Professional Documents
Culture Documents
LRM P2
LRM P2
LRM P2
After awarding the contract in November 2017 and amending the completion
date in February 2018 from 2026 to 2025 without any funding, works are to be
initiated at a faster rate and advanced technology is to be undertaken to
complete the project in the requested time, which can lead to financial risks.
Geological investigation can result in spending more money, and dealing with
the disposal of soil will incur more cost than anticipated. Large tunnelling
projects have faced cost blowouts due to geotechnical challenges in the site.
The client had changed the goals for the project after the contract was signed.
This has led to contentions with the client on the CYP consortiums behalf.
This risk can be mitigated by avoiding constant changes in design and scope
during the later phases of construction and ensuring the contractors are capable
and experienced enough to carry out such vast projects. Melbourne Metro
tunnel project being private-public partnership has chances to end up in the
court or forcing opposition party to demand the cost blow out.
Environmental Risks:
Melbourne Metro Tunnel project involves many ecological risks, and improper
assessment can lead to difficulties. Environmental Risks Assessment is a part of
design development so that the prepared design confines to the alternative
approaches and are environment risk-free. Melbourne Metro project involves
nine kilometres of tunnel underground and mining between CBD North Station
to CBD South Station. The underground tunnelling can cause environmental
effects on society and is prioritized as client risk as environmental activists can
oppose this project which might cause delays.
Inputs of surface sediments, chemical and rubbish from the construction zone
directly to river bodies and rainwater drainage will affect the aquatic ecology
and River Health. During the tunnelling process, infiltration can happen into the
tunnel causing extra works. Care should be taken to sustainably discharge off
contaminants collected during construction.
Project Delay:
Late completion of project not only delays revenue earning, it also incurs
additional costs to use other facilities in the interim. Delayed projects inevitably
incur additional supervision and management costs and also damage the
reputation. Some of the reasons for late completion are:
Latent conditions
A study done by (Zou, Zhang & Wang 2007) observed “Tight project schedule”
to be an influential factor on all project objectives. A lengthy schedule wrecks
cost benefit, therefore, clients should prepare a practical schedule allowing
sufficient but not excess time to accommodate all design and construction tasks.
In the construction phase, clients should develop a clear and appropriate plan,
envisage a contingency fund, secure standby cash flow in advance and control
schedule and cost. There is also political pressure to finish the project early
which might not be achievable and constant obstruction to the traffic flow
enrages public as stretches of roads are needed to be shut down for the purpose
of construction.
https://www.roadsonline.com.au/metro-tunnel-goes-virtual/
https://www.theage.com.au/national/victoria/john-holland-wants-taxpayers-to-
cop-the-risk-of-a-blowout-on-north-east-link-20200304-p546u1.html
https://www.commercialrealestate.com.au/news/governments-will-have-to-take-
more-risk-on-big-projects-john-holland-949266/
https://www.theage.com.au/national/victoria/metro-tunnel-construction-to-get-
back-on-track-20191212-p53j79.html
https://www.score.org/blog/8-options-when-your-clients-refuse-to-pay-you
Zou, PXW, Zhang, G & Wang, J 2007, ‘Understanding the key risks in
construction projects in China’, International Journal of Project Management,
vol. 25, no. 6, pp. 601–614.