BASEMENT TAKE-OFF

TAKE-OFF LIST

1 Bulk Excavations for basement pit


2 R.F.R
3 E.O for excavating in hard pickable material
4 Ditto hard rock
5 Excavate trench for basement footing & R.F.R
6 E.O for excavating in hard pickable material
7 Ditto hard rock
8 Risk of collapse
9 Storm and surface water
10 Scarify and compact bottom of excavations
11 Cement sand blinding
12 Reinforced concrete basement slab & reinforcement
14 Horizontal asphalt
15 50 mm protective cement sand screed
16 Reinforced concrete loading slab and reinforcement
17 Ddt R.F.R & Add Cartaway
18 Striking off and curing
19 Reinforced concrete basement wall and reinforcement
20 Sawn softwood formwork to sides of basement wall
21 Sleeve duct
22 20 mm thick vertical asphalt
23 30 mm thick cement sand grout
24 Half brick thick load bearing brickwork and Brickforce
25 Reinforced concrete floor slab
26 Striking off and curing
27 Sawn formwork to sides of floor slab
28 Ditto to soffits

Bulk Excavations for basement pit


Length
14500
2/115 230 (walls
2./30 60 (grout
2./20 40 (asphalt
2/200 400 (conc
(wkng
Add 2/ 2000 4000 4730 space)
19230

Width
6500
2/115 230
2./30 60
2./20 40
2/200 400
Add 2/ 2000 4000 4730
11230

Depth
4205
Less 400 (up to dpc
275 675 (footing
3530
Add 75 (blinding
3605

Bulk excavations for basement commencing from natural ground level


19.23 exceeding 2m but not exceeding 4m deep
11.23 &
3.61 Return Fill and Ram
778.51 &
Extra over for excavating in hard pickable material
x15%..............................................................( ) cubic

Ditto hard rock


x10%..............................................................( ) cubic

Excavate trench for basement footing


Length
14500
2/115 230 (walls
2./30 60 (grout
2./20 40 (asphalt
2/200 400 730 (conc
15230

Width
6500
2/115 230 (walls
2./30 60 (grout
2./20 40 (asphalt
2/200 400 730 (conc
7230
Girth
Length 15230
Width 7230
2/ 22460
44920
Less 4/0.5 / 2 / 1500 6000
38920

Depth
275
Less 75 (blinding
200

38.92 Excavate trench for basement footing


1.50 &
0.20 Return Fill and Ram
11.68 &
Extra over for excavating in hard pickable material
x15%..............................................................( ) cubic
&
Ditto hard rock
x10%..............................................................( ) cubic

Risk of collapse
Basement Pit

Girth
Length 19230
Width 11230
2/ 30460
60920

Depth
4205
Less 400 (up to dpc
200 600 (footing
3605
Allow for maintaining and supporting sides of excavations and making
60.92 good all slips by providing timbering
2 3.61 219.62
38.92
0.20 15.57
235.18

Storm and surface water

Item Allow for keeping excavations free from storm and surface water or
mud for the entire duration of the contract by pumping and bailing

Compact bottom of excavations

15.23 Scarify and compact bottom of excavations


7.23 &
110.11 75 mm thick Blinding (Grade 10 Mpa)

Concrete footing

Vibrated reinforced concrete grade 25 Mpa to basement concrete


38.92 footing
1.50 &
0.20 Reinforcement (All sizes) including cutting ,bending and fixing
11.68 x 120 kgs /m3………………………………………………………..( ) kg
&
Deduct Return, Fill and Ram
&
Add Cartaway
Basement Slab

15.23 Vibrated reinforced concrete grade 25 Mpa to basement slab


7.23 &
0.30 Reinforcement (All sizes) including cutting ,bending and fixing
33.03 x 120 kgs /m3………………………………………………………..( ) kg
&
Deduct Return, Fill and Ram
&
Add Cartaway

Horizontal asphalt
Length
Add 14500
2. /115 230
2. /30 60
2. /20 40 330
14830

Width
Add 6500
2. /115 230
2. /30 60
2. /20 40 330
6830

14.83 30 mm thick horizontal asphalt


6.83
101.289
Protective Screed

Length
14500
2. /115 230
2. /30 60
14790

Width
6500
2. /115 230
2. /30 60
6790

14.79 50 mm protective cement sand screed


6.79
100.42

Floor slab and reinforcement

14.79 Vibrated reinforced concrete grade 25 Mpa to concrete floor slab


6.79 &
0.15 Reinforcement (All sizes) including cutting ,bending and fixing
15.06 x 120 kgs /m3………………………………………………………..( ) kg
&
Deduct Return, Fill and Ram
&
Add Cartaway

Concrete basement wall and reinforcement


Girth
Length 15230
Width 7230
2/ 22460
44920
Less 4/ 0.5/ 2/200 800
44120
Height
3200
150
50
30
3430

44.12 Vibrated reinforced concrete grade 25 Mpa to basement wall


0.20 &
3.43 Reinforcement (All sizes) including cutting ,bending and fixing
30.27 x 120 kgs /m3………………………………………………………..( ) kg
&
Deduct Return, Fill and Ram
&
Add Cartaway

Sawn softwood formwork to sides of basement wall

Outer face
Girth
Length 15230
Width 7230
2/ 22460
44920

Depth
4205

Inner Face
Girth
Length 15230
Width 7230
2/ 22460
44920
less 4/ 0.5/2/200 800
44120

Depth
3430
44.92 Wrot softwood formwork to sides of concrete basement wall
4.21 188.89
44.12
3.43 151.33
340.22

20 mm thick vertical asphalt


Length Width
14500 6500
Add 2/115 230 230
Add 2/30 60 60
Add 2/20 40 40
14830 6830

Girth
Length 14830
Width 6830
2/ 21660
43320

Depth
3200
150
50
3400

43.32 20 mm thick vertical asphalt


3.40
147.29
30 mm thick cement sand grout

Length Width
14500 6500
Add 2/115 230 230

14730 6730
Girth
Length 14730
Width 6730
2/ 21460
42920
Add 4/0.5/2/30 120
43040

43.04 30 mm (1:3) cement sand grout


3.20
#REF!

Half brick thick load bearing brickwork and Brickforce

Girth
Length 14500
Width 6500
2/ 21000
42000
Add 4/0.5/2/115 460
42460

Brickforce after every 3 rd Course


1/3(0.085) = 3.92 m/m2

Half brick thick loadbearing brick wall in stretcher bond, c/s Morta mix
42.46 (1:4)
3.20 &
135.87
Brickforce suitable for half brickwalls cotts Ref C1
x 3.92 m / m2 …………………………………………………..( )lineal
Reinforced concrete floor slab

Vibrated reinforced concrete grade 25 Mpa to basement concrete floor


14.83 slab
6.83 &
0.20 Reinforcement (All sizes) including cutting ,bending and fixing
20.26 x 120 kgs /m3………………………………………………………..( ) kg

Sawn formwork to sides of floor slab

44.92 Sawn softwood formwork to sides of concrete basement floor slab


0.20
8.98

Ditto to soffits

14.50 Sawn softwood formwork to soffits of concrete basement floor slab


6.50
94.25

Strike off and cure tops of concrete


Basement Slab
Length Width
14500 6500
Add 2/115 230 230 (walls)
2./30 60 60
2./20 40 40
14830 6830
14.83 Strike off and cure tops of concrete
6.83 101.29
14.79
6.79 100.42
14.83
6.83 101.29
303.00

TOTAL