Professional Documents
Culture Documents
Technical Specifications - Site Development 65-Hectare in New Clark City 0420202
Technical Specifications - Site Development 65-Hectare in New Clark City 0420202
SITE DEVELOPMENT
65-HECTARE
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 1
SCOPE OF WORK
The construction procedures shall be done in accordance with the latest DPWH Standard
Specifications and in full compliance with the approved plans and specifications.
Pertinent notes appearing in the Contract Plans or Drawings shall also be considered as part and parcel
of the technical specifications. Such notes shall take precedence over the General Specifications.
A.1.1 (1) Construction of Combined Field Office, Laboratory and Living Quarters Building for
the Engineer
A.1.1 (11) Provision for Furniture/ Fixtures, Equipment and Appliances for the Living Quarters
for the Engineer
A.1.1 (14) Provision for Laboratory Testing Equipment, Apparatus and Publications for the
Engineer
A.1.1 (15) Operation and Maintenance of Temporary Field Office, Laboratory and Living
Quarters for the Engineer
1. The Contractor shall provide and maintain field offices and testing laboratories, including all
the necessary electricity, water, drainage, and telephone services for the use of the Engineer
and his staff. The offices and laboratories shall have at least the floor area prescribed on the
Plans and shall contain the equipment, supplies and furnishings specified in the Contract.
Testing equipment supplied in accordance with the Special Provisions shall be located in testing
laboratories as required by the Engineer. All offices and laboratories shall be ready for
occupancy and use by the Engineer within two (2) months of the commencement of the Works.
Their location and final plan shall require the approval of the Engineer prior to the start of
construction. It is the intent of this Specification to locate the field offices and laboratories in
government owned lots so that the use by the government of these facilities can be maximized
even after the completion of the project.
All facilities provided by the Contractor shall be near the job site, where necessary and shall
conform to the best standard for the required types. On completion of the Contract, the facilities
provided by the Contractor including utilities and communication facilities shall revert to the
Government including office equipment, apparatus, pieces of furniture, laboratory equipment,
etc., unless otherwise specified in the Contract documents.
The Contractor shall be responsible for raising the ground (if necessary), grading and drainage
in the vicinity of each facility with suitable access walkways, seeding and sodding of the ground
around as directed and approved by the Engineer. Also, the Contractor shall construct a parking
area for the compound near the buildings and a satisfactory access road to the parking areas.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 2
The Contractor shall be responsible for the maintenance and protection of all facilities to be
provided during the duration of the Contract, including providing adequate stock of all
expendable items, such as light bulbs, light tubes, laboratory equipment and supplies at all times
to ensure proper and continuous functioning of all the Engineer’s facilities.
The whole area of the Engineer’s compound shall be fenced with barbed wire (or equivalent)
with necessary gates as directed by the Engineer.
The Contractor shall provide suitable utilities and services, such as potable water, electricity,
sewerage, and security on a 24-hourbasis.
2. The Contractor shall provide qualified and experienced laboratory staff to carry out all the
materials quality control and all the tests specified in the Contract and required by the Engineer.
The person appointed by the Contractor to manage the laboratory shall be well experienced in
the type of work to be undertaken and shall be subject to the approval of the Engineer. He shall
work full time and shall be responsible to the Engineer for all works carried out.
3. The Contractor shall provide and maintain the communication facilities for the exclusive use
of the Engineer and Engineers representative as listed below:
Equipment
B. Cellular Phone
In order to have continuous operation and efficient maintenance of the equipment, the
Contractor shall provide monthly operating expenses including cost for servicing and minor
repairs.
The Contractor shall provide the communication facility/ equipment within thirty (30) days from
the issuance of the Notice to Proceed.
4. Any portable offices required in the Contract shall be dismantled, moved, and erected from
time to time as directed by the Engineer.
5. All offices, stores, and testing laboratories shall be proficiently guarded at all times of the day
and night, regularly and properly cleaned, adequately supplied and maintained for the duration
of the Contract.
A.1.2 PROVISION OF VEHICLES FOR THE ENGINEER INCLUDING PROVISION OF FUELS AND
MAINTENANCE SERVICES
A.1.2 (2) Provision for 4x4 Pick Up Type Service for the Engineer (Rental Basis) (4 units)
The Contractor shall provide within thirty (30) calendar days after notice to commence work,
the vehicles listed in the Special Provisions for the exclusive use of the Engineer. The vehicles
to be provided by the Contractor shall be to the satisfaction of the Engineer. All vehicles shall
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 3
comply in all respects with all relevant Philippine national or local laws statutes and regulations.
All vehicles shall carry or be fitted with the accessories as may be prescribed by laws and have
comprehensive insurance. The vehicles on delivery shall be new and shall be driven by a
competent qualified and experienced driver who shall be under the direct order of the Engineer.
The Contractor shall maintain the vehicle in first class condition and shall be supplied with
appropriate fuel and lubricants at all times.
The Contractor shall provide equivalent substitute vehicles during any period when the specified
vehicles are taken out of service for maintenance, repair or any other reason. Unless otherwise
specified, the vehicle shall at the end of the Contract become the property of the Government.
A.1.4 PHOTOGRAPHS
The Contractor shall provide record photographs taken as, when, and where directed by the
Engineer at intervals of not more than one month. The photographs shall be sufficient in number
and location to record the exact progress of the Works. The Contractor shall provide one proof
print of each photograph taken, and the negative and ten copies, not less than 254 mm x 203
mm and printed on glossy paper, of any of the photographs by the Engineer. The photographs
retained by the Engineer will become the property of the Government and the Contractor shall
supply approved albums to accommodate them. Two copies are to be signed by the Contractor,
one of which will be signed by the Engineer and returned to the Contractor.
The Contractor shall provide and maintain such offices, stores, workshops latrines, housing,
and messing accommodations as necessary. These shall be located in the Contractor’s
compound, distinct, and separate from the Engineer’s compound. The location, dimensions,
and layout of such buildings and places shall be subjected to the approval of the Engineer. The
Contractor shall not be permitted to erect temporary buildings or structures on the site without
the specific permission in writing of the Engineer including approval of the dimensions of such
buildings or structures. Before the commencement of the period Warranty, the contractor shall
fence off the Contractor’s store area from the rest of the site. By the end of the P
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 4
1. Description
This item shall consist of furnishing the necessary equipment and material to survey,
stake, calculate, and record data for the control of work in accordance with this
Specification and in conformity with the lines, grades, and dimensions shown on the
Plans or as established by the Engineer.
2. Construction Requirements
A. General
The Engineer shall set initial reference lines, horizontal and vertical control points, and
shall furnish the data for use in establishing control for the completion of each element
of the work. Data relating to horizontal and vertical alignments, theoretical slope stake
catch points, and other design data shall be furnished.
The Contractor shall be responsible for the true settling of the works or improvements
and for correctness of positions, levels, dimensions and alignment of all parts of the
works. He shall provide all necessary instruments, appliances, materials and supplies,
and labor in connection therewith. The Contractor shall provide a survey crew supervisor
at the project site whenever surveying/staking activity is in progress.
Prior to construction, the Engineer shall be notified of any missing initial reference lines,
controls, points, or stakes. The Engineer shall reestablish missing initial reference lines,
controls, points, or stakes.
All initial reference and control points shall be preserved. At the start of construction, all
destroyed or disturbed initial reference or control points necessary to the work shall be
replaced.
Before surveying and staking, the Contractor shall discuss and coordinate the following
with the Engineer:
Table 1
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 5
Existing Government network control point ±20 mm ±8 mm x VK<2)
d. Referencing
e. Structure control
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 6
(5) Take the cross-sections normal to the centerline + 1 degree.
(6) Bridge control is established as local network and the tolerances are relative
to that network.
The Contractor shall prepare field notes in an approved format. All field notes
and supporting documentation shall become the property of the government
upon completion of the work.
Work shall only be started after shaking for the affected work is accepted.
The construction survey and staking work may be spot-checked by the Engineer
for accuracy and unacceptable portions of work may be rejected. Rejected work
shall be resurveyed and work that is not within the tolerances specified in Table
1 shall be corrected. Acceptance of the construction staking shall not relieve the
Contractor of responsibility for correcting errors discovered during the work and
for bearing all additional costs associated with the error, unless such error is
based on incorrect data supplied in writing by the Engineer, in which case, the
expense in rectifying the same shall be at the expense of the Government.
All flagging, lath, stakes, and other staking materials shall be removed and
disposed after the project is completed.
B. Equipment
Acceptable tools, supplies, and stakes of the type and quality normally used in highway
survey work and suitable for the intended use shall be furnished. Stakes and hubs of
sufficient length to provide a solid set in the ground with sufficient surface area above
ground for necessary legible markings shall also be furnished.
All survey, staking, recording of data, and calculations necessary to construct the project
from the initial layout to final completion shall be performed. Stakes shall be reset as
many times as necessary to construct the work.
a. Control Points
b. Roadway Cross-Sections
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 7
Roadway cross-sections shall be taken normal or perpendicular to the centerline.
When the centerline horizontal vertical parabolic curve radius is less than or
equal to 100 meters, cross-sections shall be taken at a maximum centerline
spacing of 10 meters. When the centerline horizontal curve radius is greater than
150 meters and vertical parabolic curve radius is greater than 100 meters, cross-
sections shall be taken at a maximum centerline spacing of 20 meters. Additional
cross-sections shall be taken at significant breaks in topography and at changes
in the typical roadway section including transition change to super elevated
sections. Along each cross-section, points shall be measured and recorded at
breaks in topography and at changes in typical roadway section including
transition change to super elevated sections and shall be no further apart than 5
meters. Points shall be measured and recorded to at least the anticipated slope
stake and reference locations. All cross-section distances shall be reduced to
horizontal distances from centerline.
Slope stakes and references shall be set on both sides of centerline at the cross-
section locations. Slope stakes shall be established in the field as the actual
point of intersection of the design roadway slope with the natural ground line.
Slope stake references shall be set outside the clearing limits. All reference point
and slope stake information shall be included on the reference stakes. When
initial references are provided, slope stakes may be set from these points with
verification of the slope stake location with field measurements. Slope stakes on
any section that do not match with the staking report within the tolerances
established in Table 1 shall be recatched. Roadway cross-section data shall be
taken between centerline and the new slope stake location. Additional
references shall be set even when the initial references are provided.
Clearing and grubbing limits shall be set on both sides of centerline at roadway
cross-section locations, extending one (1) meter beyond the toe of the fill slopes
or beyond rounding of cut slopes as the case maybe for the entire length of the
project unless otherwise shown on the plans or as directed by the Engineer.
e. Centerline Reestablishment
Grade finishing stakes shall be set for grade elevations and horizontal alignment,
at the centerline and at each shoulder of roadway cross-section locations.
Stakes shall be set at the top of subgrade and the top of each aggregate course.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 8
Where turnouts are constructed, stakes shall be set at the centerline, at each
normal shoulder, and at the shoulder of the turnout. In parking areas, hubs shall
be set at the center and along the edges of the parking area. Stakes shall be set
at all ditches to be paved.
The maximum longitudinal spacing between stakes shall be 10 meters when the
centerline horizontal curve radius is less than or equal to 150 meters and vertical
parabolic curve radius is less than or equal to 100 meters. When the centerline
horizontal curve radius is greater than 150 meters and vertical parabolic curve
radius is greater than 100 meters, the maximum longitudinal spacing between
stakes shall be 20 meters. The maximum transverse spacing between stakes
shall be 5 meters. Brushes or guard stakes shall be used at each stake.
g. Culverts
Culverts shall be staked to fit field conditions. The location of culverts may differ
from the plans. The following shall be performed:
g.1 Survey and record the ground profile along the culvert centerline
including inlet and outlet channel profile of at least 10 meters and as
additionally directed by the Engineer so as to gather all necessary data
for the preparation of pipe projection plan.
g.2 Determine the slope catch points at the inlet and outlet.
g.4 Plot into scale the profile along the culvert centerline reflecting the
natural ground elevation, invert elevation, the flow line, the roadway
section, and the size, length and the degree of elbow of culvert, end
treatments, grade and other appurtenances.
g.5 Plot into scale the cross-section of inlet and outlet channel at not
more than 5 meters interval.
g.6 Submit the plotted Pipe Projection Plan for approval of final culvert
length, alignment and headwall.
g.7 When the Pipe Projection Plan has been approved, set drainage
culvert structure survey and reference stakes, and stake inlet and outlet
to make the structure functional.
h. Bridges
Adequate horizontal and vertical control and reference points shall be set for all
bridge structure and superstructure components. The bridge chord or the bridge
tangent shall be established and referenced. The centerline of each pier, bent,
and abutment shall also be established and referenced.
Set at least three (3) reference points each at downstream and upstream portion.
Conduct topographic survey and plot into scale at least 100 meters upstream
and downstream from centerline of bridge.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 9
i. Retaining Walls and Other Types of Slope Protection Works
Profile measurements along the face of the proposed wall and 2 meters in front
of the wall face shall be surveyed and recorded. Cross-sections shall be taken
within the limits designated by the Engineer at every 5 meters along the length
of the wall and all major breaks in terrain. For each cross-section, points shall be
measured and recorded every 5 meters and at all major breaks in terrain.
Adequate references and horizontal and vertical control points shall be set.
The work essential for initial layout and measurement of the borrow or waste site
shall be performed. A referenced baseline, site limits, and clearing limits shall be
established. Initial and final cross-sections shall be surveyed and recorded.
All surveying, staking, and recording of data essential for establishing the layout
and control of the following shall be performed, as applicable:
l.2 Road Right of Way and Construction limit in accordance with the
approved Parcellary Plan.
l.4 Guardrail
l.10 Utilities
3. Method of Measurement
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 10
Bridge survey and staking, and retaining wall survey and staking shall be measured by
the lump sum.
Slope, reference, and clearing and grubbing stakes shall be measured by the kilometer.
Permanent monuments and markers shall be measured by each unit placed and
installed at the proper locations.
Miscellaneous survey and staking shall be measured by the hour of survey work ordered
or by the lump sum. For miscellaneous survey and staking paid by the hour, the
minimum survey crew size shall be 2 persons. Time spent in making preparations,
travelling to and from the project site, performing calculations, plotting cross sections
and other data, processing computer data, and other efforts necessary to successfully
accomplish construction survey and staking shall not be measured separately but
deemed included as subsidiary for each of the Pay Item.
1. Description
This section shall consist of clearing, grubbing, removing, and disposing of all vegetation
and debris within the limits of the project site, including the borrow site, as designated in
the Contract except those objects that are designated to remain in place or are to be
removed in consonance with other provisions of this specification. The work shall also
include the preservations from injury or defacement of all objects designated to remain.
2. Construction Requirements
A. General
The Engineer will establish the limits of work and designate all trees, shrubs, plants,
and other things to remain if there are any.
Contact the Engineer at least 72 hours prior to construction for the location of all
existing underground utilities. Movement of construction machinery and equipment
over pipes and utilities during grading shall be at the Contractor's risk. For exposing
a utility or other buried obstruction, use hand or light equipment for excavation.
Start hand or light equipment stripping on each side of the indicated obstruction
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 11
and continue until the obstruction is uncovered or until clearance for the new grade
is assured. Support uncovered lines or other existing work as affected by the
contract grading until approval for filling is granted by the Engineer. Report damage
to utility lines or subsurface construction immediately to the Engineer. It will be the
responsibility and expense of the Contractor to repair and restore the damage to
its original state or even better.
All surface objects and all trees, stumps, roots and other protruding obstructions,
not designated to remain, shall be cleared and/or grubbed, including mowing as
required, except as provided below:
Except in areas to be excavated, stump holes and other holes from which
obstructions are removed shall be backfilled with suitable material and
compacted to the required density.
Materials and debris which cannot be burned and perishable material may
be disposed of by methods and at locations approved by the Engineer on
or off the project site. If the disposal location is outside the project area, the
Contractor shall make all necessary arrangements with the property owner
or owners in writing for obtaining suitable disposal locations. The cost
involved shall be included in the unit bid price. A copy of such agreement
shall be furnished to Owner or Engineer.
D. Method of Measurement
The work to be paid shall be the number of square meters and fractions thereof
acceptably cleared and grubbed within the limits indicated on the plans.
1. Trees
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 12
Comply with Department of Environment and Natural Resources (DENR)
regulations for protection of natural resources.
All concrete pavement, base course, sidewalks, curbs, gutters, etc., designated for
removal shall be:
2. Broken into pieces, the size of which shall not exceed 300 mm (12 inches) in any
dimension and stockpiled at designated locations on the project for use by the
Government, or
There will be no separate payment for excavating for removal of structures and
obstructions or for backfilling and compacting the remaining cavity.
1. GENERAL
A. Scope
This section includes demolition and removal of existing work in the way of new
construction.
B. References
C. General Requirements
Do not begin demolition until authorization is received from the Owner or Engineer.
Remove rubbish and debris from the project site. Store materials that cannot be
removed daily in areas specified by the Engineer.
D. Submittals
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 13
a. Demolition plan
Prevent the spread of dust and debris and avoid the creation of a nuisance or
hazard in the surrounding area. Do not use water if it results in hazardous or
objectionable conditions such as, but not limited to, flooding or pollution.
G. Protection
Where pedestrian and driver safety are endangered in the area of removal
work, use traffic barricades with flashing lights. Anchor barricades in a
manner to prevent displacement. Notify the Engineer prior to beginning
such work.
b. Existing Work
c. Weather Protection
d. Facilities
H. Burning
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 14
Burning will not be permitted. Where burning is permitted, adherence to local
regulations shall be required.
I. Relocations
3. CONSTRUCTION REQUIRMENTS
a. Structures
1. Description
ThisItemshallconsistofroadwayanddrainageandborrowexcavationandthedis
posal of material in accordance with this Specification and in conformity with
the lines, grades and dimensions shown on the Plans or established by the
Engineer.
2. Roadway Excavation
1. GENERAL
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 15
This section shall include the use of shoring, sheeting, bracing and all the other excavation
support system required during trench excavations for structures and pipes as specified
and directed herein.
2. TECHNICAL REQUIREMENTS
A. General
The Contractor shall furnish, install and maintain such sheeting, shoring, bracing
and other support system as may be required to support the sides of trench or
structural excavations, to prevent any earth movement which could diminish the
excavation width to below that necessary for construction, and to protect adjacent
structures from damage. The Engineer may direct that additional trench supports
be installed by the Contractor, at the Contractor's expense, should the existing
supports be deemed insufficient. Provision of additional supports (or acceptance
of existing supports) shall not relieve the Contractor of his sole responsibility for the
provision of adequate support of excavations, especially for the protection of
workmen.
Sheeting, shoring and bracing shall be placed to avoid the formation of voids
outside of the excavation, but if voids are formed, they shall be immediately filled
with compacted sand. The Contractor shall leave sheeting, shoring and bracing,
in place to be embedded in the backfill if directed to do so by the Engineer. The
Engineer may direct that sheeting and bracing be cut off at any specified elevation
and left in place. The Contractor will be paid for sheeting left in place in accordance
with the specifications. All sheeting not left in place shall be removed cautiously in
the presence of the Engineer to prevent damage to the construction or nearby
structures. Any voids formed by removal of sheeting shall be filled with structural
fill or as directed by the Engineer. Wood sheeting shall not be withdrawn if driven
below the spring line of a pipe, and any wood sheeting shall be cut off no lower
than one foot above the top of any pipe.
C. Responsibility
Failure by the Engineer to direct that sheeting, shoring or bracing shall be left in
place, will not relieve the Contractor of his responsibility for any damage caused
by removal of sheeting, whether due to his negligence or not. The Contractor is
fully responsible for providing a safe working condition for his and other
employees working on the site.
1. Description
This Item shall consist of the construction of embankment in accordance with this
Specification and in conformity with the lines, grades and dimensions shown on the
Plans or established by the Engineer.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 16
2. MaterialRequirement
Selected Borrow, for topping – soil of such gradation that all particles will
pass a sieve with 75 mm (3 inches) square openings and not more than
15 mass percent will pass the 0.075 mm (No. 200) sieve, as determined
by AASHTO T 11. The material shall have a plasticity index of not more
than 6 as determined by ASSHTO T 90 and a liquid limit of not more than
30 as determined by AASHTO T 89.
(e) Soils with very low natural density, 800 kg/m3 orlower.
3. Construction Requirements
A. General
Embankments and backfills shall contain no muck, peat, sod, roots or other
deleterious matter. Rocks, broken concrete or other solid, bulky materials
shall not be placed in embankment areas where piling is to be placed or
driven.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 17
Where shown on the Plans or directed by the Engineer, the surface of the
existing ground shall be compacted to a depth of 150 mm (6 inches) and to
the specified requirements of this Item.
Where provided on the Plans and Bill of Quantities the top portions of the
roadbed in both cuts and embankments, as indicated, shall consist of
selected borrow for topping fromexcavations.
B. Methods of Construction
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 18
Unless shown otherwise on the Plans or special Provisions, where an
embankment of less than 1.2 m (4 feet) below subgrade is to be made,
all sod and vegetable matter shall be removed from the surface upon
which the embankment is to be placed, and the cleared surfaced shall
be completely broken up by plowing, scarifying, or steeping to a
minimum depth of 150 mm except as provided in Subsection 102.2.2.
This area shall then be compacted as provided in Subsection 104.3.3.
Sod not required to be removed shall be thoroughly disc harrowed or
scarified before construction of embankment. Wherever a compacted
road surface containing granular materials lies within 900 mm (36
inches) of the subgrade, such old road surface shall be scarified to a
depth of at least 150 mm (6 inches) whenever directed by the
Engineer. This scarified material shall then be compacted as provided
in Subsection 104.3.3.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 19
exceeding in thickness theapproximate average size of the larger
rocks, but not greater than 600 mm (24 inches).
Dumping and rolling areas shall be kept separate, and no lift shall be
covered by another until compaction complies with the requirements
of Subsection 104.3.3.
C. Compaction
a. Compaction Trials
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 20
Throughout the periods when compaction of earthwork is in
progress, the Contractorshall adhere to the compaction
procedures found from compaction trials for each type of
material being compacted, each type of compaction equipment
employed and each degree of compaction specified.
b. Earth
c. Rock
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 21
During the construction of the roadway, the roadbed shall be
maintained in such condition that it will be well drained at all times.
Side ditches or gutters emptying from cuts to embankments or
otherwise shall be so constructed as to avoid damage to
embankments by erosion.
E. Protection of Structure
After the roadbed has been substantially completed, the full width
shall be conditioned by removing any soft or other unstable
material that will not compact properly or serve the intended
purpose. The resulting areas and all other low sections, holes of
depressions shall be brought to grade with suitable selected
material. Scarifying, blading, dragging, rolling, or other methods
of work shall be performed or used as necessary to provide a
thoroughly compacted roadbed shaped to the grades and cross-
sections shown on the Plans or as staked by the Engineer.
All earth slopes shall be left with roughened surfaces but shall be
reasonably uniform, without any noticeable break, and in reasonably
close conformity with the Plans or other surfaces indicated on the
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 22
Plans or as staked by the Engineer, with no variations therefromreadily
discernible as viewed from the road.
