Concrete Required 1,000 m3

Rate Each (per No. Units on


Equipment Total Rate Hours required
hour) Site

Batching Plant 1
45 m3 1 no. 45 m3/hr 22 hrs
(full production)
Batching Plant 2
90 m3 1 no. 90 m3/hr 11 hrs
(full production)
Concrete Trucks 8m3
24 m3 3 no. 72 m3/hr 14 hrs
( 3 loads per hour)
Concrete Pumps
96 m3 1 no. 96 m3/hr 10 hrs
(8m3 every 5 minutes)

Materials Capacity on Site Capacity No. Units on Total Concrete


Site
Cement Silos Batching Plant 1 100 tonnes 3 no. 300 tonnes 825 m3
Cement Silos Batching Plan2 100 tonnes 3 no. 300 tonnes 825 m3
Storage Yard Sand 3,000 m3
(capacity 3000 m3)
Storage Yard Agregate 3,000 m3
(capacity 3000 m3)
Hours required
Combined

7 hrs

14 hrs

10 hrs

% needed Combined
121.21%
60.61%
121.21%
33.33% 33.33%

33.33% 33.33%