Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

2019 3rd International Conference on Recent Developments in Control, Automation & Power Engineering (RDCAPE)

Microgrid System for A Rural Area - An Analysis


of HOMER Optimised Model Using MATLAB
Gourav Kumar Suman Om Prakash Roy
Dept. of Electrical Engineering Dept. of Electrical Engineering
NERIST NERIST
Nirjuli, India Nirjuli, India
gauravsuman283@gmail.com opr@nerist.ac.in

Abstract—There have been many methods of attaining a explained in [6], [7] viz. HOMER, iHOGA etc, this work uses
suitable combination of renewable energy sources. This work one such result and analyses the transient behaviour of the
analyses the stability of one such system optimised by HOME- system on an event of occurrence of fault. This work realises
Rquickstart for a small community at Gurmia, India; on the
occurrence of faults. The chosen location has a fair potential of the importance of PV and wind sources in addition to their
solar and wind energy, trapping of these resources efficiently compatibility in a microgrid for a community load.
in the form of hybrid microgrid systems could solve major
power issues and in the same time supersede the old grids. This II. M ETHODOLOGY
work involves simulation of an optimised model obtained from A microgrid has to ensure reliability, cost effectiveness and
HOMERquickstart package using Simulink. Various cases are
considered in interlinking of the energy sources for the microgrid efficiency in operation. This has to be maintained for the cases
and their respective transient behaviour in the occurrence of of both islanded and grid connected mode of operation. Opti-
faults are observed. misation of hybrid system is necessary in order to minimise the
Index Terms—Microgrid, HRES, Transient stability, Simulink, cost at the desired operating condition maintaining the required
HOMERquickstart constraints. ”Optimisation could be referred as formulation of
a mathematical problem based on the desired output within
I. I NTRODUCTION the design constraint” as stated in [8]. For designing an
Conventionally the mode of generation of electrical energy optimum configuration of a hybrid system, substantial research
was through the utilisation of fossil fuel relied upon as primary is required on environmental conditions throughout the year
source of energy. The crunch in traditional sources and their in the location of interest. For designing any mG, the first
adverse impacts to the environment has posed a challenge to and the most crucial step is to learn the load demand of the
the future of civilisation [1] which is predominantly dependent target location. The aforesaid step is very crucial in designing
on these sources for energy. Renewable energy sources may the system and any discrepancy in this stage could lead
act as saviours from this scenario. In addition to lower mainte- to wrong estimation of demand, which in turn would lead
nance and operational costs the most important characteristic to unmet loads or excessive energy beyond the capacity of
carried by renewable resources is their environment friendly storage. Several software tools exist for optimisation of hybrid
nature. As of now, the renewable energy sources account for a systems, one such tool namely; HOMER is used in this work.
total of 63% share in total generation capacity as per the data HOMER software is meant for single-objective and nonlinear
from Renewables 2019 Global Status Report (Paris, 2019). analysis of a system. This software makes the decision making
Amid all the renewable energy sources, solar and wind energy possible by simulation of many methods and technological
sources have gained higher attention with greater impact to the cost variation which otherwise would have been a tough task.
power system. The only limitation being their intermittency The software provides an optimal configuration for the desired
which could be coped up by certain-combination of these location maintaining the user defined constraints at the same
sources to attain a Hybrid Renewable Energy System (HRES) time. Basic version of HOMER i.e. HOMERquickstart has
[2]. In addition microgrids seem to have brought a revolution been used in this work for optimal sizing of the renewable
in power industry with its ability to set up at hostile landscapes energy sources involved in the system. This work discusses the
[3]. There is an increase in demand of electrical energy due options for hybrid renewable energy sources for a small section
to the growing population, the need is highly apt in country in a village Gurmia in the Indian State of Bihar. The location
like India where the power failures are pretty common with chosen is as shown in Fig. 1. The random nature of renewable
many of the rural areas facing inadequate supply of power [4], energy sources makes their prediction a challenge hence
[5]. With ideas on significance of renewable energy sources, optimisation method study would reduce the cost of the system
the application of the same has been discussed for a locality and make the system more reliable. An optimum management
in India in present work. There are various methods and of resource is important for a reasonable balance between
softwares for optimisation of renewables in hybrid system as the system components and economy. The selected location

978-1-7281-2068-3/19/$31.00 ©2019 IEEE 534

Authorized licensed use limited to: University of Melbourne. Downloaded on May 16,2020 at 22:02:57 UTC from IEEE Xplore. Restrictions apply.
2019 3rd International Conference on Recent Developments in Control, Automation & Power Engineering (RDCAPE)

Fig. 3. Load profile - as used in HOMERquickstart

Fig. 1. Chosen location, Gurmia, India

Fig. 4. The Hybrid Renewable Energy Sources chosen in HOMERquickstart

Fig. 2. Availability and variation chart of solar and wind energy at Gurmia where the blue bins represent the demand on weekdays and
the amber bins represent the demand on weekends. During
the early hours it could be seen that the power demand is
has a sufficient source of solar and wind energy. The average low and the load demand increases from 0500 hours onwards.
solar radiation at the surface was 9.483 kW h/m2 /day, wind As it is a community load profile, the trend of increase in
speed was measured to be 4.43 m/s [Surface Meteorology and power demand lasts upto 2100 hours. Additionally, peak hours
Database - NASA]. The clearness index at the location was of the day lie between 1800 to 2100 hours as most of the
observed to be varying between 0.691 (max) and 0.411(min). people are home by then. The demand eventually decreases
The availability of sources of energy at Gurmia is represented after 2100 hours marking end of the day or time of rest.
in figure 2, where the blue bins represent the solar radiation, Coming to the design of solar resource, HOMERquickstart
the amber bins represent wind speed and the curve denote takes the average radiation along with ambient temperature as
the clearness index of solar radiation on the surface. The its input for defining the output PV power. The mathematical
maximum solar radiation is recorded in the month of April explanation of the output defined by HOMERquickstart does
which is about 7 kW h/m2 /day and the minimum of 4.07 not fall in our scope for present piece of work but the same
kW h/m2 /day in the month of December. This plot shows could be seen from literature such as [9]. The optimised system
that the potential of solar energy in the area is quite good as obtained from HOMERquickstart is shown in fig. 4. The
making it an inevitable source of energy in the region. output of the PV array as obtained from HOMERquickstart
The energy demand of 63 houses in the locality was consid- has been depicted in fig. 5. It can clearly be seen from the
ered with an average demand of about 165 kW h/day. In the plot that the maximum solar output is generated during the
presented system the load can be met up as per the availability time interval of 0600-1800 hours and the output is high in
of energy source like during the morning hours PV can be used every month but for July and August owing to low clearness
and during the peak hours the load can be met by wind farm. index as shown in fig. 2. In addition the battery state of charge
The load applied to the system bears a load factor of 0.34 with has also been given in fig. 6, from which it is clearly visible
a peak load of 20.46 kW at a hourly variation of 20% and daily that the battery remains completely charged between 1200 -
variation of 10%, all loads are considered to be AC loads. A 1800 hours, as the demand is met by the available renewable
typical community load profile could be as seen from fig. 3, energy sources during this period.

535

Authorized licensed use limited to: University of Melbourne. Downloaded on May 16,2020 at 22:02:57 UTC from IEEE Xplore. Restrictions apply.
2019 3rd International Conference on Recent Developments in Control, Automation & Power Engineering (RDCAPE)

B. Wind Farm Modelling


Model of wind turbine is designed with the help of follow-
ing equations [13]–[15]:

ρV ω 3 RCp
TΩ = 0.5 (3)
ωr
Fig. 5. PV output
Cf
λi = R (4)
λ

Cp = 0.5(0.22β − λi − 2)eλi (5)

