore Generation Cable Connections
CIGRE
TB 303 “Revision of Qualification Procedures for HV and EHV AC Extruded Underground Systems” [7.1]
ELECTRA 171 “Recommendation for Mechanical test of Sub-Marine Cables” (under revision by B1.43)
[7.8]
IEC 60502, “Power cables with extruded insulation and their accessories for rated voltages from 1 kV
(Um=1.2 kV) up to 30 kV (Um=36kV)” [7.7]
ELECTRA 171 “Recommendation for Mechanical test of Sub-Marine Cables” [7.8] (under revision by
B1.43)
Also tests or test philosophies from TB 490 [7.2], is relevant on e.g. water tightness test, test of
semiconducting core jackets if applicable.
Furthermore, even if cables up to 30 (36) kV are usually array cables, and thus often delivered in short
lengths, they may be used as export cables, and depending the layup of the delivery, it may not be
possible to get array cables into the factory routine test laboratory for PD testing. This means that for
routine testing, it may be challenging to meet PD requirements in IEC 60 502, with sufficiently low noise
levels and a test philosophy similar to that of TB 490 could be adopted.
7.3.2 DC
TB 496 “Recommendations for Testing DC Extruded Cable Systems for Power Transmission at a Rated
Voltage up to 500 kV” [7.3]
TB 496 replaces TB 219, that even if it applies to only up 250 kV have been used as the basis for
qualifying cable systems up to 300/320 kV prior to publication of TB 496.
IEC has started work to implement the TB 496 in the IEC standards but only for up to 320 kV and land
cable.
TB 496 will cover submarine cable with its references to CIGRÈ ELECTRA 171 (under revision) for
mechanical testing.
Also ELECTRA 189 [7.4] (DC) is referenced for some electrical tests and even IEC 62067 [7.6] for
material testing.
7.3.2.2 MI DC CABLES
For Mass Impregnate cables tests are described in:
CIGRÉ ELECTRA 189 “Recommendations for Test of Power Transmission DC Cables for a Rate Voltage
up to 800 kV” [7.4].
Again the submarine part is covered with its references to CIGRÉ ELECTRA 171 [7.8] (under revision) for
mechanical testing.
Page 123
Offshore Generation Cable Connections
An overview of test of fibres included in power cables can be found in this sub-standard:
IEC 60794-1-2 Optical fibre cables - Part 1-2: Generic specification - Cross reference table for optical
cable test procedures.
«Applies to optical fibre cables for use with telecommunication equipment and devices employing similar
techniques, and to cables having a combination of both optical fibres and electrical conductors.»
And depending on specified fibres typically the following sub-standards can be referenced:
IEC 60793-2-40 for Multimode fibres and/or IEC 60793-2-50 for Singlemode fibres.
Page 124
Offshore Generation Cable Connections
For submarine cable systems, some maintenance activities need to be taken into account, such as: route
inspections/surveys (subsea), verification of burial depth, survey of subsea crossings with other cables or
conduits, inspection of the scour protections at platform entries (J-tubes), marine growth (J-tube entry,
dynamic cables), etc.
The use of monitoring techniques can provide an input for maintenance techniques.
As described in TB 279 [8.1], Maintenance for HV Cables and Accessories, there are three fundamentally
different ways to carry out maintenance:
• Time Based Maintenance (TBM), to perform preventive maintenance based on specified
predetermined schedule
• Condition Based Maintenance (CBM), to perform preventive maintenance based on the present
condition of the component (condition assessment)
• Corrective Maintenance (CM), to repair or replace broken items
The maintenance activities for submarine cables are not only related to the cables but also to the
surroundings. The mechanical protection of submarine cables is very important and a main part of the
maintenance has to do with this.
TBM and CBM both have the intention to avoid failures in service. CBM can also be called “Predictive
Maintenance”, meaning maintenance to be carried out to determine which maintenance actions will follow
in order to avoid failures in service.
TBM is often the basis and is carried out as offshore surveys. The observations from the TBM may result
in CBM. The time interval between particular activities may be changed because of the observed
conditions during TBM or monitoring.
Corrective maintenance is activities directly on the submarine cable. Corrective maintenance on the
protection system (e.g. burial depth) can be seen as CBM.
Before performing offshore maintenance activities, the people going offshore must follow safety trainings
for the different offshore activities. Also appropriate personal safety equipment must be used when going
offshore.
Page 125
Offshore Generation Cable Connections
The periodicity of this maintenance should be analysed and take into account the following conditions:
• Marine activities (shipping lanes, shipping activities, other activities in the neighbourhood of the
submarine cable)
• Profile of the seabed (slopes, etc.)
• Stability of the seabed (moving sand bars, etc.)
• Impact of outage of the submarine cable system (availability) which can lead to financial claims,
loss of reputations, etc.
• Consent requirements
Period between inspections can be increased if no significant changes are observed over several
inspections.
For submarine cable systems, the maintenance activities described below are often time based.
Inspections can be made using drop down video, ROV/AUV (Autonomous Underwater Vehicle) or they
can be made by a diver (e.g. at shore ends). See also Section 3.2.1 and Appendix C - Geophysical
surveys.
In areas with seismic activities a plan should be made to re-survey the route after seismic activity has
been observed.
Page 126
Offshore Generation Cable Connections
When the scour protection at the cable is no longer intact, this can lead to extra mechanical forces on the
submarine cable. These forces have a dynamic behaviour which can lead to accelerated mechanical
fatigue and failure of the cable system.
These spare parts must also be inspected on a regular basis, mainly visual inspections. Some products in
the accessory kits have an expiring date. These products have to be replaced before the expiring date.
The management of the spare parts can also be outsourced to the submarine cable supplier.
8.2.10 Measurements
In addition to above mentioned maintenance activities, some additional tests or maintenance activities
can be performed such as:
• TDR measurements
o Before commissioning for “initial finger print”
o In case of failure
• OTDR measurement if applicable (fibre optic cable)
o Before commissioning for “initial finger print”
o In case of failure
• Partial discharge measurement at terminations
The measurements mentioned here are offline methods made with specific time intervals determined by
risk or failures. Online measurements (monitoring) are mentioned in Section 8.5.
Page 127
Offshore Generation Cable Connections
Triggers for CBM can be based upon observations during a TBM activity, monitoring (see Section 8.5) or
diagnostic measurements.
Diagnostics measurements that can be applied on the cable system and that can give an input for CBM
are:
• Online PD monitoring at termination level. This monitoring can give an indication when something
is going wrong at the termination. Especially for the offshore side this could be helpful. Due to the
fact that the submarine cables are rather long this monitoring is less suited to monitor the
complete cable length since the PD pulses will almost disappear after several km.
• Dielectric loss angle (tanδ) measurements will give an indication of the condition of the main
insulation of the cable system (offline measurement).
• Temperature monitoring (see Section 8.5) to determine hotspots along the cable route.
• Sheath testing for land part of the route.
• Tests on oil when using oil filled accessories.
• Thermal inspection of connection point with infra-red camera to detect local hotspots.
Most of above diagnostic measurements are not pass or fail measurements that requires immediate
intervention. The purpose of these measurements is to follow the evolution of the system. Based upon
this evolution appropriate maintenance activities can be planned (e.g. preventive replacement of a GIS
termination).
Furthermore during repair works or other planned cable works it may be interesting to take a cable
sample for more detailed inspection of the aged cable (insulation, lead sheath, armour, etc.). This will give
a more complete overview of the condition of the cable system.
Although this also can be considered as corrective maintenance, above activities can be planned on a
longer term depending of the risk for the submarine cable system.
Page 128
Offshore Generation Cable Connections
Monitoring techniques can give useful input for the maintenance activities. When it is decided to install
monitoring equipment, it is recommended to integrate the different monitoring techniques at a
management level so that the different informations from each monitoring can be synchronised.
Possible monitoring techniques that can be provided on submarine cable systems are described in the
following sections.
The DTS system can be equipped with a Real Time Thermal Rating (RTTR) (previously called Dynamic
Cable Rating (DCR)) system, which continuously can show the actual load and calculate the maximum
continuous load of the cable system based upon the temperature measured by the DTS system. The
RTTR system is also capable to calculate overload conditions for the submarine cable system without
exceeding maximum allowable conductor temperature.
For each project it is necessary to make a risk assessment of the failures that can happen and the
frequency of the failures. Based on this, a proposition of needed spare parts can be made. Spare parts
are to be foreseen not only for the operation and maintenance phase, but also for the installation phase.
The spare submarine cable length depends on several parameters such as:
• Number of repairs to foresee (risk analysis)
• Maximum water depth for a repair
• Length of special crossings such as shipping lanes were it is restricted to perform a repair
• Exposure to water ingress (time needed between failure and repair has an impact)
• Layout of the repair vessel
• Expected accuracy of the fault localisation
Page 129
Offshore Generation Cable Connections
Besides the spare parts themselves, a suitable location for these spare parts has to be found. For the
submarine cable the location must be chosen so that the location can be reached by the laying or repair
vessel and that all equipment is available for safe loading without damaging the cable.
Another possibility is to bury the cable in the seabed in the neighbourhood of the link in operation (this
must be included in the permits).
The management of the spare parts can also be outsourced to the submarine cable supplier. In this case
a maintenance contract is recommended including SLA (Service Level Agreements).
The contents of service contracts are not a part of the scope in this TB, but it is recommended to make an
assessment of the risks and costs in case of failures and conclude how to prepare a repair.
Service contracts can also be made regarding monitoring of shipping traffic, offshore surveys and
transport by boat or helicopter to OHVS or wind turbines.
Although cable systems are very reliable, it is possible that there will be a cable failure during the entire
life time of the system. Often these failures have an external cause.
After the failure has been noted, the type and location of the failure must be found. When the fault
location has been detected (or even before), the mobilisation of a repair vessel can start and the cable
repair crew can be contacted as well.
When mobilisation is finished, the repair work shall be done. The whole process may take weeks or
months. The better prepared for the repair work, the shorter is the repair time expected to be.
8.8.1.1 INTRODUCTION
Conditions and methods for cable fault localisation on submarine power cables can differ from classical
cable fault localisation on buried land cables. The following highlights some effective fault localisation
methods. Measurements performed in the field show that a fault localisation system especially designed
Page 130
Offshore Generation Cable Connections
for submarine cables can detect faults with a good error accuracy helping to reduce the outage time for
repair activities.
It is important to note that special safety measures are required for long submarine cables as they can
store a tremendous amount of electrical energy that may be of high risk for the operator as well as the
instruments.
In the event of a possible cable failure, following steps (Figure 8-1) are recommended to be followed:
Final
Pre- Route localisation
Test of cable system
localisation determination and cable
identification
The next section describes recommended diagnostic methods that can be used in the pre-localization
and fault localization steps. In the following sections possible actions in the steps are described.
The CIGRÉ WG B1.52, “Fault location on land and submarine links (AC and DC)”, is investigating fault
localisation methods and it is recommended to consult the Technical Brochure from this working group,
when it is ready.
If the distance relays, which may have been installed to protect the cable connection, have been set
correctly, these can often be used to localise (roughly) a fault. The methods below may be used for the
fault types listed.
TABLE 8-1 DIAGNOSTIC METHODS BASED UPON FAULT TYPE (MANFRED BAWART [8.3])
Page 131
Offshore Generation Cable Connections
Simultaneously, some investigation can be made of possible activities in the vicinity of the cable route.
Due to the long cable length for offshore purposes, following voltage sources can be used:
• Series-resonance test equipment (resonance frequency between 10 and 300 Hz)
• VLF (Very Low Frequency) test equipment, typical 0.1 Hz
• DC voltage for paper insulated cable systems and HVDC cable systems
When the cable failure is confirmed by the voltage test, the next step can be planned: pre-localization of
the cable fault.
For the pre-localization several techniques can be used. See Table 8-1
TDR measurement
This measurement technique can be used to pre-locate low resistive faults.
In order to do this, it is recommended to have a TDR measurement done after installation of the link and
before energizing. This measurement will be used as a starting point to compare the new measurement.
It is not always possible to obtain sufficiently precision using only one method. Depending on the fault
type other methods as mentioned in Table 8-1 and Appendix F.1 Diagnostic methods for fault localisation
on submarine cables, may be found useful.
Page 132
Offshore Generation Cable Connections
OTDR measurement
Since this is a fairly easy and accurate measurement, this measurement can be used as a first test in
trying to pre-locate possible cable damage. Since it is not sure that there is a FO break at the cable fault
spot, or there might be another FO break, this measurement technique is only used to give an indication.
The cable fault itself still has to be pre-located and confirmed by measuring techniques for the HV cable
itself.
OTDR can detect heavy cable damage. Since fibre breaks also can occur spontaneously without a failure
in the electric cable, and an electric insulation breakdown not necessarily damages the fibre, a direct
relation between damage in the power cable and a detectable fibre break is not given.
Carrying out fault localisation using fibres, the fibre length should be referenced to the actual cable length.
If no failure can be detected on the optical fibres but on the power cable, it may be possible to locate the
failure by use of a Distributed Temperature Sensing (DTS) system, because a test current in the cable
may increase the temperature in the cable fault.
DTS measurement
In certain cases where the fibre cable is integrated into the power cable and where the fault occurs within
the distance range of a DTS system, the fibre optic cables can be used to trace localised heating at the
point of the fault. If the cable is subjected to a controllable fault current (external voltage source) it may be
possible to measure a temperature rise at the position of the breakdown in the cable. Consideration
needs to be given to the helix length of the fibre tube installed within the cable, the packing length of the
fibre within the tube and any cable over length at the terminations. While the DTS system may identify a
linear distance to the fault location, engineering is still required to identify the exact position of the fault
location offshore. Correlation of the DTS fault position with known OTDR measurements which identify
previous splice positions which may have known coordinates may be one option, while another method
may be to create localised hotspots on the cable offshore for cross reference.
This can be done by acoustic means. From landsite the faulty phase of the cable system is connected to
a shockwave generator. This shockwave generator will generate acoustic shock waves which can be
detected by means of a digiphone. See also Table 8-1 and Appendix F.1 Diagnostic methods for fault
localisation on submarine cables.
Once the fault is localized, the repair can be planned taken into account the situation at the fault location.
This will determine the type of equipment needed for the repair.
It is not possible to mobilize before the fault location is found and the circumstances of the work are
clarified. Some of the same issues as discussed in Chapter 6, Installation, are relevant here. The water
Page 133
Offshore Generation Cable Connections
depth, wind, tide and current must be taken into account in the choice of vessel. The vessel must be with
sufficient space to be equipped with the necessary tools for the repair.
On shallow water the cable repair can be done on a locally mobilized barge, on deeper water a special
vessel is needed.
If the faulty cable is buried, it must be uncovered before repair of the cable can start. This must be taken
into account in the planning of the repair.
It is also necessary to arrange any permits that may be necessary to grant access to the area for repairs.
Fault location
Pull up the
• TDR Make joint
second end Laying cable
• OTDR Pull up the between first
• Visual inspection Cutting cable and make (with burial if
first end end and spare
joint with needed)
cable
spare cable
8.9 Decommissioning
In the permits there may be regulations about cables no longer in service. In some areas, the submarine
cable may be left buried in the sea bottom.
If the submarine cable is taken out of service, but in the near future might be commissioned again (for
example for a new offshore generation purpose) it is recommended to leave the cable buried at sea, if
there are no restrictions against it. The lifetime of a submarine cable is normally longer than the lifetime of
an offshore wind farm. When a wind farm is decommissioned, a new wind farm or another type of
Page 134
Offshore Generation Cable Connections
offshore generation may be installed. Because of the longer life time, the submarine cable may be utilised
for a new offshore plant. The condition of the submarine cable should be considered before decision of
reuse is taken.
If submarine cables must be removed after decommissioning, many of the same issues that are
discussed regarding installation of cables must be handled.
The method to remove the submarine cables and the possible tools for de-burial and removal of the cable
should be described including their influence on the environment. Stakeholders should be contacted and
agreement about the conditions must be made with authorities.
Cables buried very deep can be hard to remove. It is recommended to take that into consideration before
decision about burial depth is taken.
Crossings, especially of later installed, cables or pipes may also make removal of the submarine cable
more difficult. Agreement between the involved parties should be made regarding the removal. This
should be implemented in the crossing agreement.
Risk analyses should be made for the different processes to find the optimal solutions.
There is no risk of leak from extruded or MI submarine cables during the removal.
After removal of the submarine cables, the cables should be handed over to a qualified company which is
able, in an approved environmental manner, to separate the different cable layers and recycle as much
as possible. The metal (copper, aluminium, lead) can normally be reused.
Page 135
Offshore Generation Cable Connections
Floating structures require mechanically dynamic cables that can sustain the perpetual wave movements
during the lifetime of the generation plant. Special emphasis must be given to the cable constituents and
their fatigue-resistant designs. If a metallic sheath is considered necessary (e.g. at rated voltages over 36
kV) lead sheaths are not appropriate due to a lack of fatigue resistance; copper or other metallic sheaths
have a much better fatigue performance.
Wave energy convertors have been suggested in a large array of different shapes and sizes. They have
in common that the output power of each individual unit is relatively low, so very many units are needed
to make up an offshore power plant. This requires a simple, low-voltage submarine cable utilising a fast
installation technology. Such cables are not covered here, however the principles are much the same.
The growing demand for deep-water offshore wind turbine installations, associated with the consistently
stronger and steady winds, prompted the development of floating wind generators.
Based on the limited experience with such type of floating structures, this chapter addresses a few basic
guidelines for the design of MV and HV cable power collecting/feeding systems to or from floating
generators and platforms.
The design of the cable needs to address the combined hydro-dynamic loads that result in the most
unfavourable scenarios in terms of overall mechanical stresses during service. The dynamic loads and
motions are caused by:
Page 136
Offshore Generation Cable Connections
Waves
For shallow waters wave loading predominates as the main contribution to the total dynamic load applied
to the dynamic cable. Hence the cable design should take into account the statistical wave data for each
specific location.
Load combinations emerging from the regular and irregular wave analysis must be addressed. The sea
states are normally represented by statistical analysis that take into account relevant information such as:
significant wave height, wave period, and directionality.
Currents
A current velocity pattern showing the magnitude and direction as a function of water depth shall be used
for design analysis. For deep waters, wave loading will affect mainly the upper section of the free span
while currents will dominate the dynamic loading on most of the length down to the touch-down point.
Wind
Wind loads are directly applied to floating platforms and hence to the anchor point of the dynamic cable.
Moreover, whenever the bend stiffener is not submerged and a short span of the dynamic cables remains
above the water surface, wind loading on this surface cable must also be addressed.
Marine growth
Marine growth will accumulate on the cable over time leading to additional loading that must be
considered in the design of the dynamic cables.
Tides
Water depth variation needs to be taken into account for shallow water applications.
Emergency
Extreme conditions and emergency situations (e.g. mooring breakdown) shall be carefully addressed and
taken into consideration.
The final configuration for the cable section between the seabed and the floating generator/platform is
defined by the magnitude of the movements of the later and restrictions settled by the position of the
mooring lines. A few possible configurations are shown in Figure 9-2:
A: Catenary
The cable is a simple hang-off from the floating generator/platform describing a catenary shape.
B: Lazy wave
The U-shaped free span between the floating generator/platform (anchor point) and the buoyancy set
provides enough slack to absorb the movement of the former.
C: Steep wave
Similar to a lazy wave but with a steeper configuration near the seabed.
D: Pliant wave
Basically a lazy wave with a tether restraining the touch-down point.
E: Lazy S
A tethered buoy keeps the lower section of the wave configuration and the touch-down point in an almost
static position.
Page 137
Offshore Generation Cable Connections
F: Chinese Lantern
U-shaped cable slack keeping the tether vertically aligned with the cable entry in the floating
generator/platform.
FIGURE 9-2 CONFIGURATION FOR THE DYNAMIC CABLE BETWEEN SEA BED AND FLOATING GENERATOR
Page 138
Offshore Generation Cable Connections
Since most of the cable components are assembled with a helix structure – electric cores, fillers, fibre
optical cable and armour wires – the respective axial stresses built-up during the cable bending will be
released through the slippage of these elements.
The friction associated with the reaction forces between the helix components should be carefully
addressed when high axial stresses are expected, as in deep water installations. For shallow waters the
structural behaviour is dominated by the elastic strain of each component.
The assessment of fatigue life time shouldl take into account the reference sea states, winds, currents
and associated cyclic loading features. The loading conditions associated with the cyclic behaviour of
wave loading, the hang-off connector motion as well as vortex-induced vibration will require multiple
short-term conditions to be assessed to completely understand the long-term behaviour.
The critical cable components in terms of fatigue issues should be identified and a fatigue test performed
to obtain the respective S-N curve (behaviour of the magnitude of a cyclic stress - S - against the
logarithmic scale of cycles to failure –N).
Page 139
Offshore Generation Cable Connections
The manufacturer will normally identify the most suitable solution, depending on the project electric
requirements, particularly the voltage and fault current level.
The thickness of this sheath should be sufficient to ensure a correct distribution of the radial compression
by the armour wire layers laid over the sheath.
To release the axial stresses during bending, the coefficient of friction between the sheath and the
sheaths of the electric cores and other components (optical fibre cable, fillers etc.) should be minimized.
9.2.3.5 ARMOUR
Typically the armour design for static submarine cables is driven by the installation water depth and other
installation issues specific for each project.
For submarine dynamic cables this concept changes radically. The armour design must address the
same installation issues as for the static cables, and at the same time satisfy all of the post-installation
dynamic loads experienced by the free span between the floating generator/platform and the touch-down
point (TD).
Standard static submarine cables designed for shallow waters, require normally single layer armour. For
higher axial loads the twisting action induced by the single layer of stranded wires prompts a significant
load transfer to the inner core. Two or more contra-helically wound layers of stranded armour wires need
to be applied to counteract the twisting action.
On grounds of tensile strength and anti-torsion requirements, dynamic cables hanging off a floating
generator/platform should have at least a double layer armour and each armour layer lay direction should
be in the opposite lay direction (clockwise/counter clockwise). Moreover such armour will provide the
required ballast for a better stability during the dynamic operation. In addition the cable design should be
torque balanced, and such behaviour verified during the type test qualification.
The bending stiffness performance and ballast of the dynamic cable will also be adjustable through a
correct choice of lay lengths of the helically stranded components. For a less demanding tensile
performance, a few metallic wires can be replaced by thermoplastic filler rods.
Page 140
Offshore Generation Cable Connections
In order to facilitate the underwater operations during the cable installation, the outer serving should have
a high-visibility colour. To assist the installation of complementary hardware on the cable and to provide a
visual indication of the twisting during the cable deployment, a metric marking shall be printed with
another contrasting colour and with a suitable size and intervals.
The stiffener body is a conical mass of polymer material with a central axial opening to allow the passage
of the dynamic cable. The bending stiffener consists of two main components:
• Internal steelwork
• Elastomer moulding
The internal steelwork promotes load transfer to the attachment point - typically the base of the J- tube.
The bending stiffness of this structure increases gradually from the tip to the top of rigid section.
The bend stiffener is designed to cope with a combination of tension (T) and angle (θ) for a representative
scenario of sea-states. The supplier of the bend stiffener should address the load situations specified by
the purchaser of the system. Such load cases combine the associates tensions and angles from the
dynamic analysis.
The angle of the rigid section and the operation temperature should also be considered.
FIGURE 9-4 THE BEND STIFFENER IS DESIGNED TO COPE WITH A COMBINATION OF TENSION T AND ANGLE Θ
A temporary tip clamp should be attached to the tip of the bend stiffener to prevent sliding relative to the
dynamic cable during the installation process. This clamp shall be removed after fixing the bend stiffener
to the floating platform.
Page 141
Offshore Generation Cable Connections
The attachment to the floating platform can be made by a flange mounted at the base of an I-tube or
directly to the support structure on the floating generator/platform:
FIGURE 9-5 CABLE WITH HANG-OFF AND STIFFENER WITH FLANGE MOUNTED TO THE I-TUBE
The bend stiffener can be complete with a spool section for diver assisted connection.
The conical mass of polymer material over the cable outer serving should be taken into consideration for
the cable rating calculations.
For a correct bend stiffener design the data below will be required (as a minimum):
• Load cases (tension, angle)
• Minimum dynamic operating bending radius of the cable
• Temperature
• Breaking load of the cable
• Maximum allowable axial compression
• Axial stiffness of the cable
• Torsional stiffness of the cable
• Bending stiffness of the cable
• Weight of the cable (air and in water)
• Cable outer diameter and respective tolerance
• Characteristics of the cable outer serving
• Temperature: The ambient temperature surrounding the bending stiffener and the temperature on
the cable outer serving
As an alternative a bell-mouth (trumpet termination of I-tube) could be used instead of bend stiffener. For
smaller array cables it may be a simpler and cheaper solution.
Page 142
Offshore Generation Cable Connections
The application of the internal clamp should not be harmful to the outer serving of the dynamic cable. The
reduction of the minimum outer diameter of the cable should be carefully assessed taking into account
the maximum axial tensile loads and long-term creep.
The effects of seawater absorption and hydrostatic compression should also be carefully addressed.
The fatigue associated with the vortex induced vibrations should be carefully addressed to assess if
helical strakes are required.
The additional mass and drag associated with the utilization of helical strakes should be considered for
the hydrodynamic analysis of the free span.
The hang-off should provide adequate corrosion protection for the cable tensioner (armour).
The hang-off should also be designed to have a fatigue life time higher than the one required by the
project (normally 25 years).
To counteract the abrasion issues at the touchdown point, the outer serving of the dynamic cable can be
protected with specially designed sleeves.
The extra weight and diameter that results from the application of these sleeves has a beneficial damping
effect that counteracts the cable movement.
Page 143
Offshore Generation Cable Connections
Alternatively a standard export static cable will be connected to the dynamic cable that collects the power
from the floating generator/substation or platform:
Such a connection can be performed using either a permanent joint or a mate-able (plug-able) solution.
The principle of a permanent joint is similar to other joints; therefore once the joint is completed it cannot
be separated without cutting the cable.
The mate-able solutions can be disassembled and re-connected without cutting the cables. This type of
connection can be separated into two categories (see also Section 5.8.3):
• Dry-mate connectors: assembled outside the water on a barge/vessel.
• Wet-mate connectors: the connector mate and de-mate can be performed underwater -
prompting cost reduction (remotely operated vehicles can perform the connection on the sea-bed
avoiding the assembly of the joint on a barge). Amid cost effectiveness the wet-mate technology
is currently voltage-limited, and proven solutions for the higher voltage connections would be
scarce.
The transition joint should be designed and qualified to cope with the water pressure and with the
electrical features specified for the dynamic/static cables.
Regarding the electric current rating the dynamic cable is designed to cope with a more demanding heat
extraction process than its static counterpart. While the latter is normally designed to cope with the
environmental conditions through the landfall crossing, the electric current rating of the dynamic cables is
calculated taking into account the heat dissipation inside the I-tube and through all the additional layers of
plastic materials deployed over the cable outer serving (namely: bend stiffeners and protection sleeves).
Therefore the conductor cross-section for the dynamic cable is normally higher than its static counterpart,
and the transition joint shall be designed accordingly.
The transition joint can include an optical fibre splice box or a patch panel for jointing the fibres with
connectors. Both solutions should accommodate the optical fibres so that they are free of tensile or
bending stresses.
Bend restrictors should be incorporated on each side of the transition joint to limit the bending of the
dynamic and static cables.
Page 144
Offshore Generation Cable Connections
The visual inspection should be carried out using a ROV equipped with a video camera or a side-scan
sonar (test of basic configuration).
The design of dynamic cables is driven by software simulations based on the physical characteristics of
the multiple cable components. Therefore, to validate a specific cable design, the cable materials that
drive such simulations should be tested to verify a match with the data used in the software models.
Once the data used in the software models is validated, the static and dynamic behaviours of the dynamic
cables and complementary hardware should be tested. The tests should be made on full scale samples
from the production length. The tests below are guidelines only for qualification or verification purposes,
the final test package shall be agreed between the manufacturer and the purchaser:
• Bend stiffness test
• Dynamic fatigue test
• Hydrostatic diameter reduction
• Specific test for the buoyancy modules:
o Density verification
o Water absorption
o Buoyancy loss verification
o Hydrostatic crush pressure test
o Axial slippage test
o Full scale buoyancy test
o Full scale hydrostatic test
o Fit-up and assembly test
Page 145
Offshore Generation Cable Connections
10 GUIDANCE TO TENDERS
The below list can be used as an indicative check list for tenders. These lists highlight recommended
information to gather or supply to various parties involved in the tender process.
Below are some considerations that the project engineer must consider prior to going to the cable
supplier as each item can change the overall system design and/or cable design.
1. Redundancy requirements
2. HVAC or HVDC connections
3. Voltage level (maybe possible to choose among more levels)
4. Current load profile
5. FO – type (single- and/or multi-mode) and number of fibres
6. Compensation method (location, type: reactors, SVC etc.)
7. Cable length
Page 146
Offshore Generation Cable Connections
8. Thermal conditions (thermal resistivity, air and soil temperature, burial depth, HDD with
information about size and material of pipe, backfill, J-tube, open or closed J-tube, solar radiation
etc.)
9. Terminations (GIS or open air) and transition joints
10. If coilable design of cable or not
11. Installation conditions (water depth, HDD length and depth, static or dynamic etc.)
12. Spare parts
Waiting on weather is in some areas of the world very common. It must be clarified if the risk on waiting
on weather is considered by the client or the contractor. The weather criteria for the vessels must be
agreed between the parties as a part of the contract.
Page 147
Offshore Generation Cable Connections
l. Reporting
m. As laid documentation
18. If simultaneous burial is required
Page 148
Offshore Generation Cable Connections
11 CONCLUSION
Cigré WG B1.40, Offshore Generation Cable Connections, has described in this Technical Brochure the
main issues regarding submarine cable projects related to offshore generation.
Most attention has been paid to offshore wind generation, but many of the principles and ideas about
submarine cable connections can be used for submarine cables in general. Special requirements for
submarine cables used to connect floating generation or platforms are discussed in a separate chapter.
The TB can be used as a guide for both novices and experienced cable engineers, installation
companies, authorities responsible for offshore activities and other stakeholders. This guide does not
cover every detail, but it is possible to obtain an overview of the necessary actions and decisions to be
taken during the design and installation of an offshore cable project. Relevant references are made to
other Technical Brochures from Cigré, where further information can be found on specific topics.
In addition, the TB can also be used as a general guide for the design, installation and maintenance of
submarine cables.
Page 149
Offshore Generation Cable Connections
12 BIBLIOGRAPHY
12.1 Reference list
Initial studies, surveys and permissions:
[3.1] ICPC Recommendation No. 9, Minimum Technical Requirements for a Desktop Study, March
2012
System design:
[4.1] TB 483, Guidelines for the Design and Construction of AC Offshore Substations for Wind Power
Plants
[4.2] TB 556, Power System Technical Performance Issues Related to the Application of Long HVAC
Cables
[4.3] TB 492, Voltage Source Converter (VSC) HVDC for Power Transmission - Economic Aspects
and Comparison with other AC and DC Technologies
[4.4] Reactive Power Generation by DFIG Based Wind Farms with AC Grid Connection, M. Wilch, V.S.
Pappala, S.N. Singh, I. Erlich
[4.5] TB 379 Update of service experience of HV underground and submarine cable systems
[4.7] TB 490 Recommendations for testing of long AC submarine cables with extruded insulation
above 30kV to 500kV
[4.8] TB 496 Recommendations for Testing DC Extruded Cable Systems for Power Transmission at a
Rated Voltage up to 500 kV
[4.9] Electra 171, Recommendations for mechanical test on submarine cables (expected to be
replaced by a new TB from working group B1.43, Recommendations for mechanical testing of
submarine cables
Cable design:
[5.1] TB 490 Recommendations for Testing of Long AC Submarine Cables with Extruded Insulation for
System Voltage above 30 (36) to 500 (550) kV
[5.2] IEC 60287-3-2 Electric cables - Calculation of the current rating - Part 3-2: Sections on operating
conditions - Economic optimization of power cable size
[5.3] IEC 60050-461 International Electrotechnical Vocabulary - Part 461: Electric cables
[5.5] L. BENARD et a.: “DC extruded Cable System Design and its main characteristics”, Jicable-
HVDC ’13, Montpellier, France, 2013
[5.6] IEC 60949 Calculation of thermally permissible short-circuit currents, taking into account non-
adiabatic heating effects
[5.7] IEC 61443 Short-circuit temperature limits of electric cables with rated voltages above 30 kV (Um
= 36 kV)
[5.8] Selection of cable sheath lead alloys for fatigue resistance, IEEE Transactions on Power
Apparatus and Systems, Vol. PAS-96, No. 1, January/February 1977. D.G. Havard.
Page 150
Offshore Generation Cable Connections
[5.9] The fatigue life of lead alloy E as a sheathing material for submarine power cables, IEEE/PES
(July 20-25, 1986) Summer Meeting Mexico City. P. Anelli, F. Donazzi, W.G. Lawson.
[5.10] CENELEC standard EN 50307-2002 "Lead and lead alloys - Lead and lead alloy sheaths and
sleeves of electric cables"
[5.11] Electra 171, Recommendations for mechanical test on submarine cables (expected to be
replaced by a new TB from working group B1.43, Recommendations for mechanical testing of
submarine cables
[5.12] IEC 60502-2 Power cables with extruded insulation and their accessories for rated voltages from
1 kV (Um = 1,2 kV) up to 30 kV (Um = 36 kV) - Part 2: Cables for rated voltages from 6 kV (Um =
7,2 kV) up to 30 kV (Um = 36 kV)
[5.13] IEC 60840 Power cables with extruded insulation and their accessories for rated voltages above
30 kV (Um = 36 kV) up to 150 kV (Um = 170 kV) - Test methods and requirements
[5.14] IEC 62067 Power cables with extruded insulation and their accessories for rated voltages above
150 kV (Um = 170 kV) up to 500 kV (Um = 550 kV) - Test methods and requirements
[5.15] Ernesto Zaccone, Mechanical Aspects of Submarine Cable Armour – ICC Minutes Spring 2012,
Submarine Cables, discussion group C11D
[5.16] EN-10257-2 Zinc or zinc alloy coated non-alloy steel wire for armouring either power cables or
telecommunication cables - Part 2: Submarine cables
[5.17] IEC 60287 Calculation of the continuous current rating of cables (100% load factor)
[5.18] TB 483, Guidelines for the Design and Construction of AC Offshore Substations for Wind Power
Plants
Cable installation:
[6.2] ICPC Recommendation No. 3 Telecommunications Cable and Oil Pipeline / Power Cables
Crossing Criteria
[6.3] TB 490 Recommendations for testing of long AC submarine cables with extruded insulation
above 30kV to 500kV
Testing:
[7.1] TB 303 Revision of qualification procedures for HV and EHV AC extruded underground cable
systems
[7.2] TB 490 Recommendations for testing of long AC submarine cables with extruded insulation
above 30kV to 500kV
[7.3] TB 496 Recommendations for Testing DC Extruded Cable Systems for Power Transmission at a
Rated Voltage up to 500 kV
[7.4] ELECTRA 189 “Recommendations for Test of Power Transmission DC Cables for a Rate Voltage
up to 800 kV” (Under revision).
Page 151
Offshore Generation Cable Connections
[7.5] IEC 60840 Power cables with extruded insulation and their accessories for rated voltages above
30 kV (Um = 36 kV) up to 150 kV (Um = 170 kV) - Test methods and requirements
[7.6] IEC 62067 Power cables with extruded insulation and their accessories for rated voltages above
150 kV (Um = 170 kV) up to 500 kV (Um = 550 kV) - Test methods and requirements
[7.7] IEC 60502 Power cables with extruded insulation and their accessories for rated voltages from 1
kV (Um = 1,2 kV) up to 30 kV (Um = 36 kV)
[7.8] Electra 171, Recommendations for mechanical test on submarine cables (expected to be
replaced by a new TB from working group B1.43, Recommendations for mechanical testing of
submarine cables
[7.19] IEC 60793-2-40 for Multimode fibres and/or IEC 60793-2-50 for Singlemode fibres
[7.20] IEC 60794-1-2 Optical fibre cables - Part 1-2: Generic specification - Cross reference table for
optical cable test procedures.
[8.3] Manfred Bawart & Massimo Marzinotto, “Fault Location on Long Submarine Power Cables”,
IEEE, ICC 2012, Fall Minutes, St Petersburg, Florida.
[9.1] IEC 60502-1 Power cables with extruded insulation and their accessories for rated voltages from
1 kV (Um = 1,2 kV) up to 30 kV (Um = 36 kV) - Part 1: Cables for rated voltages of 1 kV (Um =
1,2 kV) and 3 kV (Um = 3,6 kV)
[9.2] IEC 60502-2 Power cables with extruded insulation and their accessories for rated voltages from
1 kV (Um = 1,2 kV) up to 30 kV (Um = 36 kV) – Part 2: Cables for rated voltages from 6 kV (Um =
7,2 kV) up to 30 kV (Um = 36 kV)
Appendices:
[13.2] Summary expert report on technical feasibility of offshore wind farm grid connection concepts on
the example of the clusters DolWin, HelWin and SylWin on behalf of TenneT Offshore GmbH,
Prof. Dr.-Ing. habil. Lutz Hofmann, June 2012)
[13.3] Manfred Bawart & Massimo Marzinotto, “Fault Location on Long Submarine Power Cables”,
IEEE, ICC 2012, Fall Minutes, St Petersburg, Florida.
Page 152
Offshore Generation Cable Connections
01. Abernethy, R. B. “The New Weibull Handbook”, 4th edition, ISBN 0-9653062-1-6.
02. Agrawal K C (2001). Industrial Power Engineering and Applications Handbook. Newnes, 2001,
ISBN 0750673516, 9780750673518.
03. Anders G J (1997). Rating of electric power cables, IEEE Press, McGraw-Hill, 1997, ISBN 07803-
1177-9
04. Bartnikas R and Srivastiva KD (Ed.) (2000). Power and Communication Cables, IEEE Press
series on Power Engineering, ISBN 0-7803-1196-5
05. DNV-RP-J301 Subsea Power Cables in Shallow Water, DNV Recommended Practice
06. Gilbertson O (2000). Electric Cables for Power and Signal Transmission, John Wiley & Sons,
2000
07. Heinhold L (Ed.) (1990). Power Cables and their Applications, Siemens Aktiengesellschaft 1990,
Berlin/Munich, Germany, ISBN 3-8009-1535-9
08. IEEE Standard 1120, “IEEE Guide for the Planning, Design, Installation and Repair of Submarine
Power Cable Systems, 2004 (reaffirmed 2010).
09. McAllister D (1982). Electric Cables Handbook, Granada Technical Books Ltd, 1982, ISBN 0-246-
11467-3
10. Moore GF, “Electric Cables Handbook”, Third Edition, BICC Cables, Blackwell Science, 1998,
ISBN: 0632040750
11. Offshore Transmission Technology, entsoe, European Network of Transmission System
Operators for Electricity, 24.11.2011, prepared by the regional group North Sea for NSCOGI
(North Seas Countries’ Offshore Grid Initiative)
12. Tanaka, T and Greenwood, A, “Advanced Power Cable Technology, Volumes I & II, CRC Press,
Inc. ISBN 0-8493-5165-0 and ISBN 0-8493-5166-9, 1983
13. TB 370 Integration of Large Scale Wind Generation Using HVDC and Power Electronics
14. Worzyk T (2009) Submarine Power Cables: Design, Installation, Repair, Environmental Aspects,
Power Systems, Springer, ISBN 978-3-642-26916-5
System design:
20. Foxall R G et al (1984). Design, Manufacture and Installation of a 525 kV Alternating Current
Submarine Cable Link from Mainland Canada to Vancouver Island. Paper 21-04, Cigré Session
1984, Paris, France
21. Giorgi G et al. (2002). The Italy – Greece HVDC Link, Cigré paper 14-116, Cigré session 2002,
Paris, France
22. TB 531 Cable Systems Electrical Characteristics
23. Worzyk T (2007). 100 years of high voltage DC links, Modern Power Systems, 2007, Vol 27; No.
11
Page 153
Offshore Generation Cable Connections
Cable design:
24. Bow, K.E., “Development of an Under-jacket Moisture Barrier Cable as a Counter Measure
against Treeing”, IEEE Transactions on Power Delivery, Vol. 5, No. 1, January 1990, pp. 47-53
25. Bow, K.E., “New Developments in Medium and High Voltage Cable with Laminate Sheaths as
Moisture Barriers”, IEEE Electrical Insulation Magazine, Sept.-Oct. 1993 Volume 9, Issue: 5, pp.
17-28
26. Chong Y L et al. (2007). Temperature Effect on Space Charge Dynamics in XLPE Insulation,
IEEE Transactions on Dielectrics and Electrical Insulation Vol. 14, No. 1; February 2007
27. Eoll C K (1975). Theory of Stress Distribution in Insulation of High-Voltage DC Cables: Part 1,
IEEE Transaction on Electrical Insulation, Vol. Ei-10, No. 1 March 1975
28. Goodwin F E et al (1994). Recent technological developments for lead sheathed cables.
Transmission and Distribution Conference, 1994., Proceedings of the 1994 IEEE Power
Engineering Society Volume , Issue , 10-15 Apr 1994, p. 568ff
29. Hagen ST & Ildstad E; “Reduction of AC breakdown strength due to particle inclusions in XLPE
cable insulation”; Conf on Power cables and Accessories 10kV – 500kV 1993 pp 165 – 168
30. Jeroense M J P (1997). Charges and Discharges in HVDC Cables: in particular in mass-
impregnated HVDC cables, Ph.D. Thesis, Delft University of Technology, The Netherlands, 1997,
also published as ISBN 90-407-1438-X at Delft University Press
31. Leebeck, A., “Longitudinal Watertight XLPE-Insulated Cables”, Power Technology International,
1990, pp. 257, 258, 260
32. Orton HE and Hartlein R., “Long-life XLPE Insulated Power Cables”. 2006
33. Ross R et al (1998). Application of Polyethylene sheath and swelling powder against water
treeing. IEEE Intern. Conf. on Conduction and Breakdown in Solid Dielectrics, June 22-25, 1998,
Västerås, Sweden
34. Schaefer, W. and Graber, P., “Swellable Non-wovens for Cables”, Wire Industry Vol. 57, No. 670,
October 1989, pp. 629-632, 635
35. TB 268 Transient voltages affecting long cables
36. TB 446 Advanced Design of Metal Laminated Coverings. Recommendations for Tests, Guide to
Use, Operational Feed Back
37. TB 272 Large cross-sections and composite screens design
Cable installation:
38. Allan P G (2001). Hydrographic Information and the Submarine Cable Industry. Proc. Hydro
2001, Norwich, UK, March 2001
39. Allan P G et al. (2001). The selection of Appropriate Burial Tools and Burial Depths, Displayed at
SubOptic, Kyoto, May 2001
40. Carbon Trust, CTC835, February 2015, Cable Burial Risk Assessment Methodology Guidance for
the Preparation of Cable Burial Depth of Lowering Specification
41. Det norske Veritas DnV-RP-F109: On Bottom Stability of Offshore Pipeline Systems
42. Doyen H et al. (1989): Experiences with Different Cable Designs and Laying Methods in
Conjunction with the Power Supply of the Islands in the North and Baltic Sea, CIRED 1989
43. Hettinger F et al. (2006). Cable and Pipeline Burial at 3000 Meters, Oceans 2005, Sept 19-23,
Palmer A C and King R A (2006). Subsea Pipeline Engineering, PennWell, Tulsa, Ok., USA
44. ICPC Recommendation No. 10 The Minimum Requirements for Load and Lay Reporting and
Charting
45. ICPC Recommendation No. 11 Standardization of Electronic Formatting of Route Position Lists
46. ICPC Recommendation No. 6 (2007). Recommended Actions for Effective Cable Protection (Post
Installation)
47. Mechanical Protections, IEEE Trans. On Power Delivery, Vol. 7, No 2, April 1992
48. Review of cabling techniques and environmental effects applicable to the offshore wind farm
industry, BERR, January 2008
Page 154
Offshore Generation Cable Connections
49. Sharples M, P.E. Offshore Electrical Cable Burial for Wind Farms: State of the Art, Standards and
Guidance & Acceptable Burial Depths, Separation Distances and Sand Wave Effect, Offshore
Submarine Power Cable, November 2011
50. TB 476 Cable Accessory Workmanship on Extruded High Voltage Cables
51. Worzyk T, Karlstrand J, “On the Optimal Burial Depth of Submarine Power Cables”, Jicable 2011,
Paper A.7.4
Testing:
52. Schikarski P et al. (1999). Two Years of Experience with a Mobile Resonant Test System for
Testing Of Installed Medium- And High Voltage Power Cables, Int. Symp. On High-Voltage
Engineering, London, UK, August 1999
53. TB 415 Test Procedure for HV Transition Joints for Rated Voltages 30 kV up to 500 kV
54. Balog G et al. (2006). Vortex Induced Vibration on Submarine Cables, Cigré Paper B1-208, Cigré
Session 2006.
55. Hauge O et al (1988) Performance of the ± 250 kV HVDC Skagerrak submarine cables. IEEE
Trans. Power Delivery, Vol. 3, No.1, January 1988
56. Vandiver J K et al. (1988). Predicted and Measured Response of Flexible Cylinders in Sheared
Flow, Proc. ASME Winter Annual Meeting, Symposium on Flow-Induced Vibration, Chicago,
December 1988.
Associated Organisations
Below is a list of organisations that deal with either the electrical, material or installation aspect of the
cable system or all of the above. These organisations can hold useful information.
• AEIC
• ANSI
• ASTM
• CENELEC
• CIGRE
• EUROPACABLE
• EWEA
• ICC
• ICEA
• ICF
• ICPC
• IEC
• IEC Catalogues
• IEEE
• IEEE DEIS
There may be other national bodies or companies that can also provide useful information.
Page 155
Offshore Generation Cable Connections
13 APPENDICES
Appendix A - Selection of cable routes
A.1 Steps to examine during route selection
The processes to find the best cable route and to obtain the necessary permits can be run in parallel, but
it is often an advantage to make some of the studies and surveys in a specific order. However, it is not
possible to provide an overall sequence which has to be followed rigidly every time, but the flow chart
below suggests an order in the initial work that can often be used.
Page 156
Offshore Generation Cable Connections
A new offshore generation site has a possible 14 routes. To correctly select one route and have a
reasonable back up plan some analysis has to be undertaken. These routes go through a selection
process of three rounds, as seen below.
Round 1
1. The first route goes through a highly mobile sand bars and open rock fissures some spanning
100 m with a depth of 500 m. A small number of wrecks with some minor historical interest is in
the area. The route is technically possible, very challenging and very costly.
2. The second route has a gentle slopping route with minor wrecks, but there is a high degree of
marine life, though none is protected/endangered.
3. The third route has some sand bars, and is a major historic location; e.g. Trafalgar, with a diverse
marine life settled on the wrecks.
4. The fourth route has some sand bars, a few wrecks, but has a diverse marine life/ecology.
5. The fifth route has a highly mobile sand bar, along with a diverse marine life which has specific
requirements for their protection.
6. The sixth route has an easy installation route, but it has both a diverse and protected marine life
with heavy seasonal restrictions.
7. The seventh route has a relatively easy installation route, with some minor restrictions due to the
environment. There are a few historic wrecks with some wildlife.
8. The eighth route has a relatively easy installation route with little environmental issues or
restrictions.
9. The ninth route has an easy installation with some requirements due to a few areas of natural
interest and historical sites.
10. The tenth route has some shifting sand bars, the main interest is the coral reef, which has a large
number of restrictions due to the protected nature of coral reefs.
11. The eleventh route has a dormant underground volcano, with heavy restrictions on vibration,
burial depths, and routine surveys and monitoring vessels. The route is over sharp rocky surface,
with a large diversity using the latent heat.
12. The twelfth route has a challenging installation route, with some small rock fissures, sheer
subsea cliffs, minor restrictions, (no collapsing a subsea cliff) there is little to no marine life.
13. The thirteenth route has a challenging installation route, with some small rock fissures, sheer
subsea cliffs, minor restrictions, (no collapsing a subsea cliff) there is little to no marine life. In
addition there is a historic wreck /site which ran aground.
14. The fourteenth route has some challenges with the route terrain wise and due to natural
formations and a diverse marine life with some restrictions.
An assessment and score is given for each route as seen in Table 13-1. From this a number of informed
decisions are taken and a number of routes are eliminated in favour of the more consentable/practicable
routes.
Round 2
2. The second route has a higher than normal ecological system with some
recommendations/restrictions made. The soil survey indicates good soil for installation, stable
and the bathymetry indicate an easy installation. Due to the ecological report for this route there
has been an increase in marine consents, along with installation through a dredging area. Along
the route there is an increased chance of un-exploded ordnance due to an old dumping site in the
near vicinity. No crossings involved.
4. The fourth route has higher than normal ecological system with some
recommendations/restrictions made. The bathymetry indicates rocks and an undulating ground
where before it was believed to be flat. Due to the ecology report along this route there has been
an increase in some marine consent. One submarine fibre optic cable crossing.
Page 157
Offshore Generation Cable Connections
7. The seventh route has a moderate ecological system, with subsea fauna and flora, the soil trials
and bathymetry indicate there are some rocks and some stiff soils. The route crosses a
submarine fibre optic cable and a submarine power cable. There is increased marine traffic along
the route.
8. The eighth route has a deep channel crossing; this crossing is a main seaway traffic route. The
restrictions and consents required to limit shipping for installation, the route also contains a fibre
optic submarine cable that requires crossing. The ecology and soil stability test reports were
positive.
9. The ninth route had no crossings, with little to no shipping traffic, soil stability trials found the soil
to be highly turbid and rocky. An ecology report found a species not believed to be in the area
before; the report includes restrictions and requirements to protect the species.
12. The twelfth route has good soil conditions, the lay of the seabed is good for installation purposes,
there is little to no marine traffic. There is a high pressure oil pipeline pumping hot oil from an oil
field to an onshore refinery. The risk of damaging the pipeline and subsequent losses are the
main factors here.
An assessment and score is given for each route as seen in Table 13-1. From this a number of informed
decisions are taken and a number of routes are eliminated in favour of the more consentable/practicable
routes.
Round 3
2. The second route: The soil and burial assessment is carried out and the route is optimised and
found to be relatively easy. Due to no crossings there is no crossing agreement to be made,
again an easy route. The dialogue with the local council regards the landfall and sea defence and
local populace proves to be difficult.
4. The fourth route: The soil and burial assessment is carried out and the route is optimised and
found to be a minor challenge. There are some minor issues with the crossing agreement with
the fibre optic owner. There is a strong local opinion against the landfall for this route.
12. The twelfth route: The soil and burial assessment is carried out and the route is optimised and
found to be a minor challenge. The crossing agreement and risk with the oil pipeline has come
down due to agreed mitigation. The risk may have come down to 1/5 but the outcome may still be
5/5. The local populace are indifferent to the landfall and appreciate it may bring benefits to the
local community.
In order to make a decision on which route to proceed with all three routes must be investigated in some
detail and a preference determined – usually it is difficult to get local government and population support.
Page 158
Offshore Generation Cable Connections
Route 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Hydrographic survey 10 1 4 4 8 1 2 2 1 4 9 7 8 4
Initial Environmental 2 2 2 5 5 4 2 1 1 2 9 1 2 4
Round 1
Environmental requirements 2 4 5 3 5 8 2 2 5 9 8 2 2 3
Ecology Report 6 6 5 1 8 1
Bathymetry Survey 1 5 3 4 5 2
Undischarged Ordnance
2 1 2 2 1 1
survey
Marine Consents 5 3 4 7 1 3
Marine traffic 1 1 2 7 1 1
Finalisation of crossing
1 3 6
negotiations
Ease of Dialogue with local
8 5 3
government
Page 159
Offshore Generation Cable Connections
B.1 Bathymetry
Indicates seabed geometry/geology/features, water depth in m.
B.2 Enviromental
Bathymetry with an overlay of environmental layers, indicating high levels of fauna and flora.
Page 160
Offshore Generation Cable Connections
Page 161
Offshore Generation Cable Connections
Page 162
Offshore Generation Cable Connections
FIGURE 13-9 DEPLOYMENT OF VARIOUS SHALLOW-WATER SUB-BOTTOM PROFILING SYSTEMS (STOKER ET AL.
[13.1])
Page 163
Offshore Generation Cable Connections
Several physical parameters of the acoustic signal emitted, such as output power, signal frequency, and
pulse length affect the performance of the instrument and influence its usefulness in various marine
environments. Increased output power allows greater penetration into the substrate. However, in the case
of harder seabeds (e.g. gravels or highly compacted sands) or very shallow water, higher power will result
in multiple reflections and more noise in the data. Higher frequency systems (up to 20 kHz) produce high
definition data of sediment layers immediately below the seabed, and are able to discriminate between
layers that are close together (e.g. 10's of cms). Lower frequency systems give greater substrate
penetration, but at a lower vertical resolution. Longer pulse length transmissions (or 'pings') yield more
energy and result in greater penetration of substrate. However, they decrease the system resolution. The
depth of penetration also depends on the hardness of the upper layers and is significantly limited by the
presence of gas deposits.
Page 164
Offshore Generation Cable Connections
Substation 1
Substation 2
Export
Export Cable #2
Cable #1 Export
Cable #3
Export
Cable #4
FIGURE 13-10: LONDON ARRAY WIND FARM LAYOUT AND EXPORT CABLE ROUTE
The original consent was for 1000 MW, with a Phase 2 of up to 370 MW dependent on the lifting of a
consent constraint related to the impact of the extension on wintering birds. The owners of the project
announced in February 2014 that they would not be proceeding with Phase 2.
Page 165
Offshore Generation Cable Connections
OWF (400 MW, offshore platform converter (±150 kV, 400 MW), transformer,
140 km offshore and 10 offshore cable switchgear, auxiliary systems, etc.
km onshore route length) onshore cable ±150 kV 1600 mm² Cu cable
onshore substation at PGCTSO ±150 kV 2400 mm² Al cable
converter (±150 kV, 400 MW), transformer,
switchgear, auxiliary systems, etc.
OWF (400 MW, offshore platform converter (±150 kV, 400 MW), transformer,
200 km offshore and 10 offshore cable switchgear, auxiliary systems, etc.
km onshore route length) onshore cable ±150 kV 1600 mm² Cu cable
onshore substation at PGCTSO ±150 kV 2400 mm² Al cable
converter (±150 kV, 400 MW), transformer,
switchgear, auxiliary systems, etc.
6
PGC: Point of grid connection = offshore grid connection point
7
PCC: Point of common coupling = on-offshore transition point
8
PGCTSO: Point of grid coupling = onshore grid coupling point
Page 166
Offshore Generation Cable Connections
Figure 13-11 present specific values of investment-, loss- and maintenance costs for the different
technical concepts for grid connection of a fictitious 400 MW OWF for different offshore route length
(Source: Prof. Dr.-Ing. habil. Lutz Hofmann, June 2012) [13.2].
It is recommended to use the case study figures with reservation, since the relative prices may have
changed. The “start-costs” of HVDC connections are not well known and may influence the break-even
point.
FIGURE 13-12 GERMAN PLAN FOR OFFSHORE WIND POWER PLANTS IN NORTH SEA
Page 167
Offshore Generation Cable Connections
Choshi, Chiba, JP 22 3 2
Hirono, Fukushima,
22 25 2
(floating), JP
Rudong Seashore,
35 5 240
Jiangsu, CN
Middelgrunden, DK 36 4 40
TABLE 13-3 EXAMPLES OF EXPORT CABLES FOR OFFSHORE WIND FARMS IN SERVICE [13.4]
Examples of planned offshore wind farms with HVDC export cables. The list shows expected voltage
levels, route length and installed capacity.
Insulation Submarine Installed
DC voltage Land route
Project, country material route length Capacity
[kV] length [km]
[km] [MW]
Borwin I, DE ±150 XLPE 125 75 400
TABLE 13-4 EXAMPLES OF OFFSHORE WIND FARMS UNDER CONSTRUCTION WITH HVDC EXPORT CABLES [13.5]
Page 168
Offshore Generation Cable Connections
FIGURE 13-13: CALCULATED LOAD FACTORS BASED ON THE FINO 1 DATA, 7 DAY AVERAGE VALUE (BLUE) AND 45
DAYS (RED) AVERAGE VALUE, 100 M TURBINE HEIGHT, FROM MARCH 2004 TO MARCH 2011
Design criteria from a German TSO for the cable rating based on the above calculated load factors
1) The whole cable must be capable to transmit 100% load
2) Obtaining local environmental temperature rise criterion with so called wind load: 77% continuous
preload, 99% peak load for 7 day, 77% followed load for 45 days
Page 169
Offshore Generation Cable Connections
The example below is from an offshore wind farm during one winter month (January). The current is
shown in Ampere as a function of time (days). The measured values are 5 minutes values.
In some Danish examples both of the load profiles 1 and 2 shown below have been used as concurrent
requirements to the export cables. So far no rating problems have been found.
800
700
600
Load [A]
500
400
300
200
100
0
0 200 400 600 800 1000 1200
Time [hours]
Page 170
Offshore Generation Cable Connections
800
700
600
Load [A]
500
400
300
200
100
0
0 200 400 600 800 1000
Time [hours]
The value of IR in Table 13-5 is important. In the example above IR is equal to the highest measured value
(510 A). Normally it should be based on the total installed and running power (700 A).
In each case the probability of maximum load and load duration should be assessed.
But an optimization of the export cable could be made by looking at the actual load generated by the
wind, especially if the cable is buried more than one metre e.g. in the landfall, resulting in long thermal
time constants of the cable surroundings (many months or even years). This, however, requires a method
to assess the worst predictable production scenario or “worst case load event” in the lifetime of the cable.
The reason for trying this approach on the offshore export cable of the HR3 project, was because it is to
be installed in an area with great seabed mobility near the shore, so in this location it is expected that the
cable can be covered with up to 5 metres of sand. Therefore it was expected that a significant saving
would be achieved by looking at the dynamic load of the wind farm. It is important in this case as it was
predicted that a requirement to transmit the maximum power continuously, could potentially result in a
need for a second cable, even though a 245 kV single cable solution was used on the 400 MW sister
wind farm project at Anholt.
The data used in the example are based on production data from a nearby wind farm (Horns Reef 2,
HR2) adjusted for the later development of wind turbines, but checked against historical wind data and
wind data models for the actual area in combination with “power curves” for state of the art wind turbines.
The conversion of wind models to power production is not covered in this example.
The resulting load curve for a “worst case load event” that was included in the Invitation to Tender, and is
given in Figure 13-17.
Page 171
Offshore Generation Cable Connections
FIGURE 13-17 WORST CASE LOAD EVENT GIVEN IN THE TECHNICAL SPECIFICATION FOR THE 400 MW DANISH
WIND FARM HORNS REEF 3
Before starting the analysis it is important to remember that the cable losses are proportional to the AC
resistance in the cable times the square of the current. Therefore the average of current squared (and
thus the MW production squared) will be related to the losses. It is therefore also relevant to talk about
the RMS value of the current for a certain period, referring to the “long term RMS” value seen in scale of
the thermal time constants, rather than the 50 Hz RMS.
