RADIO SITE INSTALLATION DOCUMENTATION

TRV004 (BURA)

Airtel Kenya - Ericsson RAN Modernization Project 2021

Ericsson GSM / UMTS / LTE Systems


CAPTION LIST Document List 1
Document No

001 53-LZB-IPA 019 0431 Uen


Date Rev

2021-08-07 A

Site Documents 2

RADIO SITE
INSTALLATION
Plant Specification 3
DOCUMENTATION

Airtel Kenya - Ericsson RAN


Modernization Project 2021
Cabling Diagrams 4

TRV004

GARSEN External Alarms 5

Ericsson GSM / UMTS / LTE


Systems

G900+G1800+U900 (5 MHz)
Test Documents
+U2100 (10 MHz) + 2*2 MIMO L800 6
(10 MHz)

Enclosure 6130 (DC)

Product Lists 7

ATTENTION
This documentation must be updated
on site. All the documents must be Check Lists 8
corrected, where changes have
occurred, and signed by the
Installation Supervisor.

This documentation must then


be returned to Installation Supporting Documents 9
Engineering Department for the
preparation of the Radio Site Design
Documentation.
DOCUMENT LIST
Prepared (also subject responsible if other) Document No

BNEWOGJH Amit Vats 001 51-LZB-IPA 019 0431 Uen


A 2014-07-15

Doc respons/Approved Checked Date Rev File


MMEAFCJO (Shekhar Kukreja) 2021-08-07 A TRV004

Project: Airtel Kenya - Ericsson RAN Modernization Project 2021


Site: TRV004

Document name Document number Rev

RADIO SITE 001 53-LZB-IPA 019 0431 Uen A


INSTALLATION DOCUMENTATION

1 DOCUMENT LIST 001 51-LZB-IPA 019 0431 Uen A

2 SITE DOCUMENTS
Configuration Data (Radio) 1/127 04-IPA 019 0431 Uen A
Situating Plan 153 38-IPA 019 0431 Uen A
Antenna Placement Drawing 153 12-IPA 019 0431 Uen A
Equipment / Floor Layout 193 05-IPA 019 0431 Uen A

3 PLANT SPECIFICATION
Plant Specification (Radio) 1/127 11-IPA 019 0431 Uen A

4 CABLING DIAGRAMS
Block diagram (Power & Earthing) 1/193 18-IPA 019 0431 Uen A
Signal Cable Diagram 2/193 18-IPA 019 0431 Uen A
Cabinet Allocation Drawing (Enclosure) 3/193 13-IPA 019 0431 Uen A
Block Diagram (Antenna System) 4/193 18-IPA 019 0431 Uen A

5 EXTERNAL ALARMS
Allocation Table 1/127 11-IPA 019 0431 Uen A

6 TEST DOCUMENTS
Test Report (Radio) 1/153 83-IPA 019 0431 Uen A

7 PRODUCT LISTS
Product List (Radio) 1/193 32-IPA 019 0431 Uen A

8 CHECK LISTS
Site Installation Checklist (Radio) 1/153 11-IPA 019 0431 Uen A

9 SUPPORTING DOCUMENTS
Design Document
Provisional Acceptance Certificate
Site Return Material
CONFIGURATION DATA (RADIO)
Prepared (also subject responsible if other) Document No.
BNEWOGJH Amit Vats 1/127 04-IPA 019 0431 Uen
A 2014-07-15

Doc respons/Approved Checked Date Rev. File


MMEAFCJO (Shekhar Kukreja) 2021-08-07 A TRV004

Project: Airtel Kenya - Ericsson RAN Modernization Project 2021


Site: TRV004

1 GENERAL SITE DATA


1.1 Geographical coordinates(WGS 84) Long : 39.838162 Lat : -1.19313
1.2 Region GARSEN
1.3 Site Address GARISSA
1.3 Type of Site Outdoor
1.4 Site Position Greenfield Building Height (m) : XX
1.5 ODU PAD/Plinth Dimensions (LxW in meter) (EXISTING SLAB)

2 TECHNICAL DATA
2.1 Type of RBS/Enclosure Enclosure 6130 (DC)
2.2 System / Technology G900+G1800+U900+U2100+L800
2.3 No: of Sectors 3
2.4 Configuration of L800 3x1
2.5 Configuration of U900 3x1
2.6 Configuration of G900 / G1800 1+ 1+1 / 1+ 1+1
2.7 Configuration of U2100 3x1
2.8 Type of Baseband & Qty. (Tech.) Electrical Baseband 6630 & 3
2.9 No. of Radio 4480 44B1/44B3 (3x1) MM
2.10 No. of Radio 2279 22B8 / 22B20 C (3x1) MM
2.11 Radio 4480 44B1/44B3 (Dimensions (H x W x D) mm) (260 x 495 x 645) mm 31.7 kg
2.12 Radio 2279 22B8 / 22B20 C (Dimensions (H x W x D) mm) (447 × 398 × 138) mm 20.2 kg

3 ANTENNA SYSTEM (All Technologies) Sec: A Sec: B Sec: C Sec: D


3.1 Antenna Type (New / Existing / Re-use) New New New N/A
3.2 Antenna Height 41 41 41 N/A
3.3 Antenna Azmuth / Direction Deg (°) 60° 135° 340° N/A
3.4 Antenna Electrical Tilt 2/NA 2/NA 2/NA N/A
3.5 Antenna Mechanical Tilt 1 1 1 N/A
3.6 Antenna Model 84510866
3.7 Antenna Dimension (2697 x 353 x 164) mm
3.8 Weight of Antenna 32 kg
3.9 Length of Fiber 70m
3.10 Length of Jumper 3m
3.11 Type of Jumper 4.3-4.3

4 ELECTRICAL DATA
Fuse and Circuit Breaker recommended for reliable
4.1 50A and 32 A
operation (Radio 4480 & 2279 )
Fuse and Circuit Breaker recommended for reliable
4.2 125 A
operation (Enclosure 6130)

5 ANTENNA SUPPORT STRUCTURE


5.1 Type of Tower/Mast 4 Leg Self support Tower
5.2 Tower/Mast height (m.a.g.l.) 42m
5.3 Antenna support L Profile
SITUATING PLAN
Prepared (also subject responsible if other) Document No.

BNEWOGJH Amit Vats 153 38-IPA 019 0431 Uen


Doc response/Approved Checked Date Rev. File
MMEAFCJO (Shekhar Kukreja) 2021-08-07 A TRV004
.
Project: Airtel Kenya - Ericsson RAN Modernization Project 2021
Site: TRV004

SITE GEOGRAPHICAL DATA


1.1 Geographical coordinates(WGS 84) Long : 39.838162 Lat : -1.19313
1.2 Site Address GARSEN
PLANT SPECIFICATION (RADIO)
Prepared (also subject responsible if other) Document No.
BNEWOGJH Amit Vats 1/127 11-IPA 019 0431 Uen
Doc respons/Approved Checked Date Rev. File
MMEAFCJO (Shekhar Kukreja) 2021/08/07 A TRV004

Project: Airtel Kenya - Ericsson RAN Modernization Project 2021


Site: TRV004

ITEM DESCRIPTION PRODUCT CODE QTY/UNIT


Radio 2279
Radio 2279 B8 B20 KRC161864/1 3
Circular Power cable connector RNT44732/02 3

Radio 4480
Radio 4480 B1 B3 KRC161777/1 3
Fan unit for Oslo 4T4R, Radio 4480 BKV106246/1 3
Circular Power cable connector RNT44732/02 3

Single ERS Bracket


Single ERS Steel Bracket SXK1092006/1 6

Radio Installation Material


EARTHING CABLE/16mm2,BK,2m,with 1 lug RPM1191647/2 6
TIE STRAP/TIE STRAPS B=9,5 L=457 RFST SET145095/457 200
Rosenberger 1/2" jumper cable, 4.3-10(m)-4.3-10(m), 3 m TSR951362/3 18
3M Slim Lock Mini Closure/SKYDDSSLANG MPB901029/2 36
CABLE WITH CONNECTOR/2F LC(FullAXS)-LC S RPM2531610/50M 12
SFP CPRI & 1000BASE-LX 125-248 RDH10247/2 6
SFP+ SM 10.3Gb/s 1.4km 1310nm RDH10265/2 19
Marking Set Main Remote 3-Sect NTB1010381/2 3
INSTALLATION KIT/Common installation mat NTB1010354/1 1
1XR44xx Per Sec_4.3 3M Jmp_wo Fbr- New_Conn NTB1011598/1 3
1XRxx Per Sec_wo Jmp_wo Fbr NTB1011596/1 3

Power cables
2x16 mm2;UL;LSOH;Alu+Cu-screen (UV-Protect) 500m TFL492326/500M 150m
Power Cable, 2x10 mm2, 500m TFL492325/500M 150m
Battery Cable, Halogenfree, 90 C, 50 MM2, GREY TFL103106/08 40
D.C. CONVERTER/PSU 48 13 BMR91193/1 1
FUSE HOLDER/50A, 80V, UL NFN95021/50 3
QUANTITY PACKAGE/63A 4p CB w FORK SUNSEA NTB1010797/1 1
CABLE WITH CONNECTOR/power cable assembl RPM1192634/02000 2
CABLE LUG/Power dual lug M6 Right angled SNG81812/1 6
MECHANICAL COMPONENT/Cable Ladder 19 in SXA1345524/3 1
Cable lug 16mm2 hole 8mm 100pcs SNG90460/1 9
Tube kit 25m, Roof top NTM2013811/1 0.25

BaseBand 6630
COMBINED UNIT/Baseband 6630 with fan (se KDV127621/11 3
CABLE WITH CONNECTOR/SIGNAL CABLE RPM777143/02000 6
CABLE WITH CONNECTOR/SIGNAL CABLE RPM777341/00650 3
CABLE WITH CONNECTOR/POWER CABLE RPM777528/02500 6
CABLE WITH CONNECTOR/Grounding Cable RPM777567/02500 3
CABLE WITH CONNECTOR/SIGNAL CABLE RPM777579/02000 3
CABLE WITH CONNECTOR/SIGNAL CABLE RPM777381/02050 3
CABLE WITH CONNECTOR/SIGNAL CABLE RPM777417/01800 3

Optical / Electrical Cascading cables


Optical fiber cable, single mode, LCD-LC RPM2533512/10M 1
Ethernet cable RJ45-RJ45, 15m TSR432151/15M 1

Mounting Set for BaseBand 6630


MOUNTING SET/RACK SCREW KIT SXK111539/1 3
PLANT SPECIFICATION (RADIO)
Prepared (also subject responsible if other) Document No.
BNEWOGJH Amit Vats 1/127 11-IPA 019 0431 Uen
Doc respons/Approved Checked Date Rev. File
MMEAFCJO (Shekhar Kukreja) 2021/08/07 A TRV004

Project: Airtel Kenya - Ericsson RAN Modernization Project 2021


Site: TRV004

ITEM DESCRIPTION PRODUCT CODE QTY/UNIT

Antenna System
Triple band antenna 84510866 3
BRACKET/Down tilt kit 85010009 3
RET Control Cable (3GPP / AISG), black, 3 m 1/TSR48421/3000 3

Enclosure6130 I DC w Pole Mount


Enclosure6130 I DC w Pole Mount BMK905053/2 1
QUANTITY PACKAGE/L-Support 19 inch NTB101934/3 3
Lifting eyes 6130/6140 NTK102340/1 1
CIRCUIT BREAKER/50A;1p m (extension BBS) NFS89990/11050 3
Grounding cable set, 6 m (extension BBS) NTM503112/2 1
OVP kit, 8 Ext Alarm for SAU 02 01 NTB101242/2 2
External Alarm Cable (TEL3016004/4 15m SPOOLED) TPM1010010/15M 2

GPS with its material


1/4inch Feeder cable, 300m FAB1021639/01 30
1/4inch grounding kit, Alu and Cu cables, tape sealing NGT90128/1 1
1/4inch N-Connector (m) RPT899271/1 2
Robust GNSS active antenna KRE1012395/2 1
GRU 04 01; GNSS Receiver Unit NCD90165/1 1
GPS Mount, Steel SXK1091931/1 1
Clamp Kit 7,6 mm 10 pcs NTM203219/10 3
GPS RF jumper N(f)-SMA(m) 1.5m TSR951339/1500 1
EARTHING CABLE/16mm2,BK,2m,with 1 lug RPM1191647/2 1
Sealing Set, Feeder Connectors NTM2012426 9
ALLOCATION TABLE
Prepared (also subject responsible if other) Document No.

BNEWOGJH Amit Vats 1/127 11-IPA 019 0431 Uen


Doc respons/Approved Checked Date Rev. File
MMEAFCJO (Shekhar Kukreja) 2021-08-07 A TRV004

Project: Airtel Kenya - Ericsson RAN Modernization Project 2021


Site: TRV004

External Alarms NC : Normally Closed


NO : Normally Open

Type
Alarm Inlet Definition Alarm ID Severity Remarks
(NC/NO)

MAINS FAILURE 1 G+L


Rectifier Module Fail 2 G+L
Battery Low Voltage 3 G+L
Load on DG 4 G+L
DG Common Fail 5 G+L
Rectifier Mains Fail 6 G+L
Beacon Alarm 7 G+L
Low Fuel 8 G+L
Intrusion 9 W
Alarm Arming ON/OFF 10 W
Battery High Temperature 11 W
Fan Alarm 12 W
Door Alarm 13 W
Spare 14 W
Spare 15 W
Spare 16 W

Comments
1

Ericsson Representative AirTel Representative

Name: …………...……………………… Name: …………...………………………

Sign: …………...……………………… Sign: …………...………………………

Date: …………...……………………… Date: …………...………………………


TEST PROTOCOL (RADIO)
Prepared (also subject responsible if other) Document No.

BNEWOGJH Amit Vats 1/153 83-IPA 019 0431 Uen


Doc response/Approved Checked Date Rev. File

MMEAFCJO (Shekhar Kukreja) 2021/08/07 A TRV004

Project: Airtel Kenya - Ericsson RAN Modernization Project 2021


Site No: TRV004

Site Installation Test

Date: RBS/Enclosure :

Cabinet Serial no. : IP Address:

Site Type: GF RF Power Type: DC AC

N/A Ok Fail Remarks

Visual Inspection

Cable connections inspected

System voltage verified

Configuration Script Loaded

LED Status checked

RBS reset (Power Off/On) Test

CV is saved
TEST PROTOCOL (RADIO)
Prepared (also subject responsible if other) Document No.

BNEWOGJH Amit Vats 1/153 83-IPA 019 0431 Uen


Doc response/Approved Checked Date Rev. File

MMEAFCJO (Shekhar Kukreja) 2021/08/07 A TRV004

Project: Airtel Kenya - Ericsson RAN Modernization Project 2021


Site No: TRV004

Site Integration Test

Voice Call:
Make Voice Call from each Sector.

Cell Scrambling Code Result Comments


Sector 1 Passed Failed
Sector 2 Passed Failed
Sector 3 Passed Failed

Circuit Switched - Video Call:


Make Video Call from each Sector.

Cell Scrambling Code Result Comments


Sector 1 Passed Failed
Sector 2 Passed Failed
Sector 3 Passed Failed

Packet Switched - Data Call:


Make Data Call from each Sector.
Cell Scrambling Code Result Comments
Sector 1 Passed Failed
Sector 2 Passed Failed
Sector 3 Passed Failed

Softer Handover Testing:


Make softer handover as specified below.
Cell Scrambling Code Result Comments
Sector 1 to 2 / Passed Failed
Sector 2 to 3 / Passed Failed
Sector 3 to 1 / Passed Failed
Sector 1 to 3 / Passed Failed
Sector 3 to 2 / Passed Failed
Sector 2 to 1 / Passed Failed

Test Call from


PSTN to MS: MS to PSTN: MS to MS:
TEST PROTOCOL (RADIO)
Prepared (also subject responsible if other) Document No.

BNEWOGJH Amit Vats 1/153 83-IPA 019 0431 Uen


Doc response/Approved Checked Date Rev. File

MMEAFCJO (Shekhar Kukreja) 2021/08/07 A TRV004

Project: Airtel Kenya - Ericsson RAN Modernization Project 2021


Site No: TRV004

Antenna Test

TMA: Yes No RET: Yes No

Visual Check: Antenna: New Existing Re-use

Sector 1 Sector 2 Sector 3 Sector 4

Antenna Type

Antenna Make

Antenna Model

Antenna Directions (o)

Antenna Height (m)

Remarks:

Signature Name Date

Performed by (Ericsson Rep.)

Approved by (AirTel Rep.)


PRODUCT LIST (RADIO)
Prepared (also subject responsible if other) Document No.
BNEWOGJH Amit Vats 1/193 32-IPA 019 0431 Uen
Doc respons/Approved Checked Date Rev. File
MMEAFCJO (Shekhar Kukreja) 2021-08-07 A TRV004

Project: Airtel Kenya - Ericsson RAN Modernization Project 2021


Site: TRV004

Supervisor name: Date:

SERIAL MANF.
POS UNIT PART NUMBER REV NUMBER DATE

Baseband

Baseband 6630 KDV127621/11

Baseband 6630 KDV127621/11

Baseband 6630 KDV127621/11

Radio

Radio 2279 B8 B20 KRC161864/1


Radio 2279 B8 B20 KRC161864/1
Radio 2279 B8 B20 KRC161864/1
Radio 4480 B1 B3 KRC161777/1
Radio 4480 B1 B3 KRC161777/1
Radio 4480 B1 B3 KRC161777/1
PRODUCT LIST (RADIO)
Prepared (also subject responsible if other) Document No.
BNEWOGJH Amit Vats 1/193 32-IPA 019 0431 Uen
Doc respons/Approved Checked Date Rev. File
MMEAFCJO (Shekhar Kukreja) 2021-08-07 A TRV004

Project: Airtel Kenya - Ericsson RAN Modernization Project 2021


Site: TRV004

Supervisor name: Date:

SERIAL MANF.
POS UNIT PART NUMBER REV NUMBER DATE

Enclosure 6130 DC

Enclosure6130 I DC

SAU 02 01

ESC 03 02

Antenna

Sec-A TRIBAND 84510866

Sec-B TRIBAND 84510866

Sec-C TRIBAND 84510866

GPS

GRU 04 01; GNSS Receiver UnitNCD90165/1

Robust GNSS active antenna KRE1012395/2


SITE INSPECTION LIST (RADIO)
Prepared (also subject responsible if other) Document No.
A 2002-02-15 BNEWOGJH Amit Vats 1/153 11-IPA 019 0431 Uen
Doc respons/Approved Checked Date Rev. File
MMEAFCJO (Shekhar Kukreja) 2021-08-07 A TRV004

Project: Airtel Kenya - Ericsson RAN Modernization Project 2021


Site: TRV004
OK = Correctly installed; Not OK = Not correctly installed, needs to be rectified; N/A = Not applicable

A MECHANICAL INSTALLATION OK NOK N/A COMMENTS


1 Material Delivery is complete & undamaged
2 Radio cabinet properly secured as per SID.
3 Power cabinet properly secured.
4 Cable ladder, Trunking and Cables inside secured.
Radio 2279/4480/RRUS properly mounted with radio
5
mounting Brackets.
6 Baseband 662x/521x/DU installed in Cabinet.
7 Cable lead-in (Cable glands)
8 Cable ladder
9 Wall brackets
10 Antenna supports

B EARTHING INSTALLATION AND CONNECTION OK NOK N/A COMMENTS


1 Radio Cabinet is Earthed/Grounded properly.
2 Power Cabinet is Earthed/Grounded properly.
3 Radio 2279/4480/RRUS are Earthed/Grounded properly.
4 Antennas are Earthed/Grounded properly.
5 Feeder / Fiber cables are Earthed/Grounded properly.
6 Cable ladders are Earthed/Grounded properly.
7 GPS / TMAs are Earthed/Grounded properly.

C CABLING OK NOK N/A COMMENTS


1 Power cables(AC & DC) are routed & secured
2 Alarm cables are routed & connected
3 Transmission cables are routed & connected
4 Fiber optical cables are routed & connected
5 Ethernet cables are routed & connected
6 RBS connected to power cabinet/source
7 Power Cabinet connected to main power source.
8 DC cables between rectifier cabinet(s) and battery
9 All Cables are properly Labeled

D ANTENNA INSTALLATION OK NOK N/A COMMENTS


1 Verify the Antenna direction
2 Verify the Antenna height
3 Verify the Antenna downtilt (Not applicable if RET is used)
4 GPS / TMA installed properly

E ANTENNA CABLE INSTALLATION AND CONNECTION OK NOK N/A COMMENTS


1 Fiber / Feeder cables installed
2 Fiber / Feeder clamps or cable ties installed
3 Jumper cables installed
4 Sealing of Fiber / Feeder / Jumper connectors
5 Jumper cables are routed & secured
6 Fiber / Feeder/Jumper cable connectors secured with correct torque.
7 Fiber / Feeder marking done
8 Record of Fiber / Feeder sweep test saved as soft copy.
SITE INSPECTION LIST (RADIO)
Prepared (also subject responsible if other) Document No.
A 2002-02-15 BNEWOGJH Amit Vats 1/153 11-IPA 019 0431 Uen
Doc respons/Approved Checked Date Rev. File
MMEAFCJO (Shekhar Kukreja) 2021-08-07 A TRV004

Project: Airtel Kenya - Ericsson RAN Modernization Project 2021


Site: TRV004

F DOCUMENTATION/GENERAL OK NOK N/A COMMENTS


1 Site Installation Documentation marked as-built
2 Verification of installation at site
3 Update the SID (Red Marking, if required)

G CONCLUDING ROUTINES OK NOK N/A COMMENTS


Clean the site and remove objects such as wrapping paper
1 and cable clippings.
2 Dispose of waste in accordance with local regulations.
3 Report any faults according to local requirements.

H PRE SWAP Checklist OK NOK N/A COMMENTS


1 Pre drive test done
2 CR/WO/CRQ approved
3 Login with NOC (Airtel and Eaton)
4 NOC confirms alarms status (both Equipment /environmental
5 OHS Audit with RSC
6 Material unpacking & verification
7 Installation New Enclosure/Antenna & RRU installation/Cabling
8 Transmission testing (if port is available)
9 Pre-Integration
10 NOKIA HW status check
11 Pre-Cut Over Checks
12 Open/Start MDT with NOC
13 Integration
14 Rollback Checkpoint
15 Technology activation
16 Close MDT

I POST SWAP checklist OK NOK N/A COMMENTS


1 Trouble shooting and post checks
2 Power off existing RBS
3 Health check on newly installed HW
4 Site Testing/Call testing
5 Handshake with NOC
6 Existing BTS/RRUs physical recovery/Recording details
7 Site clean up
8 Quality Check; Remote QA
9 Packing and recovery
10 Customer Acceptance
SITE INSPECTION LIST (RADIO)
Prepared (also subject responsible if other) Document No.
A 2002-02-15 BNEWOGJH Amit Vats 1/153 11-IPA 019 0431 Uen
Doc respons/Approved Checked Date Rev. File
MMEAFCJO (Shekhar Kukreja) 2021-08-07 A TRV004

Project: Airtel Kenya - Ericsson RAN Modernization Project 2021


Site: TRV004

All installation activities have been completed YES NO (if no, specify below)

Outstanding Item List Summary

The outstanding item has to be completed before the site is ready for acceptance.

Item Remarks and Description AirTel Representative


no. Name/Sign/Date Inspected

Signature Name Date

Performed by (Ericsson Rep.)

Approved by (AirTel Rep.)


PROVISIONAL ACCEPTANCE CERTIFICATE
Contract between ERICSSON and AirTel -Kenya

Radio Site: TRV004 (BURA)

This Provisional Acceptance Certificate certifies that the Contractor


has fulfilled the scope of supply and other obligations in order to
reach Acceptance as specified in the Contract.

Acceptance has been performed in accordance with the conditions


defined in the Contract and as detailed in the Acceptance Plans.

The supplied System is suitable to be placed into service or (Soft


Launch).

The Final Acceptance Certificate (FAC) milestone is passed.

Any remaining outstanding items are not of sufficient severity to


delay passing the FAC milestone or to prevent payments as defined
in the Contract.

Warranty period as defined in the Contract commences from the


date of this certificate..

Issued at ……………………. on the …………… day of ……………………, 20__, which is the


Date of Final Acceptance.

This Certificate has been duly signed by the Parties in two (2) originals and the
Parties have taken one each.

For: Ericsson For: AirTel

Name: ……………………………. Name: …………………………….

Sig: ……………………………… Sig: ………………………………

Date: ……………………….. Date: ………………………..


Site Return Material
No.: SRN:
Date:

Project Name: Airtel Kenya RAN Modernisation Request Delivery Date:


Pick-up Address:
Contact Person at Pick-up Address (Name/Mobile No.):
Site ID: KEXXXX Site NAME: SAMPLE-IBS
Remark:
Destination of Delivery:
Contact Person at destination: (Name/Mobile
Materials Information
Case No. Unit of Quantity
Item No. Vendor ITEM CODE PARENT DESCRIPTION OCI
Ericsson Product Code Measure Dismantle
1 Nokia
2 Nokia
3 Nokia
4 Nokia
5 Nokia
6 Nokia
7 Nokia
8 Nokia
9 Nokia
10 Nokia
11 Nokia
12 Nokia
13 Nokia
14 Nokia
15 Nokia
16 Nokia
17 Nokia
18 Nokia
19 Nokia
20 Nokia
21 Nokia
22 Nokia
23 Nokia
24 Nokia
25 Nokia
26 Nokia
27 Nokia
28 Nokia
29 Nokia
30 Nokia

Requestor/Applicant (Name): Name/Signature/Date:


Airtel Line Manager (Name)*: Name/ Signature/Date:
Finance Approver (Name)*: Name/ Signature/Date:
Airtel SCM (Warehouse) Approver (Name)*: Name/ Signature/Date:
SDV Warehouse Manager (Name): Name/ Signature/Date:
Issued By: Name/ Signature/Date:
Collected By: Name/ Signature/Date: