Method Statement for Piling Works Constructions —
Drilling
By Web Master | January 7, 2018 0.Comment
A crawler mounted piling ig will be used to install bored cast in situ piles of dia 1200 mm, The
procedure For the construction of bored piles, with temporary casing under bentonite / water support
‘system, compricas the following key elements:
= Setting up at the pile location
= Inctallation of temporary gulde casing
= Drilling of the pile borehole
Recycling of Bentonite and checking
= Reinforcement cages installation
= Sonic logging Tube installation
= Conereting
= Removal of temporary guide casing
‘Temporary Guide Casing
‘Atemporary guide casing of internal diameter 1200 mm according to the approved pile layout drawing
‘shall be inctalled to the pile center as previously marked on the working platform. The casing shall be
lowered to the ground with the help of turntable of the rotary unit or with vibrator. Engineer's approval
«will be sought prior to the use of vibrator.
‘The temporary casing used will be free from any distortion and shall be uniform cross-section
throughout the length. The length of the casing will be approx. 6.0 meters, depending on the cut-off
level. The temporary steel casing will be driven in the pile center with 2 minimum over lap of 50 cm
below cut-off level.
‘Two numbers reference steel pins will be installed
equidistant from the pile point. The distance of the
‘steal casing Is measured From the reference pins
and adjustment made so that the reference pins are
equidistant from the steel casing, The verticality of
the steel casing is checked with a spirit level in two
perpendicular directions. Further the verticality can
be controlled by an in-built inclinameter fixed to the
boom of machine, The verticality of drilled borehole
‘will be recorded in the pile record sheet. The piles.
drilled from -13.33 m DID and below will be drilled
using temporary long casing and ground water subject to achieving satisfactory performance from the
trial drilling. All other piles that drilled from -2.25 m to -12.35m working platform level shall be drilled
‘with temporary casing and bentonite slurry support system. A crial bore hole to be constructed to check
the Feasibility of drilling with water.Drilling With Water And Temporary Casing
Atrial bore hole shall be carried out at the required working platform level (-13.33 m DMD) to check the
Feasibility of boring using water as drilling Fluid. The water level inside the bore shall be kept minimum
1.50 m higher than the surrounding ground water level. The bottom of the borehole to be cleaned
using cleaning bucket. The bore hole to be monitored for minimum 12 hours, f excessive sedimentation
(or collapse is noticad during the tral drilling the bore hole will be back filled immediately and the
‘working pile inctallation willbe carried out using temporary casing and bentonite slurry support
system.
DRILLING OF PILE BOREHOLE USING BENTONITE ( For piles drilled from Higher working Platform
level Above 13.33 m DMD)
‘After installation of the temporary guide casing, the borehole will be drilled using appropriate drilling
tools and the verticality of the drilled borehole shall be encured to its Full depth. The Slurry Support.
‘System relies on the presence of a thixotropic mud-water mix to maintain the stability of the sidewalls
ine drilled borehole. Further the positive hydrostatic pressure developed by the slurry also avoids
ground water penetration in the drilled pile shaft.
Bentonite complying with Specification DFCP-4 drilling Auid materials will be used to Form the Slurry.
Control tests will be performed on the bentonite suspension as per specifications. The drilling Fluid is
prepared in mixers and kept in tanks for storage and hydration purpose For a minimum period of 6
hours. After fixing of guide casing, the borehole will be drilled down to ies Final level by means of
bucket and auger.
‘The drilled borehole will be filled with bentonite slurry and the slurry level maintained at working
platform level atall times. Care shall be takan to maintain the slurry 1.50 m above the ground water
table. In the event of a rapid loss of drilling Fluid, the borehole will be backfilled without delay using
the drilled material from the heap near the boreholes. The Engineer's approval must be obtained
before resuming boring in that location.Drilling penetration rate and soil cuttings will be kept under observation to notice any change in the
‘sub-soil conditions from previous soil investigation. The record of strata will be made during excavation
ofthe pile and recordad on che pile racord sheet.
‘Any noticeable variation shall be brought to the attention of the Engineer. The depth of borehole shall
be measured using an end weighted measuring tape and to be recorded in the pile record sheet. The
verticality of the borahole will be guarantead in two ways:
1. Ahand held spirit level of 1.0 m length shall be used to check the verticality af mast and thereby
that of the casing at two directions of 90° to one another at intervals.
2.Some machines are equipped with in built inclinometers Fixed to the boom of the machine, which
‘can monitor the drilling operations to keep the verticality within the specified limits. The
maximum out of verticality allowed as per specification is 12.5% of the pile diameter or 1.5% of
pile langth which ever i smaller.
Excavate shafts for closely spaced drilled piles (< 3 x diameter), only after adjacent drilled piles are
filled with concrete and allowed to set. (Normally after 12.0 hours)
RECYCLING IN CASE OF BENTONITE DRILLING
‘The process of cleening the bentonite suspension from sands and silts to keep its quality within the
allowable limits is called recycling. The bentonite quality will be verified by checking the sample taken
From the top and bottom of the borehole. IF excassive sand contents are noticed in the bentonite
‘sample then fresh bentonite semple shall be pumped through the sealed tremie pipe. The tremie pipe
‘shall extend to the bottom of the borehole. The sample From the borehole shall be checked for its
compliance with specification requirements.
Recycling will be performed after excavation has been completed and before the bentonite slurry has
been replaced by concrete. The suspension from the borehole will be pumped to the desanding plant
during concreting, After being cleaned in the plant, the bentonite will be pumped to the bentonite
tank for Further use. For cleaning operation of the bottom of the borehole a cleaning bucket will be
used,BENTONITE SUSPENSION
‘We propose a bentonite concentration of 5%. Bentonite slurry will have the following properties.
Supply to ‘Sample from
Pile Borahole
Density < 1.10 gfem?
Plastic Viscosity 2 <100P
Viscosity + 30 to 40 seconds
Ph value 9.5 to 10.80
Sand content <1%
Shear Strength 4-25Njme
Fluid loss, +: <30 mil.
Pile Borehole
1.45 gfem?
<200P
<60 seconds
95 to 11,70
3%
4-25 N/m?
<40 mil,
In order to achieve concentration of 5%, 50 kg of bentonite will be added to approximately 1000 liters,
of water.
‘Mixing will take place in a mixing plant designed by BAUER for this purpose. The bentonite slurry chall
restin a tank For at least 6 hours to allow proper hydration,
“The schematic layout of the bentonite mixing arrangement is attached,
Capacity of storage tank =
no. x (12x25 x25) m= 3000m?
‘The maximum number of piles to be drilled at one time = 5 nos.
Required volume of suspension = 5x { p (1.20)? x41.0mx 12 }/4
= 278m?
Hence required volume of suspension « capacity of storage tank. Hence safe,
‘TESTING FREQUENCY OF BENTONITE
‘The bentonite slurry shall be checked for specification compliance at suitable intervals. One sample
shall be taken from the top of the borehole and another sample Fram the bottom to check compliance
‘with the specification requirements. We propose the Following sequence of bentonite slurry testing
For each pile
1, Sample from the tank to the borehole,
2. The sample during drilling of the borehole.
43. The sample prior to concreting (one sample from the tap & one sample From the bottom),
‘The bentonite powder is supplied with the test certificate from independent agency. However
‘occasional testing can be carried out on powder sample IF required by Engincer.