Professional Documents
Culture Documents
SCOPE of WORK New For Arsad Camp Replacement AC
SCOPE of WORK New For Arsad Camp Replacement AC
SCOPE of WORK New For Arsad Camp Replacement AC
MESS BUILDING
REVISION HISTROY
Eng.
REV.0 03/2021
Al-Harrasi
MESS BUILDING
P a g e 1 | 27
Mechanical Scope of work MOD/0000/000
Contents
SECTION 1.0.................................................................................................. 4
GENERAL CONDITIONS/ REQUIREMENTS ........................................... 4
SECTION 2.0.................................................................................................. 7
VENTILATION & AIR CONDITIONING INSTALLATION
SPECIFICATIONS ......................................................................................... 7
2.1 Design Conditions............................................................................................... 7
2.2 AHU+CU and Package Units Specifications.................................................... 7
2.2.1 Compressor: ................................................................................................ 7
2.2.2 Condensers: ................................................................................................... 8
2.2.3 Evaporator: .................................................................................................... 9
2.2.4 Condensers Fans & Motors:.......................................................................... 9
2.2.5 Cabinet: ....................................................................................................... 10
2.2.6 Piping Connections: .................................................................................... 11
2.2.7 Refrigerant Pipe Work: ............................................................................... 11
2.2.8 Condensate: ................................................................................................. 11
2.2.9 Filters: ......................................................................................................... 11
2.2.10 Ventilation: ................................................................................................. 12
2.3 Ductwork: ......................................................................................................... 12
2.3.1 Anchors ...................................................................................................... 12
2.3.2 Flexible Connections ................................................................................. 13
2.3.3 Duct ends.................................................................................................... 13
2.3.4 Duct Supports ............................................................................................ 13
2.3.5 Duct Material ............................................................................................ 13
2.3.6 Thermal Duct Insulation .......................................................................... 13
2.3.7 Splitters and Dampers inside Ducts ........................................................ 14
2.3.8 Fire Dampers ............................................................................................. 15
2.3.9 Volume Control Dampers ........................................................................ 15
2.3.10 Grilles, Registers & Diffusers .................................................................. 16
2.3.11 Sound Attenuators .................................................................................... 18
2.3.12 Anti-Vibration Mountings ....................................................................... 19
MESS BUILDING
P a g e 2 | 27
Mechanical Scope of work MOD/0000/000
MESS BUILDING
P a g e 3 | 27
Mechanical Scope of work MOD/0000/000
SECTION 1.0
1.0 General:
1.1 The Contractor shall design, supply, assemble, install, connect; test
and commission the complete gas and air conditioning installation as
per MODES Design Drawings and as per the following Standards:
a. MOD Standard Specification.
b. OES Specification for electrical installation.
1.2 The Contractor shall submit detailed Shop Drawings for MODES
approval.
1.3 All equipment and materials shall be suitable for Maximum dry-bulb
ambient temperature and humidity prevailing at Oman.
1.4 Final position of all equipment shall be agreed with the site engineer
prior to installation and adjustments in locations as shown on
drawings shall be carried without additional cost.
1.5 For the HVAC system (AHU-CU and PACKAGE), the contractor
shall submit at least three alternatives of products that are included
on the approval list. However, the approval will be given "but not
limited to" base on the evaluation of the equipments efficiency. The
contractor shall submit this evaluation to MODES engineer along
with the material approval.
1.6 The contractor shall submit Compliance Statement for all mechanical
systems clearly indicate any deviation from the specifications for
approval.
1.7 The contractor shall replace all external (with sound attenuator) AC
ducts with Dampers, Insulation & Aluminum Cladding.
MESS BUILDING
P a g e 4 | 27
Mechanical Scope of work MOD/0000/000
1.8 The contractor should install the thermostat device for all A/C units
(AHUs & Package) inside the building and be secured.
1.9 The contractor shall inspect and clean all existing internal ducts
against fungus, dust and particular contaminants and shall conduct
air balancing for proper air circulation, cooling and distribution.
1.10 The contractor shall clean all existing grills and diffusers,
replacement of any damaged diffusers.
1.11 The contractor shall uninstall and dismantle the existing HVAC
equipment’s (AHU+CU, Package, Extract & Supply Fans and power
& control cable). Contractor shall load the removed equipments and
machines at presence of MODES engineer from the unit and
transported them to MODES store. All the works and transportation
shall be liaised and prearranged with the MODES Project Engineer
for unloading at the right location.
1.12 The contractor shall supply, install, test and commission new
AHU+CU (1No.), Package units (3 Nos.) as per existing and
required capacity including all related peripherals and power & control
cable which is to be replaced as per the scope of work.
1.13 The contractor shall supply, install, test and commission new
Kitchen extract fan (1No.), supply fan (1 No.) as per existing and
required capacity including all related peripherals and power & control
cable which is to be replaced as per the scope of work.
1.14 The contractor shall clean the existing kitchen hood canopy, repair
of any damaged parts.
MESS BUILDING
P a g e 5 | 27
Mechanical Scope of work MOD/0000/000
1.17 The contractor shall use the existing foundations and carry out the
necessary civil work modifications required.
1.18 The contractor shall consider all related civil work like replacement
of the damaged false ceiling and any modifications in wall openings,
which will be shown to the contactor during pre-tender site visit.
1.19 The contractor shall replace the existing false ceiling by supply
and install new square tiles ceiling in the kitchen area.
1.20 The contractor shall submit 3 sets of final As built drawings, Manual
and Technical details in hard copies & soft copy.
1.21 Work place to be kept clean and tidy after completion of work.
1.22 The contractor shall attend pre-tender site visit in order to know any
modifications required.
1.24 The contractor shall supply, install, test and commission TPN/SPN
isolators for AC units and extract fans, rating as per AC supplier
recommendation.
1.25 The contractor shall replace the existing cable tray on the roof and
supply, install, test and commission new heavy-duty cable tray with
cover.
1.26 The contractor shall supply, lay, test and commission new LV cables
from isolators to AC panels for all units.
1.27 The contractor shall replace the existing kitchen lights fitting and
design, supply, install, test and commission new LED lights, IP 54
opal diffuser to give 500 Lux level.
1.28 The contractor shall replace existing cable for kitchen supply fan and
extract fan by new, size as per manufacturer.
MESS BUILDING
P a g e 6 | 27
Mechanical Scope of work MOD/0000/000
1.29 The contract period shall be 180 days. The work at all locations shall
be commenced and executed at same period.
SECTION 2.0
MESS BUILDING
P a g e 7 | 27
Mechanical Scope of work MOD/0000/000
MESS BUILDING
P a g e 8 | 27
Mechanical Scope of work MOD/0000/000
2.2.3 Evaporator:
2.2.3.1 Evaporator coils shall be manufactured from
seamless copper tubes mechanically bonded to
aluminum waven fins to ensure optimum heat
transfer.
MESS BUILDING
P a g e 9 | 27
Mechanical Scope of work MOD/0000/000
MESS BUILDING
P a g e 10 | 27
Mechanical Scope of work MOD/0000/000
MESS BUILDING
P a g e 11 | 27
Mechanical Scope of work MOD/0000/000
MESS BUILDING
P a g e 12 | 27
Mechanical Scope of work MOD/0000/000
MESS BUILDING
P a g e 13 | 27
Mechanical Scope of work MOD/0000/000
MESS BUILDING
P a g e 14 | 27
Mechanical Scope of work MOD/0000/000
MESS BUILDING
P a g e 15 | 27
Mechanical Scope of work MOD/0000/000
MESS BUILDING
P a g e 16 | 27
Mechanical Scope of work MOD/0000/000
MESS BUILDING
P a g e 17 | 27
Mechanical Scope of work MOD/0000/000
MESS BUILDING
P a g e 18 | 27
Mechanical Scope of work MOD/0000/000
2.3.13 Painting
2.3.13.1 All items to be painted. Factory finished items
which become damaged shall be restored to
original condition. All work, which has to be
field painted, shall be free of scale, oil or dirt of
any kind.
MESS BUILDING
P a g e 19 | 27
Mechanical Scope of work MOD/0000/000
SECTION 3.0
DOCUMENTATION
MESS BUILDING
P a g e 20 | 27
Mechanical Scope of work MOD/0000/000
3.1.5 Testing
3.1.5.1 The Contractor shall provide MODES with type
written schedules readings taken during the
balancing and testing operation indicating the
design valves and the final balanced readings.
Details shall be provided for all equipment i.e.
Size, type, speed, static pressure in KPa or Pa, air
quantity in m3/h, and motor load amperes.
3.1.6 Training
3.1.6.1 The contractor shall arrange to train the designated
employer’s personal regarding the operation and
routine maintenance of all specified systems in this
document.
3.1.6.2 The training shall be performed at side by qualified
and factory trained engineer employed by the
supplier.
MESS BUILDING
P a g e 21 | 27
Mechanical Scope of work MOD/0000/000
MESS BUILDING
P a g e 22 | 27
Mechanical Scope of work MOD/0000/000
MESS BUILDING
P a g e 23 | 27
Mechanical Scope of work MOD/0000/000
MESS BUILDING
P a g e 24 | 27
Mechanical Scope of work MOD/0000/000
MESS BUILDING
P a g e 25 | 27
Mechanical Scope of work MOD/0000/000
MESS BUILDING
P a g e 26 | 27
Mechanical Scope of work MOD/0000/000
The following items shall be checked and/or tested and recorded on the
site-test Certificate:
3.3 Spares:
The Contractor shall provide for within his tender, the supply of the
manufactures recommended spare parts for an operational period of 2
years. The cost of these spares is to be independently identified within the
tender document Tie down points.
MESS BUILDING
P a g e 27 | 27