Download as pdf or txt
Download as pdf or txt
You are on page 1of 136

GLOBAL CONSTRUCTION PRACTICE

CONSTRUCTION 
SCHEDULING GAMES –
REVISITED 

Session 1
March 2, 2011

Amanda Amadon
Steve Pitaniello
Jim Zack
The Presenters
GLOBAL CONSTRUCTION PRACTICE

¾ Amanda Amadon
ƒ Associate Director, Navigant                                   
Consulting, Inc.
ƒ Coral Gables, Florida
ƒ BS, Civil Engineering
ƒ Experienced in scheduling, delay                            
analysis,  acceleration, damages &                                        
lost productivity
ƒ Worked for owners, contractors,                                  
subcontractors & legal counsel
ƒ Projects include buildings, highways, power plants, 
radio transmission systems & spent nuclear fuel 
facilities
ƒ PMP
© Navigant Consulting, Inc. - 2011 2
The Presenters
GLOBAL CONSTRUCTION PRACTICE

¾ Stephen Pitaniello
ƒ Managing Director, Navigant
Consulting, Inc.
ƒ New York & Fairfield, CT
ƒ BS, Mechanical Engineering & MS,                                    
Systems Management
ƒ Experienced in design, CM, estimating,                        contract 
administration & inspection, delay,                                          
productivity analysis & damages
ƒ Worked for owners, design professionals, contractors, 
subcontractors & legal counsel
ƒ Projects include airports, highway & bridges, sport complexes, 
railway, schools & universities
ƒ PE (California & Connecticut) & CFCC

© Navigant Consulting, Inc. - 2011 3


The Presenters
GLOBAL CONSTRUCTION PRACTICE

¾ James G. Zack, Jr.
ƒ Executive Director, Navigant                                          
Construction Forum
9 “The construction industry’s premier resource
for thought leadership and best practices on
avoidance and resolution of construction project
disputes globally”
ƒ Nearly 40 years experience in construction
management & dispute analysis & resolution
ƒ Involved in more than 5,000 claims throughout U.S., Canada,
Egypt, China, Germany, Kazakhstan, Saudi Arabia, The
Russian Federation & Trinidad & Tobago
ƒ Fellow of AACE International & Royal Institution of Chartered
Surveyors
ƒ CCM, CFCC & PMP
© Navigant Consulting, Inc. - 2011 4
Introduction to “Revisited Paper”
GLOBAL CONSTRUCTION PRACTICE

¾ Original article – 1990
ƒ 4 page, bullet point memorandum to firm’s CM staff
¾ Published as “Scheduling Games People Play 
and Some Suggested Remedies” – 1991
ƒ AACE International annual transactions – 18 pages
¾ Published again “Construction Scheduling 
Games & Ways to Winʺ – 1995
ƒ CMAA annual meeting – 25 pages
¾ It’s time to bring paper into 21st Century!

© Navigant Consulting, Inc. - 2011 5


Introduction to Original Paper
GLOBAL CONSTRUCTION PRACTICE

¾ Purpose of construction scheduling
ƒ Ensure adequate planning
ƒ List all activities required
ƒ Apply logic to activities
ƒ Assist in coordination between owner, contractor, 
subcontractors, suppliers, outside agencies, etc.
ƒ Forecast time required to complete
¾ Frequent use of construction schedules
ƒ Changes
ƒ Claims

© Navigant Consulting, Inc. - 2011 6


Contractors Perform Scheduling
GLOBAL CONSTRUCTION PRACTICE

¾ Because it is
ƒ Contract requirement
ƒ “Condition precedent” to monthly payment
¾ Scheduling to some contractors
ƒ Not a project management tool
ƒ Not a coordination tool
ƒ Not a project control tool
¾ Tool to assist with recovery when seeking 
change orders or making claims

© Navigant Consulting, Inc. - 2011 7


Construction Schedule “Risk”
GLOBAL CONSTRUCTION PRACTICE

¾ Owners assume risk when require, receive & 
review contractor schedules
ƒ “Accepted” or “Approved” schedules take on legal 
status
ƒ Schedule may help document claims & damages 
against owner
¾ Some owners contend
ƒ Schedules are construction industry’s version of self 
incrimination

© Navigant Consulting, Inc. - 2011 8


Construction Schedule “Risk”
GLOBAL CONSTRUCTION PRACTICE

¾ Risk of not requiring project schedules?
ƒ Little or no planning
ƒ No way to measure progress (physical progress vs. time 
elapsed)
ƒ No way to check on or affect coordination
9 2010 Chartered Institute of Building (CIOB) study concluded 
only 14% of U.K. contractors had fully linked CPM schedules 
& 54% used only bar charts
9 Australian study concluded only 10% used CPM schedules
¾ Conclusion
ƒ Risk of not requiring schedules far outweighs risk of 
requiring, reviewing & accepting schedules

© Navigant Consulting, Inc. - 2011 9


Common Scheduling Games & Defenses
GLOBAL CONSTRUCTION PRACTICE

¾ Common Scheduling Games
ƒ Played with routine frequency
ƒ Owners need to guard against schedule gamesmanship
ƒ Some games derive from more sophisticated software
¾ Suggested Defenses
ƒ First, owners need to plan for such situations
ƒ Why?
9 Some defenses must be written into specifications prior to 
bidding
9 May require input from legal counsel
ƒ Other defense more pragmatic
9 Can be handled by owner & PM/CM if prepare in advance

© Navigant Consulting, Inc. - 2011 10


GLOBAL CONSTRUCTION PRACTICE

GAMES & DEFENSES

BASELINE SCHEDULES

© Navigant Consulting, Inc. - 2011 11


Game: Failure to Provide Schedule 
GLOBAL CONSTRUCTION PRACTICE

¾ No schedule submitted at start of project
ƒ Occurs most often when no scheduling specification
ƒ Or, when contract reads “Contractor shall submit a 
plan for constructing the work.”
¾ Owner unable to detect & demonstrate 
contractor’s failure to plan, coordinate & manage 
work properly
¾ No project schedule at outset leaves contractor 
(& claims consultant) free to build as‐planned 
vs. as‐built schedule to “prove” delay claim at 
end of project

© Navigant Consulting, Inc. - 2011 12


Defense: Detailed Scheduling Specification
GLOBAL CONSTRUCTION PRACTICE

¾ Contractors rarely volunteer to do anything 
more than contract requires
ƒ Margins too thin
¾ During design, owner & design professional 
should craft scheduling specification
ƒ Commensurate with how much control & 
involvement owner wants 
ƒ Align specification with size & complexity of project
ƒ Amount of time & cost spent will more than pay for 
itself in proper planning & coordination during 
construction

© Navigant Consulting, Inc. - 2011 13


Defense: Mobilization Payment Based on Submittal & 
Approval  of Baseline Schedule
GLOBAL CONSTRUCTION PRACTICE

¾ Lack of schedules sometimes caused by lack of 
financial incentive 
ƒ Not a pay item 
¾ Use Mobilization Payment to “entice” submittal 
& approval of Baseline Schedule
ƒ Single Mobilization Payment – make contingent upon 
submittal & approval of Baseline Schedule
ƒ Multiple Mobilization Payments –
9 1st payment – submittal of Baseline Schedule
9 2nd payment – approval of Baseline Schedule
9 3rd payment – submittal & approval of 1st schedule update

© Navigant Consulting, Inc. - 2011 14


Defense: Scheduling Start at Notice of Award  
GLOBAL CONSTRUCTION PRACTICE

¾ Project scheduling often started too late
ƒ Many specifications require schedule submittals within
“x” days after Notice to Proceed
¾ Time between Notice of Award & Notice to 
Proceed often not used for planning & 
scheduling
ƒ Contractors focus on buying out subs & material, etc.
¾ Tie schedule submittals to “x” days after Notice 
of Award
ƒ Requires contractors to use time to plan & schedule

© Navigant Consulting, Inc. - 2011 15


Defense: Milestone for Baseline Schedule Submittal &Approval
GLOBAL CONSTRUCTION PRACTICE

¾ Add contract milestone for Baseline Schedule 
submittal & approval
ƒ Create financial incentive to perform scheduling 
ƒ Reinforce with addition of liquidated damages for 
failure to achieve milestone
¾ Alternative –Tie milestone to Notice to Proceed
ƒ Two step Notice to Proceed process
9 NTP 1 – Proceed with scheduling & mobilization
9 NTP 2 – Proceed with work
ƒ “Notice to Proceed with work will not be issued until 
“x” days after Baseline Schedule submitted & approved”
¾ Submittal & review process must be clearly 
defined in contract
© Navigant Consulting, Inc. - 2011 16
Defense: Pre‐Construction Scheduling Conference
GLOBAL CONSTRUCTION PRACTICE

