Type of improvements : THREE STOREY COMMERCIAL BUILDING WITH BASEMENT AND ROOF DECK(CONCRETE)
Floor area : 415.88 sqm.
1.00 say 1.00 : lot : Delivery and Pull-out Charges : 5,000.00 : 5,000.00
Total for Scaffolding Works P 62,536.64
V. REMOVAL OF MASONRY
Total Area of 6" CHB Masonry = 1,536.65 x 0.125 = 192.08 cum
Total Area of 4" CHB Masonry = 240.13 x 0.100 = 24.01 cum
Total Volume of Masonry = 216.09 cum
REFERENCE:
[1]
DO no. 22 Series of 2015: Revised Guidelines in the Preparation of Approved Budget for the Contructor (ABC)
[2]
DO no. 68 Series of 2016: Road Costruction Cost Estimation Manual
[3]
Standard Labor Rates for DPWH Regional/District Engineering Offices (Memorandum: January 7, 2019)
[4]
DO no. 137 Series of 2017 Cost Estimation Manual for Low Rise Buildings
NOTES : UNIT COSTS ARE BASED ON THE DPWH'S CONSTRUCTION MATERIALS PRICE DATA AS OF 4th QUARTER OF CY 2016.
VINCENT C. PAGDATOON
MARK JOSEPH C. DOMINGO
Engineer II Engineer III
3.150 cu.m
Class A Concrete Volume Factor [1] Quantity
Cement = 3.15 x 9.00 = 28.35 bags
Sand = 3.15 x 0.50 = 1.58 cu.m.
Gravel = 3.15 x 1.00 = 3.15 cu.m.
1.995 cu.m
Class A Concrete Volume Factor [1] Quantity
Cement = 2.00 x 9.00 = 17.96 bags
Sand = 2.00 x 0.50 = 1.00 cu.m.
Gravel = 2.00 x 1.00 = 2.00 cu.m.
4.657 cu.m
Class B Concrete Volume Factor [1] Quantity
Cement = 4.66 x 8.00 = 37.25 bags
Sand = 4.66 x 0.50 = 2.33 cu.m.
Gravel = 4.66 x 1.00 = 4.66 cu.m.
2.438 cu.m
Class A Concrete Volume Factor [1]
Quantity
Cement = 2.44 x 9.00 = 21.94 bags
Sand = 2.44 x 0.50 = 1.22 cu.m.
Gravel = 2.44 x 1.00 = 2.44 cu.m.
11.819 cu.m
Class A Concrete Volume Factor [1] Quantity
Cement = 11.82 x 9.00 = 106.37 bags
Sand = 11.82 x 0.50 = 5.91 cu.m.
Gravel = 11.82 x 1.00 = 11.82 cu.m.
B. Formworks/Scaffoldings
Formworks
a. Column Perimeter = 2*(width x thickness) + 0.2 [1]
Perimeter Height Pieces Quantity
C1 = 0.90 x 4.75 x 8.00 = 34.20
C2 = 1.00 x 4.75 x 2.00 = 9.50
C3 = 1.00 x 4.75 x 2.00 = 9.50
53.200 sq.m.
Area Factor [1] No. of Uses
1/2" Ordinary Plywood = 53.20 / 2.880 / 2.00 = 9.24 say 10.00 pcs
No. of Plywood Factor [1] No. of Uses
2" x 2" Lumber for Column = 10.00 x 29.670 / 2.00 = 148.35 bd.ft.
Total Board Foot Factor [1]
Assorted Common Wire Nails = 148.35 x 0.018 = 2.67 kgs
Scaffoldings
Total Length
a. Column = 57.00 m
Using 2" x 2" Total Length Factor [1] No. of Uses Quantity
Vertical Support: 57.00 x 4.70 / 2.00 = 133.95 bdft
Horizontal Support: 57.00 x 21.00 / 2.00 = 598.50 bdft
Diagonal Braces: 57.00 x 11.70 / 2.00 = 333.45 bdft
Total Board Foot Factor [1]
Common Wire Nails 1,065.90 x 0.018 = 19.19 kgs
Total Length
b. Roof beam = 51.60 m
Using 2" x 2" Total Length Factor [1] No. of Uses Quantity
Vertical Support: = 51.60 x 4.00 / 2.00 = 103.20 bd.ft.