Where, TΩ is the torque of wind turbine, ρ is the density


of air, Vω is the wind velocity, R is the blade radius, Cp is
the power coefficient, λi is the tip speed ratio and β is the
Fig. 6. Battery state of charge pitch angle. The basic parameters of the system used for the
model is shown in the table I. The model designed with the
aforementioned parameters in simulink could be seen from
III. S YSTEM D ESCRIPTION AND S IMULATION Fig. 7. This model comprises of PV system, Doubly Fed
Induction Generator (DFIG) windfarm and a generator set.
The system chosen for this work is PV-Wind hybrid system Photovoltaic system bears its own boost converter along with
in combination with a generator set and battery storage system MPPT control. A method of perturb and observe technique
in order to maintain the smoothness and accuracy in power have been implemented for extracting most of the power from
flow [9], [10]. The initial cost in this case may be higher than the PV arrays [16].
conventional systems but this system proves to be cost effec-
tive in the long run owing to its lower maintenance and fuel IV. A NALYSIS
costs. The optimised system obtained from HOMERquickstart
was then designed in MATLAB simulink and analysed. For The designed system as shown in fig. 7 is tested for transient
evaluation of advantages of PV-wind configuration, an islanded stability under three phase to ground fault. It has been seen
microgrid has been obtained in simulink. The conventional that on occurrence of three phase faults the terminal voltage
generation is rated so that it could supply the entire load in falls down and a sag is observed in voltages from all the
absence of renewable energy sources (at some interval) thereby sources [17]. This could be prevented to an extent by using a
keeping the system reliable. Transient stability of the system battery backup. The microGrid designed here was analysed in
is realised by taking each of the renewable energy sources certain combinations among themselves, giving rise to three
separately and also in hybrid combination of renewable energy of the given possibilities. These cases were analysed over a
sources. time period of (0-500)ms, with a brief period of three phase
short circuit fault (3L-G) for about 100ms. During the event
A. PV Modelling of fault, the behaviour of each of the energy generation units
at their respective terminals were observed and are detailed as
A photovoltaic cell harnesses and converts solar energy follows.
into electrical energy. A single diode solar cell model is
implemented in the model to make and array of solar cells. A. First combination - Generator with PV
The current generated could be given by equation 1 [11], [12].
For this analysis the windfarm subsystem is excluded from
q(V +IRs ) V + IRs the model and a 3L-G fault is applied at the duration of 200
I = Iph − Is [e N KT − 1] − (1)
Rsh to 300 ms, the voltages at different points of the model is
observed during the pre and post fault condition. The plots in
where, I is the generated current, V is the voltage, Iph is the Fig. 8 show the voltages at generator terminals, solar array,
photocurrent, Is the diode saturation current, K(1380X10−23 ) bus and load. It could clearly be seen from the plots that the
being the Boltzmann constant, T is the temperature and N is bus voltage during the post fault scenario reaches a mark of
the factor of ideality of diode, Rs and Rsh are the series and 2 pu, which then restores back to the nominal voltage range
shunt resistances. The photocurrent is given by equation 2. after 10 ms of fault clearance. This variation of voltage at
G the bus causes large oscillations at the load terminal which is
Iph = [Isc + Ki (T − 298)] (2) not healthy from load point of view. This configuration shows
1000
us the impact of PV array on attained terminal voltage at the
Where, Isc is the photocurrent at temperature T and irradiance load, making a system based on only PV source and generator
G, Ki is the temperature coefficient of short circuit. quite unsuitable.

536

Authorized licensed use limited to: University of Melbourne. Downloaded on May 16,2020 at 22:02:57 UTC from IEEE Xplore. Restrictions apply.
2019 3rd International Conference on Recent Developments in Control, Automation & Power Engineering (RDCAPE)

TABLE I
PARAMETERS OF THE MODEL

Pnom (kVA) VL−L (kV) Xd Xd’ Xd” Xq


Generator 1500 13 1.305 0.296 0.252 0.474
data Xq” Tdo’ Tdo” Tqo”
0.18 0.243 4.49 0.0513
Step up Pn Vp Vs R1 and R2 L1 and L2 –
xmer 1.5 MVA 13 kV 25 kV 0.08/30 pu 0.08 pu –
Txn r1 (Ω/km) r0 (Ω/km) I1 (H/km) I0 (H/km) C1 (F/km) C0 (F/km)
lines 0.1153 0.413 1.05e-3 3.32e-3 11.33e-9 5.01e-3
PV Pnom (kW) Vp (V) Vs (kV) R1, R2 (pu) L1, L2 (pu) –
Output 150 260 25 0.001 0.03 –
Wind Pnom (MW) Vdcbus (kV) Swind (m/s) H (s) θpmax deg VL−L (V)
Output 1.5 1.15 4.43 4.32 27 575
Step-down Pn (MVA) Vp (V) Vs (kV) R1, R2 (pu) L1, L2 (pu) –
xmer 1.75 575 25 0.25/30 0.25 –

