Professional Documents
Culture Documents
Material Requirements Planning (MRP) : Computer
Material Requirements Planning (MRP) : Computer
Material Requirements Planning (MRP) : Computer
1
Independent and Dependent Demand
Independent demand: Demand for final products.
Dependent demand: Demand fort items that are subassemblies or
component parts to be used in production of finished goods.
Independent Demand
A
Dependent Demand
B(4) C(2)
The book claims that “the independent demand is continuous while the
dependent demand is lumpy”. I do not believe in this statement.
Indep. Demand
Dep. Demand
“Lumpy” demand
Stable demand
Time Time
Amount on hand
Amount on hand
Safety stock
Time Time 3
The dependent demand is not necessarily any
lumpier than the independent demand
• Example: Say shoe demand rate is 80 pairs per week at a
retailer. The demand rate for shoe sole is 80 for left and 80
for the right pair. The demand rate for shoe laces is 160
per week.
• Example continued: What is the demand rate for the shoe
lace supplier? Still 160 per week. But if the orders for the
laces are placed once a week, lace demand is lumpy.
Changes
Order releases
Master
schedule Planned-order
schedules
Primary
reports Exception reports
Bill of Planning reports
materials MRP computer Secondary
Performance-
programs reports control
reports
Inventory
records Inventory
transaction
5
MRP Inputs: 1. MPS
7
Product Structure Tree
Level Chair
0
1 Leg Back
Assembly Seat Assembly
8
Explosion Example
B(2) C
B(2) C
Assembly
Subassembly
Fabrication
Procurement
1 2 3 4 5 6 7 8 9 10
12
Assembly Time Chart
Procurement of
raw material D Fabrication
of part E
Subassembly A
Procurement of Final assembly
raw material F and inspection
Procurement of
part C
Procurement of
part H
Subassembly B
Procurement of Fabrication
raw material I of part G
1 2 3 4 5 6 7 8 9 10 11
Days
13
MRP input: 3. Inventory levels
• Beginning inventory on hand
• Scheduled receipts
– Pipeline inventory not received yet but it is in the
process of coming to the inventory. We know
when this will be available for use.
14
MPR Processing
• Gross requirements
– Total expected demand
• Scheduled receipts
– Open orders scheduled to arrive
• Planned on hand
– Expected inventory on hand at the beginning of each time period
• Net requirements
– Actual amount needed in each time period
• Planned-order receipts
– Quantity expected to received at the beginning of the period
– Offset by lead time
• Planned-order releases
– Planned amount to order in each time period
15
MRP Processing
Periods 0 1 2 3
Gross requirements 6 11 7 Inputs
Scheduled receipts 2 3 0
Projected on hand 10 6 0 0
Net requirements 0 2 7
Outputs
Planned order receipts 2 7
Planned order releases 2 7
17
Figure 13-8
18
Other Considerations
• Safety Stock
– Not much for items with dependent demand
• Lot sizing
– Lot-for-lot ordering
– Economic order quantity
– Fixed-period ordering
– Part-period model
19
MRP example with Lot size=5, LT=2 and 1 level
Periods 0 1 2 3
Gross requirements 6 11 9 Inputs
Scheduled receipts 2 3 0
Projected on hand 10 6 3 4
Net requirements 5 10
Outputs
Planned order receipts 5 10
Planned order releases 5 10
20
Figure 13-9
21