Amoa Housing Gantt Chart (Rev 1.0 - Sep 20, 2021)

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

 

   
PROPOSED AMOA HOUSING (REV 1.0) CONTRACTOR: MARIÑAS & CO. BUILDERS INC 20-Sep-21 13:09
 
Activity ID Activity Name BL BL Project BL Project Activity % Activity
Project Start Finish Complete Status 2022 2023
Duration Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
540 18-Oct-21 10-Apr-23 D AMOA HOUSING, 0%
D AMOA HOUSING
D.6 PRELIMINARIES 540 18-Oct-21 10-Apr-23 D.6 PRELIMINARIES, 0%
A2130 Power & Water Supply 540 18-Oct-21 10-Apr-23 0% Not Started 0%, Power & Water Supply
A2120 Material Testing 540 18-Oct-21 10-Apr-23 0% Not Started 0%, Material Testing
A2110 As-Built Plans and Shop Drawings (Asha) 124 08-Dec-22 10-Apr-23 0% Not Started 0%, As-Built Plans and Shop Drawings (Asha)
A2100 Mobilization / Demobilization 540 18-Oct-21 10-Apr-23 0% Not Started 0%, Mobilization / Demobilization
A2090 Project Supervison 540 18-Oct-21 10-Apr-23 0% Not Started 0%, Project Supervison
A2080 Temporary Fac ilit ies 540 18-Oct-21 10-Apr-23 0% Not Started 0%, Temporary Facilities
A2070 Safety Requirements 540 18-Oct-21 10-Apr-23 0% Not Started 0%, Safety Requirements
A2060 Covid-19 Reqmts 540 18-Oct-21 10-Apr-23 0% Not Started 0%, Covid-19 Reqmts
A2050 Bonds 540 18-Oct-21 10-Apr-23 0% Not Started 0%, Bonds
D.2 ASHA (2SD) 30% UH - 5 UNITS 308 18-Oct-21 21-Aug-22 D.2 ASHA (2SD) 30% UH - 5 UNITS, 0%
D.2.D3 CONCRETE 175 15-Nov-21 08-May-22 D.2.D3 CONCRETE, 0%
D.2.D3.1 Concrete Forming 144 15-Nov-21 07-Apr-22 D.2.D3.1 Concrete Forming, 0%
A2250 to sides of column 45 30-Nov-21 13-Jan-22 0% Not Started 0%, to sides of column
A2240 to suspended beam 60 22-Jan-22 22-Mar-22 0% Not Started 0%, to suspended beam
A2230 to sides of bearing wall 50 11-Jan-22 01-Mar-22 0% Not Started 0%, to sides of bearing wall
A2220 to sides of wall footings & stair footings 40 15-Nov-21 24-Dec-21 0% Not Started 0%, to sides of wall footings & stair footings
A2210 to sides and soffits of beams 48 12-Jan-22 28-Feb-22 0% Not Started 0%, to sides and soffits of beams
A2200 to stairs 45 10-Dec-21 23-Jan-22 0% Not Started 0%, to stairs
A2190 to edges of slab on grade beds and the like; width
45<15-Dec-21
300mm 28-Jan-22 0% Not Started 0%, to edges of slab on grade beds and the like; width < 300mm
A2180 to ledge 40 23-Dec-21 31-Jan-22 0% Not Started 0%, to ledge
A2170 to edges of ledge 40 23-Dec-21 31-Jan-22 0% Not Started 0%, to edges of ledge
A2160 to volada 45 28-Dec-21 10-Feb-22 0% Not Started 0%, to volada
A2150 to edges of volada 45 02-Jan-22 15-Feb-22 0% Not Started 0%, to edges of volada
A2140 to suspended slab 50 17-Feb-22 07-Apr-22 0% Not Started 0%, to suspended slab
D.2.D3.0 Concrete Reinforcing 149 15-Nov-21 12-Apr-22 D.2.D3.0 Concrete Reinforcing, 0%
A2330 in wall footings, stair footings (10mm & 12mm) 35 15-Nov-21 19-Dec-21 0% Not Started 0%, in wall footings, stair footings (10mm & 12mm)
A2320 in bearing walls (10mm, 12mm, 16mm) 50 21-Jan-22 11-Mar-22 0% Not Started 0%, in bearing walls (10mm, 12mm, 16mm)
A2310 in slabs on grade (10mm) 35 10-Feb-22 16-Mar-22 0% Not Started 0%, in slabs on grade (10mm)
A2300 in suspended slabs (10mm) 40 04-Mar-22 12-Apr-22 0% Not Started 0%, in suspended slabs (10mm)
A2290 in staircases (10mm, 12mm, 16mm) 35 24-Jan-22 27-Feb-22 0% Not Started 0%, in staircases (10mm, 12mm, 16mm)
A2280 in ledges (10mm) 32 07-Jan-22 07-Feb-22 0% Not Started 0%, in ledges (10mm)
A2270 in volada (10mm) 32 11-Feb-22 14-Mar-22 0% Not Started 0%, in volada (10mm)
A2260 in column (10mm, 16mm) 38 15-Dec-21 21-Jan-22 0% Not Started 0%, in column (10mm, 16mm)
D.2.D3.2 Cast in-place Concrete 160 30-Nov-21 08-May-22 D.2.D3.2 Cast in-place Concrete, 0%
A2410 in stair footings (10mm & 12mm) 35 30-Nov-21 03-Jan-22 0% Not Started 0%, in stair footings (10mm & 12mm)
A2401 in bearing walls @ 2F 55 15-Mar-22 08-May-22 0% Not Started 0%, in bearing walls @ 2F
A2400 in bearing walls @ GF 55 03-Feb-22 29-Mar-22 0% Not Started 0%, in bearing walls @ GF
A2390 in slabs on grade (10mm) 45 20-Feb-22 05-Apr-22 0% Not Started 0%, in slabs on grade (10mm)
A2380 in beams and girders 40 16-Mar-22 24-Apr-22 0% Not Started 0%, in beams and girders
A2370 in staircases (10mm, 12mm, 16mm) 30 03-Feb-22 04-Mar-22 0% Not Started 0%, in staircases (10mm, 12mm, 16mm)
A2360 in ledges (10mm) 30 08-Feb-22 09-Mar-22 0% Not Started 0%, in ledges (10mm)
A2350 in volada (10mm) 30 23-Feb-22 24-Mar-22 0% Not Started 0%, in volada (10mm)
A2340 in column (10mm, 16mm) 43 28-Dec-21 08-Feb-22 0% Not Started 0%, in column (10mm, 16mm)
D.2.D4 MASONRY 50 20-Dec-21 07-Feb-22 D.2.D4 MASONRY, 0%
A2420 CHB Laying (100 thk) 50 20-Dec-21 07-Feb-22 0% Not Started 0%, CHB Laying (100 thk)
D.2.D5 METALS 108 05-Mar-22 20-Jun-22 D.2.D5 METALS, 0%
A2461 Anchor Bolts, Tie Rods, Angle Bars etc. 50 05-Apr-22 24-May-22 0% Not Started 0%, Anchor Bolts, Tie Rods, Angle Bars etc.
A2460 Installation of Rafters 35 17-Apr-22 21-May-22 0% Not Started 0%, Installation of Rafters
A2450 Installation of Canopy 35 02-May-22 05-Jun-22 0% Not Started 0%, Installation of Canopy
A2440 Installation of Purlins 35 17-May-22 20-Jun-22 0% Not Started 0%, Installation of Purlins
D.2.D5.1 Metal Fabrications 62 05-Mar-22 05-May-22 D.2.D5.1 Metal Fabrications, 0%
A2500 For Stairs handrill 21 05-Mar-22 25-Mar-22 0% Not Started 0%, For Stairs handrill
A2480 To Porch 21 15-Apr-22 05-May-22 0% Not Started 0%, To Porch
A2470 To Volada 21 25-Mar-22 14-Apr-22 0% Not Started 0%, To Volada
D.2.D6 WOOD, PLASTICS, AND COMPOSITES 75 08-Feb-22 23-Apr-22 D.2.D6 WOOD, PLASTICS, AND COMPOSITES, 0%
A2510 Supply and installation of Fr 2" thick solid wood for
75tread
08-Feb-22 23-Apr-22 0% Not Started 0%, Supply and installation of Fr 2" thick solid wood for tread
D.2.D7 THERMAL AND MOISTURE PROTECTION 95 10-Apr-22 13-Jul-22 D.2.D7 THERMAL AND MOISTURE PROTECTION, 0%

Project Baseline Bar Critical Remaining Work Summary   OWNER: ABOITIZLAND


Actual Work Milestone LOCATION: Tamiao, Compostela, Cebu City
Page 1 of 10
Remaining Work % Complete PREPARED BY: MARIÑAS & CO. BUILDERS INC. (ENGG DEPT)
     
PROPOSED AMOA HOUSING (REV 1.0) CONTRACTOR: MARIÑAS & CO. BUILDERS INC 20-Sep-21 13:09
 
Activity ID Activity Name BL BL Project BL Project Activity % Activity
Project Start Finish Complete Status 2022 2023
Duration Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A2530 Installation of Roof Insulation 60 15-May-22 13-Jul-22 0% Not Started 0%, Installation of Roof Insulation
A2520 Application of Waterproofing at Toilet 40 23-Apr-22 01-Jun-22 0% Not Started 0%, Application of Waterproofing at Toilet
D.2.D7.1 Roofing and Siding Panel 70 10-Apr-22 18-Jun-22 D.2.D7.1 Roofing and Siding Panel, 0%
A2580 Installation of Canopy 50 10-Apr-22 29-May-22 0% Not Started 0%, Installation of Canopy
A2570 Installation of Roofing 50 15-Apr-22 03-Jun-22 0% Not Started 0%, Installation of Roofing
A2560 Installation of Gutter 50 20-Apr-22 08-Jun-22 0% Not Started 0%, Installation of Gutter
A2550 Installation of Fascia Board 50 25-Apr-22 13-Jun-22 0% Not Started 0%, Installation of Fascia Board
A2540 Installation of Eaves 50 30-Apr-22 18-Jun-22 0% Not Started 0%, Installation of Eaves
D.2.D8 OPENINGS 88 26-May-22 21-Aug-22 D.2.D8 OPENINGS, 0%
A2620 Supply and Installation of Metal Doors 50 26-May-22 14-Jul-22 0% Not Started 0%, Supply and Installation of Metal Doors
A2610 Supply and Installation of Wood Doors 50 07-Jun-22 26-Jul-22 0% Not Started 0%, Supply and Installation of Wood Doors
A2600 Supply and Installation of Windows 50 20-Jun-22 08-Aug-22 0% Not Started 0%, Supply and Installation of Windows
A2590 Supply and Installation of Hardware 50 03-Jul-22 21-Aug-22 0% Not Started 0%, Supply and Installation of Hardware
D.2.D9 FINISHES 141 08-Feb-22 28-Jun-22 D.2.D9 FINISHES, 0%
A2700 Installation Gypsum Board for Drywall Partition 58 08-Feb-22 06-Apr-22 0% Not Started 0%, Installation Gypsum Board for Drywall Partition
A2690 Plaster and Render (Plastering) 58 16-Feb-22 14-Apr-22 0% Not Started 0%, Plaster and Render (Plastering)
A2680 Installation Gypsum Board for Ceiling 58 24-Feb-22 22-Apr-22 0% Not Started 0%, Installation Gypsum Board for Ceiling
A2670 Tile and Slab Finishes 60 14-Mar-22 12-May-22 0% Not Started 0%, Tile and Slab Finishes
A2660 Application of Exterior Painting 31 13-May-22 12-Jun-22 0% Not Started 0%, Application of Exterior Painting
A2650 Application of Interior Painting 31 29-May-22 28-Jun-22 0% Not Started 0%, Application of Interior Painting
D.2.D10 SPECIALTIES 48 23-Apr-22 09-Jun-22 D.2.D10 SPECIALTIES, 0%
A2720 Toilet paper holder 28 23-Apr-22 20-May-22 0% Not Started 0%, Toilet paper holder
A2710 Installation of Soap Holder 28 13-May-22 09-Jun-22 0% Not Started 0%, Installation of Soap Holder
D.2.D12 FURNISHINGS 40 06-May-22 14-Jun-22 D.2.D12 FURNISHINGS, 0%
A2730 Installation of Countertops 40 06-May-22 14-Jun-22 0% Not Started 0%, Installation of Countertops
D.2.D22 PLUMBING 206 22-Nov-21 15-Jun-22 D.2.D22 PLUMBING, 0%
A2750 Installation of Plumbing Fixtures (OSM) 70 07-Apr-22 15-Jun-22 0% Not Started 0%, Installation of Plumbing Fixtures (OSM)
A2740 Installation of Storage Drainage System 44 25-Dec-21 06-Feb-22 0% Not Started 0%, Installation of Storage Drainage System
D.2.D22.1 SOIL, WASTE AND VENT SYSTEM 188 22-Nov-21 28-May-22 D.2.D22.1 SOIL, WASTE AND VENT SYSTEM, 0%
A2841 Excavation of Trenches 28 09-Jan-22 05-Feb-22 0% Not Started 0%, Excavation of Trenches
A2840 Supply and Installation of PE Septic Tank (OSM)21 19-Feb-22 11-Mar-22 0% Not Started 0%, Supply and Installation of PE Septic Tank (OSM)
A2830 Supply and fix Grease Trap (catch basin type, exterior)
60 22-Nov-21 20-Jan-22 0% Not Started 0%, Supply and fix Grease Trap (catch basin type, exterior)
A2820 Installation of Polyvinyl Chloride pipes for vent thru
45roof
17-Jan-22 02-Mar-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes for vent thru roof
A2810 Installation of Polyvinyl Chloride pipes to floor cleanouts
35 12-Jan-22 15-Feb-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes to floor cleanouts
A2800 Installation of Polyvinyl Chloride pipes to ceilings 40
and26-Mar-22
soffits 04-May-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes to ceilings and soffits
A2780 Installation of Polyvinyl Chloride pipes < 200mm diameter
55 16-Feb-22 11-Apr-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes < 200mm diameter
A2770 Installation of Polyvinyl Chloride pipes for trenches
53 06-Apr-22 28-May-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes for trenches
A2760 Installation of Polyvinyl Chloride pipes to walls and
53floors
06-Apr-22 28-May-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes to walls and floors
D.2.D22.4 COLD WATER SYSTEM 90 15-Jan-22 14-Apr-22 D.2.D22.4 COLD WATER SYSTEM, 0%
A2911 Excavation of Trenches (w/ necessary backfilling)
55 15-Jan-22 10-Mar-22 0% Not Started 0%, Excavation of Trenches (w/ necessary backfilling)
A2910 Pipework Ancillaries and accesories for Gate Valve
55 20-Jan-22 15-Mar-22 0% Not Started 0%, Pipework Ancillaries and accesories for Gate Valve
A2900 Pipework Ancillaries and accesories for Hose bibb
55 25-Jan-22 20-Mar-22 0% Not Started 0%, Pipework Ancillaries and accesories for Hose bibb
A2890 Pipework Ancillaries and accesories for Water Meter
55 25-Jan-22 20-Mar-22 0% Not Started 0%, Pipework Ancillaries and accesories for Water Meter
A2870 Installation of Polyvinyl Chloride pipes < 200mm diameter
55 30-Jan-22 25-Mar-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes < 200mm diameter
A2860 Polyrpropylene pipes (PPrC) and fittings by Thermovar
60 04-Feb-22
for trenches04-Apr-22 0% Not Started 0%, Polyrpropylene pipes (PPrC) and fittings by Thermovar for trenches
A2850 Polyrpropylene pipes (PPrC) and fittings by Thermovar
60 14-Feb-22
to walls and14-Apr-22
floors 0% Not Started 0%, Polyrpropylene pipes (PPrC) and fittings by Thermovar to walls and floors
D.2.D26 ELECTRICAL 259 15-Nov-21 31-Jul-22 D.2.D26 ELECTRICAL, 0%
A2930 MAINS AND SUB-MAINS DISTRIBUTION SYSTEMS
40 15-Nov-21 24-Dec-21 0% Not Started 0%, MAINS AND SUB-MAINS DISTRIBUTION SYSTEMS
A2920 GENERAL LIGHTING AND POWER 35 27-Jun-22 31-Jul-22 0% Not Started 0%, GENERAL LIGHTING AND POWER
D.2.D27 COMMUNICATIONS 50 02-Jul-22 20-Aug-22 D.2.D27 COMMUNICATIONS, 0%
A2950 TELEPHONE SYSTEM 40 02-Jul-22 10-Aug-22 0% Not Started 0%, TELEPHONE SYSTEM
A2940 CATV SYSTEM 40 12-Jul-22 20-Aug-22 0% Not Started 0%, CATV SYSTEM
D.2.D31 EARTHWORK 124 18-Oct-21 18-Feb-22 D.2.D31 EARTHWORK, 0%
A4093 Excavation works for PE Septic tank 45 05-Jan-22 18-Feb-22 0% Not Started 0%, Excavation works for PE Septic tank
A4083 Approved well compacted granular fill 55 22-Nov-21 15-Jan-22 0% Not Started 0%, Approved well compacted granular fill
A4073 Gravel Bedding 25 10-Nov-21 04-Dec-21 0% Not Started 0%, Gravel Bedding
A4063 Staking and lay-out 28 07-Nov-21 04-Dec-21 0% Not Started 0%, Staking and lay-out
A4053 Soil Treatment 25 02-Nov-21 26-Nov-21 0% Not Started 0%, Soil Treatment
A4043 Structural excavation 35 18-Oct-21 21-Nov-21 0% Not Started 0%, Structural excavation
D.4 ASHA (2SD) 30% UH - 4 UNITS 314 22-Nov-21 01-Oct-22 D.4 ASHA (2SD) 30% UH - 4 UNITS, 0%

Project Baseline Bar Critical Remaining Work Summary   OWNER: ABOITIZLAND


Actual Work Milestone LOCATION: Tamiao, Compostela, Cebu City
Page 2 of 10
Remaining Work % Complete PREPARED BY: MARIÑAS & CO. BUILDERS INC. (ENGG DEPT)
     
