Professional Documents
Culture Documents
Materials Today: Proceedings
Materials Today: Proceedings
a r t i c l e i n f o a b s t r a c t
Article history: Time has become a major constraint in nearly all fields of life, let it be science, technology, medicine, arts
Received 14 March 2020 or any other field. In the context of manufacturing its impact comes to fore in the form of larger demands
Received in revised form 19 April 2020 that are supposed to be met in less time. In such a scenario, managers are forced to bring improvements
Accepted 7 May 2020
to their production systems to meet the required production target in less time. Cycle Time has to be
Available online xxxx
taken into consideration a feasible alternative whilst an agency is attempting to enhance: efficiency, pro-
ductivity, value base, customer responsiveness, velocity to the marketplace of latest services, merging of
Keywords:
tactics publish-acquisition, and flexibility. By casting off ‘‘fats” within the methods an organization is able
Kaizen
Lean Manufacturing (LM)
to make itself ‘‘lean”. This research focuses on suggesting feasible alternatives to decrease the cycle time
Non Value added activities and consequently increase the throughput of a batch production system in a sheet metal parts manufac-
Reduction turing firm. Siemens Tecnomatix has been used as the prime software in this research. In this research,
Lead time simulation is used as the main tool to experiment on the system with various feasible alternatives. After
the results of the simulation, the analysis has been presented regarding the extent of achievement of an
objective about various methods employed.
Ó 2020 Elsevier Ltd. All rights reserved.
Selection and peer-review under responsibility of the scientific committee of the International
Conference on Aspects of Materials Science and Engineering
https://doi.org/10.1016/j.matpr.2020.05.195
2214-7853/Ó 2020 Elsevier Ltd. All rights reserved.
Selection and peer-review under responsibility of the scientific committee of the International Conference on Aspects of Materials Science and Engineering
Please cite this article as: H. Kumar Banga, R. Kumar, P. Kumar et al., Productivity improvement in manufacturing industry by lean tool, Materials Today:
Proceedings, https://doi.org/10.1016/j.matpr.2020.05.195
2 H. Kumar Banga et al. / Materials Today: Proceedings xxx (xxxx) xxx
Table 1
Feasibility matrix for assembly line balancing.
Tasks A B C D E F G H I J K L M N O P Q R S
A 1 1 1 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1
B 1 1 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1
C 1 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1
D 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1
E 1 1 1 0 0 0 1 1 1 1 1 1 1 1
F 1 1 0 0 0 1 1 1 1 1 1 1 1
G 1 0 0 0 1 1 1 1 1 1 1 1
H 0 0 0 1 1 1 1 1 1 1 1
I 1 1 0 0 0 0 1 1 1 1
J 1 0 1 1 1 1 1 1 1
K 0 0 0 0 1 1 1 1
L 1 1 1 1 1 1 1
M 1 1 1 1 1 1
N 1 1 1 1 1
O 1 1 1 1
P 1 1 1
Q 1 1
R 1
S
iv. Work study, and adaptability of a framework to change, stock issues and
v. Reenactment and demonstrating. arranging of creation related exercises. In their work, they have
additionally clarified the significance and job of measurable con-
The sequential construction system adjusting issue contains a templations and irregularity in the improvement of a recreation
successful appropriation of complete work in regards to assem- model[15].
bling of an item among all the work stations [4] recommended that The hypothesis of imperatives was given by Eli Goldratt during
there are different ways to deal with mechanical production sys- the mid-1980s. The idea of hypothesis imperatives is condensed
tem adjusting as which incorporate heuristics, scientific demon- underneath as deciphered and depicted by [16]. Each framework
strating, tasks investigate based strategies, for example, direct should have at any rate one limitation. The nearness of limitations
programming and dynamic programming and careful methodol- delineates odds of improvement. As indicated by Goldratt as por-
ogy, for example, branch and bound strategy and so forth. Notwith- trayed by [16] while managing limitations administrators, for the
standing, heuristics don’t guarantee an ideal arrangement however most part, need to take three choices –
an almost ideal arrangement is required to be accomplished [5].
They talked about the fundamental heuristics which include the Decision of what should be changed.
positioning of errands as per a specific measure and afterward Decision of what it ought to be changed to.
redistributing the remaining task at hand to adjust the sequential Decision with respect to how to bring that change.
construction system [6–9]. The portrayed PC reproduction as an
unbendingly settled help apparatus for dynamic in the assembling Its about the significance of the hypothesis of limitations in
scene. They discovered an assortment of information, age of model assembling. They talked about decreasing lead time through the
and experimentation as the mainstays of recreation and if these hypothesis of limitations [17,18]. examined the use of the hypoth-
three components are of terrible quality, at that point there will esis of requirements for the coordinated poultry industry. They
be sure restraint to great outcomes. [10] After saw that when forms found that the hypothesis of imperatives tackled the issue of
as dissected become progressively tangled and perplexing and as throughput increase with no significant speculation. They pro-
more factors need to include, at that point re-enactment turns posed the improvement of the online data innovation framework
out to be increasingly significant with its examination of genuine and changes in deals strategy and deals choice criteria [19].
procedures. [11] These procedures can’t be secured by scientific The inspected the outcomes acquired from the utilization of the
procedures or advancement procedures or they might be done dis- hypothesis of limitations in the past writing. They found that the
tinctly by abusing countless assets. The point of reproduction is to hypothesis of limitations has been applied to various zones in
go ahead target choices by the energetic investigation, to engage recent years. They found that the associations which applied the
administrators to safely draw the plan, at last, to decrease cost hypothesis of limitations in the past have announced sizeable
[12] led a review on the utilization of re-enactment as an instru- enhancements in significant execution parameters as lead time,
ment for the activity and structure of assembling frameworks, throughput, and income and so on [20].
his examination additionally secured the advancement of recre- The case (sheet metal parts manufacturing firm) company man-
ation programming for assembling frameworks. [13,14] They ufactures various sheet metal parts such as ironing board, chassis
found that out of all-out writing he considered 49% of the papers support, fuel tanks, etc. The problem addressed in this study is of
were from the assembling frameworks plan classification, 41% of ironing board manufacturing process. The problem before the com-
the exploration papers had a place with the assembling frame- pany was that the customer for whom the ironing board was being
works activity classification and 9% papers were from the repro- manufactured was asking continuously to increase the supply, but
duction programming improvement region. the company due to the limited resource capacity and limited per-
The portrayed the nuts and bolts of the recreation of assembling sonnel was unable to meet out that demand of the customer.
frameworks. In their work they have expressly characterized the Therefore, there arose a possibility of slipping the orders from
advantages of recreation for assembling frameworks as throughput the company to any other similar company, due to this it became
assessment, arranging of control methodology, work in process essential for the company to somehow manage to increase its
examination, the prerequisite of laborers and hardware, versatility capacity and fulfill the demand of the customer. The current
Please cite this article as: H. Kumar Banga, R. Kumar, P. Kumar et al., Productivity improvement in manufacturing industry by lean tool, Materials Today:
Proceedings, https://doi.org/10.1016/j.matpr.2020.05.195
H. Kumar Banga et al. / Materials Today: Proceedings xxx (xxxx) xxx 3
production system produces nearly 900 (as discussed by the com- iii. Building a simulation model.
pany officials) parts per day. The customer wanted the company to iv. Experimentation on the simulation model.
supply 200 to 300 more pieces per day. Following points will be v. Analysis of results.
capable enough to present the problem more lucidly: - vi. Conclusion.
Fig. 1. Process Flow for the ironing board top manufacturing process.
Please cite this article as: H. Kumar Banga, R. Kumar, P. Kumar et al., Productivity improvement in manufacturing industry by lean tool, Materials Today:
Proceedings, https://doi.org/10.1016/j.matpr.2020.05.195
4 H. Kumar Banga et al. / Materials Today: Proceedings xxx (xxxx) xxx
Fig. 2. Precedence diagram for the ironing board top manufacturing process.
assembly line balancing was considered as an alternative which to fix the mesh in the frame of the ironing board top. So, it was
could reduce the cycle time and increase the throughput, but thought that if something could be done to fix the mesh in the
assembly line balancing was not feasible with this assembly line. frame and these processes could be eliminated as they were con-
The main alternatives which are considered in this study are- suming too much of time, then there can be a certain benefit to
the organization.
i. Assembly line balancing
ii. Theory of constraints 3.6. Building a simulation model
iii. Change in design of the product.