Horizontal Support: = 51.60 x 4.70 / 2.00 = 121.26 bd.ft.
Total Board Foot Factor [1]
Assorted Common Wire Nails = 224.46 x 0.018 = 4.04 kgs
Total Area
c. Slab = 4.50 sq.m.
Using 2" x 2" Total Area Factor [1] No. of Uses Quantity
Vertical Support: = 4.50 x 6.10 / 2.00 = 13.73 bd.ft.
Total Board Foot Factor [1]
Assorted Common Wire Nails = 13.73 x 0.018 = 0.25 kgs
C. Reinforcement
a. Column Footing
>RSB C.F1= 12 mm Ø - 6.0 m Length
1.00
No. of pcs. Longitudinal = + 1.00 = 8.00
No. of pcs. Longitudinal = + 1.00 = 8.00
0.16
1.00
No. of pcs. Transverse = + 1.00 = 8.00
0.16
6.00
No. of pcs. per comm'l L = = 4.62 say 4.00 pcs
1.30
b. Column
>C1 Main bar= 12 mm Ø - 6.00 m Length
given length = 4.75 m No. of bars= 4.00 pcs
total length with dev't length = 5.25 m No. of col.= 8.00 pcs
6.00
No. of pcs. per comm'l L = = 1.14 say 1.00 pcs
5.25
=[ 4.00 / 1.00 ] x [ 8.00 ]= 32.00 pcs
no. of bar weight per 6m length [1]
c. Wall Footing
>RSB W.F Longitudinal= 10 mm Ø - 6.00 m Length
given length = 73.92 m qty = 1.00 pcs
total length with dev't length = 79.92 m No. of bars = 3.00 pcs
79.92
No. of pcs. per comm'l L = = 13.32 say 14.00 pcs
6.00
=[ 14.00 x 1.00 ] x [ 3.00 ]= 42.00 pcs
no. of bar weight per 6m length [1]
d. Roof Beam
>RB Main bar= 12 mm Ø - 6.00 m Length
given length = 51.60 m No. of bars= 4.00 pcs
total length with dev't length = 57.60 m No. of beam= 1.00 pcs
57.60
No. of pcs. per comm'l L = = 9.60 say 10.00 pcs
6.00
=[ 10.00 x 4.00 ] x [ 1.00 ]= 40.00 pcs
no. of bar weight per 6m length [1]
e. Slab
Slab on fill (Main)
>RSB Slab Longitudinal= 10 mm Ø - 6.00 m Length
given length = 10.00 m spacing = 0.50 m
total length with dev't length = 10.50 m No. of bars = 16.00 pcs
10.50
No. of pcs. per comm'l L = = 1.75 say 2.00 pcs
6.00
= 2.00 x 16.00 = 32.00 pcs
no. of bar weight per 6m length [1]
c. Cement Plaster Plastered Area (x2) (Class B) Factor [1] Quantity + 5% allow for wastage [4]
Cement = 385.27 x 0.144 = 55.48 = 58.25 bags
Sand = 385.27 x 0.012 = 4.62 = 4.85 cu.m.
5.42 sq.m.
29.23 sq.m.
B. Built-in cabinets
L=2.1m surface area
1/2 ordinary plywood w/ S4S
a. Hanging cabinet-1 = lumber, hinges, door and door W=0.60m = 5.50 = 1.00 unit
handle L=2.2m
1/2 ordinary plywood w/ S4S H=0.63m
b. Hanging cabinet-2 = lumber, hinges, door and door W=0.60m = 15.84 = 1.00 unit
handle L=2.18m
1/2 ordinary plywood w/ S4S H=2.40m
c. Hanging cabinet-3 = lumber, hinges, door and door W=0.60m = 8.18 = 1.00 unit
handle L=1.15m
1/2 ordinary plywood w/ S4S H=1.00m
d. Hanging cabinet-4 = lumber, hinges, door and door W=0.60m = 7.68 = 2.00 units
handle L=4.17m
1/2 ordinary plywood w/ S4S H=1.80m
e. Hanging cabinet-5 = lumber, hinges, door and door W=0.40m = 16.13 = 1.00 unit
handle
H=1.40m
C. Panel Wall
Gross Area Opening Net Area
Area = 17.46 - 3.87 = 13.59
Area = 13.59 sq.m.