PROPOSED AMOA HOUSING (REV 1.0) CONTRACTOR: MARIÑAS & CO. BUILDERS INC 20-Sep-21 13:09
 
Activity ID Activity Name BL BL Project BL Project Activity % Activity
Project Start Finish Complete Status 2022 2023
Duration Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
D.4.D3 CONCRETE 165 04-Jan-22 17-Jun-22 D.4.D3 CONCRETE, 0%
D.4.D3.1 Concrete Forming 146 04-Jan-22 29-May-22 D.4.D3.1 Concrete Forming, 0%
A7153 to sides of column 36 24-Jan-22 28-Feb-22 0% Not Started 0%, to sides of column
A7143 to suspended beam 60 17-Mar-22 15-May-22 0% Not Started 0%, to suspended beam
A7133 to sides of bearing wall 50 25-Feb-22 15-Apr-22 0% Not Started 0%, to sides of bearing wall
A7123 to sides of wall footings & stair footings 45 04-Jan-22 17-Feb-22 0% Not Started 0%, to sides of wall footings & stair footings
A7113 to sides and soffits of beams 48 09-Mar-22 25-Apr-22 0% Not Started 0%, to sides and soffits of beams
A7103 to stairs 45 25-Jan-22 10-Mar-22 0% Not Started 0%, to stairs
A7093 to edges of slab on grade beds and the like; width
45<09-Feb-22
300mm 25-Mar-22 0% Not Started 0%, to edges of slab on grade beds and the like; width < 300mm
A7083 to ledge 40 17-Feb-22 28-Mar-22 0% Not Started 0%, to ledge
A7073 to edges of ledge 40 17-Feb-22 28-Mar-22 0% Not Started 0%, to edges of ledge
A7063 to volada 40 27-Feb-22 07-Apr-22 0% Not Started 0%, to volada
A7053 to edges of volada 40 04-Mar-22 12-Apr-22 0% Not Started 0%, to edges of volada
A7043 to suspended slab 48 12-Apr-22 29-May-22 0% Not Started 0%, to suspended slab
D.4.D3.0 Concrete Reinforcing 146 09-Jan-22 03-Jun-22 D.4.D3.0 Concrete Reinforcing, 0%
A7233 in wall footings, stair footings (10mm & 12mm) 32 09-Jan-22 09-Feb-22 0% Not Started 0%, in wall footings, stair footings (10mm & 12mm)
A7223 in bearing walls (10mm, 12mm, 16mm) 50 07-Mar-22 25-Apr-22 0% Not Started 0%, in bearing walls (10mm, 12mm, 16mm)
A7213 in slabs on grade (10mm) 35 27-Mar-22 30-Apr-22 0% Not Started 0%, in slabs on grade (10mm)
A7203 in suspended slabs (10mm) 40 25-Apr-22 03-Jun-22 0% Not Started 0%, in suspended slabs (10mm)
A7193 in staircases (10mm, 12mm, 16mm) 35 11-Mar-22 14-Apr-22 0% Not Started 0%, in staircases (10mm, 12mm, 16mm)
A7183 in ledges (10mm) 32 04-Mar-22 04-Apr-22 0% Not Started 0%, in ledges (10mm)
A7173 in volada (10mm) 32 08-Apr-22 09-May-22 0% Not Started 0%, in volada (10mm)
A7163 in column (10mm, 16mm) 38 30-Jan-22 08-Mar-22 0% Not Started 0%, in column (10mm, 16mm)
D.4.D3.2 Cast in-place Concrete 152 17-Jan-22 17-Jun-22 D.4.D3.2 Cast in-place Concrete, 0%
A7893 in bearing walls @ 2F 45 04-May-22 17-Jun-22 0% Not Started 0%, in bearing walls @ 2F
A7313 in stair footings (10mm & 12mm) 35 17-Jan-22 20-Feb-22 0% Not Started 0%, in stair footings (10mm & 12mm)
A7303 in bearing walls @ GF 45 20-Mar-22 03-May-22 0% Not Started 0%, in bearing walls @ GF
A7293 in slabs on grade (10mm) 35 06-Apr-22 10-May-22 0% Not Started 0%, in slabs on grade (10mm)
A7283 in beams and girders 30 10-May-22 08-Jun-22 0% Not Started 0%, in beams and girders
A7273 in staircases (10mm, 12mm, 16mm) 30 21-Mar-22 19-Apr-22 0% Not Started 0%, in staircases (10mm, 12mm, 16mm)
A7263 in ledges (10mm) 35 05-Apr-22 09-May-22 0% Not Started 0%, in ledges (10mm)
A7253 in volada (10mm) 35 20-Apr-22 24-May-22 0% Not Started 0%, in volada (10mm)
A7243 in column (10mm, 16mm) 43 07-Feb-22 21-Mar-22 0% Not Started 0%, in column (10mm, 16mm)
D.4.D4 MASONRY 50 10-Feb-22 31-Mar-22 D.4.D4 MASONRY, 0%
A7323 CHB Laying (100 thk) 50 10-Feb-22 31-Mar-22 0% Not Started 0%, CHB Laying (100 thk)
D.4.D5 METALS 95 20-Apr-22 23-Jul-22 D.4.D5 METALS, 0%
A7363 Installation of Rafters 33 01-Jun-22 03-Jul-22 0% Not Started 0%, Installation of Rafters
A7353 Installation of Canopy 30 14-Jun-22 13-Jul-22 0% Not Started 0%, Installation of Canopy
A7343 Installation of Purlins 30 24-Jun-22 23-Jul-22 0% Not Started 0%, Installation of Purlins
A7333 Anchor Bolts, Tie Rods, Angle Bars etc. 50 20-May-22 08-Jul-22 0% Not Started 0%, Anchor Bolts, Tie Rods, Angle Bars etc.
D.4.D5.1 Metal Fabrications 63 20-Apr-22 21-Jun-22 D.4.D5.1 Metal Fabrications, 0%
A7393 For Stairs handrill 14 20-Apr-22 03-May-22 0% Not Started 0%, For Stairs handrill
A7383 To Porch 14 08-Jun-22 21-Jun-22 0% Not Started 0%, To Porch
A7373 To Volada 14 25-May-22 07-Jun-22 0% Not Started 0%, To Volada
D.4.D6 WOOD, PLASTICS, AND COMPOSITES 75 01-Apr-22 14-Jun-22 D.4.D6 WOOD, PLASTICS, AND COMPOSITES, 0%
A7403 Supply and installation of Fr 2" thick solid wood for
75tread
01-Apr-22 14-Jun-22 0% Not Started 0%, Supply and installation of Fr 2" thick solid wood for tread
D.4.D7 THERMAL AND MOISTURE PROTECTION 95 25-May-22 27-Aug-22 D.4.D7 THERMAL AND MOISTURE PROTECTION, 0%
A7423 Installation of Roof Insulation 60 29-Jun-22 27-Aug-22 0% Not Started 0%, Installation of Roof Insulation
A7413 Application of Waterproofing at Toilet 40 14-Jun-22 23-Jul-22 0% Not Started 0%, Application of Waterproofing at Toilet
D.4.D7.1 Roofing and Siding Panel 70 25-May-22 02-Aug-22 D.4.D7.1 Roofing and Siding Panel, 0%
A7473 Installation of Canopy 50 25-May-22 13-Jul-22 0% Not Started 0%, Installation of Canopy
A7463 Installation of Roofing 50 30-May-22 18-Jul-22 0% Not Started 0%, Installation of Roofing
A7453 Installation of Gutter 50 04-Jun-22 23-Jul-22 0% Not Started 0%, Installation of Gutter
A7443 Installation of Fascia Board 50 09-Jun-22 28-Jul-22 0% Not Started 0%, Installation of Fascia Board
A7433 Installation of Eaves 50 14-Jun-22 02-Aug-22 0% Not Started 0%, Installation of Eaves
D.4.D8 OPENINGS 48 06-Aug-22 22-Sep-22 D.4.D8 OPENINGS, 0%
A7513 Supply and Installation of Metal Doors 40 06-Aug-22 14-Sep-22 0% Not Started 0%, Supply and Installation of Metal Doors
A7503 Supply and Installation of Wood Doors 40 08-Aug-22 16-Sep-22 0% Not Started 0%, Supply and Installation of Wood Doors
A7493 Supply and Installation of Windows 40 11-Aug-22 19-Sep-22 0% Not Started 0%, Supply and Installation of Windows
A7483 Supply and Installation of Hardware 40 14-Aug-22 22-Sep-22 0% Not Started 0%, Supply and Installation of Hardware

Project Baseline Bar Critical Remaining Work Summary   OWNER: ABOITIZLAND


Actual Work Milestone LOCATION: Tamiao, Compostela, Cebu City
Page 3 of 10
Remaining Work % Complete PREPARED BY: MARIÑAS & CO. BUILDERS INC. (ENGG DEPT)
     
PROPOSED AMOA HOUSING (REV 1.0) CONTRACTOR: MARIÑAS & CO. BUILDERS INC 20-Sep-21 13:09
 
Activity ID Activity Name BL BL Project BL Project Activity % Activity
Project Start Finish Complete Status 2022 2023
Duration Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
D.4.D9 FINISHES 135 01-Apr-22 13-Aug-22 D.4.D9 FINISHES, 0%
A7573 Installation Gypsum Board for Drywall Partition 58 01-Apr-22 28-May-22 0% Not Started 0%, Installation Gypsum Board for Drywall Partition
A7563 Plaster and Render (Plastering) 58 09-Apr-22 05-Jun-22 0% Not Started 0%, Plaster and Render (Plastering)
A7553 Installation Gypsum Board for Ceiling 58 17-Apr-22 13-Jun-22 0% Not Started 0%, Installation Gypsum Board for Ceiling
A7543 Tile and Slab Finishes 60 05-May-22 03-Jul-22 0% Not Started 0%, Tile and Slab Finishes
A7533 Application of Exterior Painting 28 04-Jul-22 31-Jul-22 0% Not Started 0%, Application of Exterior Painting
A7523 Application of Interior Painting 28 17-Jul-22 13-Aug-22 0% Not Started 0%, Application of Interior Painting
D.4.D10 SPECIALTIES 48 14-Jun-22 31-Jul-22 D.4.D10 SPECIALTIES, 0%
A7593 Toilet paper holder 28 14-Jun-22 11-Jul-22 0% Not Started 0%, Toilet paper holder
A7583 Installation of Soap Holder 28 04-Jul-22 31-Jul-22 0% Not Started 0%, Installation of Soap Holder
D.4.D12 FURNISHINGS 65 22-Jun-22 25-Aug-22 D.4.D12 FURNISHINGS, 0%
A7603 Installation of Countertops 65 22-Jun-22 25-Aug-22 0% Not Started 0%, Installation of Countertops
D.4.D22 PLUMBING 213 06-Jan-22 06-Aug-22 D.4.D22 PLUMBING, 0%
A7623 Installation of Plumbing Fixtures (OSM) 70 29-May-22 06-Aug-22 0% Not Started 0%, Installation of Plumbing Fixtures (OSM)
A7613 Installation of Storage Drainage System 40 09-Feb-22 20-Mar-22 0% Not Started 0%, Installation of Storage Drainage System
D.4.D22.1 SOIL, WASTE AND VENT SYSTEM 178 06-Jan-22 02-Jul-22 D.4.D22.1 SOIL, WASTE AND VENT SYSTEM, 0%
A7713 Supply and Installation of PE Septic Tank (OSM)14 22-Mar-22 04-Apr-22 0% Not Started 0%, Supply and Installation of PE Septic Tank (OSM)
A7703 Supply and fix Grease Trap (catch basin type, exterior)
60 06-Jan-22 06-Mar-22 0% Not Started 0%, Supply and fix Grease Trap (catch basin type, exterior)
A7693 Installation of Polyvinyl Chloride pipes for vent thru
45roof
04-Mar-22 17-Apr-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes for vent thru roof
A7683 Installation of Polyvinyl Chloride pipes to floor cleanouts
35 21-Feb-22 27-Mar-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes to floor cleanouts
A7673 Installation of Polyvinyl Chloride pipes to ceilings 40
and10-May-22
soffits 18-Jun-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes to ceilings and soffits
A7663 Excavation of Trenches 28 20-Feb-22 19-Mar-22 0% Not Started 0%, Excavation of Trenches
A7653 Installation of Polyvinyl Chloride pipes < 200mm diameter
55 28-Mar-22 21-May-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes < 200mm diameter
A7643 Installation of Polyvinyl Chloride pipes for trenches
53 11-May-22 02-Jul-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes for trenches
A7633 Installation of Polyvinyl Chloride pipes to walls and
53floors
11-May-22 02-Jul-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes to walls and floors
D.4.D22.4 COLD WATER SYSTEM 60 10-Feb-22 10-Apr-22 D.4.D22.4 COLD WATER SYSTEM, 0%
A7783 Pipework Ancillaries and accesories for Gate Valve
55 15-Feb-22 10-Apr-22 0% Not Started 0%, Pipework Ancillaries and accesories for Gate Valve
A7773 Pipework Ancillaries and accesories for Hose bibb
55 15-Feb-22 10-Apr-22 0% Not Started 0%, Pipework Ancillaries and accesories for Hose bibb
A7763 Pipework Ancillaries and accesories for Water Meter
55 15-Feb-22 10-Apr-22 0% Not Started 0%, Pipework Ancillaries and accesories for Water Meter
A7753 Excavation of Trenches (w/ necessary backfilling)
55 15-Feb-22 10-Apr-22 0% Not Started 0%, Excavation of Trenches (w/ necessary backfilling)
A7743 Installation of Polyvinyl Chloride pipes < 200mm diameter
55 15-Feb-22 10-Apr-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes < 200mm diameter
A7733 Polyrpropylene pipes (PPrC) and fittings by Thermovar
55 15-Feb-22
for trenches10-Apr-22 0% Not Started 0%, Polyrpropylene pipes (PPrC) and fittings by Thermovar for trenches
A7723 Polyrpropylene pipes (PPrC) and fittings by Thermovar
55 10-Feb-22
to walls and05-Apr-22
floors 0% Not Started 0%, Polyrpropylene pipes (PPrC) and fittings by Thermovar to walls and floors
D.4.D26 ELECTRICAL 259 06-Jan-22 21-Sep-22 D.4.D26 ELECTRICAL, 0%
A7803 MAINS AND SUB-MAINS DISTRIBUTION SYSTEMS
35 06-Jan-22 09-Feb-22 0% Not Started 0%, MAINS AND SUB-MAINS DISTRIBUTION SYSTEMS
A7793 GENERAL LIGHTING AND POWER 28 25-Aug-22 21-Sep-22 0% Not Started 0%, GENERAL LIGHTING AND POWER
D.4.D27 COMMUNICATIONS 40 23-Aug-22 01-Oct-22 D.4.D27 COMMUNICATIONS, 0%
A7823 TELEPHONE SYSTEM 30 23-Aug-22 21-Sep-22 0% Not Started 0%, TELEPHONE SYSTEM
A7813 CATV SYSTEM 30 02-Sep-22 01-Oct-22 0% Not Started 0%, CATV SYSTEM
D.4.D31 EARTHWORK 120 22-Nov-21 21-Mar-22 D.4.D31 EARTHWORK, 0%
A7883 Soil Treatment 25 17-Dec-21 10-Jan-22 0% Not Started 0%, Soil Treatment
A7873 Structural excavation 45 22-Nov-21 05-Jan-22 0% Not Started 0%, Structural excavation
A7863 Approved well compacted granular fill 55 06-Jan-22 01-Mar-22 0% Not Started 0%, Approved well compacted granular fill
A7853 Gravel Bedding 25 30-Dec-21 23-Jan-22 0% Not Started 0%, Gravel Bedding
A7843 Staking and lay-out 28 22-Dec-21 18-Jan-22 0% Not Started 0%, Staking and lay-out
A7833 Excavation works for PE Septic tank 45 05-Feb-22 21-Mar-22 0% Not Started 0%, Excavation works for PE Septic tank
D.1 ASHA (2SD) 15% UH - 4 UNITS 317 05-Feb-22 18-Dec-22 D.1 ASHA (2SD) 15% UH - 4 UNITS, 0%
D.1.D3 CONCRETE 157 20-Mar-22 23-Aug-22 D.1.D3 CONCRETE, 0%
D.1.D3.1 Concrete Forming 150 20-Mar-22 16-Aug-22 D.1.D3.1 Concrete Forming, 0%
A4303 to sides of column 40 04-Apr-22 13-May-22 0% Not Started 0%, to sides of column
A4293 to suspended beam 60 04-Jun-22 02-Aug-22 0% Not Started 0%, to suspended beam
A4283 to sides of bearing wall 50 21-Apr-22 09-Jun-22 0% Not Started 0%, to sides of bearing wall
A4273 to sides of wall footings & stair footings 40 20-Mar-22 28-Apr-22 0% Not Started 0%, to sides of wall footings & stair footings
A4263 to sides and soffits of beams 48 27-May-22 13-Jul-22 0% Not Started 0%, to sides and soffits of beams
A4253 to stairs 45 14-Apr-22 28-May-22 0% Not Started 0%, to stairs
A4243 to edges of slab on grade beds and the like; width
45<29-Apr-22
300mm 12-Jun-22 0% Not Started 0%, to edges of slab on grade beds and the like; width < 300mm
A4233 to ledge 40 07-May-22 15-Jun-22 0% Not Started 0%, to ledge
A4223 to edges of ledge 40 12-May-22 20-Jun-22 0% Not Started 0%, to edges of ledge
A4213 to volada 40 17-May-22 25-Jun-22 0% Not Started 0%, to volada
A4203 to edges of volada 40 22-May-22 30-Jun-22 0% Not Started 0%, to edges of volada

Project Baseline Bar Critical Remaining Work Summary   OWNER: ABOITIZLAND


Actual Work Milestone LOCATION: Tamiao, Compostela, Cebu City
Page 4 of 10
Remaining Work % Complete PREPARED BY: MARIÑAS & CO. BUILDERS INC. (ENGG DEPT)
     
PROPOSED AMOA HOUSING (REV 1.0) CONTRACTOR: MARIÑAS & CO. BUILDERS INC 20-Sep-21 13:09
 
Activity ID Activity Name BL BL Project BL Project Activity % Activity
Project Start Finish Complete Status 2022 2023
Duration Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A4193 to suspended slab 48 30-Jun-22 16-Aug-22 0% Not Started 0%, to suspended slab
D.1.D3.0 Concrete Reinforcing 155 20-Mar-22 21-Aug-22 D.1.D3.0 Concrete Reinforcing, 0%
A4383 in wall footings, stair footings (10mm & 12mm) 32 20-Mar-22 20-Apr-22 0% Not Started 0%, in wall footings, stair footings (10mm & 12mm)
A4373 in bearing walls (10mm, 12mm, 16mm) 50 01-May-22 19-Jun-22 0% Not Started 0%, in bearing walls (10mm, 12mm, 16mm)
A4363 in slabs on grade (10mm) 35 21-May-22 24-Jun-22 0% Not Started 0%, in slabs on grade (10mm)
A4353 in suspended slabs (10mm) 40 13-Jul-22 21-Aug-22 0% Not Started 0%, in suspended slabs (10mm)
A4343 in staircases (10mm, 12mm, 16mm) 35 29-May-22 02-Jul-22 0% Not Started 0%, in staircases (10mm, 12mm, 16mm)
A4333 in ledges (10mm) 28 22-May-22 18-Jun-22 0% Not Started 0%, in ledges (10mm)
A4323 in volada (10mm) 28 26-Jun-22 23-Jul-22 0% Not Started 0%, in volada (10mm)
A4313 in column (10mm, 16mm) 38 14-Apr-22 21-May-22 0% Not Started 0%, in column (10mm, 16mm)
D.1.D3.2 Cast in-place Concrete 149 28-Mar-22 23-Aug-22 D.1.D3.2 Cast in-place Concrete, 0%
A5043 in bearing walls @ 2F 45 28-Jun-22 11-Aug-22 0% Not Started 0%, in bearing walls @ 2F
A4463 in stair footings (10mm & 12mm) 35 28-Mar-22 01-May-22 0% Not Started 0%, in stair footings (10mm & 12mm)
A4453 in bearing walls @ GF 45 14-May-22 27-Jun-22 0% Not Started 0%, in bearing walls @ GF
A4443 in slabs on grade (10mm) 35 31-May-22 04-Jul-22 0% Not Started 0%, in slabs on grade (10mm)
A4433 in beams and girders 30 25-Jul-22 23-Aug-22 0% Not Started 0%, in beams and girders
A4423 in staircases (10mm, 12mm, 16mm) 30 08-Jun-22 07-Jul-22 0% Not Started 0%, in staircases (10mm, 12mm, 16mm)
A4413 in ledges (10mm) 25 19-Jun-22 13-Jul-22 0% Not Started 0%, in ledges (10mm)
A4403 in volada (10mm) 25 04-Jul-22 28-Jul-22 0% Not Started 0%, in volada (10mm)
A4393 in column (10mm, 16mm) 43 22-Apr-22 03-Jun-22 0% Not Started 0%, in column (10mm, 16mm)
D.1.D4 MASONRY 50 21-Apr-22 09-Jun-22 D.1.D4 MASONRY, 0%
A4473 CHB Laying (100 thk) 50 21-Apr-22 09-Jun-22 0% Not Started 0%, CHB Laying (100 thk)
D.1.D5 METALS 92 08-Jul-22 07-Oct-22 D.1.D5 METALS, 0%
A4513 Installation of Rafters 33 16-Aug-22 17-Sep-22 0% Not Started 0%, Installation of Rafters
A4503 Installation of Canopy 30 29-Aug-22 27-Sep-22 0% Not Started 0%, Installation of Canopy
A4493 Installation of Purlins 30 08-Sep-22 07-Oct-22 0% Not Started 0%, Installation of Purlins
A4483 Anchor Bolts, Tie Rods, Angle Bars etc. 50 04-Aug-22 22-Sep-22 0% Not Started 0%, Anchor Bolts, Tie Rods, Angle Bars etc.
D.1.D5.1 Metal Fabrications 49 08-Jul-22 25-Aug-22 D.1.D5.1 Metal Fabrications, 0%
A4543 For Stairs handrill 14 08-Jul-22 21-Jul-22 0% Not Started 0%, For Stairs handrill
A4533 To Porch 14 12-Aug-22 25-Aug-22 0% Not Started 0%, To Porch
A4523 To Volada 14 29-Jul-22 11-Aug-22 0% Not Started 0%, To Volada
D.1.D6 WOOD, PLASTICS, AND COMPOSITES 75 10-Jun-22 23-Aug-22 D.1.D6 WOOD, PLASTICS, AND COMPOSITES, 0%
A4553 Supply and installation of Fr 2" thick solid wood for
75tread
10-Jun-22 23-Aug-22 0% Not Started 0%, Supply and installation of Fr 2" thick solid wood for tread
D.1.D7 THERMAL AND MOISTURE PROTECTION 95 09-Aug-22 11-Nov-22 D.1.D7 THERMAL AND MOISTURE PROTECTION, 0%
A4573 Installation of Roof Insulation 60 13-Sep-22 11-Nov-22 0% Not Started 0%, Installation of Roof Insulation
A4563 Application of Waterproofing at Toilet 40 29-Aug-22 07-Oct-22 0% Not Started 0%, Application of Waterproofing at Toilet
D.1.D7.1 Roofing and Siding Panel 70 09-Aug-22 17-Oct-22 D.1.D7.1 Roofing and Siding Panel, 0%
A4623 Installation of Canopy 50 09-Aug-22 27-Sep-22 0% Not Started 0%, Installation of Canopy
A4613 Installation of Roofing 50 14-Aug-22 02-Oct-22 0% Not Started 0%, Installation of Roofing
A4603 Installation of Gutter 50 19-Aug-22 07-Oct-22 0% Not Started 0%, Installation of Gutter
A4593 Installation of Fascia Board 50 24-Aug-22 12-Oct-22 0% Not Started 0%, Installation of Fascia Board
A4583 Installation of Eaves 50 29-Aug-22 17-Oct-22 0% Not Started 0%, Installation of Eaves
D.1.D8 OPENINGS 48 21-Oct-22 07-Dec-22 D.1.D8 OPENINGS, 0%
A4663 Supply and Installation of Metal Doors 40 21-Oct-22 29-Nov-22 0% Not Started 0%, Supply and Installation of Metal Doors
A4653 Supply and Installation of Wood Doors 40 23-Oct-22 01-Dec-22 0% Not Started 0%, Supply and Installation of Wood Doors
A4643 Supply and Installation of Windows 40 26-Oct-22 04-Dec-22 0% Not Started 0%, Supply and Installation of Windows
A4633 Supply and Installation of Hardware 40 29-Oct-22 07-Dec-22 0% Not Started 0%, Supply and Installation of Hardware
D.1.D9 FINISHES 141 10-Jun-22 28-Oct-22 D.1.D9 FINISHES, 0%
A4723 Installation Gypsum Board for Drywall Partition 60 10-Jun-22 08-Aug-22 0% Not Started 0%, Installation Gypsum Board for Drywall Partition
A4713 Plaster and Render (Plastering) 60 20-Jun-22 18-Aug-22 0% Not Started 0%, Plaster and Render (Plastering)
A4703 Installation Gypsum Board for Ceiling 60 30-Jun-22 28-Aug-22 0% Not Started 0%, Installation Gypsum Board for Ceiling
A4693 Tile and Slab Finishes 60 20-Jul-22 17-Sep-22 0% Not Started 0%, Tile and Slab Finishes
A4683 Application of Exterior Painting 28 18-Sep-22 15-Oct-22 0% Not Started 0%, Application of Exterior Painting
A4673 Application of Interior Painting 28 01-Oct-22 28-Oct-22 0% Not Started 0%, Application of Interior Painting
D.1.D10 SPECIALTIES 48 29-Aug-22 15-Oct-22 D.1.D10 SPECIALTIES, 0%
A4743 Toilet paper holder 28 29-Aug-22 25-Sep-22 0% Not Started 0%, Toilet paper holder
A4733 Installation of Soap Holder 28 18-Sep-22 15-Oct-22 0% Not Started 0%, Installation of Soap Holder
D.1.D12 FURNISHINGS 65 06-Sep-22 09-Nov-22 D.1.D12 FURNISHINGS, 0%
A4753 Installation of Countertops 65 06-Sep-22 09-Nov-22 0% Not Started 0%, Installation of Countertops
D.1.D22 PLUMBING 210 22-Mar-22 17-Oct-22 D.1.D22 PLUMBING, 0%

