Contract 3: Fiche – Gohatsion Road Overlay project (km 102+000 – 177+147) Ethiopian Roads Authority
Section VII:
Form of Bid, Appendix to Bid and Bid Security
Bidding Document Section VII: Form of Bid, Appendix to Bid and Bid Security
Addis Ababa – Gohatsion Road Upgrading and Overlay Project,
Contract 3: Fiche – Gohatsion Road Overlay project (km 102+000 – 177+147) Ethiopian Roads Authority-VII - 1
Form of Bid
Name of Contract: Addis Ababa – Gohatsion Road Upgrading and Overlay Project,
Contract 3: Fiche – Gohatsion Road Overlay project (km 102+000 – 177+147)
Gentlemen:
For the purpose of calculating payments, the total bid Price for the Contract Works
tendered in Part (i) above shall be apportioned to the following Output Categories
(refer to Payment Schedules) using the percentages in the following table:
4. We agree to abide by this Bid until the date 120 days from date of bid submission
specified in the Bidding Data and it shall remain binding upon us and may be accepted
at any time before that date.
Bidding Document Section VII: Form of Bid, Appendix to Bid and Bid Security
Addis Ababa – Gohatsion Road Upgrading and Overlay Project,
Contract 3: Fiche – Gohatsion Road Overlay project (km 102+000 – 177+147) Ethiopian Roads Authority-VII - 2
5. Unless and until a formal Agreement is prepared and executed, this Bid, together with
your written acceptance thereof, shall constitute a binding Contract between us.
6. We understand that you are not bound to accept the lowest or any bid you may
receive.
7. We certify/confirm that we comply with the eligibility requirements as per ITB Clause 3
of the bidding documents.
9. We hereby certify that we have taken steps to ensure that no person acting for us or
on our behalf will engage in bribery.
Address:
Witness:
Address:
Occupation
Bidding Document Section VII: Form of Bid, Appendix to Bid and Bid Security
Addis Ababa – Gohatsion Road Upgrading and Overlay Project,
Contract 3: Fiche – Gohatsion Road Overlay project (km 102+000 – 177+147) Ethiopian Roads Authority-VII - 3
Appendix to Bid
Bidders should fill in all the appropriate blank spaces. Bidders are required to sign each page
of the Appendix to Bid.
5.1 (b) The law in force is that of the Federal Democratic Republic of
Ethiopia
Priority of Contract 5.2 Other documents forming part of the contract document are:-
Documents
Anti-Bribery Pledge Form,
Performance Guarantee,
Forms Advance Payment Guarantee, Forms of
Advance Payment Disbursement Agreement and
Advance Payment Disbursement Schedule (if
applicable)and
Disputes Settlement Procedure
Performance 10.1 The performance security will be in the form of bank/insurance
Security guarantee in the amount of ten (10) percent of the Contract
price.
Access to Data 11.2 Data made available by the Employer under Sub-Clause 11.1 is
open for inspection at the Engineering Procurement
Directorate; Ethiopian Roads Authority; ERA Building, 2nd floor,
Room No. 207, Ras Abebe Aregay Street Addis Ababa; Ethiopia.
Cash Flow Estimate 14.3 Within 42 (Forty two) days of receipt of the Letter of
Acceptance.
Country of the 16.4 The country of the Employer is the Federal Democratic Republic
Employer of Ethiopia
Minimum Amount of 23.2 1,000,000 (one million) Birr per occurrence, with the number of
Third-Party occurrences unlimited.
Insurance
Time for Issue of the 41.1 Within 35 (Thirty Five) days of receipt of the Letter of
Notice to Acceptance.
