“I have three tasks: training, taking initiatives, and supplying the market.”
Herbert Grad, Plant Manager
“I truly believe that people development and delegation is one of the major
strength of this organization. When I speak with old college friends about
the companies they work for, I am amazed by the number of decisions I (as
well as my workers) am allowed to take here. What you should take home
with you is the feeling for the culture, the openness, and our deep wish that
the technicians decide.”
Oliver Geuther, Ultimate Supply System & Materials Operation Group
Manager
In a country where engineering and machines are revered, and where la-
bor costs are the highest in the world, automation is a ubiquitous strategy to
reduce labor content in manufacturing. Procter & Gamble’s Crailsheim plant
is no exception: the plant is committed to a goal of increasing revenues with
a constant headcount. But what makes it special is that this strategy is explic-
itly built on increasing the skills and capabilities of its workers. Automation
plays a crucial role, but it is the workers who are the center of it all. This is
a textbook example of how Management Quality across the board unlocks
knowledge and initiative in people’s hearts and minds.
9.1 Background
Procter & Gamble (P&G) is one of the world’s leading consumer products
companies. As of mid-1999, the firm was headquartered in Cincinnati, Ohio,
USA, and had 110,000 employees located throughout the world, revenues of
$38.1 billion, net income of $3.8 billion, and assets of $32.1 billion. Although
the firm was organized around four geographical areas (Asia; Europe, Mid-
dle East, and Africa; Latin America; North America), it can also be classified
by its six product groups: baby care, feminine care, beauty care, fabric and
home care, food and beverage, and health care, tissue, and towel.
The best P&G European plant is located in Crailsheim, Germany, a small
town situated about 100 km northeast of Stuttgart (see Fig. 9.1). Founded in
1979, the plant started to manufacture diapers (Pampers) in 1981, and added
female hygiene products (Always and Alldays) in 1989. At the beginning of
2000, it had 1,400 employees and its product mix consisted of 30% Pampers,
50% Always, and 20% Alldays. The plant delivers to 27 countries, most of
them in Europe.
The plant is the world’s leading plant for female hygiene (referred to as
“femcare” in this chapter) process improvements, a feat it achieves through
its research and process development laboratory. Diaper process improve-
ments are led by the Euskirchen sister plant located about 35 km southwest
of Cologne, Germany. At P&G, new product developments are initiated by
the marketing departments, and thus take place at headquarters in Cincin-
nati.
9.2 Strategy 159
Demand for diapers has been decreasing in Europe due to a decline in the
number of babies as well as the economic crisis in Russia. The number of di-
aper lines, therefore, was reduced by 15% in 1999. The European market for
femcare products has stagnated in parallel with demographic trends. Hence,
revenues from traditional product lines at the plant have stagnated over the
last few years. Management has aggressively sought to develop new markets
and has been awarded the opportunity to produce a new cleaning pad for
P&G – “Swiffer” (a dry pad made of electrostatic micro-fibers which, when
in contact with surfaces, catch the dust). Despite having high labor costs,
the plant won the new business because of its high productivity, process im-
provements capabilities, the seven-day running of the production floor, and
the available space.
9.2 Strategy
Crailsheim has established the following strategy in order to thrive in the
P&G world, where plants compete against each other:
• Grow revenues with constant headcount – by increasing automation and
the skills and capabilities of all employees so they can progress from man-
ual work to maintaining machines, and analyzing and improving pro-
cesses. Since this policy has been implemented for the last 11 years, man-
agement has tried to hire people with this upward potential.
• Lead femcare product upgrades in Europe, that is, to remain the manu-
facturing-process lead plant in this area.
• “Fight for every case” (the production unit in the plant’s jargon) – a pol-
icy which means accepting all production requests, even if they represent
small volumes and cause large set-ups (e.g., an extra order with special
packaging for Turkey), in order to establish company’s reputation of al-
ways being able to deliver. In a system where plants compete against
one another for attracting volume, this policy helps Crailsheim increase
revenues.
• Win new business.
• Be the best at manufacturing.
• Reduce costs through continuous process improvements based on new
technology and worker optimization.