Project Baseline Bar Critical Remaining Work Summary   OWNER: ABOITIZLAND


Actual Work Milestone LOCATION: Tamiao, Compostela, Cebu City
Page 5 of 10
Remaining Work % Complete PREPARED BY: MARIÑAS & CO. BUILDERS INC. (ENGG DEPT)
     
PROPOSED AMOA HOUSING (REV 1.0) CONTRACTOR: MARIÑAS & CO. BUILDERS INC 20-Sep-21 13:09
 
Activity ID Activity Name BL BL Project BL Project Activity % Activity
Project Start Finish Complete Status 2022 2023
Duration Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A4773 Installation of Plumbing Fixtures (OSM) 70 09-Aug-22 17-Oct-22 0% Not Started 0%, Installation of Plumbing Fixtures (OSM)
A4763 Installation of Storage Drainage System 40 24-Apr-22 02-Jun-22 0% Not Started 0%, Installation of Storage Drainage System
D.1.D22.1 SOIL, WASTE AND VENT SYSTEM 165 22-Mar-22 02-Sep-22 D.1.D22.1 SOIL, WASTE AND VENT SYSTEM, 0%
A4863 Supply and Installation of PE Septic Tank (OSM)14 14-Jun-22 27-Jun-22 0% Not Started 0%, Supply and Installation of PE Septic Tank (OSM)
A4853 Supply and fix Grease Trap (catch basin type, exterior)
60 22-Mar-22 20-May-22 0% Not Started 0%, Supply and fix Grease Trap (catch basin type, exterior)
A4843 Installation of Polyvinyl Chloride pipes for vent thru
45roof
17-May-22 30-Jun-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes for vent thru roof
A4833 Installation of Polyvinyl Chloride pipes to floor cleanouts
35 06-May-22 09-Jun-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes to floor cleanouts
A4823 Installation of Polyvinyl Chloride pipes to ceilings 40
and25-Jul-22
soffits 02-Sep-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes to ceilings and soffits
A4813 Excavation of Trenches 28 05-May-22 01-Jun-22 0% Not Started 0%, Excavation of Trenches
A4803 Installation of Polyvinyl Chloride pipes < 200mm diameter
55 10-Jun-22 03-Aug-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes < 200mm diameter
A4793 Installation of Polyvinyl Chloride pipes for trenches
53 05-Jul-22 26-Aug-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes for trenches
A4783 Installation of Polyvinyl Chloride pipes to walls and
53floors
05-Jul-22 26-Aug-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes to walls and floors
D.1.D22.4 COLD WATER SYSTEM 120 10-May-22 06-Sep-22 D.1.D22.4 COLD WATER SYSTEM, 0%
A4933 Pipework Ancillaries and accesories for Gate Valve
65 20-May-22 23-Jul-22 0% Not Started 0%, Pipework Ancillaries and accesories for Gate Valve
A4923 Pipework Ancillaries and accesories for Hose bibb
65 30-May-22 02-Aug-22 0% Not Started 0%, Pipework Ancillaries and accesories for Hose bibb
A4913 Pipework Ancillaries and accesories for Water Meter
65 09-Jun-22 12-Aug-22 0% Not Started 0%, Pipework Ancillaries and accesories for Water Meter
A4903 Excavation of Trenches (w/ necessary backfilling)
65 10-May-22 13-Jul-22 0% Not Started 0%, Excavation of Trenches (w/ necessary backfilling)
A4893 Installation of Polyvinyl Chloride pipes < 200mm diameter
65 19-Jun-22 22-Aug-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes < 200mm diameter
A4883 Polyrpropylene pipes (PPrC) and fittings by Thermovar
65 29-Jun-22
for trenches01-Sep-22 0% Not Started 0%, Polyrpropylene pipes (PPrC) and fittings by Thermovar for trenches
A4873 Polyrpropylene pipes (PPrC) and fittings by Thermovar
65 04-Jul-22
to walls and06-Sep-22
floors 0% Not Started 0%, Polyrpropylene pipes (PPrC) and fittings by Thermovar to walls and floors
D.1.D26 ELECTRICAL 267 17-Mar-22 08-Dec-22 D.1.D26 ELECTRICAL, 0%
A4953 MAINS AND SUB-MAINS DISTRIBUTION SYSTEMS 40 17-Mar-22 25-Apr-22 0% Not Started 0%, MAINS AND SUB-MAINS DISTRIBUTION SYSTEMS
A4943 GENERAL LIGHTING AND POWER 30 09-Nov-22 08-Dec-22 0% Not Started 0%, GENERAL LIGHTING AND POWER
D.1.D27 COMMUNICATIONS 40 09-Nov-22 18-Dec-22 D.1.D27 COMMUNICATIONS, 0%
A4973 TELEPHONE SYSTEM 30 09-Nov-22 08-Dec-22 0% Not Started 0%, TELEPHONE SYSTEM
A4963 CATV SYSTEM 30 19-Nov-22 18-Dec-22 0% Not Started 0%, CATV SYSTEM
D.1.D31 EARTHWORK 129 05-Feb-22 13-Jun-22 D.1.D31 EARTHWORK, 0%
A5033 Soil Treatment 25 02-Mar-22 26-Mar-22 0% Not Started 0%, Soil Treatment
A5023 Structural excavation 45 05-Feb-22 21-Mar-22 0% Not Started 0%, Structural excavation
A5013 Approved well compacted granular fill 35 22-Mar-22 25-Apr-22 0% Not Started 0%, Approved well compacted granular fill
A5003 Gravel Bedding 25 10-Mar-22 03-Apr-22 0% Not Started 0%, Gravel Bedding
A4993 Staking and lay-out 28 02-Mar-22 29-Mar-22 0% Not Started 0%, Staking and lay-out
A4983 Excavation works for PE Septic tank 45 30-Apr-22 13-Jun-22 0% Not Started 0%, Excavation works for PE Septic tank
D.5 ASHA (2SD) 15% UH - 4 UNITS- a 329 21-Apr-22 15-Mar-23 D.5 ASHA (2SD) 15% UH - 4 UNITS- a, 0%
D.5.D3 CONCRETE 150 29-May-22 25-Oct-22 D.5.D3 CONCRETE, 0%
D.5.D3.1 Concrete Forming 121 29-May-22 26-Sep-22 D.5.D3.1 Concrete Forming, 0%
A9053 to sides of column 36 13-Jun-22 18-Jul-22 0% Not Started 0%, to sides of column
A9043 to suspended beam 60 15-Jul-22 12-Sep-22 0% Not Started 0%, to suspended beam
A9033 to sides of bearing wall 50 05-Jul-22 23-Aug-22 0% Not Started 0%, to sides of bearing wall
A9023 to sides of wall footings & stair footings 40 29-May-22 07-Jul-22 0% Not Started 0%, to sides of wall footings & stair footings
A9013 to sides and soffits of beams 48 07-Jul-22 23-Aug-22 0% Not Started 0%, to sides and soffits of beams
A9003 to stairs 45 14-Jun-22 28-Jul-22 0% Not Started 0%, to stairs
A8993 to edges of slab on grade beds and the like; width
45<19-Jun-22
300mm 02-Aug-22 0% Not Started 0%, to edges of slab on grade beds and the like; width < 300mm
A8983 to ledge 40 27-Jun-22 05-Aug-22 0% Not Started 0%, to ledge
A8973 to edges of ledge 40 27-Jun-22 05-Aug-22 0% Not Started 0%, to edges of ledge
A8963 to volada 40 02-Jul-22 10-Aug-22 0% Not Started 0%, to volada
A8953 to edges of volada 40 02-Jul-22 10-Aug-22 0% Not Started 0%, to edges of volada
A8943 to suspended slab 48 10-Aug-22 26-Sep-22 0% Not Started 0%, to suspended slab
D.5.D3.0 Concrete Reinforcing 126 29-May-22 01-Oct-22 D.5.D3.0 Concrete Reinforcing, 0%
A9133 in wall footings, stair footings (10mm & 12mm) 32 29-May-22 29-Jun-22 0% Not Started 0%, in wall footings, stair footings (10mm & 12mm)
A9123 in bearing walls (10mm, 12mm, 16mm) 50 15-Jul-22 02-Sep-22 0% Not Started 0%, in bearing walls (10mm, 12mm, 16mm)
A9113 in slabs on grade (10mm) 35 04-Aug-22 07-Sep-22 0% Not Started 0%, in slabs on grade (10mm)
A9103 in suspended slabs (10mm) 40 23-Aug-22 01-Oct-22 0% Not Started 0%, in suspended slabs (10mm)
A9093 in staircases (10mm, 12mm, 16mm) 35 29-Jul-22 01-Sep-22 0% Not Started 0%, in staircases (10mm, 12mm, 16mm)
A9083 in ledges (10mm) 32 12-Jul-22 12-Aug-22 0% Not Started 0%, in ledges (10mm)
A9073 in volada (10mm) 32 11-Aug-22 11-Sep-22 0% Not Started 0%, in volada (10mm)
A9063 in column (10mm, 16mm) 38 19-Jun-22 26-Jul-22 0% Not Started 0%, in column (10mm, 16mm)
D.5.D3.2 Cast in-place Concrete 142 06-Jun-22 25-Oct-22 D.5.D3.2 Cast in-place Concrete, 0%
A9793 in bearing walls @ 2F 45 11-Sep-22 25-Oct-22 0% Not Started 0%, in bearing walls @ 2F
A9213 in stair footings (10mm & 12mm) 35 06-Jun-22 10-Jul-22 0% Not Started 0%, in stair footings (10mm & 12mm)

Project Baseline Bar Critical Remaining Work Summary   OWNER: ABOITIZLAND


Actual Work Milestone LOCATION: Tamiao, Compostela, Cebu City
Page 6 of 10
Remaining Work % Complete PREPARED BY: MARIÑAS & CO. BUILDERS INC. (ENGG DEPT)
     
PROPOSED AMOA HOUSING (REV 1.0) CONTRACTOR: MARIÑAS & CO. BUILDERS INC 20-Sep-21 13:09
 
Activity ID Activity Name BL BL Project BL Project Activity % Activity
Project Start Finish Complete Status 2022 2023
Duration Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A9203 in bearing walls @ GF 45 28-Jul-22 10-Sep-22 0% Not Started 0%, in bearing walls @ GF
A9193 in slabs on grade (10mm) 35 14-Aug-22 17-Sep-22 0% Not Started 0%, in slabs on grade (10mm)
A9183 in beams and girders 30 04-Sep-22 03-Oct-22 0% Not Started 0%, in beams and girders
A9173 in staircases (10mm, 12mm, 16mm) 30 08-Aug-22 06-Sep-22 0% Not Started 0%, in staircases (10mm, 12mm, 16mm)
A9163 in ledges (10mm) 21 13-Aug-22 02-Sep-22 0% Not Started 0%, in ledges (10mm)
A9153 in volada (10mm) 21 23-Aug-22 12-Sep-22 0% Not Started 0%, in volada (10mm)
A9143 in column (10mm, 16mm) 43 27-Jun-22 08-Aug-22 0% Not Started 0%, in column (10mm, 16mm)
D.5.D4 MASONRY 50 30-Jun-22 18-Aug-22 D.5.D4 MASONRY, 0%
A9223 CHB Laying (100 thk) 50 30-Jun-22 18-Aug-22 0% Not Started 0%, CHB Laying (100 thk)
D.5.D5 METALS 72 07-Sep-22 17-Nov-22 D.5.D5 METALS, 0%
A9263 Installation of Rafters 33 26-Sep-22 28-Oct-22 0% Not Started 0%, Installation of Rafters
A9253 Installation of Canopy 30 09-Oct-22 07-Nov-22 0% Not Started 0%, Installation of Canopy
A9243 Installation of Purlins 30 19-Oct-22 17-Nov-22 0% Not Started 0%, Installation of Purlins
A9233 Anchor Bolts, Tie Rods, Angle Bars etc. 50 14-Sep-22 02-Nov-22 0% Not Started 0%, Anchor Bolts, Tie Rods, Angle Bars etc.
D.5.D5.1 Metal Fabrications 34 07-Sep-22 10-Oct-22 D.5.D5.1 Metal Fabrications, 0%
A9293 For Stairs handrill 14 07-Sep-22 20-Sep-22 0% Not Started 0%, For Stairs handrill
A9283 To Porch 14 27-Sep-22 10-Oct-22 0% Not Started 0%, To Porch
A9273 To Volada 14 13-Sep-22 26-Sep-22 0% Not Started 0%, To Volada
D.5.D6 WOOD, PLASTICS, AND COMPOSITES 75 19-Aug-22 01-Nov-22 D.5.D6 WOOD, PLASTICS, AND COMPOSITES, 0%
A9303 Supply and installation of Fr 2" thick solid wood for
75tread
19-Aug-22 01-Nov-22 0% Not Started 0%, Supply and installation of Fr 2" thick solid wood for tread
D.5.D7 THERMAL AND MOISTURE PROTECTION 95 19-Sep-22 22-Dec-22 D.5.D7 THERMAL AND MOISTURE PROTECTION, 0%
A9323 Installation of Roof Insulation 60 24-Oct-22 22-Dec-22 0% Not Started 0%, Installation of Roof Insulation
A9313 Application of Waterproofing at Toilet 40 07-Nov-22 16-Dec-22 0% Not Started 0%, Application of Waterproofing at Toilet
D.5.D7.1 Roofing and Siding Panel 70 19-Sep-22 27-Nov-22 D.5.D7.1 Roofing and Siding Panel, 0%
A9373 Installation of Canopy 50 19-Sep-22 07-Nov-22 0% Not Started 0%, Installation of Canopy
A9363 Installation of Roofing 50 24-Sep-22 12-Nov-22 0% Not Started 0%, Installation of Roofing
A9353 Installation of Gutter 50 29-Sep-22 17-Nov-22 0% Not Started 0%, Installation of Gutter
A9343 Installation of Fascia Board 50 04-Oct-22 22-Nov-22 0% Not Started 0%, Installation of Fascia Board
A9333 Installation of Eaves 50 09-Oct-22 27-Nov-22 0% Not Started 0%, Installation of Eaves
D.5.D8 OPENINGS 48 06-Jan-23 22-Feb-23 D.5.D8 OPENINGS, 0%
A9413 Supply and Installation of Metal Doors 40 06-Jan-23 14-Feb-23 0% Not Started 0%, Supply and Installation of Metal Doors
A9403 Supply and Installation of Wood Doors 40 08-Jan-23 16-Feb-23 0% Not Started 0%, Supply and Installation of Wood Doors
A9393 Supply and Installation of Windows 40 11-Jan-23 19-Feb-23 0% Not Started 0%, Supply and Installation of Windows
A9383 Supply and Installation of Hardware 40 14-Jan-23 22-Feb-23 0% Not Started 0%, Supply and Installation of Hardware
D.5.D9 FINISHES 141 19-Aug-22 06-Jan-23 D.5.D9 FINISHES, 0%
A9473 Installation Gypsum Board for Drywall Partition 60 19-Aug-22 17-Oct-22 0% Not Started 0%, Installation Gypsum Board for Drywall Partition
A9463 Plaster and Render (Plastering) 60 29-Aug-22 27-Oct-22 0% Not Started 0%, Plaster and Render (Plastering)
A9453 Installation Gypsum Board for Ceiling 60 08-Sep-22 06-Nov-22 0% Not Started 0%, Installation Gypsum Board for Ceiling
A9443 Tile and Slab Finishes 60 28-Sep-22 26-Nov-22 0% Not Started 0%, Tile and Slab Finishes
A9433 Application of Exterior Painting 28 27-Nov-22 24-Dec-22 0% Not Started 0%, Application of Exterior Painting
A9423 Application of Interior Painting 28 10-Dec-22 06-Jan-23 0% Not Started 0%, Application of Interior Painting
D.5.D10 SPECIALTIES 55 07-Nov-22 31-Dec-22 D.5.D10 SPECIALTIES, 0%
A9493 Toilet paper holder 35 07-Nov-22 11-Dec-22 0% Not Started 0%, Toilet paper holder
A9483 Installation of Soap Holder 35 27-Nov-22 31-Dec-22 0% Not Started 0%, Installation of Soap Holder
D.5.D12 FURNISHINGS 65 22-Nov-22 25-Jan-23 D.5.D12 FURNISHINGS, 0%
A9503 Installation of Countertops 65 22-Nov-22 25-Jan-23 0% Not Started 0%, Installation of Countertops
D.5.D22 PLUMBING 205 05-Jun-22 26-Dec-22 D.5.D22 PLUMBING, 0%
A9523 Installation of Plumbing Fixtures (OSM) 70 18-Oct-22 26-Dec-22 0% Not Started 0%, Installation of Plumbing Fixtures (OSM)
A9513 Installation of Storage Drainage System 40 29-Jun-22 07-Aug-22 0% Not Started 0%, Installation of Storage Drainage System
D.5.D22.1 SOIL, WASTE AND VENT SYSTEM 158 05-Jun-22 09-Nov-22 D.5.D22.1 SOIL, WASTE AND VENT SYSTEM, 0%
A9613 Supply and Installation of PE Septic Tank (OSM)14 19-Aug-22 01-Sep-22 0% Not Started 0%, Supply and Installation of PE Septic Tank (OSM)
A9603 Supply and fix Grease Trap (catch basin type, exterior)
60 05-Jun-22 03-Aug-22 0% Not Started 0%, Supply and fix Grease Trap (catch basin type, exterior)
A9593 Installation of Polyvinyl Chloride pipes for vent thru
45roof
22-Jul-22 04-Sep-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes for vent thru roof
A9583 Installation of Polyvinyl Chloride pipes to floor cleanouts
35 11-Jul-22 14-Aug-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes to floor cleanouts
A9573 Installation of Polyvinyl Chloride pipes to ceilings 40
and04-Sep-22
soffits 13-Oct-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes to ceilings and soffits
A9563 Excavation of Trenches 28 10-Jul-22 06-Aug-22 0% Not Started 0%, Excavation of Trenches
A9553 Installation of Polyvinyl Chloride pipes < 200mm diameter
55 15-Aug-22 08-Oct-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes < 200mm diameter
A9543 Installation of Polyvinyl Chloride pipes for trenches
53 18-Sep-22 09-Nov-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes for trenches
A9533 Installation of Polyvinyl Chloride pipes to walls and
53floors
18-Sep-22 09-Nov-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes to walls and floors
D.5.D22.4 COLD WATER SYSTEM 125 15-Jul-22 16-Nov-22 D.5.D22.4 COLD WATER SYSTEM, 0%

Project Baseline Bar Critical Remaining Work Summary   OWNER: ABOITIZLAND


Actual Work Milestone LOCATION: Tamiao, Compostela, Cebu City
Page 7 of 10
Remaining Work % Complete PREPARED BY: MARIÑAS & CO. BUILDERS INC. (ENGG DEPT)
     
PROPOSED AMOA HOUSING (REV 1.0) CONTRACTOR: MARIÑAS & CO. BUILDERS INC 20-Sep-21 13:09
 
Activity ID Activity Name BL BL Project BL Project Activity % Activity
Project Start Finish Complete Status 2022 2023
Duration Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A9683 Pipework Ancillaries and accesories for Gate Valve
65 30-Jul-22 02-Oct-22 0% Not Started 0%, Pipework Ancillaries and accesories for Gate Valve
A9673 Pipework Ancillaries and accesories for Hose bibb
65 09-Aug-22 12-Oct-22 0% Not Started 0%, Pipework Ancillaries and accesories for Hose bibb
A9663 Pipework Ancillaries and accesories for Water Meter
65 19-Aug-22 22-Oct-22 0% Not Started 0%, Pipework Ancillaries and accesories for Water Meter
A9653 Excavation of Trenches (w/ necessary backfilling)
65 15-Jul-22 17-Sep-22 0% Not Started 0%, Excavation of Trenches (w/ necessary backfilling)
A9643 Installation of Polyvinyl Chloride pipes < 200mm diameter
65 29-Aug-22 01-Nov-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes < 200mm diameter
A9633 Polyrpropylene pipes (PPrC) and fittings by Thermovar
65 08-Sep-22
for trenches11-Nov-22 0% Not Started 0%, Polyrpropylene pipes (PPrC) and fittings by Thermovar for trenches
A9623 Polyrpropylene pipes (PPrC) and fittings by Thermovar
65 13-Sep-22
to walls and16-Nov-22
floors 0% Not Started 0%, Polyrpropylene pipes (PPrC) and fittings by Thermovar to walls and floors
D.5.D26 ELECTRICAL 274 26-May-22 23-Feb-23 D.5.D26 ELECTRICAL, 0%
A9703 MAINS AND SUB-MAINS DISTRIBUTION SYSTEMS 40 26-May-22 04-Jul-22 0% Not Started 0%, MAINS AND SUB-MAINS DISTRIBUTION SYSTEMS
A9693 GENERAL LIGHTING AND POWER 30 25-Jan-23 23-Feb-23 0% Not Started 0%, GENERAL LIGHTING AND POWER
D.5.D27 COMMUNICATIONS 50 25-Jan-23 15-Mar-23 D.5.D27 COMMUNICATIONS, 0%
A9723 TELEPHONE SYSTEM 30 25-Jan-23 23-Feb-23 0% Not Started 0%, TELEPHONE SYSTEM
A9713 CATV SYSTEM 30 14-Feb-23 15-Mar-23 0% Not Started 0%, CATV SYSTEM
D.5.D31 EARTHWORK 120 21-Apr-22 18-Aug-22 D.5.D31 EARTHWORK, 0%
A9783 Soil Treatment 25 16-May-22 09-Jun-22 0% Not Started 0%, Soil Treatment
A9773 Structural excavation 45 21-Apr-22 04-Jun-22 0% Not Started 0%, Structural excavation
A9763 Approved well compacted granular fill 35 05-Jun-22 09-Jul-22 0% Not Started 0%, Approved well compacted granular fill
A9753 Gravel Bedding 25 24-May-22 17-Jun-22 0% Not Started 0%, Gravel Bedding
A9743 Staking and lay-out 28 21-May-22 17-Jun-22 0% Not Started 0%, Staking and lay-out
A9733 Excavation works for PE Septic tank 45 05-Jul-22 18-Aug-22 0% Not Started 0%, Excavation works for PE Septic tank
D.3 ASTA (2SA) 15% UH - 3 UNITS 240 23-Jul-22 19-Mar-23 D.3 ASTA (2SA) 15% UH - 3 UNITS, 0%
D.3.D3 CONCRETE 130 10-Aug-22 17-Dec-22 D.3.D3 CONCRETE, 0%
D.3.D3.1 Concrete Forming 90 10-Aug-22 07-Nov-22 D.3.D3.1 Concrete Forming, 0%
A5253 to sides of column 30 25-Aug-22 23-Sep-22 0% Not Started 0%, to sides of column
A5243 to suspended beam 45 10-Sep-22 24-Oct-22 0% Not Started 0%, to suspended beam
A5233 to sides of bearing wall 50 11-Sep-22 30-Oct-22 0% Not Started 0%, to sides of bearing wall
A5223 to sides of wall footings & stair footings 40 10-Aug-22 18-Sep-22 0% Not Started 0%, to sides of wall footings & stair footings
A5213 to sides and soffits of beams 48 02-Sep-22 19-Oct-22 0% Not Started 0%, to sides and soffits of beams
A5203 to stairs 42 20-Aug-22 30-Sep-22 0% Not Started 0%, to stairs
A5193 to edges of slab on grade beds and the like; width
42<22-Aug-22
300mm 02-Oct-22 0% Not Started 0%, to edges of slab on grade beds and the like; width < 300mm
A5183 to ledge 38 27-Aug-22 03-Oct-22 0% Not Started 0%, to ledge
A5173 to edges of ledge 38 25-Aug-22 01-Oct-22 0% Not Started 0%, to edges of ledge
A5163 to volada 40 28-Aug-22 06-Oct-22 0% Not Started 0%, to volada
A5153 to edges of volada 40 28-Aug-22 06-Oct-22 0% Not Started 0%, to edges of volada
A5143 to suspended slab 48 21-Sep-22 07-Nov-22 0% Not Started 0%, to suspended slab
D.3.D3.0 Concrete Reinforcing 97 10-Aug-22 14-Nov-22 D.3.D3.0 Concrete Reinforcing, 0%
A5333 in wall footings, stair footings (10mm & 12mm) 32 10-Aug-22 10-Sep-22 0% Not Started 0%, in wall footings, stair footings (10mm & 12mm)
A5323 in bearing walls (10mm, 12mm, 16mm) 50 21-Sep-22 09-Nov-22 0% Not Started 0%, in bearing walls (10mm, 12mm, 16mm)
A5313 in slabs on grade (10mm) 35 11-Oct-22 14-Nov-22 0% Not Started 0%, in slabs on grade (10mm)
A5303 in suspended slabs (10mm) 40 04-Oct-22 12-Nov-22 0% Not Started 0%, in suspended slabs (10mm)
A5293 in staircases (10mm, 12mm, 16mm) 35 01-Oct-22 04-Nov-22 0% Not Started 0%, in staircases (10mm, 12mm, 16mm)
A5283 in ledges (10mm) 28 09-Sep-22 06-Oct-22 0% Not Started 0%, in ledges (10mm)
A5273 in volada (10mm) 28 07-Oct-22 03-Nov-22 0% Not Started 0%, in volada (10mm)
A5263 in column (10mm, 16mm) 38 25-Aug-22 01-Oct-22 0% Not Started 0%, in column (10mm, 16mm)
D.3.D3.2 Cast in-place Concrete 122 18-Aug-22 17-Dec-22 D.3.D3.2 Cast in-place Concrete, 0%
A5993 in bearing walls @ 2F 45 03-Nov-22 17-Dec-22 0% Not Started 0%, in bearing walls @ 2F
A5413 in stair footings (10mm & 12mm) 35 18-Aug-22 21-Sep-22 0% Not Started 0%, in stair footings (10mm & 12mm)
A5403 in bearing walls @ GF 45 04-Oct-22 17-Nov-22 0% Not Started 0%, in bearing walls @ GF
A5393 in slabs on grade (10mm) 35 21-Oct-22 24-Nov-22 0% Not Started 0%, in slabs on grade (10mm)
A5383 in beams and girders 30 16-Oct-22 14-Nov-22 0% Not Started 0%, in beams and girders
A5373 in staircases (10mm, 12mm, 16mm) 30 11-Oct-22 09-Nov-22 0% Not Started 0%, in staircases (10mm, 12mm, 16mm)
A5363 in ledges (10mm) 21 07-Oct-22 27-Oct-22 0% Not Started 0%, in ledges (10mm)
A5353 in volada (10mm) 21 15-Oct-22 04-Nov-22 0% Not Started 0%, in volada (10mm)
A5343 in column (10mm, 16mm) 43 02-Sep-22 14-Oct-22 0% Not Started 0%, in column (10mm, 16mm)
D.3.D4 MASONRY 38 11-Sep-22 18-Oct-22 D.3.D4 MASONRY, 0%
A5423 CHB Laying (100 thk) 38 11-Sep-22 18-Oct-22 0% Not Started 0%, CHB Laying (100 thk)
D.3.D5 METALS 65 26-Oct-22 29-Dec-22 D.3.D5 METALS, 0%
A5463 Installation of Rafters 33 07-Nov-22 09-Dec-22 0% Not Started 0%, Installation of Rafters
A5453 Installation of Canopy 30 20-Nov-22 19-Dec-22 0% Not Started 0%, Installation of Canopy
A5443 Installation of Purlins 30 30-Nov-22 29-Dec-22 0% Not Started 0%, Installation of Purlins

Project Baseline Bar Critical Remaining Work Summary   OWNER: ABOITIZLAND


Actual Work Milestone LOCATION: Tamiao, Compostela, Cebu City
Page 8 of 10
Remaining Work % Complete PREPARED BY: MARIÑAS & CO. BUILDERS INC. (ENGG DEPT)
     
PROPOSED AMOA HOUSING (REV 1.0) CONTRACTOR: MARIÑAS & CO. BUILDERS INC 20-Sep-21 13:09
 
Activity ID Activity Name BL BL Project BL Project Activity % Activity
Project Start Finish Complete Status 2022 2023
Duration Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A5433 Anchor Bolts, Tie Rods, Angle Bars etc. 50 26-Oct-22 14-Dec-22 0% Not Started 0%, Anchor Bolts, Tie Rods, Angle Bars etc.
D.3.D5.1 Metal Fabrications 28 05-Nov-22 02-Dec-22 D.3.D5.1 Metal Fabrications, 0%
A5493 For Stairs handrill 14 10-Nov-22 23-Nov-22 0% Not Started 0%, For Stairs handrill
A5483 To Porch 14 19-Nov-22 02-Dec-22 0% Not Started 0%, To Porch
A5473 To Volada 14 05-Nov-22 18-Nov-22 0% Not Started 0%, To Volada
D.3.D6 WOOD, PLASTICS, AND COMPOSITES 75 19-Oct-22 01-Jan-23 D.3.D6 WOOD, PLASTICS, AND COMPOSITES, 0%
A5503 Supply and installation of Fr 2" thick solid wood for
75tread
19-Oct-22 01-Jan-23 0% Not Started 0%, Supply and installation of Fr 2" thick solid wood for tread
D.3.D7 THERMAL AND MOISTURE PROTECTION 80 20-Oct-22 07-Jan-23 D.3.D7 THERMAL AND MOISTURE PROTECTION, 0%
A5523 Installation of Roof Insulation 60 23-Oct-22 21-Dec-22 0% Not Started 0%, Installation of Roof Insulation
A5513 Application of Waterproofing at Toilet 40 29-Nov-22 07-Jan-23 0% Not Started 0%, Application of Waterproofing at Toilet
D.3.D7.1 Roofing and Siding Panel 52 20-Oct-22 10-Dec-22 D.3.D7.1 Roofing and Siding Panel, 0%
A5573 Installation of Canopy 38 31-Oct-22 07-Dec-22 0% Not Started 0%, Installation of Canopy
A5563 Installation of Roofing 38 03-Nov-22 10-Dec-22 0% Not Started 0%, Installation of Roofing
A5553 Installation of Gutter 38 03-Nov-22 10-Dec-22 0% Not Started 0%, Installation of Gutter
A5543 Installation of Fascia Board 38 27-Oct-22 03-Dec-22 0% Not Started 0%, Installation of Fascia Board
A5533 Installation of Eaves 38 20-Oct-22 26-Nov-22 0% Not Started 0%, Installation of Eaves
D.3.D8 OPENINGS 88 22-Dec-22 19-Mar-23 D.3.D8 OPENINGS, 0%
A5613 Supply and Installation of Metal Doors 50 22-Dec-22 09-Feb-23 0% Not Started 0%, Supply and Installation of Metal Doors
A5603 Supply and Installation of Wood Doors 50 03-Jan-23 21-Feb-23 0% Not Started 0%, Supply and Installation of Wood Doors
A5593 Supply and Installation of Windows 50 16-Jan-23 06-Mar-23 0% Not Started 0%, Supply and Installation of Windows
A5583 Supply and Installation of Hardware 50 29-Jan-23 19-Mar-23 0% Not Started 0%, Supply and Installation of Hardware
D.3.D9 FINISHES 91 04-Oct-22 02-Jan-23 D.3.D9 FINISHES, 0%
A5673 Installation Gypsum Board for Drywall Partition 51 04-Oct-22 23-Nov-22 0% Not Started 0%, Installation Gypsum Board for Drywall Partition
A5663 Plaster and Render (Plastering) 48 07-Oct-22 23-Nov-22 0% Not Started 0%, Plaster and Render (Plastering)
A5653 Installation Gypsum Board for Ceiling 50 10-Oct-22 28-Nov-22 0% Not Started 0%, Installation Gypsum Board for Ceiling
A5643 Tile and Slab Finishes 50 20-Oct-22 08-Dec-22 0% Not Started 0%, Tile and Slab Finishes
A5633 Application of Exterior Painting 25 29-Nov-22 23-Dec-22 0% Not Started 0%, Application of Exterior Painting
A5623 Application of Interior Painting 25 09-Dec-22 02-Jan-23 0% Not Started 0%, Application of Interior Painting
D.3.D10 SPECIALTIES 55 19-Nov-22 12-Jan-23 D.3.D10 SPECIALTIES, 0%
A5693 Toilet paper holder 35 19-Nov-22 23-Dec-22 0% Not Started 0%, Toilet paper holder
A5683 Installation of Soap Holder 35 09-Dec-22 12-Jan-23 0% Not Started 0%, Installation of Soap Holder
D.3.D12 FURNISHINGS 50 24-Nov-22 12-Jan-23 D.3.D12 FURNISHINGS, 0%
A5703 Installation of Countertops 50 24-Nov-22 12-Jan-23 0% Not Started 0%, Installation of Countertops
D.3.D22 PLUMBING 149 22-Aug-22 17-Jan-23 D.3.D22 PLUMBING, 0%
A5723 Installation of Plumbing Fixtures (OSM) 50 09-Nov-22 28-Dec-22 0% Not Started 0%, Installation of Plumbing Fixtures (OSM)
A5713 Installation of Storage Drainage System 40 04-Sep-22 13-Oct-22 0% Not Started 0%, Installation of Storage Drainage System
D.3.D22.1 SOIL, WASTE AND VENT SYSTEM 148 22-Aug-22 16-Jan-23 D.3.D22.1 SOIL, WASTE AND VENT SYSTEM, 0%
A5813 Supply and Installation of PE Septic Tank (OSM)28 25-Oct-22 21-Nov-22 0% Not Started 0%, Supply and Installation of PE Septic Tank (OSM)
A5803 Supply and fix Grease Trap (catch basin type, exterior)
60 22-Aug-22 20-Oct-22 0% Not Started 0%, Supply and fix Grease Trap (catch basin type, exterior)
A5793 Installation of Polyvinyl Chloride pipes for vent thru
45roof
27-Sep-22 10-Nov-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes for vent thru roof
A5783 Installation of Polyvinyl Chloride pipes to floor cleanouts
35 16-Sep-22 20-Oct-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes to floor cleanouts
A5773 Installation of Polyvinyl Chloride pipes to ceilings 40
and16-Oct-22
soffits 24-Nov-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes to ceilings and soffits
A5763 Excavation of Trenches 28 15-Sep-22 12-Oct-22 0% Not Started 0%, Excavation of Trenches
A5753 Installation of Polyvinyl Chloride pipes < 200mm diameter
55 21-Oct-22 14-Dec-22 0% Not Started 0%, Installation of Polyvinyl Chloride pipes < 200mm diameter
A5743 Installation of Polyvinyl Chloride pipes for trenches
53 25-Nov-22 16-Jan-23 0% Not Started 0%, Installation of Polyvinyl Chloride pipes for trenches
A5733 Installation of Polyvinyl Chloride pipes to walls and
53floors
25-Nov-22 16-Jan-23 0% Not Started 0%, Installation of Polyvinyl Chloride pipes to walls and floors
D.3.D22.4 COLD WATER SYSTEM 120 20-Sep-22 17-Jan-23 D.3.D22.4 COLD WATER SYSTEM, 0%
A5883 Pipework Ancillaries and accesories for Gate Valve
65 30-Sep-22 03-Dec-22 0% Not Started 0%, Pipework Ancillaries and accesories for Gate Valve
A5873 Pipework Ancillaries and accesories for Hose bibb
65 10-Oct-22 13-Dec-22 0% Not Started 0%, Pipework Ancillaries and accesories for Hose bibb
A5863 Pipework Ancillaries and accesories for Water Meter
65 20-Oct-22 23-Dec-22 0% Not Started 0%, Pipework Ancillaries and accesories for Water Meter
A5853 Excavation of Trenches (w/ necessary backfilling)65 20-Sep-22 23-Nov-22 0% Not Started 0%, Excavation of Trenches (w/ necessary backfilling)
A5843 Installation of Polyvinyl Chloride pipes < 200mm diameter
65 30-Oct-22 02-Jan-23 0% Not Started 0%, Installation of Polyvinyl Chloride pipes < 200mm diameter
A5833 Polyrpropylene pipes (PPrC) and fittings by Thermovar
65 09-Nov-22
for trenches12-Jan-23 0% Not Started 0%, Polyrpropylene pipes (PPrC) and fittings by Thermovar for trenches
A5823 Polyrpropylene pipes (PPrC) and fittings by Thermovar
65 14-Nov-22
to walls and17-Jan-23
floors 0% Not Started 0%, Polyrpropylene pipes (PPrC) and fittings by Thermovar to walls and floors
D.3.D26 ELECTRICAL 196 07-Aug-22 18-Feb-23 D.3.D26 ELECTRICAL, 0%
A5903 MAINS AND SUB-MAINS DISTRIBUTION SYSTEMS 40 07-Aug-22 15-Sep-22 0% Not Started 0%, MAINS AND SUB-MAINS DISTRIBUTION SYSTEMS
A5893 GENERAL LIGHTING AND POWER 30 20-Jan-23 18-Feb-23 0% Not Started 0%, GENERAL LIGHTING AND POWER
D.3.D27 COMMUNICATIONS 40 20-Jan-23 28-Feb-23 D.3.D27 COMMUNICATIONS, 0%
A5923 TELEPHONE SYSTEM 30 20-Jan-23 18-Feb-23 0% Not Started 0%, TELEPHONE SYSTEM
A5913 CATV SYSTEM 30 30-Jan-23 28-Feb-23 0% Not Started 0%, CATV SYSTEM

Project Baseline Bar Critical Remaining Work Summary   OWNER: ABOITIZLAND


Actual Work Milestone LOCATION: Tamiao, Compostela, Cebu City
Page 9 of 10
Remaining Work % Complete PREPARED BY: MARIÑAS & CO. BUILDERS INC. (ENGG DEPT)
     
PROPOSED AMOA HOUSING (REV 1.0) CONTRACTOR: MARIÑAS & CO. BUILDERS INC 20-Sep-21 13:09
 
Activity ID Activity Name BL BL Project BL Project Activity % Activity
Project Start Finish Complete Status 2022 2023
Duration Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
D.3.D31 EARTHWORK 94 23-Jul-22 24-Oct-22 D.3.D31 EARTHWORK, 0%
A5983 Soil Treatment 25 02-Aug-22 26-Aug-22 0% Not Started 0%, Soil Treatment
A5973 Structural excavation 30 23-Jul-22 21-Aug-22 0% Not Started 0%, Structural excavation
A5963 Approved well compacted granular fill 25 22-Aug-22 15-Sep-22 0% Not Started 0%, Approved well compacted granular fill
A5953 Gravel Bedding 25 05-Aug-22 29-Aug-22 0% Not Started 0%, Gravel Bedding
A5943 Staking and lay-out 28 02-Aug-22 29-Aug-22 0% Not Started 0%, Staking and lay-out
A5933 Excavation works for PE Septic tank 45 10-Sep-22 24-Oct-22 0% Not Started 0%, Excavation works for PE Septic tank

Project Baseline Bar Critical Remaining Work Summary   OWNER: ABOITIZLAND


Actual Work Milestone LOCATION: Tamiao, Compostela, Cebu City
Page 10 of 10
Remaining Work % Complete PREPARED BY: MARIÑAS & CO. BUILDERS INC. (ENGG DEPT)

You might also like