1 𝑡=𝑇
𝐼𝑅𝑅𝑅−𝑇 = � � 𝐼2 (𝑡)𝑑𝑑
𝑇 𝑡=0
EQUATION 13-1
t=time
I(t)=Expected current as a function of time e.g. at the landfall or any expected hotspot.
The charging current should be estimated in advance, so it can be included in the current I(t), otherwise
only the current proportional to the power production P(t) should be used.
2. From a (large) number of graphs showing “rolling averages” of the data with different lengths of
averages, one can get an overview of the data, and from that derive reasonable plateau values
that can be used to find the “worst case load event”, that can be used for dimensioning, with the
requirement that the allowed maximum conductor temperature is not exceeded at the end of the
event.
The number of plateaus in the “worst case load event” should be considered from case to case,
depending on the found load patterns, and the thermal time constants of the cable surroundings.
Page 172
Offshore Generation Cable Connections
Normally the thermal time constant for the cable and its immediate surroundings is considered to
be in the magnitude of hours, the cables surroundings up to 1 metre in the magnitude of days or
weeks, and the ultimate time constant of a deep buried/covered cable would be in the magnitude
of months or even years.
FIGURE 13-18 50 DAYS (1200 H) ROLLING AVERAGE OF 3.5 YEARS OF ADJUSTED WIND PRODUCTION FROM HR2.
WORST CASE ROLLING AVERAGE OF ABOUT 0.8 PER UNIT OF THE INSTALLED EFFECT OF THE
WIND FARM
Analysis
Step 1: Preconditioning
From the historical production data from HR2, adjusted to HR3 conditions, it was found, that one year
was a metrological “normal” wind year so IRMS-1year (see formula below) was used for this year, rather than
the IRMS-3year that also could have been derived from the 3,5 years of production data available.
𝑡=1𝑦𝑦𝑦𝑦
𝐼𝑅𝑅𝑅−1 𝑦𝑦𝑦𝑦 1 1
= � � 𝐼2 (𝑡)𝑑𝑑 = 0,7 [𝑃𝑃]
𝐼𝑚𝑚𝑚 𝐼𝑚𝑚𝑚 1𝑦𝑦𝑦𝑦 𝑡=0
EQUATION 13-2
Notice that this value of course differs from the average production of the wind farm.
9
The 0.7 is used as the level of the preconditioning plateau in Figure 13-17.
9
This normal RMS value 0.7 would also be useful for assessing the expected annual load losses in the cable:
Either to request the losses P at 0.7 x Imax
or
Request the full load loses (P at Imax) - as is often requested anyway and multiply with 0.7x0.7=0.49 (0.49 would be the time of the
equivalent full load loss in PU)
Neither will be fully accurate since temperature of the conductor will be too low in the first case and too high in the second case.
Page 173
Offshore Generation Cable Connections
The three worst case plateaus are chosen because they contain a period of generally high production of
energy (wind) and they also contain periods with maximum or almost maximum production. These
periods are identified from observation of the rolling averages with increasing period, and keep an eye,
where the maximum averages seem to remain at the same high level, as the periods over which the
rolling averages is taken, is gradually increased.
The longest (and lowest) plateau was chosen to be 1000 hours (1200 hours minus the length of the two
higher plateaus (200 hours) that was found inside the same event). The level of this plateau was found
as:
𝑡=1000ℎ
𝐼𝑅𝑅𝑅−1000ℎ 1 1
= � � 𝐼2 (𝑡)𝑑𝑑 = 0,83 [𝑃𝑃]
𝐼𝑚𝑚𝑚 𝐼𝑚𝑚𝑚 1000ℎ 𝑡=0
EQUATION 13-3
This means that the 1000 hours, are the ones not including the worst 200 hours for calculating the top
plateaus.
The process was repeated for the two last plateaus, incidentally found in the beginning of the 1200 hour
period.
The final plateau (80 h of full load) is very consistent with the maximum time for a low-pressure system to
pass the wind farm.
IDENTIFICATION OF PLEATAUS
Below, an attempt is made to illustrate some of the process of identifying the plateaus. The process does
however require a great deal of intuitive assessment of the data that cannot easily be described in print.
Page 174
Offshore Generation Cable Connections
FIGURE 13-20 96 HOURS AND 120 HOURS ROLLING AVERAGE OF 3.5 YEARS OF ADJUSTED WIND PRODUCTION
FROM HR2. IDENTIFIES ONLY TWO 96 HOURS EVENT WITH CONSTANT FULL LOAD, BUT THESE ARE
NOT IDENTIFIED IN PERIODS WITH OTHERWISE CONSISTING PRODUCTION, SO THESE PERIODS ARE
NOT CONSIDERED.
FIGURE 13-21 192 HOURS AND 240 HOURS RUNNING AVERAGE OF 3.5 YEARS OF ADJUSTED WIND PRODUCTION
FROM HR2 IDENTIFIES TWO 200 HOURS EVENT OF ALMOST FULL LOAD, FURTHER ANALYSES GAVE
THE 120 HOUR LONG 0.95 PLATEAU AND THE 80 HOUR LONG 0.95 PLATEAU.
FIGURE 13-22 15 DAYS ( 360 H) AND 30 DAYS (720 H) RUNNING AVERAGE OF 3.5 YEARS OF ADJUSTED WIND
PRODUCTION FROM HR2, CONFIRMS THAT THE 1.00 AND 0.95 PLATEAUS ARE FOUND INSIDE
PERIODS THAT ALSO CONTAINS CONSISTENT HIGH PRODUCTION.
FIGURE 13-23 50 DAYS (1200 H) AND 90 DAYS (2160 H) ROLLING AVERAGE OF 3.5 YEARS OF ADJUSTED WIND
PRODUCTION FROM HR2, IDENTIFIES THE LONGEST PERIOD AND THE LOWEST PLEATEAU, AS THE
PERIODE JUST BEFORE THE PEEK VALUE START TO APPROACH THE PRECONDITIONING LOAD.
Page 175
Offshore Generation Cable Connections
As it happened, the data for the worst case event was taken from a single 1200 hours event December
2011, the second event of Figure 13-21 and Figure 13-22 and the peak of Figure 13-23.
An expansion of the event is given in Figure 13-24. These data were subjected to the appropriate RMS
integration over time to get the plateaus given for the “worst case load event” in Figure 13-17. It is seen
that in the worst case load event, the 200 hours (80+120 h) was even moved to the end of the event,
rather than in the beginning where it actually occurred.
FIGURE 13-24 ACTUAL HOUR-BY-HOUR ADJUSTED WIND PRODUCTION DATA FROM HR2 FOR THE IDENTIFIED
« WORST CASE LOAD EVENT» DECEMBER 2011.
Result
On HR3, with a burial depth of up to 5 metres offshore close to the coast, a 25% reduction of conductor
cross-section gave a material saving of approximately 10-15 %, but this also gave the possibility to use a
smaller installation vessel, with a possible saving on the installation costs of 25-50%.
It is even possible that no competitive offers would have been received with a single cable solution for the
400 MW wind farm without the reduction of the conductor cross-section.
A contract based on the described “worst case load event” given in Figure 13-17 was signed early 2014.
The conductor temperature was calculated by the manufacturer as seen in Figure 13-25.
Page 176
Offshore Generation Cable Connections
85
80
75
Temperature oC
70
Surface
Conductor
65
60
55
50
45
0 5 10 15 20 25 30 35 40 45 50
Duration days
FIGURE 13-25 CABLE TEMPERATURES IN THE OFFERED 245 KV 3X1800 MM2 AL SUBMARINE CABLE, CALCULATED
BY THE CABLE MANUFACTURER BASED ON THE WORST CASE LOAD EVENT. DURATION IS
STARTING AT THE BEGINNING OF THE 1000 HOUR PLATEAU. IT IS SEEN THAT CONDUCTOR
TEMPERATURE STAYS BELOW 90°C.
Page 177
Offshore Generation Cable Connections
The mentioned burial depth is not recommended practice but maximum depth that might be obtained
with the specific tool. Burial depth should be based on risk assessment. In general it is not
recommended to bury cables more than 1-2 m over a longer distance.
Page 178
Offshore Generation Cable Connections
Reflection factor r = z −z
2 1
length calculation: l = t x v/2
z +z
2 1
TDR Example
Page 179
Offshore Generation Cable Connections
Surge
Generator
Thumper
TDR
consider ionisation time delay on 1st period ICM on XLPE Submarine Cable
FIGURE 13-28 ICM IMPULSE CURRENT METHOD FOR APPLICATION TO HIGH IMPEDANCE FAULTS
Page 180