Professional Documents
Culture Documents
ESMF With Annex Final - Rev May 20 CLEAN
ESMF With Annex Final - Rev May 20 CLEAN
Management Framework
May 2020
TABLE OF CONTENTS
ACRONYMS ..................................................................................................................... iv
EXECUTIVE SUMMARY .................................................................................................. vi
1. INTRODUCTION ........................................................................................................... 1
1.1. Project background ............................................................................................................................ 1
1.2. Rationale and Objective of ESMF .................................................................................................... 2
2. ENVIRONMENTAL AND SOCIALREGULATIONS AND POLICY FRAMEWORK ........... 3
2.1. National and International Laws/Conventions .............................................................................. 3
2.2. International Conventions............................................................................................................... 4
2.3. World Bank Safeguard Policies ....................................................................................................... 4
2.4. Comparison of GoN and World Bank Policies ................................................................................5
3. KEY ENVIRONMENTAL AND SOCIAL CONDITIONS IN THE CLUSTER
MUNICIPALITIES ............................................................................................................ 9
4. ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) ................. 11
4.1. Environment and Social Risk Management Procedure ................................................................ 11
4.1.1. Environmental and Social Screening .................................................................................... 11
4.1.2. Scoping ................................................................................................................................... 12
4.1.3. Project categorization ............................................................................................................ 13
4.1.4. Establishment of Baseline Condition ................................................................................... 13
4.1.5. Analysis of Alternative ........................................................................................................... 15
4.1.6. Impact Assessment ................................................................................................................ 15
4.1.7. Mitigation Measures for Identified Impacts and Guide to ESMP ...................................... 19
4.1.8. Stakeholder Consultation ..................................................................................................... 20
4.1.9. Preparation of ESIA/ESMP Report ..................................................................................... 20
4.1.10. Environmental Mitigation and Enhancement Management Plan .................................... 21
4.1.11. Approval and Implementation of Site-specific ESMP ....................................................... 24
4.1.12. Environmental and Social Monitoring of Management Plans ......................................... 24
4.1.13. Applicability of ESMF on Associated Projects .................................................................. 24
4.1.14. List of Ineligible Sub-Projects ............................................................................................ 24
4.1.15. LIPW subprojects ................................................................................................................ 24
4.1.16. Legal Contract for E&S Compliance .................................................................................. 25
4.1.17. Subproject Monitoring ........................................................................................................ 25
4.2. Specific labor and OH&S-related considerations in the context of COVID-19 .......................... 25
4.3. Considerations where CERC is activated .......................................................................................27
5. RESETTLEMENT POLICY FRAMEWORK (RPF) ........................................................ 28
5.1. Principles of RPF ............................................................................................................................ 28
5.2. Land & Asset Acquisition ............................................................................................................... 28
5.2.1. Involuntary Land Acquisition .............................................................................................. 29
5.2.2. Acquisition of Land through Negotiations ......................................................................... 30
5.2.3. Voluntary Land Donation ..................................................................................................... 31
5.2.4. Loss of other Assets .............................................................................................................. 32
i
5.3. Preparation of RAP ........................................................................................................................ 33
5.4. Entitlement Policy Matrix ............................................................................................................. 33
5.5. Monitoring and Reporting of RAP ................................................................................................ 40
5.6. Stakeholder Consultation and Grievance Redress ....................................................................... 40
6. VULNERABLE COMMUNITY DEVELOPMENT FRAMEWORK (VCDF) ...................... 41
6.1. Classification of Vulnerable Groups in Nepal ................................................................................ 41
6.2. Baseline of Vulnerable Groups in Nepal ....................................................................................... 42
6.3. Preparation of VCDP for the sub-projects .................................................................................... 43
6.4. Potential Impacts and Identification of Mitigation measures ..................................................... 44
6.5. Consultation and Information Disclosure .................................................................................... 46
6.6. Institutional Responsibilities ........................................................................................................ 47
6.7. Stakeholder Consultation and Grievance Redress ....................................................................... 47
7. SEA/SH RISK MITIGATION ACTION PLAN ................................................................ 48
7.1. Need and Purpose ........................................................................................................................... 48
7.2. Legal and policy environment for women’s safety ....................................................................... 48
7.3. Recommended Actions to Adddress SEA/SH Risks .................................................................... 49
8. STAKEHOLDER ENGAGEMENT AND CONSULTATION FRAMEWORK .................... 52
8.1. Existing Stakeholder Engagement Process ................................................................................... 52
8.2. Stakeholder Mapping..................................................................................................................... 53
8.3. Mechanism for Consultation ......................................................................................................... 54
8.3.1. Subproject Identification Stage ........................................................................................... 54
8.3.2. Planning/Design Stage .........................................................................................................55
8.3.3. Implementation Stage ......................................................................................................... 56
8.3.4. Post-construction Stage ....................................................................................................... 56
8.4. Information Disclosure.................................................................................................................. 56
8.5. Adapting stakeholder consultions to COVID-19 .......................................................................... 56
9. GRIEVANCE REDRESS MECHANISM ........................................................................ 59
9.1. Existing Grievance Redress Process .............................................................................................. 59
9.2. Establishing Grievance Redress Mechanism................................................................................ 59
9.3. Channels and procedures for receiving and addressing grievances............................................ 59
9.4. Functions of GRCs ......................................................................................................................... 60
9.5. Other Mechanism for Grievance Redress ...................................................................................... 61
9.6. GRM considerations for the COVID-19 context ............................................................................ 61
10. INSTITUTIONAL ARRANGEMENT FOR ESMP IMPLEMENTATION ........................ 62
10.1. Institutional Assessment for E&S Sections/Departments ......................................................... 62
10.1.1. Existing Institutional Capacity ........................................................................................... 62
10.1.2. Capacity Development ........................................................................................................ 62
10.2. Proposed Institutional Arrangement .......................................................................................... 63
ESMP Implementation Structure and Stakeholers Responsibility .................................................. 120
ii
List of Appendix
Appendix A: Land use map of 17 Municipalities .................................................................................................... 65
Appendix B: Consultation with municipalities ........................................................................................................ 73
Appendix C: Templates for Environmental & Social Screening Checklist / ......................................................... 111
Appendix D: Initial scoping for subprojects........................................................................................................ 113
Appendix E: Environmental & Social Mitigation Measures ................................................................................. 117
Appendix F: Contents of the Resettlement Action Plan ........................................................................................ 129
Appendix G: Assessment of Institutional Capacity ............................................................................................... 131
Appendix H: Summary Environmental and Social Conditions in the Cluster Municipalities ............................... 142
Appendix I: Summary Information on the Type of Baseline Indicators ................................................................ 150
Appendix J: List of Ineligible Sub-Projects ........................................................................................................... 159
Appendix K: COVID-19 considerations in construction/civil works projects ........................................................... 0
List of Figures
List of Tables
Table 2-1List of National Policies, Rules, Laws, Regulations, Relevant to the Project .......................................... 3
Table 2-2 Listof International Conventions, Relevant to the Project ..................................................................... 4
Table3-1: Key Environmental and Social Issues in the Eastern and Western Cluster Municipalities ...................... 9
Table 4-1: Description of Social Baseline Information required for the Project................................................... 13
Table 4-2: Anticipated Environmental and Social Impacts due to Development of Sub-projects ......................... 16
Table 4-3: Anticipated Social issues pertaining to the project ............................................................................. 18
Table 4-4.Template Environnemental Mitigation & Enchancement Management Plan ....................................... 21
Table 5-1: Entitlement Matrix applicable for the Project .................................................................................... 36
Table 6-1: Classification of Indigenous People on development ......................................................................... 42
Table 6-2: Population of Indigenous People in project specific districts ............................................................. 42
Table 6-3: Potential Impacts and Mitigation measures ...................................................................................... 44
Table 7-1.Recommended actions to address SEA/SH Risks ...................................................................... 49
Table 8-1: Stakeholder Mapping and Consultation ............................................................................................. 53
Table 10-1. Capacity Development Training Requirement ................................................................................. 63
iii
ACRONYMS
ADB Asian Development Bank
ARAP Abbreviated Resettlement Action Plan
CERC Contingency Emergency Response Component
CDO Chief District Officer
DCC District Coordination Committee
DFO District Forest Officer
DHM Department of Hydrology and Meteorology
DoE Department of Environment
DoR Department of Roads
DSC Design and Supervision Consultant
DUDBC Department of Urban Development & Building Construction
EA Environmental Assessment
EIA Environmental Impact Assessment
EMP Environmental Management Plan
EPR Environmental Protection Rules
ESMF Environment & Social Management Framework
ESMP Environment and Social Management Plan
FGD Focus Group Discussion
FUG Forest User Groups
GDP Gross Domestic Product
GESI Gender equality and social inclusion
GIS Geographic Information System
GoN Government of Nepal
GRM Grievance Redress Mechanism
IDA International Development Association
IEE Initial Environmental Examination
IP Indigenous Peoples
IUCN International Union for Conservation of Nature
JICA Japan International Cooperation Agency
LACP Land Acquisition and Compensation Plan
LIPW Labor-Intensive Public Works
LRUC Local Road Users Committee
MoFE Ministry of Forests and Environment
MoUD Ministry of Urban Development
NEFIN Nepal Federation of Indigenous Nationalities
NGO Non-Governmental Organizations
NUGIP Nepal Urban Governance and Infrastructure Project
NTFP Non-timber forest products
OH&S Occupational Health and Safety
OP Operational Policy
PAF Project Affected Family
PAH Project Affected Household
PAP Project Affected People
PCO Project Coordination Office
PIA Project Influence Area
PIU Project Implementation Unit
PIM Project Implementation Manual
iv
PPE Personal Protective Equipment
RAP Resettlement Action Plan
RoW Right of Way
RPF Resettlement Policy Framework
SA Social Assessment
SEA/SH Sexual Exploitation and Abuse/Sexual Harassment
SECF Stakeholder Engagement & Consultation Framework
SHG Self Help Group
SIA Social Impact Assessment
SMO Social Mobilization Officer
SMP Social Management Plan
TOR Terms of Reference
UDGs Urban Development Grants
UDST Urban Development Support Teams
ULLs Urban Local Levels
USD United States Dollar
VCDP Vulnerable Community Development Plan
VCDF Vulnerable Community Development Framework
VDC Village Development Committee
VGs Vulnerable Groups
WB World Bank
v
EXECUTIVE SUMMARY
Nepal has recently transitioned from a unitary to federal government system, comprised of three tiers of government
with seven provinces and 753 local governments for which new legislation, institutions, and administrative
procedures are being formalized as constitutionally prescribed. To enable the federal implementation process and
to support Urban Local Levels (ULLs) in the efficient provision of assigned service delivery responsibilities in the
context of rapid urbanization, the proposed Nepal Urban Governance and Infrastructure Project (NUGIP) to be
implemented by the Ministry of Urban Development (MoUD) with support from the World Bank aims to address
two main challenges under the new federal context: (i) limited institutional systems and capacities of ULLs; and (ii)
critical gaps in core municipal services and infrastructure.
The development objective of NUGIP is to strengthen the institutional and fiscal capacities of participating ULLs
for strategic municipal infrastructure and service delivery. The proposed project comprises five components:
Component 1: Urban Development Grants (UDGs) for strategic municipal infrastructure and service delivery
(International Development Association (IDA) allocation of US$ 112 million). This component will provide UDG
to participating ULLs for financing strategic municipal infrastructure sub-projects focusing on, amongst others,
rehabilitation and improvements in municipal roads, drainage, drinking water supply and onsite sanitation (See
Annex 2 for menu of eligible investments), as well as associated design and implementation support.
Component 2 Institutional strengthening of participating ULLs (IDA financing: US$10 million). This component
will focus on strengthening institutional systems and capacities of participating ULLs for improved urban
management and service delivery.
Component 3: Support to ULLs for COVID-19 Recovery (Total financing: US$20 million). This component
provides support and relief to vulnerable groups in the target municipalities to help mitigate the short and medium
negative impact of the COVID 19 crisis through rapid labor-intensive public works (LIPW).
Component 4: Contingency Emergency Response (Total financing: US$0 million). The proposed project includes
a Contingent Emergency Response (CER) component to respond rapidly at the Government’s request in the event
of an eligible disaster, including climate-related events and pandemics.
Component 5: Project management and coordination (IDA financing: US$8 million). This component will provide
support to the MoUD for managing, coordinating and monitoring the implementation of the proposed Project, and
also for enhancing its federal policy and regulatory role for urban development.
NUGIP will support ULLs located in two strategic urban clusters: Eastern-Terai region (Provinces 1 and 2) and
Western region (Provinces 4 and 5). The eastern region includes 9 municipalities of Itahari-Mechinagar corridor
and the central region includes 8 municipalities of Pokhara-Lekhnath economic corridors. 17 ULLs were selected
as recipients of resources for municipal infrastructure and service delivery investments. Four additional ULLs in
the Central-Hill cluster were included for the capacity building program under Component 2. In addition to the 17
ULLs, 12 ULLs will supported for COVID-19 response and recovery activities under Component 3.
The present Environmental and Social Management Framework (ESMF) has been prepared to assist in the
screening, identification, and assessment of environmental and social risks applicable to the environmental and
social requirements of the Government of Nepal (GoN) and the World Bank during the sub-project design,
implementation and operation phases. It includes a Resettlement Policy Framework (RPF), a Vulnerable
Community Development Framework (VCDF), Sexual Abuse and Exploitation/Sexual Harassment (SEA/SH) Risk
Mitigation Action Plan, and a Stakeholder Engagement and Consultation Framework (SECF). The framework
provides guidance on the procedures to be followed for mitigation of impacts, along with roles and responsibilities
of the implementing agencies. The ESMF presents detailed guidelines and formats for carrying out these activities.
Under NUGIP, the municipalities are responsible for identification of sub-projects, with the engagement of citizens,
preparation of sub-project description, “screening” and “analysis of alternatives”. Based on these and other relevant
documents, the Project Coordination Office (PCO) along with the municipality will assess the need for further
environmental and social assessment (e.g., IEE/ ESIA). The schedules as per the Environment Protection Rules will
be the guiding document for categorizing the project and assessing the requirements for IEE/ EIA. The ESMF,
vi
which integrates Nepal’s laws and regulations on social and environmental safeguards, and the Bank’s policies as
well, shall be used to determine location specific issues for screening as well as defining scope for the sub-project.
The major activities to be carried out for IEE and ESIA include: (i) Identification and selection of proposed sub-
projects and the sites based on results of screening and scoping; (ii) Establishment of baseline environmental &
social conditions; (iii) Assessment, prediction and evaluation of environment and social impacts; (iv) Analysis of
alternatives; (v) Identification of mitigation measures and preparation of ESMP;(vi) Public consultations and
information dissemination;(vii) Monitoring and preparation of Environmental and Social Monitoring reports; and
(viii) Institutional arrangements and capacity building
The resettlement activities envisaged under the project aims to assist, resettle and rehabilitate the affected persons
on account of the variousproject interventions in a manner that would improve or at the minimum, retain their
previous standard of living, earning capacity and production levels. Specifically, the Resettlement Policy
Framework (RPF) has been developed to guide detailed resettlement planning to address land acquisition and
resettlement impacts. This framework establishes the procedures for land acquisition and resettlement, the
compensation principles, organizational arrangements to be applied to meet the needs of the people who may be
affected by the project activities in terms of loss of land, shelter, assets or livelihoods, and/or loss of access to
economic resources. The RPF has been prepared in accordance with the national regulations as well as the
operational policies of the World Bank, especially OP/BP 4.12: Involuntary Resettlement.
The objective of the Vulnerable Community Development Framework (VCDF) is to guide the preparation of the
Vulnerable Community Development Plan (VCDP) for the sub-projects where there are vulnerable communities,
particularly indigenous people, present in and have collective attachment to the project area. The impact on
vulnerable communities and the need of a VCDP will be identified through a social screening process. If a VCDP
is deemed to be necessary, the plan will be prepared based on the findings of the Social Assessment and will also
involvefree, prior and informed consultation. Additionally, a Sexual Exploitation and Abuse/Sexual Harassment
(SEA/SH) Risk Mitigation Action Plan which provides guidance for addressing SEA/SH risks in sub-projects is
also provided in the ESMF.
A good communication strategy among the institution and community needs to be established to ensure that the
project is implemented in a sustainable manner. There are two key objectives of Stakeholder Engagement and
Consultation Framework (SECF). First, it is to keep all stakeholders informed of the project activities, the potential
beneficial and adverse impacts. Second, it is to ensure that stakeholders actively participate in all levels of the project
cycle, i.e., they are able to share and provide inputs in the preparation and implementation of project activities,
including safeguards management; engaged in implementation and monitoring activities, where relevant; and are
well-trained and equipped to take over the responsibilities of operation and management once the project phases
out. Consultations on social and environmental issues carried out during implementation of subprojects will be done
in an inclusive manner and with active participation from women representatives, communities and vulnerable
social groups. To help support the capacity building of local governments, existing local mechanisms will be used
for engaging with stakeholders. The SECF also outlines the disclosure requirements for the project. The ESMF was
publicly disclosed on the websites of the GoN and the World Bank on October 18 and 17, 2019 respectively.
Likewise, all the other instruments prepared under the project will be similarly disclosed.
The ESMF also outlines the Grievance Redress Mechanism (GRM) set up for the project. The GRM will be a three-
tiered but an integrated mechanism for addressing complaints and feedback. The structure as well as procedures for
the GRM will draw on the existing mechanisms and processes established at the local level to help strengthen the
capacity of these local systems.
MoUD has set up a project coordination office (PCO) under the Department of Urban Development and Building
Construction (DUDBC) for NUGIP in Kathmandu, and a Project Implementation Unit (PIU) will be established in
each municipality for project implementation in the field. To ensure that the investment sub-projects are efficiently
implemented, and completed in accordance with environmental and social safeguards requirements, technical
assistance will be delivered through a Design and Supervision Consultancy (DSC). The role of the PIU/DSC
includes implementation of the ESMPs, RAPs and VCDPs.
vii
This ESMF has been revised to additional environmental and social risks and impacts arising as a result of the
COVID-19 pandemic, and as well as to addres potential risks and impacts arising under the added component for
LIPW, added to provide support and relief to vulnerable groups in target municipalities to help mitigate the short
and medium term impacts of COVID-19. Guidance has been provided to address occupational health and safety
risks and impacts to workers, and considerations for adapting citizen engagement and stakeholder engagement
requirements to the COVID-19 context have also been included. This ESMF does not address risks and impacts in
relation to the CER component (CERC), given that the type of likely emergency and indicative list of activities that
will be required under CERC cannot yet be determined. Environmental and social screening of activities under
Component 4 (CERC) will follow the procedures outlined in the ESMF and in the CER Implementation Manual. In
case new activities are identified for the CERC when triggered that go beyond the scope of the ESMF, then the
ESMF will be updated as needed and redisclosed.
viii
1. INTRODUCTION
1.1. Project background
The Project Development Objective of the Nepal Urban Governance and Infrastructure Project (NUGIP) is to
strengthen the institutional and fiscal capacities of participating ULLs for strategic municipal infrastructure and
service delivery.
Component 1: Urban Development Grants (UDGs) for strategic municipal infrastructure and service
delivery (International Development Association (IDA) allocation of US$ 112 million). This component will
provide UDG to participating ULLs for financing strategic municipal infrastructure sub-projects focusing on,
amongst others, rehabilitation and improvements in municipal roads, drainage, drinking water supply and onsite
sanitation (See Annex 2 for menu of eligible investments), as well as associated design and implementation
support. The component will support the operationalization of Nepal’s first urban sector conditional grant (UDG)
system, that focuses exclusively on strategic municipal infrastructure and service delivery improvement at the local
level. The UDG allocations have been determined based on an objective and transparent allocation formula1, and
will allow ULLs to develop their multi-year municipal investment program in year 1. ULLs will identify, design
and implement identified subprojects in line with the guidelines and procedures outlined in the Project
Implementation Manual (PIM). The component, through the design and implementation support will help the
participating ULLs in developing robust contract structuring and implementation modalities to attract private sector
participation for construction as well as operations and maintenance of the municipal infrastructure, to the extent
feasible.
Component 2 Institutional strengthening of participating ULLs (IDA financing: US$10 million). This
component will focus on strengthening institutional systems and capacities of participating ULLs for improved
urban management and service delivery of, amongst others: (a) integrated urban development planning; (b) OSR
mobilization; (c) municipal FM, procurement, and contract management; (d) citizen engagement and gender
inclusion; (e) urban infrastructure asset management system and (f) institutional performance monitoring and
reporting system for ULLs (see Annex 2). In addition to these six core urban management areas, the technical
assistance will also include dedicated support to the municipalities in the context of the COVID 19 pandemic,
including in: (i) Support to Business Continuity Plans to allow ULLs to maintain and operate key municipal
functions during the short and medium term as their staff and finances are affected by the crisis, (ii) Mapping of
particular vulnerable/high risk/highly impacted zones within the cities, (including informal settlements) and
provide targeted interventions, (iii) Communication and awareness raising campaigns on actions to limit the risks
for exposure and spread of virus, including handwashing, and (iv) Support to design targeted interventions to help
reduce the risk of spread of the virus. The specific TA can be tailored to meet the needs of the ULL.
Component 3: Support to ULLs for COVID-19 Recovery (Total financing: US$20 million). This component
provides support and relief to vulnerable groups in the target municipalities to help mitigate the short and medium
negative impact of the COVID 19 crisis through rapid labor-intensive public works (LIPW). The component will
finance (i) payment of wages for unskilled labor to undertake temporary employment in participating ULLs, (ii)
expenses for tools and materials for the implementation of such projects, and (iii) expenses related to management
of the LIPW (consultations, administration, and supervision).Target beneficiaries for the LIPW will be individuals
from poor and vulnerable households. Participants will be provided with appropriate training on construction
methods, where required, and specific occupational health and safety measures, including the use of protective
personal equipment. The selection process for beneficiaries will specifically cater to supporting vulnerable groups
including the elderly, physically challenged, minorities and disadvantaged groups. The LIPW subprojects will
require a minimum percentage representation of female workers; The criteria and other guidance for targeting
beneficiaries will be detailed in the PIM.
Component 4: Contingency Emergency Response (Total financing: US$0 million). The proposed project
includes a Contingent Emergency Response (CER) component to respond rapidly at the Government’s request in
1The agreed sectoral allocation formula is: 70 percent weightage for population; 10 percent weightage for equal share; 10 percent
weightage for area of the ULL; and 10 percent weightage for infrastructure gap.
1
the event of an eligible disaster, including climate-related events and pandemics. This Component will finance the
implementation of emergency infrastructure reconstruction, rehabilitation and associated studies (Emergency
Response Activities). Resources will be allocated to this component as needed by the project during
implementation. Disbursements will be made against a preestablished list of critical goods or the procurement of
goods, works, and consultant services required to support the immediate response and recovery needs of the GoN.
A separate Implementation Manual for this component will be prepared by the GoN and will provide detailed
guidelines and instructions on how to trigger the CER component and use funds.
Component 5: Project management and coordination (IDA financing: US$8 million). This component will
provide support to the MoUD for managing, coordinating and monitoring the implementation of the proposed
Project, and also for enhancing its federal policy and regulatory role for urban development.
In order to ensure the long-term sustainability of the projects supported under NUGIP, the Environmental and
Social Management Framework (ESMF) has been prepared. It is the guiding document to integrate the
environmental and social safeguards at subproject level through appropriate measures during the planning, design,
construction and operation phases of various activities of NUGIP. The framework will help identify the adverse
environment and social impacts and provide specific guidance on the policies and procedures to be followed for
Environmental and Social Impact Assessment (ESIA) and preparation of site-specific safeguards management plan
(e.g., ESMP, RAPs, etc), inclusive of the roles and responsibilities of the implementing agencies.
At the time of revising the ESMF, detailed design of the LIPW had not be determined. Once detailed design has
been confirmed, this ESMF will be updated in order to provide guidance to ULLs in addressing subproject
environmental and social risks and impacts.
The objective of ESMF is to frame guidelines and procedures to address environmental and social impacts
associated with the implementation of this project. The specific objectives are as follows:
• Ensure that the environment and social management plans are aligned with the requirements of the
country system as well as with the World Bank safeguard requirements
• Outline the process identify and assess the environmental and social risks/ impacts/ issues relevant to the
proposed project
• To establish clear procedures and methodologies for the environmental and social screening, review,
approval and implementation of sub-projects to be financed under the Project
• To ensure that mitigation measures are designed to effectively mitigate the potential adverse social and
environmental impacts
• To specify appropriate roles and responsibilities at the national and municipal levels, taking into
consideration the law on federalization, and outline the necessary procedures for managing and
monitoring environmental and social concerns related to sub-projects, and report on the same
• Strengthen the institutional capacity of the ULGs on safeguards management and compliance.
2
2. ENVIRONMENTAL AND SOCIALREGULATIONS AND POLICY FRAMEWORK
2.1. National and International Laws/Conventions
Table 2-1 and 2-2 list the national laws and international conventions pertinent to the project components and sectors
covered under NUGIP which are required during the process of carrying out ESIA and preparation of ESMP, RAP, VCDP,
and other relevant instruments under the project.
