Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

PROPOSED CONSTRUCTION OF KOFORIDUA REGIONAL HOSPITAL, KOFORIDUA,

GHANA

CONSTRUCTION OF 285 BED CAPACITY KOFORIDUA


REGIONAL HOSPITAL AT KOFORIDUA, EASTERN
REGION, GHANA.

Weekly Progress Report


AS AT 13th August, 2021

Employer: Ministry of Health, Ghana


Contractor: JV Tyllium.
Sub-Contractor: China State Hualong Construction (GH) Ltd.
MONTHLY PROGRESS REPORT AS AT 13TH AUGUST,2021
Commencement date: 02/08/21
Expected completion date: 02/08/22

1. WORK PROGRESS FOR SITE ACTIVITIES


PLANNED ACTUAL FORCAST
S/N ACTIVITY REMARKS
PROGRESS PROGRESS(%) PROGRESS(%)

GROUNDS WORK

1 Survey works
1.1 Establishing main building corners 100 100 Completed
1.2 Establishing fence wall Boundary 30 30 50 On schedule
1.3 Establishing Excavation line 45 On schedule

2 Earthworks
2.1 Cart away of Existing ground to 20 20 40 On schedule
Ground zero

3 Transformer Plinth works


3.1 Clearing area to receive concrete
plinth for transformer 100 100 Completed

2
3. Site Labour Force

Chinese Staff Ghanaian Staff


Project Manager 1 Civil Engineer 1
Chief Engineer 1 Safety Officer 1
Site Engineer 1 Excavator driver 1
Translator 1 Dump truck driver 2
Flagman 1
General driver 2
Safety Officer 1
Security 4
Excavator driver 1
Total: 4 Total : 14

4. Materials on Site

S/N ITEM QUANTITY UNIT

1. Diesel 130 litres

2. Laterite 800 cubic

5. Equipments on Site

S/N EQUIPMENT QUANTITY CONDITION

1. Excavator 1 Good

2. Dump trucks 2 Good

6. Health and Safety.

The site recorded no injury related issues as at 13th August,2021. A daily refresher tool box
meeting is held to refresh site workforce on all safety practices regarding work activities. The
Main Contractor`s HSE officer has arranged with China State to kick off a medical check up
exercise with the respective health care centre on 16/08/21. We have also positioned 4 No.

3
security officer on site to ensure secured working environment.

7. Weather

The site experienced showers of rains from 10-13th August during working periods.

4
8. Progress Photos.

Establishing building boundary Confirming of TBM location with Const. Manager


Fig. 1 Fig. 2

Site meeting with Consultants Site clearance for 315KVA transformer plinth
Fig. 3 Fig. 4

Carting of grounds to ground zero. Tool box meeting prior start of work
Fig. 5 Fig.6

5
6

You might also like