Professional Documents
Culture Documents
Industrial Engg (MSQ)
Industrial Engg (MSQ)
SY
Q.1 Two alternative methods can produce a product. (d) In ABC analysis, C items having highest
Method I has a fixed cost of Rs. 3000 and consumption value.
variable cost of Rs. 25 per piece. Method II has Q.2 Consider the following statements regarding
fixed cost of Rs. 2500 and a variable cost of Harris Wilson Inventory Model.
Rs. 30 per piece. The correct option(s) is(are): GATE 2021 Workbook (a) With increase in number of orders, holding
(a) Break even quantity between two alternative cost decreases.
is 100 units.
EA
(b) If the product to be produced is 200 units,
then process I should be selected.
(c) If the product to be produced is 50 units,
then process I should be selected.
(d) If the product to be produced is 100 units,
(b) With increase in order quantity, the number
of orders increases.
(c) At break even point of inventory, ordering
cost becomes equal to holding cost.
(d) If annual demand is doubled and holding
rate is halved, EOQ remains unchanged.
then process II should be selected. Which of the above statements is(are) not
Q.2 Which of the following statements is(are) correct correct?
E
regarding Break Even Analysis? Q.3 An item is produced at the rate of 30 items per
(a) Advertisement cost increases with increase day and demand occurs at the rate of 20 items
in volume of production. per day. If the set up cost is ` 200 per set up
•
Q.2 Consider the following statements regarding Q.2 Which of the following are correct regarding
sequencing. range of forecasting method’s?
(a) Average number of jobs in system will be (a) Delphi method is used for short range of
SY
least for shortest processing time (SPT) rule. forecasting.
(b) Fulkerson’s Rule is used to solve N jobs on (b) In Delphi approach, decision making is
two machine problems. based on expert opinion.
(c) Average Tardiness will be the least for (c) Delphi method is the type of Qualitative
Earliest due date (EDD) rule. technique.
(d) Earliest due date (EDD) rule gives minimum (d) Coefficient of correlation is found in Delphi
•
average job flow time. technique for decision making.
Which of the above statements are correct?
A
5
B
4
5
E
5
8
H
EA GATE 2021 Workbook
Q.1
Chapter 5.
Line Balancing
Which of the following options is(are) correct for
4 line balancing?
C
F 10
0 10 (a) In an assembly line, the cycle time is
3 8
determined by fastest work station from all
D G
E
7 work stations.
Activity time (in weeks) is given on the arrow. (b) Assembly line balancing increases
Which of the following statement are correct? productivity.
(a) The earliest expected time of the project is (c) Assembly line balancing increases in
AD
(c) The earliest expected time of the completion found as: Balance delay = 1 – Line
GATE 2021 Workbook
service rate for stable system. The correct option(s) is/are _________.
(b) If the arrivals are completely random, the (a) The minimum initial transportation cost using
probability distribution of number of arrival Vogel’s approximation method is ` 800.
SY
in a given time follows Poisson distribution. (b) The minimum initial transportation cost using
(c) In the Kendall’s notation for representing North West corner rule is ` 1000.
(c) The solution from Vogel’s approximation
queuing model, the first position represents
method is degenerate solution.
probability law for the service.
(d) This problem is the case of balanced
(d) If the number of arrival in a queue follows • transportation problem.
the Poisson distribution, then the inter arrival
time obeys exponential law.
LPP, Transportation and Assignment Q.4 A furniture maker has 6 units of wood and 2
GATE 2021 Workbook
SY
Material Requirement Planning production plans whereas expediting
Q.1 Which of the following is/are correct for the maintains then and sees them through to
Material Requirement Planning (MRP)? their successful completion.
(a) Bills of material schedule is one of the input (c) Routing in production planning and control
of the MRP. refers to the progress of work performed.
(b) Product structure is the input of Bills of (d) Huge Aircraft manufacturing is an example
•
of fixed position layout.
material.
EA
(c) MRP is done before master production
scheduling.
(d) MRP inventory status file contains material
on hand, planned order and planned order
release.
GATE 2021 Workbook
•
GATE 2021 Workbook
M