Using: 2" x 2" s4s Lumber, spaced at 40cm x 40cm [1]
D. Ceiling
Gross Area Opening Net Area
Main = 66.83 - 0.00 = 66.83
Balcony = 43.45 - 0.00 = 43.45
Area = 110.28 sq.m.
Using: 2" x 2" s4s Lumber, spaced at 40cm x 40cm [1]
1.94 say 1.94 : sqm : Main door- panel door : 2500.00 : 4,837.50
1.61 say 1.61 : sqm : Kitchen door- flush door : 650.00 : 1,048.13
4.92 say 4.92 : sqm : Bedroom door- flush door : 650.00 : 3,198.00
1.51 say 1.51 : sqm : CR door- flush door : 590.00 : 887.95
6.00 say 6.00 : pcs : Schlage lockset (Door Knob) : 390.00 : 2,340.00
12.00 say 12.00 : pair : Hinges (50mm x 101mm) : 65.00 : 780.00
1.00 say 1.00 : sqm : Main door- Alum. Screen door : 3000.00 : 3,000.00
1.00 say 1.00 : sqm : Kitchen Alum. Screen door : 3000.00 : 3,000.00
5.50 say 5.50 : sqm : Hanging cabinet-1 : 560.00 : 3,081.12
15.84 say 15.84 : sqm : Hanging cabinet-2 : 560.00 : 8,870.40
8.18 say 8.18 : sqm : Hanging cabinet-3 : 560.00 : 4,578.56
15.36 say 15.36 : sqm : Hanging cabinet-4 : 560.00 : 8,601.60
16.13 say 16.13 : sqm : Hanging cabinet-5 : 560.00 : 9,033.92
9.44 say 10.00 : pcs : 1/2" Ordinary Plywood : 530.00 : 5,300.00
38.29 say 39.00 : pcs : 1/4" Ordinary Plywood : 295.00 : 11,505.00
790.14 say 791.00 : bdft : Good Lumber : 45.00 : 35,595.00
4.09 say 4.50 : kg : Common nails : 59.00 : 265.50
B. Truss
a. Wood Framing Width Pcs 2"x3"
Main = 12.00 20.00 = 240.00 m say 393.60 bdft
Balcony = 10.64 7.00 = 74.48 m say 122.15 bdft
B. Steel Gate
Item Description Dimension Area Quantity
a. Steel gate D-7 = Steel gate grilles 0.86m x 2.10m = 1.806 = 1.00 unit
11.81 say 11.81 : sq.m. : Jalousie Window with screen and steel grilles : 1,550.00 : 18,309.38
1.00 say 1.00 : sq.m. : Steel Casement Window-2 : 1,900.00 : 1,900.00
0.24 say 0.24 : sq.m. : Steel Casement Window-3 : 1,900.00 : 456.00
0.40 say 0.40 : sq.m. : Steel Casement Window-4 : 1,900.00 : 760.00
0.65 say 0.65 : sq.m. : Steel Casement Window-5 : 1,900.00 : 1,235.00
1.81 say 2.00 : sq.m. : Steel gate D-7 : 1,000.00 : 2,000.00
5.00 say 5.00 : kgs : Welding rod : 85.00 : 425.00
b. CHB Wall
CHB (4" thick) Perimeter Height Quantity Area
Perimeter Wall = 6.80 x 1.35 x 1.00 = 9.18 sq.m.
B. Wooden Surface
Painted Area = 150.84 sq.m.
Area No. of Coatings Factor [1]
Quantity
Flatwall Latex Paint = 150.84 x 2.00 / 35.00 = 8.62 gal
Total gals. of Paint Factor [1]
REFERENCE:
[1]
"Simplified Construction Estimate" by Max B. Fajardo Jr.
[2]
"Handbook of Construction Estimate" by Rheno A. Velasco
[3]
ASEP Steel Handbook
[4]
IRR of Republic Act No. 10752, Section 6 - Replacement Cost
[5]
"Estimating Bill of Materials" by Vicente A. Tagayun
SOUTH EAST METRO MANILA EXPRESSWAY (C6)
DETAILED UNIT PRICE ANALYSIS (DUPA) [2]
Class 1 - NCR (Taguig City)
Designation No. of Person/s No. of Hour/s Hourly Rate [3] Amount (Php)
A. Labor
Truck Mounted Crane (31 - 35 mt) for 3 floors and up 1 0.25 1,861.00 465.25
Dump Truck (12 yd3) 1 0.125 1,420.00 177.50
Cutting Outfit 1 0.25 45.45 11.36
Minor Tools (10% of Labor Cost) 31.00
REFERENCE:
[1]
DO no. 22 Series of 2015: Revised Guidelines in the Preparation of Approved Budget for the Contructor (ABC)
[2]
DO no. 68 Series of 2016: Road Costruction Cost Estimation Manual
[3]
Standard Labor Rates for DPWH Regional/District Engineering Offices (Memorandum: January 7, 2019)
[4]
DO no. 137 Series of 2017 Cost Estimation Manual for Low Rise Buildings
SOUTH EAST METRO MANILA EXPRESSWAY (C6)
DETAILED UNIT PRICE ANALYSIS (DUPA) [2]
Class 1 - NCR (Taguig City)
Designation No. of Person/s No. of Hour/s Hourly Rate [3] Amount (Php)
A. Labor
Truck Mounted Crane (31 - 35 mt) for 3 floors and up 1 1.000 1,861.00 1,861.00
Service Truck/Cargo Truck (2-5 mt) 1 1.000 783.00 783.00
Cutting Outfit 1 1.000 45.45 45.45
Minor Tools (10% of Labor Cost) 68.78
REFERENCE:
[1]
DO no. 22 Series of 2015: Revised Guidelines in the Preparation of Approved Budget for the Contructor (ABC)
[2]
DO no. 68 Series of 2016: Road Costruction Cost Estimation Manual
[3]
Standard Labor Rates for DPWH Regional/District Engineering Offices (Memorandum: January 7, 2019)
[4]
DO no. 137 Series of 2017 Cost Estimation Manual for Low Rise Buildings
SOUTH EAST METRO MANILA EXPRESSWAY (C6)
DETAILED UNIT PRICE ANALYSIS (DUPA) [2]
Class 1 - NCR (Taguig City)
Designation No. of Person/s No. of Hour/s Hourly Rate [3] Amount (Php)
A. Labor
REFERENCE:
[1]
DO no. 22 Series of 2015: Revised Guidelines in the Preparation of Approved Budget for the Contructor (ABC)
[2]
DO no. 68 Series of 2016: Road Costruction Cost Estimation Manual
[3]
Standard Labor Rates for DPWH Regional/District Engineering Offices (Memorandum: January 7, 2019)
[4]
DO no. 137 Series of 2017 Cost Estimation Manual for Low Rise Buildings
SOUTH EAST METRO MANILA EXPRESSWAY (C6)
DETAILED UNIT PRICE ANALYSIS (DUPA) [2]
Class 1 - NCR (Taguig City)
Designation No. of Person/s No. of Hour/s Hourly Rate [3] Amount (Php)
A. Labor
REFERENCE:
[1]
DO no. 22 Series of 2015: Revised Guidelines in the Preparation of Approved Budget for the Contructor (ABC)
[2]
DO no. 68 Series of 2016: Road Costruction Cost Estimation Manual
[3]
Standard Labor Rates for DPWH Regional/District Engineering Offices (Memorandum: January 7, 2019)
[4]
DO no. 137 Series of 2017 Cost Estimation Manual for Low Rise Buildings
SOUTH EAST METRO MANILA EXPRESSWAY (C6)
DETAILED UNIT PRICE ANALYSIS (DUPA) [2]
Class 1 - NCR (Taguig City)
Designation No. of Person/s No. of Hour/s Hourly Rate [3] Amount (Php)
A. Labor
REFERENCE:
[1]
DO no. 22 Series of 2015: Revised Guidelines in the Preparation of Approved Budget for the Contructor (ABC)
[2]
