Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Date: 30/07/2019

ITP No: RADES-56-YC-QA-QP-CERI-7115

Rev: 0

Page No: 7
INSPECTION AND TEST PLAN (ITP)
RADES-C 450 MW CCPP PROJECT Report No:

Doc. Nr. :RADES-56-YC_-QA-QP-CERI-7115 LOCATION:RADES C 450 MW CCPP Site

EQUIPMENT/PART SERIAL NO: STEAM TURBINE GENERATOR DRAWING NO:

INSPECTION LEVEL

REFERENCED ACCEPTANCE INSPECTION VERIFYING SUPPLIER/SUBCONTRACTOR GAMA 3RD PARTY STEG


ITEM NO ACTIVITY DESCRIPTION NOTES
DOCUMENTS CRITERIA FREQUENCY RECORD
LEVEL DATE SIGN LEVEL DATE SIGN LEVEL DATE SIGN LEVEL DATE SIGN

1 Before Starting activities

Approved Dwg, Manual of As per Vendor


1.1 Document review: • Verify IFU drawings & Check revision status 100% _ H R N.A R
installation Dwg/Specification

Material Receipt: • Check materials compliance with Spec. and Material Requisition in Approved Dwg, Manual of As per Vendor
1.2
terms of mechanical and chemical features. installation Dwg/Specification
100% _ H W S

1.3 Welding Book: check presence of welding book (WPS, PQR, WPQR…) ASME IX ASME IX 100% _ H S N.A S

1.4 Welders qualification ASME IX ASME IX 100% WPQR H H H W

Approved Dwg, Manual of As per Vendor


1.5 Foundation Release
installation Dwg/Specification
100% Site Handover H H N.A H

2 FOUNDATION WORKS OF ST GENERATOR

2.1 Inspection of Foundation

Approved Dwg, Manual of As per Vendor


2.1.1 Location and height of the foundation bolt. 100% 2 H W N.A R
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


2.1.2 Location of the piping duct and opening. 100% _ H S N.A R
installation Dwg/Specification

2.2 Installation of Embedment for Generator

Approved Dwg, Manual of As per Vendor


2.2.1 Check Arrangement&Elevation&Location of Jack Plate and Flat Base Plate 100% 1,3 H W N.A W
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


2.2.2 Blue Contact Check between Taper Key&Flat Base Plate 100% _ H W N.A S
installation Dwg/Specification

3 POSITIONING OF ST GENERATOR

Approved Dwg, Manual of As per Vendor


3.1 Check Setting of Seating Plate 100% 5 H W N.A R
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


3.2 Check that no damage on generator stator 100% _ H S N.A R
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


3.3 Check Cleanliness of Foundation & GEN Feet 100% _ H S N.A R
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


3.4 Pre-set on floor level CT Trunk to GEN 100% _ H S N.A R
installation Dwg/Specification
Date: 30/07/2019
ITP No: RADES-56-YC-QA-QP-CERI-7115

Rev: 0

Page No: 7
INSPECTION AND TEST PLAN (ITP)
RADES-C 450 MW CCPP PROJECT Report No:

Doc. Nr. :RADES-56-YC_-QA-QP-CERI-7115 LOCATION:RADES C 450 MW CCPP Site

EQUIPMENT/PART SERIAL NO: STEAM TURBINE GENERATOR DRAWING NO:

INSPECTION LEVEL

REFERENCED ACCEPTANCE INSPECTION VERIFYING SUPPLIER/SUBCONTRACTOR GAMA 3RD PARTY STEG


ITEM NO ACTIVITY DESCRIPTION NOTES
DOCUMENTS CRITERIA FREQUENCY RECORD
LEVEL DATE SIGN LEVEL DATE SIGN LEVEL DATE SIGN LEVEL DATE SIGN

Approved Dwg, Manual of As per Vendor


3.5 Check Dismantling of Transportation Cover before Lifting 100% _ H S N.A R
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


3.6 ST GEN on Bolt 100% _ H S N.A W
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


3.7 Check Visual Inspection of Stator, Windings,Core,Bearing Zone against any damage 100% _ H S N.A S
installation Dwg/Specification

Check Visual Inspection Rotor Surface, Rotor Body,Journal,Coupling and Ventilation Hole Approved Dwg, Manual of As per Vendor
3.8
against any damage.
100% _ H S N.A S
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


3.9 Check Insulation Resistance Measurement of Stator&Rotor 100% 22 H W N.A R
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


3.10 Adjustment of Transport Lock Device-Check Gap of Stator Supporting Bolt 100% _ H S N.A S
installation Dwg/Specification

4 Installation Activities of ST GEN & Brushless Exciter

Approved Dwg, Manual of As per Vendor


4.1 Check Installation of CT Trunk, Bolt Tightening & Locking of Bolts 100% _ H S N.A R
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


4.2 Check Installation of Main Lead and Bolt Tighetening 100% _ H S N.A R
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


4.3 Check Insulation Tapping of Main Lead- Insulation Resistance of Stator Winding 100% 21 H W N.A S
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


4.4 Check Leakage Test of Air Cooler 100% 15 H W N.A W
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


4.5 Check Installation of Air Make Up 100% _ H S N.A R
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


4.6 Check Installation of Flow Sight 100% _ H S N.A R
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


4.7 Check Initial Alignment of ST&STG 100% 10 H W N.A W
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


4.8 Check Foundation of Brushless Exciter& Anchor Bolts 100% 6 H W N.A R
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


4.9 Check Setting of Jack Plate, Flat Plates 100% 7 H W N.A R
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


4.10 Check Grouting of Seating Plate 100% 8 H W N.A R
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


4.11 Check Final Alignment of ST&STG Rotors 100% 11,13 H W N.A W
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


4.12 Check Run Out at coupling after Combining ST&STG Rotors 100% 12 H W N.A W
installation Dwg/Specification
Date: 30/07/2019
ITP No: RADES-56-YC-QA-QP-CERI-7115

Rev: 0

Page No: 7
INSPECTION AND TEST PLAN (ITP)
RADES-C 450 MW CCPP PROJECT Report No:

Doc. Nr. :RADES-56-YC_-QA-QP-CERI-7115 LOCATION:RADES C 450 MW CCPP Site

EQUIPMENT/PART SERIAL NO: STEAM TURBINE GENERATOR DRAWING NO:

INSPECTION LEVEL

REFERENCED ACCEPTANCE INSPECTION VERIFYING SUPPLIER/SUBCONTRACTOR GAMA 3RD PARTY STEG


ITEM NO ACTIVITY DESCRIPTION NOTES
DOCUMENTS CRITERIA FREQUENCY RECORD
LEVEL DATE SIGN LEVEL DATE SIGN LEVEL DATE SIGN LEVEL DATE SIGN

Approved Dwg, Manual of As per Vendor


4.13 Check Adjustment of Anchor Keys 100% 14,9 H W N.A R
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


4.14 Check Setting of Upper Bed for Brushless Exciter 100% _ H S N.A S
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


4.15 Check Final Alignment of STG&Brushless Exciter 100% 17,2 H W N.A W
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


4.16 Check Coupling of ST GEN & Exciter and Swing Check 100% 18,19 H W N.A W
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


4.17 Check Leakage Test of Brushless Exciter Air Cooler 100% 16 H W N.A W
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


4.18 Check Final Installation of Manhole Cover 100% _ H S N.A S
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


4.19 Check Installaiton of Brushless Exciter Housing 100% _ H S N.A R
installation Dwg/Specification

5 Installation Activities of Lube Oil and Cooling Water Piping

Approved Dwg, Manual of As per Vendor


5.1 Check Piping Assembly of Lube Oil Piping 100% _ H S N.A R
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


5.2 Check Piping Pressure&Leakage Tests 100% ITR-MW-128A H W N.A W
installation Dwg/Specification

Approved Dwg, Manual of As per Vendor


5.3 Check Oil Flushing Confirmation 100% ITR-MW-129 H W N.A R
installation Dwg/Specification

SUPPLIER/SUBCONTRACTOR APPROVAL GAMA APPROVAL THIRD PARTY/AUTHORIZED INSPECTOR APPROVAL CONSORSIUM APPROVAL STEG APPROVAL
NAME/DATE/SIGN: NAME/DATE/SIGN: NAME/DATE/SIGN: NAME/DATE/SIGN: NAME/DATE/SIGN:

LEGENDS
R REVIEW OF DOCUMENTS H HOLD POINT I INSPECTION W WITNESS POINT S SPOT WITNESS

Forms & Technical Appendixes

RADES-56-YC-QA-QP-CERI-7115

You might also like