Professional Documents
Culture Documents
DG Cement WHR PDD
DG Cement WHR PDD
CONTENTS
D. Environmental impacts
E. Stakeholders‟ comments
Annexes
Annex 1: Contact information on participants in the proposed small scale project activity
1
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
2
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
DGKCC Waste Heat Recovery and Utilization for 10.4 MW Power Generation at Dera Ghazi Khan Plant
Version 11
Date: 07/11/2011
The project activity involves the installation of waste heat recovery systems to generate electricity at D.G.
Khan Cement Company (hereafter referred to as DGKCC), Khofli Sattai Dera Ghazi Khan Plant. D.G.
Cement Khofli Sattai Plant is part of Nishat Group which ranks among top five business houses of
Pakistan. DGKCC was established in 1978 and started its commercial production in April 1986 with 2000
Tonnes per Day (TPD) clinker based on dry process technology. Plant and machinery was supplied by
UBE Industries of Japan. Nishat Group acquired DGKCC in 1992 under privatization initiative by
Government of Pakistan and immediately undertook the optimization by raising the capacity to 2200 TPD
in 1993. To meet the increasing demand, another production line of 3300 TPD was added in August,
1997. The plant and machinery was supplied by M/S F.L. Smidth of Denmark.
The capacities of both kilns were enhanced in 2005; kiln 1 was upgraded to 2700 TPD whereas the
capacity of kiln 2 was increased to 4000 TPD
DGKCC currently holds QMS (Quality Management System) and EMS (Environmental Management
System) certifications, ISO9001:2000 and ISO14001:2004, respectively. The plant has two kilns with
total clinker production capacity of 6700 TPD (Kiln 1: 2700 TPD & Kiln 2: 4000 TPD) through dry
process.
Currently at DGKCC, almost all the waste heat from the clinker production process is vented to
atmosphere. The cement factory has its own captive power plant which constitutes four Niigata
18V32CLX engines (total capacity 23.84 MW) and three Wartsila 20V34SG engines (total capacity 25.42
MW). Niigata engines run on Heavy Fuel Oil (HFO) and were installed in 1996-1997, whereas Wartsila
engines run on natural gas (NG) and were recently commissioned in 2006. Diesel is consumed as an
auxiliary fuel in Niigata engines. In addition to captive power plant, the cement factory has 20 MW grid
electricity import connection. No electricity is exported to the grid.
The power export to grid is prevented by reverse current protection system already in place at DGKCC.
The system consists of a relay which detects the flow of power in reverse direction and generates an
alarm when there is such a reverse flow. Furthermore, a meter is also installed which can be used for
detection of reverse current flow. Once reverse power is detected and alarm is generated the operator
takes necessary action to stop this reverse flow. In this way it is ensured that no electricity is exported to
the grid. A same reverse current protection system has been installed for WHR project thus making sure
no electricity is fed to the grid by WHR project.
The project activity involves installation of total four heat recovery steam generators (HRSGs) of capacity
54.3 TPH and a steam turbo-generator for 9.36 MW net electricity generation. Two HRSGs will be
installed on each kiln, one at pre-heater and one on cooler. As such, the project activity will displace the
3
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
fossil fuel based grid electricity imports to DGKCC. The project will reduce Greenhouse Gas (GHG)
emissions by 33,845 t CO2 per year and will lead to sustainable development.
Environmental Development
Social Development
Economic Development
Technology Development
Kindly indicate if
the Party involved
Name of Party involved Private and/or public entity(ies)
wishes to be
((host) indicates a host project participants
considered as
Party) (as applicable)
project participant
(Yes/No)
Islamic Republic of Pakistan D.G. Khan Cement Company Ltd.
No
(host) (private entity)
Carbon Services (Private) Limited
Islamic Republic of Pakistan No
(private entity)
First Climate (Switzerland) AG
Switzerland No
(private entity)
4
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Punjab
5
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Source: http://maps.google.com
6
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
A.4.2. Type and category(ies) and technology/measure of the small-scale project activity:
In accordance with Appendix B of the simplified modalities and procedures for small-scale CDM project
activities, the Project activity fall under the following type and category:
The project activity involves installation of four HRSGs and one steam turbo-generator. All the waste
heat recovered from clinker production process would be utilized for power generation and the hot
exhaust from HRSGs would be used to preheat the raw materials. Two HRSGs (12.2 tph and 8.7 tph on
pre-heater (PH) and cooler (AQC) end respectively) on 2700 TPD kiln (Kiln 1), and two (20.0 tph and
13.4 tph on pre-heater (PH) and cooler (AQC) end respectively) on 4000 TPD kiln (Kiln 2) will be
installed. The superheated steam generated by the HRSGs will be passed to 10.4 MW steam turbine to
generate net 9.36 MW electricity. The electricity generated by the project activity will be consumed
within the cement works. Net electricity generated by the project activity (70,087.68 MWh/yr) will
displace grid electricity imports; hence this potential will result in 33,845 t CO2 reductions per year.
Kawasaki Plant Systems (KPS), Ltd is the main contractor of the project. Sojitz corporation is its local
agent in Pakistan. KPS is providing equipment for the project activity from various suppliers which
include Chinese and Japanese suppliers.
As the technology used in the project activity is new to the region, proper training was essential for
successful operation of WHR equipment. Mr. Shafqat Javed, Manager Waste Heat Recovery Project at
DGKCC, completed his training of operation and maintenance of waste heat recovery plant under
supervision of Kawasaki. He then provided further training to his subordinates at the plant.1
Name of
Quantity Manufacturer & Model Specifications
Equipment
1
All documents related to employees‟ training for new WHR system have been provided to the DOE.
7
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Cement
HRSGs
Raw
Materials
Hot exhaust for preheating
incoming raw materials
A.4.3 Estimated amount of emission reductions over the chosen crediting period:
The annual & total estimation of emission reductions for the fixed crediting period of 10 years
(01/01/2012 to 31/12/2021) is provided below:
8
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
A.4.5. Confirmation that the small-scale project activity is not a debundled component of a
large scale project activity:
According to “Guidelines on assessment of debundling for SSC project activities (Version 03, Annex 13,
EB 54)”, a proposed small-scale project activity shall be deemed to be a debundled component of a large
project activity if there is a registered small-scale CDM project activity or an application to register
another small-scale CDM project activity:
There is no registered small-scale CDM project activity or an application to register another small-scale
CDM project activity by the project participants. There are also no such projects registered in the same
category and technology within previous 2 years. Additionally, no other small scale activity is located in
the vicinity. Thus, the project activity is not a debundled component of a large scale project activity.
9
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
B.1. Title and reference of the approved baseline and monitoring methodology applied to the
small-scale project activity:
For the estimation of the capping factor, corresponding section of ACM0012 (version 03.2) is
implemented.
