Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 108

Page No:-1

SUMMARY OF COST
Project:
Location :
Year : 077/078
Item No. Description Estimate Amount (NRs.) % Remarks
1 PART 1-BUILDING
A Civil Works: COMPOUND WALL 16,378,109.15 39.51%
B Civil Works: GROUND FLOOR 6,057,452.20 14.61%
C Civil Works: FIRST FLOOR 13,742,622.98 33.15%
D Civil Works:TOP FLOOR 852,290.09 2.06%
Water Supply, Plumbing, Sanitary, Electrical Communication and Allied
E,F,G Works (Buildings) 4,122,734.67 9.95%

Sub Total Part-1= 41,153,209.09 99.3%


2 PART 2-PROVISIONAL SUMS
Sub Total Part-2= 300,189.44 0.72%
P Total of Part-1 and Part-2= 41,453,398.53 100.00%
Work Charge Staff Expanses @ 2.5% of Subtotal P 1,036,334.96 i
Other Minor Expenses @ 2.5% of Subtotal P 1,036,334.96 ii
Q Sub Total= 43,526,068.46 P+i+ii
For Budget Provision
Physical Contingencies @ 10% of Sub Total P 4,145,339.85 iii
Price Escalation @ 10% of Sub Total P 4,145,339.85 iv
R Sub Total = 51,816,748.17 Q+iii+iv
13% VAT of Sub Total R 6,736,177.26 v
Grand Total (Including VAT) 58,552,925.43 R+v Nrs.

Prepared By:- Checked By:- Recommended By:- Approved By:-


ABSTRACT OF COST
Project:
Location :
Year : 077/078

Item No. Item Description Unit Quantity Rate Amount


A Civil Works: Boundary Wall
A1 Earth Works
1 Earthwork in excavation in ordinary/medium
rock by using Manual means (without blasting)
including disposal of excavated earth, lead upto Cu.m 360.44 592.84 213,681.16
10m and lift upto 1.5 m, disposed earth to be
levelled and neatly dressed.
2 Earthwork in filling with approved earth upto
plinth level including, watering,compating by Cu.m 144.17 851.00 122,692.58
labour, dressing complete.
A2 Masonry Works
1 Providing Flat brick soling with sand fillings
Sq.m 459.85 929.60 427,471.40
in joints and bottom.
2 Brickwork in 1:4 (cement:sand) mortar in
perfect line level finish including wetting the
bricks, racking the joints, scaffolding and Cu.m 235.66 15211.00 3,584,655.33
curing the work for at least 7 days all complete.
A3 PCC works
Providing and Laying Plain Cement Concrete
( P.C.C.) in (1:3:6) M10
(cement:sand:aggregate) in footing, wall
foundation and floors including mixing, laying, Cu.m 35.04 12674.00 444,103.52
finishing to approved level, line and dimensions
and curing all complete as per specification.

A4 RCC work
1 Providing and Laying P.C.C.(1:1.5:3) M20 for
R.C.C.work in foundation, columns, beams,
slabs etc. with cement, sand, and aggregate
including mixing with concrete mixture,
Cu.m 224.74 16297.00 3,662,619.20
compacting the concrete with vibrator machine,
laying, finishing to approved level ,lines and
dimensions and curing all complete as per
instruction of site Enginner.
A5 Reinforcement Work

Providing TMT Steel Reinforcement bars


(Grade Fe500) work including straightening,
cleaning, cutting, bending, binding with 20 MT 27.14 131822.00 3,577,279.20
SWG annealed wire & fixing in position as per
drawing, bar bending schedule for foundation,
column, beam, staircase, slab & in all R.C.C.
works as per specification, drawing.
A6 Form Work

19ft water proof plywood and steel prop


formwork for all works necessary propping,
scaffoldong, staging, supporting inclusive of Sq.m 2017.57 923.00 1,862,217.61
wedging and cutting holes for utilization work
till the support is full unyielding net for
Column/Slab/Beam etc. complete work.
A7 Plastering & Pointing work
1 12.5 mm thick cement:sand (1:4) plaster on
walls of good finish including racking the joint, Sq.m 3369.59 412.00 1,388,271.83
wetting of surfaces & curing the work all
complete.
3 Providing 2 mm thick White Putty on wall and
celling as per design drawing and specification Sq.m 1684.80 293.00 493,645.20
all complete work.
A8 Painting work
2
Exterior Walls: Supplying & laying two coat
weather proof emulsion paint over 1 coat Sq.m 1684.80 357.00 601,472.14
primer on to give uniform colouring after
rendering the surface all complete.
Total Cost Of
16,378,109.15
Compound Wall

B Civil Works: GROUND FLOOR

B6 Flooring & Finishing work


1 38 mm thick P.C.C. flooring (Screeding) in
(1:2:4) for floors & top of slab with approved
quality of cement, sand & crushed stone
chips/aggregate including mixing,laying,curing
and finishing with a floating coat of neat Sq.m 643.35 739.00 475,438.07
cement slurry.

2 3mm.thick Cement:Sand Punning (1:1) on


floor, dado and skirting etc. as per specification Sq.m 643.35 315.00 202,656.28
and direction complete work.
3

Providing and Laying 6 mm thick porcelain Sq.m 106.47 3714.00 395,417.91


glazed Tiles on floors & walls jointed with neat
white cement slurry upon 20mm thick bed of
white cement:sand mortar (1:4).
B7 Plastering & Pointing work
1 12.5 mm thick cement:sand (1:4) plaster on
walls of good finish including racking the joint, Sq.m 1196.14 480.00 574,149.16
wetting of surfaces & curing the work all
complete.
2 12.5 mm thick cement:sand (1:3) plaster on
Ceiling of good finish including racking the Sq.m 690.92 293.00 202,439.45
joint, wetting of surfaces & curing the work all
complete.
3 Providing 2 mm thick White Putty on wall and
celling as per design drawing and specification Sq.m 1887.06 412.00 777,470.24
all complete work.
B8 Painting work
Interior Walls: Supplying & laying two coat
1 distemper over 1 coat primer on to give
uniform colouring after rendering the surface all Sq.m 1270.35 214.00 271,854.73
complete.
2
Exterior Walls: Supplying & laying two coat
weather proof emulsion paint over 1 coat Sq.m 616.71 357.00 220,167.07
primer on to give uniform colouring after
rendering the surface all complete.
3

Supplying & laying two coat enamel paint over Sq.m 281.54 355.00 99,947.60
1 coat primer to give uniform colouring after
rendering the surface all complete.
B9 Wood work
1
Cu.m 3.51 311688.00 1,093,994.79
Supplying and fitting sal wooden chaukose
with all neccessary hardware all complete.
2
Supplying and fitting Ready made Teak wood
Doors,special (Seasoned and Poisoned
treated ,one side teak and other side water proof Sq.m 166.58 9678.00 1,612,113.61
ply fitting) with all neccessary hardware all
complete.
B10 Iron & Steel Work

Making and fitting fixing of stainless steel pipe


railling in balcony with 50ft.dia.stainless steel Rm 43.28 3045.25 131,803.29
pipe handrail including welding , cutting all
complete.
Total Cost of
6,057,452.20
Roof =

B Civil Works: FIRST FLOOR


B1 Masonry Works
Brickwork in 1:4 (cement:sand) mortar in
perfect line level finish including wetting the
bricks, racking the joints, scaffolding and Cu.m 121.54 15803.00 1,920,775.38
curing the work for at least 7 days all complete.
B2 RCC work
Providing and Laying P.C.C.(1:1.5:3) M20 for
R.C.C.work in foundation, columns, beams,
slabs etc. with cement, sand, and aggregate
including mixing with concrete mixture,
Cu.m 141.10 16297.00 2,299,446.90
compacting the concrete with vibrator machine,
laying, finishing to approved level ,lines and
dimensions and curing all complete as per
instruction of site Enginner.
B3 Reinforcement Work

Providing TMT Steel Reinforcement bars


(Grade Fe500) work including straightening,
cleaning, cutting, bending, binding with 20 MT 18.82 131822.00 2,480,279.89
SWG annealed wire & fixing in position as per
drawing, bar bending schedule for foundation,
column, beam, staircase, slab & in all R.C.C.
works as per specification, drawing.
B4 PCC work
Providing and Laying Plain Cement Concrete
( P.C.C.) (1:1.5:3) M20
(cement:sand:aggregate) for R.C.C. work in
Sill & Lintel band including mixing, laying, Cu.m 2.97 16297.00 48,455.63
finishing to approved level, line and dimensions
and curing all complete as per specification.

B5 Form Work
19ft water proof plywood and steel prop
formwork for all works necessary propping, Sq.m 1644.82 923.00 1,518,166.05
scaffoldong, staging, supporting inclusive of
wedging and cutting holes for utilization work
till the support is full unyielding net for
Column/Slab/Beam etc. complete work.
B6 Flooring & Finishing work
1 38 mm thick P.C.C. flooring (Screeding) in
(1:2:4) for floors & top of slab with approved
quality of cement, sand & crushed stone Sq.m 687.76 739.00 508,255.31
chips/aggregate including mixing,laying,curing
and finishing with a floating coat of neat
cement slurry.
2 3mm.thick Cement:Sand Punning (1:1) on
floor, dado and skirting etc. as per specification Sq.m 684.68 315.00 215,673.98
and direction complete work.
3

Providing and Laying 6 mm thick porcelain Sq.m 103.22 3714.00 383,342.07


glazed Tiles on floors & walls jointed with neat
white cement slurry upon 20mm thick bed of
white cement:sand mortar (1:4).
B7 Plastering & Pointing work
1 12.5 mm thick cement:sand (1:4) plaster on
walls of good finish including racking the joint, Sq.m 1244.88 412.00 512,888.55
wetting of surfaces & curing the work all
complete.
2 12.5 mm thick cement:sand (1:3) plaster on
Ceiling of good finish including racking the Sq.m 690.92 480.00 331,641.41
joint, wetting of surfaces & curing the work all
complete.
3 Providing 2 mm thick White Putty on wall and
celling as per design drawing and specification Sq.m 1935.79 293.00 567,187.86
all complete work.
B8 Painting work
Interior Walls: Supplying & laying two coat
1 distemper over 1 coat primer on to give
uniform colouring after rendering the surface all Sq.m 1456.08 214.00 311,600.69
complete.
2
Exterior Walls: Supplying & laying two coat
weather proof emulsion paint over 1 coat Sq.m 479.72 357.00 171,258.87
primer on to give uniform colouring after
rendering the surface all complete.
3 Supplying & laying two coat enamel paint over
1 coat primer to give uniform colouring after Sq.m 213.69 355.00 75,859.42
rendering the surface all complete.
B9 Wood work
1
Cu.m 2.70 311688.00 840,367.55
Supplying and fitting sal wooden chaukose
with all neccessary hardware all complete.
2
Supplying and fitting Ready made Teak wood
Doors,special (Seasoned and Poisoned
treated ,one side teak and other side water proof Sq.m 127.79 9678.00 1,236,733.00
ply fitting) with all neccessary hardware all
complete.
B10 Iron and Steel Works
Making and fitting fixing of stainless steel pipe
railling in balcony with 50ft.dia.stainless steel Rm 105.31 3045.25 320,690.41
pipe handrail including welding , cutting all
complete.

Total Cost of
13,742,622.98
Roof =
C Civil Works: TOP FLOOR
C1 Masonry Works
Brickwork in 1:4 (cement:sand) mortar in
perfect line level finish including wetting the
bricks, racking the joints, scaffolding and Cu.m 15.05 15803.00 237,811.05
curing the work for at least 7 days all complete.
C2 RCC work
Providing and Laying P.C.C.(1:1.5:3) M20 for
R.C.C.work in foundation, columns, beams,
slabs etc. with cement, sand, and aggregate
including mixing with concrete mixture,
Cu.m 12.73 16297.00 207,436.23
compacting the concrete with vibrator machine,
laying, finishing to approved level ,lines and
dimensions and curing all complete as per
instruction of site Enginner.
C3 PCC work
Providing and Laying Plain Cement Concrete
( P.C.C.) (1:1.5:3) M20
(cement:sand:aggregate) for R.C.C. work in
Sill & Lintel band including mixing, laying, Cu.m 0.42 16297.00 6,907.70
finishing to approved level, line and dimensions
and curing all complete as per specification.

C4 Form Work

19ft water proof plywood and steel prop


formwork for all works necessary propping,
scaffoldong, staging, supporting inclusive of Sq.m 91.67 923.00 84,607.29
wedging and cutting holes for utilization work
till the support is full unyielding net for
Column/Slab/Beam etc. complete work.
C5 Flooring & Finishing work
1 38 mm thick P.C.C. flooring (Screeding) in
(1:2:4) for floors & top of slab with approved
quality of cement, sand & crushed stone Sq.m 62.34 739.00 46,067.72
chips/aggregate including mixing,laying,curing
and finishing with a floating coat of neat
cement slurry.
2 3mm.thick Cement:Sand Punning (1:1) on
floor, dado and skirting etc. as per specification Sq.m 62.34 315.00 19,636.44
and direction complete work.
C6 Plastering & Pointing work
1 12.5 mm thick cement:sand (1:4) plaster on
walls of good finish including racking the joint, Sq.m 145.55 412.00 59,964.77
wetting of surfaces & curing the work all
complete.
2 12.5 mm thick cement:sand (1:3) plaster on
Ceiling of good finish including racking the Sq.m 62.71 480.00 30,100.57
joint, wetting of surfaces & curing the work all
complete.
3 Providing 2 mm thick White Putty on wall and
celling as per design drawing and specification Sq.m 208.26 293.00 61,018.74
all complete work.
C7 Painting work
Interior Walls: Supplying & laying two coat
1 distemper over 1 coat primer on to give
uniform colouring after rendering the surface all Sq.m 131.30 214.00 28,098.56
complete.
2
Exterior Walls: Supplying & laying two coat
weather proof emulsion paint over 1 coat Sq.m 76.95 357.00 27,472.37
primer on to give uniform colouring after
rendering the surface all complete.
3 Supplying & laying two coat enamel paint over
1 coat primer to give uniform colouring after Sq.m 6.27 355.00 2,226.19
rendering the surface all complete.
C8 Wood work
1 Supplying and fitting sal wooden chaukose
Cu.m 0.04 311688.00 13,969.02
with all neccessary hardware all complete.
2 Supplying and fitting Ready made Teak wood
Doors,special (Seasoned and Poisoned
treated ,one side teak and other side water proof Sq.m 2.79 9678.00 26,973.46
ply fitting) with all neccessary hardware all
complete.

Total Cost 852,290.09


Water Supply, Plumbing, Sanitary,
D,E,F Electrical Communication and Allied
Works (Buildings)
Remarks
MEASUREMENT SHEET
Project:
Location :
Year : 077/078
Height/
Item No. Item Description Nos. Length (ft) Breadth (ft) Quantity Total Quantity Unit Total Quantity Unit Remarks
Thickness (ft)
A Civil Works: Boundary Wall
A1 Earth Works
1 Earthwork in excavation in ordinary/medium rock by using
Manual means (without blasting) including disposal of
excavated earth, lead upto 10m and lift upto 1.5 m, disposed
earth to be levelled and neatly dressed.
Compound Wall
i. Footing
F1 221 4.00 4.00 3.00 10608.00
ii. Wall Footing 1 1131.00 1.25 1.50 2120.63
Total= 12728.63 12,728.63 Cu.ft 360.44 Cu.m

2 Earthwork in filling with approved earth upto plinth level


including, watering,compating by labour, dressing complete.
Earth Works
Backfilling 1 Taking 40% of excavation 5091.45
Total= 5091.45 5,091.45 Cu.ft 144.17 Cu.m

A2 Masonry Works
Providing Flat brick soling with sand fillings in joints and
1
bottom.
Compound Wall
i. Footing 221 4.00 4.00 3536.00
ii. Wall Footing 1 1131.00 1.25 1413.75
Total= 4949.75 4,949.75 Sq.ft 459.85 Sq.m

Brickwork in 1:4 (cement:sand) mortar in perfect line level


finish including wetting the bricks, racking the joints,
scaffolding and curing the work for at least 7 days all
complete.
Compound Wall
Upto Plinth Level
Wall 1 1131.00 0.833 1.50 1413.69
Above Plinth
Wall 1 1131.00 0.833 7.33 6908.59
Total = 8322.28 8,322.28 Cu.ft 235.66 Cu.m

A3 PCC works
Providing and Laying Plain Cement Concrete ( P.C.C.) in
(1:3:6) M10 (cement:sand:aggregate) in footing, wall
foundation and floors including mixing, laying, finishing to
approved level, line and dimensions and curing all complete as
per specification.
Compound Wall
i. Footing
F1 221 4.00 4.00 0.25 884.00
ii. Wall Footing 1 1131.00 1.25 0.25 353.44
Total= 1237.44 1,237.44 Cu.ft 35.04 Cu.m

A4 RCC work
1
Providing and Laying P.C.C.(1:1.5:3) M20 for R.C.C.work in
foundation, columns, beams, slabs etc. with cement, sand, and
aggregate including mixing with concrete mixture, compacting
the concrete with vibrator machine, laying, finishing to
approved level ,lines and dimensions and curing all complete
as per instruction of site Enginner.
Compound Wall
i. Footing
F1 221 4.00 4.00 1.00 3536.00 Uniform/rectangular part
F1 221 A1= 1.562Sq.ft A2= 16Sq.ft 0.75 1246.51 Sloped/trapezoidal part
Total = 4782.51
ii.Column
1)Upto Plinth
C1 (10"x10") 221 0.833 0.833 3.00 460.05
2)Above Plinth
C 1(10"x10") 221 0.833 0.833 7.33 1124.51
Total= 1584.56
ii. Beam
Plinth Tie Beam
(10"x10") 1 1131.00 0.833 0.833 784.79
(10"x10") 1 1131.00 0.833 0.833 784.79
Total = 1569.58
7,936.64 Cu.ft 224.74 Cu.m

A5 Reinforcement Work
Providing TMT Steel Reinforcement bars (Grade Fe500)
work including straightening, cleaning, cutting, bending,
binding with 20 SWG annealed wire & fixing in position as
per drawing, bar bending schedule for foundation, column,
beam, staircase, slab & in all R.C.C. works as per
specification, drawing.
Compound Wall
Footing 1.00% of RCC Work 10630.96
Columns 2.50% of RCC Work 8805.74
Beams 1.50% of RCC Work 5233.48
Total= 24670.18
10 % Wastage and Contingencies shall be added 2467.02
Total= 27137.19 27.14 MT 27.14 MT

A6 Form Work
19ft water proof plywood and steel prop formwork for all
works necessary propping, scaffoldong, staging, supporting
inclusive of wedging and cutting holes for utilization work till
the support is full unyielding net for Column/Slab/Beam etc.
complete work.
Compound Wall
i. Footing
F1 221 4.000 4.000 14144.00
Total= 14144.00
ii.Column
1)Upto Plinth
C1 (10"x10") 221 0.833 3.000 1104.56
2)Above Plinth
C 1(10"x10") 221 0.833 7.333 2699.907938
Total= 3804.47
ii. Beam
Plinth Tie Beam
(10"x10") 1 1131.00 0.833 1884.25
(10"x10") 1 1131.00 0.833 1884.25
Total= 3768.49
21,716.96 Sq.ft 2,017.57 Sq.m

A7 Plastering & Pointing work


1 12.5 mm thick cement:sand (1:4) plaster on walls of good
finish including racking the joint, wetting of surfaces & curing
the work all complete.
Compound Wall
Wall 2 2015.00 9.00 36270.00
Total= 36270.00
36,270.00 Sq.ft 3,369.59 Sq.m

3 Providing 2 mm thick White Putty on wall and celling as per


design drawing and specification all complete work.
Compound Wall
Plastered Walls 1 2015.00 9.00 18135.00
Total= 18135.00 18,135.00 Sq.ft 1,684.80 Sq.m

A8 Painting work
2 Exterior Walls: Supplying & laying two coat weather proof
emulsion paint over 1 coat primer on to give uniform
colouring after rendering the surface all complete.
Compound Wall
Plastered Walls 1 2015.00 9.00 18135.00
Total= 18135.00
18,135.00 Sq.ft 1,684.80 Sq.m

B Civil Works: GROUND FLOOR


B5 Flooring & Finishing work
1 38 mm thick P.C.C. flooring (Screeding) in (1:2:4) for
floors & top of slab with approved quality of cement, sand &
crushed stone chips/aggregate including mixing,laying,curing
and finishing with a floating coat of neat cement slurry.

First Floor 1 Floor Area = 7437.00 7437.00


Deduction of Columns
Stair Case 1 Floor Area = 478.00 -478.00
C1 (1'0"x1'0") 34 1.00 1.00 -34.00
0.00 6925.00 6,925.00 Sq.ft 643.35 Sq.m

2 3mm.thick Cement:Sand Punning (1:1) on floor, dado and


skirting etc. as per specification and direction complete work.

First Floor 1 Floor Area = 7437.00 7437.00


Deduction of Columns
Stari Case 1 Floor Area = 478.00 -478.00
C1 (1'0"x1'0") 34 1.00 1.00 -34.00
0.00 6925.00 6,925.00 Sq.ft 643.35 Sq.m

3 Providing and Laying 6 mm thick porcelain glazed Tiles on


floors & walls jointed with neat white cement slurry upon
20mm thick bed of white cement:sand mortar (1:4).

Toilet Floor 1 Floor Area= 298.00 298.00


Toilet Wall (9") 1 69.50 6.00 417.00
Toilet Wall (5") 1 95.17 6.00 571.00
Deduction
Doors D1-(3'x7'6") 3 3.00 7.50 -67.50
Doors D2-(2'6"x7') 3 2.50 7.00 -52.50
Ventilation V-(10'x2'0") 1 10.00 2.00 -20.00
0.00 1146.00 1,146.00 Sq.ft 106.47 Sq.m

B6 Plastering & Pointing work


1 12.5 mm thick cement:sand (1:4) plaster on walls of good
finish including racking the joint, wetting of surfaces & curing
the work all complete.

First Floor
Main Wall (9") 1 1455.00 9.50 13822.50
Half wall between columns (5") 1 138.50 10.50 1454.25
Main Beam at Entry
X-Direction 1 45.84 1.16 53.17
Y-Direction 2 26.84 1.16 62.27
Deduction
Windows W-(8'6''x6') 15 8.50 6.00 -765.00
Windows W1-(7'x20') 1 7.00 20.00 -140.00
Windows W2-(8'x6') 1 8.00 6.00 48.00
Windows W3-(10'x16') 1 10.00 16.00 160.00
Windows W4-(5'x6') 2 5.00 6.00 -60.00
Ventilation V-(10'x2') 1 10.00 2.00 -20.00
Doors D-(6'x7'6") 1 6.00 7.50 -45.00
Doors D1-(4'x7'6") 15 4.00 7.50 -450.00
Doors D2-(2'6"x7') 6 2.50 75.00 -1125.00
Channel Door CD-(8'x7'6") 2 8.00 7.50 -120.00
Total= 12875.19 12,875.19 Sq.ft 1,196.14 Sq.m
2 12.5 mm thick cement:sand (1:3) plaster on Ceiling of good
finish including racking the joint, wetting of surfaces & curing
the work all complete.

First Floor Ceiling 1 Floor Area = 7437.00 7437.00


Total= 7437.00 7,437.00 Sq.ft 690.92 Sq.m

3 Providing 2 mm thick White Putty on wall and celling as per


design drawing and specification all complete work.

Plastered Walls 1 12875.19


First Floor Ceiling 1 Total Area = 7437.00 7437.00
Total= 20312.19 20,312.19 Sq.ft 1,887.06 Sq.m

B7 Painting work
1 Interior Walls: Supplying & laying two coat distemper over
1 coat primer on to give uniform colouring after rendering the
surface all complete.

Plastered Walls 1 6236.93


First Floor Ceiling 1 Total Area = 7437.00 7437.00
Total= 13673.93 13,673.93 Sq.ft 1,270.35 Sq.m

2 Exterior Walls: Supplying & laying two coat weather proof


emulsion paint over 1 coat primer on to give uniform
colouring after rendering the surface all complete.

Floor
Main Wall (9") 2 335.00 11.00 7370.00
Main Beam in passage
X and Y-Direction 2 36.32 1.16 84.26
Deduction
Windows W-(8'6''x6') 15 8.50 6.00 -765.00
Windows W1-(7'x20') 1 7.00 2.00 -14.00
Windows W2-(8'x6') 1 8.00 6.00 48.00
Windows W3-(10'x16') 1 10.00 16.00 160.00
Windows W4-(5'x6') 2 5.00 6.00 -60.00
Ventilation V-(10'x2') 1 10.00 2.00 -20.00
Doors D-(6'x7'6") 1 6.00 7.50 -45.00
Channel Door CD-(8'x7'6") 2 8.00 7.50 -120.00
Total= 6638.26 6,638.26 Sq.ft 616.71 Sq.m
Supplying & laying two coat enamel paint over 1 coat primer
3 to give uniform colouring after rendering the surface all
complete.

Doors Factor
Doors D-(6'x7'6") 1 6.00 2.25 7.50 101.25
Doors D1-(4'x7'6") 15 4.00 2.25 7.50 1012.50
Doors D2-(2'6"x7') 6 2.50 2.25 7.00 236.25
Windows
Windows W-(8'6''x6') 15 8.50 1.50 6.00 1147.50
Windows W1-(7'x20') 1 7.00 1.50 20.00 210.00
Windows W4-(5'x6') 2 5.00 1.50 6.00 90.00
Windows W2-(8'x6') 1 8.00 6.00 48.00
Windows W3-(10'x16') 1 10.00 16.00 160.00
Ventilation
Ventilation V-(10'x2') 1 10.00 1.25 2.00 25.00
Total= 3030.50 3,030.50 Sq.ft 281.54 Sq.m

B8 Wood work
1 Supplying and fitting sal wooden chaukose with all
neccessary hardware all complete.

Doors
Doors D-(6'x7'6") 1 21.00 X-Sec = 0.083 1.75
Doors D1-(4'x7'6") 15 19.00 X-Sec = 0.083 23.74
Doors D2-(2'6"x7') 6 16.50 X-Sec = 0.083 8.25
Windows
Windows W-(8'6''x6') 15 58.00 X-Sec = 0.08 72.47
Windows W1-(7'x20') 1 95.00 X-Sec = 0.08 7.91
Windows W4-(5'x6') 2 38.00 X-Sec = 0.08 6.33
Windows W2-(8'x6') 1 8.00 X-Sec = 0.08 0.67
Windows W3-(10'x16') 1 10.00 X-Sec = 0.08 0.83
Ventilation
Ventilation V-(10'x2') 1 24.00 X-Sec = 0.08 2.00
Total= 123.95 123.95 Cu.ft 3.51 Cu.m

2
Supplying and fitting Ready made Teak wood Doors &
Windows special (Seasoned and Poisoned treated ,one side
teak and other side water proof ply fitting) with all neccessary
hardware all complete.

Doors
Doors D-(6'x7'6") 1 6.00 7.50 45.00
Doors D1-(4'x7'6") 15 4.00 7.50 450.00
Doors D2-(2'6"x7') 6 2.50 7.00 105.00
Windows
Windows W-(8'6''x6') 15 8.50 6.00 765.00
Windows W1-(7'x20') 1 7.00 20.00 140.00
Windows W4-(5'x6') 2 5.00 6.00 60.00
Windows W2-(8'x6') 1 8.00 6.00 48.00
Windows W3-(10'x16') 1 10.00 16.00 160.00
Ventilation
Ventilation V-(10'x2') 1 10.00 2.00 20.00
Total= 1793.00 1,793.00 Sq.ft 166.58 Sq.m

B9 Iron & Steel Work


Making and fitting fixing of stainless steel pipe railling in
balcony with 50ft.dia.stainless steel pipe handrail including
welding , cutting all complete.
1 52.00 52.00
1 90.00 90.00
Total= 142.00 142.00 Rft 43.28 Rm

B Civil Works: FIRST FLOOR


B1 Masonry Works

Brickwork in 1:4 (cement:sand) mortar in perfect line level


finish including wetting the bricks, racking the joints,
scaffolding and curing the work for at least 7 days all
complete.
Main Wall (9") 1 560.00 0.75 9.50 3990.00
Half wall between columns (5") 1 48.08 0.42 10.50 212.05
Design Walls Exterior
Y-Direction 6 4.00 1.25 20.00 600.00
X-Direction 4 4.00 1.25 20.00 400.00
Deduction
Windows W-(8'6''x6') 15 8.50 0.75 6.00 -573.75
Windows W2-(8'x6') 1 8.00 0.75 6.00 -36.00
Windows W4-(5'x6') 2 5.00 0.75 6.00 -45.00
Doors D-(6'x7'6") 2 6.00 0.75 7.50 -67.50
Doors D1-(4'x7'6") 6 4.00 0.75 7.50 -135.00
Doors D2-(2'6"x7') 3 2.50 0.75 7.00 -52.50
Total = 4292.30 4,292.30 Cu.ft 121.54 Cu.m

B2 RCC work
1
Providing and Laying P.C.C.(1:1.5:3) M20 for R.C.C.work in
foundation, columns, beams, slabs etc. with cement, sand, and
aggregate including mixing with concrete mixture, compacting
the concrete with vibrator machine, laying, finishing to
approved level ,lines and dimensions and curing all complete
as per instruction of site Enginner.

i. Column
First Floor
C1 (1'0"x1'0") 34 1.00 1.00 9.60 326.40
Total = 326.40
ii. Beam
First Floor Beam (Main Beam)
X-Direction (1'6"x1') 1 507.00 1.00 1.50 760.50
Y-Direction (1'6"x1') 1 463.00 1.00 1.50 694.50
Total = 1455.00
iv. Slab
First Floor Slab + Top (2') 1 Total Floor Area 7437.00 0.42 3123.54
Deduction of Staircase 1 Area = 0.00 0.42 0.00
Total = 3123.54
v. Stair Case
Slab (Landing +Waist) 1 Area = 33.17 0.42 13.93
Steps 21 6.08 1.00 0.50 63.87
Total = 77.80 4,982.74 Cu.ft 141.10 Cu.m

2 Providing and Laying Plain Cement Concrete ( P.C.C.)


(1:1.5:3) M20 (cement:sand:aggregate) for R.C.C. work in
Sill & Lintel band including mixing, laying, finishing to
approved level, line and dimensions and curing all complete as
per specification.

Main Wall (9") 1 560.00 0.75 0.25 105.00


Total = 105.00 105.00 Cu.ft 2.97 Cu.m

B3 Reinforcement Work
Providing TMT Steel Reinforcement bars (Grade Fe500)
work including straightening, cleaning, cutting, bending,
binding with 20 SWG annealed wire & fixing in position as
per drawing, bar bending schedule for foundation, column,
beam, staircase, slab & in all R.C.C. works as per
specification, drawing.
Total= 18815.37 18.82 MT 18.82 MT
B4 Form Work
19ft water proof plywood and steel prop formwork for all
works necessary propping, scaffoldong, staging, supporting
inclusive of wedging and cutting holes for utilization work till
the support is full unyielding net for Column/Slab/Beam etc.
complete work.

i.Column
First Floor
C1 (1'2"x1'2") 34 4.00 9.60 1305.60
Total= 1305.60
ii.Beam
First Floor Beam (Main Beam)
X-Direction (1'6"x1') 1 507.00 1.50 760.50
Y-Direction (1'6"x1') 1 463.00 1.50 694.50
Total= 1455.00
iii. Slab
First Floor Slab
Bottom 1 Floor Area = 7437.00 7437.00
Side 1 Perimeter = 0.00 0.42 0.00
Deduction of Staircase 1 Area = 0.00 0.00
Total= 7437.00
iv.Stair Case
Slab (Landing +Waist) Bottom 1 Floor Area = 7437.00 7437.00
Sides 1 Perimeter = 22.00 0.42 9.24
Steps 20 6.08 0.50 60.83
Total= 7507.07 17,704.67 Sq.ft 1,644.82 Sq.m

B5 Flooring & Finishing work


1 38 mm thick P.C.C. flooring (Screeding) in (1:2:4) for
floors & top of slab with approved quality of cement, sand &
crushed stone chips/aggregate including mixing,laying,curing
and finishing with a floating coat of neat cement slurry.

First Floor 1 Floor Area = 7437.00 7437.00


Deduction of Columns
Stair Case 1 Floor Area = 0.00 0.00
C1 (1'2"x1'2") 34 1.00 1.00 -34.00
Total= 7403.00 7,403.00 Sq.ft 687.76 Sq.m

2 3mm.thick Cement:Sand Punning (1:1) on floor, dado and


skirting etc. as per specification and direction complete work.

First Floor 1 Floor Area = 7437.00 7437.00


Deduction of Columns
Stari Case 1 Floor Area = 33.17 -33.17
C1 (1'2"x1'2") 34 1.00 1.00 -34.00
Total= 7369.83 7,369.83 Sq.ft 684.68 Sq.m

3 Providing and Laying 6 mm thick porcelain glazed Tiles on


floors & walls jointed with neat white cement slurry upon
20mm thick bed of white cement:sand mortar (1:4).

Toilet Floor 1 Floor Area= 284.00 284.00


Toilet Wall (9") 1 39.33 6.00 236.00
Toilet Wall (5") 1 125.58 6.00 753.50
Deduction
Doors D1-(4'x7'6") 3 4.00 7.50 -90.00
Doors D2-(2'6"x7') 3 2.50 7.00 -52.50
Ventilation V-(10'x2') 1 10.00 2.00 -20.00
Total= 1111.00 1,111.00 Sq.ft 103.22 Sq.m

B6 Plastering & Pointing work


1 12.5 mm thick cement:sand (1:4) plaster on walls of good
finish including racking the joint, wetting of surfaces & curing
the work all complete.

First Floor
Main Wall (9") 2 508.00 10.50 10668.00
Half wall between columns (5") 2 103.00 10.00 2060.00
Parapet Wall in F.F.
Y-Direction 2 105.00 3.00 630.00
X-Direction 2 230.00 3.00 1380.00
Main Beam
X-Direction 1 23.00 1.50 34.50
Y-Direction 1 26.82 1.50 40.23
Deduction
Windows W-(8'6"x6') 15 8.50 6.00 -765.00
Windows W2-(8'x6') 1 8.00 6.00 -48.00
Windows W3-(10'x16') 1 10.00 16.00 -160.00
Windows W4-(5'x6') 2 5.00 6.00 -60.00
Ventilation V-(10'x2') 1 10.00 2.00 -20.00
Doors D-(6'x7'6") 2 6.00 7.50 -90.00
Doors D1-(4'x7'6") 6 4.00 7.50 -180.00
Doors D2-(2'6"x7') 3 4.00 7.50 -90.00
Total= 13399.73 13,399.73 Sq.ft 1,244.88 Sq.m

2 12.5 mm thick cement:sand (1:3) plaster on Ceiling of good


finish including racking the joint, wetting of surfaces & curing
the work all complete.

First Floor Ceiling 1 Floor Area = 7437.00 7437.00


Total= 7437.00 7,437.00 Sq.ft 690.92 Sq.m

3 Providing 2 mm thick White Putty on wall and celling as per


design drawing and specification all complete work.

Plastered Walls 1 13399.73


First Floor Ceiling 1 Total Area = 7437.00 7437.00
Total= 20836.73 20,836.73 Sq.ft 1,935.79 Sq.m

B7 Painting work
1 Interior Walls: Supplying & laying two coat distemper over
1 coat primer on to give uniform colouring after rendering the
surface all complete.

Plastered Walls 1 8236.10


First Floor Ceiling 1 Total Area = 7437.00 7437.00
Total= 15673.10 15,673.10 Sq.ft 1,456.08 Sq.m

2 Exterior Walls: Supplying & laying two coat weather proof


emulsion paint over 1 coat primer on to give uniform
colouring after rendering the surface all complete.

First Floor
Main Wall (9") 1 358.00 11.00 3938.00
C1 (1'2"x1'2") 34 4.00 9.50 1292.00
Parapet Wall in F.F.
X-Direction 2 115.00 3.00 690.00
Y-Direction 2 52.50 3.00 315.00
Main Beam in passage
X and Y-Direction 1 34.42 1.50 51.63
Deduction
Windows W-(8'6"x6') 15 8.50 6.00 -765.00
Windows W2-(8'x6') 1 8.00 6.00 -48.00
Windows W3-(10'x16') 1 10.00 16.00 -160.00
Windows W4-(5'x6') 2 5.00 6.00 -60.00
Doors D-(6'x7'6") 2 6.00 7.50 -90.00
Total= 5163.63 5,163.63 Sq.ft 479.72 Sq.m
Supplying & laying two coat enamel paint over 1 coat primer
3 to give uniform colouring after rendering the surface all
complete.

Doors Factor
Doors D-(6'x7'6") 2 6.00 2.25 7.50 202.50
Doors D1-(4'x7'6") 6 4.00 2.25 7.50 405.00
Doors D2-(2'6"x7') 3 2.50 2.25 7.00 118.13
Windows
Windows W-(8'6"x6') 15 8.50 1.50 6.00 1147.50
Windows W2-(8'x6') 1 8.00 1.50 6.00 72.00
Windows W3-(10'x16') 1 10.00 1.50 16.00 240.00
Windows W4-(5'x6') 2 5.00 1.50 6.00 90.00
Ventilation
Ventilation V-(10'x2') 1 10.00 1.25 2.00 25.00
Total= 2300.13 2,300.13 Sq.ft 213.69 Sq.m

B8 Wood work
1 Supplying and fitting sal wooden chaukose with all
neccessary hardware all complete.

Doors
Doors D-(6'x7'6") 2 21.00 X-Sec = 0.08 3.50
Doors D1-(4'x7'6") 6 19.00 X-Sec = 0.08 9.50
Doors D2-(2'6"x7') 3 16.50 X-Sec = 0.08 3.96
Windows
Windows W-(8'6"x6') 15 49.50 X-Sec = 0.08 61.85
Windows W2-(8'x6') 1 48.00 X-Sec = 0.08 4.00
Windows W3-(10'x16') 1 52.00 X-Sec = 0.08 4.33
Windows W4-(5'x6') 2 38.00 X-Sec = 0.08 6.08
Ventilation
Ventilation V-(10'x2') 1 24.00 X-Sec = 0.08 2.00
Total= 95.21 95.21 Cu.ft 2.70 Cu.m

2
Supplying and fitting Ready made Teak wood Doors &
Windows special (Seasoned and Poisoned treated ,one side
teak and other side water proof ply fitting) with all neccessary
hardware all complete.

Doors
Doors D-(6'x7'6") 2 6.00 7.50 90.00
Doors D1-(4'x7'6") 6 4.00 7.50 180.00
Doors D2-(2'6"x7') 3 2.50 7.00 52.50
Windows
Windows W-(8'6"x6') 15 8.50 6.00 765.00
Windows W2-(8'x6') 1 8.00 6.00 48.00
Windows W3-(10'x16') 1 10.00 16.00 160.00
Windows W4-(5'x6') 2 5.00 6.00 60.00
Ventilation
Ventilation V-(10'x2') 1 10.00 2.00 20.00
Total= 1375.50 1,375.50 Sq.ft 127.79 Sq.m

B9 Iron & Steel Work


Making and fitting fixing of stainless steel pipe railling in
balcony with 50ft.dia.stainless steel pipe handrail including
welding , cutting all complete.
1 8.00 8.00
1 90.00 90.00
Top Floor 45 5.50 2" dia 247.50
Total= 345.50 345.50 Sq.ft 105.31 Rm

C Civil Works: TOP FLOOR(STAIRCASE COVER)


C1 Masonry Works
Brickwork in 1:4 (cement:sand) mortar in perfect line level
finish including wetting the bricks, racking the joints,
scaffolding and curing the work for at least 7 days all
complete.
Main Wall (9") 1 79.83 0.75 8.50 508.93
Deduction
Doors D1-(4'x7'6") 1 4.00 0.75 7.50 22.50
Total= 531.43 531.43 Cu.ft 15.05 Cu.m
C2 RCC work
1
Providing and Laying P.C.C.(1:1.5:3) M20 for R.C.C.work in
foundation, columns, beams, slabs etc. with cement, sand, and
aggregate including mixing with concrete mixture, compacting
the concrete with vibrator machine, laying, finishing to
approved level ,lines and dimensions and curing all complete
as per instruction of site Enginner.
i. Column
Top Floor
C1 (1'2"x1'2") 4 1.00 1.00 8.50 34.00
Total= 34.00
ii. Beam
First Floor Beam (Main Beam)
X-Direction (1'6"x1') 1 46.00 1.00 1.50 69.00
Y-Direction (1'6"x1') 1 42.00 1.00 1.50 63.00
Total= 132.00
iv. Slab
First Floor Slab + Top (2') 1 Total Floor Area 675.00 0.42 283.50
Total= 283.50 449.50 Cu.ft 12.73 Cu.m

2 Providing and Laying Plain Cement Concrete ( P.C.C.)


(1:1.5:3) M20 (cement:sand:aggregate) for R.C.C. work in
Sill & Lintel band including mixing, laying, finishing to
approved level, line and dimensions and curing all complete as
per specification.
Main Wall (9") 1 79.83 0.75 0.25 14.97
Total= 14.97 14.97 Cu.ft 0.42 Cu.m

C3 Form Work
19ft water proof plywood and steel prop formwork for all
works necessary propping, scaffoldong, staging, supporting
inclusive of wedging and cutting holes for utilization work till
the support is full unyielding net for Column/Slab/Beam etc.
complete work.

i.Column
Top Floor
C1 (1'2"x1'2") 4 4.00 8.50 136.00
Total= 136.00
ii.Beam
First Floor Beam (Main Beam)
X-Direction (1'6"x1') 1 46.00 1.50 69.00
Y-Direction (1'6"x1') 1 42.00 1.50 63.00
Total= 132.00
iii. Slab
First Floor Slab
Bottom 1 Total Floor Area 675.00 675.00
Side 1 Perimeter= 104.00 0.42 43.68
Total= 718.68 986.68 Sq.ft 91.67 Sq.m
C4 Flooring & Finishing work
1 38 mm thick P.C.C. flooring (Screeding) in (1:2:4) for
floors & top of slab with approved quality of cement, sand &
crushed stone chips/aggregate including mixing,laying,curing
and finishing with a floating coat of neat cement slurry.

Top Floor 1 Total Floor Area 675.00 675.00


Deduction of Columns
C1 (1'2"x1'2") 4 1.00 1.00 -4.00
Total= 671.00 671.00 Sq.ft 62.34 Sq.m

2 3mm.thick Cement:Sand Punning (1:1) on floor, dado and


skirting etc. as per specification and direction complete work.

Top Floor 1 Total Floor Area 675.00 675.00


Deduction of Columns
C1 (1'2"x1'2") 4 1.00 1.00 -4.00
Total= 671.00 671.00 Sq.ft 62.34 Sq.m

C5 Plastering & Pointing work


1 12.5 mm thick cement:sand (1:4) plaster on walls of good
finish including racking the joint, wetting of surfaces & curing
the work all complete.

TopFloor
Main Wall (9") 2 79.83 10.00 1596.64
Deduction
Doors D1-(4'x7'6") 1 4.00 7.50 -30.00
Total= 1566.64 1,566.64 Sq.ft 145.55 Sq.m

2 12.5 mm thick cement:sand (1:3) plaster on Ceiling of good


finish including racking the joint, wetting of surfaces & curing
the work all complete.

Top Floor Ceiling 1 Total Floor Area 675.00 675.00


Total= 675.00 675.00 Sq.ft 62.71 Sq.m

3 Providing 2 mm thick White Putty on wall and celling as per


design drawing and specification all complete work.

Plastered Walls 1 1566.64


Top Floor Ceiling 1 Total Floor Area 675.00 675.00
Total= 2241.64 2,241.64 Sq.ft 208.26 Sq.m

C6 Painting work
1 Interior Walls: Supplying & laying two coat distemper over
1 coat primer on to give uniform colouring after rendering the
surface all complete.

Plastered Walls 1 738.32


Top Floor Ceiling 1 Total Floor Area 675.00 675.00
Total= 1413.32 1,413.32 Sq.ft 131.30 Sq.m

2 Exterior Walls: Supplying & laying two coat weather proof


emulsion paint over 1 coat primer on to give uniform
colouring after rendering the surface all complete.

First Floor
Main Wall (9") 1 79.83 10.00 798.32
Deduction
Doors D1-(6'x7'6") 1 4.00 7.50 30.00
Total= 828.32 828.32 Sq.ft 76.95 Sq.m
Supplying & laying two coat enamel paint over 1 coat primer
3 to give uniform colouring after rendering the surface all
complete.

Doors Factor
Doors D1-(4'x7'6") 1 4.00 2.25 7.50 67.50
Total= 67.50 67.50 Sq.ft 6.27 Sq.m
C7 Wood work
1 Supplying and fitting sal wooden chaukose with all
neccessary hardware all complete.

Doors
Doors D1-(4'x7'6") 1 19.00 X-sec= 0.08 1.58
Total= 1.58 1.58 Cu.ft 0.04 Cu.m

2
Supplying and fitting Ready made Teak wood Doors &
Windows special (Seasoned and Poisoned treated ,one side
teak and other side water proof ply fitting) with all neccessary
hardware all complete.

Doors
Doors D1-(4'x7'6") 1 4.00 7.50 30.00
Total= 30.00 30.00 Sq.ft 2.79 Sq.m
Water Supply, Plumbing, Sanitary, Electrical
D,E,F
Communication and Allied Works (Buildings)
Sanitary fittings
soil pipe(6"@) m 80.00
Page 22 of 108

PROVISIONAL SUM
Project:
Location :
Year : 077/078

S.N. Description of Work Quantity Unit Rate Amount Remark

A Insurance Provision 185,189.44


B Laboratory Test Provision
Carrying out diferrent laboratory tests of construction
material like cement, rod, bricks, sand, aggregate, filling
materials, concrete cubes etc. during construction work as 1.00 P.S. 50,000.00 50,000.00
per specification and direction.
C As Built Drawings
Provision for as build drawings as per instruction all 1.00 P.S. 50,000.00 50,000.00
D complete.
Information Display Board ( IDB)
Preparation of Information Display Board displaying the
name,cost,contractor's name, employers' Name etc on 1.00 P.S. 15,000.00 15,000.00
board and fixing at site on wooden frame.
Total = 300,189.44 Nrs.

Prepared by: Checked by: Recommended by: Approved by:


BILL OF QUANTITY
Project:
Location :
Year : 077/078
Rate
Item No. Item Description Unit Quantity Amount Remarks
In Fig In Word
A Civil Works: Boundary Wall
A1 Earth Works
1 Earthwork in excavation in ordinary/medium
rock by using Manual means (without blasting)
including disposal of excavated earth, lead upto Cu.m 360.44 592.84 213,681.16
10m and lift upto 1.5 m, disposed earth to be
levelled and neatly dressed.
2 Earthwork in filling with approved earth upto
plinth level including, watering,compating by Cu.m 144.17 851.00 122,692.58
labour, dressing complete.
A2 Masonry Works
1 Providing Flat brick soling with sand fillings
Sq.m 459.85 929.60 427,471.40
in joints and bottom.
2 Brickwork in 1:4 (cement:sand) mortar in
perfect line level finish including wetting the
bricks, racking the joints, scaffolding and Cu.m 235.66 15211.00 3,584,655.33
curing the work for at least 7 days all complete.
A3 PCC works
Providing and Laying Plain Cement Concrete
( P.C.C.) in (1:3:6) M10
(cement:sand:aggregate) in footing, wall
foundation and floors including mixing, laying, Cu.m 35.04 12674.00 444,103.52
finishing to approved level, line and dimensions
and curing all complete as per specification.

A4 RCC work
1 Providing and Laying P.C.C.(1:1.5:3) M20 for
R.C.C.work in foundation, columns, beams,
slabs etc. with cement, sand, and aggregate
including mixing with concrete mixture,
Cu.m 224.74 16297.00 3,662,619.20
compacting the concrete with vibrator machine,
laying, finishing to approved level ,lines and
dimensions and curing all complete as per
instruction of site Enginner.
A5 Reinforcement Work

Providing TMT Steel Reinforcement bars


(Grade Fe500) work including straightening,
cleaning, cutting, bending, binding with 20 MT 27.14 131822.00 3,577,279.20
SWG annealed wire & fixing in position as per
drawing, bar bending schedule for foundation,
column, beam, staircase, slab & in all R.C.C.
works as per specification, drawing.
A6 Form Work

19ft water proof plywood and steel prop


formwork for all works necessary propping,
scaffoldong, staging, supporting inclusive of Sq.m 2017.57 923.00 1,862,217.61
wedging and cutting holes for utilization work
till the support is full unyielding net for
Column/Slab/Beam etc. complete work.
A7 Plastering & Pointing work
1 12.5 mm thick cement:sand (1:4) plaster on
walls of good finish including racking the joint, Sq.m 3369.59 412.00 1,388,271.83
wetting of surfaces & curing the work all
complete.
3 Providing 2 mm thick White Putty on wall and
celling as per design drawing and specification Sq.m 1684.80 293.00 493,645.20
all complete work.
A8 Painting work
2
Exterior Walls: Supplying & laying two coat
weather proof emulsion paint over 1 coat Sq.m 1684.80 357.00 601,472.14
primer on to give uniform colouring after
rendering the surface all complete.
Total Cost Of
16,378,109.15
Compound Wall

B Civil Works: GROUND FLOOR


B6 Flooring & Finishing work
1 38 mm thick P.C.C. flooring (Screeding) in
(1:2:4) for floors & top of slab with approved
quality of cement, sand & crushed stone
chips/aggregate including mixing,laying,curing
and finishing with a floating coat of neat Sq.m 643.35 739.00 475,438.07
cement slurry.

2 3mm.thick Cement:Sand Punning (1:1) on


floor, dado and skirting etc. as per specification Sq.m 643.35 315.00 202,656.28
and direction complete work.
3

Providing and Laying 6 mm thick porcelain Sq.m 106.47 3714.00 395,417.91


glazed Tiles on floors & walls jointed with neat
white cement slurry upon 20mm thick bed of
white cement:sand mortar (1:4).
B7 Plastering & Pointing work
1 12.5 mm thick cement:sand (1:4) plaster on
walls of good finish including racking the joint, Sq.m 1196.14 480.00 574,149.16
wetting of surfaces & curing the work all
complete.
2 12.5 mm thick cement:sand (1:3) plaster on
Ceiling of good finish including racking the Sq.m 690.92 293.00 202,439.45
joint, wetting of surfaces & curing the work all
complete.
3 Providing 2 mm thick White Putty on wall and
celling as per design drawing and specification Sq.m 1887.06 412.00 777,470.24
all complete work.
B8 Painting work
Interior Walls: Supplying & laying two coat
1 distemper over 1 coat primer on to give
uniform colouring after rendering the surface all Sq.m 1270.35 214.00 271,854.73
complete.
2
Exterior Walls: Supplying & laying two coat
weather proof emulsion paint over 1 coat Sq.m 616.71 357.00 220,167.07
primer on to give uniform colouring after
rendering the surface all complete.
3

Supplying & laying two coat enamel paint over Sq.m 281.54 355.00 99,947.60
1 coat primer to give uniform colouring after
rendering the surface all complete.
B9 Wood work
1
Cu.m 3.51 311688.00 1,093,994.79
Supplying and fitting sal wooden chaukose
with all neccessary hardware all complete.
2
Supplying and fitting Ready made Teak wood
Doors,special (Seasoned and Poisoned
treated ,one side teak and other side water proof Sq.m 166.58 9678.00 1,612,113.61
ply fitting) with all neccessary hardware all
complete.
B10 Iron & Steel Work -

Making and fitting fixing of stainless steel pipe


railling in balcony with 50ft.dia.stainless steel Rm 43.28 3045.25 131,803.29
pipe handrail including welding , cutting all
complete.
Total Cost Of
6,057,452.20
Ground Floor

C Civil Works: FIRST FLOOR


C1 Masonry Works
Brickwork in 1:4 (cement:sand) mortar in
perfect line level finish including wetting the
bricks, racking the joints, scaffolding and Cu.m 121.54 15803.00 1,920,775.38
curing the work for at least 7 days all complete.
C2 RCC works

Providing and Laying P.C.C.(1:1.5:3) M20 for


R.C.C.work in foundation, columns, beams,
slabs etc. with cement, sand, and aggregate
including mixing with concrete mixture,
1 Cu.m 141.10 16297.00 2,299,446.90
compacting the concrete with vibrator machine,
laying, finishing to approved level ,lines and
dimensions and curing all complete as per
instruction of site Enginner.