Table 2-1 List of National Policies, Rules, Laws, Regulations, Relevant to the Project
1. Constitution of Nepal
2. Ancient Monument Protection Act 1956
3. Aquatic Animal Protection Act 1961
4. Environment Protection Act 1997 (2053 BS)
5. Explosive Act 1961 as Amended
6. Forest Act 1993
7. Labor Act 2017
8. Land Acquisition Act, 1977 (and amendments 2010) and Land Acquisition Regulations, 1969
9. Land Reform Act 1964
10. Local Government Operation Act 2017
11. Motor vehicle and Transport Management Act, 2049
12. National Foundation for the Development of Indigenous Nationalities Act 2002,
13. National Park and Wildlife Conservation Act, 1972 and amendments 1992
14. Plant Protection Act 2007
15. Public Road Act, 1974 and amendment 2010
16. Road Board Act 2059
17. Soil and Watershed Conservation Act, 1982 and Subsequent Amendment
18. Solid Waste Management Act 2011 and Solid Waste management Rules 2013
19. Water Resources Act 1992
20. Wildlife Conservation and Trade Act 2004
21. Drinking Water Service Charge (Recovery) Rules 1994
22. Buffer Zone Management Rules, 2052 (1996)2
23. Environment Protection Rule 1997 (2054 BS) as amended
24. Forest Rules 1995
25. Water Resources Regulations 1993
26. Wildlife Reserve Rules 1977
27. 20 Year Road Plan, 2059 –2079BS (2002-2022AD)
28. 2002, National Dalit Commission 2002
29. Forest Policy 2015
30. Hydropower Development Policy 2001
31. Land Acquisition, Resettlement and Rehabilitation0 Policy for Infrastructure Development Project 2014
32. National Biodiversity Strategy and Action Plan (NBSAP) 2014-2020
33. National Environmental Standards Information Booklet 2018
34. National Human Rights Action Plan 2005, National Women Commission
35. National Ramsar Strategy and Action Plan 2018-2024
36. Public Works Directive 2002
37. Work Procedure to Provide Forest Area for other Purposes, 2006
38. EIA guidelines for human settlement and Urban Development Sector 1996
39. EIA guidelines for Road Sector 1994
40. EIA guidelines for Sanitary Landfill Site 1996
41. EIA guidelines for Water Supply sector 1995
42. National EIA guidelines 1993
43. Operational Guideline for mainstreaming GESI in MoUD
44. Solid Waste Management Technical Guideline for Municipalities of Nepal
2
These rules will be evaluated case by case for Sub Projects. In exercise of the powers conferred by the Section-33 of the National Parks and Wildlife
Conservation Act, 1973, Government of Nepal has framed the Rules. This Regulation aims at a proper management of the buffer zone. To this end it
provides: (a) for the division of the area into units, on the basis of its status, extent and users' settlement; and (b) for the preparation of a buffer zone
management work plan for community development, environmental conservation and rational utilization of forest resources. The plan shall be submitted
to the Department of National Parks and Wildlife Conservation and shall include all the provisions listed in Part. Rule 17 - Gha of this regulation restricts
introduction of harmful chemicals, poison or explosive in to river or water sources located inside buffer zones. However, use of these materials for
development of physical infrastructures with permission is not prohibited.
3
2.2. International Conventions
Table 2-2 List of International Conventions, Relevant to the Project
4
World Bank’s Objective & Brief Description
OP/ BP
The policy is triggered when there are distinct, vulnerable, social and cultural groups in the project
area possessing the following characteristics in varying degrees:(a) self-identification as members
of a distinct indigenous cultural group and recognition of this identity byothers;(b) collective
attachment to geographically distinct habitats or ancestral territories in the project area and tothe
natural resources in these habitats and territories; (c) customary cultural, economic, social, or
political institutions that are separate from those of the dominantsociety and culture; and(d) an
indigenous language, often different from the official language of the country or region.When this
policy is triggered, an Indigenous Peoples Development Plan is to be prepared to mitigate the
potential adverse impacts or maximize the positive benefits of the
Gender and The prime objective of the Gender and Development policy is to assist member countries to reduce
Development OP poverty and enhance economic growth, human well-being, and development effectiveness by
4.20 addressing the gender disparities and inequalities that are barriers to development, and by assisting
member countries in formulating and implementing their gender and development goals. In sectors
and thematic areas where the Country AssistanceStrategy has identified the need for gender-
responsive interventions, the Bank's assistance to the country incorporates measures designed to
address this need. Projects in these sectors and thematic areas are designed to adequately take into
account the gender implications of the project. Preparation of a Gender Action Plan and its
implementation should be ensured by each project undertaken with Bank support.
Safety of Dams The policy triggered when Bank finances new dam project or existing dam on which project is
OP/BP 4.37 directly dependent. In cases where the bank financed project depends on the existing dam or a DUC
then the Bank requires that the borrower arrange for one or more independent dam specialists to (a)
inspect and evaluate the safety status of the existing dam or DUC, its appurtenances, and its
performance history; (b) review and evaluate the owner's operation and maintenance procedures;
and (c) provide a written report of findings and recommendations for any remedial work or safety-
related measures necessary to upgrade the existing dam or DUC to an acceptable standard of safety.
Necessary additional dam safety measures or remedial work may be financed under the proposed
project.
International The policy requires project state to notify other riparian of the proposed project and the intended
Waterways impact on water rights.
OP/BP 7.50 This policy applies to the following types of international waterways:
(a) any river, canal, lake, or similar body of water that forms a boundary between, or any river or
body of surface water that flows through, two or more states,
(b) any tributary or other body of surface water that is a component of any waterway described in
(a) above.
EIA is required if any natural habitat and associated with the requirements/approach
project development site physical, cultural project are omitted . The ESMP should
is located within - resources. The EMP shall in GoN policy. seek to to address all
1. Historical, cultural adequately address the Hence, the adverse
and archeological sites. relevant issues. Environmental & environmental impacts
2. Environmentally Social (E&S) arise during execution
weak and wet Areas. Screening exercise and operation of the
3. National parks, wild shall be carried out project.
life sanctuaries and to assess the The ESIA/IEE and
conservation areas. potential risk ESMP so prepared
4. Semi-arid, associated with the should be made
mountainous and project before integral part of bidding
Himalayan regions. selection of the document so that the
5. Flood prone and other project proposal. Contractor shall adhere
dangerous areas. to the provisions
6. Residential, school prescribed in the
and hospital areas. ESMP during
7. Areas with main execution of the
sources of public water project
supply
B. Physical- The EPR Rule 28 & 30 OP 4.11 and their “Chance find’ is not E&S study should
Cultural states that physical and application as an integral covered by the EPR include (a) measures to
Resources cultural resources shall part of the Bank’s requirements avoid or mitigate any
(OP/BP- not be disturbed or environmental assessment adverse impacts on
4.11) damaged without the (EA) process physical cultural
prior approval of resources; (b)
concerned authority. provisions for
managing chance finds
C. Clause 3 of the Land Full compensation at The Land ESMF, inclusive of the
Involuntary Acquisition Act states replacement cost for lost Acquisition Act of RPF, should include an
Resettlement that any asset that is assets shall be provided Nepal only has a indicative entitlement
and Loss of required for public according to asset types provision for cash matrix which indicates
Land/Structur purposes shall be and location. compensation based valuation and
e acquired by providing Resettlement and on degree of loss. It associated
Crop/Income compensation. Rehabilitation assistance does not take into compensation for
Source Compensation Fixation to affected people shall be account titleholders and non-
(OP/BP-4.12) Committee will provided by the project to vulnerability of the titleholders.
establish the enable them to improve affected person ESMP for sub-projects
Compensation rates. their living standard. upon losing the affecting livelihood or
As per OP 4.12 land/asset. economic resources
community assets needs to GoNlaws have no should also include
be replaced in consultation provision for livelihood restoration
with the community. compensation to plan
As per OP 4.12, all those non-titleholders Community assets
who are affected needs to (i.e., those who do need to be replaced in
be assisted including not possess land the same or better
tenants and sharecroppers. ownership condition than before.
Full compensation for loss certificates e.g. Livelihood assistance
of land/crop/ asset/income informal should be provided as
source shall be provided. leaseholders, per criteria set by
encroachers)
6
Government of Nepal Gaps between Recommendations to
World Bank (WB) Policy
Category (GoN) Policy GoN& WB policy Bridge the Gaps
7
Government of Nepal Gaps between Recommendations to
World Bank (WB) Policy
Category (GoN) Policy GoN& WB policy Bridge the Gaps
8
3. KEY ENVIRONMENTAL AND SOCIAL CONDITIONS IN THE CLUSTER MUNICIPALITIES
Table 3-1: Key Environmental and Social Issues in the Eastern and Western Cluster Municipalities3
Eastern Cluster Municipalities
Key Environmental issues
Birtamod Damak Urlabari SundarHaraicha Mechinagar Itahari Rajbiraj Triyuga Dhankuta
• High iron content in ground • Threat to Sal trees • Solid Waste disposal on • River bank erosion • Flooding in Mechi, • Lack of drainage • Disposal of solid • Pollution due to sewerage • Threat to
water • Threats to dhanesh bird species river banks Ninda, Timai, system & waste on the disposal water body
• Jaljale wetlands need protection • Flooding in Mawa, Hadiya contamination of riverbanks/open field. • Flooding due to
• Blockage of drainage system Bakraha, • High iron content in water through • High iron content in • Deforestation in southern siltation
(particularly in ward no 1,5,8,13) SunpakuwaKhola- and ground water effluent discharge groundwater, and part • Depletion of
• High iron content in ground water land cutting at places • Chure - from industries existing water supply • Landslide prone areas in water sources
• High iron content in Environmental • Depletion of water system unable to cater ward no 4,5,6,14,15,16
ground water Protected Area resources to the demand for • Chure - Environmental
water to growing Protected Area
population
• Flooding in Khado
River
• Depletion of ground
water
Social Baseline Condition
• Immigration rate 8-10% • Very High Immigration (5-7%) • Poverty 20% • Very High Immigration • Poverty about 10% • Very High • Very High • Very High Immigration • Very High
• Poverty 7-10% • Child marriage high in poor • Child marriage common • Poverty 10-12 % Immigration (7-9%). Immigration 1:5 in • Limited illegal mining issue Immigration
• High rates of child marriage communities in indigenous group and • Child marriage in poor • Child Marriagehigh rural areas • Ethnic communities • Aathpariya is
amongTarai caste, Muslim and • Limited threat to Dhimal community Terai caste group in Chaudahry, Dum, among Taraidalits, • Poverty 30-40% dependent to some extent on one of the
Adibasi groups • Ward 3,4, 9 has Dhimal community Jhangar, Bantar and Muslims and • Caste discrimination fishing and forest resources deprived
dependent on forest Musar communities Adibasi groups • About 10% women • Presence of marginalized community
• Limited threat to • Khanar, Budhikhola, haveland owner vulnerable group Musar and concentrated
Dhimal community Sunsari-Morang certificate due to dalits in ward number in Ward no. 8
• Ward 3,4, 9 has Dhimal Irrigation Canal. government tax 1,2,3,4,5,6,7,8,9,10,11,12,13
community dependent • There is proposal to incentive policy.
on forest construct 6 lane • Child marriage is also
road, therefore high among
diverting canal land marginalized
at the TyandraKhola communities
is required
Western Cluster Municipalities
Key Environmental Iissues
PokharaLeknath Vyas Putalibazar Baglung Tansen Ramgram Tilottama Shuklagandaki
• Flooding in Seti and Mardi River • Flooding in Madi&Seti River • Flooding in • During rainy season • During rainy season, • Flooding in Tinahu • Flooding in Tinahu • Flooding in the rivers and siltation in rainy
• Ramsar Site- Lake Cluster of • Water pollution in some stretches Aandhikhola, there is problem of there is problem of river river season
Pokhara Valley sumrekhola, bodikhola, flooding, water flooding, water • Water pollution in • Water pollution in • River pollution from crusher plants located
• Municipality boundary overlaps ringikhola pollution, siltation, pollution, siltation, dug wells dug wells near the river
with southern part’s Annapurna • Water Pollution and landslide landslide in nearby
Conservation Area siltation especially areas of
during rainy season Aandhikhola,
sumrekhola,
bodikhola,
ringikhola
Key social issues
- • Poverty rate 20% • Poverty rate 25% • Poverty rate 35% • Poverty rate 15% • Immigration from • Poverty rate of 15% • Poverty rate 20%
hilly region and
rural wards
• Poverty rate 30%
10
4. ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK (ESMF)
4.1. Environment and Social Risk Management Procedure
Under NUGIP, the municipalities are responsible for identification of sub-projects, and execution of sub-project while
integrating the Environmental and Social (E&S) safeguards issues. The guideline for effective integration of the E&S
safeguards is outlined in the ESMF. The ESMF details the procedure for the E&S Risk Assessment and mitigation
through instruments like ESIA, ESMP and RAP. The extent of the assessment is governed through screening
procedure. The flowchart for conducting ESIA is also presented in this figure.
4
As per World Bank OP 4.01, Project area of influence can be defined as: The area likely to be affected by the project, including
all its ancillary aspects, such as power transmission corridors, pipelines, canals, tunnels, relocation and access roads, borrow and
disposal areas, and construction camps, as well as unplanned developments induced by the project (e.g., spontaneous settlement,
logging, or shifting agriculture along access roads). The area of influence may include, for example, (i) the watershed within which
the project is located; (ii) any affected estuary and coastal zone; (iii) off-site areas required for resettlement or compensatory tracts;
(iv) the airshed (e.g., where airborne pollution such as smoke or dust may enter or leave the area of influence); (v) migratory routes
of humans, wildlife, or fish, particularly where they relate to public health, economic activities, or environmental conservation;
and (vi) areas used for livelihood activities (Hunting, fishing, grazing, gathering, agriculture, etc.) or religious or ceremonial
purposes of a customary nature.
11
the advice of environmental specialists and set out in the ESIAterms of reference by gathering preliminary idea
regarding the nature, extent, and phasing of environmental issues that would need to be handled during the subsequent
stages.The Zone of Influence (ZOI) varies according to the nature of project. As per Environmental Protection
Regulations (1997), the affected wards/rural municipality are considered as ZOI. This will be assessed rationally
based on the nature of sub project. Filling up the Environmental Screeningchecklist, category B sub project EA
requirements is the first step in the conduct of an ESIA and is provided in Appendix C. The following steps are key
to the screening.
• Confirm presence of environmentally sensitive areas from secondary information
• Site observations. If the sub project falls under ineligible category, avoid such sub projects. Only Category
B projects are eligible for funding under NUGIP5.
• Verify applicability of the GoN and the World Bank policies in sub-project activities
• Identify potential negative and positive direct or indirect impacts and provide clarity on issue, which needs
to be investigated under Category B EA type (for higher impact category requires ESIA, for medium impact
category requires abbreviated EMP and for lower impact category require Best Environmental Practices-
BEP).
• Incorporate feedback of public consultation and answers to published notice
• Comply with GoN specific EIA/IEE requirements in the EPA/EPR 1997
• Determine applicability of regulatory and policy and requirement of clearances and permissions
• Identify of key environmental concerns
• Scope Impact Assessment and Mitigations
4.1.2. Scoping
The scoping for E&S study will be undertaken based on the screening to fulfill the following objectives:
• Familiarize with the project
• Define the study area comprising the project site and its PIA
• Outline the environmental and social interactions pertaining to the project focused on the ESIA study
• Define the scope of work and the approach and methodology to conduct the IEE/ESIA, RAP or ARAP
For systematic definition and recording, the baseline environment is usually classified into Physical, biological, and
social environment. Important features/ parameters under each category are identified and measured during baseline
survey. The table (in Appendix J) summarizes information on the type of baseline indicators that would be adopted,
based on site-specific potential impacts as identified in the environmental screening and scoping process.
.
4.1.4.2. Establishment of Social Baseline
For Social Impact Assessment, it is very important to adequately define the “social baseline” against which projected
social impacts of a sub-project would be subsequently evaluated. The characteristics of “social baseline” would
depend on:
• Land requirement
• Social issues specifically faced by women or vulnerable groups
• Identify social needs, benefits and barriers
• Extent and type of losses even due to the changes of circumstances.
• Number of Project Affected Family
The table below summarizes the type of baseline indicators that will be required. In cases where projects, which are
categorized with very, limited social impacts, the baseline parameters will be captured through socio-economic survey
(10 % - 25% of base population depending on the type, scale and size of the sub-project). However, if the project has
significant impact, a full census survey will be conducted. It is important to project the number of affected family
andthe extent of losses incurred.
Table 4-1: Description of Social Baseline Information required for the Project
Component Possible Social Issue/ aspect Baseline Information
Demography Socio Economic Condition • Population
• Age pyramid by gender
• Sex Ratio
• Literacy
• Labor force participation, by occupation
• Population Density
Forestry Forest user group affected due to acquisition of • Forest type
forest land • Forest land getting acquired
• Uses of forest produce
• No. of users in forest user group (present in the
corridor of impact)
• No. of users under each category of social
category (caste, gender, vulnerable, disability,
economic status)
13
Component Possible Social Issue/ aspect Baseline Information
Conflict for the use of forestry resources between • Flow of migrants/ their sources of forestry
locals and labors, depletion of NTFP resources product
and invasive species • Impact due to increased accessibility.
Agriculture Loss of agricultural land due to urbanization due • Demographic and socio- economic profile
to the project along and at the project site (PIA)
Loss of crop • Land holding pattern (marginal, small, large)
Disturbance to agriculture production, influx of along and at the project site (PIA)
invasive species and pests • Land holding according to social categories
Loss of livelihood of cultivators ( farm labors) along and at the project site (PIA)
Disruption of access to water for irrigation • Farm labors employed
Flooding or drying of agricultural land • Livelihood pattern (farmer, business, industry,
service etc. within and outside the project site
(PIA?)
• Source of water for irrigation
• Low lying area
• Crop damages
• Enumeration of PAFs/PAPs
• Affected Plot No/ Survey No and details of its
ownership
• Estimation on loss of Properties (Land Area,
Structures, associated structure etc.)
• Estimation of other properties like cattle’s,
Vehicles, Crops, Trees etc.
• Demographic details of affected PAFs/ PAPs
• Quality of life (To access parameters such as
access to basic amenities such as water,
transport, education, health etc.)
• Health, Sanitation condition
• Prevalence of Social Development Programs
(Govt./NGO)
• Property prices
Personal assets Loss of land • Land holding pattern by size (new construction
Loss of major structure (house, shop etc.) of road)
Loss of minor structure (hand pump, boundary, • Type of structures
cattle sheds etc.) • Types of minor structures
Loss of assets or access to assets • Socio-economic profile of affected family
Disruption of access to common resources • Types of utility services that need to be shifted
including road, utility services etc. and no. of users
Loss of livelihood or residence (non-title holders) • Types of public/ common assets that have to be
Loss of income or means of livelihood shifted and has public consented for relocation
• Livelihood pattern
Loss of trees/ vegetation (fruit bearing trees/ • Income generated from the business/ shop/
shrubs, flowers etc.) farming
Common Disturbance/ demolition of water supply • Types of trees and count
property infrastructure, groundwater changes leading to • Types and value of fruit bearing and flowering
resources drinking water and irrigation problems shrubs
Damage to resting sheds, bus stops, water source
etc.
Land use by in- Acquisition of land and property; social conflicts, • Changing land use pattern
migrants and resettlement issues • Approximate labor requirement for the project
labor (about 30 % of the labor from outside)
Health Introduction and spreading of communicable • Existing medical facilities
diseases or respiratory disease • List of sensitive receptors (e.g. hospitalsand
schools) and their capacity
• Prevailing diseases
Road safety • Type and number of accidents
Cultural Heritage Sites of Religious/ cultural importance being • Age of the cultural site, its significance,
disturbed location, number and type of such properties
Sites of historical / • It is to be ensured that safe distance (as per the
archaeological/anthropological Importance defined regulations of GoN has been
maintained from such sites
14
Component Possible Social Issue/ aspect Baseline Information
Vulnerable Affects Vulnerable communities (Indigenous • Type of indigenous group present and their
community people) by disrupting customary rights of use and cultural practices
access to land and natural resources, cultural and • Community consultation practices
integrity • Can the project adversely impact local
knowledge and alter lifestyle?
Gender issues Not including in the decision making process of • Type and number of public consultations held
selection of beneficiaries of the project (/project for the project
design) • Record of these consultation and representation
of different social categories
• Women groups especially Dalit women were
involved in consultations?
Limit access to common property or natural • How they use the roads or tracks, will there be
resources any kind of disruption?
Excluded from opportunities ( construction and • Will women be employed for the project
maintenance work) activities?
Disparity in wages • Prevailing wages for men & women
Loss of entitlement to land/ property and • Are they also part of land ownership
compensation thereof (if women are not included entitlements?
in the land ownership certificate) • Source of income
Loss of income or means of livelihood • Instances of gender violence
Increase in instances of gender violence due to
labor influx/ in-migration
Citizen Exclusion of community from decision making • Means and number of public consultations
Engagement process • Public notice provided in accessible manner
Exclusion of certain vulnerable section from (e.g., language and means used for
decision making process and selection of information)
beneficiaries • Type and number of people with disabilities in
Project design limiting access to common the project impact corridor
resources for people with disability • Willingness to contribute to the
Coercion on donating land project,includingto donate land
• Expectation for compensation
• Legal case pending in the court for the land, if
relevant
• Use of the current grievance mechanism
established at the municipality (through ward
representative)
15
• Without-Project scenario would provide the status if the proposed interventions are not undertaken. This will
be done by analyzing the previous status using data collected during environmental-social baseline and field
investigations; and
• With-Project scenario, status with implementation of the proposed interventions, will be projected.
The envisaged impacts will be categorized as impacts during the preconstruction, construction and operation phase
of the project. There are common E&S risks which are associated with pre-construction, construction and operation
stage as listed below:
• Impact due to change in land use
• Impact on livelihoods and sources of livelihoods
• Impact due to change in drainage pattern
• Impact on ecology &biodiversity
• Impact on ambient air quality and noise levels
• Impact on water quality
• Impact on properties (by type/category) (including Community Property Resources)
• Impact on permanent or temporary use of public spaces and facilities
• Health and safety issues during construction and operation phases
• Occupation and safety hazards during preconstruction, construction and operation phase
• Temporary access control, including provision for barricading and safety signage markers if required
• Construction materials (quantity requirement and storage)
• Water requirement for the project with basis of calculations, and its sources during the construction phase
• Type of vehicle/equipment usage during construction
• Utility shifting
• Quantities of solid and hazardous wastes generated
• Disposal of excess excavated earth, waste disposal/reuse
• Waste handling and management, including construction waste, hazardous and non-hazardous waste
Additional E&S risks in the COVID-19 context to be considered include management and disposal of health-care and
medical waste including personal protective equipment (PPE), virus transmission between workers and between
workers and community members.
Qualitative and quantitative impact assessment tools (e.g. GIS mapping, analytical matrices, and other relevant
analytical tools) will be used to understand the extent of impact due to the proposed sub-projects. Effort will be given
to quantify the impacts, to the extent possible. For example, quantitative assessment of impact is essential to be carried
out for loss of land-properties- other assets, loss of trees, acquisition of forest land – waterbodies, impact on common
property resources, impact on utilities, generation of debris/waste, requirement of natural resources in the project etc.
On the other hand, qualitative impact assessment may be carried out for impact due to labour influx, safety and
security of workers and communities etc. If necessary, projection of impact though modeling /statistical analysis will
be undertaken to understand the projected level of pollution load due to the proposed sub-project.
Table 4-2: Anticipated Environmental and Social Impacts due to Development of Sub-projects
16
Sector Environmental & Social Impacts
• Generation of debris from dismantling of structures and its disposal
• Traffic congestion and disruption to local access during to preconstruction and construction
phase
• Air Pollution and noise pollution during construction and operation phase due to material
handling, vibration during construction work and movement of traffic
• Destabilization of slope which may lead to impacts such as soil erosion, sedimentation etc.
• Leaching of materials which may lead to contamination of water sources, affecting aquatic
habitats
• Air pollution during preparation of the bitumen
• Contamination of soil, water environment due to accidental spillage of oil, grease from the
construction vehicles, fuel storage area
• Possibility of contamination of surrounding soil, water environment from labor camp sites
and improper material handling/transportation
• Loss/partial acquisition of water body and siltation due to construction work
• Concerns related to excavation of quarries and borrow areas (if required)
• Increase in accidents or Deterioration of safety of road users/ pedestrians
• Urbanization and commercialization leading to drastic change in land use pattern
• Impact on migratory path of wildlife/habitat fragmentation
• Possibility of increased illegal hunting/ trapping/ fishing/poaching due to improved
accessibility
Water • Contamination of surface or ground water quality during boring/ well construction
Supply • Stress on water source. Impact on availability of water after abstraction of water for the
sub-project or drying up of water supply due to over-extraction
• Generation of muck/excavated material, other debris and its disposal
• Loss of trees and vegetation cover and associated biodiversity
• Air and water quality deterioration due to dust generation and vehicular emissions during
transportation, loading /unloading of construction materials and construction work
• Soil erosion, Contamination of water resource due to silt runoff during trenching
• Generation of noise due to excavation, other construction works, movement of vehicle and
construction equipment
• Traffic congestion and Disruption to local access due to construction, operation-
maintenance work and excavation
• Temporary disturbance to household water supply
• Impact on religious/cultural properties, utilities
• Temporary flooding of adjacent areas due to accidental leakages/bursts
• Acquisition of land requirement for water treatment plant
• Potential threat to safety of dam due to over-discharge or construction of new structure (if
water is sourced from dam)
Waste • Lack of proper hygiene and sanitation facilities in labor worker camps
Water • Land required for sewer pipe network, sewerage treatment plants and possibly for
treatment ponds
• Generation of muck/excavated material, other debris and its disposal
• Loss of trees and vegetation cover and associated biodiversity
• Air quality deterioration due to dust generation and vehicular emissions during
transportation, loading /unloading of construction materials and construction work
• Generation of noise due to excavation, other construction works, movement of vehicle and
construction equipment
• Impact on religious/cultural properties, utilities
• Soil erosion, Contamination of water resource due to silt runoff during trenching
• Temporary flooding of adjacent areas due to accidental leakages/bursts and also due to
blockages and backlogging of lines in operation phase
17
Sector Environmental & Social Impacts
• Risk of accidental contamination of Soil/surface / ground water resource and possibility of
mixing with water supply line due to leakages/ overflows from the sewer lines in operation
phase
• Traffic congestion and disruption to local access due to construction - excavation and
operation maintenance work
• Disposal of waste generated from waste treatment plant such as effluents, septage and
sludge
Solid Waste • Lack of solid waste (including medical wastes) collection, segregation and its recycling
Management facilities
• Land acquisition and site clearance for waste disposal sites
• Closure of existing open dumpsites and displacement of dependent waste pickers
• Dust emissions and noise generation from site preparation, excavation, material handling
and other construction activities at site, vehicular movement
• Tree & vegetation removal at waste disposal site and loss of associated biodiversity
• Possibility of contamination of surrounding soil, water environment from labor camp sites
and improper material handling/transportation
• Generation of landfill gas i.e. methane (CH4) and carbon dioxide (CO2)
• Nuisance due to generation of foul odor from disposal site or poor transportation/handling
of waste
• Nuisance associated with irregular collection of waste at household level
• Accidental contamination of soil and water environment during transportation and handling
of waste, including medical wastes
• No segregation of waste may lead to uncontrolled disposal of hazardous and medical waste
which may contaminate soil/water resource
• Risk of flooding of landfills (particularly in low lying areas)
• Risk of contaminating surface and ground water by seepage and leachate from disposal
sites
• Destabilization of heaps of waste at the landfill site
Anticipated social issues based on thematic areas are listed in the table below:
Table 4-3: Anticipated Social issues pertaining to the project
18
Theme Social Issues
Land & • Coercion on donating land
Asset • Loss of fruit bearing or flowering trees/ shrubs
Related • Loss of cultivable land and crops
• Loss of major or minor structure (residential)
• Loss of temporary shelters
• Loss of livelihood or residence of non-title holders (e.g., squatters, encroachers, tenants, etc)
• Loss of assets or access to assets
• Damage to Resting sheds, bus stops, water source etc. and other common community resources
• Loss of entitlement to land/ property and compensation thereof (if women/ vulnerable families
are not included in the land ownership certificate)
• Dismantling of existing structures
• Disturbance to agriculture production, influx of invasive species and pests
• Loss of visual aesthetic value of the land/area due to the sub-project
Labor influx • Increased pressure on the forest in the vicinity for fuel wood
• Impact on surface and ground water from unsanitary disposal of toilet waste
• Conflict for the use of forestry resources between locals and labors
• Introduction and spreading of communicable diseases or respiratory disease
• Acquisition of land and property; social conflicts, resettlement issues, over establishment of
labor camps
• In-migration affecting the local social and economic conditions
• Increase in instances of gender violence
Indigenous • Disruption of customary rights over use and access to land and natural resources
people • Impact on cultural and communal integrity of vulnerable groups, including indigenous people
• Altering or undermining of the recognition of indigenous knowledge
• Impact on foot trails connecting indigenous groups
19
• Implementation schedules for each activity
• Reporting procedures, including for redressing grievances related to environmental issues
The ESMP will abide by the following core principles.
i) Local Community Participation and Demand Driven Decisions
ii) Ownership of ULGs
iii) Environmental Sustainability, Protection and Enhancement
iv) Community Cohesion and Security
v) Gender Equity and Social Inclusion
vi) Empowerment of Local Communities/ULGs
vii) Resilience to Disaster, Climate Change
viii) Institutionalization of Land Donation Processes
ix) Adaptability to changing circumstances and context
The cost for implementation of the management measures, the institutional arrangements for monitoring will be
included in the estimated project cost. The Appendix E summarizes probable impact, its subsequent mitigation
measures institutional roles and responsibilities. However, the actual mitigation measures will be designed on the
basis of the project, location, IEE/ESIA findings, public recommendations and prevalent best practices.