• Live the Integrated Working System (IWS), a personnel management sys-
tem designed to get the best from the employees in making the plant
progress. The IWS itself undergoes continuous improvements and is a
refinement of a previous system that was in place in 1997, as explained
by Ingo Schimmelpfennig, the plant’s Human Resources Manager:
“In the old system, we had action plans, training, and people han-
dling, but very detailed safety and quality aspects were missing
and how to combine them. So we took the same principles but
160 9 Procter & Gamble Crailsheim
translated them: that became the IWS. There are six items on the
roof which we call PQCDSM: production, quality, cost, delivery,
safety, and morale. And the roof is built on 10 pillars, which de-
scribe the organization and its tasks: leadership, organization, fo-
cused improvement, autonomous maintenance, progressive main-
tenance, education and training, initiative management, quality,
administration and support, and health, safety, and environment.
Within these pillars there are various specific tasks that need to be
implemented. Luckily, we have 10 group managers in the plant.
Thus, every group manager has one pillar and is called a pillar
leader. We also changed our scorecards where we write the re-
sults according to what’s in the IWS. Every single technician has
received training on the applicable parts of the IWS. Each pillar has
an action plan and so on. In the ideal world you will change your
old structure, which has production modules, technical support
modules, a warehouse department, and so on, to an IWS organi-
zation in terms of having only a pillar organization. We are just at
the stage of how to implement the transfer. I think this will take
two to five years. The classical production and operations man-
agers will disappear and we will only have a pillar organisation.”
Consistent with this strategy, the plant has created the “Crailsheim vi-
sion”, targeted at employees, which states: everyone contributes to the busi-
ness goals; our customers are important to us, we make sure that they are
100% satisfied; we want to have the lowest costs compared to our competi-
tors; we work on the principle of “zero losses”. Stretch goals are included in
the Crailsheim vision, and contain two key plant measures used by corpo-
rate: manufacturing cost per unit and productivity. Manufacturing costs (all
plant costs plus logistics to the customer dock for delivered costs) are formu-
lated in statistical units (SUs) reflecting the mix of different brands. Produc-
tivity is measured in million SUs (MSUs) produced per employee and year
(excluding apprentices). There is also an output number per production line
(in cases, per line and day). In terms of productivity, the stated goal corre-
sponds to an index performance of 180 compared with the benchmark of 100
established in 1993/94. At the beginning of the year 2000, the plant was at
about 170.
In addition to hard measures, the corporation runs an annual survey of
“soft factors” across its plants which ranks different items on a scale from
one to 10 (such as capital management, quality, and safety). Crailsheim has
an overall average of 8.7 and is thus in the top group worldwide.
Crailsheim reports to the firm’s worldwide and European headquarters
which send out specific goals through what P&G calls OGSM meetings (Ob-
jectives – Goals – Strategies – Measures), held in March of each year, deriv-
ing action plans from these goals for the Crailsheim plant. Meanwhile, every
module manager develops individual goals for his/her area during work-
9.3 Supplier Management 161
shops. These proposals are handed to Mr. Grad, the Plant Manager and his
team, who aggregate them and check whether or not the plant goals are cov-
ered. If there is a gap, negotiation takes place: “Why can’t we achieve this?
With what additional support or resources can we achieve it?” Once a feasi-
ble strategy for achieving the targets is reached, the plans are communicated
in detail to every employee and deployment follows in June.
Consistent with the overarching plan, every employee develops a per-
sonal development plan for the year with his/her supervisor (e.g., the line
coordinator, module manager, or production head). These form the basis of
the annual personal evaluations (see below). Moreover, every line has goals
in terms of productivity and cost (as for the plant), volume (case rate of the
line), machine efficiency (including the effects of machine downtime and set-
ups), scrap, quality levels, and safety record. Daily performance is publicly
posted at the end of every line.
This highly developed communication and problem-solving process has
resulted in every worker knowing the overarching plant goals and being able
to explain how his/her individual performance measure contributes to them.