Referred Tools
The current project activity meets all the applicability conditions as outlined in the selected baseline
methodology AMS.III.Q/Version 03. The following table illustrates that AMS.III.Q is fully applicable to
the project activity.
The category is also applicable to project Not applicable. Project activity Category is
2 activities that use waste pressure to generate doesn‟t use waste pressure. applicable to
electricity at existing facilities. project activity.
The recovery of waste gas/heat may be a Project activity is considered as Methodology is
3
new initiative or an incremental gain in an a new initiative since the applicable to
10
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
11
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
For those facilities and recipients included in The project activity will Methodology is
the project boundary, that prior to displace electricity imports applicable to
implementation of the project activity from the national grid. (source project activity.
(current situation) generated energy on-site of energy in the baseline)
(sources of energy in the baseline), the Therefore, the credits are
credits can be claimed for minimum of the claimed for the whole crediting
6f
following time periods: period of the project activity.
(i) The remaining lifetime of
equipments currently being used;
and
(ii) Crediting period.
The waste gas/heat or waste pressure utilized Almost all waste heat (with the Methodology is
in the project activity would have been exception of minute portion applicable to
flared or released into the atmosphere in the used for heating incoming raw project activity.
absence of the project activity. This shall be materials) utilized in the
proven by one of the following options: project activity for electricity
generation would have been
(i) By direct measurements of
released to the atmosphere in
6g energy content and amount of the waste
the absence of the project
gas/heat or waste pressure for at least
activity. Appropriate evidences
three years prior to the start of the
such as Energy Bills and
project activity.
Financial Statements audited
(ii) Energy balance of relevant by competent authorities will
sections of the plant to prove that the be provided to DOE during the
waste gas/heat or waste pressure was validation.
12
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
For the purpose of this category waste The waste heat recovered from Methodology is
energy is defined as: a by-product the clinker making process applicable to
gas/heat/pressure from machines and complies with the definition project activity.
industrial processes having potential to provided above; the waste heat
provide usable energy, for which it can be from clinker production
demonstrated that it was wasted. For process was vented to the
7 example gas flared or released into the atmosphere before the project
atmosphere, the heat or pressure not activity.. The waste heat from
recovered (therefore wasted). Gases that clinker production process has
have intrinsic value in a spot market as no intrinsic value in a spot
energy carrier or chemical (e.g., natural gas, market as energy carrier or
hydrogen, liquefied petroleum gas, or their chemical. Thus this category is
substitutes) are not eligible under this applicable to the waste heat
13
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
The baseline emissions for the project activity relate to electricity imported from the grid. Pakistan has
two grid operating companies, National Transmission and Despatch Company (NTDC) and Karachi
Electric Supply Company (KESC). Both companies operate their own network within the unified grid.
Within this system baseline emission sources are limited to CO2 only.
There is no auxiliary fuel combusted in the project activity to supplement waste gas and the turbogenset
consume its own electricity for auxiliary needs. Similarly, the project activity does not incinerate any
waste gas to generate energy. Therefore, the project emissions are considered zero.
Waste Heat
Kiln 1
2700 TPD
Clinker
CEMENT WORKS
Clinker
Grid
Kiln 2
4000 TPD
Waste Heat
PROJECT BOUNDARY
In the baseline situation, only a small portion of the waste heat generated is recovered from the feed end
of the kiln and is circulated for preheating raw inputs and drying of coal. The high temperature exhaust is
vented to the atmosphere. There are no other potential alternatives of waste heat utilization in the vicinity
of the factory.
14
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
DGKCC receives electricity from two sources, grid and captive power plant. However, grid supply in
Pakistan is not reliable; therefore the captive power plant is used as base load, and does not modify its
regime once the project activity is in place. Table B.4.1 given below shows that share of grid electricity is
decreasing every year due to its unreliability. Therefore, the electricity produced by the project activity
only displaces grid electricity. This is also toward conservativeness as the grid electricity emission factor
(0.489 t CO2/MWh) is lower than the captive power plant emission factor (0.55 t CO2/MWh, see detailed
calculation in annex 3).
Table B.4.1: Historical data
Sep 2004 to Sep 2005 to Sep 2006 to
Average
Aug 2005 Aug 2006 Aug 2007
Clinker production by Kiln 1 (t/yr) 480,671 916,171 963,721 786,854
Clinker production by Kiln 2 (t/yr) 1,156,394 1,253,132 1,350,653 1,253,393
Total clinker production (t/yr) 1,637,065 2,169,303 2,314,374 2,040,247
HFO consumption by Kiln 1 (t/yr) 1,108 1,737 841 1,299
Coal consumption by Kiln 1 (t/yr) 67,469 131,151 139,864 112,828
HFO consumption by Kiln 2 (t/yr) 497 512 852 620
Coal consumption by Kiln 2 (t/yr) 149,879 162,041 167,994 159,971
NG consumption by Kiln 2 (MMCF2/yr) 0 0 150.084 50
Fuel energy consumption by Kiln 1(GJ) 1,655,279 3,200,592 3,372,052 2,742,641
Fuel energy consumption by Kiln 2(GJ) 3,597,051 3,887,903 4,189,812 3,891,588
Electricity imported from grid (MWh/yr) 93,704 111,774 57,189 87,556
Electricity generated by captive power
93,233 116,695 188,096 132,675
plant (MWh/yr)
Total electricity consumption (MWh/yr) 186,937 228,469 245,285 220,231
Share of grid electricity (%/yr) 50% 49% 23% 40%
Share of captive generation (%/yr) 50% 51% 77% 60%
Average specific fuel energy consumption for clinker production by Kiln 1 (GJ/t clinker) 3.486
Average specific fuel energy consumption for clinker production by Kiln 2 (GJ/t clinker) 3.105
So in the absence of project activity the only possible baseline scenario is that the waste heat is released to
the atmosphere and the project electricity used by cement plant is supplied by the national grid.
B.5. Description of how the anthropogenic emissions of GHG by sources are reduced below
those that would have occurred in the absence of the registered small-scale CDM project activity:
The starting date of the project activity is the 18th October 2007 when the contract was signed between
DGKCC and supplier of WHR project equipment. The project proponent was aware of the CDM long
before the start date of the project activity and CDM income proved to be a decisive factor in the
investment decision taken in September 2007 to implement the project3. Contract with CDM consultants
was finalized in November 2007 and during the whole implementation phase before validation DG
Cement was accompanied by CDM consultants.
2
MMCF = million cubic feet
3
Proofs for CDM awareness and consideration will be provided to DOE during validation.
15
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
16
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
The demonstration of additionality is realised through application of the latest version of the “Tool for the
demonstration and assessment of additionality (Version 5.2)”.
Step 1: Identification of alternatives to the project activity (consistent with current laws and
regulations)
Alternative 3. Construction of new power plant on the basis of gas reciprocating engines.