¾ Contractors may not understand importance of 
scheduling to owner
¾ May not understand requirements of scheduling 
specification
¾ Require Pre‐construction Scheduling 
Conference “x” days after Notice of Award
ƒ Emphasize criticality of scheduling
ƒ Discuss details & requirements of scheduling 
specification
¾ Require attendance of Project Manager & 
Scheduler

© Navigant Consulting, Inc. - 2011 17


Defense: Preliminary or 90 Day Schedule
GLOBAL CONSTRUCTION PRACTICE

¾ Specifications often require Baseline Schedule 
within 30 – 45 days after Notice to Proceed
ƒ Too little time to develop good schedule
ƒ Most often leads to schedule rejection & resubmittal
ƒ Both owner & contractor frustrated
¾ Avoid problem
¾ Require schedule for first 90 days of work within 
30 days after Notice of Award
ƒ Develop “short term” schedule promptly
ƒ Require Baseline Schedule within 45 days after 90 day 
schedule submitted

© Navigant Consulting, Inc. - 2011 18


Defense: No Work Started Until Baseline Schedule 
Submittal
GLOBAL CONSTRUCTION PRACTICE

¾ Contractor wants to start work immediately
ƒ Eager to start project just won
ƒ Needs cash flow
¾ Contractors focus on work, not on scheduling 
ƒ Especially true if very familiar with project work
ƒ “I know what needs to be done.”
¾ Better to delay start of work start to get a good 
plan
¾ Require –
ƒ “No construction work will be started nor any progress 
payments made until the Baseline Schedule is 
submitted & approved.”

© Navigant Consulting, Inc. - 2011 19


Game: Inadequate Scheduling
GLOBAL CONSTRUCTION PRACTICE

¾ If scheduling specification reads –
ƒ “Prior to start of construction Contractor shall submit a 
proposed schedule for Engineer’s review.”
¾ Language invites inadequate scheduling
¾ Schedule provide little/no detail
ƒ 12 line Gantt Chart (Bar Chart) for $20 million of work
¾ Object of game – confuse/hide time related 
issues
ƒ Makes analysis of delay & impacts very difficult
ƒ Denies owner opportunity to perform detailed analysis 
to ascertain cause, effect & responsibility for delay

© Navigant Consulting, Inc. - 2011 20


Defense: Detailed Scheduling Specification
GLOBAL CONSTRUCTION PRACTICE

¾ Detailed specification defeats inadequate 
scheduling
¾ Consider how much scheduling owner needs & 
specify it
¾ Project considerations related to scheduling
ƒ Size
ƒ Duration 
ƒ Complexity
ƒ Interface with other projects
¾ Keep in mind, capability of owner staff to 
manage scheduling requirements
© Navigant Consulting, Inc. - 2011 21
Defense: Minimum Number of Activities
GLOBAL CONSTRUCTION PRACTICE

¾ Symptom of inadequate scheduling
ƒ Too few activities in schedule
9 40 activities for $40 million project
ƒ Lacks sufficient detail to be useful
¾ Detailed scheduling specification can require
minimum number of activities
ƒ Influences level of schedule detail
ƒ Not interfere with “means & methods”
ƒ Increases understanding of contractor’s plan

© Navigant Consulting, Inc. - 2011 22


Defense: Maximum Duration Requirement
GLOBAL CONSTRUCTION PRACTICE

¾ Specify maximum duration of onsite 
construction activities 
ƒ Exclude submittal, fabrication & delivery activities
¾ May specify
ƒ Calendar or work days
ƒ Any duration
9 Probably specify no more than reporting period
9 If require monthly schedule submittal, duration no more 
than 30 cd’s or 20 wd’s
¾ Not interfere with “means & methods”
¾ Caution – Duration too short (i.e., 10 days) 
ƒ Needlessly increase number of activities in schedule

© Navigant Consulting, Inc. - 2011 23


Defense: Dedicated Scheduler
GLOBAL CONSTRUCTION PRACTICE

¾ Contractors often not employ “scheduler”
ƒ Frequently assign work to new Field Engineer
¾ Require dedicated project scheduler in 
scheduling specification
ƒ Contractor will include cost in bid
ƒ Set reasonable minimum experience requirements
ƒ Require personal references from previous owners
9 Check references!
¾ Require removal if found incompetent
¾ Require scheduler attend project meetings 
ƒ When discussing progress, delays, impacts, etc.

© Navigant Consulting, Inc. - 2011 24


Defense: Contractor’s Project Management Involvement
GLOBAL CONSTRUCTION PRACTICE

¾ Lack of project management team involvement 
in schedule development leads to inadequate 
scheduling
ƒ Disconnect between schedule & team’s plan for 
executing work
¾ Require project management team involvement 
in & sign off on Baseline Schedule
ƒ Contractor must identify specific individual responsible 
ƒ Discuss in Pre‐construction Scheduling Conference
¾ Should result in schedule that reflects plan to 
construct the project

© Navigant Consulting, Inc. - 2011 25


Defense: Owner’s Scheduler or Scheduling Consultant
GLOBAL CONSTRUCTION PRACTICE

¾ Inadequate scheduling also caused by lack of 
scheduling expertise on owner’s side
ƒ Owner needs qualified scheduling staff – internal or 
consultant
¾ Owner’s scheduling staff
ƒ Review for contract compliance
ƒ Review for adequacy
¾ Owner has shared responsibility for accurate & 
adequate schedule
ƒ Owner’s responsibility does not stop with specification 
issuance

© Navigant Consulting, Inc. - 2011 26


Defense: Scheduling System Requirements
GLOBAL CONSTRUCTION PRACTICE

¾ Another reason for inadequate scheduling
ƒ Failure to provide appropriate scheduling software
¾ Scheduling specification may require
ƒ Specific scheduling software
ƒ Match that used by owner
ƒ Cost of system software in bid
¾ If owner & contractor use different software 
accurate information exchange difficult
ƒ Leads to confusion & conflict
¾ Require computer system be located on site

© Navigant Consulting, Inc. - 2011 27


Game: Submittal Review Time
GLOBAL CONSTRUCTION PRACTICE

¾ If contract reads –
ƒ “Owner will review submittals within reasonable 
period of time so as not to delay work progress.”
ƒ Term “reasonable period of time” undefined
¾ Contractor may include insufficient submittal 
review activity duration in Baseline Schedule 
ƒ i.e., 5 days
¾ If Baseline Schedule accepted/approved, 
“reasonable period of time” now defined!
¾ Any review taking longer sets stage for delay 
claim

© Navigant Consulting, Inc. - 2011 28


Defense: Minimum Submittal Review Time
GLOBAL CONSTRUCTION PRACTICE

¾ Specify minimum submittal review time
ƒ “Unless specified differently elsewhere in contract 
documents the owner shall have 30 days from receipt of 
submittal to review & respond.”
¾ May specify 
ƒ Calendar or work days
ƒ 5, 10, 15, 20 days, etc.
ƒ Different time for different submittals
¾ Cautions
ƒ If specify too much time, may adversely impact project 
delivery
ƒ Some submittals (those requiring review by other agencies 
or owners) may require much longer review times
9 Note these submittals & specify longer timeframes

© Navigant Consulting, Inc. - 2011 29


Defense: Resubmittals – Same Review Time
GLOBAL CONSTRUCTION PRACTICE

¾ Specify – Resubmittals have the same review 
time
ƒ “Clock starts over again” approach
¾ Equitable risk assignment
ƒ Contractor can manage risk by paying more attention 
to quality of submittals
¾ Clarifies issue 
ƒ Owner & engineer do not have single timeframe to 
review submittal

© Navigant Consulting, Inc. - 2011 30


Game: Failure to Show Submittal Reviews
GLOBAL CONSTRUCTION PRACTICE

¾ Baseline schedule shows no submittal review 
activities despite contract requirement
¾ Contractor may assert that owner “waived” 
submittal review requirements
¾ More likely, contractor gives notice of delay or 
impact whenever submittal review “holds up” 
scheduled construction or installation activities
ƒ Use ʺdelayed submittal reviewsʺ to justify cumulative 
impact claim

© Navigant Consulting, Inc. - 2011 31


Defense: Submittal Reviews in Schedule
GLOBAL CONSTRUCTION PRACTICE

¾ Specify all submittals, submittal reviews, 
procurement/fabrication & deliveries included 
in schedule as activities
ƒ Eliminates one line “Submittal & Procurement” activity
ƒ Realistic model of how project will actually proceed
¾ Require designer to provide master list of 
submittals
ƒ Provide to contractor at Pre‐construction Scheduling 
Conference

© Navigant Consulting, Inc. - 2011 32


Defense: Submittal Schedule
GLOBAL CONSTRUCTION PRACTICE

¾ Require separate schedule for submittals & 
submittal reviews
ƒ Check to see that all required submittals in schedule
ƒ Increases contractor awareness of submittals & when 
required
¾ Helps owner & design professional plan own 
resources
¾ Assists with project coordination
ƒ Review at weekly project meetings
¾ Not an onerous requirement 
ƒ Not really a separate schedule
ƒ If code activities properly, this is breakout of schedule
© Navigant Consulting, Inc. - 2011 33
Defense: Define WBS Code Structure
GLOBAL CONSTRUCTION PRACTICE

¾ Specialty schedules easily produced if WBS code 
structure properly established at outset
¾ Require WBS code that identifies
ƒ Submittals & submittal reviews
ƒ Fabrication activities
ƒ Delivery activities
ƒ Installation activities
¾ Other WBS codes
ƒ Area
ƒ Trade or subcontractor work
ƒ Change order work
ƒ Etc.
© Navigant Consulting, Inc. - 2011 34
Game: Delivery Dates for Owner Furnished Items
GLOBAL CONSTRUCTION PRACTICE

¾ Not uncommon for owners to provide long lead 
items, bulk commodities, etc.
ƒ Owner must include in bid documents
¾ Contractor must include delivery dates in 
Baseline Schedule
ƒ If owner not include dates in bid documents
9 Contractor may include delivery very early
9 May include delivery on or near critical path
¾ If owner accepts schedule & not meet dates
ƒ Delays & impacts will be asserted

© Navigant Consulting, Inc. - 2011 35


Defense: Not Earlier Than Delivery Dates
GLOBAL CONSTRUCTION PRACTICE

¾ Specify “earliest possible delivery dates” for  
owner furnished items
¾ Or, provide written information when issue 
Notice of Award
¾ Require dates be included in Baseline Schedule
ƒ “Deliveries of owner furnished equipment or materials 
shall be shown in the schedule with the dates set forth 
in the contract documents or as provided by the owner 
or its designated representative.”

© Navigant Consulting, Inc. - 2011 36


Defense: Schedule Windows for Owner Furnished Items
GLOBAL CONSTRUCTION PRACTICE

¾ Set forth “not earlier than” and “not later than” 
dates for all owner furnished items
ƒ Include in contract documents
ƒ Or, provided when Notice of Award issued
¾ Require dates be included in Baseline Schedule
ƒ Allows better planning & coordination

© Navigant Consulting, Inc. - 2011 37


Game: Failure to Show Procurement Activities
GLOBAL CONSTRUCTION PRACTICE

¾ Schedule shows only installation activities
ƒ Shows no submittals, reviews, fabrication or delivery
ƒ “Star Trek Scheduling”
¾ Any time any installation activity starts “later 
than scheduled”
ƒ Delays or impacts alleged

© Navigant Consulting, Inc. - 2011 38


Defense: Incorporate Fabrication, Delivery & Installation 
Activities
GLOBAL CONSTRUCTION PRACTICE

¾ Require fabrication, delivery & installation 
activities be included in schedule for “all major 
pieces of equipment”
¾ Define, specify or list in contract documents 
what items are “all major pieces of equipment”
ƒ Assign responsibility for creating list to design 
professional
¾ Will improve project planning & coordination

© Navigant Consulting, Inc. - 2011 39


Defense: Equipment Procurement Schedule
GLOBAL CONSTRUCTION PRACTICE

¾ Require separate schedule showing submittals, 
submittal reviews, fabrication, delivery & 
installation for all “major pieces of equipment”
¾ Contract document must list “major pieces of 
equipment”
¾ Improves project planning & coordination

© Navigant Consulting, Inc. - 2011 40


Defense: Define WBS Code Structure
GLOBAL CONSTRUCTION PRACTICE

¾ Major equipment procurement schedule easily 
produced if WBS code structure properly 
established at outset
¾ Not onerous requirement
¾ Require WBS code that identifies for all “major 
pieces of equipment”
ƒ Submittals & submittal reviews
ƒ Fabrication activities
ƒ Delivery activities
ƒ Installation activities
¾ Purpose – Identify & track critical procurement 
activities
© Navigant Consulting, Inc. - 2011 41
Game: Failure to Include Schedule Constraints
GLOBAL CONSTRUCTION PRACTICE

¾ Owners may impose schedule constraints in 
contract documents
ƒ Activities that must be complete before others start
ƒ Phases of work with milestone dates
ƒ Construction sequences to avoid disruption of operations
¾ Contractors rarely understand owner needs
¾ Baseline schedule not include required constraints
¾ If schedule accepted without constraints –
ƒ Owner later insists upon maintaining constraints
ƒ Contractor argues owner “waived” requirements
ƒ Claims “extra” to reimpose constraints

© Navigant Consulting, Inc. - 2011 42


Defense: Constraints & Sequences Listed in   
Specifications 
GLOBAL CONSTRUCTION PRACTICE

¾ During design, owner must identify all specific 
constraints & sequences needed
¾ All required constraints & sequences must be 
clearly described & included in specifications
¾ If owner does not identify constraints & 
sequences at bid time
ƒ Not possible for contractor to include in bid 
ƒ Not included in project planning 
ƒ Not included in Baseline Schedule development

© Navigant Consulting, Inc. - 2011 43


Defense: Interim Milestone Dates
GLOBAL CONSTRUCTION PRACTICE

¾ Owners may influence construction sequences 
by establishing interim milestone dates
ƒ Assists contractor in planning & coordinating work
ƒ Alleviates some delay & impact claims because owner’s 
needs identified during bidding
ƒ Not interfere with “means & methods” since priced in 
bid
¾ Useful in various types of projects
ƒ Renovation projects
ƒ Projects in “operational environment”
ƒ Multiple prime situations
¾ Requires liquidated damages on each milestone 
to make enforceable
© Navigant Consulting, Inc. - 2011 44
Defense: Specified Constraints & Sequences
Reflected in Schedule
GLOBAL CONSTRUCTION PRACTICE

¾ If constraints & sequences in contract 
documents, scheduling specification must 
require they be included in Baseline Schedule & 
all Schedule Updates
¾ Language such as –
ƒ “All contractually required constraints & sequences 
shall be included in the Baseline Schedule.  If the 
Baseline Schedule or any Schedule Update does not 
include these constraints & sequences, acceptance of the 
schedule will not waive such requirements.”
ƒ Or “In event of conflict between accepted schedule & 
contract requirements, the requirements of the contract 
shall at all times govern.”
© Navigant Consulting, Inc. - 2011 45
GLOBAL CONSTRUCTION PRACTICE

QUESTIONS?

© Navigant Consulting, Inc. - 2011 46


End of Session 1
GLOBAL CONSTRUCTION PRACTICE

¾ For copy of Construction Scheduling Games –

Revisited paper

¾ Send e‐mail request to –

ƒ Amanda Amadon – aamadon@navigantconsulting.com

ƒ Steve Pitaniello – spitaniello@navigantconsulting.com

ƒ Jim Zack – jim.zack@navigantconsulting.com

© Navigant Consulting, Inc. - 2011 47


GLOBAL CONSTRUCTION PRACTICE

CONSTRUCTION 
SCHEDULING GAMES –
REVISITED 

Session 2
March 9, 2011

Amanda Amadon
Steve Pitaniello
Jim Zack
The Presenters
GLOBAL CONSTRUCTION PRACTICE

¾ Amanda Amadon
ƒ Associate Director, Navigant                                   
Consulting, Inc.
ƒ Coral Gables, Florida
ƒ BS, Civil Engineering
ƒ Experienced in scheduling, delay                            
analysis,  acceleration, damages &                                        
lost productivity
ƒ Worked for owners, contractors,                                  
subcontractors & legal counsel
ƒ Projects include buildings, highways, power plants, 
radio transmission systems & spent nuclear fuel 
facilities
ƒ PMP
© Navigant Consulting, Inc. - 2011 49
The Presenters
GLOBAL CONSTRUCTION PRACTICE

¾ Stephen Pitaniello
ƒ Managing Director, Navigant
Consulting, Inc.
ƒ New York & Fairfield, CT
ƒ BS, Mechanical Engineering & MS,                                    
Systems Management
ƒ Experienced in design, CM, estimating,                        contract 
administration & inspection, delay,                                          
productivity analysis & damages
ƒ Worked for owners, design professionals, contractors, 
subcontractors & legal counsel
ƒ Projects include airports, highway & bridges, sport complexes, 
railway, schools & universities
ƒ PE (California & Connecticut) & CFCC

© Navigant Consulting, Inc. - 2011 50


The Presenters
GLOBAL CONSTRUCTION PRACTICE

¾ James G. Zack, Jr.
ƒ Executive Director, Navigant                                          
Construction Forum
9 “The construction industry’s premier resource
for thought leadership and best practices on
avoidance and resolution of construction project
disputes globally”
ƒ Nearly 40 years experience in construction
management & dispute analysis & resolution
ƒ Involved in more than 5,000 claims throughout U.S., Canada,
Egypt, China, Germany, Kazakhstan, Saudi Arabia, The
Russian Federation & Trinidad & Tobago
ƒ Fellow of AACE International & Royal Institution of Chartered
Surveyors
ƒ CCM, CFCC & PMP
© Navigant Consulting, Inc. - 2011 51
Game: Phony Early Completion Schedules
GLOBAL CONSTRUCTION PRACTICE

¾ Many early completion schedules not real
ƒ Project not bid on early completion basis
ƒ No plan to accelerate work to finish early
¾ Contractor may
ƒ Discover after award they do not need full time to complete 
work
ƒ Bid on basis of using full time of performance, but then 
create early completion schedule
¾ Early completion schedule created, submitted & 
accepted
¾ Result
ƒ “Delayed early completion claim” filed at end of work
ƒ “But for actions of owner, I would have finished earlier.”
© Navigant Consulting, Inc. - 2011 52
Defense: Pre‐Bid Project Scheduling
GLOBAL CONSTRUCTION PRACTICE

¾ “Unrealistic” project duration
ƒ Either too long or too short
ƒ Too long
9 Contractor bids more field overhead, equipment rental, etc.
ƒ Too short
9 Contractor bids more labor & equipment, overtime pay, etc.
ƒ Either adversely influences contractor at time of 
bidding
¾ Pre‐bid project scheduling establishes 
“reasonable” time of performance
¾ Helps defend against phony early completion 
schedules
© Navigant Consulting, Inc. - 2011 53
Defense: Joint Ownership of Float
GLOBAL CONSTRUCTION PRACTICE

¾ Resolve issue of who “owns” float in contract
ƒ “Float is not for the exclusive use or benefit of either 
owner or contractor, but is jointly owned expiring 
resource available to both parties as needed to meet 
contract milestones & contract completion date.”
¾ If float “jointly owned” by contract, delayed 
early completion claims easier to defend against
ƒ Does not interfere with contractor’s right to finish early
ƒ Protects owner from delayed early completion claims

© Navigant Consulting, Inc. - 2011 54


Defense: Limited Form of No Damages for Delay Clause
GLOBAL CONSTRUCTION PRACTICE

¾ Broad form No Damages for Delay clauses often 
unenforceable
ƒ 15 States have prohibited by statute
ƒ Other States recognize 4 – 6 exceptions to clause
¾ Limited form of clause, carefully crafted may be 
enforceable 
ƒ “No time extensions will be granted nor delay damages 
paid under contract until all available float used & 
project work exceeds the adjusted contract completion 
date.”
¾ May also modify Differing Site Condition clause
ƒ If contractor encounters uncharted utility not owned by 
owner, entitled to cost to remove or relocate & 
appropriate time extension, but no delay damages
© Navigant Consulting, Inc. - 2011 55
Defense: Reduction of Contract Duration
GLOBAL CONSTRUCTION PRACTICE

¾ Include contract clause 
ƒ If contractor provides Baseline Schedule showing more 
than 30 days early completion
ƒ Owner may reduce contract duration via change order 
to match early completion date at no cost to owner
¾ Restores project balance
ƒ Neither party can assess damages against other at 
different points in time
¾ One time clause to be used only on Baseline 
Schedule
ƒ Clause not apply to later schedule updates

© Navigant Consulting, Inc. - 2011 56


Defense: Owner Credit for Field Overhead Associated 
with Early Completion
GLOBAL CONSTRUCTION PRACTICE

¾ Clause allows owner to issue a deductive change
ƒ Based on field office overhead costs saved by contractor 
due to early completion
ƒ Unless contractor can document they bid on early 
completion basis
9 If so, owner has already captured this cost benefit in the bid
¾ Will help defend against phone early completion 
schedules
¾ Risky clause
ƒ Bid costs may go up because contractor who has good 
idea of how to complete early may not employ this 
approach
ƒ Discourages contractors from scheduling early 
completion
© Navigant Consulting, Inc. - 2011 57
Defense: Escrow Bid Documents
GLOBAL CONSTRUCTION PRACTICE

¾ Require low bidder to submit all bid 
documentation within 48 hours after opening
¾ Specification states –
ƒ “Any documents not included in escrow bid documents 
not admissible in event of later dispute.”
¾ Bid documentation escrowed in local bank
ƒ Only designated personnel may review 
ƒ Always accompanied by personnel from other side
ƒ Only used in event of dispute
ƒ Only review portion of documents related to dispute
¾ Escrow bid documents used to prove/disprove 
claim of planned early completion when bid
© Navigant Consulting, Inc. - 2011 58
Defense: Banked Float Requirement
GLOBAL CONSTRUCTION PRACTICE

¾ Float can be created either by owner or contractor
ƒ Easier for owner – return CP submittal early
ƒ Contractor – make labor work more productively
¾ Specification provides float “created” by either 
party credited to that party
ƒ Record & bank float monthly
ƒ Delays later caused by parties offset by banked float
¾ Requires owner & contractor to jointly review 
schedule updates 
ƒ Negotiate monthly who created how much float during 
update period
ƒ Float in schedule to right of data date still jointly owned

© Navigant Consulting, Inc. - 2011 59


Game:  Preferential Logic
GLOBAL CONSTRUCTION PRACTICE

¾ Activities arranged in such a manner as to create 
maximum possible opportunity for owner 
interference
¾ Especially effective in multiple prime situations
¾ If owner accepts schedule
ƒ Delay or impacts arise whenever owner requests a 
different sequence

© Navigant Consulting, Inc. - 2011 60


Game: Sequestering of Float
GLOBAL CONSTRUCTION PRACTICE

¾ Schedule created deliberately with little or no 
float
¾ May have multiple critical paths or single 
critical path with numerous subcritical paths
¾ Methods of sequestering float
ƒ Preferential Sequencing – activities performed 
sequentially vs. concurrently to hide float
ƒ Artificial Activity Durations – Inflate activity durations 
to remove float
ƒ Zero Float Dates – establish schedule milestones with 
zero float dates
¾ Goal – Consume all float, not share float
© Navigant Consulting, Inc. - 2011 61
Defense: Thorough Review of Baseline & Schedule 
Updates
GLOBAL CONSTRUCTION PRACTICE

¾ Owners need to understand liability associated 
with reviewing & accepting schedules
ƒ Much legal risk accompanies schedule acceptance
¾ Schedule reviews as critical as review of 
technical submittals
¾ Review for –
ƒ Compliance with specification requirements
ƒ Preferential logic, unusual construction logic
ƒ Unrealistic activity durations
ƒ Submittal review times
ƒ Sequestering of float
ƒ Failure to include critical activities & mandatory 
constraints
© Navigant Consulting, Inc. - 2011 62
Defense: Subcontractor Sign Off Requirement
GLOBAL CONSTRUCTION PRACTICE

¾ Specify all “major subcontractors” required to 
review & sign off on Baseline Schedule & all 
Schedule Updates
ƒ Define “major subcontractor” in specification
ƒ Example:  Any subcontractor with more than 5% of 
contract value
¾ Contractors playing schedule games often do not 
involve subcontractors
ƒ Why?
ƒ Games against owner also likely to harm 
subcontractors
¾ Use subcontractors to detect, avoid schedule 
games
© Navigant Consulting, Inc. - 2011 63
Defense: Non‐Sequestering of Float Clause
GLOBAL CONSTRUCTION PRACTICE

¾ Include Non‐Sequestering of Float clause in 
scheduling specification
ƒ “Pursuant to float sharing requirements … use of float 
suppression techniques … are prohibited & float shall 
be shared to benefit of owner & contractor.”
¾ Clause provides that float sequestering shall be 
cause for rejection of schedule submittal

© Navigant Consulting, Inc. - 2011 64


Defense: Resource Loading of Schedule Activities
GLOBAL CONSTRUCTION PRACTICE

¾ Clause requires all onsite construction activities 
be resource loaded
ƒ Cost
ƒ Labor
ƒ Equipment
¾ Compare activity resources with activity 
durations to determine reasonableness of plan
¾ Use resource histograms to track & trend actual 
work performance
¾ Use resource loading information when 
analyzing delay & impact claims

© Navigant Consulting, Inc. - 2011 65


Game: Failure to Show Startup/Test Activities
GLOBAL CONSTRUCTION PRACTICE

¾ Baseline Schedule shows no time or nominal 
time for startup & testing
¾ Delay & impact claims arise when startup & 
testing take significantly longer
¾ Especially true if startup & testing required 
prior to “mechanical completion” or “substantial 
completion”
ƒ Claims of “superior knowledge” on part of owner 
frequently arise
ƒ Remember – Liquidated damages frequently stop at 
substantial completion date

© Navigant Consulting, Inc. - 2011 66


Defense: Estimate Startup & Testing
GLOBAL CONSTRUCTION PRACTICE

¾ Lack of schedule activities may not be a game
ƒ May result from contractor’s lack of knowledge of 
whatʹs required
¾ Owners often know more about startup & 
testing than contractor
¾ Owners should set forth required activities &  
estimate time to perform required startup & 
testing
ƒ Include list of activities required in specification
ƒ Include time estimated in contract documents
ƒ Require contractor include “no less than” estimated 
time in Baseline Schedule
© Navigant Consulting, Inc. - 2011 67
GLOBAL CONSTRUCTION PRACTICE

GAMES & DEFENSES

SCHEDULE UPDATES

© Navigant Consulting, Inc. - 2011 68


Game: No Schedule Updates
GLOBAL CONSTRUCTION PRACTICE

¾ If specification states updates only required 
when “major changes” occur
ƒ What is “major change”?
¾ Schedule updates infrequent, non‐existent
¾ Game – delays, impacts, changes must be 
analyzed on basis of as‐planned schedule
ƒ As‐Planned vs. Actual delay analysis
¾ Denies owner opportunity to analyze concurrent 
delay, pacing delay, contractor problems, etc.

© Navigant Consulting, Inc. - 2011 69


Defense: Scheduling – Pay Item on Schedule of Values
GLOBAL CONSTRUCTION PRACTICE

¾ Scheduling rarely paid for directly by owners
¾ To entice contractors to provide schedule 
updates, make schedule updates pay item on 
schedule of values
¾ Owner may
ƒ Establish value in bid for scheduling
ƒ Allow fixed % of contract cost for scheduling
ƒ Negotiate monthly pay item amount at outset of work
¾ Contractor entitled to bill for schedule update 
pay item only after update submitted & 
approved

© Navigant Consulting, Inc. - 2011 70


Defense: Pay Off the Schedule Specification
GLOBAL CONSTRUCTION PRACTICE

¾ Require all onsite construction activities be cost 
loaded
¾ Sum of all cost loaded activities must equal 
contract value at all times
¾ Monthly payment calculated from accepted 
schedule update
¾ No schedule update submittal, no monthly 
billing
ƒ No billing, no payment owed!

© Navigant Consulting, Inc. - 2011 71


Defense:  Liquidated Damages for Late Schedule 
Submittals
GLOBAL CONSTRUCTION PRACTICE

¾ May include liquidated damages for late 
schedule update submittals
¾ Emphasizes criticality of scheduling to owner
¾ Damages for late schedule updates difficult to 
ascertain
ƒ Use language similar to that used in liquidated 
damages for late completion clause
ƒ Base liquidated damages on what it would cost owner 
if owner had to take over scheduling
ƒ Assuming owner has no in‐house scheduling staff use 
daily cost of scheduling consultant as basis for 
liquidated damages

© Navigant Consulting, Inc. - 2011 72


Defense: Withholding of Payment for Failure to Submit 
Schedule Update
GLOBAL CONSTRUCTION PRACTICE

¾ If choose to take this approach –
ƒ Contract must state that submittal of schedule update is 
a “condition precedent” to making payment
¾ May be enforceable – Check with legal counsel!
ƒ But very harsh remedy
¾ However, if using Pay Off the Schedule 
specification then both logical & prudent

© Navigant Consulting, Inc. - 2011 73


Game: Inaccurate As‐Built information
GLOBAL CONSTRUCTION PRACTICE

¾ Deliberately utilize incorrect start & finish dates 
for updated schedule activities
ƒ Start dates likely to be earlier than actual
ƒ Finish dates likely to be later than actual
¾ Technique slowly “absorbs” float 
¾ At times, not a game – scheduler may
ƒ Lack documentation of actual dates
ƒ Activities statused by % complete
9 Remaining durations based on % complete times original 
duration
9 May not be accurate projection 
9 Activities in reporting period statused as 100% on day prior 
to data date vs. inputting actual dates
© Navigant Consulting, Inc. - 2011 74
Game: Schedule Away Project Delay
GLOBAL CONSTRUCTION PRACTICE

¾ If contractor behind schedule but does not want 
to show in update
ƒ Provide schedule update showing end date has not
slipped
¾ Scheduler may –
ƒ Reduce durations of remaining activities
ƒ Change logic of remaining activities
9 Activities shown as concurrent vs. finish‐start
¾ Effect of game –
ƒ Cover up project delay

© Navigant Consulting, Inc. - 2011 75


Game: Changing Project History
GLOBAL CONSTRUCTION PRACTICE

¾ Consume float by changing start & finish dates 
of previously completed activities
ƒ Run current schedule update based on changed past 
activity dates
¾ Influences schedule & consumes float

© Navigant Consulting, Inc. - 2011 76


Game: Changing Project Calendars
GLOBAL CONSTRUCTION PRACTICE

¾ Game is unintended consequence of current 
scheduling software packages
ƒ Newer software allows schedulers to change project 
calendar every time schedule is updated
¾ Software enhancement intended for use on daily 
or hourly schedules
ƒ Not typical construction schedules
¾ Changing project calendars may consume float 
slowly with each update
ƒ Even though work is proceeding as planned

© Navigant Consulting, Inc. - 2011 77


Defense: Spot Check Project History
GLOBAL CONSTRUCTION PRACTICE

¾ Require a Schedule Change Report as part of 
each update
ƒ Separate report that identifies every change made to 
schedule from last update
ƒ Includes – logic changes, durations, actual starts & 
finishes, activity additions & deletions, calendars, etc.
¾ Carefully review Schedule Change Report to 
determine no changes to previously submitted 
dates, activities, etc.
¾ May use third party forensic schedule analysis 
software to perform review
¾ Carefully review contractor’s schedule update 
narrative 
© Navigant Consulting, Inc. - 2011 78
Defense: Schedule Away Project Delay
GLOBAL CONSTRUCTION PRACTICE

¾ Common ways to schedule away project delay
ƒ Delete or Add Activities
9 Changing activities from Baseline Schedule generally poor 
scheduling practice
9 Unless owner issued changes requires this
9 Otherwise – indicator scheduler modifying schedule & 
should be questioned
ƒ Changing Original Durations
9 Changing duration from Baseline Schedule generally poor 
scheduling practice
9 Unless owner issued changes requires this
9 Otherwise – indicator scheduler modifying schedule & 
should be questioned
9 May be indication of project delay or impact & should be 
questioned & must be justified
© Navigant Consulting, Inc. - 2011 79
Defense: Schedule Away Project Delay
GLOBAL CONSTRUCTION PRACTICE

ƒ Changes in Relationships
9 Deleting or adding relationship way to increase or decrease 
time to complete project
9 May be game or may indicate project delay & impact
9 Should be questioned & justified
ƒ Use of Leads or Lags
9 Changes relationships, may be way to schedule away delay
9 Should be questioned & justified
ƒ Use of Constraints
9 Can interrupt schedule calculations
9 If constraints added – question & get justification
ƒ Retained Logic vs. Progress Override
9 Progress Override accelerates schedule, ignores logic ties

© Navigant Consulting, Inc. - 2011 80


Defense: Joint Updating Requirement
GLOBAL CONSTRUCTION PRACTICE

¾ Require joint schedule update meetings in 
scheduling specification
¾ Owner, design professional, contractor & “major 
subcontractors” 
ƒ Work together to review & update schedule monthly
ƒ Must identify who is “major subcontractor”
9 Subcontractors act as tripwire vs. schedule games
¾ Enhances communications & coordination
ƒ Not interfere with “means & methods”
¾ Reduces likelihood of schedule games
¾ Forum to discuss potential delays & impacts
ƒ Work together to resolve issues proactively

© Navigant Consulting, Inc. - 2011 81


Defense: Addition of Activities for Resubmittals
GLOBAL CONSTRUCTION PRACTICE

¾ Schedulers may include owner resubmittal 
review time in same activity as review of initial 
submittal
ƒ Gives appearance owner took too long to review
¾ Specification should require scheduler add new
activity for every resubmittal required
¾ Clearly identifies contractor responsibility vs. 
owner responsibility 
ƒ Impacts more visible, better understood
ƒ Delay more easily analyzed

© Navigant Consulting, Inc. - 2011 82


Defense: Electronic Schedule Update Submittals
GLOBAL CONSTRUCTION PRACTICE

¾ Require electronic schedule update submittals
¾ Require hard copy of Predecessor/Successor 
Report
ƒ Run same report from electronic submittal
ƒ Check to see that two reports identical
ƒ If not, something is wrong!
¾ When receive electronic submittal
ƒ Schedule checks can be run electronically using built in 
or third party schedule analysis software
ƒ Games more easily detected

© Navigant Consulting, Inc. - 2011 83


Defense: Recorder of Schedule Requirement
GLOBAL CONSTRUCTION PRACTICE

¾ Specification requires that –
ƒ Contractor creates Baseline Schedule & submits
ƒ Accepted Baseline Schedule entered into owner’s computer
ƒ Becomes “Record Schedule”
ƒ Owner’s scheduler is “Schedule Recorder” for project
¾ Monthly update process –
ƒ Contractor submits list of changes from last update
ƒ Schedule Recorder enters changes exactly as submitted
ƒ Schedule Recorder submits updated schedule to contractor 
for contractor approval
ƒ Once contractor approves, owner reviews for acceptance
ƒ Most schedule update games prevented
ƒ Schedule Recorder must be responsive to contractor’s timing 
& needs at all times

© Navigant Consulting, Inc. - 2011 84


Defense: Weekly Progress Reports
GLOBAL CONSTRUCTION PRACTICE

¾ Contractors typically use weekly bar charts for 
own trade superintendents & foreman
ƒ Referred to as “2 or 3 week look aheads”
¾ Highly accurate, detailed information
¾ Specify contractor provide  weekly ʺlook aheadʺ 
schedules to owner
¾ Accept schedules in same form as provided to 
contractor’s own staff & subcontractors
ƒ No need for contractor to create more schedules
¾ Use ʺlook aheadʺ schedules to check schedule 
update accuracy
© Navigant Consulting, Inc. - 2011 85
Game: Failure to Include Change Orders in
Schedule Updates
GLOBAL CONSTRUCTION PRACTICE

¾ Change order work not incorporated into 
schedule updates promptly
ƒ Especially true if contractor attempting to reserve rights 
for delay & delay impact in change order
¾ Or, changes included in such manner as to show 
maximum potential impact to project schedule
¾ Object of game – maximize recovery for changes

© Navigant Consulting, Inc. - 2011 86


Defense:  Time Impact Analysis Requirement
GLOBAL CONSTRUCTION PRACTICE

¾ Require that contractor submit Time Impact 
Analysis (TIA) with every change order proposal
ƒ Even if contractor not seeking time extension
¾ TIA uses “Fragnets” (fragmentary networks) to 
demonstrate impact of change on existing 
schedule
ƒ Miniature CPM networks showing all activities related 
to change, logic, sequence & duration 
ƒ Fragnet “plugged into” existing schedule to determine 
impact, if any, of change on schedule

© Navigant Consulting, Inc. - 2011 87


Defense:  Time Impact Analysis Requirement
¾ TIA well recognized schedule delay analysis 
GLOBAL CONSTRUCTION PRACTICE

technique
ƒ Dates back to 1960’s on VA & NASA projects
¾ But, a prospective delay analysis technique
ƒ Forward looking only
ƒ Take today’s schedule, add change, recalculate schedule, 
determine impact
¾ Does not work well when applied retroactively
ƒ Backward looking analysis
ƒ If changed work completed before delay analysis, TIA 
may not work 
ƒ Does not account for other ongoing activities
ƒ May need to specify a different technique for 
retrospective delay analysis
© Navigant Consulting, Inc. - 2011 88
Defense: Fee for Change Order Schedule Analysis
GLOBAL CONSTRUCTION PRACTICE

¾ Typically, contractors not entitled to payment for 
preparing & submitting change order proposals
ƒ Owners consider this contractor overhead
¾ To entice contractors to submit delay analysis on 
all change orders –
ƒ Specify fee paid to contractor for every TIA submitted
ƒ Even if shows no impact or change order not issued
ƒ Must make fee large enough to entice submittals
¾ Encourages schedule analysis submittals
¾ Enhances change order negotiations
¾ Creates contemporaneous record of impacts
© Navigant Consulting, Inc. - 2011 89
GLOBAL CONSTRUCTION PRACTICE

GAMES & DEFENSES

END OF JOB SCHEDULING

© Navigant Consulting, Inc. - 2011 90


Game: After the Job “But For” Schedules
GLOBAL CONSTRUCTION PRACTICE

¾ Claim schedule created at completion of work
¾ Typical scheduling techniques at end of job
ƒ As‐Planned vs. As‐Built
ƒ Impacted As‐Planned
ƒ But For Schedule
9 AKA – Collapsed As‐Built Schedule
¾ Often performed by claims consultant 
ƒ Was not involved in project
ƒ Relies solely upon contractor’s records & staff
¾ Frequently, As‐Built Schedule does not resemble 
contractor’s schedule updates

© Navigant Consulting, Inc. - 2011 91


Game: After the Job “But For” Schedules
GLOBAL CONSTRUCTION PRACTICE

¾ Owner required to “prove” claims schedule not
accurate, not reliable
ƒ Factually
ƒ Or, in its conclusion
¾ Requires detailed schedule analysis by owner
ƒ Very costly

© Navigant Consulting, Inc. - 2011 92


Defense: As‐Built CPM Submittal “Condition Precedent” 
to Release of Retainage
GLOBAL CONSTRUCTION PRACTICE

¾ Require final schedule update be “certified” by 
contractor as accurate representation of how job 
was built
ƒ Certified by contractor’s Project Manager & Scheduler
¾ Recognize that –
ƒ Schedule will have no logic, no critical path
ƒ But should be a contemporaneous record of actual start 
& finish dates of all activities
ƒ Can be used to analyze & challenge claims schedule
¾ Make submittal “condition precedent” to release 
of retainage to enforce requirement
ƒ To get retained earnings, must submit 
© Navigant Consulting, Inc. - 2011 93
Game: Substantial Completion Activity
GLOBAL CONSTRUCTION PRACTICE

¾ Substantial Completion –
ƒ Typically stops liquidated damages
ƒ Owner deemed to have ”benefit of bargain”, can use 
project for “intended purpose”
¾ To lessen chances of having liquidated damages 
assessed –
ƒ Contractors include “substantial completion activity” in 
schedule
ƒ Place as far forward as possible
¾ Assert any activity past substantial completion 
activity not subject to liquidated damages

© Navigant Consulting, Inc. - 2011 94


Defense: Define “Substantial Completion”
GLOBAL CONSTRUCTION PRACTICE

¾ Define term “substantial completion” in contract
ƒ Each project different
ƒ No standard definition
ƒ Owner & design professional must craft definition 
carefully
ƒ Must be done for every project individually
¾ Check Baseline Schedule & schedule updates
ƒ Ensure all activities needed to reach substantial 
completion
ƒ Actually scheduled prior to substantial completion 
activity

© Navigant Consulting, Inc. - 2011 95


GLOBAL CONSTRUCTION PRACTICE

QUESTIONS?

© Navigant Consulting, Inc. - 2011 96


End of Session 2
GLOBAL CONSTRUCTION PRACTICE

¾ For copy of Construction Scheduling Games –

Revisited paper

¾ Send e‐mail request to –

ƒ Amanda Amadon – aamadon@navigantconsulting.com

ƒ Steve Pitaniello – spitaniello@navigantconsulting.com

ƒ Jim Zack – jim.zack@navigantconsulting.com

© Navigant Consulting, Inc. - 2011 97


GLOBAL CONSTRUCTION PRACTICE

CONSTRUCTION 
SCHEDULING GAMES –
REVISITED 

Session 3
March 16, 2011

Amanda Amadon
Steve Pitaniello
Jim Zack
The Presenters
GLOBAL CONSTRUCTION PRACTICE

¾ Amanda Amadon
ƒ Associate Director, Navigant                                   
Consulting, Inc.
ƒ Coral Gables, Florida
ƒ BS, Civil Engineering
ƒ Experienced in scheduling, delay                            
analysis,  acceleration, damages &                                        
lost productivity
ƒ Worked for owners, contractors,                                  
subcontractors & legal counsel
ƒ Projects include buildings, highways, power plants, 
radio transmission systems & spent nuclear fuel 
facilities
ƒ PMP
© Navigant Consulting, Inc. - 2011 99
The Presenters
GLOBAL CONSTRUCTION PRACTICE

¾ Stephen Pitaniello
ƒ Managing Director, Navigant
Consulting, Inc.
ƒ New York & Fairfield, CT
ƒ BS, Mechanical Engineering & MS,                                    
Systems Management
ƒ Experienced in design, CM, estimating,                        contract 
administration & inspection, delay,                                          
productivity analysis & damages
ƒ Worked for owners, design professionals, contractors, 
subcontractors & legal counsel
ƒ Projects include airports, highway & bridges, sport complexes, 
railway, schools & universities
ƒ PE (California & Connecticut) & CFCC

© Navigant Consulting, Inc. - 2011 100


The Presenters
GLOBAL CONSTRUCTION PRACTICE

¾ James G. Zack, Jr.
ƒ Executive Director, Navigant                                          
Construction Forum
9 “The construction industry’s premier resource
for thought leadership and best practices on
avoidance and resolution of construction project
disputes globally”
ƒ Nearly 40 years experience in construction
management & dispute analysis & resolution
ƒ Involved in more than 5,000 claims throughout U.S., Canada,
Egypt, China, Germany, Kazakhstan, Saudi Arabia, The
Russian Federation & Trinidad & Tobago
ƒ Fellow of AACE International & Royal Institution of Chartered
Surveyors
ƒ CCM, CFCC & PMP
© Navigant Consulting, Inc. - 2011 101
GLOBAL CONSTRUCTION PRACTICE

SCHEDULE REVIEW CHECKLIST

© Navigant Consulting, Inc. - 2011 102


Schedule Review Checklist
GLOBAL CONSTRUCTION PRACTICE

¾ Following is schedule review checklist intended 
to detect & prevent schedule games
¾ Applicable to Baseline Schedule & Schedule 
Updates
¾ Broken down into 
ƒ Software settings
ƒ Dates
ƒ Activities
ƒ Critical path
ƒ Constraints
ƒ Calendars

© Navigant Consulting, Inc. - 2011 103


Defense: Software Settings
GLOBAL CONSTRUCTION PRACTICE

¾ Retained Logic vs. Progress Override
ƒ Progress Override accelerates schedule
ƒ May accelerate schedule unrealistically
ƒ Ignores logic ties & relationships
ƒ Retained Logic typically better choice
ƒ If work not proceeding as planned, Progress Override 
may give better picture of progress
¾ Continuous Activities
ƒ Software typically assume activities performed 
continuously
ƒ If default setting changed, should be reviewed & 
justified
9 If not planned continuously, need multiple activities

© Navigant Consulting, Inc. - 2011 104


Software Settings
GLOBAL CONSTRUCTION PRACTICE

¾ Total Float Calculation
ƒ Finish date is software default
9 Better reflects relationship between project completion & 
float
ƒ Changes in setting can cause variations in float 
calculations within same schedule
ƒ If settings changed, must be justified & documented

© Navigant Consulting, Inc. - 2011 105


Defense: Dates
GLOBAL CONSTRUCTION PRACTICE

¾ Start Date
ƒ Start date of schedule
ƒ Typically NTP or NTP + 1 day
ƒ May be earlier date contractor feels should be in 
schedule – must justify to owner
ƒ Once set in Baseline Schedule, never changes
¾ Data Date
ƒ Date from which unfinished work scheduled
ƒ Future activities start at beginning of closest work day 
after Data Date
ƒ Anything else should raise questions, needs justification

© Navigant Consulting, Inc. - 2011 106


Defense: Dates
GLOBAL CONSTRUCTION PRACTICE

¾ Schedule Status Through
ƒ End of last work day prior to Data Date
ƒ “Actual” work recorded & statused through this date
ƒ Anything else should raise questions
¾ Must Finish By Date (MFB)
ƒ Typically, contract completion or milestone date
ƒ Any other activities using this type of date or constraint 
must be justified by contractor

© Navigant Consulting, Inc. - 2011 107


Defense: Dates
GLOBAL CONSTRUCTION PRACTICE

¾ Calculated Finish Date
ƒ Latest calculated early finish (EF) date in schedule
ƒ Calculated project completion date
ƒ If date exceeds MFB date, negative float results
ƒ If occurs, indicates project delay
ƒ Examine closely – contractor must justify
¾ Total Calendar Day Duration
ƒ Total calendar days (not work days) from start to finish 
ƒ Compare to Time of Completion clause
ƒ More days shown – indicates project delay

© Navigant Consulting, Inc. - 2011 108


Defense: Dates
GLOBAL CONSTRUCTION PRACTICE

¾ Calendar Days Remaining
ƒ Number of calendar days remaining from Data Date to 
completion date
ƒ Add time expended to calculation & compare to Time 
of Completion clause
ƒ Anything longer indicates project delay 
¾ Percentage Calendar Days Expended
ƒ % calendar days expended to Data Date
ƒ Compare % to estimated % of work completed to see if 
correlation exists
ƒ If substantially different, may indicate project delay or 
impact (i.e., lost productivity)

© Navigant Consulting, Inc. - 2011 109


Defense: Dates
GLOBAL CONSTRUCTION PRACTICE

¾ Calendar Days Remaining to MFB Date
ƒ % calendar days remaining from Data Date to 
completion date
ƒ Compare % to estimated % work completed to see if 
there is correlation
ƒ If substantially differs, may indicate project delay or 
impact
¾ MFB/EF Variance
ƒ Difference in calendar days between MFB date & 
completion date
ƒ Negative value indicates project will not complete on 
time

© Navigant Consulting, Inc. - 2011 110


Defense: Dates
GLOBAL CONSTRUCTION PRACTICE

¾ New Actual Starts
ƒ Number of activities statused with actual start date
ƒ Does not include previous updates 
¾ Changed Actual Starts
ƒ Number of previous actual start dates changed in 
update
ƒ May indicate changing project history
ƒ Must be justified by contractor
¾ New Actual Finishes
ƒ Number of activities statused with actual finish date
ƒ Does not include previous updates 

© Navigant Consulting, Inc. - 2011 111


Defense: Dates
GLOBAL CONSTRUCTION PRACTICE

¾ Changed Actual Finishes
ƒ Number of previous actual finish dates changed in 
update
ƒ May indicate changing project history
ƒ Must be justified by contractor
¾ Actual Start Dates              Data Date
ƒ Data Date begins at start of Data Date workday
ƒ Starting point for all remaining activities
ƒ Actual starts & finishes should be “as of” work day 
prior to Data Date
ƒ Actual dates on or beyond Data Date
9 Poor scheduling practice, not how schedule calculates

© Navigant Consulting, Inc. - 2011 112


Defense: Dates
GLOBAL CONSTRUCTION PRACTICE

¾ Actual Finish Dates              Data Date
ƒ Data Date begins at start of Data Date workday
ƒ Starting point for all remaining activities
ƒ Actual starts & finishes should be “as of” work day 
prior to Data Date
ƒ Actual dates on or beyond Data Date
9 Poor scheduling practice, not how schedule calculates

© Navigant Consulting, Inc. - 2011 113


Defense: Activities
GLOBAL CONSTRUCTION PRACTICE

¾ Number of Activities
ƒ Total number of activities in schedule
ƒ Activities added to /deleted from Baseline Schedule 
must be submitted for review & approval
ƒ Identified & discussed in Update Narrative Report
¾ Net Increase or Decrease
ƒ Increase or decrease of number of schedule activities
ƒ Number of activities should remain constant unless –
9 Work scope changed 
9 Plan for performing work changed
9 Impacts incorporated into schedule
ƒ Identified & discussed in Update Narrative Report

© Navigant Consulting, Inc. - 2011 114


Defense: Activities
GLOBAL CONSTRUCTION PRACTICE

¾ Number of Relationships
ƒ Number of relationships should remain constant after 
Baseline Schedule accepted
ƒ Changes should be submitted for review & approval
¾ Net Increase or Decrease
ƒ Increase or decrease in number of relationships
¾ Relationship/Activity Ratio
ƒ Ratio of relationships to activities
ƒ Always more than 1.0
ƒ Ratio of 1.2 to 1.5 average
ƒ Higher than 1.5 may indicate logically constrained 
schedule
© Navigant Consulting, Inc. - 2011 115
Defense: Activities
GLOBAL CONSTRUCTION PRACTICE

¾ Started
ƒ Number of activities started during update period
ƒ Indicator of continued progress of work
ƒ Fewer activity starts than previous period may indicate 
project delay or impact
¾ Completed
ƒ Number of activities completed during update period
ƒ Indicator of continued progress of work
ƒ Fewer activity completions than previous period may 
indicate project delay or impact

© Navigant Consulting, Inc. - 2011 116


Defense: Activities
GLOBAL CONSTRUCTION PRACTICE

¾ In Progress
ƒ Activities in progress during update period
ƒ Increase in number of activities indicates more work 
being accomplished
ƒ Decrease in number of activities indicates less work 
being accomplished – may indicate project delay/impact 
ƒ Number usually increases until near end of job
¾ Not Started
ƒ Number should decline as work progresses
ƒ If new activities added, may not decline
9 Should be reviewed for potential schedule problems
ƒ If number constant for 2 or more updates, indicates 
project delay or impact
© Navigant Consulting, Inc. - 2011 117
Defense: Activities
GLOBAL CONSTRUCTION PRACTICE

¾ Percentage of Activities Completed
ƒ % should increase with each update
ƒ If number declines or remains constant indicates stalled 
progress, shut down period or delay & impact
¾ Activities Deleted
ƒ Total number of activities deleted in update
ƒ Deleting activities after Baseline Schedule accepted 
poor scheduling practice
ƒ If work or work plan changes significantly enough to 
warrant this, may need to rebaseline schedule