Commence
Bidding Document Section VII: Form of Bid, Appendix to Bid and Bid Security
Addis Ababa – Gohatsion Road Upgrading and Overlay Project,
Contract 3: Fiche – Gohatsion Road Overlay project (km 102+000 – 177+147) Ethiopian Roads Authority-VII - 4
Time for Completion 43.1 The Completion time for the Contract is ten (10)calendar years
from the Start Date of the Contract under which the first three
(3) years will be for undertaking of Overlay Woks from the
start date and the remaining 7 (Seven) Years will be for Road
Asset Management And Maintenance Period as per Separable
Portions detailed below:
Separable Portion 1: One (1) calendar year from the Start Date
of the Contract (Year 1)
Separable Portion 2: One (1) calendar year from the End Date
of Year 1
Separable Portion 3: One (1) calendar year from the End Date
of Year 2
Separable Portion 4: One (1) calendar year from the End Date
of Year 3
Separable Portion 5: One (1) calendar year from the End Date
of Year 4
Separable Portion 6: One (1) calendar year from the End Date
of Year 5
Separable Portion 7: One (1) calendar year from the End Date
of Year 6
Separable Portion 8: One (1) calendar year from the End Date
of Year 7
Separable Portion 9: One (1) calendar year from the End Date
of Year 8
Separable Portion 10: One (1) calendar year from the End Date
of Year 9
The completion time for the periodic overlay Works for each
Separable Portion is as defined in the Specifications – PART A.
Periodic Overlay Works that failed to achieve verified
substantial completion within these time frames will have
liquidated damaged applied in accordance with GC Clause 47.1
Amount of 47.1 0.1% of the value of the works not taken over per day.
Liquidated Damages
Bidding Document Section VII: Form of Bid, Appendix to Bid and Bid Security
Addis Ababa – Gohatsion Road Upgrading and Overlay Project,
Contract 3: Fiche – Gohatsion Road Overlay project (km 102+000 – 177+147) Ethiopian Roads Authority-VII - 5
Damages
Defects Liability 49.1 365 days from the issue of the Taking Over Certificate of the last
Period section under Clause 48.
Maximum Amount 60.7 Maximum Amount of advance payment shall be 20% (twenty
of Advance Payment percent) of the of the sum of Apportioned Values for Periodic
overlay maintenance Works and Management and Maintenance
Services under the Contract, with the associated amount of VAT
less Contingencies, Provisional Sum and Day works fulfilling the
following conditions;
Start Repayment of 60.7 After certification of 30 (thirty) percent of the Contract Price
Advance Payment less Contingencies, Specified Provisional Sum and Day works.
Monthly Recovery of 60.7 40 (forty) percent of the amount of monthly Interim Payment
Advance Payment Certificates less Contingencies, Specified Provisional Sum and
Day works.
Final Statement
Settlement of 67.1 The appointing authority shall be:
Disputes
Addis Ababa Chamber of Commerce and Sectoral Associations
Arbitration Institute
Rules of procedure 67.3.2 Addis Ababa Chamber of Commerce and Sectoral Associations
Arbitration Institute Rules
Arbitration shall take place in Addis Ababa
Notice to Employer 68.2 The Employer’s address is:
and Engineer
The Director General
Ethiopian Roads Authority
Ras Abebe Aregay Street
P.O.Box 1770
Addis Ababa
Ethiopia
The items on the following pages are to be filled in by the bidder as part of its bid,
Rate of Interest 60.8 1 (one) percent above the National Bank of Ethiopia
upon Unpaid Sums lending rate.
In Tables A, bidders shall (a) indicate their amounts of payment, (b) indicate their proposed
source and base price /indices for the different elements of cost, (c) derive their proposed
weightings for payment as indicated below.
1. Sources of cost price adjustment indices shall be from recognized relevant national
organizations and shall be acceptable to the Employer.
2. The Base Values of indices shall be those prevailing at the date 28 days prior to the
latest date for submission of Bids and shall be substantiated by Bidders by appending
copies of the relevant publication.
3. General part of the priced Bill of Quantities, Bill I – General Provision is a non
adjustable portion.
Bidding Document Section VII: Form of Bid, Appendix to Bid and Bid Security
Addis Ababa – Gohatsion Road Upgrading and Overlay Project,
Contract 3: Fiche – Gohatsion Road Overlay project (km 102+000 – 177+147) Ethiopian Roads Authority-VII - 7
Table A1: Weightings Applicable for Series 1000 – General (Non adjustable)
Bidder’s Bidder’s
Index Index Source of Base value related proposed
code description index and date currency weighting
amount
- Non-adjustable — — — a:15%
E Equipment b:60%
B Bitumen c:
F Fuel d:20%
Reinforcing
S e:
Steel
C Cement f:
Total 100%
Bidder’s Bidder’s
Index Index Source of Base value related proposed
code description index and date currency weighting
amount
- Non-adjustable — — — a:15%
E Equipment b:30%
B Bitumen c:
F Fuel d:5%
Reinforcing
S e:15%
Steel
C Cement f :35%
Total 100%
Bidding Document Section VII: Form of Bid, Appendix to Bid and Bid Security
Addis Ababa – Gohatsion Road Upgrading and Overlay Project,
Contract 3: Fiche – Gohatsion Road Overlay project (km 102+000 – 177+147) Ethiopian Roads Authority-VII - 8
Bidder’s Bidder’s
Index Index Source of Base value related proposed
code description index and date currency weighting
amount
- Non-adjustable — — — a:15%
E Equipment b:70%
B Bitumen c:
F Fuel d:15%
Reinforcing
S e:
Steel
C Cement f:
Total 100%
Table A5: Weightings Applicable for Series 5000 – Sub Base, Road Base & Gravel Wearing
Course
Bidder’s Bidder’s
Index Index Source of Base value related proposed
code description index and date currency weighting
amount
- Non-adjustable — — — a:15%
E Equipment b:75%
B Bitumen c:
F Fuel d:10%
Reinforcing
S e:
Steel
C Cement f:
Total 100%
Table A6: Weightings Applicable for Series 6000 – Bituminous Surfacing and Road Bases
Bidder’s Bidder’s
Index Source of Base value related proposed
Index description
code index and date currency weighting
amount
- Non-adjustable — — — a:15%
E Equipment b:50%
B Bitumen c:25%
F Fuel d:10%
S Reinforcing Steel e:
C Cement f:
Total 100%
Bidding Document Section VII: Form of Bid, Appendix to Bid and Bid Security
Addis Ababa – Gohatsion Road Upgrading and Overlay Project,
Contract 3: Fiche – Gohatsion Road Overlay project (km 102+000 – 177+147) Ethiopian Roads Authority-VII - 9
Bidder’s Bidder’s
Index Source of Base value related proposed
Index description
code index and date currency weighting
amount
- Non-adjustable — — — a:15%
E Equipment b:30%
B Bitumen c:
F Fuel d:5%
S Reinforcing Steel e:15%
C Cement f :35%
Total 100%
Bidder’s Bidder’s
Index Source of Base value related proposed
Index description
code index and date currency weighting
amount
- Non-adjustable — — — a:15%
E Equipment b:20%
B Bitumen c:
F Fuel d:5%
C Cement f :20%
Total 100%
Bidding Document Section VII: Form of Bid, Appendix to Bid and Bid Security
Addis Ababa – Gohatsion Road Upgrading and Overlay Project,
Contract 3: Fiche – Gohatsion Road Overlay project (km 102+000 – 177+147) Ethiopian Roads Authority-VII - 10
Wearing Course
ndex code
Clearance
Works
Non-
- 15% 15% 15% 15% 15% 15% 15%
adjustable
E Equipment 55 - 65% 25 - 35% 55-70% 55 -80% 50 - 60% 25 - 35% 15 -20%
B Bitumen - - - - 15 - 30% - -
Bidding Document Section VII: Form of Bid, Appendix to Bid and Bid Security
Addis Ababa – Gohatsion Road Upgrading and Overlay Project,
Contract 3: Fiche – Gohatsion Road Overlay project (km 102+000 – 177+147) Ethiopian Roads Authority-VII - 11
a. The bidder shall enter in this schedule a list of the specialized works and approximate value
of the work for which he proposes to use specialist subcontractors, together with the names
and addresses of the proposed subcontractors.
SEALED WITH THE Common Seal of the said Bank this______ day of ________, 20__.
1. if the Bidder withdraws his bid during the period of bid validity specified in the Form
of bid
OR
OR
3. if the Bidder having been notified of the acceptance of his Bid by the Employer
during the period of Bid validity:
(a) fails or refuses to execute the Form of Agreement in accordance with the Instruction to
Bidders
(b) Fails or refuses to furnish the performance security in accordance with the Instruction to
Bidders.
We undertake to pay to the Employer up to the above amount upon receipt of his first
written demand, without the Employer having to substantiate his demand, provided that in
his demand the Employer will note that the amount claimed by him due to him is owing to
the occurrence of one or more of the above conditions, specifying the occurred condition or
conditions.
Bidding Document Section VII: Form of Bid, Appendix to Bid and Bid Security
Addis Ababa – Gohatsion Road Upgrading and Overlay Project,
Contract 3: Fiche – Gohatsion Road Overlay project (km 102+000 – 177+147) Ethiopian Roads Authority-VII - 12
This Guarantee will remain in force up to and including the date 28 days after the date of
expiration of the bid validity, as stated in the Instruction to Bidders or as it may be extended
by the Employer, notice of which extension(s) to the Bank is hereby waived. Any demand in
respect of this Guarantee should reach the Bank not later than the above date.
DATE____________________
Bidding Document Section VII: Form of Bid, Appendix to Bid and Bid Security
Addis Ababa – Gohatsion Road Upgrading and Overlay Project,
Contract 3: Fiche – Gohatsion Road Overlay project (km 102+000 – 177+147) Ethiopian Roads Authority-VII - 13
Know all men by these presents that we, the principal and the surety, above named are held
and firmly bound unto Ethiopian Roads Authority (Hereinafter Called” The Client”) in the
bond amount stated above for the payment of which sum well and truly to be made we bind
ourselves, our heirs, executors, administrators, successors and assigns jointly and severally
by these presents.
At the request of the bidder, we ------------------------------ hereby undertake to pay you any sum or
sums not exceeding in the total amount Birr --------------------(----------------------) accompanied by a
written statement stating that the bidder is in breach of its obligation (s) under the bid
conditions because the bidder:-
a) has withdrawn its bid during the period of bid validity specified by the bidder in the
form of bid; or
b) having been notified of the acceptance of its bid by the employer during the period
of bid validity, (i) fails or refuses to execute the contract form, if require or (ii) fails or
refuses to furnish the performance security, in accordance with the instructions to
bidders and (iii) refuses to accept the Arithmetic correction of error in his bid
This guarantee will expire: (a) if the bidder is the successful bidder, upon our receipt of
copies of the contract signed by the bidder and the performance security issued to you upon
the instruction of the bidder; or (b) if the bidder is not the successful bidder, upon the earlier
of (i) our receipt of a copy of your notification to the bidder of the name of the successful
bidder; (ii) twenty – eight days after the expiration of the bidder’s bid.
Consequently, any demand for payment under the guarantee must be recovered by us at the
office on or before that date.
Bidding Document Section VII: Form of Bid, Appendix to Bid and Bid Security
Addis Ababa – Gohatsion Road Upgrading and Overlay Project,
Contract 3: Fiche – Gohatsion Road Overlay project (km 102+000 – 177+147) Ethiopian Roads Authority-VII - 14
–––––––––––––––––––––– –––––––––––––––––––––
Principal Surety
Bidding Document Section VII: Form of Bid, Appendix to Bid and Bid Security