BACK UP PERHITUNGAN

KEGIATAN : PEMBANGUNAN GEDUNG KANTOR


PEKERJAAN : PEMBANGUNAN GEDUNG KANTOR KECAMATAN SRUWENG
LOKASI : KEC. SRUWENG, KEBUMEN
TAHUN ANGGARAN : 2017

A. PEMBANGUNAN PAGAR DAN HALAMAN

TOTAL
NO PERHITUNGAN VOLUME Sat
VOLUME
I PEKERJAAN PERSIAPAN
1 Pengukuran dan Pemasangan Bouwplank 1.00 m'

= = 1.00 m'

2 Pasang Paving Blok Segi 6 t= 8 cm, K-175, abu-abu (lokal) 1,694.11 m'
Lebar Panjang
1. Area rumah dinas dan Gedung serbaguna = 3.88 x 6.14 = 23.82 m2
= 3.88 + 2.32 x 7.62 = 23.62 m2
2.00
= 9.03 x 6.14 = 55.44 m2
= 0.25 x 3.14 x 4.84 = (3.80) m2
= 7.62 x 6.33 = 48.23 m2
= 16.55 x 4.65 = 76.96 m2
= 5.00 x 0.68 x 0.90 = (3.06) m2
2. Plat deuker = 15.76 + 17.72 x 1.36 = 22.77 m2
2.00
3. Kantor camat dan Pendopo = 6.45 + 6.93 x 1.45 = 9.70 m2
2.00
= 4.85 + 1.24 x 11.59 = 35.29 m2
2.00
= 6.75 + 5.74 x 3.25 = 20.30 m2
2.00
= 0.25 x 3.14 x 10.56 = (8.29) m2
= 25.84 + 23.68 x 7.37 = 182.48 m2
2.00
= 6.50 x 6.40 = 41.60 m2
= 33.15 + 30.33 x 7.12 = 225.99 m2
2.00
= 18.20 + 11.20 x 16.66 = 244.90 m2
2.00
= 32.30 + 25.40 x 20.94 = 604.12 m2
2.00
4. Pengurang Pendopo = = (190.00) m2
5. Pengurang Lainnya = = (9.84) m2
6. Tambahan = 293.88 m2
1,694.11 m2

II PEKERJAAN TANAH
1 Galian tanah biasa sedalam 1 meter 70.50 m3
lbr tinggi pj.pagar
1. Pagar Belakang
Pas. batu kali
- Tipe A = 0.80 x 0.40 x 53.66 = 17.17 m3
- Tipe B.1 = 0.60 x - x 3.00 - plat deuker = - m3
- Tipe B.2 = 0.60 x 0.30 x 2.60 = 0.47 m3
- Tipe B.3 = 0.80 x 0.40 x 53.92 = 17.25 m3
- Tipe C = 0.60 x 0.50 x 42.25 = 12.68 m3
Jumlah Total = 155.43 m'
- Footplat tipe A = 0.70 x 0.70 x 0.25 x 10.00 = 1.23 m3
- Footplat tipe B = 0.70 x 0.70 x 0.25 x 11.00 = 1.35 m3
- Footplat tipe C = 0.70 x 0.70 x 0.25 x 7.00 = 0.86 m3
Jumlah Total = 28.00 bh
2. Pagar Depan
- Pas. batu kali = 0.55 x 0.45 x 49.43 = 12.23 m3
- Footplat = 0.60 x 0.60 x 0.15 x 18.00 = 1.35 m3
- Pot. bunga = 0.15 x 0.15 x 49.43 = 1.11 m3
3. Area Taman
- Pendopo = 0.15 x 0.20 x 31.40 = 0.94 m3
- Pagar Pendopo = 0.15 x 0.20 x 30.85 = 0.93 m3
- Kantor Pelayanan = 0.15 x 0.20 x 32.20 = 0.97 m3
= 0.15 x 0.20 x 10.21 = 0.31 m3
- Pagar Kantor Pelayanan = 0.15 x 0.20 x 49.80 = 1.49 m3
- Rumah Dinas = 0.15 x 0.20 x 5.70 = 0.17 m3
160.16 m' 70.50 m'

2 Urugan Kembali 21.15 m3

Hal. 1 dari 297


TOTAL
NO PERHITUNGAN VOLUME Sat
VOLUME
= 0.30 x 70.50 = 21.15 m3

Hal. 2 dari 297


TOTAL
NO PERHITUNGAN VOLUME Sat
VOLUME
3 Urugan pasir bawah pondasi dan lantai kerja 7.72 m3
pj lbr tbl pasir jml
1. Pagar Belakang
Pondasi = 53.66 x 0.80 x 0.05 x 1.00 = 2.15 m3
= 3.00 x 0.60 x - x 1.00 = - m3
= 2.60 x 0.60 x 0.05 x 1.00 = 0.08 m3
= 53.92 x 0.80 x 0.05 x 1.00 = 2.16 m3
= 42.25 x 0.60 x 0.05 x 1.00 = 1.27 m3
Footplat = 0.70 x 0.70 x 0.05 x 28.00 = 0.69 m3
2. Pagar Depan
Pondasi = 49.43 x 0.55 x 0.05 x 1.00 = 1.36 m3
Footplat = 0.05 x 0.60 x 0.05 x 18.00 = 0.03 m3
Jumlah Total = 7.72 m3

4 Pengurugan 1 m3 tanah cadas padat 3,182.86 m3


pj.1 pj.2 lebar tinggi
Area A = 51.40 + 43.34 x 14.51 x 2.30 = 1,580.33 m3
2
Area B = 17.86 + 15.92 x 1.47 x 0.80 = 19.86 m3
2
Area C.1 = 14.04 + 6.65 x 24.40 x 0.80 = 201.93 m3
2
Area C.2 = 25.46 x 9.71 x 0.80 = 197.77 m3
Area C.3 = 11.45 + 9.71 x 14.71 x 0.80 = 124.51 m3
2
Area C.4 = 0.50 x 1.10 x 11.45 x 0.80 = 10.08 m3
Area D.1 = 11.10 + 6.79 x 11.50 x 0.10 = 10.29 m3
2
Area D.2 = 0.50 x 11.63 x 1.06 x 0.10 = 1.23 m3
Area E.1 = 14.69 x 11.21 x 1.00 = 164.67 m3
Area E.2 = 26.80 x 8.75 x 1.00 = 234.50 m3
Area F = 19.28 + 14.95 x 8.75 x 0.50 = 74.88 m3
2
Area G = 26.80 x 6.62 x 0.80 = 141.93 m3
Area H = 21.91 + 19.28 x 6.62 x 0.30 = 40.90 m3
2
Area I.1 = 12.52 x 17.28 x 1.20 = 259.61 m3
Area I.2 = 2.45 + 1.20 x 11.15 x 1.20 = 24.42 m3
2
Area I.3 = 0.50 x 1.20 x 1.50 x 1.20 = 2.16 m3
Area J.1 = 23.31 + 17.28 x 35.80 x 0.10 = 72.66 m3
2
Area J.2 = 0.50 x 9.06 x 23.31 x 0.10 = 21.12 m3
Jumlah Total = 3,182.86 m3

III PEKERJAAN PONDASI


1 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP 170.13 m3

1. Pagar Belakang lbr1 lbr2 tggi jml


- Tipe A = 0.80 + 0.30 x 2.00 x 53.66 = 59.03 m3
2
= 0.80 x 0.60 x 53.66 x 1.00 = 25.76 m3
- Tipe B.1 = 0.60 + 0.30 x 0.80 x 3.00 = 1.08 m3
2
- Tipe B.2 = 0.60 + 0.30 x 0.70 x 2.60 = 0.82 m3
2
= 0.60 x 0.30 x 2.60 x 1.00 = 0.47 m3
- Tipe B.3 = 0.80 + 0.30 x 1.20 x 53.92 = 35.59 m3
2
= 0.80 x 0.40 x 53.92 x 1.00 = 17.25 m3
- Tipe C = 0.60 + 0.30 x 0.60 x 42.25 = 11.41 m3
2
= 0.60 x 0.30 x 42.25 x 1.00 = 7.61 m3

2. Pagar Depan lbr1 lbr2 tggi jml


- Tipe A = 0.45 + 0.30 x 0.60 x 49.43 = 11.12 m3
2
Jumlah Total = 170.13 m3

2 Pemasangan 1 m3 batu kosong (anstamping) - m3


lbr1 lbr2 tggi
Pondasi kolom = - x - x - = - m3

IV PEKERJAAN DINDING
1 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu
campuran 1SP : 3PP 116.37 m2
1. Pot bunga pagar depan
Arah horizontal = 49.43 x 0.55 = 27.19 m2
Arah vertikal = 0.50 x 0.55 x 4.00 = 1.10 m2
2. Taman = 160.16 x 0.55 = 88.09 m2

Hal. 3 dari 297


TOTAL
NO PERHITUNGAN VOLUME Sat
VOLUME
Jumlah = 116.37 m2

Hal. 4 dari 297


TOTAL
NO PERHITUNGAN VOLUME Sat
VOLUME
2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu
campuran 1SP : 6PP 38.16 m2
1. Pintu gerbang sisi bawah = 2.00 x 0.35 x 1.20 = 0.84 m2
sisi atas = 2.00 x 2.01 x 1.40 = 5.63 m2
2 2. Kolom biasa sisi bawah = 16.00 x 0.35 x 1.00 = 5.60 m2
sisi atas = 16.00 x 1.46 x 1.00 = 23.36 m2
3. Papan nama = 1.00 x 1.30 x 2.10 = 2.73 m2
Jumlah = 38.16 m2

3 Pemasangan 1 cm2 dinding conblock HB10 campuran 1SP :3PP 287.55 m2


pj tinggi jml
* Arah H = 155.43 x 1.85 x 1.00 = 287.55 m2

V PEKERJAAN PLESTERAN
1 Pekerjaan plesteran 1 PC : 6 PP, tebal 15 mm 329.03 m2

1. Pagar Belakang
a. Sloof = 0.20 x 1.00 x 155.43 = 31.09 m2
b. Kolom = 0.20 x 1.00 x 48.10 = 9.62 m2
c. Balok = 0.30 x 1.00 x 155.43 = 46.63 m2
d. Pondasi = 0.20 x 1.00 x 155.43 = 31.09 m2
2. Pagar Depan
a. Kolom
- Pintu gerbang sisi bawah = 2.00 x 0.16 x 2.96 = 0.95 m2
= 2.00 x 0.10 x 2.72 = 0.54 m2
= 2.00 x 0.03 x 2.20 = 0.13 m2
kolom utama = 2.00 x 1.97 x 2.00 = 7.88 m2
= 2.00 x 0.09 x 2.48 = 0.45 m2
Puncak segitiga = 8.00 x 0.20 x 0.62 = 0.99 m2
- Pagar sisi bawah = 16.00 x 0.06 x 2.60 = 2.50 m2
= 16.00 x 0.12 x 2.52 = 4.84 m2
= 16.00 x 0.03 x 1.84 = 0.88 m2
kolom utama = 16.00 x 1.45 x 1.60 = 37.12 m2
= 16.00 x 0.06 x 2.08 = 2.00 m2
Puncak segitiga = 64.00 x 0.15 x 0.52 = 4.99 m2
Pengurang Plesteran pada Kolom = - m2
- Sambungan dengan sloof = 4.00 x 1.00 x 0.02 = (0.09) m2
= 14.00 x 2.00 x 0.02 = 0.63 m2
- Pengurang pada kolom papan nama = 2.00 x 1.50 x 0.40 = (1.20) m2
- Plesteran Ciprat = = (6.93)
b. Papan Nama
sisi belakang = 2.73 m2
sisi atas 0.15 x 2.10 = 0.32 m2
c. Sloof dan pondasi = 2.00 x 1.06 x 49.43 = 52.40 m2
- Sloof tertutup kolom 1 = 2.00 x 1.06 x 0.60 = (0.64) m2
- Sloof tertutup kolom 2 = 16.00 x 1.06 x 0.50 = (0.53) m2
d. Pot bunga arah horizontal = 0.40 x 51.43 = 20.57 m2
3. Taman = 0.50 x 160.16 = 80.08 m2
Jumlah = 329.03 m2

2 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP 6.93 m2


sisi jumlah tinggi ats/bwh
1. Kolom 1 2.00 x 2.00 x 1.55 x 0.25 = 1.55 m2
2. Kolom 2 2.00 x 16.00 x 1.05 x 0.16 = 5.38 m2
Jumlah = 6.93 m2

3 Pekerjaan Acian 329.03 m2

Pekerjaan plesteran = 329.03 x 1.00 = 329.03 m2

Jumlah Total = 329.03 m2

4 Sponengan 73.60 m'


sisi jumlah tinggi lebar
1. Kolom 1 4.00 x 2.00 x 0.60 x 2.00 = 9.60 m'
2. Kolom 2 4.00 x 16.00 x 0.50 x 2.00 = 64.00 m'
Jumlah = 73.60 m'

VI PEKERJAAN BETON
1 Sloof 15/20
1. Pagar Belakang
a. Begisting = 0.20 x 2.00 x 155.43 = 62.17 x 0.50 = 31.09 m2
b. Pembesian
-Besi 4 Ø 12 = 4.00 x 0.89 x 155.43 = 551.94 kg
-Angkur Ø 8 - 500 = 155.00 x 0.39 x 0.50 = 30.58 kg
-Begel Ø 6 - 150 = 1,036.00 x 0.22 x 0.55 = 125.36 kg
707.87 kg

c. Beton bertulang = 0.12 x 0.20 x 155.43 = 3.73 m3

Hal. 5 dari 297


TOTAL
NO PERHITUNGAN VOLUME Sat
VOLUME
2. Pagar Depan
a. Begisting = 0.20 x 2.00 x 49.43 = 19.77 x 0.50 = 9.89 m2
b. Pembesian
-Besi 4 Ø 12 = 4.00 x 0.89 x 49.43 = 175.53 kg
-Angkur Ø 8 - 500 = 49.00 x 0.39 x 0.50 = 9.67 kg
-Begel Ø 6 - 150 = 330.00 x 0.22 x 0.55 = 39.93 kg
225.12 kg

c. Beton bertulang = 0.12 x 0.18 x 49.43 = 1.07 m3

a. Begisting = 31.09 + 9.89 = 40.97 m2 40.97 m2


b. Pembesian = 707.87 + 225.12 = 933.00 kg 933.00 kg
c. Beton bertulang = 3.73 + 1.07 = 4.80 m3 4.80 m3

2 Foot Plate 0,6 x 0,6 m

a. Begisting = 0.20 x 2.40 x 28.00 = 13.44 m2 x 1.00 13.44 m2


b. Pembesian
-Besi Ø 10 - 150 = 5.00 x 0.62 x 1.45 x 28.00 = 125.15 kg
-Besi Ø 10 - 150 = 5.00 x 0.62 x 1.45 x 28.00 = 125.15 kg
= 250.30 kg 250.30 kg

c. Beton bertulang = 0.60 x 0.60 x 0.20 x 28.00 = 2.02 m3 2.02 m3

3 Kolom 20/20
1. Menggunakan footplat
Panjang Kolom Bawah
Tipe A = 10.00 x 2.60 = 26.00
Tipe B = 11.00 x 1.80 = 19.80
Tipe C = 7.00 x 0.90 = 6.30
52.10 m'
Panjang Kolom Atas
Pas.batako = 28.00 x 1.85 = 51.80 m'
103.90 m'
Panjang Sambungan = 4.00 x 28.00 x 0.75 = 84.00 m'
= 4.00 x 28.00 x 0.20 = 22.40 m'
106.40 m'
jml panjang
a. Begisting = 0.18 x 4.00 x 103.90 = 74.81 m2 x 0.50 37.40 m2
b. Pembesian
-Besi 4 Ø 12 = 103.90 x 1.00 x 0.89 = 92.24 kg
= 106.40 x 1.00 x 0.89 = 94.46 kg
-Begel Ø 6 - 150 = 695.00 x 0.22 x 0.65 = 100.26 kg
= 286.96 kg

c. Beton bertulang = 0.18 x 0.18 x 210.30 = 6.81 m3

2. Tidak menggunakan footplat


Panjang Kolom Bawah
Tipe A = 9.00 x 1.85 = 16.65
Tipe B = 10.00 x 1.85 = 18.50
Tipe C = 7.00 x 1.85 = 12.95
48.10 m'
Panjang Sambungan = 4.00 x 26.00 x 0.20 = 20.80 m'

a. Begisting = 0.18 x 4.00 x 48.10 = 34.63 m2 x 0.50 17.32 m2


b. Pembesian
-Besi 4 Ø 12 = 48.10 x 1.00 x 0.89 = 48.99 kg
= 20.80 x 1.00 x 0.89 = 21.69 kg
-Begel Ø 6 - 150 = 321.00 x 0.22 x 0.65 = 46.31 kg
= 116.98 kg

c. Beton bertulang = 0.18 x 0.18 x 48.10 = 1.56 m3


3. Pagar Depan
Panjang kolom pintu utama = 2.00 x 2.86 = 5.72
Panjang kolom = 16.00 x 2.31 = 36.96
42.68 m'
Panjang Sambungan = 18.00 x 4.00 x 0.15 = 10.80
53.48 m'

a. Begisting = 0.18 x 4.00 x - = 0.00 m2 x 0.50 - m2


b. Pembesian
-Besi 4 Ø 12 = 53.48 x 1.00 x 0.89 = 54.37 kg
-Begel Ø 6 - 150 = 285.00 x 0.22 x 0.89 = 56.15 kg
= 110.52 kg
c. Beton bertulang = 0.18 x 0.18 x 42.68 = 1.38 m3
c. Beton bertulang = 0.21 x 0.05 x 18.00 = 0.19 m3

Hal. 6 dari 297


TOTAL
NO PERHITUNGAN VOLUME Sat
VOLUME
= = 1.57 m3

Hal. 7 dari 297


TOTAL
NO PERHITUNGAN VOLUME Sat
VOLUME
a. Begisting = 37.40 + 17.32 + - = 54.72 m2
b. Pembesian = 286.96 + 116.98 + 110.52 = 403.94 kg 403.94 kg
c. Beton bertulang = 6.81 + 1.56 + 1.57 = 8.37 m3 8.37 m3

a. Begisting = = 31.02 m2 31.02 m2


a. Begisting ( CCO.1 ) = 54.72 - 31.02 = 36.52 m2 36.52 m2

4 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm - m2

5 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 155.43 m'

VII PENUTUP LANTAI DAN PENUTUP DINDING


1 Pemasangan 1m2 lantai keramik ukuran 40cm x40cm 3.99 m2

c.
Volume
Beton bertulang = 1.00 x 2.10 x 1.90 = 3.99 m2

2 Pemasangan 1 m2 dinding batu tempel candi - m2

VIII PEKERJAAN BESI DAN ALUMUNIUM


1 Pasang Pagar dan Pintu Besi Ulir (lengkap) 54.35 m2
jumlah tinggi panjang
1. Pintu = 1.00 x 1.50 x 5.00 = 7.50 m2
2. Pagar : Sisi Barat = 1.00 x 1.15 x 3.47 = 3.99 m2
= 7.00 x 1.15 x 2.60 = 20.93 m2
: Sisi Timur = 1.00 x 1.15 x 3.47 = 3.99 m2
= 6.00 x 1.15 x 2.60 = 17.94 m2
Jumlah Total = 54.35 m2

2 Pasang Grill Saluran 19.90 m'

Berat Grill U 20 D 13 4.00 x 1.00 x 1.04 = 4.17 kg


D 13 3.00 x 0.22 x 1.04 = 0.69 kg
siku (40x40x3) 2.00 x 1.00 x 1.83 = 3.67 kg
Berat / m' = 8.52 kg

1. Pendopo = 6.50 + 5.60 + 7.80 = 19.90 m'


2. Depan kantor = - + - + = - m'
19.90 m'
19.90 x 8.52 = 169.56 kg

3 Roda Pintu Ø 2,5" 6.00 bh


jumlah pasang pasang
Pintu 1.00 x 3.00 x 2.00 = 6.00 bh

4 Gembok 1.00 bh
jumlah pasang pasang
Pintu 1.00 x 1.00 x 1.00 = 1.00 bh

IX PEKERJAAN PENGECATAN
1 Pengecatan tembok interior & plafond (ex. Catylac) 329.03 m2

Dinding Gedung = Pek.acian = 329.03 m2

2 Pengecatan permukaan baja (galbani) secara semprot dengan sistem 1 lapis cat mutakhir dengan tebal 200 um 58.33 m2

1. Pagar besi = 54.35 m2


2. Grill U jumlah lebar panjang
1.00 x 0.20 x 19.90 = 3.98 m2
Jumlah Total = 58.33 m2

X PEKERJAAN INSTALASI LISTRIK


1 Titik Lampu 1.00 m'
2 Saklar Ganda 1.00 m'
3 Pemasangan Lampu Taman 1.00 m'

X PEKERJAAN LAIN LAIN


1 Pasang saluran U 20 cm, termasuk pasangan dinding 53.20 m'

1. Pendopo = = 35.40 m'


2. Depan kantor = = 17.80 m'
3. Depan mushola arsip = = - m'
53.20 m'

2 Tanah subur 278.72 m3

1. Pot Pagar Depan = 49.43 x 0.60 x 0.40 = 11.86 m3


2. Taman
- Pendopo = 0.35 x 2.70 x 5.15 x 2.00 = 27.81 m3
- Pagar Pendopo = 0.35 x 30.85 x 2.60 x 0.50 = 40.11 m3

Hal. 8 dari 297


TOTAL
NO PERHITUNGAN VOLUME Sat
VOLUME
- Kantor Pelayanan = 0.35 x 32.20 x 3.25 x 1.00 = 104.65 m3
= 0.35 x 3.14 x 10.56 x 0.50 = 16.58 m3
- Pagar Kantor Pelayanan = 0.35 x 49.80 x 1.50 x 1.00 = 74.70 m3
- Rumah Dinas = 0.35 x 4.30 x 0.70 x 1.00 = 3.01 m3
278.72 m3

3 Pembuatan taman 123.06 m2

1. Pot Pagar Depan = 49.43 x 0.60 = 29.66 m2


2. Taman = 266.86 \ 0.35 = 93.40 m2
123.06 m2

Hal. 9 dari 297


BACK UP PERHITUNGAN

KEGIATAN : PEMBANGUNAN GEDUNG KANTOR


PEKERJAAN : PEMBANGUNAN GEDUNG KANTOR KECAMATAN SRUWENG
LOKASI : KEC. SRUWENG, KEBUMEN
TAHUN ANGGARAN : 2017

C. KANTOR PELAYANAN

TOTAL
NO PERHITUNGAN VOLUME
VOLUME
I PEKERJAAN PERSIAPAN

1 Pengukuran dan pemasangan bauwplank 1.00 ls

II PEKERJAAN TANAH
1 Penggalian 1 m3 tanah biasa sedalam 1 m 62.24 m3
Panjang total pondasi batu kali
arah H = 4.00 + 1.50 + 39.50 + 11.00 + 19.50 = 75.50 m'
3.00 + 33.00 + 5.50 + 3.50 = 45.00 m'
arah V = 12.00 + 3.00 + 12.00 + 4.00 + 5.00 = 36.00 m'
2.00 + 2.00 + 6.00 4.00 9.00 = 23.00 m'
3.00 + 6.00 + 3.00 3.00 = 15.00 m'
194.50 m'
Volume Galian
1. Pas. batu kali = 0.80 x 0.40 x 194.50 = 62.24 m3
2. Rollag = 0.20 x 0.20 x - = - m3
62.24 m3

2 Pengurugan kembali 1 m3 galian tanah 18.67 m3


= 0.30 x 62.24 = 18.67 m3

3 Pengurugan 1 m3 dengan pasir urug 25.98 m3


Panjang Lebar Jumlah
1. Lantai 20/20
1-2. KM/WC 1 = 1.35 x 1.35 x 2.00 = 3.65 m2
11-12. KM/WC 1 = 1.85 x 1.35 x 2.00 = 5.00 m2
3. Tempat Wudlu = 2.35 x 2.85 x 1.00 = 6.70 m2
15.34 m2
2. Lantai 40/40
4. Mushola = 3.85 x 3.85 x 1.00 = 14.82 m2
5. Ruang Arsip = 3.85 x 4.85 x 1.00 = 18.67 m2
6. Ruang Kerja = 10.85 x 8.85 x 1.00 = 96.02 m2
= 3.15 x 4.85 x 1.00 = 15.28 m2
= 5.35 x 5.85 x 1.00 = 31.30 m2
7. Ruang Sekcam = 2.85 x 3.85 x 1.00 = 10.97 m2
8. Ruang Rapat = 6.85 x 3.85 x 1.00 = 26.37 m2
9. Ruang Kasubag = 6.85 x 4.85 x 1.00 = 33.22 m2
10. Ruang Camat = 5.35 x 3.85 x 1.00 = 20.60 m2
13. Ruang Tunggu = 7.85 x 5.85 x 1.00 = 45.92 m2
14. Ruang Komputer = 6.85 x 2.85 x 1.00 = 19.52 m2
16. Teras Depan = 3.00 x 3.00 x 1.00 = 9.00 m2
15. Teras Samping = 3.50 x 2.00 x 1.00 = 7.00 m2
348.70 m2
Luas Urugan Pasir
1. Lantai 20/20 = 15.34 x 0.05 = 0.77 m2
2. Lantai 40/40 = 348.70 x 0.05 = 17.44 m2
3. Pondasi = 0.80 x 194.50 x 0.05 = 7.78 m2
Jumlah Total = 25.98 m3

4 Pengurugan 1 m3 cadas padat 109.21 m3

Volume = 15.34 + 348.70 x 0.30 = 109.21 m3

III PEKERJAAN PONDASI

1 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP 89.00 m3

Pbk =( 0.30 + 0.80 ) x 1.35 x 39.50 m' = 29.33 m3


2
=( 0.30 + 0.80 ) x 0.70 x 155.00 m' = 59.68 m3
2
Jumlah total = 29.33 + 59.68 = 89.00 m3

2 Pemasangan 1 m3 batu kosong (anstamping) 31.12 m3


Gedung
Pbk = 0.80 x 0.20 x 194.50 m' = 31.12 m3

Hal. 10 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
IV PEKERJAAN DINDING

1 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP - m2

Tasram = - x 0.20 x 1.00 = = - m2

2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 3PP 81.20 m2

Dinding = 178.00 x 0.50 x 1.00 = 89.00 m2


Luas Perlubangan
P1 = 2.00 x 0.50 x 2.00 = 2.00 m2
P3 = 0.80 x 0.50 x 10.00 = 4.00 m2
P4 = 0.70 x 0.50 x 4.00 = 1.40 m2
PS = 0.80 x 0.50 x 1.00 = 0.40 m2
7.80 m2
Luas Netto = 89.00 - 7.80 = 81.20 m2

3 Pemasangan 1m2 dinding bata merah (5x11x22)cmtebal ½ batu campuran 1SP : 6PP 485.21 m2

Dinding lantai 1 = 163.50 x 3.80 x 1.00 = 621.30 m2


= 14.50 x 3.30 x 1.00 = 47.85 m2
= 1.00 x 8.00 x 1.00 = 8.00 m2
= 1.00 x 7.50 x 1.00 = 7.50 m2
= 1.00 x 7.50 x 1.00 = 7.50 m2
= 0.80 x 2.35 x 4.00 = 7.52 m2
699.67 m2
Luas Perlubangan jml
P1 = 2.00 x 2.95 x 2.00 = 11.80 m2
= 0.40 x 2.52 x 4.00 = 4.03 m2
P3 = 0.80 x 2.77 x 10.00 = 22.16 m2
P4 = 0.70 x 2.77 x 4.00 = 7.76 m2
PS = 0.80 x 2.10 x 1.00 = 1.68 m2
J3 = 0.70 x 1.70 x 6.00 = 7.14 m2
J1 = 1.36 x 1.86 x 6.00 = 15.18 m2
J2 = 2.01 x 1.86 x 16.00 = 59.82 m2
B1 = 0.67 x 0.70 x 4.00 = 1.88 m2
B2 = 0.67 x 1.36 x 2.00 = 1.82 m2
= 133.26 m2
Perlubangan Pas. Trasram
Luas Netto = 699.67 - 133.26 - 81.20 = 485.21 m2

V PEKERJAAN PLESTERAN
1 Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. 1,100.58 m2

1. Luas utuh = 2.00 x 566.41 = 1,132.82 m2


2. Plint keramik = 20.80 x 0.05 = (1.04) m2
3. Dinding keramik = = (31.20) m2
Jumlah Total = 1,100.58 m2

2 Pemasangan 1 m2 acian. 1,103.69 m2

= 1,100.58 x 1.00 = 1,100.58 m2


= 31.10 x 0.10 = 3.11 m2
Jumlah Total = 1,103.69 m2

3 Sponengan 31.10 m'

= 2.85 x 2.00 x 1.00 = 5.70 m1


= 2.55 x 4.00 x 1.00 = 10.20 m1
= 2.00 x 4.00 x 1.00 = 8.00 m1
= 3.60 x 2.00 x 1.00 = 7.20 m1
Jumlah Total = 31.10 m1

VI PEKERJAAN BETON
1 Lantai Kerja, Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87 18.20 m3

1. Lantai 20/20 = 15.34 x 0.05 = 0.77 m3


2. Lantai 40/40 = 348.70 x 0.05 = 17.44 m3
18.20 m3

2 Rabat Beton, membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87 6.30 m3

Tritisan = 16.50 x 2.00 x 1.00 x 0.10 = 3.30 m3


= 15.00 x 2.00 x 1.00 x 0.10 = 3.00 m3
6.30 m3

3 Sloof 15/25

a. Begisting = 0.25 x 2.00 x 199.50 = 99.75 m2 x 0.50 49.88 m2

Hal. 11 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
b. Pembesian
-Besi 5 D 13 = 5.00 x 1.04 x 199.50 = 1,037.40 kg
-Begel Ø 8 - 150 = 1,330.00 x 0.393 x 0.70 = 365.88 kg
1,403.28 kg 1,403.28 kg

c. Beton bertulang = 0.15 x 0.25 x 199.50 = 7.48 m3 7.48 m3

4 Kolom 30/30

a. Begisting = 0.3 x 4 x 3.00 = 3.60 m2 x 0.50 7.20 m2


= 3.60 x 4.00 = 14.40 m2
b. Pembesian
-Besi 6 D 13 = 6.00 x 3.00 + 0.30 = 19.80 m1
= 19.80 x 4.00 x 1.04 = 82.37 kg
-Besi 4 Ø 10 = 2.00 x 3.00 + 0.30 = 6.60 m1
= 6.60 x 4.00 x 0.62 = 16.37 kg
-Begel Ø 6 - 150 = 80.00 x 0.22 x 1.10 = 19.36 kg
101.73 kg 101.73 kg

c. Beton bertulang = 0.3 x 0.3 x 12.00 = 1.08 m3 1.08 m3

5 Kolom 20/20

a. Begisting = 0.20 x 4.00 x 4.00 = 3.20 m2 x 0.50 60.80 m2


= 3.20 x 38.00 = 121.60 m2
b. Pembesian
-Besi 4 Ø 10 = 4.00 x 4.00 + 0.30 = 17.20 m1
= 17.20 x 38.00 x 0.62 = 405.23 kg
-Begel Ø 6 - 150 = 1,013.00 x 0.22 x 0.70 = 156.00 kg
561.23 kg 561.23 kg

c. Beton bertulang = 0.2 x 0.2 x 144.40 = 5.78 m3 5.78 m3

6 Kolom 11/11 114.40 m1

= 3.80 x 23.00 x 1.00 = 87.40 m1


= 3.00 x 9.00 x 1.00 = 27.00 m1
114.40

7 Balok 15/40

a. Begisting = 0.375 x 2 x 5.50 = 4.13 m2 x 0.50 2.06 m2


b. Pembesian
-Besi 8 D 13 = 8.00 x 1.04 x 5.50 = 45.76 kg
-Begel Ø 6 - 150 = 37.00 x 0.22 x 1.00 = 8.14 kg
53.90 kg 53.90 kg

c. Beton bertulang = 0.15 x 0.4 x 5.50 = 0.33 m3 0.33 m3


8 Balok 15/30

a. Begisting = 0.375 x 2.00 x 19.00 = 14.25 m2 x 0.50 7.13 m2


b. Pembesian
-Besi 6 D 13 = 6.00 x 1.04 x 19.00 = 118.56 kg
-Begel Ø 6 - 150 = 127.00 x 0.22 x 0.80 = 22.35 kg
140.91 kg 140.91 kg

c. Beton bertulang = 0.15 x 0.3 x 19.00 = 0.86 m3 0.86 m3

9 Balok 15/20
a. Begisting Panjang Sloof
= 0.20 x 2.00 x 199.50 = 79.80 m2 x 0.50 39.90 m2
b. Pembesian
-Besi 5 D 13 = 5.00 x 1.04 x 199.50 = 1,037.40 kg
-Begel Ø 8 - 150 = 1,330.00 x 0.393 x 0.60 = 313.61 kg
1,351.01 kg 1,351.01 kg

c. Beton bertulang = 0.15 x 0.20 x 199.50 = 5.99 m3 5.99 m3

10 Balok Latai 10/15 97.00 m2

= 1.00 x 1.00 x 97.00 = 97.00 m2 x 1.00

11 Plat Atap

a. Begisting = 4.00 x 5.50 x 1.00 = 22.00 m2 x 0.50 25.00 m2


= 4.00 x 3.00 x 1.00 = 12.00 m2
= 4.00 x 4.00 x 1.00 = 16.00 m2
50.00 m2

Hal. 12 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
b. Pembesian
-Besi Ø 10 - 150 = 4.10 x 0.62 x 74.00 = 188.11 kg
-Besi Ø 10 - 150 = 5.60 x 0.62 x 54.00 = 187.49 kg

-Besi Ø 10 - 150 = 4.10 x 0.62 x 40.00 = 101.68 kg


-Besi Ø 10 - 150 = 3.10 x 0.62 x 54.00 = 103.79 kg

-Besi Ø 10 - 150 = 4.10 x 0.62 x 54.00 = 137.27 kg


-Besi Ø 10 - 150 = 4.10 x 0.62 x 54.00 = 137.27 kg
855.60 kg 855.60 kg

c. Beton bertulang = 4.00 x 5.50 x 0.12 x 1.00 = 2.64 m3 6.00 m3


= 4.00 x 3.00 x 0.12 x 1.00 = 1.44 m3
= 4.00 x 4.00 x 0.12 x 1.00 = 1.92 m3
6.00

12 Shading

a. Begisting = 0.60 x 48.70 x 1.00 = 29.22 m2 x 0.50 14.61 m2


b. Pembesian
-Besi Ø 10 - 150 = 0.80 x 0.62 x 325.00 = 161.20 kg
-Besi Ø 10 - 150 = 48.70 x 0.62 x 4.00 = 120.78 kg
281.98 kg 281.98 kg

c. Beton bertulang = 0.60 x 48.7 x 0.1 x 1.00 = 2.92 m3 2.92 m3

13 Plat Lisplang

a. Begisting = 0.36 x 19.50 x 1.00 = 7.02 m2 x 0.50 3.51 m2


b. Pembesian
-Besi Ø 10 - 150 = 0.56 x 0.62 x 130.00 = 45.14 kg
-Besi Ø 10 - 150 = 19.50 x 0.62 x 2.00 = 24.18 kg
69.32 kg 69.32 kg

c. Beton bertulang = 0.36 x 19.5 x 0.1 x 1.00 = 0.70 m3 0.70 m3

VII PEKERJAAN KAYU, ATAP DAN PLAFOND


1 Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I 24.36 m2

P3 = 1.68 x 10.00 = 16.80 m2


P4 = 1.47 x 4.00 = 5.88 m2
PS = 1.68 x 1.00 = 1.68 m2
24.36

2 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas II ( kruing ) 6.99 m3

= 0.01 x 10.00 x 13.00 = 1.46 m3


= 0.01 x 5.00 x 13.00 = 0.62 m3
= 0.01 x 10.00 x 13.00 = 1.25 m3
= 0.01 x 6.60 x 13.00 = 0.82 m3
= 0.01 x 2.00 x 13.00 = 0.25 m3
= 0.01 x 22.00 x 13.00 = 2.06 m3

= 0.01 x 5.50 x 2.00 = 0.11 m3


= 0.01 x 4.20 x 2.00 = 0.08 m3
= 0.01 x 5.00 x 2.00 = 0.10 m3
= 0.01 x 3.30 x 2.00 = 0.06 m3
= 0.01 x 2.00 x 2.00 = 0.04 m3
= 0.01 x 10.00 x 2.00 = 0.14 m3
6.99 m3

3 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruing ) 3.57 m3

= 0.01 x 47.50 x 2.00 = 0.91 m3


= 0.01 x 41.50 x 2.00 = 0.80 m3
= 0.01 x 35.50 x 2.00 = 0.68 m3
= 0.01 x 8.00 x 4.00 = 0.31 m3
= 0.01 x 1.50 x 4.00 = 0.06 m3
= 0.01 x 32.50 x 1.00 = 0.31 m3
= 0.01 x 7.00 x 10.00 = 0.50 m3
3.57 m3

4 Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II 533.00 m2

= 35.25 x 6.50 x 2.00 x 1.00 = 458.25 m2


= 5.75 x 6.50 x 2.00 x 1.00 = 74.75 m2
533.00 m2

Hal. 13 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
5 Lisplang GRC Board tebal 9 mm, L = 30 cm (terpasang & pengecatan), motif kayu 105.00 m1

= 41.00 x 2.00 = 82.00 m1


= 11.50 x 2.00 = 23.00 m1
105.00 m'

6 Pemasangan 1 m2 atap genteng palentong besar/super 533.00 m2

= 35.25 x 6.50 x 2.00 x 1.00 = 458.25 m2


= 5.75 x 6.50 x 2.00 x 1.00 = 74.75 m2
= 533.00 m2

7 Pemasangan 1 m’ bubung genteng palentong besar 61.50 m1

= 29.50 x 1.00 = 29.50 m1


= 8.00 x 4.00 = 32.00 m1
61.50 m'

8 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III 463.00 m2

= 38.50 x 9.00 = 346.50 m2


= 2.00 x 3.50 = 7.00 m2
= 1.00 x 8.50 = 8.50 m2
= 3.00 x 3.00 = 9.00 m2
= 3.00 x 4.00 = 12.00 m2
= 0.80 x 100.00 = 80.00 m2
463.00 m2

9 Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm 383.00 m2

= 38.50 x 9.00 = 346.50 m2


= 2.00 x 3.50 = 7.00 m2
= 1.00 x 8.50 = 8.50 m2
= 3.00 x 3.00 = 9.00 m2
= 3.00 x 4.00 = 12.00 m2
383.00

10 Pemasangan 1 m2 langit-langit kalsiboard ukuran (120x240x4) mm, tebal 4 mm 80.00 m2

= 0.80 x 100.00 = 80.00 m2

11 Pemasangan 1 m’ list langit-langit gypsum profil 436.80 m1

= 11.00 x 1.00 = 11.00 m1


= 12.00 x 1.00 = 12.00 m1
= 18.00 x 1.00 = 18.00 m1
= 16.00 x 1.00 = 16.00 m1
= 5.40 x 2.00 = 10.80 m1
= 11.00 x 1.00 = 11.00 m1
= 67.00 x 1.00 = 67.00 m1
= 8.00 x 1.00 = 8.00 m1
= 14.00 x 1.00 = 14.00 m1
= 22.00 x 1.00 = 22.00 m1
= 19.00 x 1.00 = 19.00 m1
= 7.00 x 2.00 = 14.00 m1
= 20.00 x 1.00 = 20.00 m1
= 28.00 x 1.00 = 28.00 m1
= 12.00 x 1.00 = 12.00 m1
= 77.00 x 2.00 = 154.00 m1
436.80 m1

VIII PEKERJAAN SANITASI

IX PEKERJAAN BESI DAN ALUMINIUM


1 Pemasangan 1 m kusen pintu alluminium 489.42 m'

P3 = 7.32 x 10.00 = 73.20 m'


P4 = 7.10 x 4.00 = 28.40 m'
J3 = 4.80 x 6.00 = 28.80 m'
J1 = 9.66 x 6.00 = 57.96 m'
J2 = 15.48 x 16.00 = 247.68 m'
B1 = 2.74 x 4.00 = 10.96 m'
B2 = 4.73 x 2.00 = 9.46 m'
P1 = 16.48 x 2.00 = 32.96 m'
489.42 m'

Hal. 14 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
2 Pemasangan 1 m2 jendela kaca rangka alluminium 74.83 m2

P3 = 0.47 x 10.00 = 4.70 m2


P4 = 0.41 x 4.00 = 1.62 m2
J3 = - x 6.00 = - m2
J1 = 2.11 x 6.00 = 12.66 m2
J2 = 3.17 x 16.00 = 50.65 m2
B1 = 0.35 x 4.00 = 1.42 m2
B2 = 0.71 x 2.00 = 1.42 m2
P1 = 1.18 x 2.00 = 2.36 m2
74.83 m2

X PEKERJAAN KUNCI DAN KACA


1 Pemasangan 1 buah engsel pintu 42.00 m'

P3 = 3.00 x 10.00 = 30.00 m'


P4 = 3.00 x 4.00 = 12.00 m'
42.00 m'

2 Pemasangan 1 buah engsel jendela kupu-kupu 304.00 bh

P3 = 2.00 x 10.00 = 20.00 bh


P4 = 2.00 x 4.00 = 8.00 bh
J3 = 2.00 x 6.00 = 12.00 bh
J1 = 8.00 x 6.00 = 48.00 bh
J2 = 12.00 x 16.00 = 192.00 bh
B1 = 2.00 x 4.00 = 8.00 bh
B2 = 4.00 x 2.00 = 8.00 bh
P1 = 4.00 x 2.00 = 8.00 bh
304.00 bh

3 Pemasangan 1 buah kait angin 304.00 bh

P3 = 2.00 x 10.00 = 20.00 bh


P4 = 2.00 x 4.00 = 8.00 bh
J3 = 2.00 x 6.00 = 12.00 bh
J1 = 8.00 x 6.00 = 48.00 bh
J2 = 12.00 x 16.00 = 192.00 bh
B1 = 2.00 x 4.00 = 8.00 bh
B2 = 4.00 x 2.00 = 8.00 bh
P1 = 4.00 x 2.00 = 8.00 bh
304.00 bh

4 Pemasangan 1 buah kunci slot 14.00 bh

P3 = 1.00 x 10.00 = 10.00 bh


P4 = 1.00 x 4.00 = 4.00 bh
14.00 bh

5 Pemasangan 1 m2 kaca tebal 5 mm 180.80 m2

P3 = 1.09 x 10.00 = 10.90 m2


P4 = 0.99 x 4.00 = 3.96 m2
J3 = 1.07 x 6.00 = 6.42 m2
J1 = 4.78 x 6.00 = 28.68 m2
J2 = 7.17 x 16.00 = 114.72 m2
B1 = 0.91 x 4.00 = 3.64 m2
B2 = 1.82 x 2.00 = 3.64 m2
P1 = 4.42 x 2.00 = 8.84 m2
180.80 m2

2 Grendel pintu 170.00 bh

P3 = 2.00 x 10.00 = 20.00 bh


P4 = 2.00 x 4.00 = 8.00 bh
J3 = 2.00 x 6.00 = 12.00 bh
J1 = 4.00 x 6.00 = 24.00 bh
J2 = 6.00 x 16.00 = 96.00 bh
B1 = 1.00 x 4.00 = 4.00 bh
B2 = 1.00 x 2.00 = 2.00 bh
P1 = 2.00 x 2.00 = 4.00 bh
170.00 bh

XI PEKERJAAN PENUTUP LANTAI DAN DINDING


1 Pemasangan 1m2 lantai keramik ukuran 40cm x40cm 348.70 m2

= 348.70 m2

Hal. 15 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
2 Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm 15.34 m2

= 15.34 m2

3 Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm 20.80 m1

1. KM/WC Selatan = 4.70 x 2.00 = 9.40 m1


2. KM/WC Utara = 5.70 x 2.00 = 11.40 m1
20.80 m1

4 Pemasangan 1 m2 dinding keramik 20cm x 20cm 31.20 m2

= 20.80 x 1.50 = 31.20 m2

5 Pemasangan 1 m2 dinding batu tempel susun sirih 12.64 m2

1. Teras utara = 0.80 x 2.35 x 4.00 = 7.52 m2


2. Teras barat = 0.80 x 3.20 x 2.00 = 5.12 m2
12.64 m2

XII PEKERJAAN PENGECATAN


1 Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) 1,103.69 m2
1,103.69 x 1.00 = 1,103.69 m2

2 Pengecatan 1 m2 plafon ( 1 lapis cat dasar, 2 lapis cat penutup) 463.00 m2


463.00 x 1.00 = 463.00 m2

XIII PEKERJAAN INSTALASI LISTRIK


1 Pemasangan meter listrik lama 5500 watt 1.00 bh
2 Instalasi Listrik 57.00 ttk
SL 18 watt = 33.00 bh = 33.00 ttk
Pijar 5 w = 9.00 bh = 9.00 ttk
Stop kontak = 15.00 bh = 15.00 ttk
= 57.00 ttk

3 Saklar ganda 3.00 bh


4 Saklar tunggal 12.00 bh
5 Stop kontak 15.00 bh
6 Lampu pijar 5 W philips 9.00 bh
7 Lampu SL 18 Watt Phillips 33.00 bh

XIV PEKERJAAN LAIN - LAIN


1 Pasang salura U Ø 20 cm, termasuk pas. Dinding
= 116.00 x 1.00 = 116.00 m'
116.00 m' 116.00 m'

Hal. 16 dari 297


BACK UP PERHITUNGAN

KEGIATAN : PEMBANGUNAN GEDUNG KANTOR


PEKERJAAN : PEMBANGUNAN GEDUNG KANTOR KECAMATAN SRUWENG
LOKASI : KEC. SRUWENG, KEBUMEN
TAHUN ANGGARAN : 2017

D. GEDUNG SERBAGUNA

TOTAL
NO PERHITUNGAN VOLUME
VOLUME

I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan bauwplank 1.00 ls

II PEKERJAAN TANAH
1 Penggalian 1 m3 tanah biasa sedalam 1 m 2.08 m3
Panjang total pondasi batu kali
arah H = 16.00 + 16.00 + 2.50 + 1.50 + 18.50 = 54.50 m'
arah V = 8.00 + 6.00 + 2.00 + 8.00 + 6.00 = 30.00 m'
84.50 m'

Vol. Pbk = 0.80 x 0.40 x 84.50 = 27.04 m3


Rollax = 0.20 x 0.20 x 52.00 = 2.08 m3
2.08 m3

2 Pengurugan kembali 1 m3 galian tanah 8.11 m3


= 0.30 x 27.04 = 8.11 m3

3 Pengurugan 1 m3 dengan pasir urug 9.88 m3

Panjang Lebar Jumlah


1. Lantai 20/20
4-5. KM/WC 1 = 1.35 x 1.35 x 2.00 = 3.65 m2
6. Selasar = 2.85 x 0.85 x 1.00 = 2.42 m2
6.07 m2
2. Lantai 40/40
1. Teras = 16.00 x 2.00 x 1.00 = 32.00 m2
2. Ruang PKK = 3.85 x 5.85 x 1.00 = 22.52 m2
3. Ruang Serbaguna = 11.85 x 5.85 x 1.00 = 69.32 m2
123.85 m2
Luas Urugan Pasir
1. Lantai 20/20 = 6.07 x 0.05 = 0.30 m2
2. Lantai 40/40 = 123.85 x 0.05 = 6.19 m2
3. Pondasi = 0.80 x 84.50 x 0.05 = 3.38 m2
Jumlah Total = 9.88 m3

4 Pengurugan 1 m3 cadas padat 38.97 m3

Volume = 6.07 + 123.85 x 0.30 = 38.97 m3

III PEKERJAAN PONDASI

1 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP 32.53 m3


Gedung
Pbk =( 0.30 + 0.80 ) x 0.70 x 84.50 m' = 32.53 m3
2

2 Pemasangan 1 m3 batu kosong (anstamping) 13.52 m3


Gedung
Pbk = 0.80 x 0.20 x 84.50 m' = 13.52 m3

III PEKERJAAN DINDING


1 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP 16.40 m2

Tasram = 52.00 x 0.20 x 1.00 = 10.40 m2


= 0.80 x 0.20 x 15.00 = 2.40 m2
= 0.30 x 2.40 x 5.00 = 3.60 m2
16.40 m2

2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 3PP 51.43 m2

Dinding = 84.50 x 0.50 x 1.00 = 42.25 m2


= 2.20 x 0.60 x 5.00 = 6.60 m2 Kolom hias
48.85 m2
Luas Perlubangan
P1 = 0.90 x 0.50 x 3.00 = 1.35 m2
P2 = 0.80 x 0.50 x 2.00 = 0.80 m2
Ongliong = 0.85 x 0.50 x 1.00 = 0.43 m2
2.58 m2
Luas Netto = 48.85 - 2.58 = 51.43 m2

Hal. 17 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
3 Pemasangan 1m2 dinding bata merah (5x11x22)cmtebal ½ batu campuran 1SP : 6PP 226.13 m2

Dinding lantai 1 = 71.00 x 3.80 x 1.00 = 269.80 m2


= 13.50 x 3.30 x 1.00 = 44.55 m2
314.35 m2
Luas Perlubangan jml
P1 = 0.90 x 2.77 x 3.00 = 7.48 m2
P2 = 0.80 x 2.77 x 2.00 = 4.43 m2
J1 = 1.36 x 1.86 x 12.00 = 30.36 m2
B1 = 0.67 x 0.70 x 3.00 = 1.41 m2
Ongliong = 0.85 x 3.30 x 1.00 = 2.81 m2
= 1.35 x 1.30 x 2.00 = 3.51 m2
= 49.99 m2
Perlubangan Pas. Trasram Kolom hias
Luas Netto = 314.35 - 49.99 - 44.83 + 6.60 = 226.13 m2

V PEKERJAAN PLESTERAN
1 Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. 564.25 m2

1. Pasangan bata = 2.00 x 277.56 = 555.12 m2


2. Kolom hias = 0.80 x 2.40 x 5.00 = 9.60 m2
3. Plint keramik = 9.40 x 0.05 = (0.47) m2
4. Dinding keramik = = (14.10) m2
Jumlah Total = 564.25 m2

2 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP 4.48 m2

Kolom Hias = 0.10 x 0.55 x 5.00 = 0.28 m2


= 0.60 x 0.55 x 5.00 = 1.65 m2
= 0.30 x 0.70 x 5.00 = 1.05 m2
= 0.25 x 1.20 x 5.00 = 1.50 m2
Jumlah Total = 4.48 m2

3 Pemasangan 1 m2 acian. 569.05 m2

1. Plesteran = 564.25 x 1.00 = 564.25 m2


2. Sponengan = 48.00 x 0.10 = 4.80 m2
Jumlah Total = 569.05 m2

4 Sponengan 48.00 m1

= 0.80 x 12.00 x 5.00 = 48.00 m1

VI PEKERJAAN BETON
1 Lantai Kerja 6.50 m3
Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Lantai = 6.07 + 123.85 x 0.05 = 6.50 m3

2 Rabat Beton 4.10 m3


Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Tritisan = 17.60 x 2.00 x 0.80 x 0.10 = 2.82 m3
= 8.00 x 2.00 x 0.80 x 0.10 = 1.28 m3
4.10 m3

3 Sloof 15/25

a. Begisting = 0.25 x 2.00 x 84.50 = 42.25 m2 x 0.50 21.13 m2


b. Pembesian
-Besi 5 D 13 = 5.00 x 1.04 x 84.50 = 439.40 kg
-Begel Ø 8 - 150 = 563.00 x 0.393 x 0.70 = 154.88 kg
594.28 kg 594.28 kg

c. Beton bertulang = 0.15 x 0.25 x 84.50 = 3.17 m3 3.17 m3

4 Kolom 20/20

a. Begisting = 0.20 x 4.00 x 3.00 = 2.40 m2 x 0.50 6.00 m2


= 2.40 x 5.00 = 12.00 m2
b. Pembesian
-Besi 4 Ø 10 = 4.00 x 3.00 + 0.30 = 13.20 m1
= 13.20 x 5.00 x 0.62 = 40.92 kg
-Begel Ø 6 - 150 = 100.00 x 0.22 x 0.70 = 15.40 kg
56.32 kg 56.32 kg

c. Beton bertulang = 0.20 x 0.20 x 13.50 = 0.54 m3 0.54 m3

5 Kolom 11/11

1. Ruang utama = 22.00 x 3.80 = 83.60 m1 103.40 m1


2. KM/WC = 6.00 x 3.30 = 19.80 m1
103.40 m1

Hal. 18 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
6 Balok 15/30

a. Begisting = 0.375 x 2.00 x 16.00 = 12.00 m2 x 0.50 6.00 m2


b. Pembesian
-Besi 6 D 13 = 6.00 x 1.04 x 16.00 = 99.84 kg
-Begel Ø 6 - 150 = 107.00 x 0.22 x 0.80 = 18.83 kg
118.67 kg 118.67 kg

c. Beton bertulang = 0.15 x 0.20 x 16.00 = 0.48 m3 0.48 m3

9 Balok 15/20
Sloof Balok 15/30 Balok miring Balok miring
Panjang Ringbalk = 84.50 - 16.00 - 6.00 + 10.00
= 72.50 m'

a. Begisting = 0.20 x 2.00 x 72.50 = 29.00 m2 x 0.50 14.50 m2


b. Pembesian
-Besi 5 D 13 = 5.00 x 1.04 x 72.50 = 377.00 kg
-Begel Ø 8 - 150 = 483.00 x 0.393 x 0.60 = 113.89 kg
490.89 kg 490.89 kg

c. Beton bertulang = 0.15 x 0.20 x 72.50 = 2.18 m3 2.18 m3

10 Balok Latai 10/15 32.00 m1

= 16.00 x 2.00 = 32.00 m1

11 Plat Atap

a. Begisting = 3.00 x 3.50 x 1.00 = 10.50 m2 x 0.50 5.25 m2


b. Pembesian
-Besi Ø 10 - 150 = 3.10 x 0.62 x 46.00 = 88.41 kg
-Besi Ø 10 - 150 = 3.60 x 0.62 x 40.00 = 89.28 kg
177.69 kg 177.69 kg

c. Beton bertulang = 3.00 x 3.5 x 0.10 x 1.00 = 1.05 m3 1.05 m3

12 Shading

a. Begisting = 0.60 x 9.45 x 1.00 = 5.67 m2 x 0.50 2.84 m2


b. Pembesian
-Besi Ø 10 - 150 = 0.80 x 0.62 x 63.00 = 31.25 kg
-Besi Ø 10 - 150 = 9.45 x 0.62 x 4.00 = 23.44 kg
54.68 kg 54.68 kg

c. Beton bertulang = 0.60 x 9.45 x 0.12 x 1.00 = 0.68 m3 0.68 m3

VII PEKERJAAN KAYU


1 Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I 7.98 m2

P1 = 1.68 x 3.00 = 5.04 m2


P2 = 1.47 x 2.00 = 2.94 m2
7.98 m2

2 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas II ( kruing ) 1.45 m3

= 0.01 x 7.15 x 5.00 = 0.34 m3


= 0.01 x 1.80 x 5.00 = 0.09 m3
= 0.01 x 6.80 x 5.00 = 0.33 m3
= 0.01 x 2.90 x 5.00 = 0.14 m3
= 0.01 x 8.00 x 5.00 = 0.29 m3

= 0.01 x 4.00 x 2.00 = 0.08 m3


= 0.01 x 1.80 x 2.00 = 0.03 m3
= 0.01 x 3.40 x 2.00 = 0.07 m3
= 0.01 x 1.45 x 2.00 = 0.03 m3
= 0.01 x 4.00 x 2.00 = 0.06 m3
Jumlah Total = 1.45 m3

3 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruing ) 1.47 m3

= 0.01 x 22.00 x 2.00 = 0.42 m3


= 0.01 x 16.00 x 1.00 = 0.15 m3
= 0.01 x 16.00 x 2.00 = 0.31 m3
= 0.01 x 6.00 x 4.00 = 0.23 m3
= 0.01 x 1.50 x 4.00 = 0.06 m3
= 0.01 x 10.00 x 1.00 = 0.10 m3
= 0.01 x 7.00 x 4.00 = 0.20 m3
Jumlah Total = 1.47 m3

Hal. 19 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
4 Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II ( kruing ) 240.50 m2

= 14.25 x 5.00 x 2.00 x 1.00 = 142.50 m2


= 4.25 x 5.00 x 2.00 x 1.00 = 42.50 m2
= 18.50 x 3.00 x 1.00 x 1.00 = 55.50 m2
Jumlah Total = 240.50 m2

5 Lisplang GRC Board tebal 9 mm, L = 30 cm (terpasang & pengecatan), motif kayu 61.00 m1

= 18.50 x 2.00 = 37.00 m1


= 12.00 x 2.00 = 24.00 m1
Jumlah Total = 61.00 m1

6 Pemasangan 1 m2 atap genteng palentong kecil 240.50 m2

= 14.25 x 5.00 x 2.00 x 1.00 = 142.50 m2


= 4.25 x 5.00 x 2.00 x 1.00 = 42.50 m2
= 18.50 x 3.00 x 1.00 x 1.00 = 55.50 m2
Jumlah Total = 240.50 m2

7 Pemasangan 1 m’ bubung genteng palentong 34.00 m1


= 10.00 x 1.00 = 10.00 m1
= 6.00 x 4.00 = 24.00 m1
Jumlah Total = 34.00 m1

8 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III 186.28 m2
= 6.00 x 16.00 = 96.00 m2
= 3.00 x 17.60 = 52.80 m2
= 35.60 x 0.80 = 28.48 m2
= 3.00 x 3.00 = 9.00 m2
Jumlah Total = 186.28 m2

9 Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm 143.72 m2


= 6.00 x 16.00 = 96.00 m2
= 2.20 x 17.60 = 38.72 m2
= 3.00 x 3.00 = 9.00 m2
Jumlah Total = 143.72 m2

10 Pemasangan 1 m2 langit-langit kalsiboard ukuran (120x240x4) mm, tebal 4 mm 42.56 m2


= 0.80 x 17.60 = 14.08 m2
= 35.60 x 0.80 = 28.48 m2
Jumlah Total = 42.56 m2

11 Pemasangan 1 m’ list langit-langit gypsum profil 227.80 m1


= 12.00 x 4.00 = 48.00 m1
= 20.00 x 1.00 = 20.00 m1
= 36.00 x 1.00 = 36.00 m1
= 9.00 x 1.00 = 9.00 m1
= 5.40 x 2.00 = 10.80 m1
= 52.00 x 2.00 = 104.00 m1
Jumlah Total = 227.80 m1

VIII PEKERJAAN SANITASI

IX PEKERJAAN BESI DAN ALUMINIUM


1 Pemasangan 1 m kusen pintu alluminium 160.30 m'

P1 = 7.32 x 3.00 = 21.96 m'


P2 = 7.10 x 2.00 = 14.20 m'
J1 = 9.66 x 12.00 = 115.92 m'
B1 = 2.74 x 3.00 = 8.22 m'
Jumlah Total = 160.30 m'

2 Pemasangan 1 m2 jendela kaca rangka alluminium 28.61 m2

P1 = 0.47 x 3.00 = 1.41 m2


P2 = 0.41 x 2.00 = 0.81 m2
J1 = 2.11 x 12.00 = 25.33 m2
B1 = 0.35 x 3.00 = 1.06 m2
Jumlah Total = 28.61 m2

X PEKERJAAN KUNCI DAN KACA


1 Pemasangan 1 buah engsel pintu 15.00 m'
P1 = 3.00 x 3.00 = 9.00 m'
P2 = 3.00 x 2.00 = 6.00 m'
Jumlah Total = 15.00 m'

Hal. 20 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
2 Pemasangan 1 buah engsel jendela kupu-kupu 112.00 bh
P1 = 2.00 x 3.00 = 6.00 bh
P2 = 2.00 x 2.00 = 4.00 bh
J1 = 8.00 x 12.00 = 96.00 bh
B1 = 2.00 x 3.00 = 6.00 bh
Jumlah Total = 112.00 bh

3 Pemasangan 1 buah kait angin 112.00 bh


P1 = 2.00 x 3.00 = 6.00 bh
P2 = 2.00 x 2.00 = 4.00 bh
J1 = 8.00 x 12.00 = 96.00 bh
B1 = 2.00 x 3.00 = 6.00 bh
Jumlah Total = 112.00 bh

4 Pemasangan 1 buah kunci slot 5.00 bh


P1 = 1.00 x 3.00 = 3.00 bh
P2 = 1.00 x 2.00 = 2.00 bh
Jumlah Total = 5.00 bh

5 Pemasangan 1 m2 kaca tebal 5 mm 41.06 m2


P1 = 1.09 x 3.00 = 3.27 m2
P2 = 0.99 x 2.00 = 1.98 m2
J1 = 2.76 x 12.00 = 33.11 m2
B1 = 0.90 x 3.00 = 2.70 m2
Jumlah Total = 41.06 m2

6 Grendel pintu 61.00 m'


P1 = 2.00 x 3.00 = 6.00 m'
P2 = 2.00 x 2.00 = 4.00 m'
J1 = 4.00 x 12.00 = 48.00 m'
B1 = 1.00 x 3.00 = 3.00 m'
Jumlah Total = 61.00 m'

XI PEKERJAAN PENUTUP LANTAI DAN DINDING


1 Pemasangan 1m2 lantai keramik ukuran 40cm x40cm 123.85 m2
= 123.85 m2

2 Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm 6.07 m2


= 6.07 m2

3 Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm 9.40 m1

= 4.70 x 1.00 x 2.00 = 9.40 m1

4 Pemasangan 1 m2 dinding keramik 20cm x 20cm 14.10 m2

= 9.40 x 1.50 = 14.10 m2

XII PEKERJAAN PENGECATAN


1 Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) 569.05 m2

569.05 x 1.00 = 569.05 m2

2 Pengecatan 1 m2 plafon ( 1 lapis cat dasar, 2 lapis cat penutup) luas total 186.28 m2

186.28 x 1.00 = 186.28 m2

XIII PEKERJAAN INSTALASI LISTRIK


1 Instalasi Listrik 28.00 ttk
SL 18 watt = 16.00 bh = 16.00 ttk
Pijar 5 w = 6.00 bh = 6.00 ttk
Stop kontak = 6.00 bh = 6.00 ttk
= 28.00 ttk

2 Saklar ganda = 2.00 bh 2.00 bh


3 Saklar tunggal = 6.00 bh 6.00 bh
4 Stop kontak = 6.00 bh 6.00 bh
5 Lampu pijar 5 W philips = 6.00 bh 6.00 bh
6 Lampu SL 18 Watt Phillips = 16.00 bh 16.00 bh

XIV PEKERJAAN LAIN - LAIN


1 Pasang salura U Ø 20 cm, termasuk pas. Dinding 60.00 m'
= 30.00 x 2.00 = 60.00 m'

60.00 m'

Hal. 21 dari 297


BACK UP PERHITUNGAN

KEGIATAN : PEMBANGUNAN GEDUNG KANTOR


PEKERJAAN : PEMBANGUNAN GEDUNG KANTOR KECAMATAN SRUWENG
LOKASI : KEC. SRUWENG, KEBUMEN
TAHUN ANGGARAN : 2017

F. RUMAH DINAS

TOTAL
NO PERHITUNGAN VOLUME
VOLUME

I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan bauwplank 1.00

II PEKERJAAN TANAH

1 Penggalian 1 m3 tanah biasa sedalam 1 m 2.36


Panjang total pondasi batu kali
arah H = 12.50 + 9.00 + 13.50 + 12.00 = 47.00 m'
arah V = 3.00 + 3.00 + 6.50 + 6.00 + 3.50 = 22.00 m'
= 6.50 + 2.00 + 3.00 + 9.50 = 21.00 m'
90.00 m'

Vol. Pbk = 0.80 x 0.40 x 90.00 = 28.80 m3


Rollax = 0.20 x 0.20 x 59.00 = 2.36 m3
2.36 m3

2 Pengurugan kembali 1 m3 galian tanah 8.64

= 0.30 x 28.80 = 8.64 m3

3 Pengurugan 1 m3 dengan pasir urug 9.38

Panjang Lebar Jumlah


1. Lantai 20/20
10. KM/WC 1 = 1.35 x 1.85 x 1.00 = 2.50 m2
2.50 m2
2. Lantai 40/40
1. Teras = 1.50 x 3.00 x 1.00 = 4.50 m2
2. Ruang Tidur = 4.35 x 2.85 x 1.00 = 12.40 m2
3. Ruang Tamu = 3.85 x 2.85 x 1.00 = 10.97 m2
4. Garasi = 5.35 x 3.35 x 1.00 = 17.92 m2
5. Rg. Keluarga = 4.35 x 3.00 x 1.00 = 13.05 m2
= 6.35 x 2.85 x 1.00 = 18.10 m2
6. Ruang Tidur = 2.85 x 3.35 x 1.00 = 9.55 m2
7. Ruang Tidur = 3.35 x 2.85 x 1.00 = 9.55 m2
8. Ruang Cuci = 2.85 x 3.00 x 1.00 = 8.55 m2
9.Dapur = 1.50 x 1.50 x 1.00 = 2.25 m2
= 1.85 x 3.35 x 1.00 = 6.20 m2
113.03 m2
Luas Urugan Pasir
1. Lantai 20/20 = 2.50 x 0.05 = 0.12 m2
2. Lantai 40/40 = 113.03 x 0.05 = 5.65 m2
3. Pondasi = 0.80 x 90.00 x 0.05 = 3.60 m2
Jumlah Total = 9.38 m3

4 Pengurugan 1 m3 cadas padat 34.66

Volume = 2.50 + 113.03 x 0.30 = 34.66 m3

III PEKERJAAN PONDASI


1 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP 34.65
Gedung
Pbk =( 0.30 + 0.80 ) x 0.70 x 90.00 m' = 34.65 m3
2

2 Pemasangan 1 m3 batu kosong (anstamping) 14.40


Gedung
Pbk = 0.80 x 0.20 x 90.00 m' = 14.40 m3

IV PEKERJAAN DINDING
1 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP 11.80

Tasram = 59.00 x 0.20 x 1.00 = 11.80 m2

Hal. 22 dari 297


2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 3PP 42.11

Dinding = 90.00 x 0.50 x 1.00 = 45.00 m2


= 3.35 x 0.80 x 1.00 = 2.68 m2
47.68 m2
Luas Perlubangan
P1 = 1.36 x 0.50 x 1.00 = 0.68 m2
P2 = 0.94 x 0.50 x 6.00 = 2.82 m2
P3 = 0.80 x 0.50 x 1.00 = 0.40 m2
Folding = 3.35 x 0.50 x 1.00 = 1.68 m2
5.58 m2
Luas Netto = 47.68 - 5.58 = 42.11 m2

3 Pemasangan 1m2 dinding bata merah (5x11x22)c, tebal ½ batu campuran 1SP : 6PP 280.06

Dinding lantai 1 = 84.50 x 3.80 x 1.00 = 321.10 m2


= 5.50 x 1.00 x 1.00 = 5.50 m2
= 0.35 x 2.70 x 4.00 = 3.78 m2
330.38 m2
Luas Perlubangan jml
P1 = 1.36 x 2.16 x 1.00 = 2.94 m2
P2 = 0.94 x 2.16 x 6.00 = 12.18 m2
P3 = 0.80 x 2.16 x 1.00 = 1.73 m2
Folding = 3.35 x 2.52 x 1.00 = 8.44 m2
J1 = 0.50 x 1.88 x (2.00) = (1.88) m2
J2 = 0.50 x 2.32 x (8.00) = (9.28) m2
B1 = 0.50 x 1.08 x (6.00) = (3.24) m2
= 10.89 m2
Perlubangan Trasram
Luas Netto = 330.38 - 10.89 - 39.43 = 280.06 m2

V PEKERJAAN PLESTERAN
1 Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. 629.00

1. Pasangan bata = 2.00 x 322.17 = 644.34 m2


2. Plin keramik = 9.90 x 0.05 = (0.50) m2
3. Dinding keramik = (14.85) m2
Jumlah Total = 629.00 m2

2 Pemasangan 1 m2 acian. 629.00

= 629.00 x 1.00 = 629.00 m2

VI PEKERJAAN BETON
1 Lantai Kerja 5.78
Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Lantai = 2.50 + 113.03 x 0.05 = 5.78 m3

2 Rabat Beton 6.46


Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Tritisan = 24.00 x 2.00 x 1.20 x 0.10 = 5.76 m3
= 3.50 x 2.00 x 1.00 x 0.10 = 0.70 m3
Jumlah Total = 6.46 m3

3 Sloof 15/25

a. Begisting = 0.25 x 2.00 x 93.00 = 46.50 m2 x 0.50 23.25


b. Pembesian
-Besi 5 D 13 = 5.00 x 1.04 x 93.00 = 483.60 kg
-Begel Ø 8 - 150 = 620.00 x 0.393 x 0.70 = 170.56 kg
654.16 kg 654.16

c. Beton bertulang = 0.15 x 0.25 x 93.00 = 3.49 m3 3.49

4 Kolom 15/25

a. Begisting = 0.20 x 4.00 x 4.00 = 3.20 m2 x 0.50 25.60


= 3.20 x 16.00 = 51.20 m2
b. Pembesian
-Besi 6 D 13 = 6.00 x 4.00 + 0.30 = 25.80 m1
= 25.80 x 16.00 x 1.04 = 429.31 kg
-Begel Ø 8 - 150 = 427.00 x 0.39 x 0.70 = 117.47 kg
546.78 kg 546.78

c. Beton bertulang = 0.15 x 0.25 x 64.00 = 2.40 m3 2.40

5 Kolom 11/11 60.00

= 4.00 x 15.00 x 1.00 = 60.00 m1

Hal. 23 dari 297


6 Balok 15/30

a. Begisting = 0.375 x 2.00 x 5.50 = 4.13 m2 x 0.50 2.06


b. Pembesian
-Besi 6 D 13 = 6.00 x 1.04 x 5.50 = 34.32 kg
-Begel Ø 6 - 150 = 37.00 x 0.22 x 0.80 = 6.51 kg
40.83 kg 40.83

c. Beton bertulang = 0.15 x 0.3 x 5.50 = 0.25 m3 0.25

7 Balok 15/20

a. Begisting = 0.20 x 2.00 x 93.00 = 37.20 m2 x 0.50 18.60


b. Pembesian
-Besi 5 D 13 = 5.00 x 1.04 x 93.00 = 483.60 kg
-Begel Ø 8 - 150 = 620.00 x 0.393 x 0.60 = 146.20 kg
629.80 kg 629.80

c. Beton bertulang = 0.15 x 0.20 x 93.00 = 2.79 m3 2.79

8 Balok Latai 10/15 32.50

= 1.00 x 1.00 x 32.50 = 32.50 m2

9 Plat Atap

a. Begisting = 0.50 x 3.00 x 1.00 = 1.50 m2 x 0.50 0.75


b. Pembesian
-Besi Ø 10 - 150 = 0.60 x 0.62 x 40.00 = 14.88 kg
-Besi Ø 10 - 150 = 3.10 x 0.62 x 6.00 = 11.53 kg
26.41 kg 26.41

c. Beton bertulang = 0.50 x 3.00 x 0.12 x 1.00 = 0.18 m3 0.18

10 Shading

a. Begisting = 0.60 x 13.00 x 1.00 = 7.80 m2 x 0.50 3.90


b. Pembesian
-Besi Ø 10 - 150 = 0.80 x 0.62 x 87.00 = 43.15 kg
-Besi Ø 10 - 150 = 13.00 x 0.62 x 4.00 = 32.24 kg
75.39 kg 75.39

c. Beton bertulang = 0.60 x 13 x 0.1 x 1.00 = 0.78 m3 0.78

11 Meja Dapur

a. Begisting = 0.60 x 3.00 x 1.00 = 1.80 m2 x 0.50 0.90


b. Pembesian
-Besi Ø 10 - 150 = 0.80 x 0.62 x 20.00 = 9.92 kg
-Besi Ø 10 - 150 = 3.00 x 0.62 x 4.00 = 7.44 kg
17.36 kg 17.36

c. Beton bertulang = 0.60 x 3 x 0.1 x 1.00 = 0.18 m3 0.18

VII PEKERJAAN KAYU, ATAP DAN PLAFOND


1 Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau I 0.89

P1 = 0.04 x 1.00 = 0.04 m3


P2 = 0.04 x 6.00 = 0.24 m3
P3 = 0.04 x 1.00 = 0.04 m3
J1 = 0.04 x 2.00 = 0.07 m3
J2 = 0.04 x 8.00 = 0.35 m3
B1 = 0.03 x 6.00 = 0.15 m3
Jumlah Total = 0.89 m3

2 Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I atau II 14.70

P1 = 1.26 x 2.10 x 1.00 = 2.65 m2


P2 = 0.84 x 2.10 x 6.00 = 10.58 m2
P3 = 0.70 x 2.10 x 1.00 = 1.47 m2
Jumlah Total = 14.70 m2

3 Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I atau II 3.96
J1 = 0.35 x 2.00 = 0.70 m2
J2 = 0.41 x 8.00 = 3.26 m2
B1 = - x 6.00 = - m2
Jumlah Total 3.96 m2