© Navigant Consulting, Inc. - 2011 118


Defense: Activities
GLOBAL CONSTRUCTION PRACTICE

¾ Activities Added
ƒ Total number of activities added in update
ƒ Many valid reasons for adding new activities
ƒ All should be submitted for approval in Update 
Schedule Narrative
¾ Original Durations Changes
ƒ Original durations from Baseline Schedule should not
change unless approved
ƒ Changing durations  (shortening) may be indicator of 
changing project history, scheduling away project delay
ƒ If durations increase, may be indicator of delay or 
impact

© Navigant Consulting, Inc. - 2011 119


Defense: Activities
GLOBAL CONSTRUCTION PRACTICE

¾ Activity Descriptions Edited/Changed
ƒ Descriptions in Baseline Schedule should not change
ƒ Difficult to compare progressed schedule to Baseline 
Schedule when activity descriptions/titles changed
ƒ Should be submitted for review & approval
¾ Number of Deleted Relationships
ƒ Total number of activities deleted in update
ƒ Deleting relationships after Baseline Schedule accepted 
poor scheduling practice
ƒ If work or work plan changes significantly enough to 
warrant this, may need to rebaseline schedule

© Navigant Consulting, Inc. - 2011 120


Defense: Activities
GLOBAL CONSTRUCTION PRACTICE

¾ Number of Added Relationships
ƒ Total number of activities added in update
ƒ Adding relationships after Baseline Schedule accepted  
poor scheduling practice
ƒ If work or work plan changes significantly enough to 
warrant this, may need to rebaseline schedule
¾ Activities with Lags
ƒ Lags represent “hidden activities” 
9 Similar to “dummies” in I‐J networks
ƒ Lags often justified but should be submitted for review 
& approval in Baseline Schedule
ƒ Lags more than 15 days should be defined as activities  
& included in schedule for better visibility
© Navigant Consulting, Inc. - 2011 121
Defense: Activities
GLOBAL CONSTRUCTION PRACTICE
¾ Activities with Negative Lag
ƒ Negative lag often prohibited in scheduling 
specifications
ƒ Negative lags identified, justified in schedule narrative
¾ Relationship Lags Changes
ƒ Any changes in previously submitted value should be 
submitted for review & approval in schedule narrative
¾ Activities with No Predecessors
ƒ Only one activity should have no predecessor – start of 
schedule
ƒ Others with no predecessor must be fixed
ƒ Missing relationships can produce unrealistic dates & 
float values
© Navigant Consulting, Inc. - 2011 122
Defense: Activities
GLOBAL CONSTRUCTION PRACTICE

¾ Activities with No Successors
ƒ Only one activity should have no successor – finish of 
schedule
ƒ Others with no successor must be fixed
ƒ Missing relationships can produce unrealistic dates & 
float values
¾ Activities Working Out of Sequence
ƒ Out of sequence progress common in construction
ƒ Indicates project not being built as planned
ƒ Scheduling specifications often require out of sequence 
work progress be resolved with each update
ƒ Progress Override ignores logic, accelerates schedule, 
reduces impact of out of sequence work
9 May accelerate schedule unrealistically
© Navigant Consulting, Inc. - 2011 123
Defense: Activities
GLOBAL CONSTRUCTION PRACTICE

¾ Constraints Added
ƒ Constraints interrupt schedule calculations
ƒ All constraints, changes to constraints identified in 
Schedule Narrative for review & approval
¾ Constraints Deleted
ƒ All constraints, changes to constraints identified in 
Schedule Narrative for review & approval
¾ Existing Constraints Changes
ƒ All constraints, changes to constraints identified in 
Schedule Narrative for review & approval

© Navigant Consulting, Inc. - 2011 124


Defense: Activities
GLOBAL CONSTRUCTION PRACTICE

¾ Activities That Should Have Started
ƒ When activities do not start when planned, may 
indicate progress not keeping up with plan
ƒ May indicate project delay or impact
ƒ Examine carefully
¾ Activities That Should Have Finished
ƒ When activities do not finish when planned, may 
indicate progress not keeping up with plan
ƒ May indicate project delay or impact
ƒ Examine carefully

© Navigant Consulting, Inc. - 2011 125


Defense: Activities
GLOBAL CONSTRUCTION PRACTICE

¾ Number of Activities Percent Complete Reduced
ƒ On in‐progress activity, percent complete should 
increase from update to update
ƒ If percent complete decreases, indicates negative 
progress for update period or schedule games
ƒ Examine carefully

© Navigant Consulting, Inc. - 2011 126


Defense: Critical Path
GLOBAL CONSTRUCTION PRACTICE

¾ Lowest Total Float
ƒ Shows lowest total float on project
ƒ Ideal = zero float
ƒ Positive float indicates early completion
ƒ Negative float indicates late completion
¾ Activities on Critical Path
ƒ Number of activities on CP in each update
ƒ If number increases from month to month, may 
indicate near critical activities becoming critical & 
project slipping
ƒ Increase may indicate project delay or impact

© Navigant Consulting, Inc. - 2011 127


Defense: Constraints
GLOBAL CONSTRUCTION PRACTICE

¾ Number of Constraints
ƒ Total number of constraints in schedule
ƒ Many scheduling specifications require only milestones 
be used as constraints
ƒ All constraints should be submitted for review & 
approval in Schedule Narrative
¾ Number of Zero Total Float Constraints
ƒ Zero Total Float Constraint makes an activity appear to 
be critical
ƒ May indicate poor scheduling practice or schedule 
games

© Navigant Consulting, Inc. - 2011 128


Defense: Constraints
GLOBAL CONSTRUCTION PRACTICE

¾ Number of Mandatory Constraints
ƒ Mandatory constraints force activity to start or finish on 
exact date
ƒ Reality in construction, activity may start/finish earlier 
or later
ƒ Date rarely mandatory
ƒ Mandatory constraints often misused

© Navigant Consulting, Inc. - 2011 129


Defense: Calendars
GLOBAL CONSTRUCTION PRACTICE

¾ Calendars
ƒ Number of calendars used in schedule increases 
schedule complexity
ƒ High number of calendars used may indicate
9 Overly complex schedule
9 Scheduling games
¾ Calendars without Holidays
ƒ One purpose of calendars in schedule, define non‐work 
days so activities not scheduled on those days
ƒ No holidays in schedule could add as much as 10 work 
days/year to schedule – unrealistic!

© Navigant Consulting, Inc. - 2011 130


Defense: Calendars
GLOBAL CONSTRUCTION PRACTICE

¾ Untitled Calendars
ƒ Indication of poor scheduling practice
ƒ All calendars should be titled so scheduler & schedule 
reviewer understand what calendar is
¾ Number of Calendars on Critical Path
ƒ Multiple calendars on CP can result in interruption of 
float values on CP or longest path
ƒ Should be submitted for review & approval as to 
purpose & justification

© Navigant Consulting, Inc. - 2011 131


Defense: Calendars
GLOBAL CONSTRUCTION PRACTICE

¾ Number of Calendar Changes
ƒ Calendar assignments should not change from update 
to update
ƒ Changes to calendars should be submitted & justified 
in Schedule Update Narrative

© Navigant Consulting, Inc. - 2011 132


Schedule Review Checklist Wrap Up
GLOBAL CONSTRUCTION PRACTICE

¾ These are checks schedule reviewer should 
make with every review
¾ Schedule analysis software make checking 
easier
¾ Schedule reviewer ought to –
ƒ Create spreadsheet with each check on vertical access & 
Baseline Schedule & Schedule Updates on horizontal 
access
ƒ Creates pictorial view of updates
ƒ Review can compare numbers, update to update
ƒ Determine what needs more thorough review or 
justification
© Navigant Consulting, Inc. - 2011 133
Conclusion
GLOBAL CONSTRUCTION PRACTICE

¾ Intended purpose of scheduling to provide 
proper planning, coordination & management of 
project
¾ Schedules frequently used for other purposes
¾ Schedule games often played
¾ Means & methods available to defend against 
schedule gamesmanship
ƒ Restore schedule to status of planning, coordination & 
management tool

© Navigant Consulting, Inc. - 2011 134


GLOBAL CONSTRUCTION PRACTICE

QUESTIONS?

© Navigant Consulting, Inc. - 2011 135


End of Session 3
GLOBAL CONSTRUCTION PRACTICE

¾ For copy of Construction Scheduling Games –

Revisited paper

¾ Send e‐mail request to –

ƒ Amanda Amadon – aamadon@navigantconsulting.com

ƒ Steve Pitaniello – spitaniello@navigantconsulting.com

ƒ Jim Zack – jim.zack@navigantconsulting.com

© Navigant Consulting, Inc. - 2011 136

You might also like