Although this alternative will provide outputs and services comparable to CDM project activity, still
it is not a realistic and credible alternative to the proposed CDM project activity as the circumstances
are such that the baseline situation does not require DGKCC to make an investment for construction
of new power plant.
The existing power sources (grid + captive power plant) are quite capable of meeting the complete
power demand of the cement plant. Table B.4.1 provided above shows that the average annual
electricity consumption by DGKCC is 220,231 MWh/yr. To fulfil this demand in 312 operational
17
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
days, DGKCC needs only 29.41 MW4 power generation capacity whereas it already has 69.26 MW
(49.26 MW captive + 20 MW grid) of electricity supply capacity. Therefore, there is no reason as to
why DGKCC shall construct/purchase new gas reciprocating engines when the circumstances or the
baseline situation do not require it to do so.
If DGKCC had planned a capacity expansion of its existing clinker production lines and which had
necessitated for it to add more power generation capacity, only then alternative 3 would have been a
realistic and credible alternative to proposed CDM project activity. Since this is not the case, it is
eliminated and not further discussed under Step 2
Furthermore, the elimination of alternative 3 is in compliance with the guidance provided in “Tool for
the demonstration and assessment of additionality” V 5.2; justifications are briefly provided below:
It is stated in Footnote 4 to Paragraph (1) of Sub-step 1 (a) that “For example, a coal-fired power
station or hydropower may not be an alternative for an independent power producer investing in wind
energy or for a sugar factory owner investing in a co-generation, but may be an alternative for a
public utility. Alternatives are, therefore, related to technology and circumstances as well as to the
investor.”
Since the circumstances/baseline situation do not compel DGKCC to make an investment for
construction of new power plant, alternative 3 cannot be considered as a realistic and credible
alternative to the project activity.
The importance of circumstances and baseline situation is further highlighted in the Section:
Investment comparison analysis and benchmark analysis, Paragraph 15 of the Annex to Tool for the
demonstration and assessment of additionality, wherein it is stated that:
“Guidance: If the proposed baseline scenario leaves the project participant no other choice than to
make an investment to supply the same (or substitute) products or services, a benchmark analysis is
not appropriate and an investment comparison analysis shall be used. If the alternative to the project
activity is the supply of electricity from a grid this is not to be considered an investment and a
benchmark approach is considered appropriate.
Rationale: The purpose of an investment analysis in the context of the CDM is to determine whether
the project is less financially attractive than at least one alternative in which the project participants
could have invested. In cases where the alternative requires investment anyhow and baseline
emissions are based on that alternative, the only means of determining that the project activity is less
financially attractive than at least one alternative is to conduct an investment comparison analysis.
The benchmark approach is therefore suited to circumstances where the baseline does not require
investment or is outside the direct control of the project developer, i.e. cases where the choice of the
developer is to invest or not to invest.”
In view of above it is clear that elimination of alternative 3 is as per the guidance provided in
Footnote 4 and Paragraph 15 of the Annex to the Tool and that the proposed CDM project activity is
purely a voluntary initiative undertaken by DGKCC only due the environmental benefits associated
with the project activity.
4
220,231 / (312 * 24) = 29.41 MW
18
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
As an outcome of Sub-step 1a, the only realistic and credible alternative to the proposed CDM project
activity is business-as-usual (continuation of the current practice).
None of the alternative is prevented by the existing legislation in Pakistan. All alternatives are in
compliance with applicable laws and regulations.
Sub-step 2a:
For the investment analysis Option III (Benchmark Analysis) of the „Tool for the demonstration and
assessment of additionality‟ is chosen.
The investment analysis is done in line with the “Guidance on the Investment Analysis”5.
Referring to guidance provided by document, fulfillment of this guidance by the proposed project
activity‟s investment analysis is shown below:
5
Annex 5 to EB 62
19
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
should be calculated in accordance with local inflow in the final year. The same is
accounting regulations where available, or reflected in the investment analysis
international best practice. It is expected that such spreadsheet.
fair value calculations will include both the book
value of the asset and the reasonable expectation
of the potential profit or loss on the realization of
the assets.
5 Depreciation, and other non-cash items related to Applicable and fulfilled:
the project activity, which have been deducted in Depreciation, which is a non cash item
estimating gross profits on which tax is calculated, was deducted to calculate tax, and was
should be added back to net profits for the purpose added back to calculate post tax cash
of calculating the financial indicator (e.g. IRR, flows. Taxation has been included as
NPV). Taxation should only be included as an an expense because the IRR calculated
expense in the IRR/NPV calculation in cases is post tax IRR. The same is reflected
where the benchmark or other financial indicator is in the investment analysis spreadsheet.
intended for post-tax comparisons.
6 Input values used in all investment analysis should Applicable and fulfilled:
be valid and applicable at the time of the All input values, variables and
investment decision taken by the project assumptions used in the investment
participant. The DOE is therefore expected to analysis are valid and applicable at the
validate the timing of the investment decision and time of decision making. The same is
the consistency and appropriateness of the input reflected in the investment analysis
values with this timing. The DOE should also spreadsheet.
validate that the listed input values have been
consistently applied in all calculations.
7 In the case of project activities for which Not Applicable:
implementation ceases after the commencement Implementation of the project activity
and where implementation is recommenced due to has not ceased since its
consideration of the CDM the investment analysis commencement.
should reflect the economic decision making
context at point of the decision to recommence the
project. Therefore capital costs incurred prior to
the revised project activity start date can be
reflected as the recoverable value of the assets,
which are limited to the potential reuse/resale of
tangible assets.
8 Project participants should supply spreadsheet Applicable and fulfilled:
versions of all investment analysis. All formulas Unprotected/readable versions of all
used in this analysis be readable and all relevant investment analysis related
cells be viewable and unprotected. The spreadsheets would be provided to the
spreadsheet will be made available to the DoE and UNFCCC EB.
Executive Board, UNFCCC secretariat and others
contracted to assess the request for registration on
behalf of the Board including assigned members of
the Registration and Issuance Team. In cases
where the project participant does not wish to
make such a spreadsheet available to the public an
exact read-only or PDF copy shall be provided for
general publication. In case the PP wishes to
20
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
21
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
benchmark based on parameters that are standard participant too. The benchmark used
in the market is suitable in the context of the for the project activity is based on
underlying project activity. publically available data source, i.e.
local commercial lending rate.
14 Internal company benchmarks/expected returns Not Applicable:
(including those used as the expected return on The proposed project activity consists
equity in the calculation of a weighted average of utilizing waste heat from clinker
cost of capital - WACC), should only be applied in production process for electricity
cases where there is only one possible project generation and can be developed by
developer and should be demonstrated to have entities other than the project
been used for similar projects with similar risks, participant too. The benchmark used
developed by the same company or, if the for the project activity is based on
company is brand new, would have been used for publically available data source, i.e.
similar projects in the same sector in the local commercial lending rate.
country/region. This shall require as a minimum
clear evidence of the resolution by the company‟s
Board and/or shareholders and will require the
validating DOE to undertake a thorough
assessment of the financial statements of the
project developer - including the proposed WACC
- to assess the past financial behavior of the entity
during at least the last 3 years in relation to similar
projects.
15 If the benchmark is based on parameters that are Not Applicable:
standard in the market, the cost of equity should be Project IRR is used for additionality
determined either by: (a) selecting the values demonstration.
provided in Appendix A; or by (b) calculating the
cost of equity using best financial practices, based
on data sources which can be clearly validated by
the DOE, while properly justifying all underlying
factors. The values in the table in Appendix A may
also be used, as a simple default option, if a
company's internal benchmark is used.
16 If a company‟s internal benchmark is used for the Not Applicable:
expected return on equity, the cost of debt should Company‟s internal benchmark is not
be based on the weighted average cost of debt used.
financing of the legal entity owning the CDM
project activity. For loans, use the weighted
average cost of outstanding long-term debt. For
bonds, use the weighted average yield of the bonds
during the last three months prior to the
submission of the CDM-PDD for validation or
prior to the investment decision, whichever is
earlier. The use of bonds to determine the cost of
debt is only appropriate for corporate bonds issued
in the host country of the CDM project. In cases
where the debt finance structure of the project is
not yet available (e.g. a letter of intent for debt
funding is not available), the cost of debt can be
22
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
23
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
24
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Benchmark:
The local lending and borrowing rates in Pakistan are based on Karachi Inter-bank Offered Rate (KIBOR)
plus the credit spread over the KIBOR charged by the local bank. In February 2004, KIBOR was
officially introduced by State Bank of Pakistan as a reference rate for all corporate lending in Pakistan6.
Thus the KIBOR portion of the commercial lending rate is always determined by SBP. The credit spread
calculation is performed by local banks which determine it based on various project specific risks or
characteristics of a project type.
For this project activity, DGKCC considered a 6 month tenor average KIBOR of 10.13 % for August
20077 and adopted 200 basis points as reasonable credit spread8. The benchmark thus evaluated was
(10.13 % + 2.0%) = 12.13 %9. This corporate lending rate calculation is in line with the guidance
provided by Citibank10 which estimates a credit spread between 200 to 350 basis points above the 3 or 6
month KIBOR as appropriate for a 7 year term loan (including 2 years grace period), for a loan amount
over PKR 100 million.
Table B.5.1 Electricity Production & Consumption in Baseline and Project Situation
Electricity production
6
Press release by State Bank of Pakistan: http://www.sbp.org.pk/press/2004/jan-21-04.pdf
Third Quarterly report of State Bank of Pakistan FY04:
http://sbp.org.pk/reports/quarterly/fy04/thirdQtr/Money%20Market.pdf
7
KIBOR rate of 2007 are available at the website of State Bank of Pakistan:
http://sbp.org.pk/ecodata/kibor/2007/Aug/index.asp
8
The spread of 200 basis points used in benchmark calculation is based on the loan offer that PP got from Bank
Alfalah Limited, a local bank in Pakistan, (a copy of this loan offer letter has been provided to DOE).
9
See the attached investment analysis spreadsheet
10
Citibank letter has been provided to the DOE.
25
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Electricity prices:
The grid electricity prices paid by DGKCC between July 2006 and June 2007 were considered as basic
values to evaluate and compare the costs of the baseline and project situation. The considered grid
electricity price is 4,261.56 PKR per MWh and the resulting grid electricity costs displaced by the project
electricity are provided below
In the baseline scenario, no additional investment is necessary and only electricity purchase costs are
considered for the investment comparison. In the project scenario, an important investment is necessary
and annual maintenance costs have to be covered. Every four years, a major overhaul of the equipment is
necessary and creates supplementary costs. The major overhaul costs already consider the yearly cost
increase. Table B.5.3 shows the project investment and costs.
26
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Depreciation period is 20 years at the end of which the project will have a salvage value of 10% of the
initial cost, which is in line with DG policy for calculation of depreciation. The 10% residual value of the
equipment is added in the last year of evaluation. Yearly depreciation and financial expenditures are not
taken into account in the financial analysis. The net income is taxed at 35% and is considered in the
analysis.
Table B.5.5 shows the exchange rate (August 2007), the yearly estimated increase rate of grid electricity11
as well as the expected increase in operation and maintenance costs.
As shown in table B.5.6, the IRR of the project activity is 9.96 % which is below the benchmark of
12.13 %. In this case, DGKCC would not invest into the project, because the expected return is below the
commercial lending rate in Pakistan. With the CER revenues, the IRR of the project activity crosses the
benchmark value which is more attractive for the project owner to invest.
To show the robustness of the results, a sensitivity analysis is carried out for the variation of the decisive
variables of the project activity. These are the initial project investment, grid electricity cost, yearly O&M
cost, major overhaul costs, and operational hours. The results of the sensitivity analysis are shown in
Table B.5.7
11
The input values for estimating yearly increase in grid electricity price have been taken from Annual Energy
Outlook 2007 (AEO 2007) (www.eia.doe.gov) and Pakistan Energy Yearbook. Detailed calculation file has been
provided to DOE.
27
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
The sensitivity analysis shows that the results of the Investment analysis are robust. For a change of +/-
10% in project investment, grid electricity cost, O&M cots and overhaul cost, the IRR for the project
activity is still below the benchmark, thus strengthening the conclusions about the additionality of the
project activity. In all the cases analyzed above, the Project IRR is below the benchmark and would not
be considered as economically attractive by DGKCC.
Investment analysis has been selected to demonstrate the additionality of the project activity. Step 3
“Barrier analysis” is optional and has not been considered for assessment & demonstration of
additionality of the proposed CDM project activity.
Sub-step 4a: Analyze other activities similar to the proposed project activity:
The geographical area chosen for this analysis is the whole country, Pakistan. Most of cement factories in
Pakistan tend to produce the required electricity in their captive power plants and use grid electricity as a
backup option only or as source of additional electricity supply to meet the peak demand12. At the time of
the investment decision of the project, in all the cement factories, the waste heat from the clinker
production process was only used for pre-heating the raw materials and the major portion was vented to
the atmosphere. The waste heat recovery and utilization system for power generation was not in operation
in any cement factory of the country.
Table B.5.8 shows the total number of cement plants (29) in operation as of Sep 2010. Out of the twenty
nine plants, only eight (Sr. No. 22 to 29) are those where waste heat recovery system has either been
installed or is being implemented for power generation; among these eight plants, six (Sr. No. 24 to 29)
belong to the category of either registered CDM projects or have been published on UNFCCC website for
global stakeholder consultation; therefore, as per the guidance provided in step 4a of the Tool for the
Demonstration and Assessment of Additionality (Version 5.2), these are not considered in the common
practice analysis. Hence, only two cement plants, Attock Cement (Sr. No. 22) & Fecto Cement (Sr. No.
