Weekly Progress Report (13TH August)
Weekly Progress Report (13TH August)
GHANA
GROUNDS WORK
1 Survey works
1.1 Establishing main building corners 100 100 Completed
1.2 Establishing fence wall Boundary 30 30 50 On schedule
1.3 Establishing Excavation line 45 On schedule
2 Earthworks
2.1 Cart away of Existing ground to 20 20 40 On schedule
Ground zero
2
3. Site Labour Force
4. Materials on Site
5. Equipments on Site
1. Excavator 1 Good
The site recorded no injury related issues as at 13th August,2021. A daily refresher tool box
meeting is held to refresh site workforce on all safety practices regarding work activities. The
Main Contractor`s HSE officer has arranged with China State to kick off a medical check up
exercise with the respective health care centre on 16/08/21. We have also positioned 4 No.
3
security officer on site to ensure secured working environment.
7. Weather
The site experienced showers of rains from 10-13th August during working periods.
4
8. Progress Photos.
Site meeting with Consultants Site clearance for 315KVA transformer plinth
Fig. 3 Fig. 4
Carting of grounds to ground zero. Tool box meeting prior start of work
Fig. 5 Fig.6
5