Fig. 7. Designed islanded microgrid with PV and wind farms

537

Authorized licensed use limited to: University of Melbourne. Downloaded on May 16,2020 at 22:02:57 UTC from IEEE Xplore. Restrictions apply.
2019 3rd International Conference on Recent Developments in Control, Automation & Power Engineering (RDCAPE)

Fig. 8. Voltages at different places of microgrid in presence of generator and PV only

Fig. 9. Voltages at different points of microgrid in presence of generator and wind only

B. Second combination - Generator with wind figure 10. It has clearly been seen from figures 8 - 10 that
In this case the PV subsystem is removed from the simu- wind farm has a positive impact on post fault transients of
lation and a 3L-G fault is applied at the load for a period of the hybrid system. Figures depict that hybrid system of PV-
200 to 300 ms, the voltages at various points of the model Wind responds better than the PV system working alone as a
is observed during the pre fault and post fault condition. The renewable energy source. The bus voltage at the fault clearance
plots in figure 9 show the voltages at various points in the scenario ranges to upto 0.8 pu. From the plots it is clear
microgrid. Unlike previous combination, it could clearly be that the post fault oscillations are lesser when compared to
seen from the plots that the oscillations at the bus has reduced the first case of PV and generator. Though wind/generator
in the post fault scenario. The terminal voltage at the load combination proves to be healthy for a load, the concern
is within the limit with less or no vigorous oscillations as in a microgrid is meeting the demand of the load which
compared to the case with PV and generator. The post fault could not be achieved with wind sources alone owing to its
voltage reaches upto 0.75 pu unlike 2 pu of previous case. This varying nature and intermittency. As a result the combination
result makes the wind and generator based system a bit suitable of PV/Wind/generator has been considered to be the best suited
for the load if the load demand could be met completely. system.
V. C ONCLUSION
C. Third combination - Generator with PV and wind An islanded microgrid was modelled in simulink with
With respect to the previous cases of PV/generator and various input parameters as obtained from HOMERquickstart
Wind/Generator, the final case was studied. In the final case software consisting of wind farm integrated with solar, diesel
both PV and Wind sources are included in the simulation and and battery units to supply a load of 165 kW h/day of a
the respective voltages at various points in the microgrid has rural area (Gurmia,India). Three phase fault was applied to
been observes for a 3L-G fault applied near the load as similar the system near the load and the voltages were checked
to the previous cases. The voltage plots have been shown in at various terminals of the system. The results suggest that

538

Authorized licensed use limited to: University of Melbourne. Downloaded on May 16,2020 at 22:02:57 UTC from IEEE Xplore. Restrictions apply.
2019 3rd International Conference on Recent Developments in Control, Automation & Power Engineering (RDCAPE)

Fig. 10. Voltages at different points of microgrid in presence of generator, PV and wind