This step includes the construction of a simulation model.
3.3. Assembly line balancing Building the simulation model requires the probability distribution
of various processing times taken on different work stations. It also
The assembly line balancing approach for the reduction of cycle requires data regarding availability and MTTR. Then using simula-
time was also seen as an alternative in this study, as shown in Fig. 1 tion software such as TECNOMATIX in which the simulation model
the precedence diagram was referred for the generation of the fea- will be built.
sibility matrix [21,22]. After the precedence diagram was known
the next step was to construct the feasibility matrix. The Feasibility 3.7. Experimentation on the model
matrix for assembly line balancing as shown in Table 1. In con-
structing the flexibility matrix following are the basic rules This step includes the experimentation part of the already built
involved- simulation model. The experimentation process is necessary to
evaluate and analyze the results after the selection of alternatives.
i. The number of rows (I) and columns (j) of the matrix corre- The simulation also gives the real-time analysis of the assembly
spond to the number of task elements in the assembly line
problem.
ii. If task I must precede task j, a 1 is entered at the intersection 3.8. Analysis of results
of row I and column j otherwise, a 0 is entered at this
intersection. After experimentation results of the experiment needs to be
iii. The upper right half of the matrix is then used to calculate analyzed which will give an insight into how far have the selected
the F-ratio by the following formula: alternatives been able to meet the desired goal.
2h 4. Selection process
F¼
kðk 1Þ
The collection of data was the first step that was taken in the
The F ratio in this case came out to be 0.29, which means there
process. Data were collected by observing the work being done
is only 29% probability for this line to get balanced. So, this alterna-
in the case company. Data regarding the following activities were
tive was not further considered for the reduction of cycle time.
taken into consideration-
3.4. Theory of constraints i. Processing times (shown in Table 2) + loading and unloading
times
The theory of constraints tells about finding the bottleneck in ii. Availability of machines
the process and exploiting the bottleneck to make the best out of iii. Time taken to take the parts from one workstation to the
the system. Initially, in this process, we found that the whole sys- other.
tem is suffering from one or two big bottleneck processes. The first
bottleneck operation was extended cage forming operation which 4.1. Processing times and loading & unloading times
had the highest processing time of 41 s which was hindering in
other operations’ productivity. If, somehow this is improved or The readings of processing times and loading and unloading
removed the second big bottleneck was full welding straight times were taken considering both the times as a single unit
(FWS) operation which had a mean cycle time of 45.08 s. because in some processes it was difficult to separate the tasks
of loading and unloading from processing, for example in the pro-
3.5. Change in design of the product cess of Extended Cage Forming the coils of steel sheet automati-
cally unroll and the mesh is formed. In this process, it is difficult
In the study of the process it was analyzed that three continu- to separate the two. Moreover, the total time spent by a part on
ous welding operations i.e. tacking, full welding straight and full a workstation is the sum of both the times, therefore, loading,
welding radial were contributing to only one purpose which was unloading, and processing times have been taken as a single unit.
Please cite this article as: H. Kumar Banga, R. Kumar, P. Kumar et al., Productivity improvement in manufacturing industry by lean tool, Materials Today:
Proceedings, https://doi.org/10.1016/j.matpr.2020.05.195
H. Kumar Banga et al. / Materials Today: Proceedings xxx (xxxx) xxx 5
Table 2
Sample data of processing times (seconds) observed for a batch of size 30.
Arch making FWS Mesh fitting FWR Blanking Shaping Channel fitting Tacking Seam weld MIG weld
1236.9 1350.3 1205.1 709.8 1056 669.3 457.2 763.8 436.8 677.1
770.4 1230.9 1233.3 660.3 1371.3 600.3 501.6 744 371.7 1011.6
1565.7 1280.1 1170.6 1106.1 932.7 462.9 359.7 834.3 389.4 477.3
891 1046.1 1262.1 1203.3 1362 540 474 699.9 420 744.9
960 1533.3 1033.2 680.4 1176.6 444 639.3 810 520.8 870
999.3 1259.7 1287.9 1205.1 1119.6 417.6 619.5 843 562.5 559.2
1129.5 1458.6 1194 1026.6 1682.7 513.9 575.1 750 444 1056.6
1135.2 1374.3 1716.3 908.4 872.1 559.5 514.2 864 650 513
1266 1284 1146.3 970.2 1302 657 529.5 883.7 514.2 567
1164.6 1485 1284.9 953.4 945.6 569.1 303.6 696.3 512.7 715.2
1042.5 1232.1 807.9 1024.8 1582.5 421.2 480.9 814.2 600.9 747.9
1122 1347.6 1233.6 796.2 1026 467.1 577.5 774 480 810
970.5 1315.2 1149.9 891.3 1098.9 450.6 511.8 835.8 618 671.4
896.1 1383 1221 841.5 1050 598.8 513 799.2 661.4 624
865.2 1429.5 1253.7 931.2 1164.3 480.3 453.6 846.3 435.9 721.5
1131 1509 1226.7 814.5 1229.1 513.9 600.3 719.4 389.4 746.1
1035 1362 1113 885 1173 457.2 603.9 750.3 394.2 700.5
1128 1374 1294.2 760.2 1054.5 646.2 421.5 830.4 414.6 918
1121.7 1385.7 1231.2 897.3 903.3 591 436.5 735.6 437.1 681
1113.6 1435.5 1258.8 707.1 1092.6 357 527.4 822 501.9 690.3
1167.3 1233.6 1125.6 903.3 1476.3 418.5 688.8 702.9 595.8 641.1
1188.6 1320.9 1164 970.2 1014.6 632.1 657.9 762.3 868.2 687
1129.5 1355.4 1215.9 1134.3 1588.5 540.9 749.1 893.4 402.6 693.9
1025.4 1380 1602.3 871.2 1205.1 360 717.3 798.9 503.1 836.1
1377 1330.2 1140.3 1002.6 974.4 471.3 664.5 844.2 561.6 909.3
1410 1698.9 1197 834.3 1267.5 580.5 497.4 737.1 513.3 509.4
1169.4 1373.4 1370.1 702.3 1530 487.5 528.3 930.6 507 723.9
1203 1465.8 688.2 874.2 1254.9 453 567 901.6 615.9 608.1
977.7 1200.6 1113.9 846 1125 414.9 612 786 470.4 706.5
1204.8 1512.9 1255.5 931.5 948.9 474 570.3 835.5 503.7 754.2
The observations of processing and loading and unloading times 4.2.2. Blanking
for a single part as well as batch sizes of 10, 20, 30, 40 and 50. Blanking is another operation that faces such unavoidable hin-
The observations of times of only two segments of assembly line drance to production. In this case, the stoppage is due to the accu-
were made as the time for the third segment is very less as com- mulation of removed material on the bed of the press due to the
pared to the other two, therefore, a simulation study of only the press’ action. After every 12 pieces, the operator needs to clean
first two segments was required to increase the throughput. Table 2 the bed so that the press can function properly. Twenty readings
shows the sample processing times observed for a batch of 30. were taken to find out the meantime taken by the operator to clean
the bed. The mean came out to be 23.885. It takes 39.66 s to pro-
4.2. Availability of machines cess one piece in the blanking process so 12 pieces would take
475.92 s. So after every 475.92 s, there would be a lapse of
Data regarding the availability of machines was gathered from 23.885 s. Total operation time for one day is 52,776 s. So availabil-
the company and it was found that there are no considerable fail- ity can be given as under –
ures in the past one year but there are some small hindrances due
to which operation has to be stopped during work. This stoppage is
total operation time total down time
periodic and cannot be avoided hence it has been counted as a av ilability ¼
reduction in the availability of the machine. There are two such total operation time
workstations namely
If taken for one day, it comes out to be –
4.2.1. MIG welding
In MIG welding it was found that after every 18 pieces, an 52776 ð5277623:885Þ
electrode was changed and time consumed was observed 20 av ailability ¼ 475:92
¼ 0:9498 ¼ 94:98%
52776
times and mean was taken to represent the time taken to
change the electrode, the table below shows the sample. The The availability as calculated comes out to be 94.98% and 95.6%
mean came out to be 18.73 s. According to our data 24.03 is
the meantime taken by a job on MIG welding station, so 18
pieces would take 432.6 s. Now, after every 432.6 s, there will 4.3. Travel time
be a lapse of 18.73 s.