Hal. 24 dari 297


4 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas II ( kruing ) 1.95
Jml kuda kuda
1. Balok tarik = 0.01 x 9.65 x 1.00 x 2.00 = 0.19 m3
2. Balok pengaku = 0.01 x 1.00 x 2.00 x 2.00 = 0.04 m3
3. Balok gapit bawah = 0.0072 x 2.99 x 4.00 x 2.00 = 0.17 m3
4. Balok gapit atas = 0.01 x 5.00 x 1.00 x 2.00 = 0.10 m3
5. Balok tekan = 0.01 x 5.35 x 2.00 x 2.00 = 0.21 m3
6. Balok miring = 0.01 x 1.33 x 2.00 x 2.00 = 0.05 m3
= 0.01 x 2.23 x 2.00 x 2.00 = 0.09 m3
7. Kaki kuda2 = 0.01 x 1.55 x 2.00 x 2.00 = 0.06 m3
= 0.01 x 2.00 x 1.00 x 2.00 = 0.04 m3
1. Balok tarik = 0.01 x 9.65 x 1.00 x 2.00 = 0.19 m3
2. Balok pengaku = 0.01 x 1.00 x 2.00 x 2.00 = 0.04 m3
3. Balok gapit bawah = 0.0072 x 2.99 x 4.00 x 2.00 = 0.17 m3
4. Balok gapit atas = 0.01 x 5.00 x 1.00 x 2.00 = 0.10 m3
5. Balok tekan = 0.01 x 3.40 x 2.00 x 2.00 = 0.13 m3
6. Balok miring = 0.01 x 1.33 x 2.00 x 2.00 = 0.05 m3
= 0.01 x 2.23 x 2.00 x 2.00 = 0.09 m3
7. Kaki kuda2 = 0.01 x 2.00 x 1.00 x 2.00 = 0.04 m3

1. Balok tarik = 0.01 x 3.00 x 1.00 x 2.00 = 0.06 m3


2. Balok pengaku = 0.01 x 1.00 x 1.00 x 2.00 = 0.02 m3
3. Balok tekan = 0.01 x 5.35 x 1.00 x 2.00 = 0.10 m3
4. Balok miring = 0.01 x 2.23 x 1.00 x 2.00 = 0.04 m3
Jumlah Total = 1.95 m3

5 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruing ) 1.90


1. Murplat = 0.01 x 21.50 x 2.00 = 0.41 m3
2. Gording 1 = 0.01 x 16.90 x 2.00 = 0.32 m3
3. Gording 2 = 0.01 x 12.00 x 2.00 = 0.23 m3
4. Gording 3 = 0.01 x 7.90 x 2.00 = 0.15 m3
5. Nok = 0.01 x 2.60 x 2.00 = 0.05 m3
6. Nok jurai = 0.01 x 8.30 x 4.00 = 0.32 m3
7. Murplat teras = 0.01 x 6.00 x 1.00 = 0.06 m3
8. Nok jurai = 0.01 x 3.75 x 2.00 = 0.07 m3
9. Nok talang = 0.01 x 3.75 x 2.00 = 0.07 m3
10. Nok teras = 0.01 x 1.50 x 1.00 = 0.01 m3
11. Kaki kuda teras = 0.01 x 0.60 x 1.00 = 0.00 m3
12. Balok angin = 0.01 x 2.80 x 2.00 = 0.05 m3
13. Balok sokong = 0.01 x 3.60 x 4.00 = 0.14 m3
Jumlah Total = 1.90 m3

6 Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II ( kruing ) 208.59

= 8.40 x 6.90 x 2.00 x 1.00 = 115.92 m2


= 5.90 x 6.90 x 2.00 x 1.00 = 81.42 m2
= 1.50 x 3.75 x 2.00 x 1.00 = 11.25 m2
Jumlah Total = 208.59 m2

7 Lisplang GRC Board tebal 9 mm, L = 30 cm (terpasang & pengecatan), motif kayu 55.20

= 11.80 x 2.00 = 23.60 m1


= 15.80 x 2.00 = 31.60 m1
Jumlah Total = 55.20 m1

8 Pemasangan 1 m2 atap genteng palentong kecil 208.59

= 8.40 x 6.90 x 2.00 x 1.00 = 115.92 m2


= 5.90 x 6.90 x 2.00 x 1.00 = 81.42 m2
= 1.50 x 3.75 x 2.00 x 1.00 = 11.25 m2
Jumlah Total = 208.59 m2

9 Pemasangan 1 m’ bubung genteng palentong 51.00

= 2.80 x 1.00 = 2.80 m1


= 8.30 x 4.00 = 33.20 m1
= 3.75 x 4.00 = 15.00 m1
Jumlah Total = 51.00 m1

10 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III 150.31

= 9.50 x 12.00 = 114.00 m2


= 2.00 x 3.00 = 6.00 m2
= 29.46 x 0.98 = 28.87 m2
= 3.00 x 0.48 = 1.44 m2
Jumlah Total = 150.31 m1

11 Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm 117.60

= 9.50 x 12.00 = 114.00 m2


= 1.20 x 3.00 = 3.60 m2
Jumlah Total = 117.60 m2

Hal. 25 dari 297


12 Pemasangan 1 m2 langit-langit kalsiboard ukuran (120x240x4) mm, tebal 4 mm 30.31

= 29.46 x 0.98 = 28.87 m2


= 3.00 x 0.48 = 1.44 m2
Jumlah Total = 30.31 m2

Hal. 26 dari 297


13 Pemasangan 1 m’ list langit-langit gypsum profil 223.00

= 9.00 x 1.00 = 9.00 m1


= 15.00 x 1.00 = 15.00 m1
= 14.00 x 1.00 = 14.00 m1
= 18.00 x 1.00 = 18.00 m1
= 13.00 x 1.00 = 13.00 m1
= 7.00 x 1.00 = 7.00 m1
= 14.00 x 1.00 = 14.00 m1
= 9.00 x 1.00 = 9.00 m1
= 13.00 x 1.00 = 13.00 m1
= 19.00 x 1.00 = 19.00 m1
= 46.00 x 2.00 = 92.00 m1
Jumlah Total = 223.00 m1

VIII PEKERJAAN SANITASI

IX PEKERJAAN BESI DAN ALUMINIUM


1 Pintu besi Folding Gate (tepasang) 8.44

= 3.35 x 2.52 = 8.44 m2

X PEKERJAAN KUNCI DAN KACA


1 Pemasangan 1 buah engsel pintu 27.00

P1 = 6.00 x 1.00 = 6.00 bh


P2 = 3.00 x 6.00 = 18.00 bh
P3 = 3.00 x 1.00 = 3.00 bh
= 27.00 bh

2 Pemasangan 1 buah engsel jendela kupu-kupu 36.00

J1 = 2.00 x 2.00 = 4.00 bh


J2 = 4.00 x 8.00 = 32.00 bh
= 36.00 bh

3 Pemasangan 1 buah kait angin 36.00

J1 = 2.00 x 2.00 = 4.00 bh


J2 = 4.00 x 8.00 = 32.00 bh
= 36.00 bh

4 Pemasangan 1 buah kunci slot 15.00

P1 = 1.00 x 1.00 = 1.00 bh


P2 = 1.00 x 6.00 = 6.00 bh
P3 = 1.00 x 1.00 = 8.00 bh
= 15.00 bh

5 Pemasangan 1 m2 kaca tebal 5 mm 13.33

J1 = 1.50 x 2.00 = 3.00 m2


J2 = 0.99 x 8.00 = 7.96 m2
B1 = 0.39 x 6.00 = 2.37 m2
= 13.33 m2

2 Grendel pintu 29.00

J1 = 1.00 x 2.00 = 2.00 m'


J2 = 2.00 x 8.00 = 16.00 m'
P1 = 4.00 x 1.00 = 4.00 m'
P2 = 1.00 x 6.00 = 6.00 m'
P3 = 1.00 x 1.00 = 1.00 m'
29.00 m'

XI PEKERJAAN PENUTUP LANTAI DAN DINDING


1 Pemasangan 1m2 lantai keramik ukuran 40cm x40cm 113.03

Jumlah Total = 113.03 m2

2 Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm 2.50

Jumlah Total = 2.50 m2

3 Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm 9.90

= 5.70 x 1.00 x 1.00 = 5.70 m1


= 4.20 x 1.00 x 1.00 = 4.20 m1
Jumlah Total = 9.90 m1

Hal. 27 dari 297


4 Pemasangan 1 m2 dinding keramik 20cm x 20cm 14.85

= 5.70 x 1.50 x 1.00 = 8.55 m2


= 4.20 x 1.50 x 1.00 = 6.30 m2
Jumlah Total = 14.85 m2

5 Pemasangan 1 m2 dinding batu tempel susun sirih 5.58

= 2.70 x 0.35 x 4.00 = 3.78 m2


= 1.00 x 1.80 x 1.00 = 1.80 m2
Jumlah Total = 5.58 m2

XII PEKERJAAN PENGECATAN


1 Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) 629.00

629.00 x 1.00 = 629.00 m2

2 Pengecatan 1 m2 plafon ( 1 lapis cat dasar, 2 lapis cat penutup) 147.91

147.91 x 1.00 = 147.91 m2

XIII PEKERJAAN INSTALASI LISTRIK


1 Pemasangan meter listrik 900 watt 1.00
2 Instalasi Listrik 30.00
SL 18 watt = 17.00 bh = 17.00 ttk
Pijar 5 w = 5.00 bh = 5.00 ttk
Stop kontak = 8.00 bh = 8.00 ttk
= 30.00 ttk

3 Saklar ganda 1.00 bh 1.00


4 Saklar tunggal 10.00 bh 10.00
5 Stop kontak 8.00 bh 8.00
6 Lampu pijar 5 W philips 5.00 bh 5.00
7 Lampu SL 18 Watt Phillips 17.00 bh 17.00

XIV PEKERJAAN LAIN - LAIN


1 Pasang salura U Ø 20 cm, termasuk pas. Dinding 45.50

= 45.50 x 1.00 = 45.50 m'

Hal. 28 dari 297


BACK UP PERHITUNGAN

TOTAL
VOLUME

ls

m3

m3

m3

m3

m3

m3

m2

Hal. 29 dari 297


m2

m2

m2

m2

m3

m3

m2

kg

m3

m2

kg

m3

m3

Hal. 30 dari 297


m2

kg

m3

m2

kg

m3

m1

m2

kg

m3

m2

kg

m3

m2

kg

m3

m3

m2

m2

Hal. 31 dari 297


m3

m3

m2

m1

m2

m1

m2

m2

Hal. 32 dari 297


m2

Hal. 33 dari 297


m1

m2

bh

bh

bh

bh

m2

m'

m2

m2

m1

Hal. 34 dari 297


m2

m2

m2

m2

bh
ttk

bh
bh
bh
bh
bh

m'

Hal. 35 dari 297


BACK UP PERHITUNGAN

KEGIATAN : PEMBANGUNAN GEDUNG KANTOR


PEKERJAAN : PEMBANGUNAN GEDUNG KANTOR KECAMATAN SRUWENG
LOKASI : KEC. SRUWENG, KEBUMEN
TAHUN ANGGARAN : 2017

C. KANTOR PELAYANAN

TOTAL
NO PERHITUNGAN VOLUME
VOLUME

I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan bauwplank 1.00 ls

2 1 M2 Pasang Paving blok segi 4, t. 8 cm 190.00 m2


II PEKERJAAN TANAH
1 Penggalian 1 m3 tanah biasa sedalam 1 m 40.20 m3
Panjang total pondasi batu kali
arah H = 16.00 + 16.00 + 5.00 = 37.00 m'
arah V = 14.00 + 2.50 + 2.50 + 14.00 = 33.00 m'
70.00 m'

Vol. Pbk = 1.00 x 0.35 x 70.00 = 24.50 m3


Foot Plat = 1.00 x 0.65 x 18.00 = 11.70 m3
Rollax = 0.20 x 0.20 x 71.40 = 2.86 m3
= 0.20 x 0.15 x 38.00 = 1.14 m3
40.20 m3

2 Pengurugan kembali 1 m3 galian tanah 12.06 m3

= 0.30 x 40.20 = 12.06 m3

3 Pengurugan 1 m3 dengan pasir urug 35.16 m3


tebal pasir
Foot Plat = 1.00 x 18.00 x 0.10 = 1.80 m3
Lantai = 16.00 x 14.00 x 0.10 = 22.40 m3
= 3.10 x 6.40 x 0.10 = 1.98 m3
= 3.60 x 5.50 x 0.10 = 1.98 m3
Pondasi = 1.00 x 70.00 x 0.10 = 7.00 m3
Jumlah Total = 35.16 m3

4 Pengurugan 1 m3 cadas padat 145.38 m3

= 16.00 x 14.00 x 0.57 = 127.73 m3


= 2.80 x 5.80 x 0.57 = 9.26 m3
= 3.00 x 4.90 x 0.57 = 8.38 m3
145.38 m3

III PEKERJAAN PONDASI


1 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP 26.95 m3
Gedung
Pbk =( 0.30 + 0.80 ) x 0.70 x 70.00 m' = 26.95 m3
2

2 Pemasangan 1 m3 batu kosong (anstamping) 14.00 m3


Gedung
Pbk = 1.00 x 0.20 x 70.00 m' = 14.00 m3

IV PEKERJAAN DINDING
1 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP 5.70 m2

Tasram = 38.00 x 0.15 x 1.00 = 5.70 m2

2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 3PP 28.82 m2

Dinding = 16.00 x 0.50 x 1.00 = 8.00 m2


Tasram = 71.40 x 0.30 x 1.00 = 21.42 m2
29.42 m2

Luas Perlubangan = 0.20 x 0.50 x 6.00 = 0.60 m2


Luas Netto = 29.42 - 0.60 = 28.82 m2

Hal. 36 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
3 Pemasangan 1m2 dinding bata merah (5x11x22)cm, tebal ½ batu campuran 1SP : 6PP 125.07 m2

Dinding lantai 1 = 16.00 x 3.95 x 1.00 = 63.20 m2


= 43.00 x 1.45 x 1.00 = 62.35 m2
= 2.50 x 2.00 x 2.00 = 10.00 m2
135.55 m2
jml
Luas Perlubangan = 0.15 x 0.30 x 18.00 = 0.81 m2
= 0.20 x 3.95 x 6.00 = 4.74 m2
= 0.20 x 1.45 x 17.00 = 4.93 m2
= 10.48 m2
Perlubangan
Luas Netto = 135.55 - 10.48 = 125.07 m2

V PEKERJAAN PLESTERAN
1 Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. 314.35 m2

= 2.00 x 132.47 = 264.94 m2


= 0.60 x 3.95 x 6.00 = 14.22 m2
= 0.60 x 1.45 x 17.00 = 14.79 m2
= 0.80 x 1.50 x 17.00 = 20.40 m2
Jumlah Total = 314.35 m2

2 Pemasangan 1 m2 acian. 658.24 m2

= 314.35 x 2.00 = 628.70 m2


= 295.40 x 0.10 = 29.54 m2
Jumlah Total = 658.24 m2

3 Sponengan 295.40 m1

= 4.00 x 3.95 x 6.00 = 94.80 m1


= 4.00 x 1.45 x 17.00 = 98.60 m1
= 4.00 x 1.50 x 17.00 = 102.00 m1
Jumlah Total = 295.40 m1

VI PEKERJAAN BETON
1 Lantai Kerja 22.38 m3
Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Foot plat = 1.00 x 1.00 x 0.10 x 14.00 = 1.40 m3

Lantai = 14.00 x 16.00 x 1.00 x 0.08 = 17.92 m3


= 6.40 x 3.10 x 1.00 x 0.08 = 1.59 m3
= 5.10 x 1.80 x 2.00 x 0.08 = 1.47 m3
22.38 m3

2 Rabat Beton 5.86 m3


Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Tritisan = 17.60 x 1.00 x 0.80 x 0.10 = 1.41 m3
= 4.40 x 4.00 x 0.80 x 0.10 = 1.41 m3
= 5.90 x 2.00 x 0.80 x 0.10 = 0.94 m3
= 7.50 x 2.00 x 0.30 x 0.10 = 0.45 m3
= 11.80 x 2.00 x 0.70 x 0.10 = 1.65 m3
5.86 m3

3 Pondasi Foot Plat 0.8 x 0.8 m

a. Begisting 4.48 m2
= 0.20 x 3.20 x 14.00 = 8.96 m2 x 0.5
b. Pembesian
-Begel Ø 12 - 150 = 5.00 x 0.89 x 2.30 x 14.00 = 142.81 kg
= 5.00 x 0.89 x 2.30 x 14.00 = 142.81 kg
285.61 kg 285.61 kg

c. Beton bertulang = 0.8 x 0.80 x 0.15 x 14.00 = 1.34 m3 2.06 m3


= 0.04 x 0.64 x 0.15 x 14.00 = 0.71 m3
2
2.06 m3

4 Sloof 15/20

a. Begisting = 0.20 x 2.00 x 108.00 = 43.20 m2 x 0.50 21.60 m2


b. Pembesian
-Besi 4 Ø 12 = 4.00 x 0.89 x 108.00 = 383.18 kg
-Begel Ø 6 - 150 = 720.00 x 0.22 x 0.60 = 95.04 kg
478.22 kg 478.22 kg

c. Beton bertulang = 0.15 x 0.20 x 108.00 = 3.24 m3 3.24 m3

Hal. 37 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
5 Kolom 30/30

a. Begisting = 0.30 x 4.00 x 9.75 = 11.70 m2 x 0.50 23.40 m2


= 11.70 x 4.00 = 46.80 m2
b. Pembesian
-Besi 4 Ø 12 = 4.00 x 9.75 + 0.50 = 41.00 m1
= 41.00 x 4.00 x 0.89 = 145.47 kg
-Besi 4 Ø 12 = 4.00 x 9.75 + 0.89 = 42.55 m1
= 42.55 x 9.75 x 0.89 = 367.97 kg
-Begel Ø 8 - 150 = 260.00 x 0.39 x 1.10 = 112.40 kg
625.83 kg 625.83 kg

c. Beton bertulang = 0.30 x 0.30 x 39.00 = 3.51 m3 3.51 m3

-
6 Kolom 20/20

a. Begisting = 0.20 x 4.00 x 6.55 = 5.24 m2 x 0.50 36.68 m2


= 5.24 x 14.00 = 73.36 m2
b. Pembesian
-Besi 4 Ø 12 = 4.00 x 6.55 + 0.50 = 28.20 m1
= 28.20 x 14.00 x 0.89 = 350.19 kg
-Begel Ø 8 - 150 = 611.00 x 0.39 x 0.70 = 168.09 kg
518.27 kg

c. Beton bertulang = 0.2 x 0.2 x 91.70 = 3.67 m3

a. Begisting = 0.2 x 4 x 5.00 = 4.00 m2 x 0.50 18.00 m2


= 4.00 x 9.00 = 36.00 m2
b. Pembesian
-Besi 4 Ø 12 = 4.00 x 5.00 + 0.25 = 21.00 m1
= 21.00 x 9.00 x 0.89 = 167.64 kg
-Begel Ø 8 - 150 = 300.00 x 0.39 x 0.70 = 82.53 kg
250.17 kg

c. Beton bertulang = 0.2 x 0.2 x 45.00 = 1.80 m3

a. Begisting = 36.68 + 18.00 = 54.68 m2 54.68 m2


b. Pembesian = 518.27 + 250.17 = 768.45 kg 768.45 kg
c. Beton bertulang = 3.67 + 1.80 = 5.47 m3 5.47 m3

7 Kolom 15/15

a. Begisting = 0.5 x 2 x 2.00 = 2.00 m2 x 0.50 2.00 m2


= 2.00 x 2.00 = 4.00 m2
b. Pembesian
-Besi 4 Ø 12 = 4.00 x 2.00 + 0.00 = 8.00 m1
= 8.00 x 2.00 x 0.89 = 14.19 kg
-Begel Ø 6 - 150 = 27.00 x 0.22 x 0.50 = 2.97 kg
17.16 kg 17.16 kg

c. Beton bertulang = 0.15 x 0.15 x 4.00 = 0.09 m3 0.09 m3

8 Balok 20/35
a. Begisting
= 0.45 x 2 x 144.00 = 129.60 m2 x 0.50 64.80 m2

b. Pembesian
-Besi 5 Ø 12 = 5.00 x 0.89 x 144.00 = 638.64 kg
-Besi 2 Ø 10 = 2.00 x 0.62 x 144.00 = 178.56 kg
-Begel Ø 86 - 125 = 1,152.00 x 0.22 x 1.00 = 253.44 kg
1,070.64 kg 1,070.64 kg

c. Beton bertulang = 0.2 x 0.35 x 144.00 = 10.08 m3 10.08 m3

9 Balok 15/20
a. Begisting
= 0.2 x 2 x 57.00 = 22.80 m2 x 0.50 11.40 m2

b. Pembesian
-Besi 4 Ø 12 = 4.00 x 0.89 x 57.00 = 202.24 kg
-Begel Ø 6 - 150 = 380.00 x 0.22 x 0.60 = 50.16 kg
252.40 kg 252.40 kg

c. Beton bertulang = 0.15 x 0.2 x 57.00 = 1.71 m3 1.71 m3

Hal. 38 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
10 Balok Latai 15/20
a. Begisting
= 0.2 x 2 x 16.00 = 6.40 m2 x 0.50 3.20 m2
b. Pembesian
-Besi 4 Ø 12 = 4.00 x 0.89 x 16.00 = 56.77 kg
-Begel Ø 6 - 150 = 107.00 x 0.22 x 0.60 = 14.12 kg
70.89 kg 70.89 kg

c. Beton bertulang = 0.15 x 0.2 x 16.00 = 0.48 m3 0.48 m3

11 Ring Balok 15/20

a. Begisting = 0.2 x 2 x 82.50 = 33.00 m2 x 0.50 16.50 m2

b. Pembesian
-Besi 4 Ø 12 = 4.00 x 0.89 x 82.50 = 292.71 kg
-Begel Ø 6 - 150 = 550.00 x 0.22 x 0.60 = 72.60 kg
365.31 kg 365.31 kg

c. Beton bertulang = 0.15 x 0.2 x 82.50 = 2.48 m3 2.48 m3

12 Plat Shading

a. Begisting = 0.60 x 5.00 x 1.00 = 3.00 m2 x 0.50 1.50 m2


b. Pembesian
-Besi Ø 8 - 150 = 0.80 x 0.39 x 33.00 = 10.38 kg
-Besi Ø 8 - 150 = 5.00 x 0.39 x 4.00 = 7.86 kg
18.24 kg 18.24 kg

c. Beton bertulang = 0.60 x 5 x 0.08 x 0.08 = 0.02 m3 0.02 m3

VII PEKERJAAN KAYU


1 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas II ( kruing ) 0.42 m3

= 0.01 x 5.50 x 2.00 = 0.11 m3


= 0.01 x 2.80 x 2.00 = 0.05 m3
= 0.01 x 6.80 x 2.00 = 0.13 m3
= 0.01 x 2.90 x 2.00 = 0.06 m3
= 0.01 x 5.00 x 2.00 = 0.07 m3
0.42 m3

2 Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas II ( kruing ) 0.85 m3

= 0.01 x 4.25 x 19.00 = 0.58 m3


= 0.01 x 6.15 x 6.00 = 0.27 m3
0.85 m3

3 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruing ) 0.48 m3

= 0.01 x 1.50 x 1.00 = 0.01 m3


= 0.01 x 6.50 x 2.00 = 0.12 m3
= 0.01 x 9.50 x 2.00 = 0.18 m3
= 0.01 x 4.00 x 4.00 = 0.15 m3
0.48 m3

4 Pemasangan 1 m3 konstruksi gordeng expose, kayu kelas II ( kruing ) 3.19 m3

= 0.01 x 16.40 x 2.00 = 0.31 m3


= 0.01 x 22.50 x 2.00 = 0.43 m3
= 0.01 x 27.50 x 2.00 = 0.53 m3
= 0.01 x 8.50 x 4.00 = 0.33 m3
= 0.01 x 2.00 x 4.00 = 0.08 m3
= 0.01 x 55.00 x 1.00 = 0.53 m3
= 0.01 x 59.00 x 1.00 = 0.57 m3
= 0.01 x 6.30 x 2.00 = 0.12 m3
= 0.01 x 4.60 x 2.00 = 0.09 m3
= 0.01 x 6.20 x 1.00 = 0.06 m3
= 0.01 x 4.50 x 2.00 = 0.09 m3
= 0.01 x 3.50 x 2.00 = 0.07 m3
3.19 m3

5 Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II 33.00 m2

= 3.25 x 3.00 x 2.00 x 1.00 = 19.50 m2


= 2.25 x 3.00 x 2.00 x 1.00 = 13.50 m2
= 33.00 m2

Hal. 39 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
6 Pemasangan 1 m2 rangka atap genteng beton expose, kayu kelas II ( kruing ) 410.50 m2

= 11.38 x 7.00 x 2.00 x 1.00 = 159.25 m2


= 10.13 x 6.00 x 2.00 x 1.00 = 121.50 m2
= 16.88 x 1.50 x 2.00 x 1.00 = 50.63 m2
= 5.00 x 1.50 x 1.00 x (1.00) = (7.50) m2
= 14.88 x 1.50 x 2.00 x 1.00 = 44.63 m2
= 6.30 x 1.00 x 2.00 x 1.00 = 12.60 m2
= 3.50 x 4.20 x 2.00 x 1.00 = 29.40 m2
= 410.50 m2

7 Lisplang GRC Board tebal 9 mm, L = 30 cm (terpasang & pengecatan), motif kayu 141.60 m1

= 18.00 x 2.00 = 36.00 m1


= 16.50 x 2.00 = 33.00 m1
= 4.20 x 2.00 = 8.40 m1
= 1.00 x 4.00 = 4.00 m1
= 17.70 x 1.00 = 17.70 m1
= 18.70 x 1.00 = 18.70 m1
= 5.20 x 2.00 = 10.40 m1
= 6.70 x 2.00 = 13.40 m1
141.60

8 Pemasangan 1 m2 atap genteng palentong besar/super 443.50 m2

= 11.38 x 7.00 x 2.00 x 1.00 = 159.25 m2


= 10.13 x 6.00 x 2.00 x 1.00 = 121.50 m2
= 16.88 x 1.50 x 2.00 x 1.00 = 50.63 m2
= 5.00 x 1.50 x 1.00 x (1.00) = (7.50) m2
= 14.88 x 1.50 x 2.00 x 1.00 = 44.63 m2
= 6.30 x 1.00 x 2.00 x 1.00 = 12.60 m2
= 3.50 x 4.20 x 2.00 x 1.00 = 29.40 m2
= 3.25 x 3.00 x 2.00 x 1.00 = 19.50 m2
= 2.25 x 3.00 x 2.00 x 1.00 = 13.50 m2
= 443.50 m2

9 Pemasangan 1 m’ bubung genteng palentong besar 61.70 m1

= 1.50 x 1.00 = 1.50 m1


= 3.00 x 4.00 = 12.00 m1
= 8.50 x 4.00 = 34.00 m1
= 6.20 x 1.00 = 6.20 m1
= 2.00 x 4.00 = 8.00 m1
61.70

10 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III 22.50 m2

= 4.50 x 5.00 = 22.50 m2

11 Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm 22.50 m2

= 4.50 x 5.00 = 22.50 m2

12 Pemasangan 1 m2 langit-langit kalsiboard ukuran (120x240x4) mm, tebal 4 mm 410.50 m2

= 11.38 x 7.00 x 2.00 x 1.00 = 159.25 m2


= 10.13 x 6.00 x 2.00 x 1.00 = 121.50 m2
= 16.88 x 1.50 x 2.00 x 1.00 = 50.63 m2
= 5.00 x 1.50 x 1.00 x (1.00) = (7.50) m2
= 14.88 x 1.50 x 2.00 x 1.00 = 44.63 m2
= 6.30 x 1.00 x 2.00 x 1.00 = 12.60 m2
= 3.50 x 4.20 x 2.00 x 1.00 = 29.40 m2
= 410.50 m2

13 Pemasangan 1 m’ list langit-langit gypsum profil 19.00 m1

= 9.00 + 10.00 = 19.00 m1

14 Pasang Papan pembungkus kolom beton (2 x 30 )cm, kayu Jati finising politur 28.32 m2

= 7.08 x 4.00 = 28.32 m2

Hal. 40 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
15 Membuat dan memasang rangka pagar, Kayu Kruwing 0.68 m3

= 0.01 x 0.90 x 4.00 x 1.00 = 0.02 m3


= 0.01 x 1.35 x 4.00 x 1.00 = 0.03 m3
= 0.00 x 0.90 x 4.00 x 1.00 = 0.01 m3
= 0.00 x 1.00 x 4.00 x 1.00 = 0.01 m3
= 0.01 x 0.90 x 4.00 x 2.00 = 0.04 m3
= 0.01 x 1.10 x 4.00 x 2.00 = 0.05 m3
= 0.00 x 0.90 x 4.00 x 2.00 = 0.03 m3
= 0.00 x 1.00 x 4.00 x 2.00 = 0.03 m3
= 0.01 x 0.90 x 2.00 x 8.00 = 0.09 m3
= 0.01 x 2.08 x 2.00 x 8.00 = 0.20 m3
= 0.01 x 0.90 x 2.00 x 4.00 = 0.04 m3
= 0.01 x 2.45 x 2.00 x 4.00 = 0.12 m3
0.68 m3

16 Membuat dan memasang Pagar , Kayu Kruwing 27.65 m2

= 0.18 x 1.00 x 12.00 x 1.00 = 2.16 m2


= 0.18 x 1.10 x 2.00 x 1.00 = 0.40 m2
= 0.18 x 1.20 x 2.00 x 1.00 = 0.43 m2
= 0.18 x 1.30 x 2.00 x 1.00 = 0.47 m2
= 0.18 x 1.00 x 10.00 x 2.00 = 3.60 m2
= 0.18 x 1.10 x 2.00 x 2.00 = 0.79 m2
= 0.18 x 1.20 x 2.00 x 2.00 = 0.86 m2
= 0.18 x 1.30 x 2.00 x 2.00 = 0.94 m2
= 0.18 x 1.00 x 8.00 x 8.00 = 11.52 m2
= 0.18 x 1.00 x 9.00 x 4.00 = 6.48 m2
27.65 m2

VIII PEKERJAAN BESI DAN ALUMINIUM


1 Pemasangan 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm 10.00 m'

= 5.00 x 2.00 = 10.00 m'

IX PEKERJAAN KUNCI DAN KACA


1 Pemasangan 1 buah engsel pintu 12.00 m'

= 4.00 x 3.00 = 12.00 m'

2 Grendel pintu 6.00 m'

= 2.00 x 3.00 = 6.00 m'

X PEKERJAAN PENUTUP LANTAI DAN DINDING


1 Pemasangan 1m2 lantai keramik ukuran 40cm x40cm 276.82 m2

= 14.00 x 16.00 x 1.00 = 224.00 m2


= 6.40 x 3.10 x 1.00 = 19.84 m2
= 5.10 x 1.80 x 2.00 = 18.36 m2
= 10.00 x 0.18 x 1.00 = 1.80 m2
= 11.40 x 0.18 x 1.00 = 2.05 m2
= 12.60 x 0.18 x 1.00 = 2.27 m2
= 7.00 x 0.18 x 2.00 = 2.52 m2
= 7.90 x 0.18 x 2.00 = 2.84 m2
= 8.70 x 0.18 x 2.00 = 3.13 m2
= 276.82 m2

2 Pemasangan 1 m2 dinding batu tempel candi 30.15 m2

= 1.20 x 0.90 x 16.00 = 17.28 m2


= 0.90 x 0.90 x 7.00 = 5.67 m2
= 2.00 x 0.90 x 4.00 = 7.20 m2
= 30.15 m2

XI PEKERJAAN PENGECATAN
1 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) 538.81 m2

= 118.06 x 0.36 = 42.50 m2


= 332.29 x 0.32 = 106.33 m2
= 410.50 x 0.95 = 389.98 m2
538.81 m2

Hal. 41 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
2 Pelaburan 1 m2 bidang kayu dengan politur luas total 100.17 m2

99.65 x 0.32 = 31.89 m2


22.80 x 0.30 = 6.84 m2
153.61 x 0.40 = 61.44 m2
= 100.17 m2

3 Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) 658.24 m2

658.24 x 1.00 = 658.24 m2

4 Pengecatan 1 m2 plafon ( 1 lapis cat dasar, 2 lapis cat penutup) luas total 433.00 m2

433.00 x 1.00 = 433.00 m2

XII PEKERJAAN INSTALASI LISTRIK


1 Instalasi Listrik 13.00 ttk
SL 18 watt = 11.00 bh = 11.00 ttk
Pijar 40 w = - bh = - ttk
Stop kontak = 2.00 bh = 2.00 ttk
= 13.00 ttk
= 13.00 ttk

2 Saklar ganda = 6.00 bh 6.00 bh


3 Stop kontak = 2.00 bh 2.00 bh
4 MCB = 1.00 bh 1.00 bh
5 Lampu Gantung Artistik = 1.00 bh 1.00 bh
6 Lampu SL 18 Watt Phillips = 11.00 bh 11.00 bh

XIII PEKERJAAN LAIN - LAIN


1 Pasang salura U Ø 20 cm, termasuk pas. Dinding 80.00 m'

= 40.00 x 2.00 = 80.00 m'

2 Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm 4.00 bh

= 1.00 x 4.00 = 4.00 bh

3 Pasang logo keramik (ukuran 35 x 45) cm 1.00 bh

= 1.00 x 1.00 = 1.00 bh

4 Pasang Tulisan (bahan alluminium) 1.00 bh

= 1.00 x 1.00 = 1.00 bh

Hal. 42 dari 297


A.4.2.1. HARGA SATUAN PEKERJAAN BESI

A.4.2.1.1. Pemasangan 1 kg besi profil

Harga Satuan Jumlah


(Rp) Harga
No Uraian Kode Satuan Koefisien (Rp)
A TENAGA
Pekerja L.01 OH 0.06 57,400.00 3,444.00
Tukang Las L.03 OH 0.06 62,300.00 3,738.00
Konstruksi
Kepala tukang 0.006 67,700.00 406.20
L.03 OH
Mandor L.04 OH 0.003 70,300.00 210.90
JUMLAH TENAGA KERJA 7,799.100
B BAHAN
Besi Profil Kg 1.15 17,600.00 20,240.00
JUMLAH HARGA BAHAN 20,240.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 28,039.10


E Overhead & Profit (Contoh 10 %) 0.10 x D 2,803.91
F Harga Satuan Pekerjaan (D+E) 30,843.01 kg

A.4.2.1.8. Pemasangan 1 m2 pintu lipat (folding gate)

Harga Satuan Jumlah


(Rp) Harga
No Uraian Kode Satuan Koefisien (Rp)
A TENAGA
Pekerja L.01 OH 0.44 57,400.00 25,256.00
Tukang L.03 OH 0.44 62,300.00 27,412.00
Kepala tukang L.03 OH 0.044 67,700.00 2,978.80
Mandor L.04 OH 0.022 70,300.00 1,546.60
JUMLAH TENAGA KERJA 57,193.40
B BAHAN
Pintu lipat m2 1 365,000.00 365,000.00
JUMLAH HARGA BAHAN 365,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 422,193.40


E Overhead & Profit (Contoh 10 %) 0.10 x D 42,219.34
F Harga Satuan Pekerjaan (D+E) 464,412.74 m²
A.4.4.1. HARGA SATUAN PEKERJAAN PASANGAN DINDING

A. 4.4.1.20. Pemasangan 1 cm2 dinding conblock HB10 campuran 1SP :3PP

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah


(Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.3 57,400.00 17,220.00
Tukang Batu L.02 OH 0.1 62,300.00 6,230.00
Kepala Tukang L.03 OH 0.01 67,700.00 677.00
Mandor L.04 OH 0.015 70,300.00 1,054.50
JUMLAH TENAGA KERJA 25,181.50
B BAHAN
HB-10 m3 12.5 3,400.00 42,500.00
Semen Portland Kg 15.16 1,350.00 20,466.00
Pasir Pasang m3 0.0364 157,000.00 5,714.80
Besi angker dia 8 Kg 0.28 11,000.00 -
JUMLAH HARGA BAHAN 68,680.80
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 93,862.30


E Overhead & Profit (Contoh 10 %) 0.10 x D 9,386.23
F Harga Satuan Pekerjaan (D+E) 103,248.53 m²
A. 4.4.1.21. Pemasangan 1 cm2 dinding conblock HB10 campuran 1SP :4PP

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah


(Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.3 57,400.00 17,220.00
Tukang Batu L.02 OH 0.1 62,300.00 6,230.00
Kepala Tukang L.03 OH 0.01 67,700.00 677.00
Mandor L.04 OH 0.015 70,300.00 1,054.50
JUMLAH TENAGA KERJA 25,181.50
B BAHAN
HB-10 m3 12.5 3,400.00 42,500.00
Semen Portland Kg 12.13 1,350.00 16,375.50
Pasir Pasang m3 0.0388 157,000.00 6,091.60
Besi angker dia 8 Kg 0.28 11,000.00 -
JUMLAH HARGA BAHAN 64,967.10
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 90,148.60


E Overhead & Profit (Contoh 10 %) 0.10 x D 9,014.86
F Harga Satuan Pekerjaan (D+E) 99,163.46 m²
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO
KECAMATAN KARANGGAYAM
TAHUN ANGGARAN 2019

PENYEDIA JASA :
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

LAPORAN BULANAN

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

DAFTAR PERHITUNGAN MUTHUAL CHECK AKHIR


( MC.100 )

PEKERJAAN :
PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO
KECAMATAN KARANGGAYAM
TAHUN ANGGARAN 2019

PENYEDIA JASA :
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

DAFTAR PERHITUNGAN MUTHUAL CHECK


AKHIR ( MC.100 )

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN KARANGGAYAM
TAHUN ANGGARAN 2019

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

DAFTAR PERHITUNGAN MUTHUAL CHECK AKHIR ( MC.100 )

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : III ( Tiga )
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

DAFTAR PERHITUNGAN MUTHUAL CHECK AKHIR ( MC.100 )

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : IV ( Empat )
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

DAFTAR PERHITUNGAN MUTHUAL CHECK AKHIR ( MC.100 )

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : V ( Lima )
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

DAFTAR PERHITUNGAN MUTHUAL CHECK AKHIR ( MC.100 )

VI ( Enam )

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : ###
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
PEMERINTAH KABUPATEN KEBUMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan H.M. Sarbini No37 Telp ( 0287 ) 381128 Fax. (0287 ) 382821 Kebumen

DAFTAR PERHITUNGAN MUTHUAL CHECK AKHIR ( MC.100 )

PEKERJAAN :
PEMBANGUNAN GEDUNG KANTOR
KECAMATAN SRUWENG
TAHUN ANGGARAN 2017

0 : VII ( Tujuh )
0 : ###
0 : #REF! %
0 : #REF! %
0 : #REF! %
0 : #REF! %

PENYEDIA JASA :
0
0
BACK UP PERHITUNGAN

KEGIATAN : Perencanaan Pengembangan Infrastruktur


PEKERJAAN : Penyusunan Dokumen Perencanaan Teknik pengembangan Infrastruktur Bidang Cipta Karya ( Paket 25 )
Pembangunan Kantor Kecamatan Sruweng (Lanjutan)
LOKASI : Kabupaten Kebumen
TAHUN ANGGARAN : 2017

TOTAL
NO PERHITUNGAN VOLUME
VOLUME
F. RUMAH DINAS
I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan bauwplank 23.00 ls
= 23.00 X 1.00 = 23.00 ls

23.00 ls

II PEKERJAAN TANAH
1 Penggalian 1 m3 tanah biasa sedalam 1 m
Panjang total pondasi batu kali 70.40 m3
arah H = 38.00 + 2.00 + 6.00 + + = 46.00 m'

46.00 m'

arah V = 13.50 + 13.50 + 9.00 + 12.50 + = 48.50 m'

48.50 m'

Panjang Tot = 46.00 + 48.50 = 94.50 m'

Vol. Pbk = 0.80 x 0.90 x 94.50 = 68.04 m3

Rollax = 0.20 x 0.20 x 59.00 = 2.36 m3

2.36 m3

2 Pengurugan kembali 1 m3 galian tanah


= 0.30 x 68.04 = 20.41 m3 20.41 m3
20.41 m3
3 Pengurugan 1 m3 dengan pasir urug
tebal pasir
Lantai = 12.00 x 9.50 x 0.05 = 5.70 m3
= 3.00 x 2.00 x 0.05 = 0.30 m3
Pondasi = 0.80 x 94.50 x 0.10 = 7.56 m3
Jumlah Total = 13.56 m3 13.56 m3
4 Pengurugan 1 m3 cadas padat
= 12.00 x 9.50 x 0.40 = 45.60 m3
= 3.00 x 2.00 x 0.40 = 2.40 m3

48.00 m3 48.00 m3
III PEKERJAAN PONDASI
1 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP
Gedung
Pbk =( 0.30 + 0.80 ) x 2.05 x 94.50 m' = 106.55 m3
2
Jumlah total
= 106.55 = 106.55 m3 106.55 m3

2 Pemasangan 1 m3 batu kosong (anstamping)


Gedung
Pbk = 0.80 x 0.20 x 94.50 m' = 15.12 m3

Jumlah total
= 15.12 = 15.12 m3 15.12 m3

IV PEKERJAAN DINDING
1 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP

Tasram = 59.00 x 0.20 x 1.00 = 11.80 m2 11.80 m2

11.80 m2

2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 3PP

Dinding = 86.00 x 0.50 x 1.00 = 43.00 m2 40.11 m2


= 3.35 x 0.80 x 1.00 = 2.68 m2

45.68 m2
Luas Perlubangan
P1 = 1.36 x 0.50 x (1.00) = (0.68) m2
P2 = 0.94 x 0.50 x (6.00) = (2.82) m2
P3 = 0.80 x 0.50 x (1.00) = (0.40) m2
Folding = 3.35 x 0.50 x (1.00) = (1.68) m2

(5.58) m2
Luas Netto = 45.68 + (5.58) = 40.11 m2

Hal. 81 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
3 Pemasangan 1m2 dinding bata merah (5x11x22)cm
tebal ½ batu campuran 1SP : 6PP
Dinding lantai = 80.50 x 3.80 x 1.00 = 305.90 m2
= 5.50 x 1.00 x 1.00 = 5.50 m2
= 0.35 x 2.70 x 4.00 = 3.78 m2

315.18 m2

Luas Perlubangan jml


P1 = 1.36 x 2.16 x (1.00) = (2.94) m2
P2 = 0.94 x 2.16 x (6.00) = (12.18) m2
P3 = 0.80 x 2.16 x (1.00) = (1.73) m2
Folding = 3.35 x 2.52 x (1.00) = (8.44) m2
J1 = 0.50 x 1.88 x (2.00) = (1.88) m2
J2 = 0.50 x 2.32 x (8.00) = (9.28) m2
B1 = 0.50 x 1.08 x (6.00) = (3.24) m2

= (39.69) m2
Perlubangan
Luas Netto = 315.18 + (39.69) = 275.49 m2 = 275.49 m2
= 275.49 m2

Luas total = 275.49 = 275.49 m2 275.49 m2

V PEKERJAAN PLESTERAN
1 Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm.
= 2.00 x 315.60 = 631.20 m2
= 20.93 x (1.00) = (20.93) m2

Jumlah Total = 610.28 m2 610.28 m2

2 Pemasangan 1 m2 acian.
= 610.28 x 1.00 = 610.28 m2

Jumlah = 610.28 m2 610.28 m2

VI PEKERJAAN KAYU
1 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas II ( kruing )
= 0.01 x 11.65 x 2.00 = 0.22 m3 1.52 m3
= 0.01 x 5.15 x 2.00 = 0.10 m3
= 0.01 x 10.80 x 2.00 = 0.21 m3
= 0.01 x 9.00 x 2.00 = 0.17 m3
= 0.01 x 22.00 x 2.00 = 0.32 m3

= 0.01 x 5.50 x 2.00 = 0.11 m3


= 0.01 x 4.35 x 2.00 = 0.08 m3
= 0.01 x 5.40 x 2.00 = 0.10 m3
= 0.01 x 3.50 x 2.00 = 0.07 m3
= 0.01 x 2.80 x 1.00 = 0.03 m3
= 0.01 x 8.00 x 2.00 = 0.12 m3

1.52 m3
2 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruing )
= 0.01 x 21.50 x 2.00 = 0.41 m3 1.84 m3
= 0.01 x 6.00 x 1.00 = 0.06 m3
= 0.01 x 16.90 x 2.00 = 0.32 m3
= 0.01 x 12.00 x 2.00 = 0.23 m3
= 0.01 x 7.90 x 2.00 = 0.15 m3
= 0.01 x 8.30 x 4.00 = 0.32 m3
= 0.01 x 3.00 x 4.00 = 0.12 m3
= 0.01 x 3.75 x 4.00 = 0.14 m3
= 0.01 x 4.00 x 1.00 = 0.04 m3
= 0.01 x 6.00 x 1.00 = 0.04 m3

1.84 m3

3 Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II ( kruing )


208.59 m2
= 8.40 x 6.90 x 2.00 x 1.00 = 115.92 m2
= 5.90 x 6.90 x 2.00 x 1.00 = 81.42 m2
= 1.50 x 3.75 x 2.00 x 1.00 = 11.25 m2

= 208.59 m2

4 Lisplang GRC Board tebal 9 mm, L = 30 cm (terpasang & pengecatan), motif kayu
= 11.80 x 2.00 = 23.60 m1 55.20 m1
= 15.80 x 2.00 = 31.60 m1

55.20

5 Pemasangan 1 m2 atap genteng palentong kecil


208.59 m2
= 8.40 x 6.90 x 2.00 x 1.00 = 115.92 m2
= 5.90 x 6.90 x 2.00 x 1.00 = 81.42 m2
= 1.50 x 3.75 x 2.00 x 1.00 = 11.25 m2

= 208.59 m2

Hal. 82 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
6 Pemasangan 1 m’ bubung genteng palentong
= 4.00 x 1.00 = 4.00 m1 52.20 m1
= 8.30 x 4.00 = 33.20 m1
= 3.75 x 4.00 = 15.00 m1

52.20

7 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III
= 9.50 x 12.00 = 114.00 m2 150.31 m2
= 2.00 x 3.00 = 6.00 m2
= 29.46 x 0.98 = 28.87 m2
= 3.00 x 0.48 = 1.44 m2

150.31

8 Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm


= 9.50 x 12.00 = 114.00 m2 117.60 m2
= 1.20 x 3.00 = 3.60 m2

117.60

9 Pemasangan 1 m’ list langit-langit gypsum profil


= 9.00 x 1.00 = 9.00 m1 223.00 m1
= 15.00 x 1.00 = 15.00 m1
= 14.00 x 1.00 = 14.00 m1
= 18.00 x 1.00 = 18.00 m1
= 13.00 x 1.00 = 13.00 m1
= 7.00 x 1.00 = 7.00 m1
= 14.00 x 1.00 = 14.00 m1
= 9.00 x 1.00 = 9.00 m1
= 13.00 x 1.00 = 13.00 m1
= 19.00 x 1.00 = 19.00 m1
= 46.00 x 2.00 = 92.00 m1

223.00

10 Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I atau II


P1 = 2.65 x 1.00 = 2.65 m2 14.70 m2
P2 = 1.76 x 6.00 = 10.58 m2
P3 = 1.47 x 1.00 = 1.47 m2

14.70

11 Pemasangan 1 m2 langit-langit kalsiboard ukuran (120x240x4) mm, tebal 4 mm


= 29.46 x 0.98 = 28.87 m2 30.31 m2
= 3.00 x 0.48 = 1.44 m2

30.31

12 Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III
P1 = 0.04 x 1.00 = 0.04 m3 0.89 m3
P2 = 0.04 x 6.00 = 0.24 m3
P3 = 0.04 x 1.00 = 0.04 m3
J1 = 0.04 x 2.00 = 0.07 m3
J2 = 0.04 x 8.00 = 0.35 m3
B1 = 0.03 x 6.00 = 0.15 m3

0.89

13 Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I atau II
J1 = 0.35 x 2.00 = 0.70 m2 3.96 m2
J2 = 0.41 x 8.00 = 3.26 m2
B1 = - x 6.00 = - m2

3.96

VII PEKERJAAN BETON


1 Lantai Kerja
Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Lantai = 12.00 x 9.50 x 1.00 x 0.05 = 5.70 m3
= 3.00 x 2.00 x 1.00 x 0.05 = 0.30 m3

6.00 m3 6.00 m3

2 Rabat Beton
Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Tritisan = 24.00 x 2.00 x 1.20 x 0.10 = 5.76 m3
= 3.50 x 2.00 x 1.00 x 0.10 = 0.70 m3

6.46 m3 6.46 m3

3 Sloof 15/25
a. Begisting = 0.25 x 2 x 97.50 = 48.75 m2 x 0.50 24.38 m2
b. Pembesian
-Besi 5 D 13 = 5.00 x 1.04 x 97.50 = 507.00 kg
-Begel Ø 8 - 150 = 650.00 x 0.393 x 0.70 = 178.82 kg
685.82 kg 685.82 kg

c. Beton bertulang = 0.15 x 0.25 x 97.50 = 3.66 m3 3.66 m3

Hal. 83 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
4 Kolom 15/25
a. Begisting = 0.2 x 4 x 4.00 = 3.20 m2 x 0.50 25.60 m2
= 3.20 x 16.00 = 51.20 m2
b. Pembesian
-Besi 6 D 13 = 6.00 x 4.00 + 0.30 = 25.80 m1
= 25.80 x 16.00 x 1.04 = 429.31 kg
-Begel Ø 8 - 150 = 427.00 x 0.39 x 0.70 = 117.47 kg
546.78 kg 546.78 kg

c. Beton bertulang = 0.15 x 0.25 x 64.00 = 2.40 m3 2.40 m3

5 Kolom 11/11
= 4 x 15 x 1.00 = 60.00 m1 60.00 m3

60.00

6 Balok 15/30
a. Begisting
= 0.375 x 2 x 5.50 = 4.13 m2 x 0.50 2.06 m2

b. Pembesian
-Besi 6 D 13 = 6.00 x 1.04 x 5.50 = 34.32 kg
-Begel Ø 6 - 150 = 37.00 x 0.22 x 0.80 = 6.51 kg
40.83 kg 40.83 kg

c. Beton bertulang = 0.15 x 0.3 x 5.50 = 0.25 m3 0.25 m3

9 Balok 15/20
a. Begisting
= 0.2 x 2 x 97.50 = 39.00 m2 x 0.50 19.50 m2

b. Pembesian
-Besi 5 D 13 = 5.00 x 1.04 x 97.50 = 507.00 kg
-Begel Ø 8 - 150 = 650.00 x 0.393 x 0.60 = 153.27 kg
660.27 kg 660.27 kg

c. Beton bertulang = 0.15 x 0.2 x 97.50 = 2.93 m3 2.93 m3

10 Balok Latai 10/15

= 1 x 1 x 32.50 = 32.50 m2 x 1.00 32.50 m2

11 Plat Atap
a. Begisting = 0.50 x 3.00 x 1.00 = 1.50 m2 x 0.50 0.75 m2

1.50 m2
b. Pembesian
-Besi Ø 10 - 150 = 0.60 x 0.62 x 40.00 = 14.88 kg
-Besi Ø 10 - 150 = 3.10 x 0.62 x 6.00 = 11.53 kg

26.41 kg 26.41 kg

c. Beton bertulang = 0.50 x 3 x 0.12 x 1.00 = 0.18 m3 0.18 m3

0.18

12 Shading
a. Begisting = 0.60 x 13.00 x 1.00 = 7.80 m2 x 0.50 3.90 m2

7.80 m2
b. Pembesian
-Besi Ø 10 - 150 = 0.80 x 0.62 x 87.00 = 43.15 kg
-Besi Ø 10 - 150 = 13.00 x 0.62 x 4.00 = 32.24 kg

75.39 kg 75.39 kg

c. Beton bertulang = 0.60 x 13 x 0.1 x 1.00 = 0.78 m3 0.78 m3

0.78

13 Meja Dapur
a. Begisting = 0.60 x 3.00 x 1.00 = 1.80 m2 x 0.50 0.90 m2

1.80 m2
b. Pembesian
-Besi Ø 10 - 150 = 0.80 x 0.62 x 20.00 = 9.92 kg
-Besi Ø 10 - 150 = 3.00 x 0.62 x 4.00 = 7.44 kg

17.36 kg 17.36 kg

c. Beton bertulang = 0.60 x 3 x 0.1 x 1.00 = 0.18 m3 0.18 m3

0.18

Hal. 84 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
XI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Pemasangan 1m2 lantai keramik ukuran 40cm x40cm
= 12.00 x 9.50 x 1.00 = 114.00 m2
= 3.00 x 2.00 x 1.00 = 6.00 m2
= 2.00 x (1.00) x 1.50 = (3.00) m2

= 117.00 m2 117.00 m2
2 Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm
= 2.00 x 1.50 x 1.00 = 3.00 m2
= 0.60 x 3.00 x 1.00 = 1.80 m2

= 4.80 m2 4.80 m2

3 Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm


= 5.70 x 1.00 x 1.00 = 5.70 m1
= 4.20 x 1.00 x 1.00 = 4.20 m1

= 9.90 m1 9.90 m1

4 Pemasangan 1 m2 dinding keramik 20cm x 20cm


= 5.70 x 1.50 x 1.00 = 8.55 m2
= 4.20 x 1.50 x 1.00 = 6.30 m2

= 14.85 m2 14.85 m2
5 Pemasangan 1 m2 dinding batu tempel susun sirih
= 2.70 x 0.35 x 4.00 = 3.78 m2
= 1.00 x 1.80 x 1.00 = 1.80 m2

= 5.58 m2 5.58 m2
XII PEKERJAAN KUNCI DAN KACA
1 Pemasangan 1 buah engsel pintu
P1 = 6.00 x 1.00 = 6.00 bh
P2 = 3.00 x 6.00 = 18.00 bh
P3 = 3.00 x 1.00 = 3.00 bh

27.00 bh 27.00 bh

2 Pemasangan 1 buah engsel jendela kupu-kupu


J1 = 2.00 x 2.00 = 4.00 bh
J2 = 4.00 x 8.00 = 32.00 bh

36.00 bh 36.00 bh

3 Pemasangan 1 buah kait angin


J1 = 2.00 x 2.00 = 4.00 bh
J2 = 4.00 x 8.00 = 32.00 bh

36.00 bh 36.00 bh

4 Pemasangan 1 buah kunci slot


P1 = 1.00 x 1.00 = 1.00 bh
P2 = 1.00 x 6.00 = 6.00 bh
P3 = 1.00 x 1.00 = 8.00 bh

15.00 bh 15.00 bh

5 Pemasangan 1 m2 kaca tebal 5 mm


J1 = 1.50 x 2.00 = 3.00 m2
J2 = 0.99 x 8.00 = 7.96 m2
B1 = 0.39 x 6.00 = 2.37 m2

13.33 m2 13.33 m2

2 Grendel pintu
J1 = 1.00 x 2.00 = 2.00 m'
J2 = 2.00 x 8.00 = 16.00 m'
P1 = 4.00 x 1.00 = 4.00 m'
P2 = 1.00 x 6.00 = 6.00 m'
P3 = 1.00 x 1.00 = 1.00 m'

29.00 m' 29.00 m'

XIII PEKERJAAN BESI DAN ALUMINIUM


1 Pintu besi Folding Gate (tepasang)
= 3.35 x 2.52 = 8.44 m2

8.44 m2 8.44 m2

XIV PEKERJAAN PENGECATAN


1 Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
610.28 x 1.00 = 610.28 m2

610.28 m2 610.28 m2
2 Pengecatan 1 m2 plafon ( 1 lapis cat dasar, 2 lapis cat penutup) luas total
147.91 x 1.00 = 147.91 m2

= 147.91 m2 147.91 m2

Hal. 85 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
XIV PEKERJAAN INSTALASI LISTRIK
1 Instalasi Listrik
SL 18 watt = 17.00 bh = 17.00 ttk
Pijar 5 w = 5.00 bh = 5.00 ttk
Stop kontak = 8.00 bh = 8.00 ttk
= 30.00 ttk
= 30.00 ttk 30.00 ttk

2 Saklar ganda = 1.00 bh 1.00 bh


2 Saklar tunggal = 10.00 bh 10.00 bh
3 Stop kontak = 8.00 bh 8.00 bh
5 Lampu pijar 5 W philips = 5.00 bh 5.00 bh
6 Lampu SL 18 Watt Phillips = 17.00 bh 17.00 bh

XV PEKERJAAN LAIN - LAIN


1 Pasang salura U Ø 20 cm, termasuk pas. Dinding
= 45.50 x 1.00 = 45.50 m'

45.50 m' 45.50 m'

Hal. 86 dari 297


BACK UP PERHITUNGAN

KEGIATAN : Perencanaan Pengembangan Infrastruktur


PEKERJAAN : Penyusunan Dokumen Perencanaan Teknik pengembangan Infrastruktur Bidang Cipta Karya ( Paket 25 )
Pembangunan Kantor Kecamatan Sruweng (Lanjutan)
LOKASI : Kabupaten Kebumen
TAHUN ANGGARAN : 2017

TOTAL
NO PERHITUNGAN VOLUME
VOLUME
D. GEDUNG SERBA GUNA
I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan bauwplank 28.00 ls
= 28.00 X 1.00 = 28.00 ls

28.00 ls

II PEKERJAAN TANAH
1 Penggalian 1 m3 tanah biasa sedalam 1 m
Panjang total pondasi batu kali 58.60 m3
arah H = 6.00 + 17.00 + 32.00 + + = 55.00 m'

55.00 m'

arah V = 6.00 + 1.50 + 16.00 + + = 23.50 m'

23.50 m'

Panjang Tot = 55.00 + 23.50 = 78.50 m'

Vol. Pbk = 0.80 x 0.90 x 78.50 = 56.52 m3

Rollax = 0.20 x 0.20 x 52.00 = 2.08 m3

2.08 m3

2 Pengurugan kembali 1 m3 galian tanah


= 0.30 x 56.52 = 16.96 m3 16.96 m3
16.96 m3
3 Pengurugan 1 m3 dengan pasir urug
tebal pasir
Lantai = 16.00 x 8.00 x 0.05 = 6.40 m3
= 3.00 x 3.00 x 0.05 = 0.45 m3
Pondasi = 0.80 x 78.50 x 0.10 = 6.28 m3
Jumlah Total = 13.13 m3 13.13 m3
4 Pengurugan 1 m3 cadas padat
= 16.00 x 8.00 x 0.40 = 51.20 m3
= 3.00 x 3.00 x 0.40 = 3.60 m3

54.80 m3 54.80 m3
III PEKERJAAN PONDASI
1 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP
Gedung
Pbk =( 0.30 + 0.80 ) x 2.05 x 78.50 m' = 88.51 m3
2
Jumlah total
= 88.51 = 88.51 m3 88.51 m3

2 Pemasangan 1 m3 batu kosong (anstamping)


Gedung
Pbk = 0.80 x 0.20 x 78.50 m' = 12.56 m3

Jumlah total
= 12.56 = 12.56 m3 12.56 m3

IV PEKERJAAN DINDING
1 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP

Tasram = 52.00 x 0.20 x 1.00 = 10.40 m2 16.40 m2


= 0.80 x 0.20 x 15.00 = 2.40 m2
= 0.30 x 2.40 x 5.00 = 3.60 m2

16.40 m2

2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 3PP

Dinding = 72.50 x 0.50 x 1.00 = 36.25 m2 40.30 m2


Hal. 87 dari 297
TOTAL
NO PERHITUNGAN VOLUME
VOLUME
= 2.20 x 0.60 x 5.00 = 6.60 m2

42.85 m2

Hal. 88 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
Luas Perlubangan
P1 = 0.90 x 0.50 x (3.00) = (1.35) m2
P2 = 0.80 x 0.50 x (3.00) = (1.20) m2

(2.55) m2
Luas Netto = 42.85 + (2.55) = 40.30 m2

3 Pemasangan 1m2 dinding bata merah (5x11x22)cm


tebal ½ batu campuran 1SP : 6PP
Dinding lantai = 62.00 x 3.80 x 1.00 = 235.60 m2
= 10.50 x 3.30 x 1.00 = 34.65 m2

270.25 m2

Luas Perlubangan jml


P1 = 0.90 x 2.77 x (3.00) = (7.48) m2
P2 = 0.80 x 2.77 x (3.00) = (6.65) m2
J1 = 1.36 x 1.86 x (12.00) = (30.36) m2
B1 = 0.67 x 0.70 x (3.00) = (1.41) m2

= (45.89) m2
Perlubangan
Luas Netto = 270.25 + (45.89) = 224.36 m2 = 224.36 m2
= 224.36 m2

Luas total = 224.36 = 224.36 m2 224.36 m2

V PEKERJAAN PLESTERAN
1 Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm.
= 2.00 x 264.66 = 529.32 m2
= 0.80 x 2.40 x 5.00 = 9.60 m2
= 14.57 x (1.00) = (14.57) m2

Jumlah Total = 524.35 m2 524.35 m2

2 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP


= 0.10 x 0.55 x 5.00 = 0.28 m2
= 0.60 x 0.55 x 5.00 = 1.65 m2
= 0.30 x 0.70 x 5.00 = 1.05 m2
= 0.25 x 1.20 x 5.00 = 1.50 m2

Jumlah = 4.48 m2 4.48 m2

3 Pemasangan 1 m2 acian.
= 524.35 x 1.00 = 524.35 m2
= 48.00 x 0.10 = 4.80 m2

Jumlah = 529.15 m2 529.15 m2

4 Sponengan
= 0.80 x 12.00 x 5.00 = 48.00 m1

Jumlah = 48.00 m1 48.00 m1

VI PEKERJAAN KAYU
1 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas II ( kruing )
= 0.01 x 7.15 x 5.00 = 0.34 m3 1.45 m3
= 0.01 x 1.80 x 5.00 = 0.09 m3
= 0.01 x 6.80 x 5.00 = 0.33 m3
= 0.01 x 2.90 x 5.00 = 0.14 m3
= 0.01 x 8.00 x 5.00 = 0.29 m3

= 0.01 x 4.00 x 2.00 = 0.08 m3


= 0.01 x 1.80 x 2.00 = 0.03 m3
= 0.01 x 3.40 x 2.00 = 0.07 m3
= 0.01 x 1.45 x 2.00 = 0.03 m3
= 0.01 x 4.00 x 2.00 = 0.06 m3

1.45 m3
2 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruing )
Hal. 89 dari 297
TOTAL
NO PERHITUNGAN VOLUME
VOLUME
= 0.01 x 22.00 x 2.00 = 0.42 m3 1.47 m3
= 0.01 x 16.00 x 1.00 = 0.15 m3

Hal. 90 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
= 0.01 x 16.00 x 2.00 = 0.31 m3
= 0.01 x 6.00 x 4.00 = 0.23 m3
= 0.01 x 1.50 x 4.00 = 0.06 m3
= 0.01 x 10.00 x 1.00 = 0.10 m3
= 0.01 x 7.00 x 4.00 = 0.20 m3

1.47 m3

3 Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II ( kruing )


240.50 m2
= 14.25 x 5.00 x 2.00 x 1.00 = 142.50 m2
= 4.25 x 5.00 x 2.00 x 1.00 = 42.50 m2
= 18.50 x 3.00 x 1.00 x 1.00 = 55.50 m2

= 240.50 m2

4 Lisplang GRC Board tebal 9 mm, L = 30 cm (terpasang & pengecatan), motif kayu
= 18.50 x 2.00 = 37.00 m1 61.00 m1
= 12.00 x 2.00 = 24.00 m1

61.00

5 Pemasangan 1 m2 atap genteng palentong kecil


240.50 m2
= 14.25 x 5.00 x 2.00 x 1.00 = 142.50 m2
= 4.25 x 5.00 x 2.00 x 1.00 = 42.50 m2
= 18.50 x 3.00 x 1.00 x 1.00 = 55.50 m2

= 240.50 m2

6 Pemasangan 1 m’ bubung genteng palentong


= 10.00 x 1.00 = 10.00 m1 34.00 m1
= 6.00 x 4.00 = 24.00 m1

34.00

7 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III
= 6.00 x 16.00 = 96.00 m2 186.28 m2
= 3.00 x 17.60 = 52.80 m2
= 35.60 x 0.80 = 28.48 m2
= 3.00 x 3.00 = 9.00 m2

186.28

8 Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm


= 6.00 x 16.00 = 96.00 m2 143.72 m2
= 2.20 x 17.60 = 38.72 m2
= 3.00 x 3.00 = 9.00 m2

143.72

9 Pemasangan 1 m’ list langit-langit gypsum profil


= 12.00 x 4.00 = 48.00 m1 227.80 m1
= 20.00 x 1.00 = 20.00 m1
= 36.00 x 1.00 = 36.00 m1
= 9.00 x 1.00 = 9.00 m1
= 5.40 x 2.00 = 10.80 m1
= 52.00 x 2.00 = 104.00 m1

227.80

10 Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I


P1 = 1.68 x 3.00 = 5.04 m2 9.45 m2
P2 = 1.47 x 3.00 = 4.41 m2

9.45

11 Pemasangan 1 m2 langit-langit kalsiboard ukuran (120x240x4) mm, tebal 4 mm


= 0.80 x 17.60 = 14.08 m2 42.56 m2
= 35.60 x 0.80 = 28.48 m2

42.56

Hal. 91 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
VII PEKERJAAN BETON
1 Lantai Kerja
Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Lantai = 8.80 x 16.00 x 1.00 x 0.05 = 7.04 m3
= 3.00 x 3.00 x 1.00 x 0.05 = 0.45 m3

7.49 m3 7.49 m3

2 Rabat Beton
Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Tritisan = 17.60 x 2.00 x 0.80 x 0.10 = 2.82 m3
= 8.00 x 2.00 x 0.80 x 0.10 = 1.28 m3

4.10 m3 4.10 m3

3 Sloof 15/25
a. Begisting = 0.25 x 2 x 78.50 = 39.25 m2 x 0.50 19.63 m2
b. Pembesian
-Besi 5 D 13 = 5.00 x 1.04 x 78.50 = 408.20 kg
-Begel Ø 8 - 150 = 523.00 x 0.393 x 0.70 = 143.88 kg
552.08 kg 552.08 kg

c. Beton bertulang = 0.15 x 0.25 x 78.50 = 2.94 m3 2.94 m3

4 Kolom 20/20
a. Begisting = 0.2 x 4 x 3.00 = 2.40 m2 x 0.50 6.00 m2
= 2.40 x 5.00 = 12.00 m2
b. Pembesian
-Besi 4 Ø 10 = 4.00 x 3.00 + 0.30 = 13.20 m1
= 13.20 x 5.00 x 0.62 = 40.92 kg
-Begel Ø 6 - 150 = 100.00 x 0.22 x 0.70 = 15.40 kg
56.32 kg 56.32 kg

c. Beton bertulang = 0.2 x 0.2 x 15.00 = 0.60 m3 0.60 m3

5 Kolom 11/11
= 4 x 22 x 1.00 = 88.00 m1 106.00 m3
= 3 x 6 x 1.00 = 18.00 m1

106.00

6 Balok 15/30
a. Begisting
= 0.375 x 2 x 16.00 = 12.00 m2 x 0.50 6.00 m2

b. Pembesian
-Besi 6 D 13 = 6.00 x 1.04 x 16.00 = 99.84 kg
-Begel Ø 6 - 150 = 107.00 x 0.22 x 0.80 = 18.83 kg
118.67 kg 118.67 kg

c. Beton bertulang = 0.15 x 0.3 x 16.00 = 0.72 m3 0.72 m3

9 Balok 15/20
a. Begisting
= 0.2 x 2 x 66.50 = 26.60 m2 x 0.50 13.30 m2

b. Pembesian
-Besi 5 D 13 = 5.00 x 1.04 x 66.50 = 345.80 kg
-Begel Ø 8 - 150 = 443.00 x 0.393 x 0.60 = 104.46 kg
450.26 kg 450.26 kg

c. Beton bertulang = 0.15 x 0.2 x 66.50 = 2.00 m3 2.00 m3

10 Balok Latai 10/15

= 1 x 1 x 36.50 = 36.50 m2 x 1.00 36.50 m2

11 Plat Atap
a. Begisting = 4.00 x 3.50 x 1.00 = 14.00 m2 x 0.50 7.00 m2

14.00 m2
b. Pembesian
-Besi Ø 10 - 150 = 4.10 x 0.62 x 46.00 = 116.93 kg
Hal. 92 dari 297
TOTAL
NO PERHITUNGAN VOLUME
VOLUME
-Besi Ø 10 - 150 = 3.60 x 0.62 x 54.00 = 120.53 kg

Hal. 93 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME

237.46 kg 237.46 kg

c. Beton bertulang = 4.00 x 3.5 x 0.1 x 1.00 = 1.40 m3 1.40 m3

1.40

12 Shading
a. Begisting = 0.60 x 11.70 x 1.00 = 7.02 m2 x 0.50 3.51 m2

7.02 m2
b. Pembesian
-Besi Ø 10 - 150 = 0.80 x 0.62 x 78.00 = 38.69 kg
-Besi Ø 10 - 150 = 11.70 x 0.62 x 4.00 = 29.02 kg

67.70 kg 67.70 kg

c. Beton bertulang = 0.60 x 11.7 x 0.12 x 1.00 = 0.84 m3 0.84 m3

0.84

XI PEKERJAAN PENUTUP LANTAI DAN DINDING


1 Pemasangan 1m2 lantai keramik ukuran 40cm x40cm
= 8.80 x 16.00 x 1.00 = 140.80 m2

= 140.80 m2 140.80 m2
2 Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm
= 3.00 x 3.00 x 1.00 = 9.00 m2

= 9.00 m2 9.00 m2

3 Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm


= 4.70 x 1.00 x 2.00 = 9.40 m1

= 9.40 m1 9.40 m1

4 Pemasangan 1 m2 dinding keramik 20cm x 20cm


= 4.70 x 1.50 x 2.00 = 14.10 m2

= 14.10 m2 14.10 m2

XII PEKERJAAN KUNCI DAN KACA


1 Pemasangan 1 buah engsel pintu
P1 = 3.00 x 3.00 = 9.00 m'
P2 = 3.00 x 3.00 = 9.00 m'

18.00 m' 18.00 m'

2 Pemasangan 1 buah engsel jendela kupu-kupu


P1 = 2.00 x 3.00 = 6.00 bh
P2 = 2.00 x 3.00 = 6.00 bh
J1 = 8.00 x 12.00 = 96.00 bh
B1 = 2.00 x 3.00 = 6.00 bh

114.00 bh 114.00 bh

3 Pemasangan 1 buah kait angin


P1 = 2.00 x 3.00 = 6.00 bh
P2 = 2.00 x 3.00 = 6.00 bh
J1 = 8.00 x 12.00 = 96.00 bh
B1 = 2.00 x 3.00 = 6.00 bh

114.00 bh 114.00 bh

4 Pemasangan 1 buah kunci slot


P1 = 1.00 x 3.00 = 3.00 bh
P2 = 1.00 x 3.00 = 3.00 bh

6.00 bh 6.00 bh

5 Pemasangan 1 m2 kaca tebal 5 mm


P1 = 1.09 x 3.00 = 3.27 m2
P2 = 0.99 x 3.00 = 2.97 m2
J1 = 2.76 x 12.00 = 33.11 m2
B1 = 0.90 x 3.00 = 2.70 m2

Hal. 94 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
42.05 m2 42.05 m2

Hal. 95 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME

2 Grendel pintu
P1 = 2.00 x 3.00 = 6.00 m'
P2 = 2.00 x 3.00 = 6.00 m'
J1 = 4.00 x 12.00 = 48.00 m'
B1 = 1.00 x 3.00 = 3.00 m'

63.00 m' 63.00 m'

XIII PEKERJAAN BESI DAN ALUMINIUM


1 Pemasangan 1 m kusen pintu alluminium
P1 = 7.32 x 3.00 = 21.96 m'
P2 = 7.10 x 3.00 = 21.30 m'
J1 = 9.66 x 12.00 = 115.92 m'
B1 = 2.74 x 3.00 = 8.22 m'

167.40 m' 167.40 m'

2 Pemasangan 1 m2 jendela kaca rangka alluminium


P1 = 0.47 x 3.00 = 1.41 m2
P2 = 0.41 x 3.00 = 1.22 m2
J1 = 2.11 x 12.00 = 25.33 m2
B1 = 0.35 x 3.00 = 1.06 m2

29.02 m2 29.02 m2

XIV PEKERJAAN PENGECATAN


1 Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
529.15 x 1.00 = 529.15 m2

529.15 m2 529.15 m2
2 Pengecatan 1 m2 plafon ( 1 lapis cat dasar, 2 lapis cat penutup) luas total
186.28 x 1.00 = 186.28 m2

= 186.28 m2 186.28 m2

XIV PEKERJAAN INSTALASI LISTRIK


1 Instalasi Listrik
SL 18 watt = 16.00 bh = 16.00 ttk
Pijar 5 w = 6.00 bh = 6.00 ttk
Stop kontak = 6.00 bh = 6.00 ttk
= 28.00 ttk
= 28.00 ttk 28.00 ttk