H. Serrated Slopes
Cut slopes in rippable material (soft rock) having slope ratios between
0.75:1 and 2:1 shall be constructed so that the final slope line shall
consist of a series of small horizontal steps. The step rise and tread
dimensions shall be shown on the Plans. No scaling shall be
performed on the stepped slopes except for removal of large rocks
which will obviously be a safety hazard if they fall into the ditchline or
roadway.
I. Earth Berms
a. Compacted Berm
Compactedbermconstructionshallconsistofmoisteningordrying
andplacingmaterial as necessary in locations shown on the
drawings or as established by the Engineer. Material shall
contain no frozen material, roots, sod, or other deleterious
materials. Contractor shall take precaution to prevent material
from escaping over the embankment slope. Shoulder surface
beneath berm will be roughened to provide a bond between the
berm and shoulderwhen completed. The Contractor shall
compact the material placed until at least 90 masspercent of
the maximum density is obtained as determined by AASHTO T
99, Method C. The cross-section of the finished compacted
berm shall reasonably conform to the typical cross- section as
shown on the Plans.
b. Uncompacted Berm
J. Method of Measurement
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 23
The quantity of embankment to be paid for shall be the volume of
material compacted in place, accepted by the Engineer and formed
with material obtained from any source.
Material for Selected Borrow topping will be measured and paid for
under the same conditions specified in the preceding paragraph.
1. Description
This work item shall consist of the preparation of the subgrade for the support
of overlying structural layers. It shall extend to full width of the roadway. The
road subgrade shall be brought to the elevation shown on the drawings. It
shall be compacted to a minimum of 95% Modified Proctor Density.
2. Materials Requirements
Unless otherwise stated in the Contract, all materials below subgrade level in
earth cuts to a depth of 150mm or to such greater depth as shown on the
plans or directed by the Engineer shall meet the requirements of Item 2.0,
Earthworks.
3. Construction Requirements
Prior to finishing of the subgrade, all culverts, cross drains, ducts and the like
(including their fully compacted backfill), drains and drainage outlets shall be
completed. Any work on the preparation of the subgrade shall not be started
unless prior work herein described shall have been approved by the
Engineer.
Permitted Variation from Design Longitudinal Grade over 25m length ±0.1%
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 24
Where material has been removed from below subgrade level, the resulting
surface shall be compacted to a depth of 150mm. The surface shall then be
replaced with approved suitable materials immediately below subgrade level
in earth cuts to a depth of 150mm, or to such greater depth as may be
specified and shall be compacted in accordance with the requirements of the
specifications.
1. Description
2. Materials Requirements
Grading Requirements
50 2" 100 -
25.0 1" 60 - 85 -
19.0 3/4" - 60 - 85
12.5 1/2" 35 - 65 -
4.75 No. 4 20 - 50 30 - 55
0.425 No. 40 5 - 20 8 - 25
The fraction passing the 0.075mm (No. 200) sieve shall not be greater
than 0.66 (two thirds) of the fraction passing the 0.425mm (No. 40)
sieve.
The fraction passing the 0.425mm (No. 40) sieve shall have a liquid
limit not greater than 25 and plasticity index not greater than 6 as
determined by AASHTO T89 and T90, respectively.
The coarse portion, retained on a 2.00mm (No. 10) sieve, shall have
a mass percent of wear not exceeding 50 by the Los Angeles
Abrasion test determined by AASHTO T96.
The material passing the 19mm (3/4 inch) sieve shall have a soaked
CBR value of not less than 80% as determined by AASHTO T193.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 26
The CBR value shall be obtained at the maximum dry density (MDD)
as determined by AASHTO T180, Method D.
3. Construction Requirements
B. Placing
D. Trial Sections
E. Tolerances
-10mm
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 27
Permitted Surface Irregularity 5mm
1. Description
This Item shall consist of a pavement of Portland Cement Concrete, with or without
reinforcement, constructed on the prepared base in accordance with this specification
and in conformity with the lines, grades, thickness and typical cross-sections shown
on the plans.
2. Material Requirements
A. Portland Cement
It shall conform to the applicable requirements of item 700, Hydraulic Cement. Only
Type I Portland Cement shall be used unless otherwise provided for in the Special
provisions. Different brands or the same brands from different mills shall not be mixed
nor shall they be used alternatively unless the mix is approved by the Engineer.
However, the use of Portland Pozzolan Cement Type IP meeting the requirements
of AASHTO M 240/ASTM C 595, Specifications for Blended Hydraulic Cement shall
be allowed, provided that trial mixes shall be done and that the mixes meet the
concrete strength requirements, the AASHTO/ASTM provisions pertinent to the use
of Portland Pozzolan Cement Type IP shall be adopted.
Cement which for any reason has become partially set or which contains
lumps of caked cement shall be rejected. Cement salvaged from discarded
or used bags shall not be used.
B. Fine Aggregate
It shall consist of natural sand, stone screenings, or other inert materials with similar
characteristics, or combinations thereof, having hard, strong and durable particles.
Fine aggregate from different sources of supply shall not be mixed or stored in the
same pile nor used alternately in the same class of concrete without the approval of
the Engineer.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 28
It shall not contain more than three (3) mass percent of material passing the 0.075
mm (No. 200 sieve) by washing nor more than one (1) mass percent each of clay
lumps or shale. The use of beach sand will not be allowed without the approval of the
Engineer.
If the fine aggregate is subjected to five (5) cycles of the sodium sulfate soundness
test, the weighted loss shall not exceed 10 mass percent.
The fine aggregate shall be free from injurious amounts of organic impurities. If
subjected to the colorimatic test for organic impurities and a color darker than the
standard is produced, it shall be rejected. However, when tested for the effect of
organic impurities on strength of mortar by AASHTO T 71, the fine aggregate may be
used if the relative strength at 7 and 28 days is not less than 95 percent.
The fine aggregate shall be well-graded from coarse to fine and shall conform to Table 1
Table 1
2.36 mm (No. 8) -
C. Coarse Aggregates
It shall consist of crushed stone, gravel, blast furnace slag, or other approved inert
materials (coralline or dolomites) of similar characteristics, or combinations thereof,
having hard, strong, durable pieces and free from any adherent coatings.
It shall consist of crushed stone, gravel, blast furnace slag, or other approved inert
materials of similar characteristics, or combinations thereof, having hard, strong,
durable pieces and free from any adherent coatings.
It shall contain no more than one (1) mass percent of material passing the 0.075 mm
(No. 200) sieve, not more than 0.25 mass percent of clay lumps, nor more than 3.5
mass percent of soft fragments.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 29
If the coarse aggregate is subjected to five (5) cycles of the sodium sulfate soundness
test, the weighted loss shall not exceed 12 mass percent.
It shall have a mass percent of wear not exceeding 40 when tested by AASHTO T
96.
If the slag is used, its density shall not be less than 1120 kg/m3. The gradation of the
coarse aggregate shall conform to Table 2.
Only one grading specification shall be used from any one source.
Table 2
37.5 1-1/2" 25 - 60 35 - 70 -
25.0 1" - 0 - 15 35 - 70
19.0 3/4" 0 - 10 - -
D. Water
E. Reinforcing Steel
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 30
It shall conform to the requirements of Item 404, Reinforcing Steel. Dowels and tie
bars shall conform to the requirements of AASHTO M31 or M42, except that rail steel
shall not be used for tie bars that are to be bent and restraightened during
construction. Tie bars shall be deformed bars. Dowels shall be plain round bars.
Before delivery to the site of work, one half of the length of each dowel shall be
painted with one coat of approved lead or tar paint.
The sleeves of dowel bars shall be metal of approved design to cover 50mm (2 in.),
plus or minus 5mm (1/4 in.) of the dowel with closed end, and with a suitable stop to
hold the end of the sleeve at least 25mm (1 in.) from the end of the dowel. Sleeves
shall be of such design that they do not collapse during construction.
F. Wire Mesh
The diameter of wire for lateral and longitudinal directions shall not be less than 6 mm
in diameter. Tie wire shall be No. 16 gauged annealed wire.
The spacing on the lateral direction is twice wider than that of the
longitudinal direction. The weight of wire mesh shall not be less than
3 kg/m2. It shall be fabricated by welding or binding at each crossing
point and shall meet the requirements of ASTM A 185.
G. Joint Fillers
Poured joint fillers shall be mixed asphalt and mineral or rubber filler
conforming to the applicable requirements of Item 705, Joint Materials.
Preformed joint filler shall conform to the applicable requirements of Item 705.
It shall be punched to admit the dowels where called for in the plans. The
filler of each joint shall be furnished in a single piece for the full depth and
width required for the joint.
H. Admixtures
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 31
Air-entraining admixture shall conform to the requirements of AASHTO M
154.
I. Curing Materials
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 32
The handling and storing of concrete aggregates shall be such as to prevent
segregation or the inclusion of foreign materials. The engineer may require
that aggregates be stored in separate platforms at satisfactory locations.
The Contractor shall prepare the design mix based on the absolute volume
method as outlined in the American Concrete Institute (ACI) Standard 211.1,
"Recommended Practice for Selecting Proportions for Normal and
Heavyweight Concrete".
The designer shall consider the use of lean concrete (econocrete) mixtures
using local materials or specifically modified conventional concrete mixes in
base course and in the lower course of composite, monolithic concrete
pavements using a minimum of 75mm (3 inches) of conventional concrete as
the surface course.
The mix design shall be submitted to the Engineer for approval and shall be
accompanied with certified test data from an approved laboratory
demonstrating the adequacy of the mix design. A change in the source of
materials during the progress of work may necessitate a new design mix.
3. Construction Requirements
a. General
The Contractor shall be responsible for the quality control of all materials
during the handling, blending, mixing and placement operations.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 33
b. Quality Control Plan
The Contractor shall furnish the Engineer a Quality Control Plan detailing his
production control procedures and the type and frequency of sampling and
testing to ensure that the concrete he produces complies with the
specifications. The Engineer shall be provided free access to recent plant
production records, and if requested, informational copies of mix design,
material certifications and sampling and testing reports.
c. Qualification of Workmen
The Contractor shall perform all sampling, testing and inspection necessary
to assure quality control of the component materials and the concrete.
The Contractor shall be responsible for determining the gradation of fine and
coarse aggregates and for testing the concrete mixture for slump, air content,
water-cement ratio and temperature. He shall conduct his operations so as
to produce a mix conforming to the approved mix design.
e. Documentation
The Contractor shall maintain adequate records of all inspections and tests.
The records shall indicate the nature and number of observations made the
number and type of deficiencies found, the quantities approved and rejected,
and nature of any corrective action taken.
B. Equipment
Equipment and tools necessary for handling materials and performing all parts of the
work shall be approved by the Engineer as to design, capacity and mechanical
condition. The equipment shall be at the jobsite sufficiently ahead of construction
operations to be examined thoroughly and approved.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 34
shall be equipped with a suitable non-resettable batch counter which
will correctly indicate the number of batches proportioned.
b. Mixers
b.3Truck Mixer and Truck Agitators. Truck mixers used for mixing and
hauling concrete, and truck agitators used for hauling central-mixed
concrete shall conform to the requirements of AASHTO M157.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 35
c. Paving and Finishing Equipment
The finishing machine shall be equipped with at least two (2) oscillating type
transverse screed.
d. Concrete Saw
e. Forms
C. Preparation of Grade
After the subgrade or base has been placed and compacted to the required density,
the areas which will support the paving machine and the grade on which the
pavement is to be constructed shall be trimmed to the proper elevation by means of
a properly designed machine extending the prepared work areas compacted at least
60 cm beyond each edge of the proposed concrete pavement. If loss of density
results from the trimming operations, it shall be restored by additional compaction
before concrete is placed. If any traffic is allowed to use the prepared subgrade or
base, the surface shall be checked and corrected immediately ahead of the placing
concrete.
The subgrade or base shall be uniformly moist when the concrete is placed.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 36
D. Setting Forms
a. Base Support.
The foundation under the forms shall be hard and true to grade so that the
form when set will be firmly in contact for its whole length and at the specified
grade. Any roadbed, which at the form line is found below established grade,
shall be filled with approved granular materials to grade in lifts of three (3) cm
or less, and thoroughly rerolled or tamped. Imperfections or variations above
grade shall be corrected by tamping or by cutting as necessary.
b. Form Setting.
Forms shall be set sufficiently in advance of the point where concrete is being
placed. After the forms have been set to correct grade, the grade shall be
thoroughly tamped, mechanically or by hand, at both the inside and outside
edges of the base of the forms. The forms shall not deviate from true line by
more than one (1) cm at any point.
The alignment and grade elevations of the forms shall be checked and
corrections made by the Contractor immediately before placing the concrete.
Testing as to crown and elevation, prior to placing of concrete can be made
by means of holding an approved template in a vertical position and moved
backward and forward on the forms.
When any form has been disturbed or any grade has become unstable, the
form shall be reset and rechecked.
When side forms have been securely set to grade, the subgrade or base coarse shall
be brought to proper cross-section. High areas shall be trimmed to proper elevation.
Low areas shall be filled and compacted to a condition similar to that of surrounding
grade. The finished grade shall be maintained in a smooth and compacted condition
until the pavement is placed.
Unless waterproof subgrade or base course cover material is specified, the subgrade
or base course shall be uniformly moist when the concrete is placed. If it subsequently
becomes too dry, the subgrade or base course shall be sprinkled, but the method of
sprinkling shall not be such as to form mud or pools of water.
The batch plant site, layout, equipment and provisions for transporting material shall
be such as to assure continuous supply of material to the work.
Stockpiles shall be built up in layers of not more than one (1) meter in thickness. Each
layer shall be completely in place before beginning the next which shall not be
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 37
allowed to "cone" down over the next lower layer. Aggregates from different sources
and of different grading shall not be stockpiled together.
When mixing is done at the side of the work, aggregates shall be transported from
the batching plant to the mixer in batch boxes, vehicle bodies, or other containers of
adequate capacity and construction to properly carry the volume required. Partitions
separating batches shall be adequate and effective to prevent spilling from one
compartment to another while in transit or being dumped. When bulk cement is used,
the Contractor shall use a suitable method of handling the cement from weighing
hopper to transporting container or into the batch itself for transportation to the mixer,
with chute, boot or other approved device, to prevent loss of cement, and to provide
positive assurance of the actual presence in each batch of the entire cement content
specified.
Bulk cement shall be transported to the mixer in tight compartments carrying the full
amount of cement required for the batch. However, if allowed in the Special
Provisions, it may be transported between the fine and coarse aggregate. When
cement is placed in contact with aggregates, batches may be rejected unless mixed
within 1-1/2 hours of such contact. Cement in original shipping packages may be
transported on top of the aggregates, each batch containing the number of sacks
required by the job mix.
The mixer shall be charged without loss of cement. Batching shall be so conducted
as to result in the weight to each material required within a tolerance of one (1)
percent for the cement and two (2) percent for aggregates.
Water may be measured either by volume or weight. The accuracy of measuring the
water shall be within a range of error of not more than one (1) percent. Unless the
water is to be weighed, the water-measuring equipment shall include an auxiliary tank
from which the measuring tank shall be equipped with an outside tap and valve to
provide checking the setting, unless other means are provided for readily and
accurately determining the amount of water in the tank. The volume of the auxiliary
tank shall be at least equal to that of the measuring tank.
G. Mixing Concrete
The concrete may be mixed at the site of the work in a central-mix plant, or in truck
mixers. The mixer shall be of an approved type and capacity. Mixing time will be
measured from the time all materials, except water, are in the drum. Ready-mixed
concrete shall be mixed and delivered in accordance with requirements of AASHTO
M 157, except that the minimum required revolutions at the mixing speed for transmit-
mixed concrete may be reduced to not less than that recommended by the mixer
manufacturer. The number of revolutions recommended by the mixer manufacturer
shall be indicated on the manufacturer’s serial plate attached to the mixer. The
contractor shall furnish test data acceptable to the Engineer verifying that the make
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 38
and model of the mixer will produce uniform concrete conforming to the provisions of
AASHTO M 157 at the reduced number of revolutions shown on the serial plate.
When mixed at the site or in a central mixing plant, the mixing time shall not be less
than fifty (50) seconds nor more than ninety (90) seconds for drum type of central
mixers, unless mixer performance tests prove adequate mixing of the concrete in
shorter time period.
The operation and mixing time for pan, twin shaft and other type of central mixers
shall be based on the mixer manufacturer’s instructions.
Four (4) seconds shall be added to the specified mixing time if timing starts at the
instant the skip reaches its minimum raised positions. Mixing time ends when the
discharge chute opens. Transfer time in multiply drum mixers is included in mixing
time. The contents of an individual mixer drum shall be removed before a succeeding
batch is emptied therein.
The mixer shall be operated at the drum speed as shown on the manufacturer’s name
plate attached on the mixer. Any concrete mixed less than the specified time shall be
discarded and disposed off by the Contractor at his expense. The volume of concrete
mixed per batch shall not exceed the mixer’s nominal capacity may be permitted
provided concrete test data for strength, segregation, and uniform consistency are
satisfactory, and provided no spillage of concrete takes place.
The batches shall be so charged into the drum that a portion of the mixing water shall
be entered in advance of the cement and aggregates. The flow of water shall be
uniform and all water shall be in the drum by the end of the first fifteen (15) seconds
of the mixing period. The throat of the drum shall be kept free of such accumulations
as may restrict the free flow of materials into the drum.
Mixed concrete from the central mixing plant shall be transported in truck mixers,
truck agitators or non-agitating truck specified in Subsection 311.3.2, Equipment. The
time elapsed from the time water is added to the mix until the concrete is deposited
in place at the Site shall not mix until the concrete is deposited in place at the Site
shall not exceed forty five (45) minutes when the concrete is hauled on non-agitating
trucks, nor ninety (90) minutes when hauled in truck mixers or truck agitators, except
that in hot weather or under other conditions contributing to quick hardening of the
concrete, the maximum allowable time may be reduced by the Engineer.
In exceptional cases and when volumetric measurements are authorized for small
project requiring less than 75 cu.m. of concrete per day of pouring, the weight
proportions shall be converted to equivalent volumetric proportions. In such cases,
suitable allowance shall be made for variations in the moisture of the aggregates,
including the bulking effect in the fine aggregate. Batching and mixing shall be in
accordance with ASTM C 685, Section 6 through 9.
Concrete mixing by chute is allowed provided that a weighing scale for determining
the batch weight will be used.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 39
Re-tempering concrete by adding water or by other means shall not be permitted,
except that the concrete is delivered in truck mixers, additional water may be added
to the batch materials and additional mixing performed to increase the slump to meet
the specified requirements, if permitted by the Engineer, provided all these operations
are performed within forty-five (45) minutes after the initial mixing operation and the
water-cement ratio is not exceeded. Concrete that is not within the specified slump
limits at the time of placement shall not be used. Admixtures for increasing the
workability or got accelerating the setting of the concrete will be permitted only when
specifically approved by the Engineer.
H. Limitation of Mixing
No concrete shall be mixed, placed or finished when natural light is insufficient, unless
an adequate and approved artificial lighting system is operated.
During hot weather, the Engineer shall require that steps be taken to prevent the
temperature of mixed concrete from exceeding a maximum temperature of 32°C.
Concrete not in place within ninety (90) minutes from the time the ingredients were
charged into the mixing drum or that has developed initial set shall not be used.
Retempering of concrete or mortar which has partially hardened, that is remixing with
or without additional cement, aggregate, or water, shall not be permitted.
In order that the concrete may be properly protected against the effects of rain before
the concrete is sufficiently hardened, the Contractor will be required to have available
at all times materials for the protection of the edges and surface of the unhardened
concrete.
I. Placing Concrete
Concrete shall be thoroughly consolidated against and along the faces of all forms
and along the full length and on both sides of all joint assemblies by means of
vibrators inserted in the concrete. Vibrators shall not be permitted to come in contact
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 40
with a joint assembly, the grade, or a side form. In no case shall the vibrator be
operated longer than fifteen (15) seconds in any location. Concrete shall be deposited
as near as possible to the expansion and contraction joints without disturbing them,
but shall not be dumped from the discharge bucket or hopper into a joint assembly
unless the hopper is well centered on the joint assembly. Should any concrete
material fall on or be worked into the surface of a complete slab, it shall be removed
completely.
J. Test Specimens
As work progresses, at least one (1) set consisting of three (3) concrete beam test
specimens, 150 mm x 150 mm x 525 mm shall be taken from each 330 m² of
pavement, 230 mm depth, or fraction thereof placed each day. Test specimens shall
be made under the supervision of the Engineer, and the Contractor shall provide all
concrete and other facilities necessary in making the test specimens and shall protect
them from damage by construction operations. Cylinder samples shall not be used
as substitute for determining the adequacy of the strength of concrete.
The beams shall me made, cured, and tested in accordance with AASHTO T. 23 and
T 97.
Following the placing of the concrete, it shall be struck off to conform to the cross-
section shown on the Plans and to an elevation such that when concrete is properly
consolidated and finished, the surface of the pavement will be at the elevation shown
on the Plans. When reinforced concrete pavement is placed in two (2) layers, the
bottom layer shall be struck off and consolidated to such length and depth that the
sheet of fabric or bar mat may be laid full length on the concrete in its final position
without further manipulation. The reinforcement shall then be placed directly upon the
concrete, after which the top layer of the concrete shall be placed, struck off and
screeded. Any portion of the bottom layer of concrete which has been placed more
than 30 minutes without being covered with the top layer shall be removed and
replaced with freshly mixed concrete at the Contractor’s expense. When reinforced
concrete is placed in one layer, the reinforcement may be firmly positioned in advance
of concrete placement or it may be placed at the depth shown on the Plans in plastic
concrete, after spreading by mechanical or vibratory means.
Reinforcing steel shall be free from dirt, oil, paint, grease, mill scale and loose or thick
rust which could impair bond of the steel with the concrete.
L. Joints
Joints shall be constructed of the type and dimensions, and at the location required
by the plans or special provisions. All joints shall be protected from the intrusion of
injurious foreign material until sealed.
a. Longitudinal Joint
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 41
Deformed steel tie bars of specified length, size, spacing and materials shall
be placed perpendicular to the longitudinal joints; they shall be placed by
approved mechanical equipment rigidly secured by chair or other approved
supports to prevent displacement. Tie bars shall not be painted or coated
with asphalt or other material, or enclosed in tubes or sleeves. When shown
on the plans and when adjacent lanes of pavement are constructed
separately, steel side forms shall be used which will form a keyway along the
construction joint. Tie bars, except those made of rail steel, may be bent at
right angles against the form of the first lane constructed and straightened
into final position before the concrete of the adjacent lane is placed, or in lieu
of bent tie bars, approved two-piece connectors may be used.
The expansion joint filler shall be continuous from form to form shaped to the
subgrade and to the keyway along the form. Preformed joint filler shall be
furnished in lengths equal to the pavement width or equal to the width of one
lane. Damaged or repaired joint filler shall not be used.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 42
c. Transverse Contraction Joint
Dowels, when used, shall be held in position parallel to the surface and center
line of the slab by a metal device that is left in the pavement.
The portion of each dowel painted with one coat of lead or tar, in conformance
with the requirements of Section 03200, Concrete Reinforcement, shall be
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 43
thoroughly coated with approved bituminous material e.g., MC-70, or an
approved lubricant, to prevent the concrete from binding to that portion of the
dowel. The sleeves of dowels shall be metal designed to cover 50mm plus
or minus 5mm (1/4 inch), of the dowel, with a watertight closed end and with
a suitable stop to hold the end of the sleeves at least 25mm (1 inch) from the
end of the dowel. In lieu of using dowel assemblies at contraction joints, dowel
may be placed in the full thickness of pavement by a mechanical device
approved by the Engineer.
Strike off and screed the concrete to the required crown and cross-
section by the use of wood or metal screed. Transverse rotating tube
or pipe shall not be permitted unless approved by the Engineer. The
elevation of the concrete shall be such that, when consolidated and
finished, the surface of the pavement will be adequately consolidated
and at the required grade. Equip the finishing tools with two screeds
readily and accurately adjustable for changes in pavement crown and
compensation for wear and other causes. It shall make as many trips
over each area of pavement and as such intervals as necessary to
give the proper compaction, retain the coarse aggregate near the
finished surface, and produce a surface of uniform texture, true to
grade and crown. Excessive operation over an area, which results in
an excess of mortar and water being brought to the surface, will not
be permitted.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 44
Strike-off and screed the surface of the concrete to elevations slightly
above finish grade so that when the concrete is consolidated and
finished, the surface of the pavement is at the indicated elevation.
Vibrate the entire surface until the required compaction and reduction
of surface is secured with a strike-off template.
After the longitudinal floating has been completed and the excess
water removed, but while the concrete is still plastic, test the slab with
an accurate 3 meter straightedge. Hold the straightedge in
successive positions to centerline of the slab in contact with the
surface of the concrete, and go over the whole slab area from one
side of the slab to the other as necessary. Advance along the
centerline of the slab in successive stages of not more than one-half
the length of the straightedge. Fill all depressions immediately with
freshly mixed concrete, strike-off, consolidate, and refinish.
Straightedge testing and surface correction shall continue until the
entire surface is within the tolerance specified.
f.8 Texturing
Before the surface sheen has disappeared and before the concrete
becomes non-plastic, the surface of the pavement shall be given a
texture as specified below, Surface Finish.
f.10 Edging
g. Surface Test
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 46
As soon as the concrete has hardened sufficiently, the pavement surface
shall be tested with a 3-m straight-edge or other specified device. Areas
showing high spots of more than 3 mm but not exceeding 12 mm in 3 m shall
be marked and immediately ground down with an approved grinding toll to an
elevation where the area or spot will not show surface deviations in excess of
3 mm when tested with 3 m straight0edge. Where the departure from correct
cross-section exceeds 12 mm, the pavement shall be removed and replaced
by and at the expense of the Contractor.
Any area or section so removed shall be not less than 1.5 m in length and not
less than the full width of the lane involved. When it is necessary to remove
and replace a section of pavement, any remaining portion of the slab adjacent
to the joints is less than 1.5 m in length, shall also be removed and replaced.
h. Curing
Immediately after the finishing operations have been completed and the
concrete has sufficiently set, the entire surface of the newly placed concrete
shall be cured in accordance with either one of the methods described herein.
Failure to provide sufficient cover material of whatever kind the Contractor
may elect to use, or the lack of water to adequately take care of both curing
and other requirements, shall be a cause for immediate suspension of
concreting operations. The concrete shall not be left exposed for more than
½ hour between stages of curing or during the curing period.
The surface of the pavement shall be entirely covered with mats. The
mats used shall be of such length (or width) that as laid they will
extend at least twice the thickness of the pavement beyond the edges
of the slab. The mat shall be placed so that the entire surface and the
edges of the slab are completely sovered. Prior to being placed, the
mats shall be saturated thoroughly with water. The mat shall be so
placed and weighted down so as to cause them to remain in intimate
contact with the covered surface. The mat shall be maintained fully
wetted and in position for 72 hours after the concrete has been placed
unless otherwise specified.
The top surface and sides of the pavement shall be entirely covered
with waterproof paper, the units shall be lapped at least 45 cm. The
paper shall be so placed and weighted down so as to cause it to
remain in intimate contact with the surface covered. The paper shall
have such dimension but each unit as laid will extend beyond the
edges of the slab at least twice the thickness of the pavement, or at
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 47
pavement width and 60 cm strips of paper for the edges. If laid
longitudinally, paper not manufactured in sizes which will provide this
width shall be securely sewed or cemented together, the joints being
securely sealed in such manner that they do not open up or separate
during the curing period. Unless otherwise specified, the covering
shall be maintained in place for 72 hours after the concrete has been
placed. The surface of the pavement shall be thoroughly wetted prior
to the placing of the paper.
When this type of curing is used, the pavement shall be cured initially
with burlap or cotton mats, until after final set of the concrete or, in any
case, for 12 hours after placing the concrete. As soon as the mats are
removed, the surface and sides of the pavement shall be thoroughly
wetted and covered with at least 20 cm of straw or hay, thickness of
which is to be measured after wetting. If the straw or hay covering
becomes displaced during the curing period, it shall be replaced to
the original depth and saturated. It shall be kept thoroughly saturated
with water for 72 hours and thoroughly wetted down during the
morning of the fourth day, and the cover shall remain in place until the
concrete has attained the required strength.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 48
h.5 White Polyethylene Sheet
The top surface and sides of the pavement shall be entirely covered
with polyethylene sheeting. The units used shall be lapped at least 45
cm. The sheeting shall be so placed and weighted down so as to
cause it to remain intimate contact with the surfaced covered. The
sheeting as prepared for use shall have such dimension that each unit
as laid will extend beyond the edges of the slab at least twice the
thickness of the pavement. Unless otherwise specified, the covering
shall be maintained in place for 72 hours after the concrete has been
placed.
i. Removal of Forms
Forms for concrete shall remain in place undisturbed for not less than twenty-
four (24) hours after pouring. In the removal of forms, crowbars should be
used in pulling out nails and pins. Care should be taken so as not to break
the edges of the pavement. In case portions of the concrete are spalled, they
shall be immediately repaired with fresh mortar mixed in the proportion of one
part of Portland Cement and two parts fine aggregates. Major honeycomb
areas will be considered as defective work, and shall be removed and
replaced at the expense of the Contractor. Any area or section so removed
shall not be less than the distance between weakened plane joint nor less
than the full width of the lane involved.
j. Sealing Joints
Joints shall be sealed soon after completion of the curing period and before
the pavement is opened to traffic, including the Contractor's equipment. Just
prior to sealing, each joint shall be thoroughly cleaned of all foreign materials
including membrane curing compound and the joint faces shall be cleaned
and surface dry when the seal is applied.
The sealing material shall be applied to each joint opening to conform to the
details shown on the plans or as directed by the Engineer. Materials for seal
applied hot shall be stirred during heating so that localized overheating does
not occur. The pouring shall be done in such a manner that the material will
not be spilled on the exposed surfaces of the concrete. The use of sand or
similar material as a cover for the seal will not be permitted.
The seals shall be in one piece for the full width of each transverse joint.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 49
k. Pavement Protection
Keep pavement closed to vehicular traffic until the concrete is more than 7
days old and has attained a minimum flexural strength of 3.10 MPa as
determined by tests of the field-cured test beams. At that time the pavement
may be opened to limited traffic. Prevent damage to edges of slabs if
subgrade planer, concrete finishing machine, or similar equipment is
supported on previously constructed slabs. After the concrete has reached
the specified 28 days flexural strength as verified by the laboratory-cured test
beams, equipment with the wheel loads capacity exceeding 2,280 kg may be
used for transporting concrete or heavy equipment with the prior approval of
the Engineer.
l. Acceptance of Concrete
During the progress of the work, verify the flexural strength by testing
beams made from concrete taken from the forms at intervals indicated
herein. Mold and cure beams in accordance with ASTM C31.
Perform tests in accordance with ASTM C78. Mold at least 8 beams
each day from concrete placed that day. Select one group of four
beams at the beginning of the work and a second group of four beams
near the end of concrete placement. An approved laboratory shall
furnish all necessary labor, concrete and facilities for molding,
handling, and storing the beams at the site of the work and testing the
beams. Perform tests at 7 days and 28 days.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 50
l.2 Core Test
5 to less than 10 80
10 to less than 15 70
15 to less than 20 60
20 to less than 25 50
25 or more 0
Each lot will be divided into five (5) equal segments and one core will
be obtained from each segment in accordance with AASHTO T24.
Deficiency in the Average Thickness Per Percent of Contract Price Per Lot
Lot (mm)
6 – 10 95% payment
11 – 15 85% payment
16 – 20 70% payment
21 – 25 50% payment
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 52
More than 25 Remove and Replace Concrete
(No Payment)
m. Opening to Traffic
The Engineer will decide when the pavement may be opened to traffic. The
road will not be opened until test specimens molded and cured have attained
the minimum strength requirements. If such tests are not conducted prior to
the specified age, the pavement shall not be opened to traffic until 14 days
after the concrete was placed. Before opening to traffic, the pavement shall
be cleaned and joint sealing completed.
1. Description
This Item shall consist of furnishing, bending, fabricating and placing of steel
reinforcement of the type, size, shape and grade required in accordance with
this Specification and in conformity with the requirements shown on the Plans
or as directed by the Engineer.
2. Material Requirement
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 53
Cold-Drawn Steel Wire for AASHTO M 32 (ASTM A 82)
Concrete Reinforcement
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 54
High-tensile wire AASHTO M 204 (ASTM A 421)
High-tensile-strengthalloybarsshallbecoldstretchedtoaminimumof895.7
MPa (30,000 psi). The resultant physical properties shall be asfollows:
3. Construction Requirement
A. Order Lists
B. Protection of Material
C. Bending
10 to20 6d
8d
25 to28
10d
32 and greater
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 56
provision may be rejected and removal may be required. If fabric
reinforcement is shipped in rolls, it shall be straightened before
being placed. Bundled bars shall be tied together at not more than
1.8m intervals.
E. Splicing
4. Method of Measurement
The quantity of reinforcing steel to be paid for will be the final quantity
placed and accepted in the completed structure.
When there is no item for reinforcing steel in the Bill of Quantities, costs
will be considered as incidental to the other items in the Bill of Quantities.
1. Description
A. Scope
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 58
Class A – All superstructures and heavily reinforced substructures. The
important parts of the structure included are slabs, beams, girders,
columns, arch ribs, box culverts, reinforced abutments, retaining walls,
and reinforced footings.
2. Material Requirements
A. Portland Cement
Cement which for any reason, has become partially set or which
contains lumps of caked cement will be rejected. Cement salvaged from
discarded orused bags shall not be used.
B. Fine Aggregate
It shall not contain more than three (3) mass percent of material passing
the 0.075 mm (No. 200 sieve) by washing nor more than one (1) mass
percent each of clay lumps or shale. The use of beach sand will not be
allowed without the approval of the Engineer.
If the fine aggregate is subjected to five (5) cycles of the sodium sulfate
soundness test, the weighted loss shall not exceed 10 mass percent.
The fine aggregate shall be well-graded from coarse to fine and shall
conform to Table 311.1
2.36 mm (No. 8) -
C. Coarse Aggregate
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 60
Standard Alternate Grading Grading Grading
Mm A B C
U.S.
Standard
* The measured cement content shall be within plus (+) or minus (-) 2
mass percent of the design cement content.
D. Water
311.2.4 Water
E. Reinforcing Steel
F. Admixtures
311.2.8 Admixtures
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 61
Air-entraining admixture shall conform to the requirements of AASHTO
M 154.
G. Curing Materials
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 62
These shall conform to AASHTO M 251 or Item 412 - Elastomeric Bearing
Pads.
As work progresses, at least one (1) sample consisting of three (3) concrete
cylinder test specimens, 150 x 300mm (6 x 12 inches), shall be taken from
each seventy-five (75) cubic meters of each class of concrete or fraction
thereof placed each day.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 63
Weight per cubic meter and air
T 121
content (gravi-metric) of concrete
T 27
Sieve Analysis of fine and coarse
aggregates
4. Production Requirements
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 64
Minimum Maximum Consistency Designated Minimum
Cement Water/ Range in Size of Coarse CompressiveStre
Class of Content Cement Slump Aggregate ngth of
Concrete Per m3 Ratio 150x300mm
Concrete
kg Cylinder
(bag**) Square Opening Specimen at 28
kg/kg Std. mm days, MN/m2
mm (inch) (psi)
** Based on 40 kg/bag
B. Consistency
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 65
Concrete as dry as it is practical to place with the equipment
specified shall be used.
C. Batching
a. Portland Cement
b. Water
c. Aggregates
e. Batching
f. Admixtures
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 67
In exceptional cases and when volumetric measurements are
authorized, for small project requiring less than 75 cu.m. per day
of pouring, the weight proportions shall be converted to
equivalent volumetric proportions. In such cases, suitable
allowance shall be made for variations in the moisture condition
of the aggregates, including the bulking effect in the fine
aggregate. Batching and mixing shall be in accordance with
ASTM C 685, Section 6 through 9.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 68
Retempering concrete will not be permitted. Admixtures for
increasing the workability, for retarding the set, or for
accelerating the set or improving the pumping characteristics of
the concrete will be permitted only when specifically provided for
in the Contract, or authorized in writing by the Engineer.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 69
mass percent for any size of aggregate, or one (1) mass
percent for the total aggregate in any batch.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 70
All concrete shall be mixed for a period of not less than 1-
1/2 minutes after all materials, including water, are in the
mixer. During the period of mixing, the mixer shall operate
at the speed for which it has been designed.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 71
cement is charged into a mixer drum containing water or
surface wet aggregate and when the temperature is above
32oC, this limit shall be reduced to 15 minutes. The
limitation in time between the introduction of the cement
to the aggregate and the beginning of the mixing may be
waived when, in the judgement of the Engineer, the
aggregate is sufficiently free from moisture, so that there
will be no harmful effects on the cement.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 72
The Contractor shall have sufficient plant capacity and
transportation apparatus to ensure continuous delivery at
the rate required. The rate of delivery of concrete during
concreting operations shall be such as to provide for the
proper handling, placing and finishing of the concrete.
The rate shall be such that the interval between batches
shall not exceed 20 minutes. The methods of delivering
and handling the concrete shall be such as will facilitate
placing of the minimum handling.
E. Method of Measurement
500(1) Pipe Culverts (375mm., 450mm., 600mm., 750mm., 900mm., 1050mm., 1200mm., and
1500mm. diameters)
1. Description
This item shall consist of the construction or reconstruction of pipe culverts and
storm drains, hereinafter referred to as “conduit” in accordance with this
Specification and in conformity with the lines and grades shown on the Plans or as
established by the Engineer.
2. Material Requirements
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 73
Reinforced concrete elliptical culvert, storm drain AASHTO M 2017
and sewer pipe
Asbestos cement pipe for culverts and storm drains AASHTO M 217
Joint Mortar – Joint mortar for concrete pipes shall consist of 1 part, by volume of Portland
Cement and two (2) parts of approved sand with water as necessary to obtain the required
consistency.
Portland Cement and sand shall conform to the requirements of Item 405, Structural
Concrete. Mortar shall be used within 30 minutes after its preparation.
Oakum – Oakum for joints in bell and spigot pipes shall be made from hemp (Cannavis
Sativa) line or Benares Sunn fiber or from a combination of these fibers. The oakum shall
be thoroughly corded and finished and practically free from lumps, dirt and extraneous
matter.
When the location of manufacturing plants allow, the plants will be inspected periodically
for compliance with specified manufacturing methods, and material samples will be
obtained for laboratory testing for compliance with materials quality requirements. This
shall be the basis for acceptance of manufacturing lots as to quality.
Prior to and during incorporation of materials in the work, these materials will be subjected
to the latest inspection and approval of the Engineer.
3. Construction Requirements
A. Trenches Excavation
The completed trench bottom shall be firm for its full length and width. Where
required, in the case of crop drains, the trench shall have a longitudinal camber of
the magnitude specified.
When so specified on the Plans, the excavation for conduits placed in embankment
fill, shall be made after the embankment has been completed to the specified or
directed height above the designed grade of the conduit.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 74
B. Bedding
The bedding shall conform to one of the classes specified. When no bedding class
is specified, the requirements for Class C bedding shall apply.
Class B bedding shall consist of bedding the conduit to a depth of not less than 30
percent of the vertical outside diameter of the conduit. The minimum thickness of
bedding material beneath the pipe shall be 100 mm. The bedding material shall be
sand or selected sandy soil all of which passes a 9.5 mm sieve and not more than
10 percent of which passes a 0.075 mm sieve. The layer of the bedding material
shall be shaped to fit the conduit for at least 15 percent of its total height. Recesses
in the trench bottom shall be shaped to accommodate the bell when bell and spigot
type conduit isused.
Class C bedding shall consist of bedding the conduit to a depth of not less than 10
percent of its total height. The foundation surface, completed in accordance with
Item 103, Structure Excavation, shall be shaped to fit the conduit and shall have
recesses shaped to receive the bells, if any.
For flexible pipe, the bed shall be roughly shaped and a bedding blanket of sand
or fine granular material as specified above shall be provided as follows:
10 mm 25 mm
25 mm 50 mm
50 mm 75 mm
For large diameter structural plate pipes the shaped bed need not exceed
the width of bottom plate.
C. Laying Conduit
The conduit laying shall begin at the downstream end of the conduit line.
The lower segment of the conduit shall be in contact with the shaped
bedding throughout its full length. Bell or groove ends of rigid conduits and
outside circumferential laps of flexible conduits shall be placed facing
upstream. Flexible conduit shall be placed with longitudinal laps or seams at
the sides.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 75
Paved or partially-lined conduit shall be laid such that the longitudinal center
line of the paved segment coincides with the flow line. Elliptical and
elliptically reinforced conduits shall be placed with the major axis within 5
degrees of a vertical plane through the longitudinal axis of the conduit.
D. Jointing Conduit
Rigid conduits may either be of bell and spigot or tongue and groove design
unless another type is specified. The method of joining conduit sections shall
be such that the ends are fully entered and the inner surfaces are reasonably
flush and even.
Joints shall be made with (a) Portland Cement mortar, (b) Portland Cement
grout, (c) rubber gaskets, (d) oakum and mortar, (e) oakum and joint
compound, (f) plastic sealing compound, or by a combination of these types,
or any other type, as may be specified. Mortar joints shall be made with an
excess of mortar to form a continuous bead around the outside of the conduit
and finished smooth on the inside. For grouted joints, molds or runners shall
be used to retain the poured grout. Rubber ring gaskets shall be installed so
as to form a flexible water-tight seal. Where oakum is used, the joint shall be
called with this material and then sealed with the specified material.
When Portland Cement mixtures are used, the completed joints shall be
protected against rapid drying by any suitable covering material.
Conduits shall be inspected before any backfill is placed. Any pipe found to
be out of alignment, unduly settled, or damaged shall be taken up and repaid
or replaced.
E. Field Strutting
When required by the Plans, vertical diameter of round flexible conduit shall
be increased 5 percent by shop elongation or by means of jacks applied after
the entire line of conduit has been installed on the bending but before
backfilling. The vertical elongation shall be maintained by means of sills and
struts or by horizontal ties shall be used on paved invertpipe.
Ties and struts shall be 300 mm in place until the embankment is completed
and compacted, unless otherwise shown on the Plans.
F. Backfilling
Materials for backfilling on each side of the conduit for the full trench width
and to an elevation of 300 mm above the top of the conduit shall be fine,
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 76
readily compactible soil or granular material selected from excavation or
from a source of the Contractor’s choice, and shall not contain stones that
would be retained on a 50 mm sieve, chunks of highly plastic clay, or other
objectionable material. Granular backfill material shall have not less than 95
percent passing a 12.5 mm sieve and not less than 95 percent retained on
a 4.75 mm sieve. Oversized material, if present, shall be removed at the
source of the material, except as directed by the Engineer.
When the top of the conduit is flushed with or below the top of the trench,
backfill material shall be placed at or near optimum moisture content and
compacted in layers not exceeding 150 mm (compacted) on both sides to
an elevation 300 mm above the top of the conduit. Care shall be exercised
to thoroughly compact the backfill under the haunches of the conduit. The
backfill shall be brought up evenly on both sides of the conduit for the full
required length. Except where negative projecting embankment-type
installation is specified, the backfill material shall be placed and compacted
for the full depth of the trench.
When the top of the conduit is above the top of the trench, backfill shall be
placed at or near optimum moisture content and compacted in layers not
exceeding 300 mm (compacted) and shall be brought up evenly on both
sides of the conduit for its full length to an elevation 300 mm above the top
of the conduit. The width of the backfill on each side of the conduit for the
portion above the top of the trench shall be equal to twice the diameter of
the conduit or 3.5 m, whichever is less. The backfill material used in the
trench section and the portion above the top of the trench for a distance on
each side of the conduit equal to the horizontal inside diameter and to 300
mm above the top of the conduit shall conform to the requirements for
backfill materials in this Subsection. The remainder of the backfill shall
consist of materials from excavation and borrow that is suitable for
embankment construction.
All conduits after being bedded and backfill as specified in this Subsection
shall be protected by one meter cover of fill before heavy equipment is
permitted to cross during construction of the roadway.
G. Imperfect trench
Under this method, for rigid conduit, the embankment shall be completed as
described in Subsection 500.3.6, Backfilling, to a height above the conduit
equal to the vertical outside diameter of the conduit plus 300 mm. A trench
equal in width to the outside horizontal diameter of the conduit and to the
length shown on the plans or as directed by the Engineer shall then be
excavated to within 300 mm of the top of the conduit, trench walls being as
nearly vertical as possible. The trench shall be loosely filled with highly
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 77
compressible soil. Construction of embankment above shall then proceed in
a normal manner.
4. Method of Measurement
Conduit of the different types and sizes, both new and re-laid, will be measured by
the linear meter in place. Conduit with sloped or skewed ends will be measured
along the invert.
Branch connection and elbows will be included in the length measurement for
conduit, or they may be measured by the number of units installed.
Class B bedding material placed and approved shall be measured by the cubic
meter in place.
When the Bid Schedule contains an estimated quantity for “Furnishing and Placing
Backfill Material, Pipe Culvert”, the quantity to be paid for will be the number of cubic
meter complete in place and accepted, measured in final position between limits as
follows:
B. When the original ground line is less than 300 mm above the top of the
pipe, the measurement will also include the placing of all backfill materials,
above the original ground line adjacent to the pipe for a height of 300 mm
above the top of pipe and for a distance on each side of the pipe not greater
than the widest horizontal dimension of thepipe.
5. Basis of Payment
Excavation for culverts and storm drains, including excavation below flow line grade
and for imperfect trench, shall be measured and paid for as provided in Item 103,
StructureExcavation.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 78
Concrete for Class A bedding will be paid for under Item 405, Structural Concrete.