23), fall into the category of similar options and is discussed in the next section
12
Source: Platt‟s Database 2007. Extract from relevant section is provided to DOE.
13
Source: http://www.apcma.com/pages/data_productioncapacity.html, accessed on Sep 24, 2010
28
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Only two waste heat recovery based activities, which are similar to the project activity, have been
identified above. However, according to the Project Proponent‟s knowledge of the cement sector, Attock
Cement and Fecto Cement have also implemented waste heat recovery project only after considering the
benefits of CDM19.
14
http://cdm.unfccc.int/Projects/DB/TUEV-SUED1269600034.75/view
15
http://cdm.unfccc.int/Projects/Validation/DB/Y1EJLWQAP09NS8CD2M6YHC5BKIGHT4/view.html
16
http://cdm.unfccc.int/Projects/Validation/DB/95H1A0HXY2G5482CYRPB2WJM8ITS1V/view.html
17
http://cdm.unfccc.int/Projects/Validation/DB/YW549ZAEG1IIP5DDVUIE42U3ZZ5CAH/view.html
18
http://cdm.unfccc.int/Projects/Validation/DB/4KAY98DK2HVFNSMYSYTR1OBBPIOQ53/view.html
19
Both these projects (Fecto & Attock Cement) have submitted prior CDM consideration intimations to UNFCCC.
29
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
The analysis provided above shows that no WHR project has been implemented without prior
consideration of the revenues generated by carbon credits 20. Hence it can be concluded that the recovery
and utilization of waste heat from the clinker production process for power generation is not a common
practice in Pakistan cement industry.
As explained in the Investment Analysis, the present project would not be economically attractive without
the consideration of the CER revenue and would not be realised. Since all necessary steps of the Tool are
satisfied, we can make a conclusion that the Project Activity is fully additional.
The emission reductions of the project activity were calculated according to AMS-III.Q.
Baseline emissions
In the situation where the electricity is obtained from a specific existing power plant or from the grid,
baseline emissions can be calculated as follows:
Where:
BEelec,y Baseline emissions due to displacement of electricity during the year y in tons of
CO2
EGi,j,y The quantity of electricity supplied to the recipient j by generator, that in the
absence of the project activity would have been sourced from ith source (i can be
either grid or identified source) during the year y in MWh, and
EFelec,i,j,y The CO2 emission factor for the electricity source i (i=gr (grid) or i=is (identified
source)), displaced due to the project activity, during the year y in tons CO2/MWh
fwcm Fraction of total electricity generated by the project activity using waste energy.
This fraction is 1 if the electricity generation is purely from use of waste energy.
If the boiler providing steam for electricity generation uses both waste and fossil
fuels, this factor is estimated using equation (7). If the steam used for generation
of the electricity is produced in dedicated boilers but supplied through common
header, this factor is estimated using equation (7)/(9).
Note: For project activity using waste pressure to generate electricity, electricity
generated from waste pressure use should be measurable and this fraction is 1
fcap Capping factor to exclude increased waste energy utilization in the project year y
due to increased level of activity of the plant, relative to the level of activity in the
20
A confirmation of the fact that WHR based electricity generation is not a common practice in Pakistani cement
sector was provided by DNA Pakistan to the DOE
30
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
base years before project start. The ratio is 1 if the waste energy generated in
project year y is same or less than that generated in base years.
fcap shall be estimated according to the corresponding section of ACM0012.
As the project activity will displace grid electricity the parameter EGi,j,y corresponds to EGgr,y and the
emission factor EFelec,i,j,y corresponds to EFElec,gr,y.
Calculation of EFElec,gr,y
According to the baseline scenario the displaced electricity is supplied by a connected electrical grid and
so it should be determined using the “Tool to calculate the emission factor for an electricity system”
Version 02.2.0.
Electricity baseline emission factor (EFGrid, CM, BL) is calculated ex-ante as a combined margin consisting
of a combination of operating margin (OM) and build margin (BM) factors according to the following
steps:
Pakistani DNA has not published any delineation of the project electricity system and a connected
electricity system. Moreover, the criteria provided in the “Tool to calculate the emission factor for an
electricity system” under Step 1 do not result in a clear grid boundary as
In such cases, the “Tool to calculate the emission factor for an electricity system” (Version 02.2.0)
suggests “to use a regional grid definition in the case of large countries with layered dispatch systems
(e.g. provincial/regional/national)” to distinguish a connected electricity system. In Pakistan, the
electricity supply business is a sort of monopoly of two companies. For Karachi city and adjoining areas
of Sindh and Balochistan, it is under Karachi Electric Supply Corporation (KESC). For rest of the
Pakistan it falls under Water and Power Development Authority (WAPDA). In 1998, as part of the
government‟s privatization policy, the National Transmission & Despatch Company (NTDC)21 “was
organized to take over all the properties, rights and assets obligations and liabilities of 220 KV and
500KV Grid Stations and Transmission Lines/Network Transmission Lines/Network owned by Pakistan
Water and Power Development Authority (WAPDA). Both NTDC and KESC operate their own
transmission networks but they are also physically interconnected to each other at two points 22 and trade
21
cf. www.ntdc.com.pk
22
One is the Jamshoro - BinQasim link in East of Karachi and other is HUBCO-KESC link in West of Karachi.
31
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
electricity in significant amounts23 in a sort that they both together constitute the national grid system,
which becomes the project electricity system also.
The project activity is connected to the grid of Multan Electric Power Company Limited (MEPCO),
which is one of nine newly created distribution companies24 and connected to NTDC, which is part of the
national grid system.
Step 2: Choose whether to include off-grid power plants in the project electricity system (optional)
The “Tool to calculate the emission factor for an electricity system” (Version 02.2.0) allows the project
participant to choose between the following two options to calculate the operating margin and build
margin emission factor:
Option II: Both grid power plants and off-grid power plants are included in the calculation.
Option I is chosen as data is publicly available only for grid power plants.
The “Tool to calculate the emission factor for an electricity system” (Version 02.2.0) offers four options
for the calculation of the Operating Margin emission factor(s) (EFgrid,OM,y):
Information to carry out a detailed dispatch data analysis is not publicly available; therefore the dispatch
data analysis OM is not selected for the proposed project and the Simple OM option is chosen.
The Simple OM requires that the share of low-cost/must-run resources constitutes less than 50% of the
total net electricity generation of the national grid. In Pakistan, the share of low-cost/must-run resources
usually constitutes less than 50% of the total net electricity generation of the national grid.
According to the “Tool to calculate the emission factor for an electricity system” (Version 02.2.0), for
simple OM, the emission factor can be calculated using either of the two following data vintages:
Ex ante option: For grid power plants, a 3-year generation weighted average, based on the most
recent data available at the time of submission of the CDM-PDD for validation, without
requirement to monitor and recalculate the emissions factor during the crediting period. For off-
23
Actually 32% of total electricity supply in KESC in the year 2006/7 was purchased from NTDC. Cf.
PEPCO/National Transmission & Despatch Co. (NTDC)/Planning Power Department (NTDC) 2008: Electricity
Marketing Data (Power Systems Statistics), 32nd issue, Updated up to 30th June 2007. p. 90
24
http://www.nepra.org.pk/lic_distribution.htm
32
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
grid power plants, use a single calendar year within the 5 most recent calendar years prior to the
time of submission of CDM-PDD or
Ex post option: The year in which the project activity displaces grid electricity, requiring the
emission factor to be updated annually during monitoring. The data required to calculate the
emission factor for year y is usually only available later than six months after the end of year y.
Project proponents employ “ex-ante vintage for grid power plants” for its operating margin calculation.
Step 4 - Calculate the operating margin emission factor according to the selected method
The simple OM emission factor is calculated as the generation-weighted average CO2 emissions per unit
of net electricity generated (tCO2/MWh) by all generating power plants serving the system, not including
low-cost/must-run power/units. The “Tool to calculate the emission factor for an electricity system”
(Version 02.2.0) offers two options for the calculation of the Simple OM.
Option A: Based on the net electricity generation and a CO2 emission factor of each power unit; or
Option B: Based on the total net electricity generation of all power plants serving the system and the fuel
types and total fuel consumption of the project electricity system
In the Pakistani public available data, CO2 emission factor for each power generation unit is not available.
Only nuclear and renewable generation are considered as low-cost/must-run sources; furthermore, the
quantity of electricity supplied to the grid by these sources is known. Finally, off-grid plants are not
considered in the calculation; therefore, Option B is chosen.
For Option B, the Simple OM emission factor is calculated based on the net electricity supplied to the
grid by all power plants serving the system, not including low-cost / must-run power plants / units, and
based on the fuel type(s) and total fuel consumption of the project electricity system:
FC
i
i, y * NCVi , y * EFCO 2,i , y
EFGrid , OM simple, y = [2]
EGy
Where:
EFGrid, OM simple, y is the simple operating margin CO2 emission factor in year y (tCO2/MWh)
33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
FCi,y is the amount of fossil fuel type i consumed in the project electricity system in
year y (mass or volume unit)
NCVi,y is the net calorific value (energy content) of fossil fuel type i in year y (GJ / mass
or volume unit)
EFCO2,i,y is the CO2 emission factor of fossil fuel type i in year y (tCO2/GJ)
EGy is the net electricity generated and delivered to the grid by all power sources
serving the system, not including low-cost / must-run power plants / units, in year
y (MWh)
i are all fossil fuel types combusted in power sources in the project electricity
system in the baseline period
On the basis of the data available, the operating margin emission factor (three-year generation-weighted
average) is:
In terms of vintage of data, project participants can choose between one of the following two options:
Option 1. For the first crediting period, calculate the build margin emission factor ex-ante based on the
most recent information available on units already built for sample group m at the time of CDM-PDD
submission to the DOE for validation. For the second crediting period, the build margin emission factor
should be updated based on the most recent information available on units already built at the time of
submission of the request for renewal of the crediting period to the DOE. For the third crediting period,
the build margin emission factor calculated for the second crediting period should be used. This option
does not require monitoring the emission factor during the crediting period.
Option 2. For the first crediting period, the build margin emission factor shall be updated annually, ex-
post, including those units built up to the year of registration of the project activity or, if information up to
the year of registration is not yet available, including those units built up to the latest year for which
information is available. For the second crediting period, the build margin emissions factor shall be
calculated ex-ante, as described in option 1 above. For the third crediting period, the build margin
emission factor calculated for the second crediting period should be used.
In accordance with the ex-ante calculation of the operating margin (see Step 3), Option 1 is chosen.
The sample group of power units m used to calculate the build margin consists should be determined as
per the following procedure, consistent with the data vintage selected above:
34
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
(a) Identify the set of five power units, excluding power units registered as CDM project activities,
that started to supply electricity to the grid most recently (SET5-units) and determine their annual
electricity generation (AEGSET-5-units, in MWh);
(b) Determine the annual electricity generation of the project electricity system, excluding power
units registered as CDM project activities (AEGtotal, in MWh). Identify the set of power units,
excluding power units registered as CDM project activities, that started to supply electricity to
the grid most recently and that comprise 20% of AEGtotal (if 20% falls on part of the generation
of a unit, the generation of that unit is fully included in the calculation) (SET ≥20%) and determine
their annual electricity generation (AEGSET-≥20%, in MWh);
(c) From SET5-units and SET≥20% select the set of power units that comprises the larger annual
electricity generation (SETsample); Identify the date when the power units in SETsample started to
supply electricity to the grid. If none of the power units in SET sample started to supply electricity
to the grid more than 10 years ago, then use SETsample to calculate the build margin. Ignore steps
(d), (e) and (f).
Otherwise:
(d) Exclude from SETsample the power units which started to supply electricity to the grid more than
10 years ago. Include in that set the power units registered as CDM project activity, starting with
power units that started to supply electricity to the grid most recently, until the electricity
generation of the new set comprises 20% of the annual electricity generation of the project
electricity system (if 20% falls on part of the generation of a unit, the generation of that unit is
fully included in the calculation) to the extent is possible. Determine for the resulting set
(SETsample-CDM) the annual electricity generation (AEGSET-sample-CDM, in MWh);
If the annual electricity generation of that set is comprises at least 20% of the annual electricity
generation of the project electricity system (i.e. AEGSET-sample-CDM ≥ 0.2 × AEGtotal), then use the
sample group SETsample-CDM to calculate the build margin. Ignore steps (e) and (f).
Otherwise:
(e) Include in the sample group SETsample-CDM the power units that started to supply electricity to the
grid more than 10 years ago until the electricity generation of the new set comprises 20% of the
annual electricity generation of the project electricity system (if 20% falls on part of the
generation of a unit, the generation of that unit is fully included in the calculation);
(f) The sample group of power units m used to calculate the build margin is the resulting set
(SETsample-CDM->10yrs).
As shown in the attached EXCEL file, AEGSET-5-units is largely below AEGSET-≥20%, so SET≥20% is selected
as SETsample. Also, given that there are not CDM power plants that can be included and the SET sample
includes plants that are operating since more than 10 years, SETsample is equivalent to SETsample-CDM->10yrs.
Then the build margin emissions factor is the generation-weighted average emission factor (tCO2/MWh)
of all power units m during the most recent 3 years (2004-05, 2005-06, 2006-07) for which power
generation data is available, calculated as follows:
35
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
m
EG * EF
m, y EL , m , y
EFGrid , BM , y = [3]
EG
m
m, y
Where:
EFGrid, BM, y is the Build Margin CO2emission factor in the year y (tCO2/MWh)
EGm,y is the net quantity of electricity generated and delivered to the grid by power unit m in the
year y (MWh)
y is the most recent historical year for which the power generation data is available
The CO2 emission factor of each power unit m (EFEL,m,y ) should be determined as per the guidance in step
4 (a) for the simple OM, using options A1, A2 or A3, using for y the most recent historical year for which
power generation data is available, and using for m the power units included in the build margin.
If the power units included in the build margin m correspond to the sample group SETsample-CDM->10yrs, then,
as a conservative approach, only option A2 from guidance in Step 4 (a) can be used and the default values
provided in Annex 1 of the Tool shall be used to determine the parameter ηm,y.
Using this method, the EFGrid, BM, BL in Pakistan is calculated as 0.242 tCO2/MWh.
The calculation of the combined margin (CM) emission factor (EFgrid,CM,y) is based on one of the
following methods:
(a) Weighted average CM; or
(b) Simplified CM.
The weighted average CM method (option A) should be used as the preferred option.
The simplified CM method (option b) can only be used if:
The project activity is located in a Least Developed Country (LDC) or in a country with less than
10 registered projects at the starting date of validation; and
The data requirements for the application of step 5 above cannot be met.
36
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Where:
EFGrid, BM, y is the build margin CO2 emission factor in the year y (tCO2/MWh)
EFGrid, OM, y is the operating margin CO2 emission factor in the baseline period (tCO2/MWh)
wOM is the weighting of operating margin emissions factor (%)
On the basis of these weights the combined margin emission factor is calculated, and fixed ex-ante:
Calculation of fwcm
The electricity generation of the project is purely from use of waste heat, then according to the
methodology fwcm= 1.
Calculation of fcap
According to the requirements of AMS.III.Q the capping factor fcap should be calculated using proper
equations from ACM0012.
As an introduction to the element of conservativeness, this methodology requires that baseline emissions
should be capped irrespective of planned/unplanned or actual increase in output of plant, change in
operational parameters and practices, change in fuel type and quantity resulting in an increase in
generation of waste energy. In case of planned expansion a separate CDM project should be registered for
additional capacity. The cap can be estimated using the three Methods described below. Project
proponents shall use Method-1 to estimate the cap if data is available. In case of project activities
implemented in a new facility, or in facilities where three-year data on production is unavailable, Method-
2 shall be used. In case the project proponents demonstrate technical limitations in direct monitoring of
waste heat / pressure of waste energy carrying medium (WECM), then Method-3 is used.
Method-1
Where the historical data on energy released by the waste energy carrying medium is available, the
baseline emissions are capped at the maximum quantity of waste energy released into the atmosphere
under normal operation conditions in the three years previous to the project activity.
Method-2
The manufacturer‟s data for the industrial facility shall be used to estimate the amount of waste energy
the industrial facility generates per unit of product generated by the process that generates waste energy
(either product of departmental process or product of entire plant, whichever is more justifiable and
accurate). In case any modification is carried out by the project proponent or in case the manufacturer‟s
37
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
data is not available for an assessment, this should be carried out by independent qualified/certified
external process experts such as a chartered engineer on a conservative quantity of waste energy
generated by plant per unit of product manufactured by the process generating waste energy. The value
arrived based on above sources of data, shall be used to estimate the baseline cap (fcap). The
documentation of such assessment shall be verified by the validating DOE.
Method-3
In some cases, it may not be possible to measure the waste energy (heat, sensible heat, heat of reaction,
heat of combustion etc.), enthalpy or pressure content of WECM. Therefore there is no historic data
available for these cases. These cases may be of following two types.
Case 1: The energy is recovered from WECM and converted into final output energy through waste heat
recovery equipment. For such cases fcap should be the ratio of maximum theoretical energy recoverable
using the project activity waste heat recovery equipment and actual energy recovered under the project
activity (using direct measurement). For estimating the theoretical recoverable energy, manufacturer‟s
specifications can be used. Alternatively, technical assessment can be conducted by independent
qualified/certified external process experts such as chartered engineers.
Case 2: The energy is recovered from WECM in intermediate energy recovery equipment using an
intermediate source. For example, an intermediate source to carry energy from primary WECM may
include the sources such as water, oil or air to extract waste energy entrapped in chemicals (heat of
reaction) or solids (sensible heat). This intermediate energy source is finally used to generate the output
energy in the final waste heat recovery equipment. For these cases fcap is the ratio of maximum
theoretical intermediate energy recoverable from intermediate waste heat recovery equipment and actual
intermediate energy recovered under the project activity (using direct measurement). For estimating the
theoretical energy, manufacturer‟s specifications can be used. Alternatively, technical assessment can be
carried out by independent qualified/certified external process experts such as chartered engineers.
Since there is no historical data on parameters of the waste energy from the cement clinker production
and it‟s not possible to measure it due to different technical reasons Method-3 for fcap calculation was
chosen. Since there are heat exchangers in the project scenario where waste energy is transferred from
WECM to water for steam generation and further production of electricity case 1 of Method-3 for fcap
calculation was used.
QOE ,BL
f cap [5]
QOE , y
Where:
QOE , BL Output/intermediate energy that can be theoretically produced (in appropriate unit), to be
determined on the basis of maximum recoverable energy from the WECM, which would
have been released (or WECM would have been flared or energy content of WECM
would have been wasted) in the absence of CDM project activity
QOE , y Quantity of actual output/intermediate energy during year y (in appropriate unit)
38
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
In the proposed project, the theoretical electricity output QOE , BL is 70,088 MWh/year. The actual output
electricity QOE , y will be determined ex post by actual measurement. Since the project activity isn‟t
operational yet there is no reason to believe that the energy recovered will be different from the
theoretical value for which the waste heat recovery system has been designed. Therefore, the ratio is
assumed to be 1 for ex ante calculations and will be settled ex post.
Project Emissions
There is no auxiliary fuel combusted in the project activity to supplement waste gas and the turbogenset
consume its own electricity for auxiliary needs. Similarly, the project activity does not incinerate any
waste gas to generate energy. Therefore, the project emissions are considered zero.
PE y 0 . [6]
Leakages
The project activity only involves installation of new equipment; no retrofit or replacement will take place
and hence no existing equipment can be transferred outside the project boundary. Since no transfer of
equipment is considered in the project activity, the leakages are: LE y 0 .