2 Saklar ganda = 2.00 bh 2.00 bh


2 Saklar tunggal = 6.00 bh 6.00 bh
3 Stop kontak = 6.00 bh 6.00 bh
5 Lampu pijar 5 W philips = 6.00 bh 6.00 bh
6 Lampu SL 18 Watt Phillips = 16.00 bh 16.00 bh

XV PEKERJAAN LAIN - LAIN


1 Pasang salura U Ø 20 cm, termasuk pas. Dinding
= 30.00 x 2.00 = 60.00 m'

60.00 m' 60.00 m'

Hal. 96 dari 297


BACK UP PERHITUNGAN

KEGIATAN : Perencanaan Pengembangan Infrastruktur


PEKERJAAN : Penyusunan Dokumen Perencanaan Teknik pengembangan Infrastruktur Bidang Cipta Karya ( Paket 25 )
Pembangunan Kantor Kecamatan Sruweng (Lanjutan)
LOKASI : Kabupaten Kebumen
TAHUN ANGGARAN : 2017

TOTAL
NO PERHITUNGAN VOLUME
VOLUME
E. MUSHOLA
I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan bauwplank 11.50 ls
= 11.50 X 1.00 = 11.50 ls

11.50 ls

II PEKERJAAN TANAH
1 Penggalian 1 m3 tanah biasa sedalam 1 m
Panjang total pondasi batu kali 27.07 m3
arah H = 3.25 + 5.00 + 6.25 + + = 14.50 m'

14.50 m'

arah V = 6.50 + 1.50 + 6.50 + + = 14.50 m'

14.50 m'

Panjang Tot = 14.50 + 14.50 = 29.00 m'

Vol. Pbk = 0.95 x 0.90 x 29.00 = 24.80 m3

Rollax = 0.20 x 0.20 x 3.55 = 0.14 m3


= 0.30 x 2.00 x 3.55 = 2.13 m3

2.27 m3

2 Pengurugan kembali 1 m3 galian tanah


= 0.30 x 24.80 = 7.44 m3 7.44 m3
7.44 m3
3 Pengurugan 1 m3 dengan pasir urug
tebal pasir
Lantai = 5.00 x 5.00 x 0.05 = 1.25 m3
= 1.50 x 5.25 x 0.05 = 0.39 m3
Pondasi = 0.95 x 29.00 x 0.10 = 2.76 m3
Jumlah Total = 4.40 m3 4.40 m3
4 Pengurugan 1 m3 cadas padat
= 5.00 x 5.00 x 0.90 = 22.50 m3
= 1.50 x 5.25 x 0.90 = 7.09 m3

29.59 m3 29.59 m3
III PEKERJAAN PONDASI
1 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP
Gedung
Pbk =( 0.30 + 0.95 ) x 1.35 x 29.00 m' = 24.47 m3
2

= 2.00 x 0.45 x 3.55 m' = 3.20 m3


= 1.70 x 0.15 x 3.55 m' = 0.91 m3
= 1.40 x 0.15 x 3.55 m' = 0.75 m3
= 1.10 x 0.15 x 3.55 m' = 0.59 m3
= 0.80 x 0.15 x 3.55 m' = 0.43 m3
= 0.50 x 0.15 x 3.55 m' = 0.27 m3

6.12
Jumlah total
= 24.47 + 6.12 = 30.59 m3 30.59 m3

2 Pemasangan 1 m3 batu kosong (anstamping)


Gedung
Pbk = 0.95 x 0.20 x 29.00 m' = 5.51 m3

Jumlah total
= 5.51 = 5.51 m3 5.51 m3

IV PEKERJAAN DINDING

1 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 3PP

Dinding = 29.00 x 0.50 x 1.00 = 14.50 m2 23.84 m2


= 3.55 x 0.40 x 5.00 = 7.10 m2
= 2.35 x 0.70 x 2.00 = 3.29 m2

24.89 m2
Luas Perlubangan
P3 = 0.80 x 0.50 x (1.00) = (0.40) m2
P7 = 1.30 x 0.50 x (1.00) = (0.65) m2

(1.05) m2
Luas Netto = 24.89 + (1.05) = 23.84 m2

Hal. 97 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
3 Pemasangan 1m2 dinding bata merah (5x11x22)cm
tebal ½ batu campuran 1SP : 6PP
Dinding lantai = 21.25 x 3.80 x 1.00 = 80.75 m2
= 7.75 x 2.70 x 1.00 = 20.93 m2

101.68 m2

Luas Perlubangan jml


P3 = 0.80 x 2.64 x (1.00) = (2.11) m2
P7 = 1.30 x 2.64 x (1.00) = (3.43) m2
J8 = 0.69 x 2.22 x (10.00) = (15.32) m2

= (20.86) m2
Perlubangan
Luas Netto = 101.68 + (20.86) = 80.81 m2 = 80.81 m2
= 80.81 m2

Luas total = 80.81 = 80.81 m2 80.81 m2

3 Pemasangan main dinding GRC


= 0.40 x 4.00 = 1.60 m2
= 0.65 x 3.00 = 1.95 m2
= 1.73 x 2.00 = 3.45 m2

Jumlah Total = 7.00 m2 7.00 m2

V PEKERJAAN PLESTERAN
1 Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm.
= 2.00 x 104.65 = 209.30 m2
= 16.90 x (1.00) = (16.90) m2

Jumlah Total = 192.41 m2 192.41 m2

2 Pemasangan 1 m2 acian.
= 192.41 x 1.00 = 192.41 m2

Jumlah = 192.41 m2 192.41 m2

VI PEKERJAAN KAYU
1 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas II ( kruing )
= 0.01 x 6.15 x 1.00 = 0.06 m3 0.20 m3
= 0.01 x 1.70 x 1.00 = 0.02 m3
= 0.01 x 6.00 x 1.00 = 0.06 m3
= 0.01 x 2.90 x 1.00 = 0.03 m3
= 0.01 x 6.00 x 1.00 = 0.04 m3

0.20 m3
2 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruing )
= 0.01 x 5.00 x 4.00 = 0.19 m3 0.50 m3
= 0.01 x 2.50 x 4.00 = 0.10 m3
= 0.01 x 5.50 x 4.00 = 0.21 m3

0.50 m3

3 Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II ( kruing )


67.50 m2
= 3.75 x 4.50 x 2.00 x 2.00 = 67.50 m2

= 67.50 m2

4 Lisplang GRC Board tebal 9 mm, L = 30 cm (terpasang & pengecatan), motif kayu
= 7.50 x 4.00 = 30.00 m1 30.00 m1

30.00

5 Pemasangan 1 m2 atap genteng palentong kecil


67.50 m2
= 3.75 x 4.50 x 2.00 x 2.00 = 67.50 m2

= 67.50 m2

6 Pemasangan 1 m’ bubung genteng palentong


= 5.50 x 4.00 = 22.00 m1 22.00 m1

22.00

7 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III
= 7.00 x 7.00 = 49.00 m2 58.75 m2
= 3.00 x 3.25 = 9.75 m2

58.75

8 Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm


= 5.00 x 5.00 = 25.00 m2 32.15 m2
= 2.20 x 3.25 = 7.15 m2

32.15

Hal. 98 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
9 Pemasangan 1 m’ list langit-langit gypsum profil
= 20.00 x 2.00 = 40.00 m1 52.50 m1
= 6.50 x 1.00 = 6.50 m1
= 6.00 x 1.00 = 6.00 m1

52.50

10 Pemasangan 1 m2 langit-langit kalsiboard ukuran (120x240x4) mm, tebal 4 mm


= 1.00 x 14.00 = 14.00 m2 24.00 m2
= 1.00 x 10.00 = 10.00 m2

24.00

VII PEKERJAAN BETON


1 Lantai Kerja
Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Lantai = 1.50 x 1.50 x 1.00 x 0.05 = 0.11 m3
= 5.00 x 5.00 x 1.00 x 0.05 = 1.25 m3
= 2.75 x 3.50 x 1.00 x 0.05 = 0.48 m3
= 1.50 x 1.75 x 1.00 x 0.05 = 0.13 m3

1.98 m3 1.98 m3

2 Rabat Beton
Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Tritisan = 1.00 x 3.50 x 1.00 x 0.10 = 0.35 m3
= 1.50 x 1.75 x 1.00 x 0.10 = 0.26 m3

0.61 m3 0.61 m3

3 Sloof 15/25
a. Begisting = 0.25 x 2 x 29.00 = 14.50 m2 x 0.50 7.25 m2
b. Pembesian
-Besi 5 D 13 = 5.00 x 1.04 x 29.00 = 150.80 kg
-Begel Ø 8 - 150 = 193.00 x 0.393 x 0.70 = 53.09 kg
203.89 kg 203.89 kg

c. Beton bertulang = 0.15 x 0.25 x 29.00 = 1.09 m3 1.09 m3

4 Kolom 11/11
= 4 x 22 x 1.00 = 88.00 m1 106.00 m3
= 3 x 6 x 1.00 = 18.00 m1

106.00

5 Balok 15/30
a. Begisting
= 0.375 x 2 x 6.00 = 4.50 m2 x 0.50 2.25 m2

b. Pembesian
-Besi 6 D 13 = 6.00 x 1.04 x 6.00 = 37.44 kg
-Begel Ø 6 - 150 = 40.00 x 0.22 x 0.80 = 7.04 kg
44.48 kg 44.48 kg

c. Beton bertulang = 0.15 x 0.3 x 6.00 = 0.27 m3 0.27 m3

6 Balok 15/20
a. Begisting
= 0.2 x 2 x 31.75 = 12.70 m2 x 0.50 6.35 m2

b. Pembesian
-Besi 5 D 13 = 5.00 x 1.04 x 31.75 = 165.10 kg
-Begel Ø 8 - 150 = 212.00 x 0.393 x 0.60 = 49.99 kg
215.09 kg 215.09 kg

c. Beton bertulang = 0.15 x 0.2 x 31.75 = 0.95 m3 0.95 m3

7 Balok Latai 10/15

= 1 x 1 x 20.00 = 20.00 m2 x 1.00 20.00 m2

8 Plat Atap
a. Begisting = 2.00 x 4.25 x 1.00 = 8.50 m2 x 0.50 10.63 m2
= 1.50 x 8.50 x 1.00 = 12.75 m2

21.25 m2
b. Pembesian
-Besi Ø 10 - 150 = 2.10 x 0.62 x 56.00 = 72.91 kg
-Besi Ø 10 - 150 = 4.35 x 0.62 x 26.00 = 70.12 kg

-Besi Ø 10 - 150 = 1.60 x 0.62 x 114.00 = 113.09 kg


-Besi Ø 10 - 150 = 8.60 x 0.62 x 20.00 = 106.64 kg

362.76 kg 362.76 kg

c. Beton bertulang = 2.00 x 4.25 x 0.12 x 1.00 = 1.02 m3 2.55 m3


= 1.50 x 8.5 x 0.12 x 1.00 = 1.53 m3

2.55

Hal. 99 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
9 Shading
a. Begisting = 0.60 x 10.00 x 1.00 = 6.00 m2 x 0.50 3.00 m2

6.00 m2
b. Pembesian
-Besi Ø 10 - 150 = 0.80 x 0.62 x 67.00 = 33.23 kg
-Besi Ø 10 - 150 = 10.00 x 0.62 x 4.00 = 24.80 kg

58.03 kg 58.03 kg

c. Beton bertulang = 0.60 x 10 x 0.1 x 1.00 = 0.60 m3 0.60 m3

0.60

XI PEKERJAAN PENUTUP LANTAI DAN DINDING


1 Pemasangan 1m2 lantai keramik ukuran 40cm x40cm
= 1.50 x 1.50 x 1.00 = 2.25 m2
= 5.00 x 5.00 x 1.00 = 25.00 m2
= 2.75 x 3.50 x 1.00 = 9.63 m2

= 36.88 m2 36.88 m2
2 Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm
= 1.50 x 1.75 x 1.00 = 2.63 m2

= 2.63 m2 2.63 m2

3 Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm


= 5.45 x 1.00 x 2.00 = 10.90 m1

= 10.90 m1 10.90 m1

4 Pemasangan 1 m2 dinding keramik 20cm x 20cm


= 5.45 x 1.50 x 2.00 = 16.35 m2

= 16.35 m2 16.35 m2

XII PEKERJAAN KUNCI DAN KACA


1 Pemasangan 1 buah engsel pintu
P3 = 6.00 x 1.00 = 6.00 bh
P7 = 3.00 x 1.00 = 3.00 bh

9.00 bh 9.00 bh

2 Pemasangan 1 buah engsel jendela kupu-kupu


P3 = 2.00 x 1.00 = 2.00 bh
P7 = 2.00 x 1.00 = 2.00 bh
J8 = 4.00 x 10.00 = 40.00 bh

44.00 bh 44.00 bh

3 Pemasangan 1 buah kait angin


P3 = 2.00 x 1.00 = 2.00 bh
P7 = 2.00 x 1.00 = 2.00 bh
J8 = 4.00 x 10.00 = 40.00 bh

44.00 bh 44.00 bh

4 Pemasangan 1 buah kunci slot


P3 = 1.00 x 1.00 = 1.00 bh
P7 = 1.00 x 1.00 = 1.00 bh
J8 = - x 10.00 = - bh

2.00 bh 2.00 bh

5 Pemasangan 1 m2 kaca tebal 5 mm


P3 = 3.24 x 1.00 = 3.24 m2
P7 = 0.17 x 1.00 = 0.17 m2
J8 = 2.22 x 10.00 = 22.20 m2

25.61 m2 25.61 m2

6 Grendel pintu
P3 = 5.00 x 1.00 = 5.00 m'
P7 = 2.00 x 1.00 = 2.00 m'
J8 = 2.00 x 10.00 = 20.00 m'

27.00 m' 27.00 m'

XIII PEKERJAAN BESI DAN ALUMINIUM


1 Pemasangan 1 m kusen pintu alluminium
P3 = 8.31 x 1.00 = 8.31 m'
P7 = 6.86 x 1.00 = 6.86 m'
J8 = 6.54 x 10.00 = 65.40 m'

80.57 m' 80.57 m'


2 Pemasangan 1 m2 pintu alluminium strip lebar 8 cm
P7 = 1.47 x 1.00 = 1.47 m2

1.47 m2 1.47 m2

3 Pemasangan 1 m2 pintu kaca rangka alluminium


P3 = 2.52 x 1.00 = 2.52 m2

Hal. 100 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
2.52 m2 2.52 m2

Hal. 101 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
2 Pemasangan 1 m2 jendela kaca rangka alluminium
P3 = 0.51 x 1.00 = 0.51 m2
P7 = 0.32 x 1.00 = 0.32 m2
J8 = 1.28 x 10.00 = 12.81 m2

13.64 m2 13.64 m2

XIV PEKERJAAN PENGECATAN


1 Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
192.41 x 1.00 = 192.41 m2

192.41 m2 192.41 m2
2 Pengecatan 1 m2 plafon ( 1 lapis cat dasar, 2 lapis cat penutup) luas total
56.15 x 1.00 = 56.15 m2

= 56.15 m2 56.15 m2

XIV PEKERJAAN INSTALASI LISTRIK


1 Instalasi Listrik
SL 18 watt = 5.00 bh = 5.00 ttk
Pijar 5 w = 1.00 bh = 1.00 ttk
Stop kontak = 2.00 bh = 2.00 ttk
= 8.00 ttk
= 8.00 ttk 8.00 ttk

2 Saklar ganda = 2.00 bh 2.00 bh


2 Saklar tunggal = 2.00 bh 2.00 bh
3 Stop kontak = 2.00 bh 2.00 bh
5 Lampu pijar 5 W philips = 1.00 bh 1.00 bh
6 Lampu SL 18 Watt Phillips = 5.00 bh 5.00 bh

Hal. 102 dari 297


BACK UP PERHITUNGAN

KEGIATAN : Perencanaan Pengembangan Infrastruktur


PEKERJAAN : Penyusunan Dokumen Perencanaan Teknik pengembangan Infrastruktur Bidang Cipta Karya ( Paket 25 )
Pembangunan Kantor Kecamatan Sruweng (Lanjutan)
LOKASI : Kabupaten Kebumen
TAHUN ANGGARAN : 2017

TOTAL
NO PERHITUNGAN VOLUME
VOLUME
C. KANTOR PELAYANAN
I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan bauwplank 53.50 ls
= 53.50 X 1.00 = 53.50 ls

53.50 ls

II PEKERJAAN TANAH
1 Penggalian 1 m3 tanah biasa sedalam 1 m
Panjang total pondasi batu kali 146.12 m3
arah H = 45.00 + 28.50 + 43.50 + 5.50 + = 122.50 m'

122.50 m'

arah V = 27.00 + 8.00 + 6.00 + 27.00 + 6.00 = 74.00 m'

74.00 m'

Panjang Tot = 122.50 + 74.00 = 196.50 m'

Vol. Pbk = 0.80 x 0.90 x 196.50 = 141.48 m3

Rollax = 0.20 x 0.20 x 116.00 = 4.64 m3

4.64 m3

2 Pengurugan kembali 1 m3 galian tanah


= 0.30 x 141.48 = 42.44 m3 42.44 m3
42.44 m3
3 Pengurugan 1 m3 dengan pasir urug
tebal pasir
Lantai = 38.50 x 9.00 x 0.05 = 17.33 m3
= 2.00 x 3.50 x 0.05 = 0.35 m3
= 1.00 x 8.50 x 0.05 = 0.43 m3
= 3.00 x 3.00 x 0.05 = 0.45 m3
= 3.00 x 4.00 x 0.05 = 0.60 m3
Pondasi = 0.80 x 196.50 x 0.10 = 15.72 m3
Jumlah Total = 34.87 m3 34.87 m3
4 Pengurugan 1 m3 cadas padat
= 38.50 x 9.00 x 0.40 = 138.60 m3
= 2.00 x 3.50 x 0.40 = 2.80 m3
= 1.00 x 8.50 x 0.40 = 3.40 m3
= 3.00 x 3.00 x 0.40 = 3.60 m3
= 3.00 x 4.00 x 0.40 = 4.80 m3

153.20 m3 153.20 m3
III PEKERJAAN PONDASI
1 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP
Gedung
Pbk =( 0.30 + 0.80 ) x 1.35 x 157.00 m' = 116.57 m3
2

=( 0.30 + 0.80 ) x 1.35 x 39.50 m' = 29.33 m3


2

Jumlah total
= 116.57 + 29.33 = 145.90 m3 145.90 m3

2 Pemasangan 1 m3 batu kosong (anstamping)


Gedung
Pbk = 0.80 x 0.20 x 196.50 m' = 31.44 m3

Jumlah total
= 31.44 = 31.44 m3 31.44 m3

IV PEKERJAAN DINDING
1 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP

Tasram = 116.00 x 0.20 x 1.00 = 23.20 m2 23.20 m2

23.20 m2

2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 3PP

Dinding = 180.00 x 0.50 x 1.00 = 90.00 m2 82.20 m2

90.00 m2
Luas Perlubangan
P1 = 2.00 x 0.50 x (2.00) = (2.00) m2
P3 = 0.80 x 0.50 x (10.00) = (4.00) m2
P4 = 0.70 x 0.50 x (4.00) = (1.40) m2
PS = 0.80 x 0.50 x (1.00) = (0.40) m2

(7.80) m2

Hal. 103 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
Luas Netto = 90.00 + (7.80) = 82.20 m2

Hal. 104 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
3 Pemasangan 1m2 dinding bata merah (5x11x22)cm
tebal ½ batu campuran 1SP : 6PP
Dinding lantai = 165.50 x 3.80 x 1.00 = 628.90 m2
= 14.50 x 3.30 x 1.00 = 47.85 m2
= 1.00 x 8.00 x 1.00 = 8.00 m2
= 1.00 x 7.50 x 1.00 = 7.50 m2
= 1.00 x 7.50 x 1.00 = 7.50 m2
= 0.80 x 2.35 x 4.00 = 7.52 m2

707.27 m2

Luas Perlubangan jml


P1 = 2.00 x 2.95 x (2.00) = (11.80) m2
= 0.40 x 5.04 x (2.00) = (4.03) m2
P3 = 0.80 x 2.77 x (10.00) = (22.16) m2
P4 = 0.70 x 2.77 x (4.00) = (7.76) m2
PS = 0.80 x 2.10 x (1.00) = (1.68) m2
J3 = 0.70 x 1.70 x (6.00) = (7.14) m2
J1 = 1.36 x 1.86 x (6.00) = (15.18) m2
J2 = 2.01 x 1.86 x (16.00) = (59.82) m2
B1 = 0.67 x 0.70 x (4.00) = (1.88) m2
B2 = 0.67 x 1.36 x (2.00) = (1.82) m2

= (133.26) m2
Perlubangan
Luas Netto = 707.27 + (133.26) = 574.01 m2 = 574.01 m2
= 574.01 m2

Luas total = 574.01 = 574.01 m2 574.01 m2

V PEKERJAAN PLESTERAN
1 Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm.
= 2.00 x 656.21 = 1,312.42 m2
= 32.24 x (1.00) = (32.24) m2

Jumlah Total = 1,280.18 m2 1,280.18 m2

2 Pemasangan 1 m2 acian.
= 1,280.18 x 1.00 = 1,280.18 m2
= 31.10 x 0.10 = 3.11 m2

Jumlah = 1,283.29 m2 1,283.29 m2

3 Sponengan
= 2.85 x 2.00 x 1.00 = 5.70 m1
= 2.55 x 4.00 x 1.00 = 10.20 m1
= 2.00 x 4.00 x 1.00 = 8.00 m1
= 3.60 x 2.00 x 1.00 = 7.20 m1

Jumlah = 31.10 m1 31.10 m1

VI PEKERJAAN KAYU
1 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas II ( kruing )
= 0.01 x 10.00 x 13.00 = 1.46 m3 6.99 m3
= 0.01 x 5.00 x 13.00 = 0.62 m3
= 0.01 x 10.00 x 13.00 = 1.25 m3
= 0.01 x 6.60 x 13.00 = 0.82 m3
= 0.01 x 2.00 x 13.00 = 0.25 m3
= 0.01 x 22.00 x 13.00 = 2.06 m3

= 0.01 x 5.50 x 2.00 = 0.11 m3


= 0.01 x 4.20 x 2.00 = 0.08 m3
= 0.01 x 5.00 x 2.00 = 0.10 m3
= 0.01 x 3.30 x 2.00 = 0.06 m3
= 0.01 x 2.00 x 2.00 = 0.04 m3
= 0.01 x 10.00 x 2.00 = 0.14 m3

6.99 m3
2 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruing )
= 0.01 x 47.50 x 2.00 = 0.91 m3 3.57 m3
= 0.01 x 41.50 x 2.00 = 0.80 m3
= 0.01 x 35.50 x 2.00 = 0.68 m3
= 0.01 x 8.00 x 4.00 = 0.31 m3
= 0.01 x 1.50 x 4.00 = 0.06 m3
= 0.01 x 32.50 x 1.00 = 0.31 m3
= 0.01 x 7.00 x 10.00 = 0.50 m3

3.57 m3

3 Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II


533.00 m2
= 35.25 x 6.50 x 2.00 x 1.00 = 458.25 m2
= 5.75 x 6.50 x 2.00 x 1.00 = 74.75 m2

= 533.00 m2

Hal. 105 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME

4 Lisplang GRC Board tebal 9 mm, L = 30 cm (terpasang & pengecatan), motif kayu
= 41.00 x 2.00 = 82.00 m1 105.00 m1
= 11.50 x 2.00 = 23.00 m1

105.00

5 Pemasangan 1 m2 atap genteng palentong besar/super


533.00 m2
= 35.25 x 6.50 x 2.00 x 1.00 = 458.25 m2
= 5.75 x 6.50 x 2.00 x 1.00 = 74.75 m2

= 533.00 m2

6 Pemasangan 1 m’ bubung genteng palentong besar


= 29.50 x 1.00 = 29.50 m1 61.50 m1
= 8.00 x 4.00 = 32.00 m1

61.50

7 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III
= 38.50 x 9.00 = 346.50 m2 463.00 m2
= 2.00 x 3.50 = 7.00 m2
= 1.00 x 8.50 = 8.50 m2
= 3.00 x 3.00 = 9.00 m2
= 3.00 x 4.00 = 12.00 m2
= 0.80 x 100.00 = 80.00 m2

463.00

8 Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm


= 38.50 x 9.00 = 346.50 m2 383.00 m2
= 2.00 x 3.50 = 7.00 m2
= 1.00 x 8.50 = 8.50 m2
= 3.00 x 3.00 = 9.00 m2
= 3.00 x 4.00 = 12.00 m2

383.00

9 Pemasangan 1 m’ list langit-langit gypsum profil


= 11.00 x 1.00 = 11.00 m1 436.80 m1
= 12.00 x 1.00 = 12.00 m1
= 18.00 x 1.00 = 18.00 m1
= 16.00 x 1.00 = 16.00 m1
= 5.40 x 2.00 = 10.80 m1
= 11.00 x 1.00 = 11.00 m1
= 67.00 x 1.00 = 67.00 m1
= 8.00 x 1.00 = 8.00 m1
= 14.00 x 1.00 = 14.00 m1
= 22.00 x 1.00 = 22.00 m1
= 19.00 x 1.00 = 19.00 m1
= 7.00 x 2.00 = 14.00 m1
= 20.00 x 1.00 = 20.00 m1
= 28.00 x 1.00 = 28.00 m1
= 12.00 x 1.00 = 12.00 m1
= 77.00 x 2.00 = 154.00 m1

436.80

10 Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I


P3 = 1.68 x 10.00 = 16.80 m2 24.36 m2
P4 = 1.47 x 4.00 = 5.88 m2
PS = 1.68 x 1.00 = 1.68 m2

24.36

11 Pemasangan 1 m2 langit-langit kalsiboard ukuran (120x240x4) mm, tebal 4 mm


= 0.80 x 100.00 = 80.00 m2 80.00 m2

80.00

VII PEKERJAAN BETON


1 Lantai Kerja
Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Lantai = 38.50 x 9.00 x 1.00 x 0.05 = 17.33 m3
= 2.00 x 3.50 x 1.00 x 0.05 = 0.35 m3
= 1.00 x 8.50 x 1.00 x 0.05 = 0.43 m3
= 3.00 x 4.00 x 1.00 x 0.05 = 0.60 m3

18.70 m3 18.70 m3

2 Rabat Beton
Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Tritisan = 16.50 x 2.00 x 1.00 x 0.10 = 3.30 m3
= 15.00 x 2.00 x 1.00 x 0.10 = 3.00 m3

6.30 m3 6.30 m3

Hal. 106 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
3 Sloof 15/25
a. Begisting = 0.25 x 2 x 201.50 = 100.75 m2 x 0.50 50.38 m2
b. Pembesian
-Besi 5 D 13 = 5.00 x 1.04 x 201.50 = 1,047.80 kg
-Begel Ø 8 - 150 = 1,343.00 x 0.393 x 0.70 = 369.46 kg
1,417.26 kg 1,417.26 kg

c. Beton bertulang = 0.15 x 0.25 x 201.50 = 7.56 m3 7.56 m3

4 Kolom 20/20
a. Begisting = 0.2 x 4 x 4.00 = 3.20 m2 x 0.50 60.80 m2
= 3.20 x 38.00 = 121.60 m2
b. Pembesian
-Besi 4 Ø 10 = 4.00 x 4.00 + 0.30 = 17.20 m1
= 17.20 x 38.00 x 0.62 = 405.23 kg
-Begel Ø 6 - 150 = 1,013.00 x 0.22 x 0.70 = 156.00 kg
561.23 kg 561.23 kg

c. Beton bertulang = 0.2 x 0.2 x 152.00 = 6.08 m3 6.08 m3

5 Kolom 11/11
= 4 x 23 x 1.00 = 92.00 m1 119.00 m3
= 3 x 9 x 1.00 = 27.00 m1

119.00

6 Balok 15/30
a. Begisting
= 0.375 x 2 x 19.00 = 14.25 m2 x 0.50 7.13 m2

b. Pembesian
-Besi 6 D 13 = 6.00 x 1.04 x 19.00 = 118.56 kg
-Begel Ø 6 - 150 = 127.00 x 0.22 x 0.80 = 22.35 kg
140.91 kg 140.91 kg

c. Beton bertulang = 0.15 x 0.3 x 19.00 = 0.86 m3 0.86 m3

7 Balok 15/20
a. Begisting
= 0.2 x 2 x 201.50 = 80.60 m2 x 0.50 40.30 m2

b. Pembesian
-Besi 5 D 13 = 5.00 x 1.04 x 201.50 = 1,047.80 kg
-Begel Ø 8 - 150 = 1,343.00 x 0.393 x 0.60 = 316.68 kg
1,364.48 kg 1,364.48 kg

c. Beton bertulang = 0.15 x 0.2 x 201.50 = 6.05 m3 6.05 m3

8 Balok Latai 10/15

= 1 x 1 x 97.00 = 97.00 m2 x 1.00 97.00 m2

9 Plat Atap
a. Begisting = 4.00 x 5.50 x 1.00 = 22.00 m2 x 0.50 25.00 m2
= 4.00 x 3.00 x 1.00 = 12.00 m2
= 4.00 x 4.00 x 1.00 = 16.00 m2

50.00 m2
b. Pembesian
-Besi Ø 10 - 150 = 4.10 x 0.62 x 74.00 = 188.11 kg
-Besi Ø 10 - 150 = 5.60 x 0.62 x 54.00 = 187.49 kg

-Besi Ø 10 - 150 = 4.10 x 0.62 x 40.00 = 101.68 kg


-Besi Ø 10 - 150 = 3.10 x 0.62 x 54.00 = 103.79 kg

-Besi Ø 10 - 150 = 4.10 x 0.62 x 54.00 = 137.27 kg


-Besi Ø 10 - 150 = 4.10 x 0.62 x 54.00 = 137.27 kg

855.60 kg 855.60 kg

c. Beton bertulang = 4.00 x 5.5 x 0.12 x 1.00 = 2.64 m3 6.00 m3


= 4.00 x 3 x 0.12 x 1.00 = 1.44 m3
= 4.00 x 4 x 0.12 x 1.00 = 1.92 m3

6.00

10 Shading
a. Begisting = 0.60 x 48.70 x 1.00 = 29.22 m2 x 0.50 14.61 m2

29.22 m2
b. Pembesian
-Besi Ø 10 - 150 = 0.80 x 0.62 x 325.00 = 161.20 kg
-Besi Ø 10 - 150 = 48.70 x 0.62 x 4.00 = 120.78 kg

281.98 kg 281.98 kg

c. Beton bertulang = 0.60 x 48.7 x 0.1 x 1.00 = 2.92 m3 2.92 m3

2.92

Hal. 107 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME

Hal. 108 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
11 Plat Lisplang
a. Begisting = 0.36 x 19.50 x 1.00 = 7.02 m2 x 0.50 3.51 m2

7.02 m2
b. Pembesian
-Besi Ø 10 - 150 = 0.56 x 0.62 x 130.00 = 45.14 kg
-Besi Ø 10 - 150 = 19.50 x 0.62 x 2.00 = 24.18 kg

69.32 kg 69.32 kg

c. Beton bertulang = 0.36 x 19.5 x 0.1 x 1.00 = 0.70 m3 0.70 m3

0.70

12 Balok 15/40
a. Begisting
= 0.375 x 2 x 5.50 = 4.13 m2 x 0.50 2.06 m2

b. Pembesian
-Besi 8 D 13 = 8.00 x 1.04 x 5.50 = 45.76 kg
-Begel Ø 6 - 150 = 37.00 x 0.22 x 1.00 = 8.14 kg
53.90 kg 53.90 kg

c. Beton bertulang = 0.15 x 0.4 x 5.50 = 0.33 m3 0.33 m3

13 Kolom 30/30
a. Begisting = 0.3 x 4 x 3.00 = 3.60 m2 x 0.50 7.20 m2
= 3.60 x 4.00 = 14.40 m2
b. Pembesian
-Besi 6 D 13 = 6.00 x 3.00 + 0.30 = 19.80 m1
= 19.80 x 4.00 x 1.04 = 82.37 kg
-Besi 4 Ø 10 = 2.00 x 3.00 + 0.30 = 6.60 m1
= 6.60 x 4.00 x 0.62 = 16.37 kg
-Begel Ø 6 - 150 = 80.00 x 0.22 x 1.10 = 19.36 kg
101.73 kg 101.73 kg

c. Beton bertulang = 0.3 x 0.3 x 12.00 = 1.08 m3 1.08 m3

XI PEKERJAAN PENUTUP LANTAI DAN DINDING


1 Pemasangan 1m2 lantai keramik ukuran 40cm x40cm
= 38.50 x 9.00 x 1.00 = 346.50 m2
= 2.00 x 3.50 x 1.00 = 7.00 m2
= 1.00 x 8.50 x 1.00 = 8.50 m2
= 3.00 x 4.00 x 1.00 = 12.00 m2
= 15.00 x (1.00) x 1.00 = (15.00) m2

= 359.00 m2 359.00 m2
2 Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm
= 3.00 x 3.00 x 1.00 = 9.00 m2
= 2.00 x 3.00 x 1.00 = 6.00 m2

= 15.00 m2 15.00 m2

3 Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm


= 4.70 x 1.00 x 2.00 = 9.40 m1
= 5.70 x 1.00 x 2.00 = 11.40 m1

= 20.80 m1 20.80 m1

4 Pemasangan 1 m2 dinding keramik 20cm x 20cm


= 4.70 x 1.50 x 2.00 = 14.10 m2
= 5.70 x 1.50 x 2.00 = 17.10 m2

= 31.20 m2 31.20 m2

5 Pemasangan 1 m2 dinding batu tempel susun sirih


= 0.80 x 2.35 x 4.00 = 7.52 m2
= 0.80 x 3.20 x 2.00 = 5.12 m2

= 12.64 m2 12.64 m2

XII PEKERJAAN KUNCI DAN KACA


1 Pemasangan 1 buah engsel pintu
P3 = 3.00 x 10.00 = 30.00 m'
P4 = 3.00 x 4.00 = 12.00 m'

42.00 m' 42.00 m'

2 Pemasangan 1 buah engsel jendela kupu-kupu


P3 = 2.00 x 10.00 = 20.00 bh
P4 = 2.00 x 4.00 = 8.00 bh
J3 = 2.00 x 6.00 = 12.00 bh
J1 = 8.00 x 6.00 = 48.00 bh
J2 = 12.00 x 16.00 = 192.00 bh
B1 = 2.00 x 4.00 = 8.00 bh
B2 = 4.00 x 2.00 = 8.00 bh
P1 = 4.00 x 2.00 = 8.00 bh

304.00 bh 304.00 bh

Hal. 109 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
3 Pemasangan 1 buah kait angin
P3 = 2.00 x 10.00 = 20.00 bh
P4 = 2.00 x 4.00 = 8.00 bh
J3 = 2.00 x 6.00 = 12.00 bh
J1 = 8.00 x 6.00 = 48.00 bh
J2 = 12.00 x 16.00 = 192.00 bh
B1 = 2.00 x 4.00 = 8.00 bh
B2 = 4.00 x 2.00 = 8.00 bh
P1 = 4.00 x 2.00 = 8.00 bh

304.00 bh 304.00 bh

4 Pemasangan 1 buah kunci slot


P3 = 1.00 x 10.00 = 10.00 bh
P4 = 1.00 x 4.00 = 4.00 bh

14.00 bh 14.00 bh

5 Pemasangan 1 m2 kaca tebal 5 mm


P3 = 1.09 x 10.00 = 10.90 m2
P4 = 0.99 x 4.00 = 3.96 m2
J3 = 1.07 x 6.00 = 6.42 m2
J1 = 4.78 x 6.00 = 28.68 m2
J2 = 7.17 x 16.00 = 114.72 m2
B1 = 0.91 x 4.00 = 3.64 m2
B2 = 1.82 x 2.00 = 3.64 m2
P1 = 4.42 x 2.00 = 8.84 m2

180.80 m2 180.80 m2
2 Grendel pintu
P3 = 2.00 x 10.00 = 20.00 bh
P4 = 2.00 x 4.00 = 8.00 bh
J3 = 2.00 x 6.00 = 12.00 bh
J1 = 4.00 x 6.00 = 24.00 bh
J2 = 6.00 x 16.00 = 96.00 bh
B1 = 1.00 x 4.00 = 4.00 bh
B2 = 1.00 x 2.00 = 2.00 bh
P1 = 2.00 x 2.00 = 4.00 bh

170.00 bh 170.00 bh
XIII PEKERJAAN BESI DAN ALUMINIUM
1 Pemasangan 1 m kusen pintu alluminium
P3 = 7.32 x 10.00 = 73.20 m'
P4 = 7.10 x 4.00 = 28.40 m'
J3 = 4.80 x 6.00 = 28.80 m'
J1 = 9.66 x 6.00 = 57.96 m'
J2 = 15.48 x 16.00 = 247.68 m'
B1 = 2.74 x 4.00 = 10.96 m'
B2 = 4.73 x 2.00 = 9.46 m'
P1 = 16.48 x 2.00 = 32.96 m'

489.42 m' 489.42 m'

2 Pemasangan 1 m2 jendela kaca rangka alluminium


P3 = 0.47 x 10.00 = 4.70 m2
P4 = 0.41 x 4.00 = 1.62 m2
J3 = - x 6.00 = - m2
J1 = 2.11 x 6.00 = 12.66 m2
J2 = 3.17 x 16.00 = 50.65 m2
B1 = 0.35 x 4.00 = 1.42 m2
B2 = 0.71 x 2.00 = 1.42 m2
P1 = 1.18 x 2.00 = 2.36 m2

74.83 m2 74.83 m2
XIV PEKERJAAN PENGECATAN
1 Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
1,283.29 x 1.00 = 1,283.29 m2

1,283.29 m2 1,283.29 m2
2 Pengecatan 1 m2 plafon ( 1 lapis cat dasar, 2 lapis cat penutup) luas total
463.00 x 1.00 = 463.00 m2

= 463.00 m2 463.00 m2
XIV PEKERJAAN INSTALASI LISTRIK
1 Instalasi Listrik
SL 18 watt = 33.00 bh = 33.00 ttk
Pijar 5 w = 9.00 bh = 9.00 ttk
Stop kontak = 15.00 bh = 15.00 ttk
= 57.00 ttk
= 57.00 ttk 57.00 ttk

2 Saklar ganda = 3.00 bh 3.00 bh


2 Saklar tunggal = 12.00 bh 12.00 bh
3 Stop kontak = 15.00 bh 15.00 bh
5 Lampu pijar 5 W philips = 9.00 bh 9.00 bh
6 Lampu SL 18 Watt Phillips = 33.00 bh 33.00 bh

XV PEKERJAAN LAIN - LAIN


1 Pasang salura U Ø 20 cm, termasuk pas. Dinding
= 116.00 x 1.00 = 116.00 m'

116.00 m' 116.00 m'

Hal. 110 dari 297


BACK UP PERHITUNGAN

KEGIATAN : Perencanaan Pengembangan Infrastruktur


PEKERJAAN : Penyusunan Dokumen Perencanaan Teknik pengembangan Infrastruktur Bidang Cipta Karya ( Paket 25 )
Pembangunan Kantor Kecamatan Sruweng (Lanjutan)
LOKASI : Kabupaten Kebumen
TAHUN ANGGARAN : 2017

TOTAL
NO PERHITUNGAN VOLUME
VOLUME
B. PEMBANGUNAN PENDOPO
I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan bauwplank 34.00 ls
= 34.00 X 1.00 = 34.00 ls

34.00 ls

2 1 M2 Pasang Paving blok segi 4, t. 8 cm 190.00 m2


= 10.00 X 19.00 = 190.00 m2

190.00 m2
II PEKERJAAN TANAH
1 Penggalian 1 m3 tanah biasa sedalam 1 m
Panjang total pondasi batu kali 40.20 m3
arah H = 16.00 + 16.00 + 5.00 = 37.00 m'

37.00 m'

arah V = 14.00 + 2.50 + 2.50 + 14.00 = 33.00 m'

33.00 m'

Panjang Tot = 37.00 + 33.00 = 70.00 m'

Vol. Pbk = 1.00 x 0.35 x 70.00 = 24.50 m3

Foot Plat = 1.00 x 0.65 x 18.00 = 11.70 m3


Rollax = 0.20 x 0.20 x 71.40 = 2.86 m3
= 0.20 x 0.15 x 38.00 = 1.14 m3

15.70 m3

2 Pengurugan kembali 1 m3 galian tanah


= 0.30 x 40.20 = 12.06 m3 12.06 m3
12.06 m3
3 Pengurugan 1 m3 dengan pasir urug
tebal pasir
Foot Plat = 1.00 x 18.00 x 0.10 = 1.80 m3
Lantai = 16.00 x 14.00 x 0.10 = 22.40 m3
= 3.10 x 6.40 x 0.10 = 1.98 m3
= 3.60 x 5.50 x 0.10 = 1.98 m3
Pondasi = 1.00 x 70.00 x 0.10 = 7.00 m3
Jumlah Total = 35.16 m3 35.16 m3
4 Pengurugan 1 m3 cadas padat
= 16.00 x 14.00 x 0.57 = 127.73 m3
= 2.80 x 5.80 x 0.57 = 9.26 m3
= 3.00 x 4.90 x 0.57 = 8.38 m3
145.38 m3 145.38 m3
III PEKERJAAN PONDASI
1 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP
Gedung
Pbk =( 0.30 + 0.80 ) x 0.70 x 70.00 m' = 26.95 m3
2
Jumlah total
= 26.95 = 26.95 m3 26.95 m3

2 Pemasangan 1 m3 batu kosong (anstamping)


Gedung
Pbk = 1.00 x 0.20 x 70.00 m' = 14.00 m3

Jumlah total
= 14.00 = 14.00 m3 14.00 m3

IV PEKERJAAN DINDING
1 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP

Tasram = 38.00 x 0.15 x 1.00 = 5.70 m2 5.70 m2

5.70 m2

2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 3PP

Dinding = 16.00 x 0.50 x 1.00 = 8.00 m2 28.82 m2


Tasram = 71.40 x 0.30 x 1.00 = 21.42 m2

29.42 m2
Luas Perlubangan
= 0.20 x 0.50 x (6.00) = (0.60) m2

(0.60) m2
Luas Netto = 29.42 + (0.60) = 28.82 m2

Hal. 111 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
3 Pemasangan 1m2 dinding bata merah (5x11x22)cm
tebal ½ batu campuran 1SP : 6PP
Dinding lantai = 16.00 x 3.95 x 1.00 = 63.20 m2
= 43.00 x 1.45 x 1.00 = 62.35 m2
= 2.50 x 2.00 x 2.00 = 10.00 m2

135.55 m2

Luas Perlubangan jml


= 0.15 x 0.30 x (18.00) = (0.81) m2
= 0.20 x 3.95 x (6.00) = (4.74) m2
= 0.20 x 1.45 x (17.00) = (4.93) m2

= (10.48) m2
Perlubangan
Luas Netto = 135.55 + (10.48) = 125.07 m2 = 125.07 m2
= 125.07 m2

Luas total = 125.07 = 125.07 m2 125.07 m2

V PEKERJAAN PLESTERAN
1 Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm.
= 2.00 x 132.47 = 264.94 m2
= 0.60 x 3.95 x 6.00 = 14.22 m2
= 0.60 x 1.45 x 17.00 = 14.79 m2
= 0.80 x 1.50 x 17.00 = 20.40 m2

Jumlah Total = 314.35 m2 314.35 m2


2 Pemasangan 1 m2 acian.
= 314.35 x 2.00 = 628.70 m2
= 295.40 x 0.10 = 29.54 m2

Jumlah = 658.24 m2 658.24 m2

3 Sponengan
= 4.00 x 3.95 x 6.00 = 94.80 m1
= 4.00 x 1.45 x 17.00 = 98.60 m1
= 4.00 x 1.50 x 17.00 = 102.00 m1

Jumlah = 295.40 m1 295.40 m1

VI PEKERJAAN KAYU
1 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas II ( kruing )
= 0.01 x 5.50 x 2.00 = 0.11 m3 0.42 m3
= 0.01 x 2.80 x 2.00 = 0.05 m3
= 0.01 x 6.80 x 2.00 = 0.13 m3
= 0.01 x 2.90 x 2.00 = 0.06 m3
= 0.01 x 5.00 x 2.00 = 0.07 m3

0.42 m3
2 Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas II ( kruing )
= 0.01 x 4.25 x 19.00 = 0.58 m3 0.85 m3
= 0.01 x 6.15 x 6.00 = 0.27 m3

0.85 m3

3 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruing )


= 0.01 x 1.50 x 1.00 = 0.01 m3 0.48 m3
= 0.01 x 6.50 x 2.00 = 0.12 m3
= 0.01 x 9.50 x 2.00 = 0.18 m3
= 0.01 x 4.00 x 4.00 = 0.15 m3

0.48 m3

4 Pemasangan 1 m3 konstruksi gordeng expose, kayu kelas II ( kruing )


= 0.01 x 16.40 x 2.00 = 0.31 m3 3.19 m3
= 0.01 x 22.50 x 2.00 = 0.43 m3
= 0.01 x 27.50 x 2.00 = 0.53 m3
= 0.01 x 8.50 x 4.00 = 0.33 m3
= 0.01 x 2.00 x 4.00 = 0.08 m3
= 0.01 x 55.00 x 1.00 = 0.53 m3
= 0.01 x 59.00 x 1.00 = 0.57 m3
= 0.01 x 6.30 x 2.00 = 0.12 m3
= 0.01 x 4.60 x 2.00 = 0.09 m3
= 0.01 x 6.20 x 1.00 = 0.06 m3
= 0.01 x 4.50 x 2.00 = 0.09 m3
= 0.01 x 3.50 x 2.00 = 0.07 m3

3.19 m3

5 Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II


33.00 m2
= 3.25 x 3.00 x 2.00 x 1.00 = 19.50 m2
= 2.25 x 3.00 x 2.00 x 1.00 = 13.50 m2

= 33.00 m2

Hal. 112 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
6 Pemasangan 1 m2 rangka atap genteng beton expose, kayu kelas II ( kruing )
410.50 m2
= 11.38 x 7.00 x 2.00 x 1.00 = 159.25 m2
= 10.13 x 6.00 x 2.00 x 1.00 = 121.50 m2
= 16.88 x 1.50 x 2.00 x 1.00 = 50.63 m2
= 5.00 x 1.50 x 1.00 x (1.00) = (7.50) m2
= 14.88 x 1.50 x 2.00 x 1.00 = 44.63 m2
= 6.30 x 1.00 x 2.00 x 1.00 = 12.60 m2
= 3.50 x 4.20 x 2.00 x 1.00 = 29.40 m2

= 410.50 m2

7 Lisplang GRC Board tebal 9 mm, L = 30 cm (terpasang & pengecatan), motif kayu
= 18.00 x 2.00 = 36.00 m1 141.60 m1
= 16.50 x 2.00 = 33.00 m1
= 4.20 x 2.00 = 8.40 m1
= 1.00 x 4.00 = 4.00 m1
= 17.70 x 1.00 = 17.70 m1
= 18.70 x 1.00 = 18.70 m1
= 5.20 x 2.00 = 10.40 m1
= 6.70 x 2.00 = 13.40 m1

141.60

8 Pemasangan 1 m2 atap genteng palentong besar/super


443.50 m2
= 11.38 x 7.00 x 2.00 x 1.00 = 159.25 m2
= 10.13 x 6.00 x 2.00 x 1.00 = 121.50 m2
= 16.88 x 1.50 x 2.00 x 1.00 = 50.63 m2
= 5.00 x 1.50 x 1.00 x (1.00) = (7.50) m2
= 14.88 x 1.50 x 2.00 x 1.00 = 44.63 m2
= 6.30 x 1.00 x 2.00 x 1.00 = 12.60 m2
= 3.50 x 4.20 x 2.00 x 1.00 = 29.40 m2
= 3.25 x 3.00 x 2.00 x 1.00 = 19.50 m2
= 2.25 x 3.00 x 2.00 x 1.00 = 13.50 m2

= 443.50 m2

9 Pemasangan 1 m’ bubung genteng palentong besar


= 1.50 x 1.00 = 1.50 m1 61.70 m1
= 3.00 x 4.00 = 12.00 m1
= 8.50 x 4.00 = 34.00 m1
= 6.20 x 1.00 = 6.20 m1
= 2.00 x 4.00 = 8.00 m1

61.70

10 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III
= 4.50 x 5.00 = 22.50 m2 22.50 m2

22.50

11 Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm


= 4.50 x 5.00 = 22.50 m2 22.50 m2

22.50

12 Pemasangan 1 m2 langit-langit kalsiboard ukuran (120x240x4) mm, tebal 4 mm


410.50 m2
= 11.38 x 7.00 x 2.00 x 1.00 = 159.25 m2
= 10.13 x 6.00 x 2.00 x 1.00 = 121.50 m2
= 16.88 x 1.50 x 2.00 x 1.00 = 50.63 m2
= 5.00 x 1.50 x 1.00 x (1.00) = (7.50) m2
= 14.88 x 1.50 x 2.00 x 1.00 = 44.63 m2
= 6.30 x 1.00 x 2.00 x 1.00 = 12.60 m2
= 3.50 x 4.20 x 2.00 x 1.00 = 29.40 m2

= 410.50 m2

13 Pemasangan 1 m’ list langit-langit gypsum profil


= 9.00 + 10.00 = 19.00 m1 19.00 m1

19.00
14 Pasang Papan pembungkus kolom beton (2 x 30 )cm, kayu Jati finising politur
= 7.08 x 4.00 = 28.32 m2 28.32 m2

28.32

15 Membuat dan memasang rangka pagar, Kayu Kruwing


= 0.01 x 0.90 x 4.00 x 1.00 = 0.02 m3 0.68 m3
= 0.01 x 1.35 x 4.00 x 1.00 = 0.03 m3
= 0.00 x 0.90 x 4.00 x 1.00 = 0.01 m3
= 0.00 x 1.00 x 4.00 x 1.00 = 0.01 m3
= 0.01 x 0.90 x 4.00 x 2.00 = 0.04 m3
= 0.01 x 1.10 x 4.00 x 2.00 = 0.05 m3
= 0.00 x 0.90 x 4.00 x 2.00 = 0.03 m3
= 0.00 x 1.00 x 4.00 x 2.00 = 0.03 m3
= 0.01 x 0.90 x 2.00 x 8.00 = 0.09 m3
= 0.01 x 2.08 x 2.00 x 8.00 = 0.20 m3
= 0.01 x 0.90 x 2.00 x 4.00 = 0.04 m3
= 0.01 x 2.45 x 2.00 x 4.00 = 0.12 m3

0.68 m3

Hal. 113 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME

Hal. 114 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
16 Membuat dan memasang Pagar , Kayu Kruwing
= 0.18 x 1.00 x 12.00 x 1.00 = 2.16 m2 27.65 m2
= 0.18 x 1.10 x 2.00 x 1.00 = 0.40 m2
= 0.18 x 1.20 x 2.00 x 1.00 = 0.43 m2
= 0.18 x 1.30 x 2.00 x 1.00 = 0.47 m2
= 0.18 x 1.00 x 10.00 x 2.00 = 3.60 m2
= 0.18 x 1.10 x 2.00 x 2.00 = 0.79 m2
= 0.18 x 1.20 x 2.00 x 2.00 = 0.86 m2
= 0.18 x 1.30 x 2.00 x 2.00 = 0.94 m2
= 0.18 x 1.00 x 8.00 x 8.00 = 11.52 m2
= 0.18 x 1.00 x 9.00 x 4.00 = 6.48 m2

27.65 m2

VII PEKERJAAN BETON


1 Lantai Kerja
Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Foot plat = 1.00 x 1.00 x 0.10 x 14.00 = 1.40 m3

Lantai = 14.00 x 16.00 x 1.00 x 0.08 = 17.92 m3


= 6.40 x 3.10 x 1.00 x 0.08 = 1.59 m3
= 5.10 x 1.80 x 2.00 x 0.08 = 1.47 m3

22.38 m3 22.38 m3

2 Rabat Beton
Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Tritisan = 17.60 x 1.00 x 0.80 x 0.10 = 1.41 m3
= 4.40 x 4.00 x 0.80 x 0.10 = 1.41 m3
= 5.90 x 2.00 x 0.80 x 0.10 = 0.94 m3
= 7.50 x 2.00 x 0.30 x 0.10 = 0.45 m3
= 11.80 x 2.00 x 0.70 x 0.10 = 1.65 m3

5.86 m3 5.86 m3

3 Pondasi Foot Plat 0.8 x 0.8 m


a. Begisting 4.48 m2
* foot plat = 0.2 x 3.2 x 14.00 = 8.96 m2
8.96 x 0.5
b. Pembesian
* foot plat
-Begel Ø 12 - 150 = 5.00 x 0.89 x 2.30 x 14.00 = 142.81 kg
= 5.00 x 0.89 x 2.30 x 14.00 = 142.81 kg

285.61 kg 285.61 kg

c. Beton bertulang = 0.8 x 0.80 x 0.15 x 14.00 = 1.34 m3 2.06 m3


= 0.04 x 0.64 x 0.15 x 14.00 = 0.71 m3
2
2.06 m3

4 Sloof 15/20
a. Begisting = 0.2 x 2 x 108.00 = 43.20 m2 x 0.50 21.60 m2
b. Pembesian
-Besi 4 Ø 12 = 4.00 x 0.89 x 108.00 = 383.18 kg
-Begel Ø 6 - 150 = 720.00 x 0.22 x 0.60 = 95.04 kg
478.22 kg 478.22 kg

c. Beton bertulang = 0.15 x 0.2 x 108.00 = 3.24 m3 3.24 m3

5 Kolom 30/30
a. Begisting = 0.3 x 4 x 9.75 = 11.70 m2 x 0.50 23.40 m2
= 11.70 x 4.00 = 46.80 m2
b. Pembesian
-Besi 4 Ø 12 = 4.00 x 9.75 + 0.50 = 41.00 m1
= 41.00 x 4.00 x 0.89 = 145.47 kg
-Besi 4 Ø 12 = 4.00 x 9.75 + 0.89 = 42.55 m1
= 42.55 x 9.75 x 0.89 = 367.97 kg
-Begel Ø 8 - 150 = 260.00 x 0.39 x 1.10 = 112.40 kg
625.83 kg 625.83 kg

c. Beton bertulang = 0.3 x 0.3 x 39.00 = 3.51 m3 3.51 m3

-
6 Kolom 20/20
a. Begisting = 0.2 x 4 x 6.55 = 5.24 m2 x 0.50 36.68 m2
= 5.24 x 14.00 = 73.36 m2
b. Pembesian
-Besi 4 Ø 12 = 4.00 x 6.55 + 0.50 = 28.20 m1
= 28.20 x 14.00 x 0.89 = 350.19 kg
-Begel Ø 8 - 150 = 611.00 x 0.39 x 0.70 = 168.09 kg
518.27 kg 518.27 kg

c. Beton bertulang = 0.2 x 0.2 x 91.70 = 3.67 m3 3.67 m3

a. Begisting = 0.2 x 4 x 5.00 = 4.00 m2 x 0.50 18.00 m2


= 4.00 x 9.00 = 36.00 m2
b. Pembesian
-Besi 4 Ø 12 = 4.00 x 5.00 + 0.25 = 21.00 m1
= 21.00 x 9.00 x 0.89 = 167.64 kg
-Begel Ø 8 - 150 = 300.00 x 0.39 x 0.70 = 82.53 kg
250.17 kg 250.17 kg

Hal. 115 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
c. Beton bertulang = 0.2 x 0.2 x 45.00 = 1.80 m3 1.80 m3

Hal. 116 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
7 Kolom 15/15
a. Begisting = 0.5 x 2 x 2.00 = 2.00 m2 x 0.50 2.00 m2
= 2.00 x 2.00 = 4.00 m2
b. Pembesian
-Besi 4 Ø 12 = 4.00 x 2.00 + 0.00 = 8.00 m1
= 8.00 x 2.00 x 0.89 = 14.19 kg
-Begel Ø 6 - 150 = 27.00 x 0.22 x 0.50 = 2.97 kg
17.16 kg 17.16 kg

c. Beton bertulang = 0.15 x 0.15 x 4.00 = 0.09 m3 0.09 m3

8 Balok 20/35
a. Begisting
= 0.45 x 2 x 135.00 = 121.50 m2 x 0.50 60.75 m2

b. Pembesian
-Besi 5 Ø 12 = 5.00 x 0.89 x 135.00 = 598.73 kg
-Besi 2 Ø 10 = 2.00 x 0.62 x 135.00 = 167.40 kg
-Begel Ø 86 - 125 = 1,080.00 x 0.22 x 1.00 = 237.60 kg
1,003.73 kg 1,003.73 kg

c. Beton bertulang = 0.2 x 0.35 x 135.00 = 9.45 m3 9.45 m3

9 Balok 15/20
a. Begisting
= 0.2 x 2 x 57.00 = 22.80 m2 x 0.50 11.40 m2

b. Pembesian
-Besi 4 Ø 12 = 4.00 x 0.89 x 57.00 = 202.24 kg
-Begel Ø 6 - 150 = 380.00 x 0.22 x 0.60 = 50.16 kg
252.40 kg 252.40 kg

c. Beton bertulang = 0.15 x 0.2 x 57.00 = 1.71 m3 1.71 m3

10 Balok Latai 15/20


a. Begisting
= 0.2 x 2 x 16.00 = 6.40 m2 x 0.50 3.20 m2

b. Pembesian
-Besi 4 Ø 12 = 4.00 x 0.89 x 16.00 = 56.77 kg
-Begel Ø 6 - 150 = 107.00 x 0.22 x 0.60 = 14.12 kg
70.89 kg 70.89 kg

c. Beton bertulang = 0.15 x 0.2 x 16.00 = 0.48 m3 0.48 m3

11 Ring Balok 15/20


a. Begisting
= 0.2 x 2 x 82.50 = 33.00 m2 x 0.50 16.50 m2

b. Pembesian
-Besi 4 Ø 12 = 4.00 x 0.89 x 82.50 = 292.71 kg
-Begel Ø 6 - 150 = 550.00 x 0.22 x 0.60 = 72.60 kg
365.31 kg 365.31 kg

c. Beton bertulang = 0.15 x 0.2 x 82.50 = 2.48 m3 2.48 m3

12 Plat Shading
a. Begisting = 0.60 x 5.00 x 1.00 = 3.00 m2 x 0.50 1.50 m2

3.00 m2
b. Pembesian
-Besi Ø 8 - 150 = 0.80 x 0.39 x 33.00 = 10.38 kg
-Besi Ø 8 - 150 = 5.00 x 0.39 x 4.00 = 7.86 kg

18.24 kg 18.24 kg

c. Beton bertulang = 0.60 x 5 x 0.08 x 0.08 = 0.02 m3 0.02 m3

0.02

XI PEKERJAAN PENUTUP LANTAI DAN DINDING


1 Pemasangan 1m2 lantai keramik ukuran 40cm x40cm
= 14.00 x 16.00 x 1.00 = 224.00 m2
= 6.40 x 3.10 x 1.00 = 19.84 m2
= 5.10 x 1.80 x 2.00 = 18.36 m2
= 10.00 x 0.18 x 1.00 = 1.80 m2
= 11.40 x 0.18 x 1.00 = 2.05 m2
= 12.60 x 0.18 x 1.00 = 2.27 m2
= 7.00 x 0.18 x 2.00 = 2.52 m2
= 7.90 x 0.18 x 2.00 = 2.84 m2
= 8.70 x 0.18 x 2.00 = 3.13 m2

= 276.82 m2 276.82 m2
2 Pemasangan 1 m2 dinding batu tempel candi
= 1.20 x 0.90 x 16.00 = 17.28 m2
= 0.90 x 0.90 x 7.00 = 5.67 m2
= 2.00 x 0.90 x 4.00 = 7.20 m2

= 30.15 m2 30.15 m2

Hal. 117 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
XII PEKERJAAN KUNCI DAN KACA
1 Pemasangan 1 buah engsel pintu
= 4.00 x 3.00 = 12.00 m'

12.00 m' 12.00 m'


2 Grendel pintu
= 2.00 x 3.00 = 6.00 m'

6.00 m' 6.00 m'

XIII PEKERJAAN BESI DAN ALUMINIUM


1 Pemasangan 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm
= 5.00 x 2.00 = 10.00 m'

10.00 m' 10.00 m'

XIV PEKERJAAN PENGECATAN


1 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)

= 118.06 x 0.36 = 42.50 m2


= 332.29 x 0.32 = 106.33 m2
= 410.50 x 0.95 = 389.98 m2

538.81 m2 538.81 m2
2 Pelaburan 1 m2 bidang kayu dengan politur luas total
99.65 x 0.32 = 31.89 m2
22.80 x 0.30 = 6.84 m2
153.61 x 0.40 = 61.44 m2

= 100.17 m2 100.17 m2

3 Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
658.24 x 1.00 = 658.24 m2

658.24 m2 658.24 m2
4 Pengecatan 1 m2 plafon ( 1 lapis cat dasar, 2 lapis cat penutup) luas total
433.00 x 1.00 = 433.00 m2

= 433.00 m2 433.00 m2

XIV PEKERJAAN INSTALASI LISTRIK


1 Instalasi Listrik
SL 18 watt = 11.00 bh = 11.00 ttk
Pijar 40 w = - bh = - ttk
Stop kontak = 2.00 bh = 2.00 ttk
= 13.00 ttk
= 13.00 ttk 13.00 ttk

2 Saklar ganda = 6.00 bh 6.00 bh


3 Stop kontak = 2.00 bh 2.00 bh
4 MCB = 1.00 bh 1.00 bh
5 Lampu Gantung Artistik = 1.00 bh 1.00 bh
6 Lampu SL 18 Watt Phillips = 11.00 bh 11.00 bh

XV PEKERJAAN LAIN - LAIN


1 Pasang salura U Ø 20 cm, termasuk pas. Dinding
= 40.00 x 2.00 = 80.00 m'

80.00 m' 80.00 m'


2 Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm
= 1.00 x 4.00 = 4.00 bh

4.00 bh 4.00 bh

3 Pasang logo keramik (ukuran 35 x 45) cm


= 1.00 x 1.00 = 1.00 bh

1.00 bh 1.00 bh
4 Pasang Tulisan (bahan alluminium)
= 1.00 x 1.00 = 1.00 bh

1.00 bh 1.00 bh

Hal. 118 dari 297


BACK UP PERHITUNGAN

KEGIATAN : Perencanaan Pengembangan Infrastruktur


PEKERJAAN : Penyusunan Dokumen Perencanaan Teknik pengembangan Infrastruktur Bidang Cipta Karya ( Paket 25 )
Pembangunan Kantor Kecamatan Sruweng (Lanjutan)
LOKASI : Kabupaten Kebumen
TAHUN ANGGARAN : 2017

TOTAL
NO PERHITUNGAN VOLUME
VOLUME
A. PAGAR DAN HALAMAN
I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan bauwplank 10.00 ls
= 10.00 X 1.00 = 10.00 ls

10.00 ls
II PEKERJAAN TANAH
1 Penggalian 1 m3 tanah biasa sedalam 1 m
Panjang total pondasi batu kali 101.36 m3
arah H = 49.00 + 36.00 + 22.00 + 18.50 + = 125.50 m'
= - + - + - + + = - m'

125.50 m'

arah V = 19.00 + - + + + = 19.00 m'


= - + + + + = - m'

19.00 m'

Panjang Tot = 125.50 + 19.00 = 144.50 m'

Vol. Pbk = 0.80 x 0.60 x 144.50 = 69.36 m3

Foot Plat 80/80 = 0.64 x 1.00 x 50.00 = 32.00 m3

32.00 m3

2 Pengurugan kembali 1 m3 galian tanah


= 0.30 x 69.36 = 20.81 m3 20.81 m3
20.81 m3
3 Pengurugan 1 m3 dengan pasir urug
tebal pasir
Pondasi = 0.80 x 144.50 x 0.10 = 11.56 m3
= 0.64 x 50.00 x 0.10 = 3.20 m3

Jumlah Total = 14.76 m3 14.76 m3


4 Pengurugan 1 m3 cadas padat
= 49.30 x 47.25 x 0.20 = 465.89 m3
= 22.45 x 25.65 x 0.56 = 322.47 m3
= 15.50 x 23.33 x 1.71 = 616.78 m3
= 14.95 x 25.90 x 2.14 = 830.17 m3

2,235.31 m3 2,235.31 m3
III PEKERJAAN PONDASI
1 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP
Gedung
Pbk =( 0.30 + 0.80 ) x 1.20 x 144.50 m' = 95.37 m3
2
Jumlah total
= 95.37 = 95.37 m3 95.37 m3

2 Pemasangan 1 m3 batu kosong (anstamping)


Gedung
Pbk = 0.80 x 0.20 x 144.50 m' = 23.12 m3

Jumlah total
= 23.12 = 23.12 m3 23.12 m3

IV PEKERJAAN DINDING
1 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 3PP

Dinding = 37.60 x 0.40 x 1.00 = 15.04 m2 15.04 m2

15.04 m2

3 Pemasangan 1m2 dinding bata merah (5x11x22)cm


tebal ½ batu campuran 1SP : 6PP
Dinding lantai = 1.00 x 1.50 x 15.00 = 22.50 m2 247.05 m2
= 0.70 x 2.30 x 17.00 = 27.37 m2
= 2.75 x 1.50 x 1.00 = 4.13 m2
= 2.10 x 3.90 x 2.00 = 16.38 m2
= 95.50 x 1.85 x 1.00 = 176.68 m2

247.05 m2

V PEKERJAAN PLESTERAN
1 Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm.
= 2.00 x 262.09 = 524.18 m2
= 0.20 x 17.00 = 3.40 m2
= 0.27 x 17.00 = 4.59 m2
= 0.30 x 4.00 = 1.20 m2
= 144.50 x 0.50 = 72.25 m2
= 95.50 x 0.40 = 38.20 m2

Hal. 119 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
Jumlah Total = 643.82 m2 643.82 m2

Hal. 120 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
2 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP
= 0.25 x 1.35 x 17.00 = 5.74 m2

Jumlah = 5.74 m2 5.74 m2

3 Pemasangan 1 m2 acian.
= 643.82 x 1.00 = 643.82 m2
= 80.57 x 0.10 = 8.06 m2

Jumlah = 651.88 m2 651.88 m2

4 Sponengan
= 4.03 x 17.00 x 1.00 = 68.57 m1
= 3.00 x 4.00 x 1.00 = 12.00 m1

Jumlah = 80.57 m1 80.57 m1

VII PEKERJAAN BETON


1 Sloof 15/25
a. Begisting = 0.25 x 2 x 144.50 = 72.25 m2 x 0.50 36.13 m2
b. Pembesian
-Besi 5 D 13 = 5.00 x 1.04 x 144.50 = 751.40 kg
-Begel Ø 8 - 150 = 963.00 x 0.393 x 0.70 = 264.92 kg
1,016.32 kg 1,016.32 kg

c. Beton bertulang = 0.15 x 0.25 x 144.50 = 5.42 m3 5.42 m3

2 Kolom 20/20
a. Begisting = 0.2 x 4 x 4.15 = 3.32 m2 x 0.50 28.22 m2
= 3.32 x 17.00 = 56.44 m2
b. Pembesian
-Besi 4 Ø 10 = 4.00 x 4.15 + 0.30 = 17.80 m1
= 17.80 x 17.00 x 0.62 = 187.61 kg
-Begel Ø 6 - 150 = 470.00 x 0.22 x 0.70 = 72.38 kg
259.99 kg 259.99 kg

c. Beton bertulang = 0.2 x 0.2 x 70.55 = 2.82 m3 2.82 m3

a. Begisting = 0.2 x 4 x 3.50 = 2.80 m2 x 0.50 2.80 m2


= 2.80 x 2.00 = 5.60 m2
b. Pembesian
-Besi 4 Ø 10 = 4.00 x 3.50 + 0.30 = 15.20 m1
= 15.20 x 2.00 x 0.62 = 18.85 kg
-Begel Ø 6 - 150 = 47.00 x 0.22 x 0.70 = 7.24 kg
26.09 kg 26.09 kg

c. Beton bertulang = 0.2 x 0.2 x 7.00 = 0.28 m3 0.28 m3

3 Kolom 11/11
= 3.75 x 33 x 1.00 = 123.75 m1 123.75 m3

123.75

4 Ring Balok 10/15

= 1 x 1 x 95.50 = 95.50 m2 x 1.00 95.50 m2

5 Foot Plat 80/80


a. Begisting 16.00 m2
* foot plat = 0.2 x 3.2 x 50.00 = 32.00 m2
32.00 x 0.5
b. Pembesian
* foot plat
-Besi Ø 10 -150 = 5.00 x 0.62 x 1.60 x 50.00 = 248.00 kg
-Besi Ø 10 -150 = 5.00 x 0.62 x 1.60 x 50.00 = 248.00 kg

496.00 kg 496.00 kg

= 0.80 x 0.80 x 0.15 x 50.00 = 4.80 m3 5.63 m3


= 0.80 x 0.80 + 0.15 x 0.15 = 0.33 m3
2.00
= 0.33 x 0.05 x 1.00 x 50.00 = 0.83 m3
5.63 m3

XI PEKERJAAN PENUTUP LANTAI DAN DINDING


1 Pemasangan 1m2 lantai keramik ukuran 40cm x40cm
= 2.75 x 1.50 x 1.00 = 4.13 m2

= 4.13 m2 4.13 m2

2 Pemasangan 1 m2 dinding batu tempel susun sirih


= 0.50 x 2.50 x 2.00 = 2.50 m2
= 0.50 x 1.50 x 17.00 = 12.75 m2

= 15.25 m2 15.25 m2

Hal. 121 dari 297


TOTAL
NO PERHITUNGAN VOLUME
VOLUME
VIII PEKERJAAN BESI DAN ALUMINIUM
1 Pintu besi hollow (terpasang) dan pengecatan
= 7.00 x 2.50 x 1.00 = 17.50 m2

= 17.50 m2 17.50 m2

2 Pagar besi hollow (terpasang) dan pengecatan


= 1.50 x 1.35 x 14.00 = 28.35 m2

= 28.35 m2 28.35 m2

XIV PEKERJAAN PENGECATAN


1 Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
651.88 x 1.00 = 651.88 m2

651.88 m2 651.88 m2
XIV PEKERJAAN INSTALASI LISTRIK
1 Instalasi Listrik
Lampu Taman = 8.00 bh = 8.00 ttk
Pijar 5 w = - bh = - ttk
Stop kontak = - bh = - ttk
= 8.00 ttk
= 8.00 ttk 8.00 ttk

2 Saklar ganda = 4.00 bh 4.00 bh


3 Pemasangan Lampu Taman = 8.00 bh 8.00 bh

XV PEKERJAAN LAIN - LAIN


1 Pasang salura U Ø 20 cm, termasuk pas. Dinding
= 95.50 x 2.00 = 191.00 m'

191.00 m' 191.00 m'

Hal. 122 dari 297


DRAFT DAFTAR PERHITUNGAN CONTRACK CHANGE ORDER ( CCO.1 )

KEGIATAN : PEMBANGUNAN GEDUNG KANTOR NOMOR KONTRAK : 050 / 099 / SP / VI / 2017


PEKERJAAN : PEMBANGUNAN GEDUNG KANTOR KECAMATAN SRUWENG 027 / PT.MKK / SP / VI / 2017
LOKASI : KEC. SRUWENG, KEBUMEN TANGGAL KONTRAK : 19 JUNI 2016
TAHUN ANGGARAN : 2017 NILAI KONTRAK : Rp. 3.324.897.000, -
PENYEDIA JASA : PT. MULTI KARYA KEBUMEN

MC.0 CCO.1
SELISIH TAMBAH SELISIH KURANG
HARGA
NO KODE ANALISA JENIS PEKERJAAN SAT SATUAN JUMLAH JUMLAH JUMLAH JUMLAH KET
( Rp ) VOLUME HARGA VOLUME HARGA VOLUME HARGA VOLUME HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp )

A PAGAR DAN HALAMAN


I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls 500,000.00 1.00 500,000.00 - - - - 1.00 500,000.00

2 A.2.2.1.15a. 1 M2 pasang paving blok segi 4, t = 8 cm m2 84,000.00 - - 1,694.11 142,305,454.94 - - 1,694.11 142,305,454.94

JUMLAH I 500,000.00 142,305,454.94 - 142,805,454.94


II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 49,018.75 101.36 4,968,540.50 - - 30.86 1,512,750.49 70.50 3,455,790.01

2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 16,339.58 20.81 340,026.73 0.34 5,552.27 - - 21.15 345,579.00

3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 118,607.50 14.76 1,750,646.70 - - 7.04 834,875.23 7.72 915,771.47

4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 83,393.75 2,235.31 186,410,883.31 947.55 79,019,849.55 - - 3,182.86 265,430,732.87

5 A.2.3.1.14. Pengurugan 1 m3 sirtu padat m3 136,193.75 119.20 16,234,295.00 - - - - 119.20 16,234,295.00

JUMLAH II 209,704,392.24 79,025,401.82 2,347,625.71 286,382,168.35


III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 516,466.50 95.37 49,255,410.11 74.76 38,608,788.91 - - 170.13 87,864,199.02

2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 279,576.00 23.12 6,463,797.12 - - 23.12 6,463,797.12 - -