Travel time is the time taken in taking the part from one work-
station to the other. Since the parts are carried manually in trolleys,
total operation time total down time
av ailability ¼ therefore, there is not constant or fixed travel time between any
total operation time two workstations. So, it becomes necessary to mean or average
If taken for one day, it comes out to be – the time by taking a random sample of travel time between differ-
ent workstations. A sample of size 20 was selected and observa-
52776 ð5277618:3 Þ tions were made for the travel time between different
av ailability ¼ 432:6
¼ 0:956 ¼ 95:6%
52776 workstations.
Please cite this article as: H. Kumar Banga, R. Kumar, P. Kumar et al., Productivity improvement in manufacturing industry by lean tool, Materials Today:
Proceedings, https://doi.org/10.1016/j.matpr.2020.05.195
6 H. Kumar Banga et al. / Materials Today: Proceedings xxx (xxxx) xxx
Please cite this article as: H. Kumar Banga, R. Kumar, P. Kumar et al., Productivity improvement in manufacturing industry by lean tool, Materials Today:
Proceedings, https://doi.org/10.1016/j.matpr.2020.05.195
H. Kumar Banga et al. / Materials Today: Proceedings xxx (xxxx) xxx 7
[13] J. Mabin Victoria, J. Balderstone Steven, The performance of the theory of [18] Scholl Armin, Vob Stefan, Simple assembly line balancing – heuristic
constraints methodology: analysis and discussion of success full TOC approaches, J. Heuristics 2 (1996) 217–244.
applications, Int. J. Oper. Prod. Manage. 23 (6) (2003) 568–595. [19] Smith S. Jeffrey, Survey on the use of simulation for manufacturing system
[14] Miller Scott, Pegden Dennis, Introduction to manufacturing simulation, design and operation, J. Manuf. Syst. 22 (2) (2003) 157–171.
Proceedings of the Winter Simulation Conference, 2000. [20] Sokolowsky A. John, Banks M. Catherine, Modeling Simulation Fundamentals
[15] Narasimhan, Mcleavy, Billington, Production Planning and Inventory Control, Theoretical Underpinnings and Practical Domains, Wiley, 2010.
2nd edition., Prentice Hall of India, 2010. [21] Suresh Prasad, Dinesh Khanduja, Surrender K. Sharma, A study on
[16] M. Pagliosa, G. Tortorella, J. Ferreira, Industry 4.0 and lean manufacturing: a implementation of lean manufacturing in Indian foundry industry by
systematic literature review and future research directions, J. Manuf. Technol. analysing lean waste issues, Proc. Inst. Mech. Eng., Part B 232 (2) (2018)
Manage., Emerald Publishing Limited (2019). 371–378.
[17] Rahman Shams-Ur, Theory of constraints: a review of the philosophy and its [22] Richard J. Tersine, Edward A. Hummingbird, Lead-time reduction: the search
applications, Int. J. Oper. Prod. Manage. 18 (4) (1998) 336–355. for competitive advantage, Int. J. Oper. Prod. Manage. 15 (2) (1995) 8–18.
Please cite this article as: H. Kumar Banga, R. Kumar, P. Kumar et al., Productivity improvement in manufacturing industry by lean tool, Materials Today:
Proceedings, https://doi.org/10.1016/j.matpr.2020.05.195