Budget for ESMP
Each sub-project will have its own budget to cover the ESMP implementation costs relating to mitigation measures,
enhancements, and monitoring costs. In addition, training and capacity building costs willbe added for specific issues
that ESIA may bring out. For instance, there may be a need to have short courses on specific topics, experience
exchanges on any particular issue, and so on.
20
impacts. These instruments also provide a platform for getting views from stakeholders including the directly affected
community and institutions to improve the design so that the asset quality is improved (refer to Appendices E and F).
Construction
Stage/ Environmental Mitigation/ Enhancement Schedule Responsible Costs
Environmental Impact Measures of party (NRs)
aspects Actions
PRE-CONSTRUCTION STAGE
Physical Environnent
Change in land The project Appropriate route selection to DPR, ESIA None
use intervention may minimize impacts Consultants,
impact the Maximum use of existing road PCO,
existing land use and public land Municipalities
pattern of the area Collection of spoils and its
management in scientific way
Biological / Chemical Environment
Ecologically Adjoining Prior care willbe given during DPR, ESIA None
sensitive areas environmentally project screening. Project will Consultants,
sensitive areas not be developed in PCO,
(National Parks, ecologically fragile areas. Municipalities
Wildlife
Reserves,
Ramsar Sites etc)
can be affected
Social-Economic /Cultural Environment
Cultural Sites of cultural Prior care will be given during DPR, ESIA None
heritage and historical project screening. Historically Consultants,
importance can significant PCO,
be affected archaeological/anthropological Municipalities
site will be avoided in design
stage
CONSTRUCTION STAGE
21
Implementation of measures to
address COVID-19 risks
Occupational Accidents Implementation of OSH Contractor, Integrated
Health Hazard causing Deaths/ activities. Distribution and PCO, in total
and Safety Injuries mandatory use of safety hats, Municipalities, project
shoes, follow-up of safety DSC cost
regulation, well-
communication of construction
safety instructions at all levels
22
Traffic co- ordination
congestion, Plan for traffic decongestion with DSC
possible will be kept. Barricades will be
accidents and maintained including signs and
death flagmen as required. The
construction works will not
interfere with or cause
inconvenience to public or
restrict the access to use of
properties.
POST-CONSTRUCTION STAGE
Physical Environment
Risk of virus Provision of information Contractor, Integrated
transmission around hygiene, particularly PCO, in total
with regards to COVID-19. Municipalities, project
Implementation of measures to DSC cost
address COVID-19 risks
Disposal of Possible Careful segregation of wastes, Contractor, Integrated
solid waste, contamination, regular collection and PCO in total
waste materials disturbance to treatment of wastes and proper project
and community, disposal cost
construction accidents Project site and working area
spoils will be cleared of unutilized
construction materials, heavy
equipment and debris; and a
final clean-up of solid wastes
will be conducted.
Biological / Chemical Environment
Restoration of Clogging of Disturbance of waterways will Contractor, Integrated
waterways water bodies, be cleared to avoidobstruction PCO in total
surface run off from construction debris and project
other waste materials. cost
Social-Economic /Cultural Environment
Termination of
Loss of The local workforce will be Contractor, Integrated
emplyoment temporary jobs briefed in advance about the PCO, in total
by the local work loss of job after project Municipalities project
force after project completion. Compensation, if cost
completion, applicable, will be provided
OPERATION STAGE
Physical Environment
Soil/Water Pollution of Proper drainage network and PCO, Integrated
quality water bodies, silt fencing will beprovided to Municipalities in total
degradation erosion ensure that the water quality is project
due to surface not impaired due to cost
run-off contaminants from road run-
off.
Biological/Chemical Environment
Replacement Survival of The replacement plantation PCO, Integrated
plantation planted seedling will be maintained and taken Municipalities in total
and their growth care to ensure the survival of project
the seedlings to mitigate cost
23
vegetation loss during
construction
Social-Economic /Cultural Environment
Removal of Loss of The fruit trees will be PCO, Integrated
fruit trees production compensated at market value Municipalities in total
on the basis of loss of future project
production, based on 5 years cost
annual net production.
24
4.1.16. Legal Contract for E&S Compliance
The environmental and social safeguard and mitigation measures willbe integrated in the design of the project itself.
Such approach will enhance the mitigation measures in terms of specific mitigation design, cost estimation of the
mitigation measures and specific implementation criteria. Integration of mitigation measures in the design phase will
also help in strengthening the benefits and sustainability of the project. The legal contractswill include at least the
following commitments:
• Design, construct, operate, maintain and monitor the subprojects in compliance with the specified applicable
E&S requirements.
• Implement the environmental and social mitigation measures specified in the IEE/ESIA-ESMP prepared
based on ESMF, including all conditions stipulated in the ESMP and other relevant plans prepared based on
the process of identification of E&S risks and impacts pursuant provisions tothe World Bank’s safeguard
policies. The project sponsor will also ensure that adequate E&S contracts are included in their bidding and
legal documentation with contractors and suppliers, as needed.
• Use all reasonable efforts to ensure that theenvironmental and social performance of the subproject is in
compliance with the applicable E&S requirements during implementation, including E&S monitoring.
• Provide periodic E&S performance reporting to the PCO andthe World Bank according to an agreed template
within a specified timeframe.
The tender instruction to bidders will explicitly mention the site-specific mitigation measures to be performed, the
materials to be used, the specified and excluded sites for material retrieval, labor camp specifications, arrangements,
labor influx management and waste management and disposal areas, as well other site-specific environmental and
social requirements. Such a definition would clearly exhibit the cost requirement to undertake mitigation measures,
which otherwise might be lost as the bidders in an attempt to be more competitive may not include the price realistic
enough to fund mitigation measures and other protection measures.
The project contractor willbe bound by the parameters of contractual clauses which will be identified through ESIA
studies pertaining to specific mitigation measures in the subproject. Measures will be taken to ensure that the
contractor is aware and understand the respective contractual clauses and obligations. The final acceptance of the
completed works will not occur until the environmental and social clauses have been satisfactorily implemented.
Role of contractors will be to ensure compliance with ESMP, if any sub-contractors will be hired. There willbe a legal
contract between contractors and subcontractors to adhere to ESMP. Zero tolerance for child/forced labor, gender-
based violence, community H&S, equal wages, labor camp standards for contractors/subcontractors, will be well-
articulated and communicated to the laborers and others.
The contractor’s environmental and social management plan (CESMP) will be prepared by contractor and submitted
to the respective PIU within 45 days of contract signing. This applies to subcontractors too. The subcontractors report
to the main contractor regarding their E and S compliances on regular basis.
In the context of COVID-19, special consideration needs to be given with regards to labor procedures including the
health and safety of workers, the community members with whom workers come into contact, as well as the
management of medical and health care waste. To ensure that workers are safe in the workplace, or that workers who
are at risk or could put others at risk are not at work, is an important first step.
25
Considerations for workers
The World Bank has developed a Safeguards Interim Guidance Note on COVID-19 Considerations in Construction
and Civil Works Projects, which is included in Annex L. Some practical mitigation measures for prevention and
response is provided below.6
• Provide information on COVID-19: Provide information on good practices for preventing COVID-19
transmission, particularly observing recommendations on social distancing, and training to workers to
recognize the symptions of COVID-19.
• Ask sick or potentially infected workers to stay at home: To prevent potentially affected staff from entering
a worksite and infecting co-workers, the project should request workers to stay away from the worksite
where they exhibit any COVID-19 symptons or have been in close contact with a confirmed COVID-19
patient during the past 14 days
• Cough hygiene: Workers should be instructed to follow cough etiquette to reduce the risk of spreading the
virus when coughing or sneezing, which includes covering the mouth when coughing or sneezing with tissue
and disposing used tissue into wastebasket, or coughing into elbow or sleeve, cleaning hands after coughing
or sneezing preferably by using hand wash or hand sanitizing gel.
• Social distancing: To prevent person-to-person infection, direct contact between workers should be
minimized. Where required to work or meet, a safe distance of 2 metres between people should be observed.
Workers should be informed about the hazards of close contact, and to promote alternative behaviours such
as maintaining safe distances. The contractor may also consider establishing alternative working days or
adding shifts to reduce the total number of employees on a work site at a given time.
• Hand washing: the project should promote frequent and thorough water-soap hand washing and provide
enough places for workers to wash their hands. If soap and running water are not immediately available,
provide alcohol-based hand rubs containing at least 60% alcohol.
• Cleansing and disinfecting: Touched surfaces should be frequently cleaned such as equipment, handrails,
toilets etc, and instruct workers to clean equipment/workplaces at the end of a shift.
• Food preparation: Staff in labour camps should help ensure that food served to workers is safe. Measures
include: not working if they have symptons; being trained in common food safety practices; required to wash
hands regularly; prevent cross contamination caused by people sharing the same serving spoons.
• Air quality measures: Consider air quality control measures particularly for labor camps
• Personal Protective Equipment: People who come into contact with possibly infected workers or with
infected materials should use gloves and breathing protection
• Workers accommodation: Additional measures to those provided above include preventing infected persons
from entering workers’ accommodation areas, promote, respect and enforce occupancy density limits in
worker accommodations, and where new workers arrive from areas with high risk of COVID-19, ensure that
these persons are adequately quarantined as per local regulations or recommendations from international
organizations.
6 For more details, see Interim Advice on Supporting Workers in the Context of COVID-19, Interim Advice for IFC Clients on
Preventing and Manaing Health Risks of COVID-19 in the Workplace, as well as Interim Advice for IFC Clients on developing
a COVID-19 Emergency Preparedness & Response Plan.
26
Further details are provided at: https://www.who.int/publications-detail/water-sanitation-hygiene-and-waste-
management-for-covid-19
In the interest of delivering a rapid response in such emergency situations, the updated ESMF where prepared, will
adopt a flexible, “adaptive management” approach. A rapid assessment of the environmental and social baseline of
the CERC activities will be undertaken, based on readily available information. A phased approach to implementation
may be used. Based on the EAP, the CERC activities will be grouped into: (i) those activities which can proceed as
soon as the CERC is activated and with no additional environmental and social assessment; (ii) those activities which
would require an environmental and social assessment, stakeholder consultation, and disclosure of the relevant
management plans (eg ESMP), prior to CERC activities commencing.
The updated ESMF will describe: the potential emergencies and the types of activities likely to be financed and an
evaluation of the potential risks and mitigation measures associated with those activities; identify likely vulnerable
groups and/or locations and includes, where needed, a social assessment to guide emergency responses, such as
potential of exacerbating existing social conflicts. The ESMF will include a screening process for the potential CERC
activities, the institutional arrangements for environmental and social due diligence, and any needed capacity building
measures to implement the CERC-ESMF, generic guidance on emergency small scale civil works, and any additional
safeguard instruments which may be required for the CERC.
It will be determined at the time of CERC activiation whether MOUD-DUDBC will be retained as the implementing
agency, of if a different agency will be responsible for implementing the CERC activities. If procurement of goods
and services is required, the revised ESMF will provide how this will be undertaken.
Additional details regarding CERC implementation will be outlined in the PIM for NUGIP.
27
5. RESETTLEMENT POLICY FRAMEWORK (RPF)
The resettlement policy/strategy adopted for the project aims to ensure that in cases where there is any form of land
acquisition or resettlement on account of sub-projects supported under the project, the affected persons will be
resettled and rehabilitated in a manner that they do not suffer from adverse impacts and that their standard of living,
earning capacities and production levels will either beimproved or at the minimum, will be retained to pre-project
levels. It is also an effort of the project to ensure that resettlement will minimize dependency and be sustainable
socially, economically and institutionally. Special attention will be given to the improvement of living standards of
marginalized and vulnerable groups.
The rationale for the Resettlement Policy Framework has originated from the fact that specific subproject sites and
activities are yet to be identified under the project to be able to understand the exact nature, scope and scale of their
impacts. Thus, this Resettlement Policy Framework (RPF) has been developed to guide detailed resettlement planning
to address land acquisition and resettlement impacts during project implementation. Specifically, this framework
establishes the involuntary resettlement and compensation principles, organizational arrangements to be applied to
meet the needs of the people who may be affected by the project activities due to land acquisition, loss of shelter,
assets or livelihoods, and/or loss of access to economic resources. The RPF is prepared while adhering to the national
regulations as well as the safeguard policy guidelines of the World Bank.
If the impacts include physical relocation, the resettlement plan or resettlement policy framework will
includemeasures to ensure that the displaced persons are
i) provided assistance (such as moving allowances) during relocation; and
“Land and Asset Acquisition” here refers to all methods of obtaining land and other asset for project purposes,
7
which may include involuntary acquisition, acquisition through negotiation and voluntary donation
28
ii) provided with residential housing, or housing sites, or, as required, agricultural sites for which a combination of
productive potential, location advantages, and other factors is at least equivalent to the advantages of the old site.
Where necessary to achieve the objectives of the policy, the resettlement plan or resettlement policy framework also
includes measures to ensure that displaced persons are
i) Offered support after displacement, for a transition period, based on a reasonable estimate of the time likely to
be needed to restore their livelihood and standards of living; and
ii) Provided with development assistance in addition to compensation measures such as land preparation, credit
facilities, training, or job opportunities.
As per the World Bank policy, the RPF requires that no land will be acquired (taken possession of) before
compensation is paid fully and completely to the affected people. Depending on extent of land requirement for sub-
project, the nature of land acquisition process could be through three processes viz. involuntary land acquisition,
acquisition through negotiation, voluntary land donation.
Prerequisites for sub-project finalization and initiation of the land acquisition process
Prior to sub-project finalization and initiation of land acquisition process under NUGIP, the concerned municipalities
have to ensure that:
• Land recordshavebeen correctly updated in revenue record as well as the cadastral maps by the concerned
authorities
• Land and asset acquisition has been done in accordance to the regulation of GoN and World Bank safeguard
standards
• Land and asset acquisition has been done in legal, documented and transparent manner. The documents
pertaining to transfer of land, consents from owners areproperly documented and published in public domain.
• No land is acquired before compensation is paid completely to the affected people, as per World Bank’s
policy requirements.
• If the land is already transferred to the proponent (executing agency 'EA"), the land entitlement certificate
(LalPurja) is in the name of the EA prior initiation of construction activities. This could be verified with
district land revenue office
• All grievances especially related to the land acquisition is communicated to the World Bank along with the
redress process followed.
The Land Acquisition Act 1977 authorizes the Government of Nepal to acquire any land in any place for any public
purpose as long as compensation is provided for loss of land and assets. According to the Act, public purposes include
functions undertaken in the interest of or, for the benefit or use of, the general public as well as functions to be
undertaken by GoN.
In preparing the RAPs RPF, the following steps will be followed, in accordance with the Land Acquisition Act and
World Bank policy OP4.12:
• The acquisition and compensation of privately-owned assets are undertaken according to a formal procedure,
consisting of (a) initial procedures, (b) a preliminary investigation process, (c) acquisition notification, (d)
compensation notification, and (e) appeal procedures
• Compensation Determination Committees are established (at district level) to ascertain compensation rates
for land and other assets
29
• Compensation must be paid: (a) for damages caused as a result of investigations during the preliminary
investigation process, and (b) for land and assets permanently acquired by the project (including, standing
crops, trees, houses and other assets)
• Compensation must take depreciation for salvage materials into account
• Under World Bank policy, preference should be given to land-based resettlement strategies where livelihoods
are land-based
• Compensation will be made to the person who has the right to claim for the compensation; to be entitled to
compensation for land, a person must submit an official land registration certificate at the time of
compensation claim
• Titleholders are required to submit compensation claims or complaints within a specified period after the land
acquisition notice had been issued by the Local Authority (Chief District Officer). Compensation for land is
paid after determination of rates and verification of the list of entitled applicants by the Compensation
Determination Committee (CDC)
• Two separate rates of compensation can be paid i) to titleholders who lose all their land, and ii) to titleholders
who lose only some part of their land.
• In determining the compensation amount, the committee has to consider relevant periodic guidelines of
GoN and the loss suffered by persons due to acquisition of land, shift of residence or place of business to
another place.
• While determining the compensation amount, the CFC has to consider price of the land prevailing at the
time of notification of land acquisition, price of standing crops and structure, and damage incurred by
persons being compelled to shift their residence or place of business due to land acquisition.
• After the completion of land transfer process, the municipality in coordination with Land Survey Office will
initiate cadastral survey to update the land record and ensure tax relaxation for the acquired land
However, the acquisition of land through negotiations willbe based on the following criteria
• Preparation of Land Acquisition Plan (LAP) for the Project: The project design layout will be superimposed
on cadastral map to identify the affected plots and its corresponding area by Municipality in consultation with
the Design and Supervision Consultant (DSC). The details of other assets will also be identified during this
process
• The LAP will be officially verified and ownership details of affected land parcels will be identified by land
survey - land revenue department and the details should be shared with municipality
• The land acquisition through negotiation will be carried out in a transparent manner and without any
pressure/threat on asset ownership. The documents pertaining to transfer of land, consents from owners willbe
properly documented and published in public domain
• The land owners will be consulted by DSC and municipality to explain the project proposal and acquisition
of land through direct negotiation process
• The value of land and other assets willbe decided through negotiation between the land owner and
municipality, with the negotiation process adequately documented.
• The value of land and assets will be at least as per the prevailing market price
• After the completion of land transfer process, the municipality in coordination with Land Survey Office will
initiate cadastral survey to update the land record and ensure tax relaxation for the acquired land.
In case the legal owner fails to be present to receive compensation within given time by the project, compensation
can be handed over to their spouse or legitimate heirs or to the nearest relatives if they have no immediate heirs
such as spouse or children. For this, the compensation receiving person must submit evidences to prove that they
30
are legitimate heirs along with certification from concerned municipality describing reason of inability of legal
owner to presence themselves for claiming compensation
31
• The municipality through Social Development section or departments/DSC will prepare documents of each
event and finally forward it to PCO in monthly, quarterly and annual report.
The project will adopt different methods of social recognition such as writing names in the hoarding board, and/ or
offering letter of appreciation to the owners for voluntary land donation. Where voluntary land donation has taken
place following the Project Concept Note review and prior to appraisal, the RAP will provide guidance on undertaking
due diligence to demonstrate that World Bank Policy on Involuntary Resettlement has been followed.
Crop Damage
In case of possible damage of crops by the subprojects, the concerned people will be informed in advance giving time
to harvest the crops from the field. However, in cases where crop damage do occur due to subproject activities, it will
be considered as direct impacts for which the project will provide replacement value of the crops as per current market
price in the same vicinity.
Construction-related losses
Care will be taken to avoid any kind of damage to private and public properties during construction. In case of any
damages to private or public property, the affected parties will be compensated by the contractor.
Full details regarding loss of assets and other losses, together with corresponding compensation and other support are
provided in the entitlement matrix at Table 5.1.
The outcome of the SIA will help determine the extent of the impacted PAPs which in turn will govern the preparation
of the resettlement plans – which can either be an Abbreviated Resettlement Action Plans (ARAPs) or a full
Resettlement Action Plan (RAPs). The PIU, with or without external support, will prepare the RAP. The
compensation (if triggered) will be determined by the Compensation Fixation Committee (CFC) of the district. The
project proponent is responsible for the implementation of RAP.
Abbreviated Resettlement Action Plans (ARAPs): An ARAP is prepared when the impacts of the entire displaced
population are minor (if the affected people are not physically displaced and less than 10 percent of their productive
assets are lost), or fewer than 200 people are affected.
Resettlement Action Plan is prepared for (a) projects involving acquisition of private land or permanent loss of private
assets and livelihood, (b) if the project involves physical displacement and causes adverse impacts on more than 200
PAPs and (c) projects which requires resettlement sites.
The resettlement plans will be prepared based on the principles of World Bank Operational Policy (OP) 4.12 on
Involuntary Resettlement, the national laws on land acquisition and this RPF. All affected persons will be fully
consulted so that they have a chance to participate in the design and implementation of the A/RAPs. The Executive
summary of thereport will be translated in Nepali language, communicated in local language and specifically
announced though public consultation where the indigenous community is not integrated in mainstream community.
Only after the Bank has accepted the RAPs will compensation, resettlement and restoration activities be initiated.
Such activities will be completed before the commencement of civil engineering. The content of RAP & ARAP is
provided in Appendix G.
Key definitions
1. Affected area: means such area as may be notified by the appropriate Government for the purposes of land
acquisition
2. Agricultural land: Means land used for the purpose of: (i) agriculture or horticulture; (ii) dairy farming,
poultry farming, pisciculture, sericulture, seed farming breeding of livestock or nursery growing medicinal
herbs; (iii) raising of crops, trees, grass or garden produce; and (iv) land used for the grazing of cattle;
3. Building: Means a house or other roofed structure of any material whatsoever but does not include a tent or
other portable and temporary shelter;
33
4. Encroacher: A person who has extended their building, agricultural lands, business premises or workplaces
into public/government land without authority;
5. Income: Income of the PAP shall mean the amount prior to the cut-off date from all occupations taken
together calculated by an objective assessment;
6. Land: "land" includes benefits to arise out of land, and things attached to the earth or permanently fastened
to anything attached to the earth
7. Project Affected Family: The Project Affected Family (PAF) includes the following:
• family whose land or other immovable property has been acquired;
• family which does not own any land but a member or members of such family may be agricultural
laborers, tenants including any form of tenancy or holding of usufruct right, share-croppers or
artisans or who may be working in the affected area for three years prior to the acquisition of the
land, whose primary source of livelihood stand affected by the acquisition of land;
• indigenous people and other traditional forest dwellers who have lost any of their forest rights
recognized under the operational plan of community forest
• family whose primary source of livelihood for three years prior to the acquisition of the land is
dependent on forests or water bodies and includes gatherers of forest produce, hunters, fisher folk
and boatmen and such livelihood is affected due to acquisition of land;
• member of the family who has been assigned land by the State Government or the Central
Government under any of its schemes and such land is under acquisition;
• family residing on any land in the urban areas for preceding three years or more prior to the
acquisition of the land or whose primary source of livelihood for three years prior to the acquisition
of the land is affected by the acquisition of such land;
8. Project Affected Person (PAP) is any person affected either directly or indirectly by the project and/or
project related activity, irrespective of the legal status and would include the following.
• Title holders,
• Encroachers,
• Squatters,
• Tenants, Leaseholders, Sharecroppers,
• Employees, Landless laborers,
9. ProjectAffected Household (PAH): A social unit consisting of a family and/or non-family members living
together, and is affected by the project negatively and/or positively;
10. Replacement Cost: A replacement cost/value of any land or other asset is the cost/value equivalent to or
sufficient to replace/purchase the same land or other asset and other applicable taxes to be incurred by the
affected person.
11. Shop: Means any premises where any trade or business is carried on and where services are rendered to
customers;
12. Squatter: A person who has settled on public/government land, land belonging to institutions, trust, etc.,
and or someone else’s land illegally for residential, business and or other purposes and/or has been occupying
land and building/asset without authority;
13. Temporary Impact: Impact expected during implementation of the project in the form of earth spoil,
tremors and vibrations, etc. affecting land and structure
14. Tenant: A person who holds/occupies land-/structure of another person and (but for a special contract)
would be liable to pay rent for that land/structure. This arrangement includes the predecessor and successor-
in-interest of the tenant but does not include mortgage of the rights of a landowner or a person to whom
holding has been transferred; or an estate/holding has been let in farm for the recovery of an arrear of land
revenue; or of a sum recoverable as such an arrear or a person who takes from Government a lease of
unoccupied land for the purpose of subletting it.
15. Vulnerable Households/PAPs: Vulnerable households/PAPs are those defined in VCDF as being
vulnerable (see next section)
34
16. Cut-off date: In the cases of land acquisition affecting legal titleholders, the cut-off date willbe the date of
issuing the preliminary notice under the Land Acquisition Act 2034. In cases where people lack title, the
cutoff-date shall be the start date when the census survey was undertaken by the project authority
The exact value of compensation and replacement cost will be different for each sub-project activity at different
project locations and willbe based on the economic and social survey of the area of the activity and of the affected
persons. An indicative entitlement matrix for NUGIP project is furnished in thetable below.
35
Table 5-1: Entitlement Matrix applicable for the Project
Type of Loss Entitlement Unit Description of Entitlement Implementation procedures
Agricultural, Residential, Commercial, Pasture and Forestry Land
Loss of Private Titleholder • Provide compensation at full • A List of available public land in
land under any replacement cost or provide full each municipality is required.
form of tenure title to land of equal area and • A list of affected and entitled
productivity acceptable to owner persons and the area of land loss is
in the vicinity. required.
• If land is not available • Notice to vacate the land should
elsewhere, provide cash be served at least a month priorto
compensation at full acquisition date.
replacement cost based on • To ensure fair compensation,
current market rate. determination of rates will be
• In the case of farmland, established not more than one year
compensation for cultivation prior to property acquisition.
disruption allowance equal to • Land registration in the name of
one-year production. both landowner and spouse (in case
• In case of vulnerable groups, of land for land compensation)
give preference for land-for-land • In case of cash compensation,
compensation deposited into a joint account in
• Ensure that resettlement the name of both landowner and
assistance in addition to spouse.
compensation for land occupied
(land, other assets, employment)
at least restore their livelihoods
and standards of living to pre-
displacement levels.
• If remaining land becomes
unusable as a result of land
acquisition, option provided to
landowner to relinquish
unusable remaining portion of
land and receive similar benefits
to those losing all their land
parcel(s).
Loss of Landowners • Both the landlord & the tenant • Where a renter/leaseholder has a
Tenancy Land Tenants will be entitled for 50 percent of share cropping arrangement, the
land compensation amount each compensation payable should be
(As per 2058 B.S. amendment in apportioned according to the
Land Reform Act). arrangement.
• Non-registered • An advance prior notice will be
tenant/renter/lease holder does provided to landlord and tenant
not qualify for compensation for
land losses; however, they will
be entitled to compensation for
standing crops and any other
assets built by them. Any
upfront cost for the tenancy
agreement will be reimbursed.
Temporary Titleholder Tenants • Compensation for crop, land • Advance notice for crop
Loss of Private and landlord productivity and other property harvesting
Land (As both are the losses for the duration of
owner of equal (i.e. temporary occupation.
36
Type of Loss Entitlement Unit Description of Entitlement Implementation procedures
50 %) share, hence • Compensation for other • The owner/entitled party will sign
treated as private disturbances & damages caused a temporary occupation contract
land holder. to property. specifying:
• Project and the municipalities 1. Period of occupancy,
to ensure that persons other than 2. The terms and conditions for
the owner affected as a result of calculation of production
temporary acquisition are losses,
compensated for the temporary 3. The frequency of
period. compensation payment, and
• Land should be returned to the 4. Annual inflation adjustment
owner at the end of temporary 5. Land protection and
acquisition period, restored to its rehabilitation measures.
original condition or improved • Advance notice to vacate the land
as agreed with owner. before civil works start
• Compensation for any losses
crops/structures,
Land donations Voluntary donation • No compensation for the • Verify the requirements of the
is accepted only if : donated land, but entitled for donation
• AP is direct compensation of other assets • Carry out due diligence on the
project beneficiary such as minor structure, trees, owners and users of land donated:
and is fully crops, allowances, etc. identify rightful owner(s); any
consulted and • Transfer of land ownership competing claims of ownership or
informed about • Free of any transfer costs, use; structures and assets on the
rights and choices registration fees or charges land; any encumbrances on the
available to them; • Preferential employment in land.
• AP doesn’t fall project construction • Ensure appropriate consultation
below poverty line and disclosure
after land donation; • Establish informed consent of the
• No household person donating land
relocation is • Sign written commitment; local
involved. witness or third-party verification
• Landowners have to the commitment letter
agreed to donate; • Maintain a transparent record of
• AP is freely all consultations and agreements
willing to donate, reached.
is awarethat refusal
is an option (with
an agreement,
including a "no
coercion" verified
by a third party);
and
• Impact limited to
less than 10% of
landholding and
minor assets
• Land is free from
disputes regarding
ownership or
tenure
Trees and Crops
37
Type of Loss Entitlement Unit Description of Entitlement Implementation procedures
Loss of Trees & Owner of affected • Advance notice to harvest • Inventory of the tree and plant
Crops trees, fruits and crops species list
(Perennial/ crops • Net value of existing crops • List of owners, non-perennial
Non- perennial) where harvesting is not possible. crops and the area (if applicable) of
• The crops, which live, in short cultivation
time will be paid in accordance • The APs will get notice 2 months
with one-year output value. The in advance regarding crop
crops which have lived for harvesting. Crops grown after the
several years will be issue of the notice will not be
compensated at market value on compensated.
the basis of loss of future • The work schedule for
production, based on 5 years construction works will be adjusted
annual net production for fruit & considering the crop seasons for
fodder trees & 3 years annual avoiding crop damage.
net production for timber/ fuel • Crop/trees/bamboo market values
wood trees & other perennial will be determined by the CDCs in
crops consultation with District
agriculture and forestry office.
• Where a tenant/renter/lessee &
landowner have a share cropping
arrangement, the compensation
payable will be apportioned
according to the lease arrangement.
• Materials may be salvaged with
no deduction from compensation
Structures and Other basic facilities
Loss of Titleholder /non- • Compensation for full or • Replacement cost at market value
privately- titleholder partial loss of structures at full of structures will be determined by
owned replacement cost of materials the municipalities in consultation
structures and labor according to structure with the Malpot (land revenue
(residential, type, with no deduction for office), local experts and
commercial depreciation. compensation prices will be
and other • Resettlement assistance (rental, finalized with participation of AP
structure) dislocation and transportation representatives.
allowances) for residential and • Other structures that will be
commercial structures. considered for compensation if
• Households which lose affected under the project include:
residential structures and/or toilet, sheds, walls, fences, water
more than 10% of their land. mills, workshop etc.
Are entitled to receive additional • Materials may be salvaged with
training or benefits no deduction from compensation.
• Notice to vacate at least 90 days
prior to acquisition.
• Renter/ lessee holder will not be
entitled for compensation of
structures. However, if the
structures are made by them, they
will be entitled to compensation or
the nature of compensation will be
in accordance to the lessee
agreement
Community and Cultural Assets/ Facilities
38
Type of Loss Entitlement Unit Description of Entitlement Implementation procedures
Loss of land Local community • Restoration of affected • The land revenue office in the
and structures user’s group structures by the project leaving district and concerned Municipality
such facilities in a better will be requested to assist
condition than they were before; communities for land replacement
or cash compensation at full identifying the area nearby.
replacement cost.
• Restoration of access to
community resources.
• The land revenue office in the
district and concerned
Municipality will be requested
to assist communities for land
replacement identifying the area
nearby.
Loss of Forest user’s group • Mitigation measures should be • List of plant and tree species lost
community (FUG)/Other initiated to control erosion and an assessment for maintaining
forests and Concerned Groups caused by tree cutting, and to the samekind of vegetation.
other natural stabilize and rehabilitate the • Compensation for trees calculated
resources due slopes with suitable on the basis of type, age, and
to construction bioengineering works and productive value of affected trees
vegetation. in consultation with concerned
• Community forestland lost due forest office and FUG.
to construction activities should • To minimize damage, the
be replaced and reforested. concerned forest office will be
• Advance notice to harvest requested to take necessary action.
resources from affected
community forest areas.
• Compensation for trees to the
FUG.
Rehabilitation Assistance
Displacement Titleholders • Housing displacement • Displaced households will
of household Tenants allowance for loss of own receive a house rent allowance for
residential accommodation 6 months
• House rental allowance • Allowances will be paid at the
• Transportation allowance time of serving the notice to
vacate.
Loss of income AP from • One-time financial assistance Vulnerable groups as defined in the
Vulnerable groups in case of loss of income; or VCDF
• Skills training and income
generation support
• Preferential access to
employment opportunities in
project-related construction
works
• Priority to vulnerable group
and affected households for
skilled/unskilled employment.
Damages caused during Construction – temporary losses
Any kind of All categories of • Extreme care willbe taken by
private and entitled persons municipalities and their
public contractors to avoid damaging
properties public and private property.
39
Type of Loss Entitlement Unit Description of Entitlement Implementation procedures
• Where damages do occur to
public or private property as a
result of construction works, the
affected parties shall be
compensated immediately for
damages to crops and trees,
damaged land, structure and
infrastructure shall be restored
immediately to their former
conditions.
• Compensation at market price
for the loss of income, damaged
crops, trees etc.
The role of DSC in this process will include impact assessments, resettlement planning/management, supervision of
compensation disbursement, on-site safety, etc. It is proposed that E&S Department of municipality will review RAP-
ARAP Reports prepared by DSCs, disbursement of compensation to PAPs and to supervise contractors work to ensure
E&S Safeguard as per World Bank standard.
The manner in which stakeholder consultations are carried out may need to be altered to minimize the risk of COVID-
19 transmission. Chapter 8 Stakeholder Engagement provides some guidance for adapting stakeholder consultations
in the COVID-19 context.
In order to ensure that the affected persons have a channel to lodge any grievance on any issue concerned to land
acquisition and resettlement, a grievance redress procedure will be available at the various levels, which includes
relevant escalation points. A separate grievance redress mechanism will not be created for the project if there is
already an existing grievance mechanism at the local level. Where there is none existing at the local level, one will
be created. Unsatisfied grievant will also have recourse to judicial and administrative mechanism, and the World
Bank’s Grievance Redressal System (GRS).
40
6. VULNERABLE COMMUNITY DEVELOPMENT FRAMEWORK (VCDF)
The objective of the Vulnerable Community Development Framework (VCDF) is to guide the preparation of the
Vulnerable Community Development Plan (VCDP) for the sub projects that will have animpact on vulnerable
communities. The impact on vulnerable communities and the need of a VCDP will be identified through a social
screening process.
The VCDF serves as a practical tool that will help ensure that the project fully respects the dignity, human rights,
economies and cultures of vulnerable communities (VCs), including the Indigenous Peoples. The framework also
aims to ensure that the project benefits are accessible to all vulnerable communities living in subproject areas.
Additionally, it details agreed principles, policies, guidelines and procedures to be integrated into project
implementation and will be in compliance with the applicable GoN’s laws relating to indigenous peoples and other
marginalized groups, and the World Bank’s safeguard policies and objectives relating to Indigenous Peoples.
While NUGIP will supportinfrastructure that will benefit all groups, due to social conditions of vulnerable
communities (VCs), their representation, participation and access to services could be limited, hence there is a
requirement foradditional support from the project. Specifically, the project will provideextra consideration to
Adivasi-Janajati and other vulnerable communities that will minimize the magnitude of impacts and provide support
to ensure benefits; and will also ensure their participation in the project cycles. Thus, this Vulnerable Community
Development Planning Framework (VCDF) has been designed to ensure that vulnerable groups, including Indigenous
Peoples, are regarded as special interest groups, and that impacts on their livelihoods are minimized and addressed in
a sensitive manner.
As per the Article 42 of GoN’s Constitutional Right to Social Justice(1-5),socially backward women, Dalits,
indigenous people, Madhesi, Tharu, Muslim, people with disability, farmers, laborers, people from backward region
could be termed as vulnerable and need special protection and provision for empowerment. Therefore, vulnerable
groups can be broadly be categorized as
1. Indigenous Peoples
2. Poorest of the poor, irrespective of class, caste, gender and ethnicity
3. Female headed poor households
4. Marginal land holders
5. Elderly-headed (Jestha Nagarik) or child-headed households
6. Household members with disability
7. All Dalit and ethnic minorities/ indigenous groups as categorized by GoN as being vulnerable
Given the multi-ethnic, multi-lingual, multi-religious and multi-cultural nature of the social system in the project
specific municipalities, it is difficult to clearly separate the Indigenous Peoples (IPs) from other vulnerable groups.
The IPs and disadvantaged groups, though belonging to different ethnicity and/or social group, share commonalities
in terms of their economic and livelihood activities. Further, gender, caste and ethnicity have been officially
acknowledged as primary factors that determine a group's vulnerability and marginal status owing to: (i) limited
access to livelihood, assets and services; (ii) low levels of social inclusion and empowerment; (iii) restricted legal
inclusion and representation in decision-making positions; and (iv) economic marginalization. Thus, this framework
has been prepared in a manner that would ensure that the principles of World Bank’s OP 4.10 on Indigenous People
are followed and that the different categories of vulnerable groups, including indigenous people, are able to benefit
equally from the project while the adverse impacts are minimized.
41
6.2. Baseline of Vulnerable Groups in Nepal
The advanced group is not taken into consideration while describing the vulnerable groups. In Nepal, census survey
was conducted in 2011 and the data so collected is disaggregated only on the basis of caste and gender. Therefore, it
is very difficult to estimate number of people under other vulnerable group.
Table 6-2: Population of Indigenous People in project specific districts
Name of the District Population of IP in the Total Population of the Percentage distribution
district district of IPs in the districts
Baglung 84656 268,613 31.51597
Dhankuta 84393 163,412 51.64431
Jhapa 309308 812,650 38.06165
Kaski 152104 492,098 30.90929
Morang 333528 965,370 34.54924
Palpa 145167 261,180 55.58121
Parsa 78230 601,017 13.01627
Rupandehi 207444 880,196 23.56793
42
Name of the District Population of IP in the Total Population of the Percentage distribution
district district of IPs in the districts
Saptari 128249 639,284 20.06135
Sunsari 237064 763,487 31.05017
Syangja 91550 289,148 31.66199
Tanahu 144310 323,288 44.63822
Terhathum 52186 101,577 51.3758
Udayapur 162731 317,532 51.24869
Grand Total 2210920 6,878,852 36.34872
The data above depicts that close to 37% of the population in the project specific districts is constituted by indigenous
peoples.
Madhesis
Madhesi by definition means people who inhabit the flat southern region of Nepal (the Terai plains). All the NUGIP
municipalities in the eastern cluster, except Dhankuta have presence of madhesi groups. In these municipalities,
theTeraidalits, terai caste groups, dumjhangar, bantar, muslims, are the most socially backward groups. The
composition of these caste groupsis shown in the graph below:
Data on other vulnerable groups is not available in census data as the survey did not capture these dimensions.
If social screening indicates presence of Indigenous Peoples in the subproject area, a social assessment will be carried
out. The assessment will comprise ofsocio-economic survey, focused group discussion and social mapping etc., in
the subproject area to identify the vulnerable groups and determine the magnitude of impact andascertain losses such
as temporary impacts, severity of impacts etc. Information will be collected from separate group meetings withthe
different groups of vulnerable communities. A free, prior and informed consultation will be carried with indigenous
43
peoples to ensure that there is broad community support for the project. The significance of impacts of the subprojects
on vulnerable community will be determined by assessing the magnitude of impact in terms of:
• Socioeconomic status
• Cultural and communal integrity
• Health, education, livelihood, and social security status and on the level of vulnerability of the affected
person/group/community
• Inclusion/exclusion dynamics
• Customary rights of use and access to land and natural resources
VCDP will be prepared based on the findings from social assessment and consultations with the vulnerable groups,
including indigenous people. The VCDP will include mitigation measures of potential adverse impacts through
revision of subproject design and development assistance to maximize subproject benefits. The subproject willensure
that the rights of vulnerable groups, including indigenous people, will not be violated and that if land acquisition or
structural losses involve vulnerable communities then they will be compensated for the use of any part of their land
or property in a manner that is socially and culturally acceptable to them. The subprojects will follow the process and
procedures as well as compensation measures prescribed in RPF.
4 Baseline data not disaggregated Public consultation Social Assessment/ DPR and ESIA
and thus assessment of needs, during baseline Planning Stage consultants
benefits and impacts of the project survey
inadequate
44
Arrangement for various concerned
alternative route to authorities
provide access to
the resource
Arrangement for
alternative access
to the same
resource
7 Persistent discrimination and ill- Engaging VCs in Preconstruction,
practices against VCs various project Construction &
development Operation stage
Lack of proper attention to activities at various
measures to empower vulnerable stages of project
groups
Engaging
representatives of
VCs in decision-
making forums
relating to project
design,
implementation
and monitoring
45
13 Project features inattentive to the Adopt universal Preconstruction,
needs of people with disability access as a major Construction Phase
design principle
Ensure disability-
friendly design
consideration in the
project, to the
extent possible
14 Inadequate representation of Include women Preconstruction
women in opportunities provided when targeting
under LIPW beneficiaries under
the LIPW
Once the project-targeted vulnerable groups have been identified, ‘free, prior, and informed consultations’ will be
held with vulnerable groups, including IPs. Concerns raised during the consultations will be documented and
incorporated in the overall project design, the project implementation plan and the individual vulnerable community
development plan.
During the preparation of VCDP, consultations will also be held with relevant departments and district level offices
of the government, project-affected groups, community-based organizations, women’s groups, indigenous peoples’
organizations, etc., and also at local levels about the project’s environmental and social aspects. To ensure meaningful
consultations, the concerned groups will be provided with the draft documents in a timely manner prior to consultation
and in a form and language that is understandable and accessible to the groups to be consulted (See SECF of the
Environment and Social Management Framework (ESMF) for summary discussions of the consultations).
Once the VCDPs are prepared they will be disclosed through municipalities’ website. The VCDP will also be made
available at both central/sub-project level project co-ordination offices and municipalities and respective ward offices.
Further, summary of VCDPs in Nepali language will be made available to the concerned communities, local level
NGOs and the others concerned at the subproject sites.
A detailed engagement and consultation process is outlined in the SECF section of the ESMF which is also applicable
to vulnerable communities.
The manner in which stakeholder consultations are carried out may need to be altered to minimize the risk of COVID-
19 transmission. Chapter 8 Stakeholder Engagement provides some guidance to adapting stakeholder consultations
in the COVID-19 context.
46
6.6. Institutional Responsibilities
As mentioned above, the necessity for a VCDP will be determined based on social assessment and stakeholder
consultations which will be conducted by DSCs and municipal officers. If it is found that VCDP is necessary for any
sub-project, the DSC will develop VCDP and get it approved through municipality and PCO. The VCDP will be
implementedthroughout the initial design and planning, construction, post construction and operational phase of
project to ensure that concerns pertaining to vulnerable community for the subproject/s are well addressed and
complied with the requirements mentioned in ESMF. The safeguards staff (E&S) within Municipalities, DSCs and
PCO will monitor the project site in the municipalities, prepare quarterly progress reports and submit them to PCO.
The PCO will prepare semi-annual monitoring reports and submit to the World Bank. The reports will cover the
implementation of VCDP, among others, focusing on compliance and any corrective actions that may be needed.
Public consultations will be conducted as necessary during the preconstruction, construction, operation phases of the
subprojects. The role of DSC includes preparing VCDP for subproject/s, if applicable while the E&S departments of
the respective municipalities will review VCDP prepared by DSCs, disbursement of compensation to PAPs, and to
supervise contractors work to ensure effective implementation of VCDP as per the ESMF.
47
7. SEA/SH RISK MITIGATION ACTION PLAN
7.1. Need and Purpose
Nepal ranks 118 out of 160 countries on the Gender Inequality Index 8. In relation to that, most women face various
kinds of violence since the time they are conceived to old age. Violence against women are gender-based where there
is unequal distribution of power dynamic between men and women.
The Nepal Demographic and Health Survey (NDHS) 2016 records 23 percent women experiencing physical violence
with significant differences across various social groups. The experience of such violence was highest among Madhesi
Dalit women at 44 percent, Muslims at 38 percent while only 9 percent of hill Brahminsreported having experienced
it. By province, women’s experience of physical violence varies from a low of 12 percent in Province 4 to a high of
34 percent in Province 2. Besides physical violence, about 12 percent of women in Nepal also reported having
experienced emotional violence with 17 percent to 19 percent Madhesi Brahman Chhetri, hill Dalit and Newar
women, respectively experiencing it. Seven percent of women aged 15-49 reported having experienced sexual
violence. Divorced, separated, or widowed women are much more likely to have experienced sexual violence (20%)
than currently married women (8%) and never married women (2%). Likewise, women with only primary or no
education are more vulnerable to sexual violence than educated women.
The current status of gender inequality and gender-based violence in Nepal reveals the need to mainstream gender
sensitivity and GBV, and more specifically, sexual exploitation and abuse, and sexual harassment (SEA/SH) risk
mitigation measures at all organization levels and all phases of project cycle. In Nepal, SEA/SH is prevalent due to
unequal gender relations and discrimination towards women in both public and private sphere. It has direct
implications on the reproductive health status of women and physical, emotional, and mental health of their children.
The purpose of this action plan is to identify the issues, stakeholders, possible service providers and assess their
capacity and document the legal and institutional mechanisms that aid in accessing grievance redressal related to
gender-based violence. The action plan focuses on sensitizing the communities and other stakeholders
andstrengthening the institutional capacities to respond to the risks of such violence. In preparing the plan, a survivor-
centric approach is followed - all through, victimssurvivors’ care and provision for access to different referral
mechanisms, are considered key aspects of this plan.
One of the key aims of the project is to address critical gaps in core municipal services and infrastructure. For Year
1, four sub-project areas have been identified namely, in Pokhara, Damak, Urlabari and Birtamod, all of which except
for Pokhara, fall in Terai belt. All four subprojects involve upgradingof the road within the ROW (Right of Way).
Out of the total human resources, approximately two thirds are unskilled labors and one third skilled labors. To the
extent possible, laborers will be from the host community, and if not, from other parts of Nepal or neighboring
countriesincluding India. There are cases of domestic violence in the sub-projects and at least 80% of women do not
report cases of domestic violence, and beating is considered a common practice. In Birtamod, the practice of child
marriage is prevalent within the Dhimal and Satar community while in Pokhara teenage marriage has become a
common practice. With Pokhara being a tourist spot, risk of child labour is also prevalent as well a commercial sex
work leading to high risks of sexually transmitted disease. Trafficking of girls is high in Jhapa as they share border
with India.
Based on the SEA/SH Risk Assessment checklist and assessment carried out for the project by the World Bank, the
Project’s SEA/SH risks are assessed to be “Low”. Accordingly, this action plan has addressed “Table – 1:
Recommended actions to address SEA/SH Risks in IPF Projects” as per the “Good Practice Note” published by the
World Bank in September 2018.
This action plan is intended for and is applicable to Project implementing agencies, including contractors, and cover
the Project’s footprint and adjoining communities.
The Gender Equality Act in 2006, brought tangible legal changes to sexual violence against women. A major
achievement of this act is the provision that an offender convicted for rape must compensate the victim for mental
and physical damage. Also important is the 2009 Domestic Violence (Crime and Punishment) Act, which recognized
for the first time that domestic violence is a crime punishable by law. However, while the act recognizes domestic
violence as a crime, it contains provisions for negotiations through police offices, which seems contradictory. Also
the National Civil Code Act 2017 states not to commit any inhumane or degrading treatment or domestic violence
and the Criminal Code Act 2017 states that violence against women in form of accusing of witchcraft or practicing
of ‘chhaupadi’ tradition9 and sexual violence is treated as criminal offense. Although there are some laws and
provisions against domestic violence, many victims are left without support mainly because of the poor mechanism
to deliver support services as well as a lack of awareness among people regarding such provisions.
The Human Trafficking Act (2007) extended the definition of trafficking to include the offense of transportation for
the purpose of trafficking. With this extended definition and other support measures, the new Act helps to control
human trafficking and affords needed support and care for victims.
Apart from these laws and policies, the Supreme Court has also issued orders at different times prohibiting different
malpractices that contribute to GBV. For example, the Supreme Court issued a directive order that required the
government to declare Chhaupadi as a malpractice based on superstitious beliefs. Similarly, the court issued a
directive order requiring the government to launch a massive awareness campaign to stop the exploitation of women
accused of practicing witchcraft.
Further, the government's National Safe Motherhood Plan (2002-2017) recognizes GBV as an important issue for
women's health. The Nepal Health Sector Implementation Plan 2010-2015 has outlined GBV as an integral
component of health care provision. Protocols on the management of GBV, including sexual abuse, have been
developed and are now operational. These protocols will study the feasibility of implementing a screening and support
program at Maternity Hospital, Kathmandu for GBV.
7.3. Recommended Actions to Adddress SEA/SH Risks
9Chhaupadiis a tradition associated with the menstrual taboo, in the western part of Nepal which prohibits Hindu
women and girls from participating in normal family activities while menstruating, as they are considered "impure"
49
Reflect SEA/SH SEA/SH Action Address how SEA/SH-related During PCO/PIU
risks, and measures plan included in the costs will be reflectedin the preparatio
to address them, in ESMP contract, including the n of ESMP
Project ESMP and procurement documents, to
Contractor ESMP Procurement for mitigate risks.
including the costs. SEA/SH related
activities and costs Clearly define the
outlined in the SEA/SHrequirements and
contract. expectations in a note to bidders.
Develop # of awareness and TOR developed for community During PCO/PIU10
stakeholder consultations held awareness raising activities preparatio
engagement plan (specialized service n of ESMP
Inform providers/contractors/NGOs
communities in identified and hired under Prior to
project areas of contract) and awareness and contractor
SEA/SH risks and consultations carried out. mobilizati
options for on
response
Formulate and CoC developed, Develop CoC and include it in all Prior to PCO/PIU/Cont
adopt code of included in all contracts and also in operations contractor ractor
conduct including contracts, and staff, manual and provide training to all mobilizati
sections on safety consultants, on
of women and girls contractors trained.
Project Implementation
Codes of Conduct # of people oriented Ensure requirements in CoCs are Contractor,
signed and and trained on CoC. clearly understood by those Consultant,
understood signing it. PIU.
# of people who
signed CoCs Have CoCs signed by all those
with a physical presence at the
project site.
51
8. STAKEHOLDER ENGAGEMENT AND CONSULTATION FRAMEWORK
A good communication strategy among the institution and community needs to be established to ensure that the
project is implemented in sustainable manner. There are two key objectives of stakeholder engagement and
consultation framework prepared for the project. First, it is to keep all stakeholders informed of the project activities,
the potential beneficial and adverse impacts. Second, it is to ensure that stakeholders actively participate in all levels
of the project cycles, are able to share local knowledge, mitigation plans are able to minimize the potential negative
impacts of the project, and the relevant stakeholders are well-trained and equipped to take over the responsibilities of
operation and management once the project phases out. These will ultimately contribute towards narrowing down the
gaps between the project officials and beneficiaries and help create a conduciveenvironment to mitigate the adverse
social and environmental issues through optimal cooperation from the project beneficiaries themselves. Stakeholder
engagement strategy outlines engagement through the project development phases and recommends a set of
stakeholders’ engagement activities to be carried out throughout the project development cycle. The SECF reiterates
elements of the strategy that is relevant to social and environmental issues in general and the ESMF in particular. In
addition, it also outlines the disclosure requirements of documents already prepared and planned under the project. It
should be noted that consultations on social and environmental issues carried out during implementation of
subprojects will be done in an inclusive manner, including the inclusion of vulnerable social groups (such as poor
household, caste, and persons with disabilities, among others) and women. Each municipality will develop a citizen
engagement strategy based on the principles laid out in the Stakeholder Engagement and Consultation Framework.
This chapter should be read in the current COVID-19 context. Social restrictions and other measures to prevent the
further transmission of COVID-19 may impact on the ability to follow guidance on carrying stakeholder engagements
provided in this chapter. Section 8.5 provides suggestions for adapting stakeholder engagement to the COVID-19
context.
A three-layered decision-making procedure will befollowed to identify the need for infrastructural sub-project at
municipality level. The first level is the Tole Coordination committee, which will be formed with theparticipation of
representatives of households of the respective Toles. The next level is Ward Level followed by municipality. At the
Tole level, meetingswill beorganized on regular interval to discuss the needs of the tole, including the infrastructure
need of the area. The requirements of particular toles are then forwarded to next level i.e. ward level. The ward office
will review the demand from various toles, screen the proposed interventionsand then forward their recommendation
further to municipality level for assessment and budgetary allocation. After receiving the demands from various wards
covering various toles, the municipality will prioritize the projects considering the available fund. In case a
municipality is not able to cater to the need of any particular area (Ward/tole) due to unavailability of funds, the said
project will automatically become apriority for next year, and this decision will be shared with all the concerned
stakeholders. In all municipalities, the citizens will be engaged in the decision-making process through Tole Meetings
for identification of project (Refer to Appendix B).
52
Project/Need
Municipality prioritization and
budgetary allocation
Through the formal and informal consultation, stakeholder mapping willbe done, and their interests concerning the
various project activities willbe identified. The indicative types of stakeholders are furnished in Table 8-1.
53
District Coordination
Committee
Municipality Offices Primary Project selection,
Ward offices selection of beneficiary
Tole Development and their needs
Committees
Sub-project Level Ward Representative Primary Impact of the project and
Associations (Business) & possible measures for
user groups ( road, water, mitigating them
irrigation, forest)
Women/ Mothers groups
Shopkeepers & vendors
Farmers group
Households
Extended users of the Secondary Projection of the usage of
project the project infrastructure
The Project Implementation Manual (PIM) for NUGIP provides in detail the steps for identifying and selecting sub-
projects for investment. The municipalities will establish mechanisms to ensure that stakeholders are enagaged at
each step of the process. Some examples of mechanisms to engage with stakeholders are outlined below:
At step 1: Identification and selection of investment sub-projects, two processes will be followed while identifying
investment sub-projects:
• Conducting a comprehensive needs assessment and gap analysis for core municipal
services/infrastructure; and
• Conducting consultations with elected representatives, ULG Thematic Sections, civil society
organizations and community groups, to validate the gap analysis and to identify the local municipal
service delivery needs and priorities.
At step 2: Technical prioritization of investment sub-projects, based on the pre-appraisal of all selected investment
sub-projects conducted under Step 1, the ULG Planning Section will bring together ward representatives, municipal
officials, elected representatives to share and discuss the prioritized sub-projects that will be submitted to the
Municipal Executive.
At step 3: Executive prioritization of investment sub-projects, the Municipal Executive decides on a prioritized and
sequenced list of potential investment sub-projects which will be presented to and discussed with the Municipal
Investment Forum, the outomces of which will be presented to stakeholders
At step 4, the Municipal Executive presents its sub-project recommendations to a consultative forum, the Municipal
Investment Forum and seeks feedback and comments from citizens and local stakeholders. It is the Step during which
citizens and local stakeholders are informed of the Municipal Executive’s recommendations with respect to the
investment sub-projects to be financed out of the ULG’s UDG allocations.
54
• Representatives of 3-4 community-based groups in the ULG jurisdiction. Such groups include women’s
associations, youth organizations, pensioner associations, etc.;
• Representatives of local economic actors (e.g. Chamber of Commerce, trades unions, transport associations,
cooperatives, etc.);
• Representatives of local NGOs;
• Representatives of the local media etc;
The list of MIF members will be agreed upon and drawn up by the Municipal Executive; and posted on the ULG
notice board. MIF will include for example women and other vulnerable community representatives. Members will
be formally invited to the MIF at least one week before the meeting. Invited MIF members willbe informed of the
meeting agenda in advance.
By the end of the MIF session, the Municipal Executive willbe able to make a final decision on the prioritization of
its sub-project proposals for UDG funding. Minutes of the MIF meeting will be kept and made available to the public.
At step 5 – Sequencing of investment sub-project implementation over three (or four) years, the Planning Section will
draft a three-year UDG investment plan. The 3-year investment plan will then be translated into annual budget
proposals, to be confirmed by the Municipal Executive, included in each year’s annual budget proposals and then
submitted to the Municipal Assembly for approval and then will be publicly disclosed. These subprojects will then
be supported under NUGIP. For the subprojects that are selected, social and environmental screening, assessments
and preparation of safeguards management plans will be developed.
The outcome of consultations will be incorporated as appropriate in the designs and mitigation plans. As part of such
consultations, the draft safeguard management plans will also be presented and explained to the people on the content
and process of the implementation of the plans. Consultations with Project Affected Persons and their profiling are
mandatory as per the requirements of ESIA and preparation of RAP, ESMP, VCDP, etc. Consultations with respect
to cultural aspects are to be carried out as part of the Social Impact Assessments for all alternatives and the selected
alternative subproject option.
During ESIA study, two rounds of consultation meetings will be conducted, including consultations for obtaining the
informed views of the affected people and local Non-governmental Organizations (NGOs).
In all subprojects involving resettlement, and prior to the preparation of Resettlement Action Plans, the PAPs will be
informed of the project objectives, likely impacts and essential provisions of Resettlement Policy through the
following activities:
• Awareness campaigns using local Cable TV channel, print media such as posters or information leaflets;
• Holding public information meetings in various project site locations and affected areas;
• Arranging interactive sessions with the PAPs & their representative stakeholder groups;
• Formation of focus groups involving key stakeholders, like local leaders, women, vulnerable group members
etc.; these could also serve as local community monitoring groups
55
For disseminating information pertaining to the subproject, work schedule and the procedures involved; finalization
of project components with identification of impacts, entitled persons, mitigation measures; and Grievance Redress
Mechanisms to be adopted.
In order to discuss and seek opinions and suggestions, all the PAPs and/or their representativeswill be formally invited
to participate in various meetings regarding resettlement issue as convened by the municipality. During such
consultations, draft RAPs will be presented and its contents, processes, eligible entitlements, institutional roles and
responsibilities, etc., will be shared publicly. Once the individual safeguards management plans have been finalized,
they will be shared with the PCO and the World Bank for review and clearance.
Accordingly, in collaboration with different local authority, NGOs and other groups, the project willdisclose all the
relevant information to PAPs and other relevant stakeholders during the different stages of project cycle. Agencies
working for environmental and social aspects willalso be informed at both local and national level about the ongoing
and planed activities, to identify jointly appropriate protective or corrective measures. Subprojects will adopt the
following approaches to make information accessible to all the concerned stakeholders throughout the project cycle.
Project documents will be disclosed in the Nepali language, and if relevant in the local languages.
• Mass Media: Local media like newspaper, radio and TV will be used to broadcast any information
regarding the project.
• Meeting/Workshops: Meetings and workshops will be held to disseminate the information.
•Distribution of project document: Project related information materials in Nepali version will be
distributed prior to each construction work to local officials, PAPs and other concerned offices like
Municipality, Ward, Tole Committee etc. Such information will among othersinclude project description,
project benefits and impacts, entitlements, implementation arrangements, entitlement frameworks as well as
various periodic information sheets on compensation entitlements, project time frames etc.
An information centre will be established during implementation stage at the municipality level to disseminate all the
documents related to the project activities. Based on the policy on public information disclosure, PCO and
Municipality will also disclosethe information through its website.
57
o If smaller meetings are permitted, conduct meetings in small-group sessions, ensuring that meeting sizes
adhere to local regulations, and for example, space members at least 1.5 metres
o Project team members should express their understandings on social behaviour and good hygiene practices,
and that any consultations are preceded with the procedure for articulating such hygiene practices
• Undertake consultation meetings virtually where feasible: The project should consider the following for those
consultations which cannot be postponed, and where all participants have proper ICT access and can be notified
in advance regarding timing and format of meetings. Some considerations:
o Where all participants have proper ICT access, deploy online meeting facilities, where large meetings,
workshops and consultations are essential, such Webex, Skype and Zoom. In the case of low ICT access,
audio meeting means can also be effective used (including Viber and Whatsapp)
o Vulnerabilities of participants need to be considered to ensure that vulnerable participants are not
disadvantaged by being unable to connect.
o Where direct consultation and engagement with beneficiaries is required, such for completion of
resettlement activities or indigenous peoples plans, identify direct channels for communication with the
affected household via a combination of email messages, text messages, dedicated phone lines
• Review the range of digital platforms which can be drawn upon for completing CE requirements such as
data collection: In-person data collection methods can be substituted by remote data collection methods, which
take into account limitations related to ICT access and literacy of community members. SMS surveys are a
common way to collect community-level data required to complete safeguard document requirements.
Customized SMS-based surveys can gather data from remote villages and traditionally hard-to-reach places as it
requires only access to mobile numbers of local users, without dependency on data plans or internet access. Local
partners and social mobilizers, as discussed above, can assist in obtaining mobile numbers.
58
9. GRIEVANCE REDRESS MECHANISM
An accessible and responsive complaint management process is an important part of any stakeholder engagement
strategy. A Grievance Redress Mechanism will accessible wherein all project stakeholders will be provided with a
forum to lodge complaints regarding any aspect of the land acquisition, compensation, resettlement requirements,
hygiene, pollution, safety and any other project-related issues. The affected persons will have access to all levels of
grievance redress procedures.
The project should drawn upon mechanisms established by local municipalities for receiving and addressing
grievances, to help strengthen these local systems and to support and build the capacity of local governments in
receiving and addressing grievances. As part of developing sub-project ESIAs, existing mechanisms for receiving
and addressing grievances will be identified and assessed. Grievants will first raise their grievances with the ward-
level mediation centre before going to the judicial committee. A grievance officer assigned to the municipality level
will also have the proper knowledge on the issues. The GRM mechanism as well as its procedures will also be detailed
in the Project Implementation Manual (PIM). The decision as to whether the case is addressed by the judicial
committee, or by the ward level GRM, is decided by the municipality Grievance Officer. The Grievance Officer will
keep all detailed documentation regarding the grievance with proper verification to answer how and when the
grievance was reported and addressed.
The complainant will follow up based that unique number with Operator at PCO-Kathmandu. All complaints will be
responded to within two weeks at any level. In case a response is not received fromthe first level within two weeks,
the complaint will be escalated to next level and the complainant will be notified accordingly. If a complaint remains
11As per Article 221 (Subsection 1) of the Constitution of Nepal 2015, the municipalities are required to establish a separate act
or regulation which will outline the roles and responsibilities of the judicial committee.
59
unaddressed at 1st and 2nd GRC levels, within maximum 30 days after registering the compliant, it will be elevated to
3rd level of GRC at PCO level. GRC-PCO within 7 days of time willinstruct the concerned GRC at Municipality level
to arrange for a hearing within maximum 5 days of time. Effort will be given by all level of GRCs to conduct hearing
and resolve the concern at their level up to the satisfaction of complainant within the stipulated timeframe. After
conducting hearing at any level of GRC, the decision should be communicated to the complainant within maximum
30 daysof time in writing.
All local contact information and options for complaint submission willbe available on site, on Toles, Wards,
Municipalities, PCO on information boards and municipality websites. A half yearly report on grievance redress by
the subproject project willbe prepared and sent to Municipalities’GRCs by Wards’ GRCs and ultimately to GRC of
PCO. The PCO will forward the same to World Bank.
Online Grievance
• E-mail
• Toll Free No
PCO
3rd Level GRC
GRM 7 Days Max.
Register/Operator
(at PCO)
5 Days Max.
Municipality:
NyayikSamiti
2nd Level GRC 15 Days
Max.
Hearing of
Grievance
Wards
1st Level GRC 15 Days
Max.
30 Days
Max.
Offline
Grievance
from Tole or Verdict by GRC
Subproject
Level
GRC will give its decision/verdict within 30 days after hearing the issues/concerns of the aggrieved person. The final
verdict of the GRC will be given by the Head of GRC in consultation with other members of the GRCs and will be
binding to all other members.
60
An indicative list of grievance, which will be addressed under the project are furnished below-
i. Rehabilitation &resettlement and compensation issue
ii. Loss of livelihood
iii. Access to resource /utility/facility
iv. Ambient air and noise quality
v. Impact on water quality/resource
vi. Grievance from vulnerable community
vii. Gender related issues
viii. Labor-related matters
ix. Safety risksrelated to the project
• The grievance mechanisms used should be reviewed to check that they are currently functioning and capable
of receiving grievances, given potentially restrictions on being able to access ward offices or project sites to
raise grievances
• Channels for receiving grievances should be reviewed to maximise ways to submit and response to grievances.
For example, whilst the project may envisage communities going to ward offices to submit grievances, the
project should consider establishing a phone line for people to call in concerns. Where feasible, ICT-related
options such as SMS or via email should be implemented and communicated
• Members assigned to receive and respond to or escalate grievances should be taught on how to respond to
grievances related to COVID-19
12
http://www.worldbank.org/en/projects-operations/products-and-services/grievance-redress-service#3
61
10. INSTITUTIONAL ARRANGEMENT FOR ESMP IMPLEMENTATION
10.1. Institutional Assessment for E&S Sections/Departments
10.1.1. Existing Institutional Capacity
In Nepal, the municipalities usually have a separate social development sectionand a separate environmental section.
The municipalities like Birtamod, Damak, Sundarharaicha, Mechinagar, Itahari, Rajbiraj, Triyuga, Dhankuta,
PokharaLekhnath, Putalibazar, Tansen, Tilottama have environmental &social development department. Whereas
Vyas has only Social Development Department. Urlabari, Baglung, Ramgram municipalities do not have
Environmental and Social Development Department. To ensure that the investment sub-projects are efficiently
implemented, delivered on time, and completed in accordance with environmental and social safeguards
requirements, technical assistance will be provided by design and supervision consultant (DSC) to the concerned
municipalities. DSC will deploy engineering, procurement, E&S safeguards and other technical specialists to work
closely with ULG municipal engineers and other technical staff to design and supervise the implementation of sub-
projects in a socially and environmentally sustainable manner.
62
and Western) of ULGs. One UDST (Eastern Cluster) will be based in Biratnagar and the second UDST (Western
Cluster) will be based in Pokhara.
Each UDST will consist of a team of full-time professionals to provide TA inputs that are aimed at strengthening the
overall ULG management capabilities. These inputs will be in areas such as urban and investment planning, citizen
engagement and gender inclusion, procurement, financial management, budgeting and budget execution, asset
management (O&M, etc.), E&S safeguards and other issues. UDST members will provide regular mentoring,
facilitation and on-the-job support to the ULGs within their respective clusters. UDSTs, however, will be responsible
for coordinating, quality assuring and backstopping such formal ICD processes and for providing advice on the
substance of training sessions, workshops and the like.
Apart from the regular mentoring and on-the-job support functions, each UDST will be responsible for drawing up
an annual TA plan and budget for training and other formal activities in its respective cluster. Annual plans willbe
based on needs identified by each ULG; such plans would ensure that training and other TA activities are efficiently
organized. These annual plans and budgets will be submitted to and discussed with the PCO by each UDST. Once
agreed, the PCO will allocate funds and then procure trainers/consultants. Implementation of annual cluster plans for
TA activities would be coordinated and overseen by the PCO and the UDSTs (for their respective cluster).
At subproject level, the contractor will be responsible for ESMP implementation. Each municipality will need
Environmental and Social Development (ESD) expert to review IEE/ESIA-ESMP, RAP-ARAP, etc. The E&Ssocial
safeguard specialists of DSCs will regularly visit both cluster municipalities and work closely with its technical staff
to ensure project implementation in accordance to World Bank’s safeguard standards. The ESD will bepart of PIU.
The DSCs provide municipalities’ technical staff with on-the-job training and mentoring. The role of DSC will also
include ensuring compliance of pertaining laws, policies, regulation for all sub projects, coordination and liaising
with government stakeholders as well as the World Bank with respect to various E&S issues. The PCO will have
overall responsibility to ensure compliance withpertaining laws, policies, regulation for all sub projects, and
development of sub-projects in sustainable way and allocation of fund for institutional capacity development. The
reporting of the PMST on the monitoring and evaluation on the project’s safeguard performance to WB is done
internally by the PCO and externally by the WB experts. The capacity of Municipalities isattached in the
Annex.
Project Coordinating
Office (PCO-e.g.
DUDBC)
Project Mgmt
Support Team (PMST)
Design & Supervision Municipalities (in East &
Consultancy (DSC) West Clusters)
Municipals Project
Implementation Unit
(PIU-e.g ESD)
.
64
Appendix A: Land use map of 17 Municipalities
Land use map of 17 Municipalities showing various physiographic features and drainage patterns
65
A.3. Itahari & Sundarharaicha
A.4. Rajbiraj
66
A.5. Triyuga
A.6. Dhankuta
67
A.7. Pokhara Lekhnath
A.8. Byas
68
A.9. Putalibazar
A.10. Baglung
69
A.11. Shuklagandaki
A.12. Tansen
70
A.13. Ramgram
A.14. Tilottama
71
72
Appendix B: Consultation with municipalities
1. Birtamod
73
74
75
Pictures from stakeholder consultations
76
2. Damak
77
Pictures from the stakeholder consultations
78
3. Urlabari
79
80
Pictures from stakeholder consultations
81
4. SundarHaraicha
82
5. Mechinagar
83
6. Itahari
84
Pictures from the stakeholder consultations
85
7. Rajbiraj
86
Pictures from the stakeholder consultation
87
8. Triyuga
88
Pictures from stakeholder consultation
89
Attendance sheet for the stakeholder consultations
90
9. PokharaLeknath
91
92
Pictures from the stakeholder consultation
93
10. Vyas
94
Pictures from the consultation
95
Putalibazar
96
97
Pictures from the stakeholder consultation
98
11. Baglung
99
100
Pictures from the stakeholder consultations
101
102
12. Shuklagandaki
103
13. Tansen
104
Pictures from the stakeholder consultation
105
14. Ramgram
106
Pictures from stakeholder consultation
15. Tilottama
107
Attendance sheet for the stakeholder consultation
108
109
Pictures from the stakeholder consultation
110
Appendix C: Templates for Environmental & Social Screening Checklist /
Environment and Social Impact Assessment (ESIA) / Environment and Social
Management Plan (ESMP)
Project Details
Environmental Aspects
Checklist for Environmental Screening
S. Can’t
Particulars Yes No Remarks
No Say
1. Is the site vulnerable to major natural or induced hazards
such as: Landslides, Flooding, Storm surge, Severe wind
damage, Earthquakes, Fire, Explosion, Other (specify)
2. Is the project area adjacent to or within any of thefollowing
environmentally sensitive areas?
• Cultural heritage site (historical, religious,
traditional, or cultural significance)
• Protected Area (National Parks, Wildlife Reserve,
Hunting Reserve, Conservation Areas, and Buffer
Zones etc.)
• Wetland/Ramsar Site/Simsar
• Forest
• Special area for protecting biodiversity/interest
• Breeding/nesting ground of wildlife/occurrence of
migratory species
• Migration route/Wildlife corridor
• Any site of national or international importance
3. Likely impact on trees (including Timber & fruit
bearing)and vegetation cover
4. Possibility of degradation of land and ecosystems of
surrounding?
5. Is the project area densely populated?
6. Heavy with development activities/big industries nearby &
type?
111
S. Can’t
Particulars Yes No Remarks
No Say
7. Alteration of surface water hydrology of waterways due to
the project resulting in increased sediment in streams
affected by increased soil erosion at construction site?
8. Chance of deterioration of surface water quality due to silt
runoff and sanitary wastes from worker-based camps and
chemicals used in construction
9. Does the sub project requires significant extraction
ofsurface or ground water?
10. Increased risk of water pollution from oil, grease, fuel spills
and other materials
11. Impact on water quality due to release of sewage/sludge?
12. Possibility of flooding due to sewage
13. Possibility of increased air pollution during
preconstruction/construction/operation phase?
14. Other pollution concerns relating to inconveniences in living
conditions that may trigger cases of upper respiratory
problems?
15. Risks and vulnerabilities related to occupational health and
safety due to physical, chemical, biological hazards during
project construction and operation
16. Noise and vibration due to blasting and/or other civil works?
17. Possibility of poor sanitation and solid waste disposal
18. Creation of temporary breeding habitats for diseases such as
those transmitted by mosquitoes and rodents?
19. Accident risks associated with pre construction, construction
& operation phases of project
20. large population influx during project construction and
operation that causes increased burden on social
infrastructure and services (such as water supply and
sanitation systems)
21. Risks to community health and safety due to the transport,
storage, and use and/or disposal of materials such as
explosives, fuel and other chemicals during construction and
operation?
22. interference with other utilities and blocking of access to
resource/utility
23. Generation of solid waste and/or hazardous waste during
construction/operation of project?
24. Conduct of medical health screening and testing to identify
the presence of suspected covid-19 positive individuals
among the construction workers in the workers’ labor camps
or among the community members that might infect the
construction workers
112
Social Aspects
Checklist for Social Screening
S. No. Particulars Details
Present use of Govt. Land that will be used for the project activities
d.
with Persons/Households using
Present use of Govt. Land that will be used for the project activities
with Persons/Households using
✓ Agricultural purposes
f.
✓ Residential purposes
✓ Commercial purposes
✓ Other purposes (Indicate)
113
S. No. Particulars Details
Describe any other impacts that have not been covered in this screening
i.
form
k. RAP/ARAP Requirement
The potential negative and positive direct or indirect impacts and provide clarity on issue, which needs to be
investigated under Category B EA type (for higher impact category requires ESIA, for medium impact category
requires abbreviated EMP and for lower impact category require Best Environmental Practices-BEP).
Medium to High Impact Category B project: NUGIP Intervention Requiring ESIA and ESMP
Sub projects under this category havepotentially major Impacts of (CAT B range type); complex issues; likely need
for significant mitigation and monitoring. The indicative sub projects under this category include:
• Construction of sanitary landfill
• Construction of new waste water treatment plant, water supply projects
ESIA Template
• Executive Summary
• Introduction about sub project (nature, type, project location, site characteristics : physical, biological,
socio-economic)
• ESIA methodology
• Environmental and Social Baseline
• Legal and Regulatory Framework
• Environmental and Social Screening, Impact Identification, Prediction, and Management
• Resettlement Action Plan (RAP), Gender Action Plan, VCDP (as applicable)
• Environmental and Social Management Plan
• Information Dissemination and Communication Plan
• Appendix
Such NUGIP sub projects require ESMP. The format and table of content for preparing ESMP is included below. The
following process will be followed to prepare the ESMP:
114
C. Environment and Social Management Plan (ESMP)
Phase I: Preparation of ESMP. The ESMP is an overall plan, which addresses the minor to moderate safeguard
issues arising from implementation of the NUGIP sub projects and suggests a strategy and action plan to mitigate the
adverse environmental and social impacts and enhance the beneficial impacts of the interventions. The EMP for such
sub projects consists of the set of mitigation, monitoring, and institutional measures to be taken during implementation
and operation to eliminate adverse environmental and social impacts, offset them, or reduce them to acceptable levels.
The plan also includes the actions needed to implement these measures. An EMP is required for the following
indicative sub projects
• Existing road upgrading related sub projects
• Waste to energy sub project projects
• Renovation and upgrading of sewerage and water supply projects
The PCO with external support (as required) will prepare the ESMP in the prescribed ESMP format incorporating all
information and data.
115
ESIA TEMPLATE
TABLE OF CONTENTS
CHAPTER 1
PROJECT DESCRIPTION
1. Introduction
1.1 Background
Project Activities
The project activities may be categorized mainly into two phase which are activities in the Pre- Construction,
Construction and Operational Phases.
CHAPTER 2
Environmental impacts on the physical, biological, and socio-economic and cultural environments during the pre-
construction, construction and operation and maintenance phases are discussed here in detail with the mitigating
measures.
The summary of the anticipated environmental impacts and the mitigation measures are given in matrix form attached
with this document
116
2.3.1.2 Construction Phase
a. Environmental impacts due to project construction
i. Physical Environment (Examples)
Water and land pollution
Pollution due to air, noise and vibrations
ii. Biological Environment
iii. Socio-Economic and Cultural Environment
Reinstatement of damaged community services and infrastructure
Influx of outside workforce, money and unwanted activities
Occupational Health and Safety (OHS)
Traffic management
The envisaged impacts due to implementation of NUGIP component could be grouped into positive and adverse
impacts. The goal of mitigation measures is to maximize the positive impacts and minimize or reduce the adverse
impacts.
The proposed mitigation measures for predicted adverse impacts could be grouped into three categories as Physical,
Biological, Socio-economic and cultural environment. Such impacts could be further classified as impacts during the
construction stage and operation stage.
3.1 Mitigation Cost: The environmental and social mitigation cost in ESMP are basically related to activities
associated with the physical constructions, environmental conservations, health and safety and awareness raising. The
construction related mitigation measures are linked to the project's DPR and such costs are included in construction
Bill of Quantity. For such mitigation measures, the ESMP shall clearly highlight "included in project BoQ" and ensure
that DPR has included such cost in BoQ. For other mitigation costs like environmental and social enhancement,
awareness raising etc, the ESMP report should include the cost based on the district rates, or norms of the government.
Such mitigation cost should of clearly included in mitigation cost. This type of mitigation cost will apply for
construction and operation phases of the project.
Environmental management actions to be undertaken and to be adopted for the realization of environmental mitigation
and enhancement for construction and operation phases are presented in the table below. The Environmental
Mitigation and Enhancement Management Plan (EMEMP) which is part of the ESMP describes impacts, description
of enhancement/mitigation action required, individual or agency responsible, national standards and guidelines,
timing of actions, responsible authority, and tentative financial requirements.
Physical Environment
S.N Identified Impacts Environment Mitigation Measures
1 Impacts associated with management of The excavated materials shall be used as construction material
excavated materials (as applicable). The unused materials will be sold to needy,
non-sellable items shall be disposed properly in identified
areas.
2 Impacts of air pollution (particularly Vehicle speed control and sprinkling of water in road and in
dust) and its impacts on surrounding construction site in a regular basis. Use of old and worn out
environment vehicles shall be avoided to control air pollution.