JUMLAH III 55,719,207.23 38,608,788.91 6,463,797.12 87,864,199.02


IV PEKERJAAN DINDING
1 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 97,798.25 15.04 1,470,885.68 101.33 9,910,067.82 - - 116.37 11,380,953.50

campuran 1SP : 3PP

2 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 92,281.75 247.05 22,798,206.34 - - 208.89 19,276,919.32 38.16 3,521,287.02

campuran 1SP : 6PP

3 A. 4.4.1.20. Pemasangan 1 cm2 dinding conblock HB10 campuran 1SP :3PP m2 103,248.53 - - 287.55 29,688,650.18 - - 287.55 29,688,650.18

JUMLAH IV 24,269,092.02 39,598,718.00 19,276,919.32 44,590,890.70


V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 38,633.10 643.82 24,872,762.44 - - 314.79 12,161,417.86 329.03 12,711,344.58

2 A.4.4.2.23. Pemasangan 1 m2 plesteran ciprat 1SP : 2PP m2 35,337.50 5.74 202,837.25 1.19 41,910.28 - - 6.93 244,747.53
3 A.4.4.2.27. Pemasangan 1 m2 acian m2 23,815.00 651.88 15,524,522.20 - - 322.85 7,688,737.05 329.03 7,835,785.15

4 Ls Sponengan m1 20,000.00 80.57 1,611,400.00 - - 6.97 139,400.00 73.60 1,472,000.00

JUMLAH V 42,211,521.89 41,910.28 19,989,554.91 22,263,877.26


VI PEKERJAAN BETON
1 Sloof 15/25

A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 166,529.00 36.13 6,016,692.77 4.84 806,333.42 - - 40.97 6,823,026.19

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 1,016.32 13,270,928.70 - - 83.32 1,088,014.88 933.00 12,182,913.83

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 5.42 4,814,109.23 - - 0.62 552,460.78 4.80 4,261,648.45

slump (12 ± 2) cm, w/c = 0,87

2 Foot Plat 80/80

A.4.1.1.20. Pemasangan 1 m2 bekisting untuk pondasi m2 154,429.00 16.00 2,470,864.00 - - 2.56 395,338.24 13.44 2,075,525.76

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 496.00 6,476,681.20 - - 245.70 3,208,320.66 250.30 3,268,360.54

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 5.63 5,000,633.75 - - 3.61 3,209,998.29 2.02 1,790,635.46

slump (12 ± 2) cm, w/c = 0,87

3 Kolom 20/20

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 31.02 7,824,857.04 - - - - 31.02 7,824,857.04

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 197,116.70 - - 36.52 7,198,701.88 - - 36.52 7,198,701.88 CCO

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 286.08 3,735,582.58 117.86 1,539,003.40 - - 403.94 5,274,585.98

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 3.10 2,753,457.31 5.27 4,682,795.96 - - 8.37 7,436,253.26

slump (12 ± 2) cm, w/c = 0,87

4 Kolom 11/11

A.4.1.1.35 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 63,268.15 123.75 7,829,433.56 - - 123.75 7,829,433.56 - -

5 Ring Balok 10/15

A.4.1.1.36 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 86,781.75 95.50 8,287,657.13 59.93 5,200,830.28 - - 155.43 13,488,487.40

JUMLAH VI 68,480,897.26 19,427,664.94 16,283,566.41 71,624,995.79


VII PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 145,153.25 4.13 599,482.92 - - 0.14 20,321.46 3.99 579,161.47

2 A.4.4.3.58. Pemasangan 1 m2 dinding batu tempel candi m2 236,692.50 15.25 3,609,560.63 - - 15.25 3,609,560.63 - -

JUMLAH VII 4,209,043.55 - 3,629,882.08 579,161.47


VIII PEKERJAAN BESI DAN ALUMUNIUM
1 Ditaksir Pintu besi terpasang dan pengecatan m2 400,000.00 17.50 7,000,000.00 - - 17.50 7,000,000.00 - -

2 Ditaksir Pagar besi terpasang dan pengecatan m2 350,000.00 28.35 9,922,500.00 - - 28.35 9,922,500.00 - -

3 A.4.2.1.1. Pemasangan 1 kg besi profil kg 30,843.01 - - - - - - - -

4 Ditaksir Pasang kawat duri m1 10,000.00 - - - - - - - -

5 LS Pasang Pagar dan Pintu Besi Ulir (Lengkap) m2 455,000.00 - - 54.35 24,729,705.00 - - 54.35 24,729,705.00

6 Ditaksir Pasang Grill Saluran m' 180,000.00 - - 19.90 3,582,000.00 - - 19.90 3,582,000.00

7 LS Pasang Roda Pintu dia. 2,5" bh 50,000.00 - - 6.00 300,000.00 - - 6.00 300,000.00

8 LS Gembok bh 25,000.00 - - 1.00 25,000.00 - - 1.00 25,000.00

9 LS Pembuatan Tiang Bendera bh 2,500,000.00 - - 1.00 2,500,000.00 - - 1.00 2,500,000.00

JUMLAH VIII 16,922,500.00 31,136,705.00 16,922,500.00 31,136,705.00


IX PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 17,222.98 651.88 11,227,312.94 - - 322.85 5,560,483.98 329.03 5,666,828.96

cat dasar, 2 lapis cat penutup )

2 A.4.7.1.10. Pengecatan permukaan baja (galbani) secara semprot dengan m2 82,832.60 - - 58.33 4,831,708.39 - - 58.33 4,831,708.39

sistem 1 lapis cat mutakhir dengan tebal 200 um

JUMLAH IX 11,227,312.94 4,831,708.39 5,560,483.98 10,498,537.35


X PEKERJAAN INSTALASI LISTRIK
1 Ditaksir Titik Lampu ttk 85,000.00 8.00 680,000.00 - - 8.00 680,000.00 - -

2 Ditaksir Saklar Ganda bh 22,500.00 4.00 90,000.00 - - 4.00 90,000.00 - -

3 Ditaksir Pemasangan Lampu Taman bh 525,000.00 8.00 4,200,000.00 - - 8.00 4,200,000.00 - -

JUMLAH X 4,970,000.00 - 4,970,000.00 -


XI PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm, termasuk pasangan dinding m1 75,500.00 191.00 14,420,500.00 - - 137.80 10,403,900.00 53.20 4,016,600.00

2 Ls Tanah subur m3 120,000.00 9.28 1,113,600.00 269.44 32,332,959.00 - - 278.72 33,446,559.00

3 Ls Pembuatan taman m2 225,000.00 46.40 10,440,000.00 76.66 17,248,127.34 - - 123.06 27,688,127.34

4 Ls Pasang logo keramik ( uk 35 x 45 ) cm bh 750,000.00 1.00 750,000.00 - - - - 1.00 750,000.00

5 Ls Pasang tulisan ( bahan alumunium ) unit 3,500,000.00 1.00 3,500,000.00 - - - - 1.00 3,500,000.00

JUMLAH XI 30,224,100.00 49,581,086.34 10,403,900.00 69,401,286.34

JUMLAH ( A ) 468,438,067.13 404,557,438.63 105,848,229.53 767,147,276.22

B PEMBANGUNAN PENDOPO
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls 500,000.00 1.00 500,000.00 - - - - 1.00 500,000.00

2 A.2.2.1.15a. 1 M2 pasang paving blok segi 4, t = 8 cm ls 84,000.00 190.00 15,960,000.00 - - - - 190.00 15,960,000.00

JUMLAH I 16,460,000.00 - - 16,460,000.00


II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 49,018.75 40.20 1,970,553.75 - - - - 40.20 1,970,553.75

2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 16,339.58 12.06 197,055.38 - - - - 12.06 197,055.38

3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 118,607.50 35.16 4,170,239.70 - - - - 35.16 4,170,239.70

4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 83,393.75 145.38 12,123,783.38 - - - - 145.38 12,123,783.38

JUMLAH II 18,461,632.21 - - 18,461,632.20


III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 516,466.50 26.95 13,918,772.18 - - - - 26.95 13,918,772.18

2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 279,576.00 14.00 3,914,064.00 - - - - 14.00 3,914,064.00

JUMLAH III 17,832,836.18 - - 17,832,836.18


IV PEKERJAAN DINDING
1 A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 201,619.00 5.70 1,149,228.30 - - - - 5.70 1,149,228.30

campuran 1SP : 3PP


2 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 97,798.25 28.82 2,818,545.57 - - - - 28.82 2,818,545.57

campuran 1SP : 3PP

3 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 92,281.75 125.07 11,541,678.47 - - - - 125.07 11,541,678.47

campuran 1SP : 6PP

JUMLAH IV 15,509,452.34 - - 15,509,452.34


V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 38,633.10 314.35 12,144,314.99 - - - - 314.35 12,144,314.99

2 A.4.4.2.27. Pemasangan 1 m2 acian m2 23,815.00 658.24 15,675,985.60 - - - - 658.24 15,675,985.60

3 Ls Sponengan m1 20,000.00 295.40 5,908,000.00 - - - - 295.40 5,908,000.00

JUMLAH V 33,728,300.59 - - 33,728,300.59


VI PEKERJAAN BETON
1 Lantai kerja

A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 712,475.42 22.38 15,945,199.93 - - - - 22.38 15,945,199.93

slump (12 ± 2) cm, w/c = 0,87

2 Rabat Beton

A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 756,474.46 5.86 4,432,940.35 - - - - 5.86 4,432,940.35

slump (12 ± 2) cm, w/c = 0,87

3 Pondasi Foot Plat 80/80

A.4.1.1.20. Pemasangan 1 m2 bekisting untuk pondasi m2 154,429.00 4.48 691,841.92 - - - - 4.48 691,841.92

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 285.61 3,729,445.40 - - - - 285.61 3,729,445.40

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 2.06 1,829,716.79 - - - - 2.06 1,829,716.79

slump (12 ± 2) cm, w/c = 0,87

4 Sloof 15/25

A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 166,529.00 21.60 3,597,026.40 - - - - 21.60 3,597,026.40

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 478.22 6,244,513.07 - - - - 478.22 6,244,513.07

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 3.24 2,877,806.99 - - - - 3.24 2,877,806.99

slump (12 ± 2) cm, w/c = 0,87

5 Kolom 30/30

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 23.40 5,902,696.80 - - - - 23.40 5,902,696.80 CCO

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 197,116.70 - - - - - - - -

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 625.83 8,171,978.62 - - - - 625.83 8,171,978.62

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 3.51 3,117,624.24 - - - - 3.51 3,117,624.24

slump (12 ± 2) cm, w/c = 0,87

6 Kolom 20/20

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 54.68 13,793,139.36 - - - - 54.68 13,793,139.36 CCO

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 197,116.70 - - - - - - - -

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 768.44 10,034,155.04 - - - - 768.44 10,034,155.04

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 5.47 4,858,519.83 - - - - 5.47 4,858,519.83

slump (12 ± 2) cm, w/c = 0,87


7 Kolom 15/15

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 2.00 504,504.00 - - - - 2.00 504,504.00 CCO

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 197,116.70 - - - - - - - -

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 17.16 224,072.28 - - - - 17.16 224,072.28

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 0.09 79,939.08 - - - - 0.09 79,939.08

slump (12 ± 2) cm, w/c = 0,87

8 Balok 20/35

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 60.75 15,484,689.00 4.05 1,032,312.60 - - 64.80 16,517,001.60 CCO

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 197,116.70 - - - - - - - -

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 1,003.73 13,106,530.69 66.91 873,699.07 - - 1,070.64 13,980,229.76

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 9.45 8,393,603.72 0.63 559,573.58 - - 10.08 8,953,177.31

slump (12 ± 2) cm, w/c = 0,87

9 Balok 15/20

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 11.40 2,905,768.80 - - - - 11.40 2,905,768.80 CCO

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 197,116.70 - - - - - - - -

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 252.40 3,295,795.03 - - - - 252.40 3,295,795.03

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 1.71 1,518,842.58 - - - - 1.71 1,518,842.58

slump (12 ± 2) cm, w/c = 0,87

10 Balok latai 15/20

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 3.20 815,654.40 - - - - 3.20 815,654.40 CCO

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 197,116.70 - - - - - - - -

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 70.89 925,669.21 - - - - 70.89 925,669.21

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 0.48 426,341.78 - - - - 0.48 426,341.78

slump (12 ± 2) cm, w/c = 0,87

11 Ring balok 15/20

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 16.50 4,205,718.00 - - - - 16.50 4,205,718.00 CCO

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 197,116.70 - - - - - - - -

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 365.31 4,770,154.05 - - - - 365.31 4,770,154.05

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 2.48 2,202,765.85 - - - - 2.48 2,202,765.85

slump (12 ± 2) cm, w/c = 0,87

12 Shading

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 319,352.00 1.50 479,028.00 - - - - 1.50 479,028.00 CCO

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 241,666.70 - - - - - - - -

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 18.24 238,174.73 - - - - 18.24 238,174.73

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 0.02 17,764.24 - - - - 0.02 17,764.24

slump (12 ± 2) cm, w/c = 0,87

JUMLAH VI 144,821,620.18 - - 147,287,205.43


VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 9,944,550.00 0.42 4,176,711.00 - - - - 0.42 4,176,711.00

kayu kelas II (kruink )


2 A.4.6.1.13.a Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas II (kruink ) m3 10,071,050.00 0.85 8,560,392.50 - - - - 0.85 8,560,392.50

3 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 10,651,671.25 0.48 5,112,802.20 - - - - 0.48 5,112,802.20 CCO

4 A.4.6.1.15.a Pemasangan 1 m3 konstruksi gordeng expose , kayu kelas II ( kruink ) m3 10,778,171.25 3.19 34,382,366.29 - - - - 3.19 34,382,366.29

5 A.4.6.1.17. Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II m2 153,051.25 33.00 5,050,691.25 - - - - 33.00 5,050,691.25

6 A.4.6.1.17.a Pemasangan 1 m2 rangka atap genteng beton expose , m2 178,351.25 410.50 73,213,188.13 - - - - 410.50 73,213,188.13

kayu kelas II ( kruink )


7 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) motif kayu m1 22,500.00 141.60 3,186,000.00 - - - - 141.60 3,186,000.00

8 A.4.5.2.3.a Pemasangan 1 m2 atap genteng palentong besar/super m2 59,793.25 443.50 26,518,306.38 - - - - 443.50 26,518,306.38

9 A.4.5.2.6. Pemasangan 1 m’ bubung genteng palentong besar m1 63,189.50 61.70 3,898,792.15 - - - - 61.70 3,898,792.15

10 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 77,038.50 22.50 1,733,366.25 - - - - 22.50 1,733,366.25

11 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 34,538.90 22.50 777,125.25 - - - - 22.50 777,125.25

ukuran (120x240x9) mm, tebal 9 mm

12 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 32,937.30 410.50 13,520,761.65 - - - - 410.50 13,520,761.65

ukuran (120x240x9) mm, tebal 4 mm

13 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 19,049.25 19.00 361,935.75 - - - - 19.00 361,935.75

14 Ls Pasang papan pembungkus kolom beton (2x30) cm, m2 325,000.00 28.32 9,204,000.00 - - - - 28.32 9,204,000.00

kayu jati finishing politur

15 A.4.6.1.2. Membuat dan memasang rangka pagar, kayu kruink m3 10,925,172.50 0.68 7,429,117.30 - - - - 0.68 7,429,117.30

16 A.4.6.1.10. Membuat dan memasang pagar, kayu kruink m2 667,975.00 27.65 18,469,508.75 - - - - 27.65 18,469,508.75

JUMLAH VII 215,595,064.84 - - 215,595,064.84


VIII PEKERJAAN BESI DAN ALUMUNIUM
1 A.4.2.1.18. Pemasangan 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm m1 103,541.63 10.00 1,035,416.25 - - - - 10.00 1,035,416.25

JUMLAH VIII 1,035,416.25 - - 1,035,416.25


IX PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh 25,185.60 12.00 302,227.20 - - - - 12.00 302,227.20

2 Ditaksir Grendel pintu bh 10,000.00 6.00 60,000.00 - - - - 6.00 60,000.00

JUMLAH IX 362,227.20 - - 362,227.20


X PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 145,153.25 276.82 40,181,322.67 - - - - 276.82 40,181,322.67

2 A.4.4.3.58. Pemasangan 1 m2 dinding natu tempel candi m2 239,442.50 30.15 7,219,191.38 - - - - 30.15 7,219,191.38

JUMLAH X 47,400,514.05 - - 47,400,514.04


XI PEKERJAAN PENGECATAN
1 A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis m2 44,480.15 538.81 23,966,349.62 - - - - 538.81 23,966,349.62

cat dasar, 2 lapis cat penutup)

2 A.4.7.1.7. Pelaburan 1 m2 bidang kayu dengan politur m2 49,024.25 100.17 4,910,759.12 - - - - 100.17 4,910,759.12 CCO

3 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 17,222.98 658.24 11,336,851.06 - - - - 658.24 11,336,851.06

cat dasar, 2 lapis cat penutup )

4 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 13,132.90 433.00 5,686,545.70 - - - - 433.00 5,686,545.70

JUMLAH XI 45,900,505.51 - - 45,900,505.51


XII PEKERJAAN INSTALASI LISTRIK
1 Ls Titik Lampu Titik 85,000.00 13.00 1,105,000.00 - - - - 13.00 1,105,000.00

2 Ls Saklar ganda bh 22,500.00 6.00 135,000.00 - - - - 6.00 135,000.00

3 Ls Stop Kontak bh 22,500.00 2.00 45,000.00 - - - - 2.00 45,000.00

4 Ls MCB bh 250,000.00 1.00 250,000.00 - - - - 1.00 250,000.00

5 Ls Lampu gantung artistik bh 1,750,000.00 1.00 1,750,000.00 - - - - 1.00 1,750,000.00


6 Ls Lampu SL 18watt phillips bh 35,500.00 11.00 390,500.00 - - - - 11.00 390,500.00

JUMLAH XII 3,675,500.00 - - 3,675,500.00


XIII PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm termasuk pas dinding m1 75,500.00 80.00 6,040,000.00 - - - - 80.00 6,040,000.00

2 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30 x 30 tinggi 35 cm bh 318,991.75 4.00 1,275,967.00 - - - - 4.00 1,275,967.00

3 Ditaksir Pasang logo keramik ( ukuran 35 x 45 ) cm unit 750,000.00 1.00 750,000.00 - - - - 1.00 750,000.00

4 Ditaksir Pasang Tulisan ( bahan alumunium ) unit 2,250,000.00 1.00 2,250,000.00 - - - - 1.00 2,250,000.00

JUMLAH XIII 10,315,967.00 - - 10,315,967.00

JUMLAH ( B ) 571,099,036.33 - - 573,564,621.57

C KANTOR PELAYANAN
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls 500,000.00 1.00 500,000.00 - - - - 1.00 500,000.00

JUMLAH I 500,000.00 - - 500,000.00


II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 49,018.75 146.12 7,162,619.75 - - 83.88 4,111,692.75 62.24 3,050,927.00

2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 16,339.58 42.44 693,451.92 - - 23.77 388,359.22 18.67 305,092.70

3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 118,607.50 34.87 4,135,843.53 - - 8.89 1,054,183.46 25.98 3,081,660.07

4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 83,393.75 153.20 12,775,922.50 - - 43.99 3,668,324.28 109.21 9,107,598.23

JUMLAH II 24,767,837.70 - 9,222,559.70 15,545,277.99


III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 516,466.50 145.90 75,352,462.35 - - 56.90 29,385,007.10 89.00 45,967,455.25

2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 279,576.00 31.44 8,789,869.44 - - 0.32 89,464.32 31.12 8,700,405.12

JUMLAH III 84,142,331.79 - 29,474,471.42 54,667,860.37


IV PEKERJAAN DINDING
1 A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 201,619.00 23.20 4,677,560.80 - - 23.20 4,677,560.80 - -

campuran 1SP : 3PP

2 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 97,798.25 82.20 8,039,016.15 - - 1.00 97,798.25 81.20 7,941,217.90

campuran 1SP : 3PP

3 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 92,281.75 574.01 52,970,647.32 - - 88.80 8,194,767.05 485.21 44,775,880.27

campuran 1SP : 6PP

JUMLAH IV 65,687,224.27 - 12,970,126.10 52,717,098.17


V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 38,633.10 1,280.18 49,457,321.96 - - 179.60 6,938,628.39 1,100.58 42,518,693.57

2 A.4.4.2.27. Pemasangan 1 m2 acian m2 23,815.00 1,283.29 30,561,551.35 - - 179.60 4,277,250.21 1,103.69 26,284,301.14

3 Ls Sponengan m1 20,000.00 31.10 622,000.00 - - - - 31.10 622,000.00

JUMLAH V 80,640,873.31 - 11,215,878.59 69,424,994.71


VI PEKERJAAN BETON
1 Lantai kerja

A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 712,475.42 18.70 13,323,290.38 - - 0.50 354,812.76 18.20 12,968,477.62

slump (12 ± 2) cm, w/c = 0,87

2 Rabat Beton

A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 756,474.46 6.30 4,765,789.12 - - - - 6.30 4,765,789.12

slump (12 ± 2) cm, w/c = 0,87

3 Sloof 15/20

A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 166,529.00 50.38 8,389,731.02 - - 0.50 83,264.50 49.88 8,306,466.52

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 1,417.26 18,506,333.06 - - 13.98 182,548.39 1,403.28 18,323,784.67

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 7.56 6,352,240.04 - - 0.08 67,219.47 7.48 6,285,020.57

slump (12 ± 2) cm,w/c=0,87

4 Kolom 30/30

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 7.20 1,816,214.40 - - - - 7.20 1,816,214.40 CCO

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 101.73 1,328,372.54 - - - - 101.73 1,328,372.54

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 1.08 907,462.86 - - - - 1.08 907,462.86

slump (12 ± 2) cm,w/c=0,87

5 Kolom 20/20

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 60.80 15,336,921.60 - - - - 60.80 15,336,921.60 CCO

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 561.23 7,328,443.12 - - - - 561.23 7,328,443.12

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 6.08 5,108,679.82 - - 0.30 252,073.02 5.78 4,856,606.80

slump (12 ± 2) cm,w/c=0,87

6 Kolom 15/15

A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 252,252.00 119.00 30,017,988.00 - - 4.60 1,160,359.20 114.40 28,857,628.80 CCO

7 Balok 15/40

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 282,612.00 2.06 582,180.72 - - - - 2.06 582,180.72 CCO

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 53.90 703,816.77 - - - - 53.90 703,816.77

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.33 277,280.32 - - - - 0.33 277,280.32

slump (12 ± 2) cm, w/c = 0,87

8 Ring balok 15/30

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 282,612.00 7.13 2,015,023.56 - - - - 7.13 2,015,023.56 CCO

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 140.91 1,839,978.12 - - - - 140.91 1,839,978.12

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.86 722,609.32 - - - - 0.86 722,609.32

slump (12 ± 2) cm, w/c = 0,87


9 Ring balok 15/20

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 86,781.75 40.30 3,497,304.53 - - 0.40 34,712.70 39.90 3,462,591.83

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 1,364.48 17,817,141.06 - - 13.47 175,888.90 1,351.01 17,641,252.15

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 6.05 5,083,472.52 - - 0.06 50,414.60 5.99 5,033,057.91

slump (12 ± 2) cm, w/c = 0,87

10 Balok Latai 10/15

A.4.1.1.36. Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 86,781.75 97.00 8,417,829.75 - - - - 97.00 8,417,829.75

11 Plat atap

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 222,552.00 25.00 5,563,800.00 - - - - 25.00 5,563,800.00

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 855.60 11,172,275.07 - - - - 855.60 11,172,275.07

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 6.00 5,041,460.35 - - - - 6.00 5,041,460.35

slump (12 ± 2) cm, w/c = 0,87

12 Shading

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 319,352.00 14.61 4,665,732.72 - - - - 14.61 4,665,732.72 CCO

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 281.98 3,682,045.49 - - - - 281.98 3,682,045.49

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 2.92 2,453,510.70 - - - - 2.92 2,453,510.70

slump (12 ± 2) cm, w/c = 0,87

13 Plat lisplang

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 319,352.00 3.51 1,120,925.52 - - - - 3.51 1,120,925.52 CCO

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 69.32 905,168.43 - - - - 69.32 905,168.43

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.70 588,170.37 - - - - 0.70 588,170.37

slump (12 ± 2) cm, w/c = 0,87

JUMLAH VI 189,331,191.28 - 2,361,293.55 186,969,897.72


VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.11. Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I m3 652,159.75 24.36 15,886,611.51 - - - - 24.36 15,886,611.51

2 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 9,944,550.00 6.99 69,512,404.50 - - - - 6.99 69,512,404.50

kayu kelas II (kruink )

3 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 10,651,671.25 3.57 38,026,466.36 - - - - 3.57 38,026,466.36 CCO

4 A.4.6.1.17. Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II m2 153,051.25 533.00 81,576,316.25 - - - - 533.00 81,576,316.25

5 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) motif kayu m1 22,500.00 105.00 2,362,500.00 - - - - 105.00 2,362,500.00

6 A.4.5.2.3.a Pemasangan 1 m2 atap genteng palentong besar/super m2 59,793.25 533.00 31,869,802.25 - - - - 533.00 31,869,802.25

7 A.4.5.2.6. Pemasangan 1 m’ bubung genteng palentong besar m1 63,189.50 61.50 3,886,154.25 - - - - 61.50 3,886,154.25

8 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 77,038.50 463.00 35,668,825.50 - - - - 463.00 35,668,825.50

9 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 34,538.90 383.00 13,228,398.70 - - - - 383.00 13,228,398.70

ukuran (120x240x9) mm, tebal 9 mm

10 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 32,937.30 80.00 2,634,984.00 - - - - 80.00 2,634,984.00

ukuran (120x240x9) mm, tebal 4 mm


436.80
11 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 19,049.25 8,320,712.40 - - - - 436.80 8,320,712.40

JUMLAH VII 302,973,175.72 - - 302,973,175.72


VIII PEKERJAAN SANITASI
1 A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen bh 290,097.50 4.00 1,160,390.00 - - - - 4.00 1,160,390.00

2 A.5.1.1 10. Pemasangan 1 buah bak air fibreglass vol 1 m3 bh 342,354.10 4.00 1,369,416.40 - - - - 4.00 1,369,416.40

3 A.5.1.1 14. Pemasangan 1 buah floor drain bh 26,331.25 4.00 105,325.00 - - - - 4.00 105,325.00

4 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm bh 318,991.75 4.00 1,275,967.00 - - - - 4.00 1,275,967.00

5 A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4” m1 45,375.00 4.00 181,500.00 - - - - 4.00 181,500.00

6 A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” m1 14,250.50 60.00 855,030.00 - - - - 60.00 855,030.00

7 A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” m` 33,310.75 12.00 399,729.00 - - - - 12.00 399,729.00

8 A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4” m1 72,312.63 12.00 867,751.50 - - - - 12.00 867,751.50

9 Ditaksir Fiber glas tangki air kap 1100 ltr bh 1,450,000.00 1.00 1,450,000.00 - - - - 1.00 1,450,000.00

JUMLAH VIII 7,665,108.90 - - 7,665,108.90


IX PEKERJAAN BESI DAN ALUMUNIUM
1 A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium m1 81,947.80 489.42 40,106,892.28 - - - - 489.42 40,106,892.28

2 A.4.2.1.13. Pemasangan 1 m2 pintu kaca rangka alluminium m2 466,303.75 74.83 34,893,509.61 - - - - 74.83 34,893,509.61

3 Ls Pemasangan pintu tempered t = 12 mm ( komplit ) unit 10,000,000.00 4.00 40,000,000.00 - - - - 4.00 40,000,000.00

JUMLAH IX 115,000,401.89 - - 115,000,401.89


X PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh 25,185.60 42.00 1,057,795.20 - - - - 42.00 1,057,795.20

2 A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu bh 21,921.63 304.00 6,664,174.00 - - - - 304.00 6,664,174.00

3 A.4.6.2.9. Pemasangan 1 buah kait angin bh 25,641.00 304.00 7,794,864.00 - - - - 304.00 7,794,864.00

4 A.4.6.2.11. Pemasangan 1 buah kunci slot bh 97,083.25 14.00 1,359,165.50 - - - - 14.00 1,359,165.50

5 A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm bh 115,371.85 180.80 20,859,230.48 - - - - 180.80 20,859,230.48

6 Ditaksir Grendel pintu bh 10,000.00 170.00 1,700,000.00 - - - - 170.00 1,700,000.00

JUMLAH X 39,435,229.18 - - 39,435,229.18


XI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 145,153.25 359.00 52,110,016.75 - - 10.30 1,494,715.59 348.70 50,615,301.16

2 A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm m2 213,889.50 15.00 3,208,342.50 0.34 72,187.71 - - 15.34 3,280,530.21 CCO

3 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm m1 38,173.30 20.80 794,004.64 - - - - 20.80 794,004.64 CCO

4 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20cm x 20cm m2 204,226.00 31.20 6,371,851.20 - - - - 31.20 6,371,851.20

5 A.4.4.3.58. Pemasangan 1 m2 dinding batu tempel candi m2 236,692.50 12.64 2,991,793.20 - - - - 12.64 2,991,793.20

JUMLAH XI 65,476,008.29 72,187.71 1,494,715.59 64,053,480.40


XII PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 17,222.98 1,283.29 22,102,071.59 - - 179.60 3,093,246.31 1,103.69 19,008,825.28

cat dasar, 2 lapis cat penutup )

2 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 13,132.90 463.00 6,080,532.70 - - - - 463.00 6,080,532.70

JUMLAH XII 28,182,604.29 - 3,093,246.31 25,089,357.98


XIII PEKERJAAN INSTALASI LISTRIK
1 Ls Pemasangan meter listrik lama 5500 watt unit 750,000.00 1.00 750,000.00 - - - - 1.00 750,000.00

2 Ls Titik Lampu Titik 85,000.00 57.00 4,845,000.00 - - - - 57.00 4,845,000.00

3 Ls Saklar ganda bh 22,500.00 3.00 67,500.00 - - - - 3.00 67,500.00

4 Ls Saklar tunggal bh 20,000.00 12.00 240,000.00 - - - - 12.00 240,000.00

5 Ls stop kontak bh 22,500.00 15.00 337,500.00 - - - - 15.00 337,500.00

6 Ls lampu pijar 5W Philips bh 10,000.00 9.00 90,000.00 - - - - 9.00 90,000.00

7 Ls Lampu SL 18 Watt Phillips bh 35,500.00 33.00 1,171,500.00 - - - - 33.00 1,171,500.00

JUMLAH XIII 7,501,500.00 - - 7,501,500.00


XIV PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm termasuk pas dinding m1 75,500.00 116.00 8,758,000.00 - - - - 116.00 8,758,000.00

2 A.5.1.1 15. Membuat Septic Tank bh 1,150,000.00 1.00 1,150,000.00 - - - - 1.00 1,150,000.00

3 Ditaksir Membuat peresapan bh 750,000.00 1.00 750,000.00 - - - - 1.00 750,000.00

4 Ditaksir tanah Subur m3 120,000.00 0.36 43,200.00 - - 0.36 43,200.00 - -

5 Ditaksir Pembuatan taman m2 225,000.00 1.80 405,000.00 - - 1.80 405,000.00 - -

JUMLAH XIV 11,106,200.00 - 448,200.00 10,658,000.00

JUMLAH ( C ) 1,022,409,686.62 72,187.71 70,280,491.27 952,201,383.04

D SERBA GUNA
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls 500,000.00 1.00 500,000.00 - - - - 1.00 500,000.00

JUMLAH I 500,000.00 - - 500,000.00


II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 49,018.75 58.60 2,872,498.75 - - 56.52 2,770,539.75 2.08 101,959.00

2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 16,339.58 16.96 277,119.33 - - 8.85 144,572.63 8.11 132,546.70

3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 118,607.50 13.13 1,557,316.48 - - 3.25 385,993.28 9.88 1,171,323.19

4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 83,393.75 54.80 4,569,977.50 - - 15.83 1,319,810.34 38.97 3,250,167.16

JUMLAH II 9,276,912.06 - 4,620,916.00 4,655,996.06


III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 516,466.50 88.51 45,712,449.92 - - 55.98 28,910,503.50 32.53 16,801,946.41

2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 279,576.00 12.56 3,511,474.56 0.96 268,392.96 - - 13.52 3,779,867.52

JUMLAH III 49,223,924.48 268,392.96 28,910,503.50 20,581,813.93


IV PEKERJAAN DINDING
1 A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 201,619.00 16.40 3,306,551.60 - - - - 16.40 3,306,551.60

campuran 1SP : 3PP

2 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 97,798.25 40.30 3,941,269.48 11.13 1,088,494.52 - - 51.43 5,029,764.00

campuran 1SP : 3PP

3 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 92,281.75 224.36 20,704,333.43 1.77 163,504.80 - - 226.13 20,867,838.23

campuran 1SP : 6PP

JUMLAH IV 27,952,154.51 1,251,999.33 - 29,204,153.83


V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 38,633.10 524.35 20,257,265.99 39.90 1,541,460.69 - - 564.25 21,798,726.68

2 A.4.4.2.23. Pemasangan 1 m2 plesteran ciprat 1SP : 2PP m2 32,392.25 4.48 145,117.28 - - - - 4.48 145,117.28

2 A.4.4.2.27. Pemasangan 1 m2 acian m2 23,815.00 529.15 12,601,707.25 39.90 950,218.50 - - 569.05 13,551,925.75

3 Ls Sponengan m1 15,000.00 48.00 720,000.00 - - - - 48.00 720,000.00

JUMLAH V 33,724,090.52 2,491,679.19 - 36,215,769.71


VI PEKERJAAN BETON
1 Lantai kerja

A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 712,475.42 7.49 5,336,440.91 - - 0.99 708,467.75 6.50 4,627,973.16

slump (12 ± 2) cm, w/c = 0,87

2 Rabat Beton

A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 756,474.46 4.10 3,101,545.30 - - - - 4.10 3,101,545.30

slump (12 ± 2) cm, w/c = 0,87

3 Sloof 15/25

A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 166,529.00 19.63 3,268,964.27 1.50 249,793.50 - - 21.13 3,518,757.77

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 552.08 7,208,964.03 42.20 551,040.21 - - 594.28 7,760,004.24

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 2.94 2,470,315.57 0.23 193,255.98 - - 3.17 2,663,571.55

slump (12 ± 2) cm,w/c=0,87

4 Kolom 20/20

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 6.00 1,513,512.00 - - - - 6.00 1,513,512.00 CCO

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 56.32 735,416.70 - - - - 56.32 735,416.70

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 0.60 504,146.03 - - 0.06 50,414.60 0.54 453,731.43

slump (12 ± 2) cm,w/c=0,87

5 Kolom 15/15

A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 252,252.00 106.00 26,738,712.00 - - 2.60 655,855.20 103.40 26,082,856.80 CCO

6 Ring balok 15/30

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 6.00 1,529,352.00 - - - - 6.00 1,529,352.00 CCO

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 118.67 1,549,572.09 - - - - 118.67 1,549,572.09

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.72 604,975.24 - - 0.24 201,658.41 0.48 403,316.83

slump (12 ± 2) cm, w/c = 0,87

7 Ring balok 15/20

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 86,781.75 13.30 1,154,197.28 1.20 104,138.10 - - 14.50 1,258,335.38

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 450.26 5,879,416.28 40.63 530,539.43 - - 490.89 6,409,955.71

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 2.00 1,680,486.78 0.18 151,243.81 - - 2.18 1,831,730.59

slump (12 ± 2) cm, w/c = 0,87

8 Balok Latai 10/15

A.4.1.1.36. Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 86,781.75 36.50 3,167,533.88 - - 4.50 390,517.88 32.00 2,777,016.00

9 Plat atap

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 222,552.00 7.00 1,557,864.00 - - 1.75 389,466.00 5.25 1,168,398.00

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 237.46 3,100,711.12 - - 59.77 780,466.20 177.69 2,320,244.92
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 1.40 1,176,340.75 - - 0.35 294,085.19 1.05 882,255.56

slump (12 ± 2) cm, w/c = 0,87

10 Shading

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 319,352.00 3.51 1,120,925.52 - - 0.68 215,562.60 2.84 905,362.92 CCO

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 67.70 884,014.75 - - 13.02 170,012.88 54.68 714,001.87

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.84 705,804.45 - - 0.16 134,102.85 0.68 571,701.60

slump (12 ± 2) cm, w/c = 0,87

JUMLAH VI 74,989,210.96 1,780,011.04 3,990,609.55 72,778,612.44


VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.11. Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I m3 652,159.75 9.45 6,162,909.64 - - 1.47 958,674.83 7.98 5,204,234.81

2 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 9,944,550.00 1.45 14,419,597.50 - - - - 1.45 14,419,597.50

kayu kelas II (kruink )

3 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 10,651,671.25 1.47 15,657,956.74 - - - - 1.47 15,657,956.74 CCO

4 A.4.6.1.16. Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II m2 152,556.25 240.50 36,689,778.13 - - - - 240.50 36,689,778.13

5 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) motif kayu m1 22,500.00 61.00 1,372,500.00 - - - - 61.00 1,372,500.00

6 A.4.5.2.1. Pemasangan 1 m2 atap genteng palentong kecil m2 59,211.63 240.50 14,240,395.81 - - - - 240.50 14,240,395.81

7 A.4.5.2.4. Pemasangan 1 m’ bubung genteng palentong m1 65,939.50 34.00 2,241,943.00 - - - - 34.00 2,241,943.00

8 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 77,038.50 186.28 14,350,731.78 - - - - 186.28 14,350,731.78

9 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 34,538.90 143.72 4,963,930.71 - - - - 143.72 4,963,930.71

ukuran (120x240x9) mm, tebal 9 mm

10 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 32,937.30 42.56 1,401,811.49 - - - - 42.56 1,401,811.49

ukuran (120x240x9) mm, tebal 4 mm

11 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 19,049.25 227.80 4,339,419.15 - - - - 227.80 4,339,419.15

JUMLAH VII 115,840,973.94 - 958,674.83 114,882,299.11


VIII PEKERJAAN SANITASI
1 A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen bh 290,097.50 2.00 580,195.00 - - - - 2.00 580,195.00

2 A.5.1.1 10. Pemasangan 1 buah bak air fibreglass vol 1 m3 bh 342,354.10 2.00 684,708.20 - - - - 2.00 684,708.20

3 A.5.1.1 14. Pemasangan 1 buah floor drain bh 26,331.25 2.00 52,662.50 - - - - 2.00 52,662.50

4 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm bh 318,991.75 4.00 1,275,967.00 - - - - 4.00 1,275,967.00

5 A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4” m1 45,375.00 2.00 90,750.00 - - - - 2.00 90,750.00

6 A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” m1 14,250.50 24.00 342,012.00 - - - - 24.00 342,012.00

7 A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” m` 33,310.75 12.00 399,729.00 - - - - 12.00 399,729.00

8 A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4” m1 72,312.63 12.00 867,751.50 - - - - 12.00 867,751.50

JUMLAH VIII 4,293,775.20 - - 4,293,775.20


IX PEKERJAAN BESI DAN ALUMUNIUM
1 A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium m1 81,947.80 167.40 13,718,061.72 - - 7.10 581,829.38 160.30 13,136,232.34

2 A.4.2.1.13. Pemasangan 1 m2 pintu kaca rangka alluminium m2 466,303.75 29.02 13,532,134.83 - - 0.41 191,184.54 28.61 13,340,950.29

JUMLAH IX 27,250,196.55 - 773,013.92 26,477,182.63


X PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh 25,185.60 18.00 453,340.80 - - 3.00 75,556.80 15.00 377,784.00
2 A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu bh 21,921.63 114.00 2,499,065.25 - - 2.00 43,843.25 112.00 2,455,222.00

3 A.4.6.2.9. Pemasangan 1 buah kait angin bh 25,641.00 114.00 2,923,074.00 - - 2.00 51,282.00 112.00 2,871,792.00

4 A.4.6.2.11. Pemasangan 1 buah kunci slot bh 97,083.25 6.00 582,499.50 - - 1.00 97,083.25 5.00 485,416.25

5 A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm bh 115,371.85 42.05 4,851,386.29 - - 0.99 114,218.13 41.06 4,737,168.16

6 Ditaksir Grendel pintu bh 10,000.00 63.00 630,000.00 - - 2.00 20,000.00 61.00 610,000.00

JUMLAH X 11,939,365.84 - 401,983.43 11,537,382.41


XI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 199,798.50 140.80 28,131,628.80 - - 16.96 3,387,583.57 123.85 24,744,045.23 CCO

2 A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm m2 213,889.50 9.00 1,925,005.50 - - 2.93 627,230.96 6.07 1,297,774.54 CCO

3 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm m1 38,173.30 9.40 358,829.02 - - - - 9.40 358,829.02 CCO

4 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20cm x 20cm m2 204,226.00 14.10 2,879,586.60 - - - - 14.10 2,879,586.60

JUMLAH XI 33,295,049.92 - 4,014,814.53 29,280,235.39


XII PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 17,222.98 529.15 9,113,537.22 39.90 687,196.70 - - 569.05 9,800,733.92

cat dasar, 2 lapis cat penutup )

2 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 13,132.90 186.28 2,446,396.61 - - - - 186.28 2,446,396.61

JUMLAH XII 11,559,933.83 687,196.70 - 12,247,130.54


XIII PEKERJAAN INSTALASI LISTRIK
1 Ls Titik Lampu Titik 85,000.00 28.00 2,380,000.00 - - - - 28.00 2,380,000.00

2 Ls Saklar ganda bh 22,500.00 2.00 45,000.00 - - - - 2.00 45,000.00

3 Ls Saklar tunggal bh 20,000.00 6.00 120,000.00 - - - - 6.00 120,000.00

4 Ls stop kontak bh 22,500.00 6.00 135,000.00 - - - - 6.00 135,000.00

5 Ls lampu pijar 5W Philips bh 10,000.00 6.00 60,000.00 - - - - 6.00 60,000.00

6 Ls Lampu SL 18 Watt Phillips bh 35,500.00 16.00 568,000.00 - - - - 16.00 568,000.00

JUMLAH XIII 3,308,000.00 - - 3,308,000.00


XIV PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm termasuk pas dinding m1 75,500.00 60.00 4,530,000.00 - - - - 60.00 4,530,000.00

2 Ls Membuat Septic Tank bh 1,150,000.00 1.00 1,150,000.00 - - - - 1.00 1,150,000.00

3 Ls Membuat peresapan bh 750,000.00 1.00 750,000.00 - - - - 1.00 750,000.00

4 Ls tanah Subur m3 120,000.00 0.48 57,600.00 - - 0.48 57,600.00 - -

5 Ls Pembuatan taman m2 225,000.00 0.80 180,000.00 - - 0.80 180,000.00 - -

JUMLAH XIV 6,667,600.00 - 57,600.00 6,430,000.00

JUMLAH ( D ) 409,821,187.80 6,479,279.21 43,728,115.77 372,392,351.24

E MUSHOLLA
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls 500,000.00 1.00 500,000.00 - - 1.00 500,000.00 - -

JUMLAH I 500,000.00 - 500,000.00 -


II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 49,018.75 27.07 1,326,937.56 - - 27.07 1,326,937.56 - -
2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 16,339.58 7.44 121,566.50 - - 7.44 121,566.50 - -

3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 118,607.50 4.40 521,873.00 - - 4.40 521,873.00 - -

4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 83,393.75 29.59 2,467,621.06 - - 29.59 2,467,621.06 - -

JUMLAH II 4,437,998.12 - 4,437,998.13 -


III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 516,466.50 30.59 15,798,710.24 - - 30.59 15,798,710.24 - -

2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 279,576.00 5.51 1,540,463.76 - - 5.51 1,540,463.76 - -

JUMLAH III 17,339,174.00 - 17,339,174.00 -


IV PEKERJAAN DINDING
1 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 97,798.25 23.84 2,331,510.28 - - 23.84 2,331,510.28 - -

campuran 1SP : 3PP

2 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 92,281.75 80.81 7,457,288.22 - - 80.81 7,457,288.22 - -

campuran 1SP : 6PP

3 Ls Pemasangan main dinding GRC m2 42,000.00 7.00 294,000.00 - - 7.00 294,000.00 - -

JUMLAH IV 10,082,798.50 - 10,082,798.50 -


V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 38,633.10 192.41 7,433,394.77 - - 192.41 7,433,394.77 - -

2 A.4.4.2.27. Pemasangan 1 m2 acian m2 23,815.00 192.41 4,582,244.15 - - 192.41 4,582,244.15 - -

JUMLAH V 12,015,638.92 - 12,015,638.92 -


VI PEKERJAAN BETON
1 Lantai kerja

A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 712,475.42 1.98 1,410,701.33 - - 1.98 1,410,701.33 - -

slump (12 ± 2) cm, w/c = 0,87

2 Rabat Beton

A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 756,474.46 0.61 461,449.42 - - 0.61 461,449.42 - -

slump (12 ± 2) cm, w/c = 0,87

3 Sloof 15/25

A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 166,529.00 7.25 1,207,335.25 - - 7.25 1,207,335.25 - -

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 203.89 2,662,359.94 - - 203.89 2,662,359.94 - -

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 1.09 915,865.30 - - 1.09 915,865.30 - -

slump (12 ± 2) cm,w/c=0,87

4 Kolom 15/15

A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 63,268.15 106.00 6,706,423.90 - - 106.00 6,706,423.90 - -

5 Balok 15/30

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 2.25 573,507.00 - - 2.25 573,507.00 - -

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 44.48 580,812.06 - - 44.48 580,812.06 - -

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.27 226,865.72 - - 0.27 226,865.72 - -

slump (12 ± 2) cm, w/c = 0,87


6 Ring balok 15/20

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 86,781.75 6.35 551,064.11 - - 6.35 551,064.11 - -

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 215.09 2,808,607.58 - - 215.09 2,808,607.58 - -

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.95 798,231.22 - - 0.95 798,231.22 - -

slump (12 ± 2) cm, w/c = 0,87

7 Balok Latai 10/15

A.4.1.1.36. Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 86,781.75 20.00 1,735,635.00 - - 20.00 1,735,635.00 - -

8 Plat atap

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 222,552.00 10.63 2,365,727.76 - - 10.63 2,365,727.76 - -

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 362.76 4,736,856.60 - - 362.76 4,736,856.60 - -

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 2.55 2,142,620.65 - - 2.55 2,142,620.65 - -

slump (12 ± 2) cm, w/c = 0,87

9 Shading

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 319,352.00 3.00 958,056.00 - - 3.00 958,056.00 - -

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 58.03 757,745.58 - - 58.03 757,745.58 - -

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.60 504,146.03 - - 0.60 504,146.03 - -

slump (12 ± 2) cm, w/c = 0,87

JUMLAH VI 32,104,010.45 - 32,104,010.45 -


VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 9,944,550.00 0.20 1,988,910.00 - - 0.20 1,988,910.00 - -

kayu kelas II (kruink )

2 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 10,651,671.25 0.50 5,325,835.63 - - 0.50 5,325,835.63 - -

3 A.4.6.1.16. Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II m2 152,556.25 67.50 10,297,546.88 - - 67.50 10,297,546.88 - -

4 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) motif kayu m1 22,500.00 30.00 675,000.00 - - 30.00 675,000.00 - -

5 A.4.5.2.1. Pemasangan 1 m2 atap genteng palentong kecil m2 59,211.63 67.50 3,996,784.69 - - 67.50 3,996,784.69 - -

6 A.4.5.2.4. Pemasangan 1 m’ bubung genteng palentong m1 65,939.50 22.00 1,450,669.00 - - 22.00 1,450,669.00 - -

7 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 77,038.50 58.75 4,526,011.88 - - 58.75 4,526,011.88 - -

8 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 34,538.90 32.15 1,110,425.64 - - 32.15 1,110,425.64 - -

ukuran (120x240x9) mm, tebal 9 mm

9 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 32,937.30 24.00 790,495.20 - - 24.00 790,495.20 - -

ukuran (120x240x9) mm, tebal 4 mm

10 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 19,049.25 52.50 1,000,085.63 - - 52.50 1,000,085.63 - -

JUMLAH VII 31,161,764.52 - 31,161,764.52 -


VIII PEKERJAAN SANITASI
1 A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen bh 290,097.50 1.00 290,097.50 - - 1.00 290,097.50 - -

2 A.5.1.1 10. Pemasangan 1 buah bak air fibreglass vol 1 m3 bh 342,354.10 1.00 342,354.10 - - 1.00 342,354.10 - -

3 A.5.1.1 14. Pemasangan 1 buah floor drain bh 26,331.25 1.00 26,331.25 - - 1.00 26,331.25 - -

4 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm bh 318,991.75 4.00 1,275,967.00 - - 4.00 1,275,967.00 - -

5 A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4” m1 45,375.00 4.00 181,500.00 - - 4.00 181,500.00 - -
6 A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” m1 14,250.50 24.00 342,012.00 - - 24.00 342,012.00 - -

7 A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” m` 33,310.75 12.00 399,729.00 - - 12.00 399,729.00 - -

8 A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4” m1 72,312.63 12.00 867,751.50 - - 12.00 867,751.50 - -

JUMLAH VIII 3,725,742.35 - 3,725,742.35 -


IX PEKERJAAN BESI DAN ALUMUNIUM
1 A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium m1 81,947.80 80.57 6,602,534.25 - - 80.57 6,602,534.25 - -

2 A.4.2.1.12. Pemasangan 1 m2 pintu alluminium strip lebar 8 cm m1 422,405.78 1.47 620,936.49 - - 1.47 620,936.49 - -

3 A.4.2.1.13. Pemasangan 1 m2 pintu kaca rangka alluminium m2 466,303.75 2.52 1,175,085.45 - - 2.52 1,175,085.45 - -

4 A.4.2.1.13. Pemasangan 1 m2 pintu kaca rangka alluminium m2 466,303.75 13.64 6,360,383.15 - - 13.64 6,360,383.15 - -

5 Ls Pemasangan kubah bh 2,000,000.00 1.00 2,000,000.00 - - 1.00 2,000,000.00 - -

JUMLAH IX 16,758,939.34 - 16,758,939.34 -


X PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh 25,185.60 9.00 226,670.40 - - 9.00 226,670.40 - -

2 A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu bh 21,921.63 44.00 964,551.50 - - 44.00 964,551.50 - -

3 A.4.6.2.9. Pemasangan 1 buah kait angin bh 25,641.00 44.00 1,128,204.00 - - 44.00 1,128,204.00 - -

4 A.4.6.2.11. Pemasangan 1 buah kunci slot bh 97,083.25 2.00 194,166.50 - - 2.00 194,166.50 - -

5 A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm bh 115,371.85 25.61 2,954,673.08 - - 25.61 2,954,673.08 - -

6 Ditaksir Grendel pintu bh 10,000.00 27.00 270,000.00 - - 27.00 270,000.00 - -

JUMLAH X 5,738,265.48 - 5,738,265.48 -


XI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 199,798.50 36.88 7,368,568.68 - - 36.88 7,368,568.68 - -

2 A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm m2 213,889.50 2.63 562,529.39 - - 2.63 562,529.39 - -

3 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm m1 38,173.30 10.90 416,088.97 - - 10.90 416,088.97 - -

4 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20cm x 20cm m2 204,226.00 16.35 3,339,095.10 - - 16.35 3,339,095.10 - -

JUMLAH XI 11,686,282.14 - 11,686,282.14 -


XII PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 17,222.98 192.41 3,313,872.62 - - 192.41 3,313,872.62 - -

cat dasar, 2 lapis cat penutup )

2 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 13,132.90 56.15 737,412.34 - - 56.15 737,412.34 - -

JUMLAH XII 4,051,284.96 - 4,051,284.95 -


XIII PEKERJAAN INSTALASI LISTRIK
1 Ls Pemasangan meter listrik 900 watt unit 1,650,000.00 1.00 1,650,000.00 - - 1.00 1,650,000.00 - -

2 Ls Titik Lampu Titik 85,000.00 8.00 680,000.00 - - 8.00 680,000.00 - -

3 Ls Saklar ganda bh 22,500.00 2.00 45,000.00 - - 2.00 45,000.00 - -

4 Ls Saklar tunggal bh 20,000.00 2.00 40,000.00 - - 2.00 40,000.00 - -

5 Ls stop kontak bh 22,500.00 2.00 45,000.00 - - 2.00 45,000.00 - -

6 Ls lampu pijar 5W Philips bh 10,000.00 1.00 10,000.00 - - 1.00 10,000.00 - -

7 Ls Lampu SL 18 Watt Phillips bh 35,500.00 5.00 177,500.00 - - 5.00 177,500.00 - -

JUMLAH XIII 2,647,500.00 - 2,647,500.00 -


XIV PEKERJAAN LAIN-LAIN
2 Ls Membuat Septic Tank bh 1,150,000.00 1.00 1,150,000.00 - - 1.00 1,150,000.00 - -

3 Ls Membuat peresapan bh 750,000.00 1.00 750,000.00 - - 1.00 750,000.00 - -

4 Ls tanah Subur m3 120,000.00 0.76 91,200.00 - - 0.76 91,200.00 - -

5 Ls Pembuatan taman m2 225,000.00 1.26 283,500.00 - - 1.26 283,500.00 - -

JUMLAH XIV 2,274,700.00 - 2,274,700.00 -

JUMLAH ( E ) 154,524,098.78 - 154,524,098.77 -

F RUMAH DINAS
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls 500,000.00 1.00 500,000.00 - - - - 1.00 500,000.00

JUMLAH I 500,000.00 - - 500,000.00


II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 49,018.75 70.40 3,450,920.00 - - 68.04 3,335,235.75 2.36 115,684.25

2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 16,339.58 20.41 333,490.90 - - 11.77 192,316.90 8.64 141,174.00

3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 118,607.50 13.56 1,608,317.70 - - 4.18 496,194.48 9.38 1,112,123.22

4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 83,393.75 48.00 4,002,900.00 - - 13.34 1,112,556.02 34.66 2,890,343.98

JUMLAH II 9,395,628.60 - 5,136,303.14 4,259,325.46


III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 516,466.50 106.55 55,029,505.58 - - 71.90 37,133,941.35 34.65 17,895,564.23

2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 279,576.00 15.12 4,227,189.12 - - 0.72 201,294.72 14.40 4,025,894.40

JUMLAH III 59,256,694.70 - 37,335,236.07 21,921,458.63


IV PEKERJAAN DINDING
1 A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 201,619.00 11.80 2,379,104.20 - - - - 11.80 2,379,104.20

campuran 1SP : 3PP

2 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 97,798.25 40.11 3,922,687.81 2.00 195,596.50 - - 42.11 4,118,284.31

campuran 1SP : 3PP

3 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 92,281.75 275.49 25,422,699.31 4.57 421,727.60 - - 280.06 25,844,426.91

campuran 1SP : 6PP

JUMLAH IV 31,724,491.32 617,324.10 - 32,341,815.41


V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 38,633.10 610.28 23,577,008.27 18.72 723,211.63 - - 629.00 24,300,219.90

2 A.4.4.2.27. Pemasangan 1 m2 acian m2 23,815.00 610.28 14,533,818.20 18.72 445,816.80 - - 629.00 14,979,635.00

JUMLAH V 38,110,826.47 1,169,028.43 - 39,279,854.90


VI PEKERJAAN BETON
1 Lantai kerja

A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 712,475.42 6.00 4,274,852.53 - - 0.22 159,238.26 5.78 4,115,614.27

slump (12 ± 2) cm, w/c = 0,87


2 Rabat Beton

A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 756,474.46 6.46 4,886,825.03 - - - - 6.46 4,886,825.03

slump (12 ± 2) cm, w/c = 0,87

3 Sloof 15/25

A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 166,529.00 24.38 4,059,977.02 - - 1.13 188,177.77 23.25 3,871,799.25

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 685.82 8,955,317.54 - - 31.66 413,410.74 654.16 8,541,906.80

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 3.66 3,075,290.81 - - 0.17 142,841.38 3.49 2,932,449.44

slump (12 ± 2) cm,w/c=0,87

4 Kolom 15/25

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 25.60 6,457,651.20 - - - - 25.60 6,457,651.20 CCO

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 546.78 7,139,757.55 - - - - 546.78 7,139,757.55

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 2.40 2,016,584.14 - - - - 2.40 2,016,584.14

slump (12 ± 2) cm,w/c=0,87

5 Kolom 15/15

A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 63,268.15 60.00 3,796,089.00 - - - - 60.00 3,796,089.00

6 Ring balok 15/30

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 2.06 525,077.52 - - - - 2.06 525,077.52 CCO

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 40.83 533,150.99 - - - - 40.83 533,150.99

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.25 210,060.85 - - - - 0.25 210,060.85

slump (12 ± 2) cm, w/c = 0,87

7 Ring balok 15/20

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 19.50 4,970,394.00 - - 0.90 229,402.80 18.60 4,740,991.20 CCO

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 660.27 8,621,690.11 - - 30.47 397,871.93 629.80 8,223,818.19

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 2.93 2,461,913.14 - - 0.14 117,634.07 2.79 2,344,279.06

slump (12 ± 2) cm, w/c = 0,87

8 Balok Latai 10/15

A.4.1.1.36. Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 86,781.75 32.50 2,820,406.88 - - - - 32.50 2,820,406.88

9 Plat atap

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 222,552.00 0.75 166,914.00 - - - - 0.75 166,914.00

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 26.41 344,857.16 - - - - 26.41 344,857.16

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.18 151,243.81 - - - - 0.18 151,243.81

slump (12 ± 2) cm, w/c = 0,87

10 Shading

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 222,552.00 3.90 867,952.80 - - - - 3.90 867,952.80

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 75.39 984,429.43 - - - - 75.39 984,429.43

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.78 655,389.85 - - - - 0.78 655,389.85

slump (12 ± 2) cm, w/c = 0,87


11 Meja dapur

A.4.1.1.33. Membuat 1 m3 dinding beton bertulang (150 kg besi + bekisting) m2 222,552.00 0.90 200,296.80 - - - - 0.90 200,296.80

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 17.36 226,683.84 - - - - 17.36 226,683.84

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.18 151,243.81 - - - - 0.18 151,243.81

slump (12 ± 2) cm, w/c = 0,87

JUMLAH VI 68,554,049.81 - 1,648,576.95 66,905,472.86


VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.2. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas Im3 10,925,172.50 0.89 9,723,403.53 - - - - 0.89 9,723,403.53

2 A.4.6.1.5. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I atau II m2 591,717.50 14.70 8,698,247.25 - - - - 14.70 8,698,247.25

3 A.4.6.1.6. Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I atau m2 410,058.00 3.96 1,623,829.68 - - - - 3.96 1,623,829.68

4 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 9,944,550.00 1.52 15,115,716.00 0.43 4,276,156.50 - - 1.95 19,391,872.50

kayu kelas II (kruink )

5 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 10,651,671.25 1.84 19,599,075.10 0.06 639,100.27 - - 1.90 20,238,175.38 CCO

6 A.4.6.1.16. Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II m2 152,556.25 208.59 31,821,708.19 - - - - 208.59 31,821,708.19

7 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) motif kayu m1 22,500.00 55.20 1,242,000.00 - - - - 55.20 1,242,000.00

8 A.4.5.2.1. Pemasangan 1 m2 atap genteng palentong kecil m2 59,211.63 208.59 12,350,952.86 - - - - 208.59 12,350,952.86

9 A.4.5.2.4. Pemasangan 1 m’ bubung genteng palentong m1 65,939.50 52.20 3,442,041.90 - - 1.20 79,127.40 51.00 3,362,914.50

10 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 77,038.50 150.31 11,579,656.94 - - - - 150.31 11,579,656.94

11 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 34,538.90 117.60 4,061,774.64 - - - - 117.60 4,061,774.64

ukuran (120x240x9) mm, tebal 9 mm

12 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 32,937.30 30.31 998,329.56 - - - - 30.31 998,329.56

ukuran (120x240x9) mm, tebal 4 mm

13 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 19,049.25 223.00 4,247,982.75 - - - - 223.00 4,247,982.75

14 Ls Pemasangan rooster kayu bh 25,000.00 5.00 125,000.00 - - - - 5.00 125,000.00

JUMLAH VII 124,629,718.39 4,915,256.78 79,127.40 129,465,847.76


VIII PEKERJAAN SANITASI
1 A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen bh 290,097.50 1.00 290,097.50 - - - - 1.00 290,097.50

2 A.5.1.1 5. Pemasangan 1 buah wastafel bh 696,960.00 1.00 696,960.00 - - - - 1.00 696,960.00 CCO

3 A.5.1.1 10. Pemasangan 1 buah bak air fibreglass vol 1 m3 bh 342,354.10 1.00 342,354.10 - - 1.00 342,354.10 - -

4 A.5.1.1 12. Pemasangan 1 buah bak cuci piring stainlessteel bh 267,093.75 1.00 267,093.75 - - - - 1.00 267,093.75

5 A.5.1.1 14. Pemasangan 1 buah floor drain bh 26,331.25 1.00 26,331.25 - - - - 1.00 26,331.25

6 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm bh 318,991.75 4.00 1,275,967.00 - - - - 4.00 1,275,967.00

7 A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4” m1 45,375.00 1.00 45,375.00 - - - - 1.00 45,375.00

8 A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” m1 14,250.50 32.00 456,016.00 - - - - 32.00 456,016.00

9 A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” m` 33,310.75 12.00 399,729.00 - - - - 12.00 399,729.00

10 A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4” m1 72,312.63 12.00 867,751.50 - - - - 12.00 867,751.50

JUMLAH VIII 4,667,675.10 - 342,354.10 4,325,321.00


IX PEKERJAAN BESI DAN ALUMUNIUM
1 Ls Pintu besi Folding Gate ( Terpasang ) m2 275,000.00 8.44 2,321,000.00 0.00 550.00 - - 8.44 2,321,550.00

JUMLAH IX 2,321,000.00 550.00 - 2,321,550.00


X PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh 25,185.60 27.00 680,011.20 - - - - 27.00 680,011.20

2 A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu bh 21,921.63 36.00 789,178.50 - - - - 36.00 789,178.50

3 A.4.6.2.9. Pemasangan 1 buah kait angin bh 25,641.00 36.00 923,076.00 - - - - 36.00 923,076.00

4 A.4.6.2.11. Pemasangan 1 buah kunci slot bh 97,083.25 15.00 1,456,248.75 - - - - 15.00 1,456,248.75

5 A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm bh 115,371.85 13.33 1,537,906.76 - - - - 13.33 1,537,906.76

6 Ditaksir Grendel pintu bh 10,000.00 29.00 290,000.00 - - - - 29.00 290,000.00

JUMLAH X 5,676,421.21 - - 5,676,421.21


XI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 199,798.50 117.00 23,376,424.50 - - 3.97 792,700.55 113.03 22,583,723.95 CCO

2 A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm m2 213,889.50 4.80 1,026,669.60 - - 2.30 492,480.57 2.50 534,189.03 CCO

3 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm m1 38,173.30 9.90 377,915.67 - - - - 9.90 377,915.67 CCO

4 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20cm x 20cm m2 204,226.00 14.85 3,032,756.10 - - - - 14.85 3,032,756.10

5 A.4.4.3.58. Pemasangan 1 m2 dinding batu tempel susun sirih m2 239,442.50 5.58 1,336,089.15 - - - - 5.58 1,336,089.15

JUMLAH XI 29,149,855.02 - 1,285,181.12 27,864,673.90


XII PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 17,222.98 610.28 10,510,837.18 18.72 322,414.09 - - 629.00 10,833,251.28

cat dasar, 2 lapis cat penutup )

2 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 13,132.90 147.91 1,942,487.24 - - - - 147.91 1,942,487.24

JUMLAH XII 12,453,324.42 322,414.09 - 12,775,738.51


XIII PEKERJAAN INSTALASI LISTRIK
1 Ls Pemasangan meter listrik 900 watt unit 750,000.00 1.00 750,000.00 - - - - 1.00 750,000.00

2 Ls Titik Lampu Titik 85,000.00 30.00 2,550,000.00 - - - - 30.00 2,550,000.00

3 Ls Saklar ganda bh 22,500.00 1.00 22,500.00 - - - - 1.00 22,500.00

4 Ls Saklar tunggal bh 20,000.00 10.00 200,000.00 - - - - 10.00 200,000.00

5 Ls stop kontak bh 22,500.00 8.00 180,000.00 - - - - 8.00 180,000.00

6 Ls lampu pijar 5W Philips bh 10,000.00 5.00 50,000.00 - - - - 5.00 50,000.00

7 Ls Lampu SL 18 Watt Phillips bh 35,500.00 17.00 603,500.00 - - - - 17.00 603,500.00

JUMLAH XIII 4,356,000.00 - - 4,356,000.00


XIV PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm termasuk pas dinding m1 75,500.00 45.50 3,435,250.00 - - - - 45.50 3,435,250.00

2 Ls Tanah Subur m3 120,000.00 0.43 51,600.00 - - 0.43 51,600.00 - -

3 Ls Pembuatan taman m2 225,000.00 0.71 159,750.00 - - 0.71 159,750.00 - -


4 Ls Membuat Septictank bh 1,150,000.00 1.00 1,150,000.00 - - - - 1.00 1,150,000.00

5 Ls Membuat Peresapan bh 750,000.00 1.00 750,000.00 - - - - 1.00 750,000.00

JUMLAH XIV 5,546,600.00 - 211,350.00 5,335,250.00

JUMLAH ( F ) 396,342,285.04 7,024,573.40 46,038,128.78 357,328,729.64


JUMLAH TOTAL 3,022,634,361.70 418,133,478.94 420,419,064.11 3,022,634,361.70
PPN 10 % 302,263,436.17 41,813,347.89 42,041,906.41 302,263,436.17
JUMLAH TOTAL 3,324,897,797.87 459,946,826.84 462,460,970.53 3,324,897,797.87
DIBULATKAN 3,324,897,000.00 459,946,000.00 462,460,000.00 3,324,897,000.00

KEBUMEN, 21 JULI 2016

PANITIA PENELITI PENYEDIA JASA :


PELAKSANAAN KONTRAK ( PPPK ) : PT. MULTI KARYA KEBUMEN
Mengetahui, Menyetujui,
Kepala Bidang Cipta Karya KaSi Bangunan Gedung Bidang Cipta Karya 1. AGUS HANAFI, SST. MT 1………………… 1. RAHMAT 1………………..
Dinas Pekerjaan Umum Kab.Kebumen Dinas Pekerjaan Umum Kab.Kebumen Ketua Direktur Utama
Selaku Pejabat Pembuat Komitmen Selaku Pejabat PelaksanaTeknis Kegiatan
2. FRESTIANA MANURUNG, S.Ars 2………………… 2. IKBALUDIN 2………………..
Sekretaris Pelaksana

3. DWI AMDI 3………………… KONSULTAN PENGAWAS :


Anggota CV. RUMAH KEONG
Ir. MISRODIN BACHTIAR ACHMAD, ST, M.Ec.Dev
NIP. 19610327 199403 1 001 NIP. 19770429 200604 1 004 4. TEGUH AHMAD SUMARSONO, ST 4………………… 1. TEGUH BUDIONO, ST 1………………..
Anggota Site Engeneer

5. SISWORO 5………………… 2. IRWAN SETIADI, ST 2………………..


Anggota Inspector
M12 (2)

LAPORAN MINGGUAN

KEGIATAN : PEMBANGUNAN GEDUNG KANTOR MINGGU KE : #REF!


PEKERJAAN : PEMBANGUNAN GEDUNG KANTOR KECAMATAN SRUWENG WAKTU : #REF!
LOKASI : KEC. SRUWENG, KEBUMEN RENCANA : #REF!
TAHUN ANGGARAN : 2017 PROGRES/DEVIASI : #REF! / #REF!

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)

A PAGAR DAN HALAMAN


I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls 500,000.00 1.00 500,000.00 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.2.2.1.15a. 1 M2 pasang paving blok segi 4, t = 8 cm m2 84,000.00 1,694.11 142,305,454.94 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH I 142,805,454.94 #REF! #REF! #REF! #REF!
II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 49,018.75 70.50 3,455,790.01 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 16,339.58 21.15 345,579.00 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 118,607.50 7.72 915,771.47 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 83,393.75 3,182.86 265,430,732.87 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
5 A.2.3.1.14. Pengurugan 1 m3 sirtu padat m3 136,193.75 119.20 16,234,295.00 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH II 286,382,168.35 #REF! #REF! #REF! #REF!
III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 #REF! 170.13 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 #REF! - #REF! #REF! #REF!
JUMLAH III #REF! #REF! #REF! #REF! #REF!
IV PEKERJAAN DINDING
1 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 97,798.25 116.37 11,380,953.50 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
campuran 1SP : 3PP
2 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 92,281.75 38.16 3,521,287.02 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
campuran 1SP : 6PP

3 A. 4.4.1.20. Pemasangan 1 cm2 dinding conblock HB10 campuran 1SP :3PP m2 103,248.53 287.55 29,688,650.18 #REF! #REF! #REF! 94.89 #REF! #REF! #REF! #REF!
JUMLAH IV 44,590,890.70 #REF! #REF! #REF! #REF!
V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 38,633.10 329.03 12,711,344.58 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.4.2.23. Pemasangan 1 m2 plesteran ciprat 1SP : 2PP m2 35,337.50 6.93 244,747.53 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.4.4.2.27. Pemasangan 1 m2 acian m2 23,815.00 329.03 7,835,785.15 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 Ls Sponengan m1 20,000.00 73.60 1,472,000.00 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH V 22,263,877.26 #REF! #REF! #REF! #REF!
VI PEKERJAAN BETON
1 Sloof 15/25
A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 166,529.00 40.97 6,823,026.19 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 933.00 12,182,913.83 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 4.80 4,261,648.45 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87

Page 146 of 297


M12 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
2 Foot Plat 80/80
A.4.1.1.20. Pemasangan 1 m2 bekisting untuk pondasi m2 154,429.00 13.44 2,075,525.76 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 250.30 3,268,360.54 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 2.02 1,790,635.46 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
3 Kolom 20/20
A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 31.02 7,824,857.04 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 197,116.70 36.52 7,198,701.88 #REF! - #REF! 36.52 #REF! 36.52 #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 403.94 5,274,585.98 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 8.37 7,436,253.26 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
4 Kolom 11/11
A.4.1.1.35 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 63,268.15 - - #REF! #REF!
5 Ring Balok 10/15
A.4.1.1.36 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 86,781.75 155.43 13,488,487.40 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
JUMLAH VI 71,624,995.79 #REF! #REF! #REF! #REF!
VII PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 145,153.25 3.99 579,161.47 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.4.3.58. Pemasangan 1 m2 dinding batu tempel candi m2 236,692.50 - - #REF! #REF!
JUMLAH VII 579,161.47 #REF! #REF! - #REF! #REF!
VIII PEKERJAAN BESI DAN ALUMUNIUM
1 Ditaksir Pintu besi terpasang dan pengecatan m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 Ditaksir Pagar besi terpasang dan pengecatan m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.4.2.1.1. Pemasangan 1 kg besi profil
4 Ditaksir Pasang kawat duri
5 LS Pasang Pagar dan Pintu Besi Ulir (Lengkap)
6 Ditaksir Pasang Grill Saluran
7 LS Pasang Roda Pintu dia. 2,5"
8 LS Gembok
9 LS Pembuatan Tiang Bendera
JUMLAH VIII #REF! #REF! #REF! #REF! #REF!
IX PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
cat dasar, 2 lapis cat penutup ) #REF!
JUMLAH IX #REF! #REF! #REF! #REF! #REF!
X PEKERJAAN INSTALASI LISTRIK
1 Ditaksir Titik Lampu ttk #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 Ditaksir Saklar Ganda bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 Ditaksir Pemasangan Lampu Taman bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH X #REF! #REF! #REF! #REF! #REF!
XI PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm, termasuk pasangan dinding m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 Ls Tanah subur m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 Ls Pembuatan taman m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 Ls Pasang logo keramik ( uk 35 x 45 ) cm bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 Ls Pasang tulisan ( bahan alumunium ) unit #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH XI #REF! #REF! #REF! #REF! #REF!
Page 147 of 297
M12 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
#REF! #REF! #REF! #REF! #REF!
B PEMBANGUNAN PENDOPO
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.2.2.1.15a. 1 M2 pasang paving blok segi 4, t = 8 cm ls #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH I #REF! #REF! #REF! #REF! #REF!
II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH II #REF! #REF! #REF! #REF! #REF!

Page 148 of 297


M12 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH III #REF! #REF! #REF! #REF! #REF!
IV PEKERJAAN DINDING
1 A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
campuran 1SP : 3PP
2 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
campuran 1SP : 3PP
3 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
campuran 1SP : 6PP
JUMLAH IV #REF! #REF! #REF! #REF! #REF!
V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
2 A.4.4.2.27. Pemasangan 1 m2 acian m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 Ls Sponengan m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH V #REF! #REF! #REF! #REF! #REF!
VI PEKERJAAN BETON
1 Lantai kerja
A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 -
2 Rabat Beton -
A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 -
3 Pondasi Foot Plat 80/80 -
A.4.1.1.20. Pemasangan 1 m2 bekisting untuk pondasi m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 -
4 Sloof 15/25 -
A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 -
5 Kolom 30/30 -
A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 -
6 Kolom 20/20 -
A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 -

Page 149 of 297


M12 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
7 Kolom 15/15 -
A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 -
8 Balok 20/35 -
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
9 Balok 15/20
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
10 Balok latai 15/20
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
11 Ring balok 15/20
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
12 Shading
A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
JUMLAH VI #REF! #REF! #REF! #REF! #REF!
VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
kayu kelas II (kruink ) #REF!
2 A.4.6.1.13.a Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas II (krui m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.4.6.1.15.a Pemasangan 1 m3 konstruksi gordeng expose , kayu kelas II ( kruin m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 A.4.6.1.17. Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
6 A.4.6.1.17.a Pemasangan 1 m2 rangka atap genteng beton expose , m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
kayu kelas II ( kruink ) #REF!
7 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) moti m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
8 A.4.5.2.3.a Pemasangan 1 m2 atap genteng palentong besar/super m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
9 A.4.5.2.6. Pemasangan 1 m’ bubung genteng palentong besar m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
10 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
11 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
ukuran (120x240x9) mm, tebal 9 mm #REF!

Page 150 of 297


M12 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
12 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
ukuran (120x240x9) mm, tebal 4 mm #REF!
13 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
14 Ls Pasang papan pembungkus kolom beton (2x30) cm, m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
kayu jati finishing politur #REF!
15 A.4.6.1.2. Membuat dan memasang rangka pagar, kayu kruink m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
16 A.4.6.1.10. Membuat dan memasang pagar, kayu kruink m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH VII #REF! #REF! #REF! #REF! #REF!
VIII PEKERJAAN BESI DAN ALUMUNIUM
1 A.4.2.1.18. Pemasangan 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH VIII #REF! #REF! #REF! #REF! #REF!
IX PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 Ditaksir Grendel pintu bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH IX #REF! #REF! #REF! #REF! #REF!
X PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.4.3.58. Pemasangan 1 m2 dinding natu tempel candi m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH X #REF! #REF! #REF! #REF! #REF!
XI PEKERJAAN PENGECATAN
1 A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
cat dasar, 2 lapis cat penutup)
2 A.4.7.1.7. Pelaburan 1 m2 bidang kayu dengan politur m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
cat dasar, 2 lapis cat penutup )
4 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH XI #REF! #REF! #REF! #REF! #REF!
XII PEKERJAAN INSTALASI LISTRIK
1 Ls Titik Lampu Titik #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 Ls Saklar ganda bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 Ls Stop Kontak bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 Ls MCB bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 Ls Lampu gantung artistik bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
6 Ls Lampu SL 18watt phillips bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH XII #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
XIII PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm termasuk pas dinding m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30 x 30 tinggi 35 c bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 Ditaksir Pasang logo keramik ( ukuran 35 x 45 ) cm unit #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 Ditaksir Pasang Tulisan ( bahan alumunium ) unit #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH XIII #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
C KANTOR PELAYANAN
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls 3,000,000.00 1.00 3,000,000.00 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH I 3,000,000.00 #REF! #REF! #REF! #REF!

Page 151 of 297


M12 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 14,027.66 6,189.00 86,817,162.41 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 799.33 7,493.71 5,989,946.66 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 82,255.51 149.60 12,305,424.30 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 855.69 58,957.91 50,449,698.12 #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH II 155,562,231.50 #REF! #REF! #REF! #REF!
III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH III #REF! #REF! #REF! #REF! #REF!
IV PEKERJAAN DINDING
1 A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
campuran 1SP : 3PP
2 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
campuran 1SP : 3PP
3 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
campuran 1SP : 6PP
JUMLAH IV #REF! #REF! #REF! #REF! #REF!
V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.4.2.27. Pemasangan 1 m2 acian m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 Ls Sponengan m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH V #REF! #REF! #REF! #REF! #REF!
VI PEKERJAAN BETON
1 Lantai kerja
A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
2 Rabat Beton
A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
3 Sloof 15/20
A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm,w/c=0,87
4 Kolom 30/30
A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm,w/c=0,87
5 Kolom 20/20
A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm,w/c=0,87
6 Kolom 15/15
A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!

Page 152 of 297


M12 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
7 Balok 15/40 #REF! #REF!
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
8 Ring balok 15/30
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
9 Ring balok 15/20
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
10 Balok Latai 10/15
A.4.1.1.36. Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
11 Plat atap
A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
12 Shading
A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
13 Plat lisplang
A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 #REF!
JUMLAH VI #REF! #REF! #REF! #REF! #REF!
VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.11. Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
kayu kelas II (kruink ) #REF!
3 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.4.6.1.17. Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) moti m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
6 A.4.5.2.3.a Pemasangan 1 m2 atap genteng palentong besar/super m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
7 A.4.5.2.6. Pemasangan 1 m’ bubung genteng palentong besar m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
8 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
9 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
ukuran (120x240x9) mm, tebal 9 mm #REF!

Page 153 of 297


M12 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
10 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
ukuran (120x240x9) mm, tebal 4 mm #REF!
11 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH VII #REF! #REF! #REF! #REF! #REF!
VIII PEKERJAAN SANITASI
1 A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.5.1.1 10. Pemasangan 1 buah bak air fibreglass vol 1 m3 bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.5.1.1 14. Pemasangan 1 buah floor drain bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4” m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
6 A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
7 A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” m` #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
8 A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4” m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
9 Ditaksir Fiber glas tangki air kap 1100 ltr bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH VIII #REF! #REF! #REF! #REF! #REF!
IX PEKERJAAN BESI DAN ALUMUNIUM
1 A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.2.1.13. Pemasangan 1 m2 pintu kaca rangka alluminium m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 Ls Pemasangan pintu tempered t = 12 mm ( komplit ) unit #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH IX #REF! #REF! #REF! #REF! #REF!
X PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.4.6.2.9. Pemasangan 1 buah kait angin bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.4.6.2.11. Pemasangan 1 buah kunci slot bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
6 Ditaksir Grendel pintu bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH X #REF! #REF! #REF! #REF! #REF!
XI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20cm x 20cm m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 A.4.4.3.58. Pemasangan 1 m2 dinding batu tempel candi m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH XI #REF! #REF! #REF! #REF! #REF!
XII PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
cat dasar, 2 lapis cat penutup )
2 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH XII #REF! #REF! #REF! #REF! #REF!
XIII PEKERJAAN INSTALASI LISTRIK
1 Ls Pemasangan meter listrik lama 5500 watt unit #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 Ls Titik Lampu Titik #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 Ls Saklar ganda bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 Ls Saklar tunggal bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 Ls stop kontak bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!

Page 154 of 297


M12 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
6 Ls lampu pijar 5W Philips bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
7 Ls Lampu SL 18 Watt Phillips bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH XIII #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
XIV PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm termasuk pas dinding m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.5.1.1 15. Membuat Septic Tank bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 Ditaksir Membuat peresapan bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 Ditaksir Tanah Subur m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 Ditaksir Pembuatan taman m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH XIV #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
D SERBA GUNA
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH I #REF! #REF! #REF! #REF! #REF!
II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH II #REF! #REF! #REF! #REF! #REF!
III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH III #REF! #REF! #REF! #REF! #REF!
IV PEKERJAAN DINDING
1 A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
campuran 1SP : 3PP
2 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
campuran 1SP : 3PP
3 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
campuran 1SP : 6PP #REF!
JUMLAH IV #REF! #REF! #REF! #REF! #REF!
V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.4.2.23. Pemasangan 1 m2 plesteran ciprat 1SP : 2PP m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.4.2.27. Pemasangan 1 m2 acian m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 Ls Sponengan m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH V #REF! #REF! #REF! #REF! #REF! #REF!
VI PEKERJAAN BETON #REF!
1 Lantai kerja #REF!
A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
2 Rabat Beton
A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 #REF!

Page 155 of 297


M12 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
3 Sloof 15/25 #REF!
A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm,w/c=0,87
4 Kolom 20/20
A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm,w/c=0,87
5 Kolom 15/15
A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
6 Ring balok 15/30 #REF!
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
7 Ring balok 15/20
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
8 Balok Latai 10/15
A.4.1.1.36. Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
9 Plat atap
A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
10 Shading
A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
JUMLAH VI #REF! #REF! #REF! #REF! #REF!
VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.11. Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
kayu kelas II (kruink )
3 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.4.6.1.16. Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) moti m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
6 A.4.5.2.1. Pemasangan 1 m2 atap genteng palentong kecil m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
7 A.4.5.2.4. Pemasangan 1 m’ bubung genteng palentong m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
8 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
9 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
ukuran (120x240x9) mm, tebal 9 mm

Page 156 of 297


M12 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
10 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
ukuran (120x240x9) mm, tebal 4 mm
11 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH VII #REF! #REF! #REF! #REF! #REF!
VIII PEKERJAAN SANITASI
1 A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.5.1.1 10. Pemasangan 1 buah bak air fibreglass vol 1 m3 bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.5.1.1 14. Pemasangan 1 buah floor drain bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4” m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
6 A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
7 A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” m` #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
8 A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4” m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH VIII #REF! #REF! #REF! #REF! #REF!
IX PEKERJAAN BESI DAN ALUMUNIUM
1 A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.2.1.13. Pemasangan 1 m2 pintu kaca rangka alluminium m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH IX #REF! #REF! #REF! #REF! #REF!
X PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.4.6.2.9. Pemasangan 1 buah kait angin bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.4.6.2.11. Pemasangan 1 buah kunci slot bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
6 Ditaksir Grendel pintu bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH X #REF! #REF! #REF! #REF! #REF!
XI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20cm x 20cm m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH XI #REF! #REF! #REF! #REF! #REF!
XII PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
cat dasar, 2 lapis cat penutup )
2 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH XII #REF! #REF! #REF! #REF! #REF!
XIII PEKERJAAN INSTALASI LISTRIK
1 Ls Titik Lampu Titik #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 Ls Saklar ganda bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 Ls Saklar tunggal bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 Ls stop kontak bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 Ls lampu pijar 5W Philips bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
6 Ls Lampu SL 18 Watt Phillips bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH XIII #REF! #REF! #REF! #REF! #REF!

Page 157 of 297


M12 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
XIV PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm termasuk pas dinding m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 Ls Membuat Septic Tank bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 Ls Membuat peresapan bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 Ls Tanah Subur m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 Ls Pembuatan taman m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH XIV #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
E MUSHOLLA
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH I #REF! #REF! #REF! #REF! #REF!
II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH II #REF! #REF! #REF! #REF! #REF!
III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH III #REF! #REF! #REF! #REF! #REF!
IV PEKERJAAN DINDING
1 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
campuran 1SP : 3PP
2 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
campuran 1SP : 6PP
3 Ls Pemasangan main dinding GRC m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH IV #REF! #REF! #REF! #REF! #REF!
V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.4.2.27. Pemasangan 1 m2 acian m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH V #REF! #REF! #REF! #REF! #REF!
VI PEKERJAAN BETON
1 Lantai kerja
A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
2 Rabat Beton
A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
3 Sloof 15/25
A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm,w/c=0,87
4 Kolom 15/15
A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!

Page 158 of 297


M12 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
5 Balok 15/30
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
6 Ring balok 15/20
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
7 Balok Latai 10/15
A.4.1.1.36. Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
8 Plat atap
A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
9 Shading
A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
JUMLAH VI #REF! #REF! #REF! #REF! #REF!
VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
kayu kelas II (kruink ) #REF!
2 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.4.6.1.16. Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) moti m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 A.4.5.2.1. Pemasangan 1 m2 atap genteng palentong kecil m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
6 A.4.5.2.4. Pemasangan 1 m’ bubung genteng palentong m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
7 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
8 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
ukuran (120x240x9) mm, tebal 9 mm
9 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
ukuran (120x240x9) mm, tebal 4 mm
10 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH VII #REF! #REF! #REF! #REF! #REF!
VIII PEKERJAAN SANITASI
1 A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.5.1.1 10. Pemasangan 1 buah bak air fibreglass vol 1 m3 bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.5.1.1 14. Pemasangan 1 buah floor drain bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4” m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
6 A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
7 A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” m` #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
8 A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4” m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH VIII #REF! #REF! #REF! #REF! #REF!
Page 159 of 297
M12 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
IX PEKERJAAN BESI DAN ALUMUNIUM
1 A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.2.1.12. Pemasangan 1 m2 pintu alluminium strip lebar 8 cm m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.4.2.1.13. Pemasangan 1 m2 pintu kaca rangka alluminium m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.4.2.1.13. Pemasangan 1 m2 pintu kaca rangka alluminium m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 Ls Pemasangan kubah bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH IX #REF! #REF! #REF! #REF! #REF!
X PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.4.6.2.9. Pemasangan 1 buah kait angin bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.4.6.2.11. Pemasangan 1 buah kunci slot bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
6 Ditaksir Grendel pintu bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH X #REF! #REF! #REF! #REF! #REF!
XI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20cm x 20cm m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH XI #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
XII PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
cat dasar, 2 lapis cat penutup )
2 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH XII #REF! #REF! #REF! #REF! #REF!
XIII PEKERJAAN INSTALASI LISTRIK
1 Ls Pemasangan meter listrik 900 watt unit #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 Ls Titik Lampu Titik #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 Ls Saklar ganda bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 Ls Saklar tunggal bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 Ls stop kontak bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
6 Ls lampu pijar 5W Philips bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
7 Ls Lampu SL 18 Watt Phillips bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH XIII #REF! #REF! #REF! #REF! #REF!
XIV PEKERJAAN LAIN-LAIN
2 Ls Membuat Septic Tank bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 Ls Membuat peresapan bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 Ls Tanah Subur m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 Ls Pembuatan taman m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH XIV #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
F RUMAH DINAS
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH I #REF! #REF! #REF! #REF! #REF!

Page 160 of 297


M12 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH II #REF! #REF! #REF! #REF! #REF!
III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH III #REF! #REF! #REF! #REF! #REF!
IV PEKERJAAN DINDING
1 A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
campuran 1SP : 3PP
2 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
campuran 1SP : 3PP
3 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
campuran 1SP : 6PP
JUMLAH IV #REF! #REF! #REF! #REF! #REF!
V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.4.2.27. Pemasangan 1 m2 acian m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH V #REF! #REF! #REF! #REF! #REF!
VI PEKERJAAN BETON
1 Lantai kerja
A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
2 Rabat Beton
A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
3 Sloof 15/25
A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm,w/c=0,87
4 Kolom 15/25
A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm,w/c=0,87
5 Kolom 15/15
A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
6 Ring balok 15/30
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87

Page 161 of 297


M12 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
7 Ring balok 15/20
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
8 Balok Latai 10/15
A.4.1.1.36. Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
9 Plat atap
A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
10 Shading
A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
11 Meja dapur
A.4.1.1.33. Membuat 1 m3 dinding beton bertulang (150 kg besi + bekisting) m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
JUMLAH VI #REF! #REF! #REF! #REF! #REF!
VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.2. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kaym3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.6.1.5. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I atam2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.4.6.1.6. Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelasm2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
kayu kelas II (kruink )
5 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
6 A.4.6.1.16. Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
7 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) moti m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
8 A.4.5.2.1. Pemasangan 1 m2 atap genteng palentong kecil m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
9 A.4.5.2.4. Pemasangan 1 m’ bubung genteng palentong m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
10 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
11 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
ukuran (120x240x9) mm, tebal 9 mm
12 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
ukuran (120x240x9) mm, tebal 4 mm
13 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
14 Ls Pemasangan rooster kayu bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH VII #REF! #REF! #REF! #REF! #REF!
VIII PEKERJAAN SANITASI
1 A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.5.1.1 5. Pemasangan 1 buah wastafel bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.5.1.1 10. Pemasangan 1 buah bak air fibreglass vol 1 m3 bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.5.1.1 12. Pemasangan 1 buah bak cuci piring stainlessteel bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!

Page 162 of 297


M12 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
5 A.5.1.1 14. Pemasangan 1 buah floor drain bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
6 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
7 A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4” m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
8 A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
9 A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” m` #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
10 A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4” m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH VIII #REF! #REF! #REF! #REF! #REF! #REF! #REF!
IX PEKERJAAN BESI DAN ALUMUNIUM
5 Ls Pintu besi Folding Gate ( Terpasang ) m2 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
JUMLAH IX #REF! #REF! #REF! #REF! #REF!
X PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.4.6.2.9. Pemasangan 1 buah kait angin bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.4.6.2.11. Pemasangan 1 buah kunci slot bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
6 Ditaksir Grendel pintu bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH X #REF! #REF! #REF! #REF! #REF!
XI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20cm x 20cm m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 A.4.4.3.58. Pemasangan 1 m2 dinding batu tempel susun sirih m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH XI #REF! #REF! #REF! #REF! #REF!
XII PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
cat dasar, 2 lapis cat penutup )
2 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH XII #REF! #REF! #REF! #REF! #REF!
XIII PEKERJAAN INSTALASI LISTRIK
1 Ls Pemasangan meter listrik 900 watt unit #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 Ls Titik Lampu Titik #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 Ls Saklar ganda bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
4 Ls Saklar tunggal bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 Ls stop kontak bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
6 Ls lampu pijar 5W Philips bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
7 Ls Lampu SL 18 Watt Phillips bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH XIII #REF! #REF! #REF! #REF! #REF!
XIV PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm termasuk pas dinding m1 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
2 Ls Tanah Subur m3 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
3 Ls Pembuatan taman m2 #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!

Page 163 of 297


M12 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
4 Ls Membuat Septictank bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
5 Ls Membuat Peresapan bh #REF! #REF! #REF! #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH XIV #REF! #REF! #REF! - #REF! #REF! #REF! #REF!
JUMLAH ( F ) #REF! #REF! #REF! #REF! #REF!
JUMLAH TOTAL #REF! #REF! #REF! #REF! #REF!
PPN 10 % #REF!
JUMLAH TOTAL #REF!
DIBULATKAN #REF!

Menyetujui,
KaSi Bangunan Gedung Bidang Cipta Karya
Dinas Pekerjaan Umum Kab.Kebumen
Selaku Pejabat PelaksanaTeknis Kegiatan

BACHTIAR ACHMAD, ST, M.Ec.Dev


NIP. 19770429 200604 1 004

Page 164 of 297


DAFTAR PERHITUNGAN CONTRACK CHANGE ORDER ( CCO.2 )

KEGIATAN : PEMBANGUNAN GEDUNG KANTOR NOMOR KONTRAK : 050 / 099 / SP / VI / 2017


PEKERJAAN : PEMBANGUNAN GEDUNG KANTOR KECAMATAN SRUWENG 027 / PT.MKK / SP / VI / 2017
LOKASI : KEC. SRUWENG, KEBUMEN TANGGAL KONTRAK : 19 JUNI 2016
TAHUN ANGGARAN : 2017 NILAI KONTRAK : Rp. 3.324.897.000, -
PENYEDIA JASA : PT. MULTI KARYA KEBUMEN

CCO.1 CCO.2
SELISIH TAMBAH SELISIH KURANG
HARGA
NO KODE ANALISA JENIS PEKERJAAN SAT SATUAN JUMLAH JUMLAH JUMLAH JUMLAH KET
( Rp ) VOLUME HARGA VOLUME HARGA VOLUME HARGA VOLUME HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp )

A PAGAR DAN HALAMAN


I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls 500,000.00 1.00 500,000.00 - - - - 1.00 500,000.00

2 A.2.2.1.15a. 1 M2 pasang paving blok segi 4, t = 8 cm m2 84,000.00 1,694.11 142,305,454.94 - - 1,694.11 142,305,454.94 - -

3 A.2.2.1.15b. 1 M2 pasang paving blok segi 4, t = 6 cm m2 79,000.00 - - 1,714.50 135,445,752.80 - - 1,714.50 135,445,752.80

JUMLAH I 142,805,454.94 135,445,752.80 142,305,454.94 135,945,752.80


II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 49,018.75 70.50 3,455,790.01 0.65 31,857.29 - - 71.15 3,487,647.30

2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 16,339.58 21.15 345,579.00 0.19 3,185.73 - - 21.34 348,764.73

3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 118,607.50 7.72 915,771.47 - - 0.09 10,766.60 7.63 905,004.88

4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 83,393.75 3,182.86 265,430,732.87 1,239.02 103,326,470.64 - - 4,421.88 368,757,203.50

5 A.2.3.1.14. Pengurugan 1 m3 sirtu padat m3 136,193.75 119.20 16,234,295.00 - - 119.20 16,234,295.00 - -

JUMLAH II 286,382,168.35 103,361,513.65 16,245,061.60 373,498,620.41


III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 516,466.50 170.13 87,864,199.02 4.67 2,410,529.92 - - 174.79 90,274,728.93

2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 279,576.00 - - - - - - - -

JUMLAH III 87,864,199.02 2,410,529.92 - 90,274,728.93


IV PEKERJAAN DINDING
1 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 97,798.25 116.37 11,380,953.50 - - 74.16 7,252,889.37 42.21 4,128,064.13

campuran 1SP : 3PP

2 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 92,281.75 38.16 3,521,287.02 28.95 2,671,279.82 - - 67.11 6,192,566.83

campuran 1SP : 6PP

3 A. 4.4.1.20. Pemasangan 1 cm2 dinding conblock HB10 campuran 1SP :3PP m2 103,248.53 287.55 29,688,650.18 - - 19.94 2,059,085.43 267.60 27,629,564.75
JUMLAH IV 44,590,890.70 2,671,279.82 9,311,974.80 37,950,195.72
V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 38,633.10 329.03 12,711,344.58 - - 86.46 3,340,206.24 242.57 9,371,138.35

2 A.4.4.2.23. Pemasangan 1 m2 plesteran ciprat 1SP : 2PP m2 35,337.50 6.93 244,747.53 - - 2.11 74,512.65 4.82 170,234.87

3 A.4.4.2.27. Pemasangan 1 m2 acian m2 23,815.00 329.03 7,835,785.15 - - 86.46 2,059,037.76 242.57 5,776,747.39

4 Ls Sponengan m1 20,000.00 73.60 1,472,000.00 - - - - 73.60 1,472,000.00

JUMLAH V 22,263,877.26 - 5,473,756.64 16,790,120.61


VI PEKERJAAN BETON
1 Rabat Beton

A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 756,474.46 - - 6.83 5,169,273.68 - - 6.83 5,169,273.68

slump (12 ± 2) cm, w/c = 0,87

2 Sloof 15/25

A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 166,529.00 40.97 6,823,026.19 - - 0.02 3,663.64 40.95 6,819,362.55

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 933.00 12,182,913.83 - - 57.49 750,722.75 875.51 11,432,191.08

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 4.80 4,261,648.45 - - 0.00 2,067.76 4.80 4,259,580.69

slump (12 ± 2) cm, w/c = 0,87

3 Foot Plat 80/80

A.4.1.1.20. Pemasangan 1 m2 bekisting untuk pondasi m2 154,429.00 13.44 2,075,525.76 - - - - 13.44 2,075,525.76

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 250.30 3,268,360.54 - - - - 250.30 3,268,360.54

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 2.02 1,790,635.46 - - - - 2.02 1,790,635.46

slump (12 ± 2) cm, w/c = 0,87

4 Kolom 20/20

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 31.02 7,824,857.04 - - - - 31.02 7,824,857.04

A.4.1.1.22.b Pemasangan 1 m2 bekisting untuk kolom m2 197,116.70 36.52 7,198,701.88 - - 12.82 2,527,036.09 23.70 4,671,665.79

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 403.94 5,274,585.98 - - 14.39 187,842.66 389.56 5,086,743.32

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 8.37 7,436,253.26 - - - - 8.37 7,436,253.26

slump (12 ± 2) cm, w/c = 0,87

5 Kolom 11/11

A.4.1.1.35 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 63,268.15 - - 6.75 427,060.01 - - 6.75 427,060.01

6 Ring Balok 10/15

A.4.1.1.36 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 86,781.75 155.43 13,488,487.40 50.47 4,379,874.92 - - 205.90 17,868,362.33

JUMLAH VI 71,624,995.79 9,976,208.62 3,471,332.90 78,129,871.51


VII PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 145,153.25 3.99 579,161.47 - - 0.67 97,920.38 3.32 481,241.09

2 A.4.4.3.58. Pemasangan 1 m2 dinding batu tempel candi m2 236,692.50 - - - - - - - -

JUMLAH VII 579,161.47 - 97,920.38 481,241.09


VIII PEKERJAAN BESI DAN ALUMUNIUM
1 Ditaksir Pintu besi terpasang dan pengecatan m2 400,000.00 - - - - - - - -
2 Ditaksir Pagar besi terpasang dan pengecatan m2 350,000.00 - - - - - - - -

3 A.4.2.1.1. Pemasangan 1 kg besi profil kg 30,843.01 - - - - - - - -

4 Ditaksir Pasang kawat duri m1 10,000.00 - - - - - - - -

5 LS Pasang Pagar dan Pintu Besi Ulir (Lengkap) m2 455,000.00 54.35 24,729,705.00 7.67 3,488,940.00 - - 62.02 28,218,645.00

6 Ditaksir Pasang Grill Saluran m' 180,000.00 19.90 3,582,000.00 3.80 684,000.00 - - 23.70 4,266,000.00

7 LS Pasang Roda Pintu dia. 2,5" bh 50,000.00 6.00 300,000.00 - - 6.00 300,000.00 - -

8 LS Gembok bh 25,000.00 1.00 25,000.00 - - 1.00 25,000.00 - -

9 LS Pembuatan Tiang Bendera bh 2,500,000.00 1.00 2,500,000.00 - - - - 1.00 2,500,000.00

JUMLAH VIII 31,136,705.00 4,172,940.00 325,000.00 34,984,645.00


IX PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 17,222.98 329.03 5,666,828.96 - - 86.46 1,489,093.25 242.57 4,177,735.71

cat dasar, 2 lapis cat penutup )

2 A.4.7.1.10. Pengecatan permukaan baja (galbani) secara semprot dengan m2 82,832.60 58.33 4,831,708.39 - - 58.33 4,831,708.39 - -

sistem 1 lapis cat mutakhir dengan tebal 200 um

JUMLAH IX 10,498,537.35 - 6,320,801.64 4,177,735.71


X PEKERJAAN INSTALASI LISTRIK
1 Ditaksir Titik Lampu ttk 85,000.00 - - - - - - - -

2 Ditaksir Saklar Ganda bh 22,500.00 - - - - - - - -

3 Ditaksir Pemasangan Lampu Taman bh 525,000.00 - - - - - - - -

JUMLAH X - - - -
XI PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm, termasuk pasangan dinding m1 75,500.00 53.20 4,016,600.00 165.80 12,517,900.00 - - 219.00 16,534,500.00

2 Ls Tanah subur m3 120,000.00 278.72 33,446,559.00 - - 272.29 32,674,719.00 6.43 771,840.00

3 Ls Pembuatan taman m2 225,000.00 123.06 27,688,127.34 - - 106.98 24,070,127.34 16.08 3,618,000.00

4 Ls Pasang logo keramik ( uk 35 x 45 ) cm bh 750,000.00 1.00 750,000.00 - - - - 1.00 750,000.00

5 Ls Pasang tulisan ( bahan alumunium ) unit 3,500,000.00 1.00 3,500,000.00 - - - - 1.00 3,500,000.00

6 Ditaksir Pasang gorong gorong dia.100 m' 350,000.00 - - 17.00 5,950,000.00 - - 17.00 5,950,000.00

7 Ditaksir Pasang atap galvalume m2 450,000.00 - - 66.39 29,874,375.00 - - 66.39 29,874,375.00

JUMLAH XI 69,401,286.34 48,342,275.00 56,744,846.34 60,998,715.00

767,147,276.22 306,380,499.80 240,296,149.25 833,231,626.77

B PEMBANGUNAN PENDOPO
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls 500,000.00 1.00 500,000.00 - - - - 1.00 500,000.00

2 A.2.2.1.15a. 1 M2 pasang paving blok segi 4, t = 8 cm ls 84,000.00 190.00 15,960,000.00 - - 190.00 15,960,000.00 - -

JUMLAH I 16,460,000.00 - 15,960,000.00 500,000.00


II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 49,018.75 40.20 1,970,553.75 - - 0.00 196.07 40.20 1,970,357.68

2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 16,339.58 12.06 197,055.38 - - 0.00 19.61 12.06 197,035.77

3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 118,607.50 35.16 4,170,239.70 - - - - 35.16 4,170,239.70

4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 83,393.75 145.38 12,123,783.38 - - 28.14 2,346,718.00 117.24 9,777,065.37

JUMLAH II 18,461,632.20 - 2,346,933.69 16,114,698.51


III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 516,466.50 26.95 13,918,772.18 - - - - 26.95 13,918,772.18

2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 279,576.00 14.00 3,914,064.00 - - - - 14.00 3,914,064.00

JUMLAH III 17,832,836.18 - - 17,832,836.18


IV PEKERJAAN DINDING
1 A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 201,619.00 5.70 1,149,228.30 - - - - 5.70 1,149,228.30

campuran 1SP : 3PP

2 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 97,798.25 28.82 2,818,545.57 - - - - 28.82 2,818,545.57

campuran 1SP : 3PP

3 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 92,281.75 125.07 11,541,678.47 - - - - 125.07 11,541,678.47

campuran 1SP : 6PP

JUMLAH IV 15,509,452.34 - - 15,509,452.34


V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 38,633.10 314.35 12,144,314.99 - - - - 314.35 12,144,314.99

2 A.4.4.2.27. Pemasangan 1 m2 acian m2 23,815.00 658.24 15,675,985.60 - - - - 658.24 15,675,985.60

3 Ls Sponengan m1 20,000.00 295.40 5,908,000.00 - - - - 295.40 5,908,000.00

JUMLAH V 33,728,300.59 - - 33,728,300.59


VI PEKERJAAN BETON
1 Lantai kerja

A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 712,475.42 22.38 15,945,199.93 0.40 284,990.17 - - 22.78 16,230,190.10

slump (12 ± 2) cm, w/c = 0,87

2 Rabat Beton

A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 756,474.46 5.86 4,432,940.35 0.26 198,120.66 - - 6.12 4,631,061.01

slump (12 ± 2) cm, w/c = 0,87

3 Pondasi Foot Plat 80/80

A.4.1.1.20. Pemasangan 1 m2 bekisting untuk pondasi m2 154,429.00 4.48 691,841.92 1.28 197,669.12 - - 5.76 889,511.04

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 285.61 3,729,445.40 155.05 2,024,615.77 - - 440.66 5,754,061.16

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 2.06 1,829,716.79 0.59 524,045.10 - - 2.65 2,353,761.89

slump (12 ± 2) cm, w/c = 0,87


4 Sloof 15/25

A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 166,529.00 21.60 3,597,026.40 - - - - 21.60 3,597,026.40

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 478.22 6,244,513.07 - - - - 478.22 6,244,513.07

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 3.24 2,877,806.99 - - - - 3.24 2,877,806.99

slump (12 ± 2) cm, w/c = 0,87

5 Kolom 30/30

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 23.40 5,902,696.80 - - - - 23.40 5,902,696.80

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 625.83 8,171,978.62 - - 226.21 2,953,810.59 399.62 5,218,168.03

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 3.51 3,117,624.24 - - - - 3.51 3,117,624.24

slump (12 ± 2) cm, w/c = 0,87

6 Kolom 20/20

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 54.68 13,793,139.36 - - 2.00 504,504.00 52.68 13,288,635.36

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 768.44 10,034,155.04 - - 35.69 466,012.88 732.75 9,568,142.16

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 5.47 4,858,519.83 - - 0.20 179,418.83 5.27 4,679,101.00

slump (12 ± 2) cm, w/c = 0,87

7 Kolom 15/15

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 2.00 504,504.00 - - 0.05 12,612.60 1.95 491,891.40

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 17.16 224,072.28 39.42 514,739.46 - - 56.58 738,811.74

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 0.09 79,939.08 0.20 177,642.41 - - 0.29 257,581.49

slump (12 ± 2) cm, w/c = 0,87

8 Balok 20/35

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 64.80 16,517,001.60 - - - - 64.80 16,517,001.60

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 1,070.64 13,980,229.76 - - - - 1,070.64 13,980,229.76

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 10.08 8,953,177.31 - - - - 10.08 8,953,177.31

slump (12 ± 2) cm, w/c = 0,87

9 Balok 15/20

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 11.40 2,905,768.80 - - - - 11.40 2,905,768.80

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 252.40 3,295,795.03 - - - - 252.40 3,295,795.03

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 1.71 1,518,842.58 - - - - 1.71 1,518,842.58

slump (12 ± 2) cm, w/c = 0,87

10 Balok latai 15/20

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 3.20 815,654.40 - - - - 3.20 815,654.40

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 70.89 925,669.21 - - - - 70.89 925,669.21

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 0.48 426,341.78 - - - - 0.48 426,341.78

slump (12 ± 2) cm, w/c = 0,87


11 Ring balok 15/20

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 16.50 4,205,718.00 - - - - 16.50 4,205,718.00

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 365.31 4,770,154.05 - - - - 365.31 4,770,154.05

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 2.48 2,202,765.85 - - - - 2.48 2,202,765.85

slump (12 ± 2) cm, w/c = 0,87

12 Shading

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 319,352.00 1.50 479,028.00 - - - - 1.50 479,028.00

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 18.24 238,174.73 - - 0.61 7,965.27 17.63 230,209.45

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 0.02 17,764.24 0.22 195,406.65 - - 0.24 213,170.89

slump (12 ± 2) cm, w/c = 0,87

JUMLAH VI 147,287,205.43 4,117,229.33 4,124,324.18 147,280,110.59


VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 9,944,550.00 0.42 4,176,711.00 - - - - 0.42 4,176,711.00

kayu kelas II (kruink )

2 A.4.6.1.13.a Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas II (kruink m3 10,071,050.00 0.85 8,560,392.50 - - - - 0.85 8,560,392.50

3 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 10,651,671.25 0.48 5,112,802.20 - - - - 0.48 5,112,802.20

4 A.4.6.1.15.a Pemasangan 1 m3 konstruksi gordeng expose , kayu kelas II ( kruink ) m3 10,778,171.25 3.19 34,382,366.29 - - - - 3.19 34,382,366.29

5 A.4.6.1.17. Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II m2 153,051.25 33.00 5,050,691.25 - - - - 33.00 5,050,691.25

6 A.4.6.1.17.a Pemasangan 1 m2 rangka atap genteng beton expose , m2 178,351.25 410.50 73,213,188.13 - - - - 410.50 73,213,188.13

kayu kelas II ( kruink )

7 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) motif k m1 22,500.00 141.60 3,186,000.00 0.40 9,000.00 - - 142.00 3,195,000.00

8 A.4.5.2.3.a Pemasangan 1 m2 atap genteng palentong besar/super m2 59,793.25 443.50 26,518,306.38 - - - - 443.50 26,518,306.38

9 A.4.5.2.6. Pemasangan 1 m’ bubung genteng palentong besar m1 63,189.50 61.70 3,898,792.15 - - - - 61.70 3,898,792.15

10 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 77,038.50 22.50 1,733,366.25 5.40 416,007.90 - - 27.90 2,149,374.15

11 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 34,538.90 22.50 777,125.25 5.40 186,510.06 - - 27.90 963,635.31

ukuran (120x240x9) mm, tebal 9 mm

12 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 32,937.30 410.50 13,520,761.65 - - - - 410.50 13,520,761.65

ukuran (120x240x9) mm, tebal 4 mm

13 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 19,049.25 19.00 361,935.75 - - - - 19.00 361,935.75

14 Ls Pasang papan pembungkus kolom beton (2x30) cm, m2 325,000.00 28.32 9,204,000.00 - - - - 28.32 9,204,000.00

kayu jati finishing politur

15 A.4.6.1.2. Membuat dan memasang rangka pagar, kayu kruink m3 10,925,172.50 0.68 7,429,117.30 - - - - 0.68 7,429,117.30

16 A.4.6.1.10. Membuat dan memasang pagar, kayu kruink m2 667,975.00 27.65 18,469,508.75 - - - - 27.65 18,469,508.75

JUMLAH VII 215,595,064.84 611,517.96 - 216,206,582.80


VIII PEKERJAAN BESI DAN ALUMUNIUM
1 A.4.2.1.18. Pemasangan 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm m1 103,541.63 10.00 1,035,416.25 - - - - 10.00 1,035,416.25
JUMLAH VIII 1,035,416.25 - - 1,035,416.25
IX PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh 25,185.60 12.00 302,227.20 - - - - 12.00 302,227.20

2 Ditaksir Grendel pintu bh 10,000.00 6.00 60,000.00 - - - - 6.00 60,000.00

JUMLAH IX 362,227.20 - - 362,227.20


X PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 145,153.25 276.82 40,181,322.67 - - - - 276.82 40,181,322.67

2 A.4.4.3.58. Pemasangan 1 m2 dinding natu tempel candi m2 239,442.50 30.15 7,219,191.38 - - 1.35 323,247.38 28.80 6,895,944.00

JUMLAH X 47,400,514.04 - 323,247.38 47,077,266.67


XI PEKERJAAN PENGECATAN
1 A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis m2 44,480.15 538.81 23,966,349.62 - - - - 538.81 23,966,349.62

cat dasar, 2 lapis cat penutup)

2 A.4.7.1.7. Pelaburan 1 m2 bidang kayu dengan politur m2 49,024.25 100.17 4,910,759.12 - - - - 100.17 4,910,759.12

3 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 17,222.98 658.24 11,336,851.06 - - - - 658.24 11,336,851.06

cat dasar, 2 lapis cat penutup )

4 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 13,132.90 433.00 5,686,545.70 5.40 70,917.66 - - 438.40 5,757,463.36

JUMLAH XI 45,900,505.51 70,917.66 - 45,971,423.17


XII PEKERJAAN INSTALASI LISTRIK
1 Ls Titik Lampu Titik 85,000.00 13.00 1,105,000.00 - - - - 13.00 1,105,000.00

2 Ls Saklar ganda bh 22,500.00 6.00 135,000.00 - - - - 6.00 135,000.00

3 Ls Stop Kontak bh 22,500.00 2.00 45,000.00 - - - - 2.00 45,000.00

4 Ls MCB bh 250,000.00 1.00 250,000.00 - - - - 1.00 250,000.00

5 Ls Lampu gantung artistik bh 1,750,000.00 1.00 1,750,000.00 - - - - 1.00 1,750,000.00

6 Ls Lampu SL 18 watt phillips bh 35,500.00 11.00 390,500.00 - - - - 11.00 390,500.00

JUMLAH XII 3,675,500.00 - - 3,675,500.00


XIII PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm termasuk pas dinding m1 75,500.00 80.00 6,040,000.00 - - 30.40 2,295,200.00 49.60 3,744,800.00

2 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30 x 30 tinggi 35 cm bh 318,991.75 4.00 1,275,967.00 - - 4.00 1,275,967.00 - -

3 Ditaksir Pasang logo keramik ( ukuran 35 x 45 ) cm unit 750,000.00 1.00 750,000.00 - - - - 1.00 750,000.00

4 Ditaksir Pasang Tulisan ( bahan alumunium ) unit 2,250,000.00 1.00 2,250,000.00 - - - - 1.00 2,250,000.00

5 Ditaksir Pasang papan back ground unit 3,500,000.00 - - 1.00 3,500,000.00 - - 1.00 3,500,000.00

JUMLAH XIII 10,315,967.00 3,500,000.00 3,571,167.00 10,244,800.00

573,564,621.57 8,299,664.95 26,325,672.24 555,538,614.28

C KANTOR PELAYANAN
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls 500,000.00 1.00 500,000.00 - - - - 1.00 500,000.00
JUMLAH I 500,000.00 - - 500,000.00
II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 49,018.75 62.24 3,050,927.00 4.47 219,015.78 - - 66.71 3,269,942.78

2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 16,339.58 18.67 305,092.70 - - - - 18.67 305,092.70

3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 118,607.50 25.98 3,081,660.07 0.24 28,661.50 - - 26.22 3,110,321.57

4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 83,393.75 109.21 9,107,598.23 - - 42.12 3,512,386.30 67.09 5,595,211.92

JUMLAH II 15,545,277.99 247,677.28 3,512,386.30 12,280,568.97


III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 516,466.50 89.00 45,967,455.25 4.26 2,201,438.46 - - 93.27 48,168,893.71

2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 279,576.00 31.12 8,700,405.12 - - - - 31.12 8,700,405.12

JUMLAH III 54,667,860.37 2,201,438.46 - 56,869,298.83


IV PEKERJAAN DINDING
1 A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 201,619.00 - - - - - - - -

campuran 1SP : 3PP

2 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 97,798.25 81.20 7,941,217.90 44.63 4,364,246.91 - - 125.83 12,305,464.81

campuran 1SP : 3PP

3 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 92,281.75 485.21 44,775,880.27 - - 71.77 6,622,932.00 413.44 38,152,948.26

campuran 1SP : 6PP

JUMLAH IV 52,717,098.17 4,364,246.91 6,622,932.00 50,458,413.07


V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 38,633.10 1,100.58 42,518,693.57 - - 64.13 2,477,355.26 1,036.45 40,041,338.31

2 A.4.4.2.27. Pemasangan 1 m2 acian m2 23,815.00 1,103.69 26,284,301.14 - - 21.66 515,947.21 1,082.02 25,768,353.93

3 Ls Sponengan m1 20,000.00 31.10 622,000.00 - - - - 31.10 622,000.00

JUMLAH V 69,424,994.71 - 2,993,302.48 66,431,692.24


VI PEKERJAAN BETON
1 Lantai kerja

A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 712,475.42 18.20 12,968,477.62 0.24 172,169.69 - - 18.44 13,140,647.31

slump (12 ± 2) cm, w/c = 0,87

2 Rabat Beton

A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 756,474.46 6.30 4,765,789.12 0.11 80,640.18 - - 6.41 4,846,429.29

slump (12 ± 2) cm, w/c = 0,87

3 Pondasi Foot Plat 80/80

A.4.1.1.20. Pemasangan 1 m2 bekisting untuk pondasi m2 154,429.00 - - 1.28 197,669.12 - - 1.28 197,669.12

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 - - 97.92 1,278,684.90 - - 97.92 1,278,684.90

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 - - 0.59 522,268.68 - - 0.59 522,268.68

slump (12 ± 2) cm, w/c = 0,87


4 Sloof 15/20

A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 166,529.00 49.88 8,306,466.52 - - - - 49.88 8,306,466.52

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 1,403.28 18,323,784.67 - - 151.75 1,981,524.94 1,251.53 16,342,259.72

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 7.48 6,285,020.57 - - - - 7.48 6,285,020.57

slump (12 ± 2) cm,w/c=0,87

5 Kolom 30/30

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 7.20 1,816,214.40 5.88 1,483,241.76 - - 13.08 3,299,456.16

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 101.73 1,328,372.54 53.24 695,198.60 - - 154.97 2,023,571.14

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 1.08 907,462.86 0.88 739,414.18 - - 1.96 1,646,877.05

slump (12 ± 2) cm,w/c=0,87

6 Kolom 20/20

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 60.80 15,336,921.60 - - 1.60 403,603.20 59.20 14,933,318.40

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 561.23 7,328,443.12 409.95 5,353,055.36 - - 971.18 12,681,498.48

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 5.78 4,856,606.80 - - 0.16 134,438.94 5.62 4,722,167.86

slump (12 ± 2) cm,w/c=0,87

7 Kolom 15/15

A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 252,252.00 114.40 28,857,628.80 - - 1.40 353,152.80 113.00 28,504,476.00

8 Balok 15/40

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 282,612.00 2.06 582,180.72 0.22 62,174.64 - - 2.28 644,355.36

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 53.90 703,816.77 - - 6.16 80,436.20 47.74 623,380.57

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.33 277,280.32 - - - - 0.33 277,280.32

slump (12 ± 2) cm, w/c = 0,87

9 Ring balok 15/30

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 282,612.00 7.13 2,015,023.56 0.42 118,697.04 - - 7.55 2,133,720.60

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 140.91 1,839,978.12 38.33 500,506.43 - - 179.24 2,340,484.55

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.86 722,609.32 0.35 294,085.19 - - 1.21 1,016,694.50

slump (12 ± 2) cm, w/c = 0,87

10 Ring balok 15/20

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 86,781.75 39.90 3,462,591.83 - - 5.39 467,753.63 34.51 2,994,838.19

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 1,351.01 17,641,252.15 - - 290.53 3,793,689.90 1,060.48 13,847,562.26

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 5.99 5,033,057.91 - - 0.81 680,597.15 5.18 4,352,460.77

slump (12 ± 2) cm, w/c = 0,87

11 Balok Latai 10/15

A.4.1.1.36. Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 86,781.75 97.00 8,417,829.75 - - - - 97.00 8,417,829.75

12 Plat atap

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 222,552.00 25.00 5,563,800.00 - - - - 25.00 5,563,800.00
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 855.60 11,172,275.07 - - - - 855.60 11,172,275.07
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 6.00 5,041,460.35 - - - - 6.00 5,041,460.35

slump (12 ± 2) cm, w/c = 0,87

13 Shading

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 319,352.00 14.61 4,665,732.72 16.78 5,358,726.56 - - 31.39 10,024,459.28

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 281.98 3,682,045.49 81.54 1,064,735.05 - - 363.52 4,746,780.54

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 2.92 2,453,510.70 2.10 1,766,527.71 - - 5.02 4,220,038.41

slump (12 ± 2) cm, w/c = 0,87

14 Plat lisplang

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 319,352.00 3.51 1,120,925.52 - - - - 3.51 1,120,925.52

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 69.32 905,168.43 - - - - 69.32 905,168.43

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.70 588,170.37 - - - - 0.70 588,170.37

slump (12 ± 2) cm, w/c = 0,87

JUMLAH VI 186,969,897.72 19,687,795.08 7,895,196.77 198,762,496.04


VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.11. Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I m3 652,159.75 24.36 15,886,611.51 - - - - 24.36 15,886,611.51

2 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 9,944,550.00 6.99 69,512,404.50 - - - - 6.99 69,512,404.50

kayu kelas II (kruink )

3 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 10,651,671.25 3.57 38,026,466.36 - - 0.03 319,550.14 3.54 37,706,916.23

4 A.4.6.1.17. Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II m2 153,051.25 533.00 81,576,316.25 - - 9.10 1,392,766.38 523.90 80,183,549.88

5 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) motif k m1 22,500.00 105.00 2,362,500.00 - - 3.00 67,500.00 102.00 2,295,000.00

6 A.4.5.2.3.a Pemasangan 1 m2 atap genteng palentong besar/super m2 59,793.25 533.00 31,869,802.25 - - 9.10 544,118.58 523.90 31,325,683.68

7 A.4.5.2.6. Pemasangan 1 m’ bubung genteng palentong besar m1 63,189.50 61.50 3,886,154.25 0.10 6,318.95 - - 61.60 3,892,473.20

8 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 77,038.50 463.00 35,668,825.50 - - 54.61 4,206,841.37 408.39 31,461,984.13

9 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 34,538.90 383.00 13,228,398.70 - - 14.13 487,931.04 368.87 12,740,467.66

ukuran (120x240x9) mm, tebal 9 mm

10 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 32,937.30 80.00 2,634,984.00 - - 40.48 1,333,301.90 39.52 1,301,682.10

ukuran (120x240x9) mm, tebal 4 mm

11 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 19,049.25 436.80 8,320,712.40 - - 159.70 3,042,165.23 277.10 5,278,547.18

JUMLAH VII 302,973,175.72 6,318.95 11,394,174.63 291,585,320.05


VIII PEKERJAAN SANITASI
1 A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen bh 290,097.50 4.00 1,160,390.00 - - - - 4.00 1,160,390.00

2 A.5.1.1 10. Pemasangan 1 buah bak air fibreglass vol 1 m3 bh 342,354.10 4.00 1,369,416.40 - - 4.00 1,369,416.40 - -

3 A.5.1.1 14. Pemasangan 1 buah floor drain bh 26,331.25 4.00 105,325.00 1.00 26,331.25 - - 5.00 131,656.25

4 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm bh 318,991.75 4.00 1,275,967.00 - - 4.00 1,275,967.00 - -

5 A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4” m1 45,375.00 4.00 181,500.00 3.00 136,125.00 - - 7.00 317,625.00

6 A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” m1 14,250.50 60.00 855,030.00 9.80 139,654.90 - - 69.80 994,684.90
7 A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” m` 33,310.75 12.00 399,729.00 2.50 83,276.88 - - 14.50 483,005.88
8 A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4” m1 72,312.63 12.00 867,751.50 1.00 72,312.63 - - 13.00 940,064.13

9 Ditaksir Fiber glas tangki air kap 1100 ltr bh 1,450,000.00 1.00 1,450,000.00 - - - - 1.00 1,450,000.00

10 Ditaksir Pasang sumur bor m' 180,000.00 - - 8.00 1,440,000.00 - - 8.00 1,440,000.00

11 Ditaksir Pasang mesin pompa air listrik PW-120 jet bh 1,250,000.00 - - 1.00 1,250,000.00 - - 1.00 1,250,000.00

12 Ditaksir Ember dan gayung bh 100,000.00 - - 4.00 400,000.00 - - 4.00 400,000.00

JUMLAH VIII 7,665,108.90 3,547,700.65 2,645,383.40 8,567,426.15


IX PEKERJAAN BESI DAN ALUMUNIUM
1 A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium m1 81,947.80 489.42 40,106,892.28 - - - - 489.42 40,106,892.28

2 A.4.2.1.13. Pemasangan 1 m2 pintu/jendela kaca rangka alluminium m2 466,303.75 74.83 34,893,509.61 7.24 3,376,039.15 - - 82.07 38,269,548.76

3 Ls Pemasangan pintu tempered t = 12 mm ( komplit ) unit 10,000,000.00 4.00 40,000,000.00 - - - - 4.00 40,000,000.00

JUMLAH IX 115,000,401.89 3,376,039.15 - 118,376,441.04


X PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh 25,185.60 42.00 1,057,795.20 - - - - 42.00 1,057,795.20

2 A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu bh 21,921.63 304.00 6,664,174.00 - - - - 304.00 6,664,174.00

3 A.4.6.2.9. Pemasangan 1 buah kait angin bh 25,641.00 304.00 7,794,864.00 - - - - 304.00 7,794,864.00

4 A.4.6.2.11. Pemasangan 1 buah kunci slot bh 97,083.25 14.00 1,359,165.50 - - - - 14.00 1,359,165.50

5 A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm bh 115,371.85 180.80 20,859,230.48 - - - - 180.80 20,859,230.48

6 Ditaksir Grendel pintu bh 10,000.00 170.00 1,700,000.00 - - - - 170.00 1,700,000.00

JUMLAH X 39,435,229.18 - - 39,435,229.18


XI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 145,153.25 348.70 50,615,301.16 11.53 1,673,689.55 - - 360.23 52,288,990.71

2 A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm m2 213,889.50 15.34 3,280,530.21 - - 6.70 1,432,524.93 8.64 1,848,005.28

3 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm m1 38,173.30 20.80 794,004.64 1.95 74,437.94 - - 22.75 868,442.58

4 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20cm x 20cm m2 204,226.00 31.20 6,371,851.20 9.74 1,989,263.35 - - 40.94 8,361,114.55

5 A.4.4.3.58. Pemasangan 1 m2 dinding batu tempel candi m2 236,692.50 12.64 2,991,793.20 - - 12.64 2,991,793.20 - -

JUMLAH XI 64,053,480.40 3,737,390.84 4,424,318.13 63,366,553.12


XII PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 17,222.98 1,103.69 19,008,825.28 - - 21.67 373,221.87 1,082.02 18,635,603.41

cat dasar, 2 lapis cat penutup )

2 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 13,132.90 463.00 6,080,532.70 - - 54.61 717,187.67 408.39 5,363,345.03

JUMLAH XII 25,089,357.98 - 1,090,409.54 23,998,948.44


XIII PEKERJAAN INSTALASI LISTRIK
1 Ls Pemasangan meter listrik lama 5500 watt unit 750,000.00 1.00 750,000.00 - - 1.00 750,000.00 - -

2 Ls Pasang meteran listrik baru 5500 Va unit 10,000,000.00 - - 1.00 10,000,000.00 - - 1.00 10,000,000.00

3 Ls Titik Lampu Titik 85,000.00 57.00 4,845,000.00 - - - - 57.00 4,845,000.00

4 Ls Saklar ganda bh 22,500.00 3.00 67,500.00 - - - - 3.00 67,500.00


5 Ls Saklar tunggal bh 20,000.00 12.00 240,000.00 1.00 20,000.00 - - 13.00 260,000.00
6 Ls stop kontak bh 22,500.00 15.00 337,500.00 - - - - 15.00 337,500.00

7 Ls lampu pijar 5W Philips bh 10,000.00 9.00 90,000.00 - - 4.00 40,000.00 5.00 50,000.00

8 Ls Lampu SL 18 Watt Phillips bh 35,500.00 33.00 1,171,500.00 4.00 142,000.00 - - 37.00 1,313,500.00

JUMLAH XIII 7,501,500.00 10,162,000.00 790,000.00 16,873,500.00


XIV PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm termasuk pas dinding m1 75,500.00 116.00 8,758,000.00 - - 3.64 274,820.00 112.36 8,483,180.00

2 A.5.1.1 15. Membuat Septic Tank bh 1,150,000.00 1.00 1,150,000.00 1.00 1,150,000.00 - - 2.00 2,300,000.00

3 Ditaksir Membuat peresapan bh 750,000.00 1.00 750,000.00 1.00 750,000.00 - - 2.00 1,500,000.00

4 Ditaksir Tanah Subur m3 120,000.00 - - 8.96 1,075,320.00 - - 8.96 1,075,320.00

5 Ditaksir Pembuatan taman m2 225,000.00 - - 59.34 13,351,500.00 - - 59.34 13,351,500.00

JUMLAH XIV 10,658,000.00 16,326,820.00 274,820.00 26,710,000.00

952,201,383.04 63,657,427.31 41,642,923.24 974,215,887.11

D SERBA GUNA
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls 500,000.00 1.00 500,000.00 - - - - 1.00 500,000.00

JUMLAH I 500,000.00 - - 500,000.00


II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 49,018.75 2.08 101,959.00 27.93 1,369,152.51 - - 30.01 1,471,111.51

2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 16,339.58 8.11 132,546.70 0.89 14,564.45 - - 9.00 147,111.15

3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 118,607.50 9.88 1,171,323.19 - - - - 9.88 1,171,323.19

4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 83,393.75 38.97 3,250,167.16 - - 21.01 1,751,922.56 17.97 1,498,244.61

JUMLAH II 4,655,996.06 1,383,716.96 1,751,922.56 4,287,790.46


III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 516,466.50 32.53 16,801,946.41 - - - - 32.53 16,801,946.41

2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 279,576.00 13.52 3,779,867.52 - - - - 13.52 3,779,867.52

JUMLAH III 20,581,813.93 - - 20,581,813.93


IV PEKERJAAN DINDING
1 A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 201,619.00 16.40 3,306,551.60 - - 16.40 3,306,551.60 - -

campuran 1SP : 3PP

2 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 97,798.25 51.43 5,029,764.00 21.75 2,126,622.95 - - 73.18 7,156,386.94

campuran 1SP : 3PP

3 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 92,281.75 226.13 20,867,838.23 - - 104.75 9,666,670.19 121.38 11,201,168.04

campuran 1SP : 6PP

JUMLAH IV 29,204,153.83 2,126,622.95 12,973,221.79 18,357,554.99


V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 38,633.10 564.25 21,798,726.68 - - 193.96 7,493,276.08 370.29 14,305,450.60

2 A.4.4.2.23. Pemasangan 1 m2 plesteran ciprat 1SP : 2PP m2 32,392.25 4.48 145,117.28 - - 3.15 101,970.80 1.33 43,146.48

3 A.4.4.2.27. Pemasangan 1 m2 acian m2 23,815.00 569.05 13,551,925.75 - - 189.69 4,517,467.35 379.36 9,034,458.40

4 Ls Sponengan m1 15,000.00 48.00 720,000.00 - - - - 48.00 720,000.00

JUMLAH V 36,215,769.71 - 12,112,714.23 24,103,055.48


VI PEKERJAAN BETON
1 Lantai kerja

A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 712,475.42 6.50 4,627,973.16 - - - - 6.50 4,627,973.16

slump (12 ± 2) cm, w/c = 0,87

2 Rabat Beton

A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 756,474.46 4.10 3,101,545.30 - - 1.39 1,047,807.91 2.71 2,053,737.39

slump (12 ± 2) cm, w/c = 0,87

3 Sloof 15/25

A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 166,529.00 21.13 3,518,757.77 - - - - 21.13 3,518,757.77

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 594.28 7,760,004.24 - - 74.97 978,945.14 519.31 6,781,059.10

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 3.17 2,663,571.55 - - - - 3.17 2,663,571.55

slump (12 ± 2) cm,w/c=0,87

4 Kolom 20/20

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 6.00 1,513,512.00 - - 0.86 216,936.72 5.14 1,296,575.28

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 56.32 735,416.70 - - 4.65 60,718.89 51.67 674,697.82

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 0.54 453,731.43 - - 0.03 25,207.30 0.51 428,524.13

slump (12 ± 2) cm,w/c=0,87

5 Kolom 15/15

A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 252,252.00 103.40 26,082,856.80 - - 8.60 2,169,367.20 94.80 23,913,489.60

6 Ring balok 15/30

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 6.00 1,529,352.00 - - - - 6.00 1,529,352.00

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 118.67 1,549,572.09 - - 12.46 162,700.50 106.21 1,386,871.59

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.48 403,316.83 0.20 168,048.68 - - 0.68 571,365.51

slump (12 ± 2) cm, w/c = 0,87

7 Ring balok 15/20

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 86,781.75 14.50 1,258,335.38 0.60 52,069.05 - - 15.10 1,310,404.43

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 490.89 6,409,955.71 - - 26.90 351,255.49 463.99 6,058,700.22

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 2.18 1,831,730.59 0.09 75,621.91 - - 2.27 1,907,352.50

slump (12 ± 2) cm, w/c = 0,87


8 Balok Latai 10/15

A.4.1.1.36. Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 86,781.75 32.00 2,777,016.00 3.00 260,345.25 - - 35.00 3,037,361.25

9 Plat atap

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 222,552.00 5.25 1,168,398.00 6.44 1,432,567.22 - - 11.69 2,600,965.22

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 177.69 2,320,244.92 22.28 290,928.34 - - 199.97 2,611,173.27

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 1.05 882,255.56 0.12 99,736.89 - - 1.17 981,992.45

slump (12 ± 2) cm, w/c = 0,87

10 Shading

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 319,352.00 2.84 905,362.92 0.82 260,910.58 - - 3.65 1,166,273.50

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 54.68 714,001.87 19.64 256,447.85 - - 74.32 970,449.72

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.68 571,701.60 - - 0.10 80,730.59 0.58 490,971.02

slump (12 ± 2) cm, w/c = 0,87

JUMLAH VI 72,778,612.44 2,896,675.77 5,093,669.73 70,581,618.48


VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.11. Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I m3 652,159.75 7.98 5,204,234.81 - - - - 7.98 5,204,234.81

2 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 9,944,550.00 1.45 14,419,597.50 0.07 696,118.50 - - 1.52 15,115,716.00

kayu kelas II (kruink )

3 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 10,651,671.25 1.47 15,657,956.74 - - 0.13 1,384,717.26 1.34 14,273,239.48

4 A.4.6.1.16. Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II m2 152,556.25 240.50 36,689,778.13 - - 56.99 8,694,516.31 183.51 27,995,261.81

5 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) motif k m1 22,500.00 61.00 1,372,500.00 - - 6.26 140,850.00 54.74 1,231,650.00

6 A.4.5.2.1. Pemasangan 1 m2 atap genteng palentong kecil m2 59,211.63 240.50 14,240,395.81 - - 56.99 3,374,600.77 183.51 10,865,795.04

7 A.4.5.2.4. Pemasangan 1 m’ bubung genteng palentong m1 65,939.50 34.00 2,241,943.00 - - - - 34.00 2,241,943.00

8 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 77,038.50 186.28 14,350,731.78 - - 8.02 617,810.25 178.26 13,732,921.53

9 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 34,538.90 143.72 4,963,930.71 - - 4.55 157,238.34 139.17 4,806,692.37

ukuran (120x240x9) mm, tebal 9 mm

10 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 32,937.30 42.56 1,401,811.49 - - 3.47 114,193.62 39.09 1,287,617.87

ukuran (120x240x9) mm, tebal 4 mm

11 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 19,049.25 227.80 4,339,419.15 - - 95.50 1,819,203.38 132.30 2,520,215.78

JUMLAH VII 114,882,299.11 696,118.50 16,303,129.94 99,275,287.67


VIII PEKERJAAN SANITASI
1 A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen bh 290,097.50 2.00 580,195.00 - - - - 2.00 580,195.00

2 A.5.1.1 10. Pemasangan 1 buah bak air fibreglass vol 1 m3 bh 342,354.10 2.00 684,708.20 - - 2.00 684,708.20 - -

3 A.5.1.1 14. Pemasangan 1 buah floor drain bh 26,331.25 2.00 52,662.50 - - - - 2.00 52,662.50

4 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm bh 318,991.75 4.00 1,275,967.00 - - 4.00 1,275,967.00 - -

5 A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4” m1 45,375.00 2.00 90,750.00 - - - - 2.00 90,750.00

6 A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” m1 14,250.50 24.00 342,012.00 16.00 228,008.00 - - 40.00 570,020.00
7 A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” m` 33,310.75 12.00 399,729.00 - - 8.50 283,141.38 3.50 116,587.63

8 A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4” m1 72,312.63 12.00 867,751.50 - - 5.00 361,563.13 7.00 506,188.38

10 Ditaksir Pasang sumur bor m' 180,000.00 - - 8.00 1,440,000.00 - - 8.00 1,440,000.00

11 Ditaksir Pasang mesin pompa air listrik PW-120 jet bh 1,250,000.00 - - 1.00 1,250,000.00 - - 1.00 1,250,000.00

9 Ditaksir Ember dan gayung unit 100,000.00 - - 2.00 200,000.00 - - 2.00 200,000.00

10 Ditaksir Fiber glas tangki air kap 1100 ltr unit 1,450,000.00 - - 1.00 1,450,000.00 - - 1.00 1,450,000.00

JUMLAH VIII 4,293,775.20 4,568,008.00 2,605,379.70 6,256,403.50


IX PEKERJAAN BESI DAN ALUMUNIUM
1 A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium m1 81,947.80 160.30 13,136,232.34 9.66 791,615.75 - - 169.96 13,927,848.09

2 A.4.2.1.13. Pemasangan 1 m2 pintu kaca rangka alluminium m2 466,303.75 28.61 13,340,950.29 0.84 391,695.15 - - 29.45 13,732,645.44

JUMLAH IX 26,477,182.63 1,183,310.90 - 27,660,493.53


X PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh 25,185.60 15.00 377,784.00 - - - - 15.00 377,784.00

2 A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu bh 21,921.63 112.00 2,455,222.00 6.00 131,529.75 - - 118.00 2,586,751.75

3 A.4.6.2.9. Pemasangan 1 buah kait angin bh 25,641.00 112.00 2,871,792.00 6.00 153,846.00 - - 118.00 3,025,638.00

4 A.4.6.2.11. Pemasangan 1 buah kunci slot bh 97,083.25 5.00 485,416.25 - - - - 5.00 485,416.25

5 A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm bh 115,371.85 41.06 4,737,168.16 - - 2.94 339,193.24 38.12 4,397,974.92

6 Ditaksir Grendel pintu bh 10,000.00 61.00 610,000.00 3.00 30,000.00 - - 64.00 640,000.00

JUMLAH X 11,537,382.41 315,375.75 339,193.24 11,513,564.92


XI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 199,798.50 123.85 24,744,045.23 - - - - 123.85 24,744,045.23

2 A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm m2 213,889.50 6.07 1,297,774.54 - - - - 6.07 1,297,774.54

3 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm m1 38,173.30 9.40 358,829.02 - - - - 9.40 358,829.02

4 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20cm x 20cm m2 204,226.00 14.10 2,879,586.60 - - - - 14.10 2,879,586.60

JUMLAH XI 29,280,235.39 - - 29,280,235.39


XII PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 17,222.98 569.05 9,800,733.92 - - 189.69 3,267,026.13 379.36 6,533,707.80

cat dasar, 2 lapis cat penutup )

2 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 13,132.90 186.28 2,446,396.61 - - 8.02 105,319.29 178.26 2,341,077.32

JUMLAH XII 12,247,130.54 - 3,372,345.42 8,874,785.12


XIII PEKERJAAN INSTALASI LISTRIK
1 Ls Titik Lampu Titik 85,000.00 28.00 2,380,000.00 - - - - 28.00 2,380,000.00

2 Ls Saklar ganda bh 22,500.00 2.00 45,000.00 - - - - 2.00 45,000.00

3 Ls Saklar tunggal bh 20,000.00 6.00 120,000.00 - - - - 6.00 120,000.00

4 Ls stop kontak bh 22,500.00 6.00 135,000.00 - - - - 6.00 135,000.00

5 Ls lampu pijar 5W Philips bh 10,000.00 6.00 60,000.00 - - - - 6.00 60,000.00


6 Ls Lampu SL 18 Watt Phillips bh 35,500.00 16.00 568,000.00 - - - - 16.00 568,000.00
7 Ls Pemindahan meteren lama 5500 watt unit 750,000.00 - - 1.00 750,000.00 - - 1.00 750,000.00

JUMLAH XIII 3,308,000.00 750,000.00 - 4,058,000.00


XIV PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm termasuk pas dinding m1 75,500.00 60.00 4,530,000.00 - - 60.00 4,530,000.00 - -

2 Ls Membuat Septic Tank bh 1,150,000.00 1.00 1,150,000.00 - - - - 1.00 1,150,000.00

3 Ls Membuat peresapan bh 750,000.00 1.00 750,000.00 - - - - 1.00 750,000.00

4 Ls Tanah Subur m3 120,000.00 - - 0.40 47,880.00 - - 0.40 47,880.00

5 Ls Pembuatan taman m2 225,000.00 - - 1.00 224,437.50 - - 1.00 224,437.50

JUMLAH XIV 6,430,000.00 272,317.50 4,530,000.00 2,172,317.50

372,392,351.24 14,192,146.33 59,081,576.60 327,502,920.96

E MUSHOLLA
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls 500,000.00 - - - - - - - -

JUMLAH I - - - -
II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 49,018.75 - - - - - - - -

2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 16,339.58 - - - - - - - -

3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 118,607.50 - - - - - - - -

4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 83,393.75 - - - - - - - -

JUMLAH II - - - -
III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 516,466.50 - - - - - - - -

2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 279,576.00 - - - - - - - -

JUMLAH III - - - -
IV PEKERJAAN DINDING
1 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 97,798.25 - - - - - - - -

campuran 1SP : 3PP -

2 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 92,281.75 - - - - - - - -

campuran 1SP : 6PP -

3 Ls Pemasangan main dinding GRC m2 42,000.00 - - - - - - - -

JUMLAH IV - - - -
V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 38,633.10 - - - - - - - -

2 A.4.4.2.27. Pemasangan 1 m2 acian m2 23,815.00 - - - - - - - -

JUMLAH V - - - -
VI PEKERJAAN BETON
1 Lantai kerja

A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 712,475.42 - - - - - - - -

slump (12 ± 2) cm, w/c = 0,87

2 Rabat Beton

A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 756,474.46 - - - - - - - -

slump (12 ± 2) cm, w/c = 0,87

3 Sloof 15/25

A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 166,529.00 - - - - - - - -

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 - - - - - - - -

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 - - - - - - - -

slump (12 ± 2) cm,w/c=0,87

4 Kolom 15/15

A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 63,268.15 - - - - - - - -

5 Balok 15/30

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 - - - - - - - -

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 - - - - - - - -

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 - - - - - - - -

slump (12 ± 2) cm, w/c = 0,87

6 Ring balok 15/20

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 86,781.75 - - - - - - - -

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 - - - - - - - -

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 - - - - - - - -

slump (12 ± 2) cm, w/c = 0,87

7 Balok Latai 10/15

A.4.1.1.36. Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 86,781.75 - - - - - - - -

8 Plat atap

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 222,552.00 - - - - - - - -

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 - - - - - - - -

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 - - - - - - - -

slump (12 ± 2) cm, w/c = 0,87

9 Shading

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 319,352.00 - - - - - - - -

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 - - - - - - - -

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 - - - - - - - -

slump (12 ± 2) cm, w/c = 0,87


JUMLAH VI - - - -
VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 9,944,550.00 - - - - - - - -

kayu kelas II (kruink )

2 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 10,651,671.25 - - - - - - - -

3 A.4.6.1.16. Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II m2 152,556.25 - - - - - - - -

4 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) motif k m1 22,500.00 - - - - - - - -

5 A.4.5.2.1. Pemasangan 1 m2 atap genteng palentong kecil m2 59,211.63 - - - - - - - -

6 A.4.5.2.4. Pemasangan 1 m’ bubung genteng palentong m1 65,939.50 - - - - - - - -

7 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 77,038.50 - - - - - - - -

8 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 34,538.90 - - - - - - - -

ukuran (120x240x9) mm, tebal 9 mm

9 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 32,937.30 - - - - - - - -

ukuran (120x240x9) mm, tebal 4 mm

10 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 19,049.25 - - - - - - - -

JUMLAH VII - - - -
VIII PEKERJAAN SANITASI
1 A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen bh 290,097.50 - - - - - - - -

2 A.5.1.1 10. Pemasangan 1 buah bak air fibreglass vol 1 m3 bh 342,354.10 - - - - - - - -

3 A.5.1.1 14. Pemasangan 1 buah floor drain bh 26,331.25 - - - - - - - -

4 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm bh 318,991.75 - - - - - - - -

5 A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4” m1 45,375.00 - - - - - - - -

6 A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” m1 14,250.50 - - - - - - - -

7 A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” m` 33,310.75 - - - - - - - -

8 A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4” m1 72,312.63 - - - - - - - -

JUMLAH VIII - - - -
IX PEKERJAAN BESI DAN ALUMUNIUM
1 A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium m1 81,947.80 - - - - - - - -

2 A.4.2.1.12. Pemasangan 1 m2 pintu alluminium strip lebar 8 cm m1 422,405.78 - - - - - - - -

3 A.4.2.1.13. Pemasangan 1 m2 pintu kaca rangka alluminium m2 466,303.75 - - - - - - - -

4 A.4.2.1.13. Pemasangan 1 m2 pintu kaca rangka alluminium m2 466,303.75 - - - - - - - -

5 Ls Pemasangan kubah bh 2,000,000.00 - - - - - - - -

JUMLAH IX - - - -
X PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh 25,185.60 - - - - - - - -

2 A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu bh 21,921.63 - - - - - - - -

3 A.4.6.2.9. Pemasangan 1 buah kait angin bh 25,641.00 - - - - - - - -


4 A.4.6.2.11. Pemasangan 1 buah kunci slot bh 97,083.25 - - - - - - - -

5 A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm bh 115,371.85 - - - - - - - -

6 Ditaksir Grendel pintu bh 10,000.00 - - - - - - - -

JUMLAH X - - - -
XI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 199,798.50 - - - - - - - -

2 A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm m2 213,889.50 - - - - - - - -

3 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm m1 38,173.30 - - - - - - - -

4 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20cm x 20cm m2 204,226.00 - - - - - - - -

JUMLAH XI - - - -
XII PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 17,222.98 - - - - - - - -

cat dasar, 2 lapis cat penutup )

2 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 13,132.90 - - - - - - - -

JUMLAH XII - - - -
XIII PEKERJAAN INSTALASI LISTRIK
1 Ls Pemasangan meter listrik 900 watt unit 1,650,000.00 - - - - - - - -

2 Ls Titik Lampu Titik 85,000.00 - - - - - - - -

3 Ls Saklar ganda bh 22,500.00 - - - - - - - -

4 Ls Saklar tunggal bh 20,000.00 - - - - - - - -

5 Ls stop kontak bh 22,500.00 - - - - - - - -

6 Ls lampu pijar 5W Philips bh 10,000.00 - - - - - - - -

7 Ls Lampu SL 18 Watt Phillips bh 35,500.00 - - - - - - - -

JUMLAH XIII - - - -
XIV PEKERJAAN LAIN-LAIN
2 Ls Membuat Septic Tank bh 1,150,000.00 - - - - - - - -

3 Ls Membuat peresapan bh 750,000.00 - - - - - - - -

4 Ls Tanah Subur m3 120,000.00 - - - - - - - -

5 Ls Pembuatan taman m2 225,000.00 - - - - - - - -

JUMLAH XIV - - - -

- - -
F RUMAH DINAS

I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls 500,000.00 1.00 500,000.00 - - - - 1.00 500,000.00

JUMLAH I 500,000.00 - - 500,000.00


II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 49,018.75 2.36 115,684.25 27.71 1,358,270.35 - - 30.07 1,473,954.60

2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 16,339.58 8.64 141,174.00 - - - - 8.64 141,174.00

3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 118,607.50 9.38 1,112,123.22 0.01 1,707.95 - - 9.39 1,113,831.17

4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 83,393.75 34.66 2,890,343.98 - - 20.96 1,748,103.12 13.70 1,142,240.86

JUMLAH II 4,259,325.46 1,359,978.30 1,748,103.12 3,871,200.63


III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 516,466.50 34.65 17,895,564.23 4.95 2,556,509.18 - - 39.60 20,452,073.40

2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 279,576.00 14.40 4,025,894.40 - - - - 14.40 4,025,894.40

JUMLAH III 21,921,458.63 2,556,509.18 - 24,477,967.80


IV PEKERJAAN DINDING
1 A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 201,619.00 11.80 2,379,104.20 - - 10.60 2,137,161.40 1.20 241,942.80

campuran 1SP : 3PP

2 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 97,798.25 42.11 4,118,284.31 - - 7.68 751,090.56 34.43 3,367,193.75

campuran 1SP : 3PP

3 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 92,281.75 280.06 25,844,426.91 - - 42.02 3,877,826.79 238.04 21,966,600.12

campuran 1SP : 6PP

JUMLAH IV 32,341,815.41 - 6,766,078.75 25,575,736.67


V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 38,633.10 629.00 24,300,219.90 - - 88.02 3,400,485.46 540.98 20,899,734.44

2 A.4.4.2.27. Pemasangan 1 m2 acian m2 23,815.00 629.00 14,979,635.00 - - 71.46 1,701,874.67 557.54 13,277,760.33

JUMLAH V 39,279,854.90 - 5,102,360.14 34,177,494.76


VI PEKERJAAN BETON
1 Lantai kerja

A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 712,475.42 5.78 4,115,614.27 0.01 10,259.65 - - 5.79 4,125,873.92

slump (12 ± 2) cm, w/c = 0,87

2 Rabat Beton

A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 756,474.46 6.46 4,886,825.03 - - 3.72 2,812,390.50 2.74 2,074,434.53

slump (12 ± 2) cm, w/c = 0,87

3 Sloof 15/25

A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 166,529.00 23.25 3,871,799.25 - - - - 23.25 3,871,799.25

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 654.16 8,541,906.80 - - 82.52 1,077,531.72 571.64 7,464,375.08

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 3.49 2,932,449.44 - - - - 3.49 2,932,449.44

slump (12 ± 2) cm,w/c=0,87


4 Kolom 15/25

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 25.60 6,457,651.20 6.80 1,715,313.60 - - 32.40 8,172,964.80

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 546.78 7,139,757.55 - - 20.58 268,730.04 526.20 6,871,027.52

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 2.40 2,016,584.14 0.17 142,841.38 - - 2.57 2,159,425.52

slump (12 ± 2) cm,w/c=0,87

5 Kolom 15/15

A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 63,268.15 60.00 3,796,089.00 - - 4.00 253,072.60 56.00 3,543,016.40

6 Ring balok 15/30

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 2.06 525,077.52 - - 2.06 525,077.52 - -

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 40.83 533,150.99 - - 40.83 533,150.99 - -

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.25 210,060.85 - - 0.25 210,060.85 - -

slump (12 ± 2) cm, w/c = 0,87

7 Ring balok 15/20

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 18.60 4,740,991.20 - - - - 18.60 4,740,991.20

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 629.80 8,223,818.19 - - 69.94 913,264.28 559.86 7,310,553.90

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 2.79 2,344,279.06 - - - - 2.79 2,344,279.06

slump (12 ± 2) cm, w/c = 0,87

8 Balok Latai 10/15

A.4.1.1.36. Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 86,781.75 32.50 2,820,406.88 - - - - 32.50 2,820,406.88

9 Plat atap

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 222,552.00 0.75 166,914.00 - - 0.75 166,914.00 - -

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 26.41 344,857.16 - - 26.41 344,857.16 - -

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.18 151,243.81 - - 0.18 151,243.81 - -

slump (12 ± 2) cm, w/c = 0,87

10 Shading

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 222,552.00 3.90 867,952.80 2.76 614,243.52 - - 6.66 1,482,196.32

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 75.39 984,429.43 60.03 783,861.23 - - 135.42 1,768,290.66

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.78 655,389.85 0.29 240,410.44 - - 1.07 895,800.28

slump (12 ± 2) cm, w/c = 0,87

11 Meja dapur

A.4.1.1.33. Membuat 1 m3 dinding beton bertulang (150 kg besi + bekisting) m2 222,552.00 0.90 200,296.80 0.37 82,344.24 - - 1.27 282,641.04

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 17.36 226,683.84 - - 5.84 76,257.70 11.52 150,426.14

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.18 151,243.81 0.03 27,223.89 - - 0.21 178,467.70

slump (12 ± 2) cm, w/c = 0,87

JUMLAH VI 66,905,472.86 3,616,497.94 7,332,551.17 63,189,419.64


VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.2. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu m
k3 10,925,172.50 0.89 9,723,403.53 0.06 655,510.35 - - 0.95 10,378,913.88

2 A.4.6.1.5. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I atau m2 591,717.50 14.70 8,698,247.25 - - 0.50 295,858.75 14.20 8,402,388.50

3 A.4.6.1.6. Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I m2 410,058.00 3.96 1,623,829.68 - - - - 3.96 1,623,829.68

4 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 9,944,550.00 1.95 19,391,872.50 0.07 696,118.50 - - 2.02 20,087,991.00

kayu kelas II (kruink )

5 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 10,651,671.25 1.90 20,238,175.38 0.02 213,033.43 - - 1.92 20,451,208.80

6 A.4.6.1.16. Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II m2 152,556.25 208.59 31,821,708.19 - - 13.91 2,122,057.44 194.68 29,699,650.75

7 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) motif k m1 22,500.00 55.20 1,242,000.00 - - 2.90 65,250.00 52.30 1,176,750.00

8 A.4.5.2.1. Pemasangan 1 m2 atap genteng palentong kecil m2 59,211.63 208.59 12,350,952.86 - - 13.91 823,633.70 194.68 11,527,319.16

9 A.4.5.2.4. Pemasangan 1 m’ bubung genteng palentong m1 65,939.50 51.00 3,362,914.50 - - 4.29 282,880.46 46.71 3,080,034.05

10 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 77,038.50 150.31 11,579,656.94 3.47 267,400.63 - - 153.78 11,847,057.57

11 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 34,538.90 117.60 4,061,774.64 - - 1.78 61,548.32 115.82 4,000,226.32

ukuran (120x240x9) mm, tebal 9 mm

12 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 32,937.30 30.31 998,329.56 7.65 252,069.16 - - 37.96 1,250,398.72

ukuran (120x240x9) mm, tebal 4 mm

13 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 19,049.25 223.00 4,247,982.75 - - 106.11 2,021,315.92 116.89 2,226,666.83

14 Ls Pemasangan rooster kayu bh 25,000.00 5.00 125,000.00 4.00 100,000.00 - - 9.00 225,000.00

JUMLAH VII 129,465,847.76 2,184,132.07 5,672,544.58 125,977,435.25


VIII PEKERJAAN SANITASI
1 A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen bh 290,097.50 1.00 290,097.50 - - - - 1.00 290,097.50

2 A.5.1.1 5. Pemasangan 1 buah wastafel bh 696,960.00 1.00 696,960.00 - - - - 1.00 696,960.00

3 A.5.1.1 10. Pemasangan 1 buah bak air fibreglass vol 1 m3 bh 342,354.10 - - - - - - - -

4 A.5.1.1 12. Pemasangan 1 buah bak cuci piring stainlessteel bh 267,093.75 1.00 267,093.75 - - - - 1.00 267,093.75

5 A.5.1.1 14. Pemasangan 1 buah floor drain bh 26,331.25 1.00 26,331.25 - - - - 1.00 26,331.25

6 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm bh 318,991.75 4.00 1,275,967.00 - - 4.00 1,275,967.00 - -

7 A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4” m1 45,375.00 1.00 45,375.00 2.00 90,750.00 - - 3.00 136,125.00

8 A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” m1 14,250.50 32.00 456,016.00 - - 7.00 99,753.50 25.00 356,262.50

9 A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” m` 33,310.75 12.00 399,729.00 - - 8.00 266,486.00 4.00 133,243.00

10 A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4” m1 72,312.63 12.00 867,751.50 - - 4.00 289,250.50 8.00 578,501.00

JUMLAH VIII 4,325,321.00 90,750.00 1,931,457.00 2,484,614.00


IX PEKERJAAN BESI DAN ALUMUNIUM
1 Ls Pintu besi Folding Gate ( Terpasang ) m2 275,000.00 8.44 2,321,550.00 - - - - 8.44 2,321,550.00

JUMLAH IX 2,321,550.00 - - 2,321,550.00


X PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh 25,185.60 27.00 680,011.20 - - - - 27.00 680,011.20

2 A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu bh 21,921.63 36.00 789,178.50 - - - - 36.00 789,178.50

3 A.4.6.2.9. Pemasangan 1 buah kait angin bh 25,641.00 36.00 923,076.00 - - - - 36.00 923,076.00

4 A.4.6.2.11. Pemasangan 1 buah kunci slot bh 97,083.25 15.00 1,456,248.75 - - - - 15.00 1,456,248.75

5 A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm bh 115,371.85 13.33 1,537,906.76 - - 6.43 741,841.00 6.90 796,065.77

6 Ditaksir Grendel pintu bh 10,000.00 29.00 290,000.00 - - - - 29.00 290,000.00

JUMLAH X 5,676,421.21 - 741,841.00 4,934,580.22


XI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 199,798.50 113.03 22,583,723.95 0.29 57,541.97 - - 113.32 22,641,265.92

2 A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm m2 213,889.50 2.50 534,189.03 - - - - 2.50 534,189.03

3 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm m1 38,173.30 9.90 377,915.67 - - 3.95 150,784.54 5.95 227,131.14

4 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20cm x 20cm m2 204,226.00 14.85 3,032,756.10 0.35 71,479.10 - - 15.20 3,104,235.20

5 A.4.4.3.58. Pemasangan 1 m2 dinding batu tempel susun sirih m2 239,442.50 5.58 1,336,089.15 - - 5.58 1,336,089.15 - -

JUMLAH XI 27,864,673.90 129,021.07 1,486,873.69 26,506,821.28


XII PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 17,222.98 629.00 10,833,251.28 - - 71.46 1,230,793.41 557.54 9,602,457.87

cat dasar, 2 lapis cat penutup )

2 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 13,132.90 147.91 1,942,487.24 5.87 77,103.26 - - 153.78 2,019,590.49

JUMLAH XII 12,775,738.51 77,103.26 1,230,793.41 11,622,048.36


XIII PEKERJAAN INSTALASI LISTRIK
1 Ls Pemasangan meter listrik 900 watt unit 750,000.00 1.00 750,000.00 - - - - 1.00 750,000.00

2 Ls Titik Lampu Titik 85,000.00 30.00 2,550,000.00 - - - - 30.00 2,550,000.00

3 Ls Saklar ganda bh 22,500.00 1.00 22,500.00 1.00 22,500.00 - - 2.00 45,000.00

4 Ls Saklar tunggal bh 20,000.00 10.00 200,000.00 - - 2.00 40,000.00 8.00 160,000.00

5 Ls Stop kontak bh 22,500.00 8.00 180,000.00 - - - - 8.00 180,000.00

6 Ls lampu pijar 5W Philips bh 10,000.00 5.00 50,000.00 - - - - 5.00 50,000.00

7 Ls Lampu SL 18 Watt Phillips bh 35,500.00 17.00 603,500.00 - - - - 17.00 603,500.00


JUMLAH XIII 4,356,000.00 22,500.00 40,000.00 4,338,500.00
XIV PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm termasuk pas dinding m1 75,500.00 45.50 3,435,250.00 - - 45.50 3,435,250.00 - -

2 Ls Tanah Subur m3 120,000.00 - - 0.54 64,800.00 - - 0.54 64,800.00

3 Ls Pembuatan taman m2 225,000.00 - - 0.90 202,500.00 - - 0.90 202,500.00

4 Ls Membuat Septictank bh 1,150,000.00 1.00 1,150,000.00 - - - - 1.00 1,150,000.00


5 Ls Membuat Peresapan bh 750,000.00 1.00 750,000.00 - - - - 1.00 750,000.00

JUMLAH XIV 5,335,250.00 267,300.00 3,435,250.00 2,167,300.00

JUMLAH ( F ) 357,328,729.64 10,303,791.80 35,487,852.84 332,144,668.60


JUMLAH TOTAL 3,022,634,361.70 402,833,530.19 402,834,174.17 3,022,633,717.72
PPN 10 % 302,263,436.17 40,283,353.02 40,283,417.42 302,263,371.77
JUMLAH TOTAL 3,324,897,797.87 443,116,883.21 443,117,591.59 3,324,897,089.49
DIBULATKAN 3,324,897,000.00 443,116,000.00 443,117,000.00 3,324,897,000.00

KEBUMEN, 14 DESEMBER 2017

PANITIA PENELITI PENYEDIA JASA :


PELAKSANAAN KONTRAK ( PPPK ) : PT. MULTI KARYA KEBUMEN
Mengetahui, Menyetujui,
Kepala Bidang Cipta Karya KaSi Bangunan Gedung Bidang Cipta Karya 1. AGUS HANAFI, SST. MT 1………………… 1. RAHMAT 1………………..
Dinas Pekerjaan Umum Kab.Kebumen Dinas Pekerjaan Umum Kab.Kebumen Ketua Direktur Utama
Selaku Pejabat Pembuat Komitmen Selaku Pejabat PelaksanaTeknis Kegiatan
2. FRESTIANA MANURUNG, S.Ars 2………………… 2. IKBALUDIN 2………………..
Sekretaris Pelaksana

3. DWI AMDI 3………………… KONSULTAN PENGAWAS :


Anggota CV. RUMAH KEONG
Ir. MISRODIN BACHTIAR ACHMAD, ST, M.Ec.Dev
NIP. 19610327 199403 1 001 NIP. 19770429 200604 1 004 4. TEGUH AHMAD SUMARSONO, ST 4………………… 1. TEGUH BUDIONO, ST 1………………..
Anggota Site Engeneer

5. SISWORO 5………………… 2. IRWAN SETIADI, ST 2………………..


Anggota Inspector
DAFTAR PERHITUNGAN MUTHUAL CHECK AKHIR ( MC.100 )

KEGIATAN : PEMBANGUNAN GEDUNG KANTOR NOMOR KONTRAK : 050 / 099 / SP / VI / 2017


PEKERJAAN : PEMBANGUNAN GEDUNG KANTOR KECAMATAN SRUWENG 027 / PT.MKK / SP / VI / 2017
LOKASI : KEC. SRUWENG, KEBUMEN TANGGAL KONTRAK : 19 JUNI 2016
TAHUN ANGGARAN : 2017 NILAI KONTRAK : Rp. 3.324.897.000, -
PENYEDIA JASA : PT. MULTI KARYA KEBUMEN

CCO.2 MC.100
SELISIH TAMBAH SELISIH KURANG
HARGA
NO KODE ANALISA JENIS PEKERJAAN SAT SATUAN JUMLAH JUMLAH JUMLAH JUMLAH KET
( Rp ) VOLUME HARGA VOLUME HARGA VOLUME HARGA VOLUME HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp )

A PAGAR DAN HALAMAN


I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls 500,000.00 1.00 500,000.00 - - - - 1.00 500,000.00

2 A.2.2.1.15b. 1 M2 pasang paving blok segi 4, t = 6 cm m2 79,000.00 1,714.50 135,445,752.80 - - - - 1,714.50 135,445,752.80

JUMLAH I 135,945,752.80 - - 135,945,752.80


II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 49,018.75 71.15 3,487,647.30 - - - - 71.15 3,487,647.30

2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 16,339.58 21.34 348,764.73 - - - - 21.34 348,764.73

3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 118,607.50 7.63 905,004.88 - - - - 7.63 905,004.88

4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 83,393.75 4,421.88 368,757,203.50 - - - - 4,421.88 368,757,203.50

JUMLAH II 373,498,620.41 - - 373,498,620.41


III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 516,466.50 174.79 90,274,728.93 - - - - 174.79 90,274,728.93

JUMLAH III 90,274,728.93 - - 90,274,728.93


IV PEKERJAAN DINDING
1 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 97,798.25 42.21 4,128,064.13 - - - - 42.21 4,128,064.13

campuran 1SP : 3PP

2 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 92,281.75 67.11 6,192,566.83 - - - - 67.11 6,192,566.83

campuran 1SP : 6PP

3 A. 4.4.1.20. Pemasangan 1 cm2 dinding conblock HB10 campuran 1SP :3PP m2 103,248.53 267.60 27,629,564.75 - - - - 267.60 27,629,564.75

JUMLAH IV 37,950,195.72 - - 37,950,195.72


V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 38,633.10 242.57 9,371,138.35 - - - - 242.57 9,371,138.35

2 A.4.4.2.23. Pemasangan 1 m2 plesteran ciprat 1SP : 2PP m2 35,337.50 4.82 170,234.87 - - - - 4.82 170,234.87
3 A.4.4.2.27. Pemasangan 1 m2 acian m2 23,815.00 242.57 5,776,747.39 - - - - 242.57 5,776,747.39

4 Ls Sponengan m1 20,000.00 73.60 1,472,000.00 - - - - 73.60 1,472,000.00

JUMLAH V 16,790,120.61 - - 16,790,120.61


VI PEKERJAAN BETON
1 Rabat Beton

A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 756,474.46 6.83 5,169,273.68 - - - - 6.83 5,169,273.68

slump (12 ± 2) cm, w/c = 0,87

2 Sloof 15/25

A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 166,529.00 40.95 6,819,362.55 - - - - 40.95 6,819,362.55

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 875.51 11,432,191.08 - - - - 875.51 11,432,191.08

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 4.80 4,259,580.69 - - - - 4.80 4,259,580.69

slump (12 ± 2) cm, w/c = 0,87

3 Foot Plat 80/80

A.4.1.1.20. Pemasangan 1 m2 bekisting untuk pondasi m2 154,429.00 13.44 2,075,525.76 - - - - 13.44 2,075,525.76

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 250.30 3,268,360.54 - - - - 250.30 3,268,360.54

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 2.02 1,790,635.46 - - - - 2.02 1,790,635.46

slump (12 ± 2) cm, w/c = 0,87

4 Kolom 20/20

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 31.02 7,824,857.04 - - - - 31.02 7,824,857.04

A.4.1.1.22.b Pemasangan 1 m2 bekisting untuk kolom m2 197,116.70 23.70 4,671,665.79 - - - - 23.70 4,671,665.79

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 389.56 5,086,743.32 - - - - 389.56 5,086,743.32

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 8.37 7,436,253.26 - - - - 8.37 7,436,253.26

slump (12 ± 2) cm, w/c = 0,87

5 Kolom 11/11

A.4.1.1.35 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 63,268.15 6.75 427,060.01 - - - - 6.75 427,060.01

6 Ring Balok 10/15

A.4.1.1.36 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 86,781.75 205.90 17,868,362.33 - - - - 205.90 17,868,362.33

JUMLAH VI 78,129,871.51 - - 78,129,871.51


VII PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 145,153.25 3.32 481,241.09 - - - - 3.32 481,241.09

JUMLAH VII 481,241.09 - - 481,241.09


VIII PEKERJAAN BESI DAN ALUMUNIUM
1 LS Pasang Pagar dan Pintu Besi Ulir (Lengkap) m2 455,000.00 62.02 28,218,645.00 - - - - 62.02 28,218,645.00

2 Ditaksir Pasang Grill Saluran m' 180,000.00 23.70 4,266,000.00 - - - - 23.70 4,266,000.00

3 LS Pembuatan Tiang Bendera bh 2,500,000.00 1.00 2,500,000.00 - - - - 1.00 2,500,000.00

JUMLAH VIII 34,984,645.00 - - 34,984,645.00


IX PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 17,222.98 242.57 4,177,735.71 - - - - 242.57 4,177,735.71

cat dasar, 2 lapis cat penutup )

JUMLAH IX 4,177,735.71 - - 4,177,735.71


X PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm, termasuk pasangan dinding m1 75,500.00 219.00 16,534,500.00 - - - - 219.00 16,534,500.00

2 Ls Tanah subur m3 120,000.00 6.43 771,840.00 - - - - 6.43 771,840.00

3 Ls Pembuatan taman m2 225,000.00 16.08 3,618,000.00 - - - - 16.08 3,618,000.00

4 Ls Pasang logo keramik ( uk 35 x 45 ) cm bh 750,000.00 1.00 750,000.00 - - - - 1.00 750,000.00

5 Ls Pasang tulisan ( bahan alumunium ) unit 3,500,000.00 1.00 3,500,000.00 - - - - 1.00 3,500,000.00

6 Ditaksir Pasang gorong gorong dia.100 m' 350,000.00 17.00 5,950,000.00 - - - - 17.00 5,950,000.00

7 Ditaksir Pasang atap galvalume m2 450,000.00 66.39 29,874,375.00 - - - - 66.39 29,874,375.00

JUMLAH X 60,998,715.00 - - 60,998,715.00

833,231,626.77 - - 833,231,626.77

B PEMBANGUNAN PENDOPO
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls 500,000.00 1.00 500,000.00 - - - - 1.00 500,000.00

JUMLAH I 500,000.00 - - 500,000.00


II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 49,018.75 40.20 1,970,357.68 - - - - 40.20 1,970,357.68

2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 16,339.58 12.06 197,035.77 - - - - 12.06 197,035.77

3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 118,607.50 35.16 4,170,239.70 - - - - 35.16 4,170,239.70

4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 83,393.75 117.24 9,777,065.37 - - - - 117.24 9,777,065.37

JUMLAH II 16,114,698.51 - - 16,114,698.51


III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 516,466.50 26.95 13,918,772.18 - - - - 26.95 13,918,772.18

2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 279,576.00 14.00 3,914,064.00 - - - - 14.00 3,914,064.00

JUMLAH III 17,832,836.18 - - 17,832,836.18


IV PEKERJAAN DINDING
1 A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 201,619.00 5.70 1,149,228.30 - - - - 5.70 1,149,228.30

campuran 1SP : 3PP

2 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 97,798.25 28.82 2,818,545.57 - - - - 28.82 2,818,545.57

campuran 1SP : 3PP

3 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 92,281.75 125.07 11,541,678.47 - - - - 125.07 11,541,678.47

campuran 1SP : 6PP

JUMLAH IV 15,509,452.34 - - 15,509,452.34


V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 38,633.10 314.35 12,144,314.99 - - - - 314.35 12,144,314.99

2 A.4.4.2.27. Pemasangan 1 m2 acian m2 23,815.00 658.24 15,675,985.60 - - - - 658.24 15,675,985.60

3 Ls Sponengan m1 20,000.00 295.40 5,908,000.00 - - - - 295.40 5,908,000.00

JUMLAH V 33,728,300.59 - - 33,728,300.59


VI PEKERJAAN BETON
1 Lantai kerja

A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 712,475.42 22.78 16,230,190.10 - - - - 22.78 16,230,190.10

slump (12 ± 2) cm, w/c = 0,87

2 Rabat Beton

A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 756,474.46 6.12 4,631,061.01 - - - - 6.12 4,631,061.01

slump (12 ± 2) cm, w/c = 0,87

3 Pondasi Foot Plat 80/80

A.4.1.1.20. Pemasangan 1 m2 bekisting untuk pondasi m2 154,429.00 5.76 889,511.04 - - - - 5.76 889,511.04

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 440.66 5,754,061.16 - - - - 440.66 5,754,061.16

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 2.65 2,353,761.89 - - - - 2.65 2,353,761.89

slump (12 ± 2) cm, w/c = 0,87

4 Sloof 15/25

A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 166,529.00 21.60 3,597,026.40 - - - - 21.60 3,597,026.40

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 478.22 6,244,513.07 - - - - 478.22 6,244,513.07

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 3.24 2,877,806.99 - - - - 3.24 2,877,806.99

slump (12 ± 2) cm, w/c = 0,87

5 Kolom 30/30

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 23.40 5,902,696.80 - - - - 23.40 5,902,696.80

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 197,116.70 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 399.62 5,218,168.03 - - - - 399.62 5,218,168.03

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 3.51 3,117,624.24 - - - - 3.51 3,117,624.24

slump (12 ± 2) cm, w/c = 0,87

6 Kolom 20/20

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 52.68 13,288,635.36 - - - - 52.68 13,288,635.36

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 197,116.70 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 732.75 9,568,142.16 - - - - 732.75 9,568,142.16

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 5.27 4,679,101.00 - - - - 5.27 4,679,101.00

slump (12 ± 2) cm, w/c = 0,87

7 Kolom 15/15

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 1.95 491,891.40 - - - - 1.95 491,891.40

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 197,116.70 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 56.58 738,811.74 - - - - 56.58 738,811.74

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 0.29 257,581.49 - - - - 0.29 257,581.49

slump (12 ± 2) cm, w/c = 0,87


8 Balok 20/35

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 64.80 16,517,001.60 - - - - 64.80 16,517,001.60

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 197,116.70 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 1,070.64 13,980,229.76 - - - - 1,070.64 13,980,229.76

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 10.08 8,953,177.31 - - - - 10.08 8,953,177.31

slump (12 ± 2) cm, w/c = 0,87

9 Balok 15/20

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 11.40 2,905,768.80 - - - - 11.40 2,905,768.80

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 197,116.70 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 252.40 3,295,795.03 - - - - 252.40 3,295,795.03

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 1.71 1,518,842.58 - - - - 1.71 1,518,842.58

slump (12 ± 2) cm, w/c = 0,87

10 Balok latai 15/20

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 3.20 815,654.40 - - - - 3.20 815,654.40

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 197,116.70 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 70.89 925,669.21 - - - - 70.89 925,669.21

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 0.48 426,341.78 - - - - 0.48 426,341.78

slump (12 ± 2) cm, w/c = 0,87

11 Ring balok 15/20

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 16.50 4,205,718.00 - - - - 16.50 4,205,718.00

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 197,116.70 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 365.31 4,770,154.05 - - - - 365.31 4,770,154.05

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 2.48 2,202,765.85 - - - - 2.48 2,202,765.85

slump (12 ± 2) cm, w/c = 0,87

12 Shading

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 319,352.00 1.50 479,028.00 - - - - 1.50 479,028.00

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 241,666.70 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 17.63 230,209.45 - - - - 17.63 230,209.45

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 0.24 213,170.89 - - - - 0.24 213,170.89

slump (12 ± 2) cm, w/c = 0,87

JUMLAH VI #REF! #REF! #REF! #REF!


VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 9,944,550.00 0.42 4,176,711.00 - - - - 0.42 4,176,711.00

kayu kelas II (kruink )

2 A.4.6.1.13.a Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas II (kruink m3 10,071,050.00 0.85 8,560,392.50 - - - - 0.85 8,560,392.50

3 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 10,651,671.25 0.48 5,112,802.20 - - - - 0.48 5,112,802.20

3 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 9,274,100.00 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
4 A.4.6.1.15.a Pemasangan 1 m3 konstruksi gordeng expose , kayu kelas II ( kruink ) m3 10,778,171.25 3.19 34,382,366.29 - - - - 3.19 34,382,366.29

5 A.4.6.1.17. Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II m2 153,051.25 33.00 5,050,691.25 - - - - 33.00 5,050,691.25

6 A.4.6.1.17.a Pemasangan 1 m2 rangka atap genteng beton expose , m2 178,351.25 410.50 73,213,188.13 - - - - 410.50 73,213,188.13

kayu kelas II ( kruink )

7 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) motif k m1 22,500.00 142.00 3,195,000.00 - - - - 142.00 3,195,000.00

8 A.4.5.2.3.a Pemasangan 1 m2 atap genteng palentong besar/super m2 59,793.25 443.50 26,518,306.38 - - - - 443.50 26,518,306.38
9 A.4.5.2.6. Pemasangan 1 m’ bubung genteng palentong besar m1 63,189.50 61.70 3,898,792.15 - - - - 61.70 3,898,792.15

10 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 77,038.50 27.90 2,149,374.15 - - - - 27.90 2,149,374.15

11 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 34,538.90 27.90 963,635.31 - - - - 27.90 963,635.31

ukuran (120x240x9) mm, tebal 9 mm

12 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 32,937.30 410.50 13,520,761.65 - - - - 410.50 13,520,761.65

ukuran (120x240x9) mm, tebal 4 mm

13 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 19,049.25 19.00 361,935.75 - - - - 19.00 361,935.75

14 Ls Pasang papan pembungkus kolom beton (2x30) cm, m2 325,000.00 28.32 9,204,000.00 - - - - 28.32 9,204,000.00

kayu jati finishing politur

15 A.4.6.1.2. Membuat dan memasang rangka pagar, kayu kruink m3 10,925,172.50 0.68 7,429,117.30 - - - - 0.68 7,429,117.30

16 A.4.6.1.10. Membuat dan memasang pagar, kayu kruink m2 667,975.00 27.65 18,469,508.75 - - - - 27.65 18,469,508.75

JUMLAH VII #REF! #REF! #REF! #REF!


VIII PEKERJAAN BESI DAN ALUMUNIUM
1 A.4.2.1.18. Pemasangan 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm m1 103,541.63 10.00 1,035,416.25 - - - - 10.00 1,035,416.25

JUMLAH VIII 1,035,416.25 - - 1,035,416.25


IX PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh 25,185.60 12.00 302,227.20 - - - - 12.00 302,227.20

2 Ditaksir Grendel pintu bh 10,000.00 6.00 60,000.00 - - - - 6.00 60,000.00

JUMLAH IX 362,227.20 - - 362,227.20


X PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 145,153.25 276.82 40,181,322.67 - - - - 276.82 40,181,322.67

2 A.4.4.3.58. Pemasangan 1 m2 dinding natu tempel candi m2 239,442.50 28.80 6,895,944.00 - - - - 28.80 6,895,944.00

JUMLAH X 47,077,266.67 - - 47,077,266.67


XI PEKERJAAN PENGECATAN
1 A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis m2 44,480.15 538.81 23,966,349.62 - - - - 538.81 23,966,349.62

cat dasar, 2 lapis cat penutup)

2 A.4.7.1.7. Pelaburan 1 m2 bidang kayu dengan politur m2 49,024.25 100.17 4,910,759.12 - - - - 100.17 4,910,759.12

2 A.4.7.1.7. Pelaburan 1 m2 bidang kayu dengan politur m2 43,478.49 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

3 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 17,222.98 658.24 11,336,851.06 - - - - 658.24 11,336,851.06

cat dasar, 2 lapis cat penutup )

4 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 13,132.90 438.40 5,757,463.36 - - - - 438.40 5,757,463.36

JUMLAH XI #REF! #REF! #REF! #REF!


XII PEKERJAAN INSTALASI LISTRIK
1 Ls Titik Lampu Titik 85,000.00 13.00 1,105,000.00 - - - - 13.00 1,105,000.00

2 Ls Saklar ganda bh 22,500.00 6.00 135,000.00 - - - - 6.00 135,000.00

3 Ls Stop Kontak bh 22,500.00 2.00 45,000.00 - - - - 2.00 45,000.00

4 Ls MCB bh 250,000.00 1.00 250,000.00 - - - - 1.00 250,000.00


5 Ls Lampu gantung artistik bh 1,750,000.00 1.00 1,750,000.00 - - - - 1.00 1,750,000.00
6 Ls Lampu SL 18 watt phillips bh 35,500.00 11.00 390,500.00 - - - - 11.00 390,500.00

JUMLAH XII 3,675,500.00 - - 3,675,500.00


XIII PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm termasuk pas dinding m1 75,500.00 49.60 3,744,800.00 - - - - 49.60 3,744,800.00

2 Ditaksir Pasang logo keramik ( ukuran 35 x 45 ) cm unit 750,000.00 1.00 750,000.00 - - - - 1.00 750,000.00

3 Ditaksir Pasang Tulisan ( bahan alumunium ) unit 2,250,000.00 1.00 2,250,000.00 - - - - 1.00 2,250,000.00

4 Ditaksir Pasang papan back ground unit 3,500,000.00 1.00 3,500,000.00 - - - - 1.00 3,500,000.00

JUMLAH XIII 10,244,800.00 - - 10,244,800.00

#REF! #REF! #REF! #REF!

C KANTOR PELAYANAN
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls 500,000.00 1.00 500,000.00 - - - - 1.00 500,000.00

JUMLAH I 500,000.00 - - 500,000.00


II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 49,018.75 66.71 3,269,942.78 - - - - 66.71 3,269,942.78

2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 16,339.58 18.67 305,092.70 - - - - 18.67 305,092.70

3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 118,607.50 26.22 3,110,321.57 - - - - 26.22 3,110,321.57

4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 83,393.75 67.09 5,595,211.92 - - - - 67.09 5,595,211.92

JUMLAH II 12,280,568.97 - - 12,280,568.97


III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 516,466.50 93.27 48,168,893.71 - - - - 93.27 48,168,893.71

2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 279,576.00 31.12 8,700,405.12 - - - - 31.12 8,700,405.12

JUMLAH III 56,869,298.83 - - 56,869,298.83


IV PEKERJAAN DINDING
1 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 97,798.25 125.83 12,305,464.81 - - - - 125.83 12,305,464.81

campuran 1SP : 3PP

2 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 92,281.75 413.44 38,152,948.26 - - - - 413.44 38,152,948.26

campuran 1SP : 6PP

JUMLAH IV 50,458,413.07 - - 50,458,413.07

V PEKERJAAN PLESTERAN

1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 38,633.10 1,036.45 40,041,338.31 - - - - 1,036.45 40,041,338.31

2 A.4.4.2.27. Pemasangan 1 m2 acian m2 23,815.00 1,082.02 25,768,353.93 - - - - 1,082.02 25,768,353.93

3 Ls Sponengan m1 20,000.00 31.10 622,000.00 - - - - 31.10 622,000.00

JUMLAH V 66,431,692.24 - - 66,431,692.24


VI PEKERJAAN BETON
1 Lantai kerja

A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 712,475.42 18.44 13,140,647.31 - - - - 18.44 13,140,647.31

slump (12 ± 2) cm, w/c = 0,87

2 Rabat Beton

A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 756,474.46 6.41 4,846,429.29 - - - - 6.41 4,846,429.29

slump (12 ± 2) cm, w/c = 0,87

3 Pondasi Foot Plat 80/80

A.4.1.1.20. Pemasangan 1 m2 bekisting untuk pondasi m2 154,429.00 1.28 197,669.12 - - - - 1.28 197,669.12

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 97.92 1,278,684.90 - - - - 97.92 1,278,684.90

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 888,212.03 0.59 522,268.68 - - - - 0.59 522,268.68

slump (12 ± 2) cm, w/c = 0,87

4 Sloof 15/20

A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 166,529.00 49.88 8,306,466.52 - - - - 49.88 8,306,466.52

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 1,251.53 16,342,259.72 - - - - 1,251.53 16,342,259.72

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 7.48 6,285,020.57 - - - - 7.48 6,285,020.57

slump (12 ± 2) cm,w/c=0,87

5 Kolom 30/30

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 13.08 3,299,456.16 - - - - 13.08 3,299,456.16

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 154.97 2,023,571.14 - - - - 154.97 2,023,571.14

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 1.96 1,646,877.05 - - - - 1.96 1,646,877.05

slump (12 ± 2) cm,w/c=0,87

6 Kolom 20/20

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 59.20 14,933,318.40 - - - - 59.20 14,933,318.40

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 971.18 12,681,498.48 - - - - 971.18 12,681,498.48

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 5.62 4,722,167.86 - - - - 5.62 4,722,167.86

slump (12 ± 2) cm,w/c=0,87

7 Kolom 15/15

A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 252,252.00 113.00 28,504,476.00 - - - - 113.00 28,504,476.00

A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 68,390.19 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

8 Balok 15/40

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 282,612.00 2.28 644,355.36 - - - - 2.28 644,355.36

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 197,116.70 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 47.74 623,380.57 - - - - 47.74 623,380.57

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.33 277,280.32 - - - - 0.33 277,280.32

slump (12 ± 2) cm, w/c = 0,87

9 Ring balok 15/30


A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 282,612.00 7.55 2,133,720.60 - - - - 7.55 2,133,720.60

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 197,116.70 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 179.24 2,340,484.55 - - - - 179.24 2,340,484.55
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 1.21 1,016,694.50 - - - - 1.21 1,016,694.50

slump (12 ± 2) cm, w/c = 0,87

10 Ring balok 15/20

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 86,781.75 34.51 2,994,838.19 - - - - 34.51 2,994,838.19

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 1,060.48 13,847,562.26 - - - - 1,060.48 13,847,562.26

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 5.18 4,352,460.77 - - - - 5.18 4,352,460.77

slump (12 ± 2) cm, w/c = 0,87

11 Balok Latai 10/15

A.4.1.1.36. Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 86,781.75 97.00 8,417,829.75 - - - - 97.00 8,417,829.75

12 Plat atap

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 222,552.00 25.00 5,563,800.00 - - - - 25.00 5,563,800.00

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 855.60 11,172,275.07 - - - - 855.60 11,172,275.07

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 6.00 5,041,460.35 - - - - 6.00 5,041,460.35

slump (12 ± 2) cm, w/c = 0,87

13 Shading

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 319,352.00 31.39 10,024,459.28 - - - - 31.39 10,024,459.28

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 241,666.70 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 363.52 4,746,780.54 - - - - 363.52 4,746,780.54

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 5.02 4,220,038.41 - - - - 5.02 4,220,038.41

slump (12 ± 2) cm, w/c = 0,87

14 Plat lisplang

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 319,352.00 3.51 1,120,925.52 - - - - 3.51 1,120,925.52

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 241,666.70 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 69.32 905,168.43 - - - - 69.32 905,168.43

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.70 588,170.37 - - - - 0.70 588,170.37

slump (12 ± 2) cm, w/c = 0,87

JUMLAH VI #REF! #REF! #REF! #REF!


VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.11. Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I m3 652,159.75 24.36 15,886,611.51 - - - - 24.36 15,886,611.51

2 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 9,944,550.00 6.99 69,512,404.50 - - - - 6.99 69,512,404.50

kayu kelas II (kruink )

3 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 10,651,671.25 3.54 37,706,916.23 - - - - 3.54 37,706,916.23

3 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 9,274,100.00 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

4 A.4.6.1.17. Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II m2 153,051.25 523.90 80,183,549.88 - - - - 523.90 80,183,549.88

5 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) motif k m1 22,500.00 102.00 2,295,000.00 - - - - 102.00 2,295,000.00

6 A.4.5.2.3.a Pemasangan 1 m2 atap genteng palentong besar/super m2 59,793.25 523.90 31,325,683.68 - - - - 523.90 31,325,683.68

7 A.4.5.2.6. Pemasangan 1 m’ bubung genteng palentong besar m1 63,189.50 61.60 3,892,473.20 - - - - 61.60 3,892,473.20
8 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 77,038.50 408.39 31,461,984.13 - - - - 408.39 31,461,984.13

9 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 34,538.90 368.87 12,740,467.66 - - - - 368.87 12,740,467.66

ukuran (120x240x9) mm, tebal 9 mm


10 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 32,937.30 39.52 1,301,682.10 - - - - 39.52 1,301,682.10

ukuran (120x240x9) mm, tebal 4 mm

11 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 19,049.25 277.10 5,278,547.18 - - - - 277.10 5,278,547.18

JUMLAH VII #REF! #REF! #REF! #REF!


VIII PEKERJAAN SANITASI
1 A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen bh 290,097.50 4.00 1,160,390.00 - - - - 4.00 1,160,390.00

2 A.5.1.1 14. Pemasangan 1 buah floor drain bh 26,331.25 5.00 131,656.25 - - - - 5.00 131,656.25

3 A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4” m1 45,375.00 7.00 317,625.00 - - - - 7.00 317,625.00

4 A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” m1 14,250.50 69.80 994,684.90 - - - - 69.80 994,684.90

5 A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” m` 33,310.75 14.50 483,005.88 - - - - 14.50 483,005.88

6 A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4” m1 72,312.63 13.00 940,064.13 - - - - 13.00 940,064.13

7 Ditaksir Fiber glas tangki air kap 1100 ltr bh 1,450,000.00 1.00 1,450,000.00 - - - - 1.00 1,450,000.00

8 Ditaksir Pasang sumur bor m' 180,000.00 8.00 1,440,000.00 - - - - 8.00 1,440,000.00

9 Ditaksir Pasang mesin pompa air listrik PW-120 jet bh 1,250,000.00 1.00 1,250,000.00 - - - - 1.00 1,250,000.00

10 Ditaksir Ember dan gayung bh 100,000.00 4.00 400,000.00 - - - - 4.00 400,000.00

JUMLAH VIII 8,567,426.15 - - 8,567,426.15


IX PEKERJAAN BESI DAN ALUMUNIUM
1 A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium m1 81,947.80 489.42 40,106,892.28 - - - - 489.42 40,106,892.28

2 A.4.2.1.13. Pemasangan 1 m2 pintu/jendela kaca rangka alluminium m2 466,303.75 82.07 38,269,548.76 - - - - 82.07 38,269,548.76

3 Ls Pemasangan pintu tempered t = 12 mm ( komplit ) unit 10,000,000.00 4.00 40,000,000.00 - - - - 4.00 40,000,000.00

JUMLAH IX 118,376,441.04 - - 118,376,441.04


X PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh 25,185.60 42.00 1,057,795.20 - - - - 42.00 1,057,795.20

2 A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu bh 21,921.63 304.00 6,664,174.00 - - - - 304.00 6,664,174.00

3 A.4.6.2.9. Pemasangan 1 buah kait angin bh 25,641.00 304.00 7,794,864.00 - - - - 304.00 7,794,864.00

4 A.4.6.2.11. Pemasangan 1 buah kunci slot bh 97,083.25 14.00 1,359,165.50 - - - - 14.00 1,359,165.50

5 A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm bh 115,371.85 180.80 20,859,230.48 - - - - 180.80 20,859,230.48

6 Ditaksir Grendel pintu bh 10,000.00 170.00 1,700,000.00 - - - - 170.00 1,700,000.00

JUMLAH X 39,435,229.18 - - 39,435,229.18


XI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 145,153.25 360.23 52,288,990.71 - - - - 360.23 52,288,990.71

2 A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm m2 213,889.50 8.64 1,848,005.28 - - - - 8.64 1,848,005.28

3 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm m1 38,173.30 22.75 868,442.58 - - - - 22.75 868,442.58

4 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20cm x 20cm m2 204,226.00 40.94 8,361,114.55 - - - - 40.94 8,361,114.55

JUMLAH XI 63,366,553.12 - - 63,366,553.12


XII PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 17,222.98 1,082.02 18,635,603.41 - - - - 1,082.02 18,635,603.41
cat dasar, 2 lapis cat penutup )

2 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 13,132.90 408.39 5,363,345.03 - - - - 408.39 5,363,345.03

JUMLAH XII 23,998,948.44 - - 23,998,948.44


XIII PEKERJAAN INSTALASI LISTRIK
1 Ls Pasang meteran listrik baru 5500 Va unit 10,000,000.00 1.00 10,000,000.00 - - - - 1.00 10,000,000.00

2 Ls Titik Lampu Titik 85,000.00 57.00 4,845,000.00 - - - - 57.00 4,845,000.00

3 Ls Saklar ganda bh 22,500.00 3.00 67,500.00 - - - - 3.00 67,500.00

4 Ls Saklar tunggal bh 20,000.00 13.00 260,000.00 - - - - 13.00 260,000.00

5 Ls stop kontak bh 22,500.00 15.00 337,500.00 - - - - 15.00 337,500.00

6 Ls lampu pijar 5W Philips bh 10,000.00 5.00 50,000.00 - - - - 5.00 50,000.00

7 Ls Lampu SL 18 Watt Phillips bh 35,500.00 37.00 1,313,500.00 - - - - 37.00 1,313,500.00

JUMLAH XIII 16,873,500.00 - - 16,873,500.00


XIV PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm termasuk pas dinding m1 75,500.00 112.36 8,483,180.00 - - - - 112.36 8,483,180.00

2 A.5.1.1 15. Membuat Septic Tank bh 1,150,000.00 2.00 2,300,000.00 - - - - 2.00 2,300,000.00

3 Ditaksir Membuat peresapan bh 750,000.00 2.00 1,500,000.00 - - - - 2.00 1,500,000.00

4 Ditaksir Tanah Subur m3 120,000.00 8.96 1,075,320.00 - - - - 8.96 1,075,320.00

5 Ditaksir Pembuatan taman m2 225,000.00 59.34 13,351,500.00 - - - - 59.34 13,351,500.00

JUMLAH XIV 26,710,000.00 - - 26,710,000.00

#REF! #REF! #REF! #REF!

D SERBA GUNA
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls 500,000.00 1.00 500,000.00 - - - - 1.00 500,000.00

JUMLAH I 500,000.00 - - 500,000.00


II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 49,018.75 30.01 1,471,111.51 - - - - 30.01 1,471,111.51

2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 16,339.58 9.00 147,111.15 - - - - 9.00 147,111.15

3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 118,607.50 9.88 1,171,323.19 - - - - 9.88 1,171,323.19

4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 83,393.75 17.97 1,498,244.61 - - - - 17.97 1,498,244.61

JUMLAH II 4,287,790.46 - - 4,287,790.46

III PEKERJAAN PONDASI

1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 516,466.50 32.53 16,801,946.41 - - - - 32.53 16,801,946.41

2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 279,576.00 13.52 3,779,867.52 - - - - 13.52 3,779,867.52

JUMLAH III 20,581,813.93 - - 20,581,813.93


IV PEKERJAAN DINDING
1 A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 201,619.00 - - - - - - - -

campuran 1SP : 3PP

2 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 97,798.25 73.18 7,156,386.94 - - - - 73.18 7,156,386.94

campuran 1SP : 3PP

3 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 92,281.75 121.38 11,201,168.04 - - - - 121.38 11,201,168.04

campuran 1SP : 6PP

JUMLAH IV 18,357,554.99 - - 18,357,554.99


V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 38,633.10 370.29 14,305,450.60 - - - - 370.29 14,305,450.60

2 A.4.4.2.23. Pemasangan 1 m2 plesteran ciprat 1SP : 2PP m2 32,392.25 1.33 43,146.48 - - - - 1.33 43,146.48

3 A.4.4.2.27. Pemasangan 1 m2 acian m2 23,815.00 379.36 9,034,458.40 - - - - 379.36 9,034,458.40

4 Ls Sponengan m1 15,000.00 48.00 720,000.00 - - - - 48.00 720,000.00

JUMLAH V 24,103,055.48 - - 24,103,055.48


VI PEKERJAAN BETON
1 Lantai kerja

A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 712,475.42 6.50 4,627,973.16 - - - - 6.50 4,627,973.16

slump (12 ± 2) cm, w/c = 0,87

2 Rabat Beton

A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 756,474.46 2.71 2,053,737.39 - - - - 2.71 2,053,737.39

slump (12 ± 2) cm, w/c = 0,87

3 Sloof 15/25

A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 166,529.00 21.13 3,518,757.77 - - - - 21.13 3,518,757.77

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 519.31 6,781,059.10 - - - - 519.31 6,781,059.10

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 3.17 2,663,571.55 - - - - 3.17 2,663,571.55

slump (12 ± 2) cm,w/c=0,87

4 Kolom 20/20

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 5.14 1,296,575.28 - - - - 5.14 1,296,575.28

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 51.67 674,697.82 - - - - 51.67 674,697.82

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 0.51 428,524.13 - - - - 0.51 428,524.13

slump (12 ± 2) cm,w/c=0,87

5 Kolom 15/15

A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 252,252.00 94.80 23,913,489.60 - - - - 94.80 23,913,489.60

6 Ring balok 15/30

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 6.00 1,529,352.00 - - - - 6.00 1,529,352.00

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 106.21 1,386,871.59 - - - - 106.21 1,386,871.59
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.68 571,365.51 - - - - 0.68 571,365.51

slump (12 ± 2) cm, w/c = 0,87

7 Ring balok 15/20

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 86,781.75 15.10 1,310,404.43 - - - - 15.10 1,310,404.43

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 463.99 6,058,700.22 - - - - 463.99 6,058,700.22

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 2.27 1,907,352.50 - - - - 2.27 1,907,352.50

slump (12 ± 2) cm, w/c = 0,87

8 Balok Latai 10/15

A.4.1.1.36. Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 86,781.75 35.00 3,037,361.25 - - - - 35.00 3,037,361.25

9 Plat atap

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 222,552.00 11.69 2,600,965.22 - - - - 11.69 2,600,965.22

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 199.97 2,611,173.27 - - - - 199.97 2,611,173.27

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 1.17 981,992.45 - - - - 1.17 981,992.45

slump (12 ± 2) cm, w/c = 0,87

10 Shading

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 319,352.00 3.65 1,166,273.50 - - - - 3.65 1,166,273.50

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 74.32 970,449.72 - - - - 74.32 970,449.72

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.58 490,971.02 - - - - 0.58 490,971.02

slump (12 ± 2) cm, w/c = 0,87

JUMLAH VI 70,581,618.48 - - 70,581,618.48


VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.11. Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I m3 652,159.75 7.98 5,204,234.81 - - - - 7.98 5,204,234.81

2 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 9,944,550.00 1.52 15,115,716.00 - - - - 1.52 15,115,716.00

kayu kelas II (kruink ) -

3 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 10,651,671.25 1.34 14,273,239.48 - - - - 1.34 14,273,239.48

3 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 9,274,100.00 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

4 A.4.6.1.16. Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II m2 152,556.25 183.51 27,995,261.81 - - - - 183.51 27,995,261.81

5 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) motif k m1 22,500.00 54.74 1,231,650.00 - - - - 54.74 1,231,650.00

6 A.4.5.2.1. Pemasangan 1 m2 atap genteng palentong kecil m2 59,211.63 183.51 10,865,795.04 - - - - 183.51 10,865,795.04

7 A.4.5.2.4. Pemasangan 1 m’ bubung genteng palentong m1 65,939.50 34.00 2,241,943.00 - - - - 34.00 2,241,943.00

8 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 77,038.50 178.26 13,732,921.53 - - - - 178.26 13,732,921.53

9 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 34,538.90 139.17 4,806,692.37 - - - - 139.17 4,806,692.37

ukuran (120x240x9) mm, tebal 9 mm

10 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 32,937.30 39.09 1,287,617.87 - - - - 39.09 1,287,617.87

ukuran (120x240x9) mm, tebal 4 mm

11 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 19,049.25 132.30 2,520,215.78 - - - - 132.30 2,520,215.78

JUMLAH VII #REF! #REF! #REF! #REF!


VIII PEKERJAAN SANITASI
1 A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen bh 290,097.50 2.00 580,195.00 - - - - 2.00 580,195.00

2 A.5.1.1 14. Pemasangan 1 buah floor drain bh 26,331.25 2.00 52,662.50 - - - - 2.00 52,662.50

3 A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4” m1 45,375.00 2.00 90,750.00 - - - - 2.00 90,750.00

4 A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” m1 14,250.50 40.00 570,020.00 - - - - 40.00 570,020.00

5 A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” m` 33,310.75 3.50 116,587.63 - - - - 3.50 116,587.63

6 A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4” m1 72,312.63 7.00 506,188.38 - - - - 7.00 506,188.38

7 Ditaksir Pasang sumur bor m' 180,000.00 8.00 1,440,000.00 - - - - 8.00 1,440,000.00

8 Ditaksir Pasang mesin pompa air listrik PW-120 jet bh 1,250,000.00 1.00 1,250,000.00 - - - - 1.00 1,250,000.00

9 Ditaksir Ember dan gayung unit 100,000.00 2.00 200,000.00 - - - - 2.00 200,000.00

10 Ditaksir Fiber glas tangki air kap 1100 ltr unit 1,450,000.00 1.00 1,450,000.00 - - - - 1.00 1,450,000.00

JUMLAH VIII 6,256,403.50 - - 6,256,403.50


IX PEKERJAAN BESI DAN ALUMUNIUM
1 A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium m1 81,947.80 169.96 13,927,848.09 - - - - 169.96 13,927,848.09

2 A.4.2.1.13. Pemasangan 1 m2 pintu kaca rangka alluminium m2 466,303.75 29.45 13,732,645.44 - - - - 29.45 13,732,645.44

JUMLAH IX 27,660,493.53 - - 27,660,493.53


X PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh 25,185.60 15.00 377,784.00 - - - - 15.00 377,784.00

2 A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu bh 21,921.63 118.00 2,586,751.75 - - - - 118.00 2,586,751.75

3 A.4.6.2.9. Pemasangan 1 buah kait angin bh 25,641.00 118.00 3,025,638.00 - - - - 118.00 3,025,638.00

4 A.4.6.2.11. Pemasangan 1 buah kunci slot bh 97,083.25 5.00 485,416.25 - - - - 5.00 485,416.25

5 A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm bh 115,371.85 38.12 4,397,974.92 - - - - 38.12 4,397,974.92

6 Ditaksir Grendel pintu bh 10,000.00 64.00 640,000.00 - - - - 64.00 640,000.00

JUMLAH X 11,513,564.92 - - 11,513,564.92


XI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 199,798.50 123.85 24,744,045.23 - - - - 123.85 24,744,045.23

1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 137,257.45 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

2 A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm m2 213,889.50 6.07 1,297,774.54 - - - - 6.07 1,297,774.54

2 A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm m2 172,545.18 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

3 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm m1 38,173.30 9.40 358,829.02 - - - - 9.40 358,829.02

3 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm m1 18,995.31 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

4 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20cm x 20cm m2 204,226.00 14.10 2,879,586.60 - - - - 14.10 2,879,586.60

JUMLAH XI #REF! #REF! #REF! #REF!


XII PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 17,222.98 379.36 6,533,707.80 - - - - 379.36 6,533,707.80

cat dasar, 2 lapis cat penutup )

2 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 13,132.90 178.26 2,341,077.32 - - - - 178.26 2,341,077.32
JUMLAH XII 8,874,785.12 - - 8,874,785.12
XIII PEKERJAAN INSTALASI LISTRIK
1 Ls Titik Lampu Titik 85,000.00 28.00 2,380,000.00 - - - - 28.00 2,380,000.00

2 Ls Saklar ganda bh 22,500.00 2.00 45,000.00 - - - - 2.00 45,000.00

3 Ls Saklar tunggal bh 20,000.00 6.00 120,000.00 - - - - 6.00 120,000.00

4 Ls stop kontak bh 22,500.00 6.00 135,000.00 - - - - 6.00 135,000.00

5 Ls lampu pijar 5W Philips bh 10,000.00 6.00 60,000.00 - - - - 6.00 60,000.00

6 Ls Lampu SL 18 Watt Phillips bh 35,500.00 16.00 568,000.00 - - - - 16.00 568,000.00

7 Ls Pemindahan meteren lama 5500 watt unit 750,000.00 1.00 750,000.00 - - - - 1.00 750,000.00

JUMLAH XIII 4,058,000.00 - - 4,058,000.00


XIV PEKERJAAN LAIN-LAIN
1 Ls Membuat Septic Tank bh 1,150,000.00 1.00 1,150,000.00 - - - - 1.00 1,150,000.00

2 Ls Membuat peresapan bh 750,000.00 1.00 750,000.00 - - - - 1.00 750,000.00

3 Ls Tanah Subur m3 120,000.00 0.40 47,880.00 - - - - 0.40 47,880.00

4 Ls Pembuatan taman m2 225,000.00 1.00 224,437.50 - - - - 1.00 224,437.50

JUMLAH XIV 2,172,317.50 - - 2,172,317.50

#REF! #REF! #REF! #REF!

E RUMAH DINAS

I PEKERJAAN PERSIAPAN

1 Ditaksir Pengukuran dan pemasangan bauwplank ls 500,000.00 1.00 500,000.00 - - - - 1.00 500,000.00

JUMLAH I 500,000.00 - - 500,000.00

II PEKERJAAN TANAH

1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 49,018.75 30.07 1,473,954.60 - - - - 30.07 1,473,954.60

2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 16,339.58 8.64 141,174.00 - - - - 8.64 141,174.00

3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 118,607.50 9.39 1,113,831.17 - - - - 9.39 1,113,831.17

4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 83,393.75 13.70 1,142,240.86 - - - - 13.70 1,142,240.86

JUMLAH II 3,871,200.63 - - 3,871,200.63

III PEKERJAAN PONDASI

1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 516,466.50 39.60 20,452,073.40 - - - - 39.60 20,452,073.40

2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 279,576.00 14.40 4,025,894.40 - - - - 14.40 4,025,894.40

JUMLAH III 24,477,967.80 - - 24,477,967.80

IV PEKERJAAN DINDING

1 A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 201,619.00 1.20 241,942.80 - - - - 1.20 241,942.80

campuran 1SP : 3PP


2 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 97,798.25 34.43 3,367,193.75 - - - - 34.43 3,367,193.75

campuran 1SP : 3PP

3 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 92,281.75 238.04 21,966,600.12 - - - - 238.04 21,966,600.12

campuran 1SP : 6PP

JUMLAH IV 25,575,736.67 - - 25,575,736.67

V PEKERJAAN PLESTERAN

1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 38,633.10 540.98 20,899,734.44 - - - - 540.98 20,899,734.44

2 A.4.4.2.27. Pemasangan 1 m2 acian m2 23,815.00 557.54 13,277,760.33 - - - - 557.54 13,277,760.33

JUMLAH V 34,177,494.76 - - 34,177,494.76

VI PEKERJAAN BETON

1 Lantai kerja

A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 712,475.42 5.79 4,125,873.92 - - - - 5.79 4,125,873.92

slump (12 ± 2) cm, w/c = 0,87

2 Rabat Beton

A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 756,474.46 2.74 2,074,434.53 - - - - 2.74 2,074,434.53

slump (12 ± 2) cm, w/c = 0,87

3 Sloof 15/25

A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 166,529.00 23.25 3,871,799.25 - - - - 23.25 3,871,799.25

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 571.64 7,464,375.08 - - - - 571.64 7,464,375.08

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 3.49 2,932,449.44 - - - - 3.49 2,932,449.44

slump (12 ± 2) cm,w/c=0,87

4 Kolom 15/25

A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 252,252.00 32.40 8,172,964.80 - - - - 32.40 8,172,964.80

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 526.20 6,871,027.52 - - - - 526.20 6,871,027.52

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 840,243.39 2.57 2,159,425.52 - - - - 2.57 2,159,425.52

slump (12 ± 2) cm,w/c=0,87

5 Kolom 15/15

A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 63,268.15 56.00 3,543,016.40 - - - - 56.00 3,543,016.40

6 Ring balok 15/20

A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 254,892.00 18.60 4,740,991.20 - - - - 18.60 4,740,991.20

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 559.86 7,310,553.90 - - - - 559.86 7,310,553.90

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 2.79 2,344,279.06 - - - - 2.79 2,344,279.06

slump (12 ± 2) cm, w/c = 0,87


7 Balok Latai 10/15

A.4.1.1.36. Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 86,781.75 32.50 2,820,406.88 - - - - 32.50 2,820,406.88

8 Shading

A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 222,552.00 6.66 1,482,196.32 - - - - 6.66 1,482,196.32

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 135.42 1,768,290.66 - - - - 135.42 1,768,290.66

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 1.07 895,800.28 - - - - 1.07 895,800.28

slump (12 ± 2) cm, w/c = 0,87

9 Meja dapur

A.4.1.1.33. Membuat 1 m3 dinding beton bertulang (150 kg besi + bekisting) m2 222,552.00 1.27 282,641.04 - - - - 1.27 282,641.04

A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg 13,057.83 11.52 150,426.14 - - - - 11.52 150,426.14

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 840,243.39 0.21 178,467.70 - - - - 0.21 178,467.70

slump (12 ± 2) cm, w/c = 0,87

JUMLAH VI 63,189,419.64 - - 63,189,419.64

VII PEKERJAAN KAYU, ATAP DAN PLAFOND

1 A.4.6.1.2. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu m3
k 10,925,172.50 0.95 10,378,913.88 - - - - 0.95 10,378,913.88

2 A.4.6.1.5. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I atau m2 591,717.50 14.20 8,402,388.50 - - - - 14.20 8,402,388.50

3 A.4.6.1.6. Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I m2 410,058.00 3.96 1,623,829.68 - - - - 3.96 1,623,829.68

4 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 9,944,550.00 2.02 20,087,991.00 - - - - 2.02 20,087,991.00

kayu kelas II (kruink )

5 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 10,651,671.25 1.92 20,451,208.80 - - - - 1.92 20,451,208.80

6 A.4.6.1.16. Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II m2 152,556.25 194.68 29,699,650.75 - - - - 194.68 29,699,650.75

7 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) motif k m1 22,500.00 52.30 1,176,750.00 - - - - 52.30 1,176,750.00

8 A.4.5.2.1. Pemasangan 1 m2 atap genteng palentong kecil m2 59,211.63 194.68 11,527,319.16 - - - - 194.68 11,527,319.16

9 A.4.5.2.4. Pemasangan 1 m’ bubung genteng palentong m1 65,939.50 46.71 3,080,034.05 - - - - 46.71 3,080,034.05

10 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 77,038.50 153.78 11,847,057.57 - - - - 153.78 11,847,057.57

11 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 34,538.90 115.82 4,000,226.32 - - - - 115.82 4,000,226.32

ukuran (120x240x9) mm, tebal 9 mm

12 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 32,937.30 37.96 1,250,398.72 - - - - 37.96 1,250,398.72

ukuran (120x240x9) mm, tebal 4 mm

13 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 19,049.25 116.89 2,226,666.83 - - - - 116.89 2,226,666.83

14 Ls Pemasangan rooster kayu bh 25,000.00 9.00 225,000.00 - - - - 9.00 225,000.00

JUMLAH VII 125,977,435.25 - - 125,977,435.25


VIII PEKERJAAN SANITASI

1 A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen bh 290,097.50 1.00 290,097.50 - - - - 1.00 290,097.50

2 A.5.1.1 5. Pemasangan 1 buah wastafel bh 696,960.00 1.00 696,960.00 - - - - 1.00 696,960.00

4 A.5.1.1 12. Pemasangan 1 buah bak cuci piring stainlessteel bh 267,093.75 1.00 267,093.75 - - - - 1.00 267,093.75

5 A.5.1.1 14. Pemasangan 1 buah floor drain bh 26,331.25 1.00 26,331.25 - - - - 1.00 26,331.25

7 A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4” m1 45,375.00 3.00 136,125.00 - - - - 3.00 136,125.00

8 A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” m1 14,250.50 25.00 356,262.50 - - - - 25.00 356,262.50

9 A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” m` 33,310.75 4.00 133,243.00 - - - - 4.00 133,243.00

10 A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4” m1 72,312.63 8.00 578,501.00 - - - - 8.00 578,501.00

JUMLAH VIII 2,484,614.00 - - 2,484,614.00

IX PEKERJAAN BESI DAN ALUMUNIUM

1 Ls Pintu besi Folding Gate ( Terpasang ) m2 275,000.00 8.44 2,321,550.00 - - - - 8.44 2,321,550.00

JUMLAH IX 2,321,550.00 - - 2,321,550.00


X PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh 25,185.60 27.00 680,011.20 - - - - 27.00 680,011.20

2 A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu bh 21,921.63 36.00 789,178.50 - - - - 36.00 789,178.50

3 A.4.6.2.9. Pemasangan 1 buah kait angin bh 25,641.00 36.00 923,076.00 - - - - 36.00 923,076.00

4 A.4.6.2.11. Pemasangan 1 buah kunci slot bh 97,083.25 15.00 1,456,248.75 - - - - 15.00 1,456,248.75

5 A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm bh 115,371.85 6.90 796,065.77 - - - - 6.90 796,065.77

6 Ditaksir Grendel pintu bh 10,000.00 29.00 290,000.00 - - - - 29.00 290,000.00

JUMLAH X 4,934,580.22 - - 4,934,580.22


XI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 199,798.50 113.32 22,641,265.92 - - - - 113.32 22,641,265.92

2 A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm m2 213,889.50 2.50 534,189.03 - - - - 2.50 534,189.03

3 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm m1 38,173.30 5.95 227,131.14 - - - - 5.95 227,131.14

4 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20cm x 20cm m2 204,226.00 15.20 3,104,235.20 - - - - 15.20 3,104,235.20

JUMLAH XI 26,506,821.28 - - 26,506,821.28


XII PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 17,222.98 557.54 9,602,457.87 - - - - 557.54 9,602,457.87

cat dasar, 2 lapis cat penutup )

2 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 13,132.90 153.78 2,019,590.49 - - - - 153.78 2,019,590.49

JUMLAH XII 11,622,048.36 - - 11,622,048.36


XIII PEKERJAAN INSTALASI LISTRIK
1 Ls Pemasangan meter listrik 900 watt unit 750,000.00 1.00 750,000.00 - - - - 1.00 750,000.00
2 Ls Titik Lampu Titik 85,000.00 30.00 2,550,000.00 - - - - 30.00 2,550,000.00
3 Ls Saklar ganda bh 22,500.00 2.00 45,000.00 - - - - 2.00 45,000.00
4 Ls Saklar tunggal bh 20,000.00 8.00 160,000.00 - - - - 8.00 160,000.00
5 Ls stop kontak bh 22,500.00 8.00 180,000.00 - - - - 8.00 180,000.00
6 Ls lampu pijar 5W Philips bh 10,000.00 5.00 50,000.00 - - - - 5.00 50,000.00
7 Ls Lampu SL 18 Watt Phillips bh 35,500.00 17.00 603,500.00 - - - - 17.00 603,500.00
JUMLAH XIII 4,338,500.00 - - 4,338,500.00
XIV PEKERJAAN LAIN-LAIN
1 Ls Tanah Subur m3 120,000.00 0.54 64,800.00 - - - - 0.54 64,800.00
2 Ls Pembuatan taman m2 225,000.00 0.90 202,500.00 - - - - 0.90 202,500.00
3 Ls Membuat Septictank bh 1,150,000.00 1.00 1,150,000.00 - - - - 1.00 1,150,000.00
4 Ls Membuat Peresapan bh 750,000.00 1.00 750,000.00 - - - - 1.00 750,000.00

JUMLAH XIV 2,167,300.00 - - 2,167,300.00

JUMLAH ( F ) 332,144,668.60 - - 332,144,668.60


JUMLAH TOTAL #REF! #REF! #REF! #REF!
PPN 10 % #REF! #REF! #REF! #REF!
JUMLAH TOTAL #REF! #REF! #REF! #REF!
DIBULATKAN #REF! #REF! #REF! #REF!

KEBUMEN, 14 DESEMBER 2017

PANITIA PENELITI PENYEDIA JASA :


PELAKSANAAN KONTRAK ( PPPK ) : PT. MULTI KARYA KEBUMEN
Mengetahui, Menyetujui,
Kepala Bidang Cipta Karya KaSi Bangunan Gedung Bidang Cipta Karya 1. AGUS HANAFI, SST. MT 1………………… 1. RAHMAT 1………………..
Dinas Pekerjaan Umum Kab.Kebumen Dinas Pekerjaan Umum Kab.Kebumen Ketua Direktur Utama
Selaku Pejabat Pembuat Komitmen Selaku Pejabat PelaksanaTeknis Kegiatan
2. FRESTIANA MANURUNG, S.Ars 2………………… 2. IKBALUDIN 2………………..
Sekretaris Pelaksana

3. DWI AMDI 3………………… KONSULTAN PENGAWAS :


Anggota CV. RUMAH KEONG
Ir. MISRODIN BACHTIAR ACHMAD, ST, M.Ec.Dev
NIP. 19610327 199403 1 001 NIP. 19770429 200604 1 004 4. TEGUH AHMAD SUMARSONO, ST 4………………… 1. TEGUH BUDIONO, ST 1………………..
Anggota Site Engeneer

5. SISWORO 5………………… 2. IRWAN SETIADI, ST 2………………..


Anggota Inspector
M21 (2)

LAPORAN MINGGUAN

KEGIATAN : PEMBANGUNAN GEDUNG KANTOR MINGGU KE : #REF!


PEKERJAAN : PEMBANGUNAN GEDUNG KANTOR KECAMATAN SRUWENG WAKTU : #REF!
LOKASI : KEC. SRUWENG, KEBUMEN
TAHUN ANGGARAN : 2017

BOBOT
HARGA NILAI
CCO.1 S / D MINGGU LALU MINGGU INI S / D MINGGU INI TIMBAN
KODE SATUAN BOBOT
NO JENIS PEKERJAAN SAT G
ANALISA
(Rp) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)

A PAGAR DAN HALAMAN


I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan bauwplank Ditaksir ls 500,000.00 1.00 500,000.00 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 1 M2 pasang paving blok segi 4, t = 8 cm A.2.2.1.15a. m2 84,000.00 - - 0.00 #REF!
3 A.2.2.1.15b. 1 M2 pasang paving blok segi 4, t = 6 cm A.2.2.1.15b. m2 79,000.00 1,714.50 135,445,752.80 4.48 - 0.00 - 0.00 - 0.00 0.00
JUMLAH I 135,945,752.80 #REF!
II PEKERJAAN TANAH #REF!
1 Penggalian 1 m3 tanah biasa sedalam 1 m A.2.3.1.1. m3 49,018.75 71.15 3,487,647.30 0.12 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pengurugan kembali 1 m3 galian tanah A.2.3.1.9. m3 16,339.58 21.34 348,764.73 0.01 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3 Pengurugan 1 m3 dengan pasir urug A.2.3.1.11. m3 118,607.50 7.63 905,004.88 0.03 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Pengurugan 1 m3 tanah cadas padat A.2.3.1.14.a m3 83,393.75 4,421.88 368,757,203.50 12.20 #REF! #REF! - 0.00 #REF! #REF! #REF!
5 Pengurugan 1 m3 sirtu padat A.2.3.1.14. m3 136,193.75 - - 0.00 #REF!
JUMLAH II 373,498,620.41 #REF!
III PEKERJAAN PONDASI #REF!
1 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP A.3.2.1.4. m3 516,466.50 174.79 90,274,728.93 2.99 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 m3 batu kosong (anstamping) A.3.2.1.9. m3 279,576.00 - 0.00 #REF! 0.00 - 0.00 #REF! 0.00 0.00
JUMLAH III 90,274,728.93 #REF!
IV PEKERJAAN DINDING #REF!
1 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu A. 4.4.1.8. m2 97,798.25 42.21 4,128,064.13 0.14 #REF! #REF! - 0.00 #REF! #REF! #REF!
campuran 1SP : 3PP #REF!
2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu A. 4.4.1.11. m2 92,281.75 67.11 6,192,566.83 0.20 #REF! #REF! - 0.00 #REF! #REF! #REF!
campuran 1SP : 6PP #REF!
3 Pemasangan 1 cm2 dinding conblock HB10 campuran 1SP :3PP A. 4.4.1.20. m2 103,248.53 267.60 27,629,564.75 0.91 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH IV 37,950,195.72 #REF!
V PEKERJAAN PLESTERAN #REF!
1 Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. A.4.4.2.6. m2 38,633.10 242.57 9,371,138.35 0.31 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP A.4.4.2.23. m2 35,337.50 4.82 170,234.87 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Pemasangan 1 m2 acian A.4.4.2.27. m2 23,815.00 242.57 5,776,747.39 0.19 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Sponengan Ls m1 20,000.00 73.60 1,472,000.00 0.05 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH V 16,790,120.61 #REF!
VI PEKERJAAN BETON #REF!
1 Rabat Beton
Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), A.4.1.1.1. m3 756,474.46 6.83 5,169,273.68 0.17 - 0.00 6.83 0.17 6.83 0.17 100.00
slump (12 ± 2) cm, w/c = 0,87 -
2 Sloof 15/25 - #REF!
Pemasangan 1 m2 bekisting untuk sloof A.4.1.1.21. m2 166,529.00 40.95 6,819,362.55 0.23 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 875.51 11,432,191.08 0.38 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 888,212.03 4.80 4,259,580.69 0.14 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!

Page 223 of 297


M21 (2)

BOBOT
HARGA NILAI
CCO.1 S / D MINGGU LALU MINGGU INI S / D MINGGU INI TIMBAN
KODE SATUAN BOBOT
NO JENIS PEKERJAAN SAT G
ANALISA
(Rp) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)
3 Foot Plat 80/80 - #REF!
Pemasangan 1 m2 bekisting untuk pondasi A.4.1.1.20. m2 154,429.00 13.44 2,075,525.76 0.07 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 250.30 3,268,360.54 0.11 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 888,212.03 2.02 1,790,635.46 0.06 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
4 Kolom 20/20 - #REF!
Pemasangan 1 m2 bekisting untuk kolom A.4.1.1.22.a m2 252,252.00 31.02 7,824,857.04 0.26 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 197,116.70 23.70 4,671,665.79 0.15 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 389.56 5,086,743.32 0.17 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 888,212.03 8.37 7,436,253.26 0.25 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
5 Kolom 11/11 - #REF!
Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm A.4.1.1.35 m1 63,268.15 6.75 427,060.01 0.01 #REF! 0.00 - 0.00 #REF! 0.00 0.00
6 Ring Balok 10/15 - #REF!
Membuat 1 m’ ring balok beton bertulang (10 x 15) cm A.4.1.1.36 m1 86,781.75 205.90 17,868,362.33 0.59 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH VI 78,129,871.51 #REF!
VII PEKERJAAN PENUTUP LANTAI DAN DINDING #REF!
1 Pemasangan 1m2 lantai keramik ukuran 40cm x40cm A.4.4.3.9.a m2 145,153.25 3.32 481,241.09 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 m2 dinding batu tempel candi A.4.4.3.58. m2 236,692.50 - - 0.00 #REF! 0.00 - 0.00 #REF! 0.00 0.00
JUMLAH VII 481,241.09 #REF!
VIII PEKERJAAN BESI DAN ALUMUNIUM #REF!
1 Pintu besi terpasang dan pengecatan Ditaksir m2 400,000.00 - - 0.00 #REF! 0.00 - 0.00 #REF! 0.00 0.00
2 Pagar besi terpasang dan pengecatan Ditaksir m2 350,000.00 - - 0.00 #REF! 0.00 - 0.00 #REF! 0.00 0.00
3 Pemasangan 1 kg besi profil A.4.2.1.1. kg 30,843.01 - - 0.00 #REF! 0.00 - 0.00 #REF! 0.00 0.00
4 Pasang kawat duri Ditaksir m1 10,000.00 - - 0.00 #REF! 0.00 - 0.00 #REF! 0.00 0.00
5 Pasang Pagar dan Pintu Besi Ulir (Lengkap) LS m2 455,000.00 62.02 28,218,645.00 0.93 #REF! #REF! - 0.00 #REF! #REF! #REF!
6 Pasang Grill Saluran Ditaksir m' 180,000.00 23.70 4,266,000.00 0.14 #REF! #REF! - 0.00 #REF! #REF! #REF!
7 Pasang Roda Pintu dia. 2,5" LS bh 50,000.00 - - 0.00 #REF!
8 Gembok LS bh 25,000.00 - - 0.00 #REF!
9 Pembuatan Tiang Bendera LS bh 2,500,000.00 1.00 2,500,000.00 0.08 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH VIII 34,984,645.00 #REF!
IX PEKERJAAN PENGECATAN #REF!
1 Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis A.4.7.1.10. m2 17,222.98 242.57 4,177,735.71 0.14 #REF! #REF! - 0.00 #REF! #REF! #REF!
cat dasar, 2 lapis cat penutup ) - #REF!
2 Pengecatan permukaan baja (galbani) secara semprot dengan A.4.7.1.10. m2 82,832.60 - - 0.00 #REF!
sistem 1 lapis cat mutakhir dengan tebal 200 um #REF!
JUMLAH IX 4,177,735.71 #REF!
X PEKERJAAN INSTALASI LISTRIK #REF!
1 Titik Lampu Ditaksir ttk 85,000.00 - - 0.00 #REF! 0.00 - 0.00 #REF! 0.00 0.00
2 Saklar Ganda Ditaksir bh 22,500.00 - - 0.00 #REF! 0.00 - 0.00 #REF! 0.00 0.00
3 Pemasangan Lampu Taman Ditaksir bh 525,000.00 - - 0.00 #REF! 0.00 - 0.00 #REF! 0.00 0.00
JUMLAH X - #REF!
XI PEKERJAAN LAIN-LAIN #REF!

Page 224 of 297


M21 (2)

BOBOT
HARGA NILAI
CCO.1 S / D MINGGU LALU MINGGU INI S / D MINGGU INI TIMBAN
KODE SATUAN BOBOT
NO JENIS PEKERJAAN SAT G
ANALISA
(Rp) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)
1 Pasang saluran U 20 cm, termasuk pasangan dinding Ls m1 75,500.00 219.00 16,534,500.00 0.55 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Tanah subur Ls m3 120,000.00 6.43 771,840.00 0.03 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Pembuatan taman Ls m2 225,000.00 16.08 3,618,000.00 0.12 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Pasang logo keramik ( uk 35 x 45 ) cm Ls bh 750,000.00 1.00 750,000.00 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
5 Pasang tulisan ( bahan alumunium ) Ls unit 3,500,000.00 1.00 3,500,000.00 0.12 #REF! #REF! - 0.00 #REF! #REF! #REF!
6 Pasang gorong gorong dia.100 Ditaksir m' 350,000.00 17.00 5,950,000.00 0.20 - 0.00 - 0.00 - 0.00 0.00
7 Pasang atap galvalume Ditaksir m2 450,000.00 66.39 29,874,375.00 0.99 - 0.00 - 0.00 - 0.00 0.00
JUMLAH XI 60,998,715.00 #REF!

JUMLAH ( A ) 833,231,626.77 #REF!

Page 225 of 297


M21 (2)

BOBOT
HARGA NILAI
CCO.1 S / D MINGGU LALU MINGGU INI S / D MINGGU INI TIMBAN
KODE SATUAN BOBOT
NO JENIS PEKERJAAN SAT G
ANALISA
(Rp) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)

B PEMBANGUNAN PENDOPO #REF!


I PEKERJAAN PERSIAPAN #REF!
1 Pengukuran dan pemasangan bauwplank Ditaksir ls 500,000.00 1.00 500,000.00 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 1 M2 pasang paving blok segi 4, t = 8 cm A.2.2.1.15a. ls 84,000.00 - - 0.00 #REF!
JUMLAH I 500,000.00 #REF!
II PEKERJAAN TANAH #REF!
1 Penggalian 1 m3 tanah biasa sedalam 1 m A.2.3.1.1. m3 49,018.75 40.20 1,970,357.68 0.07 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pengurugan kembali 1 m3 galian tanah A.2.3.1.9. m3 16,339.58 12.06 197,035.77 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Pengurugan 1 m3 dengan pasir urug A.2.3.1.11. m3 118,607.50 35.16 4,170,239.70 0.14 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Pengurugan 1 m3 tanah cadas padat A.2.3.1.14.a m3 83,393.75 117.24 9,777,065.37 0.32 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH II 16,114,698.51 #REF!
III PEKERJAAN PONDASI #REF!
1 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP A.3.2.1.4. m3 516,466.50 26.95 13,918,772.18 0.46 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 m3 batu kosong (anstamping) A.3.2.1.9. m3 279,576.00 14.00 3,914,064.00 0.13 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH III 17,832,836.18 #REF!
IV PEKERJAAN DINDING #REF!
1 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu A. 4.4.1.2. m2 201,619.00 5.70 1,149,228.30 0.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
campuran 1SP : 3PP - #REF!
2 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu A. 4.4.1.8. m2 97,798.25 28.82 2,818,545.57 0.09 #REF! #REF! - 0.00 #REF! #REF! #REF!
campuran 1SP : 3PP - #REF!
3 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu A. 4.4.1.11. m2 92,281.75 125.07 11,541,678.47 0.38 #REF! #REF! - 0.00 #REF! #REF! #REF!
campuran 1SP : 6PP #REF!
JUMLAH IV 15,509,452.34 #REF!
V PEKERJAAN PLESTERAN #REF!
1 Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. A.4.4.2.6. m2 38,633.10 314.35 12,144,314.99 0.40 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 m2 acian A.4.4.2.27. m2 23,815.00 658.24 15,675,985.60 0.52 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Sponengan Ls m1 20,000.00 295.40 5,908,000.00 0.20 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH V 33,728,300.59 #REF!
VI PEKERJAAN BETON #REF!
1 Lantai kerja #REF!
Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), A.4.1.1.4. m3 712,475.42 22.78 16,230,190.10 0.54 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
2 Rabat Beton - #REF!
Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), A.4.1.1.1. m3 756,474.46 6.12 4,631,061.01 0.15 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
3 Pondasi Foot Plat 80/80 - #REF!
Pemasangan 1 m2 bekisting untuk pondasi A.4.1.1.20. m2 154,429.00 5.76 889,511.04 0.03 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 440.66 5,754,061.16 0.19 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.7. m3 888,212.03 2.65 2,353,761.89 0.08 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
4 Sloof 15/25 - #REF!
Pemasangan 1 m2 bekisting untuk sloof A.4.1.1.21. m2 166,529.00 21.60 3,597,026.40 0.12 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 478.22 6,244,513.07 0.21 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.7. m3 888,212.03 3.24 2,877,806.99 0.10 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!

Page 226 of 297


M21 (2)

BOBOT
HARGA NILAI
CCO.1 S / D MINGGU LALU MINGGU INI S / D MINGGU INI TIMBAN
KODE SATUAN BOBOT
NO JENIS PEKERJAAN SAT G
ANALISA
(Rp) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)
5 Kolom 30/30 - #REF!
Pemasangan 1 m2 bekisting untuk kolom A.4.1.1.22.a m2 252,252.00 23.40 5,902,696.80 0.20 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 399.62 5,218,168.03 0.17 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.7. m3 888,212.03 3.51 3,117,624.24 0.10 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
6 Kolom 20/20 - #REF!
Pemasangan 1 m2 bekisting untuk kolom A.4.1.1.22.a m2 252,252.00 52.68 13,288,635.36 0.44 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 732.75 9,568,142.16 0.32 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.7. m3 888,212.03 5.27 4,679,101.00 0.15 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
7 Kolom 15/15 - #REF!
Pemasangan 1 m2 bekisting untuk kolom A.4.1.1.22.a m2 252,252.00 1.95 491,891.40 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 56.58 738,811.74 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.7. m3 888,212.03 0.29 257,581.49 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
8 Balok 20/35 - #REF!
Pemasangan 1 m2 bekisting untuk balok A.4.1.1.23.a m2 254,892.00 64.80 16,517,001.60 0.55 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 1,070.64 13,980,229.76 0.46 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.7. m3 888,212.03 10.08 8,953,177.31 0.30 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
9 Balok 15/20 - #REF!
Pemasangan 1 m2 bekisting untuk balok A.4.1.1.23.a m2 254,892.00 11.40 2,905,768.80 0.10 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 252.40 3,295,795.03 0.11 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.7. m3 888,212.03 1.71 1,518,842.58 0.05 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
10 Balok latai 15/20 - #REF!
Pemasangan 1 m2 bekisting untuk balok A.4.1.1.23.a m2 254,892.00 3.20 815,654.40 0.03 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 70.89 925,669.21 0.03 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.7. m3 888,212.03 0.48 426,341.78 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
11 Ring balok 15/20 - #REF!
Pemasangan 1 m2 bekisting untuk balok A.4.1.1.23.a m2 254,892.00 16.50 4,205,718.00 0.14 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 365.31 4,770,154.05 0.16 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.7. m3 888,212.03 2.48 2,202,765.85 0.07 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
12 Shading - #REF!
Pemasangan 1 m2 bekisting untuk lantai A.4.1.1.24.a m2 319,352.00 1.50 479,028.00 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.7. m3 13,057.83 17.63 230,209.45 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 888,212.03 0.24 213,170.89 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH VI 147,280,110.59 #REF!
VII PEKERJAAN KAYU, ATAP DAN PLAFOND #REF!
1 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, A.4.6.1.13. m3 9,944,550.00 0.42 4,176,711.00 0.14 #REF! #REF! - 0.00 #REF! #REF! #REF!
kayu kelas II (kruink ) - #REF!
2 Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas II (kruink ) A.4.6.1.13.a m3 10,071,050.00 0.85 8,560,392.50 0.28 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) A.4.6.1.15. m3 10,651,671.25 0.48 5,112,802.20 0.17 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Pemasangan 1 m3 konstruksi gordeng expose , kayu kelas II ( kruink ) A.4.6.1.15.a m3 10,778,171.25 3.19 34,382,366.29 1.14 #REF! #REF! - 0.00 #REF! #REF! #REF!
5 Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II A.4.6.1.17. m2 153,051.25 33.00 5,050,691.25 0.17 #REF! #REF! - 0.00 #REF! #REF! #REF!
6 Pemasangan 1 m2 rangka atap genteng beton expose , A.4.6.1.17.a m2 178,351.25 410.50 73,213,188.13 2.42 #REF! #REF! - 0.00 #REF! #REF! #REF!
kayu kelas II ( kruink ) - #REF!

Page 227 of 297


M21 (2)

BOBOT
HARGA NILAI
CCO.1 S / D MINGGU LALU MINGGU INI S / D MINGGU INI TIMBAN
KODE SATUAN BOBOT
NO JENIS PEKERJAAN SAT G
ANALISA
(Rp) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)
7 Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) motif kay Ls m1 22,500.00 142.00 3,195,000.00 0.11 #REF! #REF! - 0.00 #REF! #REF! #REF!
8 Pemasangan 1 m2 atap genteng palentong besar/super A.4.5.2.3.a m2 59,793.25 443.50 26,518,306.38 0.88 #REF! #REF! - 0.00 #REF! #REF! #REF!
9 Pemasangan 1 m’ bubung genteng palentong besar A.4.5.2.6. m1 63,189.50 61.70 3,898,792.15 0.13 #REF! #REF! - 0.00 #REF! #REF! #REF!
10 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun A.4.6.1.20. m2 77,038.50 27.90 2,149,374.15 0.07 #REF! #REF! - 0.00 #REF! #REF! #REF!
11 Pemasangan 1 m2 langit-langit gypsum board A.4.5.1.7. m2 34,538.90 27.90 963,635.31 0.03 #REF! #REF! - 0.00 #REF! #REF! #REF!
ukuran (120x240x9) mm, tebal 9 mm - #REF!
12 Pemasangan 1 m2 langit-langit kalsiboard A.4.5.1.7.a m2 32,937.30 410.50 13,520,761.65 0.45 #REF! #REF! - 0.00 #REF! #REF! #REF!
ukuran (120x240x9) mm, tebal 4 mm - #REF!
13 Pemasangan 1 m’ list langit-langit gypsum profil A.4.5.1.10. m1 19,049.25 19.00 361,935.75 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
14 Pasang papan pembungkus kolom beton (2x30) cm, Ls m2 325,000.00 28.32 9,204,000.00 0.30 #REF! #REF! - 0.00 #REF! #REF! #REF!
kayu jati finishing politur - #REF!
15 Membuat dan memasang rangka pagar, kayu kruink A.4.6.1.2. m3 10,925,172.50 0.68 7,429,117.30 0.25 #REF! #REF! - 0.00 #REF! #REF! #REF!
16 Membuat dan memasang pagar, kayu kruink A.4.6.1.10. m2 667,975.00 27.65 18,469,508.75 0.61 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH VII 216,206,582.80 #REF!
VIII PEKERJAAN BESI DAN ALUMUNIUM #REF!
1 Pemasangan 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm A.4.2.1.18. m1 103,541.63 10.00 1,035,416.25 0.03 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH VIII - 1,035,416.25 #REF!
IX PEKERJAAN KUNCI DAN KACA - #REF!
1 Pemasangan 1 buah engsel pintu A.4.6.2.5. bh 25,185.60 12.00 302,227.20 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Grendel pintu Ditaksir bh 10,000.00 6.00 60,000.00 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH IX - 362,227.20 #REF!
X PEKERJAAN PENUTUP LANTAI DAN DINDING - #REF!
1 Pemasangan 1m2 lantai keramik ukuran 40cm x40cm A.4.4.3.9.a m2 145,153.25 276.82 40,181,322.67 1.33 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 m2 dinding natu tempel candi A.4.4.3.58. m2 239,442.50 28.80 6,895,944.00 0.23 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH X 47,077,266.67 #REF!
XI PEKERJAAN PENGECATAN #REF!
1 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis A.4.7.1.4. m2 44,480.15 538.81 23,966,349.62 0.79 #REF! #REF! - 0.00 #REF! #REF! #REF!
cat dasar, 2 lapis cat penutup) - #REF!
2 Pelaburan 1 m2 bidang kayu dengan politur A.4.7.1.7. m2 49,024.25 100.17 4,910,759.12 0.16 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis A.4.7.1.10. m2 17,222.98 658.24 11,336,851.06 0.38 #REF! #REF! - 0.00 #REF! #REF! #REF!
cat dasar, 2 lapis cat penutup ) - #REF!
4 Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) A.4.7.1.11. m2 13,132.90 438.40 5,757,463.36 0.19 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH XI 45,971,423.17 #REF!
XII PEKERJAAN INSTALASI LISTRIK #REF!
1 Titik Lampu Ls Titik 85,000.00 13.00 1,105,000.00 0.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Saklar ganda Ls bh 22,500.00 6.00 135,000.00 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Stop Kontak Ls bh 22,500.00 2.00 45,000.00 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 MCB Ls bh 250,000.00 1.00 250,000.00 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
5 Lampu gantung artistik Ls bh 1,750,000.00 1.00 1,750,000.00 0.06 #REF! #REF! - 0.00 #REF! #REF! #REF!
6 Lampu SL 18watt phillips Ls bh 35,500.00 11.00 390,500.00 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH XII 3,675,500.00 #REF!
XIII PEKERJAAN LAIN-LAIN #REF!
1 Pasang saluran U 20 cm termasuk pas dinding Ls m1 75,500.00 49.60 3,744,800.00 0.12 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 buah bak kontrol pasangan bata 30 x 30 tinggi 35 cm A.5.1.1 15. bh 318,991.75 - - 0.00 #REF!
3 Pasang logo keramik ( ukuran 35 x 45 ) cm Ditaksir unit 750,000.00 1.00 750,000.00 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Pasang Tulisan ( bahan alumunium ) Ditaksir unit 2,250,000.00 1.00 2,250,000.00 0.07 #REF! #REF! - 0.00 #REF! #REF! #REF!
5 Pasang papan back ground Ditaksir unit 3,500,000.00 1.00 3,500,000.00 0.12 #REF! #REF! 1.00 0.12 #REF! #REF! #REF!
JUMLAH XIII 10,244,800.00 #REF!

Page 228 of 297


M21 (2)

BOBOT
HARGA NILAI
CCO.1 S / D MINGGU LALU MINGGU INI S / D MINGGU INI TIMBAN
KODE SATUAN BOBOT
NO JENIS PEKERJAAN SAT G
ANALISA
(Rp) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)
JUMLAH ( B ) 555,538,614.28 #REF!

Page 229 of 297


M21 (2)

BOBOT
HARGA NILAI
CCO.1 S / D MINGGU LALU MINGGU INI S / D MINGGU INI TIMBAN
KODE SATUAN BOBOT
NO JENIS PEKERJAAN SAT G
ANALISA
(Rp) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)

C KANTOR PELAYANAN #REF!


I PEKERJAAN PERSIAPAN #REF!
1 Pengukuran dan pemasangan bauwplank Ditaksir ls 500,000.00 1.00 500,000.00 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH I - 500,000.00 #REF!
II PEKERJAAN TANAH - #REF!
1 Penggalian 1 m3 tanah biasa sedalam 1 m A.2.3.1.1. m3 49,018.75 66.71 3,269,942.78 0.11 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pengurugan kembali 1 m3 galian tanah A.2.3.1.9. m3 16,339.58 18.67 305,092.70 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Pengurugan 1 m3 dengan pasir urug A.2.3.1.11. m3 118,607.50 26.22 3,110,321.57 0.10 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Pengurugan 1 m3 tanah cadas padat A.2.3.1.14.a m3 83,393.75 67.09 5,595,211.92 0.19 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH II - 12,280,568.97 #REF!
III PEKERJAAN PONDASI - #REF!
1 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP A.3.2.1.4. m3 516,466.50 93.27 48,168,893.71 1.59 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 m3 batu kosong (anstamping) A.3.2.1.9. m3 279,576.00 31.12 8,700,405.12 0.29 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH III 56,869,298.83 #REF!
IV PEKERJAAN DINDING #REF!
1 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu A. 4.4.1.2. m2 201,619.00 - - 0.00 #REF! 0.00 - 0.00 #REF! 0.00 0.00
campuran 1SP : 3PP - #REF!
2 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu A. 4.4.1.8. m2 97,798.25 125.83 12,305,464.81 0.41 #REF! #REF! - 0.00 #REF! #REF! #REF!
campuran 1SP : 3PP - #REF!
3 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu A. 4.4.1.11. m2 92,281.75 413.44 38,152,948.26 1.26 #REF! #REF! - 0.00 #REF! #REF! #REF!
campuran 1SP : 6PP - #REF!
JUMLAH IV - 50,458,413.07 #REF!
V PEKERJAAN PLESTERAN - #REF!
1 Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. A.4.4.2.6. m2 38,633.10 1,036.45 40,041,338.31 1.32 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 m2 acian A.4.4.2.27. m2 23,815.00 1,082.02 25,768,353.93 0.85 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Sponengan Ls m1 20,000.00 31.10 622,000.00 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH V 66,431,692.24 #REF!
VI PEKERJAAN BETON #REF!
1 Lantai kerja #REF!
Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), A.4.1.1.4. m3 712,475.42 18.44 13,140,647.31 0.43 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
2 Rabat Beton - #REF!
Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), A.4.1.1.1. m3 756,474.46 6.41 4,846,429.29 0.16 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
Pondasi Foot Plat 80/80
Pemasangan 1 m2 bekisting untuk pondasi A.4.1.1.20. m2 154,429.00 1.28 197,669.12 0.01 - 0.00 - 0.00 - 0.00 0.00
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 97.92 1,278,684.90 0.04 - 0.00 - 0.00 - 0.00 0.00
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.7. m3 888,212.03 0.59 522,268.68 0.02 - 0.00 - 0.00 - 0.00 0.00
slump (12 ± 2) cm, w/c = 0,87 -
3 Sloof 15/20 -
Pemasangan 1 m2 bekisting untuk sloof A.4.1.1.21. m2 166,529.00 49.88 8,306,466.52 0.27 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 1,251.53 16,342,259.72 0.54 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), A.4.1.1.5. m3 840,243.39 7.48 6,285,020.57 0.21 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm,w/c=0,87 - #REF!

Page 230 of 297


M21 (2)

BOBOT
HARGA NILAI
CCO.1 S / D MINGGU LALU MINGGU INI S / D MINGGU INI TIMBAN
KODE SATUAN BOBOT
NO JENIS PEKERJAAN SAT G
ANALISA
(Rp) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)
4 Kolom 30/30 - #REF!
Pemasangan 1 m2 bekisting untuk kolom A.4.1.1.22.a m2 252,252.00 13.08 3,299,456.16 0.11 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 154.97 2,023,571.14 0.07 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), A.4.1.1.5. m3 840,243.39 1.96 1,646,877.05 0.05 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm,w/c=0,87 - #REF!
5 Kolom 20/20 - #REF!
Pemasangan 1 m2 bekisting untuk kolom A.4.1.1.22.a m2 252,252.00 59.20 14,933,318.40 0.49 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 971.18 12,681,498.48 0.42 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), A.4.1.1.5. m3 840,243.39 5.62 4,722,167.86 0.16 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm,w/c=0,87 - #REF!
6 Kolom 15/15 - #REF!
Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm A.4.1.1.35. m1 252,252.00 113.00 28,504,476.00 0.94 #REF! #REF! - 0.00 #REF! #REF! #REF!
7 Balok 15/40 - #REF!
Pemasangan 1 m2 bekisting untuk balok A.4.1.1.23.a m2 282,612.00 2.28 644,355.36 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 47.74 623,380.57 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 840,243.39 0.33 277,280.32 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
8 Ring balok 15/30 - #REF!
Pemasangan 1 m2 bekisting untuk balok A.4.1.1.23.a m2 282,612.00 7.55 2,133,720.60 0.07 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 179.24 2,340,484.55 0.08 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 840,243.39 1.21 1,016,694.50 0.03 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF! -
9 Ring balok 15/20 - #REF! -
Pemasangan 1 m2 bekisting untuk balok A.4.1.1.23.a m2 86,781.75 34.51 2,994,838.19 0.10 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 1,060.48 13,847,562.26 0.46 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 840,243.39 5.18 4,352,460.77 0.14 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
10 Balok Latai 10/15 - #REF!
Membuat 1 m’ ring balok beton bertulang (10 x 15) cm A.4.1.1.36. m1 86,781.75 97.00 8,417,829.75 0.28 #REF! #REF! - 0.00 #REF! #REF! #REF!
11 Plat atap - #REF! -
Pemasangan 1 m2 bekisting untuk lantai A.4.1.1.24.a m2 222,552.00 25.00 5,563,800.00 0.18 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 855.60 11,172,275.07 0.37 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 840,243.39 6.00 5,041,460.35 0.17 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
12 Shading - #REF!
Pemasangan 1 m2 bekisting untuk lantai A.4.1.1.24.a m2 319,352.00 31.39 10,024,459.28 0.33 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 363.52 4,746,780.54 0.16 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 840,243.39 5.02 4,220,038.41 0.14 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
13 Plat lisplang - #REF!
Pemasangan 1 m2 bekisting untuk lantai A.4.1.1.24.a m2 319,352.00 3.51 1,120,925.52 0.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 69.32 905,168.43 0.03 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 840,243.39 0.70 588,170.37 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 #REF!
JUMLAH VI 198,762,496.04 #REF!
VII PEKERJAAN KAYU, ATAP DAN PLAFOND #REF!
1 Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I A.4.6.1.11. m3 652,159.75 24.36 15,886,611.51 0.53 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, A.4.6.1.13. m3 9,944,550.00 6.99 69,512,404.50 2.30 #REF! #REF! - 0.00 #REF! #REF! #REF!
kayu kelas II (kruink ) - #REF!
3 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) A.4.6.1.15. m3 10,651,671.25 3.54 37,706,916.23 1.25 #REF! #REF! - 0.00 #REF! #REF! #REF!
Page 231 of 297
M21 (2)

BOBOT
HARGA NILAI
CCO.1 S / D MINGGU LALU MINGGU INI S / D MINGGU INI TIMBAN
KODE SATUAN BOBOT
NO JENIS PEKERJAAN SAT G
ANALISA
(Rp) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)
4 Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II A.4.6.1.17. m2 153,051.25 523.90 80,183,549.88 2.65 #REF! #REF! - 0.00 #REF! #REF! #REF!
5 Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) motif kay Ls m1 22,500.00 102.00 2,295,000.00 0.08 #REF! #REF! - 0.00 #REF! #REF! #REF!
6 Pemasangan 1 m2 atap genteng palentong besar/super A.4.5.2.3.a m2 59,793.25 523.90 31,325,683.68 1.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
7 Pemasangan 1 m’ bubung genteng palentong besar A.4.5.2.6. m1 63,189.50 61.60 3,892,473.20 0.13 #REF! #REF! - 0.00 #REF! #REF! #REF!
8 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun A.4.6.1.20. m2 77,038.50 408.39 31,461,984.13 1.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
9 Pemasangan 1 m2 langit-langit gypsum board A.4.5.1.7. m2 34,538.90 368.87 12,740,467.66 0.42 #REF! #REF! - 0.00 #REF! #REF! #REF!
ukuran (120x240x9) mm, tebal 9 mm - #REF!
10 Pemasangan 1 m2 langit-langit kalsiboard A.4.5.1.7.a m2 32,937.30 39.52 1,301,682.10 0.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
ukuran (120x240x9) mm, tebal 4 mm - #REF!
11 Pemasangan 1 m’ list langit-langit gypsum profil A.4.5.1.10. m1 19,049.25 277.10 5,278,547.18 0.17 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH VII 291,585,320.05 #REF!
VIII PEKERJAAN SANITASI #REF!
1 Pemasangan 1 buah closet jongkok porslen A.5.1.1 2. bh 290,097.50 4.00 1,160,390.00 0.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 buah bak air fibreglass vol 1 m3 A.5.1.1 10. bh 342,354.10 - - 0.00 #REF!
3 Pemasangan 1 buah floor drain A.5.1.1 14. bh 26,331.25 5.00 131,656.25 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm A.5.1.1 15. bh 318,991.75 - - 0.00 #REF!
5 Pemasangan 1 buah kran diameter ½” atau 3/4” A.5.1.1 19. m1 45,375.00 7.00 317,625.00 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
6 Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” A.5.1.1 26. m1 14,250.50 69.80 994,684.90 0.03 #REF! #REF! - 0.00 #REF! #REF! #REF!
7 Pemasangan 1 m’ pipa PVC tipe AW diameter 2” A.5.1.1 29. m` 33,310.75 14.50 483,005.88 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
8 Pemasangan 1 m’ pipa PVC tipe AW diameter 4” A.5.1.1 32. m1 72,312.63 13.00 940,064.13 0.03 #REF! #REF! - 0.00 #REF! #REF! #REF!
9 Fiber glas tangki air kap 1100 ltr Ditaksir bh 1,450,000.00 1.00 1,450,000.00 0.05 #REF! #REF! - 0.00 #REF! #REF! #REF!
10 Pasang sumur bor Ditaksir m' 180,000.00 8.00 1,440,000.00 0.05 - 0.00 1.00 0.01 1.00 0.01 12.50
11 Pasang mesin pompa air listrik PW-120 jet Ditaksir bh 1,250,000.00 1.00 1,250,000.00 0.04 - 0.00 2.00 0.08 2.00 0.08 200.00
12 Ember dan gayung Ditaksir bh 100,000.00 4.00 400,000.00 0.01 - 0.00 3.00 0.01 3.00 0.01 75.00
JUMLAH VIII 8,567,426.15 -
IX PEKERJAAN BESI DAN ALUMUNIUM #REF!
1 Pemasangan 1 m kusen pintu alluminium A.4.2.1.11. m1 81,947.80 489.42 40,106,892.28 1.33 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 m2 pintu kaca rangka alluminium A.4.2.1.13. m2 466,303.75 82.07 38,269,548.76 1.27 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Pemasangan pintu tempered t = 12 mm ( komplit ) Ls unit 10,000,000.00 4.00 40,000,000.00 1.32 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH IX 118,376,441.04 #REF!
X PEKERJAAN KUNCI DAN KACA #REF!
1 Pemasangan 1 buah engsel pintu A.4.6.2.5. bh 25,185.60 42.00 1,057,795.20 0.03 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 buah engsel jendela kupu-kupu A.4.6.2.6. bh 21,921.63 304.00 6,664,174.00 0.22 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Pemasangan 1 buah kait angin A.4.6.2.9. bh 25,641.00 304.00 7,794,864.00 0.26 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Pemasangan 1 buah kunci slot A.4.6.2.11. bh 97,083.25 14.00 1,359,165.50 0.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
5 Pemasangan 1 m2 kaca tebal 5 mm A.4.6.2.17. bh 115,371.85 180.80 20,859,230.48 0.69 #REF! #REF! - 0.00 #REF! #REF! #REF!
6 Grendel pintu Ditaksir bh 10,000.00 170.00 1,700,000.00 0.06 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH X 39,435,229.18 #REF!
XI PEKERJAAN PENUTUP LANTAI DAN DINDING #REF!
1 Pemasangan 1m2 lantai keramik ukuran 40cm x40cm A.4.4.3.9.a m2 145,153.25 360.23 52,288,990.71 1.73 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm A.4.4.3.36. m2 213,889.50 8.64 1,848,005.28 0.06 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm A.4.4.3.41. m1 38,173.30 22.75 868,442.58 0.03 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Pemasangan 1 m2 dinding keramik 20cm x 20cm A.4.4.3.54. m2 204,226.00 40.94 8,361,114.55 0.28 #REF! #REF! - 0.00 #REF! #REF! #REF!
5 Pemasangan 1 m2 dinding batu tempel candi A.4.4.3.58. m2 236,692.50 - - 0.00 #REF!
JUMLAH XI 63,366,553.12 #REF!

Page 232 of 297


M21 (2)

BOBOT
HARGA NILAI
CCO.1 S / D MINGGU LALU MINGGU INI S / D MINGGU INI TIMBAN
KODE SATUAN BOBOT
NO JENIS PEKERJAAN SAT G
ANALISA
(Rp) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)
XII PEKERJAAN PENGECATAN #REF!
1 Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis A.4.7.1.10. m2 17,222.98 1,082.02 18,635,603.41 0.62 #REF! #REF! - 0.00 #REF! #REF! #REF!
cat dasar, 2 lapis cat penutup ) - #REF!
2 Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) A.4.7.1.11. m2 13,132.90 408.39 5,363,345.03 0.18 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH XII 23,998,948.44 #REF!
XIII PEKERJAAN INSTALASI LISTRIK #REF!
1 Pemasangan meter listrik lama 5500 watt Ls unit 750,000.00 - - 0.00 #REF!
2 Pasang meteran listrik baru 5500 Va Ls Titik 10,000,000.00 1.00 10,000,000.00 0.33 - 0.00 - 0.00 - 0.00 0.00
3 Titik Lampu Ls Titik 85,000.00 57.00 4,845,000.00 0.16 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Saklar ganda Ls bh 22,500.00 3.00 67,500.00 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
5 Saklar tunggal Ls bh 20,000.00 13.00 260,000.00 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
6 stop kontak Ls bh 22,500.00 15.00 337,500.00 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
7 lampu pijar 5W Philips Ls bh 10,000.00 5.00 50,000.00 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
8 Lampu SL 18 Watt Phillips Ls bh 35,500.00 37.00 1,313,500.00 0.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH XIII 16,873,500.00 #REF!
XIV PEKERJAAN LAIN-LAIN #REF!
1 Pasang saluran U 20 cm termasuk pas dinding Ls m1 75,500.00 112.36 8,483,180.00 0.28 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Membuat Septic Tank A.5.1.1 15. bh 1,150,000.00 2.00 2,300,000.00 0.08 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Membuat peresapan Ditaksir bh 750,000.00 2.00 1,500,000.00 0.05 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Tanah Subur Ditaksir m3 120,000.00 8.96 1,075,320.00 0.04 #REF! 0.00 - 0.00 #REF! 0.00 0.00
5 Pembuatan taman Ditaksir m2 225,000.00 59.34 13,351,500.00 0.44 #REF! 0.00 - 0.00 #REF! 0.00 0.00
JUMLAH XIV 26,710,000.00 #REF!
JUMLAH ( C ) 974,215,887.11 #REF!

D SERBA GUNA #REF!


I PEKERJAAN PERSIAPAN #REF!
1 Pengukuran dan pemasangan bauwplank Ditaksir ls 500,000.00 1.00 500,000.00 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH I - 500,000.00 #REF!
II PEKERJAAN TANAH - #REF!
1 Penggalian 1 m3 tanah biasa sedalam 1 m A.2.3.1.1. m3 49,018.75 30.01 1,471,111.51 0.05 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pengurugan kembali 1 m3 galian tanah A.2.3.1.9. m3 16,339.58 9.00 147,111.15 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Pengurugan 1 m3 dengan pasir urug A.2.3.1.11. m3 118,607.50 9.88 1,171,323.19 0.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Pengurugan 1 m3 tanah cadas padat A.2.3.1.14.a m3 83,393.75 17.97 1,498,244.61 0.05 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH II - 4,287,790.46 #REF!
III PEKERJAAN PONDASI - #REF!
1 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP A.3.2.1.4. m3 516,466.50 32.53 16,801,946.41 0.56 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 m3 batu kosong (anstamping) A.3.2.1.9. m3 279,576.00 13.52 3,779,867.52 0.13 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH III - 20,581,813.93 #REF!
IV PEKERJAAN DINDING - #REF!
1 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu A. 4.4.1.2. m2 201,619.00 - - 0.00 #REF!
campuran 1SP : 3PP - #REF!
2 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu A. 4.4.1.8. m2 97,798.25 73.18 7,156,386.94 0.24 #REF! #REF! - 0.00 #REF! #REF! #REF!
campuran 1SP : 3PP - #REF!
3 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu A. 4.4.1.11. m2 92,281.75 121.38 11,201,168.04 0.37 #REF! #REF! - 0.00 #REF! #REF! #REF!
campuran 1SP : 6PP - #REF!
JUMLAH IV - 18,357,554.99 #REF!

Page 233 of 297


M21 (2)

BOBOT
HARGA NILAI
CCO.1 S / D MINGGU LALU MINGGU INI S / D MINGGU INI TIMBAN
KODE SATUAN BOBOT
NO JENIS PEKERJAAN SAT G
ANALISA
(Rp) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)
V PEKERJAAN PLESTERAN - #REF!
1 Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. A.4.4.2.6. m2 38,633.10 370.29 14,305,450.60 0.47 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP A.4.4.2.23. m2 32,392.25 1.33 43,146.48 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Pemasangan 1 m2 acian A.4.4.2.27. m2 23,815.00 379.36 9,034,458.40 0.30 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Sponengan Ls m1 15,000.00 48.00 720,000.00 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH V - 24,103,055.48 #REF!
VI PEKERJAAN BETON - #REF!
1 Lantai kerja - #REF!
Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), A.4.1.1.4. m3 712,475.42 6.50 4,627,973.16 0.15 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
2 Rabat Beton - #REF!
Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), A.4.1.1.1. m3 756,474.46 2.71 2,053,737.39 0.07 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
3 Sloof 15/25 - #REF!
Pemasangan 1 m2 bekisting untuk sloof A.4.1.1.21. m2 166,529.00 21.13 3,518,757.77 0.12 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 519.31 6,781,059.10 0.22 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), A.4.1.1.5. m3 840,243.39 3.17 2,663,571.55 0.09 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm,w/c=0,87 - #REF!
4 Kolom 20/20 - #REF!
Pemasangan 1 m2 bekisting untuk kolom A.4.1.1.22.a m2 252,252.00 5.14 1,296,575.28 0.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 51.67 674,697.82 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), A.4.1.1.5. m3 840,243.39 0.51 428,524.13 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm,w/c=0,87 - #REF!
5 Kolom 15/15 - #REF!
Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm A.4.1.1.35. m1 252,252.00 94.80 23,913,489.60 0.79 #REF! #REF! - 0.00 #REF! #REF! #REF!
6 Ring balok 15/30 - #REF!
Pemasangan 1 m2 bekisting untuk balok A.4.1.1.23.a m2 254,892.00 6.00 1,529,352.00 0.05 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 106.21 1,386,871.59 0.05 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 840,243.39 0.68 571,365.51 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
7 Ring balok 15/20 - #REF!
Pemasangan 1 m2 bekisting untuk balok A.4.1.1.23.a m2 86,781.75 15.10 1,310,404.43 0.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 463.99 6,058,700.22 0.20 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 840,243.39 2.27 1,907,352.50 0.06 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
8 Balok Latai 10/15 - #REF!
Membuat 1 m’ ring balok beton bertulang (10 x 15) cm A.4.1.1.36. m1 86,781.75 35.00 3,037,361.25 0.10 #REF! #REF! - 0.00 #REF! #REF! #REF!
9 Plat atap - #REF!
Pemasangan 1 m2 bekisting untuk lantai A.4.1.1.24.a m2 222,552.00 11.69 2,600,965.22 0.09 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 199.97 2,611,173.27 0.09 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 840,243.39 1.17 981,992.45 0.03 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
10 Shading - #REF!
Pemasangan 1 m2 bekisting untuk lantai A.4.1.1.24.a m2 319,352.00 3.65 1,166,273.50 0.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 74.32 970,449.72 0.03 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 840,243.39 0.58 490,971.02 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 #REF!
JUMLAH VI 70,581,618.48 #REF!

Page 234 of 297


M21 (2)

BOBOT
HARGA NILAI
CCO.1 S / D MINGGU LALU MINGGU INI S / D MINGGU INI TIMBAN
KODE SATUAN BOBOT
NO JENIS PEKERJAAN SAT G
ANALISA
(Rp) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)
VII PEKERJAAN KAYU, ATAP DAN PLAFOND #REF!
1 Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I A.4.6.1.11. m3 652,159.75 7.98 5,204,234.81 0.17 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, A.4.6.1.13. m3 9,944,550.00 1.52 15,115,716.00 0.50 #REF! #REF! - 0.00 #REF! #REF! #REF!
kayu kelas II (kruink ) - #REF!
3 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) A.4.6.1.15. m3 10,651,671.25 1.34 14,273,239.48 0.47 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II A.4.6.1.16. m2 152,556.25 183.51 27,995,261.81 0.93 #REF! #REF! - 0.00 #REF! #REF! #REF!
5 Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) motif kay Ls m1 22,500.00 54.74 1,231,650.00 0.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
6 Pemasangan 1 m2 atap genteng palentong kecil A.4.5.2.1. m2 59,211.63 183.51 10,865,795.04 0.36 #REF! #REF! - 0.00 #REF! #REF! #REF!
7 Pemasangan 1 m’ bubung genteng palentong A.4.5.2.4. m1 65,939.50 34.00 2,241,943.00 0.07 #REF! #REF! - 0.00 #REF! #REF! #REF!
8 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun A.4.6.1.20. m2 77,038.50 178.26 13,732,921.53 0.45 #REF! #REF! - 0.00 #REF! #REF! #REF!
9 Pemasangan 1 m2 langit-langit gypsum board A.4.5.1.7. m2 34,538.90 139.17 4,806,692.37 0.16 #REF! #REF! - 0.00 #REF! #REF! #REF!
ukuran (120x240x9) mm, tebal 9 mm - #REF!
10 Pemasangan 1 m2 langit-langit kalsiboard A.4.5.1.7.a m2 32,937.30 39.09 1,287,617.87 0.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
ukuran (120x240x9) mm, tebal 4 mm - #REF!
11 Pemasangan 1 m’ list langit-langit gypsum profil A.4.5.1.10. m1 19,049.25 132.30 2,520,215.78 0.08 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH VII 99,275,287.67 #REF!
VIII PEKERJAAN SANITASI #REF!
1 Pemasangan 1 buah closet jongkok porslen A.5.1.1 2. bh 290,097.50 2.00 580,195.00 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 buah bak air fibreglass vol 1 m3 A.5.1.1 10. bh 342,354.10 - - 0.00 #REF!
3 Pemasangan 1 buah floor drain A.5.1.1 14. bh 26,331.25 2.00 52,662.50 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm A.5.1.1 15. bh 318,991.75 - - 0.00 #REF!
5 Pemasangan 1 buah kran diameter ½” atau 3/4” A.5.1.1 19. m1 45,375.00 2.00 90,750.00 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
6 Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” A.5.1.1 26. m1 14,250.50 40.00 570,020.00 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
7 Pemasangan 1 m’ pipa PVC tipe AW diameter 2” A.5.1.1 29. m` 33,310.75 3.50 116,587.63 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
8 Pemasangan 1 m’ pipa PVC tipe AW diameter 4” A.5.1.1 32. m1 72,312.63 7.00 506,188.38 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
9 Pasang sumur bor Ditaksir m' 180,000.00 8.00 1,440,000.00 0.05 - 0.00 - 0.00 - 0.00 0.00
10 Pasang mesin pompa air listrik PW-120 jet Ditaksir bh 1,250,000.00 1.00 1,250,000.00 0.04 - 0.00 - 0.00 - 0.00 0.00
11 Ember dan gayung Ditaksir unit 100,000.00 2.00 200,000.00 0.01 - 0.00 - 0.00 - 0.00 0.00
12 Fiber glas tangki air kap 1100 ltr Ditaksir unit 1,450,000.00 1.00 1,450,000.00 0.05 - 0.00 - 0.00 - 0.00 0.00
JUMLAH VIII 6,256,403.50 #REF!
IX PEKERJAAN BESI DAN ALUMUNIUM #REF!
1 Pemasangan 1 m kusen pintu alluminium A.4.2.1.11. m1 81,947.80 169.96 13,927,848.09 0.46 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 m2 pintu kaca rangka alluminium A.4.2.1.13. m2 466,303.75 29.45 13,732,645.44 0.45 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH IX 27,660,493.53 #REF!
X PEKERJAAN KUNCI DAN KACA #REF!
1 Pemasangan 1 buah engsel pintu A.4.6.2.5. bh 25,185.60 15.00 377,784.00 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 buah engsel jendela kupu-kupu A.4.6.2.6. bh 21,921.63 118.00 2,586,751.75 0.09 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Pemasangan 1 buah kait angin A.4.6.2.9. bh 25,641.00 118.00 3,025,638.00 0.10 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Pemasangan 1 buah kunci slot A.4.6.2.11. bh 97,083.25 5.00 485,416.25 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
5 Pemasangan 1 m2 kaca tebal 5 mm A.4.6.2.17. bh 115,371.85 38.12 4,397,974.92 0.15 #REF! #REF! - 0.00 #REF! #REF! #REF!
6 Grendel pintu Ditaksir bh 10,000.00 64.00 640,000.00 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH X 11,513,564.92 #REF!
XI PEKERJAAN PENUTUP LANTAI DAN DINDING #REF!
1 Pemasangan 1m2 lantai keramik ukuran 40cm x40cm A.4.4.3.9.a m2 199,798.50 123.85 24,744,045.23 0.82 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm A.4.4.3.36. m2 213,889.50 6.07 1,297,774.54 0.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm A.4.4.3.41. m1 38,173.30 9.40 358,829.02 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Pemasangan 1 m2 dinding keramik 20cm x 20cm A.4.4.3.54. m2 204,226.00 14.10 2,879,586.60 0.10 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH XI 29,280,235.39 #REF!

Page 235 of 297


M21 (2)

BOBOT
HARGA NILAI
CCO.1 S / D MINGGU LALU MINGGU INI S / D MINGGU INI TIMBAN
KODE SATUAN BOBOT
NO JENIS PEKERJAAN SAT G
ANALISA
(Rp) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)
XII PEKERJAAN PENGECATAN #REF!
1 Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis A.4.7.1.10. m2 17,222.98 379.36 6,533,707.80 0.22 #REF! #REF! - 0.00 #REF! #REF! #REF!
cat dasar, 2 lapis cat penutup ) - #REF!
2 Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) A.4.7.1.11. m2 13,132.90 178.26 2,341,077.32 0.08 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH XII 8,874,785.12 #REF!
XIII PEKERJAAN INSTALASI LISTRIK #REF!
1 Titik Lampu Ls Titik 85,000.00 28.00 2,380,000.00 0.08 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Saklar ganda Ls bh 22,500.00 2.00 45,000.00 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Saklar tunggal Ls bh 20,000.00 6.00 120,000.00 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 stop kontak Ls bh 22,500.00 6.00 135,000.00 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
5 lampu pijar 5W Philips Ls bh 10,000.00 6.00 60,000.00 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
6 Lampu SL 18 Watt Phillips Ls bh 35,500.00 16.00 568,000.00 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
7 Pemindahan meteren lama 5500 watt Ls bh 750,000.00 1.00 750,000.00 0.02 #REF! #REF! 1.00 0.02 #REF! #REF! #REF!
JUMLAH XIII 4,058,000.00 #REF!
XIV PEKERJAAN LAIN-LAIN #REF!
1 Pasang saluran U 20 cm termasuk pas dinding Ls m1 75,500.00 - - 0.00 #REF!
2 Membuat Septic Tank Ls bh 1,150,000.00 1.00 1,150,000.00 0.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Membuat peresapan Ls bh 750,000.00 1.00 750,000.00 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Tanah Subur Ls m3 120,000.00 0.40 47,880.00 0.00 #REF! 0.00 - 0.00 #REF! 0.00 0.00
5 Pembuatan taman Ls m2 225,000.00 1.00 224,437.50 0.01 #REF! 0.00 - 0.00 #REF! 0.00 0.00
JUMLAH XIV 2,172,317.50 #REF!
JUMLAH ( D ) 327,502,920.96 #REF!

E MUSHOLLA #REF!
I PEKERJAAN PERSIAPAN #REF!
1 Pengukuran dan pemasangan bauwplank Ditaksir ls 500,000.00 - - 0.00 #REF! - - - - - -
JUMLAH I - #REF!
II PEKERJAAN TANAH #REF!
1 Penggalian 1 m3 tanah biasa sedalam 1 m A.2.3.1.1. m3 49,018.75 - - 0.00 #REF! - - - - - -
2 Pengurugan kembali 1 m3 galian tanah A.2.3.1.9. m3 16,339.58 - - 0.00 #REF! - - - - - -
3 Pengurugan 1 m3 dengan pasir urug A.2.3.1.11. m3 118,607.50 - - 0.00 #REF! - - - - - -
4 Pengurugan 1 m3 tanah cadas padat A.2.3.1.14.a m3 83,393.75 - - 0.00 #REF! - - - - - -
JUMLAH II - #REF!
III PEKERJAAN PONDASI #REF!
1 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP A.3.2.1.4. m3 516,466.50 - - 0.00 #REF! - - - - - -
2 Pemasangan 1 m3 batu kosong (anstamping) A.3.2.1.9. m3 279,576.00 - - 0.00 #REF! - - - - - -
JUMLAH III - #REF!
IV PEKERJAAN DINDING #REF!
1 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu A. 4.4.1.8. m2 97,798.25 - - 0.00 #REF! - - - - - -
campuran 1SP : 3PP #REF!
2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu A. 4.4.1.11. m2 92,281.75 - - 0.00 #REF! - - - - - -
campuran 1SP : 6PP #REF!
3 Pemasangan main dinding GRC Ls m2 42,000.00 - - 0.00 #REF! - - - - - -
JUMLAH IV - #REF!
V PEKERJAAN PLESTERAN #REF!
1 Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. A.4.4.2.6. m2 38,633.10 - - 0.00 #REF! - - - - - -
2 Pemasangan 1 m2 acian A.4.4.2.27. m2 23,815.00 - - 0.00 #REF! - - - - - -

Page 236 of 297


M21 (2)

BOBOT
HARGA NILAI
CCO.1 S / D MINGGU LALU MINGGU INI S / D MINGGU INI TIMBAN
KODE SATUAN BOBOT
NO JENIS PEKERJAAN SAT G
ANALISA
(Rp) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)
JUMLAH V - #REF!
VI PEKERJAAN BETON #REF!
1 Lantai kerja #REF!
Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), A.4.1.1.4. m3 712,475.42 - - 0.00 #REF! - - - - - -
slump (12 ± 2) cm, w/c = 0,87 #REF!
2 Rabat Beton #REF!
Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), A.4.1.1.1. m3 756,474.46 - - 0.00 #REF! - - - - - -
slump (12 ± 2) cm, w/c = 0,87 #REF!
3 Sloof 15/25 #REF!
Pemasangan 1 m2 bekisting untuk sloof A.4.1.1.21. m2 166,529.00 - - 0.00 #REF! - - - - - -
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 - - 0.00 #REF! - - - - - -
Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), A.4.1.1.5. m3 840,243.39 - - 0.00 #REF! - - - - - -
slump (12 ± 2) cm,w/c=0,87 #REF!
4 Kolom 15/15 #REF!
Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm A.4.1.1.35. m1 63,268.15 - - 0.00 #REF! - - - - - -

Page 237 of 297


M21 (2)

BOBOT
HARGA NILAI
CCO.1 S / D MINGGU LALU MINGGU INI S / D MINGGU INI TIMBAN
KODE SATUAN BOBOT
NO JENIS PEKERJAAN SAT G
ANALISA
(Rp) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)
5 Balok 15/30 #REF!
Pemasangan 1 m2 bekisting untuk balok A.4.1.1.23.a m2 254,892.00 - - 0.00 #REF! - - - - - -
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 - - 0.00 #REF! - - - - - -
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 840,243.39 - - 0.00 #REF! - - - - - -
slump (12 ± 2) cm, w/c = 0,87 #REF!
6 Ring balok 15/20 #REF!
Pemasangan 1 m2 bekisting untuk balok A.4.1.1.23.a m2 86,781.75 - - 0.00 #REF! - - - - - -
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 - - 0.00 #REF! - - - - - -
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 840,243.39 - - 0.00 #REF! - - - - - -
slump (12 ± 2) cm, w/c = 0,87 #REF!
7 Balok Latai 10/15 #REF!
Membuat 1 m’ ring balok beton bertulang (10 x 15) cm A.4.1.1.36. m1 86,781.75 - - 0.00 #REF! - - - - - -
8 Plat atap #REF!
Pemasangan 1 m2 bekisting untuk lantai A.4.1.1.24.a m2 222,552.00 - - 0.00 #REF! - - - - - -
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 - - 0.00 #REF! - - - - - -
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 840,243.39 - - 0.00 #REF! - - - - - -
slump (12 ± 2) cm, w/c = 0,87 #REF!
9 Shading #REF!
Pemasangan 1 m2 bekisting untuk lantai A.4.1.1.24.a m2 319,352.00 - - 0.00 #REF! - - - - - -
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 - - 0.00 #REF! - - - - - -
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 840,243.39 - - 0.00 #REF! - - - - - -
slump (12 ± 2) cm, w/c = 0,87 #REF!
JUMLAH VI - #REF!
VII PEKERJAAN KAYU, ATAP DAN PLAFOND #REF!
1 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, A.4.6.1.13. m3 9,944,550.00 - - 0.00 #REF! - - - - - -
kayu kelas II (kruink ) #REF!
2 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) A.4.6.1.15. m3 10,651,671.25 - - 0.00 #REF! - - - - - -
3 Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II A.4.6.1.16. m2 152,556.25 - - 0.00 #REF! - - - - - -
4 Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) motif kay Ls m1 22,500.00 - - 0.00 #REF! - - - - - -
5 Pemasangan 1 m2 atap genteng palentong kecil A.4.5.2.1. m2 59,211.63 - - 0.00 #REF! - - - - - -
6 Pemasangan 1 m’ bubung genteng palentong A.4.5.2.4. m1 65,939.50 - - 0.00 #REF! - - - - - -
7 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun A.4.6.1.20. m2 77,038.50 - - 0.00 #REF! - - - - - -
8 Pemasangan 1 m2 langit-langit gypsum board A.4.5.1.7. m2 34,538.90 - - 0.00 #REF! - - - - - -
ukuran (120x240x9) mm, tebal 9 mm #REF!
9 Pemasangan 1 m2 langit-langit kalsiboard A.4.5.1.7.a m2 32,937.30 - - 0.00 #REF! - - - - - -
ukuran (120x240x9) mm, tebal 4 mm #REF!
10 Pemasangan 1 m’ list langit-langit gypsum profil A.4.5.1.10. m1 19,049.25 - - 0.00 #REF! - - - - - -
JUMLAH VII - #REF!
VIII PEKERJAAN SANITASI #REF!
1 Pemasangan 1 buah closet jongkok porslen A.5.1.1 2. bh 290,097.50 - - 0.00 #REF! - - - - - -
2 Pemasangan 1 buah bak air fibreglass vol 1 m3 A.5.1.1 10. bh 342,354.10 - - 0.00 #REF! - - - - - -
3 Pemasangan 1 buah floor drain A.5.1.1 14. bh 26,331.25 - - 0.00 #REF! - - - - - -
4 Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm A.5.1.1 15. bh 318,991.75 - - 0.00 #REF! - - - - - -
5 Pemasangan 1 buah kran diameter ½” atau 3/4” A.5.1.1 19. m1 45,375.00 - - 0.00 #REF! - - - - - -
6 Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” A.5.1.1 26. m1 14,250.50 - - 0.00 #REF! - - - - - -
7 Pemasangan 1 m’ pipa PVC tipe AW diameter 2” A.5.1.1 29. m` 33,310.75 - - 0.00 #REF! - - - - - -
8 Pemasangan 1 m’ pipa PVC tipe AW diameter 4” A.5.1.1 32. m1 72,312.63 - - 0.00 #REF! - - - - - -
JUMLAH VIII - #REF!

Page 238 of 297


M21 (2)

BOBOT
HARGA NILAI
CCO.1 S / D MINGGU LALU MINGGU INI S / D MINGGU INI TIMBAN
KODE SATUAN BOBOT
NO JENIS PEKERJAAN SAT G
ANALISA
(Rp) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)
IX PEKERJAAN BESI DAN ALUMUNIUM #REF!
1 Pemasangan 1 m kusen pintu alluminium A.4.2.1.11. m1 81,947.80 - - 0.00 #REF! - - - - - -
2 Pemasangan 1 m2 pintu alluminium strip lebar 8 cm A.4.2.1.12. m1 422,405.78 - - 0.00 #REF! - - - - - -
3 Pemasangan 1 m2 pintu kaca rangka alluminium A.4.2.1.13. m2 466,303.75 - - 0.00 #REF! - - - - - -
4 Pemasangan 1 m2 pintu kaca rangka alluminium A.4.2.1.13. m2 466,303.75 - - 0.00 #REF! - - - - - -
5 Pemasangan kubah Ls bh 2,000,000.00 - - 0.00 #REF! - - - - - -
JUMLAH IX - #REF!
X PEKERJAAN KUNCI DAN KACA #REF!
1 Pemasangan 1 buah engsel pintu A.4.6.2.5. bh 25,185.60 - - 0.00 #REF! - - - - - -
2 Pemasangan 1 buah engsel jendela kupu-kupu A.4.6.2.6. bh 21,921.63 - - 0.00 #REF! - - - - - -
3 Pemasangan 1 buah kait angin A.4.6.2.9. bh 25,641.00 - - 0.00 #REF! - - - - - -
4 Pemasangan 1 buah kunci slot A.4.6.2.11. bh 97,083.25 - - 0.00 #REF! - - - - - -
5 Pemasangan 1 m2 kaca tebal 5 mm A.4.6.2.17. bh 115,371.85 - - 0.00 #REF! - - - - - -
6 Grendel pintu Ditaksir bh 10,000.00 - - 0.00 #REF! - - - - - -
JUMLAH X - #REF!
XI PEKERJAAN PENUTUP LANTAI DAN DINDING #REF!
1 Pemasangan 1m2 lantai keramik ukuran 40cm x40cm A.4.4.3.9.a m2 199,798.50 - - 0.00 #REF! - - - - - -
2 Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm A.4.4.3.36. m2 213,889.50 - - 0.00 #REF! - - - - - -
3 Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm A.4.4.3.41. m1 38,173.30 - - 0.00 #REF! - - - - - -
4 Pemasangan 1 m2 dinding keramik 20cm x 20cm A.4.4.3.54. m2 204,226.00 - - 0.00 #REF! - - - - - -
JUMLAH XI - #REF!
XII PEKERJAAN PENGECATAN #REF!
1 Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis A.4.7.1.10. m2 17,222.98 - - 0.00 #REF! - - - - - -
cat dasar, 2 lapis cat penutup ) #REF!
2 Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) A.4.7.1.11. m2 13,132.90 - - 0.00 #REF! - - - - - -
JUMLAH XII - #REF!
XIII PEKERJAAN INSTALASI LISTRIK #REF!
1 Pemasangan meter listrik 900 watt Ls unit 1,650,000.00 - - 0.00 #REF! - - - - - -
2 Titik Lampu Ls Titik 85,000.00 - - 0.00 #REF! - - - - - -
3 Saklar ganda Ls bh 22,500.00 - - 0.00 #REF! - - - - - -
4 Saklar tunggal Ls bh 20,000.00 - - 0.00 #REF! - - - - - -
5 stop kontak Ls bh 22,500.00 - - 0.00 #REF! - - - - - -
6 lampu pijar 5W Philips Ls bh 10,000.00 - - 0.00 #REF! - - - - - -
7 Lampu SL 18 Watt Phillips Ls bh 35,500.00 - - 0.00 #REF! - - - - - -
JUMLAH XIII - #REF!
XIV PEKERJAAN LAIN-LAIN #REF!
1 Membuat Septic Tank Ls bh 1,150,000.00 - - 0.00 #REF! - - - - - -
2 Membuat peresapan Ls bh 750,000.00 - - 0.00 #REF! - - - - - -
3 Tanah Subur Ls m3 120,000.00 - - 0.00 #REF! - - - - - -
4 Pembuatan taman Ls m2 225,000.00 - - 0.00 #REF! - - - - - -
JUMLAH XIV - #REF!
JUMLAH ( E ) - #REF!

F RUMAH DINAS #REF!


I PEKERJAAN PERSIAPAN #REF!
1 Pengukuran dan pemasangan bauwplank Ditaksir ls 500,000.00 1.00 500,000.00 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH I - 500,000.00 #REF!

Page 239 of 297


M21 (2)

BOBOT
HARGA NILAI
CCO.1 S / D MINGGU LALU MINGGU INI S / D MINGGU INI TIMBAN
KODE SATUAN BOBOT
NO JENIS PEKERJAAN SAT G
ANALISA
(Rp) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)
II PEKERJAAN TANAH - #REF!
1 Penggalian 1 m3 tanah biasa sedalam 1 m A.2.3.1.1. m3 49,018.75 30.07 1,473,954.60 0.05 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pengurugan kembali 1 m3 galian tanah A.2.3.1.9. m3 16,339.58 8.64 141,174.00 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Pengurugan 1 m3 dengan pasir urug A.2.3.1.11. m3 118,607.50 9.39 1,113,831.17 0.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Pengurugan 1 m3 tanah cadas padat A.2.3.1.14.a m3 83,393.75 13.70 1,142,240.86 0.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH II - 3,871,200.63 #REF!
III PEKERJAAN PONDASI - #REF!
1 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP A.3.2.1.4. m3 516,466.50 39.60 20,452,073.40 0.68 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 m3 batu kosong (anstamping) A.3.2.1.9. m3 279,576.00 14.40 4,025,894.40 0.13 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH III - 24,477,967.80 #REF!
IV PEKERJAAN DINDING - #REF!
1 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu A. 4.4.1.2. m2 201,619.00 1.20 241,942.80 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
campuran 1SP : 3PP - #REF!
2 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu A. 4.4.1.8. m2 97,798.25 34.43 3,367,193.75 0.11 #REF! #REF! - 0.00 #REF! #REF! #REF!
campuran 1SP : 3PP - #REF!
3 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu A. 4.4.1.11. m2 92,281.75 238.04 21,966,600.12 0.73 #REF! #REF! - 0.00 #REF! #REF! #REF!
campuran 1SP : 6PP - #REF!
JUMLAH IV - 25,575,736.67 #REF!
V PEKERJAAN PLESTERAN - #REF!
1 Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. A.4.4.2.6. m2 38,633.10 540.98 20,899,734.44 0.69 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 m2 acian A.4.4.2.27. m2 23,815.00 557.54 13,277,760.33 0.44 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH V 34,177,494.76 #REF!
VI PEKERJAAN BETON #REF!
1 Lantai kerja #REF!
Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), A.4.1.1.4. m3 712,475.42 5.79 4,125,873.92 0.14 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
2 Rabat Beton - #REF!
Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), A.4.1.1.1. m3 756,474.46 2.74 2,074,434.53 0.07 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
3 Sloof 15/25 - #REF!
Pemasangan 1 m2 bekisting untuk sloof A.4.1.1.21. m2 166,529.00 23.25 3,871,799.25 0.13 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 571.64 7,464,375.08 0.25 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), A.4.1.1.5. m3 840,243.39 3.49 2,932,449.44 0.10 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm,w/c=0,87 - #REF!
4 Kolom 15/25 - #REF!
Pemasangan 1 m2 bekisting untuk kolom A.4.1.1.22.a m2 252,252.00 32.40 8,172,964.80 0.27 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 526.20 6,871,027.52 0.23 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), A.4.1.1.5. m3 840,243.39 2.57 2,159,425.52 0.07 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm,w/c=0,87 - #REF!
5 Kolom 15/15 - #REF!
Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm A.4.1.1.35. m1 63,268.15 56.00 3,543,016.40 0.12 #REF! #REF! - 0.00 #REF! #REF! #REF!
6 Ring balok 15/30 - #REF!
Pemasangan 1 m2 bekisting untuk balok A.4.1.1.23.a m2 254,892.00 - - 0.00 #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 - - 0.00 #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 840,243.39 - - 0.00 #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!

Page 240 of 297


M21 (2)

BOBOT
HARGA NILAI
CCO.1 S / D MINGGU LALU MINGGU INI S / D MINGGU INI TIMBAN
KODE SATUAN BOBOT
NO JENIS PEKERJAAN SAT G
ANALISA
(Rp) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)
7 Ring balok 15/20 - #REF!
Pemasangan 1 m2 bekisting untuk balok A.4.1.1.23.a m2 254,892.00 18.60 4,740,991.20 0.16 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 559.86 7,310,553.90 0.24 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 840,243.39 2.79 2,344,279.06 0.08 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
8 Balok Latai 10/15 - #REF!
Membuat 1 m’ ring balok beton bertulang (10 x 15) cm A.4.1.1.36. m1 86,781.75 32.50 2,820,406.88 0.09 #REF! #REF! - 0.00 #REF! #REF! #REF!
9 Plat atap - #REF!
Pemasangan 1 m2 bekisting untuk lantai A.4.1.1.24.a m2 222,552.00 - - 0.00 #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 - - 0.00 #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 840,243.39 - - 0.00 #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
10 Shading - #REF!
Pemasangan 1 m2 bekisting untuk lantai A.4.1.1.24.a m2 222,552.00 6.66 1,482,196.32 0.05 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 135.42 1,768,290.66 0.06 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 840,243.39 1.07 895,800.28 0.03 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - #REF!
11 Meja dapur - #REF!
Membuat 1 m3 dinding beton bertulang (150 kg besi + bekisting) A.4.1.1.33. m2 222,552.00 1.27 282,641.04 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17. kg 13,057.83 11.52 150,426.14 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , A.4.1.1.5. m3 840,243.39 0.21 178,467.70 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 #REF!
JUMLAH VI 63,189,419.64 #REF!
VII PEKERJAAN KAYU, ATAP DAN PLAFOND #REF!
1 Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kel A.4.6.1.2. m3 10,925,172.50 0.95 10,378,913.88 0.34 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I atau II A.4.6.1.5. m2 591,717.50 14.20 8,402,388.50 0.28 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I at A.4.6.1.6. m2 410,058.00 3.96 1,623,829.68 0.05 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, A.4.6.1.13. m3 9,944,550.00 2.02 20,087,991.00 0.66 #REF! #REF! - 0.00 #REF! #REF! #REF!
kayu kelas II (kruink ) - #REF!
5 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) A.4.6.1.15. m3 10,651,671.25 1.92 20,451,208.80 0.68 #REF! #REF! - 0.00 #REF! #REF! #REF!
6 Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II A.4.6.1.16. m2 152,556.25 194.68 29,699,650.75 0.98 #REF! #REF! - 0.00 #REF! #REF! #REF!
7 Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) motif kay Ls m1 22,500.00 52.30 1,176,750.00 0.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
8 Pemasangan 1 m2 atap genteng palentong kecil A.4.5.2.1. m2 59,211.63 194.68 11,527,319.16 0.38 #REF! #REF! - 0.00 #REF! #REF! #REF!
9 Pemasangan 1 m’ bubung genteng palentong A.4.5.2.4. m1 65,939.50 46.71 3,080,034.05 0.10 #REF! #REF! - 0.00 #REF! #REF! #REF!
10 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun A.4.6.1.20. m2 77,038.50 153.78 11,847,057.57 0.39 #REF! #REF! - 0.00 #REF! #REF! #REF!
11 Pemasangan 1 m2 langit-langit gypsum board A.4.5.1.7. m2 34,538.90 115.82 4,000,226.32 0.13 #REF! #REF! - 0.00 #REF! #REF! #REF!
ukuran (120x240x9) mm, tebal 9 mm - #REF!
12 Pemasangan 1 m2 langit-langit kalsiboard A.4.5.1.7.a m2 32,937.30 37.96 1,250,398.72 0.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
ukuran (120x240x9) mm, tebal 4 mm - #REF!
13 Pemasangan 1 m’ list langit-langit gypsum profil A.4.5.1.10. m1 19,049.25 116.89 2,226,666.83 0.07 #REF! #REF! - 0.00 #REF! #REF! #REF!
14 Pemasangan rooster kayu Ls bh 25,000.00 9.00 225,000.00 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH VII 125,977,435.25 #REF!
VIII PEKERJAAN SANITASI #REF!
1 Pemasangan 1 buah closet jongkok porslen A.5.1.1 2. bh 290,097.50 1.00 290,097.50 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 buah wastafel A.5.1.1 5. bh 696,960.00 1.00 696,960.00 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Pemasangan 1 buah bak air fibreglass vol 1 m3 A.5.1.1 10. bh 342,354.10 - - 0.00 #REF! 0.00 - 0.00 #REF! 0.00 0.00
4 Pemasangan 1 buah bak cuci piring stainlessteel A.5.1.1 12. bh 267,093.75 1.00 267,093.75 0.01 #REF! 0.00 - 0.00 #REF! 0.00 0.00
5 Pemasangan 1 buah floor drain A.5.1.1 14. bh 26,331.25 1.00 26,331.25 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
6 Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm A.5.1.1 15. bh 318,991.75 - - 0.00 #REF!
7 Pemasangan 1 buah kran diameter ½” atau 3/4” A.5.1.1 19. m1 45,375.00 3.00 136,125.00 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
Page 241 of 297
M21 (2)

BOBOT
HARGA NILAI
CCO.1 S / D MINGGU LALU MINGGU INI S / D MINGGU INI TIMBAN
KODE SATUAN BOBOT
NO JENIS PEKERJAAN SAT G
ANALISA
(Rp) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)
8 Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” A.5.1.1 26. m1 14,250.50 25.00 356,262.50 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
9 Pemasangan 1 m’ pipa PVC tipe AW diameter 2” A.5.1.1 29. m` 33,310.75 4.00 133,243.00 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
10 Pemasangan 1 m’ pipa PVC tipe AW diameter 4” A.5.1.1 32. m1 72,312.63 8.00 578,501.00 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH VIII 2,484,614.00 #REF!
IX PEKERJAAN BESI DAN ALUMUNIUM #REF!
1 Pintu besi Folding Gate ( Terpasang ) Ls m2 275,000.00 8.44 2,321,550.00 0.08 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH IX 2,321,550.00 #REF!
X PEKERJAAN KUNCI DAN KACA #REF!
1 Pemasangan 1 buah engsel pintu A.4.6.2.5. bh 25,185.60 27.00 680,011.20 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1 buah engsel jendela kupu-kupu A.4.6.2.6. bh 21,921.63 36.00 789,178.50 0.03 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Pemasangan 1 buah kait angin A.4.6.2.9. bh 25,641.00 36.00 923,076.00 0.03 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Pemasangan 1 buah kunci slot A.4.6.2.11. bh 97,083.25 15.00 1,456,248.75 0.05 #REF! #REF! - 0.00 #REF! #REF! #REF!
5 Pemasangan 1 m2 kaca tebal 5 mm A.4.6.2.17. bh 115,371.85 6.90 796,065.77 0.03 #REF! #REF! - 0.00 #REF! #REF! #REF!
6 Grendel pintu Ditaksir bh 10,000.00 29.00 290,000.00 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH X 4,934,580.22 #REF!
XI PEKERJAAN PENUTUP LANTAI DAN DINDING #REF!
1 Pemasangan 1m2 lantai keramik ukuran 40cm x40cm A.4.4.3.9.a m2 199,798.50 113.32 22,641,265.92 0.75 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm A.4.4.3.36. m2 213,889.50 2.50 534,189.03 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm A.4.4.3.41. m1 38,173.30 5.95 227,131.14 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Pemasangan 1 m2 dinding keramik 20cm x 20cm A.4.4.3.54. m2 204,226.00 15.20 3,104,235.20 0.10 #REF! #REF! - 0.00 #REF! #REF! #REF!
5 Pemasangan 1 m2 dinding batu tempel susun sirih A.4.4.3.58. m2 239,442.50 - - 0.00 #REF!
JUMLAH XI 26,506,821.28 #REF!
XII PEKERJAAN PENGECATAN #REF!
1 Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis A.4.7.1.10. m2 17,222.98 557.54 9,602,457.87 0.32 #REF! #REF! - 0.00 #REF! #REF! #REF!
cat dasar, 2 lapis cat penutup ) - #REF!
2 Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) A.4.7.1.11. m2 13,132.90 153.78 2,019,590.49 0.07 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH XII 11,622,048.36 #REF!
XIII PEKERJAAN INSTALASI LISTRIK #REF!
1 Pemasangan meter listrik 900 watt Ls unit 750,000.00 1.00 750,000.00 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
2 Titik Lampu Ls Titik 85,000.00 30.00 2,550,000.00 0.08 #REF! #REF! - 0.00 #REF! #REF! #REF!
3 Saklar ganda Ls bh 22,500.00 2.00 45,000.00 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
4 Saklar tunggal Ls bh 20,000.00 8.00 160,000.00 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
5 stop kontak Ls bh 22,500.00 8.00 180,000.00 0.01 #REF! #REF! - 0.00 #REF! #REF! #REF!
6 lampu pijar 5W Philips Ls bh 10,000.00 5.00 50,000.00 0.00 #REF! #REF! - 0.00 #REF! #REF! #REF!
7 Lampu SL 18 Watt Phillips Ls bh 35,500.00 17.00 603,500.00 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH XIII 4,338,500.00 #REF!

Page 242 of 297


M21 (2)

BOBOT
HARGA NILAI
CCO.1 S / D MINGGU LALU MINGGU INI S / D MINGGU INI TIMBAN
KODE SATUAN BOBOT
NO JENIS PEKERJAAN SAT G
ANALISA
(Rp) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)
XIV PEKERJAAN LAIN-LAIN #REF!
1 Pasang saluran U 20 cm termasuk pas dinding Ls m1 75,500.00 - - 0.00 #REF!
2 Tanah Subur Ls m3 120,000.00 0.54 64,800.00 0.00 #REF! 0.00 - 0.00 #REF! 0.00 0.00
3 Pembuatan taman Ls m2 225,000.00 0.90 202,500.00 0.01 #REF! 0.00 - 0.00 #REF! 0.00 0.00
4 Membuat Septictank Ls bh 1,150,000.00 1.00 1,150,000.00 0.04 #REF! #REF! - 0.00 #REF! #REF! #REF!
5 Membuat Peresapan Ls bh 750,000.00 1.00 750,000.00 0.02 #REF! #REF! - 0.00 #REF! #REF! #REF!
JUMLAH XIV 2,167,300.00
JUMLAH ( F ) 332,144,668.60

JUMLAH TOTAL 3,022,633,717.72 100.00 #REF! #REF! #REF!


PPN 10 % 302,263,371.77

JUMLAH TOTAL 3,324,897,089.49

DIBULATKAN 3,324,897,000.00

KEBUMEN, 17 SEPTEMBER 2017

Konsultan Pengawas
CV ADHI JAYA CONSULTANT

IRWAN SETIADI, ST
Inspektoor

Page 243 of 297


M1 (2)

LAPORAN MINGGUAN

KEGIATAN : PEMBANGUNAN GEDUNG KANTOR MINGGU KE : XIII ( Tiga Belas )


PEKERJAAN : PEMBANGUNAN GEDUNG KANTOR KECAMATAN SRUWENG WAKTU : 11 - 17 September 2017
LOKASI : KEC. SRUWENG, KEBUMEN RENCANA : 0.46
HUN ANGGARAN : 2,017.00 PROGRES/DEVIASI : - (0.46)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)

A PAGAR DAN HALAMAN


I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH I #REF! #REF! #REF! #REF! #REF!
II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 A.2.3.1.14. Pengurugan 1 m3 sirtu padat m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH II #REF! #REF! #REF! #REF! #REF!
III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH III #REF! #REF! #REF! #REF! #REF!
IV PEKERJAAN DINDING
1 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
campuran 1SP : 3PP
2 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
campuran 1SP : 6PP
JUMLAH IV #REF! #REF! #REF! #REF! #REF!
V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.4.2.23. Pemasangan 1 m2 plesteran ciprat 1SP : 2PP m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.4.4.2.27. Pemasangan 1 m2 acian m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 Ls Sponengan m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH V #REF! #REF! #REF! #REF! #REF!
VI PEKERJAAN BETON
1 Sloof 15/25
A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
2 Foot Plat 80/80
A.4.1.1.20. Pemasangan 1 m2 bekisting untuk pondasi m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!

Page 244 of 297


M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
slump (12 ± 2) cm, w/c = 0,87

Page 245 of 297


M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
3 Kolom 20/20
A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
4 Kolom 11/11
A.4.1.1.35 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 Ring Balok 10/15 , ,
A.4.1.1.36 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH VI #REF! #REF! #REF! #REF! #REF!
VII PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.4.3.58. Pemasangan 1 m2 dinding batu tempel candi m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH VII #REF! #REF! - #REF! - #REF! #REF!
VIII PEKERJAAN BESI DAN ALUMUNIUM
1 Ditaksir Pintu besi terpasang dan pengecatan m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 Ditaksir Pagar besi terpasang dan pengecatan m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH VIII #REF! #REF! #REF! #REF! #REF!
IX PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
cat dasar, 2 lapis cat penutup )
JUMLAH IX #REF! #REF! #REF! #REF! #REF!
X PEKERJAAN INSTALASI LISTRIK
1 Ditaksir Titik Lampu ttk #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 Ditaksir Saklar Ganda bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 Ditaksir Pemasangan Lampu Taman bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH X #REF! #REF! #REF! #REF! #REF!
XI PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm, termasuk pasangan dinding m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 Ls Tanah subur m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 Ls Pembuatan taman m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 Ls Pasang logo keramik ( uk 35 x 45 ) cm bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 Ls Pasang tulisan ( bahan alumunium ) unit #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH XI #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!
B PEMBANGUNAN PENDOPO
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.2.2.1.15a. 1 M2 pasang paving blok segi 4, t = 8 cm ls #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH I #REF! #REF! #REF! #REF! #REF!
II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH II #REF! #REF! #REF! #REF! #REF!
III PEKERJAAN PONDASI
Page 246 of 297
M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH III #REF! #REF! - #REF! - #REF! - #REF! #REF!

Page 247 of 297


M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
IV PEKERJAAN DINDING
1 A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
campuran 1SP : 3PP
2 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
campuran 1SP : 3PP
3 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
campuran 1SP : 6PP
JUMLAH IV #REF! #REF! #REF! #REF! #REF!
V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.4.2.27. Pemasangan 1 m2 acian m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 Ls Sponengan m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH V #REF! #REF! #REF! #REF! #REF!
VI PEKERJAAN BETON
1 Lantai kerja
A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - -
2 Rabat Beton - -
A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - -
3 Pondasi Foot Plat 80/80 - -
A.4.1.1.20. Pemasangan 1 m2 bekisting untuk pondasi m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - -
4 Sloof 15/25 - -
A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - -
5 Kolom 30/30 - -
A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - -
6 Kolom 20/20 - -
A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - -
7 Kolom 15/15 - -
A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87 - -
8 Balok 20/35 - -
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!

Page 248 of 297


M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
9 Balok 15/20
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
10 Balok latai 15/20
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
11 Ring balok 15/20
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
12 Shading
A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
JUMLAH VI #REF! #REF! #REF! #REF! #REF!
VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
kayu kelas II (kruink )
2 A.4.6.1.13.a Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas II (krui m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.4.6.1.15.a Pemasangan 1 m3 konstruksi gordeng expose , kayu kelas II ( kruin m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 A.4.6.1.17. Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
6 A.4.6.1.17.a Pemasangan 1 m2 rangka atap genteng beton expose , m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
kayu kelas II ( kruink )
7 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) moti m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
8 A.4.5.2.3.a Pemasangan 1 m2 atap genteng palentong besar/super m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
9 A.4.5.2.6. Pemasangan 1 m’ bubung genteng palentong besar m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
10 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
11 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
ukuran (120x240x9) mm, tebal 9 mm

Page 249 of 297


M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
12 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
ukuran (120x240x9) mm, tebal 4 mm
13 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
14 Ls Pasang papan pembungkus kolom beton (2x30) cm, m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
kayu jati finishing politur
15 A.4.6.1.2. Membuat dan memasang rangka pagar, kayu kruink m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
16 A.4.6.1.10. Membuat dan memasang pagar, kayu kruink m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH VII #REF! #REF! - #REF! - #REF! - #REF! #REF!
VIII PEKERJAAN BESI DAN ALUMUNIUM
1 A.4.2.1.18. Pemasangan 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH VIII #REF! #REF! #REF! #REF! #REF!
IX PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 Ditaksir Grendel pintu bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH IX #REF! #REF! #REF! #REF! #REF!
X PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.4.3.58. Pemasangan 1 m2 dinding natu tempel candi m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH X #REF! #REF! #REF! #REF! #REF!
XI PEKERJAAN PENGECATAN
1 A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
cat dasar, 2 lapis cat penutup)
2 A.4.7.1.7. Pelaburan 1 m2 bidang kayu dengan politur m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
cat dasar, 2 lapis cat penutup )
4 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH XI #REF! #REF! #REF! #REF! #REF!
XII PEKERJAAN INSTALASI LISTRIK
1 Ls Titik Lampu Titik #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 Ls Saklar ganda bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 Ls Stop Kontak bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 Ls MCB bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 Ls Lampu gantung artistik bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
6 Ls Lampu SL 18watt phillips bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH XII #REF! #REF! - #REF! - #REF! - #REF! #REF!
XIII PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm termasuk pas dinding m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30 x 30 tinggi 35 c bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!

Page 250 of 297


M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
3 Ditaksir Pasang logo keramik ( ukuran 35 x 45 ) cm unit #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 Ditaksir Pasang Tulisan ( bahan alumunium ) unit #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH XIII #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!
C KANTOR PELAYANAN
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls 3,000,000.00 1.00 3,000,000.00 #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH I 3,000,000.00 #REF! #REF! #REF! #REF!
II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 14,027.66 7,794.00 109,331,582.04 #REF! - #REF! - #REF! - #REF! #REF!
2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 799.33 8,986.00 7,182,779.38 #REF! - #REF! - #REF! - #REF! #REF!
3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 82,255.51 150.45 12,375,341.48 #REF! - #REF! - #REF! - #REF! #REF!
4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 855.69 38,907.00 33,292,330.83 #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH II 162,182,033.74 #REF! #REF! #REF! #REF!
III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH III #REF! #REF! #REF! #REF! #REF!
IV PEKERJAAN DINDING
1 A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
campuran 1SP : 3PP
2 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
campuran 1SP : 3PP
3 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
campuran 1SP : 6PP
JUMLAH IV #REF! #REF! #REF! #REF! #REF!
V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.4.2.27. Pemasangan 1 m2 acian m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 Ls Sponengan m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH V #REF! #REF! #REF! #REF! #REF!
VI PEKERJAAN BETON
1 Lantai kerja
A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87

Page 251 of 297


M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
2 Rabat Beton
A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
3 Sloof 15/20
A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm,w/c=0,87
4 Kolom 30/30
A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm,w/c=0,87
5 Kolom 20/20
A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm,w/c=0,87
6 Kolom 15/15
A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
7 Balok 15/40 #REF! #REF!
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
8 Ring balok 15/30
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
9 Ring balok 15/20
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
10 Balok Latai 10/15
A.4.1.1.36. Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!

Page 252 of 297


M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
11 Plat atap
A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
12 Shading
A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
13 Plat lisplang
A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
JUMLAH VI #REF! #REF! #REF! #REF! #REF!
VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.11. Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
kayu kelas II (kruink ) #REF! #REF!
3 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.4.6.1.17. Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) moti m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
6 A.4.5.2.3.a Pemasangan 1 m2 atap genteng palentong besar/super m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
7 A.4.5.2.6. Pemasangan 1 m’ bubung genteng palentong besar m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
8 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
9 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
ukuran (120x240x9) mm, tebal 9 mm
10 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
ukuran (120x240x9) mm, tebal 4 mm
11 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH VII #REF! #REF! #REF! #REF! #REF!
VIII PEKERJAAN SANITASI
1 A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.5.1.1 10. Pemasangan 1 buah bak air fibreglass vol 1 m3 bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.5.1.1 14. Pemasangan 1 buah floor drain bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4” m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!

Page 253 of 297


M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
6 A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
7 A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” m` #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
8 A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4” m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
9 Ditaksir Fiber glas tangki air kap 1100 ltr bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH VIII #REF! #REF! #REF! #REF! #REF!
IX PEKERJAAN BESI DAN ALUMUNIUM
1 A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.2.1.13. Pemasangan 1 m2 pintu kaca rangka alluminium m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 Ls Pemasangan pintu tempered t = 12 mm ( komplit ) unit #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH IX #REF! #REF! #REF! #REF! #REF!
X PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.4.6.2.9. Pemasangan 1 buah kait angin bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.4.6.2.11. Pemasangan 1 buah kunci slot bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
6 Ditaksir Grendel pintu bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH X #REF! #REF! #REF! #REF! #REF!
XI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20cm x 20cm m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 A.4.4.3.58. Pemasangan 1 m2 dinding batu tempel candi m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH XI #REF! #REF! #REF! #REF! #REF!
XII PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
cat dasar, 2 lapis cat penutup )
2 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH XII #REF! #REF! #REF! #REF! #REF!
XIII PEKERJAAN INSTALASI LISTRIK
1 Ls Pemasangan meter listrik lama 5500 watt unit #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 Ls Titik Lampu Titik #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 Ls Saklar ganda bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 Ls Saklar tunggal bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 Ls stop kontak bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
6 Ls lampu pijar 5W Philips bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
7 Ls Lampu SL 18 Watt Phillips bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH XIII #REF! #REF! - #REF! - #REF! - #REF! #REF!
XIV PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm termasuk pas dinding m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.5.1.1 15. Membuat Septic Tank bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 Ditaksir Membuat peresapan bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 Ditaksir Tanah Subur m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 Ditaksir Pembuatan taman m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH XIV #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!

Page 254 of 297


M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
D SERBA GUNA
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH I #REF! #REF! #REF! #REF! #REF!
II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH II #REF! #REF! #REF! #REF! #REF!
III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH III #REF! #REF! #REF! #REF! #REF!
IV PEKERJAAN DINDING
1 A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
campuran 1SP : 3PP
2 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
campuran 1SP : 3PP
3 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
campuran 1SP : 6PP
JUMLAH IV #REF! #REF! #REF! #REF! #REF!
V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.4.2.23. Pemasangan 1 m2 plesteran ciprat 1SP : 2PP m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.4.2.27. Pemasangan 1 m2 acian m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 Ls Sponengan m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH V #REF! #REF! #REF! #REF! #REF!

Page 255 of 297


M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
VI PEKERJAAN BETON
1 Lantai kerja
A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
2 Rabat Beton
A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
3 Sloof 15/25
A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm,w/c=0,87
4 Kolom 20/20
A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm,w/c=0,87
5 Kolom 15/15
A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
6 Ring balok 15/30
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
7 Ring balok 15/20
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
8 Balok Latai 10/15
A.4.1.1.36. Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
9 Plat atap
A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
10 Shading
A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!

Page 256 of 297


M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
JUMLAH VI #REF! #REF! #REF! #REF! #REF!
VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.11. Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
kayu kelas II (kruink )
3 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.4.6.1.16. Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) moti m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
6 A.4.5.2.1. Pemasangan 1 m2 atap genteng palentong kecil m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
7 A.4.5.2.4. Pemasangan 1 m’ bubung genteng palentong m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
8 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
9 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
ukuran (120x240x9) mm, tebal 9 mm
10 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
ukuran (120x240x9) mm, tebal 4 mm
11 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH VII #REF! #REF! #REF! #REF! #REF!
VIII PEKERJAAN SANITASI
1 A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.5.1.1 10. Pemasangan 1 buah bak air fibreglass vol 1 m3 bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.5.1.1 14. Pemasangan 1 buah floor drain bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4” m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
6 A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
7 A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” m` #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
8 A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4” m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH VIII #REF! #REF! #REF! #REF! #REF!
IX PEKERJAAN BESI DAN ALUMUNIUM
1 A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.2.1.13. Pemasangan 1 m2 pintu kaca rangka alluminium m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH IX #REF! #REF! #REF! #REF! #REF!
X PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.4.6.2.9. Pemasangan 1 buah kait angin bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.4.6.2.11. Pemasangan 1 buah kunci slot bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!

Page 257 of 297


M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
5 A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
6 Ditaksir Grendel pintu bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH X #REF! #REF! #REF! #REF! #REF!
XI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20cm x 20cm m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH XI #REF! #REF! #REF! #REF! #REF!
XII PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
cat dasar, 2 lapis cat penutup )
2 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH XII #REF! #REF! #REF! #REF! #REF!
XIII PEKERJAAN INSTALASI LISTRIK
1 Ls Titik Lampu Titik #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 Ls Saklar ganda bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 Ls Saklar tunggal bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 Ls stop kontak bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 Ls lampu pijar 5W Philips bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
6 Ls Lampu SL 18 Watt Phillips bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH XIII #REF! #REF! #REF! #REF! #REF!
XIV PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm termasuk pas dinding m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 Ls Membuat Septic Tank bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 Ls Membuat peresapan bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 Ls Tanah Subur m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 Ls Pembuatan taman m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH XIV #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!
E MUSHOLLA
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH I #REF! #REF! #REF! #REF! #REF!
II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!

Page 258 of 297


M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH II #REF! #REF! #REF! #REF! #REF!
III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH III #REF! #REF! #REF! #REF! #REF!
IV PEKERJAAN DINDING
1 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
campuran 1SP : 3PP
2 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
campuran 1SP : 6PP
3 Ls Pemasangan main dinding GRC m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH IV #REF! #REF! #REF! #REF! #REF!
V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.4.2.27. Pemasangan 1 m2 acian m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH V #REF! #REF! #REF! #REF! #REF!
VI PEKERJAAN BETON
1 Lantai kerja
A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
2 Rabat Beton
A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
3 Sloof 15/25
A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm,w/c=0,87
4 Kolom 15/15
A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 Balok 15/30
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87

Page 259 of 297


M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
6 Ring balok 15/20
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
7 Balok Latai 10/15
A.4.1.1.36. Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
8 Plat atap
A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
9 Shading
A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
JUMLAH VI #REF! #REF! #REF! #REF! #REF!
VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
kayu kelas II (kruink ) #REF! #REF! #REF!
2 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.4.6.1.16. Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) moti m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 A.4.5.2.1. Pemasangan 1 m2 atap genteng palentong kecil m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
6 A.4.5.2.4. Pemasangan 1 m’ bubung genteng palentong m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
7 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
8 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
ukuran (120x240x9) mm, tebal 9 mm
9 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
ukuran (120x240x9) mm, tebal 4 mm
10 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH VII #REF! #REF! #REF! #REF! #REF!
VIII PEKERJAAN SANITASI
1 A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.5.1.1 10. Pemasangan 1 buah bak air fibreglass vol 1 m3 bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.5.1.1 14. Pemasangan 1 buah floor drain bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4” m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!

Page 260 of 297


M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
6 A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
7 A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” m` #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
8 A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4” m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH VIII #REF! #REF! #REF! #REF! #REF!
IX PEKERJAAN BESI DAN ALUMUNIUM
1 A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.2.1.12. Pemasangan 1 m2 pintu alluminium strip lebar 8 cm m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.4.2.1.13. Pemasangan 1 m2 pintu kaca rangka alluminium m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.4.2.1.13. Pemasangan 1 m2 pintu kaca rangka alluminium m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 Ls Pemasangan kubah bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH IX #REF! #REF! #REF! #REF! #REF!
X PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.4.6.2.9. Pemasangan 1 buah kait angin bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.4.6.2.11. Pemasangan 1 buah kunci slot bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
6 Ditaksir Grendel pintu bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH X #REF! #REF! #REF! #REF! #REF!
XI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20cm x 20cm m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH XI #REF! #REF! - #REF! - #REF! - #REF! #REF!
XII PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
cat dasar, 2 lapis cat penutup ) #REF! #REF!
2 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH XII #REF! #REF! #REF! #REF! #REF!
XIII PEKERJAAN INSTALASI LISTRIK
1 Ls Pemasangan meter listrik 900 watt unit #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 Ls Titik Lampu Titik #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 Ls Saklar ganda bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 Ls Saklar tunggal bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 Ls stop kontak bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
6 Ls lampu pijar 5W Philips bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
7 Ls Lampu SL 18 Watt Phillips bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH XIII #REF! #REF! #REF! #REF! #REF!
XIV PEKERJAAN LAIN-LAIN
2 Ls Membuat Septic Tank bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 Ls Membuat peresapan bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 Ls Tanah Subur m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 Ls Pembuatan taman m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH XIV #REF! #REF! #REF! #REF! - #REF!
#REF! #REF! #REF! #REF! #REF! 0.01 #REF!
F RUMAH DINAS
Page 261 of 297
M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
I PEKERJAAN PERSIAPAN
1 Ditaksir Pengukuran dan pemasangan bauwplank ls #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH I #REF! #REF! #REF! #REF! #REF!
II PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.2.3.1.14.a Pengurugan 1 m3 tanah cadas padat m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH II #REF! #REF! #REF! #REF! #REF!
III PEKERJAAN PONDASI
1 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping) m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH III #REF! #REF! #REF! #REF! #REF!
IV PEKERJAAN DINDING
1 A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
campuran 1SP : 3PP
2 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
campuran 1SP : 3PP
3 A. 4.4.1.11. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
campuran 1SP : 6PP
JUMLAH IV #REF! #REF! #REF! #REF! #REF!
V PEKERJAAN PLESTERAN
1 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm. m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.4.2.27. Pemasangan 1 m2 acian m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH V #REF! #REF! #REF! #REF! #REF!
VI PEKERJAAN BETON
1 Lantai kerja
A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87

Page 262 of 297


M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
2 Rabat Beton
A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
3 Sloof 15/25
A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm,w/c=0,87
4 Kolom 15/25
A.4.1.1.22.a Pemasangan 1 m2 bekisting untuk kolom m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm,w/c=0,87
5 Kolom 15/15
A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
6 Ring balok 15/30
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
7 Ring balok 15/20
A.4.1.1.23.a Pemasangan 1 m2 bekisting untuk balok m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
8 Balok Latai 10/15
A.4.1.1.36. Membuat 1 m’ ring balok beton bertulang (10 x 15) cm m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
9 Plat atap
A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
10 Shading
A.4.1.1.24.a Pemasangan 1 m2 bekisting untuk lantai m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87

Page 263 of 297


M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
11 Meja dapur
A.4.1.1.33. Membuat 1 m3 dinding beton bertulang (150 kg besi + bekisting) m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.17. Pembesian 1 kg dengan besi polos atau besi ulir kg #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275) , m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
slump (12 ± 2) cm, w/c = 0,87
JUMLAH VI #REF! #REF! #REF! #REF! #REF!
VII PEKERJAAN KAYU, ATAP DAN PLAFOND
1 A.4.6.1.2. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kaym3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.6.1.5. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I atam2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.4.6.1.6. Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelasm2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
kayu kelas II (kruink )
5 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II ( kruink ) m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
6 A.4.6.1.16. Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
7 Ls Lisplang GRC Board tebal 9 mmL = 30 cm (terpasang dan cat ) moti m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
8 A.4.5.2.1. Pemasangan 1 m2 atap genteng palentong kecil m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
9 A.4.5.2.4. Pemasangan 1 m’ bubung genteng palentong m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
10 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu Tahun m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
11 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
ukuran (120x240x9) mm, tebal 9 mm
12 A.4.5.1.7.a Pemasangan 1 m2 langit-langit kalsiboard m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
ukuran (120x240x9) mm, tebal 4 mm
13 A.4.5.1.10. Pemasangan 1 m’ list langit-langit gypsum profil m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
14 Ls Pemasangan rooster kayu bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH VII #REF! #REF! #REF! #REF! #REF!
VIII PEKERJAAN SANITASI
1 A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.5.1.1 5. Pemasangan 1 buah wastafel bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.5.1.1 10. Pemasangan 1 buah bak air fibreglass vol 1 m3 bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.5.1.1 12. Pemasangan 1 buah bak cuci piring stainlessteel bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 A.5.1.1 14. Pemasangan 1 buah floor drain bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
6 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
7 A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4” m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
8 A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
9 A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” m` #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
10 A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4” m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH VIII #REF! #REF! #REF! #REF! - #REF! #REF!

Page 264 of 297


M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
IX PEKERJAAN BESI DAN ALUMUNIUM
5 Ls Pintu besi Folding Gate ( Terpasang ) m2 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
JUMLAH IX #REF! #REF! #REF! #REF! #REF!
X PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.5. Pemasangan 1 buah engsel pintu bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.4.6.2.9. Pemasangan 1 buah kait angin bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.4.6.2.11. Pemasangan 1 buah kunci slot bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
6 Ditaksir Grendel pintu bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH X #REF! #REF! #REF! #REF! #REF!
XI PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.9.a Pemasangan 1m2 lantai keramik ukuran 40cm x40cm m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5cm x 20cm m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20cm x 20cm m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 A.4.4.3.58. Pemasangan 1 m2 dinding batu tempel susun sirih m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH XI #REF! #REF! #REF! #REF! #REF!
XII PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan tembok baru Interior ex. Catylac ( 1 lapis plamir, 1 lapis m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
cat dasar, 2 lapis cat penutup )
2 A.4.7.1.11. Pengecatan 1 m2 plafond ( 1 lapis cat dasar, 2 lapis cat penutup) m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH XII #REF! #REF! #REF! #REF! #REF!
XIII PEKERJAAN INSTALASI LISTRIK
1 Ls Pemasangan meter listrik 900 watt unit #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 Ls Titik Lampu Titik #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 Ls Saklar ganda bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
4 Ls Saklar tunggal bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 Ls stop kontak bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
6 Ls lampu pijar 5W Philips bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
7 Ls Lampu SL 18 Watt Phillips bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH XIII #REF! #REF! #REF! #REF! #REF!
XIV PEKERJAAN LAIN-LAIN
1 Ls Pasang saluran U 20 cm termasuk pas dinding m1 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
2 Ls Tanah Subur m3 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
3 Ls Pembuatan taman m2 #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!

Page 265 of 297


M1 (2)

HARGA NILAI BOBOT


KONTRAK S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
( Rp ) (%) (%) (%)
4 Ls Membuat Septictank bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
5 Ls Membuat Peresapan bh #REF! #REF! #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH XIV #REF! #REF! - #REF! - #REF! - #REF! #REF!
JUMLAH ( F ) #REF! #REF! #REF! #REF! #REF!
JUMLAH TOTAL #REF! #REF! #REF! #REF! #REF!
PPN 10 % #REF!
JUMLAH TOTAL #REF!
DIBULATKAN #REF!

Page 266 of 297


Gedung II
BACK UP PERHITUNGAN

KEGIATAN : REHABILITASI PEMELIHARAAN JALAN


PEKERJAAN : PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO
LOKASI : KABUPATEN KEBUMEN
TAHUN ANGGARAN : 2019

TOTAL
NO PERHITUNGAN VOLUME
VOLUME

A BACKUP JEMBATAN

I PEKERJAAN PERSIAPAN

Panjang x jml x BJ x jml


RaMobilisasi = 1 x 1.00 x 1 x 1.00 1.00 UNIT

GuMobilisasi = 1 x 1.00 x 1 x 1.00 1.00 UNIT

I PEKERJAAN BESI

Rangka JEMBATAN
Jembatan Besi L 60.60.6
= Panjang x jml x BJ x jml

= 1.7 x 220 x 5.42 x 1 = 2,027.08 kg


2,027.08
Jembatan Besi L 50.50.5 kg
= 88 x 2.00 x 3.78 x 1 = 665.28 kg

Jembatan Besi L 40.40.4


= Panjang x jml x BJ x jml
= 44 x 2.00 x 2.45 x 1 = 215.60 kg

215.60 kg

Plat T: 6mm ( Plat Sambung ) x Lebar x jml x BJ x jml


= 0.12 x 0.08 x 220.00 x 48.61 x 4 = 410.67 kg
SAMBUNGAN IWF = 0.25 x 0.12 x 7.00 x 48.61 x 2 = 20.42 kg
SAMBUNGAN IWF = 0.25 x 0.07 x 7.00 x 48.61 x 1 = 5.95 kg

437.04 Kg

IWF 150X75X5X7 = Panjang x jml x BJ x lokasi


= 88 x 1.00 x 14.00 x 1 = 1,232.00 kg

1,232.00 kg

Plat bordes tebal 2,3mm x Lebar x jml x BJ x jml


= 1.2 x 2.4 x 31.00 x 18.06 x 1 = 1,612.00 kg

1,612.00 kg

jumlah total Penyediaan Baja Struktur 6,189.00 6,189.00 kg

Pemasangan Baja Struktur


jumlah total Penyediaan Baja Struktur 6,189.00
plat bordes ful = 13.6 x 1.2 x 1.00 x 18.06 x 1 = 294.67 kg
= 88 x 0.5 x 1.00 x 18.06 x 1 = 794.44 kg
Jembatan Besi L 40.40.4 = 44 x 2.00 x 2.45 x 1 = 215.60 kg
7,493.71 7,493.71 kg

pembongkaran rangka baja 149.60 m2


= 88 x 1.7 x 1.00 x 1.00 x 1 = 149.60 m2

Mur Baut Ø 12 mm = jmlh x titik x lokasi 3,272.00 bh


buhul = = 2.00 x 4 x 220 = 1,760.00 bh
sambungan iwf = = 12.00 x 3 x 7 = 252.00 bh
plat bordes = = 35.00 x 36 x 1 = 1,260.00 bh

3,272.00 bh

Pengerjaan 10 cm pengelasan dengan las listrik 58,957.91 CM


buhul = 18.00 x 4 x 220.00 x 2 = 31,679.83 CM
siku.60.60 = 12.00 x 4 x 220.00 x 1 = 10,560.00 CM
siku.50.50 = 10.00 x 4 x 220.00 x 1 = 8,800.00 CM
siku.40.40 = 8.00 x 4 x 220.00 x 1 = 7,040.00 CM
iwf = 62.72 x 2.00 x 7.00 x 1 = 878.08 CM
58,957.91

Hal. 267 dari 297


Gedung II
TOTAL
NO PERHITUNGAN VOLUME
VOLUME
Pengecetan
bordes = jmlh x titik x lokasi
Bordes = 1.7 x 88 x 1.00 x 1.00 x 1 = 149.60 m2
iwf = 0.45 x 88 x 1.00 x 1.00 x 2 = 79.20 m2
siku 40.40 = 0.16 x 88 x 1.00 x 1.00 x 1 = 14.08 m2
siku 50.50 = 0.2 x 88 x 1.00 x 1.00 x 2 = 35.20 m2
siku 60.60 = 0.24 x 374 x 1.00 x 1.00 x 1 = 89.76 m2
pager
siku 50.50 = 0.2 x 1 x 46.00 x 1.00 x 2 = 18.40 m2
siku 50.50 = 0.2 x 88 x 1.00 x 1.00 x 2 = 35.20 m2
siku 50.50 = 0.2 x 3.8 x 46.00 x 1.00 x 2 = 69.92 m2
491.36 491.36 m2

Pengeboran = 3,020.00 x 2 x 1 = 6,040.00 bh 6,376.00 bh


iwf sambungan 12.00 x 4 7.00 = 336.00 bh
6,376.00 bh

Hal. 268 dari 297


DAFTAR PERHITUNGAN MUTHUAL CHECK AWAL ( MC.0 )

KEGIATAN : REHABILITASI PEMELIHARAAN JALAN NOMOR KONTRAK : 050/24/SPK/BM.008/IV/2019


PEKERJAAN : PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO
LOKASI : KABUPATEN KEBUMEN TANGGAL KONTRAK : 4-Apr-19
TAHUN ANGGARAN : 2019 NILAI KONTRAK : Rp199,000,000
PENYEDIA JASA : CV. KAHURIPAN

KONTRAK SELISIH TAMBAH SELISIH KURANG MC.0


HARGA
NO KODE ANALISA JENIS PEKERJAAN SAT SATUAN JUMLAH JUMLAH JUMLAH JUMLAH KET
( Rp ) VOLUME HARGA VOLUME HARGA VOLUME HARGA VOLUME HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp )

PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO


I DIVISI 1. UMUM
1 1.2 Mobilisasi ls 3,000,000.00 1.00 3,000,000.00 - - - - 1.00 3,000,000.00
2 Taksir Gudang Material/alat-alat kerja Is 1,500,000.00 1.00 1,500,000.00 - - - - 1.00 1,500,000.00
JUMLAH I 4,500,000.00 - - 4,500,000.00
II DIVISI 7. STRUKTUR
1 7.4 (1) a Penyediaan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 14,027.66 7,794.00 109,331,582.04 - - 1,605.00 22,514,419.63 6,189.00 86,817,162.41
2 7.4 (2) a Pemasangan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 799.33 8,986.00 7,182,779.38 - - 1,492.29 1,192,832.72 7,493.71 5,989,946.66
3 7.15.(5) Pembongkaran Rangka Baja M2 82,255.51 150.45 12,375,341.48 - - 0.85 69,917.18 149.60 12,305,424.30
4 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik Cm 855.69 38,907.00 33,292,330.83 20,050.91 17,157,367.29 - - 58,957.91 50,449,698.12
5 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 22,621.50 72.00 1,628,748.00 419.36 9,486,552.24 - - 491.36 11,115,300.24
6 Taksir Pengeboran Baja Struktur Ls/Lobang 500.00 7,511.00 3,755,500.00 - - 1,135.00 567,500.00 6,376.00 3,188,000.00
7 Taksir Pengadaan Mur Baut buah 2,000.00 3,626.00 7,252,000.00 - - 354.00 708,000.00 3,272.00 6,544,000.00
8 Taksir Pelumasan Baja dengan Paselin kg 63,650.00 25.00 1,591,250.00 - - 25.00 1,591,250.00 - -

JUMLAH II 176,409,531.73 26,643,919.53 26,643,919.53 176,409,531.73


JUMLAH TOTAL 180,909,531.73 26,643,919.53 26,643,919.53 180,909,531.73
PPN 10 % 18,090,953.17 2,664,391.95 2,664,391.95 18,090,953.17
JUMLAH TOTAL 199,000,484.90 29,308,311.49 29,308,311.49 199,000,484.90
DIBULATKAN 199,000,000.00 29,308,000.00 29,308,000.00 199,000,000.00

KEBUMEN, 04 APRIL 2019

Mengetahui, Menyetujui, PANITIA PENELITI PENYEDIA JASA :


Kepala Bidang Bina marga KaSi Operasional dan Pemeliharaan Jalan PELAKSANAAN KONTRAK ( PPPK ) : CV. KAHURIPAN
Dinas Pekerjaan Umum dan Dinas Pekerjaan Umum dan
Penataan Ruang Penataan Ruang 1. NYAMIRUN 1………………… 1. SLAMAET RIYADI 1………………..
Kabupaten Kebumen Kabupaten Kebumen Ketua Direktur Utama
Selaku Pejabat Pembuat Komitmen Selaku Pejabat PelaksanaTeknis Kegiatan
2. ROBIYANTORO, A.Md 2………………… 2. FUAD FAHMI 2………………..
Sekretaris Pelaksana

3. H. SOEGENG HENDARMIN 3………………… PENGAWAS DINAS :


Anggota
HANNA WIDYAWATI, ST. KURNIA HADI, ST. 1. SUPARMAN 1………………..
NIP. 19780226 200903 2 003 NIP. 19750511 201001 1 008
2. SAKUN 2………………..
M1

LAPORAN MINGGUAN

KEGIATAN : REHABILITASI PEMELIHARAAN JALAN MINGGU KE : I ( Satu )


PEKERJAAN : PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO WAKTU : 04 - 10 April 2019
LOKASI : KABUPATEN KEBUMEN RENCANA : 2.07%
TAHUN ANGGARAN : 2019 PROGRES/DEVIASI : 2.49% 0.42%

NILAI
HARGA MC.0 % S / D MINGGU LALU MINGGU INI S / D MINGGU INI
BOBOT
NO KODE ANALISA JENIS PEKERJAAN SAT SATUAN
( Rp ) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
(%) (%) (%)

PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO


I DIVISI 1. UMUM
1 1.2 Mobilisasi ls 3,000,000.00 1.00 3,000,000.00 1.66 - - 1.00 1.66 1.00 1.66
2 Taksir Gudang Material/alat-alat kerja Is 1,500,000.00 1.00 1,500,000.00 0.83 - - 1.00 0.83 1.00 0.83
JUMLAH I 4,500,000.00 2.49 - 2.49 2.49
II DIVISI 7. STRUKTUR
1 7.4 (1) a Penyediaan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 14,027.66 6,189.00 86,817,162.41 47.99 - - - - - -
2 7.4 (2) a Pemasangan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 799.33 7,493.71 5,989,946.66 3.31 - - - - - -
3 7.15.(5) Pembongkaran Rangka Baja M2 82,255.51 149.60 12,305,424.30 6.80 - - - - - -
4 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik Cm 855.69 58,957.91 50,449,698.12 27.89 - - - - - -
5 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 22,621.50 491.36 11,115,300.24 6.14 - - - - - -
6 Taksir Pengeboran Baja Struktur Ls/Lobang 500.00 6,376.00 3,188,000.00 1.76 - - - - - -
7 Taksir Pengadaan Mur Baut buah 2,000.00 3,272.00 6,544,000.00 3.62 - - - - - -
8 Taksir Pelumasan Baja dengan Paselin kg 63,650.00 - - -
JUMLAH II 176,409,531.73 97.51 - - -

JUMLAH TOTAL 180,909,531.73 100.00 - 2.49 2.49


PPN 10 % 18,090,953.17
JUMLAH TOTAL 199,000,484.90
DIBULATKAN 199,000,000.00

Kebumen, 04 April 2019

Menyetujui, Menyetujui, Dibuat,


Pengawas Dinas Pengawas Dinas CV. KAHURIPAN

SUPARMAN SAKUN FUAD FAHMI


Pelaksana

Page 271 of 297


M1

PORAN MINGGUAN

BOBOT
TIMBA-NG

(%)

100.00
100.00

-
-
-
-
-
-
-

04 April 2019

Page 272 of 297


M2

LAPORAN MINGGUAN

KEGIATAN : REHABILITASI PEMELIHARAAN JALAN MINGGU KE : II ( Dua )


PEKERJAAN : PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO WAKTU : 11 - 17 April 2019
LOKASI : KABUPATEN KEBUMEN RENCANA : 2.49%
TAHUN ANGGARAN : 2019 PROGRES/DEVIASI : 2.49% 0.00%

HARGA NILAI
MC.0 % S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT
NO KODE ANALISA JENIS PEKERJAAN SAT
( Rp BOBOT BOBOT BOBOT
) VOLUME JUMLAH HARGA (%) VOLUME VOLUME VOLUME
(%) (%) (%)

PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO


I DIVISI 1. UMUM
1 1.2 Mobilisasi ls 3,000,000.00 1.00 3,000,000.00 1.66 1.00 1.66 - - 1.00 1.66
2 Taksir Gudang Material/alat-alat kerja Is 1,500,000.00 1.00 1,500,000.00 0.83 1.00 0.83 - - 1.00 0.83
JUMLAH I 4,500,000.00 2.49 2.49 - 2.49
II DIVISI 7. STRUKTUR
1 7.4 (1) a Penyediaan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 14,027.66 6,189.00 86,817,162.41 47.99 - - - - - -
2 7.4 (2) a Pemasangan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 799.33 7,493.71 5,989,946.66 3.31 - - - - - -
3 7.15.(5) Pembongkaran Rangka Baja M2 82,255.51 149.60 12,305,424.30 6.80 - - - - - -
4 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik Cm 855.69 58,957.91 50,449,698.12 27.89 - - - - - -
5 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 22,621.50 491.36 11,115,300.24 6.14 - - - - - -
6 Taksir Pengeboran Baja Struktur Ls/Lobang 500.00 6,376.00 3,188,000.00 1.76 - - - - - -
7 Taksir Pengadaan Mur Baut buah 2,000.00 3,272.00 6,544,000.00 3.62 - - - - - -
8 Taksir Pelumasan Baja dengan Paselin kg 63,650.00 - - -
JUMLAH II 176,409,531.73 97.51 - - -

JUMLAH TOTAL 180,909,531.73 100.00 2.49 - 2.49


PPN 10 % 18,090,953.17
JUMLAH TOTAL 199,000,484.90
DIBULATKAN 199,000,000.00

Kebumen, 17 April 2019

Menyetujui, Menyetujui, Dibuat,


Pengawas Dinas Pengawas Dinas CV. KAHURIPAN

SUPARMAN SAKUN FUAD FAHMI


Pelaksana

Page 273 of 297


M2

PORAN MINGGUAN

BOBOT
TIMBA-NG

(%)

100.00
100.00

-
-
-
-
-
-
-

17 April 2019

Page 274 of 297


M3

LAPORAN MINGGUAN

KEGIATAN : REHABILITASI PEMELIHARAAN JALAN MINGGU KE : III ( Tiga )


PEKERJAAN : PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO WAKTU : 18 - 24 April 2019
LOKASI : KABUPATEN KEBUMEN RENCANA : 4.77%
TAHUN ANGGARAN : 2019 PROGRES/DEVIASI : 5.21% 0.44%

HARGA NILAI
MC.0 % S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT
NO KODE ANALISA JENIS PEKERJAAN SAT
( Rp BOBOT BOBOT BOBOT
) VOLUME JUMLAH HARGA (%) VOLUME VOLUME VOLUME
(%) (%) (%)

PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO


I DIVISI 1. UMUM
1 1.2 Mobilisasi ls 3,000,000.00 1.00 3,000,000.00 1.66 1.00 1.66 - - 1.00 1.66
2 Taksir Gudang Material/alat-alat kerja Is 1,500,000.00 1.00 1,500,000.00 0.83 1.00 0.83 - - 1.00 0.83
JUMLAH I 4,500,000.00 2.49 2.49 - 2.49
II DIVISI 7. STRUKTUR
1 7.4 (1) a Penyediaan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 14,027.66 6,189.00 86,817,162.41 47.99 - - - - - -
2 7.4 (2) a Pemasangan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 799.33 7,493.71 5,989,946.66 3.31 - - - - - -
3 7.15.(5) Pembongkaran Rangka Baja M2 82,255.51 149.60 12,305,424.30 6.80 - - 59.84 2.72 59.84 2.72
4 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik Cm 855.69 58,957.91 50,449,698.12 27.89 - - - - - -
5 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 22,621.50 491.36 11,115,300.24 6.14 - - - - - -
6 Taksir Pengeboran Baja Struktur Ls/Lobang 500.00 6,376.00 3,188,000.00 1.76 - - - - - -
7 Taksir Pengadaan Mur Baut buah 2,000.00 3,272.00 6,544,000.00 3.62 - - - - - -
8 Taksir Pelumasan Baja dengan Paselin kg 63,650.00 - - -
JUMLAH II 176,409,531.73 97.51 - 2.72 2.72

JUMLAH TOTAL 180,909,531.73 100.00 2.49 2.72 5.21


PPN 10 % 18,090,953.17
JUMLAH TOTAL 199,000,484.90
DIBULATKAN 199,000,000.00

Kebumen, 24 April 2019

Menyetujui, Menyetujui, Dibuat,


Pengawas Dinas Pengawas Dinas CV. KAHURIPAN

SUPARMAN SAKUN FUAD FAHMI


Pelaksana

Page 275 of 297


M3

PORAN MINGGUAN

BOBOT
TIMBA-NG

(%)

100.00
100.00

-
-
40.00
-
-
-
-

24 April 2019

Page 276 of 297


M4

LAPORAN MINGGUAN

KEGIATAN : REHABILITASI PEMELIHARAAN JALAN MINGGU KE : IV ( Empat )


PEKERJAAN : PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO WAKTU : 25 April - 01 Mei 2019
LOKASI : KABUPATEN KEBUMEN RENCANA : 7.05%
TAHUN ANGGARAN : 2019 PROGRES/DEVIASI : 9.29% 2.24%

NILAI BOBOT
HARGA MC.0 % S / D MINGGU LALU MINGGU INI S / D MINGGU INI
BOBOT TIMBA-NG
NO KODE ANALISA JENIS PEKERJAAN SAT SATUAN
( Rp ) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%)
(%) (%) (%)

PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO


I DIVISI 1. UMUM
1 1.2 Mobilisasi ls 3,000,000.00 1.00 3,000,000.00 1.66 1.00 1.66 - - 1.00 1.66 100.00
2 Taksir Gudang Material/alat-alat kerja Is 1,500,000.00 1.00 1,500,000.00 0.83 1.00 0.83 - - 1.00 0.83 100.00
JUMLAH I 4,500,000.00 2.49 2.49 - 2.49
II DIVISI 7. STRUKTUR
1 7.4 (1) a Penyediaan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 14,027.66 6,189.00 86,817,162.41 47.99 - - - - - - -
2 7.4 (2) a Pemasangan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 799.33 7,493.71 5,989,946.66 3.31 - - - - - - -
3 7.15.(5) Pembongkaran Rangka Baja M2 82,255.51 149.60 12,305,424.30 6.80 59.84 2.72 89.76 4.08 149.60 6.80 100.00
4 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik Cm 855.69 58,957.91 50,449,698.12 27.89 - - - - - - -
5 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 22,621.50 491.36 11,115,300.24 6.14 - - - - - - -
6 Taksir Pengeboran Baja Struktur Ls/Lobang 500.00 6,376.00 3,188,000.00 1.76 - - - - - - -
7 Taksir Pengadaan Mur Baut buah 2,000.00 3,272.00 6,544,000.00 3.62 - - - - - - -
8 Taksir Pelumasan Baja dengan Paselin kg 63,650.00 - - -
JUMLAH II 176,409,531.73 97.51 2.72 4.08 6.80

JUMLAH TOTAL 180,909,531.73 100.00 5.21 4.08 9.29


PPN 10 % 18,090,953.17
JUMLAH TOTAL 199,000,484.90
DIBULATKAN 199,000,000.00

Kebumen, 01 Mei 2019

Menyetujui, Menyetujui, Dibuat,


Pengawas Dinas Pengawas Dinas CV. KAHURIPAN

SUPARMAN SAKUN FUAD FAHMI


Pelaksana

Page 277 of 297


B1

LAPORAN BULANAN

KEGIATAN : REHABILITASI PEMELIHARAAN JALAN BULAN KE : I ( Satu )


PEKERJAAN : PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO WAKTU : 04 April - 01 Mei 2019
LOKASI : KABUPATEN KEBUMEN RENCANA : 7.05%
TAHUN ANGGARAN : 2019 PROGRES/DEVIASI : 9.29% 2.24%

NILAI
HARGA MC.0 % S / D BULAN LALU BULAN INI S / D BULAN INI
BOBOT
NO KODE ANALISA JENIS PEKERJAAN SAT SATUAN
( Rp ) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
(%) (%) (%)

PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO


I DIVISI 1. UMUM
1 1.2 Mobilisasi ls 3,000,000.00 1.00 3,000,000.00 1.66 - - 1.00 1.66 1.00 1.66
2 Taksir Gudang Material/alat-alat kerja Is 1,500,000.00 1.00 1,500,000.00 0.83 - - 1.00 0.83 1.00 0.83
JUMLAH I 4,500,000.00 2.49 - - 2.49 2.49
II DIVISI 7. STRUKTUR -
1 7.4 (1) a Penyediaan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 14,027.66 6,189.00 86,817,162.41 47.99 - - - - - -
2 7.4 (2) a Pemasangan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 799.33 7,493.71 5,989,946.66 3.31 - - - - - -
3 7.15.(5) Pembongkaran Rangka Baja M2 82,255.51 149.60 12,305,424.30 6.80 - - 149.60 6.80 149.60 6.80
4 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik Cm 855.69 58,957.91 50,449,698.12 27.89 - - - - - -
5 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 22,621.50 491.36 11,115,300.24 6.14 - - - - - -
6 Taksir Pengeboran Baja Struktur Ls/Lobang 500.00 6,376.00 3,188,000.00 1.76 - - - - - -
7 Taksir Pengadaan Mur Baut buah 2,000.00 3,272.00 6,544,000.00 3.62 - - - - - -
8 Taksir Pelumasan Baja dengan Paselin kg 63,650.00 - - - -
JUMLAH II 176,409,531.73 97.51 - 6.80 6.80

JUMLAH TOTAL 180,909,531.73 100.00 - 9.29 9.29


PPN 10 % 18,090,953.17
JUMLAH TOTAL 199,000,484.90
DIBULATKAN 199,000,000.00

Kebumen, 01 Mei 2019

Menyetujui, Menyetujui, Dibuat,


Pengawas Dinas Pengawas Dinas CV. KAHURIPAN

SUPARMAN SAKUN FUAD FAHMI


Pelaksana

Page 278 of 297


B1

APORAN BULANAN

BOBOT
TIMBA-NG

(%)

100.00
100.00

-
-
100.00
-
-
-
-

01 Mei 2019

Page 279 of 297


M5

LAPORAN MINGGUAN

KEGIATAN : REHABILITASI PEMELIHARAAN JALAN MINGGU KE : V ( Lima )


PEKERJAAN : PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO WAKTU : 02 - 08 Mei 2019
LOKASI : KABUPATEN KEBUMEN RENCANA : 21.41%
TAHUN ANGGARAN : 2019 PROGRES/DEVIASI : 19.80% -1.61%

HARGA NILAI
MC.0 % S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT
NO KODE ANALISA JENIS PEKERJAAN SAT
VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
( Rp ) (%) (%) (%)

PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO


I DIVISI 1. UMUM
1 1.2 Mobilisasi ls 3,000,000.00 1.00 3,000,000.00 1.66 1.00 1.66 - - 1.00 1.66
2 Taksir Gudang Material/alat-alat kerja Is 1,500,000.00 1.00 1,500,000.00 0.83 1.00 0.83 - - 1.00 0.83
JUMLAH I 4,500,000.00 2.49 - 2.49 - 2.49
II DIVISI 7. STRUKTUR -
1 7.4 (1) a Penyediaan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 14,027.66 6,189.00 86,817,162.41 47.99 - - 1,232.00 9.55 1,232.00 9.55
2 7.4 (2) a Pemasangan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 799.33 7,493.71 5,989,946.66 3.31 - - 1,232.00 0.54 1,232.00 0.54
3 7.15.(5) Pembongkaran Rangka Baja M2 82,255.51 149.60 12,305,424.30 6.80 149.60 6.80 - - 149.60 6.80
4 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik Cm 855.69 58,957.91 50,449,698.12 27.89 - - 878.08 0.42 878.08 0.42
5 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 22,621.50 491.36 11,115,300.24 6.14 - - - - - -
6 Taksir Pengeboran Baja Struktur Ls/Lobang 500.00 6,376.00 3,188,000.00 1.76 - - - - - -
7 Taksir Pengadaan Mur Baut buah 2,000.00 3,272.00 6,544,000.00 3.62 - - - - - -
8 Taksir Pelumasan Baja dengan Paselin kg 63,650.00 - - - -
JUMLAH II 176,409,531.73 97.51 6.80 10.51 17.31

JUMLAH TOTAL 180,909,531.73 100.00 9.29 10.51 19.80


PPN 10 % 18,090,953.17
JUMLAH TOTAL 199,000,484.90
DIBULATKAN 199,000,000.00

Kebumen, 08 Mei 2019

Menyetujui, Menyetujui, Dibuat,


Pengawas Dinas Pengawas Dinas CV. KAHURIPAN

SUPARMAN SAKUN FUAD FAHMI


Pelaksana

Page 280 of 297


M5

PORAN MINGGUAN

BOBOT
TIMBA-NG

(%)

100.00
100.00

19.91
16.44
100.00
1.49
-
-
-

08 Mei 2019

Page 281 of 297


M6

LAPORAN MINGGUAN

KEGIATAN : REHABILITASI PEMELIHARAAN JALAN MINGGU KE : VI ( Enam )


PEKERJAAN : PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO WAKTU : 09 - 15 Mei 2019
LOKASI : KABUPATEN KEBUMEN RENCANA : 33.50%
TAHUN ANGGARAN : 2019 PROGRES/DEVIASI : 42.82% 9.32%

HARGA NILAI
MC.0 % S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT
NO KODE ANALISA JENIS PEKERJAAN SAT
( Rp BOBOT BOBOT BOBOT
) VOLUME JUMLAH HARGA (%) VOLUME VOLUME VOLUME
(%) (%) (%)

PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO


I DIVISI 1. UMUM
1 1.2 Mobilisasi ls 3,000,000.00 1.00 3,000,000.00 1.66 1.00 1.66 - - 1.00 1.66
2 Taksir Gudang Material/alat-alat kerja Is 1,500,000.00 1.00 1,500,000.00 0.83 1.00 0.83 - - 1.00 0.83
JUMLAH I 4,500,000.00 2.49 - 2.49 - 2.49
II DIVISI 7. STRUKTUR -
1 7.4 (1) a Penyediaan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 14,027.66 6,189.00 86,817,162.41 47.99 1,232.00 9.55 1,700.00 13.18 2,932.00 22.73
2 7.4 (2) a Pemasangan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 799.33 7,493.71 5,989,946.66 3.31 1,232.00 0.54 1,700.00 0.75 2,932.00 1.30
3 7.15.(5) Pembongkaran Rangka Baja M2 82,255.51 149.60 12,305,424.30 6.80 149.60 6.80 - - 149.60 6.80
4 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik Cm 855.69 58,957.91 50,449,698.12 27.89 878.08 0.42 19,200.00 9.08 20,078.08 9.50
5 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 22,621.50 491.36 11,115,300.24 6.14 - - - - - -
6 Taksir Pengeboran Baja Struktur Ls/Lobang 500.00 6,376.00 3,188,000.00 1.76 - - - - - -
7 Taksir Pengadaan Mur Baut buah 2,000.00 3,272.00 6,544,000.00 3.62 - - - - - -
8 Taksir Pelumasan Baja dengan Paselin kg 63,650.00 - - -
JUMLAH II 176,409,531.73 97.51 17.31 23.01 40.33

JUMLAH TOTAL 180,909,531.73 100.00 19.80 23.01 42.82


PPN 10 % 18,090,953.17
JUMLAH TOTAL 199,000,484.90
DIBULATKAN 199,000,000.00

Kebumen, 15 Mei 2019

Menyetujui, Menyetujui, Dibuat,


Pengawas Dinas Pengawas Dinas CV. KAHURIPAN

SUPARMAN SAKUN FUAD FAHMI


Pelaksana

Page 282 of 297


M6

PORAN MINGGUAN

BOBOT
TIMBA-NG

(%)

100.00
100.00

47.37
39.13
100.00
34.05
-
-
-

15 Mei 2019

Page 283 of 297


M7

LAPORAN MINGGUAN

KEGIATAN : REHABILITASI PEMELIHARAAN JALAN MINGGU KE : VII ( Tujuh )


PEKERJAAN : PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO WAKTU : 16 - 22 Mei 2019
LOKASI : KABUPATEN KEBUMEN RENCANA : 46.91%
TAHUN ANGGARAN : 2019 PROGRES/DEVIASI : 63.40% 16.49%

NILAI
HARGA MC.0 % S / D MINGGU LALU MINGGU INI S / D MINGGU INI
BOBOT
NO KODE ANALISA JENIS PEKERJAAN SAT SATUAN
( Rp ) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
(%) (%) (%)

PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO


I DIVISI 1. UMUM
1 1.2 Mobilisasi ls 3,000,000.00 1.00 3,000,000.00 1.66 1.00 1.66 - - 1.00 1.66
2 Taksir Gudang Material/alat-alat kerja Is 1,500,000.00 1.00 1,500,000.00 0.83 1.00 0.83 - - 1.00 0.83
JUMLAH I 4,500,000.00 2.49 - 2.49 - 2.49
II DIVISI 7. STRUKTUR -
1 7.4 (1) a Penyediaan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 14,027.66 6,189.00 86,817,162.41 47.99 2,932.00 22.73 1,200.00 9.30 4,132.00 32.04
2 7.4 (2) a Pemasangan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 799.33 7,493.71 5,989,946.66 3.31 2,932.00 1.30 1,200.00 0.53 4,132.00 1.83
3 7.15.(5) Pembongkaran Rangka Baja M2 82,255.51 149.60 12,305,424.30 6.80 149.60 6.80 - - 149.60 6.80
4 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik Cm 855.69 58,957.91 50,449,698.12 27.89 20,078.08 9.50 19,190.00 9.08 39,268.08 18.57
5 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 22,621.50 491.36 11,115,300.24 6.14 - - 80.00 1.00 80.00 1.00
6 Taksir Pengeboran Baja Struktur Ls/Lobang 500.00 6,376.00 3,188,000.00 1.76 - - 890.00 0.25 890.00 0.25
7 Taksir Pengadaan Mur Baut buah 2,000.00 3,272.00 6,544,000.00 3.62 - - 385.00 0.43 385.00 0.43
8 Taksir Pelumasan Baja dengan Paselin kg 63,650.00 - - - -
JUMLAH II 176,409,531.73 97.51 40.33 20.58 60.91

JUMLAH TOTAL 180,909,531.73 100.00 42.82 20.58 63.40


PPN 10 % 18,090,953.17
JUMLAH TOTAL 199,000,484.90
DIBULATKAN 199,000,000.00

Kebumen, 22 Mei 2019

Menyetujui, Menyetujui, Dibuat,


Pengawas Dinas Pengawas Dinas CV. KAHURIPAN

SUPARMAN SAKUN FUAD FAHMI


Pelaksana

Page 284 of 297


M7

PORAN MINGGUAN

BOBOT
TIMBA-NG

(%)

100.00
100.00

66.76
55.14
100.00
66.60
16.28
13.96
11.77

22 Mei 2019

Page 285 of 297


M8

LAPORAN MINGGUAN

KEGIATAN : REHABILITASI PEMELIHARAAN JALAN MINGGU KE : VIII ( Delapan )


PEKERJAAN : PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO WAKTU : 23 - 29 Mei 2019
LOKASI : KABUPATEN KEBUMEN RENCANA : 64.92%
TAHUN ANGGARAN : 2019 PROGRES/DEVIASI : 96.36% 31.44%

HARGA NILAI
MC.0 % S / D MINGGU LALU MINGGU INI S / D MINGGU INI
SATUAN BOBOT
NO KODE ANALISA JENIS PEKERJAAN SAT
( Rp BOBOT BOBOT BOBOT
) VOLUME JUMLAH HARGA (%) VOLUME VOLUME VOLUME
(%) (%) (%)

PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO


I DIVISI 1. UMUM
1 1.2 Mobilisasi ls 3,000,000.00 1.00 3,000,000.00 1.66 1.00 1.66 - - 1.00 1.66
2 Taksir Gudang Material/alat-alat kerja Is 1,500,000.00 1.00 1,500,000.00 0.83 1.00 0.83 - - 1.00 0.83
JUMLAH I 4,500,000.00 2.49 - 2.49 - 2.49
II DIVISI 7. STRUKTUR -
1 7.4 (1) a Penyediaan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 14,027.66 6,189.00 86,817,162.41 47.99 4,132.00 32.04 2,057.00 15.95 6,189.00 47.99
2 7.4 (2) a Pemasangan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 799.33 7,493.71 5,989,946.66 3.31 4,132.00 1.83 3,361.71 1.49 7,493.71 3.31
3 7.15.(5) Pembongkaran Rangka Baja M2 82,255.51 149.60 12,305,424.30 6.80 149.60 6.80 - - 149.60 6.80
4 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik Cm 855.69 58,957.91 50,449,698.12 27.89 39,268.08 18.57 19,689.83 9.31 58,957.91 27.89
5 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 22,621.50 491.36 11,115,300.24 6.14 80.00 1.00 120.00 1.50 200.00 2.50
6 Taksir Pengeboran Baja Struktur Ls/Lobang 500.00 6,376.00 3,188,000.00 1.76 890.00 0.25 5,486.00 1.52 6,376.00 1.76
7 Taksir Pengadaan Mur Baut buah 2,000.00 3,272.00 6,544,000.00 3.62 385.00 0.43 2,887.00 3.19 3,272.00 3.62
8 Taksir Pelumasan Baja dengan Paselin kg 63,650.00 - - -
JUMLAH II 176,409,531.73 97.51 60.91 32.96 93.87

JUMLAH TOTAL 180,909,531.73 100.00 63.40 32.96 96.36


PPN 10 % 18,090,953.17
JUMLAH TOTAL 199,000,484.90
DIBULATKAN 199,000,000.00

Kebumen, 29 Mei 2019

Menyetujui, Menyetujui, Dibuat,


Pengawas Dinas Pengawas Dinas CV. KAHURIPAN

SUPARMAN SAKUN FUAD FAHMI


Pelaksana

Page 286 of 297


M8

PORAN MINGGUAN

BOBOT
TIMBA-NG

(%)

100.00
100.00

100.00
100.00
100.00
100.00
40.70
100.00
100.00

29 Mei 2019

Page 287 of 297


B2

LAPORAN BULANAN

KEGIATAN : REHABILITASI PEMELIHARAAN JALAN BULAN KE : II ( Dua )


PEKERJAAN : PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO WAKTU : 02 - 29 Mei 2019
LOKASI : KABUPATEN KEBUMEN RENCANA : 64.92%
TAHUN ANGGARAN : 2019 PROGRES/DEVIASI : 96.36% 31.44%

NILAI
HARGA MC.0 % S / D BULAN LALU BULAN INI S / D BULAN INI
BOBOT
NO KODE ANALISA JENIS PEKERJAAN SAT SATUAN
( Rp ) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
(%) (%) (%)

PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO


I DIVISI 1. UMUM
1 1.2 Mobilisasi ls 3,000,000.00 1.00 3,000,000.00 1.66 1.00 1.66 - - 1.00 1.66
2 Taksir Gudang Material/alat-alat kerja Is 1,500,000.00 1.00 1,500,000.00 0.83 1.00 0.83 - - 1.00 0.83
JUMLAH I 4,500,000.00 2.49 - 2.49 - - 2.49
II DIVISI 7. STRUKTUR - -
1 7.4 (1) a Penyediaan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 14,027.66 6,189.00 86,817,162.41 47.99 - - 6,189.00 47.99 6,189.00 47.99
2 7.4 (2) a Pemasangan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 799.33 7,493.71 5,989,946.66 3.31 - - 7,493.71 3.31 7,493.71 3.31
3 7.15.(5) Pembongkaran Rangka Baja M2 82,255.51 149.60 12,305,424.30 6.80 149.60 6.80 - - 149.60 6.80
4 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik Cm 855.69 58,957.91 50,449,698.12 27.89 - - 58,957.91 27.89 58,957.91 27.89
5 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 22,621.50 491.36 11,115,300.24 6.14 - - 200.00 2.50 200.00 2.50
6 Taksir Pengeboran Baja Struktur Ls/Lobang 500.00 6,376.00 3,188,000.00 1.76 - - 6,376.00 1.76 6,376.00 1.76
7 Taksir Pengadaan Mur Baut buah 2,000.00 3,272.00 6,544,000.00 3.62 - - 3,272.00 3.62 3,272.00 3.62
8 Taksir Pelumasan Baja dengan Paselin kg 63,650.00 - - - -
JUMLAH II 176,409,531.73 97.51 6.80 87.07 93.87

JUMLAH TOTAL 180,909,531.73 100.00 9.29 87.07 96.36


PPN 10 % 18,090,953.17
JUMLAH TOTAL 199,000,484.90
DIBULATKAN 199,000,000.00

Kebumen, 29 Mei 2019

Menyetujui, Menyetujui, Dibuat,


Pengawas Dinas Pengawas Dinas CV. KAHURIPAN

SUPARMAN SAKUN FUAD FAHMI


Pelaksana

Page 288 of 297


B2

APORAN BULANAN

BOBOT
TIMBA-NG

(%)

100.00
100.00

100.00
100.00
100.00
100.00
40.70
100.00
100.00

29 Mei 2019

Page 289 of 297


M9

LAPORAN MINGGUAN

KEGIATAN : REHABILITASI PEMELIHARAAN JALAN MINGGU KE : IX ( Sembilan )


PEKERJAAN : PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO WAKTU : 30 Mei- 05 Juni 2019
LOKASI : KABUPATEN KEBUMEN RENCANA : 85.98%
TAHUN ANGGARAN : 2019 PROGRES/DEVIASI : 99.36% 13.38%

NILAI
HARGA MC.0 % S / D MINGGU LALU MINGGU INI S / D MINGGU INI
BOBOT
NO KODE ANALISA JENIS PEKERJAAN SAT SATUAN
( Rp ) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
(%) (%) (%)

PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO


I DIVISI 1. UMUM
1 1.2 Mobilisasi ls 3,000,000.00 1.00 3,000,000.00 1.66 1.00 1.66 - - 1.00 1.66
2 Taksir Gudang Material/alat-alat kerja Is 1,500,000.00 1.00 1,500,000.00 0.83 1.00 0.83 - - 1.00 0.83
JUMLAH I 4,500,000.00 2.49 - 2.49 - 2.49
II DIVISI 7. STRUKTUR -
1 7.4 (1) a Penyediaan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 14,027.66 6,189.00 86,817,162.41 47.99 6,189.00 47.99 - - 6,189.00 47.99
2 7.4 (2) a Pemasangan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 799.33 7,493.71 5,989,946.66 3.31 7,493.71 3.31 - - 7,493.71 3.31
3 7.15.(5) Pembongkaran Rangka Baja M2 82,255.51 149.60 12,305,424.30 6.80 149.60 6.80 - - 149.60 6.80
4 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik Cm 855.69 58,957.91 50,449,698.12 27.89 58,957.91 27.89 - - 58,957.91 27.89
5 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 22,621.50 491.36 11,115,300.24 6.14 200.00 2.50 240.00 3.00 440.00 5.50
6 Taksir Pengeboran Baja Struktur Ls/Lobang 500.00 6,376.00 3,188,000.00 1.76 6,376.00 1.76 - - 6,376.00 1.76
7 Taksir Pengadaan Mur Baut buah 2,000.00 3,272.00 6,544,000.00 3.62 3,272.00 3.62 - - 3,272.00 3.62
8 Taksir Pelumasan Baja dengan Paselin kg 63,650.00 - - -
JUMLAH II 176,409,531.73 97.51 93.87 - 96.87

JUMLAH TOTAL 180,909,531.73 100.00 96.36 - 99.36


PPN 10 % 18,090,953.17
JUMLAH TOTAL 199,000,484.90
DIBULATKAN 199,000,000.00

Kebumen, 05 Juni 2019

Menyetujui, Menyetujui, Dibuat,


Pengawas Dinas Pengawas Dinas CV. KAHURIPAN

SUPARMAN SAKUN FUAD FAHMI


Pelaksana

Page 290 of 297


M9

PORAN MINGGUAN

BOBOT
TIMBA-NG

(%)

100.00
100.00

100.00
100.00
100.00
100.00
89.55
100.00
100.00

05 Juni 2019

Page 291 of 297


M10

LAPORAN MINGGUAN

KEGIATAN : REHABILITASI PEMELIHARAAN JALAN MINGGU KE : X ( Sepuluh )


PEKERJAAN : PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO WAKTU : 06 - 10 Juni 2019
LOKASI : KABUPATEN KEBUMEN RENCANA : 93.62%
TAHUN ANGGARAN : 2019 PROGRES/DEVIASI : 100.00% 6.38%

NILAI
MC.0 % S / D MINGGU LALU MINGGU INI S / D MINGGU INI
HARGA BOBOT
NO KODE ANALISA JENIS PEKERJAAN SAT SATUAN
( Rp ) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME VOLUME BOBOT
(%) BOBOT (%) (%)

PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO


I DIVISI 1. UMUM
1 1.2 Mobilisasi ls 3,000,000.00 1.00 3,000,000.00 1.66 1.00 1.66 - - 1.00 1.66
2 Taksir Gudang Material/alat-alat kerja Is 1,500,000.00 1.00 1,500,000.00 0.83 1.00 0.83 - - 1.00 0.83
JUMLAH I 4,500,000.00 2.49 - 2.49 - 2.49
II DIVISI 7. STRUKTUR -
1 7.4 (1) a Penyediaan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 14,027.66 6,189.00 86,817,162.41 47.99 6,189.00 47.99 - - 6,189.00 47.99
2 7.4 (2) a Pemasangan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 799.33 7,493.71 5,989,946.66 3.31 7,493.71 3.31 - - 7,493.71 3.31
3 7.15.(5) Pembongkaran Rangka Baja M2 82,255.51 149.60 12,305,424.30 6.80 149.60 6.80 - - 149.60 6.80
4 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik Cm 855.69 58,957.91 50,449,698.12 27.89 58,957.91 27.89 - - 58,957.91 27.89
5 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 22,621.50 491.36 11,115,300.24 6.14 440.00 5.50 51.36 0.64 491.36 6.14
6 Taksir Pengeboran Baja Struktur Ls/Lobang 500.00 6,376.00 3,188,000.00 1.76 6,376.00 1.76 - - 6,376.00 1.76
7 Taksir Pengadaan Mur Baut buah 2,000.00 3,272.00 6,544,000.00 3.62 3,272.00 3.62 - - 3,272.00 3.62
8 Taksir Pelumasan Baja dengan Paselin kg 63,650.00 - - -
JUMLAH II 176,409,531.73 97.51 96.87 - 97.51

JUMLAH TOTAL 180,909,531.73 100.00 99.36 - 100.00


PPN 10 % 18,090,953.17
JUMLAH TOTAL 199,000,484.90
DIBULATKAN 199,000,000.00

Kebumen, 10 Juni 2019

Menyetujui, Menyetujui, Dibuat,


Pengawas Dinas Pengawas Dinas CV. KAHURIPAN

SUPARMAN SAKUN FUAD FAHMI


Pelaksana

Page 292 of 297


M10

PORAN MINGGUAN

BOBOT
TIMBA-NG

(%)

100.00
100.00

100.00
100.00
100.00
100.00
100.00
100.00
100.00

10 Juni 2019

Page 293 of 297


B3

LAPORAN BULANAN

KEGIATAN : REHABILITASI PEMELIHARAAN JALAN BULAN KE : III ( Tiga )


PEKERJAAN : PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO WAKTU : 30 Mei - 10 Juni 2019
LOKASI : KABUPATEN KEBUMEN RENCANA : 100.00%
TAHUN ANGGARAN : 2019 PROGRES/DEVIASI : 100.00% 0.00%

NILAI
HARGA MC.0 % S / D BULAN LALU BULAN INI S / D BULAN INI
BOBOT
NO KODE ANALISA JENIS PEKERJAAN SAT SATUAN
( Rp ) VOLUME JUMLAH HARGA (%) VOLUME BOBOT VOLUME VOLUME BOBOT
(%) BOBOT (%) (%)

PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO


I DIVISI 1. UMUM
1 1.2 Mobilisasi ls 3,000,000.00 1.00 3,000,000.00 1.66 1.00 1.66 - - 1.00 1.66
2 Taksir Gudang Material/alat-alat kerja Is 1,500,000.00 1.00 1,500,000.00 0.83 1.00 0.83 - - 1.00 0.83
JUMLAH I 4,500,000.00 2.49 - 2.49 - - 2.49
II DIVISI 7. STRUKTUR - -
1 7.4 (1) a Penyediaan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 14,027.66 6,189.00 86,817,162.41 47.99 6,189.00 47.99 - - 6,189.00 47.99
2 7.4 (2) a Pemasangan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 799.33 7,493.71 5,989,946.66 3.31 7,493.71 3.31 - - 7,493.71 3.31
3 7.15.(5) Pembongkaran Rangka Baja M2 82,255.51 149.60 12,305,424.30 6.80 149.60 6.80 - - 149.60 6.80
4 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik Cm 855.69 58,957.91 50,449,698.12 27.89 58,957.91 27.89 - - 58,957.91 27.89
5 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 22,621.50 491.36 11,115,300.24 6.14 200.00 2.50 291.36 3.64 491.36 6.14
6 Taksir Pengeboran Baja Struktur Ls/Lobang 500.00 6,376.00 3,188,000.00 1.76 6,376.00 1.76 - - 6,376.00 1.76
7 Taksir Pengadaan Mur Baut buah 2,000.00 3,272.00 6,544,000.00 3.62 3,272.00 3.62 - - 3,272.00 3.62
8 Taksir Pelumasan Baja dengan Paselin kg 63,650.00 - - - -
JUMLAH II 176,409,531.73 97.51 93.87 3.64 97.51

JUMLAH TOTAL 180,909,531.73 100.00 96.36 3.64 100.00


PPN 10 % 18,090,953.17
JUMLAH TOTAL 199,000,484.90
DIBULATKAN 199,000,000.00

Kebumen, 10 Juni 2019

Menyetujui, Menyetujui, Dibuat,


Pengawas Dinas Pengawas Dinas CV. KAHURIPAN

SUPARMAN SAKUN FUAD FAHMI


Pelaksana

Page 294 of 297


B3

APORAN BULANAN

BOBOT
TIMBA-NG

(%)

100.00
100.00

100.00
100.00
100.00
100.00
100.00
100.00
100.00

10 Juni 2019

Page 295 of 297


DAFTAR PERHITUNGAN MUTHUAL CHECK AKHIR ( MC.100 )

KEGIATAN : REHABILITASI PEMELIHARAAN JALAN NOMOR KONTRAK : 050/24/SPK/BM.008/IV/2019


PEKERJAAN : PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO
LOKASI : KEC. KARANGSAMBUNG, KEBUMEN TANGGAL KONTRAK : 4-Apr-19
TAHUN ANGGARAN : 2019 NILAI KONTRAK : Rp199,000,000
PENYEDIA JASA : CV. KAHURIPAN

MC.0 SELISIH TAMBAH SELISIH KURANG MC.100


HARGA
NO KODE ANALISA JENIS PEKERJAAN SAT SATUAN JUMLAH JUMLAH JUMLAH JUMLAH KET
( Rp ) VOLUME HARGA VOLUME HARGA VOLUME HARGA VOLUME HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp )

PEMELIHARAAN JEMBATAN GANTUNG WONOTIRTO


I DIVISI 1. UMUM
1 1.2 Mobilisasi ls 3,000,000.00 1.00 3,000,000.00 - - - - 1.00 3,000,000.00
2 Taksir Gudang Material/alat-alat kerja Is 1,500,000.00 1.00 1,500,000.00 - - - - 1.00 1,500,000.00
JUMLAH I 4,500,000.00 - - 4,500,000.00
II DIVISI 7. STRUKTUR
1 7.4 (1) a Penyediaan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 14,027.66 6,189.00 86,817,162.41 - - - - 6,189.00 86,817,162.41
2 7.4 (2) a Pemasangan Baja Struktur BJ 34 (Titik Leleh 210 MPa) kg 799.33 7,493.71 5,989,946.66 - - - - 7,493.71 5,989,946.66
3 7.15.(5) Pembongkaran Rangka Baja M2 82,255.51 149.60 12,305,424.30 - - - - 149.60 12,305,424.30
4 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik Cm 855.69 58,957.91 50,449,698.12 - - - - 58,957.91 50,449,698.12
5 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 22,621.50 491.36 11,115,300.24 - - - - 491.36 11,115,300.24
6 Taksir Pengeboran Baja Struktur Ls/Lobang 500.00 6,376.00 3,188,000.00 - - - - 6,376.00 3,188,000.00
7 Taksir Pengadaan Mur Baut buah 2,000.00 3,272.00 6,544,000.00 - - - - 3,272.00 6,544,000.00
8 Taksir Pelumasan Baja dengan Paselin kg 63,650.00 - - - - - - - -

JUMLAH II 176,409,531.73 - - 176,409,531.73


JUMLAH TOTAL 180,909,531.73 - - 180,909,531.73
PPN 10 % 18,090,953.17 - - 18,090,953.17
JUMLAH TOTAL 199,000,484.90 - - 199,000,484.90
DIBULATKAN 199,000,000.00 - - 199,000,000.00

KEBUMEN, 10 JUNI 2019

Mengetahui, Menyetujui, PANITIA PENELITI PENYEDIA JASA :


Kepala Bidang Bina marga KaSi Operasional dan Pemeliharaan Jalan PELAKSANAAN KONTRAK ( PPPK ) : CV. KAHURIPAN
Dinas Pekerjaan Umum dan Dinas Pekerjaan Umum dan
Penataan Ruang Penataan Ruang 1. NYAMIRUN 1………………… 1. SLAMAET RIYADI 1………………..
Kabupaten Kebumen Kabupaten Kebumen Ketua Direktur Utama
Selaku Pejabat Pembuat Komitmen Selaku Pejabat PelaksanaTeknis Kegiatan
2. ROBIYANTORO, A.Md 2………………… 2. FUAD FAHMI 2………………..
Sekretaris Pelaksana

3. H. SOEGENG HENDARMIN 3………………… PENGAWAS DINAS :