Satnam Gobal Temporary Facilities Development Schedule as discussed on

Updated 20-09-2021
Dt. 07.09.2021
SCHEDULE REVISED
SL. NO. ACTIVITY/DESCRIPTION COMPLETION COMPLETION FORECAST As On Date Status
DATE DATE
1 OFFICE CONTAINER RECEIPT AT SITE 31-Aug-21 27-Aug-21 Completed 02 nos. office Container Received
2 FABRICATION YARD IDENTIFICATION & MARKING 16-Aug-21 28-Aug-21 Completed Revised Plan Layout Submitted on Dt. 27.08.21
3 JOB PROCEDURE, WPS & PQR SUBMISSION 28-Aug-21 Completed Job Procedure submitted and approved
4 HSE JHA, HSE PLAN & HSE PROCEDURE SUBMISSION 28-Aug-21 Completed JHA submitted and approved
5 CRANE DOCUMENT SUBMISSION 30-Aug-21 Completed Crane Mobilized
6 SCAFFOLDING MATERIAL LOT RECEIPT AT SITE FOR TCF WORK 20-Aug-21 02-Sep-21 Completed Scaffolding Material Receipt at site on Dt. 03.09.2021
7 MOBILIZATION OF 60 MT CRANE 03-Sep-21 Completed Crane mobilied and functional
8 MOBILIZATION OF F15-Faranna 03-Sep-21 Completed 01 nos. Faranna Mobilized and functional
9 MOBILIZATION OF TRAILOR 03-Sep-21 Completed 01 nos. Faranna Mobilized and functional
10 MOBILIZATION OF 80 MT CRANE 07-Sep-21 Completed Crane mobilized
11 BIO-TOILET RECEIPT 07-Sep-21 Completed Receipt at site on Dt. 11.09.2021
JHA and Erection Scheme Submitted on Dt.07.09.2021,
12 JHA & Erection scheme for Strcuture Erection with 80 MT Crane 07-Sep-21 Completed
approval awaited
13 SCAFFOLDING MATERIAL LOT RECEIPT AT SITE 08-Sep-21 Completed Scaffolding Material Receipt at site on Dt. 03.09.2021
14 Query Spoil for area levelling for site erection area 10-Sep-21 Completed Completed
15 PACKING PLATE RECEIPT 10-Sep-21 Completed Reached at site
16 Grouting Material Receipt at Site 10-Sep-21 Completed Reached at site
17 Torquing Machine with Calibration Receipt at Site 11-Sep-21 Completed Reached at site
20 nos. Manpower reached IOC, safety induction and
18 Structure Manpower to reach at site (23-24 nos.) 11-Sep-21 Completed
gate pass under progress
21 Crane 80 mt Movement to Erection Site 18-Sep-21 18-Sep-21 Completed
22 Crane Assmebly at Erection Site 20-Sep-21 Completed
23 Crane TPI at Site after assembly 21-Sep-21 Completed on Dt.20-Sep-21
24 Planning for PR-01-M4 15-Sep-21 18-Sep-21 Completed on Dt.20-Sep-21
25 Planning for PR-01-M3 14-Sep-21 22-Sep-21
26 Crane Documents submission for 250 MT 20-Sep-21 20-Sep-21 Completed
27 WORKER'S RESTING SHED AT ERTECTION SITE 26-Aug-21 10-Sep-21 21-Sep-21 Subjected to weather condition
28 Start of Structure Assembly at site 12-Sep-21 21-Sep-21
29 DG SHED INSTALLATION AT SITE 14-Sep-21 22-Sep-21 Subjected to weather condition
30 PORTABLE TOILET & SEVAGE TANK FOR ERECTION SITE 31-Aug-21 05-Sep-21 22-Sep-21 Subjected to weather condition
31 CIVIL FOUNDATION FOOTING FOR OFFICE AND BLASTING SHED-( 50 Footing ) 12-Sep-21 22-Sep-21 18 nos. footing raft casted
32 Availibility of Manlift for erection 13-Sep-21 23-Sep-21
33 TPI for Manlift at Site 24-Sep-21
34 Start of Structure Erection at site 14-Sep-21 24-Sep-21
Blasting Shed Pre-Fabricated Structure Material (12 Mtr
35 BLASTING AND PAINTING SHED ERECTION AT FABRICATION YARD 30-Aug-21 12-Sep-21 23-Sep-21
X 20 Mtr) received on Dt. 27.08.2021
36 BLASTING SHED SHEETING AT FABRICATION YARD 12-Sep-21 25-Sep-21 Material Received at Site on Dt.28.08.2021

For Satnam 1 of 2 For TCMPL


Satnam Gobal Temporary Facilities Development Schedule as discussed on
Updated 20-09-2021
Dt. 07.09.2021
SCHEDULE REVISED
SL. NO. ACTIVITY/DESCRIPTION COMPLETION COMPLETION FORECAST As On Date Status
DATE DATE
Material Dispatched from Amreli on 27.08.2021
37 FABRICATION SHED PREPARATION & ERETION AT FABRICATION YARD 22-Aug-21 23-Sep-21 24-Sep-21
Material Received at Site on Dt.29.08.2021
38 FABRICATION SHED SHEETING AT FABRICATION YARD 23-Sep-21 27-Sep-21 Material Received at Site on Dt.31.08.2021
39 All TCF Facilities to prepared at fabrication yard and at site 23-Sep-21 27-Sep-21 Subjected to weather condition
40 TOOL ROOM SHED AT FABRICATION YARD 28-Aug-21 05-Sep-21 27-Sep-21 Subjected to weather condition
41 MAINTENANCE ROOM SHED AT FABRICATION YARD 30-Aug-21 05-Sep-21 27-Sep-21 Subjected to weather condition
42 CLINIC SHED AT FABRICATION YARD 31-Aug-21 05-Sep-21 27-Sep-21 Subjected to weather condition
43 PORTABLE TOILET & SEVAGE TANK FOR FABRICATION SITE 27-Sep-21 Subjected to weather condition
44 Solar Lights Installation for Late Night Stay 11-Sep-21 27-Sep-21
45 MOBILIZATION OF 2ND F15, FARANA 31-Aug-21 06-Sep-21 31-sep-21 01 nos. Faranna Reached at Vadodra (Under Repair)
46 FABRICATION YARD WIRE FENCING 24-Aug-21 04-Sep-21 05-Oct-21 will start after all TCF activity completion

For Satnam 2 of 2 For TCMPL