3 Impacts related to noise created by the Night time construction work shall not be allowed (in general
vehicle used for the transportation of conditions, for urgent work local community should be
construction material informed and consent should be obtained). Vehicle speed
control and maintained vehicle shall be used. Use of old and
worn out vehicles shall be avoided to control noise pollution.
5 Impacts related to traffic obstruction and Adequate traffic signs, warning signs, and scheduling of
traffic management transport operator in off office hours to avoid traffic congestion
and inconvenience to people.
6 Possibility of contamination of water Regular water sprinkling in approach road, construction sites.
source due sub project construction Discourage use of direct discharge of water in to water bodies
activities. without proper treatment.
7 Impacts related to health and safety of Social distancing during construction and medical testing to
workers, and visitors /worshippers determine the presence of covid-19 positive individuals among
the constructions workers or in the communities where the sub-
projects are located
8 Impacts related to obstruction and Adequate signs shall be used, construction materials shall be
disturbances to visitors/worshippers of stored in designated areas with proper fencing, and
temple/shrine construction work shall be planned in such a way that it won’t
stop worshippers.
9 Impacts related to liquid waste, solid Implementation of solid and liquid waste management
waste, and sewage management during segregation, collection and treatment technology. Prohibition
construction phases of the project of littering and illegal dumping of waste in premises and its
surroundings.
Biological Environment
118
S.N Identified Impacts Environment Mitigation Measures
1 Impacts related to disturbance to flora Trees should be protected and its cutting/removal is strictly not
and it’s cutting/removal during recommended.
construction period
1 Disturbance to local residents due to Prior information dissemination to the public regarding the
obstruction to their access, pollution etc nature, schedule of work in advance
The impact monitoring in the plan relates to only those measurable indicators in the socio-economic,
Cultural/Physical, Chemical and Biological environments. For each of the monitoring indicators, monitoring
methods, frequency of monitoring, responsible parties along with the required cost estimates have been estimated.
119
and disposed in approved
landfill sites.
Contaminated medical
wastes are properly
segregated, treated and
disposed in approved
landfill sites.
120
The overall project environmental management is the responsibility of PIU. The ESMP shall be prepared to show
linkages with different parties to be involved directly or indirectly during the different phases of project
development and operation in compliance with the existing Act and Rules.
The generic environmental best practices to be followed for NUGIP Sub projects and interventions are elaborated
below:
▪ Solid Waste Management, including medical wastes, should be based on Reduce, Reuse, and Recycle (3R)
principles: Generation of solid, semi-solid and liquid waste requires proper on site management and scientific
disposal.
▪ As there may be settlements around the component 2 activities, no or few nuisances to the community should be
produced. Examples: use of less noisy equipment and no work during night hours as well as adoption of
Environmentally Sound Technologies (energy efficient system design, selection of less polluting technology) in
civil construction.
▪ Covid-19 regulations and Health and Safety Standards (e.g., use of personal protective equipment, use of safety
signs) should be adopted in construction areas and replacement activities,
▪ Environment, Health, and Safety (EHS) related orientation and job specific training should be provided to
employees; IFCs General Environmental Health and Safety Guidelines section 2.2 (Occupational Health and
Safety ; Communication and Training shall be followed
▪ Strict implementation of ESMP, adherence to GoN Rules, Regulations, Policies and World Bank policies, and
compliance with formats and checklists developed by ministries
▪ Correction of shortcomings, periodic review meetings, clear assignment of roles and responsibilities
▪ Environmentally friendly technologies and awareness rising in environmental (including cultural and
archeological) should be promoted.
▪ Information dissemination and public consultations prior, during and concomitant to the garner understanding
and consensus should be an integral part of all activities under NUGIP
121
Appendix D: Initial scoping for subprojects
113
113
113
Urlabari Municipality: Upgradation of Krishna Chowk to Community forest office road
114
114
114
Damak Municipality: Upgradation of road at ward no. 2 and 5- P21
115
115
115
Birtamod Municipality: Upgradation of Buttabari-Pyakurel Road-P15
Key Environmental Issues
• There is a National Forest Patch (CharaliForest) maintained by community at the eastern
side of project road at a distance of 0.250 to 1.000Km range. Denia Khola, a perennial
river flows adjacent to the forest area on the easternside of project road. But as the road is
Proposed length: 6.26Km intermediate which will have limited traffic there by limited environmental impact
• Roads have water streams and culverts over it, during construction water pollution
could be an issue
• Electric poles need to be shifted
• Road have sensitive receptor (school)–air pollution and noise pollution
RoW: 12m (9-10mat Saraswati Is an important issue
School Area) Carriageway: 7m • Near Khoparion proposed road, there was a low-lying small section of 50m which was
affected due to waterlogging for quite a long time
Design features: Road, utility duct on
• Herdof migratory Elephant (6-13 in a herd) use to follow Charali forest patch
both sides, pavement, street, Tactile tile to aid movement
tomigratetowards Jalthal National Forest. Jalthal Forest is located about 8km away to the
of visually impaired, Junction improvement at E-W
southern side of project road. Elephant migration occurs about 3 times in the year during
Highway Junction and Birtamod Chandragadhi Road,
harvesting seasons in the associated area
minor bridges
• Clearing of private trees
116
116
116
Appendix E: Environmental & Social Mitigation Measures
Environmental Impacts and Mitigation Measures
EnvironmentalImpact / ResponsibleEntity
MitigationMeasures
Aspect
DESIGNSTAGE
The proposed alignment/design to be selected/ DPR consultant, PCO,
adjusted Municipalities
to minimize land acquisition
Consideration of Design to avoid socially, culturally & environmentally
Alternatives
sensitive areas–structures, Common Property
Resources, cultural properties, waterbodies,
vegetation cover, forestetc.
Various issues raised during public consultation to be DPR consultant, PCO,
Issues from stakeholder examined & suitably incorporated based on merit & Municipalities
consultations other safety measures
Design for Geologically Provision of retaining wall/breast wall (as DPR consultant, PCO,
Unstable/Land Slide prone areas applicable) and other suitable measures for Municipalities
land stabilization should be adopted
Impact on Ecologically Prior care should be given to finalize the project DPR consultant, PCO,
Sensitive areas like Protected location/s. Project shouldn’t be developed in such Municipalities
Areas (National Parks, Wildlife ecologically fragile or in the vicinity which may
Reserve, Hunting Reserve, have plausible impact on these ecosystems
Conservation Areas, Buffer
Zones), Ramsar Site, Breeding,
Nesting Ground of
migratoryspecies, Wildlife
Corridor/Migration Route etc.
To avoid impact on historically significant DPR consultant, PCO,
Impact on historically significant archaeological/ anthropological sites, the Municipalities
sites project development shouldn’t be commenced in
the vicinity of historically important sites
Road safety issue due to poor Design of geometric improvements as per DPR consultant, PCO,
geometrics design standards Municipalities
PRE-CONSTRUCTION
STAGE
Land Acquisition and
Loss of Properties
Acquisition of Private Land Compensation for loss ESIA consultant, ULGs,
Impact on structures/properties Livelihood restoration PCO, Municipalities
Training and capacity building
Impact on vulnerable Engaging PAPs in process of project development
communities
Shifting of Utilities
All community underground and overhead DPR consultant, concerned
utilities will be shifted as per proper Utility department/s, PCO,
Relocation of Utilities Shifting Plan after taking prior permission Municipalities
from concerned departments like Electricity,
Telecommunications, Waterworks etc.
117
EnvironmentalImpact/ ResponsibleEntity
Aspect MitigationMeasures
Drinking water source to be replaced in DPR consultant,
consultation with the locals. Temporary concerned stakeholders,
Loss of drinking water source arrangements should be provided, if the PCO, Municipalities
existing water supply is likely to be
disrupted/disturbed
Mobilisation&Site
Clearance
Trees and Vegetation cover will be removed from ESIA Consultant,
the project development area before the Contractor, PCO,
Commencement of Construction after obtaining Municipalities
necessary permissions from the forest
Removal of Trees & Vegetation Department. Provision for compensatory plantation
Cover should be kept as per the guideline of the Forest
Department
118
EnvironmentalImpact/ ResponsibleEntity
MitigationMeasures
Aspect
To ensure that pollution emission levels comply
with the relevant requirements of MoFE
Regular monitoring of ambient air quality should
be conducted for the parameters like PM10,
PM2.5, SO2,NOx,CO,O3, at suitable locations
Cultural and Religious properties should be Contractor, PCO,
Shifting of Cultural/Religious shifted to the nearby location in consultation with Municipalities in
Properties local community and administration. coordination with DSC
CONSTRUCTIONSTAGE
Prior to initiation of construction work ESIA Consultant,
Clearances and approvals necessary permissions are to be taken from Contractor, PCO,
respective stakeholders. Municipalities
Land
Main reason of soil erosion is downpour. Contractor, PCO,
Contractor should plan the activities so that no Municipalities in
naked /loose earth surface is left out before the onset coordination with DSC
of monsoon. For minimising the soil erosion
following preventive measures to be taken such as:
Top soil from borrow area, debris disposal sites,
construction site to be protected/ covered for soil
erosion.
Debris due to excavation of foundation,
dismantling of existing structure will be removed
from the watercourse immediately and should be
Soil Erosion and reused for backfilling.
Sedimentation control Along locations abutting waterbodies, stone
pitching can be carried out.
Embankment slopes to be covered, soon after
completion.
Diversions for bridges/culverts will be removed
from the water course before the onset of
monsoon
All areas to be permanently covered or borrow areas Contractor, PCO,
will be stripped to a depth of 150mm and Municipalities in
Stored in stockpile. The stockpile will be designed coordination with DSC
such that the slope does not exceed 1:2 (vertical to
horizontal), and the height of the pile is to be
restricted to 2m. The stockpiles should be covered
with gunny bags or tarpaulin.
Top soil will be safeguarded from erosion and
will be reused as follows:
Loss of agricultural topsoil
Covering all borrow areas after excavation is
over.
Dressing of slopes of road embankment
Agricultural field, acquired temporarily
Landscaping
Construction vehicles should operate within the Contractor, PCO,
Compaction of Soil and
project development zone to avoid damaging Municipalities in
Damage to Vegetation
soil and vegetation of outside. coordination with DSC
EnvironmentalImpact/ ResponsibleEntity
MitigationMeasures
Aspect
119
Diversions, access roads used will be redeveloped
by Contractor to the satisfaction of the owner/
villagers once the construction work is over. While
operating on temporarily acquired agricultural
land for any construction activities, topsoil will be
preserved in stockpiles.
Due to handling of Hazardous waste Contractor, PCO,
Vehicle/machinery and equipment operation, Municipalities in
maintenance and refueling shall be carried out in coordination with DSC
such a fashion that spillage of fuels and lubricants
does not contaminate the ground.
Fuel storage shall be in proper bunded areas. All
spills and collected petroleum products shall be
disposed of in accordance with Government of
Nepal guidelines at designated locations.
Contamination of soil Oil interceptor should be installed at construction
site for wash down and refueling areas.
Septic tank will be constructed for safe disposal
of labour camp waste.
Air
Vehicles delivering materials should be covered Contractor, PCO,
to reduce spills and dust blowing off the load. Municipalities in
Clearing and grubbing to be done, just before the coordination with DSC
Dust generation and gaseous start of next activity on that site.
emission from construction
Waterspraying is needed to aid compaction of the
activities and equipment
earth material. After the compaction,
120
EnvironmentalImpact/ ResponsibleEntity
MitigationMeasures
Aspect
water spraying should be carried out at regular
intervals to limit the dust to below
Construction surfaces should be cleaned with air
compressor and vacuum cleaners prior to the
construction works.Manual labour using brooms
should be avoided, if used labour to be provided
with masks.
For roads, embankment slopes to be covered with
turfing/stonepitching immediately after
completion.
The Contractor shall take every precaution to
reduce the level of dust emission from the hot
mix plants and the batching plants
Plants,machinery and equipment shall be so
handled (including dismantling) as to
minimisegenerationofdust.
All vehicles,equipment and machinery used for
construction shall be regularly maintained to
ensure that pollution emission levels comply with
the relevant requirements of MoFE
Regular monitoring of ambient air quality should
be conducted for the parameters like PM10,
PM2.5, SO2,NOx,CO,O3,Pb at suitable locations
121
EnvironmentalImpact/ ResponsibleEntity
MitigationMeasures
Aspect
completed prior to disruption of the actual source
Alternate measures to be taken/ensured during
disrupted period.
Source to be replaced immediately, in case of
accidental loss.
122
EnvironmentalImpact/ ResponsibleEntity
MitigationMeasures
Aspect
should be avoided.
Oil interceptor should be in stalled at suitable
locations
Water quality (surface and ground) should be
monitored at suitable locations
Contaminationof Ground Necessary care should be given during well Contractor, PCO,
waterduringboring/well construction to prevent accidental contamination Municipalities in
construction of Groundwater coordination with DSC
Noise
Noise standard at processing sites, e.g. aggregate Contractor, PCO,
crushing plants, batching plant, hot mix plant will Municipalities in
be strictly monitored to prevent exceeding of coordination with DSC
noise standards.
Workers in vicinity of loud noise, and workers
working with or incrushing, compaction, concrete
mixing operations shall wear earplugs and their
working time should be limited as a safety
measure.
In construction sites within 150m of sensitive
receptors construction will be stopped in Night-
time (from 22:00 to 06:00).
Machinery and vehicles will bemaintained to keep
Noise from Vehicles, Plants
their noise to a minimum level.
and Equipment, Blasting or
Pre-splitting Operations Noise barriers may be constructed at sensitive
receptor locations.
All vehicles and equipment used in construction
shall be fitted with exhaust silencers.
During routine servicing operations, the
effectiveness of exhaust silencers should be
checked and if found to be defective shall be
replaced.
Sites of Historical
/Cultural Importance
The contractor should keep provisions for Contractor, PCO,
managing chance finds which will be applied in Municipalities in
the event if cultural heritage is subsequently coordination with DSC
discovered or encountered unexpectedly during
project development. The contractor should
Chance Finds ensure no disturbance to any chance find further
until an assessment by competent professionals is
made and action is taken by concerned authority.
Flora&Fauna
Clearing of vegetation/trees must be limited Contractor, PCO,
only within project development zone. Municipalities in
Avoidable trees must be saved coordination with DSC
Felling of trees and
Possibility for transplantation of trees should be
disturbance of vegetation
explored
cover
Plantation/afforestation activity should be
activity initiated in accordance to Govt.of
123
EnvironmentalImpact/ ResponsibleEntity
MitigationMeasures
Aspect
Nepal afforestation policy
Provision of LPG should be kept for
construction camp as fuel source to avoid tree
cutting
Construction camps should be located away from Contractor, PCO,
ecologically sensitive areas Municipalities in
Construction workers must protect natural coordination with DSC
resources and wild animals.
Hunting must be prohibited.
Nesting grounds & migratory paths/wildlife
Impact on Fauna corridor of the vicinity (if any) should be
protected.
Compensatory afforestation should be taken up to
mitigate loss of biodiversity associated with loss
of tree and vegetation cover
124
EnvironmentalImpact/ ResponsibleEntity
MitigationMeasures
Aspect
Such barricades, including signs, markings, flags,
lights and flagmen as may be required for the
information and protection of traffic approaching
or passing through the section of the road under
improvement.
The Contractor is required to comply with all the Contractor, PCO,
precautions as required for the safetyof the Municipalities in
workers as per the International Labour Org coordination with DSC
anisation (ILO).
The Contractor shall supply all necessary safety
appliances such as safety goggles, helmets,
masks, etc., to the workers and staff.
Risk from Construction Work The Contractor has to comply with all regulation
regarding safe scaffolding, ladders, working
platforms, gangway, stairwells, excavations,
trenches and safe means of entry and egress.
No child labour shall be utilized in the project
125
EnvironmentalImpact/ ResponsibleEntity
MitigationMeasures
Aspect
The effluents can be diverted for horticulture
inside the camps.
Workers must have access to potable water.
Garbage bins must be provided in the camps
and regularly disposed off in a hygienic
manner.
Adequate health care facility should be
provided for the workforce. Unless otherwise
arranged for by the locals anitary authority, the
local medical health or municipal authorities.
On completion of the works, all such temporary
structures shall be cleared away, septic tank
and other disposal pits should be filled in
environmentally acceptable manner
Signages, barriers, road obstructions • Removal barriers and other signages Contractor
OPERATION STAGE
Siltfencing, Oil & Grease traps, etc. shall be PCO, Municipalities
provided to ensure that the waterquality is not
impaired due to contaminants from road run-
Soil/Water quality degradation off.
due to surface run-off Monitoring shall be carried out at suitable
locations
Provision for proper drainage network should
be kept
Contingency plans to be in place for cleaning PCO, Municipalities
up of spills of oil, fuel and toxic chemicals.
Spill of oil, fuel and automobile servicing units
without adequate disposal systems in place to
be discouraged.
Accidental spills are potentially disastrous, but
its probability is quite low as one of the
Contamination of Soil and Water objectives of this project is to enhance road
Resources from Spills/Accidents safety.
The Public will be informed about the
regulations on land pollution.
Land pollution monitoring program has been
devised for checking pollution level and
suggesting remedial measures.
EnvironmentalImpact/ ResponsibleEntity
MitigationMeasures
Aspect
In Ambient Air
HORN PROHIBITED sign post will be enforced PCO, Municipalities
Maintenance of noise barriers
Noise The public will be informed about the regulations
on noise pollution.
Contents of the Resettlement Action Plan (RAP) shall include the following as a basic minimum:
Executive Summary
Project description
Type of impacts
Institutional Arrangements
Implementation Arrangements
Monitoringand Evaluation
Particulars Birtamod Damak Urlabari Sundar Mechinagar Itahari Rajbiraj Triyuga Dhankuta
Haraicha
Separate Yes Yes No Yes Yes Yes Yes Yes Yes
Environment
& Social cell
Efficacy of •5 Environment •Environment •Staff are •10 permanent •Staff are •Head of the unit •Both experts •1 Environmental
E&S and 3 Social staff staff are hired permanent staff involved in permanent ispermanent and are Staff & 3 Social
departments (including on temporary •Staff are not survey work and temporary others staff are permanent Staff
permanent and basis. Social involved in pertaining to •The temporary. •Staff are not •Staff are not
temporary) involv staff is project social and Environment •Department is involved in involved in
ed in preliminary permanent planning or environmental officer had past responsible for project project
survey work •Staff are not appraisal assessment experience of coordination and planning or planning or
pertaining to involved in process conducting facilitation of the appraisal appraisal
social and project •Municipality IEE/ESIA environmental process process
environmental planning or has studies. He is and social •Municipality •Municipality
assessment (like appraisal experience also committee under has hasexperience
assessment of process in preparing responsiblefor the municipality experience of preparing
impact on trees, •Municipality ESIA/ESMP monitoring of •The department’s of preparing EIA/ ESMF
structures) has through efficacy of roles include ESIA/ESMP but all were
experience of external EMP being management of through outsourced
preparing agencies adopted in education, external •One of the staff
ESIA/ ESMP •Hasn’t various health, social agencies was engaged in
through prepared industries security, •Haven’t review of
external ESIA / prior to issuing sanitation etc. prepared ESIA-ESMP
agencies ESMP for pollution related issues ESIA/ESMP prepared by
multilateral under control •Staff are not for external
funding certificate involved in multilateral consultant for
agencies project planning funding UGDP (ADB
or appraisal agencies funded)-2
process weekly market
•Staff carry out development
preliminary project
social and
environmental
131
131
131
Particulars Birtamod Damak Urlabari Sundar Mechinagar Itahari Rajbiraj Triyuga Dhankuta
Haraicha
survey (like
assessment of
impact on trees,
structures) after
project
identification
132
132
132
Particulars Pokhara Vyas Putalibazar Baglung Tansen Ramgram Tilottama Shuklagandaki
Leknath
•Municipality has ESMP through •Municipality has
experience of external agencies experience of
preparing •Have experience of preparing
ESIA/ESMP working with ADB ESIA/ ESMP
through through external
external agencies
agencies
•Have
experience of
working with
ADB and JICA
•Technicalteam
examines and
conducts
survey;prepare
feasibility
report and the
DPR.
133
133
133
Parameters Pokhara Putalibazar Shuklagandaki Itahari Dhankuta S.Haraincha
Conservation, Waste Management, River environmental Cleanliness, supervision of solid
Conservation of religious Bank Protection& Flood plantation & greenery wastemanagement
trees, Control, Monitoring of development
plantation activity
Key Expertise/ - The staff completed - The staff had been Solid waste management & -
Specialization LLB in Environmental Involved in preparation of landfill site management
lawin2017 ESIA/IEE Reports.
Had verygood
understanding about
Environmental laws and
regulationsofGoN.
Involvement in Project Not involved/consulted Not involved/consulted Not involved/consulted Not involved/consulted Notinvolved/consulted Notinvolved/consulted
execution (Planning, during planning of during planning of during planning of during planning of during planning of during planning of
Construction & Operation) infrastructure development infrastructure development infrastructure development infrastructure development infrastructure development infrastructure development
project project project project. project project
Sometimes, theviewof
Env. cell is considered by
the municipality. For eg.
in case of extraction of
borrow material from river
banks, the staff’s
recommendation was
adopted by the
municipality. On other
hand, the suggestion of
expert is not considered in
case of dumping of solid
waste in forest area (as
there is no immediate
alternative is available).
Pertinent to state that,
currently the solid waste is
disposed in Hasposa
Community Forest.
Ratio of budget allocated to 20 Cr (4% of total Budget) 5% of Total Budget approx. 1% of total Not any specific budget approx. 1% of total approx. 0.3% of total
Environment cell to the Budget kept. But project specific Budget Budget
total budget of the budget is kept like
municipality fortesting of water quality
(during
134
134
134
Parameters Pokhara Putalibazar Shuklagandaki Itahari Dhankuta S.Haraincha
construction/operation
phase),Plantation etc.
Understanding of The staff neither had The staff had quite a The staff neither had The staff had quite a The staff neither had The staff neither had
Environmental laws and the understanding of fair awareness about the understanding of good understanding the understanding of the understanding of
regulations of Nepal Environmental laws Environmental laws Environmental laws about Environmental Environmental laws and Environmental laws and
pertaining to and regulations of and regulations of GoN and regulations of laws andregulationsof regulations of Nepal regulations of Nepal
infrastructure Nepal nor aware about Nepal nor aware about GoN. The operational nor aware about nor aware about
development project EIA/IEE requirements EIA/IEE requirements procedure forItahari EIA/IEE requirements EIA/IEE requirements
Municipality for
Pollution Prevention &
Control,2018 is
prepared by the staff
Understanding of World The staff does not have The staff does not have The staff does not have The staff was not The staff does not have The staff does not have
Bank/ADB understanding about understanding about understanding about involved in any World understanding about understanding about
Policies/Experience of World Bank’s OPs/BPs World Bank’s OPs/BPs World Bank’s OPs/BPs Bank-funded project World Bank’s OPs/BPs World Bank’s OPs/BPs
Working with any of and other safeguard and other safeguard and other safeguard but worked in LGCDP and other safeguard and other safeguard
the above policies. The present policies. The present policies. The present project which was policies. The present policies. The present
staff have never worked staff have never worked staff have never worked funded by ADB in past staff have never worked staff have never worked
in any multilateral in any multilateral in any multilateral (not in Itahari in any multilateral in any multilateral
General understanding agency funded
The staff project
had very basic agency
The stafffunded project
had very basic agency
The stafffunded project
had very basic Municipality)
The staff had very good agency funded
The staff had a project
very agency funded
The staff project
had very
of Environmental Issues idea of common ideaof common idea of common understanding of good understanding of generic understanding
pertaining to environmental impacts environmental impacts environmental impacts environmental solid waste of common
development of due to aninfrastructure due to an infrastructure due to an infrastructure concerns/issues as he management including environmental impacts
infrastructure project project such as impact project. Thestaff added project. The staff added was engaged in its disposal. (lacking understanding
on trees, dust that hiring of an that hiring of an preparation of IEE/ESIA However, had very of project specific
generation etc. Environmental Expert Environmental Expert reports. His current generic understanding environmental impacts)
however, they lacked for supervising ESMP for supervising ESMP responsibility also of common
project specific and implementation work implementation work includes monitoring of environmental impacts
location specific would be of help. would be of help. environmental pollution (lacking understanding
environmental impacts. of project specific
environmental impacts)
Understanding of The staff had no idea of The staff had no in The staff had no in The staff has a very The staff had no idea of The staff had no idea of
Environmental Environmental depth idea of depth idea of thorough idea of Environmental Environmental
Standards (like Standards such as on Environmental Environmental Environmental Standards such as on Standards such as on
Ambient Air,Noise etc.) air, noise and water Standards such as on Standards such as on Standards and current air, noise and water air, noise and water
quality. air, noise and water air, noise and water responsibility includes quality. quality.
quality quality issue of PollutionUnder
Control Certificates for
135
135
135
136
136
136
Parameters Pokhara Putalibazar Shuklagandaki Itahari Dhankuta S.Haraincha
the operational industries
Understanding ofESIA- The staff had an The staff had an The staff had an The staff was engaged in The staff had The staff had an
ESMP process understanding about the understanding about the understanding about the the preparation of understanding about the understanding about the
purpose of ESIA- ESMP. purpose of ESIA- ESMP. purpose of ESIA- ESMP. IEE/ESIA reports for purpose of ESIA- ESMP. purpose of ESIA- ESMP.
However, had never At municipality, the staf However, had never more than 300 projects. However, had never However, had never
prepared/reviewed any ftook help from external prepared/reviewed any prepared/reviewed any prepared/reviewed any
ESIA-ESMP consultant for preparation ESIA-ESMP ESIA-ESMP ESIA-ESMP
of IEE. However, had
never prepared/reviewed
any ESIA-ESMP
Role in Stakeholder The staff is not involved in The staff is not involved The staff is not involved in The staff is not involved The staff is not involved in The staff is not involved in
Engagement Process stakeholder engagement in stakeholder engagement stakeholder engagement in stakeholder engagement stakeholder engagement stakeholder engagement
processes for development processes for development processes for development processes for development processfor development of processes for development
of any infrastructure of any infrastructure of any infrastructure of any infrastructure any infrastructure project. of any infrastructure
projects. project project projects in the project
municipality. However, he
had very fair idea of
purpose and process of
stakeholder engagements
in project development.
