Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

Why did this load

SPOTCHECKSAFETY

tip over? – part 2


In part 1 of this article, Picture 1: The transport
published in the last issue of combination shortly
before it tipped over.
HLPFI, safety expert Richard
Krabbendam described the
cause of an accident in
August 1988 and the legal
consequences it had for the
parties involved. In the final

T
part, he reviews the technical
and legal judgements.

o summarise the whole incident acknowledged that the planned 7.6 km trailer deck above the road surface at each
under investigation, party ‘A’ had journey was proceeding to plan and the corner.
subcontracted the transportation of project manager of party ‘A’ then left for the It proved that the trailer height at the
a 203-tonne reactor from refinery to open the gate and prepare the site right and left rear end was 112 cm above the
Immingham Docks, UK, to a for the offloading of the reactor. road and at the front right side 108.5 cm and
nearby refinery. The travelling distance was After about 10 minutes, when the front left side 110 cm. These measurements,
only 7.8 km, but a short distance from the transport combination did not show up, he as well as the pictures taken directly after the
docks as the trailer negotiated a long curve drove back 6 km along the planned route accident, were presented in an official
with a camber of 2.8°, the transport and found the reactor lying on its back in a accident report.
combination tipped over and the reactor ditch next to the road while the 12-axle line According to the police escort, which
landed in a ditch next to the road. trailer was still on the road and standing on drove behind the transport combination, the
The cost of the salvage operation and the its tyres (see pictures 2 and 3). trailer tilted slightly to the lower side of the
damage repair to the reactor were covered by curve, tilted a bit more and suddenly the
the transport insurance arranged at the Accident scene whole combination tipped over. The lashing
client’s request by party ‘A’, which claimed chains broke loose, the reactor landed in the
that the cause of the accident was the When the project manager arrived at the ditch at the lower side of the curve next to
negligence of the trailer operator. Party ‘B’ accident scene, he immediately investigated the road and the trailer fell back on its tyres
(the trailer operator) denied this claim. the condition of the trailer for hydraulic on the road.
It took eight years to obtain a judgement hose ruptures or other possible causes. He In the opinion of project manager ‘A’, the
in March 2013. After presenting all the also noticed that the trailer was standing at tipping of the trailer was caused by not
evidence at the High Court in London, the the same camber as the road – and this was compensating the trailer to a horizontal level
judge rejected the allegations of party ‘B’ and recorded by measuring the height of the when negotiating the curve, which had a 2.8°
found it solely responsible for the accident camber. When project manager ‘A’ arrived at
and its financial consequences. the accident he had asked the operating crew
Prior to the accident, the project manager where the spirit level was and they replied
of party ‘A’ had visited the transport that they had left it in the driver’s cabin of
combination just before it entered a long the tractor unit as the road was in good
curve in the road (see picture 1) and where, condition. They had obviously misjudged
approximately 200 m further on, it tipped the camber of this long curve.
over . He spoke with the transport The opinions of the operating crew of
supervisor and asked whether everything party ‘B’ were not as clear as the statement
Picture 2: The reactor lying by the road.
was going fine. The supervisor of party ‘B’ and accident report of project manager ‘A’.

www.heavyliftpfi.com September/October 2013 67


SPOTCHECKSAFETY

The court case Choice of suspension system Disadvantages of three-point


During a three-day court case all witnesses During the court case, party ‘B’ kept suspension
and technical experts of party ‘A’ and party insisting that party ‘A’ had made a mistake by l Smaller area of stability.
‘B’ were given the opportunity to state their setting the trailer on a four-point suspension l Less suitable for high CoG loads.
case. It soon became clear that if you end up system and had therefore caused the trailer
in court, make sure you really have a case to tip as it could not be controlled. Advantages of four-point
and that you are very secure in your Party ‘A’ proved in court by means of a
suspension
understanding of what had really happened, scale model that a three-point suspension
as the lawyers of each party will keep asking system is less stable then a four-point l Greater area of stability.
questions until they receive a satisfactory suspension system. It can be compared with l More suitable for high CoG loads.
answer. a table on three legs or four legs. If one
The legal enquiry went back to the phase crosses with the centre of gravity (CoG) Disadvantages of four-point
when party ‘A’ had asked party ‘B’ to quote over one of the lines which connects the legs
suspension
for the transport job. To the advantage of of the table, the table will tip over.
party ‘A’, the lawyers had clearly asked what A comparison of the advantages and l More difficult to control and therefore
kind of service had been required from party disadvantages of a three and four-point more labour intensive.
‘B’. They had even enclosed a transportation suspension system are summarised below: l Higher risk of overloading axles and
drawing and preliminary planning schedule trailer structure.
with the enquiry. Advantages of three-point l Preferably used only on good roads as
To the disadvantage of party ‘A’, the otherwise trailer ‘rocking’ can occur.
suspension
company had quoted the job by means of a
handwritten fax with no conditions of work l Easier operational control for levelling, If we look at all the above points, the
mentioned whatsoever in the document. It which is therefore less labour intensive. project manager of party ‘A’ stated that
had enclosed a stability calculation for a l It limits the risk of overloading the trailer although a four-point suspension would be
separate project load for which the company spine beam and platform supports as well more likely to overload the axles, he still
had quoted stating that it would prefer a as the risk of axle overload. preferred to use a four-point suspension, as
wider trailer configuration for the load, due l It is less subject to dynamic effects as the opposed to a three-point suspension system,
to critical stability. No remarks or questions load always rests on three points, thus as the CoG of the load was in his opinion
had been asked about stability and trailer eliminating ‘rocking’. rather high. Therefore he selected the “best
type selection for the reactor, which had option of the worst” and instructed the
obviously been accepted by party ‘B’. Party The diagram above shows a drawing of operators of party ‘B’ to set the trailer to a
‘A’ had then confirmed the transport order to the symmetrical three-point suspension four-point suspension mode.
party ‘B’. system for the actual load in question. It was the opinion of party ‘A’ that the

68 September/October 2013 www.heavyliftpfi.com


Exceptional craft require
an exceptional transport company

Exceptional crafts require an exceptional to be shipped, from tugs, dredgers and barges Sevenstar Exceptional Marine Transport
transport company and for that reason Sevenstar to pontoons and marina docks. In fact, as long as Contact: Richard Klabbers
Yacht Transport has a subsidiary that takes care it floats, Sevenstar EMT can transport your craft Phone: +31 204488590
of this challenging job – Sevenstar Exceptional anywhere in the World, safely and hassle-free. Mobile: +31 653548755
Marine Transport (EMT).
Discover why the most demanding shipyards
Sevenstar EMT has a bespoke professional en- and owners call us the world’s finest transport www.sevenstar-emt.com
gineering department that can provide individual service. Sevenstar EMT, shipping solutions
shipping solutions for each exceptional craft tailor made for you.
info@sevenstar-emt.com

GOLDHOFER HEAVY-DUTY MODULES

QUALIFIED SOLUTIONS FOR EXTREME


TRANSPORT CHALLENGES.
Our heavy-duty modular systems can be individually matched to meet your requirements. At Goldhofer, providing qualified solutions means not only
building resilient high quality products, but also giving our customers highly functional solutions for transportation and logistic challenges. Through
our comprehensive project engineering and competent after sales program, Goldhofer is there when you really need to get down to business.
Goldhofer products are the result of over 300 years of investment, development of new technologies, and perfection of our customer service.
One thing is absolutely clear; Economy is ultimately a function of high resale value, long term durability, and safety. This is what we stand for
and promise. Invest in your future. Goldhofer – The Original.
SPOTCHECKSAFETY

It is important to prepare a detailed


manual of the works that need to be
executed, outlining the scope of work, lifting
and transport plans, stowage plans, stability
calculations and so on.
Always ensure that if an accident occurs,
immediately see to it that injured persons
receive medical treatment and thereafter
report clearly in writing what has happened,

HLPFI
illustrated with pictures if possible.

Please note, this article is intended for


guidance only. Whilst every care has been
taken to ensure the accuracy of the contents,
Picture 3: After the accident the 12-axle line trailer was still on the road and standing on its tyres.
no responsibility will be accepted by the
publishers for any errors.
issue has never been whether a three or What have we learnt?
four-point suspension was right or wrong. Make sure that any orders for transport or
Richard Krabbendam was a heavy lift specialist
The cause of the accident was that the trailer erection work received are confirmed in during his whole working career, after which he formed
operators did not compensate the trailer any writing and that they clearly state the Krabbendam Advisory Service. A Master of Mechanical
further after it had stopped just before the conditions under which the work will be Engineering from Delft University of Technology, he has
curve where the accident happened. executed. worked with BigLift and Mammoet, and was a co-founder of
ITREC. He helped to set up Jumbo Offshore and was involved
Although one operator confirmed that the Furthermore, a checklist of critical points
in the development of its super heavy lift carrier fleet, the
trailer was compensated, the evidence, as should be made and checked before J-Class, which uses two 900-tonne mast cranes for subsea
well as the statement of another operator of transport or erection work is executed and installation works. Since his retirement from Jumbo he has
party ‘B’, proved that they did not further ensure that these points are adhered to and been working as a freelance trainer/engineering consultant.
compensate the trailer after they started to that clear instructions (in writing) are given
www.jumbo-offshore.com www.heavyliftspecialist.com
negotiate the curve. to operating personnel.

heavy modular trailers and self-propelled vehicles

INDUSTRIE COMETT
COMETTO
O S.p.A.
VIA CUNEO, 20 - 12011 BORGO S.DALMAZZO - CN - ITAL
LY
TEL. +39.0171.263300 - F
FAX
AX +39.0171.266335
cometto@cometto.com - www.cometto.com building
b u i l d i n g for
f o r the
t h e heaviest
heaviest d
duties
uties

www.heavyliftpfi.com September/October 2013 71


Meeting All Kinds
of Transport Needs

NYK Bulk & Projects Carriers Ltd., is result of merger between NYK-Hinode Line,Ltd.
and NYK Global Bulk Corporation effective on 1st October, 2013.

NYK-Hinode Line, Ltd. has been developed as one of the pioneers for Heavy lift carrier since founding in 1912.
Our multi-purpose fleet transports all kind of cargoes, including project cargoes and steel products, to the world.

One of the world's largest handy bulk carriers, NYK Global Bulk Corporation handles many kinds of bulk
cargo, coke, coal and other similar materials around the world since its establishment in 1988.

The new company operates several types of vessels. The company will expand and develop
services of all kinds to meet and exceed the customers’ needs and market demands.

www.nbpc.co.jp

You might also like