Name :
Proj. Location :
PAY ITEM
DESCRIPTION UNIT QUANTITY UNIT COST AMOUNT
NO.
1.00 FACILITIES FOR THE ENGINEER
Operation and Maintenance of Temporary Field Office, Laboratory and
1.1. l.s. 1.00 ₱ 1,694,880.00 ₱ 1,694,880.00
Living Quarters Building for the Engineer.
Sub-Total ₱ 1,694,880.00
5.00 REINFORCEMENT
5.1. Footings kgs. 26,698.65 ₱ 74.88 ₱ 1,999,194.62
5.2. Columns kgs. 30,106.98 ₱ 74.88 ₱ 2,254,410.95
5.3. Footing Tie Beam kgs. 17,507.38 ₱ 73.55 ₱ 1,287,667.50
5.4. Slab on Fill kgs. 37,203.17 ₱ 73.55 ₱ 2,736,293.45
5.5. Suspended Slab (2nd Floor) kgs. 39,391.60 ₱ 73.55 ₱ 2,897,251.89
5.6. Suspended Slab (Roof Deck) kgs. 15,318.95 ₱ 73.55 ₱ 1,126,709.07
Sub-Total ₱ 12,301,527.48
6.00 FORMWORKS
6.1. Columns sq. m. 987.61 ₱ 1,132.39 ₱ 1,118,358.56
6.2. Suspended Slab (2nd Floor) sq. m. 2,356.71 ₱ 1,132.39 ₱ 2,668,715.40
6.3. Suspended Slab (Roof Deck) sq. m. 939.30 ₱ 1,132.39 ₱ 1,063,656.19
6.4. Roof Beams sq. m. 720.00 ₱ 1,132.39 ₱ 815,320.80
6.5. Falsework sq. m. 398.78 ₱ 1,132.39 ₱ 451,574.48
Sub-Total ₱ 6,117,625.43
Submitted by: