Amoa Housing Gantt Chart (Rev 1.0 - Sep 20, 2021)
Amoa Housing Gantt Chart (Rev 1.0 - Sep 20, 2021)
Amoa Housing Gantt Chart (Rev 1.0 - Sep 20, 2021)
PROPOSED AMOA HOUSING (REV 1.0) CONTRACTOR: MARIÑAS & CO. BUILDERS INC 20-Sep-21 13:09
Activity ID Activity Name BL BL Project BL Project Activity % Activity
Project Start Finish Complete Status 2022 2023
Duration Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
540 18-Oct-21 10-Apr-23 D AMOA HOUSING, 0%
D AMOA HOUSING
D.6 PRELIMINARIES 540 18-Oct-21 10-Apr-23 D.6 PRELIMINARIES, 0%
A2130 Power & Water Supply 540 18-Oct-21 10-Apr-23 0% Not Started 0%, Power & Water Supply
A2120 Material Testing 540 18-Oct-21 10-Apr-23 0% Not Started 0%, Material Testing
A2110 As-Built Plans and Shop Drawings (Asha) 124 08-Dec-22 10-Apr-23 0% Not Started 0%, As-Built Plans and Shop Drawings (Asha)
A2100 Mobilization / Demobilization 540 18-Oct-21 10-Apr-23 0% Not Started 0%, Mobilization / Demobilization
A2090 Project Supervison 540 18-Oct-21 10-Apr-23 0% Not Started 0%, Project Supervison
A2080 Temporary Fac ilit ies 540 18-Oct-21 10-Apr-23 0% Not Started 0%, Temporary Facilities
A2070 Safety Requirements 540 18-Oct-21 10-Apr-23 0% Not Started 0%, Safety Requirements
A2060 Covid-19 Reqmts 540 18-Oct-21 10-Apr-23 0% Not Started 0%, Covid-19 Reqmts
A2050 Bonds 540 18-Oct-21 10-Apr-23 0% Not Started 0%, Bonds
D.2 ASHA (2SD) 30% UH - 5 UNITS 308 18-Oct-21 21-Aug-22 D.2 ASHA (2SD) 30% UH - 5 UNITS, 0%
D.2.D3 CONCRETE 175 15-Nov-21 08-May-22 D.2.D3 CONCRETE, 0%
D.2.D3.1 Concrete Forming 144 15-Nov-21 07-Apr-22 D.2.D3.1 Concrete Forming, 0%
A2250 to sides of column 45 30-Nov-21 13-Jan-22 0% Not Started 0%, to sides of column
A2240 to suspended beam 60 22-Jan-22 22-Mar-22 0% Not Started 0%, to suspended beam
A2230 to sides of bearing wall 50 11-Jan-22 01-Mar-22 0% Not Started 0%, to sides of bearing wall
A2220 to sides of wall footings & stair footings 40 15-Nov-21 24-Dec-21 0% Not Started 0%, to sides of wall footings & stair footings
A2210 to sides and soffits of beams 48 12-Jan-22 28-Feb-22 0% Not Started 0%, to sides and soffits of beams
A2200 to stairs 45 10-Dec-21 23-Jan-22 0% Not Started 0%, to stairs
A2190 to edges of slab on grade beds and the like; width
45<15-Dec-21
300mm 28-Jan-22 0% Not Started 0%, to edges of slab on grade beds and the like; width < 300mm
A2180 to ledge 40 23-Dec-21 31-Jan-22 0% Not Started 0%, to ledge
A2170 to edges of ledge 40 23-Dec-21 31-Jan-22 0% Not Started 0%, to edges of ledge
A2160 to volada 45 28-Dec-21 10-Feb-22 0% Not Started 0%, to volada
A2150 to edges of volada 45 02-Jan-22 15-Feb-22 0% Not Started 0%, to edges of volada
A2140 to suspended slab 50 17-Feb-22 07-Apr-22 0% Not Started 0%, to suspended slab
D.2.D3.0 Concrete Reinforcing 149 15-Nov-21 12-Apr-22 D.2.D3.0 Concrete Reinforcing, 0%
A2330 in wall footings, stair footings (10mm & 12mm) 35 15-Nov-21 19-Dec-21 0% Not Started 0%, in wall footings, stair footings (10mm & 12mm)
A2320 in bearing walls (10mm, 12mm, 16mm) 50 21-Jan-22 11-Mar-22 0% Not Started 0%, in bearing walls (10mm, 12mm, 16mm)
A2310 in slabs on grade (10mm) 35 10-Feb-22 16-Mar-22 0% Not Started 0%, in slabs on grade (10mm)
A2300 in suspended slabs (10mm) 40 04-Mar-22 12-Apr-22 0% Not Started 0%, in suspended slabs (10mm)
A2290 in staircases (10mm, 12mm, 16mm) 35 24-Jan-22 27-Feb-22 0% Not Started 0%, in staircases (10mm, 12mm, 16mm)
A2280 in ledges (10mm) 32 07-Jan-22 07-Feb-22 0% Not Started 0%, in ledges (10mm)
A2270 in volada (10mm) 32 11-Feb-22 14-Mar-22 0% Not Started 0%, in volada (10mm)
A2260 in column (10mm, 16mm) 38 15-Dec-21 21-Jan-22 0% Not Started 0%, in column (10mm, 16mm)
D.2.D3.2 Cast in-place Concrete 160 30-Nov-21 08-May-22 D.2.D3.2 Cast in-place Concrete, 0%
A2410 in stair footings (10mm & 12mm) 35 30-Nov-21 03-Jan-22 0% Not Started 0%, in stair footings (10mm & 12mm)
A2401 in bearing walls @ 2F 55 15-Mar-22 08-May-22 0% Not Started 0%, in bearing walls @ 2F
A2400 in bearing walls @ GF 55 03-Feb-22 29-Mar-22 0% Not Started 0%, in bearing walls @ GF
A2390 in slabs on grade (10mm) 45 20-Feb-22 05-Apr-22 0% Not Started 0%, in slabs on grade (10mm)
A2380 in beams and girders 40 16-Mar-22 24-Apr-22 0% Not Started 0%, in beams and girders
A2370 in staircases (10mm, 12mm, 16mm) 30 03-Feb-22 04-Mar-22 0% Not Started 0%, in staircases (10mm, 12mm, 16mm)
A2360 in ledges (10mm) 30 08-Feb-22 09-Mar-22 0% Not Started 0%, in ledges (10mm)
A2350 in volada (10mm) 30 23-Feb-22 24-Mar-22 0% Not Started 0%, in volada (10mm)
A2340 in column (10mm, 16mm) 43 28-Dec-21 08-Feb-22 0% Not Started 0%, in column (10mm, 16mm)
D.2.D4 MASONRY 50 20-Dec-21 07-Feb-22 D.2.D4 MASONRY, 0%
A2420 CHB Laying (100 thk) 50 20-Dec-21 07-Feb-22 0% Not Started 0%, CHB Laying (100 thk)
D.2.D5 METALS 108 05-Mar-22 20-Jun-22 D.2.D5 METALS, 0%
A2461 Anchor Bolts, Tie Rods, Angle Bars etc. 50 05-Apr-22 24-May-22 0% Not Started 0%, Anchor Bolts, Tie Rods, Angle Bars etc.
A2460 Installation of Rafters 35 17-Apr-22 21-May-22 0% Not Started 0%, Installation of Rafters
A2450 Installation of Canopy 35 02-May-22 05-Jun-22 0% Not Started 0%, Installation of Canopy
A2440 Installation of Purlins 35 17-May-22 20-Jun-22 0% Not Started 0%, Installation of Purlins
D.2.D5.1 Metal Fabrications 62 05-Mar-22 05-May-22 D.2.D5.1 Metal Fabrications, 0%
A2500 For Stairs handrill 21 05-Mar-22 25-Mar-22 0% Not Started 0%, For Stairs handrill
A2480 To Porch 21 15-Apr-22 05-May-22 0% Not Started 0%, To Porch
A2470 To Volada 21 25-Mar-22 14-Apr-22 0% Not Started 0%, To Volada
D.2.D6 WOOD, PLASTICS, AND COMPOSITES 75 08-Feb-22 23-Apr-22 D.2.D6 WOOD, PLASTICS, AND COMPOSITES, 0%
A2510 Supply and installation of Fr 2" thick solid wood for
75tread
08-Feb-22 23-Apr-22 0% Not Started 0%, Supply and installation of Fr 2" thick solid wood for tread
D.2.D7 THERMAL AND MOISTURE PROTECTION 95 10-Apr-22 13-Jul-22 D.2.D7 THERMAL AND MOISTURE PROTECTION, 0%