Professional Documents
Culture Documents
Dhanushadham Municipality Building Estimate Revise +boundary Wall 0520
Dhanushadham Municipality Building Estimate Revise +boundary Wall 0520
SUMMARY OF COST
Project:
Location :
Year : 077/078
Item No. Description Estimate Amount (NRs.) % Remarks
1 PART 1-BUILDING
A Civil Works: COMPOUND WALL 16,378,109.15 39.51%
B Civil Works: GROUND FLOOR 6,057,452.20 14.61%
C Civil Works: FIRST FLOOR 13,742,622.98 33.15%
D Civil Works:TOP FLOOR 852,290.09 2.06%
Water Supply, Plumbing, Sanitary, Electrical Communication and Allied
E,F,G Works (Buildings) 4,122,734.67 9.95%
A4 RCC work
1 Providing and Laying P.C.C.(1:1.5:3) M20 for
R.C.C.work in foundation, columns, beams,
slabs etc. with cement, sand, and aggregate
including mixing with concrete mixture,
Cu.m 224.74 16297.00 3,662,619.20
compacting the concrete with vibrator machine,
laying, finishing to approved level ,lines and
dimensions and curing all complete as per
instruction of site Enginner.
A5 Reinforcement Work
Supplying & laying two coat enamel paint over Sq.m 281.54 355.00 99,947.60
1 coat primer to give uniform colouring after
rendering the surface all complete.
B9 Wood work
1
Cu.m 3.51 311688.00 1,093,994.79
Supplying and fitting sal wooden chaukose
with all neccessary hardware all complete.
2
Supplying and fitting Ready made Teak wood
Doors,special (Seasoned and Poisoned
treated ,one side teak and other side water proof Sq.m 166.58 9678.00 1,612,113.61
ply fitting) with all neccessary hardware all
complete.
B10 Iron & Steel Work
B5 Form Work
19ft water proof plywood and steel prop
formwork for all works necessary propping, Sq.m 1644.82 923.00 1,518,166.05
scaffoldong, staging, supporting inclusive of
wedging and cutting holes for utilization work
till the support is full unyielding net for
Column/Slab/Beam etc. complete work.
B6 Flooring & Finishing work
1 38 mm thick P.C.C. flooring (Screeding) in
(1:2:4) for floors & top of slab with approved
quality of cement, sand & crushed stone Sq.m 687.76 739.00 508,255.31
chips/aggregate including mixing,laying,curing
and finishing with a floating coat of neat
cement slurry.
2 3mm.thick Cement:Sand Punning (1:1) on
floor, dado and skirting etc. as per specification Sq.m 684.68 315.00 215,673.98
and direction complete work.
3
Total Cost of
13,742,622.98
Roof =
C Civil Works: TOP FLOOR
C1 Masonry Works
Brickwork in 1:4 (cement:sand) mortar in
perfect line level finish including wetting the
bricks, racking the joints, scaffolding and Cu.m 15.05 15803.00 237,811.05
curing the work for at least 7 days all complete.
C2 RCC work
Providing and Laying P.C.C.(1:1.5:3) M20 for
R.C.C.work in foundation, columns, beams,
slabs etc. with cement, sand, and aggregate
including mixing with concrete mixture,
Cu.m 12.73 16297.00 207,436.23
compacting the concrete with vibrator machine,
laying, finishing to approved level ,lines and
dimensions and curing all complete as per
instruction of site Enginner.
C3 PCC work
Providing and Laying Plain Cement Concrete
( P.C.C.) (1:1.5:3) M20
(cement:sand:aggregate) for R.C.C. work in
Sill & Lintel band including mixing, laying, Cu.m 0.42 16297.00 6,907.70
finishing to approved level, line and dimensions
and curing all complete as per specification.
C4 Form Work
A2 Masonry Works
Providing Flat brick soling with sand fillings in joints and
1
bottom.
Compound Wall
i. Footing 221 4.00 4.00 3536.00
ii. Wall Footing 1 1131.00 1.25 1413.75
Total= 4949.75 4,949.75 Sq.ft 459.85 Sq.m
A3 PCC works
Providing and Laying Plain Cement Concrete ( P.C.C.) in
(1:3:6) M10 (cement:sand:aggregate) in footing, wall
foundation and floors including mixing, laying, finishing to
approved level, line and dimensions and curing all complete as
per specification.
Compound Wall
i. Footing
F1 221 4.00 4.00 0.25 884.00
ii. Wall Footing 1 1131.00 1.25 0.25 353.44
Total= 1237.44 1,237.44 Cu.ft 35.04 Cu.m
A4 RCC work
1
Providing and Laying P.C.C.(1:1.5:3) M20 for R.C.C.work in
foundation, columns, beams, slabs etc. with cement, sand, and
aggregate including mixing with concrete mixture, compacting
the concrete with vibrator machine, laying, finishing to
approved level ,lines and dimensions and curing all complete
as per instruction of site Enginner.
Compound Wall
i. Footing
F1 221 4.00 4.00 1.00 3536.00 Uniform/rectangular part
F1 221 A1= 1.562Sq.ft A2= 16Sq.ft 0.75 1246.51 Sloped/trapezoidal part
Total = 4782.51
ii.Column
1)Upto Plinth
C1 (10"x10") 221 0.833 0.833 3.00 460.05
2)Above Plinth
C 1(10"x10") 221 0.833 0.833 7.33 1124.51
Total= 1584.56
ii. Beam
Plinth Tie Beam
(10"x10") 1 1131.00 0.833 0.833 784.79
(10"x10") 1 1131.00 0.833 0.833 784.79
Total = 1569.58
7,936.64 Cu.ft 224.74 Cu.m
A5 Reinforcement Work
Providing TMT Steel Reinforcement bars (Grade Fe500)
work including straightening, cleaning, cutting, bending,
binding with 20 SWG annealed wire & fixing in position as
per drawing, bar bending schedule for foundation, column,
beam, staircase, slab & in all R.C.C. works as per
specification, drawing.
Compound Wall
Footing 1.00% of RCC Work 10630.96
Columns 2.50% of RCC Work 8805.74
Beams 1.50% of RCC Work 5233.48
Total= 24670.18
10 % Wastage and Contingencies shall be added 2467.02
Total= 27137.19 27.14 MT 27.14 MT
A6 Form Work
19ft water proof plywood and steel prop formwork for all
works necessary propping, scaffoldong, staging, supporting
inclusive of wedging and cutting holes for utilization work till
the support is full unyielding net for Column/Slab/Beam etc.
complete work.
Compound Wall
i. Footing
F1 221 4.000 4.000 14144.00
Total= 14144.00
ii.Column
1)Upto Plinth
C1 (10"x10") 221 0.833 3.000 1104.56
2)Above Plinth
C 1(10"x10") 221 0.833 7.333 2699.907938
Total= 3804.47
ii. Beam
Plinth Tie Beam
(10"x10") 1 1131.00 0.833 1884.25
(10"x10") 1 1131.00 0.833 1884.25
Total= 3768.49
21,716.96 Sq.ft 2,017.57 Sq.m
A8 Painting work
2 Exterior Walls: Supplying & laying two coat weather proof
emulsion paint over 1 coat primer on to give uniform
colouring after rendering the surface all complete.
Compound Wall
Plastered Walls 1 2015.00 9.00 18135.00
Total= 18135.00
18,135.00 Sq.ft 1,684.80 Sq.m
First Floor
Main Wall (9") 1 1455.00 9.50 13822.50
Half wall between columns (5") 1 138.50 10.50 1454.25
Main Beam at Entry
X-Direction 1 45.84 1.16 53.17
Y-Direction 2 26.84 1.16 62.27
Deduction
Windows W-(8'6''x6') 15 8.50 6.00 -765.00
Windows W1-(7'x20') 1 7.00 20.00 -140.00
Windows W2-(8'x6') 1 8.00 6.00 48.00
Windows W3-(10'x16') 1 10.00 16.00 160.00
Windows W4-(5'x6') 2 5.00 6.00 -60.00
Ventilation V-(10'x2') 1 10.00 2.00 -20.00
Doors D-(6'x7'6") 1 6.00 7.50 -45.00
Doors D1-(4'x7'6") 15 4.00 7.50 -450.00
Doors D2-(2'6"x7') 6 2.50 75.00 -1125.00
Channel Door CD-(8'x7'6") 2 8.00 7.50 -120.00
Total= 12875.19 12,875.19 Sq.ft 1,196.14 Sq.m
2 12.5 mm thick cement:sand (1:3) plaster on Ceiling of good
finish including racking the joint, wetting of surfaces & curing
the work all complete.
B7 Painting work
1 Interior Walls: Supplying & laying two coat distemper over
1 coat primer on to give uniform colouring after rendering the
surface all complete.
Floor
Main Wall (9") 2 335.00 11.00 7370.00
Main Beam in passage
X and Y-Direction 2 36.32 1.16 84.26
Deduction
Windows W-(8'6''x6') 15 8.50 6.00 -765.00
Windows W1-(7'x20') 1 7.00 2.00 -14.00
Windows W2-(8'x6') 1 8.00 6.00 48.00
Windows W3-(10'x16') 1 10.00 16.00 160.00
Windows W4-(5'x6') 2 5.00 6.00 -60.00
Ventilation V-(10'x2') 1 10.00 2.00 -20.00
Doors D-(6'x7'6") 1 6.00 7.50 -45.00
Channel Door CD-(8'x7'6") 2 8.00 7.50 -120.00
Total= 6638.26 6,638.26 Sq.ft 616.71 Sq.m
Supplying & laying two coat enamel paint over 1 coat primer
3 to give uniform colouring after rendering the surface all
complete.
Doors Factor
Doors D-(6'x7'6") 1 6.00 2.25 7.50 101.25
Doors D1-(4'x7'6") 15 4.00 2.25 7.50 1012.50
Doors D2-(2'6"x7') 6 2.50 2.25 7.00 236.25
Windows
Windows W-(8'6''x6') 15 8.50 1.50 6.00 1147.50
Windows W1-(7'x20') 1 7.00 1.50 20.00 210.00
Windows W4-(5'x6') 2 5.00 1.50 6.00 90.00
Windows W2-(8'x6') 1 8.00 6.00 48.00
Windows W3-(10'x16') 1 10.00 16.00 160.00
Ventilation
Ventilation V-(10'x2') 1 10.00 1.25 2.00 25.00
Total= 3030.50 3,030.50 Sq.ft 281.54 Sq.m
B8 Wood work
1 Supplying and fitting sal wooden chaukose with all
neccessary hardware all complete.
Doors
Doors D-(6'x7'6") 1 21.00 X-Sec = 0.083 1.75
Doors D1-(4'x7'6") 15 19.00 X-Sec = 0.083 23.74
Doors D2-(2'6"x7') 6 16.50 X-Sec = 0.083 8.25
Windows
Windows W-(8'6''x6') 15 58.00 X-Sec = 0.08 72.47
Windows W1-(7'x20') 1 95.00 X-Sec = 0.08 7.91
Windows W4-(5'x6') 2 38.00 X-Sec = 0.08 6.33
Windows W2-(8'x6') 1 8.00 X-Sec = 0.08 0.67
Windows W3-(10'x16') 1 10.00 X-Sec = 0.08 0.83
Ventilation
Ventilation V-(10'x2') 1 24.00 X-Sec = 0.08 2.00
Total= 123.95 123.95 Cu.ft 3.51 Cu.m
2
Supplying and fitting Ready made Teak wood Doors &
Windows special (Seasoned and Poisoned treated ,one side
teak and other side water proof ply fitting) with all neccessary
hardware all complete.
Doors
Doors D-(6'x7'6") 1 6.00 7.50 45.00
Doors D1-(4'x7'6") 15 4.00 7.50 450.00
Doors D2-(2'6"x7') 6 2.50 7.00 105.00
Windows
Windows W-(8'6''x6') 15 8.50 6.00 765.00
Windows W1-(7'x20') 1 7.00 20.00 140.00
Windows W4-(5'x6') 2 5.00 6.00 60.00
Windows W2-(8'x6') 1 8.00 6.00 48.00
Windows W3-(10'x16') 1 10.00 16.00 160.00
Ventilation
Ventilation V-(10'x2') 1 10.00 2.00 20.00
Total= 1793.00 1,793.00 Sq.ft 166.58 Sq.m
B2 RCC work
1
Providing and Laying P.C.C.(1:1.5:3) M20 for R.C.C.work in
foundation, columns, beams, slabs etc. with cement, sand, and
aggregate including mixing with concrete mixture, compacting
the concrete with vibrator machine, laying, finishing to
approved level ,lines and dimensions and curing all complete
as per instruction of site Enginner.
i. Column
First Floor
C1 (1'0"x1'0") 34 1.00 1.00 9.60 326.40
Total = 326.40
ii. Beam
First Floor Beam (Main Beam)
X-Direction (1'6"x1') 1 507.00 1.00 1.50 760.50
Y-Direction (1'6"x1') 1 463.00 1.00 1.50 694.50
Total = 1455.00
iv. Slab
First Floor Slab + Top (2') 1 Total Floor Area 7437.00 0.42 3123.54
Deduction of Staircase 1 Area = 0.00 0.42 0.00
Total = 3123.54
v. Stair Case
Slab (Landing +Waist) 1 Area = 33.17 0.42 13.93
Steps 21 6.08 1.00 0.50 63.87
Total = 77.80 4,982.74 Cu.ft 141.10 Cu.m
B3 Reinforcement Work
Providing TMT Steel Reinforcement bars (Grade Fe500)
work including straightening, cleaning, cutting, bending,
binding with 20 SWG annealed wire & fixing in position as
per drawing, bar bending schedule for foundation, column,
beam, staircase, slab & in all R.C.C. works as per
specification, drawing.
Total= 18815.37 18.82 MT 18.82 MT
B4 Form Work
19ft water proof plywood and steel prop formwork for all
works necessary propping, scaffoldong, staging, supporting
inclusive of wedging and cutting holes for utilization work till
the support is full unyielding net for Column/Slab/Beam etc.
complete work.
i.Column
First Floor
C1 (1'2"x1'2") 34 4.00 9.60 1305.60
Total= 1305.60
ii.Beam
First Floor Beam (Main Beam)
X-Direction (1'6"x1') 1 507.00 1.50 760.50
Y-Direction (1'6"x1') 1 463.00 1.50 694.50
Total= 1455.00
iii. Slab
First Floor Slab
Bottom 1 Floor Area = 7437.00 7437.00
Side 1 Perimeter = 0.00 0.42 0.00
Deduction of Staircase 1 Area = 0.00 0.00
Total= 7437.00
iv.Stair Case
Slab (Landing +Waist) Bottom 1 Floor Area = 7437.00 7437.00
Sides 1 Perimeter = 22.00 0.42 9.24
Steps 20 6.08 0.50 60.83
Total= 7507.07 17,704.67 Sq.ft 1,644.82 Sq.m
First Floor
Main Wall (9") 2 508.00 10.50 10668.00
Half wall between columns (5") 2 103.00 10.00 2060.00
Parapet Wall in F.F.
Y-Direction 2 105.00 3.00 630.00
X-Direction 2 230.00 3.00 1380.00
Main Beam
X-Direction 1 23.00 1.50 34.50
Y-Direction 1 26.82 1.50 40.23
Deduction
Windows W-(8'6"x6') 15 8.50 6.00 -765.00
Windows W2-(8'x6') 1 8.00 6.00 -48.00
Windows W3-(10'x16') 1 10.00 16.00 -160.00
Windows W4-(5'x6') 2 5.00 6.00 -60.00
Ventilation V-(10'x2') 1 10.00 2.00 -20.00
Doors D-(6'x7'6") 2 6.00 7.50 -90.00
Doors D1-(4'x7'6") 6 4.00 7.50 -180.00
Doors D2-(2'6"x7') 3 4.00 7.50 -90.00
Total= 13399.73 13,399.73 Sq.ft 1,244.88 Sq.m
B7 Painting work
1 Interior Walls: Supplying & laying two coat distemper over
1 coat primer on to give uniform colouring after rendering the
surface all complete.
First Floor
Main Wall (9") 1 358.00 11.00 3938.00
C1 (1'2"x1'2") 34 4.00 9.50 1292.00
Parapet Wall in F.F.
X-Direction 2 115.00 3.00 690.00
Y-Direction 2 52.50 3.00 315.00
Main Beam in passage
X and Y-Direction 1 34.42 1.50 51.63
Deduction
Windows W-(8'6"x6') 15 8.50 6.00 -765.00
Windows W2-(8'x6') 1 8.00 6.00 -48.00
Windows W3-(10'x16') 1 10.00 16.00 -160.00
Windows W4-(5'x6') 2 5.00 6.00 -60.00
Doors D-(6'x7'6") 2 6.00 7.50 -90.00
Total= 5163.63 5,163.63 Sq.ft 479.72 Sq.m
Supplying & laying two coat enamel paint over 1 coat primer
3 to give uniform colouring after rendering the surface all
complete.
Doors Factor
Doors D-(6'x7'6") 2 6.00 2.25 7.50 202.50
Doors D1-(4'x7'6") 6 4.00 2.25 7.50 405.00
Doors D2-(2'6"x7') 3 2.50 2.25 7.00 118.13
Windows
Windows W-(8'6"x6') 15 8.50 1.50 6.00 1147.50
Windows W2-(8'x6') 1 8.00 1.50 6.00 72.00
Windows W3-(10'x16') 1 10.00 1.50 16.00 240.00
Windows W4-(5'x6') 2 5.00 1.50 6.00 90.00
Ventilation
Ventilation V-(10'x2') 1 10.00 1.25 2.00 25.00
Total= 2300.13 2,300.13 Sq.ft 213.69 Sq.m
B8 Wood work
1 Supplying and fitting sal wooden chaukose with all
neccessary hardware all complete.
Doors
Doors D-(6'x7'6") 2 21.00 X-Sec = 0.08 3.50
Doors D1-(4'x7'6") 6 19.00 X-Sec = 0.08 9.50
Doors D2-(2'6"x7') 3 16.50 X-Sec = 0.08 3.96
Windows
Windows W-(8'6"x6') 15 49.50 X-Sec = 0.08 61.85
Windows W2-(8'x6') 1 48.00 X-Sec = 0.08 4.00
Windows W3-(10'x16') 1 52.00 X-Sec = 0.08 4.33
Windows W4-(5'x6') 2 38.00 X-Sec = 0.08 6.08
Ventilation
Ventilation V-(10'x2') 1 24.00 X-Sec = 0.08 2.00
Total= 95.21 95.21 Cu.ft 2.70 Cu.m
2
Supplying and fitting Ready made Teak wood Doors &
Windows special (Seasoned and Poisoned treated ,one side
teak and other side water proof ply fitting) with all neccessary
hardware all complete.
Doors
Doors D-(6'x7'6") 2 6.00 7.50 90.00
Doors D1-(4'x7'6") 6 4.00 7.50 180.00
Doors D2-(2'6"x7') 3 2.50 7.00 52.50
Windows
Windows W-(8'6"x6') 15 8.50 6.00 765.00
Windows W2-(8'x6') 1 8.00 6.00 48.00
Windows W3-(10'x16') 1 10.00 16.00 160.00
Windows W4-(5'x6') 2 5.00 6.00 60.00
Ventilation
Ventilation V-(10'x2') 1 10.00 2.00 20.00
Total= 1375.50 1,375.50 Sq.ft 127.79 Sq.m
C3 Form Work
19ft water proof plywood and steel prop formwork for all
works necessary propping, scaffoldong, staging, supporting
inclusive of wedging and cutting holes for utilization work till
the support is full unyielding net for Column/Slab/Beam etc.
complete work.
i.Column
Top Floor
C1 (1'2"x1'2") 4 4.00 8.50 136.00
Total= 136.00
ii.Beam
First Floor Beam (Main Beam)
X-Direction (1'6"x1') 1 46.00 1.50 69.00
Y-Direction (1'6"x1') 1 42.00 1.50 63.00
Total= 132.00
iii. Slab
First Floor Slab
Bottom 1 Total Floor Area 675.00 675.00
Side 1 Perimeter= 104.00 0.42 43.68
Total= 718.68 986.68 Sq.ft 91.67 Sq.m
C4 Flooring & Finishing work
1 38 mm thick P.C.C. flooring (Screeding) in (1:2:4) for
floors & top of slab with approved quality of cement, sand &
crushed stone chips/aggregate including mixing,laying,curing
and finishing with a floating coat of neat cement slurry.
TopFloor
Main Wall (9") 2 79.83 10.00 1596.64
Deduction
Doors D1-(4'x7'6") 1 4.00 7.50 -30.00
Total= 1566.64 1,566.64 Sq.ft 145.55 Sq.m
C6 Painting work
1 Interior Walls: Supplying & laying two coat distemper over
1 coat primer on to give uniform colouring after rendering the
surface all complete.
First Floor
Main Wall (9") 1 79.83 10.00 798.32
Deduction
Doors D1-(6'x7'6") 1 4.00 7.50 30.00
Total= 828.32 828.32 Sq.ft 76.95 Sq.m
Supplying & laying two coat enamel paint over 1 coat primer
3 to give uniform colouring after rendering the surface all
complete.
Doors Factor
Doors D1-(4'x7'6") 1 4.00 2.25 7.50 67.50
Total= 67.50 67.50 Sq.ft 6.27 Sq.m
C7 Wood work
1 Supplying and fitting sal wooden chaukose with all
neccessary hardware all complete.
Doors
Doors D1-(4'x7'6") 1 19.00 X-sec= 0.08 1.58
Total= 1.58 1.58 Cu.ft 0.04 Cu.m
2
Supplying and fitting Ready made Teak wood Doors &
Windows special (Seasoned and Poisoned treated ,one side
teak and other side water proof ply fitting) with all neccessary
hardware all complete.
Doors
Doors D1-(4'x7'6") 1 4.00 7.50 30.00
Total= 30.00 30.00 Sq.ft 2.79 Sq.m
Water Supply, Plumbing, Sanitary, Electrical
D,E,F
Communication and Allied Works (Buildings)
Sanitary fittings
soil pipe(6"@) m 80.00
Page 22 of 108
PROVISIONAL SUM
Project:
Location :
Year : 077/078
A4 RCC work
1 Providing and Laying P.C.C.(1:1.5:3) M20 for
R.C.C.work in foundation, columns, beams,
slabs etc. with cement, sand, and aggregate
including mixing with concrete mixture,
Cu.m 224.74 16297.00 3,662,619.20
compacting the concrete with vibrator machine,
laying, finishing to approved level ,lines and
dimensions and curing all complete as per
instruction of site Enginner.
A5 Reinforcement Work
Supplying & laying two coat enamel paint over Sq.m 281.54 355.00 99,947.60
1 coat primer to give uniform colouring after
rendering the surface all complete.
B9 Wood work
1
Cu.m 3.51 311688.00 1,093,994.79
Supplying and fitting sal wooden chaukose
with all neccessary hardware all complete.
2
Supplying and fitting Ready made Teak wood
Doors,special (Seasoned and Poisoned
treated ,one side teak and other side water proof Sq.m 166.58 9678.00 1,612,113.61
ply fitting) with all neccessary hardware all
complete.
B10 Iron & Steel Work -
B3 Reinforcement Work
C4 Form Work
D5 Form Work -
Location :
Year : 076/077
RA No. : 1
Description of item : Site Clearance :Clearing of grass, removing roots breaking sods, levelling the surface and disposal to 10m.
Unit:
Resources
Norms Specification
Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
DUDBC
Sub - total (A) 16.45 Sub - total (B) 0.00 Sub total (c)
RA No. : 2
Description of item : Earthwork in excavation by using Manual means including shoring,struting,bracing,sheeting and disposal of excavated earth, lead upto 10m and lift upto 1.5 m, disposed earth to be levelled and neatly dressed.
Unit:
Resources
Norms Specification
Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
DUDBC 11B
Sub - total (A) 500.50 Sub - total (B) 0.00 Sub total (c)
RA No. : 3
Description of item : Earth filling in 150 mm thick layer, watering, ramming with 1 ton roller including supply of filling materials within 10 m LEAD all complete.
Unit:
Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
DUDBC 11B
B2,B6 Backfill Unskilled md 1.030 715.00 736.45 Excavated Eath as Fill cu.m 0.00 1 ton roller hr 0.0167
Sub - total (A) 736.45 Sub - total (B) 1.25 Sub total (c)
Note:Filler material is taken as 70% excavated earth and 30% borrowed material. Direct Cost (A+B+C) = NRs.
Description of works: Providing one layer Flat brick soling with sand fillings in joints and bottom.
H15 Unskilled md 1.00 715.00 715.00 Brick nos 420.00 13.50 5670.00
Skilled md 0.50 1034.00 517.00 Sand m3 0.71 1664.00 1181.44
Rate(1m2) =
Chimney made Brickwork in 1:4 C/S mortar in ground floor in perfect line level finish including wetting the bricks, racking the joints, scaffolding and curing the work for at least 7 days with Lead upto 30m all
Description of item : complete.
Unit:
Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
DUDBC 11C
C2 Chimney Made Brick Nos 560.00 13.500 7560.00 tools 3 % of labour cost
Sub - total (A) 3267.00 Sub - total (B) 9861.52 Sub total (c)
RA No. : 4
Chimney made Brickwork in 1:4 C/S mortar in first floor in perfect line level finish including wetting the bricks, racking the joints,scaffolding and curing the work for at least 7 days with Lead upto 30m all complete.
Description of item :
Unit:
Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
DUDBC 11C
C2 Chimney Made Brick Nos 560.00 13.500 7560.00 tools 3 % of labour cost
Sub - total (A) 3767.50 Sub - total (B) 9861.52 Sub total (c)
RA No. : 8
Description of item : Machine made Plain cement Concrete (PCC) in 1:3:6 ratio for foundations, flooring and walls with approved quality of cement and sand and crushed stone aggregate including mixing, laying, curing etc all complete in
approval of site engineer.
Unit:
Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
D4 11D
0.2-0.28
hr 0.6000
Skilled md 0.50 1034.00 517.00 Cement Mt 0.220 17680.000 3889.60 m3 Mixer
Unskilled md 3.50 715.00 2502.50 40mm crushed aggregates cu.m 0.650 2964.000 1926.60 Vibrator hr 0.2500
Sub - total (A) 3019.50 Sub - total (B) 7602.77 Sub total (c)
RA No. : 10
Description of item : Machine made Plain cement Concrete (PCC) in 1:1.5:3 ratio for superstructures with approved quality of cement and sand and crushed stone aggregate including mixing, laying, curing etc all complete in approval of
site engineer.
Unit:
Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
D4 11D
Skilled md 0.50 1034.00 517.00 Cement Mt 0.400 17680.000 7072.00 0.2-0.28 m3hr 0.6000
Unskilled md 3.50 715.00 2502.50 40mm crushed aggregates cu.m 0.570 2964.000 1689.48 Vibrator hr 0.2500
Sub - total (A) 3019.50 Sub - total (B) 10753.45 Sub total (c)
RA No. : 11
Description of item : Providing and laying Reinforcement including cutting, bending, binding, fixing in position and lead 30m. etc. all complete as per specification and drawing.
Unit:
Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
D9 7,5
Unskilled md 12.00 715.00 8580.00 Binding Wire cu.m 10.000 124.000 1240.00
Sub - total (A) 20988.00 Sub - total (B) 93640.00 Sub total (c)
RA No. : 12
Description of item : Formwork, shuttering, centering with 19mm thick waterproof ply board and steel post for all works necessary propping, scaffolding, staging, supporting inclusive of wedging and cutting holes for utilization till the
support if fully unyielding nett.
Unit:
Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
E6 11E
Skilled md 17.20 1034.00 17784.80 19mm Ply Board sq.m 16.500 1572.000 25938.00
Sub - total (A) 36160.30 Sub - total (B) 44070.40 Sub total (c)
RA No. : 23
Description of item : 38 mm Cement Concrete Fooring (Screeding) 1:2:4 finished with a floating coat of neat cement slurry.
Unit:
Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
H1
Description of item : 3mm cement punning floor finishing work, over 38mm Cement Sand screeding work all complete.[H20]
Unit:
Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
H20
Skilled md 1.00 1034.00 1034.00 Cement mt 0.053 17600.000 936.32 tools 3 % of labour cost
Sub - total (A) 1749.00 Sub - total (B) 936.32 Sub total (c)
RA No. : 22
Description of item : Porcelain Glazed Tiles in floor, walls, jointed with neat white cement slurry upon 20mm thick bed of white cement mortar 1:4(1cement:4coarse sand)
Unit:
Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
H6
Skilled md 13.00 1034.00 13442.00 Cement mt 0.056 17680.000 990.08 tools 3 % of labour cost
Sub - total (A) 16659.50 Sub - total (B) 15138.86 Sub total (c)
Description of item : 12.5mm thick cement sand plaster in (1:4) ratio on wall of good finish including racking the joint, wetting of surfaces & curing the work all complete.
Unit:
Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
I1
Sub - total (A) 23848.00 Sub - total (B) 11941.28 Sub total (c)
RA No. : 31
Description of item : 12.5mm thick cement sand plaster in (1:4) ratio on ceiling of good finish including racking the joint, wetting of surfaces & curing the work all complete.
Unit:
Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
I1
Sub - total (A) 29810.00 Sub - total (B) 11941.28 Sub total (c)
RA No. : 35
Description of item : Providing 2 mm thick White Putty on wall and celling as per design drawing and specification all complete work.
Unit:
Resources
Norms Specification
Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
J5 Skilled md 1.00 1034.00 1034.00 White Putty kg 10.640 70.000 744.80 tools 3 % of labour cost
Sub - total (A) 1749.00 Sub - total (B) 744.80 Sub total (c)
RA No. : 32
Description of item : Colouring with two coat distemper paint with one coat primer to give uniform colouring after rendering the surface all complete.
Unit:
Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
J26
Skilled md 5.80 1034.00 5997.20 Primer lit 8.000 312.000 2496.00 tools 3 % of labour cost
Sub - total (A) 10144.20 Sub - total (B) 8144.00 Sub total (c)
RA No. : 33
Description of item : Colouring with two coat weather proof exterior emulsion paint with one coat primer to give uniform colouring after rendering the surface all complete.
Unit:
Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
J5
Unskilled md 8.00 715.00 5720.00 Emulsion Paint lit 16.0000 650.000 10400.00
Sub - total (A) 18128.00 Sub - total (B) 12927.20 Sub total (c)
Unit:
Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
J5 Skilled md 12.00 1034.00 12408.00 Primer lit 8.100 312.000 2527.20 tools 3 % of labour cost
Unskilled md 8.00 715.00 5720.00 Enamel Paint lit 16.0000 603.000 9648.00
Sub - total (A) 18128.00 Sub - total (B) 12175.20 Sub total (c)
RA No. : 13
Description of item : Well seasoned salwood chaukhats for fixed/openable door/windows with good finish of approved quality incuding fixing in postion with necessary M.S. hold fasts as per drawing and instruction all complete.
Unit:
Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
F21 11G
Skilled md 34.00 1034.00 35156.00 Sal Wood cu.m 1.100 208000.000 228800.00
Unskilled md 3.40 715.00 2431.00 Hold Fast nos. 92.000 46.000 4232.00
Sub - total (A) 37587.00 Sub - total (B) 233446.00 Sub total (c)
Description of item : Making and fitting fixing flush door shutter of 38 x 100 mm size sal wood frame with 4 mm teak ply on both side including all necessary hardware fitting all complete.
Unit:
Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
G4 11G
Skilled md 7.00 1034.00 7238.00 Sal Wood cu.m 0.035 208000.000 7196.80 tools 3 % of labour cost
Unskilled md 0.70 715.00 500.50 4 mm Teak PlyWood sq.m 4.650 598.000 2780.70
Sub - total (A) 7738.50 Sub - total (B) 10942.50 Sub total (c)
Description of item : Fixing of glazed shutter in 38x75 mm thick sal wood frame with 4 mm thick plain glass fitted including all necessary hardware fittings all complete.
Unit:
Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
G3 11G
Skilled md 9.00 1034.00 9306.00 Sal Wood cu.m 0.049 208000.000 10192.00 tools 3 % of labour cost
Sub - total (A) 9949.50 Sub - total (B) 12085.72 Sub total (c)
RA No. : 20
Description of item : Making and fitting fixing of stainless steel pipe raillingfor staircase with 3 rows of 25 mm.dia.stainless steel pipe horizontal rails and 25 mm.dia.stainless steel pipe for vertical post @ 2m. c/c including welding , cutting
all complete.
Unit:
Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
M15
Unskilled md 11.35 715.00 8115.25 25 mm steel pipe m 36.0000 210.000 7560.00 welding machine etc.
Sub - total (A) 16159.77 Sub - total (B) 7560.00 Sub total (c)
Rate Amount
0.49
16.94
2.54
19.48
1.00 cu.m
Equipment (C)
Rate Amount
15.02
515.52
77.33
592.84
1.00 cu.m.
Equipment (C)
Rate Amount
125.00 2.09
2.09
739.79
110.97
850.76
Unit : 10m2
ment (C)
Amount
0.00
9295.96
929.60
ork for at least 7 days with Lead upto 30m all
1.00 cu.m
Equipment (C)
Rate Amount
98.01
13226.53
1983.98
15210.51
1.00 cu.m
Equipment (C)
Rate Amount
113.03
13742.05
2061.31
15803.35
1.00 cu.m
Equipment (C)
Rate Amount
550.00 330.00
275.00 68.75
398.75
11021.02
1653.15
12674.17
1.00 cu.m
Equipment (C)
Rate Amount
550.00 330.00
275.00 68.75
398.75
14171.70
2125.76
16297.46
1.00 MT
Equipment (C)
Rate Amount
0.00
114628.00
17194.20
131822.20
100.00 sq.m
Equipment (C)
Rate Amount
0.00
80230.70
12034.61
92265.31
10.00 sq.m
Equipment (C)
Rate Amount
0.00
6424.90
963.74
7388.64
10.00 sq.m
Equipment (C)
Rate Amount
52.47
2737.79
410.67
3148.46
10.00 sq.m
Equipment (C)
Rate Amount
499.79
32298.15
4844.72
37142.87
100.00 sq.m
Equipment (C)
Rate Amount
0.00
35789.28
5368.39
41157.67
100.00 sq.m
Equipment (C)
Rate Amount
0.00
41751.28
6262.69
48013.97
10.00 sq.m
Equipment (C)
Rate Amount
52.47
2546.27
381.94
2928.21
100.00 sq.m
Equipment (C)
Rate Amount
304.33
18592.53
2788.88
21381.40
100.00 sq.m
Equipment (C)
Rate Amount
0.00
31055.20
4658.28
35713.48
100.00 sq.m
Equipment (C)
Rate Amount
543.84
30847.04
4627.06
35474.10
1.00 cu.m
Equipment (C)
Rate Amount
0.00
271033.00
40654.95
311687.95
te.
2.25 sq.m
Equipment (C)
Rate Amount
232.16
18913.16
2836.97
21750.13
2.23 sq.m
Equipment (C)
Rate Amount
22333.71
3350.06
25683.76
9.15 sq.m
Equipment (C)
Rate Amount
378.00
24097.77
3614.67
27712.44
S.No. Description No. No. of Bars
3 Beam
Main Beam
Extra Bar
Along Grid A-A, B-B, C-C, D-D in Grid 1-1,4-4,5-5 & 8-8
Extra Bar
Stirrups
Total
Total Quantity Unit(Kg) Remarks
727.49
459.31
112.01
164.97
192.66
154.13
78.03
486.24
291.89
129.70
129.70
65.76
110.97
9.58
70.90
166.66
292.93
Between 44&55
46.72
Between 44&55
105.83
125.54
252.99
16.27
15.71
65.07
54.88
Kg
5327.96
S.No. Description No. No. of Bars
3 Beam
Main Beam
Extra Bar
Along Grid A-A, B-B, C-C, D-D in Grid 1-1,4-4,5-5 & 8-
8
Extra Bar
Stirrups
For Beam 12"*12"
Total
Total Quantity Unit(Kg) Remarks
727.49
459.31
105.58
55.92
174.60
55.92
192.66
154.13
78.03
486.24
291.89
118.40
Between A'A' &BB
72.58
Between A'A' &BB
81.04
Between CC & DD
48.65
Between CC & DD
129.70
129.70
65.76
216.42
Except 44&55
23.24
Along 44 & 55
32.30
Along 44 & 55
110.97
9.58
409.41
Maximum dia. Taken
70.90
166.66
292.93
46.72
Between 44&55
105.83
Between 44&55
125.54
252.99
16.27
15.71
65.07
54.88
5443.00 Kg
BAR BENDING
Project:
Location :
Year: 077/078
S.No. Description No. No. of Bars Dia of Bars (mm)
4 SLAB
Ground Floor Slab
Bottom Bar
10 mm dia @ 6" c/c in X-direction Through 231 10
Bar
10 mm dia @ 6" c/c in Y-direction Through 107 10
Bar
Remaining Part
10 mm dia @ 6" c/c in X-direction Through
Bar
10 mm dia @ 6" c/c in Y-direction Through 53 10
Bar 24 10
Deduction
10 mm dia @ 6" c/c in X-direction Through
43 10
Bar
10 mm dia @ 6" c/c in Y-direction Through
Bar 28 10
Top Bar
10 mm dia @ 6" c/c in X-direction Through
139 10
Bar
10 mm dia @ 6" c/c in Y-direction Through
Bar 66 10
Deduction
10 mm dia @ 6" c/c in X-direction Through
43 10
Bar
10 mm dia @ 6" c/c in Y-direction Through
Bar 13 10
Top Bar
10 mm dia @ 6" c/c in X-direction Through
Bar
10 mm dia @ 6" c/c in Y-direction Through 139 10
Bar 66 10
Deduction
10 mm dia @ 6" c/c in X-direction Through
Bar
10 mm dia @ 6" c/c in Y-direction Through 43 10
Bar 13 10
6
6
4
4
9
9
9
9
9
9
3
3
20
20
6
6
4
4
9
9
9
9
9
9
3
2-L-8mm dia. @ 6" c/c 3 12 8
BAR BENDING SCHEDULE
Cutting Length (ft) Total Length (ft) Total Length (m) Wt/m (kg/m) Total Quantity
Along AA & DD
Along BB & CC
Along AA
Along A'A'
Along 44 & 55
Along 11 & 88
Along 22,33 & 77
Along 44 betwee CC & DD
Along 55 betwee CC & DD
Along 44 &55 between AA & CC
Kg
Along AA & DD
Along BB & CC
Along AA
Along A'A'
Along 44 & 55
Along 11 & 88
Along 22,33 & 77
Along 44 betwee CC & DD
Along 55 betwee CC & DD
Along 44 &55 between AA & CC
Kg
BAR BENDING SC
Project:
Location :
Year: 077/078
S.No. Description No. No. of Bars Dia of Bars (mm)
1 Column
C1
Plinth Level to Ground Floor
20 mm dia. Bar 8 8 20
C2
Plinth Level to Ground Floor
25 mm dia. Bar 2 4 25
16 mm dia. Bar 2 4 16
C3
Plinth Level to Ground Floor
25 mm dia. Bar 16 4 25
20 mm dia. Bar 16 4 20
C4
Plinth Level to Ground Floor
25 mm dia. Bar 8 8 25
C1
Ground Floor to First Floor
20 mm dia. Bar 8 8 20
C2
Ground Floor to First Floor
25 mm dia. Bar 2 4 25
16 mm dia. Bar 2 4 16
C3
Ground Floor to First Floor
25 mm dia. Bar 16 4 25
20 mm dia. Bar 16 4 20
C4
Ground Floor to First Floor
25 mm dia. Bar 8 8 25
C4
First Floor to Roof Floor
25 mm dia. Bar 4 8 25
2 Beam
Grid A-A, B-B, C-C, D-D
Plinth/Tie Beam
Top Bar
16mm dia Through Bar 4 3 16
Bottom Bar
16mm dia Through Bar 4 3 16
Grid 1-1,2-2,3-3,6-6,7-7,8-8
Plinth/Tie Beam
Top Bar
16mm dia Through Bar 6 3 16
Bottom Bar
16mm dia Through Bar 6 3 16
Grid 4-4,5-5
Top Bar
16mm dia Through Bar 2 3 16
Bottom Bar
16mm dia Through Bar 2 3 16
Secondary Beam Along X-direction
Top Bar
16mm dia Through Bar 2 3 16
Bottom Bar
16mm dia Through Bar 2 3 16
Secondary Beam Along Y-direction
Top Bar
16mm dia Through Bar 1 3 16
Bottom Bar
16mm dia Through Bar 1 3 16
STIRRUPS
Plinth/Tie Beam
Along Grid A-A, B-B, C-C, D-D between 1-
1&2-2,2-2&3-3,3-3&4-4,6-6&7-7,7-7&8-8
2-L-8mm dia. @ 4" c/c 20 16 8
2-L-8mm dia. @ 6" c/c 20 19 8
Along Grid A-A, B-B, C-C, D-D between 4-
4&5-5
2-L-8mm dia. @ 4" c/c 6 16 8
2-L-8mm dia. @ 6" c/c 6 33 8
Along Grid A-A, B-B, C-C, D-D between 5-
5&6-6
2-L-8mm dia. @ 4" c/c 4 16 8
2-L-8mm dia. @ 6" c/c 4 23 8
Along Grid 1-1 to 8-8 between A-A & B-B
2-L-8mm dia. @ 4" c/c 9 16 8
2-L-8mm dia. @ 6" c/c 9 27 8
Along Grid 1-1 to 8-8 between B-B & C-C
2-L-8mm dia. @ 4" c/c 9 16 8
2-L-8mm dia. @ 6" c/c 9 12 8
Along Grid 1-1 to 8-8 between C-C & D-D
2-L-8mm dia. @ 4" c/c 9 16 8
2-L-8mm
Along dia.4-4,5-5
Grid @ 6" c/c
& SB between A-A & 9 27 8
A'-A'
2-L-8mm dia. @ 4" c/c 3 16 8
2-L-8mm dia. @ 6" c/c 3 12 8
BAR BENDING SCHEDULE
Cutting Length (ft) Total Length (ft) Total Length (m) Wt/m (kg/m) Total Quantity
3218.70
691.38
Kg
Kg
BAR BENDING SC
Project:
Location :
Year: 077/078
S.No. Description No. No. of Bars Dia of Bars (mm) Cutting Length (ft)
5 STAIR
Main Bar
12 mm dia main bar
2 13 12 21.58
12 mm dia main bar(Extra)
2 13 12 10.00
12 mm dia main bar(Extra)
2 13 12 9.30
12 mm dia main bar(Extra)
4 13 12 5.30
For Second Flight
Main Bar
12 mm dia main bar
1 13 12 24.00
12 mm dia main bar(Extra)
2 13 12 10.66
12 mm dia main bar(Extra)
2 13 12 5.66
Distribution Bar
Total Length (ft) Total Length (m) Wt/m (kg/m) Total Quantity Unit(Kg)
562.13
184.57
Summary
Ground Floor Kg 0.000 MT
Total 18815.371
Kg 18.815 MT
Aurahi Municipality Officer of municipal executiveAurahi, mahottari state No:-2, Nepal RATE ANALYSIS 2076-07
Clearing and grubbing including the cutting of trees ( If necessary ) having girth of less than 30 cm when measured at 1m above the ground
Norms no- 1 Page no 20 Dolidar
Respective clauses of specifications 1-1.5(a),1-1.5(b), and 1-1.6
Earth filling with ordinary soil in layers of 15 ,15 cm and compacting manually with water sprinkling
23
NN 2 ( 25) Ka Page-11 Old For 1 Cum
Earth filling with ordinary soil in layers of 15 ,15 cm and compacting manually with no water sprinkling
24
NN 2 ( 25) Kha Page-11 Old For 1 Cum
12.5 mm thick plastering with cement sand mortar on brick walls or concretesurface with all necessary operation including full compensationfor all
labour materials scaffolding and other incidentals required to complete the work as per the specifications.
12.5 mm thick plastering with cement sand mortar on brick walls or concretesurface with all necessary operation including full compensationfor all
labour materials scaffolding and other incidentals required to complete the work as per the specifications.
12.5 mm thick plastering with cement sand mortar on brick walls or concretesurface with all necessary operation including full compensationfor all
labour materials scaffolding and other incidentals required to complete the work as per the specifications.
Formwork with timber as material. It includes all labour, materials, and other incidentals required for the construction and removal of forms as
described in the specifications. It further covers the framing work that is required for properly supporting the members until the concrete is
sufficiently curd, setand hardened.ONLY FOR BRIDGE
42
A Beam or slab ( Formwork and framework when the height is 4-8m i.e.above 4m.
N.N. 39 Page 43(Dolidar)
Respective clause specification 9
For 10 m2
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 1.25 Md 1034.00 1292.50
Labour
Aurahi Municipality Officer of municipal executiveAurahi, mahottari state No:-2, Nepal RATE ANALYSIS 2076-07
Labour
Unskilled 1.75 Md 715.00 1251.25
Sub Total (L) 2543.75
T.& P. 3% of labour cost 76.31
Total 2620.06
Timber planks/Board 0.75 m3 10400.00 7800.00
Post,batten and un-sawn timber 0.50 m3 1733.33 866.67
Material
Nails 3.50 Kg 140.40 491.40 63.88
Reinforcement for RCC work. It includes procuring steels, its bending,placing, binding and fixing in position as shown on the drawings and as
43 directed by the engineer. It also includes all devices for keeping reinforcement in approved position and jointing as per approved method with due
allowance for wastage overlapes spacer bars and annealed steel wire for bending
Cement concreting work. It includes all labour and material required for mixing, placing in position,Vibrating,compacting,finishing, curing and all
44 other incidentals required to produce concrete of specified strength as per the specifications. The rate includesthe work of making, fixing, and
removing of all centres and forms required for the works
A-a M10 Grade ( 1:3:6 mix ) PCC work in foundtion ( Including form work)
N.N. 41 Page 46(Dolidar)
Respective clause specification 11
For 1 m3
Total 3405.68
Cement 220.00 Kg 17.68 3889.60 505.65
Sand 0.47 m3 1664.00 782.08
Material Aggregate- 40mm 0.65 m3 2158.00 1402.70
Aggregate- 20mm 0.24 m3 2236.00 536.64
Aggregate- 10mm m3 1820.00 0.00
Timber 0.055 m3 10400.00 572.00
A-b M15 ( 1:2:4 mix) PCC work in foundation ( Including form works)
N.N. 41 Page 46(Dolidar)
Respective clause specification 11
For 1 m3
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 0.66 Md 1034.00 682.44
Labour
Unskilled 3.73 Md 715.00 2666.95
Sub Total (L) 3349.39
T.& P. 3% of labour cost 100.48
Total 3449.87
Cement 320.00 Kg 17.68 5657.60 735.49
Sand 0.44 m3 1664.00 732.16
Aggregate- 40mm 0.52 m3 2158.00 1122.16
Material
Aggregate- 20mm 0.22 m3 2236.00 491.92
Aggregate- 10mm 0.11 m3 1820.00 200.20
Timber 0.055 m3 10400.00 572.00
Aurahi Municipality Officer of municipal executiveAurahi, mahottari state No:-2, Nepal RATE ANALYSIS 2076-07
Work in Superstructure components (Beam, Slabs,abutment caps etc.) ( Including form works)
B
B-a M15 ( 1:2:4 mix) PCC work in super structure component ( Including form works)
N.N. 41 Page 46,47(Dolidar)
Respective clause specification 11
For 1 m3
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 0.66 Md 1034.00 682.44
Labour
Unskilled 4.73 Md 715.00 3381.95
Sub Total (L) 4064.39
T.& P. 3% of labour cost 121.93
Total 4186.32
Cement 320.00 Kg 17.68 5657.60 735.49
Sand 0.44 m3 1664.00 732.16
Material Aggregate- 40mm 0.52 m3 2158.00 1122.16
Aggregate- 20mm 0.22 m3 2236.00 491.92
Aggregate- 10mm 0.11 m3 1820.00 200.20
Timber 0.055 m3 10400.00 572.00
B-b M20 ( 1:1.5:3 mix) PCC work in super structure component ( Including form works)
N.N. 41 Page 47(Dolidar)
Respective clause specification 11
For 1 m3
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 0.66 Md 1034.00 682.44
Labour
Unskilled 4.79 Md 715.00 3424.85
Sub Total (L) 4107.29
T.& P. 3% of labour cost 123.22
Total 4230.51
Cement 400.00 Kg 17.68 7072.00 919.36
Sand 0.42 m3 1664.00 698.88
Aggregate- 40mm m3 2158.00 0.00
Material Aggregate- 20mm 0.57 m3 2236.00 1274.52
0.29 m3 527.80
Aggregate- 10mm 1820.00
Timber 0.055 m3 10400.00 572.00
A-a M10 Grade ( 1:3:6 mix ) PCC work in foundtion ( Excluding form work)
N.N. 41 Page 46(Dolidar)
Respective clause specification 11
For 1 m3
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 0.50 Md 1034.00 517.00
Labour
Unskilled 3.25 Md 715.00 2323.75
Sub Total (L) 2840.75
T.& P. 3% of labour cost 85.22
Total 2925.97
Cement 220.00 Kg 17.68 3889.60 505.65
Sand 0.47 m3 1664.00 782.08
Material
Aggregate- 40mm 0.65 m3 2158.00 1402.70
Aggregate- 20mm 0.24 m3 2236.00 536.64
A-b M15 ( 1:2:4 mix) PCC work in foundation ( Excluding form works)
N.N. 41 Page 46(Dolidar)
Respective clause specification 11
For 1 m3
Work in Superstructure components (Beam, Slabs,abutment caps etc.) ( Excluding form works)
B
B-a M15 ( 1:2:4 mix) PCC work in super structure component ( Excluding form works)
N.N. 41 Page 46,47(Dolidar)
Respective clause specification 11
For 1 m3
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 0.50 Md 1034.00 517.00
Labour
Unskilled 4.31 Md 715.00 3081.65
Sub Total (L) 3598.65
T.& P. 3% of labour cost 107.96
Total 3706.61
Cement 320.00 Kg 17.68 5657.60 735.49
Sand 0.44 m3 1664.00 732.16
Material Aggregate- 40mm 0.52 m3 2158.00 1122.16
Aggregate- 20mm 0.22 m3 2236.00 491.92
Aggregate- 10mm 0.11 m3 1820.00 200.20
B-b M20 ( 1:1.5:3 mix) PCC work in super structure component ( Excluding form works)
N.N. 41 Page 47(Dolidar)
Respective clause specification 11
For 1 m3
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 0.50 Md 1034.00 517.00
Labour
Unskilled 4.37 Md 715.00 3124.55
Sub Total (L) 3641.55
T.& P. 3% of labour cost 109.25
Total 3750.80
Cement 400.00 Kg 17.68 7072.00 919.36
Sand 0.42 m3 1664.00 698.88
Material Aggregate- 40mm m3 2158.00 0.00
Aggregate- 20mm 0.57 m3 2236.00 1274.52
Aggregate- 10mm 0.29 m3 1820.00 527.80
Structural steel work for structures. It includes the cost of all labour, materials required for fabrication, connection, oiling, paintiong , temoorary
erection, inspection, tests and complete final erection as shown on the drawings and as specified in the specification
45
Steel work riveted or bolted in built-up sections, trusses including cutting, hoisting and fixing in position
A
I In rolled steel joists
N.N. 42 Page 47(Dolidar)
Respective clause specification 12
For 1000 Kg
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 5.30 Md 1034.00 5480.20
Labour
Unskilled 10.75 Md 715.00 7686.25
Sub Total (L) 13166.45
T.& P. 3% of labour cost 394.99
Total 13561.44
Steel member 1000.00 Kg 156.00 156000.00 20280.00
Material Oil 2.50 Kg 77.50 193.75 25.19
Paint 5.00 Kg 197.60 988.00 128.44
Aurahi Municipality Officer of municipal executiveAurahi, mahottari state No:-2, Nepal RATE ANALYSIS 2076-07
Roofing works.
72 Roofing work with cement tile ( 3'x2')
For 10 Sqm
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 0.50 Md 1034.00 517.00
Labour
Unskilled 1.50 Md 715.00 1072.50
Sub Total (L) 1589.50
T.& P. 0% of labour cost 0.00
Total 1589.50
Material Cement tile 24.00 No 28.08 673.92
For 2.114 m2
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 10.00 Md 1034.00 10340.00
Labour
Unskilled 1.00 Md 715.00 715.00
Sub Total (L) 11055.00
T.& P. 0% of labour cost 0.00
Total 11055.00
wood 0.084 cum 208000.00 17472.00 2271.36
100 mm Hinge 6 No 41.60 249.60 32.45
150 mm Lower bolt 1 No 83.20 83.20 10.82
Material 300 mm Tower bolt 1 No 145.60 145.60 18.93
250 mm locking set 1 No 343.20 343.20 44.62
Handle 2 No 312.00 624.00 81.12
screw L.s. No 75.00
92 Flooring works
20 mm thick Terezotile flooring 20mm thick in 1:4 cement mortar including Rubbing and polish all complete work
Flooring works
25 mm thick marble ( 450mmx450mm) flooring in 20 mm 1:3 cement mortar including Grinding and polish all complete work
93
N.N. 11(6) Page 63(Old)
For 10 Sqm
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 2.00 Md 1034.00 2068.00
Labour
Unskilled 21.50 Md 715.00 15372.50
Sub Total (L) 17440.50
T.& P. 0% of labour cost 0.00
Total 17440.50
25 mm Marble 11 Sqm 4043.52 44478.72 5782.23
Cement 96.00 Kg 17.68 1697.28 220.65
Sand 0.195 Cum 1664.00 324.48
Material Oxalic Acid 0.37 Kg 343.20 126.98 16.51
manpolice 0.118 Kg 426.40 50.32 6.54
Tarpentine 0.538 Litre 130.00 69.94 9.09
Carborandam ( L.S.) 2 No 312.00 624.00 81.12
Sub Total (M) 47371.72
Total Rate ( L+M+T.P.) 64812.22 6116.14
15% Contractor's overhead 9721.83
Rate per Sqm. ( Contractor's Rate) Excluding VAT 7453.41
Rate per Sqm. ( User's Rate) Including VAT in Material 7092.84
Flooring works
94 Porcelene glazed tile flooring work in 1:4 cement sand mortar
Material
Sand 0.152 Cum 1664.00 252.93
White cement 3.228 Kg 52.00 167.86 21.82
Sub Total (M) 15138.86
Total Rate ( L+M+T.P.) 31798.36 1935.17
Flooring works
95 Flate brick soling in cement sand and pointing in joints in 1:2 c/s
N.N. 11(12) Page 64(Old)
For 10 Sqm
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 2.25 Md 1034.00 2326.50
Labour
Unskilled 3.250 Md 715.00 2323.75
Sub Total (L) 4650.25
T.& P. 0% of labour cost 0.00
Total 4650.25
Brick 430.00 No 13.00 5590.00
Material Cement 78.00 Kg 17.68 1379.04 179.28
Sand 0.229 Cum 1664.00 381.06
Sub Total (M) 7350.10
Total Rate ( L+M+T.P.) 12000.35 179.28
15% Contractor's overhead 1800.05
Rate per Sqm. ( Contractor's Rate) Excluding VAT 1380.04
Rate per Sqm. ( User's Rate) Including VAT in Material 1217.96
Painting work
Aurahi Municipality Officer of municipal executiveAurahi, mahottari state No:-2, Nepal RATE ANALYSIS 2076-07
C
Office of the municipal executive
State no. 2, Nepal
Aurahi, Mahottari
RATE ANALYSIS 2076-077