Professional Documents
Culture Documents
Concept of Camber and Method For Assembly of Owgs
Concept of Camber and Method For Assembly of Owgs
Concept of Camber and Method For Assembly of Owgs
Chapter IV
53
CONCEPT OF CAMBER AND METHOD FOR ASSEMBLY OF OWGs
54
CONCEPT OF CAMBER AND METHOD FOR ASSEMBLY OF OWGs
55
CONCEPT OF CAMBER AND METHOD FOR ASSEMBLY OF OWGs
3
There is no change in fabrication procedure i.e. the same drawings and
components are used for cantilever launching as well as erection on ground.
56
CONCEPT OF CAMBER AND METHOD FOR ASSEMBLY OF OWGs
4
Under load, the length of compression member will decrease.
57
CONCEPT OF CAMBER AND METHOD FOR ASSEMBLY OF OWGs
Fig 4.1: Drawing showing Nominal as well as Camber lengths of members for
a 45.7 m span (The bottom chord length does not change)
5. The change in camber length will also necessitate changes in the
lengths of bracing of the top chord in case of through type girders and
bracing of bottom chord in case of deck type OWGs. For computing
the lengths of these members, the average of nominal/ camber length
of the main chord members shall be considered.
4.3.2 Computations for Camber (Upward Deflection): Clause A-1.8 of
SBC states that Williot Diagram shall be drawn to get the downward
deflection of all nodes under design load.5,6 In order to ensure that the girder
assumes nominal shape under the design load, the girder must be given
upward deflection opposite to this value.
Procedure for drawing Williot diagram is shown in fig 4.2 below for a
simple truss ABCD. The logic can be extended further and diagram for bigger
trusses can also be drawn. The extension/shortening of members under load
has been separately worked out and indicated against each member.
5
As per clause 4.16.2 of SBC, in non prestressed open web spans, the camber of
the main girders and the corresponding variations in lengths of members shall be
such that when the girders are loaded with full dead load plus 75 per cent of the live
load without impact, the girder shall assumed nominal shape. This is applicable for
FOBs.
6
As per clause 4.16.3 of SBC, camber for prestressed open web spans shall be
based on full dead load and live load including impact. This shall be applicable for
OWGs for track.
58
CONCEPT OF CAMBER AND METHOD FOR ASSEMBLY OF OWGs
8mm D
C
100kN
6mm -9mm
-12mm
A B
-7mm
c1
Consider point A as pole and draw 7mm shortening of b
AB to b and the 6mm lengthening of AC to c1 a
c1
From B, draw 9mm shortening of c
BC to c2. Then draw perpendiculars b
to b-c2 and a-c1 which meet at c,
a
which is the displaced position of C
c2
c1
c d1
From c, draw 8mm extension of b a
CD to d1. From b, draw 12mm shortening of
BD to d2.Then draw perpendiculars
to c-d1 and b-d2 which meet at d, c2
which is the displaced position of D d2
59
CONCEPT OF CAMBER AND METHOD FOR ASSEMBLY OF OWGs
U4 U5
U3
U2
U1
60
CONCEPT OF CAMBER AND METHOD FOR ASSEMBLY OF OWGs
61
CONCEPT OF CAMBER AND METHOD FOR ASSEMBLY OF OWGs
· Guy wires
· Jacks, including camber jacks, if required.
· Crane (Optional, else derrick can be used)
· Turned bolts, drifts in adequate numbers
· Compressor
· Riveting equipment
The equipment shall be in good condition, tested before start of work
and shall be properly used/ maintained during the course of work. Sufficient
standby shall be there so that the work does not suffer in the event of some
failure.
4.6.2 Care to be taken in Assembly: The girder assembly at site of work
shall be done carefully to get the desired geometry. The following care shall
be taken during assembly:
· The availability of complete set of girder parts shall be ensured as per
the shipping list given by the workshop. The shipping marks on the
parts shall be checked with the shipping list and the material
segregated.
· The girders parts shall be checked for their physical condition i.e. it
shall be checked that no girder parts have been damaged during
transportation.
· Any minor misalignments/ bends etc shall be corrected by applying
small amounts of force which shall not damage the steel. Parts having
more damage may have to be rejected and new parts may have to be
ordered from workshop.
· The match marking of the members shall be checked as per the list
given by the workshop. In case there is any confusion, the fabricator
may be approached for clarification.
· The girder assembly shall be done on hard, level area which shall not
settle when the load of girder comes. If required, some preparation
such as hard moorum/ concrete or wooden/steel packing may be
provided over which the girder assembly shall be commenced. The
top of all packing shall be verified to be in one level.
· During assembly, the individual girder parts shall be erected with
suitable set of stays/ lateral restraints so that these do not topple
over.
· The erection shall be done systematically in proper sequence. The
members shall be handled from proper location for lifting/ assembly so
62
CONCEPT OF CAMBER AND METHOD FOR ASSEMBLY OF OWGs
63
CONCEPT OF CAMBER AND METHOD FOR ASSEMBLY OF OWGs
Fig 4.8
4.8.3 Step-3 On prepared ground, two nos CC Cribs of 0.6 m x 0.6 m x 1.8
m are erected at each panel point location, ensuring that the top level of all
CC Cribs is same. Place wooden blocks below CC Crib as well as on top of
CC Cribs. If necessary, adjustments may be done with suitable wooden
packing. This platform arrangement is meant for providing working/moving
space for workers for crossing under rather than by climbing over the girder
while working. (Fig 4.9). Wooden sleeper crib can also be provided.
64
CONCEPT OF CAMBER AND METHOD FOR ASSEMBLY OF OWGs
65
CONCEPT OF CAMBER AND METHOD FOR ASSEMBLY OF OWGs
4.8.6 Step-6 Cross girder and rail bearer of entire span are provided and
connected with turned bolts. Also the bottom lateral bracing are fixed with
20% turned bolts and 40% service bolts. Again check and ensure that entire
bottom chord is in one level. Now the girder assembly is in stage I (Fig 4.10)
Permanent Gussets
Camber Jack s
66
CONCEPT OF CAMBER AND METHOD FOR ASSEMBLY OF OWGs
standing as these are slender. Some lateral support in the form of guys/
stays etc shall be provided with. It will be desirable to connect the top ends
of the verticals/ diagonals together to provide some stability to the partly
assembled girder. But since the verticals and diagonals have been fabricated
to camber lengths, the holes cannot match. The holes will match only when
the members are elastically strained. Therefore the top end of these
members cannot be fitted in the regular gussets. To join the members
together, if regular gussets are planned to be used, smaller bolts 12/14mm
dia may be used. If the difference in the holes is more, then temporary
gussets are to be fabricated for holding the member ends together. Now the
girder assembly is in stage II (Fig 4.11). Check the level as well as tightness
of bolts of bottom panel joint.
Temporary Gussets
67
CONCEPT OF CAMBER AND METHOD FOR ASSEMBLY OF OWGs
4.8.8 Step-8 Now the bottom panel points, stringers and cross girders are
riveted if the assembly is being done in field. In case of trial assembly in
workshop, tightness of bolts is checked to ensure there is no slip in the drifts/
turned bolts when the cambering is done.
4.8.9 Step-9 Camber to each panel point is provided by lowering jacks by
requisite amounts. All jacks except centre jack are lowered by an amount
equal to camber in central panel point minus the amount of camber shown in
camber sheet at each panel point. Both the trusses are lowered
simultaneously. Maximum lowering is in the jacks at end node points. Check
levels at each panel point of both trusses by leveling instrument again to
ensure correct camber as per camber sheet. Now the girder assembly is in
stage III (Fig 4.12)
Temporary Gussets
Jacks Lowered
7
The drifting procedure is explained in Annexure IV.
68
CONCEPT OF CAMBER AND METHOD FOR ASSEMBLY OF OWGs
outwards either side. Now the girder assembly is in stage IV (Fig 4.13)
Erection sequence
69
CONCEPT OF CAMBER AND METHOD FOR ASSEMBLY OF OWGs
70
CONCEPT OF CAMBER AND METHOD FOR ASSEMBLY OF OWGs
Fig 4.16 a
71
CONCEPT OF CAMBER AND METHOD FOR ASSEMBLY OF OWGs
Fig 4.16 b
72
CONCEPT OF CAMBER AND METHOD FOR ASSEMBLY OF OWGs
The values a,b,c etc in the last column above are defined in fig 4.17 below:
Fig 4.17
q q q
73