When the Bid Schedule does not contain as estimated quantity for “Furnishing and
Placing Backfill Material, Pipe Culvert” payment for placing backfill material around
pipe culverts will be considered as included in the payment for excavation of the
backfill material.
Storm Drain, - mm
500 (2) Class - Linear Meter
502(1) Manholes (375mm., 450mm., 600mm., 750mm., 900mm., 1050mm., 1200mm., and
1500mm. diameters)
502(2)a Inlets
502(4) Concrete Covers (375mm., 450mm., 600mm., 750mm., 900mm., 1050mm., 1200mm., and
1500mm. diameters)
1. Description
This item shall consist of the construction, reconstruction or adjustment of manholes, inlets and
catch basins in accordance with this Specification and in reasonably close conformity with the
lines and grades shown on the Plans or as established by the Engineer.
2. Material Requirements
Concrete for these structures shall meet the requirements of Item 405, Structural Concrete. Other
materials shall meet the following specifications:
Corrugated Metal Units – The units shall conform to Plan dimensions and the metal to AASHTO
M 36. Bituminous coating, when specified, shall conform to ASTM D 1187, Asphalt-base Emulsion
for use as Protective Coating for Metal.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 79
Building brick (Solid masonry units AASHTO M 114
made from clay or shale)
Joint Mortar - Unless otherwise indicated on the Plans, joints mortar shall be composed of one
part Portland Cement and two parts fine aggregate by volume to which hydrated lime has been
added in an amount equal to 10 percent of the cement by weight. All materials for mortar shall
meet the requirements of Item 405, Structural Concrete.
Frames, Gratings, Covers and Ladder Rungs – Metal units shall conform to the plan dimensions
and to the following specification requirements for the designated materials.
Metal gratings and covers which are to rest on frames shall bear on them evenly. They shall be
assembled before shipment and so marked that the same pieces may be reassembled readily in
the same position when installed. Inaccuracy of bearings shall be corrected by machining, if
necessary. A frame and a grating or cover to be used with it shall constitute one pair.
All castings shall be uniformly coated with asphalt-based emulsion meeting the requirements of
ASTM D 1187, Asphalt-base Emulsion for use as Protective Coating forMetal.
Samples of the material in casting shall be taken during the casting of the units and shall be
separate casting poured from the same material as the casting they represent.
Pre-cast Concrete Units – These units shall be cast in substantial permanent steel forms.
Structural concrete used shall attain a minimum 28-day compressive strength of 20.682 MPa
(3000 psi). The pre-cast units shall be cured in accordance with AASHTO M 171. Water
absorption of individual cores taken from such units shall not exceed 7 percent. Additional
reinforcement shall be provided as necessary to provide for handling of the pre-castunits.
A sufficient number of cylinders shall be cast from the concrete for each unit permit compression
tests at 7, 14 and 28 days, and to allow for at least 3 cylinders for each test. If the strength
requirement is met at 7 or 14 days, the units shall be certified for use 14 days from the date of
casting. If the strength is not met at 28 days, all units made from that batch or load will berejected.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 80
Cracks in units, honeycombed or patched areas in excess of 2,000 square millimeters, excessive
water absorption and failure to meet strength requirements shall be the causes for rejection. Pre-
cast reinforced concrete manhole risers and tops shall conform to the requirements of AASHTO
M 199.
The plants will be inspected periodically for compliance with specified manufacturing methods,
and material samples will be obtained for laboratory testing for compliance with material quality
requirements. This may be the basis for acceptance of manufacturing lots as the quality.
All materials shall be subjected to inspection for acceptance as to condition at the latest
practicable time the Engineer has the opportunity to check for compliance prior to or during
incorporation of materials into thework.
3. Construction Requirement
Concrete construction shall conform to the requirements for Item 405, Structural Concrete.
Metal frames shall be set in full mortar bed. Pipe sections shall be flushed on the inside of the
structure wall and projected outside sufficiently for proper connection with next pipe section.
Masonry shall fit neatly and tightly around the pipe.
When grade adjustment or existing structures is specified, the frames, covers and gratings shall
be removed and the walls reconstructed as required. The cleaned frames shall be reset at the
required elevation. Upon completion, each structure shall be cleaned of any accumulation of silt,
debris, or foreign matter of any kind and shall be kept clear of such accumulation until final
acceptance of the work.
Excavation and backfill shall be done in accordance with Item 103, Structure Excavation.
4. Method of Measurement
Standard manholes, inlets and catch basins, both new and reconstructed as applicable, will be
measured by the unit. Any additional concrete, reinforcing steel, or masonry required for
authorized increases in heights of structures paid off under this Item and in excess of the standard
height shown on the Plans will be measured and paid for under Item 405, Structural Concrete and
Item 404, Reinforcing Steel, as applicable. Structures noted on the Plans as “junction boxes” will
be measured for payment asmanholes.
The number of concrete covers, pairs of metal frames and gratings, and pairs of metal frames
and covers will be measured as acceptably completed.
The number of existing manholes, inlets and catch basins adjusted as directed will be measured
as acceptably completed.
5. Basis of Payment
1. Description
This Item shall consist of the furnishing and placing of concrete slope protection including
all necessary excavation, a bed course and reinforced concrete to the required thickness
and extent to protect slopes against erosion. Construction details shall be as shown on
the Plans.
2. Material Requirements
A. Bed Course
A bed course, where required, shall be granular material which satisfies the
requirements for Item 200, Aggregate Sub-base, Grading A.
B. Formwork
C. Steel Reinforcement
D. Concrete
3. Construction Requirements
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 82
A. Excavation
B. Bed Course
Where shown on the Plans or ordered by the Engineer, the Contractor shall
provide and lay a bed course, to the depth required, and as specified in Item 200,
Aggregate Subbase Course, compacted at least 100 percent of the maximum dry
density as determined by AASHTO T 180, MethodD.
C. Concrete
The Contractor shall provide and place concrete in accordance with the
requirements of Item 405, Structural Concrete, to the required depths in the
positions and to the grades and elevations shown on the Plans. Unless otherwise
specified, the concrete slabs shall not be greater than 4m by 4m and shall have
between slabs, plain vertical straight joints with no joint filler or sealer.
The toe of the concrete slope protection shall be constructed and protected a
shown on thePlans.
D. Drainage
Drainage of the bed course or backfill shall be provided as shown on the Plans or
as required by the Engineer.
4. Method of Measurement
The quantity of granular material in the bed course to be paid for shall be measured by
the cubic meter in-place and accepted as shown on the Plans.
The quantity of concrete to be paid for shall be measured by the cubic meter in-place and
accepted as shown on the Plans.
5. Basis of Payment
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 83
510 (1) Bed Course Granular Material Cubic meter in-place
511(1) Gabions
1. Description
This Item shall consist of furnishing, forming wire mesh baskets, and placing rocks
installed at the locations designated, in accordance with this Specification and in
conformity with the lines, grades, dimensions, and arrangements shown on the Plans or
as directed by the Engineer.
2. Material Requirements
A. General
Gabions shall be constructed of wire mesh and shall be supplied in various lengths
and heights. A double twisted wire mesh container of variable sizes, uniformly
partitioned into internal cells, interconnected with other similar units, and filled with
stones at the project site to form flexible, permeable, monolithic structures such as
retaining walls, sea walls, channel linings, revetments and weirs for erosion
control. The lengths shall be multiples of 2, 3 or 4 times the width of the gabion
and heights shall be 0.50 m to 1.00 m or as shown on the plans. The horizontal
width shall not be less than one meter. Gabion furnished shall be of uniform width.
The width, height and length of the gabion as manufactured shall not differ more
Mattresses are double twisted wire mesh container uniformly partitioned into
internal cells with relatively small height in relation to other dimensions, having
smaller mesh openings than the mesh used for gabions. Mattresses are generally
used for riverbank protection and channel linings. The length shall be 3.00 m to
6.00 m, the width shall be 2.00 m and the height shall be 0.17 m, 0.23 m or 0.30
m or as shown on the Plans.
The width and length of the revet mattress as manufactured shall not differ more
than 5%, and
prior to filling.
B. Wire
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 84
The wire used in the manufactured of double-twisted mesh for use in gabions and
mattresses shall conform to the specifications as shown below as appropriate for
the styleordered.
Test Method
The PVC coating shall not show cracks or breaks after the wires are twisted in the
fabrication of the mesh.
Lacing wire and stiffeners shall be made of wire having the same coating material
as the double-twisted wire mesh conforming to Specification ASTM A 641, A 856/A
856 M or A 809 with a tensile strength in accordance with subsection 509.2.7.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 85
E. Gabion and mattresses shall be manufactured with all components
mechanically connected at the production facility with the exception of the
mattresses lid which is produced separately from the base. All gabions and
mattresses shall be supplied in the collapsed form, either folded and bundled or
rolled, forshipping.
F. Dimensions
The minimum size of the galvanized and PVC coated wire to be used in the
fabrication of the gabion and mattresses shall be as follows:
The nominal and the minimum thickness of PVC coating shall be0.50 mm and 0.38
mm, respectively.
G. Mechanical Properties
Tensile Strength – The tensile strength of Zinc-coated wire used in the fabrication
of gabion and mattresses when tested in accordance with Test Methods ASTM A
370, shall be as follows:
Strength, MPa
Gabions Mattresses
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 86
Tying a Connecting 350-515 350-515
Wire
The minimum weight of zinc per unit area of uncoated wire surface shall be in
accordance with ASTM A 975 or asfollows:
I. Rock Fill
Rock used in the gabions and mattresses shall consist of hard, durable rock pieces
that will not deteriorate when submerged in water or exposed to severe weather
conditions. Rock pieces shall be generally uniformly graded in sizes ranging from
100 mm to 200 mm. Filled gabions shall have a minimum density of 1,400 kg/m 3.
Voids shall be evenly distributed.
No rock size shall exceed 2/3 the mattress depth and at least 85% by weight of the
stone shall have a size greater than 80 mm. No stones shall be able to pass
through themesh.
The rock shall meet the requirements of AASHTO M 63 except that the sodium
sulphate soundness loss shall not exceed 9% after 5 cycles.
J. Filter Fabric
3. Construction Requirements
A. Fabrication
b. When the gabion length exceeds its width, it shall have securely tied
diaphragms connected at all edges to form individual cells of equal length
and width.
Gabions shall be fabricated in such a manner that the sides, ends, lids and
diaphragms can be assembled at the construction site into rectangular
baskets of the specified sizes. Gabions shall be of single unit construction,
base, lids, ends and sides shall be either woven into a single unit or one
edge of these members connected to the base section of the gabion in
such a manner that the strength and flexibility at the point of connection is
at least equal to that of the mesh.
All perimeter edge of the mesh forming the gabion shall be securely
selvedged so that the joints, by tying the selvedges, have at least the same
strength as the body of the mesh.
Selvedge wire used through all the edges (perimeter wire) shall not be less
than 3.80 mm diameter and shall meet the same specifications as the
wiremesh.
Each gabion unit shall be assembled by binding together all vertical edges
with wire ties on approximately 152 mm (6 inches) spacing or by a
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 88
continuous piece of connecting wire stitched around the vertical edges with
a coil every 102 mm (4 inches). Empty gabion units shall be set to line and
grade as shown on the Plans or as described by the Engineer. Wire ties or
connecting wires shall be used to join the units together in the same
manner as described above for assembling. Internal tie wires shall be
uniformly spaced and securely fastened in each cell of the structure.
A standard fence stretcher, chain fall, or iron rod may be used to stretch
the wire baskets and hold alignment.
b. When possible the subgrade of the mattress and gabion shall be properly
compacted to a depth of 150 mm. The Contractor shall consider the cost
of subgrade preparation in the unit prices. Filter fabric as beds of gabions
and mattresses forming the structure shall be suitably leveled and shall be
securely connected along the complete length of all contact edges by
means of the above specified tying and connecting wire.
c. Before the filling material is placed, the gabions and mattresses shall be
carefully selected for uniformity of size, and the pieces shall be hand placed
to provide a neat appearance as approved by the Engineer.
The gabions shall be filled with stone carefully placed by hand or machine
to assure alignment and avoid bulges with a minimum void. Alternate
placing of rock and connection wires shall be performed until the gabion is
filled. After a gabion has been filled, the lid shall be bent over until it meets
the sides and edges. The lid shall then be secured to the sides, ends and
diaphragms with the wire ties or connecting wire in the manner described
for assembling.
d. The cells in any row shall be filled in stage so that local deformation may
be avoided. That is at no time shall the cell be filled to a depth exceeding
30 cm more than the adjoining cell.
4. Method of Measurement
The quantities to be paid for shall be the number of cubic meter of gabions and mattresses
and the area of filter cloth completed and accepted.
5. Basis of Payment
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 89
Quantities determined as provided above shall be paid for at the appropriate contract unit
price per unit of measurement for the Pay Item shown in the Bid Schedule, which price
and payment shall constitute full compensation for all necessary excavation, subgrade
preparation, for furnishing, placing wire baskets and fill materials and for all labor,
equipment accessories, tools, and incidentals necessary to complete the Item.
1. Description
This item shall consist of designing, furnishing, installing, testing and stressing permanent
cement -grouted ground anchors in accordance with the Plans, these specifications, and
the Special Provision.
2. Working Drawings
At least 30 days before work id to begin, the Contractor shall submit to the Engineer for
review and approval complete working drawings and design calculations describing the
ground anchor system or systems intended for use. The submittal shall include the
following:
B. A drawing of the ground anchor tendon and the corrosion protection system,
including details for the following:
C. The grout mix design and procedures for placing the grout.
The engineer shall approve or reject the Contractor's working drawings within 30
days of receipt of a complete submittal. No work on ground anchors shall begin
until working drawings have been approved in writing by the Engineer. Such
approval shall not relieve the Contractor of any responsibility under the contract
for the successful completion of the work.
3. Material Requirements
A. Prestressing Steel
B. Grout
Cement shall be Type I, II, or III Portland Cement conforming to AASHTO M 85.
Cement used for grouting shall be fresh and shall not contain any lumps or other
indications of hydration or "pack set".
Admixtures may be used in the grout subject to the approval of the Engineer.
Expansive admixtures may only be added to the grout used for filling sealed
encapsulations, trumpets, and anchorage covers. Accelerators shall not be used.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 91
Water for mixing grout shall be potable, cleaned and free of injurious quantities of
substances known to be harmful to Portland Cement or prestressing steel.
C. Centralizers
Centralizers and spacers shall be fabricated from any type of material, except
wood, that is not deleterious to the prestressing steel.
D. Steel Elements
Bearing plates shall be fabricated from steel conforming to AASHTO M 270 (ASTM
A 709) Grade 36+ minimum, or be a ductile iron casting conforming to ASTM A
536.
Trumpets used to provide a transition from the anchorage to the unbonded length
corrosion protection shall be fabricated from a steel pipe or tube conforming to the
requirements of ASTM A 53 for pipe or ASTM A 500 for tubing. Minimum wall
thickness shall be 5mm.
Sheath for the unbonded length of a tendon shall consist of one of the following:
Encapsulation for the tendon bond length shall consist of one of the following:
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 92
a. Corrugated high-density polyethylene (HDPE) tube having a minimum
wall thickness of 0.75 mm and conforming to AASHTO M 252
requirements.
The type of sheath and encapsulation for the tendons selected shall be subjected
to the approval of the Engineer.
F. Miscellaneous Elements
Bond breaker for a tendon shall consist of smooth plastic tube or pipe that is
resistant to aging by ultra-violet light and that is capable of withstanding abrasion,
impact and bending during handling and installation.
Spacers for separation of elements of a multi-element tendon shall permit the free
flow of grout. They shall be fabricated from plastic, steel, or material which is not
detrimental to the prestressing steel. Wood shall not be used.
4. Construction Requirements
A. Fabrication
a. General
Tendons for ground anchors may be either shop or field fabricated from
materials conforming to the requirements of Prestressing Steel. Tendons
shall be fabricated as shown on the approved working drawings. The
tendon shall be sized to meet the following:
a.1 The design load does not exceed 60% of the minimum
guaranteed ultimate tensile strength of the tendon.
a.2 The maximum test load does not exceed 80% of the minimum
guaranteed ultimate tensile strength of the tendon
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 93
b. Bond Length and Tendon Bond Length
The contractor shall determine the bond length necessary to develop the
design load indicated on the plans and to satisfy the load test requirements.
The minimum tendon bond length shall be 3 m in rock, 4.5 m in soil or as
shown on the Plans, which shall not be less than 3 m.
Spacers shall be placed along the tendon bond length of multi element
tendons to separate each of the individual elements so that the
prestressing strength will bond to the grout. They shall be located at 3 m
maximum centers with the upper one located a maximum of 1.5 m from the
top of the tendon bond length and the lower one located a maximum of 1.5
m from the bottom of the tendon bond length.
Centralizers shall be placed along the bond length. They shall be located
at 3 m maximum center-to-center spacing with the upper one located a
maximum of 1.5 m from the top of the tendon bond length and the lower
one located 0.30 m from the bottom of the tendon bond length. Use
centralizers that do not impede the free flow of grout up the borehole.
Centralizers are not required on tendons installed utilizing a hollow-stem
auger if it is grouted through the auger and the drill hole is maintained full
of a stiff grout (less than 22.5 cm slump) during extraction of the auger. A
combination centralizer-spacer may be used.
e. Unbonded Length
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 94
The unbonded length of the tendon shall be a minimum of 4.5m or as
indicated on the Plans or approved working drawings.
If the sheath provided is not a smooth tube then a separate bond breaker
must be provided to prevent the tendon from bonding to the anchor grout
surrounding the unbonded length.
Bearing plates shall be sized so that the bending stresses in the plate do
not exceed the yield strength of the steel when a load equal to 95% of the
minimum guaranteed ultimate tensile strength of the tendon is applied. The
size of bearing plates shall not be less than that shown on the Plans or on
the approved working drawings.
The trumpet shall be welded to the bearing plate. The trumpet shall have
an inside diameter at least 6mm greater than the diameter of the tendon at
the anchorage. The trumpet shall be long enough to accommodate
movements of the structure during testing and stressing. For strand
tendons with encapsulation over the unbonded length, the trumpet shall be
long enough to enable the tendon to make a transition from the diameter
of the tendon in the unbonded length to the diameter of tendon at the
anchor head without damaging the encapsulation.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 95
Tendons shall be stored and handled in such a manner as to avoid damage
or corrosion. Damage to tendon’s prestressing steel as a result to
abrasions, cuts, nicks, welds, weld splatter corrosion or pitting will be a
cause for rejection by the Engineer. Grounding of welding leads to the
prestressing steel is not permitted. A slight rusting, provided it is not
sufficient to cause pits visible to the unaided eye, shall not be cause for
rejection. Prior to inserting a tendon into the drilled hole, its corrosion
protection elements shall be examined for damage. Any damage found
shall be repaired in a manner approved by the Engineer. Degrease the
bond length of tendons and remove solvent residue before installation.
B. Installation
The Contractor shall select the drilling method, the grouting procedure and
grouting pressure to be used for the installation of the ground anchor as necessary
to satisfy the load test requirements with prior approval of the Engineer.
a. Drilling
The drilling method used may be core drilling, rotary drilling, percussion
drilling, auger drilling or driven casting. The method of drilling used shall
prevent loss of ground above the drilled hole that may be detrimental to the
structure of existing structures. Casting for anchor holes, if used, shall be
removed, unless permitted by the Engineer to be left in place. The location,
inclination, and alignment of the drilled hole shall be as shown on the plans.
Inclination and alignment shall be within plus or minus 3 degrees of the
planned angle at the bearing plate, and within plus or minus 30cm of the
planned location at the ground surface (point of entry).
b. Tendon Insertion
The tendon shall be inserted into the drilled hole to the desired depth
without difficulty. When the tendon cannot be completely inserted it shall
be removed and the drill hole cleaned or redrilled to permit insertion.
Partially inserted tendons shall not be driven or forced into the hole. Do not
extend ground anchors beyond the right-of-way or easement limits.
c. Grouting
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 96
pumped in one continuous operation. The mixer shall be capable of
continuously agitating the grout during placement.
The grout shall be injected from the lowest point of the drill hole. The grout
may be placed either before or after insertion of the tendon. The grout may
be pumped though grout tubes, casing, hollow-stem augers or drill rods.
The quantity of the grout and the grout pressures for each ground anchor
shall be recorded. The grout pressures and grout take shall be controlled
to prevent excessive heaving of the ground or fracturing of rock formations.
Except as indicated below, the grout above the top of the bond length may
be placed at the same time as the bond length grout, but it shall not be
placed under pressure. The grout at the top of the drill hole shall stop
150mm from the back of the structure or from the bottom of the trumpet,
whichever is lowest.
If grout protected tendons are used for ground anchors anchored in rock,
then pressure-grouting techniques shall be utilized. Pressure grouting
requires that the drill hole be sealed and that the grout be injected until a
0.35 MPa grout pressure can be maintained on the grout within the bond
length for a period of 5 minutes.
Upon completion of grouting, the grout tube may remain in the drill hole
provided it is filled with grout.
After grouting, the tendon shall not be loaded for a minimum of 3 days.
The bearing plate and anchor head shall be placed perpendicular to the
axis of the tendon.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 97
The trumpet shall be completely filled with corrosion inhibiting grease or
grout. The grease may be placed any time during construction. The grout
shall be placed after the ground anchor has been load tested. The
Contractor shall demonstrate that the procedures selected for placement
of either grease or grout will produce a completely filled trumpet.
The Contractor shall test each ground anchor using a maximum test load not to
exceed 80% of the minimum ultimate tensile strength of the tendon. No load
greater than 10% of the design load may be applied to the ground anchor prior to
load testing. The test load shall be simultaneously applied to the entire tendon.
a. Testing Equipment
A hydraulic jack and pump shall be used to apply the test load. The jack
and a calibrated pressure gauge shall be used to measure the applied load.
The pressure gauge shall be graduated in 1 MPa increment or less. When
the theoretical elastic elongation of the total anchor length at the maximum
test load exceeds the ram travel of the jack, the procedure for recycling the
jack ram shall be included in the working drawings. Each increment of test
load shall be applied as possible.
The stressing equipment shall be placed over the ground anchor tendon in
such a manner that the jack, bearing plates, load cells and stressing
anchorage are axially aligned with the tendon and the tendon is centered
within the equipment.
b. Performance Test
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 98
The performance test shall be made by incrementally loading and
unloading the ground anchor in accordance with the following schedule
unless a different maximum test load and schedule are indicated on the
Plans. The load shall be raised from one increment to another immediately
after recording the ground anchor movement. The ground anchor
movement shall be measured and recorded to the nearest 0.025mm with
respect to an independent fixed reference point at the alignment load and
at each increment of load. The load shall be monitored with a pressure
gauge. The reference pressure gauge during each performance test. If the
load is determined by the reference pressure gauge and the jack, pressure
gauge and reference pressure gauge shall be recalibrated. At load
increments other than the maximum test load, the load shall be held just
long enough to obtain the movement reading.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 99
A graph shall be reconstructed showing a plot of ground anchor
movement versus load for each load increment marked with an
asterisk (*) in the performance test schedule and a plot of residual
ground anchor movement of the tendon at each alignment load
versus the highest previously applied load. Graph format shall be
approved by the Engineer prior to use.
c. Proof Test
AL
0.25DL 1.20DL
0.50DL 1.33DL (maximum test load)
0.75DL Reduce to lock-off load
1.00DL
The maximum test load in a proof test shall be held for 10 minutes.
The jack shall be repumped as necessary in order to maintain a
constant load. The load-hold period shall start as soon as the
maximum test load is applied and the ground anchor movement shall
be measured and recorded at 1, 2, 3, 4, 5, 6 and 10 minutes. If the
ground anchor movement between 1 minute and 10 minutes
exceeds 1mm, the maximum test load shall be held for an additional
50 minutes. If the load hold is extended, the ground anchor
movement shall be recorded at 15, 20, 30, 45 and 60 minutes. A
graph shall be constructed showing a plot of ground anchor
movement versus load for each load increment in the proof test.
Graph format shall be approved by the Engineer prior to use.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 100
d. Creep Test
AL
0.25DL 10
0.50DL 30
0.75DL 30
1.00DL 45
1.20DL 60
1.33DL 300
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 101
A performance-tested of proof-tested ground anchor with a 10
minute load hold is acceptable if the:
e.1 Ground anchor resists the maximum t6est load with less
than 1mm movement between 1 and 10 minutes; and
e.3 Total movement at the maximum test load may not exceed
the theoretical elastic elongation of the unbonded length plus
50% of the theoretical elastic elongation of the bonded length.
[Criterion (3) applies only for a performance-tested ground
anchor in competent rock.]
e.1 Ground anchor resist the maximum test load with a creep
rate that does not exceed 2 mm in the last log cycle of time.
e.3 Total movement at the maximum test load may not exceed
the theoretical elastic elongation of the bonded length.
[Criterion (3) applies only for a performance-tested ground
anchor in competent rock.]
e.1 Ground anchor carries the maximum test load with a creep
rate that does not exceed 2 mm in the last log cycle of time.
e.3 Total movement at the maximum test load may not exceed
the theoretical elastic elongation of the unbonded length plus
50% of theoretical elastic elongation of the bonded length.
[Criterion (3) applies only for a performance-tested ground
anchor in competent rock.]
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 102
If the total movement of the ground anchor at the maximum test load
does not exceed 80% of the theoretical elastic elongation of the
unbonded length, the ground anchor shall be replaced at the
Contractor’s expense.
A ground anchor which has a creep rate greater than 2 mm per log
cycle of time can be incorporated into the structure at a design load
equal to one-half of its failure load. The failure load is the load
resisted by the ground anchor after the load has been allowed to
stabilize for 10 minutes.
When a ground anchor fails, the Contractor shall modify the design
and/or the installation procedures. These modifications may include,
but are not limited to, installing a replacement ground anchor,
reducing the design load by increasing the number of ground
anchors, modifying the installation methods, increasing the bond
length of changing the ground anchor type. Any modification which
requires changes to the structure shall be approved by the Engineer.
Any modifications of design or construction procedures shall be
without additional cost to the Department and without extension of
contract time.
f. Lock Off
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 103
5. Method of Measurement
Ground anchors will be measured and paid for by the sum of the bonded and
unbonded length of anchor bars installed and accepted as shown on the Plans or
ordered by the Engineer. No change in the number of ground anchors to be paid
for will be made because of the use by the Contractor of an alternative number of
ground anchors
.
6. Basis of Payment
The accepted quantity , measured as prescribed in Section 513.5, shall be paid for
at the contract unit price paid for Permanent Ground Anchors, which price and
payment shall be full compensation for furnishing all labors, materials, tools,
equipment and incidentals and for doing all the work involved in installing the
ground anchors (including testing), complete in place, as shown on the plans and
as specified in these Specifications and the Special Provisions, and as directed by
the Engineer.
715(1) Geotextile
Drainage Outfall
1. Description
This Item covers geotextile fabrics for use in subsurface drainage, hydraulic filter,
erosion control, sediment control, pavement structures as a waterproofing and stress
relieving membrane, and as a permeable separator to prevent mixing of dissimilar
materials such as foundations and select fill materials.
Fibers used in the manufacture of geotextiles, and the threads used in joining
geotextiles by sewing, shall consist of long-chain synthetic polymers, composed of at
least 85 percent by mass polyolefins, polyesters, or polyamides. They shall be formed
into a network such that the filaments or yarns retain dimensional stability relative to
each other, including selvedges. These materials shall conform to the physical
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 104
requirements of Table 1 for the indicated application. Guidelines for the survivability
levels referred to under “Separation” in Table 1 are included in Table 2.
The product shall be subject to sampling and testing. Sampling shall be done in
accordance with ASTM D 4354 and testing procedures shall be in accordance with
the methods given in Table 1.
4. Certification
A. Manufacturer's Certificate
The manufacturer shall file with the purchaser a certificate stating the name of
the manufacturer, the chemical composition of the filaments or yarns, and
other pertinent information so as to fully describe the geotextile. The
manufacturer shall include in the certificate a guarantee stating that the
geotextile that is furnished meets the requirements of the specification. The
certificate shall be attested to by a person having legal authority to bind the
company. Either mismarking or misrepresentation by the manufacturer shall
be reason to discontinue acceptance under these specifications. Notice sent
to the manufacturer by the purchaser regarding the discontinuance of
acceptance will be considered to be notice to all wholesalers, jobbers,
distributors, agents and other intermediaries handling themanufacturer’s
product.
5. Quality Control
A. During periods of shipment and storage, the fabric shall be protected from
direct sunlight, ultra-violet rays, temperatures greater than 600C (1400F), mud,
dust, and debris. To the extent possible, the fabric shall be maintained
wrapped in a heavy-duty protective covering. Each shipping document shall
include a notation certifying that the geotextile is in accordance with the
manufacturer’s certificate and guarantee previously filed with the purchaser.
B. Product Marking
Label the fabric and its container with the manufacturer’s name fabric type or
trade name, lot number and quantity.
7. Installation
A. Separation Geotextile
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 105
The geotextile shall be unrolled as smoothly as possible on the prepared
subgrade in the direction of construction traffic. Adjacent geotextile rolls shall
be overlapped in the direction of subbase placement using the guidelines in
Table 3. Sewing is recommended where subgrade soils have a CBR value less
than 1. The geotextile maybe held in place prior to subbase placement by pins,
staples, or piles of fill or rock. On curves, the geotextile maybe folded or cut to
conform to the curve. The fold or overlap shall be in the direction of construction
and held in place as prescribed above.
B. Drainage Geotextile
In trenches, after placing the backfill material, the geotextile shall be folded
over the top of the filter material to produce a minimum overlap of 12 inches
for trenches greater than 12 inches wide. In trenches less than 12 inches in
width, the overlap shall be equal to the width of the trench. The geotextile shall
then be covered with the subsequent course. Successive sheets of geotextile
shall be overlapped a minimum of 12 inches in the direction of flow.
D. Paving Fabric
The fabric shall be placed into the asphalt sealant with minimum wrinkling prior
to the time the asphalt has cooled and lost tackiness. As directed by the
Engineer, wrinklers or folds in excess of 1 inch shall be slit and laid flat.
Brooming and/or pneumatic rolling will be required to maximize fabric contact
with the pavement surface. Overlap of fabric joints shall be sufficient to ensure
full closure of the joint, but should not exceed 6 inches. Transverse joints shall
be lapped in the direction of paving to prevent edge pickup by the paver. A
second application of asphalt sealant to fabric overlaps will be required if in the
judgment of the Engineer additional asphalt sealant is needed to ensure proper
bonding of the double fabric layer.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 106
surface. The geotextile shall be spliced together only at a support post with a
minimum 6 inches overlap.
F. Hydraulic Filter
8. Method of Measurement
A. The geotextile shall be measured by the number of square meters from the
pavement lines shown on the plans, or from the pavement lines established in
writing by the Engineer.
D. Excavation, backfill, bedding, and cover material are separate pay items.
1022,3
152 NR NR H H M M
305 NR NR H M M M
457 NR H M M M M
H = High
M = Medium
NR = Not Recommended
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 107
1 Maximum aggregate size not to exceed one-half the compacted cover thickness
3 The 102 mm minimum cover is limited to existing road bases intended for use in new
construction
2-3 762 76
9. Basis of Payment
The quantities determined as provided above shall be paid for at the contract price per
unit of measurement, respectively, for each pay item listed below.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 108
PART H. MISCELLANEOUS STRUCTURES
1.Description
This work item shall consist of the construction of curb and/or gutter made of concrete in
accordance with this specification at the location, and in conformity with the lines, grades,
dimensions and design, shown on the plans or as required by the Engineer.
2.Materials Requirements
Bed course material as shown on the plans shall consist of cinders, sand, slag, gravel,
crushed stone, or other approved porous material.
Concrete shall be of the class indicated on the plans and shall conform to the requirements
of Division 03.
3.Construction Requirements
Excavation shall be made to the required depth and the base upon which the curb and/or
gutter is to be set shall be compacted to a firm and even surface. Bed course material shall
be placed and compacted to form a bed of the required thickness as shown on the plans. All
soft and unsuitable materials shall be removed or replaced with suitable materials.
Forms shall be of wood or metal as approved by the Engineer. Forms to hold the concrete
shall be built and set-in place. Forms for at least 50m of curb and/or gutter shall be in place
and checked for alignment and grade before concrete is placed. Curbs and/or gutters
constructed on curves shall have forms of either wood or metal and they shall be accurately
shaped to the curvature shown on the plans.
Mixing, placing, finishing and curing of concrete shall conform to the requirements of Division
03, Concrete.
The concrete shall be placed in the forms in layers of 100 or 125mm each, and to the depth
required. It shall be tamped and spaded until mortar entirely covers the top and surfaces of
the forms. The top of the concrete shall be finished to a smooth and even surface and the
edges to a radius shown on the plans.
The curb and/or gutter shall be constructed in uniform sections of not more than 50m in length
except where shorter sections are required to coincide with the location of the weakened
planes or contraction joints of the concrete pavement, or for closures, but no section shall be
less than 2m long. The section shall be separated by sheet templates set perpendicular to
the face and top of the curb and/or gutter and not less than 50mm deeper than the depth of
the curb and/or gutter. The templates shall be approximately 5mm in thickness and of the
same width as that of the curb and/or gutter. Templates shall be set carefully and held firmly
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 109
during the placing of the concrete and shall remain in place until the concrete has set
sufficiently to hold its shape but shall be removed while the forms are still in place. Preformed
joint filler approved by the Engineer may be used in lieu of the sheet template mentioned
above. In this event the fiber board shall be pre-cut to the shape of the curb so that its outer
edge will be flushed with the abutting curb and/or gutter.
Expansion joints shall be formed at intervals shown on the plans. Where a curb is placed
next to a concrete pavement, expansion joints in the curb shall be located opposite expansion
joints in the pavement.
The form shall be removed within 24 hours after the concrete has been placed. Minor defects
shall be repaired with mortar containing one part of Portland Cement and two parts of fine
aggregate. The exposed surface shall be finished while the concrete is still fresh. The
concrete shall be suitably protected from the weather until thoroughly hardened.
After the concrete has set sufficiently, the spaces on the back of the curb which were
excavated for placing the curb shall be refilled to the required elevation with suitable material
which shall be tamped in layers of not more than 150mm until consolidated.
1.General
This work item shall consist of the construction of Portland cement concrete sidewalk in
accordance with this specification and to the lines, grades, levels and dimensions shown on
the plans, or as required by the Engineer.
2.Materials Requirements
The Portland cement concrete shall be Class A as specified and shown on the plans. Unless
otherwise ordered, the preformed joint filler shall have a thickness of 5mm and shall conform
to the requirements of Portland Cement Concrete Pavement. Forms shall be of wood or
metal as approved by the Engineer and shall extend to the full depth of the concrete. All
forms shall be straight, free from warps and of adequate strength t resist distortion. The bed
course material shall consist of cinders, sand, slag, gravel, crushed stone or other approved
permeable granular materials of such grading that all particles shall pass 12.5mm (1/2 inch)
sieve as shown on the plans.
3.Construction Requirements
Excavation shall be made to the depth and width required that would permit the installation
and bracing of the forms. The foundation shall be shaped and compacted to a firm and even
surface conforming to the section shown on the plans and subbase course materials shall be
placed in accordance with the specifications for Aggregate Subbase Course.
All forms shall be staked securely in position at the correct line and level. Preformed joint
filler shall be set in position shown on the plans before placing the concrete is started.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 110
The mixing, placing, finishing and curing of concrete shall be as specified in Division 03,
Concrete. The cement concrete shall be placed to the total depth shown on the plans.
The surface shall be cut through to a depth of 10mm with a trowel at intervals of 1m or, where
required, in straight lines perpendicular to the edge of the sidewalk. The surface shall then
be brushed and the edges and the transverse cuts shaped with a suitable tool so formed as
to round the edges.
1. Description
This item shall consist of furnishing and constructing posts and guardrails of the types
called for in the contract and in accordance with this Specification, at the locations, and in
conformity with the lines and grades shown on the Plans, or as required by the Engineer.
2. Material Requirement
Materials for the desired type of guardrail shall meet the requirements specified in the
following specifications:
Timber guardrail shall be well-seasoned, straight and free of injurious defects. They shall
be dressed and of sufficient length so that joints shall be on the rail posts.
Guardrail Hardware. Offset brackets of the resilient and non-resilient types shall be of the
type specified, or as shown on the Plans, and shall meet the strength requirements
specified.
Splices and end connections shall be of the type and design specified or as shown on the
Plans, and shall be such strength as to develop the full design strength of the rail elements.
Unless otherwise specified, al fittings, bolts, washers and other accessories shall be
galvanized in accordance with the requirements of AASHTO M 111 or ASTM A 153,
whichever may apply. All galvanizing shall be done after fabrication.
Guardrail Post. Post shall be of either wood, steel, or concrete, as may be specified. Only
one kind of post shall be used for any one continuous guardrail.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 111
Wood post shall be fabricated from an approved or specified timber specie and shall be
of the quality, diameter or section and length as specified, or as shown on the Plans.
Steel post shall be of the section and length as specified, or as shown on the Plans. They
shall be of a copper bearing steel when so specified. steel shall conform to the
requirements of AASHTO M 183 for the grade specified. The posts shall be galvanized or
shop painted as may be specified.
Concrete deadmen for end anchorages shall be as specified, or as shown on the Plans.
Concrete and reinforcement shall conform to the requirements as stated above the precast
reinforced concrete posts.
Paints for steel and wood shall be specified and conform to the requirements specified in
Paint.
3. Construction Requirements
A. Posts
Posts shall be set vertically in the position shown in the plans and where embedded
in a concrete foundation block, shall remain undisturbed for a minimum of 48
hours. The space around the post shall be backfilled to the ground line with
approved material in layers not exceeding 100 mm and each layer shall be
moistened and thoroughly compacted.
B. Rail Elements
Where painting of railing components is specified, any damage to the shop coat of
paint shall be corrected by an application of an approved rust-inhibitive primer prior
to further painting. Any surface inaccessible to painting after erection shall be given
the specified number of coats of paint uniformly applied by thorough brushing using
an approved pressure spray.
Galvanized surfaces which have been abraded so that the base material is
exposed, threaded portions of all fittings and fasteners and cut ends of bolts shall
be protected in a manner as may be specified or directed.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 112
pain. Painting shall be done only when the timber is dry and clean. Each coat of
paint shall be thoroughly dry before the next coat is applied. Paint shall be applied
in heavy coats, completely covering every part of the surface and shall be worked
well into the joints and open spaces. It shall be thoroughly and evenly spread that
no excess paint collects at any point.
Guardrail and posts, after erection has been completed, shall be stained with two
applications of approved creosote stain, covering the rails and the exposed
portions of the posts. The wood shall be dry before being stained. The first coat
shall be thoroughly dry before the second is applied. Stain shall to be applied
during damp weather.
For beam type guardrails, metal works not galvanized shall be given one shop coat
of red lead, zinc chromate paint or an approved fast-drying rust-inhibitive primer
and two field coats of white or aluminum paint. Untreated wood posts shall be given
three coats of paints of the color indicated of the Plans, or as specified. Painting
shall conform to the requirements of Paint.
4. Method of Measurement
Guardrail shall be measured by linear meter from center to center of end posts, except
where end connections are made on masonry or steel structures, in which case
measurement will be to the face of such structures.
End anchorages and terminal sections will be measured as units of each kind shown in
Bid Schedule. If no pay item for anchorages or terminal sections appear in the Bid
Schedule, measurement therefore shall be included in the linear meter measurement for
completed guardrail.
5. Basis of Payment
1. Description
This Item shall consist of furnishing and constructing posts and barbed wire or chain link
fences in accordance with the details, and at the locations, shown on the Plans, or as
required by the Engineer.
2. Material Requirements
A. Barbed Wire
Barbed wire shall conform to the requirements of ASTM A 121, Class I. The barbed
wire shall consist of 2 strands of 12.5 gauge wire, twisted with 2 points 14 gauge
barbs spaced 100 mm apart.
Chain link fence fabric shall be fabricated from 10 gauge galvanized wire
conforming to AASHTO M 181 and shall be of the type shown on the Plans. Before
ordering the chain link fence fabric, the Contractor shall submit a sample of the
material to the Engineer for testing and for approval.
C. Concrete Post
Concrete posts shall be made of Class A concrete in accordance with Item 405,
Structural Concrete. The posts shall be cast to a tapered section 3 m long, or to
the length shown on the detailed Plans, and shall have a smooth surface finish.
D. Steel Post
Steel posts shall be of the sections and length as specified or as shown on the
Plans. The posts shall be copper bearing steel and shall conform to the
requirements of AASHTO M 183 for the gradespecified.
E. Steel Reinforcement
Steel reinforcement for concrete posts shall be deformed steel bars conforming to
the provisions of Item 404, Reinforcing Steel.
F. Hardware
Nuts, bolts, washers and other associated hardware shall be galvanized after
fabrication as specified as ASTM 153.
3. Construction Requirements
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 114
The Contractor shall perform such clearing and grubbing as may be necessary to construct
the fence to the required grade and alignment.
Fence shall generally follow the contour of the ground. Grading shall be performed where
necessary to provide a neat appearance.
A. Erection Post
The post shall be erected vertically in position inside the formwork of the foundation
block prior to the placing of concrete and shall be adequately supported by bracing
to prevent movement of the post during the placing and setting of the concrete.
The posts shall be erected to the height and location shown on the Plans, or as
ordered by the Engineer.
The chain link fence fabric shall be set to line and elevation and pulled taut between
each post before spot welding, or other method of fixing, is carried out. Where
splicing of the fence fabric is necessary, or at joints, the lapping of the chain link
fence fabric shall be for a minimum of 100 mm and shall occur only at the post. No
horizontal splicing will be permitted. The fence fabric shall be fixed to the posts as
shown on the Plans. Any surface protective layer damaged during welding and/or
construction shall be restored properly.
4. Method of Measurement
The quantity to be paid for shall be the number of linear meter measured center to center
of posts, of fencing erected in place and accepted.
5. Basis of Payment
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 115
Fencing (Chain LinkFence
604 (2) Fabric) Linear Meter
EARTHWORK
1. General
A. Description
The specification covers general requirements for the building works of excavation
and backfilling for this project.
a. Scope
a.1 Surveying
b. Surveying
All surveying required for the works shall be performed by the contractor.
The elevations and distances shall be measured from the Owner’s
approved existing benchmarks.
All the surveying methods and records shall be submitted to the Project
Manager for approval.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 116
c. Site Clearing
The entire site as indicated on the drawings shall be cleared and the
Contractor shall take all necessary precautions in its execution.
All the existing facilities in the vicinity of the works shall be protected from
damage. Existing lighting poles, foundations of adjacent buildings, street
paving, curbs and gutter, sidewalk and drainage, etc., shall be protected as
required in a manner as approved by the Project manager.
B. Quality Assurance
2. Products
a. Approval
All fill material shall be subject for approval by the Project Manager.
b. Notification
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 117
For approval of fill material, notify the Project Manager at least two weeks
in advance of the intention to import fill material. Take samples and test as
necessary for the purpose of verifying the quality of the material for the
acceptance of the Project Manager.
Imported excavated for use as fill shall be obtained from borrow pits to be located
and secure by the Contractor. All borrow material shall be free from stumps, tree
roots and deleterious substances.
Imported cohesion less material used for trench and structural backfill shall
be free from organic substance, debris, rocks or lumps and other
deleterious matter, shall be subject for approval by the Project Manager,
and shall be particle size grading within the following limits.
b. Excavated Material
b.1 Material excavated from the site, except for deleterious material,
shall be used for back filling subject to the Project Manager’s
inspection and approval.
D. Other Materials
The Contractor subject for approval by the Project Manager shall select all other
materials not specifically described but required for a complete and proper
installation
3. Execution
A. General
a. Familiarization
Prior to all work of this Specification the Contractor should become familiar
with the site, site conditions, the sub - soil conditions, and all portions of the
work falling within this specification.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 118
b. Temporary access and drainage
If the work site is inaccessible due to soft soil or obstructions, the Contractor
should provide the necessary means of access at his own expense.
Effective temporary drainage should be designated to keep the work area
from flooding.
c. Prior to backfilling
B. Excavating
a. Excavation to Levels
b. Excavated Faces
The Contractor shall assume full responsibility for maintaining the stability
of all excavated faces until final acceptance of the foundation works.
c. Over Excavation
c.1 Backfill and compact all over excavated areas as specified for
ill below at no additional cost to the Owner.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 119
Contractor as approved by the Project Manager shall provide
protection to existing structures and facilities.
e. Soft Spots
C. Preparation of Subgrade
a. Scarifying
b. Leveling
a. Unfavorable Weather
Do not place, spread or roll and fill material during unfavorable weather
conditions. Do not resume operations until moisture content and fill density
are satisfactory to the Project Manager.
b. Flooding
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 120
Where the soil has been softened or eroded by flooding or placement
during unfavorable weather, remove all damaged areas and re-compact as
specified for fill and compaction below.
d. De - Watering
d.3 De-water by means, which will ensure dry excavations and the
preservation of the final lines, faces, and grades of bottom of
excavations.
a. Filling
After sub grade and bottoms of foundations and trenches have been
prepared and approved by the Project Manager, spread approved fill
material in layers not exceeding 300 mm in un-compacted thickness.
b. Moisture - Conditioning
Water the fill material as necessary and thoroughly mix to obtain as near
as possible optimum water content which will permit proper handling.
c. Compaction: General
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 121
Sub grade under floor slabs shall be compacted to a dry density equivalent
to 95% (min).
e. Quality Control
CAST-IN-PLACE CONCRETE
1. General
A. Description
a. Scope
In accordance with the provisions of this section and the drawings, provide:
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 122
a.1 Cast-in-place concrete, complete, in place, and properly
installed.
B. Quality Assurance
b. Reinforcement
c. Design of Formwork
d. Qualification of Installers
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 123
The contractor, before commencing any work, shall verify
the grade conditions of all ground surfaces and any other
conditions at the site and other areas which may affect his
work and shall notify the Project Manager in writing of any
discrepancies between conditions as actually existing and
as shown on the design drawings.
0 - 50 One sample
(iii) Records
C. Submittals
a. Product Data
b. Samples
b.6 Waterstops
D. Product Handling
a. Protection
Use all means necessary to protect the materials of this section before,
during, and after installation and to protect the work and materials of all
other trades.
b. Delivery
c. Storage
c.1 Cement
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 126
All cement shall be delivered in sound and properly secured bags
and shall be stored in a dry weatherproof shed with a raised wooden
floor, or other facilities approved by the Project manager.
c.2 Aggregates
c.3 Reinforcement
d. Replacements
e. Rejection
Any consignment or part of a consignment that does not comply with the
specification shall not be used in the work and shall be removed from the
site.
2. Products
A. Materials
a. Cement
a.2 Certificate
b.1 General
For the concrete of this section, all fine and coarse aggregate shall
preferably come from only one source.
b.2 Testing
c. Water
Water for mixing concrete shall be fresh and clean, and free from injurious
amounts of oil, acid, alkali, salt, or organic materials.
d. Admixtures
e. Curing Materials
For moist curing burlap cloth made from jute or kenaf and weighing
approximately 305 grams per sq. m. and shall be used in two layers.
f.2 Waterstops
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 128
Water stops shall be extruded from new stock polyvinyl chloride,
ribbed, expandable center bulb, or other approved type. The
minimum width shall be 150 mm and minimum thickness shall be
6.4 mm.
Use transit-mixed concrete from the approved batching and mixing plant.
h. Reinforcement
Double strands Ga. 16 tie wires for fixing and tying reinforcements.
For big diameter bars, use Ga. 14.
h.4 Compliance
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 129
h.5 Bending and Cutting
i. Formwork
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 130
j. Formwork Ties
j.2 Provide ties so that the portion remaining within the concrete
after removal of exterior parts is at least 3.8 cm from the outer
concrete surface.
j.3 Provide form ties that will not leave a hole larger than 2.5 cm
diameter in the concrete surface.
k. Formwork Coatings
3. Execution
A. General
Concrete for reinforced concrete structure is classified into grade, quality and
slump. The class of concrete shall be specified on the drawings, denoted by
minimum 28 days compressive strength, based on 15 cm diameter x 30 cm height.
Concrete
Grade
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 131
B. Concrete Placement
a. General
b. Placement Schedule
c.8 Use chutes for pouring concrete where a drop of more than 2.0
meters is required.
Chute arrangement:
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 132
c.8.2 In cases where concrete must be chuted from a high
elevation, vertical flexible chutes shall be used.
c.9 Pumps may be used only if they can pump the design mix. Do
not add fine aggregate or water to the mix to satisfy needs of a
pumping device.
c.12 Concrete mix should be poured within 1 hour after water has
been added to dry mix.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 133
c.17.1 Deposit and consolidate concrete slabs in a
continuous operation, within the limits of construction joints,
and/or until the placing of a panel or section is completed.
C. Consolidation
a. General
b. Procedures
b.3 Do not insert the vibrator into lower courses that have begun to
set.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 135
b.4 Use the vibrator to melt down the concrete as it is being placed,
and use the vibrator to consolidate the mass of concrete.
b.5 In the case of wall construction, assign at least one vibrator and
vibrator-operator to melting down the mix; and assign at least one
other vibrator and vibrator-operator to consolidating the mass of
concrete.
b.8 Vibration shall not be continued at any one point to the extent
that localized areas of grout are formed. Vibrators shall not touch
reinforcement.
c. Maintenance of Vibrators
Initiate a maintenance program for the vibrators to assure that they are
operating at peak efficiency at all times, and to facilitate effective
consolidation of the concrete.
D. Construction Joints
a. General
a.1 The contractor shall ensure that all construction joints are
arranged to minimize the effects of shrinkage. The position and
arrangement of construction joints shall be according to the
drawings, or otherwise that contractor shall show them in complete
detail on drawings submitted to the Project Manager for approval.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 136
a.5 At points where layer concrete strength is specifically required,
cement paste or rich-mix concrete shall be used. Concrete shall be
placed immediately.
E. Curing
a. General
a.1 For five days after pouring, concrete surfaces shall be kept
constantly wet and protected from sunlight and rapid drying. This is
to be achieved by spraying water directly on to the concrete surface
or over previously laid curing membrane or material.
F. Concrete Finishing
a. General
b.2.3 Repair and patch defective areas with all fins and other
projections completely removed and smoothed.
c.1.4 After leveling, roughen the surface before the final set
using stiff broom brush, or rake.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 138
c.2.1 Apply float finish to monolithic slab surface that are to
receive trowel finish and other finishes hereinafter specified,
and to slab surfaces which are to be covered with insulation,
and as otherwise shown on the drawings or in the
schedules.
a. General
H. Installation of Reinforcement
a. General
Comply with specified standards and for details and methods of fixing
reinforcement and supports, and as herein specified.
b. Fixing Reinforcement
b.1 Clean reinforcement to remove loose rust and mill scale, earth,
and other materials that reduce or destroy bonding with concrete.
Cover to Reinforcing
Bar
Minimum Cover
d> or = 19 mmc 6 cm
Beams, column 5 cm
The minimum concrete cover shall not be less than the diameter of
the bars.
I. Formwork
a. General
a.1 Construct forms complying to the exact size, shape lines, and
dimensions shown, and as required to obtain accurate alignment,
location, grade, level, and plumb work in finish structures.
a.3 All rubbish, shavings, saw dust, wire clipping, loose concrete
and any other refuse shall be removed from the inner face of the
forms before placing concrete.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 141
b. Fabrication
b.3 Provide top form for inclined surfaces where the slope is too
steep to place concrete with bottom form only.
d. Support Work
e. Chamfers
f. Formwork Coatings
f.2 Form oil shall be approved by the Project Manager prior to use.
Set and build into the work anchorage devices, piping, boxes, sleeves and
other embedded items required for other work that is attached to, or
supported by, cast-I-place concrete. Items are to be set firm and rigid so
that no movement occurs when concrete is being poured.
h. Removal of Formwork
h.1 Formwork shall not be removed without prior approval from the
Project Manager
i. Re-use of Formwork
Clean and repair surfaces of forms to be re-used in the work. Split, frayed,
delaminated or otherwise damaged form facing material will not be
acceptable. Apply new form coating compound material to concrete contact
surfaces as specified for new formwork. When forms are used for
successive concrete placement, thoroughly clean surfaces, remove fins,
and laitance, and tighten forms to close all joints. Align and secure joints to
avoid offsets.
J. Anchor Bolts
a. General
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 143
a.1 Deformed bolts shall not be used.
a.2 Prior to setting anchor bolts, they shall be cleaned of loose rust,
oil, grease, dust, and other foreign matter, which may reduce
concrete bonding.
a.4 The tolerance for anchor bolts embedment shall comply with
provisions as shown in Table 4.
a.6 While pouring concrete, care shall be taken so that the anchor
bolts held in place do not move, or any other interference is caused.
For setting of anchor bolts, the following two methods shall be applied in
conjunction with relevant drawings and/or instructions given by the Project
Manager. If other special methods are to be used the contractor will be
informed by the Project Manager accordingly.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 144
b.1.3 The above-mentioned support structures shall be of
sturdy construction so that they can withstand shocks and
impacts due to concrete placement, etc., without moving.
Details of these structures shall be drawn up by the
contractor and shall be subject to approval by the Project
Manager before fabrication.
K. Marking
After the concrete has hardened, the centerline of foundations shall be clearly
marked on the top surface. Also, a horizontal line at a level 100 mm below the
underside of the structure to be installed (e.g. bottom of base plate) shall be
marked on all the side surfaces of foundations.
L. Tolerances
a. Tolerances of Form
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 145
a.1.2 Maximum for entire vertical distance+/- 2.5 mm
-6mm + 10mm
b.1 Offset+/- 5 mm
b.2 Elevations+/- 5 mm
Note: when stiffener type jigs are used, Table 4 need not be followed with the exception
of projected length.
M. Inspection
a. General
The contractor shall prepare and submit an inspection sheet to the Project
manager for approval.
The above sheet shall be presented to the Project Manager shortly before
the contractor is ready to commence concreting to allow inspection
approval.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 147
b.2.5 Concrete is plastic when placed;
STRUCTURAL STEEL
1. Painting/ Coating
A. General
a. Scope
a.1 this specification covers the general philosophy for coating external
surfaces of structural steel.
B. Coating Philosophy
a. General
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 148
a.1 all applicable national and local code sand regulations on surface
preparation, coating application, storage, handling, and safety shall be
complied with. All paint manufacturer’s safety instructions and
requirements contained within the Material Safety Data Sheets shall be
followed.
a.2 the coating contractor responsible for the coating work shall ensure that
the latest issues of the product data sheets are available.
a.3 all coating materials shall be delivered and stored in the manufacturer’s
original sealed containers. The contractor shall provide storage to protect
materials from damage due to contamination, rain and adverse high and
low temperatures. Outdoor storage of coating materials and solvents is not
acceptable.
a.4 the coating contractor shall be responsible for the proper disposal of all
surplus, spent, and waste coating materials, solvents, and thinners,
including containers and solvent wipe rags.
b. Surface Preparation
b.1 Mill scale, rust and foreign matter shall be removed to the extent that
the only traces remaining are slight stains in the form of spots or stripes.
The surface shall be cleaned with a vacuum cleaner, clean dry compressed
air or a clean brush.
b.2 Prior to cleaning, all visible oil and grease shall be removed by means
of a suitable solvent by high-pressure water jetting or steam cleaning with,
if necessary, an alkaline cleaning agent. Surfaces, which have been
exposed to a polluted or salt-laden atmosphere, shall be washed down with
clean potable water.
b.3 all welds shall be smooth and free of all weld slag and weld spatter.
b.4 Power and/or hand tool cleaning shall only be used for field repair and
touch ups, where abrasive blasting is not permitted or is impractical.
c. Application
c.1 Coatings shall be applied within 4 hours after surface preparation and
before rust bloom occurs. Coatings shall not be applied when the ambient
temperature, steel substrate temperature, or coating material temperatures
are outside the range recommended by the coating manufacturer. Coatings
shall not take place under adverse weather conditions, rain, fog, etc., or
when such conditions are likely to occur before the paint has become dry.
c.2 Surface coated shall be free of all visible dust, oil grease, and other
surface contaminants. All surfaces shall be thoroughly dry prior to painting.
c.3 Before application of the first coat, all areas such as corners, edges
welds, small brackets, bolts, nuts and interstices shall be stripe coated to
ensure that these areas have at least the minimum specified dry film
thickness. Application of stripe coat shall be by brushing. The brushing
technique shall be to brush out and not to flow on the coating material.
Stripe coat material may be sprayed if followed immediately by brushing.
c.4 each coat shall be allowed to cure sufficiently, prior to application of any
subsequent coat.
C. Materials
a. General
a.2 Products from a single paint manufacturer shall be used for site
painting.
a.3 when a single coating supplier has been specified only material from
that manufacturer shall be used.
a.4 any thinning of coating materials shall be in strict accordance with the
coating manufacturer’s product data sheets and application instructions.
Only solvent recommended by the coating manufacturer shall be used for
thinning.
D. Inspection
a. General
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 150
All materials, equipment and work shall be available to the Project manager,
including the coating manufacturer’s representative at all times. Contractor shall
employ specialist paint and coating inspectors.
b. Inspection Requirements
b.1.1 Materials
b.1.1.3 Verify that the shelf life of coating materials has not
been exceeded.
b.1.1.4 Verify that materials are stored safely and that all
waste is disposed of promptly and safely.
b.1.2 Equipment
b.1.4 Application
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 151
b.1.4.4 Verify that “pot life” is not exceeded.
b.1.5 Adhesion
b.1.6 Repairs
Verify that all repairs have been made. Defective work shall be
corrected at no cost to the Owner.
b.1.7 Cure
b.1.8 Visual
The finished coating work shall pass visual inspection by the Project
manager. The final coating shall be uniform color and smooth.
Coating work indicating defects, improper application, runs, sags,
damages, and excessive repairs, incomplete curing or excessive
thickness is subject to rejection. It is the coating contractor’s
responsibility to correct work found by these inspections including
conditions discovered after acceptance, which are not in
compliance with these requirements.
2. Fabrication
A. General
a. Description
a.1 Scope
b. Quality Assurance
c. Submittals
After the award of the contract, the contractor shall submit the following to
the Project manager in timely accordance with the project requirements:
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 153
c.2 Welding Submittals
c.2.1 General
c.2.2 Qualification
Prepare the following drawing sand data and submit to the Project Manager
for approval.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 154
The contractor shall give the following minimum requirements for shop drawings,
Erection plans, Field Bolt Lists, and any drawings deemed necessary by the
Project Manager.
d.1 General
d.1.1 All shop drawings, erection plans, field bolt lists, and other
drawings shall follow the design drawings of these specifications.
Any deviation there from shall require the written approval of the
Project Manager.
d.2.1 General
d.2. 2 Connections
Detail connections and joints shall follow the Design Drawings, and
the specifications.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 155
d.3.1.2 Relevant dimensions of items, including cut length.
d.3.4 The size of fillet weld shall be given together with the symbol.
The contractor shall give the following minimum requirements for shop drawings,
Erection plans, Field Bolt Lists, and any drawings deemed necessary by the
Project Manager.
e.1 General
e.1.1 All shop drawings, erection plans, field bolt lists, and other
drawings shall follow the design drawings of these specifications.
Any deviation there from shall require the written approval of the
Project Manager.
e.2.1 General
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 156
Design drawings provide information that is required for the
detailing of the structure. Detailing on shop drawings, plans shall at
all times follow what is the essence of the Design Drawings together
with all requirements herein.
e.2.2 Connections
Detail connections and joints shall follow the Design Drawings, and
the specifications.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 157
e.3.1.8 Working point to working point dimensions including
inclinations and angles.
e.3.3 The size of fillet weld shall be given together with the symbol.
f. Product Handling
f.1.3 Fasteners
B. Execution
a. Fabrication
a.1 General
a.2 Straightening
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 158
Before marking-off, steel, which enters the shop for fabrication,
shall be checked for conformity with the standards. Any damaged
or distorted material shall be replaced. The method of repair or
correction shall be submitted to the Project manager for approval.
Approval will only be given if it can be shown that the proposed
repair will not reduce the properties of the steel below those
specified.
a.3 Marking-off
a.4 Bending
a.5 Cutting
a.6 Holing
a.7 Assembling
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 159
a.7.2 All tubular members shall be seal welded to prevent
the access of moisture to the inside of the members. Sealing
plate thickness shall be 6 mm minimum.
b. Welding
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 160
b.5 Weld Cleaning
b.6 Repairs
3. Steel Erection
A. General
a. Description
a.1 Scope
This section gives the requirements for erection and inspection of steel
structures of the project.
b. Quality Assurance
b.1.1 All qualification test records and qualified welder’s list are not
to be confirmed by the designated inspector.
b.1.2 Welders who make any defective weld during the work are not
to be allowed to continue welding.
b.2.5 Take field measurements and examine related work that may
affect erection.
c. Submittal
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 162
c.1 Product Data
c.4.2 Report daily all activities and work progress to the Project
Manager.
d. Material Handling
d.1 Delivery
d.2 Checking
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 163
d.2.1 Any movement of materials shall be under control at all times.
d.3 Storage
d.3.3 Keep all areas designated for storage clean and easy access
should be maintained for handling, identification, and inventory.
d.3.8 High strength bolts; mild steel bolts and electrodes are to be
stored in watertight and dry places.
d.4 Protection
d.4.2 Protect the work and materials from damage by all other
trades.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 164
B. Products
a. Materials
a.1 General
a.1.1 Old material having any loss of the effective thickness due to
rust or pockmark on the surface shall not be used.
C. Execution
a. Erection
a.1 General
a.2.2 Design, supply and erect necessary false work and staging.
a.3.1 Clean concrete and masonry bearing surfaces free from bond-
reducing materials, and then roughen to improve bond to surface.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 165
a.3.2 Set loose and attach base plates and bearing plates for
structural members with steel wedges or other adjusting devices.
a.3.5 Tighten anchor bolts after the supported members have been
positioned and plumbed.
a.3.10 Grouting work shall not be carried out during heavy rains.
a.3.12 No load shall be applied for at least three days after padding
or grouting.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 166
a.4.5 Level and plumb individual members of the structure within
tolerances.
a.4.9 Do not use gas cutting torches in the field for correcting
fabricating errors in the structural framing.
a.4.12 Final bolt tightening shall be made only after checking the
accuracy of the assembled frames.
b. Welding
The welding for main steel members and important joints of steel structures shall
be performed in accordance with the following requirements:
b.1 Welders
b.3.1 When wind velocity exceeds 2 m/sec for gas shielded welding
and 10 m/sec for manual arc welding, sufficient screening shall be
provided to protect the welding areas from wind and rains.
b.4.1 Prior to welding, the welding surface of the base metal shall
be cleaned of rust, slag, oil, and other foreign matter, which will
cause defects in the welding.
b.5.4 All slag per each welding layer shall be carefully removed
upon completion of individual welds.
b.5.5 Extension bars or run-off plates shall be cut off min. 3-5 mm
from edges, and shall be ground smooth avoiding damage to the
base metal.
c. Bolting
c.1.1 Contact surfaces including filler plates and splice plates shall
be free from paint, scales, burrs, dirt, oil, grease, loose rust and
other foreign matter except tight mill scales.
c.1.2 Shim plates or filler plates having a suitable thickness for the
erector shall furnish joints using high strength bolts where the gap
of the contact surface exceeds 1mm.
c.2.4 For length of bolts, a projection of two full threads beyond the
units is to be ensured, when in position.
c.2.5 The tightening order of high strength bolts shall be done from
the center outwards.
d. Inspection
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 169
d.1 Advance Inspection
d.1.1.1 Quantities
Prior to starting erection work, the quality, quantity, size, and grip
length of all high strength bolts shall be inspected to ensure no
failures and shortage, defective bolts shall be reported for
replacement.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 170
e.1 Erection
e.2 Bolting
e.3 Welding
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 171
e.6.1 Overall Dimensional Inspection
1. Description
This Item shall consist of furnishing and installing road signs in accordance with this
Specification and to the details shown on the Plans, or as required by the Engineer.
The road signs shall comply in all respects with the “Philippine International Road Signs
Manual” published by the Department of Public Works and Highways, Manila. The
categories of road signs are designated in the Manual, namely, danger warning signs,
regulatory signs and informative signs, or guide signs. These are referred to in the
Contract as warning signs and informatory signs, respectively.
Road signs shall be classified as standard or non-standard. Standard signs consist of all
warning signs, regulatory signs and informatory signs with the exception of direction signs,
place identification signs and the line. Non-standard signs consist of all informatory signs
which are not classified as standardsigns.
The size of warning and regulatory signs is the length of the side of triangular signs
(measured from the points of intersection of the extension of the edges), the horizontal
width of octagonal signs and the diameter of circular signs.
2. Material Requirements
A. Sign Panels
Sign panels for warning, regulatory, and informatory signs shall be manufactured
from aluminum sheeting at least 3 mm thick.
B. Reflective Sheeting
The reflective sheeting used on the road signs shall consist of spherical lens
elements embedded within a transparent plastic having a smooth, flat surface with
a protected pre-coat adhesive which shall be pressure sensitive for manual
application, or tack free heat activated for mechanical vacuum-heatapplication.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 172
The minimum reflective brightness values of the reflective sheeting as compared
to a magnesium oxide (MgO) shall be as given in Table 605.1. The brightness of
the reflective sheeting totally wet by rain, shall be not less than 90% of the given
values.
200 0.50 10
500 0.50 3
200 0.50 70
500 0.50 70
200 0.50 35
500 0.50 10
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 173
The sheeting shall be solvent-resistant so as to be capable of withstanding
cleaning with petrol, diesel fuel, mineral spirits, and turpentine methanol.
The adhesive shall permit the reflective sheeting to adhere accurately 48 hours
after application of temperatures of up to 900.
Wide flange posts and frames shall be fabricated from structural steel conforming
to ASTM A 283 Grade D. In lieu of wide flange steel posts, the Contractor may use
tubular steel posts conforming to ASTM A 501. All posts shall be thoroughly
cleaned, free from grease, scale and rust and shall be given one coat of rust-
inhibiting priming paint and two coats of gray paint in accordance with Item 411,
Paint.
Nuts, bolts, washers and other metal parts shall be hot-dip galvanized after
fabrication in accordance with the requirements of AASHTO M 111.
The concrete for the foundation blocks shall be Class A in accordance with Item
405, Structural Concrete and shall be of the size shown on the Plans.
3. Construction Requirements
Holes shall be excavated to the required depth to the bottom of the concrete
foundation as shown on the Plans.
Backfilling shall be carried out by using suitable material approved by the Engineer
and shall be compacted in layers not exceeding 150 mm in depth. Surplus
excavated material shall be disposed of by the Contractor as directed by the
Engineer.
B. Erection of
Posts
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 174
The posts shall be erected vertically in position inside the formwork of the
foundation block prior to the placing of the concrete and shall be adequately
supported by bracing to prevent movement of the post during the placing and
setting of concrete. The posts shall be located at the positions shown on the Plans.
Sign panels shall be installed in accordance with the details shown on the Plans.
Any chipping or bending of the sign panels shall be considered as sufficient cause
to require replacement of the panels at the Contractor’s expense.
The exposed portion of the fastening hardware on the face of the signs shall be
painted with enamels matching the background color.
All newly erected traffic road signs shall be covered until ordered removed by the
Engineer.
4. Method of Measurement
The quantities of standard reflective warning and regulatory road signs shall be the
number of such signs of the size specified, including the necessary posts and supports
erected and accepted.
The quantities for standard reflective informatory signs and non-standard reflective
informatory signs shall be the number of such, including the necessary posts and
supports, erected and accepted.
5. Basis of Payment
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 175
ITEM 606 PAVEMENT MARKINGS
1. Description
This item shall consist of placing markings on the finished pavement. The work shall include
the furnishing of non-reflective or reflective pavement marking paint, whichever is called for
is the Contract, sampling and parking, preparing the surface and applying the paint to the
pavement surface, all in accordance with this specification.
The paints shall be applied to the size, shape and location of the markings shown on the
plans, or as required by the Engineer.
In this Contract the traffic road markings shall be white thermoplastic stripping material
conforming to AASHTO M-249-74.
2.General Requirements
Characteristics:
(a) set to bear traffic when applied at air temperature of 10oC (50oF) - 2 minutes max.
(b) set to bear traffic when applied at air temperature of 32oC (90oF) - 10 minutes max.
4.) Bond strength to Portland Cement - 180 psi (1-2 MPa) minimum
6.) Softening point - 102.5oC width a tolerance of 9.5oC (15oF) either way.
8.) The thermoplastic materials shall not exude fumes which are toxic, obnoxious or injurious
to persons or property when it is heated during application.
9.) Application of additional beads by drop-on method shall be at the rate specified by the
Engineer and agreed upon by the applicator/supplier.
10.) Primer shall be used when marking a smooth surface of concrete. Rate of
application of primer shall be at a minimum of 2 grams per sq. meter.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 176
Components White
- Temperature upon application is variable and shall depend on the property of the
thermoplastic material used.
- Amount and type of yellow pigment, calcium carbonate and inert fillers shall be at the
option of the manufacturer provided all other specifications are met.
3.Construction Requirements:
The painting of lane markers and traffic strips shall include the cleaning of the pavement
surfaces, the application, protection and drying of the paint coatings, the protection of
pedestrians, vehicular or other traffic, the protection of all parts of the road structure and its
appurtenances against disfigurement by spatters, splashes or smirches of paints or paint
materials, and the supplying of all tools, labor and traffic paint necessary for the entire work.
The paint shall not be applied during rain or wet weather or when the air is misty, or when in
the opinion of the Engineer, conditions are unfavorable for the work. Paint shall not be
applied upon damp pavement surfaces, or upon pavement which has absorbed heat
sufficient to cause the paint to blister and produce a porous film of paint.
The application of paint shall preferably be carried out by a machine specially made for this
purpose but where brushes are used, only round or oval brushes not exceeding 100 mm in
width will be permitted. The paint shall be so applied as to produce a uniform, even coating
in close contact with the surface being painted.
Traffic paint shall be applied to the pavement at the rate of 0.33 L/m² and shall dry sufficiently
to be free from cracking in from 15 to 30 minutes.
1. General
A. Scope
a. This specification prescribes the technical requirements for street and perimeter
lightings required for operation on a 3-phase, 4-wire, 60 Hz solidly earthed system.
c. Lightings shall furnish any special tools for installation and maintenance.
B. References
The Street and Perimeter Lightings and associated materials shall conform to
relevant IEC standards. Each publication shall be the latest revision and
addendum in effect on the date this specification is issued for purchase, unless
noted otherwise. Except as modified by the requirements specified herein or the
details of the drawings, as a minimum, Work included in this specification shall
conform to the applicable provisions of these publications.
C. Service Conditions
b. Street and Perimeter Lightings will be installed in outdoor concrete pad in a Phil
Air Force security fencing of Phil Air Force facilities area, less than 100 meters
above sea level. The atmosphere is highly corrosive. The ambient temperature
varies between -100C and +450C. Relative humidity reaches 95% at 350C.
b.1 Satisfactory performance without any damage of any kind to any part
of street for an average temperature of and perimeter lights 350C and
maximum of 450C.
b.2 Satisfactory performance without any damage of any kind to any part
of street and perimeter lights for an average temperature of -50C and
minimum of -150C.
c. Seller shall bring to Buyer’s attention any discrepancy found in this specification.
No deviations shall be made without prior written authorization from Buyer.
D. Technical Requirements
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 178
a. General
b. General Requirements
d. Luminaire types and pole spacing shall be selected to achieve the required
levels of illuminance 150Watts HPS, 230Volts, IP56 and provide the most
economic installation.
F. Perimeter Lightings
a. Use shall be made of floodlights for general lighting of outdoor open areas.
Flood lighting luminaires shall be mounted at sufficient elevation and directed so
as not to be objectionable or dazzling to operating personnel. Poles structures
shall be used for mounting such floodlights, but where poles are used, safe access
and a working platform shall be provided for relamping and servicing.
b. Perimeter lighting shall be provided on all permanent area roads within the site
plot limits only when it is not possible to provide adequate illumination using area
and/or perimeter fence floodlighting.
G. Lighting Control
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 179
a. The site area lightings street and perimeters, shall be controlled relay by photo-
electric cell with manual over-ride facility.
b. Power Supply from Distribution Panel “DPNL” which are located together at the
transformer pad areas.
Drawings and documents (herein after called ‘documents’) will be issued to the
CONTRACTOR by the COMPANY for execution of the works. The CONTRACTOR shall
bring to COMPANY’S attention any discrepancy found in the documents. All works shall
be in strict accordance with the latest issue of documents, no deviation shall be made
without prior written authorization from the COMPANY.
a. The CONTRACTOR shall liaise with the COMPANY to clarify any queries
relating to the design intent and to resolve any unforeseen queries that affect the
installation prior to commencement of affected works.
I. Safety
b. CONTRACTOR shall assess work with regard to risks to the health and safety
of personnel during construction, operation and maintenance of the facilities.
Where practical the risks shall be combated at source, any residual risks remaining
are to be detailed and provided to persons affected. CONTRACTOR shall be pro-
active in raising such issues at regular site meetings to ensure that information is
provided prior to the execution of work and where appropriate it is recorded in the
Health and Safety File.
c. The CONTRACTOR shall produce a detailed method statement for each type
of work operation undertaken. The method statement shall detail the work and
identify any potential safety risks and hazards associated with the work and detail
the safety measures taken to counter them.
d. The CONTRACTOR shall ensure that at least one senior electrical employee
who is thoroughly familiar with the class and character of work to be executed is
present at the work site during all working hours.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 180
b. CONTRACTOR shall be responsible for coordination of all work with all trades.
Any conflicts and interferences shall be brought to the attention of the Owner or
Owner’s representative.
K. As-built Documentation
1. General
A. Scope
This section covers the requirements for plant materials, quality, delivery and
storage requirements.
B. Quality Assurance
All trees, shrubs, and ground covers shall have a normal habit of growth and shall
be sound, healthy, vigorous and free from insect infection.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 181
a. Delivery
b. Storage
c. Handling
c.2 Protect plant at all times from sun or drying winds. Plant that
cannot be planted immediately on delivery shall be kept in the
shade, well protected and adequately watered. All specimen, field
grownandfieldstockpalmsandtressshallbeplantedthesamedaytheyd
eliveredtothesite.
2. Products
A. Materials
Unless otherwise indicated, all furnished plants, materials shall be nursery grown,
well-branched, well-proportioned, and containing fibrous rootsystem.
C. Quantities
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 182
D. Nomenclature
Names of plants shall conform to the name generally accepted in the local nursery
trade, and as interpreted by the Landscape Architect. In all cases of disputes, the
decision of the Landscape Architect shall be final.
a. Plans required
b. Substitutions
b.1 Plants of kinds other than those named in the plant list will not be
acceptable unless specifically approved in writing by the Landscape
Architect. Proposed substitute in each case must possess the same
essential characteristics as the type of plant actually specified in regards to
appearance, ultimate height, shape habit of growth and other
requirements. Where the substitution is approved for the Landscape
Contractor’s convenience, plants of greater value may be accepted without
additional cost to theClient.
c. Special Guarantee
d. Minor Materials
3. Execution
A. Inspection
B. Conditions
Trees and shrubs shall have been grown in containers of the size stated on
drawings and/or specifications and shall have sufficient roots to hold the root ball
together after removal from containers without beingroot bound.
The minimum acceptable of the trees and shrubs measured after pruning, with
branches in normal position, shall conform to the measurement specified in the
plantlist.
Plants that meet the measurements specified but do not possess a normal
configuration or balance of height and spread will berejected.
Trees and shrubs larger in size then specified maybe used, but the use of larger
plant materials will make no changes in the contract price. Height shall not be
substituted for balanceform.
Any trees or shrub with a weak, thin trunk not capable of supporting itself when
planted in the open will berejected.
Rooted cuttings shall be healthy, vegetation materials with established roots at one
or morenodes.
C. Installation
D. Protection
The Landscape Contractor shall erect such fences or guards as required for the
protection of the public and his materials and maintain same in good repair until
the completion of the entire work under the contract.
1. General
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 184
A. Scope
This section covers complete requirements for soil preparation and soil mixes.
B. Submittals
a. Take representative soil samples from the proposed source area. Submit
sample to a recognize laboratory for analysis for requiredfertilizer.
Fertilizers shall be delivered to the site in unopened containers, each fully labeled,
conforming to the applicable fertilized laws and bearing the names of work of the
manufacturer. Properly notify Owner/ Landscape Architect in advance, the
deliveries of soil materials and mixes that will take place.
2. Products
A. Materials
a. Topsoil
Strip from, well-drained borrow area the top 10cm surface layer of fertile,
friable, natural surface soil, free of subsoil, clouds, shale, organic litter,
trash, toxic substances stones 5cm in maximum dimensions or larger, and
objectionable and hard to eradicate weeds or grasses. Neatly trim grades
for drainage topsoil borrow areas after completion of excavation. Topsoil to
possess characteristics or representative soils in the project vicinity that
produce heavy growth of crops, grass or other vegetation, and contain at
least 6% organic matter determined by loss on ignition on moisture-
freesamples.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 185
b. Commercial Fertilizer
c. Manure
Well-rooted, uncleansed animal manure, not less than 8 months and not
more than 2 years old, free of materials not acceptable for landscape use,
and not more than 25% by volume of straw, sawdust or their organic litter
material. Test material and approve for suitability; show certificates.
d. Mulch
e. Water
Free from oils, acids, alkali, salt, and other substances harmful to plant
growth. Source of water, service outlets used: subject to approval of
LandscapeArchitect.
3. Execution
a. For use in filling planter boxes, and where specified for backfilling plant
pits and beds; mix in central location on jobsite. Topsoil: thoroughly moisten
peat before mixing with soil. Mix thoroughly; ensure uniform distribution by
blade mixing, by use of soil shredder, by hand or other approved means.
c. Manually tilt the top 150m of all planting areas to evenly incorporate the
amendments into thesoil.
B. Protection
The Landscape Contractor shall erect such fences or guards as required for the
protection of the public and his material and maintain same in good repair until the
completion of the entire work under the contract.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 186
C. Clean-up
Keep all areas of work clean, neat and orderly at all times during the period of the
contract. Clean all construction areas at the end of each day.
1. General
A. Scope
B. Quality Assurance
All planting operations should be done by men experienced and qualified to do the
job.
2. Products
A. Materials
a. Burlaps
Shall be made of jute and shall weigh not less than 0.2226 kilogram per
square meter. Substitute cloth or materials shall possess an equal strength
and resistance totearing.
Shall be straight, sound, and rough sawn wood, not less than 5cm. x 5cm.
if square or 7.5m in diameter if round, and 2.50m. long or as otherwise
indicated. Cross braces on stakes: 2.5cm. x 10cm.board.
f. Screw eyes
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 187
3. Execution
B. Planting Operation
a.3 Layout of Major Planting. Mark on ground locations for plant and
outlines of areas to be planted. Seek approval of Landscape
Architect before any excavation. Plant shrubs no less than 90cm
from building line unless specifically indicated on drawings or
designated by the LandscapeArchitect.
b. Size of pits
b.2 Diameter or minimum width of pits for all shrub shall be 0.40m
greater than the diameter of the ball or the spread of the roots, if
barerooted.
b.3 Minimum depth of pits for all shrubs shall be 0.40m measured
from finished grade. Increase depth as necessary to accommodate
balls or roots and a minimum of 0.15m of compacted topsoil below
the balls orroots.
c. Setting Plants
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 188
Unless otherwise specified, plant in pits sets to such level that, after
settlement, plants will bear the same relation to the finished grade of the
surrounding ground as to the grade of the ground from which plants were
dug. Set trees plumed, rigidly placed in position until soil has been
tampered solidly around the ball or roots.
d. Balled Plants
Balled and Burlapped and balled and plat formed plant shall be place in a
minimum of 15cm compacted topsoil or prepared soil mixture, tamped prior
to placing plants. Place plants in pit, tamp topsoil or prepared soil mixture
to fill all voids under base around the ball to height of rope, wire, other
wrapping materials from under balls.
Properly spread out roots, carefully work in among roots topsoil or prepared
soil mixture as specified. Cut-off clean broken or frayed roots.
f. Container-grown plants
Immediately after planting, stake all 2.0m tall and smaller trees. Guy all
large trees asdetailed.
h. Mulching
Within 2 days after planting, place a layer of mulch materials covering entire
area around each plant to a depth of 5 to 7.5cm. if peat is used as much
material, saturate and thoroughly incorporate into top 5cm of thesoil.
C. Protection
Keep all areas work clean, neat and orderly at all times during the period of the
contract. Clean all planting areas at the end of each day.
1. General
A. Scope
2. Product
A. Materials
3. Execution
A. Application
a. Watering
Because the roots of the shrubs will not take up much water until
they became fully established in their respective location, irrigate
for long periods each time to allow water to soak down, through the
full depth of the plant hole to the roots. Do not water again until the
feeder roots have sufficient time to take up most of the moisture.
Plant native to the area will probably require less water for
establishment therefore after 4 months limit the watering to once
every otherday.
b. Fertilizing
c. Pruning
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 190
Thinning of plants will be necessary if they become too dense. Pruning
should be handled only by an expert with instructions from the
LandscapeArchitect.
1. General
A. References
B. Submittals
Submit the following in accordance with Item 2.0, Submittals. Submit within 90 days
after the contract award date and prior to commencing work on the system.
b. Shop Drawings
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 191
c. Certificates of Compliance
Submit certificates attesting that tests set forth in each applicable referenced
publication have been performed, whether specified in that publication to be
mandatory or otherwise and that production control tests have been performed at the
frequency or intervals specified in the publication. Other tests shall have been
performed within 3 years of the date of submittal of certificates on the same type,
class, grade, and size of material as is being provided for the project.
a.1 Piping
a.4 Handling
2. Material Requirements
a. Concrete Piping
a.2 Joints
Jointing shall be mortar composed of one part cement and two parts
sand.
b. Concrete Materials
c. Miscellaneous Materials
3. CONSTRUCTION REQUIREMENTS
a.1 Location
a.2 Earthwork
Inspect each pipe and fitting before and after installation; remove
those found defective from site and replace with new. Provide proper
facilities for lowering sections of pipe into trenches. Lay pipe with the
bell or groove ends in the upgrade direction. Adjust tongues in
grooves to produce a uniform space. Blocking or wedging between
tongues and grooves will not be permitted. Replace by one of the
proper dimensions any pipe or fitting that does not allow sufficient
space for proper calking or installation of joint material. At the end of
each work day, close open ends of pipe temporarily with wood blocks
or bulkheads. Provide batter boards not more than 25 feet apart in
trenches for checking and ensuring that pipe invert elevations are as
indicated. Laser beam method may be used in lieu of batter boards
for the same purpose.
b. Special Requirements
c. Concrete Work
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 195
the manhole. Cut existing pipe so that pipe ends are approximately flush with
the interior face of manhole wall, but not protruding beyond into the manhole.
Use resilient connectors as specified for pipe connectors to concrete
manholes.
f. Metal Work
The Engineer will conduct field inspections and witness field tests specified
in this section. The Contractor shall perform field tests and provide labor,
equipment, and incidentals required for testing. Be able to produce evidence,
when required, that each item of work have been constructed properly in
accordance with the drawings and specifications.
b. Pipeline Testing
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 196
Check each straight run of pipeline for gross deficiencies by holding a
flashlight beam in a manhole; it shall show a practically full circle of light
through the pipeline when viewed from the adjoining end of line.
Sewer Manhole
1. General
A. References
Material requirements, methods, procedures, testing and other related items called
for in this Section shall conform to the applicable standards of the American National
Standards Institute, (ANSI) and American Society for Testing and Materials (ASTM).
B. Scope of Work
Provide new and modify existing exterior sanitary sewer piping and
appurtenances. Construct each system complete and ready for operations.
The work for exterior sanitary sewer system includes furnishing of equipment,
materials, installation, and workmanship as specified and as shown in the
drawings.
C. Submittals
a.3 Valves
b. Shop Drawings
c. Samples
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 197
c.2 Pipe Joint Material
d. Certificates of Compliance
a.1Piping
a.2Metal Items
b. Handling
2. Material Requirements
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 198
The HDPE pipe shall have a minimum size of ɸ150mm I.D. The HDPE pipe
shall be manufactured in a plant capable of providing continuous quality
control through inspection. The facility shall have the necessary testing
equipment to verify that the pipe meets the requirements of AWWA C901 or
C906, NSF Standard #61 and ASTM standards. The facility shall have the
necessary testing equipment to verify that the fittings meet the requirements
of AWWA C901 for sizes ½” to 2” and AWWA C906 for sizes 3” through 54”.
Polyethylene pipe and fittings shall be made from resin meeting the
requirements of the Plastic Pipe Institute as PE 3608. The resin shall meet
the requirements of ASTM D 3350 with a cell classification of 345464C. Pipe
shall have a manufacturing standard of ASTM D 3035. Pipe shall be DR 11,
150psi working pressure rating (WPR), unless otherwise specified on the
plans. The pipe shall contain no recycled compounds except that generated
in the manufacturer's own plant from resin of the same specification from the
same raw material.
B. Miscellaneous Materials
b. Metal Items
b.2Manhole Steps
3. CONSTRUCTION REQUIREMENTS
a.1 Location
a.2 Earthwork
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 200
Perform earthwork operations in accordance with Section on
Earthworks.
a.3 Pipe Laying and Jointing to the Concrete Grade and Alignment
Inspect each pipe and fitting before and after installation; replace
those found defective and remove from site. Provide proper facilities
for lowering sections of pipe into trenches. Lay non-pressure pipe with
the bells and spigots will not be permitted. Replace by one of the
proper dimensions, pipe or fittings that do not allow sufficient space
for installation of joint material. At the end of each work day, close
open ends of pipe temporarily with wood blocks or bulkheads.
b. Manhole Construction
Metal Work
The Owner or his Technical Representative will conduct field inspections and
witness field tests specified in this section. The Contractor shall perform field
tests and provide labor, equipment, and incidentals required for testing. Be
able to produce evidence, when required, that each item of work has been
constructed in accordance with the drawings and specifications.
Check each straight run of pipeline for gross deficiencies by holding a lighted
flashlight in a manhole; it shall show a practically full circle of light through the
pipeline when viewed from the adjoining end of line. When pressure piping is
used in a non-pressure line for non-pressure use, test this piping as specified
for non-pressure pipe.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 202
Conduct testing from manhole to manhole or between more
than two manholes. The length of main tested shall not
exceed 200 meters.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 203
minimum of 0.6 meter above the crown of the pipe, or at least
0.6 meter above the existing groundwater whichever is higher.
When the average head on the test section is greater than 0.9
meter, the allowable leakage shall be multiplied by the ratio of
the square root of the average test head and the square root
of the base head of 0.9 meter.
Water Distribution
1. General
The publications listed below form a part of this specification to the extent referenced. The
publications are referred to in the text by the basic designation only.
A. REFERENCES
B. DESIGN REQUIREMENTS
C. SUBMITTALS
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 204
a. Submittals
a.3 Valves
a.4 Hydrants
a.3. Samples
a.4.3Valves
a.4.4Fire hydrants
Certificates shall attest that tests set forth in each applicable referenced
publication have been performed, whether specified in that publication to be
mandatory or otherwise and that production control tests have been
performed at the intervals or frequency specified in the publication. Other
tests shall have been performed within 3 years of the date of submittal of
certificates on the same type, class, grade, and size of material as is being
provided for the project.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 205
Inspect materials delivered to site for damage. Unload and store with
minimum handling. Store materials on site in enclosures or under protective
covering. Store plastic piping and jointing materials, and rubber gaskets under
cover out of direct sunlight. Do not store materials directly on the ground.
Keep inside of pipes and fittings free of dirt and debris.
b. Handling
2. Material Requirements
A. Piping Materials
the necessary testing equipment to verify that the fittings meet the
requirements of AWWA C901 for sizes ½” to 2” and AWWA C906 for
sizes 3” through 54”.
Polyethylene pipe and fittings shall be made from resin meeting the
requirements of the Plastic Pipe Institute as PE 3608. The resin shall
meet the requirements of ASTM D 3350 with a cell classification of
345464C. Pipe shall have a manufacturing standard of ASTM D 3035.
Pipe shall be DR 11, 150psi working pressure rating (WPR), unless
otherwise specified on the plans. The pipe shall contain no recycled
compounds except that generated in the manufacturer's own plant
from resin of the same specification from the same raw material.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 206
Material ASTM D 1248 III C 5 P34
Classification
Slow Crack
Growth
a.2 Fittings
a.3 Installation
After a section of pipe has been lowered into the prepared trench
and immediately before joining the pipe, the ends of the pipe to be
joined shall be cleaned, and the rubber gasket lubricated, with a
vegetable compound soap all in accordance with the pipe
manufacturer’s instructions. Assembly of the pipe lengths shall be
in accordance with the recommendations of the manufacturer of the
type of joint used. All special tools and appliance required for joining
the pipe shall be provided by the Contractor. When cutting or
machining of the pipe is necessary, only tools and methods
recommended by the pipe manufacturer and approved by the
Engineer shall be employed.
Mass shall be Lead Free with 90% virgin K-65 grade PVC
resin conforming to PNS 65 and ISO 4422.
b.1.2 Installation
c.1 Material
c.2 Installation
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 208
operated to thoroughly flush the service and remove any
accumulated air present prior to the hydrostatic test.
d. Service Saddle
d.1 Material
All parts of the service saddle including the clamp or strap shall
comply with the following minimum thickness requirements:
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 209
12 mm (1/2-in). The tapping thread shall be at least 30 mm deep
and drilled in accordance with iron pipe (I.P.) thread dimensions.
a. Gate Valves
c. Check Valves
d. Fire Hydrant
Wet-barrel type hydrant. Wet barrel type hydrants shall conform to AWWA
C503 or to UL 246, "Wet Barrel" design, and shall have 6-inch inlet, one 4
1/2-inch pumper connection, and two 2 1/2-inch hose connections. Pumper
connection and hose connections shall be individually valved with
independent nozzle gate valves. Inlet shall have mechanical-joint or push-on
joint end, except where flanged end is indicated; end shall conform to the
applicable requirements as specified for the joint. Size and shape of
operating nut, cap nuts, and threads on hose and pumper connections shall
be as specified in AWWA C502 or AWWA C503 or UL 246 or as indicated.
Hydrants indicated as "traffic type," shall have frangible sections as
mentioned in AWWA C502 or breakable features as mentioned in AWWA
C503. Traffic type hydrant shall have special couplings joining upper and
lower sections of hydrant barrel and upper and lower sections of hydrant stem
and shall be designed to have the special couplings break from a force not
less than that which would be imposed by a moving vehicle; hydrant shall
operate properly under normal conditions.
Provide a valve box for each gate valve on buried piping. Valve boxes
shall be of cast iron or precast concrete of a size suitable for the valve
on which it is to be used and shall be adjustable. Provide a round
head. Cast the word "WATER" on the lid. The least diameter of the
shaft of the box shall be 5 1/4 inches. Each cast-iron box shall have
a heavy coat of bituminous paint.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 211
AWWA C111/A21.11. Bolts shall be track-head type; bolts and nuts
shall be either of the following: bolts conforming to tensile
requirements of ASTM A307, Grade A, with nuts conforming to tensile
requirements of ASTM A563, Grade A; or round-head square-neck
type bolts conforming to ANSI B18.5 with hex nuts conforming to
ANSI B18.2.2. Bolts shall be 5/8 inch in diameter; Bolts hole in
follower rings shall be of a shape to hold fast the necks of the bolts
used. Do not use mechanically coupled joints using a sleeve-type
mechanical coupling as an optional method of jointing except where
pipeline is adequately anchored to resist tension pull across the joint.
The valve shall conform to Class 150B, AWWA C504, short or long
bodies with standard split V-type packing or "O" ring seals.
Tracer wire shall be bare copper or aluminum wire not less than 0.10
inch in diameter, provided in sufficient length to be continuous over
each separate run of nonmetallic pipe.
3. Construction Requirements
A. Installation of Pipelines
a.2 Earthwork
Remove fins and burrs from pipe and fittings. Before placing in
position, clean pipe, fittings, valves, and accessories and maintain in
a clean condition. Provide proper facilities for lowering sections of
pipe into trenches. Do not under any circumstances drop or dump
pipe, fittings, valves, or other water line material into trenches. Cut
pipe accurately to length established at the site and work into place
without springing or forcing. Replace by one of the proper lengths
any pipe or fitting that does not allow sufficient space for proper
installation of jointing material. Blocking or wedging between bells
and spigots will not be permitted. Lay bell-and-spigot pipe with bell
end pointing in the direction of laying.
Grade pipeline in straight lines; avoid formation of dips and low points.
Support pipe at proper elevation and grade, and secure firm, uniform
support. Wood support blocking will not be permitted. Lay pipe so
that full length of each section of pipe and each fitting will rest solidly
on the pipe bedding; excavate recesses to accommodate bells, joints,
and couplings. Provide anchors and supports where indicated and
where necessary for fastening work into place. Make proper provision
for expansion and contraction of pipelines. Keep trenches free of
water until joints have been properly made. At the end of each work
day, close open ends of pipe temporarily with wood blocks or
bulkheads. Do not lay pipe when conditions of trench or weather
prevents installation.
Install a continuous length of tracer wire for full length of each run of
nonmetallic pipe. Attach wire to top of pipe in such manner that it will
not be displaced during construction operations.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 213
After approval is obtained, make connections to existing water lines
with a minimum interruption of service on the existing line. Make
connections in accordance with the recommended procedures of the
manufacturer of the pipe being tapped.
Where service lines are located under the roadbeds or in stony or rocky
ground, sand bedding shall be provided. The sand bedding shall be of
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 214
adequate thickness to provide a depth of cover of 0.15 m. Unless otherwise
directed, all service lines shall be installed prior to the hydrostatic test of the
water main, and they shall be tested with pressure test of the water main.
Each stop cock valve shall be operated to thoroughly flush the service and
remove any accumulated air present prior to the hydrostatic test.
d. Disinfection
Flush and disinfect new potable water lines and affected portions of existing
potable water lines in accordance with AWWA C651. Apply chlorine by the
continuous feed method.
The Engineer will conduct field inspections and witness field tests specified
in this section. The Contractor shall perform field tests, and provide labor,
equipment, and incidentals required for testing. The Contractor shall produce
evidence, when required, that any item of work have been constructed
properly in accordance with the drawings and specifications. Do not begin
testing on any section of a pipeline where concrete thrust blocks have been
provided until at least 5 days after placing of the concrete.
b. Testing Procedure
Test water mains and water service lines in accordance with the applicable
specified standard, except for the special testing requirements given in
paragraph entitled "Special Testing Requirements." Test ductile-iron water
mains in accordance with the requirements of AWWA C600 for hydrostatic
testing. The amount of leakage on ductile-iron pipelines with mechanical
joints or push-on joints shall not exceed the amounts given in AWWA C600;
no leakage will be allowed at joints made by any other method.
For pressure test, use a hydrostatic pressure 50 psi greater than the
maximum working pressure of the system, except that for those portions of
the system having pipe size larger than 2 inches in diameter, hydrostatic test
pressure shall be not less than 150 psi. Hold this pressure for not less than
2 hours. Prior to the pressure test, fill that portion of the pipeline being tested
with water for a soaking period of not less than 24 hours. For leakage test,
use a hydrostatic pressure not less than the maximum working pressure of
the system. Leakage test may be performed at the same time and at the
same test pressure as the pressure test.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 215
1. Fire Hydrants shall be installed in accordance with Philippine Mechanical Code, NFPA,
Local Authority & etc.
4. Fire Hydrant shall be class c or equivalent, max 80 deg C, pillar type, meets or exceed
ANSI/AWWA C502 or equal.
5. Fire Hydrant shall have external & internal corrosion protection with high quality coating
capable to high exposed to weather condition.
6. Fire Hydrants supply with standard key tools compatible to BFP standard with chain lock.
8. Fire Hydrant outlet connection shall be facing directly into BFP access road ways.
1. General
A. Scope
a. This specification prescribes the technical requirements for street and perimeter
lightings required for operation on a 3-phase, 4-wire, 60 Hz solidly earthed system.
c. Lightings shall furnish any special tools for installation and maintenance.
B. References
The Street and Perimeter Lightings and associated materials shall conform to
relevant IEC standards. Each publication shall be the latest revision and
addendum in effect on the date this specification is issued for purchase, unless
noted otherwise. Except as modified by the requirements specified herein or the
details of the drawings, as a minimum, Work included in this specification shall
conform to the applicable provisions of these publications.
C. Service Conditions
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 216
b. Street and Perimeter Lightings will be installed in outdoor concrete pad in a Phil
Air Force security fencing of Phil Air Force facilities area, less than 100 meters
above sea level. The atmosphere is highly corrosive. The ambient temperature
varies between -100C and +450C. Relative humidity reaches 95% at 350C.
b.1 Satisfactory performance without any damage of any kind to any part
of street for an average temperature of and perimeter lights 350C and
maximum of 450C.
b.2 Satisfactory performance without any damage of any kind to any part
of street and perimeter lights for an average temperature of -50C and
minimum of -150C.
c. Seller shall bring to Buyer’s attention any discrepancy found in this specification.
No deviations shall be made without prior written authorization from Buyer.
D. Technical Requirements
a. General
b. General Requirements
d. Luminaire types and pole spacing shall be selected to achieve the required
levels of illuminance 150Watts HPS, 230Volts, IP56 and provide the most
economic installation.
F. Perimeter Lightings
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 217
a. Use shall be made of floodlights for general lighting of outdoor open areas.
Flood lighting luminaires shall be mounted at sufficient elevation and directed so
as not to be objectionable or dazzling to operating personnel. Poles structures
shall be used for mounting such floodlights, but where poles are used, safe access
and a working platform shall be provided for relamping and servicing.
b. Perimeter lighting shall be provided on all permanent area roads within the site
plot limits only when it is not possible to provide adequate illumination using area
and/or perimeter fence floodlighting.
G. Lighting Control
a. The site area lightings street and perimeters, shall be controlled relay by photo-
electric cell with manual over-ride facility.
b. Power Supply from Distribution Panel “DPNL” which are located together at the
transformer pad areas.
Drawings and documents (herein after called ‘documents’) will be issued to the
CONTRACTOR by the COMPANY for execution of the works. The CONTRACTOR shall
bring to COMPANY’S attention any discrepancy found in the documents. All works shall
be in strict accordance with the latest issue of documents, no deviation shall be made
without prior written authorization from the COMPANY.
a. The CONTRACTOR shall liaise with the COMPANY to clarify any queries
relating to the design intent and to resolve any unforeseen queries that affect the
installation prior to commencement of affected works.
I. Safety
b. CONTRACTOR shall assess work with regard to risks to the health and safety
of personnel during construction, operation and maintenance of the facilities.
Where practical the risks shall be combated at source, any residual risks remaining
are to be detailed and provided to persons affected. CONTRACTOR shall be pro-
active in raising such issues at regular site meetings to ensure that information is
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 218
provided prior to the execution of work and where appropriate it is recorded in the
Health and Safety File.
c. The CONTRACTOR shall produce a detailed method statement for each type
of work operation undertaken. The method statement shall detail the work and
identify any potential safety risks and hazards associated with the work and detail
the safety measures taken to counter them.
d. The CONTRACTOR shall ensure that at least one senior electrical employee
who is thoroughly familiar with the class and character of work to be executed is
present at the work site during all working hours.
b. CONTRACTOR shall be responsible for coordination of all work with all trades.
Any conflicts and interferences shall be brought to the attention of the Owner or
Owner’s representative.
K. As-built Documentation
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 219
Sewage Treatment Plant 3 - Process Design, Electromechanical Works, Start-up and
Commissioning of Wastewater Treatment Plant - (HOSPITAL 80 CMD)
1729.1 Description
This Item covers the provision and installation of a complete modular Sewage Treatment Plant
(STP) using Sequential Batch Reactor (SBR) Treatment System.
The proposed treatment is the Sequential Batch Reactor (SBR) aerobic biological system, an
established activated sludge biological cleaning system for all types of Sewage. This treatment
option adapts well to changing and increasing sewage load by changing the cycle periods and
characteristics without the necessity of any new constructions. Ongoing discharge does not
interfere with the settlement of sludge during the liquid/sludge separation process. As a result,
the separation of sludge from cleansed liquid can be achieved at a faster rate, and more efficiently
compared to a settlement tank in a continuous flow system. Treatment system includes (1)
Combined Pre-treatment Process, (2) Secondary Dynamic (SBR) Treatment Process, (3)
Disinfection Process, (4) Aerobic Sludge Digestion Process, (5) Sludge Dewatering
Process.
Minimum performance standards required for (SBR) aerobic biological System are:
The proposed treatment required with effluent complying with DENR Standards (DAO 2016- 08)
for SB (Sec. 1-Fishery Water Class 11, Sec. 2-Tourism Zones, Sec.3-Recreational Water Class
I) for Marine Waters. Also, RA 9275 otherwise known as the Philippine Clean Water Act.
The objective of combined preliminary treatment is the removal of coarse solids, grit, grease and
other large materials often found in raw Sewage. Removal of these materials is necessary to
enhance the operation and maintenance of subsequent treatment units.
Equipment to use shall include: (1) Combined Pre-Treatment Unit with degreasing and grit
removal process, (2) Manual Bar Fine Screen, (3) Influent Non-contact Doppler Flowmeter, (4)
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 220
Equalization Submersible Non-Clog Channel Type Transfer Pump with Cutter, (5) Equalization
Wide Band Coarse Bubble Diffusers.
The objective of secondary treatment process is the further treatment of the effluent from primary
treatment to remove the residual organics and suspended solids. In most cases, secondary
treatment follows primary treatment and involves the removal of biodegradable dissolved and
colloidal organic matter using aerobic biological treatment system. Activated Sludge System is
the biological treatment system employed in the existing sewage treatment
plant.
This process includes Dynamic Sequential Batch Reactor (SBR) Process, the pre-treated Sewage
will now be treated in a biological treatment process called Dynamic SBR. Dynamic SBR
incorporates two (2) hydraulic cycle control features that allow you to operate the system in two
(2) basic process modes: Nitrification and De-nitrification. The simple cycle provides half the cycle
for aeration and treatment of the sewage and total of two (2) hours for settle and decant. The
cycles are staggered so one (1) blower can provide air to a pair of basins while ensuring that only
one (1) basin is aerated at any time. If nutrient removal is required, the cycle time is extended to
provide time for anoxic periods to allow de-nitrification and Biochemical Oxygen Demand (BOD)
removal. The continual feed provides BOD at all times to provide good de-nitrification rates at all
points in the cycles and optimize nitrogen removal.
This process requires the use of (1) SBR Air Motorized Valve, (2) SBR Turbo Air Blower, (3) SBR
Waste Sludge Non-Clog Submersible Pump, (4) SBR Fine Bubble Diffusers, (5) Floating Decanter
wi motorized valve, (6) Decanter Motorized Valve, (7) Decanter Air Solenoid Valve and (8)
Dissolve Oxygen (DO) Meter.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 221
Table 1729.2 - Secondary Treatment - Dynamic SBR Process
Name of Thickness / Valid Values Conforming Standard /
No.
Equipment Sizes Class Others Design Code
Min. 152.4 mm Ductile Iron A536- ISO 12238, Pneumatic fluid power-
SB Air 0.024kW, 220V, 1 Ph,
1 Dia., DN600, 10 65-42-15 Epoxy Directional Control Valves –
Motorized Valve 60 Hz
bar Painted Measurement of shifting time.
Casing Aluminum
ISO 1940, Mechanical vibration -
SBR Turbo Air 21.29 m3/min @ AL 365, Impeller AL 22.4 kW, 440V, 3P,
2 Balance quality requirements for rotors
Blowers 500mbar 7075 Shaft Ti Alloy, 60Hz
in a constant state
Bearing Ni Alloy
Body Cast Iron
SBR Waste Min. 76.2 mm Dia National Electric Code (NEC) or
FC250, Motor Shaft
3 Sludge Non-Clog Bore or as per 2.2 kW, 440V, 3P, 60Hz National Fire Protection Association
Stainless Steel
Submersible Pump design capacity (NFPA) 70
SUS42OJ2
Min. 304,8 mm Polytetrafluoro-
SBR Fine Bubble US Patents 7,674,514; 7,398,499 and
4 DISC or as per ethylene (PTFE) --
Diffusers 6,811,148
design capacity Coated Membrane
Floating Decanter As per design Stainless Steel AISI
5 -- SS AISI 304 or 316
w/ motorized valve requirements 304 or 316
Min. 355.6 mm
Ductile Iron A536- ISO 12238, Pneumatic fluid power-
Decanter Dia. or as per 0.024kW, 220V, 1P,
6 65-42-15 Epoxy Directional Control Valves -
Motorized Valve design 60Hz
Painted Measurement of shifting time
requirements
Underwriters Laboratories Inc., NEMA,
IEEE, and other industrial standards
Min 25.4 mm Dia. Brass for Body,
Decanter Air ASCO Class B, F and H insulation
7 or as per design Stainless for Core 0.008kW, 220V,1P,60Hz
Solenoid Valve systems are UL listed in the
requirements Tube
Recognized Component Index (yellow
book) under Guide No. OBJY2
IEC 61298-2 – Process measurement
and control devices - General methods
Dissolve Oxygen 0-20 mg/L
8 PVC 0.01kW, 220V, 1P, 60Hz and procedures for evaluating
(DO) Meter (1pcjtank)
performance – Part 2 at nominal
operating conditions
The decanted Sewage from the SBR basins will be disinfected using Ultraviolet (UV) Disinfection
Process. This process will instantaneously neutralize microorganisms as they pass through
ultraviolet lamps submerged in the effluent. Treated effluent from the system will be discharged
to the storm drainage or nearest body by gravity. UV Sterilizer and Effluent Flow meter will be
required on this process.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 222
The excess sludge requires treatment to reduce its water and organic content and to obtain a
stabilized product suitable for end-use or final disposal. Waste sludge generated from the SBR
tank shall be stored and treated by means of biological process called Aerobic Digestion.
Aerobic digestion is a method of sludge stabilization wherein biodegradable organic matter
decomposed at about 50 percent - 80 percent reduction into a relative stable compound and
oxidized some cellular material into C02, H20, and N03. This process is possible by continuous
mixing and oxygenation/aeration using a blower and stainless-steel bubble diffusers.
Process requires the use of (1) Aerobic Sludge Digester (ASD) Wide Band Coarse Bubble
Diffusers, (2) ASD Non-Clog Submersible Transfer Pump/Screw Press Feed Pump, (3) ASD Air
Blower.
The stabilized and digested sludge from the aerobic sludge digester will be pumped to the
proposed dewatering facility. The dewatering press to be used is combination of thickener and
dewatering press which is known as Volute Screw Press. Volute Dewatering Press eliminates the
need for a thickener, sludge storage, or separate dosing facilities. One (1) duty unit of Volute
Dewatering Press will be provided. The existing Sludge Drying Bed will serve as standby unit in
case the Volute dewatering press is out for maintenance. 2.5 g - 3.0 g polymer/kg of dry solids
will be injected prior to the dewatering press using automatic polymer preparation unit to aid in
the dewatering process. The dewatered sludge cake shall have a dryness of 20 percent -25
percent. The dewatered sludge can be used as an organic fertilizer or for landfill used. This
process requires (1) Sludge reaction Loop, (2) Volute Dewatering Press, (3) Polymer Dosing
Pump, (4) Polymer Stock Solution Tank and (5) Polymer Stock Solution Tank Air Mixing.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 223
Polymer Stock As per design Republic Act 9003 or the "Ecological
4 Polyethylene --
Solution Tank requirements Solid Waste Management Act of 2000”
Min. 304.8 mm
Polytetrafluoroethylene
Polymer Solution DISC or as per US Patents 7,674,514; 7,398,499 and
5 (PTFE) Coated --
Tank Air Mixing design 6,811,148
Membrane
requirements
The anticipated odor management will comply with government regulations. The facility will
comply with ISO (International) and DIN (German) standards acceptable to even areas in close
proximity to residential areas, where odor emissions standards are stricter. Principals of odor
management are: (1) No odor is emitted from operations with natural ventilation; malodorous
Sewage is encapsulated in airtight operations. (2) Reliable equipment and backup equipment are
provided.
All manufacturing of equipment process, spare parts and related fittings on this Odor Control
process must conform to the specification & standard of ISO 9001:2008 Quality System: ISO
7005-2, 10631, 185, 1083, 5922, 5752. International standard NSF/ANSI 61 (NSF-61).
For every process of the Sewage treatment plant, there is a corresponding mechanical piping,
valves and fitting & structural/mechanical supports to insure the proper process flow of the
system. All piping materials associated with the pumping unit with its fittings shall flange to PN 10
or greater in accordance with ISO 7005-2. Disconnection of the major items of plant shall use
sufficient flanges and unions in order not to disturb the main piping works. Adequate pipe support
must be installed to allow for the removal of any section of pipework during maintenance.
Adequate clamping and guides shall be always being designed and available during construction.
All manufacturing of equipment process, spare parts and related fittings on this SBR mechanical
piping, valves, fittings and supports process must conform to the specification & standard of ISO
9001:2008 Quality System: ISO 7005-2, 10631, 185, 1083, 5922, 5752. International standard
NSF/ANSI 61 (NSF-61), Standard Specification of ASTM: A-48, A-536, A-36, A-27, A-153, A-234,
B-62, 02751, 02661-08, F409-02. Standard Specification of AWWA: C203, C504.
SBR sewage treatment control system based on PLC is introduced to put forward the
technological process and control requirements, the system introduces the composition principle
of the system and the PLC selection and allocation of resources, but also gives a flow chart of
PLC program composition and related settings, demonstrates the SBR sewage treatment method
of PLC control advantages compared with the traditional sewage treatment method.
The SBR manufacturer creates a plant-specific PLC to operate the SBR within specific
parameters for a specific treatment plant. The PLC operates all flows, aeration, valves, timers,
lights, in fact, the entire process. The PLC computer tells the SBR when to switch from one
treatment stage to the next. Once the PLC is on-line and properly programmed, the process
requires little outside input.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 224
All manufacturing of equipment process, spare parts and related fittings on this SBR Electrical,
PLC Programming & Instrumentation must conform to the specification & standard of ISO
9001:2008 Quality System: ISO 7005-2, 10631, 185, 1083, 5922, 5752.
All components of the sewage treatment system such as tanks, pumps, valves, motors/controls
and other similar equipment and appurtenances shall be located and so installed to meet the
requirements for sanitary protection of water quality, hydraulics of the system and protection
against interruption of service by fire, flood or any other hazard. In this case, all equipment shall
be elevated at least 16 cm above finished grade and all floors shall drain in such manner that the
quality of the treated water will not be endangered. Electrical controls shall be located above
grade.
All its construction & installations shall be in accordance complying with the specification &
standard set of by ISO 9001:2008 Quality System, National Building Code of the Philippines
(NBCP PD 1096) and its IRR, House Bill 3565-2016.
The Sewage treatment system shall deliver the required treated sewage quality based on RA
9275 otherwise known as the Philippine Clean Water Act as described in Water Quality Guidelines
(WQG) and General Effluent Standards (GES) for Water Environment standard parameters set
forth standards devised by the Philippine National Standards (PNS) prescribed by the Department
of Environment and Natural Resources (DENR) regulations.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 225
(a) Samples shall be taken from 9:00 AM to 4:00 PM
(b) The natural background temperature as determined by Environment Management Bureau (EMB)
shall prevail if the temperature is lower or higher than the WQG; provided that the maximum
increase is only up to 10 percent and that it will not cause any risk to human health and the
environment.
Note: (c) Unless otherwise specified, the above parameters are expressed as total metals.
Aldrin mg/L 0.03 0.03 n/a n/a n/a n/a n/a n/a n/a
Chlordane mg/L 0.2 0.2 n/a n/a n/a n/a n/a n/a n/a
Oichlorodiphenyltrichloroethane mg/L 1 1 n/a n/a n/a n/a n/a n/a n/a
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 226
(DDT) mg/L n/a n/a n/a n/a n/a n/a n/a
Dieldrin mg/L 0.03 0.03 n/a n/a n/a n/a n/a n/a n/a
Endrin mg/L 0.6 0.6 n/a n/a n/a n/a n/a n/a n/a
Heptachlor mg/L 0.03 0.03 n/a n/a n/a n/a n/a n/a n/a
Lindane mg/L 2 2 n/a n/a n/a n/a n/a n/a n/a
Methoxychlor mg/L 50 50 n/a n/a n/a n/a n/a n/a n/a
Toxaphene mg/L 4 4 n/a n/a n/a n/a n/a n/a n/a
Notes:
CAS - Chemical Abstracts Service
IUPAC - International Union of Pure and Applied Chemistry
MBAS - Methylene Blue Active Substances
mg/L - microgram per liter
(d) Polychlorinated Biphenyls (PCBs) include nine Aroclors and 19 individual PCB congeners described below:
(e) Phenols include 2-chlorophenol, 2,4-dichlorophenol, and 2,4,6 trichlorophenol
(f) When monitoring for Class AA and A waters, the individual organochlorine pesticides shall be monitored. For Class B, C, 0, SA,
SB, SC and SO; Total Organochlorine Pesticides shall be monitored, which refers to the organochlorine pesticides listed in Table 0.6
plus Benzene Hexachloride (BHe) (a,B,8,y), 4,4' Dichlorodipheyldichloroethane (ODD), 4,4' Dichlorodiphenyldichloroethylene (DOE),
Endosulfan (I,) I, and sulfate).
The quantity to be paid for will be measured as per individual process detailed below in tabulation
for the complete Sewage Treatment Plant (STP) system as furnished on site and in accordance
with this design standard, specifications and as accepted by the Engineer.
The accepted quantity, measured as prescribed in Section 1729.4 shall be paid for at the Contract
Unit Price/set/process for Sewage Treatment Plant System which price and payment shall be full
compensation for furnishing all materials, including labor, equipment, tools and incidentals
necessary to complete the work prescribed in this Item.
TECHNICAL SPECIFICATIONS
Site Development of the 65-Hectare in New Clark City
Page 227