B3 Reinforcement Work

Providing TMT Steel Reinforcement bars


(Grade Fe500) work including straightening, MT 18.82 131822.00 2,480,279.89
cleaning, cutting, bending, binding with 20
SWG annealed wire & fixing in position as per
drawing, bar bending schedule for foundation,
column, beam, staircase, slab & in all R.C.C.
works as per specification, drawing.
2 Providing and Laying Plain Cement Concrete
( P.C.C.) (1:1.5:3) M20
(cement:sand:aggregate) for R.C.C. work in
Sill & Lintel band including mixing, laying,
finishing to approved level, line and dimensions Cu.m 2.97 16297.00 48,455.63
and curing all complete as per specification.

C4 Form Work

19ft water proof plywood and steel prop


Sq.m 1644.82 923.00 1,518,166.05
formwork for all works necessary propping,
scaffoldong, staging, supporting inclusive of
wedging and cutting holes for utilization work
till the support is full unyielding net for
Column/Slab/Beam etc. complete work.
C5 Flooring & Finishing work
1 38 mm thick P.C.C. flooring (Screeding) in
(1:2:4) for floors & top of slab with approved
quality of cement, sand & crushed stone
chips/aggregate including mixing,laying,curing
and finishing with a floating coat of neat Sq.m 687.76 739.00 508,255.31
cement slurry.

2 3mm.thick Cement:Sand Punning (1:1) on


floor, dado and skirting etc. as per specification Sq.m 684.68 315.00 215,673.98
and direction complete work.
3
Providing and Laying 6 mm thick porcelain
glazed Tiles on floors & walls jointed with neat Sq.m 103.22 3714.00 383,342.07
white cement slurry upon 20mm thick bed of
white cement:sand mortar (1:4).
C6 Plastering & Pointing work
1 12.5 mm thick cement:sand (1:4) plaster on
walls of good finish including racking the joint, Sq.m 1244.88 412.00 512,888.55
wetting of surfaces & curing the work all
complete.
2 12.5 mm thick cement:sand (1:3) plaster on
Ceiling of good finish including racking the Sq.m 690.92 480.00 331,641.41
joint, wetting of surfaces & curing the work all
complete.
Providing 2 mm thick White Putty on wall and
celling as per design drawing and specification Sq.m 1935.79 293.00 567,187.86
all complete work.
C7 Painting work
1 Interior Walls: Supplying & laying two coat
distemper over 1 coat primer on to give Sq.m 1456.08 214.00 311,600.69
uniform colouring after rendering the surface all
complete.
2
Exterior Walls: Supplying & laying two coat
weather proof emulsion paint over 1 coat Sq.m 479.72 357.00 171,258.87
primer on to give uniform colouring after
rendering the surface all complete.
3 Supplying & laying two coat enamel paint over
1 coat primer to give uniform colouring after Sq.m 213.22 355.00 75,693.10
rendering the surface all complete.
C8 Wood work
1 Supplying and fitting sal wooden chaukose
Cu.m 2.70 311688.00 840,367.55
with all neccessary hardware all complete.
2 Supplying and fitting Ready made Teak wood
Doors,special (Seasoned and Poisoned
treated ,one side teak and other side water proof Sq.m 127.79 9678.00 1,236,733.00
ply fitting) with all neccessary hardware all
complete.
C9 Iron & Steel Work
Making and fitting fixing of stainless steel pipe
railling in balcony with 50ft.dia.stainless steel
pipe handrail including welding , cutting all Rm 105.31 3045.25 320,690.41
complete.
Total Cost of
13,742,456.66
First Floor =
D Civil Works: TOP FLOOR
D1 Masonry Works
Brickwork in 1:4 (cement:sand) mortar in
perfect line level finish including wetting the
bricks, racking the joints, scaffolding and Cu.m 15.05 15803.00 237,811.05
curing the work for at least 7 days all complete.
D2 RCC work
Providing and Laying P.C.C.(1:1.5:3) M20 for
R.C.C.work in foundation, columns, beams,
slabs etc. with cement, sand, and aggregate
including mixing with concrete mixture,
Cu.m 12.73 16297.00 207,436.23
compacting the concrete with vibrator machine,
laying, finishing to approved level ,lines and
dimensions and curing all complete as per
instruction of site Enginner.
D3 PCC work
Providing and Laying Plain Cement Concrete
( P.C.C.) (1:1.5:3) M20
(cement:sand:aggregate) for R.C.C. work in
Sill & Lintel band including mixing, laying, Cu.m 0.42 16297.00 6,907.70
finishing to approved level, line and dimensions
and curing all complete as per specification.

D5 Form Work -

19ft water proof plywood and steel prop


formwork for all works necessary propping,
scaffoldong, staging, supporting inclusive of Sq.m 91.67 923.00 84,607.29
wedging and cutting holes for utilization work
till the support is full unyielding net for
Column/Slab/Beam etc. complete work.
D6 Flooring & Finishing work
1 38 mm thick P.C.C. flooring (Screeding) in
(1:2:4) for floors & top of slab with approved
quality of cement, sand & crushed stone Sq.m 62.34 739.00 46,067.72
chips/aggregate including mixing,laying,curing
and finishing with a floating coat of neat
cement slurry.
2 3mm.thick Cement:Sand Punning (1:1) on
floor, dado and skirting etc. as per specification Sq.m 62.34 315.00 19,636.44
and direction complete work.
D7 Plastering & Pointing work -
1 12.5 mm thick cement:sand (1:4) plaster on
walls of good finish including racking the joint, Sq.m 145.55 412.00 59,964.77
wetting of surfaces & curing the work all
complete.
2 12.5 mm thick cement:sand (1:3) plaster on
Ceiling of good finish including racking the Sq.m 62.71 480.00 30,100.57
joint, wetting of surfaces & curing the work all
complete.
3 Providing 2 mm thick White Putty on wall and
celling as per design drawing and specification Sq.m 208.26 293.00 61,018.74
all complete work.
D8 Painting work
Interior Walls: Supplying & laying two coat
1 distemper over 1 coat primer on to give
uniform colouring after rendering the surface all Sq.m 131.30 214.00 28,098.56
complete.
2
Exterior Walls: Supplying & laying two coat
weather proof emulsion paint over 1 coat Sq.m 76.95 357.00 27,472.37
primer on to give uniform colouring after
rendering the surface all complete.
3 Supplying & laying two coat enamel paint over
1 coat primer to give uniform colouring after Sq.m 6.27 355.00 2,226.19
rendering the surface all complete.
D9 Wood work -
1 Supplying and fitting sal wooden chaukose
Cu.m 0.04 311688.00 13,969.02
with all neccessary hardware all complete.
2 Supplying and fitting Ready made Teak wood
Doors,special (Seasoned and Poisoned
treated ,one side teak and other side water proof Sq.m 2.79 9678.00 26,973.46
ply fitting) with all neccessary hardware all
complete.
Total Cost of top
852,290.09
floor=
RATE ANALYSIS
Project:

Location :

Year : 076/077

RA No. : 1
Description of item : Site Clearance :Clearing of grass, removing roots breaking sods, levelling the surface and disposal to 10m.

Unit:

Resources
Norms Specification
Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity

DUDBC

A3 11 Unskilled md 0.023 715.00 16.45 tools 3 % of labour cost

Sub - total (A) 16.45 Sub - total (B) 0.00 Sub total (c)

Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per sq.m = 19.48

RA No. : 2
Description of item : Earthwork in excavation by using Manual means including shoring,struting,bracing,sheeting and disposal of excavated earth, lead upto 10m and lift upto 1.5 m, disposed earth to be levelled and neatly dressed.

a. soft clay and silty soil

Unit:

Resources
Norms Specification
Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity

DUDBC 11B

B1 Excavation Unskilled md 0.700 715.00 500.50 tools 3 % of labour cost

Sub - total (A) 500.50 Sub - total (B) 0.00 Sub total (c)

Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per cu.m = 592.84

RA No. : 3

Description of item : Earth filling in 150 mm thick layer, watering, ramming with 1 ton roller including supply of filling materials within 10 m LEAD all complete.

Unit:

Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)

Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
DUDBC 11B

B2,B6 Backfill Unskilled md 1.030 715.00 736.45 Excavated Eath as Fill cu.m 0.00 1 ton roller hr 0.0167

Water Ltr. 5.0 0.25 1.25

Sub - total (A) 736.45 Sub - total (B) 1.25 Sub total (c)

Note:Filler material is taken as 70% excavated earth and 30% borrowed material. Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per cu.m. 851.00

Description of works: Providing one layer Flat brick soling with sand fillings in joints and bottom.

Labour (A) Material (B) Equipment (C)


Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate

H15 Unskilled md 1.00 715.00 715.00 Brick nos 420.00 13.50 5670.00
Skilled md 0.50 1034.00 517.00 Sand m3 0.71 1664.00 1181.44

Sub total of A = 1232.00 Sub total of B = 6851.44 Sub total of C =


Sub total of A +B + C = 8083.44 Contractor's overhead expenses 15% = 1212.52 Unit Rate :

Rate(1m2) =
Chimney made Brickwork in 1:4 C/S mortar in ground floor in perfect line level finish including wetting the bricks, racking the joints, scaffolding and curing the work for at least 7 days with Lead upto 30m all
Description of item : complete.
Unit:

Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)

Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
DUDBC 11C

C2 Chimney Made Brick Nos 560.00 13.500 7560.00 tools 3 % of labour cost

Bricks Unskilled md 2.400 715.00 1716.00 Cement Mt 0.10 17680.000 1768.00

Skilled md 1.500 1034.00 1551.00 Sand cu.m 0.28 1664.00 465.92

Water Ltrs 130.00 0.52 67.60

Sub - total (A) 3267.00 Sub - total (B) 9861.52 Sub total (c)

Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per cu.m. 15211.00

RA No. : 4
Chimney made Brickwork in 1:4 C/S mortar in first floor in perfect line level finish including wetting the bricks, racking the joints,scaffolding and curing the work for at least 7 days with Lead upto 30m all complete.
Description of item :

Unit:

Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)

Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity
DUDBC 11C

C2 Chimney Made Brick Nos 560.00 13.500 7560.00 tools 3 % of labour cost

Bricks Unskilled md 3.100 715.00 2216.50 Cement Mt 0.10 17680.000 1768.00

Skilled md 1.500 1034.00 1551.00 Sand cu.m 0.28 1664.00 465.92

Water Ltrs 130.00 0.52 67.60

Sub - total (A) 3767.50 Sub - total (B) 9861.52 Sub total (c)

Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per cu.m. 15803.00

RA No. : 8
Description of item : Machine made Plain cement Concrete (PCC) in 1:3:6 ratio for foundations, flooring and walls with approved quality of cement and sand and crushed stone aggregate including mixing, laying, curing etc all complete in
approval of site engineer.
Unit:

Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)

Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity

D4 11D
0.2-0.28
hr 0.6000
Skilled md 0.50 1034.00 517.00 Cement Mt 0.220 17680.000 3889.60 m3 Mixer

Unskilled md 3.50 715.00 2502.50 40mm crushed aggregates cu.m 0.650 2964.000 1926.60 Vibrator hr 0.2500

20mm crushed aggregates cu.m 0.240 3068.00 736.32

Sand cu.m 0.425 1664.00 707.20

Water Ltrs 100.000 0.52 52.00

Diesel Ltrs 3.000 93.50 280.50

Petrol Ltrs 0.100 105.50 10.55

Sub - total (A) 3019.50 Sub - total (B) 7602.77 Sub total (c)

Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per cu.m. 12674.00

RA No. : 10
Description of item : Machine made Plain cement Concrete (PCC) in 1:1.5:3 ratio for superstructures with approved quality of cement and sand and crushed stone aggregate including mixing, laying, curing etc all complete in approval of
site engineer.
Unit:
Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)

Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity

D4 11D

Skilled md 0.50 1034.00 517.00 Cement Mt 0.400 17680.000 7072.00 0.2-0.28 m3hr 0.6000

Unskilled md 3.50 715.00 2502.50 40mm crushed aggregates cu.m 0.570 2964.000 1689.48 Vibrator hr 0.2500

20mm crushed aggregates cu.m 0.290 3068.000 889.72

Sand cu.m 0.425 1664.000 707.20

Water Ltrs 200.000 0.520 104.00

Diesel Ltrs 3.000 93.500 280.50

Petrol Ltrs 0.100 105.500 10.55

Sub - total (A) 3019.50 Sub - total (B) 10753.45 Sub total (c)

Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per cu.m. 16297.00

RA No. : 11
Description of item : Providing and laying Reinforcement including cutting, bending, binding, fixing in position and lead 30m. etc. all complete as per specification and drawing.

Unit:

Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)

Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity

D9 7,5

Skilled md 12.00 1034.00 12408.00 MS Reinforcement Mt 1.050 88000.000 92400.00

Unskilled md 12.00 715.00 8580.00 Binding Wire cu.m 10.000 124.000 1240.00

Sub - total (A) 20988.00 Sub - total (B) 93640.00 Sub total (c)

Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per MT 131822.00

RA No. : 12
Description of item : Formwork, shuttering, centering with 19mm thick waterproof ply board and steel post for all works necessary propping, scaffolding, staging, supporting inclusive of wedging and cutting holes for utilization till the
support if fully unyielding nett.
Unit:

Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)

Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity

E6 11E

Skilled md 17.20 1034.00 17784.80 19mm Ply Board sq.m 16.500 1572.000 25938.00

Unskilled md 25.70 715.00 18375.50 Wood cu.m 0.230 33000.000 7590.00

Steel Posts nos 4.400 1771.000 7792.40

Nails, screws kg 25.000 110.000 2750.00

Sub - total (A) 36160.30 Sub - total (B) 44070.40 Sub total (c)

Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per sq.m. 923.00

RA No. : 23
Description of item : 38 mm Cement Concrete Fooring (Screeding) 1:2:4 finished with a floating coat of neat cement slurry.

Unit:

Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)

Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity

H1

Skilled md 1.25 1034.00 1292.50 Cement mt 0.130 17680.000 2298.40

Unskilled md 2.00 715.00 1430.00 Sand cu.m 0.1800 1664.000 299.52

12mm Aggregate cu.m 0.3600 3068.000 1104.48


Sub - total (A) 2722.50 Sub - total (B) 3702.40 Sub total (c)

Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per sq.m. 739.00

Description of item : 3mm cement punning floor finishing work, over 38mm Cement Sand screeding work all complete.[H20]

Unit:

Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)

Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity

H20

Skilled md 1.00 1034.00 1034.00 Cement mt 0.053 17600.000 936.32 tools 3 % of labour cost

Unskilled md 1.00 715.00 715.00

Sub - total (A) 1749.00 Sub - total (B) 936.32 Sub total (c)

Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per sq.m. 315.00

RA No. : 22
Description of item : Porcelain Glazed Tiles in floor, walls, jointed with neat white cement slurry upon 20mm thick bed of white cement mortar 1:4(1cement:4coarse sand)

Unit:

Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)

Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity

H6

Skilled md 13.00 1034.00 13442.00 Cement mt 0.056 17680.000 990.08 tools 3 % of labour cost

Unskilled md 4.50 715.00 3217.50 Sand cu.m 0.1520 1664.000 252.93

White Cement kg 3.2280 52.000 167.86

Tiles sq.m 11.0000 1248.000 13728.00

Sub - total (A) 16659.50 Sub - total (B) 15138.86 Sub total (c)

Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per sq.m. 3714.00

Description of item : 12.5mm thick cement sand plaster in (1:4) ratio on wall of good finish including racking the joint, wetting of surfaces & curing the work all complete.

Unit:

Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)

Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity

I1

Skilled md 12.00 1034.00 12408.00 Cement mt 0.538 17680.000 9511.84

Unskilled md 16.00 715.00 11440.00 Sand cu.m 1.4600 1664.000 2429.44

Sub - total (A) 23848.00 Sub - total (B) 11941.28 Sub total (c)

Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per sq.m. 412.00

RA No. : 31
Description of item : 12.5mm thick cement sand plaster in (1:4) ratio on ceiling of good finish including racking the joint, wetting of surfaces & curing the work all complete.
Unit:

Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)

Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity

I1

Skilled md 15.00 1034.00 15510.00 Cement mt 0.538 17680.000 9511.84

Unskilled md 20.00 715.00 14300.00 Sand cu.m 1.4600 1664.000 2429.44

Sub - total (A) 29810.00 Sub - total (B) 11941.28 Sub total (c)

Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per sq.m. 480.00

RA No. : 35
Description of item : Providing 2 mm thick White Putty on wall and celling as per design drawing and specification all complete work.

Unit:
Resources
Norms Specification
Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity

J5 Skilled md 1.00 1034.00 1034.00 White Putty kg 10.640 70.000 744.80 tools 3 % of labour cost

Unskilled md 1.00 715.00 715.00

Sub - total (A) 1749.00 Sub - total (B) 744.80 Sub total (c)

Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per sq.m. 293.00

RA No. : 32
Description of item : Colouring with two coat distemper paint with one coat primer to give uniform colouring after rendering the surface all complete.

Unit:

Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)

Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity

J26

Skilled md 5.80 1034.00 5997.20 Primer lit 8.000 312.000 2496.00 tools 3 % of labour cost

Unskilled md 5.80 715.00 4147.00 Distemper Paint kg 16.0000 353.000 5648.00

Sub - total (A) 10144.20 Sub - total (B) 8144.00 Sub total (c)

Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per sq.m. 214.00

RA No. : 33
Description of item : Colouring with two coat weather proof exterior emulsion paint with one coat primer to give uniform colouring after rendering the surface all complete.

Unit:

Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)

Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity

J5

Skilled md 12.00 1034.00 12408.00 Primer lit 8.100 312.000 2527.20

Unskilled md 8.00 715.00 5720.00 Emulsion Paint lit 16.0000 650.000 10400.00

Sub - total (A) 18128.00 Sub - total (B) 12927.20 Sub total (c)

Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per sq.m. 357.00


RA No. : 34
Description of item : Two Coats of Enamel painting on Door Frames and Panel including one coat of Primer all complete.

Unit:

Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)

Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity

J5 Skilled md 12.00 1034.00 12408.00 Primer lit 8.100 312.000 2527.20 tools 3 % of labour cost

Unskilled md 8.00 715.00 5720.00 Enamel Paint lit 16.0000 603.000 9648.00

Sub - total (A) 18128.00 Sub - total (B) 12175.20 Sub total (c)

Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per sq.m. 355.00

RA No. : 13
Description of item : Well seasoned salwood chaukhats for fixed/openable door/windows with good finish of approved quality incuding fixing in postion with necessary M.S. hold fasts as per drawing and instruction all complete.

Unit:

Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)

Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity

F21 11G

Skilled md 34.00 1034.00 35156.00 Sal Wood cu.m 1.100 208000.000 228800.00

Unskilled md 3.40 715.00 2431.00 Hold Fast nos. 92.000 46.000 4232.00

Screws/nails nos. 184.000 2.25 414.00

Sub - total (A) 37587.00 Sub - total (B) 233446.00 Sub total (c)

Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per cu.m. 311688.00

Description of item : Making and fitting fixing flush door shutter of 38 x 100 mm size sal wood frame with 4 mm teak ply on both side including all necessary hardware fitting all complete.

Unit:

Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)

Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity

G4 11G

Skilled md 7.00 1034.00 7238.00 Sal Wood cu.m 0.035 208000.000 7196.80 tools 3 % of labour cost

Unskilled md 0.70 715.00 500.50 4 mm Teak PlyWood sq.m 4.650 598.000 2780.70

100 mm Hinge nos. 3.000 41.00 123.00

150 mm chesken nos. 2.000 83.00 166.00

Mortice Lock nos. 1.000 676.00 676.00

Screws/nails LS 1.000 0.00 0.00

Sub - total (A) 7738.50 Sub - total (B) 10942.50 Sub total (c)

Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per Sq.m. 9678.00

Description of item : Fixing of glazed shutter in 38x75 mm thick sal wood frame with 4 mm thick plain glass fitted including all necessary hardware fittings all complete.

Unit:

Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)

Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity

G3 11G

Skilled md 9.00 1034.00 9306.00 Sal Wood cu.m 0.049 208000.000 10192.00 tools 3 % of labour cost

Unskilled md 0.90 715.00 643.50 4 mm Glass sq.m 1.085 832.000 902.72


75mm Hinge nos. 8.000 36.40 291.20

100 mm chesken nos. 4.000 62.40 249.60

Handle nos. 2.000 197.60 395.20

Screws/nails LS 1.000 55.00 55.00

Sub - total (A) 9949.50 Sub - total (B) 12085.72 Sub total (c)

Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per Sq.m. 11517.00

RA No. : 20
Description of item : Making and fitting fixing of stainless steel pipe raillingfor staircase with 3 rows of 25 mm.dia.stainless steel pipe horizontal rails and 25 mm.dia.stainless steel pipe for vertical post @ 2m. c/c including welding , cutting
all complete.
Unit:

Resources
Norms Specification
activity Clause Labour (A) Materials (B) Equipment (C)

Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity

M15

Skilled md 7.78 1034.00 8044.52 Cutting,drilling ,grindi 5 % of Steel cost

Unskilled md 11.35 715.00 8115.25 25 mm steel pipe m 36.0000 210.000 7560.00 welding machine etc.

Sub - total (A) 16159.77 Sub - total (B) 7560.00 Sub total (c)

Direct Cost (A+B+C) = NRs.

Contractor's Overhead @ 15 % of (A+B+C) = NRs.

Total Item Rate = NRs.

Say NRs. per sq.m. 3029.00


1.00 sq.m

Rate Amount

3 % of labour cost 0.49

0.49

16.94

2.54

19.48

osed earth to be levelled and neatly dressed.

1.00 cu.m

Equipment (C)

Rate Amount

3 % of labour cost 15.02

15.02

515.52

77.33

592.84

1.00 cu.m.

Equipment (C)

Rate Amount

125.00 2.09

2.09

739.79

110.97

850.76

Unit : 10m2

ment (C)

Amount
0.00
9295.96

929.60
ork for at least 7 days with Lead upto 30m all

1.00 cu.m

Equipment (C)

Rate Amount

3 % of labour cost 98.01

98.01

13226.53

1983.98

15210.51

or at least 7 days with Lead upto 30m all complete.

1.00 cu.m

Equipment (C)

Rate Amount

3 % of labour cost 113.03

113.03

13742.05

2061.31

15803.35

including mixing, laying, curing etc all complete in

1.00 cu.m

Equipment (C)

Rate Amount

550.00 330.00

275.00 68.75

398.75

11021.02

1653.15

12674.17

mixing, laying, curing etc all complete in approval of

1.00 cu.m
Equipment (C)

Rate Amount

550.00 330.00

275.00 68.75

398.75

14171.70

2125.76

16297.46

1.00 MT

Equipment (C)

Rate Amount

0.00

114628.00

17194.20

131822.20

wedging and cutting holes for utilization till the

100.00 sq.m

Equipment (C)

Rate Amount

0.00

80230.70

12034.61

92265.31

10.00 sq.m

Equipment (C)

Rate Amount
0.00

6424.90

963.74

7388.64

10.00 sq.m

Equipment (C)

Rate Amount

3 % of labour cost 52.47

52.47

2737.79

410.67

3148.46

10.00 sq.m

Equipment (C)

Rate Amount

3 % of labour cost 499.79

499.79

32298.15

4844.72

37142.87

100.00 sq.m

Equipment (C)

Rate Amount

0.00

35789.28

5368.39

41157.67
100.00 sq.m

Equipment (C)

Rate Amount

0.00

41751.28

6262.69

48013.97

10.00 sq.m

Equipment (C)

Rate Amount

3 % of labour cost 52.47

52.47

2546.27

381.94

2928.21

100.00 sq.m

Equipment (C)

Rate Amount

3 % of labour cost 304.33

304.33

18592.53

2788.88

21381.40

100.00 sq.m

Equipment (C)

Rate Amount

0.00

31055.20

4658.28

35713.48
100.00 sq.m

Equipment (C)

Rate Amount

3 % of labour cost 543.84

543.84

30847.04

4627.06

35474.10

per drawing and instruction all complete.

1.00 cu.m

Equipment (C)

Rate Amount

0.00

271033.00

40654.95

311687.95

te.

2.25 sq.m

Equipment (C)

Rate Amount

3 % of labour cost 232.16

232.16

18913.16

2836.97

21750.13

2.23 sq.m

Equipment (C)

Rate Amount

3 % of labour cost 298.49


298.49

22333.71

3350.06

25683.76

for vertical post @ 2m. c/c including welding , cutting

9.15 sq.m

Equipment (C)

Rate Amount

5 % of Steel cost 378.00

378.00

24097.77

3614.67

27712.44
S.No. Description No. No. of Bars

3 Beam

Main Beam

Along Grid A-A, B-B, C-C, D-D

Common main bar of Beam 12"*12" &12"*18"


4 2
20 mm through bar (Top Bar)
4 2
16 mm through bar(Bottom Bar)

Remaining main bar of Beam 12"*16"


4 2
20 mm through bar (Top Bar)
4 2
16 mm through bar(Bottom Bar)

Extra Bar

Along Grid A-A, B-B, C-C, D-D in Grid 1-1,4-4,5-5 & 8-8

For Beam 12"*12"


16 2
20 mm extra bar (Top Bar)

Along Grid A-A, B-B, C-C, D-D in Grid 2-2,3-3,6-6&7-7

16 mm extra bar (Top Bar) 16 2


Along Grid A-A, B-B, C-C, D-D between Grid 1 to 4 & 5 to
8
24 2
12 mm extra bar (Bottom Bar)

Along Grid 1-1 to 3-3 &6-6 to 8-8

For Beam 12"*14"


12 2
20 mm through bar (Top Bar)
12 2
16 mm through bar(Bottom Bar)

Along Grid 4-4 & 5-5


2 2
20 mm through bar (Top Bar)
2 2
16 mm through bar(Bottom Bar)
2 2
20 mm through bar (Top Bar)
2 2
16 mm through bar(Bottom Bar)

Along Grid 1-1 to 8-8


8 2
16 mm through bar (Top Bar)
8 2
16 mm through bar(Bottom Bar)
8 2
12 mm through bar(Bottom Bar)

Extra Bar

For Beam 12"*14"

Along Grid 1-1 to 8-8 Between A-A & B-B


14 2
20 mm extra bar (Top Bar)
2 2
20 mm extra bar (Top Bar) between A'A' & AA
2 2
20 mm extra bar (Top Bar) between AA & BB

Along Grid 1-1 to 8-8


16 2
16 mm extra bar (Bottom Bar) between AA & BB
2 2
16 mm extra bar (Bottom Bar) between A'A' & AA

For Beam 12"*14" & 12"*16"


20 2
20 mm extra bar (Top Bar)

For Beam 12"*16"

Along Grid 1-1 to 8-8 Between B-B & C-C


16 2
16 mm extra bar (Bottom Bar)

Stirrups

For Beam 12"*12"

Along A-A to D-D


4 99
2-L-8mm dia. @ 4" c/c
4 174
2-L-8mm dia. @ 6" c/c
For Beam 12"*18"

Along A'-A' to D-D


5 15
2-L-8mm dia. @ 4" c/c
5 34
2-L-8mm dia. @ 6" c/c
For Beam 12"*14"

Along 1-1 to 8-8


8 29
2-L-8mm dia. @ 4" c/c
8 58
2-L-8mm dia. @ 6" c/c

Remaining part along 4-4 & 5-5


2 15
2-L-8mm dia. @ 4" c/c
2 15
2-L-8mm dia. @ 6" c/c
For Beam 12"*16"

Along 1-1 to 8-8


8 15
2-L-8mm dia. @ 4" c/c
8 13
2-L-8mm dia. @ 6" c/c
Dia of Bars (mm) Cutting Length (ft) Total Length (ft) Total Length (m) Wt/m (kg/m)

20 120.83 966.64 294.6 2.47

16 119.20 953.60 290.7 1.58

16 29.07 232.56 70.9 1.58

20 27.40 219.20 66.8 2.47

20 8.00 256.00 78.0 2.47

320.00 97.5 1.58


16 10.00

12 6.00 288.00 87.8 0.89

20 26.92 646.08 196.9 2.47

16 25.25 606.00 184.7 1.58

20 39.33 157.32 48.0 2.47


16 37.67 150.68 45.9 1.58

20 26.92 107.68 32.8 2.47

16 25.25 101.00 30.8 1.58

16 16.83 269.28 82.1 1.58

16 16.83 269.28 82.1 1.58

12 15.17 242.72 74.0 0.89

20 10.27 287.56 87.6 2.47

20 7.72 30.88 9.4 2.47

20 10.73 42.92 13.1 2.47

16 7.20 230.40 70.2 1.58

16 4.97 19.88 6.1 1.58

20 13.60 544.00 165.8 2.47

16 4.60 147.20 44.9 1.58


8 3.50 1384.04 421.9 0.40

8 3.50 2432.64 741.5 0.40

8 5.17 388.01 118.3 0.40

8 5.17 878.90 267.9 0.40

8 4.50 1042.56 317.8 0.40

8 4.50 2100.96 640.4 0.40

8 4.50 135.09 41.2 0.40

8 4.50 130.50 39.8 0.40

8 4.50 540.36 164.7 0.40

8 4.50 455.76 138.9 0.40

Total
Total Quantity Unit(Kg) Remarks

727.49

459.31

112.01

164.97

192.66

154.13

78.03

486.24

291.89

118.40 Between A'A' &BB


72.58 Between A'A' &BB

81.04 Between CC & DD

48.65 Between CC & DD

129.70

129.70

65.76

216.42 Except 44&55

23.24 Along 44 & 55

32.30 Along 44 & 55

110.97

9.58

409.41 Maximum dia. Taken

70.90
166.66

292.93

Between 44&55
46.72
Between 44&55
105.83

125.54

252.99

16.27

15.71

65.07

54.88
Kg
5327.96
S.No. Description No. No. of Bars

3 Beam

Main Beam

Along Grid A-A, B-B, C-C, D-D

Common main bar of Beam 12"*12" &12"*18"


4 2
20 mm through bar (Top Bar)
4 2
16 mm through bar(Bottom Bar)

Remaining main bar of Beam 12"*18"


4 2
16 mm through bar (Top Bar)
4 2
12 mm through bar (Top Bar)
4 2
20 mm through bar(Bottom Bar)
4 2
12 mm through bar(Bottom Bar)

Extra Bar
Along Grid A-A, B-B, C-C, D-D in Grid 1-1,4-4,5-5 & 8-
8

For Beam 12"*12"


16 2
20 mm extra bar (Top Bar)

Along Grid A-A, B-B, C-C, D-D in Grid 2-2,3-3,6-6&7-7

16 mm extra bar (Top Bar) 16 2


Along Grid A-A, B-B, C-C, D-D between Grid 1 to 4 & 5
to 8
24 2
12 mm extra bar (Bottom Bar)

Along Grid 1-1 to 3-3 &6-6 to 8-8

For Beam 12"*14"


12 2
20 mm through bar (Top Bar)
12 2
16 mm through bar(Bottom Bar)
Along Grid 4-4 & 5-5
2 2
20 mm through bar (Top Bar)
2 2
16 mm through bar(Bottom Bar)
2 2
20 mm through bar (Top Bar)
2 2
16 mm through bar(Bottom Bar)

Along Grid 1-1 to 8-8


8 2
16 mm through bar (Top Bar)
8 2
16 mm through bar(Bottom Bar)
8 2
12 mm through bar(Bottom Bar)

Extra Bar

For Beam 12"*14"

Along Grid 1-1 to 8-8 Between A-A & B-B


14 2
20 mm extra bar (Top Bar)
2 2
20 mm extra bar (Top Bar) between A'A' & AA
2 2
20 mm extra bar (Top Bar) between AA & BB

Along Grid 1-1 to 8-8


16 2
16 mm extra bar (Bottom Bar) between AA & BB
2 2
16 mm extra bar (Bottom Bar) between A'A' & AA

For Beam 12"*14" & 12"*16"


20 2
20 mm extra bar (Top Bar)

For Beam 12"*16"

Along Grid 1-1 to 8-8 Between B-B & C-C


16 2
16 mm extra bar (Bottom Bar)

Stirrups
For Beam 12"*12"

Along A-A to D-D


4 99
2-L-8mm dia. @ 4" c/c
4 174
2-L-8mm dia. @ 6" c/c
For Beam 12"*18"

Along A'-A' to D-D


5 15
2-L-8mm dia. @ 4" c/c
5 34
2-L-8mm dia. @ 6" c/c
For Beam 12"*14"

Along 1-1 to 8-8


8 29
2-L-8mm dia. @ 4" c/c
8 58
2-L-8mm dia. @ 6" c/c

Remaining part along 4-4 & 5-5


2 15
2-L-8mm dia. @ 4" c/c
2 15
2-L-8mm dia. @ 6" c/c
For Beam 12"*16"

Along 1-1 to 8-8


8 15
2-L-8mm dia. @ 4" c/c
8 13
2-L-8mm dia. @ 6" c/c
Dia of Bars (mm) Cutting Length (ft) Total Length (ft) Total Length (m) Wt/m (kg/m)

20 120.83 966.64 294.6 2.47

16 119.20 953.60 290.7 1.58

16 27.40 219.20 66.8 1.58

12 25.80 206.40 62.9 0.89

20 29.00 232.00 70.7 2.47

12 25.80 206.40 62.9 0.89

20 8.00 256.00 78.0 2.47

320.00 97.5 1.58


16 10.00

12 6.00 288.00 87.8 0.89

20 26.92 646.08 196.9 2.47

16 25.25 606.00 184.7 1.58


20 39.33 157.32 48.0 2.47

16 37.67 150.68 45.9 1.58

20 26.92 107.68 32.8 2.47

16 25.25 101.00 30.8 1.58

16 16.83 269.28 82.1 1.58

16 16.83 269.28 82.1 1.58

12 15.17 242.72 74.0 0.89

20 10.27 287.56 87.6 2.47

20 7.72 30.88 9.4 2.47

20 10.73 42.92 13.1 2.47

16 7.20 230.40 70.2 1.58

16 4.97 19.88 6.1 1.58

20 13.60 544.00 165.8 2.47

16 4.60 147.20 44.9 1.58


8 3.50 1384.04 421.9 0.40

8 3.50 2432.64 741.5 0.40

8 5.17 388.01 118.3 0.40

8 5.17 878.90 267.9 0.40

8 4.50 1042.56 317.8 0.40

8 4.50 2100.96 640.4 0.40

8 4.50 135.09 41.2 0.40

8 4.50 130.50 39.8 0.40

8 4.50 540.36 164.7 0.40

8 4.50 455.76 138.9 0.40

Total
Total Quantity Unit(Kg) Remarks

727.49

459.31

105.58

55.92

174.60

55.92

192.66

154.13

78.03

486.24

291.89
118.40
Between A'A' &BB
72.58
Between A'A' &BB
81.04
Between CC & DD
48.65
Between CC & DD

129.70

129.70

65.76

216.42
Except 44&55
23.24
Along 44 & 55
32.30
Along 44 & 55

110.97

9.58

409.41
Maximum dia. Taken

70.90
166.66

292.93

46.72
Between 44&55
105.83
Between 44&55

125.54

252.99

16.27

15.71

65.07

54.88

5443.00 Kg
BAR BENDING
Project:
Location :
Year: 077/078
S.No. Description No. No. of Bars Dia of Bars (mm)

4 SLAB
Ground Floor Slab
Bottom Bar
10 mm dia @ 6" c/c in X-direction Through 231 10
Bar
10 mm dia @ 6" c/c in Y-direction Through 107 10
Bar
Remaining Part
10 mm dia @ 6" c/c in X-direction Through
Bar
10 mm dia @ 6" c/c in Y-direction Through 53 10
Bar 24 10
Deduction
10 mm dia @ 6" c/c in X-direction Through
43 10
Bar
10 mm dia @ 6" c/c in Y-direction Through
Bar 28 10

Top Bar
10 mm dia @ 6" c/c in X-direction Through
139 10
Bar
10 mm dia @ 6" c/c in Y-direction Through
Bar 66 10
Deduction
10 mm dia @ 6" c/c in X-direction Through
43 10
Bar
10 mm dia @ 6" c/c in Y-direction Through
Bar 13 10

Extra Top Bar


10 mm dia @ 6" c/c in X-direction Extra Bar 2 62 10
10 mm dia @ 6" c/c in X-direction Extra Bar 2 77 10
10 mm dia @ 6" c/c in X-direction Extra Bar 1 16 10
10 mm dia @ 6" c/c in X-direction
Y-direction Extra Bar
Through 1 16 10
Bar
10 mm dia @ 6" c/c in Y-direction Through 2 9 10
Bar
10 mm dia @ 6" c/c in Y-direction Through 2 35 10
Bar
10 mm dia @ 6" c/c in Y-direction Through 3 35 10
Bar
10 mm dia @ 6" c/c in Y-direction Through 1 14 10
Bar
10 mm dia @ 6" c/c in Y-direction Through 1 14 10
Bar 2 22 10

First Floor Slab


Bottom
10 Bar@ 6" c/c in X-direction Through
mm dia
Bar
10 mm dia @ 6" c/c in Y-direction Through 231 10
Bar 107 10
Remaining
10 mm dia @Part
6" c/c in X-direction Through
Bar 53 10
10 mm dia @ 6" c/c in Y-direction Through
Bar 24 10
Deduction
10 mm dia @ 6" c/c in X-direction Through
Bar
10 mm dia @ 6" c/c in Y-direction Through 43 10
Bar 28 10

Top Bar
10 mm dia @ 6" c/c in X-direction Through
Bar
10 mm dia @ 6" c/c in Y-direction Through 139 10
Bar 66 10
Deduction
10 mm dia @ 6" c/c in X-direction Through
Bar
10 mm dia @ 6" c/c in Y-direction Through 43 10
Bar 13 10

Extra Top Bar


10 mm dia @ 6" c/c in X-direction Extra Bar 2 62 10
10 mm dia @ 6" c/c in X-direction Extra Bar 2 77 10
10 mm dia @ 6" c/c in X-direction Extra Bar 1 16 10
X-direction Through
10 mm dia @ 6" c/c in Y-direction Extra Bar 1 16 10
Bar
10 mm dia @ 6" c/c in Y-direction Through 2 9 10
Bar
10 mm dia @ 6" c/c in Y-direction Through 2 35 10
Bar
10 mm dia @ 6" c/c in Y-direction Through 3 35 10
Bar
10 mm dia @ 6" c/c in Y-direction Through 1 14 10
Bar
10 mm dia @ 6" c/c in Y-direction Through 1 14 10
Bar 2 22 10
20
20

6
6

4
4

9
9

9
9

9
9

3
3

20
20

6
6

4
4

9
9

9
9

9
9

3
2-L-8mm dia. @ 6" c/c 3 12 8
BAR BENDING SCHEDULE

Cutting Length (ft) Total Length (ft) Total Length (m) Wt/m (kg/m) Total Quantity

57.00 13167.00 4013.3 0.62 2477.35

120.00 12840.00 3913.6 0.62 2415.82

12 658.26 200.6 0.62 123.85


28.00 667.52 203.5 0.62 125.59

-13.58 -583.94 -178.0 0.62 -109.87


-21.00 -591.36 -180.2 0.62 -111.26

57.00 7923.00 2414.9 0.62 1490.70


120.00 7881.60 2402.3 0.62 1482.91

-6.17 -265.31 -80.9 0.62 -49.92

-21.00 -280.14 -85.4 0.62 -52.71

8.67 1080.98 329.5 0.62 203.38


10.50 1617.00 492.9 0.62 304.24
10.81 169.28 51.6 0.62 31.85
6.70 104.92 32.0 0.62 19.74
9.83 182.44 55.6 0.62 34.33
8.00 564.80 172.2 0.62 106.27
10.00 1059.00 322.8 0.62 199.25
5.50 78.87 24.0 0.62 14.84
6.17 88.48 27.0 0.62 16.65
13.00 572.00 174.3 0.62 107.62
Total 8830.62

57.00 13167.00 4013.3 0.62 2477.35


120.00 12840.00 3913.6 0.62 2415.82

12 658.26 200.6 0.62 123.85


28.00 667.52 203.5 0.62 125.59

-13.58 -583.94 -178.0 0.62 -109.87


-21.00 -591.36 -180.2 0.62 -111.26

57.00 7923.00 2414.9 0.62 1490.70


120.00 7881.60 2402.3 0.62 1482.91

-6.17 -265.31 -80.9 0.62 -49.92


-21.00 -280.14 -85.4 0.62 -52.71

8.67 1080.98 329.5 0.62 203.38


10.50 1617.00 492.9 0.62 304.24
10.81 169.28 51.6 0.62 31.85
6.70 104.92 32.0 0.62 19.74
9.83 182.44 55.6 0.62 34.33
8.00 564.80 172.2 0.62 106.27
10.00 1059.00 322.8 0.62 199.25
5.50 78.87 24.0 0.62 14.84
6.17 88.48 27.0 0.62 16.65
13.00 572.00 174.3 0.62 107.62
Total 8830.62
3.50 124.32 37.9 0.40 14.97
Unit(Kg) Remarks

Along AA & DD
Along BB & CC
Along AA
Along A'A'
Along 44 & 55
Along 11 & 88
Along 22,33 & 77
Along 44 betwee CC & DD
Along 55 betwee CC & DD
Along 44 &55 between AA & CC
Kg
Along AA & DD
Along BB & CC
Along AA
Along A'A'
Along 44 & 55
Along 11 & 88
Along 22,33 & 77
Along 44 betwee CC & DD
Along 55 betwee CC & DD
Along 44 &55 between AA & CC
Kg
BAR BENDING SC
Project:
Location :
Year: 077/078
S.No. Description No. No. of Bars Dia of Bars (mm)

1 Column
C1
Plinth Level to Ground Floor
20 mm dia. Bar 8 8 20
C2
Plinth Level to Ground Floor
25 mm dia. Bar 2 4 25
16 mm dia. Bar 2 4 16
C3
Plinth Level to Ground Floor
25 mm dia. Bar 16 4 25
20 mm dia. Bar 16 4 20
C4
Plinth Level to Ground Floor
25 mm dia. Bar 8 8 25
C1
Ground Floor to First Floor
20 mm dia. Bar 8 8 20
C2
Ground Floor to First Floor
25 mm dia. Bar 2 4 25
16 mm dia. Bar 2 4 16
C3
Ground Floor to First Floor
25 mm dia. Bar 16 4 25
20 mm dia. Bar 16 4 20
C4
Ground Floor to First Floor
25 mm dia. Bar 8 8 25
C4
First Floor to Roof Floor
25 mm dia. Bar 4 8 25

Lateral Ties upto Plinth Level


8mm dia. @ 100mm c/c
TYPE I 34 41 8
TYPE II 34 9 8
Lateral Ties from Plinth Level to Ground
Floor
8mm dia. @ 4" c/c
TYPE I 34 11 8
TYPE II 34 11 8
8mm dia. @ 6" c/c
TYPE I 34 14 8
TYPE II
Lateral Ties from Ground Floor to First 34 14 8
Floor
8mm dia. @ 4" c/c
TYPE I 34 11 8
TYPE II 34 11 8
8mm dia. @ 6" c/c
TYPE I 34 14 8
TYPE II 34 14 8
Lateral Ties from First Floor to Roof Floor
8mm dia. @ 4" c/c
TYPE I 4 11 8
TYPE II 4 11 8
8mm dia. @ 6" c/c
TYPE I 4 14 8
TYPE II 4 14 8

2 Beam
Grid A-A, B-B, C-C, D-D
Plinth/Tie Beam
Top Bar
16mm dia Through Bar 4 3 16
Bottom Bar
16mm dia Through Bar 4 3 16
Grid 1-1,2-2,3-3,6-6,7-7,8-8
Plinth/Tie Beam
Top Bar
16mm dia Through Bar 6 3 16
Bottom Bar
16mm dia Through Bar 6 3 16
Grid 4-4,5-5
Top Bar
16mm dia Through Bar 2 3 16
Bottom Bar
16mm dia Through Bar 2 3 16
Secondary Beam Along X-direction
Top Bar
16mm dia Through Bar 2 3 16
Bottom Bar
16mm dia Through Bar 2 3 16
Secondary Beam Along Y-direction
Top Bar
16mm dia Through Bar 1 3 16
Bottom Bar
16mm dia Through Bar 1 3 16

STIRRUPS
Plinth/Tie Beam
Along Grid A-A, B-B, C-C, D-D between 1-
1&2-2,2-2&3-3,3-3&4-4,6-6&7-7,7-7&8-8
2-L-8mm dia. @ 4" c/c 20 16 8
2-L-8mm dia. @ 6" c/c 20 19 8
Along Grid A-A, B-B, C-C, D-D between 4-
4&5-5
2-L-8mm dia. @ 4" c/c 6 16 8
2-L-8mm dia. @ 6" c/c 6 33 8
Along Grid A-A, B-B, C-C, D-D between 5-
5&6-6
2-L-8mm dia. @ 4" c/c 4 16 8
2-L-8mm dia. @ 6" c/c 4 23 8
Along Grid 1-1 to 8-8 between A-A & B-B
2-L-8mm dia. @ 4" c/c 9 16 8
2-L-8mm dia. @ 6" c/c 9 27 8
Along Grid 1-1 to 8-8 between B-B & C-C
2-L-8mm dia. @ 4" c/c 9 16 8
2-L-8mm dia. @ 6" c/c 9 12 8
Along Grid 1-1 to 8-8 between C-C & D-D
2-L-8mm dia. @ 4" c/c 9 16 8
2-L-8mm
Along dia.4-4,5-5
Grid @ 6" c/c
& SB between A-A & 9 27 8
A'-A'
2-L-8mm dia. @ 4" c/c 3 16 8
2-L-8mm dia. @ 6" c/c 3 12 8
BAR BENDING SCHEDULE

Cutting Length (ft) Total Length (ft) Total Length (m) Wt/m (kg/m) Total Quantity

11.00 704.00 214.6 2.47 529.83

11.00 88.00 26.8 3.86 103.48


11.00 88.00 26.8 1.58 42.39

11.00 704.00 214.6 3.86 827.85


11.00 704.00 214.6 2.47 529.83

11.00 704.00 214.6 3.86 827.85

11.00 704.00 214.6 2.47 529.83

11.00 88.00 26.8 3.86 103.48


11.00 88.00 26.8 1.58 42.39

11.00 704.00 214.6 3.86 827.85


11.00 704.00 214.6 2.47 529.83

11.00 704.00 214.6 3.86 827.85

9.50 304.00 92.7 3.86 357.48

3.50 4849.25 1478.1 0.40 583.92


2.62 789.25 240.6 0.40 95.04

3.50 1279.25 389.9 0.40 154.04


2.62 957.61 291.9 0.40 115.31
3.50 1666.00 507.8 0.40 200.61
2.62 1247.12 380.1 0.40 150.17

3.50 1279.25 389.9 0.40 154.04


2.62 957.61 291.9 0.40 115.31

3.50 1666.00 507.8 0.40 200.61


2.62 1247.12 380.1 0.40 150.17

3.50 147.14 44.8 0.40 17.72


2.62 110.14 33.6 0.40 13.26

3.50 191.24 58.3 0.40 23.03


2.62 143.16 43.6 0.40 17.24
Total 8070.40

120.00 1440.00 438.9 1.58 693.59

120.00 1440.00 438.9 1.58 693.59

57.50 1035.00 315.5 1.58 498.52

57.50 1035.00 315.5 1.58 498.52

69.91 419.46 127.9 1.58 202.04

69.91 419.46 127.9 1.58 202.04

28.00 168.00 51.2 1.58 80.92

28.00 168.00 51.2 1.58 80.92

49.92 149.76 45.6 1.58 72.13

49.92 149.76 45.6 1.58 72.13

3.50 1120.00 341.4 0.40 134.86


3.50 1330.00 405.4 0.40 160.15
3.50 336.00 102.4 0.40 40.46
3.50 693.00 211.2 0.40 83.45

3.50 224.00 68.3 0.40 26.97


3.50 322.00 98.1 0.40 38.77

3.50 504.00 153.6 0.40 60.69


3.50 850.50 259.2 0.40 102.41

3.50 504.00 153.6 0.40 60.69


3.50 388.71 118.5 0.40 46.81

3.50 504.00 153.6 0.40 60.69


3.50 850.50 259.2 0.40 102.41

3.50 168.00 51.2 0.40 20.23


3.50 124.32 37.9 0.40 14.97
Total 4047.96
Unit(Kg) Remarks

3218.70
691.38

Kg
Kg
BAR BENDING SC
Project:

Location :

Year: 077/078
S.No. Description No. No. of Bars Dia of Bars (mm) Cutting Length (ft)

5 STAIR

Ground Floor to First Floor

For First Flight

Main Bar
12 mm dia main bar
2 13 12 21.58
12 mm dia main bar(Extra)
2 13 12 10.00
12 mm dia main bar(Extra)
2 13 12 9.30
12 mm dia main bar(Extra)
4 13 12 5.30
For Second Flight

Main Bar
12 mm dia main bar
1 13 12 24.00
12 mm dia main bar(Extra)
2 13 12 10.66
12 mm dia main bar(Extra)
2 13 12 5.66

Distribution Bar

For First Flight

At the top main bar


2 32 8 6.00
8 mm dia Distribution Bar

At the Bottom main bar upto 0.33L


4 15 8 6.00
8 mm dia Distribution Bar

At the 0.33L main bar


4 9 8 6.00
8 mm dia Distribution Bar
For Second Flight

At the top main bar


1 34 8 6.00
8 mm dia Distribution Bar

At the Bottom main bar upto 0.33L


1 15 8 6.00
8 mm dia Distribution Bar

At the 0.33L main bar


2 9 8 6.00
8 mm dia Distribution Bar
22 10 8 4.50
8 mm nosing tie bar
1 22 8 6.00
8 mm nosing bar
AR BENDING SCHEDULE

Total Length (ft) Total Length (m) Wt/m (kg/m) Total Quantity Unit(Kg)

561.08 171.0 0.89 152.02

260.00 79.2 0.89 70.44

241.80 73.7 0.89 65.51

275.60 84.0 0.89 74.67

312.00 95.1 0.89 84.53

277.16 84.5 0.89 75.09

147.16 44.9 0.89 39.87

382.44 116.6 0.40 46.05

348.00 106.1 0.40 41.90

215.88 65.8 0.40 26.00


204.00 62.2 0.40
24.56

92.94 28.3 0.40


11.19

113.88 34.7 0.40


13.71
990.00 301.8 0.40
119.21
132.00 40.2 0.40
15.89
Total
860.66
Remarks

For third flight also

For third flight also

For third flight also

For third flight also

562.13
184.57
Summary
Ground Floor Kg 0.000 MT

First Floor 18815.37


Kg 18.815 MT

Roof Floor Kg 0.000 MT

Total 18815.371
Kg 18.815 MT
Aurahi Municipality Officer of municipal executiveAurahi, mahottari state No:-2, Nepal RATE ANALYSIS 2076-07

1 Site clearance work

Clearing and grubbing including the cutting of trees ( If necessary ) having girth of less than 30 cm when measured at 1m above the ground
Norms no- 1 Page no 20 Dolidar
Respective clauses of specifications 1-1.5(a),1-1.5(b), and 1-1.6

Sources Level Qty Unit Rate Amount VAT in Material


Skilled 0 Md 1034.00 0.00
Labour
Unskilled 0.04 Md 715.00 28.60
Sub Total (L) 28.60
T.& P. 3% of labour cost 0.86
Total 29.46
Actual Rate 29.46
15% Contractor's overhead 4.42
Rate per sqm ( Contractor's Rate) 33.88
Rate per sqm ( User's Rate) 29.46

Excavation for structures


( III ) Marshy soil ( Per m3 )
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 0.00 Md 1034.00 0.00
Labour
Unskilled 3.00 Md 715.00 2145.00
Sub Total (L) 2145.00
T.& P. 3% of labour cost 64.35
Total 2209.35
Actual Rate 2209.35
15% Contractor's overhead 331.40
Rate per Cum ( Contractor's Rate) 2540.75
Rate per Cum ( User's Rate) 2209.35

Excavation for structures


( IV ) Ordinary rock ( Per m3 )
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 0.00 Md 1034.00 0.00
Labour
Unskilled 4.00 Md 715.00 2860.00
Sub Total (L) 2860.00
T.& P. 3% of labour cost 85.80
Total 2945.80
Actual Rate 2945.8
15% Contractor's overhead 441.87
Rate per Cum ( Contractor's Rate) 3387.67
Rate per Cum ( User's Rate) 2945.80

Earth filling with ordinary soil in layers of 15 ,15 cm and compacting manually with water sprinkling
23
NN 2 ( 25) Ka Page-11 Old For 1 Cum

Sources Level Qty Unit Rate Amount VAT in Material


Skilled 0.00 Md 1034.00 0.00
Labour
Unskilled 0.50 Md 715.00 357.50
Sub Total (L) 357.50
T.& P. 3% of labour cost 10.73
Total 368.23
Actual Rate 368.225
15% Contractor's overhead 55.23
Rate per Cum ( Contractor's Rate) 423.46
Rate per Cum ( User's Rate) 368.23

Earth filling with ordinary soil in layers of 15 ,15 cm and compacting manually with no water sprinkling
24
NN 2 ( 25) Kha Page-11 Old For 1 Cum

Sources Level Qty Unit Rate Amount VAT in Material


Skilled 0.00 Md 1034.00 0.00
Labour
Unskilled 0.25 Md 715.00 178.75
Sub Total (L) 178.75
T.& P. 3% of labour cost 5.36
Total 184.11
Actual Rate 184.1125
15% Contractor's overhead 27.62
Rate per Cum ( Contractor's Rate) 211.73
Rate per Cum ( User's Rate) 184.11

26 Brick masonry in 1:3 c/s mix ratio


N.N. 37 ( a) Page 37(Dolidar)
Respective clause specification 7 For 1 m3

Sources Level Qty Unit Rate Amount VAT in Material


Skilled 1.00 Md 1034.00 1034.00
Labour
Unskilled 3.97 Md 715.00 2838.55
Sub Total (L) 3872.55
T.& P. 3% of labour cost 116.18
Total 3988.73
Cement OPC Nepali 130.00 Kg 17.68 2298.40 298.79
Sand 0.33 Cum 1664.00 549.12
Material Bricks 530.00 No 13.52 7165.60 931.53
Bamboo 2.00 No 312.00 624.00
Ropes 1.00 Kg 166.40 166.40

Sub Total (M) 10803.52


Total Rate ( L+M+T.P.) 14792.25 1230.32
15% Contractor's overhead 2218.84
Aurahi Municipality Officer of municipal executiveAurahi, mahottari state No:-2, Nepal RATE ANALYSIS 2076-07

Rate per Cum ( Contractor's Rate) Excluding VAT 17011.08


Rate per Cum ( User's Rate) Including VAT in Material 16022.57
27 Brick masonry in 1:4 c/s mix ratio
N.N. 37 ( b) Page 37(Dolidar)
Respective clause specification 7 For 1 m3

Sources Level Qty Unit Rate Amount VAT in Material


Skilled 1.00 Md 1034.00 1034.00
Labour
Unskilled 3.99 Md 715.00 2852.85
Sub Total (L) 3886.85
T.& P. 3% of labour cost 116.61
Total 4003.46
Cement 100.00 Kg 17.68 1768.00 229.84
Sand 0.35 Cum 1664.00 582.40
Material Bricks 530.00 No 13.52 7165.60 931.53
Bamboo 2.00 No 312.00 624.00
Ropes 1.00 Kg 166.40 166.40

Sub Total (M) 10306.40


Total Rate ( L+M+T.P.) 14309.86 1161.37
15% Contractor's overhead 2146.48
Rate per Cum ( Contractor's Rate) Excluding VAT 16456.33
Rate per Cum ( User's Rate) Including VAT in Material 15471.22

12.5 mm thick plastering with cement sand mortar on brick walls or concretesurface with all necessary operation including full compensationfor all
labour materials scaffolding and other incidentals required to complete the work as per the specifications.

B In1:3 mix ratio


N.N. 37 (B) Page 38(Dolidar)
Respective clause specification 7-9.4,7-12 and 7.13.2
For 100 m2

Sources Level Qty Unit Rate Amount VAT in Material

Skilled 12.00 Md 1034.00 12408.00


Labour
Unskilled 11.50 Md 715.00 8222.50
Sub Total (L) 20630.50
T.& P. 3% of labour cost 618.92
Total 21249.42
Cement 463.00 Kg 17.68 8185.84 1064.16
Sand 1.38 m3 1664.00 2296.32
Material
Bamboo 2.00 No 312.00 624.00
Ropes 1.00 Kg 166.40 166.40

Sub Total (M) 11272.56


Total Rate ( L+M+T.P.) 32521.98 1064.16
15% Contractor's overhead 4878.30
Rate per Sqm ( Contractor's Rate) Excluding VAT 374.00
Rate per Sqm ( User's Rate) Including VAT in Material 335.86

12.5 mm thick plastering with cement sand mortar on brick walls or concretesurface with all necessary operation including full compensationfor all
labour materials scaffolding and other incidentals required to complete the work as per the specifications.

C In1:4 mix ratio


N.N. 37 (B) Page 38(Dolidar)
Respective clause specification 7-9.4,7-12 and 7.13.2
For 100 m2

Sources Level Qty Unit Rate Amount VAT in Material

Skilled 12.00 Md 1034.00 12408.00


Labour
Unskilled 11.59 Md 715.00 8286.85
Sub Total (L) 20694.85
T.& P. 3% of labour cost 620.85
Total 21315.70
Cement 363.00 Kg 17.68 6417.84 834.32
Sand 1.46 m3 1664.00 2429.44
Material
Bamboo 2.00 No 312.00 624.00
Ropes 1.00 Kg 166.40 166.40

Sub Total (M) 9637.68


Total Rate ( L+M+T.P.) 30953.38 834.32
15% Contractor's overhead 4643.01
Rate per Sqm ( Contractor's Rate) Excluding VAT 355.96
Rate per Sqm ( User's Rate) Including VAT in Material 317.88

12.5 mm thick plastering with cement sand mortar on brick walls or concretesurface with all necessary operation including full compensationfor all
labour materials scaffolding and other incidentals required to complete the work as per the specifications.

D In1:6 mix ratio


N.N. 37 (B) Page 38(Dolidar)
Aurahi Municipality Officer of municipal executiveAurahi, mahottari state No:-2, Nepal RATE ANALYSIS 2076-07

Respective clause specification 7-9.4,7-12 and 7.13.2


For 100 m2

Sources Level Qty Unit Rate Amount VAT in Material

Skilled 12.00 Md 1034.00 12408.00


Labour
Unskilled 11.70 Md 715.00 8365.50
Sub Total (L) 20773.50
T.& P. 3% of labour cost 623.21
Total 21396.71
Cement 288.00 Kg 17.68 5091.84 661.94
Sand 1.58 m3 1664.00 2629.12
Material
Bamboo 2.00 No 312.00 624.00
Ropes 1.00 Kg 166.40 166.40

Sub Total (M) 8511.36


Total Rate ( L+M+T.P.) 29908.07 661.94
15% Contractor's overhead 4486.21
Rate per Sqm ( Contractor's Rate) Excluding VAT 343.94
Rate per Sqm ( User's Rate) Including VAT in Material 305.70

35 3 mm thick cement Rubbing ( Punning) work


NN 11 (20) Page 66(Old)
For 10 m2
Sources Level Qty Unit Rate Amount VAT in Material

Skilled 1.00 Md 1034.00 1034.00


Labour
Unskilled 1.00 Md 715.00 715.00
Sub Total (L) 1749.00
T.& P. 0% of labour cost 0.00
Total 1749.00
Material Cement 53.20 Kg 17.68 940.58 122.27

s Sub Total (M) 940.58


Total Rate ( L+M+T.P.) 2689.58 122.27
15% Contractor's overhead 403.44
Rate per Sqm ( Contractor's Rate) Excluding VAT 309.30
Rate per Sqm ( User's Rate) Including VAT in Material 281.19

36 20 mm thick plaster in 1:3 c/s


N.N. 12 (4), Ka Page 68(Old)
For 100 m2
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 14.00 Md 1034.00 14476.00
Labour
Unskilled 19.00 Md 715.00 13585.00
Sub Total (L) 28061.00
T.& P. 0% of labour cost 0.00
Total 28061.00
Cement 960.00 Kg 17.68 16972.80 2206.46
Material
Sand 1.95 m3 1664.00 3244.80
Sub Total (M) 20217.60
Total Rate ( L+M+T.P.) 48278.60 2206.46
15% Contractor's overhead 7241.79
Rate per Sqm ( Contractor's Rate) Excluding VAT 555.20
Rate per Sqm ( User's Rate) Including VAT in Material 504.85

37 20 mm thick plaster in 1:4 c/s


N.N. 12 (4), Kha Page 68(Old)
For 100 m2
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 14.00 Md 1034.00 14476.00
Labour
Unskilled 19.00 Md 715.00 13585.00
Sub Total (L) 28061.00
T.& P. 0% of labour cost 0.00
Total 28061.00
Cement 810.00 Kg 17.68 14320.80 1861.70
Material
Sand 2.20 m3 1664.00 3660.80
Sub Total (M) 17981.60
Total Rate ( L+M+T.P.) 46042.60 1861.70
15% Contractor's overhead 6906.39
Rate per Sqm ( Contractor's Rate) Excluding VAT 529.49
Rate per Sqm ( User's Rate) Including VAT in Material 479.04

Formwork with timber as material. It includes all labour, materials, and other incidentals required for the construction and removal of forms as
described in the specifications. It further covers the framing work that is required for properly supporting the members until the concrete is
sufficiently curd, setand hardened.ONLY FOR BRIDGE
42

A Beam or slab ( Formwork and framework when the height is 4-8m i.e.above 4m.
N.N. 39 Page 43(Dolidar)
Respective clause specification 9
For 10 m2
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 1.25 Md 1034.00 1292.50
Labour
Aurahi Municipality Officer of municipal executiveAurahi, mahottari state No:-2, Nepal RATE ANALYSIS 2076-07

Labour
Unskilled 1.75 Md 715.00 1251.25
Sub Total (L) 2543.75
T.& P. 3% of labour cost 76.31
Total 2620.06
Timber planks/Board 0.75 m3 10400.00 7800.00
Post,batten and un-sawn timber 0.50 m3 1733.33 866.67
Material
Nails 3.50 Kg 140.40 491.40 63.88

Sub Total (M) 9158.07


Total Rate ( L+M+T.P.) 11778.13 63.88
15% Contractor's overhead 1766.72
Rate per Sqm ( Contractor's Rate) Excluding VAT 1354.48
Rate per Sqm ( User's Rate) Including VAT in Material 1184.20

Reinforcement for RCC work. It includes procuring steels, its bending,placing, binding and fixing in position as shown on the drawings and as
43 directed by the engineer. It also includes all devices for keeping reinforcement in approved position and jointing as per approved method with due
allowance for wastage overlapes spacer bars and annealed steel wire for bending

N.N. 40 Page 44(Dolidar)


Respective clause specification 10
For 1000 Kg
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 7.00 Md 1034.00 7238.00
Labour
Unskilled 7.00 Md 715.00 5005.00
Sub Total (L) 12243.00
T.& P. 3% of labour cost 367.29
Total 12610.29
Steel 1050.00 Kg 88.40 92820.00 12066.60
Material Binding wire 10.00 Kg 124.80 1248.00 162.24

Sub Total (M) 94068.00


Total Rate ( L+M+T.P.) 106678.29 12228.84
15% Contractor's overhead 16001.74
Rate per Kg( Contractor's Rate) Excluding VAT 122.68
Rate per Kg ( User's Rate) Including VAT in Material 118.91

Cement concreting work. It includes all labour and material required for mixing, placing in position,Vibrating,compacting,finishing, curing and all
44 other incidentals required to produce concrete of specified strength as per the specifications. The rate includesthe work of making, fixing, and
removing of all centres and forms required for the works

A-a M10 Grade ( 1:3:6 mix ) PCC work in foundtion ( Including form work)
N.N. 41 Page 46(Dolidar)
Respective clause specification 11
For 1 m3

Sources Level Qty Unit Rate Amount VAT in Material

Skilled 0.66 Md 1034.00 682.44


Labour
Unskilled 3.67 Md 715.00 2624.05
Sub Total (L) 3306.49
T.& P. 3% of labour cost 99.19

Total 3405.68
Cement 220.00 Kg 17.68 3889.60 505.65
Sand 0.47 m3 1664.00 782.08
Material Aggregate- 40mm 0.65 m3 2158.00 1402.70
Aggregate- 20mm 0.24 m3 2236.00 536.64
Aggregate- 10mm m3 1820.00 0.00
Timber 0.055 m3 10400.00 572.00

Sub Total (M) 7183.02


Total Rate ( L+M+T.P.) 10588.70 505.65
15% Contractor's overhead 1588.31
Rate per Cum ( Contractor's Rate) Excluding VAT 12177.01
Rate per Cum ( User's Rate) Including VAT in Material 11094.35

A-b M15 ( 1:2:4 mix) PCC work in foundation ( Including form works)
N.N. 41 Page 46(Dolidar)
Respective clause specification 11
For 1 m3
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 0.66 Md 1034.00 682.44
Labour
Unskilled 3.73 Md 715.00 2666.95
Sub Total (L) 3349.39
T.& P. 3% of labour cost 100.48
Total 3449.87
Cement 320.00 Kg 17.68 5657.60 735.49
Sand 0.44 m3 1664.00 732.16
Aggregate- 40mm 0.52 m3 2158.00 1122.16
Material
Aggregate- 20mm 0.22 m3 2236.00 491.92
Aggregate- 10mm 0.11 m3 1820.00 200.20
Timber 0.055 m3 10400.00 572.00
Aurahi Municipality Officer of municipal executiveAurahi, mahottari state No:-2, Nepal RATE ANALYSIS 2076-07

Sub Total (M) 8776.04


Total Rate ( L+M+T.P.) 12225.91 735.49
15% Contractor's overhead 1833.89
Rate per Cum ( Contractor's Rate) Excluding VAT 14059.80
Rate per Cum ( User's Rate) Including VAT in Material 12961.40

Work in Superstructure components (Beam, Slabs,abutment caps etc.) ( Including form works)
B
B-a M15 ( 1:2:4 mix) PCC work in super structure component ( Including form works)
N.N. 41 Page 46,47(Dolidar)
Respective clause specification 11
For 1 m3
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 0.66 Md 1034.00 682.44
Labour
Unskilled 4.73 Md 715.00 3381.95
Sub Total (L) 4064.39
T.& P. 3% of labour cost 121.93
Total 4186.32
Cement 320.00 Kg 17.68 5657.60 735.49
Sand 0.44 m3 1664.00 732.16
Material Aggregate- 40mm 0.52 m3 2158.00 1122.16
Aggregate- 20mm 0.22 m3 2236.00 491.92
Aggregate- 10mm 0.11 m3 1820.00 200.20
Timber 0.055 m3 10400.00 572.00

Sub Total (M) 8776.04


Total Rate ( L+M+T.P.) 12962.36 735.49
15% Contractor's overhead 1944.35
Rate per Cum ( Contractor's Rate) Excluding VAT 14906.72
Rate per Cum ( User's Rate) Including VAT in Material 13697.85

B-b M20 ( 1:1.5:3 mix) PCC work in super structure component ( Including form works)
N.N. 41 Page 47(Dolidar)
Respective clause specification 11
For 1 m3
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 0.66 Md 1034.00 682.44
Labour
Unskilled 4.79 Md 715.00 3424.85
Sub Total (L) 4107.29
T.& P. 3% of labour cost 123.22
Total 4230.51
Cement 400.00 Kg 17.68 7072.00 919.36
Sand 0.42 m3 1664.00 698.88
Aggregate- 40mm m3 2158.00 0.00
Material Aggregate- 20mm 0.57 m3 2236.00 1274.52

0.29 m3 527.80
Aggregate- 10mm 1820.00
Timber 0.055 m3 10400.00 572.00

Sub Total (M) 10145.20


Total Rate ( L+M+T.P.) 14375.71 919.36
15% Contractor's overhead 2156.36
Rate per Cum ( Contractor's Rate) Excluding VAT 16532.07
Rate per Cum ( User's Rate) Including VAT in Material 15295.07

A-a M10 Grade ( 1:3:6 mix ) PCC work in foundtion ( Excluding form work)
N.N. 41 Page 46(Dolidar)
Respective clause specification 11
For 1 m3
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 0.50 Md 1034.00 517.00
Labour
Unskilled 3.25 Md 715.00 2323.75
Sub Total (L) 2840.75
T.& P. 3% of labour cost 85.22
Total 2925.97
Cement 220.00 Kg 17.68 3889.60 505.65
Sand 0.47 m3 1664.00 782.08
Material
Aggregate- 40mm 0.65 m3 2158.00 1402.70
Aggregate- 20mm 0.24 m3 2236.00 536.64

Sub Total (M) 6611.02


Total Rate ( L+M+T.P.) 9536.99 505.65
15% Contractor's overhead 1430.55
Rate per Cum ( Contractor's Rate) Excluding VAT 10967.54
Rate per Cum ( User's Rate) Including VAT in Material 10042.64

A-b M15 ( 1:2:4 mix) PCC work in foundation ( Excluding form works)
N.N. 41 Page 46(Dolidar)
Respective clause specification 11
For 1 m3

Sources Level Qty Unit Rate Amount VAT in Material


Aurahi Municipality Officer of municipal executiveAurahi, mahottari state No:-2, Nepal RATE ANALYSIS 2076-07

Skilled 0.50 Md 1034.00 517.00


Labour
Unskilled 3.31 Md 715.00 2366.65
Sub Total (L) 2883.65
T.& P. 3% of labour cost 86.51
Total 2970.16
Cement 320.00 Kg 17.68 5657.60 735.49
Sand 0.44 m3 1664.00 732.16
Material Aggregate- 40mm 0.52 m3 2158.00 1122.16
Aggregate- 20mm 0.22 m3 2236.00 491.92
Aggregate- 10mm 0.11 m3 1820.00 200.20

Sub Total (M) 8204.04


Total Rate ( L+M+T.P.) 11174.20 735.49
15% Contractor's overhead 1676.13
Rate per Cum ( Contractor's Rate) Excluding VAT 12850.33
Rate per Cum ( User's Rate) Including VAT in Material 11909.69

Work in Superstructure components (Beam, Slabs,abutment caps etc.) ( Excluding form works)
B
B-a M15 ( 1:2:4 mix) PCC work in super structure component ( Excluding form works)
N.N. 41 Page 46,47(Dolidar)
Respective clause specification 11
For 1 m3
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 0.50 Md 1034.00 517.00
Labour
Unskilled 4.31 Md 715.00 3081.65
Sub Total (L) 3598.65
T.& P. 3% of labour cost 107.96
Total 3706.61
Cement 320.00 Kg 17.68 5657.60 735.49
Sand 0.44 m3 1664.00 732.16
Material Aggregate- 40mm 0.52 m3 2158.00 1122.16
Aggregate- 20mm 0.22 m3 2236.00 491.92
Aggregate- 10mm 0.11 m3 1820.00 200.20

Sub Total (M) 8204.04


Total Rate ( L+M+T.P.) 11910.65 735.49
15% Contractor's overhead 1786.60
Rate per Cum ( Contractor's Rate) Excluding VAT 13697.25
Rate per Cum ( User's Rate) Including VAT in Material 12646.14

B-b M20 ( 1:1.5:3 mix) PCC work in super structure component ( Excluding form works)
N.N. 41 Page 47(Dolidar)
Respective clause specification 11
For 1 m3
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 0.50 Md 1034.00 517.00
Labour
Unskilled 4.37 Md 715.00 3124.55
Sub Total (L) 3641.55
T.& P. 3% of labour cost 109.25
Total 3750.80
Cement 400.00 Kg 17.68 7072.00 919.36
Sand 0.42 m3 1664.00 698.88
Material Aggregate- 40mm m3 2158.00 0.00
Aggregate- 20mm 0.57 m3 2236.00 1274.52
Aggregate- 10mm 0.29 m3 1820.00 527.80

Sub Total (M) 9573.20


Total Rate ( L+M+T.P.) 13324.00 919.36
15% Contractor's overhead 1998.60
Rate per Cum ( Contractor's Rate) Excluding VAT 15322.60
Rate per Cum ( User's Rate) Including VAT in Material 14243.36

Structural steel work for structures. It includes the cost of all labour, materials required for fabrication, connection, oiling, paintiong , temoorary
erection, inspection, tests and complete final erection as shown on the drawings and as specified in the specification
45

Steel work riveted or bolted in built-up sections, trusses including cutting, hoisting and fixing in position
A
I In rolled steel joists
N.N. 42 Page 47(Dolidar)
Respective clause specification 12
For 1000 Kg
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 5.30 Md 1034.00 5480.20
Labour
Unskilled 10.75 Md 715.00 7686.25
Sub Total (L) 13166.45
T.& P. 3% of labour cost 394.99
Total 13561.44
Steel member 1000.00 Kg 156.00 156000.00 20280.00
Material Oil 2.50 Kg 77.50 193.75 25.19
Paint 5.00 Kg 197.60 988.00 128.44
Aurahi Municipality Officer of municipal executiveAurahi, mahottari state No:-2, Nepal RATE ANALYSIS 2076-07

Sub Total (M) 157181.75


Total Rate ( L+M+T.P.) 170743.19 20433.63
15% Contractor's overhead 25611.48
Rate per Kg ( Contractor's Rate) Excluding VAT 196.35
Rate per Kg ( User's Rate) Including VAT in Material 191.18

B For Every subsequent pipe having a length of minimum 1m


V Hume pipe having 750 mm diameter For 1m length
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 0.100 Md 1034.00 103.40
Labour
Unskilled 0.300 Md 715.00 214.50
Sub Total (L) 317.90
T.& P. 3% of labour cost 9.54
Total 327.44
Material Hume pipe750mm dia) NP-3 1.00 RM 7993.44 7993.44 1039.15
Cement 4.00 Kg 17.68 70.72 9.19
Jute 3.00 Kg 93.60 280.80 36.50
Bitumen 0.75 Kg 104.00 78.00 10.14
Sand 0.006 Cum 1664.00 9.98
Sub Total (M) 8432.94
Total Rate ( L+M+T.P.) 8760.38 1094.98
15% Contractor's overhead 1314.06
Rate per Rm. ( Contractor's Rate) Excluding VAT 10074.44
Rate per Rm. ( User's Rate) Including VAT in Material 9855.37

Roofing works.
72 Roofing work with cement tile ( 3'x2')
For 10 Sqm
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 0.50 Md 1034.00 517.00
Labour
Unskilled 1.50 Md 715.00 1072.50
Sub Total (L) 1589.50
T.& P. 0% of labour cost 0.00
Total 1589.50
Material Cement tile 24.00 No 28.08 673.92

Sub Total (M) 673.92


Total Rate ( L+M+T.P.) 2263.42 0.00
15% Contractor's overhead 339.51
Rate per Sqm. ( Contractor's Rate) Excluding VAT 260.29
Rate per Sqm. ( User's Rate) Including VAT in Material 226.34

78 Wood work for door and windows frame ( sal wood)


N.N. 10 (1) Page 49(Old)
For 1 m3
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 34.00 Md 1034.00 35156.00
Labour
Unskilled 3.40 Md 715.00 2431.00
Sub Total (L) 37587.00
T.& P. 0% of labour cost 0.00
Total 37587.00
wood 1.1 cum 208000.00 228800.00 29744.00
Material Hold fast 92 No 46.80 4305.60 559.73
25 mm screw 184 No 1.82 334.88 43.53

Sub Total (M) 233440.48


Total Rate ( L+M+T.P.) 271027.48 30347.26
15% Contractor's overhead 40654.12
Rate per Sqm. ( Contractor's Rate) Excluding VAT 311681.60
Rate per Sqm. ( User's Rate) Including VAT in Material 301374.74

78 Wood work for door and windows frame ( sal wood)


N.N. 10 (1) Page 49(Old)
For 1 m3
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 34.00 Md 1034.00 35156.00
Labour
Unskilled 3.40 Md 715.00 2431.00
Sub Total (L) 37587.00
T.& P. 0% of labour cost 0.00
Total 37587.00
wood 1.1 cum 208000.00 228800.00 29744.00
Material Hold fast 92 No 46.80 4305.60 559.73
25 mm screw 184 No 1.82 334.88 43.53

Sub Total (M) 233440.48


Total Rate ( L+M+T.P.) 271027.48 30347.26
15% Contractor's overhead 40654.12
Rate per Sqm. ( Contractor's Rate) Excluding VAT 311681.60
Rate per Sqm. ( User's Rate) Including VAT in Material 301374.74
Wood works.
79 Wood work for Panel shutter in 38 mm thick wooden frame ( sal wood)
N.N. 10 (2) Page 49Old)
Aurahi Municipality Officer of municipal executiveAurahi, mahottari state No:-2, Nepal RATE ANALYSIS 2076-07

For 2.114 m2
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 10.00 Md 1034.00 10340.00
Labour
Unskilled 1.00 Md 715.00 715.00
Sub Total (L) 11055.00
T.& P. 0% of labour cost 0.00
Total 11055.00
wood 0.084 cum 208000.00 17472.00 2271.36
100 mm Hinge 6 No 41.60 249.60 32.45
150 mm Lower bolt 1 No 83.20 83.20 10.82
Material 300 mm Tower bolt 1 No 145.60 145.60 18.93
250 mm locking set 1 No 343.20 343.20 44.62
Handle 2 No 312.00 624.00 81.12
screw L.s. No 75.00

Sub Total (M) 18992.60


Total Rate ( L+M+T.P.) 30047.60 2459.29
15% Contractor's overhead 4507.14
Rate per Sqm. ( Contractor's Rate) Excluding VAT 16345.67
Rate per Sqm. ( User's Rate) Including VAT in Material 15376.96

92 Flooring works

20 mm thick Terezotile flooring 20mm thick in 1:4 cement mortar including Rubbing and polish all complete work

N.N. 11(5) Page 62(Old)


For 10 Sqm
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 2.00 Md 1034.00 2068.00
Labour
Unskilled 26.10 Md 715.00 18661.50
Sub Total (L) 20729.50
T.& P. 0% of labour cost 0.00
Total 20729.50
20 mm terezotile 11 Sqm 884.00 9724.00 1264.12
Cement 81.00 Kg 17.68 1432.08 186.17
Sand 0.22 Cum 1664.00 366.08
Material Oxalic Acid 0.37 Kg 343.20 126.98 16.51
manpolice 0.118 Kg 426.40 50.32 6.54
Tarpentine 0.538 Litre 130.00 69.94 9.09
Carborandam ( L.S.) 2 No 312.00 624.00 81.12
Sub Total (M) 12393.40
Total Rate ( L+M+T.P.) 33122.90 1563.55
15% Contractor's overhead 4968.43
Rate per Sqm. ( Contractor's Rate) Excluding VAT 3809.13
Rate per Sqm. ( User's Rate) Including VAT in Material 3468.65

Flooring works

25 mm thick marble ( 450mmx450mm) flooring in 20 mm 1:3 cement mortar including Grinding and polish all complete work
93
N.N. 11(6) Page 63(Old)
For 10 Sqm
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 2.00 Md 1034.00 2068.00
Labour
Unskilled 21.50 Md 715.00 15372.50
Sub Total (L) 17440.50
T.& P. 0% of labour cost 0.00
Total 17440.50
25 mm Marble 11 Sqm 4043.52 44478.72 5782.23
Cement 96.00 Kg 17.68 1697.28 220.65
Sand 0.195 Cum 1664.00 324.48
Material Oxalic Acid 0.37 Kg 343.20 126.98 16.51
manpolice 0.118 Kg 426.40 50.32 6.54
Tarpentine 0.538 Litre 130.00 69.94 9.09
Carborandam ( L.S.) 2 No 312.00 624.00 81.12
Sub Total (M) 47371.72
Total Rate ( L+M+T.P.) 64812.22 6116.14
15% Contractor's overhead 9721.83
Rate per Sqm. ( Contractor's Rate) Excluding VAT 7453.41
Rate per Sqm. ( User's Rate) Including VAT in Material 7092.84

Flooring works
94 Porcelene glazed tile flooring work in 1:4 cement sand mortar

N.N. 11(7) Page 63(Old)


For 10 Sqm
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 13.00 Md 1034.00 13442.00
Labour
Unskilled 4.500 Md 715.00 3217.50
Sub Total (L) 16659.50
T.& P. 0% of labour cost 0.00
Total 16659.50
Persoline glazed tile 11 Sqm 1248.00 13728.00 1784.64
Cement 56.00 Kg 17.68 990.08 128.71
Material
Aurahi Municipality Officer of municipal executiveAurahi, mahottari state No:-2, Nepal RATE ANALYSIS 2076-07

Material
Sand 0.152 Cum 1664.00 252.93
White cement 3.228 Kg 52.00 167.86 21.82
Sub Total (M) 15138.86
Total Rate ( L+M+T.P.) 31798.36 1935.17

15% Contractor's overhead 4769.75


Rate per Sqm. ( Contractor's Rate) Excluding VAT 3656.81
Rate per Sqm. ( User's Rate) Including VAT in Material 3373.35

Flooring works

95 Flate brick soling in cement sand and pointing in joints in 1:2 c/s
N.N. 11(12) Page 64(Old)
For 10 Sqm
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 2.25 Md 1034.00 2326.50
Labour
Unskilled 3.250 Md 715.00 2323.75
Sub Total (L) 4650.25
T.& P. 0% of labour cost 0.00
Total 4650.25
Brick 430.00 No 13.00 5590.00
Material Cement 78.00 Kg 17.68 1379.04 179.28
Sand 0.229 Cum 1664.00 381.06
Sub Total (M) 7350.10
Total Rate ( L+M+T.P.) 12000.35 179.28
15% Contractor's overhead 1800.05
Rate per Sqm. ( Contractor's Rate) Excluding VAT 1380.04
Rate per Sqm. ( User's Rate) Including VAT in Material 1217.96

97 Dry Flate brick soling (Flooring works)


N.N. 11(15) Ka Page 65(Old)
For 10 Sqm
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 0.50 Md 1034.00 517.00
Labour
Unskilled 1.00 Md 715.00 715.00
Sub Total (L) 1232.00
T.& P. 0% of labour cost 0.00
Total 1232.00
Brick 420 No 13.00 5460.00 709.80
Material
Sand 0.71 Cum 1664.00
Sub Total (M) 5460.00
Total Rate ( L+M+T.P.) 6692.00 709.80
15% Contractor's overhead 1003.80
Rate per Sqm. ( Contractor's Rate) Excluding VAT 769.58
Rate per Sqm. ( User's Rate) Including VAT in Material 740.18
Flooring works
99 Filling works with sand including water sprinkling and compacting.
N.N. 11(19) Ka Page 66(Old)
For 10 cum
Sources Level Qty Unit Rate Amount VAT in Material
Skilled 6.50 Md 1034.00 6721.00
Labour
Unskilled 0.00 Md 715.00 0.00
Sub Total (L) 6721.00
T.& P. 0% of labour cost 0.00
Total 6721.00
Material Sand 11 Cum 1664.00 18304.00
Sub Total (M) 18304.00
Total Rate ( L+M+T.P.) 25025.00 0.00
15% Contractor's overhead 3753.75
Rate per cum. ( Contractor's Rate) Excluding VAT 2877.88
Rate per cum. ( User's Rate) Including VAT in Material 2502.50
Painting work
106 Distemper painting work ( Prime coat)
N.N. 13(3) Ka Page 70(Old)
For 100 Sqm

Sources Level Qty Unit Rate Amount VAT in Material

Labour Skilled 2.00 Md 1034.00 2068.00


Unskilled 2.00 Md 715.00 1430.00
Sub Total (L) 3498.00
T.& P. 0% of labour cost 0.00
Total 3498.00
Material Primer 8 Litre 353.60 2828.80 367.74
0.00
Sub Total (M) 2828.80
Total Rate ( L+M+T.P.) 6326.80 367.74
15% Contractor's overhead 949.02
Rate per Sqm. ( Contractor's Rate) Excluding VAT 72.76
Rate per Sqm. ( User's Rate) Including VAT in Material 66.95

Painting work
Aurahi Municipality Officer of municipal executiveAurahi, mahottari state No:-2, Nepal RATE ANALYSIS 2076-07

111 Readymade Enamel paint work (Primer coat)


N.N. 13(5) Ka Page 71(Old)
For 100 Sqm
Sources Level Qty Unit Rate Amount VAT in Material

Labour Skilled 3.00 Md 1034.00 3102.00


Unskilled 3.00 Md 715.00 2145.00
Sub Total (L) 5247.00
T.& P. 0% of labour cost 0.00
Total 5247.00
Material Primer 8.1 Litre 431.60 3495.96 454.47

Sub Total (M) 3495.96


Total Rate ( L+M+T.P.) 8742.96 454.47
15% Contractor's overhead 1311.44
Rate per Sqm. ( Contractor's Rate) Excluding VAT 100.54
Rate per Sqm. ( User's Rate) Including VAT in Material 91.97

C
Office of the municipal executive
State no. 2, Nepal
Aurahi, Mahottari
RATE ANALYSIS 2076-077

You might also like