Every level has a chance to give input as support groups have measurable
goals relating to the plant’s targets. For example, the electricians’ group must
ensure production lines are not down more than a certain percentage due to
electrical problems. In addition, group members are evaluated by line coor-
dinators for speed and quality of support service rendered. The electricians
thus understand why their work is important for the plant and this serves to
motivate them.
called Ultimate Supplier Systems project (USS) designed to forge deeper re-
lationships with suppliers as well as customers. “P&G is increasingly aware
that it can only remain competitive if it looks more to all areas of the supply
chain and that includes suppliers and customers. This requires a mindset
change for the company,” explains Mr. Geuther.
The lead USS team is located at P&G’s headquarters in Cincinnati and
there are six additional global learning sites including Crailsheim. Teams
work with pre-defined suppliers on how to decrease inventory, reduce costs,
and speed up information exchange. Results have been encouraging. For ex-
ample, the Crailsheim plant reduced inventory with one large German sup-
plier by 80% and with another by 60% in 1998. This is a shared benefit: a
decrease in stocks for the client as well as the supplier. “Just by speaking
with them, and with our test models, we believe we can easily achieve a 50%
inventory reduction for all suppliers if we apply the same tools,” explains Mr.
Geuther. Another example of the USS model involves a large Finnish tissue
supplier. The five European P&G femcare plants standardized ordering with
this supplier which led to fewer format changes (e.g., width standards), re-
duced the supplier’s waste and downtime, and meant a 2.5% price decrease
for P&G – its share of the improvements. Thus, “low hanging fruits” are
being picked, but there is a potential for more ahead.
The plant’s supply chain includes P&G’s distribution center, the wholesaler
or retailer’s distribution center, the retailer, and the end consumer. Crail-
sheim delivers 60% of its output directly to customers’ distribution centers
and 40% to wholesalers. Customer integration is another area with signifi-
cant improvement potential.
Production forecasts are derived weekly from P&G’s European head-
quarters in Geneva, Switzerland, which consolidates country sales forecasts
supplied by the brand managers into Europe-wide data. The data is shared
with the plants every Monday. The following day, the plants use the data
to plan their production. The logistics department’s workers plan the raw
material and packing on Wednesday. This weekly process is done in great
detail (by SKU) for the next 12 weeks (three months) and less thoroughly (by
product families) for the following four to 18 months.
The volatility of this data in terms of total volume is less than 10%. On
an SKU basis, however, the changes can vary by 100% from one week to
another either positively or negatively. This can happen, for example, when
a retailer decides to launch a promotion but informs P&G too late, or if the
firm’s salespeople do not pass on the information to the plants. This is an
issue for P&G and it is addressed in the USS project. “We are thinking about
integrated planning systems that would allow us to plan daily on a category
basis, automatically creating raw material orders for femcare Europe-wide.
9.5 Production 163
9.5 Production
The 60,000 m2 plant is divided into three parts: office space, manufactur-
ing, and storage of finished goods inventory. It is P&G’s largest European
plant and serves as an internal benchmark to other factories for some of its
operating processes. Figure 9.2 provides pictures of the plant floor.
Production is organized into three separate shops for diapers, pads, and
panty liners. Within each shop there are flow lines converting raw material
to packaged product. Workers form teams responsible for a whole line. Their
responsibilities include loading (at the front), checking for quality (sampling
between and at the end of the lines), filling out statistical process control
(SPC) charts, and analyzing and fixing problems. When a problem occurs
(e.g., a routine test shows a fault), the worker stops the line, looks for the
error (including upstream if necessary) and fixes it. If no error can be found
the fault is treated as a statistical incident within the control limits of the
process.
The employees cover three shifts with four teams. Teams overlap by 30
minutes in order for the incoming team to be briefed by the outgoing coor-
dinator and discuss what needs to be done. Workers have their own meet-
ing rooms where management guidelines are posted for work rules, quality
management, safety, and environmental management. In addition, there is a
production meeting room.
Line performance such as quality and reliability is continuously posted at
the end of each line. Accidents (including minor ones) are centrally posted
by line. A benchmarking graph highlighting costs of P&G plants in Italy,
Spain, Eastern Europe and other countries serves as a constant reminder to
the workers of where their plant stands.
One important performance measure for production is what P&G call
“utilization” – real productive machine time as a percentage of theoretically
available time (24 hours 365 days a year). This has increased by 15% over the
last three years which includes many weekends worked. It is broken down
into planned work time (scheduled shifts) and what P&G calls “reliability”,
which is productive work time divided by 100% of planned work time, the
difference being downtime, rework or scrap, and set-ups. The Crailsheim
plant has the best reliability mark in Europe.
Increases in utilization have led to a 22% unit cost reduction. The most
important programs to reach these utilization goals were:
• Introduction of Sunday operation, which alone increased utilization by
5%.
164 9 Procter & Gamble Crailsheim
• Taking on small volumes for the Eastern European market, despite the
cost of long set-ups, helped to find the corresponding volume increases.
• Targeted increases in automation have reduced the workers’ load and al-
lowed them to be spread over more machines. For example, packaging
automation and better material movement among machines (less worker
intervention) have reduced worker load per unit by 15%.
• Set-up times have been reduced by 50% by making the switch between
sizes and packaging types simpler, with less capacity loss.
• Workers are more flexible, both in terms of the complicated shift pattern
as well as work assignments, in order to achieve the highest utilization
possible. Worker training is critical both in terms of mastering multiple
9.6 Quality Assurance 165
However, the management team realizes that they still have considerable
potential for improvement, as manufacturing cost and quality concerns are
still not considered sufficiently early on in the design of a new product –
for example, the majority of customer quality complaints are still caused by
inadequate designs, although this is not completely in their hands.
“Our strength is the capability of our people and their Schwabian thor-
oughness – you can trust what they promise.” The Operation Manager of
Alldays panty liner, Andreas Vogel, walks down the lines several times per
shift to give honest feedback and encouragement. Staying in touch motivates
people.
technicians participate and take initiatives. They are creative, they dare to try
even when the line manager is absent. They never give up, they get the nec-
essary help when they are stuck,” explains Ms. Minkwitz. When the side
panel material posed problems on one of the Pampers lines, the technicians
performed all kinds of tests (e.g., cleaning, adjustments) and found nothing.
With no known diagnosis, they called in other line coordinators and together
changed the cutting mechanism of the machine. That are three hours of ma-
chine downtime and this went outside of standard operating procedures,
but the exchange did get the machine running again. “As a line leader I was
happy because they searched for a final solution, they didn’t just tinker with
the problem. No idea is ever rejected”, adds Ms. Minkwitz.
Ms. Minkwitz sums up her thoughts on the plant: “Everyday, a new prob-
lem comes up. No one says you have to do it this way. You can try out many
things to improve but if you are not strong enough to stick with your idea,
then it may get lost in the system. You must take initiative, push forward,
and be persistent. The support is there if you ask for it.”
Andreas Vogel, Operations Manager of Alldays panty liner, has many exam-
ples of delegation in his department. One of them concerns a new process
qualification. The shift coverage (responsibility) that traditionally belonged
to a manager is now performed by a technician. This is possible because the
technicians run test series during qualification so they become active par-
ticipants in the process introduction. The area support is still present but
performs different tasks than before – it used to take over the job when there
were problems, now it only supervises standards. Team members help tech-
nicians trouble-shoot. “This will be pushed even further to the point where
the support team performs mainly skills training. The limit is that we will
always need specialists to help the technicians trouble-shoot,” explains Mr.
Vogel.
Process improvements regularly occur in technician-led teams. Such a
team performs analysis and problem-solving and puts measures in place.
Only the resource authorization still has to be given by a manager. “We look
for people who can responsibly manage a budget,” explains Mr. Vogel. In-
centives for suggestions can include a good evaluation, more money, a day-
shift job, a better job, or a wage increase. Fundamentally, the culture is driven
by recognition and respect, not disciplining or money.
More broadly, Mr. Vogel believes that the Crailsheim plant needs to de-
velop this delegation policy in order to maintain the gap with the other
plants: “We need to use the skills of our people and their creativity to stay
ahead of the other plants. The air is getting thinner.” This is due to the
fact that headquarters has recently instituted a new policy regarding process
improvements – a global process standardization of the IWS management
170 9 Procter & Gamble Crailsheim
9.9.4 Motivation