Production Scheduling Board with PP/DS for SAP S/4HANA


(Advanced Planning) on SAP S/4HANA 1709 FPS1
9 Likes 11,599 Views 8 Comments

Introduction
With SAP S/4HANA PP/DS, there is a new Fiori App production scheduling board that uses Fiori based Gantt
chart for manual scheduling.  The app was introduced in SAP S/4HANA 1610 and further enhanced in release
1709 and in further future packs. Production scheduling board with PP/DS for SAP S/4HANA (Advanced
Planning) on SAP S/4HANA 1709 FPS1 has done a great makeover. The blog explores the features of this.

Supported List of Functionalities


Following list of functionalities that are supported by production scheduling board.

Manual Scheduling with Context Menu, Drag and Drop


Heuristics – Manual Sequencing
Heuristics Framework Support
Alert Framework Integration and Navigation
Component Issues – Missing Quantity & Late Receipts
Information on Pegged requirements
Scheduling with Alternate Resource
View resource utilization
View Order Relationships

https://blogs.sap.com/2018/02/15/production-scheduling-board-with-ppds-for-sap-s4hana-advanced-planning-on-sap-s4hana-1709-fps1/ 1/16
3/10/2021 Production Scheduling Board with PP/DS for SAP S/4HANA (Advanced Planning) on SAP S/4HANA 1709 FPS1 | SAP Blogs

View Pegging Relationships


Follow RSS feed Like
Scheduling and planning Logs
Stretch and Shrink with proposals
Manual Order Create, change, delete, Change source of supply
Customizing and Settings
Variant Management
Customer speci c elds support(extensibility) in side panel (1809 onwards)

Manual Scheduling with Context Menu, Drag and Drop


Manual scheduling  with context menu, drag and drop are fully supported. the integrated side panel will help to
show more details to enable better decision making.

Heuristics Framework Support


The application support Heuristics framework.The following standard heuristics are supported while working
with Production Scheduling Board

SAP001 – Schedule Sequence


SAP002 – Remove Backlog
SAP003 – Schedule Sequence Manually (Fiori UI pop-up supported)
SAP004 – Minimize Runtime
SAP005 – Schedule Operations
SAP_DS_01 – Stable Forward Scheduling
SAP_DS_02 – Enhanced Backward Scheduling
SAP_DS_03 – Change Fixing/Planning Intervals

https://blogs.sap.com/2018/02/15/production-scheduling-board-with-ppds-for-sap-s4hana-advanced-planning-on-sap-s4hana-1709-fps1/ 2/16
3/10/2021 Production Scheduling Board with PP/DS for SAP S/4HANA (Advanced Planning) on SAP S/4HANA 1709 FPS1 | SAP Blogs

SAP_DS_04 – Activate Seq.-Dependent Setup Activities


Follow RSS feed Like
Additional heuristics are also supported if the heuristics are con gured to be executed in the background,
without a user interface.

Heuristics – Manual Sequencing


The only Heuristics with Fiori UI is the Heuristics for manual sequencing which lets you to easy sequence the
orders.

https://blogs.sap.com/2018/02/15/production-scheduling-board-with-ppds-for-sap-s4hana-advanced-planning-on-sap-s4hana-1709-fps1/ 3/16
3/10/2021 Production Scheduling Board with PP/DS for SAP S/4HANA (Advanced Planning) on SAP S/4HANA 1709 FPS1 | SAP Blogs

Follow RSS feed Like

Alert Framework Integration and Navigation


The PP/DS Alert framework is fully integrated into production scheduling board. The alerts are displayed based
on  your alert pro e con gured in the application pro le. You can also navigate to the respective operation from
alert list

Component Issues
One of the interesting feature of production scheduling board is the integrated support to show the component
issues( component lateness and missing components)  by standard in the side panel.

Component Issues – Late Receipt

https://blogs.sap.com/2018/02/15/production-scheduling-board-with-ppds-for-sap-s4hana-advanced-planning-on-sap-s4hana-1709-fps1/ 4/16
3/10/2021 Production Scheduling Board with PP/DS for SAP S/4HANA (Advanced Planning) on SAP S/4HANA 1709 FPS1 | SAP Blogs

Follow RSS feed Like

Component Issues – Missing Quantity

Information on Pegged requirements


Another interesting feature that is available in standard is the information on the Pegged requirements, which
helps user to see the requirement of the order and its date, quantity and type.

https://blogs.sap.com/2018/02/15/production-scheduling-board-with-ppds-for-sap-s4hana-advanced-planning-on-sap-s4hana-1709-fps1/ 5/16
3/10/2021 Production Scheduling Board with PP/DS for SAP S/4HANA (Advanced Planning) on SAP S/4HANA 1709 FPS1 | SAP Blogs

Follow RSS feed Like

Scheduling with Alternate Resource


Alternate resource scheduling with drag and drop and with Heuristics is fully supported

Information on Order Relationships


Relationship of orders, order ow and pegging relationships can be displayed after selecting an operation and
choosing relationships from menu.

https://blogs.sap.com/2018/02/15/production-scheduling-board-with-ppds-for-sap-s4hana-advanced-planning-on-sap-s4hana-1709-fps1/ 6/16
3/10/2021 Production Scheduling Board with PP/DS for SAP S/4HANA (Advanced Planning) on SAP S/4HANA 1709 FPS1 | SAP Blogs

Information on Order Flow Relationships


Follow RSS feed Like

Information on Pegging Relationships

Stretch and Shrink with proposals


Another interesting feature that would be helpful for the customers in the process industry is the feature of
stretch and shrink the operations to control the throughput and automatic proposal of the value to
subsequent/preceding operations

https://blogs.sap.com/2018/02/15/production-scheduling-board-with-ppds-for-sap-s4hana-advanced-planning-on-sap-s4hana-1709-fps1/ 7/16
3/10/2021 Production Scheduling Board with PP/DS for SAP S/4HANA (Advanced Planning) on SAP S/4HANA 1709 FPS1 | SAP Blogs

Follow RSS feed Like

Order – Manual Create/Change


Order creation by selection an operation as create template and change of sources of supply is fully supported.
During changing source of supply, one very interesting feature is that the the system also lists the details of the
sources, which enables the user to help decision making

https://blogs.sap.com/2018/02/15/production-scheduling-board-with-ppds-for-sap-s4hana-advanced-planning-on-sap-s4hana-1709-fps1/ 8/16
3/10/2021 Production Scheduling Board with PP/DS for SAP S/4HANA (Advanced Planning) on SAP S/4HANA 1709 FPS1 | SAP Blogs

Follow RSS feed Like

Order – Change Source of Supply

https://blogs.sap.com/2018/02/15/production-scheduling-board-with-ppds-for-sap-s4hana-advanced-planning-on-sap-s4hana-1709-fps1/ 9/16
3/10/2021 Production Scheduling Board with PP/DS for SAP S/4HANA (Advanced Planning) on SAP S/4HANA 1709 FPS1 | SAP Blogs

Follow RSS feed Like

Logs
The planning and scheduling logs is more simple and readable now and can also be seen directly
from production scheduling board

https://blogs.sap.com/2018/02/15/production-scheduling-board-with-ppds-for-sap-s4hana-advanced-planning-on-sap-s4hana-1709-fps1/ 10/16
3/10/2021 Production Scheduling Board with PP/DS for SAP S/4HANA (Advanced Planning) on SAP S/4HANA 1709 FPS1 | SAP Blogs

Follow RSS feed Like

Customizing and Settings


There are options for customizing and settings. The time pro le and the application pro le can be customized
and can be selected in the lters. The application pro le further consists of Alert, heuristics, strategy pro les
that can further be customized.

There is also some interesting features like optionally customizing the display test of the operations with
product name/description.

https://blogs.sap.com/2018/02/15/production-scheduling-board-with-ppds-for-sap-s4hana-advanced-planning-on-sap-s4hana-1709-fps1/ 11/16
3/10/2021 Production Scheduling Board with PP/DS for SAP S/4HANA (Advanced Planning) on SAP S/4HANA 1709 FPS1 | SAP Blogs

Follow RSS feed Like

Variant Management
You can store your time pro le, application pro le, work center selections, zoom factor in the variants and
change it by just switching the changed variants.

Side Panel Extensibility (1809 On-Premise Onwards)


From 1809 release onwards, you can extend the Production Scheduling Board app according to your business
needs for

• New Fields in the side panel

You can add elds to the new panel Additional Information in the side panel of the UI by adding
SAP standard elds.

• New Customer-Speci c Fields in the side panel

You can add elds to the new panel Additional Information in the side panel of the UI by adding
customer-speci c elds.

For more detals refer SAP note 2684046

Further References
Fiori reference Lib : Production Scheduling Board

https:// oriappslibrary.hana.ondemand.com/sap/ x/externalViewer/#/detail/Apps(‘F2176’)

https://blogs.sap.com/2018/02/15/production-scheduling-board-with-ppds-for-sap-s4hana-advanced-planning-on-sap-s4hana-1709-fps1/ 12/16
3/10/2021 Production Scheduling Board with PP/DS for SAP S/4HANA (Advanced Planning) on SAP S/4HANA 1709 FPS1 | SAP Blogs

Help documentation: PP/DS Help Landing Page:


Follow RSS feed Like

S/4 HANA 1709 Landing Page( https://help.sap.com/s4hana_op_1709 ) and then navigate to Enterprise


Business Applications -> Manufacturing -> Production Planning and Detailed Scheduling (PP/DS)

Alert Moderator

Assigned tags

SCM APO Production Planning and Detailed Scheduling (PP/DS) | PP/DS for SAP S/4HANA | ppds |

Related Blog Posts

PP/DS for SAP S/4HANA (Advanced Planning) : A powerful planning and scheduling tool
By Jomerce PJ , Feb 12, 2018
PP/DS on S/4 HANA (Advanced Planning) Insights
By Venkadesh Seetharaman , Jan 17, 2019
Production scheduling board- PPDS FIORI app
By Jyoti Chalikar , Oct 04, 2019

Related Questions

PP/DS Planned Order is not shown on Scheduling Board & PDS doesn't get Activities
By Rahul Agarwal , Jul 03, 2018

https://blogs.sap.com/2018/02/15/production-scheduling-board-with-ppds-for-sap-s4hana-advanced-planning-on-sap-s4hana-1709-fps1/ 13/16
3/10/2021 Production Scheduling Board with PP/DS for SAP S/4HANA (Advanced Planning) on SAP S/4HANA 1709 FPS1 | SAP Blogs

Does SAP PP-DS requires PP-PI


Follow , Sep 26, 2019
By Lawrence Gladwell RSS feed Like

Multiple Output Planning (MOP) with PDS


By Daniil Gorbushin , Jul 25, 2019

8 Comments

You must be Logged on to comment or reply to a post.

Caetano Almeida

February 16, 2018 at 3:29 pm

Great blog Jomerce! Nice to see you sharing knowledge in SCN.

Like(0)

Mansi Pujari

March 28, 2018 at 11:29 pm

Good Explanation Jomerce...However, after activating the app are there any more settings required to see data
on the screen? I currently see 'No data' when i open this app(for 1709 on premise). Would like to see a blog on
settings, if any, for PPDS related apps. Thanks.

Like(0)

Krishna Prasad Karkala Rao

September 11, 2018 at 6:28 am

Hi Mansi,

To display data it also requires correct "Area of responsibility assigned" . Also resources are assigned with
planner. Hope this helps.

Regards,

Krishna Rao

Like(0)
https://blogs.sap.com/2018/02/15/production-scheduling-board-with-ppds-for-sap-s4hana-advanced-planning-on-sap-s4hana-1709-fps1/ 14/16
3/10/2021 Production Scheduling Board with PP/DS for SAP S/4HANA (Advanced Planning) on SAP S/4HANA 1709 FPS1 | SAP Blogs

Follow RSS feed Like

RAJA SEKHARA REDDY BANNURU

December 1, 2018 at 12:47 pm

Hi Jomerce,

It's Great Blog, very well explained in detailed.


Many Thanks for sharing this valuable & useful information.

I have one question, Please


Is there any option, to perform the Optimization from the Scheduling Board Fiori App & how to execute the
Optimization from the Fiori. ?
Kindly help me  in this regard. Best Regards : Raja

Like(0)

Jomerce PJ | Post author

January 1, 2019 at 5:27 am

No. You have to do it in a di rrent txn. You can now also extend the side panel , may be you can put a something
there? see note : https://launchpad.support.sap.com/#/notes/2684046

Like(0)

RAJA SEKHARA REDDY BANNURU

January 1, 2019 at 3:57 pm

Hi Jomerce,

Thanks a Lot for the kind Inputs &  Great Support


Sure, will follow the suggested link.
Thanks & Regards : Raja

Like(0)

nikki carol

December 17, 2018 at 6:05 am

Good Explanation Jomerce.

Very Well Explained in Detailed.

https://blogs.sap.com/2018/02/15/production-scheduling-board-with-ppds-for-sap-s4hana-advanced-planning-on-sap-s4hana-1709-fps1/ 15/16
3/10/2021 Production Scheduling Board with PP/DS for SAP S/4HANA (Advanced Planning) on SAP S/4HANA 1709 FPS1 | SAP Blogs

Like(0)
Follow RSS feed Like

Lingaiah Vanam

February 17, 2019 at 7:12 pm

Good blog and very informative

Find us on

Privacy Terms of Use

Legal Disclosure Copyright

Trademark Cookie Preferences

Newsletter Support

https://blogs.sap.com/2018/02/15/production-scheduling-board-with-ppds-for-sap-s4hana-advanced-planning-on-sap-s4hana-1709-fps1/ 16/16

You might also like