Sirajganj 225 MW CCPP (Unit-3)

Work to be performed in upcoming shutdown


S/N Activities Responsibility
1 Performing functionality test of GT HCO System just before shut
Operation
down.
2 Checking the GT operation mode, Transfer from premix to diffusion
CMC
issue.
3 Performing Low Vacuum Protection Trip during ST shutdown. All
4 Performing EPB (at GT Hall) Protection Trip during GT shutdown. All
5 GT Air Intake system Pre-Filter and Fine Filter replacement. MMD
6 Rectification of the movement of seal water flow indicator and water
MMD
leakage of Condensate Pump- B (CEP-B)
7 Cleaning the strainer of CCCW heat Exchanger-B MMD
8 GT UPS-01 to be taken into service. EMD, CMC
9 Calibration of Air intake Pressure Transmitter I&C
10 Rectification of GT hydraulic oil leakage from the outlet Pressure
MMD, I&C
Transmitter.
11 Testing the communication system between HMI & PLC of diverter
EMD, I&C, CMC
damper.
12 Replacement of limit switches of Guillotine damper. EMD, I&C
13 Replacement of Filter of Diverter Damper seal air fan. MMD, EMD
14 Replacement of Fan of GT Application server. I&C
15 Checking of Gas Detector near and surroundings of GT. I&C
16 Checking the flow transmitter of Auxiliary Cooling water. I&C
17 Installation of reduction gear of Boiler HP super heater de-
CMC
superheating water MOV.
18 Cooling Tower Fan #3, Lube oil replacement; chamber and filter
CMC
cleaning.
19 Rectification of inaccurate feedback of CWP-B outlet valve. CMC
20 Checking the Bearing spare temperature sensor of CEP-B CMC
21 Rectification of fault alarm of ST speed controller. CMC
22 Cleaning of ST UPB Box de-superheating water nozzle. CMC