Professional Documents
Culture Documents
Method Statement For Prestressing of HT Strands
Method Statement For Prestressing of HT Strands
S STRANDS
This item of work deals with the activity of Prestressing of H.T.S strands of PSC girders
with approved materials as per the specifications of the contract agreement.
1. General
This item of work shall be dealt in compliance to the clause 1800 of technical
specifications.
The materials shall confirm to section 1000 and the grout mix shall confirm to section
1808 of technical specifications.
2.Procedure
The length of the cable required shall be computed from the drawing and adding
due allowances for profiling and gripping length of Jack .
The Strand shall be cut evenly by abrasive cutter in required length.
Both ends of the cable shall be numbered in order to place the strand in correct
configuration in the bearing plate to prevent twisting of cable in duct.
The duct shall be profiled first as per the ordinates and cable shall be threaded
into the duct manually .The grout vents if required shall be provided.
Tube ducts of the anchorage shall be fixed with the end blocks as specified in the
drawings.
The ducts shall be connected to the tube units.
The cable consisting of number of strands specified in drawing will be tied
together with binding wire at suitable regular intervals and threaded into
sheathing .
Both ends of the duct shall be closed after strand installation and the protruding
length of the strands shall be wrapped suitably to protect from entry of dirt inside
during concreting.
Concreting:
During the concreting , the cables shall be moved to and fro manually at suitable
intervals to ensure that any concrete entering the duct gets disintegrated and does
not jam the cable.
The strands beyond the bearing plate shall be cleaned after concreting using petrol
in order to remove dust/rust etc.
Stressing Operation:
All protruding ends of the strands shall be cut before prestressing. Nozzles and
valves shall be fitted to the tube units at the grout holes provided at only end of
the cable.
The ducts shall be flushed with lime water .The Grout shall be prepared with
ordinary Portland cement and non shrink grout admixture.
Grouting shall be commenced initially with a low pressure of injection until it
comes out at the other end .The grout shall be allowed to flow freely from the
other end until the consistency of the grout becomes almost same a that of the
injection end.
The other end shall then be closed with suitable plug .Once the desired pressure of
injection reaches , the valve at the entry point shall be closed.
3. Equipment/Machinery
1. Hydraulic Jack
2. Pressure Gauge
3. Compressor
5. Gouting Equipment
6. Grout Cube Moulds
4. Tolerances
1. variation from the specified horizontal profile : 5mm
2. Variation from the specified vertical profile : 5mm
3. Variation from the specified position in member : 5mm