DETAIL REALISASI RAB (ACTUAL) PIC : Taufik Standar

Nama Project : Rack Dies TNA Customer :


Nilai PO : Rp120.000.000 Mulai Pelaksanaan : 20-Jun-21
Progress : 50,5 % Selesai Pelaksanaan :

' Material
Tanggal Deskripsi QTY Satuan Harga Satuan Jumlah
18-Jun-21 WF 150 112 Kg 13.000,00 1.456.000,00
18-Jun-21 WF 200 1 LS 14.500.000,00 14.500.000,00
22-Jun-21 Plat 8mm 153 Kg 13.500,00 2.065.500,00
08-Jul-21 Plat 8mm 341 Kg 13.500,00 4.603.500,00
14-Aug-21 UNP 100 9 Btg 486.000,00 4.374.000,00
18-Aug-21 WF 150 KS 12M 2 Btg 2.662.800,00 5.325.600,00
20-Aug-21 WF 150 KS 12M 3 Btg 2.662.800,00 7.988.400,00
23-Aug-21 WF 150 KS 12M 4 Btg 2.662.800,00 10.651.200,00
24-Aug-21 UNP 100 10 Btg 500.000,00 5.000.000,00
24-Aug-21 Cat Duco; Blue 116 3 Kg 37.500,00 112.500,00
24-Aug-21 Thinner HG 4 Ltr 15.000,00 60.000,00
26-Aug-21 Thinner HG 1 Jrg 320.000,00 320.000,00
26-Aug-21 Cat Duco; Blue 116 1 Pail 750.000,00 750.000,00
30-Aug-21 UNP 100 4 Btg 500.000,00 2.000.000,00
30-Aug-21 Ring plate M16 600 Pcs 1.000,00 600.000,00
30-Aug-21 Mur+Baut M16x50 360 Pcs 6.000,00 2.160.000,00
30-Aug-21 WF 150 KS 12M 3 Btg 2.679.600,00 8.038.800,00
31-Aug-21 Mur+Baut M16x50 320 Pcs 5.500,00 1.760.000,00
31-Aug-21 Ring plate M16 760 Pcs 500,00 380.000,00
04-Sep-21 WF 200 1 Btg 4.225.000,00 4.225.000,00

Total Biaya ' Material 76.370.500,00

Consumable
Tanggal Deskripsi QTY Satuan Harga Satuan Jumlah
29-Jun-21 Mata Bor Jetbrouch 1 Ls 335.000,00 335.000,00
29-Jun-21 Mata Gerinda 4" WD 25 Pcs 8.000,00 200.000,00
29-Jun-21 Spray Gun F-75 TA 0 Set 175.000,00 0,00
29-Jun-21 Mata Gerinda Poles NR 7" 4 Pcs 32.000,00 128.000,00
18-Aug-21 Mata Bor Nachi Dia 5mm 3 Pcs 30.000,00 90.000,00
18-Aug-21 Meteran 5 M 1 Pcs
18-Aug-21 Palu Godam Camel 1 Pcs
18-Aug-21 Center Punch/Penitik Besi 1 Pcs
18-Aug-21 Penggaris Siku 2 Pcs
18-Aug-21 Steker Broco 1 Pcs
18-Aug-21 Kabel NYM 2x2,5 20 M
18-Aug-21 Stop Kontak 4 Lubang 1 Pcs
18-Aug-21 Kapur Besi 1 Box 20.000,00 20.000,00
19-Aug-21 Gerinda Poles WD 4" 10 Pcs 8.000,00 80.000,00
19-Aug-21 Cutting WD 4" 1 Box 65.000,00 65.000,00
21-Aug-21 Nozel ST-25 1 Pcs 25.000,00 25.000,00
21-Aug-21 Konektor Las besar 2 Pcs
21-Aug-21 Kawat Las 3,2 RD 2 Pak 125.000,00 250.000,00
21-Aug-21 Kabel Las 50mm 13 M
24-Aug-21 Kuas 2" 2 Pcs 8.000,00 16.000,00
24-Aug-21 Roll Kecil 2 Pcs 27.500,00 55.000,00
06 September 2021 Page 1 of 3
Consumable
Tanggal Deskripsi QTY Satuan Harga Satuan Jumlah
26-Aug-21 Kain Majun 2 Kg
26-Aug-21 Kawat Las 3,2 RD 3 Pak 125.000,00 375.000,00
26-Aug-21 Roll Kecil Refill 4 Pcs 5.000,00 20.000,00
26-Aug-21 Sarung Tangan 1 Lusin
28-Aug-21 Dempul Isamu 1 Klg 60.000,00 60.000,00
04-Sep-21 Nozel ST-25 No.2 1 Pcs 50.000,00 50.000,00
04-Sep-21 Mata gerinda poles 10 Pcs 8.000,00 80.000,00
04-Sep-21 Kawat Las 2,6 RD 2 Pak 130.000,00 260.000,00
04-Sep-21 Kawat Las 3,2 RD 2 Pak 125.000,00 250.000,00
06-Sep-21 Gas LPG 5 kg 1 Tbg 75.000,00 75.000,00

Total Biaya Consumable 2.434.000,00

Man Power
Tanggal Deskripsi QTY Satuan Harga Satuan Jumlah
20-Aug-21 Kasbon Ajo 1 LS 1.000.000,00 1.000.000,00
23-Aug-21 Kasbon Ajo 2 1 LS 1.000.000,00 1.000.000,00
25-Aug-21 Kasbon Ajo 3 1 LS 1.000.000,00 1.000.000,00
30-Aug-21 Kasbon Ajo 4 1 LS 2.500.000,00 2.500.000,00
02-Sep-21 Pelunasan Rack NVH 2 Unit 1 LS 3.500.000,00 3.500.000,00
06-Sep-21 Kasbon 1 Rack RUL dan Carpet 1 LS 1.500.000,00 1.500.000,00

Total Biaya Man Power 10.500.000,00

Mob Demob
Tanggal Deskripsi QTY Satuan Harga Satuan Jumlah
18-Jun-21 Ongkir WF 1 LS 300.000,00 300.000,00
22-Jun-21 Ongkir Plate 1 LS 300.000,00 300.000,00
08-Jul-21 Ngkir Plate 1 LS 300.000,00 300.000,00
30-Aug-21 Delivery 2 unit Rak 1 LS 600.000,00 600.000,00

Total Biaya Mob Demob 1.500.000,00

Subcont
Tanggal Deskripsi QTY Satuan Harga Satuan Jumlah
29-Jun-21 Pembayaran Term 1 1 LS 1.300.000,00 1.300.000,00
01-Jul-21 Pembayaran Term 2 1 LS 1.700.000,00 1.700.000,00

Total Biaya Subcont 3.000.000,00

Support
Tanggal Deskripsi QTY Satuan Harga Satuan Jumlah
20-Aug-21 Mesin Bor Magnet 1 Unit
23-Aug-21 Mata Bor Jet Broach 18mm 1 Pcs
24-Aug-21 Mata Bor Jet Broach 18mm 1 Pcs
28-Aug-21 Mesin Gerinda 4" Ryu 1 Unit
04-Sep-21 Kunci Inggris 10" 1 Pcs

Total Biaya Support

06 September 2021 Page 2 of 3


Total Biaya 93.804.500,00

Karawang, 06-Sep-21
Diperiksa Oleh, Dibuat Oleh,

______________ Misbahul Munir


PIC Staf Admin
Diketahui Oleh,

Hasan
Direktur