Operational Alert 10-21 Inapplicability of Baker S-3 Packer in 7 Inch 35 PPF Casing - Liner
Operational Alert 10-21 Inapplicability of Baker S-3 Packer in 7 Inch 35 PPF Casing - Liner
July 2021
The Alerts are provided to all Drilling and Workover Operations Foremen and Liaisonmen so that we all learn from the
experiences of others. The knowledge of this incident could prevent similar ones from happening in the future. Saudi Aramco
policy requires the information in this Alert to be communicated to all crew members and documented on morning reports.
What happened?
On July 11, upper completion BAKER S-3 Packer with tail pipe was run to
11,441 ft (30 ft above Top of 4-1/2” Liner). While reverse circulating, pressure
increased suddenly from 970 PSI to 1700 PSI. String was free. Reverse
circulation was resumed with 1 BPM and 2600 PSI. Attempted to RIH upper
completion, tagged 4-1/2” TOL. After spaced out, packer prematurely partially
set at 11,468 ft, had 15K of slack off weight down and free up. POH with upper
completion. Checked equipment on surface and found one part from lower slips
of packer left in hole.
Consequences: