Professional Documents
Culture Documents
Six Sigma Updated PDF
Six Sigma Updated PDF
Which of the following places should be considered when selecting improvement team members?
1 / 1 point
Correct
Correct: All are valid except IV. Team leaders should never look to those who agree to easily and
are not prepared to challenge perceptions and embrace change
2.
Question 2
A key characteristic of an individual team member is:
1 / 1 point
Correct
Correct: Team members are not required to work off schedules. This is sometimes necessary. They
also do not need to possess and full knowledge of the organization or understand all elements of the
problem. A fresh set of eyes can be very valuable to the team. Much in the way the MBB serves the
team. The primary characteristic is their belief in the power of the team and its potential to leverage
abilities and adjust to changes with greater speed and efficiency.
3.
Question 3
What is the typical length of training for a black belt?
1 / 1 point
Six Weeks
Six Months
Six days
Correct
Correct: The length of black belt training typically varies. Clearly, a training regiment over six days
would hardly be effective. A nonconsecutive program is highly desirable that a project can be
pursued in parallel with the training to best apply and gain confidence in using the tools.
4.
Question 4
Which of the following are black belt roles?
I. Facilitating meetings
II. Scheduling the next meeting
1 / 1 point
II and IV only
I and II only
Correct
Correct: The team recorder or secretary will normally draft and distribute the meeting minutes
5.
Question 5
Identify the incorrect statement about black belts from below:
1 / 1 point
The level of engagement between the black belt and the master black belt stays the same
throughout the duration of the project
Each team member, not the black belt, Is responsible for completing assignments between
meetings.
Correct
Correct: The black belt is not always the boss. It is a collaborative effort with shared leadership.
Individuals are always empowered to complete their own tasks. Black belts should have training in
improvement techniques. This is part of the six sigma methodology. B is not correct. As the project
progresses, the MBB backs off so that the BB can take a more engaged direct leadership role.
6.
Question 6
What is the best reason for upper management to not provide black belt assistance to an
improvement team?
1 / 1 point
Correct
Correct: Several of the answers can be applicable, but the most practical reason to withhold black
belt resources is if it is not required.
7.
Question 7
The individual with the most technical training and knowledge in six sigma principles resides with
which role?
1 / 1 point
Black Belts
Green Belts
Sponsors
Correct
Correct: The increasing knowledge flow in six sigma goes from green belt, to black belt to master
black belt. A sponsor typically has training at the yellow belt level, if at all. However, some sponsors
can be master black belts.
8.
Question 8
Which of the following would be considered an advantage of training managers in six sigma over line
workers?
III. Managers must have a command of the terminology and methodology to gain support and advance the object
the project
1 / 1 point
Correct
Correct: Managers must lead the effort and validate training. They also must understand the
fundamentals of six sigma to be effective. Managers typically have as much or more demands on
their time.
9.
Question 9
Which group is most likely to receive the equivalent of fundamental six sigma basics training?
1 / 1 point
Senior management
Correct
Correct: Senior management would typically fill the role of champion, sponsor, or process owner and
would typical require the equivalent of yellow belt training which is the most fundamental of all the
trainings. The answer is A.
10.
Question 10
Which six sigma role is tasked with defining the objectives for a project improvement team?
1 / 1 point
Sponsor
Individual Contributor
Black Belt
Correct
Correct: Although the Master Black belt and Black belt can assist in defining the objectives, the
Sponsor is typically the role that defines and crafts the objectives for a project improvement team
Question 1
One of Dr. Deming’s 14 points states “Cease dependence upon inspection as a way to achieve
quality” What is the meaning of this statement?
1 / 1 point
Operators should be required to inspect their product to eliminate the need for inspection
The product should be designed well enough so that quality is evident and there is no need to
inspect quality in.
Inspection operations are not as robust as we need and typically miss 10-20% of defects
The cost of an inspector is overhead and adds too much cost to the problem
Correct
Correct: This answer explains the statement best. If a product is designed well enough, there is no
need for inspection. We only inspect for things that can fail. Not for things that cannot fail. Inspecting
quality into a product is ineffective and costly.
2.
Question 2
At the end of a lean six sigma project, who should be the primary beneficiary of the project results?
1 / 1 point
Employees
Top Management
Sponsors
Customer
Correct
All of the choices are considered stakeholders and are impacted by the lean six sigma project. The
customer; however, is the reason we choose to drive down variation and reduce waste. The
customer is the answer
3.
Question 3
Which of the following is not one of Harry’s original six sigma methodology phases?
1 / 1 point
Improve
Define
Control
Measure
Correct
Correct! Harry’s initial process included Measure, Analyze, Improve and Control. Define was added
later.
4.
Question 4
The prime objective associated with lean is:
1 / 1 point
Eliminating Waste
Improving quality
Correct
Correct: All answers are definitely important to any production operation. Outcomes from lean can
include any of these choices; however, the underlying tenet of lean is to eliminate any of the eight
wastes.
5.
Question 5
Why has six sigma been embraced and sustained by so many organizations?
II. +/- 1.5 sigma shift between short term and long term variation
1 / 1 point
I, II and IV only
Correct
Correct: II can be eliminated. The +/- 1.5 sigma shift is a consequence of process variation and must
accounted for in process improvement measures. It is hardly justification for embracing six sigma. I,
III, IV are far more relevant.
6.
Question 6
Six Sigma project benefits include:
1 / 1 point
No change in profit
Correct
Correct: Some project benefits can be expressed in dollars. This is ideal. Some examples include
increased sales, increased profits, reduced defects, reduced scrap, lowered warranty claims,
improved process capability, increased up time, reduced spare part inventories, fewer customer
cancellations or returned products. Other project benefits are worthwhile but harder to quantify such
as employee morale, increased skill levels, lower employee turnover, increased customer
satisfaction, more aesthetically appealing product, enhanced organizational reputation. Increased
set up time, no change in profit and increased rework would not be considered a project benefit.
7.
Question 7
Which of the following would be considered a strategic quality goal?
1 / 1 point
Correct
Correct: Strategic goals tend to be more broad in scope. Tactical goals are more detailed. Reducing
the scrap rate, improved performance inspection checks, and training 10 green belts in statistical
techniques are tactical and a is strategic.
8.
Question 8
Using the DMAIC approach to six sigma improvement, at what step would the root cause of the
determined and validated?
1 / 1 point
Define
Control
Measure
Analyze
Correct
Correct: According the slide presentation, this would be in the Analyze phase
9.
Question 9
Increasing performance in a six sigma corporation from 4 sigma to 5 sigma would reduce defects per
million by a factor of _________.
1 / 1 point
27
287
Correct
Correct: 4 sigma produces a PPM of 6210. 5 sigma produces a 233 ppm. 6210/233 ~ 27
10.
Question 10
Defect levels, as reported by Motorola in their six sigma program, are higher than one might expect
from use of a standard normal table or traditional capability calculations. Why is this true?
1 / 1 point
Correct
Correct: The central limit theorem tells us that all processes will follow a normal behavior for a high
enough data set. The normal curve is symmetrical, therefore a two tail scenario is the only
applicable. Six Sigma efforts will not increase process variation. The 1.5 sigma shift is the only
plausible explanation.
Question 1
The ideal number of team members is:
1 / 1 point
10-15
7-10
5-7
3-5
Correct
Correct!
2.
Question 2
Challenges related to team building, technology, physical distance, language, and cultural
differences are common in:
1 / 1 point
Virtual Teams
Self-Managed Teams
Correct
Correct!
3.
Question 3
A group of team members who plan and direct themselves toward a common goal is called a:
1 / 1 point
Self-Managed Team
Virtual Team
Cross-Functional Team
Correct
Correct!
4.
Question 4
Negative behavior such as excessive arguing is likely in which stage of team development?
1 / 1 point
Norming
Forming
Adjourning
Storming
Performing
Correct
Correct!
5.
Question 5
A time for reflection and celebrations occurs in which stage of team development?
1 / 1 point
Forming
Norming
Adjourning
Storming
Performing
Correct
Correct!
6.
Question 6
Members get oriented towards team goals, and team leadership is directive in which stage of team
development?
1 / 1 point
Norming
Performing
Adjourning
Forming
Storming
Correct
Correct!
7.
Question 7
Team members begin to be more constructive and to work out differences, while the leader
becomes less directive, in which stage of team development?
1 / 1 point
Storming
Norming
Performing
Forming
Adjourning
Correct
Correct!
8.
Question 8
The team members realize interdependence, and leadership tends to delegate in which stage of
team development?
1 / 1 point
Storming
Norming
Forming
Adjourning
Performing
Correct
Correct!
9.
Question 9
Team Leaders should exhibit the same consistent style of leadership throughout team development.
1 / 1 point
True
False
Correct
Correct!
10.
Question 10
Persistent negative team dynamics usually results from:
1 / 1 point
Organizational Culture
Correct
Correct!
1 / 1 point
Correct
Correct!
2.
Question 2
The most difficult step in 5S is:
1 / 1 point
Sort
Set in Order
Shine
Standardize
Sustain
Correct
Correct!
3.
Question 3
What Value Stream Mapping Symbol represents a step in the process?
1 / 1 point
Symbol:
Symbol:
Symbol:
Symbol:
Correct
Correct!
4.
Question 4
What Value Stream Mapping Symbol represents transportation?
1 / 1 point
Symbol:
Symbol:
Symbol:
Symbol:
Correct
Correct!
5.
Question 5
What Value Stream Mapping Symbol represents a supplier or customer?
1 / 1 point
Symbol:
Symbol:
Symbol:
Symbol:
Correct
Correct!
6.
Question 6
What Value Stream Mapping Symbol represents information flow?
1 / 1 point
Symbol:
Symbol:
Symbol:
Symbol:
Correct
Correct!
7.
Question 7
The Value Stream primarily focuses on activities within your facility.
1 / 1 point
True
False
Correct
Correct!
8.
Question 8
JIT is:
1 / 1 point
An inventory strategy
A visual signal
A communication strategy
Correct
Correct!
9.
Question 9
Kan Ban is:
1 / 1 point
A communication strategy
An inventory strategy
A visual signal
Correct
Correct!
10.
Question 10
The wastes (Muda) most closely associated with excessive Work in Process (WIP) are:
1 / 1 point
Correct
Correct!
Question 1
Which is not a good way to get the Voice of the Customer?
1 / 1 point
Correct
Correct! We should always listen to our customer.
2.
Question 2
Which is certainly true about Critical to Satisfactions (CTS’s)?
1 / 1 point
CTS’s is like putting an aquarium in a lobby, nice to look at but does not benefit the customer
CTS’s are the basic elements used in driving process measure, improvement and control
Correct
Correct! CTS’s are the building blocks to be used in driving process measurement, improvement and
control.)
3.
Question 3
What is the intention of Benchmarking?
1 / 1 point
Correct
Correct! Benchmarking is used to identify and compare best practices.
4.
Question 4
SWOT stands for Strengths, Weaknesses, Opposition, and Threats
1 / 1 point
True
False
Correct
Correct!
5.
Question 5
In Stakeholder Analysis, it is the ______________ of the process that determines who the customer
is.
1 / 1 point
Boundary
Beginning
Elimination
Grouping
Correct
Correct! The boundary of process is determined by the identity of the customer.
6.
Question 6
Which is not true regarding a robust quality program?
1 / 1 point
Quality is achieved through the prevention of problems, and not creating them
Correct
Correct! Remember quality is measured by exceeding customer needs. These needs are defined by
the customer. We always want to prevent problems as opposed to detecting them. This is a valuable
trait in any robust quality program.
7.
Question 7
The purpose of Business Process Management is to understand, control, and improve business
processes to create a value for all stakeholders.
1 / 1 point
True
False
Correct
Correct! The purpose of Business Process Management is to understand, control, and improve
business processes to create a value for all stakeholders
8.