wind farm is much better than PV in integration with diesel [11] S. Malla and C. Bhende, “Voltage control of stand-alone wind and solar
unit. Combination of wind/PV/diesel unit proves to be the energy system,” International Journal of Electrical Power & Energy
Systems, vol. 56, pp. 361–373, 2014.
most feasible configuration in terms of meeting up the load [12] H. Bellia, R. Youcef, and M. Fatima, “A detailed modeling of pho-
demands as well as on occurrence of faults. In addition, the tovoltaic module using matlab,” NRIAG Journal of Astronomy and
complementary nature of renewable energy sources and their Geophysics, vol. 3, no. 1, pp. 53–61, 2014.
[13] F. A. R. Abbas and M. A. Abdulsada, “Simulation of wind-turbine speed
inbuilt ability to compensate the burden on the conventional control by matlab,” International Journal of Computer and Electrical
diesel generator sets prove these to be highly acceptable in Engineering, vol. 2, no. 5, pp. 912–915, 2010.
microgrids. As presented, the popularisation can be done in [14] A. Acakpovi and E. B. Hagan, “A wind turbine system model using a
doubly-fed induction generator (dfig),” International Journal of Com-
rural areas where lack of electricity is still a concern. This puter Applications, vol. 90, no. 15, 2014.
work highlights the benefits of solar and wind configuration, [15] R. Mahalakshmi, J. Viknesh, and K. S. Thampatty, “Mathematical
with focus on transient disturbance scenario. Future work may modelling of grid connected doubly fed induction generator based wind
farm,” in 2016 IEEE International Conference on Power Electronics,
include testing of the model implementing higher ratings of Drives and Energy Systems (PEDES). IEEE, 2016, pp. 1–6.
PV and Wind farms also in grid connected mode. [16] H. Nagayoshi, T. Nakabayashi, H. Maiwa, and T. Kajikawa, “Develop-
ment of 100-w high-efficiency mppt power conditioner and evaluation
R EFERENCES of teg system with battery load,” Journal of electronic materials, vol. 40,
no. 5, pp. 657–661, 2011.
[1] M. Mehrpooya, M. Mohammadi, and E. Ahmadi, “Techno-economic- [17] N. Chitra, P. Sivakumar, S. Priyanaka, and A. Devisree, “Transient
environmental study of hybrid power supply system: A case study in behaviour of a microgrid and its impact on stability during pre and
iran,” Sustainable Energy Technologies and Assessments, vol. 25, pp. post islanding-a novel survey,” International Journal of Engineering &
1–10, 2018. Technology, vol. 7, no. 2.24, pp. 326–330, 2018.
[2] L. Zhang and Y. Li, “Optimal energy management of hybrid power
system with two-scale dynamic programming,” in 2011 IEEE/PES Power
Systems Conference and Exposition. IEEE, 2011, pp. 1–8.
[3] N. Hatziargyriou, H. Asano, R. Iravani, and C. Marnay, “Microgrids.
power and energy magazine,” IEEE, vol. 5, no. 4, pp. 78–94, 2007.
[4] A. K. Nag and S. Sarkar, “Modeling of hybrid energy system for
futuristic energy demand of an indian rural area and their optimal and
sensitivity analysis,” Renewable energy, vol. 118, pp. 477–488, 2018.
[5] J. Vishnupriyan and P. Manoharan, “Prospects of hybrid photovoltaic–
diesel standalone system for six different climate locations in indian state
of tamil nadu,” Journal of cleaner production, vol. 185, pp. 309–321,
2018.
[6] N. Saiprasad, A. Kalam, and A. Zayegh, “Comparative study of opti-
mization of hres using homer and ihoga software,” 2018.
[7] T. Lambert et al., “Micropower system modeling with homer, in
integration of alternative sources of energy by felix a. farret and m.
godoy simoes,” 2006.
[8] U. Datta, A. Kalam, and J. Shi, “Hybrid pv–wind renewable energy
sources for microgrid application: an overview,” in Hybrid-Renewable
Energy Systems in Microgrids. Elsevier, 2018, pp. 1–22.
[9] A. S. Aziz, M. F. N. Tajuddin, M. R. Adzman, M. A. Ramli,
and S. Mekhilef, “Energy management and optimization of a
pv/diesel/battery hybrid energy system using a combined dispatch strat-
egy,” Sustainability, vol. 11, no. 3, p. 683, 2019.
[10] I. Strnad and R. Prenc, “Optimal sizing of renewable sources and energy
storage in low-carbon microgrid nodes,” Electrical Engineering, vol.
100, no. 3, pp. 1661–1674, 2018.

539

Authorized licensed use limited to: University of Melbourne. Downloaded on May 16,2020 at 22:02:57 UTC from IEEE Xplore. Restrictions apply.

You might also like