Government of Nepal

Ministry of Federal Affairs and Local Development


Office of District Development Committee
District Technical Office
Jaleshwar, Mahottari
Detailed Estimate & Abstract of Cost
Maintenance Of Nepal Telecom Compound Wall
S.N. Particulars No Length Breadth Heigth Quantity Unit Rate Total Remarks
1 Site clearance 1 55 0.3 16.5 sq.m 28.43 469.062
2 Dismantling of Brickwork 1 55 0.3 1.7 28.05 cu.m 1066.05 29902.703
3 Earthwork Excavation 1 55 0.3 0.6 9.9 cu.m 355.35 3517.965
4 Flat brick soling 1 55 0.3 16.5 sq.m 742.90 12257.85
5 PCC(1:3:6) in foundation 1 55 0.3 0.0762 16.5 cu.m 10522.86 173627.26

6 RCC Work( pillar) 22 0.3 0.3 2.6 5.148 cu.m


7 RCC Work( beam) 1 55 0.3 0.6 9.9 cu.m
sub-total 15.048 cum 12980.22 195326.33

8 Reinforcement 1% of RCC Work 0.15048 cum


1181.268 kg 115.63 136590.02

9 Brickwork(1:4 cement sand mortar) 1 48.4 0.3 1.7 24.684 cu.m 15122.29 373278.68
Sub Total 924969.87
Contigency 46248.493
VAT(13%) 120246.08
Grand Total 1091464

Checked By: Approved By:


Prepared By: