Professional Documents
Culture Documents
Working Paper On Interconnection
Working Paper On Interconnection
Technical Department
******
September 14, 2021
Working Paper
BACKGROUND:
Power
Voltage Level Responsibility of Interconnection
Purchaser
132 kV or below DISCO DISCO
NTDC or DISCO
132 kV CPPA-G
* In any case, DISCO shall operate & maintain
Below 132 kV CPPA-G DISCO
220 kV or above CPPA-G NTDC
ii. NEPRA (Interconnection for Renewable Generation Facilities) Regulations 2015:
As per amendment in Interconnection Regulations vide SRO 730(I)/2018, the Authority
allowed renewable energy project to construct, own and operate specifically 33 kV and
66 kV transmission line after seeking Special Purpose Transmission License from
NEPRA. The subject amendment is reproduced below (F/C):
Provided that the renewable energy project shall construct, own, maintain and operate
the aforementioned transmission line and shall obtain a Special Purpose Transmission
license.’
4. In compliance with the above directions of the Authority, other relevant documents have
also been reviewed which revealed the following provisions in the subject matter:
a. The transmission line & interconnection with the grid from the power complex to
the grid will be built by the company and transferred to the power purchaser,
who will then own and operate the transmission line.
b. The transmission line & interconnection with the grid from the power complex to
the grid will be built by the power purchaser and the Sponsors jointly and will
then be transferred to the power purchaser, who will then own and operate the
transmission line;
ii. PPIB’s Policy Frame Work for Private Sector Transmission Line Projects, 2015:
PPIB notified Policy Framework for investors interested for investment in the field of AC
and DC Extra High Voltage (EHV) Power Transmission Lines, Substations and convertor
stations. Whereas EHV is defined to mean 220 kV and above voltage level. The salient
features of Policy Framework are listed below (F/E):
a. The list of EHV transmission line projects to be offered to private sector for
bidding will be prepared by GOP.
b. The transmission line projects would be offered in BOOT basis for 25 years term
after which they will be transferred to NTDC.
c. International Competitive Bidding (ICB) will be carried out for processing and
award of projects.
OBSERVATIONS:
5. While reviewing the aforementioned relevant documents, the following has been
observed:
i. As per Section 18B of NEPRA Act, the Provincial Grid Companies (PGCs) are
authorized to provide transmission interconnection services to national grid company and
others wherever necessary. The Section 18B is reproduced below:
ii. NEPRA (Interconnection for Renewable Generation Facilities) Regulations 2015 allows
renewable energy projects to construct, own, operate and maintain interconnection lines
of 33 kV and 66 kV after getting SPTL from NEPRA.
iii. Power Generation Policy 2015 also provides options for construction of interconnection
facilities either by power Generation Company or by Power Purchaser & Sponsors
jointly.
iv. PPIBs policy frame work for private sector transmission lines is applicable for
construction of transmission lines operating at 220 kV AC/DC and above voltage levels.
However, list of such lines offered to private sector shall prepared by GOP and awarded
to investor through International Competitive Bidding.
RECOMMENDATIONS:
6. In view of foregoing, it is proposed that following amendments in NEPRA
(Interconnection for Renewable Generation Facilities) Regulations, 2015 and NEPRA
Interconnection Guidelines, 2015 are proposed for construction of interconnection facilities:
Provided that wherever the interconnection facilities and transmission lines will
be constructed by power Generation Company, the same shall be transferred to
power purchaser for operation and maintenance.
ii. The Provincial Grid Company, under Section 18B, may provide interconnection
and transmission services to the National Grid Company and others, wherever
necessary, at NEPRA’s determined rates, charges and terms & conditions.
DECISION SOLICITED:
(Irfan Yousuf)
Consultant (RE)