Emission reductions
Emission reductions are calculated as follows:
Where:
ER y Emission reductions in year y (t CO2e/yr)
39
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
40
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
41
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
42
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Justification of the Public available source for the grid emission factor calculation
choice of data or
description of
measurement methods
and procedures actually
applied :
Any comment: Used to calculate the grid emission factor
43
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
44
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
45
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Data / Parameter: EI
Data unit: GWh
Description: Annual net imports from other grids outside the host country
Source of data used: Pakistan Energy Year Book 2007
Value applied: 2004-05 2005-06 2006-07
109 146 171
Justification of the Public available source for the grid emission factor calculation
choice of data or
description of
46
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
measurement methods
and procedures actually
applied :
Any comment: Used to calculate the grid emission factor
According to the analysis made in B.6.1, the emission reduction of the project is:
The annual & total estimation of emission reductions for the fixed crediting period of 10 years (from
01/01/2012 to 31/12/2021) is provided below:
47
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Monitoring plan involves metering the electrical energy produced by the project activity. Based on that,
fcap will be determined according to Case 1: method 3 of ACM0012 as illustrated in section B.6.1 of the
PDD.
Data will be hourly collected by the operators. Shift engineers verify and prepare daily production log
sheet which includes daily electricity generation. At final stage, Senior Manager verifies the data.
Procedures for data collection and auditing, in order to determine and verify the emissions reductions
achieved by the project activity, will be described in the Monitoring Plan.
Data will be collected for the duration of the crediting period (10 years) and stored for a minimum of two
years after the end of the crediting period or the last issuance of CERs for the project activity, whichever
occurs later. An electronic spreadsheet model may be used for archiving electronic data.
In case some data is missing or incorrect, it will be reconstructed or rectified based on the information
sought from the historical data record which is similar in terms of operating conditions and parameters.
The staff responsible for project monitoring will complete the electronic worksheets on a monthly basis.
Given that some of these data may be collected more frequently, data will be aggregated to allow monthly
inputs into the spreadsheet. The spreadsheet automatically provides annual totals in terms of emission
reductions achieved.
48
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
The person in charge of the project monitoring will conduct annual internal audits, checking the above
mentioned procedures for collecting data.
The person in charge of quality assurance would make sure that all the equipment used for measuring data
are properly and timely calibrated. Each equipment/meter should have a calibration tag attached to it
showing equipment name, model, date of last calibration and the date when next calibration is due. To
ensure the reliability of the data, calibration of all measuring devices would be done according to a
planned calibration.
B.8 Date of completion of the application of the baseline and monitoring methodology and the
name of the responsible person(s)/entity(ies)
Both, First Climate (Switzerland) AG and Carbon Services (Private) Limited, are project participants.
October 18, 2007 is the starting date of the project activity and it corresponds to date of contract between
DGKCC and the Supplier of WHR equipment.
20 years, 0 months
49
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Not applicable
Not applicable
01/01/2012 or the date of CDM registration of the project activity, whichever comes later.
C.2.2.2. Length:
10 years, 0 months
D.1. If required by the host Party, documentation on the analysis of the environmental impacts
of the project activity:
According to the host country regulations, the project activity had to receive an Environmental Approval
from the Environment Protection Department of the local government, upon submission of an Initial
Environmental Examination (IEE) Report by the project proponent.
The IEE points out that the project will be beneficial to the environment as utilization of waste heat and
thus lower consumption of fossil fuels is made possible by the new technology. No negative
environmental impacts are to be considered, as the technology to be adopted is mature and safe, once
appropriate operation and maintenance procedures are in place.
The environmental analyses conducted by DGKCC for the project are consistent in demonstrating that the
project activity is expected to remain fully compliant with NEQS (National Environmental Quality
Standards). In fact, it is expected that pollutant emissions (both of local concern and global concern, such
as CO2) will reduce from the current levels.
D.2. If environmental impacts are considered significant by the project participants or the host
Party, please provide conclusions and all references to support documentation of an environmental
impact assessment undertaken in accordance with the procedures as required by the host Party:
50
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Neither the project participants nor the host Party have any concern about negative environmental impacts
associated with the project activity, given that project activity aims at reducing the local and global
environmental impacts of the industrial site where the project activity is to be implemented.
IEE Report and the accompanying approval request letter were submitted to EPA which issued the
approval letter after review of the report. The approval letter does not raise any particular issue with
regard to the environmental impact of the project.
E.1. Brief description how comments by local stakeholders have been invited and compiled:
In addition to CDM requirements by UNFCCC, the stakeholder consultation meeting is also required by
the Designated National Authority (DNA) of Pakistan for issuance of Host Country Approval. The
Stakeholder consultation meeting was held on October 24, 2008 at D.G. Khan Cement Factory and was
open to anybody willing to participate (private citizens, representatives of associations, interest groups,
unions, public authorities, NGOs, etc.).
Stakeholders were informed about the project activity through specific advertising published by the
project owner in local newspaper. The advertisements were also displayed on the notice boards at
DGKCC. Advertisement is shown in Annex 5.
The meeting was introduced by the representative of the project owner who explained in details the
project activity and stimulated the debate and the expression of comments. Pictures of the Meeting are
shown in Annex 6.
Comments from the stakeholders were collected in written form during and after the meeting. These are
summarized in the table below.
51
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
1. Environmental betterment
Servicing in will reduce diseases.
3 Nazir Ahmed Health Primary Kofli Sattai 2. Environmental pollution
Department will reduce.
3. Electricity will be saved.
1. Electricity will be saved.
Basti 2. Employment opportunities
Abdul Majeed
4 Agriculturist Primary Laghari, DG will be available.
S/O Rahim Bux
Cement 3. It will lead to betterment of
environment
1. New job opportunities will
not require any relocation.
2. Employment opportunities
5 Ghazi Khan Transporter Primary Kofli Sattai will be available to our
children.
3. It will create awareness of
education.
E.3. Report on how due account was taken of any comments received:
Most of the comments received were expressing a positive opinion of the project. The personnel at D.G.
Khan Cement Company explained in detail the technical, environmental and social consequences of
utilization of waste heat recovery for power generation. The stakeholders were satisfied, and were
supportive to the project. In conclusion, no concerns were expressed by the stakeholders, which
eventually expressed appreciation for initiative of D.G. Khan Cement Company Limited
52
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Annex 1
53
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
54
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Annex 2
55
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Annex 3
BASELINE INFORMATION
Fuel Characteristics:
Fuel Characteristics
NCV of Natural Gas Based on Analysis BTU/ft3 922
Density of Natural Gas kg/Nm3 0.658
NCV of HFO Based on Analysis BTU/lb 17,505
NCV of Diesel BTU/lb 18,600
Density of diesel kg/Ltr 0.8438
56
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Project Emissions
Baseline Emissions
57
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Annex 4
MONITORING INFORMATION
Detailed monitoring plan and information has already been provided in Section B.7.
58
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Annex 5
Advertisements for stakeholders‟ consultation meeting are shown below.
59
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
60
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Annex 6
Pictures of stakeholders‟ consultation meeting are shown below.
61
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
62
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
63
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
64
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
-----
65