Question 8
What does SIPOC not do?
1 / 1 point
Correct
Correct! The S.I.P.O.C. will not help you identify your dog.
9.
Question 9
In the SIPOC, the P stands for:
1 / 1 point
Productivity
Process
Planning
Practically anything
Correct
Correct! The P stands for Process.
10.
Question 10
Processes exists to:
1 / 1 point
Job security
Correct
Correct! Processes exist to accomplish work and tasks.
11.
Question 11
There is only one type of critical to satisfaction measure
1 / 1 point
True
False
Correct
Correct! There are many types of critical to satisfaction measures.
1 / 1 point
Correct
Correct! The machine with the highest overall score is the likely choice.
2.
Question 2
What is the best characteristic of an Activity Network Diagram?
1 / 1 point
Consists of no dates
Correct
Correct! An activity network diagram consists of a sequence of activities with start and end dates.
3.
Question 3
Which of the following is not considered a benefit or goal of a project?
1 / 1 point
Correct
Correct! Ignoring quality concerns is not a benefit.
4.
Question 4
When is a good time to mention at a meeting any new obstacles that could delay the project?
1 / 1 point
Correct
Correct! This is the ideal time in a meeting to mention a perceived obstacle that could jeopardize the
success of the project.
5.
Question 5
Why would anyone use a Relationship Chart?
1 / 1 point
None of these
Correct
Correct! A relationship chart is used to explore the cause-and-effect of a particular problem.
6.
Question 6
Which of the following is not true? Brainstorming sessions are conducted to:
1 / 1 point
Correct
Correct! This is certainly not helping your project.
7.
Question 7
What is the importance of having measurable milestones in your project?
1 / 1 point
8.
Question 8
The Project Charter consists of the following:
1 / 1 point
Correct
Correct! These are the 5 components of the project charter.
9.
Question 9
Which of the following is not a good reason to create a Tree Diagram:
1 / 1 point
I like trees
Correct
Correct! I like trees too, but not a good reason to create a tree diagram.
10.
Question 10
Which of the following are characteristics of Information Processing?
1 / 1 point
Correct
Correct! Go on a fact finding tour with everyone involved.
1 / 1 point
8.75
5.28
3.56
4.96
Correct
Correct! You have correctly calculated the correct mean.
2.
Question 2
For this dataset, answer the following:
1 / 1 point
6.3
7.7
4.5
2.5
Correct
Correct! You have correctly calculated the median.
3.
Question 3
For this dataset, answer the following:
1 / 1 point
6.3
2.5
7.7
4.5
Correct
Correct! You have correctly calculated the mode.
4.
Question 4
For this dataset, answer the following:
1 / 1 point
3.8
5.4
5.2
Correct
Correct! 8.5 minus 2.5.
5.
Question 5
For this dataset, answer the following:
1 / 1 point
2.65
1.13
2.18
3.97
Correct
Correct! You have correctly calculated the standard deviation.
6.
Question 6
For this dataset, answer the following:
1 / 1 point
4.75
1.28
7.02
15.76
Correct
Correct! You have correctly calculated the sample variance.
7.
Question 7
What can we do to distinguish separate datasets if they have the same mean, median, and mode?
1 / 1 point
Correct
Correct! Using the measures of variability will help further distinguish between datasets.
8.
Question 8
Which is not the range?
1 / 1 point
The difference between the maximum and the minimum observances of data
Correct
Correct! The mean and the range are not the same.
9.
Question 9
Can the mean be also called the average?
1 / 1 point
No
Yes
Correct
Correct! The mean or the arithmetic mean can also be referred to as the average.
10.
Question 10
A .473 batting average is better than a .305.
1 / 1 point
False
True
Correct
Correct! In baseball, the higher the batting average, the better.
Question 1
Descriptive Statistics is a method for drawing a conclusion about a population based on its sample.
1 / 1 point
True
False
Correct
Correct! Descriptive Statistics consists of methods for organizing and summarizing information.
2.
Question 2
Which is not a sampling type?
1 / 1 point
Systematic Sample
Cluster Sample
Simple Random Sample
Correct
Correct! Difficult random sampling is not a valid sampling technique.
3.
Question 3
Which statement is not a characteristic of a Measurement System?
1 / 1 point
Correct
Correct! Measurement systems are not considered in quality analysis.
4.
Question 4
What is a Variable?
1 / 1 point
A characteristic that varies from one point of the assessment to the other
5.
Question 5
Which of the following is not a characteristics of Operational Measurements?
1 / 1 point
Go out and count all the red cars you see in the next hour
Correct
Correct! An example of a non-operationally defined measurement would be: Go out and count the
number of red cars you see in the next hour.
6.
Question 6
Which is not a step in the Data Collection Plan?
1 / 1 point
Correct
Correct! This is not a part of the data collection plan.
7.
Question 7
What is the purpose of measuring something?
1 / 1 point
To quantify performance
All of these
Correct
Correct! To gain feedback and early warnings, quantify performance, and motivate people and
prioritize opportunities are all reasons to measure something.
8.
Question 8
What is one thing we do not wish to learn from the customer?
1 / 1 point
Their needs
Their likes
Correct
Correct! Demographic data is not shared by the customer.
9.
Question 9
An advantage of using the telephone as a survey tool is that it is convenient.
1 / 1 point
True
False
Correct
Correct! The advantage of using a telephone is that it is less expensive and easier to monitor for
quality control.
10.
Question 10
When developing a data collection technique, which step would not be possibly repeated multiple
times.
1 / 1 point
Item Analysis
Pilot
Construction
Correct
Correct! We only construct the data collection technique once.
Question 1
Which statement is not a characteristic of a Measurement System?
1 / 1 point
Correct
Correct! Measurement systems are very much needed to quantify your quality analysis.
2.
Question 2
Calibration:
1 / 1 point
Correct
Correct! Calibration is applied to match the output of a measuring device to that of a known
standard.
3.
Question 3
Only the Measurement System Variability form the Total Observed Variation distribution.
1 / 1 point
False
True
Correct
Correct! Measurement errors AND process variability sum together to form the Total Observed
Variation distribution.
4.
Question 4
Gage Bias is defined as:
1 / 1 point
The (directional) difference between the observed mean of measurements and a known standard
Correct
Correct! Gage bias has direction (+-) and is the difference between the observed mean of the
measurements and a known standard.
5.
Question 5
Which is not a source of variation?
1 / 1 point
Correct
Correct! Mean shifting is not the same as variation from the mean.
6.
Question 6
Accuracy is how close the agreement is between the mean of one or more measured results to that
of a reference or standard value
1 / 1 point
True
False
Correct
Correct! Accuracy is how close the agreement is between the mean of one or more measured
results to that of a reference or standard value.
7.
Question 7
In a measurement system, what is Reproducibility precision?
1 / 1 point
The variation in measurement means when the same gage is used by the same operator
The variation in measurement averages when the same gage is used by different operators
Correct
Correct! The variation in measurement averages when the same gage is used by different operators
8.
Question 8
Accuracy and Precision are the same thing.
1 / 1 point
True
False
Correct
Correct! They are not the same.
9.
Question 9
What is the basis for Gage Repeatability and Reproducibility?
1 / 1 point
Variation in the observed measurements due to the operators and the equipment
Correct
Correct!
10.
Question 10
Linearity is the accuracy of measurements at various points along the measuring range of the
equipment.
1 / 1 point
True
False
Correct
Correct! Linearity is the accuracy of measurements at various points along the measuring range of
the equipment.
Quality Tools designated for the Analyze phase of the DMAIC model cannot be used in other
phases.
1 / 1 point
True
False
Correct
Correct!
2.
Question 2
How much of the time that product is in a factory is non-value added?
1 / 1 point
65-80%
35-50%
80-95%
50-65%
Correct
Correct!
3.
Question 3
If it is determined that a step in the process is non-value added, it can automatically be removed.
1 / 1 point
True
False
Correct
Correct!
4.
Question 4
Some companies add a sixth S to the 5S process. This extra S is for:
1 / 1 point
Standardize
Shine
Sustain
Sort
Set in order
Safety
Correct
Correct!
5.
Question 5
Which 5S step is most difficult to accomplish?
1 / 1 point
Standardize
Sustain
Sort
Set in Order
Shine
Correct
Correct!
6.
Question 6
Which 5S step tells us that we should have a place for everything and everything in its place?
1 / 1 point
Set in Order
Sort
Shine
Standardize
Sustain
Correct
Correct!
7.
Question 7
When analyzing a process to eliminate waste, the first question to ask is:
1 / 1 point
Do we have control?
Correct
Correct!
8.
Question 8
If a process step is non-value added, we might still need to keep it if:
1 / 1 point
Correct
Correct!
9.
Question 9
When implementing 5S, items that are not used every day are typically:
1 / 1 point
Stored nearby
Discarded
Correct
Correct!
10.
Question 10
In which work environment is 5S an effective tool?
1 / 1 point
Manufacturing
Service
Healthcare
Correct
Correct!
When using the 5 whys tool, it is important to ask why exactly 5 times.
1 / 1 point
True
False
Correct
Correct!
2.
Question 2
5 Whys is best used by:
1 / 1 point
Correct
Correct!
3.
Question 3
Which of the 8 wastes is made most visible by a Spaghetti Diagram?
1 / 1 point
Correct
Correct!
4.
Question 4
When creating a process map, using all of the available symbols is not important.
1 / 1 point
True
False
Correct
Correct!
5.
Question 5
Which type of tool will best help you identify process handoffs?
1 / 1 point
Spaghetti Diagram
Measles Diagram
Flow Chart
Correct
6.
Question 6
Process Mapping is often the first step in process improvement.
1 / 1 point
True
False
Correct
Correct!
7.
Question 7
When applied to an existing process, a process map should represent the process as:
1 / 1 point
It actually operates
Correct
Correct!
8.
Question 8
Who will know the most about how a process actually operates?
1 / 1 point
Correct
Correct!
9.
Question 9
Force Field Analysis requires careful and accurate data collection.
1 / 1 point
True
False
Correct
Correct!
10.
Question 10
When performing a Force Field Analysis:
1 / 1 point
Sometimes you might identify forces that belong on both sides of the chart
Correct
Correct!
Question 1
Which of the images below is right-skewed?
1 / 1 point
.
Correct
Correct!
2.
Question 2
Which of the images below is bimodal?
1 / 1 point
.
.
Correct
Correct!
3.
Question 3
Suppose heights of children in a youth baseball league are normally distributed with a mean of 48
inches and a standard deviation of 2 inches. Estimate the percentage of children in the league that
are shorter than 45 inches.
1 / 1 point
93.3%
56.7%
43.3%
6.7%
Correct
Correct!
4.
Question 4
Suppose heights of children in a youth baseball league are normally distributed with a mean of 48
inches and a standard deviation of 2 inches. Estimate the percentage of children in the league that
are taller than 44 inches.
1 / 1 point
97.7%
2.3%
47.7%
52.3%
Correct
Correct!
5.
Question 5
Suppose heights of children in a youth baseball league are normally distributed with a mean of 48
inches and a standard deviation of 2 inches. Estimate the percentage of children in the league that
are between 43 and 45 inches.
1 / 1 point
6.1%
93.9%
6.7%
93.3%
Correct
Correct!
6.
Question 6
Which of the following is NOT a requirement to model with the binomial distribution?
1 / 1 point
Correct
7.
Question 7
Which of the following COULD be modeled using the binomial distribution?
1 / 1 point
The probability of getting exactly 3 questions correct when randomly guessing on a 10 question
true/false test.
The number of each letter in the alphabet found in the next 10 license plates that pass <this does not
have two states
The probability of exactly 2 defects when taking a sample of size 20 from a lot of size 100 that is
known to be 8% defective.
The number of green lights you go through before you encounter a red light <this does not have a
set number of trials
Correct
Correct! x is discrete and equal to 3, your two states are correct and incorrect answers, there are 10
trials, and the probability of guessing correctly remains constant at 1/2.
8.
Question 8
Suppose that a sample of size 12 is randomly chosen from a batch of size 800 that is known to be
5% defective. What is the probability that there is exactly one defective item in your sample?
1 / 1 point
.070
.659
.099
.341
Correct
Correct!
9.
Question 9
Which of the following is true about variation:
1 / 1 point
Correct
Correct!
10.
Question 10
The impact of temperature fluctuations within the plant on the variability in a process would be
characterized as what type of variation?
1 / 1 point
Common cause
Bivariate
Unimodal
Special cause
Correct
Correct!
11.
Question 11
A control chart signals that the mean of your process has increased and after investigating it is
determined that an operator incorrectly adjusted the equipment. The variation due to the operator’s
incorrect adjustment is an example of what type of variation?
1 / 1 point
Common cause
Special cause
Unimodal
Bivariate
Correct
Correct!
If you are studying the relationship between the number of hours of overtime assigned at your facility
and the number of defects in your product, what would the INDEPENDENT variable be?
1 / 1 point
Both the hours of overtime assigned and the number of defects in your product
Neither the hours of overtime assigned nor the number of defects in your product
Correct
Correct answer: You are studying what happens when hours of overtime assigned varies
2.
Question 2
A scatter plot in which the plotted points are clustered approximately into a straight line from the
bottom left to the top right of the graph is displaying which of the following:
1 / 1 point
Positive correlation
Negative correlation
No correlation
Bimodal correlation
Correct
Correct answer: With a positive slope from left to right we have positive correlation
3.
Question 3
If a scatter diagram is created plotting vegetable garden square footage vs. crop yield, what would
you expect the shape of the resulting plot to show?
1 / 1 point
Positive correlation
No correlation
Negative correlation
Circular correlation
Correct
Correct answer: we would expect that the crop yield would increase as the square footage available
increases
4.
Question 4
Which of the following statements are true about correlation?
1 / 1 point
The lower the correlation coefficient is, the weaker the correlation is
A positive correlation coefficient means that as the independent variable decreases, the dependent
variable increases
5.
Question 5
In the equation for basic linear regression, what does the term “a” represent?
1 / 1 point
The y intercept
The x intercept
The error
6.
Question 6
In statistical analysis, the equation y=a+bx is most commonly used for what?
1 / 1 point
Descriptive statistics
Correct
Correct answer: This is the standard form for the linear regression equation.
7.
Question 7
What is the method used to find the equation of the regression line called?
1 / 1 point
Question 8
You collect sample data to calculate the relationship between overtime hours assigned at your
facility and the number of defects in your product. Using data ranging from 50 hours of overtime to
200 hours of overtime, you obtain the regression equation for defects of 0.75 + 0.02x with a high
correlation coefficient. How many defects would you predict if 100 hours of overtime are assigned?
(Round to the nearest 100th of a defect)
1 / 1 point
75.02
2.00
2.75
Correct
Correct answer: This comes from substituting 100 for x in the regression equation. 0.75 + 0.02*(100)
= 2.75
9.
Question 9
You collect sample data to calculate the relationship between overtime hours assigned at your
facility and the number of defects in your product. Using data ranging from 50 hours of overtime to
200 hours of overtime, you obtain the regression equation for defects of 0.75 + 0.02x with a high
correlation coefficient. How many defects would you predict if 10,000 hours of overtime are
assigned? (Round to the nearest 100th of a defect)
1 / 1 point
200.75
275.00
2.75
Correct
Correct answer: Since data collected was only from 50 to 200 hours of overtime, we cannot assume
that the same relationship holds for a huge 10,000 hours of overtime.
10.
Question 10
In which phase is regression analysis LEAST likely to be used?
1 / 1 point
Analyze
Define
Improve
Measure
Correct
Correct answer: To find out more about why this is correct review page 149 in the Yellow Belt
Handbook or the Regression for Six Sigma video.
If you want to test the claim that the mean time between failures of a particular piece of equipment
has increased from 207.1 operating hours, what would your alternative hypothesis be?
1 / 1 point
Correct
Correct answer: The claim we are making should be written as the alternative hypothesis.
2.
Question 2
If you want to test the claim that the mean time between failures of a particular piece of equipment
has increased from 207.1 operating hours, what would your null hypothesis be?
1 / 1 point
.
.
Correct
Correct! Our claim,
3.
Question 3
If the null hypothesis is true and one fails to reject it,
1 / 1 point
Correct
Correct answer: If the null hypothesis is true, then the correct answer would be not to reject it.
4.
Question 4
Suppose you want to test the claim that the mean time between failures of a particular piece of
equipment has increased from 207.1 operating hours. Your sample data leads you to reject H0. The
actual mean is 207.0. What type of error, if any, have you made?
1 / 1 point
Correct
Correct: Since the mean is 207.1, the null hypothesis is true. Therefore rejecting it is a type I error.
5.
Question 5
If a small difference truly does exist between two processes, but the sample taken is too small to
determine that difference, what type of error would likely result?
1 / 1 point
Type II
Type I
No error
Correct
Correct answer: If there is a difference, then the correct answer would be to reject the null
hypothesis. If your sample is too small, you will fail to reject, which is a type II error in that situation.
6.
Question 6
What is the opposite of the alpha risk?
1 / 1 point
Type I error
Producer’s risk
Beta risk
Correct
Correct: For more information on why this is correct you can review page 151 in the Yellow Belt
Handbook, or the Types of Errors video.
7.
Question 7
Why would one choose to set
as opposed to 0.10?
1 / 1 point
8.
Question 8
If your hypothesis test is:
1 / 1 point
Binomial
Right-tailed
Two-tailed
Left-tailed
Correct
Correct answer: Whenever our alternative hypothesis is “not equal to”, we have a 2-tailed test.