DO no. 68 Series of 2016: Road Costruction Cost Estimation Manual
[3]
Standard Labor Rates for DPWH Regional/District Engineering Offices (Memorandum: January 7, 2019)
[4]
DO no. 137 Series of 2017 Cost Estimation Manual for Low Rise Buildings
SCHEDULE OF LABOR RATES
DPWH - REGION IV-A - CALABARZON
Based from Unnumbered Memo No. 097.7 s2019 (Standard Labor Rates for DPWH Regional/District Engineering Offices)
Class 1: Bacoor, Imus, Biñan City, Laguna Techno Park, San Pedro, Cainta and Taytay
RESOURCE BASIC WAGE LABOR COST RATE PER RATE PER
DESCRIPTION
CODE NO. DAILY MONTHLY FACTOR DAY HOUR
1 Foreman 720.00 18,780.00 1.80 866.40 108.30
2 Leadman 660.00 17,215.00 1.65 798.62 99.83
3 Heavy Equipment Operator 600.00 15,650.00 1.50 728.95 91.12
4 Highly Skilled Operator 600.00 15,650.00 1.50 728.95 91.12
5 Light Skilled Operator 560.00 14,606.67 1.40 680.02 85.00
6 Driver 520.00 13,563.33 1.30 631.84 78.98
7 Skilled Laborer 520.00 13,563.33 1.30 631.84 78.98
8 Semi-Skilled Laborer 480.00 12,520.00 1.20 583.67 72.96
9 Unskilled Laborer 400.00 10,433.33 1.00 487.33 60.92
Class 2:
Cavite City, Dasmariñas City, Tagaytay City, Trece Martires City, Carmona, General Trias, Rosario,
Cabuyao, Calamba City, San Pablo City, Sta. Rosa City, Los Baños, Sta. Cruz, Batangas City, LIMA
Technology, Lipa City, Tanauan City, Antipolo City, and Lucena City
RESOURCE BASIC WAGE LABOR COST RATE PER RATE PER
DESCRIPTION
CODE NO. DAILY MONTHLY FACTOR DAY HOUR
1 Foreman 671.40 17,512.35 1.80 811.41 101.43
2 Leadman 615.00 16,052.99 1.65 748.17 93.52
3 Heavy Equipment Operator 45.00 14,593.63 1.50 679.46 84.93
4 Highly Skilled Operator 559.50 14,593.63 1.50 679.46 84.93
5 Light Skilled Operator 559.50 13,620.72 1.40 634.31 79.29
6 Driver 522.20 12,647.81 1.30 589.17 73.65
7 Skilled Laborer 484.90 12,647.81 1.30 589.17 73.65
8 Semi-Skilled Laborer 447.60 11,674.90 1.20 544.03 68.00
9 Unskilled Laborer 373.00 9,729.08 1.00 453.74 56.72
Class 3:
Kawit, Silang, Tanza, General Mariano Lavarez, Indang, Naic, Alfonso, Bauan, San Pascual, Santo Tomas,
Balayan, Calaca, Lemery, Mabini, Nasugbu, Rosario, San Jose, San Juan, Rodriguez, Tanay, Angono,
Binangonan, San Mateo, Pililia, Candelaria, Sariaya, and Tiaong
RESOURCE BASIC WAGE LABOR COST RATE PER RATE PER
DESCRIPTION
CODE NO. DAILY MONTHLY FACTOR DAY HOUR
1 Foreman 662.40 17,277.60 1.80 801.32 100.17
2 Leadman 607.20 15,837.80 1.65 738.44 92.31
3 Heavy Equipment Operator 552.00 14,398.00 1.50 671.04 83.88
4 Highly Skilled Operator 552.00 14,398.00 1.50 671.04 83.88
5 Light Skilled Operator 515.20 13,438.13 1.40 626.46 78.31
6 Driver 478.40 12,478.27 1.30 581.88 72.74
7 Skilled Laborer 478.40 12,478.27 1.30 581.88 72.74
8 Semi-Skilled Laborer 441.60 11,518.40 1.20 537.30 67.16
9 Unskilled Laborer 368.00 9,598.67 1.00 448.14 56.02
Note:
Minimum Wage Rate P 400.00
Equivalent No. Days/Year 313.00 CD
Equivalent No. Days/Month 26.08 CD
Basic Daily Compensation Minimum Wage multiplied by the Labor Cost Factor of each Factor
Monthly Rate Basic Monthly Wages + Leaves + 13th Month Pay + Social Benefits
Daily Rate Monthly Rate / Equivalent No. of Days per Month
Hourly Rate Daily Rate / 8 Hours per Day