Professional Documents
Culture Documents
Activity Template - Project Plan
Activity Template - Project Plan
Activity Template - Project Plan
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10
1.11
1.12
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
2.11
3.00
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
4
4.1
4.2
4.3
4.4
4.5
Sauce & Spoon Project Plan
Task
Ship Tablets
If the software is not on 3.0 it could take 3 days, otherwise its a load
and reboot around 4 hours (Flatplate version dependent). There is 3-4
hours work intergrating the POS system without the upgrade.
Images of food items
This is dependent andphotos,
on the the locations
needs are
testneeded
deployment on the tablet,
prepared for social media, email, and website update
needs planning and testing at first POS integrations test
Seydou stated 7-10 days with an overnight for any damaged goods.
Update: 3 -4 days will be added to shipping. We are launching with
older devices and will swap to new with Terrific Tablets about a month
after full public launch.
Developer should have all the materials from marketing, create the
site, but not enabled public yet.
Will need before hours access to North and Downtown locations. Store
may need to close during installation. Check electrician schedule and
schedule store close.
Separate secure Wi-Fi network verified
Customer survey for launch data on satisfaction
Wait staff will be informed by management. The meting itself should be
about one hour, but there are two locations and buffer for missing staff
This should take about one work week.
tablets should be available and configured for the pre-launch tests
Carter is assigned this task. It takes about 3 - 4 hours, but we do have
to upload at two locations.
Card processing test
Marketing will provide material and work directly with vendor
Managers will pass training direct instead of third party. Training may
need to beperformed at both locations. Two hours training with an hour
before and after for prep/questions.
Wait staff will be trained by the managers. This needs to happen at
both locations with possibility of missing staff. Full training cycle like
managers at 4 hours.
Reassure wait staff that tips will be simple and available Included during training
Have a small group of participants test the tablets before public rollout
Launch anouncement media only
3 days
3 days
3 days
3 days
2 days
1 day
2 days
2 days
7 days
2 days
3 days
oing operations
3 days
2 days
3 days
1 day
10 days
7 days
4 days
2 days
2 days
1 day
5 days
2 days
1 1/2 days
1/2 day
3 days
1 day
1 day
ed during training
1 day
2 days
1 day
1 day
1/2 day
oing operations
oing operations
PHASE ONE PHASE TWO PHA
WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6 WEEK 7
W R F M T W R F M T W R F M T W R F M T W R F M T W
PHASE THREE PHASE FOUR
WEEK 7 WEEK 8 WEEK 9 WEEK 10 WEEK 11 WEEK 12
R F M T W R F M T W R F M T W R F M T W R F M T W R
WEEK 12
F
Task Brainstorm
Task
Milestone 1: Vendor Research, Selection, Marketing
Prep, Restuarant Baseline
Get vendor options on packages for tablets
Get marketing design options
Get website developer options
Get foodtablet
Review photographer and location
vendor options and getphotography
stakeholderoptions
agreement
Order
Reviewtablets and installation
marketing design optionspackage
and get stakeholder
agreement, sign contract
Review photography vendor, sign contract
Finalize menu options
Review website developer options, sign contract
Coupon options created
Restaurant2:baseline
Milestone needed Requirements, Marketing
Pre-installation
Material, Physical Prep,
POS Software update and integration
Schedule
Marketing photo shoots
creation at North
of email, and
social Downtown
media, tablet
app advertising, coupons, and website update
Plan for the physical security of devices
Tablet
Website received
update in shipping
backend created and queued for
deployment
Install and verify wiring for each table
Verify Wi-Fi function and load
Develop customer
Pre-training: Anounce survey
tablet plan through
general managers
Pre-training
Milestone 3: planning
Test Install, Training, Marketing Test,
Training,
Full Pre-open
physical install Sunday Test at North and
of all tablets
Downtown
Upload new menu items and coupons
Verify full customer checkout through tablet
Verify marketing advertising functions
Training managers for staff training
Training wait staff
Demostrate tipping on the app during training
Run
Launcha pre-test on Sunday
anouncement morning
marketing in email, social media,
webstie and restaurants
Milestone 4: Full Launch
Full website re-design launch
Enable full depolyment to each table at the bar of
North and Downtown
Run follow up marketing in email, social media,
website, and restaurants
Restaurant baseline - new stats
Customer survey run
Estimated Duration
Notes (Days)
Optimistic
3 days 5 days L
3 days 5 days M
3 days 5 days M
3 days 5 days L
2 days 3 days M
1 day 2 days M
2 days 3 days M
2 days 3 days L
7 days 14 days L
2 days 3 days M
3 days 5 days M
On-going operations H
3 days 4 days L
2 days 5 days L
3 days 5 days M
1 day 3 days M
13 14 M
7 days 10 days M
4 days 5 days M
2 days 3 days M
2 days 3 days H
1 day 2 days H
5 days 7 days M
2 days 3 days M
1 day 2 days L
.5 days 1 day M
3 days 5 days L
1 day 2 days M
1 day 2 days L
Included in training M
Fixed date and value M
2 days 3 days H
1 day 2 days M
ch date at North and Downtown M
.5 days 1 day M
On-going operations H
On-going operations
Additional Resources
Title Link