9.
Question 9
The output from Minitab software is a p-value of 0.12. If the desired level of significance is 0.05 then
the conclusion is:
1 / 1 point
Correct
Correct: When the p-value is greater than alpha, we fail to reject the null hypothesis.
10.
Question 10
While performing a hypothesis test, you calculate a p-value of 0.005. If the desired level of
significance is 0.01 then the conclusion is:
1 / 1 point
Correct
Correct answer: When the p-value is less than alpha, we reject the null hypothesis.
Optimizing individual or departmental performance will always hurt the performance of the
organization
1 / 1 point
True
False
Correct
Correct. Sometimes optimizing individual or departmental performance will hurt organizational
performance. As a result, it is necessary to adopt a systems view, and see how individual or
departmental performance affects the performance of the system as a whole. Our obligation should
be to optimize the system.
2.
Question 2
Kaizen is focused on dramatic rapid improvements
1 / 1 point
True
False
Correct
Correct. Kaizen means improvement through small incremental steps.
3.
Question 3
In Kaizen, employees are empowered to change anything in the process that they think is
appropriate.
1 / 1 point
True
False
Correct
Correct. Changes are proposed by employees, and reviewed by process owners.
4.
Question 4
Kaizen blitz, or kaizen events are often spontaneous.
1 / 1 point
True
False
Correct
Correct. Kaizen events are usually carefully planned weeks in advance.
5.
Question 5
Team members are trained at the beginning of a Kaizen Blitz or Kaizen event.
1 / 1 point
True
False
Correct
Correct. By training employees at the beginning of the event, the knowledge is fresh, and since they
immediately apply their new knowledge and skills it is more likely to be retained.
6.
Question 6
In which step of the PDCA model would you evaluate the results, and check the effects of your
improvement?
1 / 1 point
Plan
Act
Check
Do
Correct
Correct. The check step is the appropriate place to evaluate solutions. Ishikawa added that this is
where you check the effects of implementation.
7.
Question 7
In which step of the PDCA model would performance predictions be made?
1 / 1 point
Plan
Check
Act
Do
Correct
Correct. In the plan step, you would define the problem, hypothesize solutions, determine targets
and goals, and make performance predictions.
8.
Question 8
In which step of the PDCA model would you document and standardize successful parts of your
solution?
1 / 1 point
Plan
Do
Check
Act
Correct
Correct. You would document and standardize in the act step, after you have implemented the
solution and evaluated the results.
9.
Question 9
In which step would you actually implement your improvements?
1 / 1 point
Act
Check
Do
Plan
Correct
Correct. Implementation happens in the Do step of the model.
10.
Question 10
The PDCA model and the DMAIC model of six sigma are incompatible.
1 / 1 point
True
False
Correct
Correct. They are not in conflict at all. In fact, you can easily map the DMAIC model or other
improvement models against PDCA.
From an ISO perspective, how can we show that our QMS is functioning?
1 / 1 point
Writing a procedure
Training employees
Producing records
Correct
Correct, From an ISO perspective, we must be able to show that our processes are suitable,
adequate and effective. Records help us, in part, satisfy this.
2.
Question 2
What is the difference between a job aid and an SOP?
1 / 1 point
There is no difference
Correct
Correct, job aid is a shortened version of the SOP
3.
Question 3
We use control charts to establish process capability.
1 / 1 point
True
False
Correct
Correct, we do use control charts to establish process capability.
4.
Question 4
A means of maintaining gains on a control plan include all except:
1 / 1 point
Training
Process mapping
Procedures
Internal Auditing
Correct
Correct, internal auditing is a tool used after the process is in place. We need tools that are proactive
and real time.
5.
Question 5
A gage control plan does not include:
1 / 1 point
Calibration
Maintenance
Purchasing
Proper Handing
Correct
Correct, gage control plan includes maintenance, calibration, proper handling.
6.
Question 6
A document is only a paper copy of a quality manual, procedure, work instruction, or record.
1 / 1 point
True
False
Correct
Correct, A document can either be electronic media or a paper hardcopy.
7.
Question 7
Documents are superior to verbal instructions for all the reasons below except:
1 / 1 point
Correct
Correct, this is not true, verbal instructions flow are often not heard, misunderstood, quickly
forgotten, difficult to follow
8.
Question 8
A component of document management is distribution.
1 / 1 point
True
False
Correct
Correct, component of document management is distribution
9.
Question 9
A dynamic control plan consists of all the following except:
1 / 1 point
SOP’s
Control plans
FMEA’s
Correct
Correct, DCP’s are SOP’s, control plans, FMEAs, gage control plans and quality planning sheets
10.
Question 10
Common cause variations can only be solved by management.
1 / 1 point
True
False
Correct
Correct, Common cause variations can only be solved by management
Six Sigma Foundations and Principles Quiz
TOTAL POINTS 5
Question 1
What can be said about the culture of services
Question 2
In summation, six sigma is considered:
1 point
Question 3
Six Sigma Projects emphasize all the following EXCEPT:
The cost savings
Question 4
Who created the initial problem solving framework that would later become DMAIC?
Question 5
Using the six sigma methodology, a company with a short term sigma level of 3.5 sigma would
see a 1.5 sigma shift to 2 sigma long term. What would be the long term failure rate.
233
308770
36510
Possess knowledge of the team’s intended purpose and ensure an alignment exists with
interests and skill set
Question 2
Some experts challenge the value of training and using employees in yellow belt roles. What
would be the best explanation for this perspective:
Yellow Belts tend to have less training and are less involved in six sigma and can only effectively
support the logistical aspects of the project team.
It is too costly
It creates a conflict of interest between the yellow belt and green belt
Question 3
If a black belt uncovers a conflict and wishes to take an assertive stance, which position should
he adopt above all else?
Collaborating
Avoiding
Accommodating
Compromising
Question 4
The function of the coach in a six sigma organization is most likely to be filled by:
Green belt
Process Owner
Champion
Question 5
Process owners can also be referred to as:
Champions or sponsors
No correlation
A negative correlation
A positive correlation
A curvilinear relationship
Question 2
The 80/20 rule is associated with which quality tool
Process Map
Checksheet
Pareto Chart
Question 3
Which of the following tools is a structured form of brainstorming?
Pareto Chart
Checksheet
Histogram
Question 4
In measuring Cost of Poor Quality, as the cost of Appraisal goes up, what would you expect to go
down?
Question 5
When calculating Defects Per Million Opportunities, it is necessary to determine the number of
ways a defect or error could occur.
True
False
Question 6
If you have a process with three steps, and each step produces 99% good quality, what is the
rolled throughput yield?
97%
98%
99.5%
99%
Question 7
Cycle Time is defined as:
The time from the beginning to the end of a process including wait time and other delays.
Team Basics Graded Quiz
TOTAL POINTS 6
Question 1
In Brainstorming, ideas should be evaluated as they are created.
True
False
Question 2
When generating ideas in a Brainstorming session, it is most important to generate a large
number of ideas, and not worry about the quality of those ideas.
True
False
Question 3
Which technique is done silently?
Multivoting
Prioritization Matrix
Affinity Diagram
Question 4
It is usually possible to greatly reduce a brainstorm list, by grouping similar ideas together.
True
False
Question 5
Specific meeting items should be identified in advance, and time allotted for each one.
True
False
Question 6
By using a carefully prepared agenda, meeting minutes can be created almost instantly.
True
False
Lean Foundations and Principles Graded Quiz
TOTAL POINTS 5
Question 1
An activity that does not change the form or function of a product or service is:
Value Added
Required
Non-Value Added
Unnecessary
Question 2
If an activity is non-value added, it must be eliminated.
True
False
Question 3
A three prong electrical plug is an example of:
Poka Yoke
Kan Ban
Standard Work
Muda
Question 4
Value is defined by customers based on their perceptions.
True
False
Question 5
Two Types of Poka Yoke devices are:
Surveys
Focus Groups
Face-to-face interviews
All of these
Question 2
An example of a Strength and Weakness is all except:
Organizational history
Financial resources
Workforce
Capital
Question 3
An advantage of benchmarking is all except:
Question 4
Which is not a component of Stakeholder Analysis?
Question 5
The SWOT analysis is a means toward:
Making profit
Question 6
Our journey for developing CTS's begins with the _______.
Product
Management
VOC
Affinity Diagrams
Question 7
In a QFD, the CTS's are the ____________.
How's
Who's
What's
When's
Question 8
The project team will consist of all except:
Black Belts
Customers
Executive Supporters
Question 9
Customers can exist only externally.
True
False
Question 10
When creating SIPOCS, we may discover __________________ we never knew we had.
Waste
Defects
The purpose or business case of the project is to identify the goal or end result.
Question 2
What may happen if you don’t negotiate resources and secure commitments from team
members?
Omit dates.
Question 4
What is usually the first question your stakeholders will likely ask?
Question 5
What is the purpose of using sticky notes and broad markers when brainstorming?
Question 7
Tree Diagrams are useful for what?
Question 8
The Six Sigma Phase Review is useful for what purpose?
To communicate the status of completion of the project and introduce any obstacles that could
jeopardize the project's success.
When you need to sequence activities with start and end dates.
Question 10
What event would status reporting, forecasting, and lessons learned be a part of?
A brainstorming session
Question 2
What is the method for measuring the reliability of conclusions about a population based on
information obtained from a sample of the population?
Inferential statistics
The mode
Descriptive statistics
Question 3
What is the range?
Question 4
Which is true about sample standard deviation?
Question 5
Which explanation below best answers the question, what is statistics?
The gathering of facts or data that can present significant information about a given subject
Facts or data that is compiled to show the growth trends for a company
Data that is calculated and placed into a table that can be used for a specific purpose.
Question 6
For this dataset:
165.5
143.4
216.1
93.3
Question 7
For this dataset:
37
91
135
120
Question 8
For this dataset:
179
99
156
113
Question 9
For this dataset:
50.29
40.29
30.29
60.29
Question 10
For this dataset:
2898.08
2528.08
2240.08
2634.08
Data Collection Graded Quiz
TOTAL POINTS 10
Question 1
What is a Continuous Variable?
Question 2
What is the relationship between a Population and a Sample?
Question 3
An Observational Study is:
Question 4
Which is not a collection mechanism?
Wild guess
Focus groups
Test marketing
Customer surveys
Question 5
Which is not a technique for insuring accuracy and integrity?
Emotional Bias
Writing characters so that they are not confused with other similar looking characters
Question 6
Determination of the sample size is based on the __________ we seek to maintain.
probability
risk
level of confidence
success rate
Question 7
Random sampling is the desired type of sampling but ____________.
typically the hardest to attain in real world applications
it is very costly
it is sometimes misleading
Question 8
The objective of surveys is:
Question 9
The selection of a focus group should be between _______ people with ________
characteristics.
10 or more, common
10 or more, diverse
Question 10
Focus group results can be obtained ______ and at low cost and tend to have high face
_________.
Quickly, reliability
Quickly, validity
Slowly, reliability
Slowly, validity
Helps align the true value with the observed value within the process.
Question 2
An Observed Variation has two sources: Actual and Measurement
True
False
Question 3
Gage Stability is the drift in the absolute output of a measurement device over time.
False
True
Question 4
What is not a source of variation?
Question 5
Accuracy is how close the agreement is between the mean of one or more measured results to
that of a reference or standard value
True
False
Question 6
If you see a tolerance of plus or minus 5 thousandths of an inch in a drawing, what is this
referring to?
Accuracy
Precision
Question 7
Repeatability and Reproducibility are a part of.....
Operator variability
Gage variability
Actual variability
Question 8
Total variability is the sum of the part-to-part variability (or actual variability) and the
measurement variability.