Experience of ESMP The present The present The present The staff’s current profile The present The present
Implementation (at least Environmental cell was Environmental cell was Environmental cell was at municipality Environmental cell was Environmental cell was
in supervisory role) not involved in ESMP not involved in ESMP not involved in ESMP includes monitoring of not involved in ESMP not involved in ESMP
implementation work implementation work implementation work efficacy of EMP being implementation work for implementation work
forany project in the past forany project in the past forany project in the past adopted in various any project in the past in foranyprojectin the past in
in any capacity and hence in any capacity and hence in any capacity and hence industries. any capacity and hence any capacity and hence
does not possess any such does not possess any such does not possess any such does not possess any does not possess any such
experience. experience. The staff experience. suchexperience. experience.
added that hiring of an
Environmental Expert for
supervising EMP
implementation work
would be of help.
Participation/Role in All grievances including All grievances including All grievances including All grievances including All grievances including All grievances including
resolving Environment environmental issues are environmental issues are environmental issues are environmental issues are environmental issues are environmental issues are
related grievances directly registered in directly registered in directly registered in directly registered in directly registered in directly registered in
municipality and are municipality and are municipality and are municipality and are municipality and are municipality and are
137
137
137
Parameters Pokhara Putalibazar Shuklagandaki Itahari Dhankuta S.Haraincha
handled by handled by handled by handled by handled by handled by
municipality’s judicial municipality’s judicial municipality’s judicial municipality’s judicial municipality’s judicial municipality’s judicial
committee (Nyayik committee (Nyayik committee (Nyayik committee (Nyayik committee (Nyayik committee (Nyayik
Samiti). The Samiti). The Samiti). The Samiti).Based on the Samiti). Based on the Samiti). TheDisaster
environmental cell is environmental cell is environmental cell is natureof grievance,the natureof grievance, the Management Officer is
not involved in this not involved in this not involvedinthis view of Env. Cell is view of Env. Cell is partof Nyayik Samity
process.Grievance can process. Grievance can process. Grievance can taken as and when taken as and when body. Basedon the
also be submitted to also be submitted to also be submitted to required. Grievance can required. Grievance can nature of grievance, the
CAO at Municipality CAO at Municipality CAO at Municipality also be submitted to also be submitted to view of Env. Cell is
levelor toWard levelor toWard levelor to Ward CAOat Municipality CAO at Municipality taken as and when
Chairmanat Ward Level Chairman at Ward Level Chairman at Ward Level levelor toWard levelor toWard required. Grievance can
ChairmanatWardLevel Chairman at Ward Level also be submitted to
CAO at Municipality
levelor toWard
Chairman at Ward Level
138
138
138
139
139
139
Parameters Pokhara Putalibazar Shuklagandaki Itahari Dhankuta S.Haraincha
mushroom farming etc.) Clean city awareness
programs and dust bin
distribution
Key Expertise/Specialization - - - - - -
Involvement in Project Not involved/consulted Not involved/consulted Not involved/consulted Not involved/consulted Not involved/consulted Not involved/consulted
execution (Planning, Construction during planning of during planning of during planning of during planning of during planning of during planning of
& Operation) infrastructure infrastructure development infrastructure infrastructure development infrastructure infrastructure
development project project development project project development project development project
Ratio of budget allocated to Approx.3Cr (less than Approx. 5 % of total Approx. 3 % of total Approx. 2 % of total Approx. 13-14% of Approx. 1% of total
Social cell to the total budget of 1% of total budget) budget budget budget totalbudget budget
the municipality
Understanding of social laws The staff doesn’t have The staff doesn’t have The staff doesn’t have The staff don’t have The staff don’t have The staff don’t have
and regulations of Nepal pertaining understanding of social understandingof social understanding of social understanding of social understanding of social understanding of social
to infrastructure safeguard legislations of safeguard legislations of safeguard legislations of safeguard legislations of safeguard legislations of safeguard legislations of
development project such as land GoN GoN GoN GoN GoN GoN
acquisition, R&R, Gender related,
Vulnerable Communities etc.
Understanding of World The staff does not have The staff do not have The staff do not have The staffdo not have The staff do not have The staff do not have
Bank/ADB Policies/Experience of understanding about understanding about understanding about understanding about understanding about understanding about
working with any of the above World Banks OPs/BPs WorldBank’s OPs/BPs World Bank’s OPs/BPs World Bank’s OPs/BPs World Bank’s OPs/BPs World Bank’s OPs/BPs
and other safeguard and other safeguard and other Safeguard and other Safeguard and other safeguard and other Safeguard
Policies of Multilateral policies. The present staff policies. The present policies. The present policies. However, one policies. The present
Agencies. However, few have never worked in any staff have never worked staff have never worked of the staff was engaged staff have never worked
of thestaff from social multi lateral agency in any multilateral in any multilateral in review of ESIA- in any multilateral
cell were involved in funded project agency funded project agency funded project ESMP prepared by agency funded project
consultation and social external consultant for
survey for Talchowk- UGDP (ADB funded)-2
Begnas Lake road in the weekly market
UGDP development project
General understanding of Social The staff had basic The staff had basic The staff had basic The staff had basic The staff had basic The staff had basic
Issues pertaining to development understanding of key understanding of key understanding of key understanding of key understandingof key understanding of key
of infrastructure project social issues and impacts social issues and impacts social issues and impacts social issues and impacts social issues and impacts social issues and impacts
pertaining to pertaining to development pertaining to pertaining to pertaining to pertaining to
development of of infrastructure project development of development of development of development of
infrastructure project infrastructure project infrastructure project infrastructure project infrastructure project
Understanding of Land The present staff had basic The present staff had basic The present staff had basic The present staff had basic The present staff had basic The present staff had basic
Acquisition,R&R Process understanding of Land understanding of Land understanding of Land understanding of Land understanding of Land understanding of Land
Acquisition and Acquisition and Acquisition and Acquisition and Acquisition and Acquisition and
138
Parameters Pokhara Putalibazar Shuklagandaki Itahari Dhankuta S.Haraincha
R&R requirement. R&R requirement. R&R requirement. R&R requirement. R&R requirement. R&R requirement.
However, theydid not However, theydidnot have However, they did not However, they did not However, they did not However, they did not
have detailed detailed understandingof have detailed have detailed have detailed have detailed
understandingof the the process, entitlements understandingof the understandingof the understandingof the understandingof the
process, entitlements and and other related process, entitlements and process, entitlements and process, entitlements and process, entitlements and
other related activities. activities. other related activities other related activities. other related activities. other related activities.
Understanding of ESIA-ESMP They had understanding They had understanding The staff did not have They had understanding One of the staff was They had understanding
process about the purpose of about the purpose of any understanding on about the purpose of engaged in review of about the purpose of
ESIA- ESIA- ESMP. However, ESIA-ESMP processes ESIA- ESIA-ESMP prepared ESIA-
ESMP.However,they they have never and had never worked ESMP.However,they byexternal consultant for ESMP.However,they
have never prepared/reviewed ESIA- onpreparingthem. have never UGDP (ADB funded)-2 have never
prepared/reviewed ESIA- ESMP prepared/reviewed ESIA- weekly market prepared/reviewed ESIA-
ESMP ESMP development project ESMP
Role in Stakeholder Engagement The social cell is not The social cell is not The social cell is not The social cell is not The social cell is not The social cell is not
Process involved in stakeholder involved in stakeholder involved in stakeholder involved in stakeholder involved in stakeholder involved in stakeholder
engagement processes for engagement processes for engagement processes engagement processes engagement processes engagement processes
development of any development of any for development of any for development of any for development of any for development of any
infrastructure project infrastructure project infrastructure project infrastructure project infrastructure project infrastructure project
Experience of ESMP The present staff of the The present staff of the The present staff of the The present staff of the The present staff of the The present staff of the
Implementation (at least in social cell have not been social cell have not been social cell have not been social cell have not been social cell have not been social cell have not been
supervisory role) involved in ESMP involved in ESMP involved in ESMP involved in ESMP involved in ESMP involved in ESMP
implementation work of implementation work of implementation work of implementation work of implementation work of implementation work of
any project in the past any project in the past any project in the past any project in the past any project in the past any project in the past
and hence do not possess and hence do not possess and hence do not possess and hence do not possess and hence do not possess and hence do not possess
any such experience. any such experience. any such experience. any such experience. any such experience. any such experience.
Participation / Role in resolving All grievances are All grievances including All grievances including All grievances are All grievances including All grievances including
social grievances directly registered in environmental and social environmental and social directly registered in environmental and social environmental issues
municipality and are issues are directly issues are directly municipality and are issues are directly are directly registered in
handled by the registered in municipality registered in handled by registered in municipality and are
municipality’s judicial and are handled by municipality andare municipality’s judicial municipality andare handled by
committee (Nyayik municipality’s judicial handled by committee (Nyayik handled by municipality’s judicial
Samiti). The social cell committee (Nyayik municipality’s judicial Samiti). Grievance can municipality’s judicial committee (Nyayik
is not involved in this Samiti).The social cell is committee (Nyayik also besubmittedto CAO committee (Nyayik Samiti). The Disaster
process. Grievances can not involved in this Samiti). The social cell at Municipality level or Samiti). Management Officer
also be submitted to the is not involved in this to Ward (part of Social Cell) is
CAO at Municipality
140
Parameters Pokhara Putalibazar Shuklagandaki Itahari Dhankuta S.Haraincha
level or to Ward process. Grievances can process. Grievances can Chairman at Ward Based on the nature of part of Nyayik Samity
Chairman atWard Level also be submitted to CAO also be submitted to Level grievance, the view of body. Based on the
at Municipality level or CAO at Municipality Social.Cell is taken as nature of grievance, the
toWard Chairman at level or toWard and when required. view of Social Cell is
Ward Level Chairman at Ward Level Grievances can also be taken as and when
submitted to the CAO at required. Grievances can
the Municipality level or also be submitted to
to Ward Chairman at CAO at Municipality
Ward Level level or to Ward
Chairman atWard Level
141
Appendix H: Summary Environmental and Social Conditions in the Cluster Municipalities
Basic Environmental and Social Conditions in the Eastern and Western Cluster municipalities
Baseline Environment and Social information in the Eastern Cluster municipalities
Particulars Birtamod Damak Urlabari Sundar Mechinagar Itahari Rajbiraj Triyuga Dhankuta
Haraicha
ULB Status Municipality Municipality Municipality Municipality Municipality Sub- Municipality Municipality Municipality
metropolitan
District Jhapa Jhapa Morang Morang Jhapa Sunsari Saptari Udayapur Dhankuta
Population 92,575 87,637 122,803 80,562 176,153 173,312 72,106 87,557 36,619
Sex ratio (F:M) 1.07 1.13 1.14 1.10 1.10 1.11 0.95 1.12 1.13
Municipal area 7824 ha 7086 ha 7462 ha 9890 ha Total: 19261 ha Total: 9378 ha 5527 ha 54744 ha 11084 ha
Physiography Terai Terai Terai Terai Terai Terai Terai Terai Hill
Climatic Zone Tropical Tropical Tropical Tropical Tropical Tropical Tropical Tropical Sub-tropical
Land Use Agriculture Agriculture Agriculture Agriculture Agriculture Agriculture Agriculture Agriculture Agriculture
land: 87.05% land: 70.32% land: 77.8% land: 45.4% land: 68.5% land: 72% land: 83% land: 13.17% land: 40%
Barren:1.46% Barren: 4.2% Barren: 7.2% Barren: 0.2% Barren: 9% Barren:0% Barren:0% Barren: 0.6% Barren: 0.6%
Forest: 1.5% Forest: 7.2% Forest: 0.9% Forest: 50% Forest: 12.9% Forest: 13.2% Forest: 0% Forest: 80% Forest: 57%
Residential: Residential: Residential: Residential: Residential: Residential: Residential: Residential: Residential:
5.04% 9.35 % 5.02% 1.4% 2.4% 10.5% 7.4% 0.2% 0.02%
Sand/ Sand/ Sand/ Sand/ Sand/ Sand/ Sand/ Sand/ Sand/
gravel/Boulders: gravel/Boulders: gravel/Boulders: gravel/Boulders: gravel/Boulders: gravel/Boulders: gravel/Boulders: gravel/Boulders: gravel/Boulders:
1% 4.7% 7.8% 1.7 6.71% 2.02% 7.5% 5.3% 2.2%
Shrubland/ Shrubland/ Shrubland/ Shrubland/ Shrubland/ Shrubland/ Shrubland/ Shrubland/ Shrubland/
grassland: 0.6% grassland: grassland: grassland: grassland: grassland: 2.3% grassland: 2.3% grassland: 1.2% grassland:
4.33% 1.35% 1.32% 0.52% 0.27%
Key Road Road Upgradation of Urban Roads; Urban Roads Upgradation of Urban Roads Urban Roads; Drinking Water
municipality upgradation; upgradation; urban roads Demand of solid and drainage Urban Roads; and drainage Water supply; Supply;
services demand Drainage; Drainage with drainage; waste system; Solid Waste especially from Public Drainage; solid
Solid waste Solid waste management Solid waste management wards 1 and 9- transportation; waste
segregation and management; facility; management and Water 16; River protection management
disposal facility; Landfill site; Water supply; system; supply pipelines Solid Waste works and disposal
Increased access Water supply Drainage along Water Supply in rural wards; Management
to Water supply (currently water the roads pipeline; Waste Water facility for
(presently 57% supply network Treatment and treatment; urban area;
of the covers 40% area proper Parking space; Water Supply
population has of management of Public
access to water municipality); sewage; Transport;
142
Particulars Birtamod Damak Urlabari Sundar Mechinagar Itahari Rajbiraj Triyuga Dhankuta
Haraicha
supply Cold storage for Parking areas; River
network); agriculture Better Traffic embankment
Lack of products management
treatment and
proper
management of
sanitation;
Parking facility;
traffic
management
Key High iron Threat to Sal Solid Waste River bank Flooding in Lack of Disposal of • Pollution due Threat to water
Environmental content in trees; Dhanesh disposal on river erosion Mechi, Ninda, drainage system solid waste on to sewerage body due to
issues ground water Bird banks Timai, Hadiya & the bank of disposal siltation
Jaljale wetlands Flooding in High iron contamination rivers or open Flooding Depletion of
need protection Mawa, Bakraha, content in of water through field Deforestation in water sources
blockage of Sunpakuwa ground water effluent High iron southern part
drainage system Khola- and land discharge from content in Landslide prone
(particularly in cutting at places industries ground water area in ward no
ward no High iron Depletion of existing water 4,5,6,14,15,16
1,5,8,13) content in water resources supply system
High iron ground water unable to cater
content in the demand of
ground water water to
growing
population
Flooding in
Khado River
Depletion of
ground water
Social Baseline Immigration Very High Poverty 20% Very High Poverty about Very High Very High Very High Very High
Condition rate 8-10% Immigration (5- Child marriage Immigration 10% Immigration (7- Immigration 1:5 Immigration Immigration
Poverty 7-10% 7%) in Indigenous Poverty 10-12 9%) in rural areas Limited illegal Aathpariya is
Child marriage Child marriage group and Terai % Child Marrige Poverty 30-40% mining issue one of the
in Tarai caste, in poor caste group Child marriage in Backward Caste Some extent to deprived
Muslim and communities in poor in caste like Tarai discrimination ethnic community
Adibasi group Limited threat Chaudahry, dalits, Muslim About 10% communities concentrated in
to Dhimal Dum, Jhangar, and Adibasi woman has land dependent on Ward no. 8
community Bantar and group owner
143
Particulars Birtamod Damak Urlabari Sundar Mechinagar Itahari Rajbiraj Triyuga Dhankuta
Haraicha
Ward 3,4, 9 has Musar Khanar, certificate due fishing and
Dhimal communities Budhikhola, to government forest resources
community Limited threat Sunsari-Morang tax incentive Presence of
dependent on to Dhimal Irrigation Canal. policy. marginalized
forest community There is Child marriage vulnerable
Ward 3,4, 9 has proposal to is also among group Musar
Dhimal construct 6 lane backward and dalits in
community road. Therefore, communities; ward number
dependent on there will be 1,2,3,4,5,6,7,8,9
forest requirement of ,10,11,12,13
diverting canal
land at the
Tyandra Khola
Local Tole committee Effective Tole meetings Effective As per the need. Effective As per the need, Effective Effective Tole
Governance meetings governance happen once a governance In the governance generally once a governance system
happen as per system. month. On the system. municipality 40- system in older month there is system. Discussion as
the need, Municipality local issues; Municipality 80 households municipal areas tole committee Municipality per program and
generally once a has 420 tole especially Discussion as have one tole whereas newly meetings. Discussion on other services
month. On the committees. infrastructure per program and development added Discuss on the project demands such as road
local issues; Discussion as development other services committee. municipalities local issues; and progress of development
especially per program and and upgrade; such as road Generally once do not have tole especially ongoing Meeting records
sanitation, other services livelihood development, a month. On the committees infrastructure projects are recorded in
awareness and such as road upliftment, Meeting records local issues; Project development Meeting records a written minute
so on. In development, saving and are recorded in especially identification as like drainage are recorded in format
Municipality, 50 women right, credit and so on a written minute saniation, a process. and widening of a written minute There are 7
households have child right, drug Project format awareness and Sometime, the existing road format steps in
1 tole issues identification as so on. municipality There are 113 No major planning
development Meeting records a process. Project informed the tole committee dispute has process where
committee are recorded in Sometime, the identification as villagers about in the come up, If any, public
They demand a written minute municipality a process. the project. municipality but it will be participation is
development format informed the Sometime, the Then they only few are resolved ensured
plan and budget villagers about municipality discuss in tole active and the through Small disputes
to tole the project. informed the and then to large numbers negotiation; and get resolved at
development Then they villagers about ward, and are inactive provision of tole committee
committee discuss in tole the project. municipality Project Justice level,
Project and then to Then they and finally the identification as committee in municipality
identification as ward, and discuss in tole municipality a process. Municipality also has Justice
a process. municipality and then to assembly Sometime, the Committee
144
Particulars Birtamod Damak Urlabari Sundar Mechinagar Itahari Rajbiraj Triyuga Dhankuta
Haraicha
Sometime, the and finally the ward, and approve the municipality
municipality municipality municipality project. Without informed the
informed the assembly and finally the women and villagers about
villagers about approve the municipality dalits the project
the project. project. Without assembly participation through FM.
Then they women and approve the project will not Then they
discuss in tole dalits project. Without be approved. discuss in tole
and then to participation women and We follow the and then to
ward, and project will not dalits government ward, and
municipality be approved. participation policy regarding municipality
and finally the We follow the project will not the participation and finally the
municipality government be approved. of women and municipality
assembly policy regarding We follow the dalits. assembly
approve the the participation government rule approve the
project. Without of women and regarding the project. Without
women and dalits. participation of women and
dalits women and dalits
participation dalits. participation
project will not project will not
be approved. be approved.
We follow the
government rule
regarding the
participation of
women and
dalits. In each
committee 33%
is women. And
Dalits are also
in committee as
per the GoN
rule.
Availability of Updation of Cadastral maps Cadastral Maps Cadastral Maps Survey is under Cadastral Maps Cadastral Maps Updation of Cadastral Maps
updated cadastral map is updated almost are not updated. are updated. process towards are updated. are not updated. cadastral map is are not updated.
cadastral maps under process entire updating There is some under process
municipality (2 cadastral maps confusion about
wards the extent of
remaining) jurisdiction. GIS
Map shows the
145
Particulars Birtamod Damak Urlabari Sundar Mechinagar Itahari Rajbiraj Triyuga Dhankuta
Haraicha
land belongs to
Dharan
Municipality,
however the
land has been
traditionally
used by Itahari
Sub-
metropolitan
city
Forest Areas One Community 300-400 ha 17 % areas in 13 Community Three - Community Community
Community Forest and Forest Land in municipality is Forests Community Forest and Forest and
Forest namely National Forest municipality. forest. managed by Forests in the National Forest National Forest
sundarnicha present in the Presence of 8 7 Community user groups municipality in the in the
Jhoda managed municipality community Forest and 2 namely municipality municipality
by user group forest and 1 collaborative Saraswati,
collaborative forest Hanspokhari
forest and Santinagar
managed by
User groups
Protected No No No No Chure - No No Chure - No
Area/Ramsar Environmental Environmental
Site Protected Area Protected Area
Source: Stakeholder consultation at Municipalities, Municipality Profiles. This data is based on the available data.
Baseline Information of Western Cluster municipalities (partial)
Baseline Information of Western Cluster municipalities
Particulars Pokhara Leknath Vyas Putalibazar Baglung Tansen Ramgram Tilottama Shuklagandaki
ULB Status Metropolitan Municipality Municipality Municipality Municipality Municipality Municipality Municipality
District Kaski Tanahun Syangia Baglung Palpa Parasi Rupandehi Tanahun
Population 444,936 81,277 70,277 59,919 51,419 62,698 100,149 39,462
Sex ratio 1.10 1.25 1.29 1.24 1.21 1.04 1.12 1.18
146
Particulars Pokhara Leknath Vyas Putalibazar Baglung Tansen Ramgram Tilottama Shuklagandaki
Climatic Zone Predominantly Tropical Tropical and Sub- Tropical Predominantly Tropical Tropical Tropical
subtropical and tropical subtropical
tropical
Land Use Agriculture land: Agriculture Agriculture land: 48% Agriculture Agriculture land: Agriculture Agriculture land:
40.29% land: 36.4% Barren: 0.02% land: 45.4% 58.4% land: 90.5% 69.48%
Barren: 0.63% Barren: 0.11% Forest: 50% Barren: 0.2% Barren: 0.7% Barren: 0.72% Barren: 0.4%
Forest: 46% Forest: 57.5% Residential: 1.4% Forest: 50% Forest: 36% Forest: 0.1% Forest: 10%
Residential: 8% Residential: Sand/ Residential: Residential: 2.8% Residential: Residential: 15%
Sand/ 0.32% gravel/Boulders: 1.8% 1.4% Sand/ 3.4% Sand/
gravel/Boulders: Sand/ Shrubland/ grassland: Sand/ gravel/Boulders: Sand/ gravel/Boulders:
4.5% gravel/Boulders: 1.32% gravel/Boulders: 1.8% gravel/Boulders: 2.1%
Shrubland/ 3% 1.7 Shrubland/ 2.71% Shrubland/
grassland: 0.5% Shrubland/ Shrubland/ grassland: 0.4% Shrubland/ grassland: 3.5%
grassland: 2.8% grassland: grassland:
1.32% 2.45%
Key municipality • Road • Solid waste Road upgradation; • Urban roads • Urban roads • Road • Road upgrade; • Road
services demanded Upgradation management Drainage and drainage and drainage upgrade; • Drainage upgradation
• Solid waste facility ( Management; • Safe and pure • Solid waste • Drainage Management • Drainage
management in especially for Safe and pure drinking collection. Management • solid waste Management,
rural wards 6 to 14 drinking water water, Segregation • Solid waste management, • safe drinking
• Water supply in wards) • Sewage and disposal management • water supply water,
rural wards • Solid waste management • Sewage • Water supply • solid waste
• Drainage along management management • Transportatio management
the roads • Water supply • Drinking water n in rural
• Public (lacking in suuply wards
Transportation wards 1,4,5) • Bus Terminal
• Road
upgradation
and drainage
Key Flooding in Seti • Flooding in • Flooding in During rainy During rainy • Flooding in • Flooding in • Flooding in the
Environmental and Mardi River Madi & Seti Aandhi khola, season there is season there is Tinahu river Tinahu river rivers and
issues River sumrekhola, problem of problem of • Water • Water pollution siltation in
• Water bodikhola, ringi flooding, water flooding, water pollution in in dug wells rainy season
pollution in khola pollution, pollution, dug wells
147
Particulars Pokhara Leknath Vyas Putalibazar Baglung Tansen Ramgram Tilottama Shuklagandaki
148
Particulars Pokhara Leknath Vyas Putalibazar Baglung Tansen Ramgram Tilottama Shuklagandaki
to take
action on
public
complaints
Forest Areas • Community • Community • Community Forest • Community • Community • Community • Community
Forest and Forest and and National Forest and Forest and Forest and Forest and
National National Forest present in National National National Forest National Forest
Forest present Forest the municipality Forest Forest present present in the present in the
in the present in the present in the in the municipality municipality
municipality municipality municipality municipality
149
Appendix I: Summary Information on the Type of Baseline Indicators
Weather and Long term climatological profile of the project area Secondary
Climatology Temperature (max/min), precipitation
Land Use Land Use pattern of immediate zone of Impact and Project Influence Area (PIA) Secondary
Cadastral map/land ownership document/record [only for new road] for immediate Zone of Impact and topographic and GIS
map for of PIA
Ambient Air Ambient Air Quality (at highest traffic volume area and closest recipient at the interval of 10km) Primary in case of site specific
• Level of PM10, PM2.5, CO, SO2, NOx secondary data of present time is
• Inventory of sensitive receptors like school, college, and hospital in the vicinity of the project area not available
•
Ambient Noise Ambient Noise Level (at highest traffic volume area and closest recipient at the interval of 10km), if primary data to Primary in case of site specific
be generated. secondary data of present time is
• Day and night time Noise Levels not available
• Inventory of sensitive receptors like school, college, and hospital in the vicinity of the project area
• Inventory of major noise generating sources/industries in PIA
Water Information on ground and surface water resources (only in new road construction) Secondary-Hydrogeology and
• Information of surface water resources in the PIA including tentative quantity, use and its distance from project site ground water availability
• Information on hydrogeology and availability of groundwater table(upto 10 m. below the road surface) Primary- quality monitoring and
inventory of surface water
resources
Soil Nature of soil in the RoW Nature of soil and fertility in the
• Soil profile RoW Secondary
Soil Quality- Secondary (DPR)
Natural Hazard Natural Hazard Threat Secondary
• Records on natural calamity like earthquake, flood, , drought, famine, etc. in the project area supported with local
consultation
Debris Disposal Site Identification of Debris Disposal Site, mainly for new alignment. Secondary
Tentative site for disposal of dismantled/construction debris may be identified, if scarifying is expected.
Quarry Sites and Identification of Licensed Quarry Sites and Borrow Areas Secondary
Borrow Areas
150
Probable Borrow Areas and Quarry sites to be used in the sub project should be listed out with lead distance and mode of
transportation
Biological Environment
Felling of Trees and Trees falling within direct impact zone Primary
Clearance of • Listing with coordinate of species, girth size of trees and poles within RoW
Vegetation Cover • Information of endemic, endangered, medicinal, protected species in 50 meter from road edge
• Information on offset areas for compensation plantation
• List ofProtected Tree Species in RoW
Forest Area Forest within the proposed RoW Primary and Secondary
• Legal status of forest land
• Block/Compartment Number of the forest area concerned
• Extent of Forest area to be acquired
• Delineation of affected forest area on map (cadastral map preferably)
• Threat to associated biodiversity (flora and fauna)
• Information of endemic, endangered, medicinal, protected species (flora and fauna)
Protected Protected Area/Ecologically Sensitive Areas/ Ramsar Sites/Important Bird Areas in PIA Primary and Secondary
Area/Ecologically • Information on presence of Protected Area (National Parks, Wildlife Reserve, Hunting Reserve, Conservation
Sensitive Areas/ Areas, Buffer Zones) / site of ecological importance like nesting, breeding ground, important bird areas, Ramsar
Ramsar sites, wildlife corridor/migration route, forest areas, any site of national/international importance etc. within PIA.
Sites/Important Bird Information should include GIS map showing distance of protected area site from the road alignment, its ecological
Areas condition and biodiversity
Biodiversity Floral and faunal community of PIA Secondary information through
• Floral and faunal community of PIA stakeholder consultation, literature
• Biodiversity of aquatic system study followed by primary survey
• Endangered/Vulnerable/rare/critically endangered species as per IUCN red list
• record of local extinction of any species or declining species (population decreasing day by day
Description of Environmental Baseline Information Required for the Water Supply Project
Environmental Baseline Information Source (Primary / Secondary)
Components/Concerns
Physical Environment
Geography Geographical information of project area Secondary
Location, physiography, geology, slope and elevation, drainage pattern, seismology, topography, landslide prone zones,
flood plain.
Contour map, flood passages and information on high levels flood periodicity as available data
151
Weather and Long term climatological profileof the project area Secondary
Climatology Temperature (max/min), precipitation, , record of natural calamity
Land Use Land Use pattern of Impact area including service areas and Project Influence Area (PIA) Secondary
Cadastral map/land ownership document/record of RoW and topographic and GIS maps of PIA
Ambient Air Baseline condition of Ambient Air Quality Primary in case of site specific
secondary data of present time is not
available
Ambient Noise Baseline condition of Ambient Noise Level through primary 24hr Monitoring Primary in case of site specific
• Day and night time noise level secondary data of present time is not
• Inventory of sensitive receptors like school, college, hospital etc. in the immediate impact area available
Water Information on ground water and surface water resources Secondary-Hydrogeology and ground
• Surface water resources in the PIA including tentative capacity, use and its distance from project site water availability
• Information on Ground water table Primary- Quality monitoring and
• Ground and surface water quality of the PIA, ( if t is to be used as source) inventory of Surface water resources
152
Protected Ecological condition of PIA Secondary
Area/Ecologically • Information on presence of Protected Area (National Parks, Wildlife Reserve, Hunting Reserve, Conservation Areas,
Sensitive Areas/ Buffer Zones) / site of ecological importance like nesting, breeding ground, Important Bird Areas, Ramsar Sites,
Ramsar Wildlife Corridor/Migration Route, Forest Areas, any site of national/international importance etc. within PIA.
Sites/Important Bird Information should include GIS Map showing distance of Protected Area site from project site, its ecological
Areas condition and biodiversity
• Record of local extinction of any species or declining species (population decreasing day by day)
Biodiversity Floral & Faunal Community of PIA Secondary information through
• Floral and faunal community of PIA stakeholder consultation, literature
• Biodiversity of aquatic system in case its within PIA study followed by primary survey
• Endangered/vulnerable/rare/critically endangered species as per IUCN red list
153
Water Information on ground water and surface water resources Secondary-Hydrogeology
• Inventory surface water resources in the PIA including tentative capacity, use and its distance from project site Primary- Quality monitoring and
• Information on hydrogeology at the treatment site inventory of Surface water resources
•
Soil Nature of soil Nature and type of soil Nature of soil and fertility in the PIA-
• Soil profile Secondary
Soil Quality- Secondary (DPR)
Natural Hazard Threat from Natural Hazard Secondary
• Records on natural calamity like flood, , epidemic, etc. in the project area supported with local consultation
• Land slide prone /geologically unstable slope areas with respect to GPS Coordinate
Debris Disposal Site Identification of Debris Disposal Site, if the conveyance size is more than 0.25 sq.m. Secondary (to be validated through
Tentative site for disposal of dismantled/construction debris may be identified stakeholder consultation)
Biological Environment
Felling of Trees and Trees falling within direct impact zone [construction site] Primary
clearance of Vegetation • Listing of Species, Girth size of affected Trees & Poles with respect to GPS Coordinates
Cover • Information of Endemic, Endangered, Medicinal, Protected species
• Details of affected protected tree species
Forest Area Acquisition of forest land for the project Primary and Secondary
• Legal status of forest land proposed for acquisition
• Block/Survey/Compartment No. of the area concerned
• Extent of Forest area to be acquired
• Delineation of affected forest area on map (Cadastral Map preferably)
• Threat to associated biodiversity (Flora & Fauna)
• Information of Endemic, Endangered, Medicinal, Protected species (Flora & Fauna)
Protected Ecological condition of treatment site Secondary
Area/Ecologically • Information on presence of Protected Area (National Parks, Wildlife Reserve, Hunting Reserve, Conservation
Sensitive Areas/ Areas, Buffer Zones) / site of ecological importance like nesting, breeding ground, Important Bird Areas, Ramsar
Ramsar Sites, Forest Areas, any site of national/international importance etc. within PIA. Information should include GIS
Sites/Important Bird Map showing distance of Protected area site from project site, its ecological condition and biodiversity
Areas
Biodiversity Floral and faunal community of PIA Secondary information through
• Floral and faunal (community of PIA stakeholder consultation, literature
• Biodiversity of aquatic system in case its within PIA study followed by primary survey
• Endangered/vulnerable/rare/critically endangered species as per IUCN red list
154
Record of communicable Collect data on communicable diseases in an around proposed treatment plant Secondary information
diseases
Description of Environmental Baseline Information required for Solid Waste Management Project
Environmental Baseline Information Source (Primary / Secondary)
Components/Concerns
Physical Environment
Geography Geographical information of Project Area Secondary
Location, physiography, geology, slope and elevation, drainage pattern, seismology, topography, landslide prone
zones, flood plain and river morphology.
Contour map, , flood passages and information on high levels flood periodicity of maximum available data
Weather and Climatology Long term climatological profile of the project area Secondary
Temperature (max/min), precipitation, wind direction, wind speed, cloud cover, humidity, record of natural calamity
Land Use Land Use pattern of immediate zone of Impact and Project Influence Area (PIA) around the Sanitary Secondary
Management Site and route from transshipment site
Cadastral map/land ownership document/record of around the Sanitary management site and 50 m on both sides
from the transshipment routeand topographic and GIS maps for Project Influence Area (PIA)
Ambient Air Baseline condition of Ambient Air Qualityat proposed Sanitary management site Primary in case of site specific
• Level of PM10, PM2.5, CO2, SOx, NOx, HC secondary data of present time is
• Indicators for odour, communicable dieses and vectors like moscutoes and fliees be added not available
• Inventory of sensitive receptors like school, college, hospital etc. in the vicinity of the project area
Ambient Noise • Noise measurement at nearest receptor Primary in case of site specific
secondary data of present time is
not available
Water Information on ground water and surface water resources at and downstream of the sanitary management site. Secondary-Hydrogeology
• Inventory Surface Water resources including tentative quantity, use and its distance from project site Primary- Quality monitoring and
inventorization of Surface water
Quality of Ground and Surface Water at the sanitary management site through primary monitoring resources
Soil • Nature and type of soil Nature of soil and fertility in the
• Soil profile PIA- Secondary
Soil Quality-Primary
155
Felling of Trees and clearance Trees falling within direct impact zone Sanitary management site and transshipment route Primary
of Vegetation Cover • Listing of Species, Girth size of affected Trees & Poles with respect to GPS Coordinates
• Information of Endemic, Endangered, Medicinal, Protected species
• Information on offset areas for tree plantation
• List of affected Protected Tree Species
Forest Area Acquisition of forest land for the project Primary and Secondary
• Legal status of forest land proposed for acquisition
• Block/Survey/Compartment No. of the area concerned
• Extent of Forest area to be acquired
• Delineation of affected forest area on map (Cadastral Map preferably)
• Threat to associated biodiversity (Flora & Fauna)
• Information of Endemic, Endangered, Medicinal, Protected species (Flora & Fauna)
Protected Area/Ecologically Ecological condition of PIA Primary and Secondary
Sensitive Areas/ Ramsar • Information on presence of Protected Area (National Parks, Wildlife Reserve, Hunting Reserve, Conservation
Sites/Important Bird Areas Areas, Buffer Zones) / site of ecological importance like nesting, breeding ground, Important Bird Areas, Ramsar
Sites, Wildlife Corridor/Migration Route, Forest Areas, any site of national/international importance etc. within
PIA. Information should include GIS Map showing distance of Protected area site from project site, its ecological
condition and biodiversity
• record of local extinction of any species or declining species (population decreasing day by day)
In case proposed land fill site is located within PIA, a detailed ecological assessment may be undertaken. The study
should cover biological diversity, species richness of the area; seasonal, Diurnal and nocturnal movement of wildlife
towards project site; probable threat from proposed project and suggested mitigation in consultation with concerned
stakeholders
Biodiversity Floral & Faunal community of PIA Secondary information through
• Floral and faunal community of PIA stakeholder consultation, literature
• Biodiversity of aquatic system in case its within PIA and 200 m downstream where treated latchet and accidental study followed by primary survey
seepage will merge.
• Endangered/Vulnerable/rare/critically endangered species as per IUCN red list
• occurrence of Protected Species in PIA
158
Appendix J: List of Ineligible Sub-Projects
Road sector
• New roads, road rehabilitation, road-surfacing or track upgrading of any kind inside critical natural habitats, forests, environmentally sensitive areas, protected areas (National Parks,
Wildlife Reserve, Hunting Reserve, Conservation Areas etc.), significant biodiversity and/or protected conservation zones
• Projects that may cause, or have the potential to result in permanent and/or significant damage to non-replicable cultural property, irreplaceable cultural relics, historical buildings and/or
archaeological sites
• Projects that may significantly convert or provide access into critical natural habitats or negatively affect rare or endangered species and their natural habitats
• New road construction that may cause habitat fragmentation and impact the wildlife corridors
• The projects that may result in large-scale involuntary land acquisition or significant physical displacement of affected communities or relocation of Indigenous Peoples that would
restrict or cease their access to traditional lands or resources
• Projects that does not meet minimum design standards with poor design or construction quality, particularly if located in vulnerable areas
Water supply
• Greenfield water supply projects: Projects involving withdrawal of surface water which may have a significantly reduce and create negative impacts13 on the quality, quantity and velocity
of the environmental flows that would affect the physical and ecological conditions, biodiversity (terrestrial and aquatic life) and ecosystem services of the surface water course at any
point in the water channel and its tributaries (from upstream, midstream and downstream).
• Brownfield water supply projects: Projects which result in the increased demand from the existing water source and if the watershed or aquifer feeding this source is not sufficient to meet
the increased demand14.
• Projects that will adversely affect the water supply and livelihoods of the communities in the project’s area of influence
• Projects which may result in abstraction of ground water in ground water stressed areas
• Projects that pass through critical natural habitats, forests, environmentally sensitive areas, significant biodiversity and/or protected conservation zones, protected areas (National Parks,
Wildlife Reserve, Hunting Reserve, Conservation Areas etc.)
• Projects that may cause, or have the potential to result in, permanent and/or significantly damage to non-replicable cultural property, irreplaceable cultural relics, historical buildings
and/or archaeological sites
• The projects that will result in large-scale involuntary land acquisition or significant physical displacement of affected communities, or relocation of Indigenous Peoples that would
restrict or cease their access to traditional lands or resources
• If the project would rely on the performance of an existing dam. The large dam (with a height of more than 15 m) triggers dam safety due diligence process and OP 4.37
Wastewater
13
To be assessed through detailed study of water availability, ecological assessment, assessment of permissible volume of water
14
To be assessed by determination of a water balance of the location of the water source and the demand from the existing water supply network and any informal extraction from deep wells,
shallow wells etc. to ensure that the replenishment rate in the water source is greater than the extraction rate of the water
159
• Treatment plant and effluent discharge is located/proposed to be located in critical natural habitats, forests, environmentally sensitive areas, significant biodiversity and/or protected
conservation zones, protected areas (National Parks, Wildlife Reserve, Hunting Reserve, Conservation Areas etc.) and environmentally fragile areas
• Projects that will cause, or have the potential to result in, permanent and/or significantly damage to non-replicable cultural property, irreplaceable cultural relics, historical buildings
and/or archaeological sites
• Projects that will adversely affect the water supply and livelihoods of the communities in the project’s area of influence
• The projects that will result in large-scale involuntary land acquisition or significant physical displacement of affected communities or relocation of Indigenous Peoples that would restrict
or cease their access to traditional lands or resources;
• Construction of wastewater treatment plant which receives industrial or hazardous influent without any pre-treatment to ensure that any incoming wastewater will not upset the designed
treatment process
Solid waste management
• Construction of a new landfill near a surface water body or aquifer, with the possibility of untreated leachate draining or contaminating any source of water supply, surface water or
groundwater resource or communities in the project’s area of influence
• Landfill site is proposed to be located in critical natural habitats, forests, environmentally sensitive areas, significant biodiversity and/or protected conservation zones, protected areas
(National Parks, Wildlife Reserve, Hunting Reserve, Conservation Areas etc.) and environmentally fragile area
• Construction of new landfill disposal site which may result in large-scale involuntary land acquisition or significant physical displacement of affected communities or relocation of
Indigenous Peoples that would restrict or cease their access to traditional lands or resources
• Waste to Energy projects with the installed capacity of greater than 25 MW or lower capacities with no air pollution control device or residual waste treatment process
• Projects involving management of significant quantities of toxic waste – toxic waste is defined as waste containing chemicals or materials that are capable of causing injury/death to life
having poisonous, radioactive, explosive, carcinogenic, mutagenic or teratogenic properties.
Storm water drainage system
• Storm water drainage network development or upgradation along new roads or existing roads inside critical natural habitats, forests, environmentally sensitive areas, protected areas
(National Parks, Wildlife Reserve, Hunting Reserve, Conservation Areas etc.), significant biodiversity and/or protected conservation zones
• Projects that would curtail, divert or reduce the environmental flows of surface water courses away from sources of water supply, agricultural lands or important water resources
• Storm water drainage projects resulting in the siltation or contamination of any surface water or groundwater resource or communities in the project’s area of influence
• Storm water drainage projects along New road construction that may cause habitat fragmentation and impact the wildlife corridors
160
Appendix K: COVID-19 considerations in construction/civil works projects
1. INTRODUCTION
The COVID-19 pandemic presents Governments with unprecedented challenges. Addressing COVID-19 related issues
in both existing and new operations starts with recognizing that this is not business as usual and that circumstances require
a highly adaptive responsive management design to avoid, minimize and manage what may be a rapidly evolving
situation. In many cases, we will ask Borrowers to use reasonable efforts in the circumstances, recognizing that what may
be possible today may be different next week (both positively, because more supplies and guidance may be available, and
negatively, because the spread of the virus may have accelerated).
This interim note is intended to provide guidance to teams on how to support Borrowers in addressing key issues
associated with COVID-19 and consolidates the advice that has already been provided over the past month. As such, it
should be used in place of other guidance that has been provided to date. This note will be developed as the global situation
and the Bank’s learning (and that of others) develops. This is not a time when ‘one size fits all’. More than ever, teams
will need to work with Borrowers and projects to understand the activities being carried out and the risks that these
activities may entail. Support will be needed in designing mitigation measures that are implementable in the context of
the project. These measures will need to take into account the capacity of the Government agencies, availability of supplies
and the practical challenges of operations on-the-ground, including stakeholder engagement, supervision and monitoring.
In many circumstances, communication itself may be challenging, where face-to-face meetings are restricted or
prohibited, and where IT solutions are limited or unreliable.
This note emphasizes the importance of careful scenario planning, clear procedures and protocols, management systems,
effective communication and coordination, and the need for high levels of responsiveness in a changing environment. It
recommends assessing the current situation of the project, putting in place mitigation measures to avoid or minimize the
chance of infection, and planning what to do if either project workers become infected or the work force includes workers
from proximate communities affected by COVID-19. In many projects, measures to avoid or minimize will need to be
implemented at the same time as dealing with sick workers and relations with the community, some of whom may also
be ill or concerned about infection. Borrowers should understand the obligations that contractors have under their existing
contracts (see Section 3), require contractors to put in place appropriate organizational structures (see Section 4) and
develop procedures to address different aspects of COVID-19 (see Section 5).
These requirements have been enhanced through the introduction of the ESF into the SPDs (edition dated July 2019). The
general FIDIC clause referred to above has been strengthened to reflect the requirements of the ESF. Beyond FIDIC’s
general requirements discussed above, the Bank’s Particular Conditions include a number of relevant requirements on the
Contractor, including:
• to provide health and safety training for Contractor’s Personnel (which include project workers and all personnel that
the Contractor uses on site, including staff and other employees of the Contractor and Subcontractors and any other
personnel assisting the Contractor in carrying out project activities)
• to put in place workplace processes for Contractor’s Personnel to report work situations that are not safe or healthy
• gives Contractor’s Personnel the right to report work situations which they believe are not safe or healthy, and to remove
themselves from a work situation which they have a reasonable justification to believe presents an imminent and serious
danger to their life or health (with no reprisal for reporting or removing themselves)
• requires measures to be in place to avoid or minimize the spread of diseases including measures to avoid or minimize
the transmission of communicable diseases that may be associated with the influx of temporary or permanent contract-
related labor
• to provide an easily accessible grievance mechanism to raise workplace concerns
Where the contract form used is FIDIC, the Borrower (as the Employer) will be represented by the Engineer (also referred
to in this note as the Supervising Engineer). The Engineer will be authorized to exercise authority specified in or
necessarily implied from the construction contract. In such cases, the Engineer (through its staff on site) will be the
interface between the PIU and the Contractor. It is important therefore to understand the scope of the Engineer’s
responsibilities. It is also important to recognize that in the case of infectious diseases such as COVID-19, project
management – through the Contractor/subcontractor hierarchy – is only as effective as the weakest link. A thorough
review of management procedures/plans as they will be implemented through the entire contractor hierarchy is important.
Existing contracts provide the outline of this structure; they form the basis for the Borrower to understand how proposed
mitigation measures will be designed and how adaptive management will be implemented, and to start a conversation
with the Contractor on measures to address COVID-19 in the project.
(d) CLEANING AND WASTE DISPOSAL Conduct regular and thorough cleaning of all site facilities, including
offices, accommodation, canteens, common spaces. Review cleaning protocols for key construction equipment
(particularly if it is being operated by different workers). This should include: • Providing cleaning staff with adequate
cleaning equipment, materials and disinfectant. • Review general cleaning systems, training cleaning staff on appropriate
cleaning procedures and appropriate frequency in high use or high-risk areas. • Where it is anticipated that cleaners will
be required to clean areas that have been or are suspected to have been contaminated with COVID-19, providing them
with appropriate PPE: gowns or aprons, gloves, eye protection (masks, goggles or face screens) and boots or closed work
shoes. If appropriate PPE is not available, cleaners should be provided with best available alternatives. • Training cleaners
in proper hygiene (including handwashing) prior to, during and after conducting cleaning activities; how to safely use
PPE (where required); in waste control (including for used PPE and materials). • Any medical waste produced during the
care of ill workers should be collected safely in designated containers or bags and treated and disposed of following
relevant requirements (e.g., national, WHO). If open burning and incineration of medical wastes is necessary, this should
be for as limited a duration as possible. Waste should be reduced and segregated, so that only the smallest amount of
waste is incinerated (for further information see WHO interim guidance on water, and sanitiation and waste management
for COVID-19)
(e) ADJUSTING WORK PRACTICES Consider changes to work processes and timings to reduce or minimize contact
between workers, recognizing that this is likely to impact the project schedule. Such measures could include: • Decreasing
the size of work teams. • Limiting the number of workers on site at any one time. • Changing to a 24-hour work rotation.
• Adapting or redesigning work processes for specific work activities and tasks to enable social distancing, and training
workers on these processes. • Continuing with the usual safety trainings, adding COVID-19 specific considerations.
Training should include proper use of normal PPE. While as of the date of this note, general advice is that construction
workers do not require COVID-19 specific PPE, this should be kept under review (for further information see WHO
interim guidance on rational use of personal protective equipment (PPE) for COVID-19). • Reviewing work methods to
reduce use of construction PPE, in case supplies become scarce or the PPE is needed for medical workers or cleaners.
This could include, e.g. trying to reduce the need for dust masks by checking that water sprinkling systems are in good
working order and are maintained or reducing the speed limit for haul trucks. • Arranging (where possible) for work
breaks to be taken in outdoor areas within the site. • Consider changing canteen layouts and phasing meal times to allow
for social distancing and phasing access to and/or temporarily restricting access to leisure facilities that may exist on site,
including gyms. • At some point, it may be necessary to review the overall project schedule, to assess the extent to which
it needs to be adjusted (or work stopped completely) to reflect prudent work practices, potential exposure of both workers
and the community and availability of supplies, taking into account Government advice and instructions.
3
(f) PROJECT MEDICAL SERVICES
Consider whether existing project medical services are adequate, taking into account existing infrastructure (size of
clinic/medical post, number of beds, isolation facilities), medical staff, equipment and supplies, procedures and training.
Where these are not adequate, consider upgrading services where possible, including:
• Expanding medical infrastructure and preparing areas where patients can be isolated. Guidance on setting up isolation
facilities is set out in WHO interim guidance on considerations for quarantine of individuals in the context of containment
for COVID-19). Isolation facilities should be located away from worker accommodation and ongoing work activities.
Where possible, workers should be provided with a single well-ventilated room (open windows and door). Where this is
not possible, isolation facilities should allow at least 1 meter between workers in the same room, separating workers with
curtains, if possible. Sick workers should limit their movements, avoiding common areas and facilities and not be allowed
visitors until they have been clear of symptoms for 14 days. If they need to use common areas and facilities (e.g. kitchens
or canteens), they should only do so when unaffected workers are not present and the area/facilities should be cleaned
prior to and after such use.
• Training medical staff, which should include current WHO advice on COVID-19 and recommendations on the specifics
of COVID-19. Where COVID-19 infection is suspected, medical providers on site should follow WHO interim guidance
on infection prevention and control during health care when novel coronavirus (nCoV) infection is suspected.
• Training medical staff in testing, if testing is available.
• Assessing the current stock of equipment, supplies and medicines on site, and obtaining additional stock, where required
and possible. This could include medical PPE, such as gowns, aprons, medical masks, gloves, and eye protection. Refer
to WHO guidance as to what is advised (for further information see WHO interim guidance on rational use of personal
protective equipment (PPE) for COVID-19).
• If PPE items are unavailable due to world-wide shortages, medical staff on the project should agree on alternatives and
try to procure them. Alternatives that may commonly be found on constructions sites include dust masks, construction
gloves and eye goggles. While these items are not recommended, they should be used as a last resort if no medical PPE
is available.
• Ventilators will not normally be available on work sites, and in any event, intubation should only be conducted by
experienced medical staff. If a worker is extremely ill and unable to breathe properly on his or her own, they should be
referred immediately to the local hospital (see (g) below).
• Review existing methods for dealing with medical waste, including systems for storage and disposal (for further
information see WHO interim guidance on water, sanitation and waste management for COVID-19, and WHO guidance
on safe management of wastes from health-care activities).
(j) TRAINING AND COMMUNICATION WITH WORKERS Workers need to be provided with regular
opportunities to understand their situation, and how they can best protect themselves, their families and the community.
They should be made aware of the procedures that have been put in place by the project, and their own responsibilities in
implementing them. • It is important to be aware that in communities close to the site and amongst workers without access
to project management, social media is likely to be a major source of information. This raises the importance of regular
information and engagement with workers (e.g. through training, town halls, toolboxes) that emphasizes what
management is doing to deal with the risks of COVID-19. Allaying fear is an important aspect of work force peace of
mind and business continuity. Workers should be given an opportunity to ask questions, express their concerns, and make
suggestions.
• Training of workers should be conducted regularly, as discussed in the sections above, providing workers with a clear
understanding of how they are expected to behave and carry out their work duties.
• Training should address issues of discrimination or prejudice if a worker becomes ill and provide an understanding of
the trajectory of the virus, where workers return to work.
• Training should cover all issues that would normally be required on the work site, including use of safety procedures,
use of construction PPE, occupational health and safety issues, and code of conduct, taking into account that work
practices may have been adjusted.
• Communications should be clear, based on fact and designed to be easily understood by workers, for example by
displaying posters on handwashing and social distancing, and what to do if a worker displays symptoms.
ANNEX
WHO Guidance
Advice for the public
WHO advice for the public, including on social distancing, respiratory hygiene, self-quarantine, and seeking medical
advice, can be consulted on this WHO website: https://www.who.int/emergencies/diseases/novel-coronavirus-
2019/advice-for-public
Technical guidance
Infection prevention and control during health care when novel coronavirus (nCoV) infection is suspected, issued on 19
March 2020
Coronavirus disease (COVID-19) outbreak: rights, roles and responsibilities of health workers, including key
considerations for occupational safety and health, issued on 18 March 2020
Risk Communication and Community Engagement (RCCE) Action Plan Guidance COVID-19 Preparedness and
Response, issued on 16 March 2020
Considerations for quarantine of individuals in the context of containment for coronavirus disease (COVID-19), issued
on 19 March 2020
Operational considerations for case management of COVID-19 in health facility and community, issued on 19 March
2020
Rational use of personal protective equipment for coronavirus disease 2019 (COVID-19), issued on 27 February 2020
Getting your workplace ready for COVID-19, issued on 19 March 2020
Water, sanitation, hygiene and waste management for COVID-19, issued on 19 March 2020
Safe management of wastes from health-care activities issued in 2014
Advice on the use of masks in the community, during home care and in healthcare settings in the context of the novel
coronavirus (COVID-19) outbreak, issued on March 19, 2020
ILO GUIDANCE
ILO Standards and COVID-19 FAQ, issued on March 23, 2020 (provides a compilation of answers to most frequently
asked questions related to international labor standards and COVID-19)
MFI GUIDANCE
IDB Invest Guidance for Infrastructure Projects on COVID-19: A Rapid Risk Profile and Decision Framework
KfW DEG COVID-19 Guidance for employers, issued on 31 March 2020
CDC Group COVID-19 Guidance for Employers, issued on 23 March 2020