Presenting By: Pemin Glen Lobo


Weekly update
Date Worked on Status Reason for
pending

02/08/2021 ● Explored the features ESP-WROOM-32 microcontroller ,also why● Completed ●

it is a better and versatile device when compared to other


microcontrollers.
03/08/2021 Setting up the Arduino IDE with ESP-WROOM-32 and implementingCompleted
the blink sketch. ●

04/08/2021 ● Did more experiments on esp32 and made a list of requiredCompleted


components for the next experiment. ●

05/08/2021 ● Went to SP road to buy some of the components required for Completed
experiment and did experiment that is using analog input of ●
ESP32 to read potentiometer DC voltage.

06/08/2021 ● Worked on Plotting real time serial data in MATLAB ofCompleted


potentiometer voltage. ●

07/08/2021 Went to field work to Surgident with Dileep.



Weekly update
Date Worked on Status Reason for
pending

09/08/2021, ● Worked on Enetra installation. Completed


10/08/2021
and ●

11/08/2021

12/08/2021 ● Helped in dispatching of the device and assisted Basavaraj sir to Completed
bring the syringe pump from hebbal. ●

13/08/2021 ● Went to bbmp hospital for testing and configuration of the Completed
device. ●
Weekly update
Date Worked on Status Reason for
pending

16/08/2021 Did experiment on how to send the message between two devices Completed
and through Bluetooth and WIFI using esp32.
17/08/2021 ●

19/08/2021an Worked on the task given by balu sir that is generating sine wave in Completed
d 20/08/2021 matlab and to measure the wavelength and frequency of the ●

generated signal.

21/08/2021 ● Went to bbmp hospital Vijayanagar to assist Dileep. Completed



Date
Estimation
Will work on
for this week
Estimation Status

23.08.2021 to ● Task given by balu sir


28.08.2021
Weekly update
Date Worked on Status Reason for
pending
24/08/2021 Worked on the task given by balu sir that is generating sine wave in esp32 and Completed
and plotting it in MATLAB. Read a research paper on Breathing Patterns in Preterm●
25/08/2021 and Term Infants Immediately After Birth.(Observations: High peak but short
inspiratory phase and low peak but long expiratory phase).

26/08/2021 ● Had a discussion with balu sir about the implementation of project. Completed
Explored basics of Java programming.

27/08/2021 Attended the meeting of the graphene project. Read a research paper onCompleted
Monitoring respiratory pattern in adult and infant using pulse radar sensor. ●


(Observations: Irregular breathing with fast and slow phases also very short
apnea events happen very frequently in babies under six months ).
28/08/2021 Worked on the task given by balu sir that is configuring the GPIO pins and
and connecting the output of that pin to analog pin from which need to plot ●
30/08/2021 square wave. Explored string methods in Java.

31/08/2021 Read a research paper on Using ECG Surface Electrodes in Measurement of Completed
Respiration Rate for Preterm Infants(Observations: Frequency band lies in the ●
range of 0.4-2.0Hz and artifacts from 0-0.4Hz and amplification of 1000 was
done).
Date
Estimation
Will work on
for this week
Estimation Status

01.09.2021 to ● Will work on the task assigned by balu sir.


04.09.2021
Weekly update
Date Worked on Status Reason for
pending
01/09/2021 Assisted Basavaraj sir with the configuration of the bedside monitors. Completed
and ●

02/09/2021

03/09/2021 ●
Read research paper and the observations were frequency band lies in theCompleted
range of 0.4-2.0Hz,artifacts from 0-0.4Hz and amplification of at least 1000
was needed.

04/09/2021 Configuring the GPIO pins and connecting the output of that pin to analog pin Completed
and from which need to get square a wave. ●

05/09/2021 Studied java programming.

06/09/2021 Studied signal processing that is band pass filtering, voltage divider circuit
which will be needed for the implementation of project Completed
Studied java programming. ●

07/09/2021 Configuration of the Enetra.



Date
Estimation
Will work on
for this week
Estimation Status

13.09.2021 and ● Designed the band pass circuit and calculated the Completed
14.09.2021 resistor value.If we take capacitor value as 1µF and ●

based on the desired frequency range we get R1=400KΩ


and R2=800KΩ.
Studied java programming.

15.09.2021 to ● Design the amplification circuit and should make list of


18.09.2021 the required components needed in signal processing
work.