True
False
True
False
Question 2
Risk Management is a critical part of:
ISO 9000/2015
Question 3
FMEA is typically done by an individual expert working alone.
True
False
Question 4
Why do we need to talk to our customers when doing FMEA?
True
False
Question 2
The use of the Prioritization Matrix can be described as
A qualitative exercise that may feel quantitative.
Question 3
When using a Prioritization Matrix a decision is reached:
Question 4
In a Prioritization Matrix, the criteria are determined:
By the team
By external standards
By company policy
Question 5
A priority Matrix should have:
Four options and four criteria
.
.
Question 2
Suppose the time to answer calls by a customer service center are normally distributed with a
mean of 2 minutes and a standard deviation of 0.5 minutes. Estimate the percentage of calls that
will take longer than 3.5 minutes to answer.
0.14%
50.14%
49.9%
99.9%
Question 3
Suppose the time to answer calls by a customer service center are normally distributed with a
mean of 2 minutes and a standard deviation of 0.5 minutes. Estimate the percentage of calls that
will take between 2.5 and 3.0 minutes to answer.
86.5%
97.7%
84.1%
13.5%
Question 4
Which of the following is NOT a requirement to model with the binomial distribution?
Question 5
Which of the following COULD be modeled using the binomial distribution?
The number of times you flip a fair coin before getting 3 heads <this does not have a set number
of trials
The probability of getting exactly 12 odd numbers when rolling a fair die 20 times.
The probability of exactly 1 defect when taking a sample of size 4 from a lot of size 40 that is
known to be 5% defective. <the population size is less than 50
The number of each type of value meal at McDonalds ordered from the first 100 cars <this does
not have two states
Question 6
Suppose that a sample of size 10 is randomly chosen from a batch of size 100 that is known to
be 8% defective. What is the probability that there is exactly two defective items in your sample?
.009
.102
.378
.148
Question 7
Which of the following is true about variation:
Control charts are used to recognize special cause variation when it occurs so that appropriate
action is taken
Common cause variation are events that can be controlled if made aware of
Unimodal
Special cause
Bivariate
Common cause
Neither the age of the manufacturing equipment and the hours of downtime of the equipment
Both the age of the manufacturing equipment and the hours of downtime of the equipment
Question 2
A scatter plot in which the plotted points are clustered approximately into a straight line from the
top left to the bottom right of the graph is displaying which of the following:
Negative correlation
Positive correlation
Bimodal correlation
No correlation
Question 3
If the pass rate of exams increases with study time, then the correlation coefficient for the study
time versus exams would be:
Equal to 1
Greater than 1
Between 0 and +1
Between 0 and -1
Question 4
Which of the following statements are true about correlation?
The lower the correlation coefficient is, the weaker the correlation is
A negative correlation coefficient means that there is not a strong relationship between the
variables
Question 5
In the equation for basic linear regression, what does the term “b” represent?
The error
The y intercept
The x intercept
Question 6
The least squares method is used for what?
Question 7
You collect sample data to calculate the relationship between age of the manufacturing
equipment at your facility and the hours of downtime of that equipment. Using data ranging from
0.5 years old to 20 years old for the equipment, you obtain the regression equation for annual
hours of downtime of y=10+0.5x with a high correlation coefficient. How many hours of downtime
would you predict for equipment that is 8 years old? (Round to the nearest 10th of a year)
8.0
14.0
4.0
Question 8
Where is regression analysis most often used by six sigma professionals?
Question 2
A null hypothesis states that a process has not changed over time. If a type II error is made,
One has failed to reject the null hypothesis when it was false
One has rejected the null hypothesis when it was false
One has failed to reject the null hypothesis when it was true
Question 3
Suppose you want to test the claim that the mean length of process time has decreased from
12.3 minutes. Your sample data leads you to fail to reject H0. The actual mean length is 12.0
minutes. What type of error, if any, have you made?
Question 4
If your hypothesis test is:
Left-tailed
Binomial
Two-tailed
Right-tailed
Question 5
While performing a hypothesis test, you calculate a p-value of 0.05. If the desired level of
significance is 0.01 then the conclusion is:
Over-optimization
Productivity optimization
Alternate optimization
Sub-optimization
Question 2
Employee empowerment is a key element of Kaizen.
True
False
Question 3
Improvements through both Kaizen and Kaizen Blitz must be carefully managed.
True
False
Question 4
Deming’s version of the model is Plan, Do, Study, Act. He changed check to study because he
wanted it to be a plan for management, and he wanted them to use this step to compare results
with predictions.
True
False
Question 5
The PDCA model is complex, and you should have an expert to lead the team.
True
False
Question 6
Which of these statements best describes net present value?
The sum of present values of incoming and outgoing cash flows over a period of time.
Question 7
Payback Period is usually
12 months.
18 months.
24 months.
It depends.
Question 8
Internal rate of return usually reflects the anticipated inflation rate.
True
False
Question 9
When an organization first starts to address quality issues, external failures are likely to go down,
while both appraisal costs and internal failures will go up.
True
False
Question 10
Generally the cost of quality will be lowest with a strong focus on:
Internal failures
External Failures
Prevention
Appraisal
Control Tools and Documentation Graded Quiz
TOTAL POINTS 10
Question 1
An example of special cause variation would not include:
No preventive maintenance
No training
No documentation
Question 2
Control charts for averages behave like what distribution?
Poisson
Normal
Weibull
Euler Phi
Question 3
In order to have a rational sample, we seek to have all of the following except:
Question 4
If we want to detect a large shift, we need a smaller sample size
True
False
Question 5
Control is the process employed to meet customer expectations
True
False
Question 6
A pitfall of document control would not include:
High Distribution
Question 7
One of focus areas in the P-D-C-A process is:
How do we plan it
How do we control it
What are our goals
How do we do it
Question 8
Control charting is only for monitoring
True
False
Question 9
Document management includes all processes except:
Creation
Deletion
Distribution
Question 10
After you assign causes and eliminate problems, you need to remove the _____________.
centerline